Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
Old Bethal Road - eMalahleni - Witbank - 1035
Organization Type
GOVERNMENT
Published
05 Jun 2026
OCDS Reference
ocds-9t57fa-158201
ESKOM invites tenders for the end-to-end delivery of a sulphuric acid storage and dilution upgrade project at duvha power station in mpumalanga. The 24-month contract requires design, supply, installation, commissioning, and testing of the system, with integration into the existing abb symphony infi90 dcs and 800xa hmi control system.
Submission Guidelines
Source: Appendix D - Acid regen tech spec signed.pdf (unknown)Returnable Documents: Not specified in the provided text.
Categories
Request for Bid(Open-Tender)
Old Bethal Road - eMalahleni - Witbank - 1035
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
Appendix D - Acid regen tech spec signed.pdf
Date & Time
Monday, 29 June 2026 - 10:00
Venue
Ms Teams
05 Jun
2026
Tender Published
Tender was published
29 Jun
2026
Closing Date
Tender closing date
Median Estimate
R 506 684
Range
Based on 14 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
Learn how to submit a winning bid with these related articles
Everything South African construction contractors need to know about how procurement officers verify cidb grades: what gauteng contractors must ensure is correct — april 2026 update — covering CIDB grading certificate, NHBRC registration (residential), step-by-step processes, common disqualification mistakes, and how Tenders-SA.org helps you find and win relevant contracts in Gauteng.
Everything South African construction contractors need to know about cidb grading system explained: what every gauteng contractor must know in 2026 — april 2026 update — covering CIDB grading certificate, NHBRC registration (residential), step-by-step processes, common disqualification mistakes, and how Tenders-SA.org helps you find and win relevant contracts in Gauteng.
Everything South African construction contractors need to know about cidb vs nhbrc: understanding dual registration requirements for residential projects in gauteng — april 2026 update — covering CIDB grading certificate, NHBRC registration (residential), step-by-step processes, common disqualification mistakes, and how Tenders-SA.org helps you find and win relevant contracts in Gauteng.
Everything South African construction contractors need to know about cidb grading system explained: what every gauteng contractor must know in 2026 — april 2026 update — covering CIDB grading certificate, NHBRC registration (residential), step-by-step processes, common disqualification mistakes, and how Tenders-SA.org helps you find and win relevant contracts in Gauteng.
💡 Want more tendering tips and strategies?
Explore Our BlogContact Information
Source: ECC3 Contract for Design Supply and installation of Duvha Acid Regen .pdf (unknown){"name":null,"email":null,"phone":null,"department":null,"address":"n the conditions of contract identified"}
Submission Guidelines
Source: ECC3 Contract for Design Supply and installation of Duvha Acid Regen .pdf (unknown)Returnable Documents: C1.1 Form of Offer and Acceptance 3 - 5, C1.1 Form of Offer & Acceptance, By the representative of the tenderer, deemed to be duly authorised, signing this part of this Form of Offer, This Offer may be accepted by the Employer by signing the Acceptance part of this Form of Offer a
Evaluation Criteria
Source: ECC3 Contract for Design Supply and installation of Duvha Acid Regen .pdf (unknown)General
Financial
Technical
Technical Specifications
Source: ECC3 Contract for Design Supply and installation of Duvha Acid Regen .pdf (unknown)Supply, installation, commissioning and testing of the sulphuric acid storage and dilution
Upgrade project
Quality Management
Source: ECC3 Contract for Design Supply and installation of Duvha Acid Regen .pdfUpgrade project at duvha power station for a period of 24 (twenty-four) months
e-mail [email protected]
10.1 The Supervisor is: (Name) TBA
Address [●]
Tel No. [●]
Fax No. [●]
e-mail [●]
11.2(13) The works are Design, Supply, Installation, Commissioning
and Testing of the Sulphuric Acid Storage and
approval. program and
approved milestone.
4 QCP, Program & 7 days after final
Upgrade project at duvha power station for a period of 24 (twenty-four) months
1 % per total value of the Purchase order(s) per day. No Submission of Quality control
Limited to 10% of the total value of the Purchase documents as per agreed upon
Order(s) of the spares item. Contract Document Submittal
have been discovered on reasonable
inspection by the Employer or the Supervisor
before the defects date, without requiring any
inspection not ordinarily carried out by the
any inspection over and above the reasonable
inspection, this does not place a greater
responsibility on the Employer or the
occupational hygiene inspection body, i.e. a SANAS accredited and Department of
B.1 Mixed bed segment
B.1.1 Design entire scope of works, sum 1
prepare drawings and submit
to Employer for approval
B.1.2 Conduct all necessary sum 1
inspections on the existing
system and provide full report
B.1.3 Manufacture/procure, delivery sum 1
and safely store on site all
required components/spares,
materials
B.1.4 Install all components/spares, sum 1
materials as per the scope of
works
B.1.5 De-commission existing sum 1
system: Strip, remove all
components/spares (mixing
tanks, pipes, valves, etc) for
the mixed bed segment and
safely dispose to a
designated area as indicated
by the project manager
B.2 Cation segment
B.2.1 Design entire scope of works, sum 1
prepare drawings and submit
to Employer for approval
B.2.2 Conduct all necessary sum 1
inspections on the existing
system and provide full report
B.2.3 Manufacture/procure, delivery sum 1
and safely store on site all
required components/spares,
materials
B.2.4 Install all components/spares, sum 1
materials as per the scope of
works
Part c2: pricing data c2 ECC3/B cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
C.1 Design entire scope of works, sum 1
prepare drawings and submit
to Employer for approval
C.2 Conduct all necessary sum 1
inspections on the existing
system and provide full report
C.3 Manufacture/procure, delivery sum 1
and safely store on site all
required components/spares,
materials
C.4 Install all components/spares, sum 1
materials as per the scope of
works
C.5 Provide fully automated sum 1
system (including software)
connected to the main
operating system
C.6 Strip, remove all damaged sum 1
components/spares (cabling
system, meters, transmiters,
etc) on the cation segment
and safely dispose to a
designated area as indicated
by the project manager
Pricing Schedule
Source: ECC3 Contract for Design Supply and installation of Duvha Acid Regen .pdfof 24 (Twenty-Four) Months
Contents: No of
pages
Part C1 Agreements & Contract Data 2 - 24
Part C2 Pricing Data 25 - 30
Part C3 Scope of Work 31 - 54
Part C4 Site Information 55 - 68
CONTRACT No. [Insert at award stage]
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Upgrade project at duvha power station for a period of 24 (twenty-four) months
Part C1: Agreements & Contract Data
Contents: No of
pages
C1.1 Form of Offer and Acceptance 3 - 5
[to be inserted from Returnable Documents at award
stage]
C1.2a Contract Data provided by the Employer 5 - 21
C1.2b Contract Data provided by the Contractor 22 - 24
[to be inserted from Returnable Documents at award
stage]
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
terms of the conditions of contract.
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Part C1 Agreements and Contract Data, (which includes this Form of Offer and Acceptance)
Part C2 Pricing Data
Part C3 Scope of Work: Works Information
Part C4 Site Information
and drawings and documents (or parts thereof), which may be incorporated by reference into the above
listed Parts.
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
1035
Tel +27 13 690 0310
Fax +27 867 516 274
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
50.1 The assessment interval is between the 25 days of each successive
month.
51.1 The currency of this contract is the South African Rand.
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
weather measurements for each calendar
month which were recorded at: Witbank Area
and which are available from: the South African Weather Bureau and
included in Annexure A to this Contract Data
provided by the Employer
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Arbitrators (Southern Africa) or its successor
body.
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
are Z1 to Z15 always apply.
Z1 Cession delegation and assignment
Z1.1 The Contractor does not cede, delegate or assign any of its rights or obligations to any person
without the written consent of the Employer.
Z1.2 Notwithstanding the above, the Employer may on written notice to the Contractor cede and
delegate its rights and obligations under this contract to any of its subsidiaries or any of its
present divisions or operations which may be converted into separate legal entities as a result
of the restructuring of the Electricity Supply Industry.
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
equal to that stated in the payment certificate.
Z7.2 If the Contractor does not provide a tax invoice in the form and by the time required by this
contract, the time by when the Employer is to make a payment is extended by a period equal
in time to the delayed submission of the correct tax invoice. Interest due by the Employer in
terms of core clause 51.2 is then calculated from the delayed date by when payment is to be
made.
Z7.3 The Contractor (if registered in South Africa in terms of the companies Act) is required to
comply with the requirements of the Value Added Tax Act, no (as amended) and to
include the Employer’s VAT number 4740101508 on each invoice he submits for payment.
Z8 Notifying compensation events
Z8.1 Delete from the last sentence in core clause 61.3, “unless the Project Manager should have
notified the event to the Contractor but did not”.
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Z12.1 A Committing Party may not take any Prohibited Action during the course of the procurement of
this contract or in execution thereof.
Z12.2 The Employer may terminate the Contractor’s obligation to Provide the Services if a Committing
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Z14.4 The Employer does not waive its rights provided for in section 30 (7) of Act , or any
replacement section dealing with the same subject matter.
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
and related control measures at the Contractor’s expense. For the purposes of compliance
the results generated from Parallel Measurements are evaluated only against South African
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
above is taken into account in assessing a compensation event.
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
61 in The hourly rates for Defined Cost of
Note: Hourly rates are estimated ‘cost to
company of the employee’ and not selling rates.
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Upgrade project at duvha power station for a period of 24 (twenty-four) months
Part 2: pricing data
ECC3 Option A
reference pages
C2.1 Pricing assumptions: Option A 24-27
C2.2 The activity schedule 27-30
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Upgrade project at duvha power station for a period of 24 (twenty-four) months
C2.1 Pricing assumptions: Option A
Part c2: pricing data c2 ECC3/B cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Upgrade project at duvha power station for a period of 24 (twenty-four) months
and incidental to Providing the Works in accordance with the Works Information, as it was at the
time of tender, as well as correct any Defects not caused by an Employer’s risk;
activities in order to fulfil the obligation to complete the works for the tendered total of the Prices.
quantity, of work within that activity later turns out to be different to that which the Contractor
estimated at time of tender. The only basis for a change to the Prices is as a result of a
compensation event.
Part c2: pricing data c2 ECC3/B cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
A.3.6 Staff transport months 24
Part c2: pricing data c2 ECC3/B cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
NB: If necessary prior
approval by Employer:
D.1 Perform detailed electrical sum 1
design for the entire works
D.2 Manufacture/procure, supply, sum 1
deliver and safely store all
necessary components and
materials on site
Part c2: pricing data c2 ECC3/B cover
Financial Requirements
Source: ECC3 Contract for Design Supply and installation of Duvha Acid Regen .pdf (unknown)Payment Terms: payment certificate from the Project Manager in terms of core
clause 51.1, the Contractor provides the Employer with a tax invoice in accordance with the
Employer's procedures stated in the Works Information, showing the amount due for payment
equal to that stated in the payment certificate.
Z7.2 If the Contractor does not provide a tax invoice in the form and b
Health & Safety
Source: ECC3 Contract for Design Supply and installation of Duvha Acid Regen .pdfsignature of Date
witness
Note: If a tenderer wishes to submit alternative tenders, use another copy of this Form of Offer and
11.2(3) The completion date for the whole of the
works is
11.2(9) The key dates and the conditions to be Condition to be met key date
met are:
1 Kick off meeting 3 days after contract
awarded
2 Safety file approval 7 days after contract
awarded
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Upgrade project at duvha power station for a period of 24 (twenty-four) months
30.1 The access dates are: Part of the Site Date
1 Site Establishment. 7 days after safety
file approval.
elsewhere in this Contract Data.
60.6 The method of measurement is [●] published by [●] and amended as stated in
Part C2.1, Pricing Assumptions.
11 Data for Option W1
W1.1 The Adjudicator is the person selected from the ICE-SA Division
(or its successor body) of the South African
Upgrade project at duvha power station for a period of 24 (twenty-four) months
Z4.5 The Contractor ensures that all his subcontractors abide by the undertakings in this clause.
Z5 Waiver and estoppel: Add to core clause 12.3:
Z5.1 Any extension, concession, waiver or relaxation of any action stated in this contract by the
rights, and does not give rise to an estoppel unless the Parties agree otherwise and confirm
such agreement in writing.
Z6 Health, safety and the environment: Add to core clause 27.4
Z6.1 The Contractor undertakes to take all reasonable precautions to maintain the health and safety
of persons in and about the execution of the works. Without limitation the Contractor:
provided for under the Construction Regulations 2014 (promulgated under the
Occupational Health & Safety Act ) (“the Construction Regulations”) for the Site;
proper compliance with the Construction Regulations, all applicable health & safety laws
and regulations and the health and safety rules, guidelines and procedures provided for in
this contract and generally for the proper maintenance of health & safety in and about the
execution of works; and
the regulations published in GNR February 2002, under the Occupational Health
and Safety Act, 1993 (Act ) (“Asbestos Regulations”). The OEL for asbestos is 0.2
regulated asbestos fibres per millilitre of air as a 4-hour TWA, averaged over any continuous
period of four hours, and the short term exposure limit of 0.6 regulated asbestos fibres per
millilitre of air as a 10-minute TWA, averaged over any 10 minutes, measured in accordance
with HSG248 and monitored according to HSG173 and OESSM.
Z15.2 Upon written request by the Contractor, the Employer certifies that these conditions prevail.
Upgrade project at duvha power station for a period of 24 (twenty-four) months
statutory limits as detailed in clause Z15.1. Control measures conform to the requirements
stipulated in the AAIA-approved asbestos work plan.
Z15.3 The Employer manages asbestos and ACM according to the Standard.
Z15.4 In the event that any asbestos is identified while Providing the Services, a risk assessment is
conducted and if so required, with reference to possible exposure to an airborne concentration
of above the AL for asbestos, immediate control measures are implemented and relevant air
monitoring conducted in order to declare the area safe.
Z15.5 The Contractor’s personnel are entitled to stop working and leave the contaminated area
forthwith until such time that the area of concern is declared safe by either Compliance
emergency asbestos work plan, if applicable.
Z15.6 The Contractor continues to Provide the Services, without additional control measures
presented, on presentation of Safe Levels. The contractually agreed dates to Provide the
statement however other clauses may also use the same data
3. Where a form field like this [ ] appears, data is required to be inserted relevant to the option
selected. Click on the form field once and type in the data. Otherwise complete by hand and in ink.
21 in The published list of Equipment is the last
Equipment in the published list is Minus %
22 in The rates of other Equipment are: Equipment Size or Rate
A.1 Fixed charge obligations
A.1.1 Site sum 1
mobilisation/establishment
A.1.2 Site De- sum 1
mobilisation/establishment
A.2 Health and safety
requirements
A.2.1 Medicals sum 1
A.2.2 PPE sum 1
A.2.3 Safety file sum 1
A.2.4 Environmental requirements sum 1
A.3 Time related:
A.3.1 Transport and rigging months 24
equipment for the removal
and installation of existing
and new works
A.3.2 Supply, erect and dismantle months 24
necessary access scaffolding
throughout project delivery
A.3.3 Site office containers months 24
A.3.4 Site storage months 24
A.3.5 Accommodation including months 24
meals (allowance) - Not
Environmental
Source: ECC3 Contract for Design Supply and installation of Duvha Acid Regen .pdfguidelines and procedures otherwise provided for under this contract and ensures that his
Subcontractors, employees and others under the Contractor’s direction and control,
likewise observe and comply with the foregoing.
Z6.2 The Contractor, in and about the execution of the works, complies with all applicable
environmental laws and regulations and rules, guidelines and procedures otherwise provided
for under this contract and ensures that his Subcontractors, employees and others under the
Contractor’s direction and control, likewise observe and comply with the foregoing.
Z7 Provision of a Tax Invoice and interest. Add to core clause 51
Z7.1 Within one week of receiving a payment certificate from the Project Manager in terms of core
clause 51.1, the Contractor provides the Employer with a tax invoice in accordance with the
dates are extended by the notification periods required by regulations 3 and 21 of the
Asbestos Regulations, 2001.
Z15.7 Any removal and disposal of asbestos, asbestos containing materials and waste, is done by a
registered asbestos contractor, instructed by the Employer at the Employer’s expense, and
conducted in line with South African legislation.
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Contractual Terms
Source: ECC3 Contract for Design Supply and installation of Duvha Acid Regen .pdfof Deviations (if any), contact the Employer’s agent (whose details are given in the Contract Data) to arrange
the delivery of any securities, bonds, guarantees, proof of insurance and any other documentation to be
provided in terms of the conditions of contract identified in the Contract Data at, or just after, the date this
agreement comes into effect. Failure to fulfil any of these obligations in accordance with those terms shall
constitute a repudiation of this agreement.
clauses and the clauses for main Option
A: Priced contract with activity schedule
dispute resolution Option W1: Dispute resolution procedure
and secondary Options
X1: Price adjustment for inflation
X2 Changes in the law
X7: Delay damages
X15: Limitation of Contractor’s liability for
design to reasonable skill and care
X16: Retention
X17: Low performance damages
X18: Limitation of liability
Z: Additional conditions of contract
of the NEC3 Engineering and
Construction Contract, April 2013 (ECC3)
10.1 The Employer is (Name): Eskom Holdings SOC Ltd (reg no:
2002/015527/30), a state owned company
incorporated in terms of the company laws of
the Republic of South Africa
Upgrade project at duvha power station for a period of 24 (twenty-four) months
51.2 The period within which the payment are 3 weeks
made is
51.4 The interest rate is the publicly quoted prime rate of interest
(calculated on a 365 day year) charged from
time to time by the Standard Bank of South
Africa Limited (as certified, in the event of any
dispute, by any manager of such bank, whose
appointment it shall not be necessary to
prove) for amounts due in Rands and
(ii) the LIBOR rate applicable at the time for
amounts due in other currencies. LIBOR is the
6 month London Interbank Offered Rate
quoted under the caption “Money Rates” in
quoted by the Reuters Monitor Money Rates
Service (or such service as may replace the
Reuters Monitor Money Rates Service) on the
due date for the payment in question, adjusted
mutatis mutandis every 6 months thereafter
and as certified, in the event of any dispute, by
any manager employed in the foreign
exchange department of The Standard Bank of
dispute to him. (see www.ice-sa.org.za). If the
elsewhere in this Contract Data.
X7 Delay damages (but not if Option X5 is
also used)
X7.1 Delay damages for Completion of the
whole of the works are Design submission - R 50 000,00 per day to a
maximum of 10%
Procuring of material - R 50 000,00 per day to a
maximum of 10%
Delivery of material - R 50 000,00 per day to a
maximum of 10%
Execution Phase - R 50 000,00 per day to a
maximum of 10%
X15 Limitation of the Contractor’s liability There is no reference to Contract Data in this
for his design to reasonable skill & Option and terms in italics are identified
care elsewhere in this Contract Data.
X16 Retention
The retention percentage is 10% of the contract value amount
X17 Low performance damages
X17.1 The amounts for low performance
damages are: Amount Performance level
1 % per total value of the Purchase order(s) per day. for the following:
Limited to 10% of the total value of the Purchase
Order(s) of the spares item. Spares delivery delay effecting
analogue output, and one alarm
output. The analyser shall be 24V
two wire loop powered.
X18 Limitation of liability
X18.1 The Contractor’s liability to the Employer R0.0 (zero Rand)
for indirect or consequential loss is limited
to:
X18.2 For any one event, the Contractor’s the amount of the deductibles relevant to the
liability to the Employer for loss of or event
damage to the Employer’s property is
limited to:
X18.3 The Contractor’s liability for Defects due The greater of
to his design which are not listed on the
Upgrade project at duvha power station for a period of 24 (twenty-four) months
from the Employer’s assets policy for
correcting the Defect (other than the
resulting physical damage which is not
excluded) plus the applicable deductible
as at contract date.
X18.4 The Contractor’s total liability to the the total of the Prices other than for the
in connection with this contract, other than
excluded matters, is limited to: The Contractor’s total liability for the
additional excluded matters is not limited.
for which the Contractor is liable under this
contract for
before the Defects Certificate is issued,
fabrication outside the Site,
the works, Plant and Materials),
right.
X18.5 The end of liability date is (i) 1 years after the defects date for latent
(ii) the date on which the liability in question
prescribes in accordance with the Prescription
Act No. (as amended or in terms of
any replacement legislation) for any other
matter.
the Contractor on their behalf.
Z2.3 The Contractor does not alter the composition of the joint venture, consortium or other
unincorporated grouping of two or more persons without the consent of the Employer having
been given to the Contractor in writing.
Z3 Change of Broad Based Black Economic Empowerment (B-BBEE) status
Z3.1 Where a change in the Contractor’s legal status, ownership or any other change to his
business composition or business dealings results in a change to the Contractor’s B-BBEE
status, the Contractor notifies the Employer within seven days of the change.
Z3.2 The Contractor is required to submit an updated verification certificate and necessary
supporting documentation confirming the change in his B-BBEE status to the Project Manager
within thirty days of the notification or as otherwise instructed by the Project Manager.
Z3.3 Where, as a result, the Contractor’s B-BBEE status has decreased since the Contract Date the
Employer may either re-negotiate this contract or alternatively, terminate the Contractor’s
obligation to Provide the Works.
Z3.4 Failure by the Contractor to notify the Employer of a change in its B-BBEE status may
constitute a reason for termination. If the Employer terminates in terms of this clause, the
procedures on termination are P1, P2 and P3 as stated in clause 92, and the amount due is
A1 and A3 as stated in clause 93.
Z4 Confidentiality
Z4.1 The Contractor does not disclose or make any information arising from or in connection with
this contract available to Others. This undertaking does not, however, apply to information
which at the time of disclosure or thereafter, without default on the part of the Contractor,
enters the public domain or to information which was already in the possession of the
Contractor at the time of disclosure (evidenced by written records in existence at that time).
Should the Contractor disclose information to Others in terms of clause 25.1, the Contractor
ensures that the provisions of this clause are complied with by the recipient.
Z4.2 If the Contractor is uncertain about whether any such information is confidential, it is to be
regarded as such until notified otherwise by the Project Manager.
Z4.3 In the event that the Contractor is, at any time, required by law to disclose any such
information which is required to be kept confidential, the Contractor, to the extent permitted by
law prior to disclosure, notifies the Employer so that an appropriate protection order and/or any
other action can be taken if possible, prior to any disclosure. In the event that such protective
order is not, or cannot, be obtained, then the Contractor may disclose that portion of the
information which it is required to be disclosed by law and uses reasonable efforts to obtain
assurances that confidential treatment will be afforded to the information so disclosed.
Z4.4 The taking of images (whether photographs, video footage or otherwise) of the works or any
portion thereof, in the course of Providing the Works and after Completion, requires the prior
written consent of the Project Manager. All rights in and to all such images vests exclusively in
the Employer.
Part c2: pricing data c2 ECC3/A cover
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Upgrade project at duvha power station for a period of 24 (twenty-four) months
Z9 Employer’s limitation of liability
Z9.1 The Employer’s liability to the Contractor for the Contractor’s indirect or consequential loss is
limited to R0.00 (zero Rand)
Z9.2 The Contractor’s entitlement under the indemnity in 83.1 is provided for in 60.1(14) and the
Employer’s liability under the indemnity is limited.
Termination: Add to core clause 91.1, at the second main bullet point, fourth sub-bullet
Z10
point, after the words "against it":
Z10.1 or had a business rescue order granted against it.
Z11 Addition to secondary Option X7 Delay damages (if applicable in this contract)
Z11.1 If the amount due for the Contractor’s payment of delay damages reaches the limits stated in
this Contract Data for Option X7 or Options X5 and X7 used together, the Employer may
terminate the Contractor’s obligation to Provide the Works using the same procedures and
payment on termination as those applied for reasons R1 to R15 or R18 stated in the
or in any other similar process, of such Prohibited Action before the Employer can terminate the
Contractor’s obligation to Provide the Services for this reason.
Z12.3 If the Employer terminates the Contractor’s obligation to Provide the Services for this reason, the
amounts due on termination are those intended in core clauses 92.1 and 92.2.
Z12.4 A Committing Party co-operates fully with any investigation pursuant to alleged Prohibited Action.
ensures that the Committing Party co-operates fully with an investigation.
Z13 Insurance
Z 13.1 Replace core clause 84 with the following:
Insurance cover 84
84.1 When requested by a Party, the other Party provides certificates from his
insurer or broker stating that the insurances required by this contract are
in force.
84.2 The Contractor provides the insurances stated in the Insurance Table A.
84.3 The insurances provide cover for events which are at the Contractor’s risk
from the starting date until the earlier of Completion and the date of the
termination certificate.
and Materials covered by the Employer’s insurance
The Employer’s policy deductible, as
Employer’s insurance
property (except the works, Plant and Employer’s property
Materials and Equipment) and liability
covered by the Employer’s insurance (not an employee of the Contractor)
caused by activity in connection with
this contract The Employer’s policy deductible, as
Employer’s insurance
Transportation (Marine) Per the insurance policy document
Z14 Nuclear Liability
Z14.1 The Employer is the operator of the Koeberg Nuclear Power Station (KNPS), a nuclear
installation, as designated by the National Nuclear Regulator of the Republic of South Africa,
and is the holder of a nuclear licence in respect of the KNPS.
Z14.2 The Employer is solely responsible for and indemnifies the Contractor or any other person
against any and all liabilities which the Contractor or any person may incur arising out of or
resulting from nuclear damage, as defined in Act , save to the extent that any
liabilities are incurred due to the unlawful intent of the Contractor or any other person or the
presence of the Contractor or that person or any property of the Contractor or such person at
or in the KNPS or on the KNPS site, without the permission of the Employer or of a person
acting on behalf of the Employer.
Z14.3 Subject to clause Z14.4 below, the Employer waives all rights of recourse, arising from the
aforesaid, save to the extent that any claims arise or liability is incurred due or attributable to
the unlawful intent of the Contractor or any other person, or the presence of the Contractor or
that person or any property of the Contractor or such person at or in the KNPS or on the
Description
Source: Eskom life-saving rules.pdfEskom's Life-Saving Rules document outlines the organization's commitment to safety, health, and environmental protection. Key points: Eskom prioritizes the safety of all individuals and the environment, aiming to prevent work-related injuries. Life-Saving Rules enforce zero tolerance for high-risk behaviors that could cause serious harm or fatalities. These rules apply to all Eskom employees, contractors, and visitors, and must be followed at all Eskom sites. Non-compliance may result in immediate removal from site or disciplinary action.
Evaluation Criteria
Source: Eskom life-saving rules.pdf (unknown)General
Technical
Safety
Quality Management
Source: Eskom life-saving rules.pdf (unknown)Compliance with ISO 9001 Quality Management Systems is required. Additional quality standards may apply as referenced in Eskom's normative documents.
Compliance Requirements
Source: Eskom life-saving rules.pdf (unknown)Mandatory compliance with Eskom Life-Saving Rules, which apply to all employees, contractors, and visitors. Key requirements include: adherence to ISO 9001, Eskom's Safety, Health, Environment and Quality Policy (32-727), and other referenced standards such as Plant Safety Regulations (36-681), Occupational Health and Safety Act, and Eskom-specific procedures (e.g., 32-136 Contractor Health and Safety Requirements). Zero tolerance for violations, with disciplinary action for non-compliance. Contractors must ensure their employees adhere to these rules and remove violators from site immediately.
Health & Safety
Source: Eskom life-saving rules.pdfMandatory adherence to Eskom's Life-Saving Rules for all employees, contractors, and visitors. Key safety requirements:
Section
Source: Eskom life-saving rules.pdfEvaluation is based on compliance with Eskom's Life-Saving Rules and referenced standards. Key criteria include: adherence to ISO 9001 Quality Management Systems and Eskom's Safety, Health, Environment and Quality Policy (32-727).
Description
Source: 240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP) rev 2.pdfProject involves the design, supply, installation, commissioning, and testing of a Sulphuric Acid Storage and Dilution Upgrade at Duvha Power Station. Duration: 24 months. A Quality Control Plan (QCP) or Inspection and Test Plan (ITP) is required, detailing intervention points, inspection methods, and acceptance criteria.
Evaluation Criteria
Source: 240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP) rev 2.pdf (unknown)General
Technical
Financial
Quality Management
Source: 240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP) rev 2.pdfQuality Control Plan (QCP) / Inspection and Test Plan (ITP) Requirements:
Description
Source: E-Tendering Help Manual for supplier.pdfEskom eTendering system is a web-based platform for submitting tender documents electronically. It replaces manual/physical submissions at Eskom tender offices. Suppliers must register, verify email/OTP, and use their CSD number to access the system. Links: TenderBulletin (https://tenderbulletin.eskom.co.za) and eTendering (https://eTendering.eskom.co.za).
Important Dates
Source: E-Tendering Help Manual for supplier.pdf (TENDER)Closing date: 2026-06-29 at 10:00. Example from system: Submission started 2022-08-23 14:28:33, finalized 2022-08-23 15:42:28 for tender #MPKUS10086PS.
Contact Information
Source: E-Tendering Help Manual for supplier.pdf (TENDER)For system issues: Contact the buyer responsible for the published tender. Automated submission confirmation emails sent from: Eskom E-Tender Document Submission <[email protected]>.
Submission Guidelines
Source: E-Tendering Help Manual for supplier.pdf (TENDER)Submit via Eskom eTendering portal: https://eTendering.eskom.co.za. Steps: 1) Register on the portal (CSD number required). 2) Verify email and OTP sent to phone/email. 3) Select tender reference number. 4) Click 'Create New Submission'. 5) Upload documents under correct categories (Technical, Commercial, Finance). 6) Name files, select type, and upload. 7) Verify all required documents are uploaded. 8) Click 'Finalize Submission' (max 50MB per file, total max 900MB). 9) Confirm final submission. 10) Save submission confirmation email with submission ID for records. Required document types: Technical, Commercial, Finance.
Returnable Documents
Source: E-Tendering Help Manual for supplier.pdf (TENDER)Required documents must be uploaded under correct categories: Technical, Commercial, Finance. File size limits: 50MB per file, 900MB total. Example submitted files: Test7.pdf (Commercial), Test1.pdf (Technical), Test15.pdf (Finance). Verify all documents are uploaded before final submission.
Evaluation Criteria
Source: E-Tendering Help Manual for supplier.pdf (TENDER)Registration
Suppliers must be registered on Eskom’s eTendering system with a valid CSD number.
Verification
Email and OTP verification required for system access.
Documentation
All required tender documents (Technical, Commercial, Finance, etc.) must be submitted.
Selection
For closed tenders, suppliers must meet Eskom’s predefined selection and evaluation criteria.
Compliance Requirements
Source: E-Tendering Help Manual for supplier.pdf (TENDER)CSD number is mandatory to access the eTendering system.
Section
Source: E-Tendering Help Manual for supplier.pdfClosed tenders are not listed on TenderBulletin but are sent directly to pre-selected suppliers who meet Eskom’s selection and evaluation criteria. These suppliers receive an email link to bid privately.
Description
Source: Duvha Power Station Sulphuric Acid Storage and Dilution System Technical Evaluation Strategy Rev 03.pdfProject purpose: Upgrade the Sulphuric Acid Storage and Dilution System at Duvha Power Station to address failures in the current system, which have caused downtime, impacted demineralized water production, and compromised safety. The new system must enable accurate, timeous, and safe regeneration of ion exchange resins in cation and mixed bed exchangers.
Context: Ion exchange resins are critical for producing demineralized water by removing unwanted cations and anions. The Sulphuric Acid Storage and Dilution System regenerates these resins. Current issues stem from pipework failures due to inadequate maintenance and design foresight.
Submission Guidelines
Source: Duvha Power Station Sulphuric Acid Storage and Dilution System Technical Evaluation Strategy Rev 03.pdf (unknown)Submit the following mandatory returnable documents with your tender:
Evaluation Criteria
Source: Duvha Power Station Sulphuric Acid Storage and Dilution System Technical Evaluation Strategy Rev 03.pdf (unknown)Mandatory
Qualitative
Technical Specifications
Source: Duvha Power Station Sulphuric Acid Storage and Dilution System Technical Evaluation Strategy Rev 03.pdf (unknown)Project objective: Design, supply, install, commission, and test a Sulphuric Acid Storage and Dilution System at Duvha Power Station to enable accurate, timeous, and safe regeneration of ion exchange resins in cation and mixed bed exchangers.
Background: Current system has significant downtime due to pipework failures caused by lack of maintenance and design foresight. This has impacted demineralized water production and compromised staff safety.
Scope: Upgrade the system to address existing failures and ensure reliable operation for resin regeneration. Must integrate with the Water Treatment Plant (WTP) Control System (ABB Symphony Infi90 DCS and 800xA HMI).
Key deliverables: System design, supply of materials, installation, commissioning, and testing over a 24-month period.
Experience & Qualifications
Source: Duvha Power Station Sulphuric Acid Storage and Dilution System Technical Evaluation Strategy Rev 03.pdfMandatory personnel qualifications:
Quality Management
Source: Duvha Power Station Sulphuric Acid Storage and Dilution System Technical Evaluation Strategy Rev 03.pdfQuality standards and references:
Compliance Requirements
Source: Duvha Power Station Sulphuric Acid Storage and Dilution System Technical Evaluation Strategy Rev 03.pdf (unknown)Mandatory compliance requirements:
Health & Safety
Source: Duvha Power Station Sulphuric Acid Storage and Dilution System Technical Evaluation Strategy Rev 03.pdfSafety considerations:
Requirements
Source: Duvha Power Station Sulphuric Acid Storage and Dilution System Technical Evaluation Strategy Rev 03.pdf (unknown)Mandatory technical requirements:
Section
Source: Duvha Power Station Sulphuric Acid Storage and Dilution System Technical Evaluation Strategy Rev 03.pdfTwo-stage evaluation:
Scoring scale:
Note: Scores of 1 or 3 are not applicable. Criteria are weighted by discipline.
Evaluation Criteria
Source: Environmental returnables for Acid Regent Project.pdf (unknown)General
Specific
Technical Specifications
Source: Environmental returnables for Acid Regent Project.pdf (unknown)Environmental returnables required for the project:
Environmental
Source: Environmental returnables for Acid Regent Project.pdfEnvironmental requirements for the project:
Submission Guidelines
Source: E-Tenderers E-Tendering Training Acknowledgement Form.pdf (unknown)Submit the completed E-Tendering Training Acknowledgement Form. Required details include: Enquiry number, Business name/JV, Contact Person, Landline, Cellphone, and Email address. The form must be signed by an authorized representative with designation and date.
Returnable Documents
Source: E-Tenderers E-Tendering Training Acknowledgement Form.pdf (unknown)Submit the E-Tendering Training Acknowledgement Form with the following completed fields: Enquiry number, Business name/JV, Contact Person, Landline, Cellphone, Email address, Tenderer’s Name, Authorized Signature, Designation, and Date. The form confirms self-training via the E-Tendering Noddy Guide, video, or clarification meeting.
Evaluation Criteria
Source: E-Tenderers E-Tendering Training Acknowledgement Form.pdf (unknown)Training
Applicants must certify completion of e-Tendering training.
Legal
Compliance with Eskom’s terms, including copyright and document handling rules.
Technical
Capability to execute the full scope (design to testing) of the sulphuric acid system upgrade.
Submission
Timely submission of all required forms and documentation by the closing date.
Description
Source: 240-109253698 CQP Template 2021.pdfThe project involves the Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade at Duvha Power Station over a 24-month period.
Scope of Work Categories (Mark applicable activities):
Tenderer must provide a full description of the Works Information as per NEC or FIDIC standards.
Contact Information
Source: 240-109253698 CQP Template 2021.pdf (unknown)Communication regarding quality-related issues must include: Supplier Representative details and contacts, E-mails, Minutes of Meetings, Fixed Contract Meetings, Weekly Progress Meetings and reporting. All documentation shall be submitted per the contract agreement.
Returnable Documents
Source: 240-109253698 CQP Template 2021.pdf (unknown)Documents to be submitted to Eskom include:
Prior to Commencement/Execution:
During and at Completion of Contract:
Captured in Supplier/Sub-Supplier QMS:
Records Control:
Databook Management:
Evaluation Criteria
Source: 240-109253698 CQP Template 2021.pdf (unknown)Experience
Applicants must demonstrate prior experience in similar projects, particularly in chemical storage and handling systems, preferably within the power generation sector.
Compliance
Compliance with South African and international quality standards (e.g., ISO 9001, SANS) is mandatory.
Technical Capability
The tenderer must have the technical capability to design, supply, install, and commission sulphuric acid storage and dilution systems.
Financial Stability
Proof of financial stability and ability to execute the project over 24 months may be required.
Legal And Regulatory
The tenderer must comply with all legal and regulatory requirements, including occupational health and safety (OHS) standards.
Technical Specifications
Source: 240-109253698 CQP Template 2021.pdf (unknown)Scope of Work includes: Design, Manufacturing, Supply and Delivery/Transportation, Construction/Installation/Maintenance, Commissioning, Professional Services, or Other. The tenderer must specify which activities are included in the Scope of Work (SOW).
Key Requirements:
Methodology
Source: 240-109253698 CQP Template 2021.pdfMethodology must include:
Experience & Qualifications
Source: 240-109253698 CQP Template 2021.pdfOrganogram must include:
Supplier must provide:
Health & Safety
Source: 240-109253698 CQP Template 2021.pdfMethod statements must include:
Contractual Terms
Source: 240-109253698 CQP Template 2021.pdfPost-delivery activities must include:
Section
Source: 240-109253698 CQP Template 2021.pdf (unknown)Communication channels between Supplier and Eskom must include:
Description
Source: (SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdfMarket Research: Open tender with no current suppliers identified.
Important Dates
Source: (SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdf (unknown)Closing date: 29 June 2026 at 10:00 AM (as per tender record).
SDL&I Implementation Schedule due: 28 days after contract award.
B-BBEE Improvement or Retention Plan due: 30 days after contract signing.
Contact Information
Source: (SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdf (unknown)Buyer: Sibusiso Mthimkhulu
Department: Duvha Power Station
Organization: Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Submission Guidelines
Source: (SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdf (unknown)Submit the following returnable documents to claim preference points:
SDL&I Objectives:
Retention and Penalties:
Returnable Documents
Source: (SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdf (unknown)Required documents to claim preference points:
Evaluation Criteria
Source: (SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdf (unknown)Mandatory
Preferential
Disqualification
Methodology
Source: (SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdfSkills Development:
Penalties and Security:
Pricing Schedule
Source: (SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdfTender response must separate local and imported components as per the Price Schedule. Local procurement content is total spending minus the imported component. Eskom’s target for local procurement content is 100%.
Financial Requirements
Source: (SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdf (unknown)Pricing:
Payment and Security:
Compliance Requirements
Source: (SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdf (unknown)B-BBEE Requirements:
CIDB Requirements:
B-BBEE Improvement Plan:
Local Content and Procurement:
Sworn Affidavit Validity:
B-BBEE Requirements
Source: (SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdf (unknown)B-BBEE Points Allocation (90/10 and 80/20 systems):
B-BBEE Improvement Plan:
Local Procurement and Designated Groups:
Sworn Affidavit Validity:
Special Conditions
Source: (SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdf (unknown)SDL&I Objectives:
Jobs:
Skills Development:
Reporting and Monitoring:
Retention and Penalties:
Requirements
Source: (SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdf (unknown)CIDB Skills Development:
Section
Source: (SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdfPoints are awarded on a 90/10 or 80/20 system (price vs. specific goals). Maximum of 10 (90/10) or 20 (80/20) points for B-BBEE status. Points are added to price points, rounded to two decimal places. Contract awarded to the highest scorer per Section 2(1)(f) of the Preferential Procurement Policy Framework Act. Failure to provide B-BBEE documentation results in scoring only out of 90 for price and 0 out of 10 for specific goals.
Description
Source: Supplier Quality Management_Returnables Latest catagory 2.xlsxThe tender involves the design, supply, installation, commissioning, and testing of a Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station over a 24-month period. Bidders must select the applicable category (e.g., Category 1, 2, 3, or 4) based on their quality management system capabilities and submit the corresponding returnable documents as specified in the template.
Submission Guidelines
Source: Supplier Quality Management_Returnables Latest catagory 2.xlsx (unknown)Submit the following returnable documents as per the selected category: Form A, ISO 9001:2015 certificate, internal and external management system audit reports (including Nonconformity, Correction, and/or Corrective Action Reports), Draft Contract Quality Plan (CQP) and Inspection and Test Plan (ITP) as per Scope of Works (Ref ISO 10005), and information for defined roles, responsibilities, and authorities. Save the completed template in PDF, sign, and preferably lock the sheet before submission. Adjust print area to fit on 1 page if necessary.
Evaluation Criteria
Source: Supplier Quality Management_Returnables Latest catagory 2.xlsx (unknown)General
Quality
Experience
Compliance Requirements
Source: Supplier Quality Management_Returnables Latest catagory 2.xlsx (unknown)ISO 9001:2015 certification is required, with the following conditions: Product/Service scoping on the certificate must be defined and relevant, the certificate must be issued by an approved and authorized certification authority with recognized international accreditation, and the certificate must be valid (not expired). Alternatively, evidence of an implemented QMS with documented information for roles, responsibilities, authorities, and audit reports (internal and external) may be accepted.
Submission Guidelines
Source: SAFETY REQUIREMENTS.pdf (unknown)Submission of returnable documents:
Returnable Documents
Source: SAFETY REQUIREMENTS.pdf (unknown)Tender returnables (must be submitted as Y=Yes, N=No, or N/A=Not Applicable):
Evaluation Criteria
Source: SAFETY REQUIREMENTS.pdf (unknown)Mandatory
Technical
Evaluation
Technical Specifications
Source: SAFETY REQUIREMENTS.pdf (unknown)Scope-specific training and competency requirements:
Site establishment requirements:
Quality Management
Source: SAFETY REQUIREMENTS.pdfOccupational hygiene and environmental monitoring requirements:
Financial Requirements
Source: SAFETY REQUIREMENTS.pdf (unknown)Health and Safety costing:
Personal Protective Clothing (PPC) requirements (per employee, per annum/month, SABS & CI approved):
Other OHS-related costs:
Compliance Requirements
Source: SAFETY REQUIREMENTS.pdf (unknown)Mandatory compliance documents and certifications:
Key personnel certifications and registrations (if applicable):
B-bbee:
Health & Safety
Source: SAFETY REQUIREMENTS.pdfHealth and Safety Plan requirements:
Baseline OHS Risk Assessment (BRA):
Personal Protective Equipment (PPE) and clothing (SABS & CI approved):
Additional OHS requirements:
Costing for Health and Safety:
Occupational Hygiene Surveys/Risk Assessments:
Policy and certifications:
Competency requirements (CVs and certificates must be submitted if applicable):
Contractual Terms
Source: SAFETY REQUIREMENTS.pdfContractual requirements:
Special Conditions
Source: SAFETY REQUIREMENTS.pdf (unknown)Special conditions:
Section
Source: SAFETY REQUIREMENTS.pdfEvaluation stages:
Required risk assessments and monitoring surveys:
Submission Guidelines
Source: Declaration of Shareholding or Beneficiaries Form.pdf (unknown)Submit a completed Declaration of Shareholding or Beneficiaries Form (T2.2a No 8). Required details include: names of all shareholders/beneficiaries, registration number of the company/trust, number/percentage of shares held, and disclosure of any shareholders/beneficiaries employed by or related to Eskom Holdings employees. The form must be signed and dated by an authorised representative.
Returnable Documents
Source: Declaration of Shareholding or Beneficiaries Form.pdf (unknown)Submit a completed Declaration of Shareholding or Beneficiaries Form. Required details: full names of all shareholders/beneficiaries (individuals or companies), company/trust registration number, number/percentage of shares held by each. Disclose if any shareholder/beneficiary is employed by or a close family member of an Eskom Holdings employee. If yes, provide details of their position in Eskom and their interest in your organisation. The form must be signed, dated, and include the designation of the authorised representative. *Close family member includes relationships by birth, marriage, domestic partnership, adoption, or guardianship.
Evaluation Criteria
Source: Declaration of Shareholding or Beneficiaries Form.pdf (unknown)Transparency
Applicants must provide transparent and complete shareholding/beneficiary information.
Compliance
Failure to disclose required information or misrepresentation may result in disqualification.
Legal Standing
Applicants must be legally registered entities (company or trust) with authorized representatives.
Ethical Standards
No undisclosed conflicts of interest with Eskom or its subsidiaries.
Important Dates
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown){"closingDate":"17 October 2021"}
Contact Information
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown){"name":null,"email":null,"phone":null,"department":"Supply Chain Management","address":null}
Evaluation Criteria
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Mandatory
Preferred
Exclusions
Technical Specifications
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Title: Supplier Quality Management: Document Identifier: 240-105658000
Alternative Reference QM 58
Number:
Area of Applicability: Eskom Holdings SOC Ltd
Functional Area: Quality Management
Revision: 3
Total Pages: 28
Next Review Date: October 2024
Disclosure Controlled Disclosure
Classification:
Compiled by Supported by Functional Authorized by
Responsibility
SA Sambo P Dondashe L Meyer K Pather
Chief Advisor Middle Manager Acting Senior General Manager
Quality Quality Manager Quality Risk and
Management Management Management Sustainability
Date: 15/10/2021 Date: 15/10/2021 Date: 15/10/2021 Date: 17 October 2021
EDC TN Formatted 15.10.2021
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Content
. Introduction ............................................................................................................................... 3
2. Supporting Clauses .................................................................................................................. 3
2.1 Scope ............................................................................................................................... 3
2.1.1 Purpose ................................................................................................................. 3
2.1.2 Applicability ........................................................................................................... 3
2.1.3 Effective date ......................................................................................................... 3
2.2 Normative/Informative References ................................................................................... 3
2.2.1 Normative .............................................................................................................. 3
2.2.2 Informative............................................................................................................. 3
2.3 Definitions ........................................................................................................................ 4
2.4 Abbreviations ................................................................................................................... 5
2.5 Roles and Responsibilities ............................................................................................... 6
2.6 Process for Monitoring ...................................................................................................... 6
2.7 Related/Supporting Documents ........................................................................................ 6
3. Pre-Contract Award: Quality Requirements .............................................................................. 7
3.1 Supplier and Sub-Supplier Quality Management System Requirements .......................... 7
3.2 Quality Plan ...................................................................................................................... 8
3.3 Contract Quality Plan........................................................................................................ 8
3.4 Quality Control Plan ....................................................................................................... 10
3.5 Pre-Contract Award: Quality Requirement ...................................................................... 13
3.6 Main Supplier and Sub-supplier Capability and Capacity Assessment ........................... 16
3.7 Post-Contract Award ...................................................................................................... 17
3.7.1 Contract Execution .............................................................................................. 17
3.7.2 Supplier Quality Performance Monitoring Phase ................................................. 18
3.7.3 Supplier Quality Audit .......................................................................................... 18
3.8 Standard Conditions ....................................................................................................... 19
3.8.1 Rights of Access .................................................................................................. 19
3.8.2 Eskom Rights to Information ................................................................................ 20
3.8.3 Preservation ........................................................................................................ 21
3.8.4 Quality Audits Related Conditions ....................................................................... 25
3.8.5 Management of Nonconformities and Nonconforming Outputs Identified by
Eskom ................................................................................................................. 25
3.8.6 Special Processes ............................................................................................... 26
4. Acceptance ............................................................................................................................. 27
5. Revisions ................................................................................................................................ 27
6. Development Team ................................................................................................................ 27
7. Acknowledgements ................................................................................................................ 28
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The intention of this specification is to specify and describe the minimum quality requirements for all
existing and potential Eskom suppliers and define the quality criteria for the selection, evaluation,
vendor registration, management, monitoring, assessment and auditing of suppliers. Eskom’s
position is to partner with suppliers who fully demonstrate commitment to the development,
implementation, and maintenance of a quality management system (QMS) that conforms to the
requirements of ISO 9001 standard. The priority is to encourage suppliers to continually improve
their QMS and enhance service delivery by implementing and conforming to the standard.
2. Supporting Clauses
2.1 Scope
2.1.1 Purpose
The purpose of this specification is to outline the requirements according to which suppliers shall
develop,
implement,
maintain, and
continually improve
a quality management system (QMS) based on ISO 9001, which should form the basis for conformity
to Eskom quality requirements and continually adhere to them throughout the duration of a contract
2.1.2 Applicability
This specification shall apply throughout Eskom Holdings Limited divisions, its subsidiaries,
suppliers, and sub-suppliers and shall form part of all Eskom requests for information (RFI)/ requests
for quotation (RFQ)/ requests for proposal (RFP), including contracts for the procurement of products
and services.
2.1.3 Effective date
Date of authorisation of the specification
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
[1] ISO 9001 Quality Management Systems – Requirements
[2] ISO 10005 Quality Management Systems – Guidelines for Quality Plans.
2.2.2 Informative
[3] ISO 9000 Quality Management Systems – Fundamentals and Vocabulary
[4] 32-727: Safety, Health, Environment, and Quality (SHEQ) Policy
[5] ISO 10006 Quality Management Systems – Guidelines for Quality Management in Projects
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
[6] ISO 9004 Quality Management – Quality of an Organisation – Guidance to Achieve Sustained
Success
[7] 32-1033: Eskom’s Procurement and Supply Chain Management Policy
[8] 32-1034: Eskom’s Procurement and Supply Chain Management Procedure
[9] PPPFA: Preferential Procurement Policy Framework Act, 2000 (Act No. )
[10] CIDB 1004: Best Practice Guideline A4: Evaluating Quality in Tender Submissions
[11] 240-12248652 Supplier Quality Management: List of Tender Returnables
[12] IAEA Safety Standard GS-R-3.1 Application of the Management System for Facilities and
Activities
[13] SANS 10845-1 Construction Procurement Part1: Processes, Methods and Procedures
2.3 Definitions
The vocabulary of ISO 9000 and the following definitions apply in the application of this specification.
2.3.1 Component: a constituent part of the product or sub-assembly of the product. The product
may comprise multiple individual components
2.3.2 Contract Quality Plan: a document of the supplier’s process for delivering the level of quality
required by the contract. It is a framework for the contractor’s process for delivering quality.
Purpose of a CQP is to outline how the results defined in the specifications will be achieved.
2.3.3 Hold Point: a predetermined stage in the quality control plan (QCP) beyond which work/
manufacturing shall not proceed without the attendance of, and written authorisation of, an
Eskom representative or Eskom inspection agency, whichever is applicable.
2.3.4 Intervention Points: those control points indicated by the various controlling bodies
concerned with the implementation of a specific QCP/ ITP. These can be in the form of
inspection, hold points, surveillances, witnesses, reviews and verifications.
2.3.5 Inspection Agency: an organisation or person appointed by Eskom for the purpose of
performing quality assurance/ quality control, monitoring, inspection and/ or expediting
services.
2.3.6 Level 1 Plant Items: equipment, whose failure has an effect on personnel safety and/ or
health, causes an environmental incident, cause a huge production loss or major equipment
damage. Equipment that are safety/ redundancy/ protective device or covered by statutory
regulations requirements.
2.3.7 Level 2 Plant Items: equipment, whose failure impacts plant availability and/or reliability,
causes significant costs or secondary damage.
2.3.8 Level 3 Plant Items: equipment that does not impact on personnel safety and/ or health,
environmental, cost, availability and/ or reliability of plant.
2.3.9 Nonconformity: a deficiency in material, composition, characteristic, or performance that
renders the quality of an item, component, or product unacceptable or indeterminate. The
term also covers a deficiency in, or deviation from/non-adherence to, the quality management
system requirements, prescribed production processes, and/or related documentation such
as procedures and instructions.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
2.3.10 Quality Plan: specification of the actions, responsibilities and associated resources to be
applied to a specific object.
2.3.11 Quality Control Plan: a document specifying the activities to be inspected throughout the
execution of the project, inclusive of test methods, procedures, and acceptance criteria (This
term is equivalent to QIP and ITP).
2.3.12 Requirement: the need or expectation that is stated, generally implied, or obligatory.
Requirements are generally specified in the purchase order and/or contract documentation,
but may not be limited to these.
2.3.13 Primary Plant (Power Plant): primary plant include High Voltage equipment situated inside
the control room (breakers, bus-bars, CT’s, VT’s and transformers).
2.3.14 Secondary Plant (Control Plant): secondary plant includes all equipment used to control
and protect the HV equipment on the primary plant side. (Protection, metering, AC/DC and
tele-control).
2.3.15 Special Process: is any production or service process which generates products or services
which cannot be measured, monitored, or verified prior to delivery and use.
2.3.16 Supplier: is a current or potential supplier, vendor, contractor, consultant, or service provider.
A supplier may be a natural or legal person and includes any employee acting within the
course and scope of his/her employment or any agent or manager acting for, or on behalf of,
or in the interests of, the person registered as supplier on the Eskom supplier database.
2.3.17 Sub-supplier: an organisation that provides a product/service to the supplier and/or that
enters into a subcontract and assumes some of the obligations of the supplier or prime
contractor.
2.3.18 Witness Point: a predetermined stage in the quality control plan where and inspection
activity will take place. Work may proceed, provided Eskom or its inspection agency has been
formally notified and confirmed that inspection is waived.
2.4 Abbreviations
Abbreviation Explanation
AIA Approved Inspection Authority
CA Corrective Action
CQP Contract Quality Plan
FIDIC Federation Internationale Des Ingenieurs- Conseils
FMECA Failure Mode, Effects and Criticality Analysis
HAZOP Hazard and Operability Study
ISO International Organisation for Standardisation
ITP Inspection and Test Plan
NC Nonconformity
NDT Non Destructive Testing
PMI Positive Material Identification
QCP Quality Control Plan
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Abbreviation Explanation
QMS Quality Management System
PQP Project Quality Plan
RFI Request for Information
RFQ Request for Quotation
RFP Request for Proposal
SHEQ Safety, Health, Environment, and Quality
SETA Skills Education Training Authorities
WPS Welding procedure specifications
WQR Welder’s Qualification Record
2.5 Roles and Responsibilities
Eskom Quality representative/ professional will select applicable requirements for existing and
potential Eskom suppliers using Form A (Tender and Contract Quality Requirements for Supplier
Quality Management: Specification 240-105658000/ QM 58 and Quality Requirements for ISO 9001
Standard).
The existing and/ or potential suppliers must complete, sign and return Form A with the other
returnable as listed in the List of Tender Returnable document (240-12248652). Other roles and
responsibilities for this standard are defined within the text of this specification.
2.6 Process for Monitoring
The application of this specification throughout Eskom shall be audited as per the management
system audit schedule.
2.7 Related/Supporting Documents
The documents superseded by this specification: all divisional and business unit supplier quality
requirements standards and/or specifications.
Forms and templates:
[1] 240-68099512 Tender and Contract Quality Requirements for Supplier Quality Management
Specification 240-105658000/ QM 58 and Quality Requirements for ISO 9001 Standard (Form
A)
[2] 240-109253698 Template for a Typical Contract Quality Plan
[3] 240-109253302 Quality Control Plan/Inspection and Test Plan
[4] 240-126469599 Method Statement Template.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3. Pre-Contract Award: Quality Requirements
The quality assessment criteria and Form A of this specification will be selected and completed by
an Eskom Quality representative/ professional who will identify the applicable supplier quality
requirements to be met.
Form A of this specification must also be completed and signed by the supplier responding to an
Eskom invitation to tender, in order to acknowledge and accept Eskom Supplier Quality requirements
as per this specification and ISO 9001 Standard or any additional quality requirements specific to
the scope of work.
3.1 Supplier and Sub-Supplier Quality Management System Requirements
3.1.1 The supplier and sub-supplier shall develop, implement, maintain and improve a formal QMS
that conforms to the latest ISO 9001 standard or any applicable standard of QMS (latest
applicable revision) and in accordance with the requirements of this specification.
3.1.2 Such a formal system shall consist of the appropriate documented information required by
ISO 9001 and may include a quality manual, quality plans, work procedures, work
instructions, method statements, work flow documentation, etc., as the case may be. This
requirement constitutes the most basic QMS requirements.
3.1.3 Unless specifically excluded from the quality list of tender returnable, as per the categories of
quality requirements (Category 1, 2, 3, or 4), such a QMS shall carry a valid ISO 9001
certificate from an accredited certification body, as indicated in the applicable Eskom
invitation (this requirement applies equally to both the supplier and any/ all manufacturing
third-party organisations mentioned above).
3.1.4 Unless specifically excluded in the quality list of tender returnable, as per the categories of
quality requirements (Category 1, 2, 3, or 4), the supplier shall have a fully developed,
documented, implemented, reviewed and maintained QMS that complies with the
requirements of ISO 9001 standard or any applicable standard of QMS. In the event that the
main supplier invariably requires the assistance of a sub-supplier in order to realise its own
supply obligations. The aforementioned requirement applies equally in all cases where any
such sub-supplier’s scope of responsibility includes the provision of any of the following
activities, namely, design and development, manufacturing, maintenance, testing, storage,
delivery, installation, commissioning, and project management, or in the cases the supplier
name changes, mergers, acquisitions and/ or cessions. Eskom Quality department must
ensure that the changed entity can still fulfil the requirements as set out in the contract
documentation.
3.1.5 Eskom reserves the right to request and perform necessary assessments at sub-supplier
facilities.
3.1.6 The main supplier shall be responsible for defining and managing the specific quality
assurance and control elements applicable to the respective sub-supplier’s scope of
work/supply and ensure that its sub-supplier(s) quality programmes support Eskom
requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.1.7 The supplier shall inform Eskom of any proposed changes to the QMS or staff that will affect
the quality system prior to implementation of these changes.
3.1.8 The main supplier shall develop and implement a performance management programme for
their sub-supplier. The programme shall include, but not limited to:
Verification of the QMS
Audits and surveillances
Regular assessment of the CQPs and reviews of QCPs.
NC and Defect Management
Inspection and test plans
Risk management
3.2 Quality Plan
The information in this section constitutes the minimum requirements for a quality plan.
3.2.1 Where specified in the Evaluation Criteria and/ or quality list of tender returnables , as per the
categories of quality requirements (Category 1, 2, 3, or 4); all individual products, services
and processes shall have a documented, implemented, reviewed and maintained contract
quality plan and/or quality control plan (inspection and test plan).
3.2.2 Where specified in the evaluation criteria and/ or quality list of tender returnables. All
production and/ or service provision shall be carried out in accordance with a documented
and agreed contract quality plan (CQP) and/ or quality control plan (QCP)/ inspection and test
plan (ITP).
3.2.3 The supplier shall plan for the required quality-related activities and interfaces within the
supplier’s quality system in order to demonstrate its ability towards both controlling and
meeting specified Eskom requirements.
Note 1: Contract Quality Plan should address the quality assurance elements related to the scope
of work and/ or technical specification.
Note 2: Quality Control Plan (QCP)/ Inspection and Test Plan (ITP) should address the quality
control elements related to the scope of work and/ or technical specification.
3.3 Contract Quality Plan
The main supplier shall require sub-suppliers to submit project quality plans (PQPs)/ contract quality
plans (CQPs) and associated documentation in accordance with the requirements of project QMS
processes applicable to the sub-supplier’s scope of work.
The supplier shall, where applicable, based on scope of work criticality, ensure that procurement
documents clearly and unambiguously require sub-supplier submission of a sub-supplier CQP for
supplier and Eskom review.
The main supplier shall ensure that sub-supplier CQPs are developed and implemented in
accordance with the ISO 10005 Quality Management System Guidelines for Quality Plans. In
addition to the elements specified in ISO 10005, the supplier’s and/ or sub-suppliers’ CQPs shall
include the following (as applicable):
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.3.1 The management of records, including material tests, positive material identification (PMI)
testing, material certification, etc.
3.3.2 The provision for free and uninhibited access by the supplier and/or personnel at the time of
inspection.
3.3.3 The proposals for submission of final documentation, the final manufacturing data book, prior
to shipment.
3.3.4 The special processes related to welding: management of the welder’s qualification record
(WQR), welding procedure specifications (WPS), and procedures qualification records (PQR)
that will be used in the performance of work for supplier review and acceptance prior to
commencing manufacture. Welders shall be qualified to the specified Codes of Construction
for the applicable procedures. The requirements for qualification shall be specified by the
supplier, and welder records shall be maintained by sub-suppliers performing the work.
3.3.5 The special installation procedures and other required fabrication or manufacturing
procedures (that is, those required for post-weld heat treatment, tube rolling, coatings, etc.)
that will be used in the performance of work shall require supplier review and acceptance
prior to commencing manufacture. The personnel carrying out special processes (for
example, NDE, welding, coating, heat treatment, etc.) where the results cannot be fully
verified by subsequent inspection and test shall be suitably qualified and, where applicable,
registered with statutory bodies as legally required, that is, as radiographic workers to conduct
radiography. The requirements for the qualification shall be specified, and personnel records
shall be maintained in accordance with the Project Quality Personnel Qualification
Specification and, where applicable, legal requirements.
3.3.6 The personnel required to perform special processes shall be certified competent through a
certificate of competency in accordance with the company’s internal training management
and competency control procedures or an external certification body (for example, NDT)
through an accredited service provider as per Skills Education Training Authorities (SETA)
requirements.
3.3.7 All personnel who perform activities that affect quality shall have their training needs identified
and documented. The required training shall be implemented in accordance with the
company’s training management and competency control procedures. All the training
certificates shall meet the SETA requirements in terms of having the unit standard completed
and the accreditation number of the service providers.
3.3.8 Instructions and requirements for equipment and materials storage, preservation, and
maintenance, including identification of materials required for preservation and maintenance,
are to be provided sufficiently prior to receipt (prior to shipment or earlier) to ensure that
appropriate resources are available at the time of delivery.
3.3.9 Specific quality monitoring and verification activities are to be undertaken on the supplier’s
sub-suppliers by Eskom or it agent.
3.3.10 The CQP information need to include, but not limited to:
Spells out the aspects of the QMS to be applied within a specific Eskom project, and the
methods to be utilised to ensure quality.
Outline the resources, the communication channels, applicable documents and records to be
generated.
Management Authority and Responsibility from both supplier and client need to outline in the
Cqp.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
List of documents and records that will be used and submitted during the execution of the
project.
Communications channels should include contact person and contact details
Monitoring & measurement procedures for activities need to be indicated.
3.3.11 The main supplier and sub-supplier CQPs shall comply with the Eskom Quality Requirements
Specifications and shall be submitted prior to the initial scope of work kick-off or initial pre-
fabrication meeting and prior to commencement of manufacturing, whichever is earlier.
3.3.12 The Eskom template for CQP provided shall be used as guideline, where the supplier does
not have a CQP template.
3.4 Quality Control Plan
The supplier shall develop and implement processes and procedures that efficiently and effectively
monitor, verify and document the quality of the scope of work for deliverables.
The main supplier shall ensure that sub-supplier QCPs/ ITPs are prepared at a level of detail
sufficient to address all quality-control-related activities in a chronological order, from contract review
through materials verification, manufacturing, fabrication, assembly, final testing, commissioning,
hand-over documentation, and certification. In addition, the supplier shall ensure compliance with
the following requirements:
3.4.1 All stages of manufacturing, fabrication, assembly and installation shall be controlled by a
supplier’s QCP/ ITP that clearly and unambiguously identifies the quality verifications to be
performed and special attention to controls related to critical products and services.
3.4.2 QCP/ ITP shall be reviewed and accepted by Eskom, its inspection authority or agency, and
they shall allow for the insertion of Eskom specific requirements, including hold and witness
points prior to the commencement of work.
3.4.3 Subsequent changes to the Eskom accepted QCP/ ITP shall require Eskom, its inspection
authority or agency’s agreement prior to the commencement of work involving an activity
affected by such changes.
3.4.4 The ITPs should cover materials certification, fabrication works, in-process inspections, final
acceptance tests, packaging and pre- shipment/ transportation, shipping/ transportation
inspections where contracted, preservation, site acceptance tests, construction and erection
works, and pre-commissioning and commissioning tests.
3.4.5 All sub-supplier QCP/ ITP activity shall be performed using an Eskom-accepted supplier
Qcp/ itp.
3.4.6 All applicable codes, standards, and relevant acceptance criteria documents are available at
the work location, and Eskom representatives on site shall have on-going access to this
information. Workplace documentation shall be available in English and in any workforce-
appropriate language.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.4.7 Where activities subject to inspection and test procedures are to be undertaken by a sub-
supplier, the QCP/ ITP shall make reference to this fact and shall include descriptive details
of the sub-supplier’s involvement. A separate QCP/ ITP shall be required for each sub-
supplier scope of work.
3.4.8 The supplier shall be ultimately accountable and responsible for the development and proper
implementation of all sub-supplier QCPs/ ITPs, including those reviewed or developed by
sub-suppliers.
3.4.9 Eskom reserves the right to select intervention points on QCPs/ ITPs for Eskom oversight of
selected functions and to perform surveillance or audits of the work.
3.4.10 Once signed, the ITPs and QCPs become addendums to the main contract. These ITPs can
be reviewed at Eskom’s discretion based on its assessment of the supplier’s performance or
other risks.
3.4.11 A QCP/ ITP shall contain the following information:
Eskom contract number and title
The supplier’s order number
Identification of the area of works/contract
Description of the work, with components, item number, and activity date
QCP/ITP unique number
A list of the sequence of operations, including inspection and tests
The identification of the specification, drawing number, or procedure for each operation,
with reference to the relevant criticality risk rating
The acceptance criteria, with reference to the technical specification, in-house, national, or
international standard, with the relevant clause number for each operation
The inspection and test activities that the supplier has nominated for its intervention points
Provision for the inclusion of intervention points nominated by Eskom and/or its authority/
agency
Provision for intervention point acceptance by date and signature for all parties having
intervention in the plan
Inspection and test records to be generated by the supplier for each operation and an
indication of records to be provided to Eskom (as applicable)
3.4.12 The main supplier shall require sub-suppliers to submit QCPs/ ITPs and associated
documentation applicable to the sub-supplier scope of work. Any changes made to the QCP
after submission must be resubmitted to Eskom for further review. The supplier shall ensure
that all sub-supplier QCPs/ ITPs are in compliance with the Eskom Quality Requirements
Specifications, including, but not limited to, the following requirements:
Clear and unambiguous description of the equipment and location(s) at which each activity
will take place, including facility location(s)
Identification of quality verification activity and stage
The details of reference documents, procedures, or method statements to be utilised in
performance of the activity, including specific reference to actual sections and pages of
procedures, standards, instructions, specifications, etc.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Definition of acceptance criteria
Listing of certifying or verifying documents generated to provide evidence of compliance
with specified requirements; documents are to be provided using the proper Eskom
document numbering requirements
Identification of main supplier and sub-supplier (where applicable) third-party/approved
inspection authority (AIA) and Eskom inspection activities defined in terms of witness, hold,
document review, and verification monitoring points and provision for sign-off of each of the
above-mentioned parties for each intervention point
Qualification requirements for quality control inspectors, including any third-party/AIA
inspectors
Listing of all proposed test procedures
Acceptance criteria for each inspection or test in alignment with specified tolerances
A section for signed acceptance of the QC/ITP by the supplier, sub-supplier (where
applicable), and Eskom prior to commencement of work
Inspection or testing intervention points, including, but not limited to, factory acceptance test
and package acceptance test, witness, and hold points
3.4.13 A quality kick-off meeting will be held at the start of the contract and, if required, at the start
of each subsequent phase.
The supplier shall arrange coordination meetings with Eskom prior to placement of orders
for items or equipment to ensure that all technical and commercial requirements are clear
and understood. Fourteen days’ advance notice of meetings shall be given to Eskom.
Supplier inspection personnel, including inspection agency personnel, shall be competent
and qualified to perform inspection and testing assignments. Mobilisation of all such
personnel shall be in compliance with the Project Quality Personnel Qualification
Specification.
3.4.14 Where QCP/ ITP is applicable, the supplier shall ensure that sub-suppliers are provided with
comprehensive, clearly written, and unambiguous inspection and testing protocols, including
processes, procedures, and methods that shall include, but not be limited to, the following:
Requirements for inspection checklists and inspection assignments, with lists of items to be
inspected
An inspection and testing report format, report content, schedule for report processing and
distribution, and report retention requirements
Inspection and test report results response tracking (log) and resolution of nonconformity in
inspection and test processes, procedures, or methods and nonconformity identified in
inspection and test results
Associated Failure Mode, Effects and Criticality Analysis (FMECA) reports relating to the
equipment and sub-systems (if applicable)
Hazard and Operability Study (HAZOP) report, as applicable
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.4.15 The supplier shall establish processes and procedures for formal assessment of sub-supplier
inspection and testing programmes. These shall include review of sub-supplier inspection
reports and other quality control documentation. Additional formal assessment of
manufacturing, fabrication, and assembly facility operations shall be conducted by the
supplier to ensure continuing suitability, adequacy, and effectiveness of the sub-supplier’s
inspection and testing programmes. Assessment frequency shall be established in
consideration of the sub-supplier scope of work, criticality of scope of work deliverables, and
performance information. The assessment scope and schedule shall be developed in
consultation with Eskom.
3.4.16 Supplier processes and procedures for verification of supplier and sub-supplier purchased
product compliance with specifications shall obtain document return/review status prior to
implementation.
3.4.17 The objective is to finalise any outstanding procedural or other issues before proceeding to
deliver the works.
3.4.18 Eskom, in consultation with the supplier, develops an agenda for the meeting, and Eskom will
keep minutes of these meetings.
3.4.19 Mandatory pre-inspection meetings will be convened by Eskom or its inspection agency or
AIA to be attended by the supplier’s and sub-supplier’s representatives, including their quality
representatives who will be involved in the works, and records are to be kept.
3.4.20 Eskom reserves the right to appoint resident quality inspectors who can be based at the
supplier’s or sub-supplier’s premises and on site where the work is being performed. The
supplier is expected to provide workspace at no cost to Eskom for the inspector, as required.
3.4.21 Eskom may appoint any organisation it prefers to perform quality assurance and quality
control activities, either in the capacity as an AIA or inspection agency, on the works
contracted to the supplier, and the supplier or its sub-suppliers may not object, prevent,
hinder, undermine, circumvent, question, discredit, or in any way make it impossible for such
organisation to carry out its work on behalf of Eskom.
3.4.22 The Eskom template for QCP/ ITP provided shall be used as guideline, where the supplier
does not have a QCP/ ITP template.
3.5 Pre-Contract Award: Quality Requirement
3.5.1 Main Supplier and Sub-supplier Categories
Eskom supplier quality requirements for all existing and potential suppliers and sub-suppliers are
classified into four categories (category 1, 2, 3 and 4). Suppliers must prepare and submit quality
documentation as per the tender selected category (indicated in Form A) using the list of tender
returnables document.
NOTE: Only one (1) category must be applicable per procurement process e.g. [Eskom requests for
information (RFI)/ requests for quotation (RFQ)/ requests for proposal (RFP), including contracts for
the procurement of products and services].
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The following are the minimum returnable documentation for Categories 1 to 4:
3.5.2 Category 1: Quality Requirements
The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
The supplier shall submit a valid copy of ISO 9001 or any applicable certificate of a QMS (the
latest applicable revision). The QMS should drive the supplier’s business management
processes to ensure that all of Eskom’s requirements are fully met on a consistent basis.
The supplier shall submit the latest copy of the management system internal and external
audit reports. The audit reports must include, if applicable, nonconformity identified, and the
resulting remedial actions (correction and/ or corrective action reports).
The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
Where applicable; the supplier shall submit a draft, or an example of an inspection and test
plan (ITP) or quality control plan (QCP) on similar and/ or previous work done.
The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
The supplier shall submit documented information retained (records) of management review
meetings that include agenda, meeting minutes, attendance registers, reports, presentations,
etc.
Note: specific requirements per tender will be selected using the List of Tender Returnable
documents (240-12248652).
3.5.3 Category 2: Quality Requirements
The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
The supplier shall submit objective evidence of a developed, implemented and maintained QMS
that complies with ISO 9001 or any applicable standard of quality management system (the latest
applicable revision). The following documents (approved/ signed copies) shall be submitted:
Quality Management System manual or a documented information that have defines and
describes the QMS and its scope
Quality Policy, aligned with the supplier’s strategic direction (documented information)
Quality Objectives (documented information)
Control of documented information (both maintain and retain documented information )
Internal audit procedure (documented information)
Control of nonconforming outputs (documented information)
Nonconformity and Corrective action procedure (documented information)
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The QMS should drive all the supplier’s business management processes to ensure that all of
Eskom’s requirements are fully met on a consistent basis.
The supplier shall submit the latest copy of the management system internal audit reports. The
audit reports must include, if applicable, nonconformity identified, and the resulting remedial
actions (correction and/ or corrective action reports).
The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
Where applicable; the supplier shall submit an example of inspection and test plan (ITP) or
quality control plan (QCP) on similar or previous work done.
The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
The supplier shall submit documented information retained (records) of management review
meetings that include agenda, meeting minutes, attendance registers, reports, presentations,
etc.
Note: specific requirements per tender will be selected using the List of Tender Returnable
document (240-12248652).
3.5.4 Category 3: Quality Requirements
The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
The supplier shall submit objective evidence of a developed QMS that complies with ISO 9001
(or the latest applicable revision). The following documented information (approved/ signed
copies) shall be submitted:
o Quality management system manual or a (documented information) that have
defines and describes the QMS and its scope
o Quality Policy, aligned with the supplier’s strategic direction (documented
information)
o Quality Objectives (documented information)
o Control of documented information (both maintain and retain documented
information )
o Internal audit procedure (documented information)
o Control of nonconforming outputs (documented information)
o Nonconformity and Corrective action procedure (documented information)
The QMS should drive all the supplier’s business management processes to ensure that all of
Eskom’s requirements are fully met on a consistent basis.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
Where applicable; the supplier shall submit an example inspection and test plan (ITP) or
quality control plan (QCP).
The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
NB: specific requirements per tender will be selected using the List of Tender Returnables
document (240-12248652).
3.5.5 Category 4: Quality Requirements
The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
The supplier shall submit a quality method statement based on ISO 9001 and specific to the
scope of work.
The quality method statement should address all the supplier’s business management
processes to ensure that all of Eskom’s requirements are fully met on a consistent basis.
The supplier shall submit a signed/ approved quality policy (aligned with the supplier’s strategic
direction). (documented information)
The supplier shall submit a copy of quality objectives. (documented information)
The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
The supplier shall submit a copy of the documented information for roles, responsibilities and
authorities, specific to the project/ scope of work/ technical requirements. Examples of relevant
documented information are; organization charts, job descriptions, work instructions, duty
statements, manuals, procedures.
Note: specific requirements per tender will be selected using the List of Tender Returnables
document (240-12248652).
3.6 Main Supplier and Sub-supplier Capability and Capacity Assessment
Supplier capability and capacity assessments shall be performed prior to contract award on potential
suppliers participating in Eskom Holdings procurement process to:
provide products and services with high risk to operational sustainability
work on critical plant and equipment
supply of critical plant items or components
provide special processes
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
All sub-suppliers used by the main supplier/ contractor, performing work on Eskom critical plant
equipment, supplying commodities and providing specialised services shall be subjected to the
capability and capacity assessment.
Critical plant includes the following:
Generation Level 1 & 2 plant
Transmission and Distribution Power Plant & Control Plant
Mega Projects
All potential quality risks identified will be included in the assessment report provided for the tender
evaluation.
Note: Form A (Enquiry/ Contract/ Quality Requirements for Supplier Quality Management:
Specification 240-105658000/ QM 58 and ISO 9001) will be used to select and indicate whether
capability and capacity assessment will be conducted.
3.7 Post-Contract Award
3.7.1 Contract Execution
The supplier shall submit the following documents within 30 days or as per stated timeline after the
contract date, prior to the commencement of work, for acceptance by Eskom:
The supplier shall complete a QCP before contract award. This shall be reviewed and
signed off by Eskom within 30 days or as per stated timeline after contract award.
The supplier shall complete a quality control plan and ITP(s) for review and acceptance by
Eskom prior to the commencement of any work, inclusive of subcontracted work, within 30
days or as per stated timeline after contract award.
The sub-supplier QCP/ ITP shall be submitted for review and comment by the supplier and
by Eskom within 30 days or as per stated timeline after the award of the tender. All supplier
and Eskom comments shall be resolved prior to commencing work.
The equipment lists and an indication of pressurised components and systems.
Note: These plans are to be compiled in line with Eskom’s requirements and will have to be
discussed with, and approved by, Eskom prior to any work commencing.
Correspondence shall be directed to the project manager, and periodic quality review
meetings shall be convened by Eskom with the supplier.
The mandatory quality review meetings are to be convened by the nominated project quality
manager or his/her representative for the contract.
Monthly quality performance and management reports are to be prepared by the supplier
during contract execution. The content of these reports shall be agreed by Eskom when
submitted to Eskom on a monthly basis.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.7.2 Supplier Quality Performance Monitoring Phase
During the contract execution phase, suppliers shall be monitored by Eskom for performance on
quality-related aspects.
The outcomes of such monitoring will enable Eskom to take any appropriate actions pertaining to
the supplier.
The monitoring shall be carried out periodically by Eskom or at predetermined intervals during the
execution of a contract using agreed key performance indicators. The monitored key performance
areas include the following:
CQP and QCP /ITP
Delivery
Design
Cost
Management system
Subsequent key performance indicators associated with these areas will include the following:
Nonconformity monitoring
Audit and assessment evaluation scoring
Management system compliance and accreditation
Achievement of delivery targets as per contractual agreements
Process improvements
Correction and corrective action response and closure
3.7.3 Supplier Quality Audit
3.7.3.1 Quality audits and related quality performance reviews are intended to provide an objective
evaluation of compliance with performance expectations defined in this specification, in the
supplier contract quality plan (CQP), and in any other project scope of work specification.
3.7.3.2 Quality audits and related quality performance reviews include, but are not limited to, any
quality or other project functional area audits, assessments, verification of compliance
reviews, surveillance, inspections, or other interim or final assessments of scope of work
deliverables provided by the supplier or sub-suppliers
3.7.3.3 Quality audits and related quality performance reviews are intended to provide an objective
evaluation of compliance with performance expectations defined in this specification, in the
supplier contract quality plan (CQP), and in any other project scope of work specification.
3.7.3.4 Quality audits and related quality performance reviews include, but are not limited to, any
quality or other project functional area audits, assessments, verification of compliance
reviews, surveillance, inspections, or other interim or final assessments of scope of work
deliverables provided by the supplier or sub-suppliers.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.7.3.5 Quality audits and related quality performance reviews shall be carried out by trained,
accredited, and experienced personnel in accordance with procedures documented in the
Cqp.
3.7.3.6 The supplier shall submit, for Eskom review, documented processes for conducting project
scope of work quality audits and related quality performance reviews. Supplier quality audits
and related quality performance review processes shall be designed to address evaluation
of progress towards completion of project functional area deliverables as well as final
deliverable quality.
3.7.3.7 The supplier shall provide a schedule of anticipated quality audits covering all functional
areas and related quality performance reviews at the time of first post-contract award CQP
submission.
3.8 Standard Conditions
3.8.1 Rights of Access
Eskom:
3.8.1.1 shall be granted electronic and hard-copy access to all quality plans, procedures,
documentation, and other quality records relating to the work, including, but not limited to,
data extracts;
3.8.1.2 reserves the right to review, inspect, and audit any or all parts of the supplier’s QMS, as well
as any documentation, materials, or equipment associated with the work, at any time or
project work location; and
3.8.1.3 reserves the right to carry out assessments and audits on all new suppliers and sub-
suppliers.
The supplier:
3.8.1.4 shall support Eskom’s effort to monitor, verify, and/or witness any activities associated with
the work at any time;
3.8.1.5 shall cooperate with Eskom requests for documentation, records, and inspection and
witnessing. Eskom participation in audits, appraisals, assessment of plans, and verification
shall be conducted at no extra cost to Eskom;
3.8.1.6 shall ensure that a sub-supplier provides access to Eskom to all work procedures, records,
and supporting documentation through provision of access to view and photocopy, as
required, to support verification of scope of work requirements. Access shall include the
ability to photograph Eskom equipment, systems, system components, materials, etc.;
3.8.1.7 shall provide access to all quality-related information pertaining to activities performed by
itself or sub-suppliers, where Eskom might not have participated in the witnessing of their
quality assurance or control (this refers to inspections, audits, etc. performed by the supplier
on its own sub-suppliers);
3.8.1.8 shall allow Eskom to assess, audit, approve, or reject any sub-suppliers employed by
Eskom’s suppliers to assist with the product and/or service delivery to Eskom; and
3.8.1.9 shall ensure that the above requirements flow down to sub-suppliers.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.2 Eskom Rights to Information
3.8.2.1 To expect that the works will be conducted in accordance with the contract between the
parties.
3.8.2.2 To have access to the supplier’s information as determined by applicable legislation.
3.8.2.3 Eskom reserves the right to oversee the supplier’s audit programmes by participating in
selected audits as an observer and by assessing the supplier during key work stages.
Eskom will coordinate with the supplier to develop an oversight schedule aligned with the
supplier’s audit schedule.
3.8.2.4 To obtain access to any audit reports of audits performed by the supplier reflected in the
audit programme.
3.8.2.5 To conduct independent quality audits during all phases of the contract, and the supplier
shall provide all resources to support these activities.
3.8.2.6 Eskom shall have the right to participate in, or request that, a technical investigation be
launched and conducted at the supplier’s and sub-suppliers’ premises or other sites when
risk to Eskom products or service deliverables is identified.
3.8.2.7 To participate in, and/or lead, investigations related to incidents involving its products.
3.8.2.8 To require from suppliers to be responsible for the cost of re-inspections.
3.8.2.9 To withhold payment from suppliers as a result of outstanding nonconformities, irrespective
of the agreed payment schedule and in accordance with the conditions of contract.
3.8.2.10 Shall be granted electronic and hard-copy access to all quality plans, procedures,
documentation, and other quality records relating to the work, including, but not limited to,
data extracts.
3.8.2.11 Reserves the right to review, inspect, and audit any or all parts of the supplier’s QMS, as
well as any documentation, materials, or equipment associated with the work, at any time or
project work location.
3.8.2.12 Shall carry out assessments and audits on all new suppliers and sub-suppliers.
3.8.2.13 Reserves the right to appoint resident quality inspectors who can be based at the supplier’s
or sub-supplier’s premises and on site where the work is being performed.
3.8.2.14 Reserves the right to select intervention points within all developed supplier QCPs/ ITPs
for Eskom oversight of selected functions and to perform surveillance or audits of the work.
3.8.2.15 Shall be given access at all reasonable times before, during, and after manufacture and
before delivery, construction, erection, and commissioning to measure, test, and inspect the
products and workmanship, as necessary, at the supplier’s premises and at Eskom sites.
3.8.2.16 Reserves the right to suspend any pending deliveries by the issuing of a cease delivery
order at any time and for any portion of the work that is not being performed in accordance
with the specified/agreed requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3 Preservation
The supplier shall develop and implement a comprehensive preservation programme consisting of
plans, processes, procedures and actions undertaken for the purpose of planning for and
maintenance of material deliverables quality. The supplier preservation programme scope includes,
but is not limited to, the following:
3.8.3.1 Engagement of personnel suitably qualified for oversight of, and (as required) direct
implementation of, preservation programme requirements.
3.8.3.2 Development and implementation of preservation programme training appropriate to work
need.
3.8.3.3 Eskom may make use of its appointed service provider tasked to provide a full suite of
services encompassing an online monitoring system and asset tracking during, but not
limited to the following stages: inspections, testing, shipping, transportation, storage, and
commissioning. The supplier is to enable full access during all of these stages in order to
allow the installation of the devices on Eskom-identified products and equipment, which
include the sub-supplier’s testing facilities, processing plant, and any other processes
deemed important towards effective and efficient quality control.
3.8.3.4 Eskom seeks cooperation between the supplier’s designers and those of Eskom’s service
provider in ensuring seamless installation of the device and other associated installations.
Moreover, there is also a need to integrate data flows and systems between Eskom and the
supplier. Further details are included in the Eskom specifications and works information.
3.8.3.5 Review and tracking of compliance with Eskom and supplier engineering specification of
preservation requirements.
3.8.3.6 Review and tracking of compliance with sub-supplier provided preservation requirements
and recommendations.
3.8.3.7 Evaluation of prospective temporary and longer-term material storage sites for consistency
with preservation programme expectations.
3.8.3.8 Preservation work plan development and plan execution performance evaluation of all
parties engaged for provision of material transportation, handling, or storage services.
3.8.3.9 Oversight of material quality preservation plan preparation and plan execution performance
at all work locations.
3.8.3.10 Development of a preservation programme records management process, in compliance
with Eskom information management requirements, which comprehensively addresses
generation, maintenance, and ready access by Eskom to all preservation programme
records.
3.8.3.11 The supplier shall deploy a clearly defined documented programme providing for
identification of all physical asset pre-operation preservation of quality requirements. In this
reference, the term “physical assets” should be understood to include bulk materials,
including consumable items, equipment systems, system components, and any other
procured or supplied materials or equipment transferred to project control, but not deployed
for operational purposes.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3.12 Where the project responsibility for equipment and materials management has been
formally delegated, the supplier’s preservation programme shall ensure clear and
unambiguous communication of pre-operation preservation of goods quality requirements
to sub-suppliers.
3.8.3.13 The supplier’s preservation programme shall clearly and unambiguously document
processes and procedures for efficient and effective monitoring of compliance with
programme requirements.
3.8.3.14 Compliance monitoring shall commence with ensuring comprehensive consideration of
preservation requirements in the engineering instruction and subsequent inclusion of said
instruction in procurement documentation and shall be applicable until such time as
equipment or materials have been incorporated in an operating or operational system or
structure.
3.8.3.15 Compliance evaluation frequency shall anticipate transfer of tactical-level responsibility for
management of preservation responsibilities between project functional areas, for example,
procurement to logistics, logistics to fabrication, fabrication to logistics, logistics to
construction, etc., and shall, in similar fashion, anticipate transfer of support for tactical-level
responsibility between various subcontracted service providers.
3.8.3.16 Supplier engineering shall ensure that preservation requirements for scope of work
systems, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented and that preservation requirements are efficiently and
effectively communicated to project procurement, logistics, construction management,
quality, security, and other project functional areas, as required, for efficient and effective
implementation of preservation requirements. This shall take the form of a preservation
programme applicable to all systems, system components, equipment, materials, customer-
supplied materials, and other goods procured or managed under the scope of work.
3.8.3.17 The supplier’s preservation management programme shall clearly and unambiguously
address temporary, long-term, and in-transit preservation requirements, including, but not
limited to:
requirements for protection against, or insulation from, atmospheric conditions,
sunlight, temperature, soil, dust, humidity, salt spray, corrosive atmospheres, or
other physical environment conditions;
detailed procedures for application, use, monitoring, and maintenance of coatings,
coverings, fasteners, lines, and other components for internal and external weather
proofing;
requirements for electrical grounding or isolation;
requirements for internal or external environment creation, for example, inert gas
charging, heating, cooling, etc., inclusive of gas storage, electric power supply, etc.;
detailed procedures for initial set-up, charging, activation, and maintenance of
internal atmosphere generation, regeneration, monitoring, and relieving systems, for
example, inert gas management systems;
requirements for protection against, or insulation from, vibration or long-period
cyclical motion in transit, for example, wave-generated movement during sea
transport;
internal and external structural integrity protection, for example, internal and external
bracing, padding, framing, chocking, etc.;
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
support structure requirements, for example, stools, pads, or other devices,
substrates, or support required to ensure in-storage and in-transit stability of
systems, system components, equipment, and material, or other discrete units or
items;
provision for physical separation and/or barriers to prevent airborne or direct
transmittal of contaminants between work areas or between work areas and storage
areas, for example, prevention of carbon steel grinding or cutting debris impact on
stainless steel elements, airborne drift of blast aggregate into vessels or machinery,
etc.;
provision for, and final disposition of, temporary and longer-term storage or transit
required supports and related binding devices, for example, stools, stands, sea
fasteners, platforms, chocks, spacers, cabling, etc.;
provision of requirements for temporary work platforms or other support structures
required to ensure provision of preservation services, for example, provision of a
self-elevating work platform for periodic access to elevated fittings, gauges, man-
ways, etc.;
requirements for protection against, or insulation from, contact with other objects, for
example, padding or other protection for external tubing, fittings, or other impact-
sensitive structures or components;
clear physical delineation of temporary and longer-term storage areas supplemented
by hard and soft barriers, as required, to maintain a protective perimeter;
documented agreements with storage facility and transportation provider
management regarding security management, including, but not limited to, facility
access and egress control and control of access to project goods and materials
within facility boundaries or aboard vehicles or vessels; and
detailed procedures for inspection and testing to verify performance of preservation
procedures and to provide for timely notice and corrective action to maintain
preservation status.
3.8.3.18 The supplier’s preservation management programme scope shall encompass
management of preservation requirements, from initial transfer of ownership or management
responsibility to project scope of responsibility, through any period of temporary or longer-
term storage and through any period of transit, including transit for final delivery at point of
active use or installation.
3.8.3.19 The supplier’s preservation management programme shall clearly and unambiguously
address processes and procedures to ensure that storage and control of materials are
accomplished in accordance with manufacturer recommendations, specifications, and
project-specific requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3.20 The supplier’s preservation management programme shall incorporate special precautions
to address preservation and control of valves, electrical motors and components,
mechanical and rotating equipment, piping and fittings, instrumentation, flange faces,
gaskets, coatings, insulation, and other materials. Special precautions include, but are not
limited to, supplier-specified maintenance procedures related to engines, electric motors,
pumps, compressors, etc., such as periodic shaft rotation, engine turnover, lubrication, etc.
3.8.3.21 The supplier shall ensure that clear and unambiguous requirements for preservation of the
system, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented in purchase orders, work authorisations, and other
communications between the supplier and sub-suppliers.
3.8.3.22 Where sub-supplier expertise is utilised in determination of the preservation protocol,
supplier procurement processes shall ensure clear and unambiguous documentation of sub-
supplier input into preservation management programme requirements.
3.8.3.23 Supplier procurement shall ensure that preservation requirements for scope of work
systems, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented and that preservation requirements are efficiently and
effectively communicated to project logistics, construction management, quality, security,
and other project functional areas, as required, for efficient and effective implementation of
preservation requirements.
3.8.3.24 The supplier shall ensure comprehensive, clear, and unambiguous designation of sub-
supplier responsibility for execution of all preservation management programme elements,
including, but not limited to, all systems, processes, procedures, methods, ready access to
records, and provision of equipment, tools, or services essential to efficient and effective
execution of the preservation management programme.
3.8.3.25 The supplier shall ensure that preservation management programme responsibilities are
clearly and unambiguously defined within the project team and efficiently and effectively
implemented at all project scope of work locations. Inclusion of supplier and sub-supplier
scope of work in the development and implementation of a preservation management
programme shall be considered essential to efficient and effective preservation
management programme execution.
3.8.3.26 The supplier shall ensure clear and unambiguous designation of project team responsibility
for oversight and management of preservation management programme elements during
every stage of project development.
3.8.3.27 The supplier shall ensure that Eskom has free and unrestricted access to all preservation
records for inspection and audit.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.4 Quality Audits Related Conditions
3.8.4.1 The supplier shall maintain an accurate quality audit and related quality performance review
schedule and shall incorporate the current schedule as an attachment to the supplier CQP.
3.8.4.2 The supplier’s quality audit and related quality performance review schedule development
process shall be designed to incorporate consideration of information generated by
previously conducted audits and reviews, by input from project risk management evaluations
(risk register), or from Eskom or sub-supplier subject matter expertise.
3.8.4.3 Eskom reserves the right to oversee supplier audit programmes by participating in selected
audits as an observer and by assessing the supplier during key work stages. Eskom will
coordinate with the supplier to develop an oversight schedule aligned with the supplier’s
audit schedule.
3.8.4.4 Eskom will have the right to obtain access to any audit reports of audits performed by the
supplier reflected in the audit programme.
3.8.4.5 Eskom reserves the right to conduct independent quality audits, scheduled and
unscheduled, during all phases of the contract. The supplier shall provide all resources to
support these activities.
3.8.4.6 Eskom shall be given access at all reasonable times before, during, and after manufacture
and before delivery, construction, erection, and commissioning to measure, test, and inspect
the products and workmanship, as necessary, at the supplier’s premises and at Eskom sites.
3.8.4.7 The supplier shall obtain access for Eskom to measure, test, witness tests, and inspect
products that are being manufactured by any sub-supplier. This includes surveillances.
3.8.4.8 The assessments and audits shall be carried out on all new suppliers and their sub-
suppliers.
3.8.4.9 Eskom shall have the right to participate in, or request that, a technical investigation be
launched and conducted at the supplier’s and sub-suppliers’ premises or other sites when
risk to Eskom products or service deliverables is identified.
3.8.4.10 Qualification requirements for supplier and sub-supplier personnel engaged in conducting
quality audits and related quality performance reviews shall be defined in the supplier CQP
and shall be in compliance with the Project Quality Personnel Qualification Specification.
3.8.5 Management of Nonconformities and Nonconforming Outputs Identified by Eskom
3.8.5.1 Nonconformity reports raised by Eskom and issued against the supplier shall be investigated
by the supplier as a matter of urgency in order to determine the root cause, corrective action
measures, as required, with implementation time frames.
3.8.5.2 A formal response shall be prepared in respect of the defined criteria and submitted to
Eskom for its review, evaluation, and acceptance, within a maximum of 14 calendar days
from the date of issue of the nonconformity and should be aligned with the site
requirements/procedure.
3.8.5.3 Eskom may, at its discretion, request a response sooner and, in any case, before the
supplier proceeding with any pending/further intervention or corrective action, as may be
required by Eskom.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.5.4 Should Eskom or its inspection authority/agency identify any nonconforming products during
the conduct of its audits/surveillances/inspections, the supplier shall be deemed to be in
breach of contract and shall be held liable for any repair, rework, and/or associated
replacement costs. The supplier may, in such instances, also be held liable for the full costs
associated with the conducting of follow-up audits/surveillances/inspections.
3.8.5.5 The nature, magnitude, and/or frequency of nonconformity and inspection defect/rejection
reports raised by Eskom or its appointed inspection authority/agency shall form the basis of
any action to rescind/withdraw the supplier’s qualification status.
3.8.5.6 Nonconforming outputs identified by Eskom shall be documented via a NC Report and
issued to the suppliers via the contract communication protocol. The suppliers shall
investigate the matter and respond in writing to Eskom of disposition within the stated
contractual conditions.
Note: The dates for the disposition should align to contractual conditions.
3.8.5.7 Eskom shall identify repeat deficiencies as systematic failures of the supplier’s QMS and
shall notify the supplier of the trends. Eskom can initiate an internal audit to highlight the
system failures. The supplier with raise a Corrective Action Report and undertake Root
Cause Analysis. In such cases, QMS rectification and/ or update measures shall be taken
immediately.
3.8.5.8 Should the Supplier fail to respond and rectify nonconforming products within stipulated
contractual conditions. The Project Manager should apply contractual remedies in
accordance with Fidic/ NEC contract.
3.8.5.9 Repeated Nonconformities; if there are any identified repeat nonconformities from the same
supplier within a period of 6 months or less. This must then be escalated to the management
review committees of the BU/ OU/ Cluster/ or Divisions for adjudication. If not resolved, then
the matter must be escalated to the supplier review committee for recommendation.
3.8.6 Special Processes
The following requirements shall be applicable as well as additional requirements as specified in the
scope of work for the provision of the following special process services:
3.8.6.1 The supplier shall ensure that all processes which require that procedures be pre-qualified
or work methods and operators tested and qualified are controlled and all steps followed
before the work can commence.
3.8.6.2 This typically covers such activities as welding, non-destructive testing, special fabrication
techniques, coating, painting, etc.
3.8.6.3 All special processes (procedures and processes) shall be submitted for review and
acceptance by Eskom, accredited or certified agency. No work shall commence until these
are accepted.
3.8.6.4 Where applicable, a relevant Management System for the special process shall be certified
or approved by an accredited body and proof of certification shall be submitted to Eskom for
review. An example for this will be the Welding Management System based on ISO 3834.
3.8.6.5 Where samples are required for acceptance, these shall be submitted to Eskom for review
and acceptance.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.6.6 The supplier shall ensure that all operators are suitably qualified for these processes in
accordance with the procedures, processes and/ or applicable standards/ codes.
3.8.6.7 The records of qualification of procedures, processes and operators shall be maintained by
the supplier in accordance with the applicable procedure or code and these made available
to Eskom at all times.
4. Acceptance
This document has been seen and accepted by:
Name Designation
Kerseri Pather General Manager: Risk and Sustainability
Lenock Meyer Acting Senior Manager: Quality Management
Pamela Dondashe Middle Manager: Quality Assurance
Mandla Mkhwanazi Middle Manager: SHEQ Procurement and Supply Chain Management
Suzette Manthe Senior Advisor: Quality Performance and Planning
Lorna Ndlela Middle Manager: Eskom Document and Records Management
5. Revisions
Date Rev. Compiler Remarks
October 2021 3 SA Sambo Specification was due for revision and in addition, to
align the requirements with the latest Eskom business
processes and systems.
October 2018 2 SA Sambo Specification reviewed to be aligned with the
requirements of ISO 9001:2015
March 2016 1 SA Sambo Specification was due for revision and also to
repackage the requirements and tender returnable
documents into four categories.
December 2011 0 A Hunter New document
6. Development Team
The following people were involved in the development of this document:
Andrew Else
Bongi Tshabalala
Feziwe Mogamisi
Lesego Garegae
Patrick Thwane
Xolani Zuma
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
7. Acknowledgements
Eskom Operational Quality Forum Members
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Quality Management
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)equipment, supplying commodities and providing specialised services shall be subjected to the capability and capacity assessment. Generation Level 1 & 2 plant Transmission and Distribution Power Plant & Control Plant Mega Projects
Contractual Terms
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)3.8.1 Rights of Access
Section
Source: 240-105658000 Supplier Quality Management Specification (3).pdfSupplier Quality Management: Specification Unique Identifier: 240-105658000
The intention of this specification is to specify and describe the minimum quality requirements for all
existing and potential Eskom suppliers and define the quality criteria for the selection, evaluation,
implementation, and maintenance of a quality management system (QMS) that conforms to the
a quality management system (QMS) based on ISO 9001, which should form the basis for conformity
to Eskom quality requirements and continually adhere to them throughout the duration of a contract
[1] ISO 9001 Quality Management Systems – Requirements
[2] ISO 10005 Quality Management Systems – Guidelines for Quality Plans.
[3] ISO 9000 Quality Management Systems – Fundamentals and Vocabulary
[4] 32-727: Safety, Health, Environment, and Quality (SHEQ) Policy
[5] ISO 10006 Quality Management Systems – Guidelines for Quality Management in Projects
[6] ISO 9004 Quality Management – Quality of an Organisation – Guidance to Achieve Sustained
[9] PPPFA: Preferential Procurement Policy Framework Act, 2000 (Act No. )
[10] CIDB 1004: Best Practice Guideline A4: Evaluating Quality in Tender Submissions
[11] 240-12248652 Supplier Quality Management: List of Tender Returnables
2.3.2 Contract Quality Plan: a document of the supplier’s process for delivering the level of quality
required by the contract. It is a framework for the contractor’s process for delivering quality.
2.3.3 Hold Point: a predetermined stage in the quality control plan (QCP) beyond which work/
2.3.4 Intervention Points: those control points indicated by the various controlling bodies
inspection, hold points, surveillances, witnesses, reviews and verifications.
performing quality assurance/ quality control, monitoring, inspection and/ or expediting
Title: Supplier Quality Management: Document Identifier: 240-105658000
Functional Area: Quality Management
Quality Quality Manager Quality Risk and
Description
Source: Eskom Supplier Integrity Pact - 02 June 2023 (1).pdfThis document is the Eskom Supplier Integrity Pact, applicable to Eskom Holdings SOC Ltd and all its wholly owned subsidiaries. It governs ethical behaviour for all existing and potential suppliers. Key points:
Contact Information
Source: Eskom Supplier Integrity Pact - 02 June 2023 (1).pdf (unknown)Submission Guidelines
Source: Eskom Supplier Integrity Pact - 02 June 2023 (1).pdf (unknown)Submit the following returnable documents:
Disqualification risks:
Reporting unethical behaviour: Contact Eskom Ethics Office ([email protected]), Forensic Team ([email protected]), or the toll-free hotline (0800 11 27 22).
Returnable Documents
Source: Eskom Supplier Integrity Pact - 02 June 2023 (1).pdf (unknown)Required returnable documents:
Evaluation Criteria
Source: Eskom Supplier Integrity Pact - 02 June 2023 (1).pdf (unknown)General
Ethical
Technical
Compliance Requirements
Source: Eskom Supplier Integrity Pact - 02 June 2023 (1).pdf (unknown)Mandatory compliance requirements:
Consequences of non-compliance:
B-BBEE Requirements
Source: Eskom Supplier Integrity Pact - 02 June 2023 (1).pdf (unknown)Employment Equity: Suppliers are encouraged to align with Eskom’s policies on employment equity, ensuring fair treatment and equal opportunities for all employees, in compliance with the Employment Equity Act.
Contractual Terms
Source: Eskom Supplier Integrity Pact - 02 June 2023 (1).pdfContractual terms and obligations:
Special Conditions
Source: Eskom Supplier Integrity Pact - 02 June 2023 (1).pdf (unknown)Special conditions for suppliers:
Description
Source: 240-68099512 Form A category 2 Rev 9.pdfProject falls under Category 2 for Pre-contract Award Quality Requirements (refer to clause 3.5.-105658000). Only one category may be selected. Site assessment applicability must be indicated. Main Supplier and Sub-supplier Capability and Capacity Assessment is referenced in clause 3.-105658000.
Submission Guidelines
Source: 240-68099512 Form A category 2 Rev 9.pdf (unknown)Complete and sign the form to acknowledge and accept Eskom Supplier Quality Requirements as per 240-105658000 Specification and ISO 9001 Standard. This is a returnable document.
Evaluation Criteria
Source: 240-68099512 Form A category 2 Rev 9.pdf (unknown)General
Quality Management
Technical Capacity
Technical Specifications
Source: 240-68099512 Form A category 2 Rev 9.pdf (unknown)Pre-contract award quality requirements apply under Category 2 (refer to clause 3.5.-105658000). Only one category may be selected. Site assessment applicability must be indicated. Main Supplier and Sub-supplier Capability and Capacity Assessment is referenced in clause 3.-105658000.
Methodology
Source: 240-68099512 Form A category 2 Rev 9.pdfMethodology must align with ISO 9001 clauses: Context of the Organisation, Leadership, Planning, Support, Operation, Performance Evaluations, and Improvement. Principles to guide methodology: Customer focus, Leadership, Engagement of people, Process approach, Improvement, Evidence-based decision making, and Relationship Management.
Quality Management
Source: 240-68099512 Form A category 2 Rev 9.pdfISO 9001 Standard compliance required for clauses: Context of the Organisation, Leadership, Planning, Support, Operation, Performance Evaluations, and Improvement. Principles: Customer focus, Leadership, Engagement of people, Process approach, Improvement, Evidence-based decision making, and Relationship Management. Post-contract: Contract Execution, Supplier Quality Performance Monitoring Phase, Eskom Rights of Access/Information, Preservation, Quality Audits, Management of Nonconformities, and Special Processes.
Compliance Requirements
Source: 240-68099512 Form A category 2 Rev 9.pdf (unknown)Compliance with Eskom Supplier Quality Requirements as per 240-105658000 Specification and ISO 9001 Standard is mandatory. Eskom retains rights of Access, Information, Preservation, and Quality Audits. Management of Nonconformities and Nonconforming Outputs Identified by Eskom is required. Special Processes (refer to clause 3.8.-105658000) must be adhered to.
Contractual Terms
Source: 240-68099512 Form A category 2 Rev 9.pdf (unknown)Contractual terms include Eskom Rights of Access, Rights to Information, Preservation, Quality Audits, Management of Nonconformities and Nonconforming Outputs, and Special Processes (refer to clause 3.8.-105658000).
Section
Source: 240-68099512 Form A category 2 Rev 9.pdfEvaluation includes compliance with ISO 9001 Standard clauses (4-10) and principles (1-7). Post-contract award evaluation covers Contract Execution and Supplier Quality Performance Monitoring Phase. Quality Audits and Management of Nonconformities are applicable.
Description
Source: Invitation to Tender (ITT) - E3020GXMPDUV (003).pdfProject involves the design, supply, installation, commissioning, and testing of a Sulphuric Acid Storage and Dilution Upgrade at Duvha Power Station over 24 months. The system must integrate with the existing Water Treatment Plant (WTP) Control System (ABB Symphony Infi90 DCS and 800xA HMI). Key deliverables include a fully functional storage and dilution system compliant with Eskom’s technical and safety standards.
Important Dates
Source: Invitation to Tender (ITT) - E3020GXMPDUV (003).pdf (TENDER)Closing date and time: 29 June 2026 at 10H00. Non-compulsory clarification meeting: 17 June 2026 at 10H00 via MS Teams (Link: https://teams.microsoft.com/meet/368378682934509?p=ag8mfpH7xVX46yljc5; Meeting ID: 368 378 682 934 509; Passcode: bo7cF6Gh). Site walk: 18 June 2026 at 11H00 at Duvha Power Station. Permits for site access must be requested by end of business on 17 June 2026, including attendee names, vehicle registration numbers, and company name. Tender validity period: 12 weeks from closing date. Clarification queries must be submitted at least 5 working days before the tender closing deadline.
Contact Information
Source: Invitation to Tender (ITT) - E3020GXMPDUV (003).pdf (TENDER)Eskom Representative: Sibusiso Mthimkulu. Tel: 013 6900 994. Email: [email protected]. For fraud or corruption reporting: 0800 11 2722 or [email protected]. Submission portal: Eskom E-tendering (https://etendering.eskom.co.za).
Submission Guidelines
Source: Invitation to Tender (ITT) - E3020GXMPDUV (003).pdf (TENDER)Submit tender electronically via Eskom E-tendering portal (https://etendering.eskom.co.za) by the closing date and time. No hard copies or zipped files accepted. Upload all documents in PDF format (max 500MB per file, total submission max 4GB). Organise submissions into folders: Technical, Commercial, Financial, and Other. Ensure submission status is marked as 'complete'. Late submissions will not be accepted. Resubmissions will override previous versions. Mandatory returnables include: Authorisation Form (Annexure A), Acknowledgement Form (Annexure B), Tenderer’s Particulars (Annexure C), Integrity Declaration Form (Annexure D), CPA Requirements (Annexure E), SBD 6.2 (Annexures G1-G4), SBD 1 (Annexure H), SBD 6.1 (Annexure I), SBD 4 (Annexure J), E-tendering Help Manual acknowledgement form, and Tax Evaluation Questionnaire (if applicable). Joint ventures must submit a valid JV agreement and proof of a single designated bank account.
Evaluation Criteria
Source: Invitation to Tender (ITT) - E3020GXMPDUV (003).pdf (TENDER)General
CIDB
B-BBEE
Methodology
Source: Invitation to Tender (ITT) - E3020GXMPDUV (003).pdfMethodology must align with ISO 9001 principles: Customer focus, Leadership, Engagement of people, Process approach, Improvement, Evidence-based decision making, Relationship management. Contract execution and supplier quality performance monitoring are mandatory. Eskom retains rights of access, information, preservation, and quality audits.
Quality Management
Source: Invitation to Tender (ITT) - E3020GXMPDUV (003).pdfQuality Management System (QMS) Requirements: Option 1: Valid ISO 9001 certification (must include product/service scoping, approved authority, international accreditation, and validity). Option 2: Documented QMS complying with ISO 9001 (QMS Manual, Quality Policy, Quality Objectives, document control, nonconforming outputs, corrective action, internal audits). Evidence of QMS in operation: Roles and responsibilities (organisation chart), control of externally provided processes, internal audit reports, certification audit reports, management review records. Contract Quality Plan (CQP) and Quality Control Plan (QCP)/Inspection and Test Plan (ITP) required, aligned with ISO 10005. Supplier Quality Performance Monitoring and Eskom Rights of Access/Information apply.
Pricing Schedule
Source: Invitation to Tender (ITT) - E3020GXMPDUV (003).pdfPricing Schedule/Bill of Quantities (BOQ) must be submitted in PDF format (max 500MB per file, total submission max 4GB). Include cataloguing costs as a line item if applicable. Pricing must be inclusive of VAT, exclude contingencies, and be corrected for arithmetical errors. Unconditional discounts are considered for evaluation; conditional discounts are applied at payment. Prices will be evaluated using Net Present Value (NPV) based on tendered programme, price adjustment factors, and risk parameters.
Financial Requirements
Source: Invitation to Tender (ITT) - E3020GXMPDUV (003).pdf (TENDER)Pricing must be inclusive of VAT, exclude contingencies, and be corrected for arithmetical errors. Prices will be adjusted for acceptable variations or deviations. Unconditional discounts are considered for evaluation; conditional discounts are applied at payment. Payment terms: For contracts ≤ R50M (incl. VAT), payment within 30 days of undisputed invoices; For contracts > R50M (incl. VAT), payment within 60 days. Pricing Schedule/BOQ must be submitted in PDF format. Cataloguing costs must be included as a line item if applicable. Prices will be evaluated using Net Present Value based on tendered programme, price adjustment factors, and risk parameters.
Compliance Requirements
Source: Invitation to Tender (ITT) - E3020GXMPDUV (003).pdf (TENDER)Mandatory: CSD registration (CSD number/report); Valid B-BBEE certificate (SANAS accredited) or sworn affidavit/CIPS affidavit; Proof of ownership/shareholding (CIPC documentation); Certified ID copies of shareholders; Tax Clearance Certificate (for local tenderers or foreign tenderers with a SA footprint); CIDB Grading 5 (ME) or higher (or proof within 21 working days of closing date for JVs); Employment Equity compliance (for designated employers); SHEQ requirements; SDL&I requirements; Financial viability (audited financial statements for the past 18 months or last year). Joint ventures must have all members registered with CIDB and a lead partner with a grading not lower than one level below the required grading. Subcontracting 100% of the scope is prohibited. Tenderers must not be on sanctions lists, Eskom’s Tender Defaulters list, or restricted by National Treasury or Eskom.
Health & Safety
Source: Invitation to Tender (ITT) - E3020GXMPDUV (003).pdfMandatory OHS Requirements: Signed Annexure B (acknowledgement of Eskom’s OHS legal requirements); Health and Safety Plan (aligned with project OHS risks, including site establishment); Detailed OHS costing (broken down, not lump sum, based on scope and risk assessment). Occupational Hygiene Surveys/Risk Assessments: Exposure risk, ergonomics, physical agents, noise, hazardous chemical/biological agents, ventilation (LEV Testing), heat/cold stress, non-ionising radiation, indoor air quality, illumination, vibration. Baseline OHS Risk Assessment (BRA) with methodology. Valid Letter of Good Standing (COIDA). OHS Policy signed by CEO. Competency Requirements: OHS Sec 16.2 Appointment Letter & Legal Liability Training; Supervisors (Legal Liability, OHS Act); LMI (ECSA-registered); LME (DOEL-registered); Safety Officer (SAMTRAC, 2+ years experience); Risk Assessor; Incident Investigator; First Aiders (Level 1-2); SHE Reps; Mobile Plant Operators; Fall Protection Planner; Temporary Electrical Installer/Inspector. PPE: Safety boots, chemical-proof overalls, reflective vests, hard hats, gloves, goggles, dust masks, hearing protection, winter/rain coats. Site Establishment: Ablution, kitchen, offices, workshop, stores, parking, safety signs. Medical Surveillance: 12-month validity for all on-site employees.
Environmental
Source: Invitation to Tender (ITT) - E3020GXMPDUV (003).pdfEnvironmental Requirements: ISO 14001:2015 certification or equivalent. Environmental Policy/Statement of Commitment from top management. Compliance with Eskom’s environmental management standards. Due Diligence: Audited financial statements for the past 18 months (or last year for start-ups). Joint ventures must submit financials for each participant.
Contractual Terms
Source: Invitation to Tender (ITT) - E3020GXMPDUV (003).pdfContract type: NEC3 Engineering and Construction Contract (ECC). Main Option: A (Priced contract with Bill of Quantities). Secondary Options: W1 (Dispute resolution), X1 (Price adjustment for inflation), X2 (Changes in law), X7 (Delay damages), X16 (Retention), X17 (Low Performance damages), X18 (Limitation of liability), Z (Additional Conditions). Contract duration: 24 months. Tender validity: 12 weeks from closing date. Subcontracting 100% of scope is prohibited. Joint ventures must confirm joint and several liability and provide a single designated bank account.
Section
Source: Invitation to Tender (ITT) - E3020GXMPDUV (003).pdfTechnical evaluation threshold: 70/100 points. Mandatory criteria: Valid ISO 3834-2 Certification (Design Codes: BS EN 13480, BS EN 13445, or P5500; Material Groups: 1, 11, 8 per ISO 15608); ECSA-registered engineers for Mechanical, Chemical, C&I, and Electrical disciplines; Demonstration of system integration with ABB Symphony Infi90 DCS and 800xA HMI. Price evaluation: Inclusive of VAT, corrected for errors, excludes contingencies, adjusted for variations. Scored out of 80 or 90 points. B-BBEE Specific Goals: Scored out of 10 or 20 points (PPPFA compliant). Ranking: Sum of Price + Specific Goals scores. Objective criteria may override highest score.
Important Dates
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER){"closingTime":"2.2","briefingSession":"{\"date\":null,\"time\":null,\"venue\":\"tend a site visit and/or clarification meeting that is stipulated as being\",\"is_compulsory\":true}"}
Briefing Session
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Seek clarification 2.16 While preparing their tenders and prior to submission, tenderers are entitled to seek clarification in respect of the Invitation to Tender documents. A request for clarification or query must be addressed, in writing, to the Eskom Representative identified in the Invitation to Tender document. No request or query may be addressed to any other Eskom official other than the Eskom Representative. Eskom will publish all requests for clarification and queries received (without divulging the tenderer’s name), together with its responses, on the platform/s on which the tender was advertised. A request for clarification or query must allow Eskom a reasonable time to respond, and a reasonable time for tenderers to make consequential adjustments to their tenders before the closing date and time for submission. In writing’ means hand-written, typed, type-written, printed or electronically made, and that results in a permanent record.
Returnable Documents
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Tender closing time 2.2 Ensure that Eskom has received the complete original tender and one (1) complete hard copy of the original tender at the address and in the tender box or e-mail address specified in the Tender Data by no later than the closing date and time for tender submission. Proof of posting or of courier delivery does not equate to proof of delivery. Eskom will not accept a tender submitted by e-mail unless stated otherwise in the Tender Data. For E-tendering the tenderer must upload and finalize the tender via Eskom Tender bulletin site on the Eskom E- tendering page by no later than the closing date and time for tender submission. It remains the sole responsibility of the tenderer to ensure that the documents (PDF/Excel) are submitted and accessible for downloading/evaluation without any challenges as well as they are not corrupt or unreadable. It is the tenderer’s responsibility to ensure that their tenders documents are submitted/uploaded, and the submission is finalised before the closing date and time For E-tendering tenderers are not permitted to deposit a tender into the Eskom tender box only electronic submission via the Eskom Tender bulletin site on the Eskom E- tendering page will be accepted. 2.3 Any reference to time will mean South African Standard Time (SAST), i.e. GMT+2 hours. The Tender Officer ensures that the clock at the tender office is synchronised with the Telkom time signal before the closing time. Within Eskom’s tender documentation, any reference to time will mean South African Standard Time (SAST). The closing time at the address and in the tender box will be determined by using the Telkom time signal, as available over the telephone. This time will be strictly adhered to. For e-tendering any reference to time mean South African Standard Time (SAST). 2.4 Accept that if Eskom extends the closing date and time for tender submission for any reason, the requirements of these Standard Conditions of Tender apply equally to the extended closing date and time for tender submission. In the case of an open tender, tenderers are required to visit the Eskom Tender Bulletin and NT e-Tender Portal regularly to ensure they keep abreast of any changes to the closing date and time for submission and of amendments and addenda to the Invitation to tender, 2.5 Any tenders that have not been placed in the tender box or have not been received by Eskom in the manner stipulated in the Tender Data at the closing date and time for tender submission will be considered to have been received late. No late tender will be accepted. Accept that Eskom will not assume any responsibility for the misplacement or premature opening of the tender if the outer package is not sealed or the address and references are marked incorrectly. The E-tendering system will not allow tenderers to change/finalize and submit their submission after the closing date and time for tender submission. No late tender will be accepted. Without limitation, Eskom takes no responsibility for any delays in any courier or postal system or any delays in transit of tenders or for tenders delivered to a location other than the tender box at the tender office stated in the Tender Data. For E-tendering Eskom will not assume any responsibility for tender not finalised before the closing date and time for tender submission, and references that are marked incorrectly. Without limitation, Eskom takes no responsibility for any network issue or delays in uploading of documents on the suppliers’ side. Eskom employees are not permitted to deposit a tender into the Eskom tender box on behalf of a tenderer. 2.8 Return the mandatory tender returnables to Eskom for evaluation purposes by tender the closing date and time for tender submission, and tender returnables that are required for contract award before contract award. All documents returned (including all forms data and schedules) must, without exception, have been completed. Where any certificate, document, proof of registration or the like is required to be submitted as a mandatory or other tender returnable, the tenderer must ensure that Eskom is placed in possession of a valid, current and, where stipulated, original document for the entire duration of the tender validity period. 2.9 Submit a complete original tender in paper form, plus one (1) complete copy of the original tender, also in paper form, at the closing date and time for tender submission. If an original tender is not submitted at all, or a copy of the original tender is not submitted at all, the tenderer will be disqualified. Eskom may also request that an additional copy of the original tender is submitted in an electronic format. For E-Tendering submit the tender via Eskom Tender bulletin site on the Eskom E- tendering page. These tenders must be submitted in English. Tenders must be submitted in English. Written tenders must be completed in ink and may not be completed in pencil. In writing’ means hand-written, typed typed-written, printed or electronically made, and that results in a permanent record. 2.10 Sign the original tender. Eskom will hold the signatory named as the person duly authorised to sign the tender on behalf of the tenderer liable for the tender. For E-Tendering, sign the electronic tender. Eskom will hold the signatory named as the person duly authorised to sign the tender on behalf of the tenderer, liable for the tender. 2.11 Submit the original tender and the copy in paper format as separate packages/envelopes marking them as "ORIGINAL" and "COPY". If an additional electronic copy was required to be submitted, it must be packaged separately and marked “ELECTRONIC COPY”. Each separate package shall, on its outside, state the relevant Eskom address given as the address at which tenders must be submitted, the Invitation to Tender number stated in the Tender Data, the tenderer's name, physical address for tenderer, email address and contact telephone number for the duly authorized representative who signed the tender on tenderer’s behalf. Seal the separate packages (containing the original tender and copies) together in an outer package that states on the outside that it is “Confidential” and further states the relevant Eskom address given as the address at which tenders must be submitted, the Invitation to Tender number stated in the Tender Data, the tenderer's name, physical address for tenderer, email address and contact telephone number for the duly authorized representative who signed the tender on tenderer’s behalf. For E-Tendering the Tender documents should be updated in the relevant folders, Technical, Commercial and Financial as indicated on e-tendering page.
Evaluation Criteria
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)General
Specific
Technical Specifications
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Supply Chain
Management Procedure 32-1034. Any addenda to an issued Invitation to Tender will be
published or issued in the same way as the Invitation to Tender was and will form part of the
Invitation to Tender documents.
Communication 1.5 Every communication between Eskom and a tenderer shall be made to or from the Eskom
Representative only, in w
Quality Management
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdfof a tenderer.
Cost of tendering 2.6 Accept that Eskom will not compensate the tenderer for any costs incurred in the preparation
and submission of a tender, including the costs of any testing necessary to demonstrate that
aspects of the tender satisfy the evaluation criteria, or the negotiation of any contract.
Submitting a tender 2.7 Check the Invitation to Tender documents on receipt and notify the Eskom representative of
any discrepancy or omitted documents. The Acknowledgement Form must be completed
and submitted with the tender and must clearly state if the tender is for the whole or part of
the works, services or supply identified in the specification and/or works information by
Pricing Schedule
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdfreasonable time for tenderers to make consequential adjustments to their tenders before
the closing date and time for submission.
In writing’ means hand-written, typed, type-written, printed or electronically made, and that
results in a permanent record.
Insurance 2.17 The extent (if any) of insurance provided by Eskom may not be for the full cover required in
the conditions of contract. The tenderer is advised to seek qualified advice regarding
insurance.
Pricing the tender 2.18 Include in the rates, prices, and the tendered total of the Prices all duties, taxes (including
VAT), and other levies payable by the tenderer if successful. Such duties, taxes and levies
are those applicable 14 (fourteen) days prior to the closing date and time for tender
submission.
2.19 Provide rates and Prices that are fixed for the duration of the contract and are not subject to
contract price adjustment except as provided for in the Invitation to Tender.
2.20 State the rates and Prices in South African Rand unless instructed otherwise in the Invitation
to Tender. The selected conditions of contract may provide for part payment in other
currencies. Therefore, submit Rates/Prices in Rands in accordance with the exchange rate
and base date as stipulated in the Invitation to tender.
Alterations to 2.21 May not make any alterations or additions to the tender documents, other than for purposes
documents of complying with instructions issued by the Eskom Representative or if necessary to correct
errors made by the tenderer. All such alterations shall be initialed by all signatories to the
tender. Corrections may not be made using correction fluid, correction tape or the like.
Alternative tenders 2.22 Submit alternative tenders only if a main tender is also submitted, and only if the submission
of alternative tenders is permitted by the Invitation to Tender. Accept that an alternative
tender may be based only on the criteria stated in the Tender Data.
Clarification and 2.23 Provide clarification and documents as may be required by the Eskom Representative
correction of Prices during the evaluation of tenders. However, documents identified as mandatory tender
after tender returnables that are required to be submitted at the closing date and time for tender
submission submission will not be requested and may not be submitted after the closing date and time.
phases, as this is regarded as ‘double dipping’.
Designated 3.12 Tenderers are also required to submit information on designated material and
materials and thresholds no later than contract award. If this information is not completed and
thresholds submitted as indicated in the Invitation to Tender, your tender will not be considered for
contract award
Functionality 3.13 If functionality is a criterion, tenderers will be scored against the functionality criteria and
requirements will be required meet the minimum threshold stated in the Tender Data to proceed to
further evaluation.
Financial analysis 3.14 Eskom has to determine the risk of doing business with a supplier who may pose a
(if applicable) financial risk to Eskom in the execution of the contract. During evaluation of a tenderer’s
financial statements, Eskom will attempt to identify mitigating factors or requirements for
the tenderer to meet, if such factors/requirements exist in the tender’s context. However,
should suitable mitigating factors not exist in the tender’s context or should mitigating
factors exist but be insufficient or if the risk is considered to be too high or should the
tenderer not agree with the mitigating factors, the tenderer will not be considered for
award.
Evaluation of Price 3.15 Evaluate the Price in accordance with the criteria/requirements in the Tender Data. Factors
such as CPA, FOREX, commodity exposure, unconditional discounts, technical
adjustment, PV and forecasted rates of invoicing are taken into account when determining
the evaluation Price.
Arithmetical errors 3.16 Check responsive tenders for arithmetical errors. If there is a discrepancy between an
amount in figures and the amount in words, the amount in words shall prevail.
Check the highest-ranked tenders for the following errors or omissions: -
(a) the misplacement of the decimal point in any unit rate; or
(b) omissions in completing the pricing schedule or bill of quantities, or
(c) arithmetical errors in line-item totals that are the result of the incorrect multiplication
of a unit rate and a quantity in a bill of quantities or schedule of prices; or
(d) arithmetical errors that are the result of the incorrect addition of the prices.
will request the tenderer to either confirm the prices as tendered or to accept the
corrected prices.
Where the tenderer elects to confirm the prices as tendered; Eskom will correct the error
as follows: -
(a) If a bill of quantities or pricing schedule applies and there is an error in the line-item
total that is the result of an error in multiplying the unit rate and the quantity, the line-
item total shall prevail, and the rate shall be corrected.
(b) Where there is a misplacement of the decimal point in the unit rate, the line-item total
as quoted shall prevail, and the unit rate shall be corrected.
(c) Where there is an error in the total of the prices that is the result either of other
corrections required by the checking process or in the tenderer’s addition of prices,
the total of the prices shall prevail, and the tenderer shall be asked to revise the
selected item prices (and their rates if a bill of quantities applies) to result in the
tendered total of the prices.
documentation by closing date and time of tender submission, the tenderer will not be
disqualified if otherwise evaluated as acceptable in all other criteria; however, the tenderer
will score zero points for Specific Goals within the 90/10 or 80/20 allocation of points.
Ranking of tenders 3.19 According to the PPPFA, Eskom will add the score for Pricing and the Specific Goals
together and rank the suppliers from the highest to the lowest.
Objective criteria 3.20 A contract may be awarded to a tenderer that did not score the highest points only in
accordance with Section 2(1) (f) of the Preferential Procurement Policy Framework Act,
2000. If Eskom intends to apply Objective Criteria envisaged in section 2(1)(f), Eskom
must stipulate the Objective Criteria in the Invitation to Tender. Functionality and any
element of the B-BBEE scorecard may not be used as Objective Criteria.
Compliance Requirements
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)CSD report or as per certificate/affidavit provided
CSD number/CSD report) must be provided at the closing date and time for
CSD number or B-BBEE certificate/affidavit will need to be
B-BBEE Details: kom Representative and
Agreement to sign the contract documents.
Proof of authority 2.25 Where an agent submits a tender on behalf of a principal, an authenticated copy of the
to act as agent authority to act as an agent of the tenderer must be submitted as a tender returnable.
Compliance with 2.26 Comply with relevant legislation and regulatory instruments such as Instruction Notes issued
relevant legislation by National Treasury, CIDB Regulations for construction works; materials designated for local
(NT instructions, content and/or production by the dtic, PPPFA Regulations; Amended B-BBEE Codes, COIDA;
CIDB, PPPFA etc) OHS Act; Eskom’s requirements for Safety, Health, Environment and Quality (SHEQ) and any other
applicable legislation or regulatory instruments indicated in the Invitation to Tender.
Proof of Safety, 2.27 Tenderers are required to provide proof to the satisfaction of Eskom that safety, health,
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
Environment and closing date and time for tender submission stipulated in the Invitation to Tender and/or
Quality Contract Award. All costs and personnel associated with SHEQ must be reflected in the
requirements tender.
CIDB 2.28 Where the Tender Data has stipulated CIDB grading/s as a qualification criterion, tenderers
are required to be registered with the Construction Industry Development Board at the
closing date and time for submission of tenders or to be capable of being so registered
within twenty-one (21) working days from the closing date and time for submission of
tenders.
Where CIDB is applicable; proof of registration on CIDB is mandatory at the closing date
and time for tender submission. Should this not be received as stipulated
Health & Safety
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdftenderers that Eskom has identified. A sole source and a single source are regarded as a
tenderer that meets the requirements stated in the Eskom Procurement and Supply Chain
Management Procedure 32-1034. Any addenda to an issued Invitation to Tender will be
published or issued in the same way as the Invitation to Tender was and will form part of the
Proof of authority 2.25 Where an agent submits a tender on behalf of a principal, an authenticated copy of the
to act as agent authority to act as an agent of the tenderer must be submitted as a tender returnable.
Compliance with 2.26 Comply with relevant legislation and regulatory instruments such as Instruction Notes issued
relevant legislation by National Treasury, CIDB Regulations for construction works; materials designated for local
(NT instructions, content and/or production by the dtic, PPPFA Regulations; Amended B-BBEE Codes, COIDA;
CIDB, PPPFA etc) OHS Act; Eskom’s requirements for Safety, Health, Environment and Quality (SHEQ) and any other
applicable legislation or regulatory instruments indicated in the Invitation to Tender.
Proof of Safety, 2.27 Tenderers are required to provide proof to the satisfaction of Eskom that safety, health,
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
requirements tender.
CIDB 2.28 Where the Tender Data has stipulated CIDB grading/s as a qualification criterion, tenderers
are required to be registered with the Construction Industry Development Board at the
closing date and time for submission of tenders or to be capable of being so registered
within twenty-one (21) working days from the closing date and time for submission of
tenders.
Where CIDB is applicable; proof of registration on CIDB is mandatory at the closing date
and time for tender submission. Should this not be received as stipulated in the Invitation to
Tender; the tender will be disqualified. However, in the event that, at the closing date and
time for tender submission, only proof of application for registration on CIDB is available,
then this must be submitted by the closing date and time for tender submission, while the
actual proof of CIDB registration (printout from CIDB database) must be submitted by
contract award
Contract Skills 2.29 If the tenderer is awarded a contract, it, as Contractor, shall achieve in the performance of
Development Goal the contract the Contract Skills Development Goals (CSDG) established in the CIDB
(CSDG) Standard for Developing Skills through Infrastructure Contract (published in GN 1779,
Government Gazette No. April 2023)
that has a duration of 12 months or more, and to:
a contract of R5 million or more, in the case of a professional service or service contract
or an order issued in terms of such a contract; or
a CIDB grading designation of grade 7 or higher, in case of an engineering and
construction works, or design and build contract or an order issued in terms of such a
contract.
Contract 2.30 The Contractor shall achieve in the performance of the contract the Contract Participation
Participation Goals Goals (CPG) relating to the engagement of targeted enterprises as established in the CIDB
(CPG) standard for indirect targeting for enterprise development through Construction works
contracts (published in Government Gazette No. February 2013).
enterprises as established in the aforesaid standard applies to:
construction works contracts in the General Building (GB) and to Civil Engineering (CE)
classes of construction works;
construction works contracts of an estimated minimum project duration of 6 months; and
construction works contracts in which at least 25% of the main contract could reasonably
be expected to be subcontracted out in one or more of the following CIDB classes of
construction works:
Civil Engineering (CE)
Electrical Engineering Work (EB)
) General Building Works (GB)
) Mechanical Engineering (ME)
2.31 Eskom may disqualify a tender if it is found that the tenderer has misrepresented or
falsified any information, certificate, affidavit or document. Eskom will report any fraud
in relation to a tenderer’s B-BBEE certificate/affidavit, or evidence of ‘fronting’ as
defined in the B-BBEE Act , as amended, to the B-BBEE Commission. The
tenderer will be suspended from business with any State-Owned Company for up to 10
years and may even be sentenced to jail.
2.32 Tenderers are also required to complete fully and submit the SDL&I Undertaking
(annexure to the Invitation to Tender) by no later than contract award. If the SDL&I
Respond 3.1 Respond to a request for clarification that Eskom receives before the closing date for
clarification clarification or queries. Eskom’s responses will be published to all tenderers in the same
manner the Invitation to Tender documents were issued. It is the tenderers’ responsibility
to check the Eskom Tender Bulletin and NT e-Tender Portal regularly for updated
responses to clarifications.
Issue Addenda 3.2 If necessary and prior to the closing date and time for tender submission, amend, amplify, or
add to the Invitation to Tender documents by way of Addenda published in the same
platform that the Invitation to Tender was issued. It is the tenderers’ responsibility to
check the Eskom Tender Bulletin and NT e-Tender Portal regularly for Addenda.
electronically. The Eskom Representative will publish the names of all tenderers received
on the Eskom Tender Bulletin and NT e-Tender Portal.
Tender Prices 3.5 Eskom will announce the names of the tenderers. Prices may be announced if so, stated
in the Tender Data.
Non-disclosure 3.6 Unless required by law, Eskom will not disclose information relating to the evaluation and
comparison of tenders and recommendations for the award of a contract to tenderers or to
any other person not officially concerned with the tender process until after the tender
award.
Grounds for 3.7 Reject a tender if Eskom establishes that there is proof that the tenderer influenced the
rejection processing of tenders or the awarding of the contract, the existence of collusion and/or bid
rigging, and/or that the tenderer has participated in any fraudulent/illegal activity in
connection with the Invitation to Tender.
Clarification of a 3.8 Obtain clarification from a tenderer in respect of any matter in the tender that may not be
tender clear or that could give rise to ambiguity in a contract arising from this tender if the matter
were not to be clarified. A document that the Invitation to Tender identifies as a mandatory
tender returnable that is required to be submitted at the closing date and time for tender
submission will not be requested, but Eskom may seek clarity on it.
may utilise reverse e-auction in certain Enquiries. Where reverse e-auction will be utilised,
this will be indicated in the respective Invitation to Tender and the reverse e-auction
supporting documents will be issued in the Invitation to Tender. Tenderers will be required
to submit a complete tender that does not contain Prices. If a tenderer has included prices
in its tender, the prices will not be considered.
Acceptance of 3.22 Notify Eskom's acceptance to the successful tender before the expiry of the validity period
tender or agreed additional validity period. Inform the successful and unsuccessful tenderers only
once approval has been granted by the Eskom Adjudication Authority. For open tenders,
this notification must be published on the Eskom Tender Bulletin and NT e-Tender Portal
Prepare contract 3.23 Revise the contract documents issued by Eskom in the Invitation to Tender documents to
documents take account of:
Addenda issued during the tender period;
inclusion of returnables stipulated in the Invitation to Tender;
inclusion of changes agreed in contract negotiations; and
Other revisions or documents agreed to between Eskom and the successful
tenderer during negotiations,
Sign Form of 3.24 Arrange for authorised signatories of both parties to complete and sign the original and one
Contractual Terms
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdfincluding the Eskom Representative shall not be liable for any losses, claims or damages of
whatsoever nature or howsoever arising that may be sustained by a tenderer or any other
person as a result of its participation in the tender or from any amendment, termination or
suspension of the process set out in the Invitation to Tender or from its exclusion from
participating in the tender process at any point.
Eskom’s right to 1.7 Eskom reserves the right to enter into mandated negotiations with any, one or more selected
negotiate tenderer(s) in accordance with Eskom’s approved procurement policies and procedures.
240-62044728 Rev 12 Eskom Standard Identifier
Conditions of Tender Effective Date 01 February 2025
Review Date January 2030
Disclaimer 1.8 While Eskom takes all reasonable measures to ensure that all information contained in the
regarding accuracy tender documents is correct and complete, Eskom does not, however, make any
of tender representations or warranties, express or implied, as to the accuracy or completeness of
documents such information and Eskom expressly disclaims any, and all liability for such
representations, warranties or statements.
Tenderer’s 2. The tenderer shall comply with the following obligations when submitting a tender and shall:
Tender validity 2.12 Hold the tender(s) valid for acceptance by Eskom at any time within the validity period after
the closing date and time for tender submission. Extend the validity period for a specified
additional period if Eskom requests the tenderer to do so. A tenderer that agrees to extend
the validity of its tender will not be required or permitted to modify its tender. A tenderer that
does not agree to extend the validity of its tender will be excluded from further
consideration. Tenderers will be requested to extend the validity of their tenders until a
contract(s) have been concluded with one or more tenderers. A request that a tenderer
extend the validity of its tender is not a representation that the tender is an acceptable
tender or that Eskom will seek to negotiate or conclude a contract with the tenderer. If the
validity of tenders expires before contracts have been concluded, the procurement process
is deemed to have concluded without an award.
Confidentiality and 2. 13 Treat as confidential all matters that arise in connection with the procurement. Use and copy
copyright of the documents provided by Eskom only for the purpose of preparing and submitting a tender
documents in response to this Invitation to Tender.
Standardised 2.14 Obtain and familiarise themselves with, if required for the purposes of submitting a tender,
specifications and the latest revision of standardised specifications and/or other documents that have been
other publications incorporated by reference into the Invitation to Tender documents by reference.
Site visit and / or 2.15 Tenderers must attend a site visit and/or clarification meeting that is stipulated as being
clarification compulsory in order to familiarise themselves with the proposed work, services, supply,
meeting location or similar. Failure to attend a clarification meeting or site visit that is identified as
compulsory will result in disqualification from participation.
Details of the meeting(s) are stated in the Tender Data. Tenderers are entitled to ask
correction of errors as required above.
Evaluation of 3.17 Score the B-BBEE level as stated on the CSD report or as per certificate/affidavit provided.
B-BBEE If the B-BBEE level is a pre-qualification criterion; then the proof of the B-BBEE level
(certificate/CSD number/CSD report) must be provided at the closing date and time for
tender submission; or the tender will be disqualified. If sub-contracting to designated groups
pre-qualification criteria are utilized (selected/mandatory) in terms of the PPPFA
Regulation, then Eskom will apply the PPPFA requirements for sub-contractors’ B-BBEE
status and the sub-contractors’ CSD number or B-BBEE certificate/affidavit will need to be
provided at the closing date and time for tender submission. Should the
information/documents provided indicate that the level is in dispute (fraudulent/ expired)
then the tender will be disqualified.
However, for the purposes of PPPFA point allocation: if no B-BBEE certificate/affidavit is
provided at Tender closing date and time for tender submission, or the
information/documents provided are fraudulent or have expired; then the tenderer will not
be disqualified (if otherwise deemed to be responsive and acceptable in all other aspects)
but will score zero under PPPFA point allocation.
Evaluation of 3.18 Score the Specific Goals with reference to the supporting documentation in the tender. If a
Requirements
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Eligibility 2.1 Submit a tender only if the tenderer (whether a single company or an incorporated or unincorporated joint venture or consortium) complies with the eligibility criteria stated in the Tender Data and the tenderer, or any of its principals, is not under any restriction to do business with Eskom or State-Owned Companies. Tenderers that Eskom finds to be ineligible will be disqualified. Tenderers are not permitted to sub-contract 100% of the scope of work (SOW). Any tender that is based on 100% sub-contracting will be deemed ineligible and will be disqualified.
Section
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdfare submitted and accessible for downloading/evaluation without any challenges as well as
It must be noted that Eskom will not measure a criterion twice in the different evaluation
Functionality 3.13 If functionality is a criterion, tenderers will be scored against the functionality criteria and
further evaluation.
(if applicable) financial risk to Eskom in the execution of the contract. During evaluation of a tenderer’s
Evaluation of Price 3.15 Evaluate the Price in accordance with the criteria/requirements in the Tender Data. Factors
the evaluation Price.
but will score zero under PPPFA point allocation.
Evaluation of 3.18 Score the Specific Goals with reference to the supporting documentation in the tender. If a
Specific Goals tenderer fails to meet Specific Goals and/or to submit the required proof/supporting
will score zero points for Specific Goals within the 90/10 or 80/20 allocation of points.
Ranking of tenders 3.19 According to the PPPFA, Eskom will add the score for Pricing and the Specific Goals
Objective criteria 3.20 A contract may be awarded to a tenderer that did not score the highest points only in
must stipulate the Objective Criteria in the Invitation to Tender. Functionality and any
element of the B-BBEE scorecard may not be used as Objective Criteria.
Reverse e-Auction 3.21 Reverse e-auction is an electronic system that utilises the 90/10 and 80/20 Price and
Preference point systems, and which is intended to achieve competitive pricing. Eskom
(NT instructions, content and/or production by the dtic, PPPFA Regulations; Amended B-BBEE Codes, COIDA;
CIDB, PPPFA etc) OHS Act; Eskom’s requirements for Safety, Health, Environment and Quality (SHEQ) and any other
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
Quality Contract Award. All costs and personnel associated with SHEQ must be reflected in the
However, for the purposes of PPPFA point allocation: if no B-BBEE certificate/affidavit is
Tenders in this industry often require registration with these bodies.
Construction Industry Development Board (CIDB) registration is mandatory for almost all public sector construction tenders. Ensure your grading matches the tender value.
Recommended Certifications
Having these can improve your winning chances: NHBRC Registration, ISO 9001:2015 (Quality Management), ISO 14001:2015 (Environmental Management), ISO 45001:2018 (Occupational Health & Safety), SACPCMP Registration, ECSA Registration
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 38 of 2000
Important for public-sector construction and infrastructure tenders that require contractor grading or construction procurement standards.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 107 of 1998
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
(SDLI) Strategy Setting - Design Supply Installation Commissioning and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station (Sibusiso).pdf
Eskom is inviting tenders for the Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station in Mpumalanga. The project duration is 24 months, with a closing date of June 29, 2026. The tender emphasizes B-BBEE compliance, local procurement, skills development, and socio-economic development (SDL&I) objectives, with penalties for non-compliance.
Eskom life-saving rules.pdf
The tender is for the Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Eskom's Duvha Power Station in Mpumalanga, with a 24-month project duration. The tender emphasizes strict adherence to Eskom's Life-Saving Rules, which are mandatory safety protocols to prevent serious injuries or fatalities. These rules apply to all employees, contractors, and visitors and include electrical safety, working at heights, seatbelt use, sobriety, and permit-to-work requirements. Non-compliance results in severe disciplinary action, including potential removal from the site.
Invitation to Tender (ITT) - E3020GXMPDUV (003).pdf
Eskom Holdings SOC Ltd invites tenders for the Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station. The contract duration is 24 months, with a tender validity period of 12 weeks. Submissions must be made electronically via Eskom’s E-tendering system by 29 June 2026 at 10:00 UTC. The project includes technical, commercial, and safety compliance requirements, with a focus on local content, B-BBEE, and CIDB grading.
E-Tenderers E-Tendering Training Acknowledgement Form.pdf
The tender is for the design, supply, installation, commissioning, and testing of a Sulphuric Acid Storage and Dilution Upgrade Project at Eskom's Duvha Power Station in Mpumalanga. The project duration is 24 months, and the tender closes on June 29, 2026. Applicants must acknowledge e-tendering training via a provided form.
Supplier Quality Management_Returnables Latest catagory 2.xlsx
The tender is for the Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station in Mpumalanga, South Africa. The project duration is 24 months, and the tender is issued by Eskom. The closing date for submissions is June 29, 2026. The tender emphasizes compliance with ISO 9001:2015 standards for Quality Management Systems (QMS) and requires detailed documentation, including quality plans, audit reports, and evidence of operational QMS.
E-Tendering Help Manual for supplier.pdf
Eskom is inviting tenders for the Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station. The project duration is 24 months, and submissions must be made via the eTendering system by June 29, 2026, 10:00 UTC.
Environmental returnables for Acid Regent Project.pdf
Eskom is inviting tenders for the Design, Supply, Installation, Commissioning, and Testing of a Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station in Mpumalanga. The project duration is 24 months, with a closing date of June 29, 2026. The tender includes environmental compliance requirements, such as adherence to ISO 14001:2015 Environmental Policy.
240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP) rev 2.pdf
The tender is for the Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Eskom's Duvha Power Station in Mpumalanga. The project duration is 24 months, with a closing date of June 29, 2026. The tender includes a Quality Control Plan (QCP) and Inspection and Test Plan (ITP) with detailed intervention points, inspection methods, and acceptance criteria.
SAFETY REQUIREMENTS.pdf
Eskom is inviting tenders for the Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station in Mpumalanga. The project duration is 24 months, with a closing date of June 29, 2026. The tender emphasizes strict Occupational Health and Safety (OHS) compliance, including detailed OHS plans, risk assessments, training, PPE, and site establishment requirements.
Declaration of Shareholding or Beneficiaries Form.pdf
The tender is for the Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Eskom's Duvha Power Station in Mpumalanga. The project duration is 24 months, and the closing date for submissions is June 29, 2026. Applicants must disclose shareholding and beneficiary details, including any conflicts of interest with Eskom employees or their close family members.
ECC3 Contract for Design Supply and installation of Duvha Acid Regen .pdf
Eskom Holdings SOC Ltd is inviting tenders for the Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station in Mpumalanga. The contract duration is 24 months, with a closing date of June 29, 2026. The project involves upgrading storage and dilution systems for sulphuric acid, including safety, compliance, and technical specifications for handling hazardous chemicals.
240-105658000 Supplier Quality Management Specification (3).pdf
The tender is for the **Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station** over **24 months**. Issued by **Eskom (Mpumalanga)**, it requires strict adherence to **Supplier Quality Management (QMS) Specification 240-105658000 (QM 58)**, mandating ISO 9001 compliance, detailed quality plans (CQP/QCP), and rigorous monitoring. Closing date: **29 June 2026**.
240-109253698 CQP Template 2021.pdf
Eskom is inviting tenders for the Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station in Mpumalanga. The project duration is 24 months, and the tender closes on 29 June 2026. The scope includes a comprehensive quality management plan (QCP) aligned with SANS 466:2005 / ISO 10005:2005, covering design, manufacturing, supply, installation, and commissioning activities. The tender requires strict adherence to quality assurance, control, and documentation processes, including sub-supplier management, risk mitigation, and compliance with industry standards.
240-68099512 Form A category 2 Rev 9.pdf
Eskom is inviting tenders for the Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station. The project duration is 24 months, and the tender closes on June 29, 2026. The tender emphasizes compliance with ISO 9001 standards and Eskom's Quality Requirements (Document 240-105658000).
Duvha Power Station Sulphuric Acid Storage and Dilution System Technical Evaluation Strategy Rev 03.pdf
Eskom is inviting tenders for the Design, Supply, Installation, Commissioning, and Testing of a Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station in Mpumalanga. The project aims to improve the regeneration of ion exchange resins by addressing design flaws and maintenance issues in the current system, which have caused downtime and safety risks. The contract duration is 24 months, with a closing date of June 29, 2026.
Eskom Supplier Integrity Pact - 02 June 2023 (1).pdf
Eskom is inviting tenders for the Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station. The project duration is 24 months. The tender is governed by Eskom’s Supplier Integrity Pact, which mandates ethical behavior, transparency, and compliance with South African laws and Eskom’s procurement policies. Suppliers must adhere to strict anti-corruption, confidentiality, and conflict-of-interest guidelines.
Eskom - Standard Conditions of Tender - 30 January 2025.pdf
Eskom is inviting tenders for the Design, Supply, Installation, Commissioning, and Testing of the Sulphuric Acid Storage and Dilution Upgrade Project at Duvha Power Station in Mpumalanga. The project duration is 24 months, with a closing date of 29 June 2026. The tender process is governed by Eskom's Standard Conditions of Tender, emphasizing fairness, transparency, and compliance with legal and regulatory frameworks.
To download these documents and access AI-powered analysis, visit the main tender page.
Organization
EskomContact Person
Sibusiso Mthimkulu
Phone
017-799-2302
[email protected]
Website
www.eskom.co.za/
Address
Maxwell Dr, Sunninghill, Sandton, 2157, South Africa
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
18
Last checked
05 Jun 2026
AI status
Enhanced
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Eskom is South Africa's primary electricity supplier, managing generation, transmission, and distribution.
Key Personnel
Safety
Financial
Sub Supplier Approval
Sub-suppliers and subcontractors must meet Eskom’s approval criteria and quality standards.
Relevant where environmental authorisations, EIAs or environmental compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 85 of 1993
Sets health and safety duties for contractors, employers and service providers working on public-sector sites.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 103 of 1977
Relevant where building standards, renovations, maintenance or construction compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Data conflicts
None detected
Maxwell Dr, Sunninghill, Sandton, 2157, South Africa
Get deep intelligence on Specialised construction activities. Unlock full pricing strategies, bid frequency, and historical win rates.