Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
Betha/Ogies Road - Kriel - Kriel - 2271
Organization Type
GOVERNMENT
Published
07 Jul 2026
OCDS Reference
ocds-9t57fa-161533
This tender, issued by ESKOM, invites bids for the supply and delivery of hp power pack and servo motors hydraulic equipment spares on an as-and-when required basis to kriel power station over a five-year period. Suppliers must comply with eskom’s code of ethics and ethical standards.
Date & Time
Tuesday, 28 July 2026 - 11:00
Venue
Microsoft Teams meeting
Categories
Request for Bid(Open-Tender)
Betha/Ogies Road - Kriel - Kriel - 2271
07 Jul
2026
Tender Published
Tender was published
28 Jul
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
Eskom - Standard Conditions of Tender (August 2024).pdf
Median Estimate
R 685 017
Range
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
Learn how to submit a winning bid with these related articles
Your meticulously crafted General sector tender submission can be disqualified for a single, seemingly minor compliance oversight. The reality for South African contractors is that technical competence is no longer sufficient; it is underpinned by a non-negotiable framework of documentary compliance. This regulatory guide: mastering CSD and BBBEE compliance for general sector tenders in south africa provides a comprehensive, step-by-step breakdown of the mandatory registrations and certificates you must secure and present. We detail the precise requirements for CSD, BBBEE, SARS TCS, CIPC, and COIDA, explaining their function within the procurement ecosystem governed by the PFMA and PPPFA. Learn the actionable steps to prepare your business, avoid the most common disqualifying errors, and leverage technology to streamline your compliance process for successful bidding in 2026 and beyond.
For South African General contractors, the path to government procurement is paved with non-negotiable regulatory requirements. The most common barrier to entry is not a lack of capability, but a failure to master the foundational compliance frameworks that govern every bid. This complete regulatory guide to CSD and BBBEE compliance for General sector tender suppliers in South Africa demystifies the process. It provides a meticulous, step-by-step field manual for ensuring your company is fully compliant and audit-ready, enabling you to confidently access the R billions in opportunities across infrastructure maintenance, facilities management, and service delivery within the General sector.
Everything South African general contractors need to know about how to write a winning tender proposal without an in-house bid team in gauteng — covering CSD, BBBEE, step-by-step processes, common disqualification mistakes, and how Tenders-SA.org helps you find and win relevant contracts in Gauteng.
This definitive guide provides General sector contractors with the precise, actionable steps required to achieve and maintain CSD and BBBEE compliance for South African public tenders in 2026. Authored by Dr. Sarah Mokwena, a Legal Compliance Specialist, it meticulously walks through the regulatory framework, mandatory registrations, and the critical documentation needed to avoid disqualification. We dissect the common, costly errors made during submission and provide a clear checklist to ensure your bid is responsive and competitive. Learn how to navigate the Central Supplier Database, validate your BBBEE status, and integrate compliance into your tender preparation process.
💡 Want more tendering tips and strategies?
Explore Our BlogRecommended Certifications
Having these can improve your winning chances: SABS Product Certification, NRCS Certification
AI Document Analysis Stages
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Review in progress
The information shown on this card is preliminary. Our procurement team is currently finalising the submission guidelines, evaluation criteria, technical specifications, financial requirements, and compliance sections so you have a clean, bid-ready summary to work from. Documents being finalised: Annex-c_Local content Declaration-Summary Schedule.pdf, Annex-d_Imports Declaration-Supporting schedule to Annex C - Copy.pdf, Technical Criteria for Refurbishment of Reheat safety_HP Bypass valves valves 2025 Rev 1 Signed.pdf and 1 more. You don’t need to refresh — this page will pick up the updated review automatically.
Contact Information
Source: NEC3 HP Power Pack.pdf (unknown){"name":null,"email":"[email protected]","phone":"011 871 3706","department":null,"address":"he parties arising from this Agreement."}
Evaluation Criteria
Source: NEC3 HP Power Pack.pdf (unknown)Any quality related issues.
Technical Specifications
Source: NEC3 HP Power Pack.pdf (unknown)Supply Contract (SC3)
Between ESKOM HOLDINGS SOC Ltd
(Reg No. 2002/015527/30)
and
(Reg No. )
for SUPPLY AND DELIVERY OF HP POWER PACK AND SERVO
Motors hydraulic equipment spares as and when
Required basis at kriel power station for the
Period of five years.
Contents: No of
pages
Part C1 Agreements & Contract Data 18
Part C2 Pricing Data 6
Part C3 Scope of Work
Pricing Schedule
Source: NEC3 HP Power Pack.pdfContents: No of
pages
Part C1 Agreements & Contract Data 18
Part C2 Pricing Data 6
Part C3 Scope of Work 13
Part C1 Agreements and Contract Data, (which includes this Form of Offer and Acceptance)
Part C2 Pricing Data
Part C3 Scope of Work: Goods Information including Supply Requirements
and drawings and documents (or parts thereof), which may be incorporated by reference into the above
listed Parts.
11.2(8) The Goods Information for the Supplier
design is in:
11.2(11) The tendered total of the Prices is R ,
(in words)
11.2(12) The price schedule is in:
11.2(14) The following matters will be included in
the Risk Register
25.2 The restrictions to access for the Supply
Part 2: pricing data
NEC3 Supply Contract
C2.1 Pricing assumptions 2
C2.2 The price schedule 3
Part c2: pricing data c2 sc3 cover
C2.1 Pricing assumptions
(12) The Price Schedule is the price schedule unless later changed in
accordance with this contract.
Assessing the 50.2 The amount due is
amount due
the Price for each lump sum item in the Price Schedule which the Supplier
has completed,
where a quantity is stated for an item in the Price Schedule, an amount
calculated by multiplying the quantity which the Supplier has completed by
the rate,
plus other amounts to be paid to the Supplier,
less amounts to be paid by or retained from the Supplier.
Clause 53.1 states: Price Schedule is not Goods Information This confirms that
instructions to do work or how it is to be done are not included in the Price Schedule but in the
Goods Information. This is further confirmed by Clause 20.1 which states Supplier Provides
the Goods and Services in accordance with the Goods Hence the Supplier does not
should insert any additional items which he considers necessary. Whichever party provides the
items in the price schedule the total of the Prices is assumed to be fully inclusive of everything
necessary to Provide the Goods and Services as described at the time of entering into this
contract.
Read Pages 8, 11, 12 and Appendix 5 of the SC3 Guidance Notes before preparing the price
schedule;
Included in his Prices and rates for correction of Defects (core clause 43.1) as there is no
Part c2: pricing data c2.1 Sc3 pricing assumptions
across other Prices and rates in order to fulfil the obligation to Provide the Goods and
Services for the tendered total of the Prices;
may arise as a result of a compensation event.
3.1. Format of the price schedule
Entries in the first four columns in the price schedule in section C2.2 are made either by the
goods and services are provided, a unit of time is stated in the Unit column and the length of time (as
a quantity of the stated units of time) is stated in the Quantity column.
Part c2: pricing data c2.1 Sc3 pricing assumptions
Financial Requirements
Source: NEC3 HP Power Pack.pdf (unknown)Payment Terms: payment certificate from the Supply Manager in terms of core
clause 51.1, the Supplier provides the Purchaser with a tax invoice in accordance with the
Purchaser's procedures stated in the Goods Information, showing the amount due for payment
equal to that stated in the payment certificate.
Z7.2 If the Supplier does not provide a tax invoice in the form and by t
Compliance Requirements
Source: NEC3 HP Power Pack.pdf (unknown)No specific requirements found
B-BBEE Minimum Level: 1
B-BBEE Details: deemed to be jointly
and severally liable to the Purchaser for the performance of this contract.
Z2.2 Unless already notified to the Purchaser, the persons or organisations notify the Supply
Manager within two weeks of the Contract Date of the key person who has the authority to bind
the Supplier on their behalf.
Z2.3 The Supplier does not alter the composition of the joint venture, consortium or other
unincorporated grouping of two or more persons without the consent of the Purchaser having
been given to the Supplier in writing.
Z3 Change of Broad Based Black Economic Empowerment (B-BBEE) status
Z3.1 Where a change in the Supplier legal status, ownership or any other change to his business
composition or business dealings results in a change to the Supplier -BBEE status, the
Supplier notifies the Purchaser within seven days of the change.
Z3.2 The Supplier is required to submit an updated verification certificate and necessary supporting
documentation confirming the change in his B-BBEE status to the Supply Manager within thirty
days of the notification or as otherwise instructed by the Supply Manager.
Z3.3 Where, as a result, the Supplier B-BBEE status has decreased since the Contract Date the
Purchaser may either re-negotiate this contract or alternatively, terminate the Supplier
obligation to Provide the Goods and Services.
Z3.4 Failure by the Supplier to notify the Purchaser of a change in its B-BBEE status may constitute
a reason for termination. If the Purchaser terminates in terms of this clause, the procedures on
termination are P1, P2 and P3 as stated in clause 92, and the amount due is A1 and A3 as
stated in clause 93.
Z4 Confidentiality
Z4.1 The Supplier does not disclose or make any information arising from or in connection wi
Health & Safety
Source: NEC3 HP Power Pack.pdfsignature of Date
witness
Note: If a tenderer wishes to submit alternative tenders, use another copy of this Form of Offer and
no rate is quoted for the currency in question
then the rate for United States Dollars, and if
no such rate appears in The Wall Street
Z4.4 The taking of images (whether photographs, video footage or otherwise) of the goods or any
portion thereof, in the course of Providing the Goods and Services and after Delivery, requires
the prior written consent of the Supply Manager. All rights in and to all such images vests
exclusively in the Purchaser.
Z4.5 The Supplier ensures that all his subcontractors abide by the undertakings in this clause.
Z5 Waiver and estoppel: Add to core clause 12.3:
Z5.1 Any extension, concession, waiver or relaxation of any action stated in this contract by the
not give rise to an estoppel unless the Parties agree otherwise and confirm such agreement in
writing.
Z6 Health, safety and the environment: Add to core clause 25.4
Z6.1 The Supplier undertakes to take all reasonable precautions to maintain the health and safety of
persons in and about the provision of the goods and execution of the services.
warrants that the total of the Prices as at the Contract Date includes a sufficient amount for
proper compliance with all applicable health & safety laws and regulations and the health
and safety rules, guidelines and procedures provided for in this contract and generally for
the proper maintenance of health & safety in and about the execution of supply and
undertakes, in and about the execution of the supply, to comply with all applicable health &
safety laws and regulations and rules, guidelines and procedures otherwise provided for
under this contract and ensures that his Subcontractors, employees and others under the
direction and control, likewise observe and comply with the foregoing.
Z6.2 The Supplier, in and about the execution of the supply, complies with all applicable
environmental laws and regulations and rules, guidelines and procedures otherwise provided
for under this contract and ensures that his Subcontractors, employees and others under the
direction and control, likewise observe and comply with the foregoing.
Z7 Provision of a Tax Invoice and interest. Add to core clause 51
Z7.1 Within one week of receiving a payment certificate from the Supply Manager in terms of core
clause 51.1, the Supplier provides the Purchaser with a tax invoice in accordance with the
the regulations published in GNR February 2002, under the Occupational Health
OEL for asbestos is 0.2
regulated asbestos fibres per millilitre of air as a 4-hour TWA, averaged over any continuous
period of four hours, and the short term exposure limit of 0.6 regulated asbestos fibres per
millilitre of air as a 10-minute TWA, averaged over any 10 minutes, measured in accordance
with HSG248 and monitored according to HSG173 and OESSM.
Z15.2 Upon written request by the Supplier, the Purchaser certifies that these conditions prevail. All
measurements and reporting are effected by an independent, competent, and certified
occupational hygiene inspection body, i.e. a SANAS accredited and Department of
and related control measures at the Supplier
results generated from Parallel Measurements are evaluated only against South African
statutory limits as detailed in clause Z15.1. Control measures conform to the requirements
stipulated in the AAIA-approved asbestos work plan.
Z15.3 The Purchaser manages asbestos and ACM according to the Standard.
Z15.4 In the event that any asbestos is identified while Providing the Services, a risk assessment is
conducted and if so required, with reference to possible exposure to an airborne concentration
of above the AL for asbestos, immediate control measures are implemented and relevant air
monitoring conducted in order to declare the area safe.
Z15.5 The Supplier
forthwith until such time that the area of concern is declared safe by either Compliance
emergency asbestos work plan, if applicable.
Z15.6 The Supplier continues to Provide the Services, without additional control measures
presented, on presentation of Safe Levels. The contractually agreed dates to Provide the
on which the spares will be required. This will ensure quality and sustainable maintenance basis for all
plant work required to provide optimal plant performance at the lowest cost possibly. The original
equipment manufacturers are required to provide specifications of the hydraulic spares to be supplied
and must be supplied or delivered with
the required documents for traceability, material certification and data books/sheets attached.
Environmental
Source: NEC3 HP Power Pack.pdfZ15.7 Any removal and disposal of asbestos, asbestos containing materials and waste, is done by a
registered asbestos contractor, instructed by the Purchaser at the Purchaser
conducted in line with South African legislation.
Part c1: agreements and contract data c1.2A Sc3 contract data part 1
Contractual Terms
Source: NEC3 HP Power Pack.pdfof Deviations (if any), contact the Purchaser
arrange the delivery of any securities, bonds, guarantees, proof of insurance and any other documentation to
be provided in terms of the conditions of contract identified in the Contract Data at, or just after, the date this
agreement comes into effect. Failure to fulfil any of these obligations in accordance with those terms shall
constitute a repudiation of this agreement.
specification.
covid restrictions.
11.2(15) The Goods Information is in Part 3: Scope of Work and all documents and
drawings to which it makes reference.
11.2(15) The Supply Requirements as part of the Part C3 of the NEC , item 3.
50.1 The assessment interval is 1 Week after each delivery acceptance.
51.1 The currency of this contract is the South African Rand
51.2 The period within which payments are 1. 30 days for Contracts with a value less than
made is R50M.
than R50M.
51.4 The interest rate is the publicly quoted prime rate of interest
(calculated on a 365 day year) charged from
time to time by the Standard Bank of South
Africa Limited (as certified, in the event of any
dispute, by any manager of such bank, whose
appointment it shall not be necessary to prove)
for amounts due in Rands and
(ii) the LIBOR rate applicable at the time for
amounts due in other currencies. LIBOR is the
6 month London Interbank Offered Rate quoted
Monitor Money Rates Service (or such service
as may replace the Reuters Monitor Money
Rates Service) on the due date for the payment
in question, adjusted mutatis mutandis every 6
months thereafter and as certified, in the event
of any dispute, by any manager employed in
the foreign exchange department of The
insurance
80.1 These are additional Purchaser risks Not applicable
88.1 The Supplier liability to the Purchaser for
Part c1: agreements and contract data c1.2A Sc3 contract data part 1
indirect or consequential loss, including
loss of profit, revenue and goodwill is
limited to R0.0 (zero Rand)
88.2 For any one event, the Supplier liability (1) for the Purchaser existing and
to the Purchaser for loss of or damage to surrounding property in the care, custody and
the Purchaser property is limited to control of the Supplier the amount of the
deductible (first amount payable) relevant to
the event
and
(2) for all other existing Purchaser property
the applicable deductible as at contract date
88.3 The Supplier liability for Defects due to his Not applicable
design which are not notified before the last
defects date is limited to:
88.4 The Supplier total liability to the The total of the Prices
in connection with this contract, other than
the excluded matters, is limited to
88.5 The end of liability date is 1 year after delivery to the spare to the plant.
dispute to him. (see www.ice-sa.org.za). If the
e-mail To be known once the dispute arises
94.2(3) The Adjudicator nominating body is: the Chairman of ICE-SA, a Division of the
obligation to Provide the Goods and Services.
Z3.4 Failure by the Supplier to notify the Purchaser of a change in its B-BBEE status may constitute
a reason for termination. If the Purchaser terminates in terms of this clause, the procedures on
termination are P1, P2 and P3 as stated in clause 92, and the amount due is A1 and A3 as
stated in clause 93.
Z4 Confidentiality
Z4.1 The Supplier does not disclose or make any information arising from or in connection with this
contract available to Others. This undertaking does not, however, apply to information which at
the time of disclosure or thereafter, without default on the part of the Supplier, enters the public
domain or to information which was already in the possession of the Supplier at the time of
disclosure (evidenced by written records in existence at that time). Should the Supplier
disclose information to Others in terms of clause 23.1, the Supplier ensures that the provisions
of this clause are complied with by the recipient.
Z4.2 If the Supplier is uncertain about whether any such information is confidential, it is to be
regarded as such until notified otherwise by the Supply Manager.
Z4.3 In the event that the Supplier is, at any time, required by law to disclose any such information
which is required to be kept confidential, the Supplier, to the extent permitted by law prior to
disclosure, notifies the Purchaser so that an appropriate protection order and/or any other
action can be taken if possible, prior to any disclosure. In the event that such protective order is
not, or cannot, be obtained, then the Supplier may disclose that portion of the information which
it is required to be disclosed by law and uses reasonable efforts to obtain assurances that
confidential treatment will be afforded to the information so disclosed.
Part c1: agreements and contract data c1.2A Sc3 contract data part 1
Z9 limitation of liability
Z9.1 The liability to the Supplier for the indirect or consequential loss is
limited to R0.00 (zero Rand)
Z9.2 The Supplier
Termination: Add to core clause 91.1, at the second main bullet point, fourth sub-bullet
Z10
point, after the words "against it":
Z10.1 or had a business rescue order granted against it.
Z11 Addition to secondary Option X7 Delay damages (if applicable in this contract)
Z11.1 If the amount due for the Supplier
Contract Data for Option X7, the Purchaser may terminate the Supplier
the Goods and Services using the same procedures and payment on termination as those
applied for reasons R1 to R15 or R18 stated in the Termination Table.
Z12 Ethics
court or in any other similar process, of such Prohibited Action before the Purchaser can
terminate the Supplier
Z12.3 If the Purchaser terminates the Supplier
the amounts due on termination are those intended in core clauses 92.1 and 92.2.
Z12.4 A Committing Party co-operates fully with any investigation pursuant to alleged Prohibited
Z13Insurance
Z 13.1 Replace core clause 84 with the following:
Insurance cover 84
84.1 When requested by a Party, the other Party provides certificates from
his insurer or broker stating that the insurances required by this
contract are in force.
84.2 The Supplier provides the insurances stated in the Insurance Table A
for events which are at the Supplier starting date until
the last defects date or a termination certificate has been issued.
Part c1: agreements and contract data c1.2A Sc3 contract data part 1
goods, plant and materials s insurance.
damage to property Purchaser
(except the goods, plant The replacement cost where not covered by the
and materials and s insurance.
equipment) and liability for
bodily injury to or death of The Purchaser
a person (not an employee Contract Date, where covered by the
of the Supplier) caused by s insurance.
activity in connection with
this contract Other property
bodily injury to employees
of the Supplier arising out
of and in the course of
their employment in
connection with this
contract
Z _13.2 Replace core clause 87 with the following:
Insurance by 87
the Purchaser
87.1 The Purchaser provides the insurances stated in the Insurance Table B
Transportation (Marine) Per the insurance policy document
Z14 Nuclear Liability
Z14.1 The Purchaser is the operator of the Koeberg Nuclear Power Station (KNPS), a nuclear
installation, as designated by the National Nuclear Regulator of the Republic of South Africa,
and is the holder of a nuclear licence in respect of the KNPS.
Z14.2 The Purchaser is solely responsible for and indemnifies the Supplier or any other person
against any and all liabilities which the Supplier or any person may incur arising out of or
resulting from nuclear damage, as defined in Act , save to the extent that any
liabilities are incurred due to the unlawful intent of the Supplier or any other person or the
presence of the Supplier or that person or any property of the Supplier or such person at or in
the KNPS or on the KNPS site, without the permission of the Purchaser or of a person acting
on behalf of the Purchaser.
Z14.3 Subject to clause Z14.4 below, the Purchaser waives all rights of recourse, arising from the
aforesaid, save to the extent that any claims arise or liability is incurred due or attributable to
the unlawful intent of the Supplier or any other person, or the presence of the Supplier or that
person or any property of the Supplier or such person at or in the KNPS or on the KNPS site,
without the permission of the Purchaser or of a person acting on behalf of the Purchaser.
Z14.4 The Purchaser does not waive its rights provided for in section 30 (7) of Act , or any
replacement section dealing with the same subject matter.
Z14.5 The protection afforded by the provisions hereof shall be in effect until the KNPS is
decommissioned.
Z15 Asbestos
insurance requirements incidental to the supply and transport of the goods from Supplier to Purchaser.
For each of the thirteen terms, Incoterms set out obligations of the seller (the Supplier) in ten paragraphs
identified as A1 to A10 and the corresponding obligations of the buyer (the Purchaser) in paragraphs B1 to
B10. These obligations cover the following subjects:
A1 Provision of goods in conformity with B1 Payment of the price
contract
A2 Licences, authorisations and formalities B2 Licences, authorisations and formalities
A3 Contracts of carriage and insurance B3 Contracts of carriage and insurance
A4 Delivery B4 Taking delivery
A5 Transfer of risks B5 Transfer of risks
A6 Division of costs B6 Division of costs
A7 Notice to the buyer B7 Notice to the seller
A8 Proof of delivery, transport document or B8 Proof of delivery, transport document or
equivalent electronic message equivalent electronic message
A9 Checking - packing - marking B9 Inspection of goods
A10 Other obligations B10 Other obligations
[Should there be a need to amplify any of the published obligations listed above for the chosen INCOTERM,
add them here.]
Part 3: Scope of Work ................................................................................................................................................ 1
C3.1: Goods Information .................................................................................................................... 2
1 Overview and purpose of the goods and services ..................................................................................... 4
2 Specification and description of the goods ................................................................................................. 4
2.1 Purchaser ............................................................................................................................... 5
2.2 Procedure for submission and acceptance of Supplier .......................................................... 5
2.3 Other requirements of the Supplier ........................................................................................ 5
2.4 Use of Supplier ....................................................................................................................... 5
2.5 Manufacture & fabrication .............................................................................................................................. 6
2.6 Factory acceptance testing (FAT) ................................................................................................................. 6
2.7 Other tests and inspections and commissioning in place of use................................................................ 6
2.8 Operating manuals and maintenance schedules ........................................................................................ 6
3 Supply Requirements ....................................................................................................................................... 6
4 Specification of the services to be provided ............................................................................................... 7
5 Constraints on how the Supplier Provides the Goods .............................................................................. 7
5.1 Programming constraints ............................................................................................................................... 7
5.2 Work to be done by the Delivery Date .......................................................................................................... 7
5.3 Marking the goods .......................................................................................................................................... 7
5.3.1 Valve name plate markings .................................................................................................................. 7
5.3.2 Valve body markings ............................................................................................................................. 7
5.4 Constraints at the delivery place and place of use ...................................................................................... 7
5.5 Cooperating with Others ................................................................................................................................ 7
5.6 Services & other things to be provided by the Purchaser or Supplier ....................................................... 8
5.7 Management meetings ................................................................................................................................... 8
5.8 Documentation control ................................................................................................................................... 8
5.9 Health and safety risk management ............................................................................................................. 8
5.10 Environmental constraints and management .......................................................................................... 8
5.11 Quality ......................................................................................................................................................... 9
5.12 Invoicing and payment .............................................................................................................................. 9
5.13 Insurance provided by the Purchaser ...................................................................................................... 9
5.14 Contract change management ................................................................................................................. 9
5.15 Provision of bonds and guarantees ........................................................................................................ 10
5.16 Records of Defined Cost, payments & assessments of compensation events to be kept by the
Supplier 10
Part c3: scope of work c3.1 Sc3 purchaser goods information
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
SDL&I strategy for Supply and Delivery of HP Power Pack and Servo Motors - Copy.pdf
Commercial Code of Ethics 32-527 Rev 0.pdf
Annex-e_Local Content Declaration-Supporting Schedule to Annex C.pdf
Annexure B.pdf
E-tendering Help Manual for supplier - 27 January 2025.docx
Eskom is inviting tenders for the supply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment Spares on an 'as and when required' basis for Kriel Power Station over a five-year period. Submissions must be made electronically via the eTendering system.
240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP) rev 2.docx
The tender is for the supply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment Spares on an 'as and when required' basis to Kriel Power Station over a five-year period. The contract is managed by Eskom and requires adherence to a detailed Quality Control Plan (QCP) with specified inspection and testing methods.
Safety Returnables.pdf
Eskom is inviting tenders for the supply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment Spares on an 'as and when required' basis to Kriel Power Station over a five-year period. The tender emphasizes strict Safety, Health, and Environmental (SHE) compliance, including signed acknowledgments, risk assessments, and valid certifications.
Technical Criteria for Refurbishment of Reheat safety_HP Bypass valves valves 2025 Rev 1 Signed.pdf
Annexure B.docx
The tender is for the supply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment Spares on an 'as and when required' basis to Kriel Power Station over a five-year period. The supplier must comply with Eskom's Occupational Health and Safety (OHS) legal requirements, policies, and standards, including statutory regulations and Eskom-specific procedures.
E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.docx
Eskom is inviting tenders for the supply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment Spares on an 'as and when required' basis to Kriel Power Station over a five-year period. The tender process requires mandatory e-tendering training acknowledgment.
List of Tender Returnables- HP Power Pack and Servo Motors Hydraulic Equipment Spares .pdf
Eskom is inviting tenders for the supply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment Spares on an 'as and when required' basis for Kriel Power Station over a five-year period. The tender emphasizes compliance with ISO 9001 Quality Management System (QMS) standards and requires documented evidence of operational QMS, a Contract Quality Plan, and a Quality Control Plan.
240-113650212 Eskom Supplier Integrity Pact Rev 2 June 2028.pdf
The tender is for the supply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment Spares on an 'as and when required' basis to Kriel Power Station over a five-year period. The procurement process is governed by Eskom's Supplier Integrity Pact, which mandates ethical behavior, transparency, and compliance with South African laws and constitutional principles.
Safety Returnables.docx
The tender is for the supply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment Spares on an 'as and when required' basis to Kriel Power Station over a five-year period. Issued by ESKOM, it emphasizes strict Safety, Health, and Environment (SHE) compliance, with detailed documentation and certifications required from bidders.
FORM A.docx
This tender, issued by ESKOM, is for the supply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment Spares on an 'as and when required' basis to Kriel Power Station over a five-year period. The tender emphasizes compliance with quality management standards, including ISO 9001, and requires adherence to Eskom's pre- and post-contract award quality requirements, supplier performance monitoring, and standard conditions such as rights of access, information, preservation, and quality audits.
Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025.pdf
Scope of Work for Kriel Power Station HP Power Pack and Servo Motors Hydraulic Equipment Spares 20251015 Rev 2_1 Signed.pdf
Annex-c_Local content Declaration-Summary Schedule.pdf
NEC3 HP Power Pack.pdf
Annex-d_Imports Declaration-Supporting schedule to Annex C - Copy.pdf
240-109253698 CQP Template.docx
Eskom General Conditions of Purchase - 31 May 2024.pdf
To download these documents and access AI-powered analysis, visit the main tender page.
Organization
EskomContact Person
Ernest Mogashoa
Phone
015-299-0125
[email protected]
Address
Betha/Ogies Road - Kriel - Kriel - 2271
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
22
Last checked
07 Jul 2026
AI status
Enhanced
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Eskom is South Africa's primary electricity supplier, managing generation, transmission, and distribution.
Submission Guidelines
Source: FORM A.docx (unknown)Returnable Documents: Complete Form A (Tender & Contract Quality Requirements) with applicable clauses marked (X) or non-applicable (-). Ensure sections for Eskom and Tenderer quality representatives are signed and dated.
Evaluation Criteria
Source: FORM A.docx (unknown)Capacity Assessment
Main supplier and sub-supplier capability and capacity assessment (Clause 3.6 of 240-105658000) is implied but not explicitly marked as applicable.
Quality Management
Must demonstrate adherence to ISO 9001 principles and Eskom’s quality requirements.
Technical Compliance
Ability to supply and deliver HP Power Pack and Servo Motors Hydraulic Equipment Spares as per Eskom’s technical and quality standards.
Legal Compliance
Compliance with all standard conditions outlined in Clause 6, including audits and nonconformity management.
Technical Specifications
Source: FORM A.docx (unknown)Scope: Supply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment spares on an 'as and when required' basis to Kriel Power Station for a 5-year period. Quality Requirements: Pre-contract award quality requirements (Clause 3) apply. Post-contract award includes Contract Execution (Clause 3.7.1) and Supplier Quality Performance Monitoring (Clause 3.7.2). Standard Conditions: Eskom retains rights of access (Clause 3.8.1), information (Clause 3.8.2), and preservation (Clause 3.8.3). Quality audits (Clause 3.8.4), management of nonconformities (Clause 3.8.5), and special processes (Clause 3.8.6) are mandatory. ISO 9001 compliance required for: Context of the Organisation, Leadership, Planning, Support, Operation, Performance Evaluations, and Improvement. Main supplier and sub-supplier capability and capacity assessment (Clause 3.6) is required.
Compliance Requirements
Source: FORM A.docx (unknown)Quality Management System: Must align with ISO 9001 principles (Customer focus, Leadership, Engagement of people, Process approach, Improvement, Evidence-based decision making, Relationship Management). Pre-contract award quality requirements (Clause 3) must be met. Post-contract compliance includes quality performance monitoring and nonconformity management.
Important Dates
Source: Eskom - Standard Conditions of Tender (August 2024).pdf (TENDER){"closingTime":"2.2","briefingSession":"{"date":null,"time":null,"venue":"tend a site visit and/or clarification meeting that is stipulated as being","is_compulsory":true}"}
Contact Information
Source: Eskom - Standard Conditions of Tender (August 2024).pdf (TENDER){"name":null,"email":null,"phone":null,"department":"Supply Chain Management","address":"g time 2.2 Ensure that Eskom has received the complete original tender and one (1) complete hard"}
Evaluation Criteria
Source: Eskom - Standard Conditions of Tender (August 2024).pdf (TENDER)demonstrate that aspects of the tender satisfy the evaluation criteria, or the negotiation of
2.8 Return the mandatory tender returnables to Eskom for evaluation purposes by tender
returnables Invitation to Tender by the required deadlines will be disqualified from further evaluation.
materials and will result in its disqualification from further evaluation.
Functionality 3.12 If functionality is a criterion, tenderers will be scored against the functionality criteria and
further evaluation.
(if applicable) financial risk to Eskom in the execution of the contract. During evaluation of a tenderer’s
Evaluation of Price 3.14 Evaluate the Price in accordance with the criteria/requirements in the Tender Data.
Evaluation of 3.16 Score the Specific Goals with reference to the supporting documentation in the tender. If
Specific Goals a tenderer fails to meet Specific Goals and/or to submit the required proof/supporting
tenderer will score zero points for Specific Goals within the 90/10 or 80/20 allocation of
Ranking of tenders 3.17 Eskom will add the score for Pricing and Specific Goals together and rank the tenderers
Objective criteria 3.18 A contract may be awarded to a tenderer that did not score the highest points only in
must stipulate the Objective Criteria in the Enquiry. Functionality and any element of the
B-BBEE scorecard may not be used as Objective Criteria.
Reverse e-Auction 3.19 Reverse e-auction is an electronic system that utilises the 90/10 and 80/20 Price and
Preference point systems, and which is intended to achieve competitive pricing. Eskom
(NT instructions, designated for local content and/or production by the dtic, PPPFA Regulations; Amended
CIDB, PPPFA etc) B-BBEE Codes, COIDA; OHS Act; Eskom’s requirements for Safety, Health, Environment and
Quality (SHEQ) and any other applicable legislation or regulatory instruments indicated in the
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
Quality reflected in the tender.
Technical Specifications
Source: Eskom - Standard Conditions of Tender (August 2024).pdf (TENDER)supply identified in the specification and/or works
Quality Management
Source: Eskom - Standard Conditions of Tender (August 2024).pdf240-62044728 Rev 11 Eskom Standard Identifier
Conditions of Tender Effective Date 01 August 2024
Review Date August 2029
Cost of tendering 2.6 Accept that Eskom will not compensate the tenderer for any costs incurred in the
preparation and submission of a tender, including the costs of any testing necessary to
demonstrate that aspects of the tender satisfy the evaluation criteria, or the negotiation of
any contract.
Submitting a tender 2.7 Check the enquiry documents on receipt and notify the Eskom representative of any
discrepancy or omitted documents. The Acknowledgement Form must be completed and
submitted with the tender and must clearly state if the tender is for the whole or part of
the works, services or supply identified in the specification and/or works information by
Pricing Schedule
Source: Eskom - Standard Conditions of Tender (August 2024).pdfa reasonable time for tenderers to make consequential adjustments to their tenders
before the closing date and time for submission.
Insurance 2.17 The extent (if any) of insurance provided by Eskom may not be for the full cover required
in the conditions of contract. The tenderer is advised to seek qualified advice regarding
insurance.
Pricing the tender 2.18 Include in the rates, prices, and the tendered total of the Prices all duties, taxes (including
VAT), and other levies payable by the tenderer if successful. Such duties, taxes and
levies are those applicable 14 (fourteen) days prior to the closing date and time for tender
submission.
2.19 Provide rates and Prices that are fixed for the duration of the contract and are not subject
to contract price adjustment except as provided for in the Enquiry.
240-62044728 Rev 11 Eskom Standard Identifier
Conditions of Tender Effective Date 01 August 2024
Review Date August 2029
2.20 State the rates and Prices in South African Rand unless instructed otherwise in the
other currencies. Submit Prices in Rands in accordance with the exchange rate and
base date as stipulated in the Invitation to tender.
Alterations to 2.21 Not make any alterations or additions to the tender documents, other than for purposes
documents of complying with instructions issued by the Eskom Representative or if necessary to
correct errors made by the tenderer. All such alterations shall be initialed by all
signatories to the tender. Corrections may not be made using correction fluid, correction
tape or the like.
Alternative tenders 2.22 Submit alternative tenders only if a main tender is also submitted, and only if the
submission of alternative tenders is permitted by the Enquiry. Accept that an alternative
tender may be based only on the criteria stated in the Tender Data.
Clarification and 2.23 Provide clarification and documents as may be required by the Eskom Representative
correction of Prices during the evaluation of tenders. Note that documents identified as mandatory tender
after tender returnables that are required to be submitted at the closing date and time for tender
submission submission will not be requested and may not be submitted after the closing date and
time. A clarification that requires the tenderer to provide a breakdown of its tendered rates
or Prices may not result in changes to prices or the substance of the submitted tender,
except as required by the Eskom Representative to confirm the correction of arithmetical
errors discovered during evaluation. The total of the Prices as corrected by Eskom with
the concurrence of the tenderer shall be binding upon the tenderer.
Sign Form of 2.24 Undertake to check the final draft of the contract provided by the Eskom Representative
rates of invoicing are taken into account when determining the tendered Price.
Arithmetical errors 3.15 Check responsive tenders for arithmetical errors. If there is a discrepancy between an
amount in figures and the amount in words, the amount in words shall prevail.
Check the highest-ranked tender for the following errors or omissions: -
a) the misplacement of the decimal point in any unit rate; or
b) omissions in completing the pricing schedule or bill of quantities, or
c) arithmetical errors in line item totals that are the result of the incorrect multiplication
of a unit rate and a quantity in a bill of quantities or schedule of prices; or
d) arithmetical errors that are the result of the incorrect addition of the prices.
will request the tenderer to either confirm the prices as tendered or to accept the
corrected prices.
Where the tenderer elects to confirm the prices as tendered; Eskom will correct the error
as follows: -
a) If a bill of quantities or pricing schedule applies and there is an error in the line-item
total that is the result of an error in multiplying the unit rate and the quantity, the line item
total shall prevail, and the rate shall be corrected.
b) Where there is a misplacement of the decimal point in the unit rate, the line-item total
as quoted shall prevail, and the unit rate shall be corrected.
c) Where there is an error in the total of the prices that is the result either of other
corrections required by the checking process or in the tenderer’s addition of prices, the
total of the prices shall prevail, and the tenderer shall be asked to revise the selected
item prices (and their rates if a bill of quantities applies) to result in the tendered total of
the prices.
documentation by closing date and time of tender submission, the tenderer will not be
disqualified if otherwise evaluated as acceptable in all other criteria; however, the
tenderer will score zero points for Specific Goals within the 90/10 or 80/20 allocation of
points.
Ranking of tenders 3.17 Eskom will add the score for Pricing and Specific Goals together and rank the tenderers
from the highest to the lowest.
Objective criteria 3.18 A contract may be awarded to a tenderer that did not score the highest points only in
accordance with Section 2(1) (f) of the Preferential Procurement Policy Framework Act,
must stipulate the Objective Criteria in the Enquiry. Functionality and any element of the
Compliance Requirements
Source: Eskom - Standard Conditions of Tender (August 2024).pdf (TENDER)CIDB 2.28 Where the Tender Data has stipulated CIDB grading/s as a qualification criterion, tenderers are required to be registered with the Construction Industry Development Board at the closing date and time for submission of tenders or to be capable of being so registered within twenty-one (21) working days from the closing date and time for submission of tenders. Contract Skills 2.29 If the tenderer is awarded a contract, it, as Contractor, shall achieve in the performance Development of the contract the Contract Skills Development Goals (CSDG) established in the CIDB Public When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 9 File name: Eskom - Standard Conditions of Tender (August 2024) Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-62044728 Rev 11 Eskom Standard Identifier Conditions of Tender Effective Date 01 August 2024 Review Date August 2029 Goal (CSDG) Standard for Developing Skills through Infrastructure Contract (published in GN 1779, Government Gazette No. April 2023) CSDG is applicable to a contract or an order issued in terms of a framework agreement that has a duration of 12 months or more, and to
a contract of R5 million or more, in the case of a professional service or service contract or an order issued in terms of such a contract; or
a cidb grading designation of grade 7 or higher, in case of an engineering and construction works, or design and build contract or an order issued in terms of such a contract. Contract 2.30 The Contractor shall achieve in the performance of the contract the Contract Participation Participation Goals (CPG) relating to the engagement of targeted enterprises as Goals (CPG) established in the CIDB standard for indirect targeting for enterprise development through Construction works contracts (published in Government Gazette No. February 2013). The requirements of a contract participation goal relating to the engagement of targeted enterprises as established in the aforesaid standard applies to: (a) construction works contracts in the General Building (GB) and to Civil Engineering (CE) classes of construction works; (b) construction works contracts of an estimated minimum project duration of 6 months; and (c) construction works contracts in which at least 25% of the main contract could reasonably be expected to be subcontracted out in one or more of the following CIDB classes of construction works
Civil Engineering (CE) ii) Electrical Engineering Work (EB) iii) General Building Works (GB) iv) Mechanical Engineering (ME) 2.31 Eskom may disqualify a tender if it is found that the tenderer has misrepresented or falsified any information, certificate, affidavit or document. Eskom will report any fraud in relation to a tenderer’s B-BBEE certificate/affidavit, or evidence of ‘fronting’ as defined in the B-BBEE Act , as amended, to the B-BBEE Commission. Cataloguing 2.32 The successful tenderer may be required to provide the cataloguing information per item after contract award and will need to ensure that all materials delivered to Eskom are labelled in line with Eskom’s labelling specifications as may be stipulated by Eskom. Where cataloguing is a requirement, the Pricing Schedule must also include a line item for cataloguing, which tenderers are required to quote for. Eskom will pay for the cataloguing. Provision of 2.33 If the provision of security for performance in the form of a performance bond or a Security for demand guarantee is a requirement, the tenderer must select a minimum of two (2) Performance financial institutions that it is likely to approach from the list provided of Eskom-approved financial institutions. Public When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 9 File name: Eskom - Standard Conditions of Tender (August 2024) Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-62044728 Rev 11 Eskom Standard Identifier Conditions of Tender Effective Date 01 August 2024 Review Date August 2029 Eskom’s 3. Eskom shall comply with the following obligations: - Obligations Respond to 3.1 Respond to a request for clarification that Eskom receives before the closing date for requests for clarification or queries. Eskom’s responses will be published to all tenderers in the same clarification manner the enquiry documents were issued. It is the tenderers’ responsibility to check the Eskom Tender Bulletin and NT e-Tender Portal regularly for updated responses to clarifications. Issue Addenda 3.2 If necessary and prior to the closing date and time for tender submission, amend, amplify, or add to the Enquiry documents by way of Addenda published in the same media that the Enquiry was issued. It is the tenderers’ responsibility to check the Eskom Tender Bulletin and NT e-Tender Portal regularly for Addenda. If a tenderer applies for an extension to the closing date and time for tender submission in order to take account of the Addenda in preparing its tender, Eskom may grant such an extension and shall publish the extension. Return late tenders 3.3 Return tenders received after the closing date and time for tender submission unopened to the tenderer. Tenders will be deemed to be late if they are not received in the designated tender box or at the designated facsimile machine at the date and time stipulated as the closing date and time for tender submission Tender opening 3.4 Open the tenders in the presence of the tenderers’ representatives who choose to attend the tenders’ opening at the time and place stated in the Tender Data. Tenders for which a notice of withdrawal has been submitted will not be opened. 3.5 At tender opening, Eskom will announce the names of the tenderers. Prices may be announced if so, stated in the Tender Data. Non-disclosure 3.6 Unless required by law, Eskom will not disclose information relating to the evaluation and comparison of tenders and recommendations for the award of a contract to tenderers or to any other person not officially concerned with the tender process until after the award. Grounds for 3.7 Reject a tender if Eskom establishes that there is proof that the tenderer influenced the rejection processing of tenders or the awarding of the contract, the existence of collusion and/or bid rigging, and/or that the tenderer has participated in any fraudulent activity in connection with the enquiry. Clarification of a 3.8 Obtain clarification from a tenderer in respect of any matter in the tender that may not be tender clear or that could give rise to ambiguity in a contract arising from this tender if the matter were not to be clarified. A document that the Enquiry identifies as a mandatory tender returnable that is required to be submitted at the closing date and time for tender submission will not be requested, but Eskom may seek clarity on it. Basic Compliance 3.9 Determine before detailed evaluation, whether each tender received meets the basic compliance requirements stated in the Enquiry. A tenderer’s failure to comply with the basic compliance requirements will render the tender non-responsive. A tenderer’s failure to have submitted an original tender in paper form or to have submitted a copy of the original, also in paper form, will result in its disqualification from further evaluation. Tenderers will not be permitted to provide a copy of the original tender after the closing date and time for tender submission. Public When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 9 File name: Eskom - Standard Conditions of Tender (August 2024) Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-62044728 Rev 11 Eskom Standard Identifier Conditions of Tender Effective Date 01 August 2024 Review Date August 2029 Mandatory tender 3.10 A tender that does not contain the mandatory documents or information stipulated in the returnables Invitation to Tender by the required deadlines will be disqualified from further evaluation. Designated 3.11 A tender’s failure to meet an Enquiry’ s stipulated requirement for designated materials materials and will result in its disqualification from further evaluation. thresholds Functionality 3.12 If functionality is a criterion, tenderers will be scored against the functionality criteria and requirements will be required meet the minimum threshold stated in the Tender Data to proceed to further evaluation. Financial analysis 3.13 Eskom has to determine the risk of doing business with a supplier who may pose a (if applicable) financial risk to Eskom in the execution of the contract. During evaluation of a tenderer’s financial statements, Eskom will attempt to identify mitigating factors or requirements for the tenderer to meet, if such factors/requirements exist in the tender’s context. However, should suitable mitigating factors not exist in the tender’s context or should mitigating factors exist but be insufficient or if the risk is considered to be too high or should the tenderer not agree with the mitigating factors, the tenderer will not be considered for award. Evaluation of Price 3.14 Evaluate the Price in accordance with the criteria/requirements in the Tender Data. Factors such as CPA, FOREX, commodity increases, discounts, NPV and forecasted rates of invoicing are taken into account when determining the tendered Price. Arithmetical errors 3.15 Check responsive tenders for arithmetical errors. If there is a discrepancy between an amount in figures and the amount in words, the amount in words shall prevail. Check the highest-ranked tender for the following errors or omissions
the misplacement of the decimal point in any unit rate; or
omissions in completing the pricing schedule or bill of quantities, or
arithmetical errors in line item totals that are the result of the incorrect multiplication of a unit rate and a quantity in a bill of quantities or schedule of prices; or
arithmetical errors that are the result of the incorrect addition of the prices. Eskom will notify the tenderer of all arithmetical errors or omissions it has identified and will request the tenderer to either confirm the prices as tendered or to accept the corrected prices. Where the tenderer elects to confirm the prices as tendered; Eskom will correct the error as follows
If a bill of quantities or pricing schedule applies and there is an error in the line-item total that is the result of an error in multiplying the unit rate and the quantity, the line item total shall prevail, and the rate shall be corrected.
Where there is a misplacement of the decimal point in the unit rate, the line-item total as quoted shall prevail, and the unit rate shall be corrected.
Where there is an error in the total of the prices that is the result either of other corrections required by the checking process or in the tenderer’s addition of prices, the total of the prices shall prevail, and the tenderer shall be asked to revise the selected item prices (and their rates if a bill of quantities applies) to result in the tendered total of the prices. Public When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 9 File name: Eskom - Standard Conditions of Tender (August 2024) Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-62044728 Rev 11 Eskom Standard Identifier Conditions of Tender Effective Date 01 August 2024 Review Date August 2029 Eskom will reject the tender if the tenderer does not correct and/or does not accept the correction of errors as required above. Evaluation of 3.16 Score the Specific Goals with reference to the supporting documentation in the tender. If Specific Goals a tenderer fails to meet Specific Goals and/or to submit the required proof/supporting documentation by closing date and time of tender submission, the tenderer will not be disqualified if otherwise evaluated as acceptable in all other criteria; however, the tenderer will score zero points for Specific Goals within the 90/10 or 80/20 allocation of points. Ranking of tenders 3.17 Eskom will add the score for Pricing and Specific Goals together and rank the tenderers from the highest to the lowest. Objective criteria 3.18 A contract may be awarded to a tenderer that did not score the highest points only in accordance with Section 2(1) (f) of the Preferential Procurement Policy Framework Act,
If Eskom intends to apply Objective Criteria envisaged in section 2(1)(f), Eskom must stipulate the Objective Criteria in the Enquiry. Functionality and any element of the B-BBEE scorecard may not be used as Objective Criteria. Reverse e-Auction 3.19 Reverse e-auction is an electronic system that utilises the 90/10 and 80/20 Price and Preference point systems, and which is intended to achieve competitive pricing. Eskom may utilise reverse e-auction in certain Enquiries. Where reverse e-auction will be utilised, this will be indicated in the Enquiry and the reverse e-auction supporting documents will be issued in the Enquiry. Tenderers will be required to submit a complete tender that does not contain Prices. If a tenderer has included prices in its tender, the prices will not be considered. Acceptance of 3.20 Notify Eskom's acceptance to the successful tenderer before the expiry of the tender tender validity period. For open tenders, publish notification of award on the platforms on which the Enquiry was issued/advertised. Prepare contract 3.21 Revise the contract documents issued by Eskom in the Enquiry documents to take documents account of: Addenda issued during the tender period; inclusion of returnables stipulated in the Enquiry; inclusion of changes agreed in contract negotiations; and other revisions or documents agreed in contract negotiations. Sign Form of 3.22 Arrange for authorised signatories of both parties to complete and sign the original and Agreement one copy of the Form of Agreement. Public When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 9 File name: Eskom - Standard Conditions of Tender (August 2024) Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
B-BBEE Details: Agreement and to sign the contract documents.
Proof of authority 2.25 Where an agent submits a tender on behalf of a principal, an authenticated copy of the
to act as agent authority to act as an agent of the tenderer must be submitted as a tender returnable.
Compliance with 2.26 Comply with relevant legislation and regulatory instruments such as Instruction Notes
relevant legislation issued by National Treasury, CIDB Regulations for construction works; materials
(NT instructions, designated for local content and/or production by the dtic, PPPFA Regulations; Amended
CIDB, PPPFA etc) B-BBEE Codes, COIDA; OHS Act; Eskom’s requirements for Safety, Health, Environment and
Quality (SHEQ) and any other applicable legislation or regulatory instruments indicated in the
Invitation to Tender.
Proof of Safety, 2.27 Tenderers are required to provide proof to the satisfaction of Eskom that safety, health,
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
Environment and deadline stipulated in the Enquiry. All costs and personnel associated with SHEQ must be
Quality reflected in the tender.
requirements
CIDB 2.28 Where the Tender Data has stipulated CIDB grading/s as a qualification criterion,
tenderers are required to be registered with the Construction Industry Development
Board at the closing date and time for submission of tenders or to be capable of being
so registered within twenty-one (21) working days from the closing date and time for
submission of tenders.
Contract Skills 2.29 If the tenderer is awarded a contract, it, as Contractor, shall achieve in the performance
Development of the contract the Contract Skills Development Goals (CSDG) established in the CIDB
Public
When downloaded from the docum
Health & Safety
Source: Eskom - Standard Conditions of Tender (August 2024).pdftenderers that Eskom has identified. A sole source and a single source are regarded as a
tenderer that meets the requirements stated in the Eskom Procurement and Supply Chain
Management Procedure 32-1034. Any addenda to an issued Invitation to Tender will be
published or issued in the same way as the Invitation to Tender was and will form part of
the enquiry documents.
Communication 1.5 Every communication between Eskom and a tenderer shall be made to or from the Eskom
Representative only, in writing, and in a format that can be read, copied and recorded. ‘In
writing’ means hand-written, type-written, printed or electronically made, and that results in
a permanent record. Communication shall be in the English language. Eskom takes no
responsibility for non-receipt of communications from or by a tenderer.
Eskom's rights to 1.6 Eskom may accept or reject any variation, deviation or alternative tender. Eskom reserves
accept or reject any the right to accept the whole or any part of the tender.
tender
Proof of authority 2.25 Where an agent submits a tender on behalf of a principal, an authenticated copy of the
to act as agent authority to act as an agent of the tenderer must be submitted as a tender returnable.
Compliance with 2.26 Comply with relevant legislation and regulatory instruments such as Instruction Notes
relevant legislation issued by National Treasury, CIDB Regulations for construction works; materials
(NT instructions, designated for local content and/or production by the dtic, PPPFA Regulations; Amended
CIDB, PPPFA etc) B-BBEE Codes, COIDA; OHS Act; Eskom’s requirements for Safety, Health, Environment and
Quality (SHEQ) and any other applicable legislation or regulatory instruments indicated in the
Proof of Safety, 2.27 Tenderers are required to provide proof to the satisfaction of Eskom that safety, health,
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
so registered within twenty-one (21) working days from the closing date and time for
submission of tenders.
Contract Skills 2.29 If the tenderer is awarded a contract, it, as Contractor, shall achieve in the performance
Development of the contract the Contract Skills Development Goals (CSDG) established in the CIDB
240-62044728 Rev 11 Eskom Standard Identifier
Conditions of Tender Effective Date 01 August 2024
Review Date August 2029
Goal (CSDG) Standard for Developing Skills through Infrastructure Contract (published in GN 1779,
Government Gazette No. April 2023)
that has a duration of 12 months or more, and to:
a) a contract of R5 million or more, in the case of a professional service or service
contract or an order issued in terms of such a contract; or
b) a cidb grading designation of grade 7 or higher, in case of an engineering and
construction works, or design and build contract or an order issued in terms of such a
contract.
Contract 2.30 The Contractor shall achieve in the performance of the contract the Contract
Participation Participation Goals (CPG) relating to the engagement of targeted enterprises as
Goals (CPG) established in the CIDB standard for indirect targeting for enterprise development
through Construction works contracts (published in Government Gazette No. February 2013).
enterprises as established in the aforesaid standard applies to:
(a) construction works contracts in the General Building (GB) and to Civil Engineering
(CE) classes of construction works;
(b) construction works contracts of an estimated minimum project duration of 6 months;
and
(c) construction works contracts in which at least 25% of the main contract could
reasonably be expected to be subcontracted out in one or more of the following CIDB
classes of construction works:
i) Civil Engineering (CE)
ii) Electrical Engineering Work (EB)
iii) General Building Works (GB)
iv) Mechanical Engineering (ME)
2.31 Eskom may disqualify a tender if it is found that the tenderer has misrepresented or
falsified any information, certificate, affidavit or document. Eskom will report any
fraud in relation to a tenderer’s B-BBEE certificate/affidavit, or evidence of ‘fronting’
as defined in the B-BBEE Act , as amended, to the B-BBEE Commission.
Cataloguing 2.32 The successful tenderer may be required to provide the cataloguing information per
item after contract award and will need to ensure that all materials delivered to Eskom
are labelled in line with Eskom’s labelling specifications as may be stipulated by Eskom.
Respond to 3.1 Respond to a request for clarification that Eskom receives before the closing date for
requests for clarification or queries. Eskom’s responses will be published to all tenderers in the same
clarification manner the enquiry documents were issued. It is the tenderers’ responsibility to check
the Eskom Tender Bulletin and NT e-Tender Portal regularly for updated responses to
clarifications.
Issue Addenda 3.2 If necessary and prior to the closing date and time for tender submission, amend, amplify, or
add to the Enquiry documents by way of Addenda published in the same media that
the Enquiry was issued. It is the tenderers’ responsibility to check the Eskom Tender
in order to take account of the Addenda in preparing its tender, Eskom may grant such
an extension and shall publish the extension.
Return late tenders 3.3 Return tenders received after the closing date and time for tender submission unopened
to the tenderer. Tenders will be deemed to be late if they are not received in the
designated tender box or at the designated facsimile machine at the date and time
stipulated as the closing date and time for tender submission
Tender opening 3.4 Open the tenders in the presence of the tenderers’ representatives who choose to attend
the tenders’ opening at the time and place stated in the Tender Data. Tenders for which
a notice of withdrawal has been submitted will not be opened.
3.5 At tender opening, Eskom will announce the names of the tenderers. Prices may be
announced if so, stated in the Tender Data.
Non-disclosure 3.6 Unless required by law, Eskom will not disclose information relating to the evaluation and
comparison of tenders and recommendations for the award of a contract to tenderers or
to any other person not officially concerned with the tender process until after the award.
Grounds for 3.7 Reject a tender if Eskom establishes that there is proof that the tenderer influenced the
rejection processing of tenders or the awarding of the contract, the existence of collusion and/or
bid rigging, and/or that the tenderer has participated in any fraudulent activity in
connection with the enquiry.
Clarification of a 3.8 Obtain clarification from a tenderer in respect of any matter in the tender that may not be
tender clear or that could give rise to ambiguity in a contract arising from this tender if the matter
were not to be clarified. A document that the Enquiry identifies as a mandatory tender
returnable that is required to be submitted at the closing date and time for tender
submission will not be requested, but Eskom may seek clarity on it.
Basic Compliance 3.9 Determine before detailed evaluation, whether each tender received meets the basic
compliance requirements stated in the Enquiry. A tenderer’s failure to comply with the basic
compliance requirements will render the tender non-responsive.
A tenderer’s failure to have submitted an original tender in paper form or to have submitted a
copy of the original, also in paper form, will result in its disqualification from further evaluation.
Contractual Terms
Source: Eskom - Standard Conditions of Tender (August 2024).pdfincluding the Eskom Representative shall not be liable for any losses, claims or damages
of whatsoever nature or howsoever arising that may be sustained by a tenderer or any
other person as a result of its participation in the tender or from any amendment,
termination or suspension of the process set out in this Invitation to Tender or from its
exclusion from participating in the tender process at any point.
Eskom’s right to 1.7 Eskom reserves the right to enter into mandated negotiations with any one or more
negotiate selected tenderer(s) in accordance with Eskom’s approved procurement policies and
procedures.
240-62044728 Rev 11 Eskom Standard Identifier
Conditions of Tender Effective Date 01 August 2024
Review Date August 2029
Tender validity 2.12 Hold the tender(s) valid for acceptance by Eskom at any time within the validity period
after the closing date and time for tender submission. Extend the validity period for a
specified additional period if Eskom requests the tenderer to do so. A tenderer that
agrees to extend the validity of its tender will not be required or permitted to modify its
tender. A tenderer that does not agree to extend the validity of its tender will be
excluded from further consideration. Tenderers will be requested to extend the validity
of their tenders until a contract(s) have been concluded with one or more tenderers. A
request that a tenderer extend the validity of its tender is not a representation that the
tender is an acceptable tender or that Eskom will seek to negotiate or conclude a
contract with the tenderer. If the validity of tenders expires before contracts have been
concluded, the procurement process is deemed to have concluded without an award.
Confidentiality and 2. 13 Treat as confidential all matters that arise in connection with the procurement. Use and
copyright of copy the documents provided by Eskom only for the purpose of preparing and submitting
documents a tender in response to this Invitation to Tender.
Standardised 2.14 Obtain and familiarize themselves with, if required for the purposes of submitting a
specifications and tender, the latest revision of standardised specifications and/or other documents that have
other publications been incorporated by reference into the enquiry documents by reference.
Site visit and / or 2.15 Tenderers must attend a site visit and/or clarification meeting that is stipulated as being
clarification compulsory in order to familiarise themselves with the proposed work, services, supply,
meeting location or similar. Failure to attend a clarification meeting or site visit that is identified
as compulsory will result in disqualification from participation.
Details of the meeting(s) are stated in the Tender Data. Tenderers are entitled to ask
questions for clarity in the course of a site visit or clarification meeting.
Seek clarification 2.16 While preparing their tenders and prior to submission, tenderers are entitled to seek
clarification in respect of the enquiry documents. A request for clarification or query must be
addressed, in writing, to the Eskom Representative identified in the enquiry document. No
request or query may be addressed to any other Eskom official other than the Eskom
for cataloguing, which tenderers are required to quote for. Eskom will pay for the
cataloguing.
Provision of 2.33 If the provision of security for performance in the form of a performance bond or a
Security for demand guarantee is a requirement, the tenderer must select a minimum of two (2)
Description
Source: Annexure B.docxThe tender pertains to the supply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment spares on an 'as and when required' basis at Kriel Power Station for a period of five years. Compliance with Eskom’s OHS legal and procedural requirements is a critical component of the scope.
Evaluation Criteria
Source: Annexure B.docx (unknown)General
OHS
Technical Specifications
Source: Annexure B.docx (unknown)The tender requires compliance with Eskom's Occupational Health and Safety (OHS) legal and procedural requirements. Key points include:
Compliance Requirements
Source: Annexure B.docx (unknown)Mandatory compliance with Eskom’s OHS legal and procedural requirements, including:
Technical Specifications
Source: Scope of Work for Kriel Power Station HP Power Pack and Servo Motors Hydraulic Equipment Spares 20251015 Rev 2_1 Signed.pdf (unknown)Kriel Power Station is situated approximately 10 kilometres from the town of Kriel in Mpumalanga and access to the
station is by road.
The purpose of this scope is to briefly outline the supply, and delivery of the estimated quantities High Pressure
Hydraulic spares to Eskom Holdings SOC Limited.
General supply requirements to Kriel Power Station in-line to its application, specification, and location on which the
spares will be required. This will ensure quality and sustainable maintenance basis for all plant work required to
provide optimal plant performance at the lowest cost possibly. The original equipment manufacturers are required to
provide specifications of the hydraulic spares to be supplied on as when required basis during “Outages and
Maintenance” and must be supplied or delivered with the required documents for traceability, material certification
and data books/sheets attached.
1.1 Technical requirements applicable to the supplier/manufacturer
(Completely assembled valves and pumps)
The following documents and data are mandatory deliverables for every order:
a) A GA drawing of each component or individual valve/pump spare part will be supplied when an order is
placed.
b) This will form part of the data book. (Data books will be supplied in hard copy and electronic copy format).
c) Supply of torque values for all fasteners.
d) Stem, plug/disc, dimensions, and stem thread details indicated on the GA drawing.
e) For power driven valves the actuator mounting attachment shall be compliant to BS EN ISO 5210 or ISO
5211 (Specified on the GA drawing and valve datasheet).
f) Clearance specification between moving and stationary components. (Specified on the valve datasheet).
g) Packing type and number of packing rings specified on the GA drawing.
h) Gland packing and Gaskets specifications (Materials of constructions and dimensions). This includes
packing, seals and gasket data sheets.
i) Face to face dimensions and total weight of the component (valves, pumps and soft spares).
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
Unique Identifier: 559-656473344 Technical Strategy for Kriel Power Station HP Power Pack and
Servo Motors Hydraulic Equipment Spares. Revision: 2
Page:
1.2 Use of supplier’s design
The Purchaser is allowed to use the designs, drawings, and documents for the purpose of verifying goods
supplied and the fulfilment of PQP/ CQP/QCP.
1.3 Factory acceptance testing (fat)
Material certification shall be in accordance with the latest version of EN 10204: “Types of Inspection Documents”
for both EN and ASME materials. EN 982: “Safety requirements for hydraulic circuit components.
Impact testing of the pressure boundary components is a standard requirement for all valves supplied in
accordance with this specification.
1.4 Operating manuals and maintenance schedules
The data book of new valves will include maintenance procedures and proposed quality control procedures for
future maintenance efforts. Maintenance manuals to be submitted upon delivery of the good.
1.5 Supply requirements
a) All pumps, valves and fittings spares shall be designed and manufactured in accordance with an
internationally accepted design standard.
b) The data book of new hard spares (pumps, fittings, pipes and valves) will include maintenance procedures
and proposed quality control procedures for future maintenance efforts.
c) Data of consumables such as seals, and gaskets shall be supplied in the form of datasheets.
d) When ordering spares, valve and pumps spare parts shall be supplied with relevant material certificates
(metallic part).
e) Valves and pumps shall be supplied with protective covers on the end connections.
f) Valve and pump packaging shall be as such that inadvertent mechanical damage to components is not
possible.
1.6 Conditions on delivery
1.6.1 Valve and Pump name plate markings
As a minimum, all valves and pumps shall have a tag plate, permanently affixed, that indicates the following
information:
a) Name of Manufacturer.
b) Country of origin.
c) Year of manufacture.
d) Manufacturer Reference (Figure Number).
e) Design Pressure (MPa) as specified by the end user.
f) Design Temperature (°C) as specified by end user.
g) Design Standard (Code of construction).
h) Maximum pressure rating.
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
Unique Identifier: 559-656473344 Technical Strategy for Kriel Power Station HP Power Pack and
Servo Motors Hydraulic Equipment Spares. Revision: 2
Page:
1.6.2 Valve and Pump body markings
For valve body marking, the minimum requirements of the following standards shall be followed:
a) BS EN19: Industrial valves – Marking of Metallic Valves
b) MSS-SP-25: Standard Marking system for valves, fittings, flanges and unions
c) ISO 4409/ASMEY32.1: Hydraulic pump marking requirements.
1.7 Scope
Supply and Delivery of HP Power Pack and Servo Motors Hydraulic Equipment Spares to Kriel Power Station, on an
as and when required basis.
Below table shows the Bill of Materials of the required spares.
Note:
Dimensional data supplied in the table are approximate and the supplier must be contacted for certified dimensions.
Supply and delivery of hp power pack and servo motors hydraulic equipment spares
As and when required basis at kriel power station for the period of five years.
Material Unit Of
Item Description Quantity
Number Measure
Repair: valve: hydraulic 2 way solenoid; ng 10 mm 1 690386 ea 72
Repair: alve: hydraulic 2 way solenoid; ng 6 mm 2 690387 ea 48
Valve, solenoid: pipe size: 12 mm; style: 3 way; design rating: 0-15
Bar; connection: thd; body material: brass; medium: liquid; orifice 3 62777 ea 48
Size: 5 mm; sundrys reg; watertight enclosure
Hose assembly, non-metallic: hose size: 1/2 in; length: 950 mm;
Connection 1: coupling fbsp; connection 2: coupling fbsp; core
Material: rubber; reinforcement material: stl braided; maximum
4 56837 ea 72
Operating pressure: 4000 psi; reference NO: 900-6; high pressure;
10Mm ID; complete with 2006 fittings both ends; for sulzer high
Pressure bypass hydraulic system
Valve: type: ng10 24 v dc; valve size: 10; design rating: 315 bars;
Temperature rating: -20 to 50 deg; connection: manifold mount;
5 695816 operated: hydraulic fluid; body material: carbon steel; ea 144
Specification: rexroth; oem p/n: r901278761; reference NO: 41025066
Rod: type: piston; application: servo motor asm63; drawing NO: 85-
6 119979 ea 48
30 rev 1
Rod: type: piston; dimensions: dia 20 x lg 250 mm; material: stl;
7 22850 model NO: 85-30-18MTR asm63 ea 24
8 771738 coupling: curved jaw;38 mm; carbon steel ea 48
Solenoid: spool valve;24 v; hydraulic 9 771739 ea 100
Valve, solenoid: style: 3 way; potential: 220 vac connection:
Bolted; body material: stl; operated: no/nc; medium: liquid; orifice
10 62759 ea 100 size: 6 mm; 50hz; general purpose enclosure; boiler
Pump: type: axial piston pump; size: 18; capacity: 280 bar; speed: 1450
Rpm; rating: 280 bar; specification: rexroth; casing material: ci;
11 695806 ea 24
Application: open circuit; oem p/n: r910949268; reference NO:
41025065;
Pump: type: hydraulic power pack; drawing NO: 2965/01/02 rev 1;
12 41519 reference NO: 1p3072cpdfb; for leak off ea 36
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
Unique Identifier: 559-656473344 Technical Strategy for Kriel Power Station HP Power Pack and
Servo Motors Hydraulic Equipment Spares. Revision: 2
Page:
Accumulator: type: ball; reference NO: hc41412x; mill; vendors
Are responsible for ensuring that they are performing against
13 36801 ea 42 the correct drawing revision number (if applicable).
Cylinder assembly, actuating linear: type: hydraulic; bore
Diameter: 200 mm; stroke: 750 mm; reference NO: lz fv 200/750 d.P.P.
14 177766 rs-pez, unk; piston dia 200mm; vendors are responsible for ea 42
Ensuring that they are performing against the correct drawing
Revision number (if applicable).
Hose assembly, non-metallic: hose size: 1/4 in; length: 1.8 M;
Connection 1: coupling bsp 90 deg; connection 2: coupling bsp
15 56855 straight; connection 2 size: 1/4 in; core material: rubber; type: ea 148
Hydraulic; specification: sae100r2; size 8mm ID
Valve, check: valve size: 20 mm; connection: bolted; body material:
Stl; operated: pilot; style: 2 way; trim: stainless steel;
16 66918 softgoods: o-ring rubber; suppl p/n: CPDG-06-E-30-2080; drawing NO: ea 60
2965/01/02 rev 1; leak-off; for feed pump leak-off hydraulic power
Pack
Bush: type: guide; drawing NO: 85-30 rev 1; reference NO: 5; servo
17 22844 ea 24 motor asm63
Pump: type: piston axial; drawing NO: BS3/A03-114 rev 1; model NO:
18 54222 hykve; for sulzer oil supply unit type ov32 ea 12
Regulator, pressure: type: control valve; connection: thd; body
Material: stl; reference NO: 86/22/19; lim; valve size: 35mm; vendors
19 73465 are responsible for ensuring that they are performing against ea 24
The correct drawing revision number (if applicable).
Valve, pilot: valve style: ng16 mounting; valve size: 1 in; material:
20 761842 ductile iron; oem p/n: CPDG-06-2-50 ea 72
1.7.1 Applicability
This document is applicable to Kriel Power station.
1.8 Normative/informative references
Parties using this document shall apply the most recent edition of the documents listed in the following paragraphs.
1.8.1 Normative
240-128557196 Procurement Standard of High Pressure and High Temperature Valves in Coal Fired Stations.
1.8.2 Informative
CCI/PCB Training, Operating and Maintenance Manual for HP Bypass Valves at Kriel Power Station.
CCI/PCB hydraulic system drawing layout, drawing number 1-103.156.196.
Drawing & Component List hp bypass Kriel circuits power pack, drawing number 5041-422.
1.9 Definitions
Definition Description
Pipework Pipes and fittings are used for the conveyance of steam, water, gases or other fluids.
Valve A device for shutting off or controlling the flow of a fluid through a pipe or duct.
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
Unique Identifier: 559-656473344 Technical Strategy for Kriel Power Station HP Power Pack and
Servo Motors Hydraulic Equipment Spares. Revision: 2
Page:
This document has been seen and accepted by:
Name Designation Signature
Mthobisi Dlamini Engineer, Kriel Boiler Engineering
Abia Makgai Supervisor, Kriel Turbine Maintenance
Date Rev. Compiler Remarks
September 2025 0.1 MJ Dlamini Draft
October 2025 1 MJ Dlamini SOW finalised.
November 2025 2 MJ Dlamini & M Meso Additional of critical spare valve
The following people were involved in the development of this document:
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
Quality Management
Source: Scope of Work for Kriel Power Station HP Power Pack and Servo Motors Hydraulic Equipment Spares 20251015 Rev 2_1 Signed.pdf. Introduction ...................................................................................................................................................... 3
1.1 Technical requirements applicable to the supplier/manufacturer (completely
Assembled valves and pumps) ............................................................................................................... 3
1.2 Use of supplier’s design ........................................................................................................................ 4
1.3 Factory acceptance testing (fat) ..................................................................................................... 4
1.4 Operating manuals and maintenance schedules ........................................................................ 4
1.5 Supply requirements .............................................................................................................................. 4
1.6 Conditions on delivery ........................................................................................................................... 4
1.6.1 Valve and Pump name plate markings ..................................................................................................... 4
1.6.2 Valve and Pump body markings................................................................................................................ 5
1.7 Scope .............................................................................................................................................................. 5
1.7.1 Applicability................................................................................................................................................ 6
1.8 Normative/informative references .................................................................................................. 6
1.8.1 Normative .................................................................................................................................................. 6
1.8.2 Informative ................................................................................................................................................. 6
1.9 Definitions .................................................................................................................................................... 6
Authorisation .................................................................................................................................................... 7
Revisions .............................................................................................................................................................. 7
Development team ........................................................................................................................................... 7
Acknowledgements ........................................................................................................................................ 7
supplied and the fulfilment of PQP/ CQP/QCP.
1.3 Factory acceptance testing (fat)
Material certification shall be in accordance with the latest version of EN 10204: “Types of Inspection Documents”
for both EN and ASME materials. EN 982: “Safety requirements for hydraulic circuit components.
future maintenance efforts. Maintenance manuals to be submitted upon delivery of the good.
1.5 Supply requirements
a) All pumps, valves and fittings spares shall be designed and manufactured in accordance with an
internationally accepted design standard.
b) The data book of new hard spares (pumps, fittings, pipes and valves) will include maintenance procedures
and proposed quality control procedures for future maintenance efforts.
c) Data of consumables such as seals, and gaskets shall be supplied in the form of datasheets.
d) When ordering spares, valve and pumps spare parts shall be supplied with relevant material certificates
(metallic part).
e) Valves and pumps shall be supplied with protective covers on the end connections.
f) Valve and pump packaging shall be as such that inadvertent mechanical damage to components is not
possible.
1.6 Conditions on delivery
1.6.1 Valve and Pump name plate markings
Pricing Schedule
Source: Scope of Work for Kriel Power Station HP Power Pack and Servo Motors Hydraulic Equipment Spares 20251015 Rev 2_1 Signed.pdf (unknown)Below table shows the Bill of Materials of the required spares. Note: Dimensional data supplied in the table are approximate and the supplier must be contacted for certified dimensions. SUPPLY AND DELIVERY OF HP POWER PACK AND SERVO MOTORS HYDRAULIC EQUIPMENT SPARES AS AND WHEN REQUIRED BASIS AT KRIEL POWER STATION FOR THE PERIOD OF FIVE YEARS. Material Unit Of Item Description Quantity Number Measure REPAIR: VALVE: HYDRAULIC 2 WAY SOLENOID; NG 10 MM 1 690386 EA 72 REPAIR: ALVE: HYDRAULIC 2 WAY SOLENOID; NG 6 MM 2 690387 EA 48 VALVE, SOLENOID: PIPE SIZE: 12 MM; STYLE: 3 WAY; DESIGN RATING: 0-15 BAR; CONNECTION: THD; BODY MATERIAL: BRASS; MEDIUM: LIQUID; ORIFICE SIZE: 5 MM; SUNDRYS REG; WATERTIGHT ENCLOSURE HOSE ASSEMBLY, NON-METALLIC: HOSE SIZE: 1/2 IN; LENGTH: 950 MM; CONNECTION 1: COUPLING FBSP; CONNECTION 2: COUPLING FBSP; CORE MATERIAL: RUBBER; REINFORCEMENT MATERIAL: STL BRAIDED; MAXIMUM OPERATING PRESSURE: 4000 PSI; REFERENCE NO: 900-6; HIGH PRESSURE; 10MM ID; COMPLETE WITH 2006 FITTINGS BOTH ENDS; FOR SULZER HIGH PRESSURE BYPASS HYDRAULIC SYSTEM VALVE: TYPE: NG10 24 V DC; VALVE SIZE: 10; DESIGN RATING: 315 BARS; TEMPERATURE RATING: -20 TO 50 DEG; CONNECTION: MANIFOLD MOUNT; OPERATED: HYDRAULIC FLUID; BODY MATERIAL: CARBON STEEL; EA 144 SPECIFICATION: REXROTH; OEM P/N: R901278761; REFERENCE NO: 41025066 ROD: TYPE: PISTON; APPLICATION: SERVO MOTOR ASM63; DRAWING NO: 85- 30 REV 1 ROD: TYPE: PISTON; DIMENSIONS: DIA 20 X LG 250 MM; MATERIAL: STL; MODEL NO: 85-30-18MTR ASM63 EA 24 COUPLING: CURVED JAW;38 MM; CARBON STEEL EA 48 SOLENOID: SPOOL VALVE;24 V; HYDRAULIC EA 100 VALVE, SOLENOID: STYLE: 3 WAY; POTENTIAL: 220 VAC CONNECTION: BOLTED; BODY MATERIAL: STL; OPERATED: NO/NC; MEDIUM: LIQUID; ORIFICE SIZE: 6 MM; 50HZ; GENERAL PURPOSE ENCLOSURE; BOILER PUMP: TYPE: AXIAL PISTON PUMP; SIZE: 18; CAPACITY: 280 BAR; SPEED: 1450 RPM; RATING: 280 BAR; SPECIFICATION: REXROTH; CASING MATERIAL: CI; APPLICATION: OPEN CIRCUIT; OEM P/N: R910949268; REFERENCE NO: 41025065; PUMP: TYPE: HYDRAULIC POWER PACK; DRAWING NO: 2965/01/02 REV 1; REFERENCE NO: 1P3072CPDFB; FOR LEAK OFF EA 36 ACCUMULATOR: TYPE: BALL; REFERENCE NO: HC41412X; MILL; VENDORS ARE RESPONSIBLE FOR ENSURING THAT THEY ARE PERFORMING AGAINST THE CORRECT DRAWING REVISION NUMBER (IF APPLICABLE). CYLINDER ASSEMBLY, ACTUATING LINEAR: TYPE: HYDRAULIC; BORE DIAMETER: 200 MM; STROKE: 750 MM; REFERENCE NO: LZ FV 200/750 D.P.P. RS-PEZ, UNK; PISTON DIA 200MM; VENDORS ARE RESPONSIBLE FOR ENSURING THAT THEY ARE PERFORMING AGAINST THE CORRECT DRAWING REVISION NUMBER (IF APPLICABLE). HOSE ASSEMBLY, NON-METALLIC: HOSE SIZE: 1/4 IN; LENGTH: 1.8 M; CONNECTION 1: COUPLING BSP 90 DEG; CONNECTION 2: COUPLING BSP STRAIGHT; CONNECTION 2 SIZE: 1/4 IN; CORE MATERIAL: RUBBER; TYPE: HYDRAULIC; SPECIFICATION: SAE100R2; SIZE 8MM ID VALVE, CHECK: VALVE SIZE: 20 MM; CONNECTION: BOLTED; BODY MATERIAL: STL; OPERATED: PILOT; STYLE: 2 WAY; TRIM: STAINLESS STEEL; SOFTGOODS: O-RING RUBBER; SUPPL P/N: CPDG-06-E-30-2080; DRAWING NO: 2965/01/02 REV 1; LEAK-OFF; FOR FEED PUMP LEAK-OFF HYDRAULIC POWER PACK BUSH: TYPE: GUIDE; DRAWING NO: 85-30 REV 1; REFERENCE NO: 5; SERVO MOTOR ASM63 PUMP: TYPE: PISTON AXIAL; DRAWING NO: BS3/A03-114 REV 1; MODEL NO: HYKVE; FOR SULZER OIL SUPPLY UNIT TYPE OV32 EA 12 REGULATOR, PRESSURE: TYPE: CONTROL VALVE; CONNECTION: THD; BODY MATERIAL: STL; REFERENCE NO: 86/22/19; LIM; VALVE SIZE: 35MM; VENDORS ARE RESPONSIBLE FOR ENSURING THAT THEY ARE PERFORMING AGAINST THE CORRECT DRAWING REVISION NUMBER (IF APPLICABLE). VALVE, PILOT: VALVE STYLE: NG16 MOUNTING; VALVE SIZE: 1 IN; MATERIAL: DUCTILE IRON; OEM P/N: CPDG-06-2-50 EA 72
Compliance Requirements
Source: Scope of Work for Kriel Power Station HP Power Pack and Servo Motors Hydraulic Equipment Spares 20251015 Rev 2_1 Signed.pdf (unknown)No specific requirements found
Important Dates
Source: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025.pdf (RFP){"closingDate":"07 July 2026","closingTime":"10h00","briefingSession":"{"date":"15 July 2026","time":"10:00","venue":"ion A non-compulsory clarification meeting/site visit with","is_compulsory":true}"}
Contact Information
Source: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025.pdf (RFP){"name":null,"email":"[email protected]","phone":"017 615 2642","department":null,"address":"ion meeting"}
Evaluation Criteria
Source: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025.pdf (RFP)1.1.9 *SBD 6.1 Preference Points Claim Form in terms of Annexure I Y
PPPFA 2022 regulations
1.1.11 Tax Evaluation questionnaire to determine whether a N/A
3.13 Functionality requirements Functionality requirements are applicable
functionality criteria: (Refer to the Technical Evaluation Criteria)
Tenderers who do not meet the threshold for functionality scoring will
3.15 Evaluation of Price Prices will be evaluated as follows
evaluation parameters relating to uncertainty and risk, where
evaluation purposes but will be implemented when payment is
Prices will be scored out of 80 or 90 points
3.18 Evaluation of Specific Goals Specific goals will be scored out of 20 or 10 points in accordance with
the PPPFA.
If a tenderer fails to submit evidence of its points claim for a Specific
Goal, it will not be disqualified. However, it will be awarded 0 points
the [90/10 or 80/20] system. Eskom will add the score from Pricing
and Specific Goals together and rank the suppliers from the highest
Contractual Requirements are not evaluation criteria. They will
be assessed after the evaluation and ranking of the tenders.
Section 1: Specific Goals
A maximum of 10/20 points may be awarded to a tenderer for the specific goal specified for the
tender. The points scored for the specific goal must be added to the points scored for price and the
scoring the highest points.
Number of points Number of points
(90/10 system) (80/20 system)
Methodology
Source: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025.pdfBursary to learners at the 1st or 2nd year National Diploma
university of technology
Note: That these targets for skills development candidates categorically exclude Eskom
employees and registered learners. The tenderers are required to take full responsibility for the
total cost of developing the requisite skills, and Eskom shall not make any financial contribution
towards the fulfilment of this obligation. Tenderers also are advised to approach their relevant
Quality Management
Source: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025.pdfEffective Date 30 October 2025
Review Date October 2030
Returnable: Examples of completed QCP 3. QCP and procedures 30
and supporting work instruction (procedure)
used for testing hydraulic components
(pumps, hoses and Valves (PRV)) to the
required ratings.
instruction correct.
instruction satisfactory
instruction is not
correct/unacceptable/ Not submitted
supply the lead times as per the spares
detailed in scope of work.
100% (5): Lead time ≤ 16 weeks
80% (4): Lead time > 16 weeks & ≤ 32
weeks
40% (2): Lead time > 32 weeks
0% (0): No lead time given
NB: The tenderer must complete and sign this form to acknowledge and accept Eskom Supplier
Quality Requirements as per QM 58, 557-4497 Specification and ISO 9001 Standard.
Unique Identifier 240-12248652
Supplier Quality Management: Revision 7
List of Tender Returnables Documents Effective Date 2022/01/26
Specification 240-105658000
Category 3 : Quality Requirements Deliverables to be evaluated indicator = 1
SECTION A : Quality Management System Requirements ISO 9001
Objective evidence of documented QMS that is not certified but complies with ISO 9001
Apply =1
A.1 QMS Manual or a document that defines and describes the QMS and its scope 1
A.2 Quality Policy Approved by top management. 1
A.3 Quality Objectives Approved by top management. 1
A.4 Control of documented information (i.e. document and record control)
Clause 7.5 of ISO 9001:2015
A.5 Documented information for Control of nonconforming outputs
Clause 8.7 of ISO 9001:2015
A.6 Documented information for Nonconformity and Corrective action
Clause 10.2 of ISO 9001:2015
A.7 Documented information for Internal audit
Clause 9.2 of ISO 9001:2015
Section A Score Option 2 7
SECTION B : Evidence of QMS in operation (Tender Quality Requirements -Ref 240-105658000)
Apply =1
B.1 Documented information for defined roles, responsibilities and authorities - Organization chart and Responsibility matrix (must include
but not limited to quality management function/role) 1
(Clause 5.3 of ISO 9001:2015)
B.2 Documented information for Control of Externally Provided Processes, Products and Services - Must include criteria for evaluation,
selection, monitoring of performance, and re-evaluation of external providers (Clause 8.4 of ISO 9001:2015)
Section B Score 2
SECTION C: Contract Quality Plan Requirements (Ref 240-105658000 and 240-109253698).
Draft Contract Quality Plan specific to the scope of work as described in the tender documents (Ref ISO 10005)
Apply (Yes=1)
NB! Draft Contract/Project Quality Plan has important QA deliverables 1
Section C Score 1
SECTION D: Quality Control Plan Requirements (Ref 240-105658000 or 240-109253302)
QCP /Checklist/ ITP (Quality Control Plans) as per Scope of Works (Ref ISO 10005)
Apply = 1
NB! Draft/ Example of an Inspection and Test Plan (ITP) or Quality Control Plan (QCP) on similar and/ or previous work done 1
Section D Score 1
SECTION E: User defined additional Requirements & miscellaneous (Ref 240-105658000)
Pricing Schedule
Source: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025.pdfEffective Date 30 October 2025
Review Date October 2030
Number Description Annexure Attached (Y /
N / n/a)
1.1.12 Reverse e-auction training acknowledgement form (if N/A
applicable)
1.1.13 Reverse e-auction process (if applicable) N/A
1.1.14 E-tendering Help Manual acknowledgement form Attached Y
1.1.15 E-tendering Help Manual for supplier Attached Y
1.1.16 CIDB Contract Skills Development Goals (CSDG) N/A
(if applicable)
1.1.17 Contract Participation Goals (CPG) N/A
(if applicable)
1.1.18 Scope of Work Attached Y
1.1.19 NEC or other Contract Attached Y
1.1.20 Pricing Schedule/BOQ (if not contained in Contract) Attached Y
option clauses, acceptable to Eskom as the Employer, selected
from the NEC Engineering and Construction Contract.
2.33 Cataloguing The successful tenderer may be required to provide the cataloguing
information per item after contract award and will need to ensure that
all materials delivered to Eskom are labelled in line with Eskom’s
labelling specifications as may be stipulated by Eskom. Where
cataloguing is a requirement, the Pricing Schedule must also include
a line item for cataloguing, which tenderers are required to quote for.
Goal, it will not be disqualified. However, it will be awarded 0 points
for that Specific Goal. [Refer to the SDL&I Requirements]
3.19 Ranking of tenders Tenderers will be ranked by applying the preferential point scoring for
the [90/10 or 80/20] system. Eskom will add the score from Pricing
and Specific Goals together and rank the suppliers from the highest
to the lowest.
Effective Date 30 October 2025
Review Date October 2030
Reference Returnable From Suppliers at at **
closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable)
to Tender Returnable Returnable Returnable
Pricing schedule Completed pricing schedule (if not already submitted √
in the NEC or other Contract).
“Local Procurement Content” refers to value added in South Africa by South African resources. Where
a single contract involves a combination of local and imported goods and/or services, the tender
response must be separated into its components as per the Price Schedule included with the tender
documents. Local procurement content is total spending minus the imported component.
Financial Requirements
Source: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025.pdf (RFP)Payment Terms: payment terms as stipulated hereunder when
submitting tenders and concluding contracts with Eskom:
For contracts valued below R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed to paying
Suppliers within 30 days of receipt of undisputed invoices.
For contracts valued above R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed
Compliance Requirements
Source: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025.pdf (RFP)ADDITIONAL CONTRACTUAL REQUIREMENTS SUPPORTING EVIDENCE Safety COIDA - Original certificate of good standing or √ proof of application issued by the Compensation Fund (COID) or a licensed compensation insurer (South African tenderers only) Quality Documents that may be required as per scope of √ work Other safety/quality Documents that may be required as per scope of √ documents as work Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 72 File name: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 27 Identifier Invitation to Tender Effective Date 30 October 2025 Review Date October 2030 Reference Returnable From Suppliers at at ** closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable) to Tender Returnable Returnable Returnable required per scope of works Environmental Documents that may be required as per scope of √ work Due
A signed copy of the public interest score (only applicable to South African entities that are not audited) o Giving the actual score o Indicating whether the company is owner managed or not o Confirming whether the annual financial statements were externally prepared or not.
Copies of the ITA34C for the current & previous years of assessment (only applicable to South African entities that are not audited) Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 72 File name: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 27 Identifier Invitation to Tender Effective Date 30 October 2025 Review Date October 2030 Reference Returnable From Suppliers at at ** closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable) to Tender Returnable Returnable Returnable
For unincorporated JV or a SPV, each partner in the JV or a SPV must submit its annual financial statements including all items listed above.
Risk Assessment DOCUMENTS REQUIRED UNDER FUNCTIONALITY/TECHINICAL CRITERIA Functionality/Technical Tenderer to submit both mandatory and quantitative √ technical requirements applicable for this tender. (Please refer to the technical evaluation criteria) Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 72 File name: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 27 Identifier Invitation to Tender Effective Date 30 October 2025 Review Date October 2030 TECHNICAL EVALUATION CRITERIA 1.1 MANDATORY TECHNICAL EVALUATION CRITERIA In the table below is a guide on how to score each technical tender returnable. This guide is obtained for the Tender Engineering Evaluation Procedure. There is no mandatory criterion for this contract. Contractors must obtain a minimum of 70% to qualify for further evaluation Table 1: Mandatory Technical Evaluation Criteria Mandatory Technical Reference to Technical Specification / Motivation for use of Criteria Criteria Description Tender Returnable None Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 72 File name: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 27 Identifier Invitation to Tender Effective Date 30 October 2025 Review Date October 2030 1.2. Qualitative Technical Evaluation Criteria Table 2: Qualitative Technical Evaluation Criteria for Part 1 Qualitative Technical Criteria Description Reference to Technical Specification / Criteria Criteria Sub Tender Returnable Weighting Weighting (%) (%) Verifiable reference that the Manufacture/Supplier has successfully 1. Returnable: Provide a list contract/purchase 30 supplied similar equipment to Power Stations/ similar industries in order of similar hydraulic equipment the last 10 years. completed by the company/supplier within the last 10 years. References shall include the customer’s name, customer reference person with contact details, project scope and order number.
100% (5) List with 3 or more purchase orders in the last 10 years
80% (4) List with 2 purchase orders in the last 10 years
40% (2) List with 1 purchase order in the last 10 years 0% (0): No list Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 72 File name: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 27 Identifier Invitation to Tender Effective Date 30 October 2025 Review Date October 2030
Hydraulic equipment technical specification Returnable: Provide technical specifications 30 of hydraulic equipment to be used for calibration of PRV’s in the scope of work by manufacturer/supplier.
100% (5) Technical specification submitted acceptable.
0% (0): Technical specification submitted not acceptable/ Not submitted Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 72 File name: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 27 Identifier Invitation to Tender Effective Date 30 October 2025 Review Date October 2030 Returnable: Examples of completed QCP 3. QCP and procedures 30 and supporting work instruction (procedure) used for testing hydraulic components (pumps, hoses and Valves (PRV)) to the required ratings. Client must have signed up for approval of QCP.
100% (5): Submitted QCP and work instruction correct.
80% (4): Submitted QCP and work instruction satisfactory
0% (0): Submitted QCP and work instruction is not correct/unacceptable/ Not submitted
Lead times Returnable: Supplier/Manufacturer to 10 supply the lead times as per the spares detailed in scope of work.
100% (5): Lead time ≤ 16 weeks
80% (4): Lead time > 16 weeks & ≤ 32 weeks
40% (2): Lead time > 32 weeks
0% (0): No lead time given Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 72 File name: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 27 Identifier Invitation to Tender Effective Date 30 October 2025 Review Date October 2030 SDL&I Requirements Section 1: Specific Goals A maximum of 10/20 points may be awarded to a tenderer for the specific goal specified for the tender. The points scored for the specific goal must be added to the points scored for price and the total must be rounded off to the nearest two decimal places. Subject to section 2(1)(f) of the Preferential Procurement Policy Framework Act, the contract must be awarded to the tenderer scoring the highest points. Number of points Number of points B-BBEE Status Level of Contributor (90/10 system) (80/20 system) 1 10 20 2 9 18 3 6 14 4 5 12 5 4 8 6 3 6 7 2 4 8 1 2 Non-compliant contributor 0 0 NB: The following documents are required to claim preference points,
Valid B-BBEE certificate issued by a SANAS accredited verification agency / sworn affidavit / CIPS affidavit
Proof of ownership / shareholding (preferably CIPC documentation) inclusive of shareholding breakdown
Certified ID copies of shareholder(s)
Proof of Disability (where applicable)
In a case of a trust, consortium or joint venture (including incorporated consortia and joint ventures), a consolidated B-BBEE status level verification certificate. Tenderer failing to provide documentation for the allocation of preference points will not be disqualified, but’
May only score point out of 90/80 for price
Scores 0 points out of 10/20 for specific goals Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 72 File name: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 27 Identifier Invitation to Tender Effective Date 30 October 2025 Review Date October 2030 Section 2: Objective criteria The inclusion of objective criteria is not mandatory but a condition for contract award. If the tenderer does not meet objective criteria; it may lead to the second-ranked tenderer being recommended for award. 2.1 Designated Sectors When applicable the following stipulated minimum threshold for Local Production and Content must be achieved in full by the tenderer YES NO
Is this Commodity or part of it a Designated ☐ Sector? Please indicate below Designated Components Commodity Components Local Content Threshold Valves and Actuators Valves 70% MV Motors and Pumps Pumps 70% Steel Products Various Steel Products 100% NOTE: SBD 6.2 Declaration Form and Annex C (Local Content Declaration-Summary Schedule) are tender returnable if applicable. Section 3: SDL&I Objectives in line with Reconstruction and Development Programme (RDP) Goals Tenderers who complete and submit the objectives as required, but who do not meet Eskom’s targets, will not be disqualified. SDL&I objectives do not form part of scoring but commitments will form part of contractual obligations
Transformation – BBBEE Improvement or Retention Plan Transformation remains an area of focus, where Eskom continuously strives to align itself with national transformation imperatives to unlock growth, drive industrialization, create employment and contribute to skills development. Eskom encourages its suppliers to constantly strive to improve their B-BBEE rating. Whereas Tenderer/s will be allocated points in terms of a preference point system based on specific goals, Eskom also requests that tenderer/s submits their B-BBEE improvement or retention plan within 30 days of signing the contract. Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 72 File name: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 27 Identifier Invitation to Tender Effective Date 30 October 2025 Review Date October 2030 Tenderer/s are therefore requested to indicate the extent to which they will maintain (only if the respondent is a Level 1) or may improve/maintain their B-BBEE status over the contract period if their B-BBEE status is level 2 or 3. Tenderer/s with a B-BBEE status level 4 at the time of contract award, shall migrate and achieve as a non-negotiable a milestone of B-BBEE Level 3 by the end of the first year of the contract and thereafter improve their B-BBEE status level or migrate by one level higher. Tenderer/s with a B-BBEE recognition status of Level 5 to Level 8 or non-compliant at the time of contract award, shall migrate and achieve as a non-negotiable a milestone of Level 4 by the end of the first year of the contract and thereafter improve at least one B-BBEE Level higher of each year from the second year of the contract. Tenderer/s are requested to submit their B-BBEE Improvement Plan as an essential document within 30 days of signing the contract. NB: A valid B-BBEE certificate or Sworn Affidavit is a condition for contract award, if your company’s annual Total Revenue is R10 Million or less you qualify as an Exempted Micro Enterprise therefore you can submit Sworn Affidavit. If your annual Total Revenue is R50 Million or less, you qualify as Qualifying Small Enterprise and must comply with all of the elements of QSE score card relevant to your sector unless an entity is at least 51% Black owned you are required to obtain a Sworn affidavit. If your Annual Total Revenue is above R50m you need to submit a Valid B-BBEE certificate.
Local Procurement Content “Local Procurement Content” refers to value added in South Africa by South African resources. Where a single contract involves a combination of local and imported goods and/or services, the tender response must be separated into its components as per the Price Schedule included with the tender documents. Local procurement content is total spending minus the imported component. Tenderers are required to submit their proposals in the table below. Local Procurement Eskom target Tenderer Proposal Content 100%
Jobs. Tenderers are required to submit proposals for the type and number of jobs that will be created and retained in South Africa as a direct result of being awarded a contract. Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 72 File name: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 27 Identifier Invitation to Tender Effective Date 30 October 2025 Review Date October 2030 Type of Jobs to be created Number of Jobs to be created Type of Jobs to be retained Number of Jobs to be retained
B-BBEE Minimum Level: 0
Points Allocation: 10 points
B-BBEE Details: es the right to negotiate with preferred bidders after a competitive bidding process or price
quotations should the tendered prices not be market-related.
Main contractors/ suppliers are discouraged from subcontracting with their subsidiary companies as this
may be interpreted as subcontracting with themselves and / or using their subsidiaries for fronting.
Where a main contractor subcontracts with a subsidiary, this must be declared in its tender documents.
A report containing a list of potential sub-contractors may be drawn by accessing the following link:
“proof of B-BBEE status level of contributor” means-
(a) the B-BBEE status level certificate issued by an authorised body or person; or
(b) a sworn affidavit as prescribed by the B-BBEE Codes of Good Practice; or
(c) any other requirement prescribed in terms of the Broad-Based Black Economic Empowerment Act
1.3 Tender returnables
The tenderer must submit the returnable set out hereunder as part of its tender at the stipulated deadline.
Note the following: -
These returnables are required to be fully completed, signed (if required on the returnable) and submitted
with the tender at Tender closing date and time. If not fully completed, signed (if required on the
returnable) and/or submitted by tender closing, the tenderer will be disqualified.
** Returnable required at Tender closing (non-disqualifiable): -
These returnables are required to be fully completed, signed (if required on the returnable) and submitted
with Tender at Tender closing date and time; however, if not submitted by Tender closing, or submitted
with incomplete information or without a required signature, the Procurement Practitioner will, in wr
Health & Safety
Source: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025.pdfSafety health criteria
at at
Award. (Non-
** required required required Reference Returnable From Suppliers closing closing. Contract
to Returnable Tender (disqualifiable)* Returnable Tender disqualifiable) Returnable prior
Safety Evaluation Criteria
Annexure B Is the acknowledgement of Eskom's SHE rules ✓
and requirements form (Annexure B) signed and
submitted by the tenderer?
Occupational
Health and Responsibility & Accountability
Safety Plan
must
address the
scope of
work OHS
risk(s) and
aligned with
the health
and safety
applicable:
2.30 Contract Participation Goals is [Please note:
[not applicable] Contractor shall achieve in the performance of the contract
the Contract Participation Goals (CPG) relating to the
engagement of targeted enterprises as established in the
development through Construction Works Contract (published
in Government Gazette No. February 2013)
the engagement of targeted enterprises as established in the
aforesaid standard applies to:
a) construction works contracts in the General Building (GB)
and to Civil Engineering (CE) classes of construction
works;
b) construction works contracts of an estimated minimum
project duration of 6 months; and
c) construction works contracts in which at least 25% of the
main contract could reasonably be expected to be sub-
contracted out in one or more of the following CIDB
classes of construction works:
Safety COIDA - Original certificate of good standing or √
proof of application issued by the Compensation
Fund (COID) or a licensed compensation insurer
(South African tenderers only)
Quality Documents that may be required as per scope of √
work
Other safety/quality Documents that may be required as per scope of √
documents as work
Effective Date 30 October 2025
Review Date October 2030
Reference Returnable From Suppliers at at **
closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable)
to Tender Returnable Returnable Returnable
the JV or a SPV must submit its annual financial
statements including all items listed above.
their validity:
authorised to depose of an affidavit. (Mark the applicable option).
address.
Statement 004, the percentage of black beneficiaries must be reflected. (No blank spaces to be left).
account. (Mark the applicable option).
(Financial year end to be stipulated by day/month/year).
status.
Effective Date 30 October 2025
Review Date October 2030
presence of the Commissioner of Oath. Furthermore the Commissioner must also sign and stamp)
sworn affidavit in which they have an interest.
Safety Requirements
Annexure B Is the acknowledgement of Eskom's SHE rules ✓
and requirements form (Annexure B) signed and
submitted by the tenderer?
Occupational
Safety Plan
must
address the
scope of
work OHS
risk(s) and
aligned with
the health
and safety
specification
or
requirements
Baseline Identification, assessment and management of ✓
Environmental
Source: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025.pdfDESCRIPTION OF PROCUREMENT / DISPOSAL: Supply and Delivery of HP Power Required Not Required
Pack and Servo Motors Hydraulic Equipment Spares “As and When
required basis” at Kriel Power Station for the period of five years
The contractor must submit an Environmental Policy and proof of communicating it with
the employees (project team). The policy should demonstrate your organization (top Required
management)’s commitment to protection of the environment which is not only intended
to prevent adverse environmental impacts through prevention of pollution, but to protect
the natural environment from harm and degradation arising from the organisation’s
activities, products and services. The policy must also
demonstrate commitment to compliance with legal and other requirements, prevent
pollution and continually improve environmental performance.
Environmental Aspects and Impacts Register Not required
The contractor shall determine the aspects related to the scope of work. Aspect is an
element of organization’s activity, products or services which may interact with the
environment and may cause negative or positive impact. While impact – refers to any
change on the environment whether adverse or beneficiary. Changes to the
environment, either adverse or beneficial, that result wholly or partially from
environmental aspects are called environmental impacts. The environmental impact can
occur at local, regional and global scales, and also can be direct, indirect or cumulative
by nature. The relationship between environmental aspects and environmental impacts
is one of cause and effect.
DESCRIPTION OF PROCUREMENT / DISPOSAL: Required Not
Required
Environmental Management Plan Not
The contractor must develop environmental management plan that demonstrate Required
how activities which have potential to cause environmental impacts will be
management during the lifespan of a project.
Convey Dangerous Goods by Road certificate Not
The Driver competence certificate for convey or handling of dangerous goods Required
Waste Transporter Certificate Not
The Contractor must submit waste transporter certificate Required
Waste Management License Not
The Contractor must Submit the facility Waste Management License for Required
recycling
Environmental Policy; Environmental Aspects and Impacts Register & EMP Required
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 72
File name: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 27
Identifier
Invitation to Tender
Effective Date 30 October 2025
Review Date October 2030
Quality Requirements
NB: The tenderer must complete and sign this form to acknowledge and accept Eskom Supplier
Quality Requirements as per QM 58, 557-4497 Specification and ISO 9001 Standard.
Unique Identifier 240-12248652
Supplier Quality Management: Revision 7
List of Tender Returnables Documents Effective Date 2022/01/26
Specification 240-105658000
Category 3 : Quality Requirements Deliverables to be evaluated indicator = 1
SECTION A : Quality Management System Requirements ISO 9001
Objective evidence of documented QMS that is not certified but complies with ISO 9001
Apply =1
A.1 QMS Manual or a document that defines and describes the QMS and its scope 1
A.2 Quality Policy Approved by top management. 1
A.3 Quality Objectives Approved by top management. 1
A.4 Control of documented information (i.e. document and record control)
Clause 7.5 of ISO 9001:2015
A.5 Documented information for Control of nonconforming outputs
Clause 8.7 of ISO 9001:2015
A.6 Documented information for Nonconformity and Corrective action
Clause 10.2 of ISO 9001:2015
A.7 Documented information for Internal audit
Clause 9.2 of ISO 9001:2015
Section A Score Option 2 7
SECTION B : Evidence of QMS in operation (Tender Quality Requirements -Ref 240-105658000)
Apply =1
B.1 Documented information for defined roles, responsibilities and authorities - Organization chart and Responsibility matrix (must include
but not limited to quality management function/role) 1
(Clause 5.3 of ISO 9001:2015)
B.2 Documented information for Control of Externally Provided Processes, Products and Services - Must include criteria for evaluation,
selection, monitoring of performance, and re-evaluation of external providers (Clause 8.4 of ISO 9001:2015)
Section B Score 2
SECTION C: Contract Quality Plan Requirements (Ref 240-105658000 and 240-109253698).
Draft Contract Quality Plan specific to the scope of work as described in the tender documents (Ref ISO 10005)
Apply (Yes=1)
NB! Draft Contract/Project Quality Plan has important QA deliverables 1
Section C Score 1
SECTION D: Quality Control Plan Requirements (Ref 240-105658000 or 240-109253302)
QCP /Checklist/ ITP (Quality Control Plans) as per Scope of Works (Ref ISO 10005)
Apply = 1
NB! Draft/ Example of an Inspection and Test Plan (ITP) or Quality Control Plan (QCP) on similar and/ or previous work done 1
Section D Score 1
SECTION E: User defined additional Requirements & miscellaneous (Ref 240-105658000)
Customer specific requirements & other standards and required can be listed and evaluated here
Apply (Yes=1)
E.1 Form A is completed and signed. 1
Section E Score 1
NAME OF ESKOM REPPRESENTATIVE Zama Sabela
DATE ISSUED 10-Apr-26
PROJECT: TENDER TITLE Supply and Delivery of HP Power Pack and Servo Motors Hydraulic Equipment Spares
Effective Date 30 October 2025
Review Date October 2030
Reference Returnable From Suppliers at at **
closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable)
to Tender Returnable Returnable Returnable
required per scope
of works
Environmental Documents that may be required as per scope of √
work
Due
Effective Date 30 October 2025
Review Date October 2030
Environmental Requirements
DESCRIPTION OF PROCUREMENT / DISPOSAL: Supply and Delivery of HP Power Required Not Required
Pack and Servo Motors Hydraulic Equipment Spares “As and When
required basis” at Kriel Power Station for the period of five years
Environmental Policy
the employees (project team). The policy should demonstrate your organization (top Required
management)’s commitment to protection of the environment which is not only intended
to prevent adverse environmental impacts through prevention of pollution, but to protect
the natural environment from harm and degradation arising from the organisation’s
activities, products and services. The policy must also
demonstrate commitment to compliance with legal and other requirements, prevent
pollution and continually improve environmental performance.
element of organization’s activity, products or services which may interact with the
environment and may cause negative or positive impact. While impact – refers to any
change on the environment whether adverse or beneficiary. Changes to the
environment, either adverse or beneficial, that result wholly or partially from
environmental aspects are called environmental impacts. The environmental impact can
occur at local, regional and global scales, and also can be direct, indirect or cumulative
by nature. The relationship between environmental aspects and environmental impacts
is one of cause and effect.
DESCRIPTION OF PROCUREMENT / DISPOSAL: Required Not
how activities which have potential to cause environmental impacts will be
management during the lifespan of a project.
recycling
Environmental Policy; Environmental Aspects and Impacts Register & EMP Required
Contractual Terms
Source: Invitation to Tender (ITT) HP Power Pack Rev. 27 - 30 October 2025.pdfsanctions list. A tenderer shall be found to have the nationality
of a country if the tenderer is a national or is constituted,
incorporated, or registered and operates in conformity with the
provisions of the laws of that country. This criterion shall also
apply to the determination of the nationality of proposed
subcontractors or suppliers for any part of the Contract including
related services.
individually or as a partner in a joint venture (JV) or consortium,
except on an E-Tendering system where there is a limit size
performance bond or a demand guarantee is a requirement, the
tenderer must select a minimum of two (2) financial institutions that it
is likely to approach from the list provided of Eskom-approved
financial institutions.
3.4 Tender Opening For E-tendering. There will be no public opening of tenders. Tenders
will be downloaded electronically.
3.5 Tender Prices Prices will not be read out.
3.9 Basic Compliance Basic compliance with this Invitation to Tender requires a tenderer to
meet all the following requirements:
submitting tenders and concluding contracts with Eskom:
For contracts valued below R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed to paying
Suppliers within 30 days of receipt of undisputed invoices.
For contracts valued above R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed to paying
suppliers within 60 days of receipt of undisputed invoices.
Description
Source: E-tendering Help Manual for supplier - 27 January 2025.docxThe tender involves the supply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment spares on an 'as and when required' basis to Kriel Power Station for a period of five years. Submission is managed via Eskom's eTendering system, a web-based platform for electronic document uploads, replacing physical submissions.
Contact Information
Source: E-tendering Help Manual for supplier - 27 January 2025.docx (unknown)For system-related issues with Tender Bulletin, eTendering, or OpenText: Contact the buyer responsible for the published tender. No direct contact details provided in the document.
Submission Guidelines
Source: E-tendering Help Manual for supplier - 27 January 2025.docx (unknown)Submit all tender documents electronically via the eTendering system (https://eTendering.eskom.co.za). Steps: 1) Register on the eTendering portal with a valid CSD number. 2) Verify your email and receive an OTP via email and SMS. 3) Log in, select the tender reference number, and click 'Create New Submission'. 4) Upload documents under correct categories (e.g., Technical, Commercial, Finance). 5) Ensure file names are clear and file types are correctly selected. 6) Individual file size must not exceed 50MB; total submission size must not exceed 900MB. 7) Review all documents, then click 'Finalize Submission' and confirm. 8) Save the submission confirmation email (includes submission ID) for future reference. Physical submissions are not accepted.
Evaluation Criteria
Source: E-tendering Help Manual for supplier - 27 January 2025.docx (unknown)Registration
Must have a valid CSD number and complete registration on eTendering system
Access
OTP verification via email and cellphone is mandatory
Technical
Compatible device and browser (Microsoft Edge recommended)
Compliance
Must adhere to Eskom’s procurement policies and submission guidelines
Technical Specifications
Source: E-tendering Help Manual for supplier - 27 January 2025.docx (unknown)The eTendering system is a web-based platform for electronic submission of tender documents. Key features: 1) Replaces manual/physical submissions at Eskom tender offices. 2) Requires supplier registration with CSD number. 3) Uses OTP verification (sent to email and SMS) for secure access. 4) Compatible with most web browsers; Microsoft Edge recommended. 5) Supports document upload, categorization, and final submission with timestamp confirmation.
Compliance Requirements
Source: E-tendering Help Manual for supplier - 27 January 2025.docx (unknown)Mandatory: Suppliers must have a valid CSD (Central Supplier Database) number to access the eTendering system. No additional compliance requirements explicitly stated in the document.
Submission Guidelines
Source: Annex-c_Local content Declaration-Summary Schedule.pdf (unknown)Returnable Documents: Not specified in the provided text.
Contact Information
Source: List of Tender Returnables- HP Power Pack and Servo Motors Hydraulic Equipment Spares .pdf (TENDER)Eskom Representative: Zama Sabela.
Submission Guidelines
Source: List of Tender Returnables- HP Power Pack and Servo Motors Hydraulic Equipment Spares .pdf (TENDER)Submit the following returnable documents as part of your bid:
Returnable Documents
Source: List of Tender Returnables- HP Power Pack and Servo Motors Hydraulic Equipment Spares .pdf (TENDER)Required returnable document:
Evaluation Criteria
Source: List of Tender Returnables- HP Power Pack and Servo Motors Hydraulic Equipment Spares .pdf (TENDER)Qms Compliance
Must demonstrate compliance with ISO 9001:2015 (certification not mandatory but alignment required).
Documentation
Must provide all requested QMS documentation and operational evidence.
Quality Plans
Must submit a Draft Contract Quality Plan and a Quality Control Plan/ITP.
Form A
Must complete and sign Form A.
Technical Capability
Implied requirement to supply hydraulic equipment spares (HP Power Pack and Servo Motors).
Section
Source: List of Tender Returnables- HP Power Pack and Servo Motors Hydraulic Equipment Spares .pdfEvaluation is based on quality requirements with the following scoring structure:
Section A: Quality Management System (QMS) Requirements (ISO 9001) – Max 7 points
Section B: Evidence of QMS in Operation – Max 2 points
Section C: Contract Quality Plan Requirements – 1 point
Section D: Quality Control Plan Requirements – 1 point
Section E: User-Defined Additional Requirements – 1 point
Submission Guidelines
Source: Safety Returnables.pdf (unknown)Submit the following returnable documents by the tender closing date:
Evaluation Criteria
Source: Safety Returnables.pdf (unknown)Mandatory
Preferred
Disqualifiers
Compliance Requirements
Source: Safety Returnables.pdf (unknown)Mandatory compliance requirements:
Health & Safety
Source: Safety Returnables.pdfOHS Policy Requirements:
Section
Source: Safety Returnables.pdfSafety Evaluation Criteria (disqualifiable if not met):
Description
Source: Eskom General Conditions of Purchase - 31 May 2024.pdfSupply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment spares on an 'as and when required' basis to Kriel Power Station for a five-year period.
Important Dates
Source: Eskom General Conditions of Purchase - 31 May 2024.pdf (unknown)Closing date for submissions: 28 July 2026 at 11:00 AM (SAST).
Contact Information
Source: Eskom General Conditions of Purchase - 31 May 2024.pdf (unknown)Fraud/corruption reporting:
Note: Submission address and primary SCM/technical contacts are not explicitly provided in the document. Verify with Eskom’s procurement portal or tender notice.
Submission Guidelines
Source: Eskom General Conditions of Purchase - 31 May 2024.pdf (unknown)Submit the following returnable documents as part of your bid:
Disqualification risks:
Technical Specifications
Source: Eskom General Conditions of Purchase - 31 May 2024.pdf (unknown)Scope: Supply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment spares on an 'as and when required' basis to Kriel Power Station for a period of five years.
Requirements:
Quality Management
Source: Eskom General Conditions of Purchase - 31 May 2024.pdfQuality and acceptance:
Pricing Schedule
Source: Eskom General Conditions of Purchase - 31 May 2024.pdfPricing details:
Financial Requirements
Source: Eskom General Conditions of Purchase - 31 May 2024.pdf (unknown)Pricing and payment terms:
Compliance Requirements
Source: Eskom General Conditions of Purchase - 31 May 2024.pdf (unknown)Mandatory compliance:
Note: Specific B-BBEE, CIDB, or CIPC requirements are not explicitly stated in the provided document. Verify with the full tender notice.
Contractual Terms
Source: Eskom General Conditions of Purchase - 31 May 2024.pdfContract amendments: Any changes to the agreement must be in writing and signed by both parties.
Important Dates
Source: SDL&I strategy for Supply and Delivery of HP Power Pack and Servo Motors - Copy.pdf (unknown){"closingDate":"01 April 2023"}
Contact Information
Source: SDL&I strategy for Supply and Delivery of HP Power Pack and Servo Motors - Copy.pdf (unknown){"name":null,"email":null,"phone":null,"department":"Kriel Power Station","address":null}
Evaluation Criteria
Source: SDL&I strategy for Supply and Delivery of HP Power Pack and Servo Motors - Copy.pdf (unknown)Section 1: Specific Goals
A maximum of 10/20 points may be awarded to a tenderer for the specific goal specified for the
tender. The points scored for the specific goal must be added to the points scored for price and the
scoring the highest points.
B-BBEE Status Level of Number of points Number of points
Contributor (90/10 system) (80/20 system)
NB: The following documents are required to claim preference points,
Tenderer failing to provide documentation for the allocation of preference points will not be
Valves and Actuators Valves 70%
MV Motors and Pumps Pumps 70%
Technical Specifications
Source: SDL&I strategy for Supply and Delivery of HP Power Pack and Servo Motors - Copy.pdf (unknown)Supply and Delivery of HP Power Pack and Servo Motors
Hydraulic Equipment Spares “As and When required basis”
Duration of the Project
Compliance Requirements
Source: SDL&I strategy for Supply and Delivery of HP Power Pack and Servo Motors - Copy.pdf (unknown)Proof of ownership / shareholding (preferably CIPC documentation) inclusive of shareholding
B-BBEE Minimum Level: 0
Points Allocation: 20 points
B-BBEE Details: nd Servo Motors
Hydraulic Equipment Spares “As and When required basis”
Duration of the Project 60 months
XXXXXX Budget
Name of Buyer Mataboge Mogashoa
Section 1: Specific Goals
A maximum of 10/20 points may be awarded to a tenderer for the specific goal specified for the
tender. The points scored for the specific goal must be added to the points scored for price and the
total must be rounded off to the nearest two decimal places. Subject to section 2(1)(f) of the
Preferential Procurement Policy Framework Act, the contract must be awarded to the tenderer
scoring the highest points.
B-BBEE Status Level of Number of points Number of points
Contributor (90/10 system) (80/20 system)
1 10 20
2 9 18
3 6 14
4 5 12
5 4 8
6 3 6
7 2 4
8 1 2
Non-compliant contributor 0 0
NB: The following documents are required to claim preference points,
CIPS affidavit
breakdown
ventures), a consolidated B-BBEE status level verification certificate.
Tenderer failing to provide documentation for the allocation of preference points will not be
disqualified, but’
Confidential
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorised version on the system. No part of this document may be re
B-BBEE Requirements
Source: SDL&I strategy for Supply and Delivery of HP Power Pack and Servo Motors - Copy.pdf (unknown)2.1 Designated Sectors achieved in full by the tenderer a) Is this Commodity or part of it a Designated Sector? Valves and Actuators Valves 70% MV Motors and Pumps Pumps 70% Steel Products Various Steel Products 100%
Special Conditions
Source: SDL&I strategy for Supply and Delivery of HP Power Pack and Servo Motors - Copy.pdf (unknown)Section 2: Objective criteria does not meet objective criteria; it may lead to the second-ranked tenderer being recommended for award.
Description
Source: Commercial Code of Ethics 32-527 Rev 0.pdfThis document is Eskom’s Code of Ethics, outlining required ethical standards and behaviour for all directors, employees, and suppliers. It emphasizes Eskom’s commitment to integrity, excellence, customer satisfaction, and innovation. The Code applies to all Eskom Holdings Limited entities, including subsidiaries, and must be followed in all business activities. Contraventions may result in disciplinary action.
Contact Information
Source: Commercial Code of Ethics 32-527 Rev 0.pdf (unknown)Ethics Office: +27 11 800 3187/3189, Fax: 086 663 4120, Email: [email protected]. Whistleblowing hotline: 0800 11 27 22. Ethics website FAQs available on Eskom Intranet.
Compliance Requirements
Source: Commercial Code of Ethics 32-527 Rev 0.pdf (unknown)Suppliers must adhere to Eskom’s Code of Ethics, which includes: compliance with all applicable legislation, policies, and professional standards; avoidance of conflicts of interest, favouritism, and nepotism; protection of confidential information; and commitment to ethical supplier relationships. Non-compliance may result in disciplinary action.
Health & Safety
Source: Commercial Code of Ethics 32-527 Rev 0.pdfEskom requires a safe and healthy environment for all stakeholders. Suppliers must comply with safety, health, and environmental legislation and Eskom policies. Workplaces must be free from sexual harassment, discrimination, and favouritism.
Contractual Terms
Source: Commercial Code of Ethics 32-527 Rev 0.pdfSuppliers must comply with Eskom’s Code of Ethics as part of contractual obligations. This includes adhering to ethical standards, avoiding conflicts of interest, and ensuring fair, transparent, and non-discriminatory practices. Non-compliance may lead to disciplinary action or contract termination.
Submission Guidelines
Source: 240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP) rev 2.docx (unknown)Returnable Documents: Not explicitly listed in the provided document. Refer to the official tender record for submission details.
Evaluation Criteria
Source: 240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP) rev 2.docx (unknown)General
Applicants must be legally registered entities capable of supplying hydraulic equipment spares.
Technical
Proven experience in supplying and delivering similar hydraulic equipment spares, preferably for power stations or industrial applications.
Quality Assurance
Certification or accreditation in quality management systems (e.g., ISO 9001) may be required.
Compliance
Compliance with South African regulatory and statutory requirements for industrial equipment supply.
Financial
Financial stability to fulfill a five-year contract with potential variable demand.
Compliance Requirements
Source: Annex-e_Local Content Declaration-Supporting Schedule to Annex C.pdf (unknown)Insufficient searchable text - AI extraction recommended
Returnable Documents
Source: Annexure B.pdf (unknown)Required returnable documents:
Compliance Requirements
Source: Annexure B.pdf (unknown)Compliance with the following is mandatory for all suppliers/contractors/tenderers:
Post-award obligations:
Penalties:
Verification:
Health & Safety
Source: Annexure B.pdfVerification and references:
Contractual Terms
Source: Annexure B.pdfContractual obligations for the main supplier/contractor:
Submission Guidelines
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.docx (unknown)Mandatory returnable: E-Tenderers E-Tendering Training Acknowledgement Form must be fully completed and submitted to Eskom within the prescribed period. Failure to submit this form will result in disqualification from the procurement process.
Evaluation Criteria
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.docx (unknown)Mandatory Training
Completion of e-tendering training and submission of acknowledgment form is mandatory
Responsiveness
Non-submission or incomplete submission of the form will render the tenderer non-responsive and lead to disqualification
Compliance
Must comply with Eskom's e-tendering solution requirements
Submission Guidelines
Source: Safety Returnables.docx (unknown)Required returnables at tender closing (disqualifiable):
Required returnables at tender closing (non-disqualifiable):
Required prior to contract award:
Evaluation Criteria
Source: Safety Returnables.docx (unknown)Mandatory
Non Disqualifiable
Compliance Requirements
Source: Safety Returnables.docx (unknown)Mandatory compliance documents:
Description
Source: 240-109253698 CQP Template.docxGeneral Scope: Supply and delivery of HP Power Pack and Servo Motors Hydraulic Equipment spares on an 'as and when required' basis for Kriel Power Station over a five-year period. Quality Focus: The tender requires a Contract Quality Plan (QCP) to ensure compliance with Eskom’s quality management expectations, referencing SANS 466:2005 / ISO 10005:2005 standards.
Submission Guidelines
Source: 240-109253698 CQP Template.docx (unknown)Returnable Documents: Submit a completed Contract Quality Plan (QCP) as per the provided template. Include all required documented information such as method statements, inspection reports, QCP/ITP forms, technical assurance reports, warranty certificates, material certificates, dimension reports, and test reports.
Description
Source: 240-113650212 Eskom Supplier Integrity Pact Rev 2 June 2028.pdfScope and purpose:
Important Dates
Source: 240-113650212 Eskom Supplier Integrity Pact Rev 2 June 2028.pdf (unknown)Closing date for document reference: 27 June 2023
Contact Information
Source: 240-113650212 Eskom Supplier Integrity Pact Rev 2 June 2028.pdf (unknown)Submission Guidelines
Source: 240-113650212 Eskom Supplier Integrity Pact Rev 2 June 2028.pdf (unknown)Required returnable documents and actions:
Returnable Documents
Source: 240-113650212 Eskom Supplier Integrity Pact Rev 2 June 2028.pdf (unknown)Required forms:
Evaluation Criteria
Source: 240-113650212 Eskom Supplier Integrity Pact Rev 2 June 2028.pdf (unknown)Registration
Suppliers must be registered on Eskom’s Vendor Database as a current or potential supplier.
Legal Compliance
Suppliers must comply with all applicable South African laws, including the Employment Equity Act and procurement regulations.
Ethical Standards
Suppliers must demonstrate a commitment to ethical business practices, including anti-corruption and fairness.
Technical Capacity
Suppliers must have the technical and operational capacity to supply and deliver HP Power Pack and Servo Motors Hydraulic Equipment Spares as required.
Financial Stability
Suppliers must be financially stable and capable of fulfilling the contract over the five-year period.
Compliance Requirements
Source: 240-113650212 Eskom Supplier Integrity Pact Rev 2 June 2028.pdf (unknown)Mandatory compliance actions:
Contractual Terms
Source: 240-113650212 Eskom Supplier Integrity Pact Rev 2 June 2028.pdfContractual obligations and enforcement:
Special Conditions
Source: 240-113650212 Eskom Supplier Integrity Pact Rev 2 June 2028.pdf (unknown)Ethical and conflict-of-interest conditions:
Data conflicts
None detected
Get deep intelligence on Supplies: General. Unlock full pricing strategies, bid frequency, and historical win rates.