Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
MAJUBA AND LETHABO POWER STATIONS - Mpumalanga and Free State - Volksrust and Viljoensdrif - 2095
Organization Type
GOVERNMENT
Published
24 Jul 2026
OCDS Reference
ocds-9t57fa-163377
This is an open request for bid issued by ESKOM for the supply and delivery of sodium bicarbonate to support dsi (dry sorbent injection) flue gas desulphurisation (fgd) phase 2 testing at majuba and lethabo power stations over a three-month period. The tender is aimed at chemical manufacturers or suppliers capable of delivering sodium bicarbonate to eskom's power stations located in the free state province. Bids close on 14 august 2026 at 10:00.
Continue with tenders sharing this issuer, category, or province.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Friday, 14 August 2026 - 10:00
Venue
MS teams
Request for Bid(Open-Tender)
MAJUBA AND LETHABO POWER STATIONS - Mpumalanga and Free State - Volksrust and Viljoensdrif - 2095
Tenders in this industry often require registration with these bodies.
Recommended Certifications
Having these can improve your winning chances: Good Manufacturing Practice (GMP), SABS Product Certification, NRCS Certification
AI Document Analysis Stages
Description
24 Jul
2026
Tender Published
Tender was published
14 Aug
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Technical Evaluation Criteria - Sodium Bicarb for DSI FGD Phase 2.pdf
Eskom seeks a supplier to deliver sodium bicarbonate for FGD Phase 2 testing at Majuba and Lethabo Power Stations for a 3-month period. The tender involves a once-off purchase with strict technical, logistical, and quality assurance requirements. Evaluation includes mandatory and qualitative technical criteria, with a minimum score of 70% required to proceed.
NEC3 SSC3 - Supply and Delivery of Sodium Bicarbonate for DSI FGD Phase 2 Research Test.pdf
Eskom requires supply and delivery of 120 tonnes (60 tonnes each) of sodium bicarbonate for DSI FGD Phase 2 testing at Majuba and Lethabo Power Stations over 3 months. The contract uses NEC3 Supply Short Contract framework with specific technical and compliance requirements.
E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025 (1).docx
Eskom tender for supply and delivery of sodium bicarbonate for FGD Phase 2 testing at Majuba and Lethabo power stations for 3 months. Requires mandatory e-tendering training acknowledgment.
OHS Evaluation.docx
Eskom tender for supply and delivery of sodium bicarbonate for DSI FGD Phase 2 testing at Majuba and Lethabo Power Stations for a 3-month period. The tender focuses heavily on OHS (Occupational Health and Safety) compliance and documentation.
37-2 agreement form.docx
Eskom tender for supply and delivery of sodium bicarbonate for FGD Phase 2 testing at Majuba and Lethabo Power Stations for three months, requiring strict compliance with Occupational Health and Safety Act.
Acknowledgement Form Life-saving Rules.docx
Eskom tender for supply and delivery of sodium bicarbonate for DSI FGD Phase 2 testing at Majuba and Lethabo Power Stations for a 3-month period, with mandatory adherence to Life-Saving Rules.
Tender Environmental Requirements - DSI FGD - Feb 2026 .pdf
Eskom tender for supply and delivery of sodium bicarbonate for DSI FGD Phase 2 testing at Majuba and Lethabo Power Stations for a 3-month period. The document focuses heavily on environmental compliance requirements for bidders.
240-126469599_Method Statement template final 18 Oct2021.docx
Eskom invites tenders for the supply and delivery of sodium bicarbonate for DSI FGD Phase 2 testing at Majuba and Lethabo Power Stations for a three-month period. The tender requires a detailed method statement addressing scope, objectives, customer focus, competency, infrastructure, leadership, risk management, process improvement, data analysis, and relationship management.
20260224_Sodium Bicarbonate_List of Tender Returnables_Cat 4_ Rev 7_signed.pdf
Eskom tender for supply and delivery of sodium bicarbonate for DSI FGD Phase 2 testing at Majuba and Lethabo Power Stations for 3 months. Focus on quality management system compliance with ISO 9001 requirements.
E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdf
Eskom invites tenders for the supply and delivery of sodium bicarbonate for DSI FGD Phase 2 testing at Majuba and Lethabo Power Stations for a 3-month period. The tender is open, uses an 80/20 scoring system (80 points for price, 20 for B-BBEE), and requires electronic submission via Eskom's e-tendering portal.
20260224_Sodium Bicarbonate _240-68099512 Form A_Cat 4_ Rev 9.docx
Eskom tender for supply and delivery of sodium bicarbonate for DSI FGD Phase 2 testing at Majuba and Lethabo Power Stations for 3 months. Tender focuses on quality assurance compliance with specific Eskom specifications and ISO 9001 standards.
Acknowledgement Form for Eskom SHE Rules and other Requirements (1).docx
Eskom tender for supply and delivery of sodium bicarbonate for FGD Phase 2 testing at Majuba and Lethabo Power Stations for 3 months, with strong emphasis on OHS compliance and contractor management.
Practice-Guide-01-of-2018-Determining-Validity-of-a-B-BBEE-Certificate.pdf
This document is a B-BBEE Practice Guide issued by the B-BBEE Commission, not the actual tender document. It provides guidelines for determining the validity of B-BBEE certificates and sworn affidavits required for tender submissions. The tender itself is for the supply and delivery of sodium bicarbonate for FGD testing at two Eskom power stations over three months.
E-tendering Help Manual for supplier - 27 January 2025 (1).docx
This is a supplier help manual for Eskom's eTendering system, not the actual tender specification for sodium bicarbonate supply. The tender itself is for supplying sodium bicarbonate for FGD testing at Majuba and Lethabo power stations for three months. The document provides instructions for electronic tender submission.
Eskom - Standard Conditions of Tender - 30 January 2025.pdf
Eskom tender for the supply and delivery of sodium bicarbonate for FGD Phase 2 testing at Majuba and Lethabo Power Stations for a 3-month period. The document outlines standard conditions of tender, including submission procedures, evaluation criteria, and compliance requirements.
240-105658000 Supplier Quality Management Specification (3).pdf
This tender document outlines Eskom's quality management requirements for suppliers bidding on the supply and delivery of sodium bicarbonate for FGD Phase 2 testing at Majuba and Lethabo Power Stations over three months. The core document is a 28-page 'Supplier Quality Management' specification (Revision 3) that mandates suppliers to have a formal Quality Management System (QMS) conforming to ISO 9001. The tender closes on August 14, 2026.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubLearn how to submit a winning bid with these related articles
Median Estimate
R 261 000
Range
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Title: Supplier Quality Management: Document Identifier: 240-105658000
Alternative Reference QM 58
Number:
Area of Applicability: Eskom Holdings SOC Ltd
Functional Area: Quality Management
Revision: 3
Total Pages: 28
Next Review Date: October 2024
Disclosure Controlled Disclosure
Classification:
Compiled by Supported by Functional Authorized by
Responsibility
SA Sambo P Dondashe L Meyer K Pather
Chief Advisor Middle Manager Acting Senior General Manager
Quality Quality Manager Quality Risk and
Management Management Management Sustainability
Date: 15/10/2021 Date: 15/10/2021 Date: 15/10/2021 Date: 17 October 2021
EDC TN Formatted 15.10.2021
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Content
. Introduction ............................................................................................................................... 3
2.1 Scope ............................................................................................................................... 3
2.1.1 Purpose ................................................................................................................. 3
2.1.2 Applicability ........................................................................................................... 3
2.1.3 Effective date ......................................................................................................... 3
2.2 Normative/Informative References ................................................................................... 3
2.2.1 Normative .............................................................................................................. 3
2.2.2 Informative............................................................................................................. 3
2.3 Definitions ........................................................................................................................ 4
2.4 Abbreviations ................................................................................................................... 5
2.5 Roles and Responsibilities ............................................................................................... 6
2.6 Process for Monitoring ...................................................................................................... 6
2.7 Related/Supporting Documents ........................................................................................ 6
3.1 Supplier and Sub-Supplier Quality Management System Requirements .......................... 7
3.2 Quality Plan ...................................................................................................................... 8
3.3 Contract Quality Plan........................................................................................................ 8
3.4 Quality Control Plan ....................................................................................................... 10
3.5 Pre-Contract Award: Quality Requirement ...................................................................... 13
3.6 Main Supplier and Sub-supplier Capability and Capacity Assessment ........................... 16
3.7 Post-Contract Award ...................................................................................................... 17
3.7.1 Contract Execution .............................................................................................. 17
3.7.2 Supplier Quality Performance Monitoring Phase ................................................. 18
3.7.3 Supplier Quality Audit .......................................................................................... 18
3.8 Standard Conditions ....................................................................................................... 19
3.8.1 Rights of Access .................................................................................................. 19
3.8.2 Eskom Rights to Information ................................................................................ 20
3.8.3 Preservation ........................................................................................................ 21
3.8.4 Quality Audits Related Conditions ....................................................................... 25
3.8.5 Management of Nonconformities and Nonconforming Outputs Identified by
Eskom ................................................................................................................. 25
3.8.6 Special Processes ............................................................................................... 26
Acceptance ............................................................................................................................. 27
Revisions ................................................................................................................................ 27
Development Team ................................................................................................................ 27
Acknowledgements ................................................................................................................ 28
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The intention of this specification is to specify and describe the minimum quality requirements for all
existing and potential Eskom suppliers and define the quality criteria for the selection, evaluation,
vendor registration, management, monitoring, assessment and auditing of suppliers. Eskom’s
position is to partner with suppliers who fully demonstrate commitment to the development,
implementation, and maintenance of a quality management system (QMS) that conforms to the
requirements of ISO 9001 standard. The priority is to encourage suppliers to continually improve
their QMS and enhance service delivery by implementing and conforming to the standard.
2.1 Scope
2.1.1 Purpose
The purpose of this specification is to outline the requirements according to which suppliers shall
develop,
implement,
maintain, and
continually improve
a quality management system (QMS) based on ISO 9001, which should form the basis for conformity
to Eskom quality requirements and continually adhere to them throughout the duration of a contract
2.1.2 Applicability
This specification shall apply throughout Eskom Holdings Limited divisions, its subsidiaries,
suppliers, and sub-suppliers and shall form part of all Eskom requests for information (RFI)/ requests
for quotation (RFQ)/ requests for proposal (RFP), including contracts for the procurement of products
and services.
2.1.3 Effective date
Date of authorisation of the specification
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
[1] ISO 9001 Quality Management Systems – Requirements
[2] ISO 10005 Quality Management Systems – Guidelines for Quality Plans.
2.2.2 Informative
[3] ISO 9000 Quality Management Systems – Fundamentals and Vocabulary
[4] 32-727: Safety, Health, Environment, and Quality (SHEQ) Policy
[5] ISO 10006 Quality Management Systems – Guidelines for Quality Management in Projects
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
[6] ISO 9004 Quality Management – Quality of an Organisation – Guidance to Achieve Sustained
Success
[7] 32-1033: Eskom’s Procurement and Supply Chain Management Policy
[8] 32-1034: Eskom’s Procurement and Supply Chain Management Procedure
[9] PPPFA: Preferential Procurement Policy Framework Act, 2000 (Act No. )
[10] CIDB 1004: Best Practice Guideline A4: Evaluating Quality in Tender Submissions
[11] 240-12248652 Supplier Quality Management: List of Tender Returnables
[12] IAEA Safety Standard GS-R-3.1 Application of the Management System for Facilities and
Activities
[13] SANS 10845-1 Construction Procurement Part1: Processes, Methods and Procedures
2.3 Definitions
The vocabulary of ISO 9000 and the following definitions apply in the application of this specification.
2.3.1 Component: a constituent part of the product or sub-assembly of the product. The product
may comprise multiple individual components
2.3.2 Contract Quality Plan: a document of the supplier’s process for delivering the level of quality
required by the contract. It is a framework for the contractor’s process for delivering quality.
Purpose of a CQP is to outline how the results defined in the specifications will be achieved.
2.3.3 Hold Point: a predetermined stage in the quality control plan (QCP) beyond which work/
manufacturing shall not proceed without the attendance of, and written authorisation of, an
Eskom representative or Eskom inspection agency, whichever is applicable.
2.3.4 Intervention Points: those control points indicated by the various controlling bodies
concerned with the implementation of a specific QCP/ ITP. These can be in the form of
inspection, hold points, surveillances, witnesses, reviews and verifications.
2.3.5 Inspection Agency: an organisation or person appointed by Eskom for the purpose of
performing quality assurance/ quality control, monitoring, inspection and/ or expediting
services.
2.3.6 Level 1 Plant Items: equipment, whose failure has an effect on personnel safety and/ or
health, causes an environmental incident, cause a huge production loss or major equipment
damage. Equipment that are safety/ redundancy/ protective device or covered by statutory
regulations requirements.
2.3.7 Level 2 Plant Items: equipment, whose failure impacts plant availability and/or reliability,
causes significant costs or secondary damage.
2.3.8 Level 3 Plant Items: equipment that does not impact on personnel safety and/ or health,
environmental, cost, availability and/ or reliability of plant.
2.3.9 Nonconformity: a deficiency in material, composition, characteristic, or performance that
renders the quality of an item, component, or product unacceptable or indeterminate. The
term also covers a deficiency in, or deviation from/non-adherence to, the quality management
system requirements, prescribed production processes, and/or related documentation such
as procedures and instructions.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
2.3.10 Quality Plan: specification of the actions, responsibilities and associated resources to be
applied to a specific object.
2.3.11 Quality Control Plan: a document specifying the activities to be inspected throughout the
execution of the project, inclusive of test methods, procedures, and acceptance criteria (This
term is equivalent to QIP and ITP).
2.3.12 Requirement: the need or expectation that is stated, generally implied, or obligatory.
Requirements are generally specified in the purchase order and/or contract documentation,
but may not be limited to these.
2.3.13 Primary Plant (Power Plant): primary plant include High Voltage equipment situated inside
the control room (breakers, bus-bars, CT’s, VT’s and transformers).
2.3.14 Secondary Plant (Control Plant): secondary plant includes all equipment used to control
and protect the HV equipment on the primary plant side. (Protection, metering, AC/DC and
tele-control).
2.3.15 Special Process: is any production or service process which generates products or services
which cannot be measured, monitored, or verified prior to delivery and use.
2.3.16 Supplier: is a current or potential supplier, vendor, contractor, consultant, or service provider.
A supplier may be a natural or legal person and includes any employee acting within the
course and scope of his/her employment or any agent or manager acting for, or on behalf of,
or in the interests of, the person registered as supplier on the Eskom supplier database.
2.3.17 Sub-supplier: an organisation that provides a product/service to the supplier and/or that
enters into a subcontract and assumes some of the obligations of the supplier or prime
contractor.
2.3.18 Witness Point: a predetermined stage in the quality control plan where and inspection
activity will take place. Work may proceed, provided Eskom or its inspection agency has been
formally notified and confirmed that inspection is waived.
2.4 Abbreviations
Abbreviation Explanation
AIA Approved Inspection Authority
CA Corrective Action
CQP Contract Quality Plan
FIDIC Federation Internationale Des Ingenieurs- Conseils
FMECA Failure Mode, Effects and Criticality Analysis
HAZOP Hazard and Operability Study
ISO International Organisation for Standardisation
ITP Inspection and Test Plan
NC Nonconformity
NDT Non Destructive Testing
PMI Positive Material Identification
QCP Quality Control Plan
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Abbreviation Explanation
QMS Quality Management System
PQP Project Quality Plan
RFI Request for Information
RFQ Request for Quotation
RFP Request for Proposal
SHEQ Safety, Health, Environment, and Quality
SETA Skills Education Training Authorities
WPS Welding procedure specifications
WQR Welder’s Qualification Record
2.5 Roles and Responsibilities
Eskom Quality representative/ professional will select applicable requirements for existing and
potential Eskom suppliers using Form A (Tender and Contract Quality Requirements for Supplier
Quality Management: Specification 240-105658000/ QM 58 and Quality Requirements for ISO 9001
Standard).
The existing and/ or potential suppliers must complete, sign and return Form A with the other
returnable as listed in the List of Tender Returnable document (240-12248652). Other roles and
responsibilities for this standard are defined within the text of this specification.
2.6 Process for Monitoring
The application of this specification throughout Eskom shall be audited as per the management
system audit schedule.
2.7 Related/Supporting Documents
The documents superseded by this specification: all divisional and business unit supplier quality
requirements standards and/or specifications.
Forms and templates:
[1] 240-68099512 Tender and Contract Quality Requirements for Supplier Quality Management
Specification 240-105658000/ QM 58 and Quality Requirements for ISO 9001 Standard (Form
A)
[2] 240-109253698 Template for a Typical Contract Quality Plan
[3] 240-109253302 Quality Control Plan/Inspection and Test Plan
[4] 240-126469599 Method Statement Template.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The quality assessment criteria and Form A of this specification will be selected and completed by
an Eskom Quality representative/ professional who will identify the applicable supplier quality
requirements to be met.
Form A of this specification must also be completed and signed by the supplier responding to an
Eskom invitation to tender, in order to acknowledge and accept Eskom Supplier Quality requirements
as per this specification and ISO 9001 Standard or any additional quality requirements specific to
the scope of work.
3.1 Supplier and Sub-Supplier Quality Management System Requirements
3.1.1 The supplier and sub-supplier shall develop, implement, maintain and improve a formal QMS
that conforms to the latest ISO 9001 standard or any applicable standard of QMS (latest
applicable revision) and in accordance with the requirements of this specification.
3.1.2 Such a formal system shall consist of the appropriate documented information required by
ISO 9001 and may include a quality manual, quality plans, work procedures, work
instructions, method statements, work flow documentation, etc., as the case may be. This
requirement constitutes the most basic QMS requirements.
3.1.3 Unless specifically excluded from the quality list of tender returnable, as per the categories of
quality requirements (Category 1, 2, 3, or 4), such a QMS shall carry a valid ISO 9001
certificate from an accredited certification body, as indicated in the applicable Eskom
invitation (this requirement applies equally to both the supplier and any/ all manufacturing
third-party organisations mentioned above).
3.1.4 Unless specifically excluded in the quality list of tender returnable, as per the categories of
quality requirements (Category 1, 2, 3, or 4), the supplier shall have a fully developed,
documented, implemented, reviewed and maintained QMS that complies with the
requirements of ISO 9001 standard or any applicable standard of QMS. In the event that the
main supplier invariably requires the assistance of a sub-supplier in order to realise its own
supply obligations. The aforementioned requirement applies equally in all cases where any
such sub-supplier’s scope of responsibility includes the provision of any of the following
activities, namely, design and development, manufacturing, maintenance, testing, storage,
delivery, installation, commissioning, and project management, or in the cases the supplier
name changes, mergers, acquisitions and/ or cessions. Eskom Quality department must
ensure that the changed entity can still fulfil the requirements as set out in the contract
documentation.
3.1.5 Eskom reserves the right to request and perform necessary assessments at sub-supplier
facilities.
3.1.6 The main supplier shall be responsible for defining and managing the specific quality
assurance and control elements applicable to the respective sub-supplier’s scope of
work/supply and ensure that its sub-supplier(s) quality programmes support Eskom
requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.1.7 The supplier shall inform Eskom of any proposed changes to the QMS or staff that will affect
the quality system prior to implementation of these changes.
3.1.8 The main supplier shall develop and implement a performance management programme for
their sub-supplier. The programme shall include, but not limited to:
Verification of the QMS
Audits and surveillances
Regular assessment of the CQPs and reviews of QCPs.
NC and Defect Management
Inspection and test plans
Risk management
3.2 Quality Plan
The information in this section constitutes the minimum requirements for a quality plan.
3.2.1 Where specified in the Evaluation Criteria and/ or quality list of tender returnables , as per the
categories of quality requirements (Category 1, 2, 3, or 4); all individual products, services
and processes shall have a documented, implemented, reviewed and maintained contract
quality plan and/or quality control plan (inspection and test plan).
3.2.2 Where specified in the evaluation criteria and/ or quality list of tender returnables. All
production and/ or service provision shall be carried out in accordance with a documented
and agreed contract quality plan (CQP) and/ or quality control plan (QCP)/ inspection and test
plan (ITP).
3.2.3 The supplier shall plan for the required quality-related activities and interfaces within the
supplier’s quality system in order to demonstrate its ability towards both controlling and
meeting specified Eskom requirements.
Note 1: Contract Quality Plan should address the quality assurance elements related to the scope
of work and/ or technical specification.
Note 2: Quality Control Plan (QCP)/ Inspection and Test Plan (ITP) should address the quality
control elements related to the scope of work and/ or technical specification.
3.3 Contract Quality Plan
The main supplier shall require sub-suppliers to submit project quality plans (PQPs)/ contract quality
plans (CQPs) and associated documentation in accordance with the requirements of project QMS
processes applicable to the sub-supplier’s scope of work.
The supplier shall, where applicable, based on scope of work criticality, ensure that procurement
documents clearly and unambiguously require sub-supplier submission of a sub-supplier CQP for
supplier and Eskom review.
The main supplier shall ensure that sub-supplier CQPs are developed and implemented in
accordance with the ISO 10005 Quality Management System Guidelines for Quality Plans. In
addition to the elements specified in ISO 10005, the supplier’s and/ or sub-suppliers’ CQPs shall
include the following (as applicable):
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.3.1 The management of records, including material tests, positive material identification (PMI)
testing, material certification, etc.
3.3.2 The provision for free and uninhibited access by the supplier and/or personnel at the time of
inspection.
3.3.3 The proposals for submission of final documentation, the final manufacturing data book, prior
to shipment.
3.3.4 The special processes related to welding: management of the welder’s qualification record
(WQR), welding procedure specifications (WPS), and procedures qualification records (PQR)
that will be used in the performance of work for supplier review and acceptance prior to
commencing manufacture. Welders shall be qualified to the specified Codes of Construction
for the applicable procedures. The requirements for qualification shall be specified by the
supplier, and welder records shall be maintained by sub-suppliers performing the work.
3.3.5 The special installation procedures and other required fabrication or manufacturing
procedures (that is, those required for post-weld heat treatment, tube rolling, coatings, etc.)
that will be used in the performance of work shall require supplier review and acceptance
prior to commencing manufacture. The personnel carrying out special processes (for
example, NDE, welding, coating, heat treatment, etc.) where the results cannot be fully
verified by subsequent inspection and test shall be suitably qualified and, where applicable,
registered with statutory bodies as legally required, that is, as radiographic workers to conduct
radiography. The requirements for the qualification shall be specified, and personnel records
shall be maintained in accordance with the Project Quality Personnel Qualification
Specification and, where applicable, legal requirements.
3.3.6 The personnel required to perform special processes shall be certified competent through a
certificate of competency in accordance with the company’s internal training management
and competency control procedures or an external certification body (for example, NDT)
through an accredited service provider as per Skills Education Training Authorities (SETA)
requirements.
3.3.7 All personnel who perform activities that affect quality shall have their training needs identified
and documented. The required training shall be implemented in accordance with the
company’s training management and competency control procedures. All the training
certificates shall meet the SETA requirements in terms of having the unit standard completed
and the accreditation number of the service providers.
3.3.8 Instructions and requirements for equipment and materials storage, preservation, and
maintenance, including identification of materials required for preservation and maintenance,
are to be provided sufficiently prior to receipt (prior to shipment or earlier) to ensure that
appropriate resources are available at the time of delivery.
3.3.9 Specific quality monitoring and verification activities are to be undertaken on the supplier’s
sub-suppliers by Eskom or it agent.
3.3.10 The CQP information need to include, but not limited to:
Spells out the aspects of the QMS to be applied within a specific Eskom project, and the
methods to be utilised to ensure quality.
Outline the resources, the communication channels, applicable documents and records to be
generated.
Management Authority and Responsibility from both supplier and client need to outline in the
Cqp.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
List of documents and records that will be used and submitted during the execution of the
project.
Communications channels should include contact person and contact details
Monitoring & measurement procedures for activities need to be indicated.
3.3.11 The main supplier and sub-supplier CQPs shall comply with the Eskom Quality Requirements
Specifications and shall be submitted prior to the initial scope of work kick-off or initial pre-
fabrication meeting and prior to commencement of manufacturing, whichever is earlier.
3.3.12 The Eskom template for CQP provided shall be used as guideline, where the supplier does
not have a CQP template.
3.4 Quality Control Plan
The supplier shall develop and implement processes and procedures that efficiently and effectively
monitor, verify and document the quality of the scope of work for deliverables.
The main supplier shall ensure that sub-supplier QCPs/ ITPs are prepared at a level of detail
sufficient to address all quality-control-related activities in a chronological order, from contract review
through materials verification, manufacturing, fabrication, assembly, final testing, commissioning,
hand-over documentation, and certification. In addition, the supplier shall ensure compliance with
the following requirements:
3.4.1 All stages of manufacturing, fabrication, assembly and installation shall be controlled by a
supplier’s QCP/ ITP that clearly and unambiguously identifies the quality verifications to be
performed and special attention to controls related to critical products and services.
3.4.2 QCP/ ITP shall be reviewed and accepted by Eskom, its inspection authority or agency, and
they shall allow for the insertion of Eskom specific requirements, including hold and witness
points prior to the commencement of work.
3.4.3 Subsequent changes to the Eskom accepted QCP/ ITP shall require Eskom, its inspection
authority or agency’s agreement prior to the commencement of work involving an activity
affected by such changes.
3.4.4 The ITPs should cover materials certification, fabrication works, in-process inspections, final
acceptance tests, packaging and pre- shipment/ transportation, shipping/ transportation
inspections where contracted, preservation, site acceptance tests, construction and erection
works, and pre-commissioning and commissioning tests.
3.4.5 All sub-supplier QCP/ ITP activity shall be performed using an Eskom-accepted supplier
Qcp/ itp.
3.4.6 All applicable codes, standards, and relevant acceptance criteria documents are available at
the work location, and Eskom representatives on site shall have on-going access to this
information. Workplace documentation shall be available in English and in any workforce-
appropriate language.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.4.7 Where activities subject to inspection and test procedures are to be undertaken by a sub-
supplier, the QCP/ ITP shall make reference to this fact and shall include descriptive details
of the sub-supplier’s involvement. A separate QCP/ ITP shall be required for each sub-
supplier scope of work.
3.4.8 The supplier shall be ultimately accountable and responsible for the development and proper
implementation of all sub-supplier QCPs/ ITPs, including those reviewed or developed by
sub-suppliers.
3.4.9 Eskom reserves the right to select intervention points on QCPs/ ITPs for Eskom oversight of
selected functions and to perform surveillance or audits of the work.
3.4.10 Once signed, the ITPs and QCPs become addendums to the main contract. These ITPs can
be reviewed at Eskom’s discretion based on its assessment of the supplier’s performance or
other risks.
3.4.11 A QCP/ ITP shall contain the following information:
Eskom contract number and title
The supplier’s order number
Identification of the area of works/contract
Description of the work, with components, item number, and activity date
QCP/ITP unique number
A list of the sequence of operations, including inspection and tests
The identification of the specification, drawing number, or procedure for each operation,
with reference to the relevant criticality risk rating
The acceptance criteria, with reference to the technical specification, in-house, national, or
international standard, with the relevant clause number for each operation
The inspection and test activities that the supplier has nominated for its intervention points
Provision for the inclusion of intervention points nominated by Eskom and/or its authority/
agency
Provision for intervention point acceptance by date and signature for all parties having
intervention in the plan
Inspection and test records to be generated by the supplier for each operation and an
indication of records to be provided to Eskom (as applicable)
3.4.12 The main supplier shall require sub-suppliers to submit QCPs/ ITPs and associated
documentation applicable to the sub-supplier scope of work. Any changes made to the QCP
after submission must be resubmitted to Eskom for further review. The supplier shall ensure
that all sub-supplier QCPs/ ITPs are in compliance with the Eskom Quality Requirements
Specifications, including, but not limited to, the following requirements:
Clear and unambiguous description of the equipment and location(s) at which each activity
will take place, including facility location(s)
Identification of quality verification activity and stage
The details of reference documents, procedures, or method statements to be utilised in
performance of the activity, including specific reference to actual sections and pages of
procedures, standards, instructions, specifications, etc.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Definition of acceptance criteria
Listing of certifying or verifying documents generated to provide evidence of compliance
with specified requirements; documents are to be provided using the proper Eskom
document numbering requirements
Identification of main supplier and sub-supplier (where applicable) third-party/approved
inspection authority (AIA) and Eskom inspection activities defined in terms of witness, hold,
document review, and verification monitoring points and provision for sign-off of each of the
above-mentioned parties for each intervention point
Qualification requirements for quality control inspectors, including any third-party/AIA
inspectors
Listing of all proposed test procedures
Acceptance criteria for each inspection or test in alignment with specified tolerances
A section for signed acceptance of the QC/ITP by the supplier, sub-supplier (where
applicable), and Eskom prior to commencement of work
Inspection or testing intervention points, including, but not limited to, factory acceptance test
and package acceptance test, witness, and hold points
3.4.13 A quality kick-off meeting will be held at the start of the contract and, if required, at the start
of each subsequent phase.
The supplier shall arrange coordination meetings with Eskom prior to placement of orders
for items or equipment to ensure that all technical and commercial requirements are clear
and understood. Fourteen days’ advance notice of meetings shall be given to Eskom.
Supplier inspection personnel, including inspection agency personnel, shall be competent
and qualified to perform inspection and testing assignments. Mobilisation of all such
personnel shall be in compliance with the Project Quality Personnel Qualification
Specification.
3.4.14 Where QCP/ ITP is applicable, the supplier shall ensure that sub-suppliers are provided with
comprehensive, clearly written, and unambiguous inspection and testing protocols, including
processes, procedures, and methods that shall include, but not be limited to, the following:
Requirements for inspection checklists and inspection assignments, with lists of items to be
inspected
An inspection and testing report format, report content, schedule for report processing and
distribution, and report retention requirements
Inspection and test report results response tracking (log) and resolution of nonconformity in
inspection and test processes, procedures, or methods and nonconformity identified in
inspection and test results
Associated Failure Mode, Effects and Criticality Analysis (FMECA) reports relating to the
equipment and sub-systems (if applicable)
Hazard and Operability Study (HAZOP) report, as applicable
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.4.15 The supplier shall establish processes and procedures for formal assessment of sub-supplier
inspection and testing programmes. These shall include review of sub-supplier inspection
reports and other quality control documentation. Additional formal assessment of
manufacturing, fabrication, and assembly facility operations shall be conducted by the
supplier to ensure continuing suitability, adequacy, and effectiveness of the sub-supplier’s
inspection and testing programmes. Assessment frequency shall be established in
consideration of the sub-supplier scope of work, criticality of scope of work deliverables, and
performance information. The assessment scope and schedule shall be developed in
consultation with Eskom.
3.4.16 Supplier processes and procedures for verification of supplier and sub-supplier purchased
product compliance with specifications shall obtain document return/review status prior to
implementation.
3.4.17 The objective is to finalise any outstanding procedural or other issues before proceeding to
deliver the works.
3.4.18 Eskom, in consultation with the supplier, develops an agenda for the meeting, and Eskom will
keep minutes of these meetings.
3.4.19 Mandatory pre-inspection meetings will be convened by Eskom or its inspection agency or
AIA to be attended by the supplier’s and sub-supplier’s representatives, including their quality
representatives who will be involved in the works, and records are to be kept.
3.4.20 Eskom reserves the right to appoint resident quality inspectors who can be based at the
supplier’s or sub-supplier’s premises and on site where the work is being performed. The
supplier is expected to provide workspace at no cost to Eskom for the inspector, as required.
3.4.21 Eskom may appoint any organisation it prefers to perform quality assurance and quality
control activities, either in the capacity as an AIA or inspection agency, on the works
contracted to the supplier, and the supplier or its sub-suppliers may not object, prevent,
hinder, undermine, circumvent, question, discredit, or in any way make it impossible for such
organisation to carry out its work on behalf of Eskom.
3.4.22 The Eskom template for QCP/ ITP provided shall be used as guideline, where the supplier
does not have a QCP/ ITP template.
3.5 Pre-Contract Award: Quality Requirement
3.5.1 Main Supplier and Sub-supplier Categories
Eskom supplier quality requirements for all existing and potential suppliers and sub-suppliers are
classified into four categories (category 1, 2, 3 and 4). Suppliers must prepare and submit quality
documentation as per the tender selected category (indicated in Form A) using the list of tender
returnables document.
NOTE: Only one (1) category must be applicable per procurement process e.g. [Eskom requests for
information (RFI)/ requests for quotation (RFQ)/ requests for proposal (RFP), including contracts for
the procurement of products and services].
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The following are the minimum returnable documentation for Categories 1 to 4:
3.5.2 Category 1: Quality Requirements
The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
The supplier shall submit a valid copy of ISO 9001 or any applicable certificate of a QMS (the
latest applicable revision). The QMS should drive the supplier’s business management
processes to ensure that all of Eskom’s requirements are fully met on a consistent basis.
The supplier shall submit the latest copy of the management system internal and external
audit reports. The audit reports must include, if applicable, nonconformity identified, and the
resulting remedial actions (correction and/ or corrective action reports).
The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
Where applicable; the supplier shall submit a draft, or an example of an inspection and test
plan (ITP) or quality control plan (QCP) on similar and/ or previous work done.
The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
The supplier shall submit documented information retained (records) of management review
meetings that include agenda, meeting minutes, attendance registers, reports, presentations,
etc.
Note: specific requirements per tender will be selected using the List of Tender Returnable
documents (240-12248652).
3.5.3 Category 2: Quality Requirements
The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
The supplier shall submit objective evidence of a developed, implemented and maintained QMS
that complies with ISO 9001 or any applicable standard of quality management system (the latest
applicable revision). The following documents (approved/ signed copies) shall be submitted:
Quality Management System manual or a documented information that have defines and
describes the QMS and its scope
Quality Policy, aligned with the supplier’s strategic direction (documented information)
Quality Objectives (documented information)
Control of documented information (both maintain and retain documented information )
Internal audit procedure (documented information)
Control of nonconforming outputs (documented information)
Nonconformity and Corrective action procedure (documented information)
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The QMS should drive all the supplier’s business management processes to ensure that all of
Eskom’s requirements are fully met on a consistent basis.
The supplier shall submit the latest copy of the management system internal audit reports. The
audit reports must include, if applicable, nonconformity identified, and the resulting remedial
actions (correction and/ or corrective action reports).
The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
Where applicable; the supplier shall submit an example of inspection and test plan (ITP) or
quality control plan (QCP) on similar or previous work done.
The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
The supplier shall submit documented information retained (records) of management review
meetings that include agenda, meeting minutes, attendance registers, reports, presentations,
etc.
Note: specific requirements per tender will be selected using the List of Tender Returnable
document (240-12248652).
3.5.4 Category 3: Quality Requirements
The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
The supplier shall submit objective evidence of a developed QMS that complies with ISO 9001
(or the latest applicable revision). The following documented information (approved/ signed
copies) shall be submitted:
o Quality management system manual or a (documented information) that have
defines and describes the QMS and its scope
o Quality Policy, aligned with the supplier’s strategic direction (documented
information)
o Quality Objectives (documented information)
o Control of documented information (both maintain and retain documented
information )
o Internal audit procedure (documented information)
o Control of nonconforming outputs (documented information)
o Nonconformity and Corrective action procedure (documented information)
The QMS should drive all the supplier’s business management processes to ensure that all of
Eskom’s requirements are fully met on a consistent basis.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
Where applicable; the supplier shall submit an example inspection and test plan (ITP) or
quality control plan (QCP).
The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
NB: specific requirements per tender will be selected using the List of Tender Returnables
document (240-12248652).
3.5.5 Category 4: Quality Requirements
The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
The supplier shall submit a quality method statement based on ISO 9001 and specific to the
scope of work.
The quality method statement should address all the supplier’s business management
processes to ensure that all of Eskom’s requirements are fully met on a consistent basis.
The supplier shall submit a signed/ approved quality policy (aligned with the supplier’s strategic
direction). (documented information)
The supplier shall submit a copy of quality objectives. (documented information)
The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
The supplier shall submit a copy of the documented information for roles, responsibilities and
authorities, specific to the project/ scope of work/ technical requirements. Examples of relevant
documented information are; organization charts, job descriptions, work instructions, duty
statements, manuals, procedures.
Note: specific requirements per tender will be selected using the List of Tender Returnables
document (240-12248652).
3.6 Main Supplier and Sub-supplier Capability and Capacity Assessment
Supplier capability and capacity assessments shall be performed prior to contract award on potential
suppliers participating in Eskom Holdings procurement process to:
provide products and services with high risk to operational sustainability
work on critical plant and equipment
supply of critical plant items or components
provide special processes
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
All sub-suppliers used by the main supplier/ contractor, performing work on Eskom critical plant
equipment, supplying commodities and providing specialised services shall be subjected to the
capability and capacity assessment.
Critical plant includes the following:
Generation Level 1 & 2 plant
Transmission and Distribution Power Plant & Control Plant
Mega Projects
All potential quality risks identified will be included in the assessment report provided for the tender
evaluation.
Note: Form A (Enquiry/ Contract/ Quality Requirements for Supplier Quality Management:
Specification 240-105658000/ QM 58 and ISO 9001) will be used to select and indicate whether
capability and capacity assessment will be conducted.
3.7 Post-Contract Award
3.7.1 Contract Execution
The supplier shall submit the following documents within 30 days or as per stated timeline after the
contract date, prior to the commencement of work, for acceptance by Eskom:
The supplier shall complete a QCP before contract award. This shall be reviewed and
signed off by Eskom within 30 days or as per stated timeline after contract award.
The supplier shall complete a quality control plan and ITP(s) for review and acceptance by
Eskom prior to the commencement of any work, inclusive of subcontracted work, within 30
days or as per stated timeline after contract award.
The sub-supplier QCP/ ITP shall be submitted for review and comment by the supplier and
by Eskom within 30 days or as per stated timeline after the award of the tender. All supplier
and Eskom comments shall be resolved prior to commencing work.
The equipment lists and an indication of pressurised components and systems.
Note: These plans are to be compiled in line with Eskom’s requirements and will have to be
discussed with, and approved by, Eskom prior to any work commencing.
Correspondence shall be directed to the project manager, and periodic quality review
meetings shall be convened by Eskom with the supplier.
The mandatory quality review meetings are to be convened by the nominated project quality
manager or his/her representative for the contract.
Monthly quality performance and management reports are to be prepared by the supplier
during contract execution. The content of these reports shall be agreed by Eskom when
submitted to Eskom on a monthly basis.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.7.2 Supplier Quality Performance Monitoring Phase
During the contract execution phase, suppliers shall be monitored by Eskom for performance on
quality-related aspects.
The outcomes of such monitoring will enable Eskom to take any appropriate actions pertaining to
the supplier.
The monitoring shall be carried out periodically by Eskom or at predetermined intervals during the
execution of a contract using agreed key performance indicators. The monitored key performance
areas include the following:
CQP and QCP /ITP
Delivery
Design
Cost
Management system
Subsequent key performance indicators associated with these areas will include the following:
Nonconformity monitoring
Audit and assessment evaluation scoring
Management system compliance and accreditation
Achievement of delivery targets as per contractual agreements
Process improvements
Correction and corrective action response and closure
3.7.3 Supplier Quality Audit
3.7.3.1 Quality audits and related quality performance reviews are intended to provide an objective
evaluation of compliance with performance expectations defined in this specification, in the
supplier contract quality plan (CQP), and in any other project scope of work specification.
3.7.3.2 Quality audits and related quality performance reviews include, but are not limited to, any
quality or other project functional area audits, assessments, verification of compliance
reviews, surveillance, inspections, or other interim or final assessments of scope of work
deliverables provided by the supplier or sub-suppliers
3.7.3.3 Quality audits and related quality performance reviews are intended to provide an objective
evaluation of compliance with performance expectations defined in this specification, in the
supplier contract quality plan (CQP), and in any other project scope of work specification.
3.7.3.4 Quality audits and related quality performance reviews include, but are not limited to, any
quality or other project functional area audits, assessments, verification of compliance
reviews, surveillance, inspections, or other interim or final assessments of scope of work
deliverables provided by the supplier or sub-suppliers.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.7.3.5 Quality audits and related quality performance reviews shall be carried out by trained,
accredited, and experienced personnel in accordance with procedures documented in the
Cqp.
3.7.3.6 The supplier shall submit, for Eskom review, documented processes for conducting project
scope of work quality audits and related quality performance reviews. Supplier quality audits
and related quality performance review processes shall be designed to address evaluation
of progress towards completion of project functional area deliverables as well as final
deliverable quality.
3.7.3.7 The supplier shall provide a schedule of anticipated quality audits covering all functional
areas and related quality performance reviews at the time of first post-contract award CQP
submission.
3.8 Standard Conditions
3.8.1 Rights of Access
Eskom:
3.8.1.1 shall be granted electronic and hard-copy access to all quality plans, procedures,
documentation, and other quality records relating to the work, including, but not limited to,
data extracts;
3.8.1.2 reserves the right to review, inspect, and audit any or all parts of the supplier’s QMS, as well
as any documentation, materials, or equipment associated with the work, at any time or
project work location; and
3.8.1.3 reserves the right to carry out assessments and audits on all new suppliers and sub-
suppliers.
The supplier:
3.8.1.4 shall support Eskom’s effort to monitor, verify, and/or witness any activities associated with
the work at any time;
3.8.1.5 shall cooperate with Eskom requests for documentation, records, and inspection and
witnessing. Eskom participation in audits, appraisals, assessment of plans, and verification
shall be conducted at no extra cost to Eskom;
3.8.1.6 shall ensure that a sub-supplier provides access to Eskom to all work procedures, records,
and supporting documentation through provision of access to view and photocopy, as
required, to support verification of scope of work requirements. Access shall include the
ability to photograph Eskom equipment, systems, system components, materials, etc.;
3.8.1.7 shall provide access to all quality-related information pertaining to activities performed by
itself or sub-suppliers, where Eskom might not have participated in the witnessing of their
quality assurance or control (this refers to inspections, audits, etc. performed by the supplier
on its own sub-suppliers);
3.8.1.8 shall allow Eskom to assess, audit, approve, or reject any sub-suppliers employed by
Eskom’s suppliers to assist with the product and/or service delivery to Eskom; and
3.8.1.9 shall ensure that the above requirements flow down to sub-suppliers.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.2 Eskom Rights to Information
3.8.2.1 To expect that the works will be conducted in accordance with the contract between the
parties.
3.8.2.2 To have access to the supplier’s information as determined by applicable legislation.
3.8.2.3 Eskom reserves the right to oversee the supplier’s audit programmes by participating in
selected audits as an observer and by assessing the supplier during key work stages.
Eskom will coordinate with the supplier to develop an oversight schedule aligned with the
supplier’s audit schedule.
3.8.2.4 To obtain access to any audit reports of audits performed by the supplier reflected in the
audit programme.
3.8.2.5 To conduct independent quality audits during all phases of the contract, and the supplier
shall provide all resources to support these activities.
3.8.2.6 Eskom shall have the right to participate in, or request that, a technical investigation be
launched and conducted at the supplier’s and sub-suppliers’ premises or other sites when
risk to Eskom products or service deliverables is identified.
3.8.2.7 To participate in, and/or lead, investigations related to incidents involving its products.
3.8.2.8 To require from suppliers to be responsible for the cost of re-inspections.
3.8.2.9 To withhold payment from suppliers as a result of outstanding nonconformities, irrespective
of the agreed payment schedule and in accordance with the conditions of contract.
3.8.2.10 Shall be granted electronic and hard-copy access to all quality plans, procedures,
documentation, and other quality records relating to the work, including, but not limited to,
data extracts.
3.8.2.11 Reserves the right to review, inspect, and audit any or all parts of the supplier’s QMS, as
well as any documentation, materials, or equipment associated with the work, at any time or
project work location.
3.8.2.12 Shall carry out assessments and audits on all new suppliers and sub-suppliers.
3.8.2.13 Reserves the right to appoint resident quality inspectors who can be based at the supplier’s
or sub-supplier’s premises and on site where the work is being performed.
3.8.2.14 Reserves the right to select intervention points within all developed supplier QCPs/ ITPs
for Eskom oversight of selected functions and to perform surveillance or audits of the work.
3.8.2.15 Shall be given access at all reasonable times before, during, and after manufacture and
before delivery, construction, erection, and commissioning to measure, test, and inspect the
products and workmanship, as necessary, at the supplier’s premises and at Eskom sites.
3.8.2.16 Reserves the right to suspend any pending deliveries by the issuing of a cease delivery
order at any time and for any portion of the work that is not being performed in accordance
with the specified/agreed requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3 Preservation
The supplier shall develop and implement a comprehensive preservation programme consisting of
plans, processes, procedures and actions undertaken for the purpose of planning for and
maintenance of material deliverables quality. The supplier preservation programme scope includes,
but is not limited to, the following:
3.8.3.1 Engagement of personnel suitably qualified for oversight of, and (as required) direct
implementation of, preservation programme requirements.
3.8.3.2 Development and implementation of preservation programme training appropriate to work
need.
3.8.3.3 Eskom may make use of its appointed service provider tasked to provide a full suite of
services encompassing an online monitoring system and asset tracking during, but not
limited to the following stages: inspections, testing, shipping, transportation, storage, and
commissioning. The supplier is to enable full access during all of these stages in order to
allow the installation of the devices on Eskom-identified products and equipment, which
include the sub-supplier’s testing facilities, processing plant, and any other processes
deemed important towards effective and efficient quality control.
3.8.3.4 Eskom seeks cooperation between the supplier’s designers and those of Eskom’s service
provider in ensuring seamless installation of the device and other associated installations.
Moreover, there is also a need to integrate data flows and systems between Eskom and the
supplier. Further details are included in the Eskom specifications and works information.
3.8.3.5 Review and tracking of compliance with Eskom and supplier engineering specification of
preservation requirements.
3.8.3.6 Review and tracking of compliance with sub-supplier provided preservation requirements
and recommendations.
3.8.3.7 Evaluation of prospective temporary and longer-term material storage sites for consistency
with preservation programme expectations.
3.8.3.8 Preservation work plan development and plan execution performance evaluation of all
parties engaged for provision of material transportation, handling, or storage services.
3.8.3.9 Oversight of material quality preservation plan preparation and plan execution performance
at all work locations.
3.8.3.10 Development of a preservation programme records management process, in compliance
with Eskom information management requirements, which comprehensively addresses
generation, maintenance, and ready access by Eskom to all preservation programme
records.
3.8.3.11 The supplier shall deploy a clearly defined documented programme providing for
identification of all physical asset pre-operation preservation of quality requirements. In this
reference, the term “physical assets” should be understood to include bulk materials,
including consumable items, equipment systems, system components, and any other
procured or supplied materials or equipment transferred to project control, but not deployed
for operational purposes.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3.12 Where the project responsibility for equipment and materials management has been
formally delegated, the supplier’s preservation programme shall ensure clear and
unambiguous communication of pre-operation preservation of goods quality requirements
to sub-suppliers.
3.8.3.13 The supplier’s preservation programme shall clearly and unambiguously document
processes and procedures for efficient and effective monitoring of compliance with
programme requirements.
3.8.3.14 Compliance monitoring shall commence with ensuring comprehensive consideration of
preservation requirements in the engineering instruction and subsequent inclusion of said
instruction in procurement documentation and shall be applicable until such time as
equipment or materials have been incorporated in an operating or operational system or
structure.
3.8.3.15 Compliance evaluation frequency shall anticipate transfer of tactical-level responsibility for
management of preservation responsibilities between project functional areas, for example,
procurement to logistics, logistics to fabrication, fabrication to logistics, logistics to
construction, etc., and shall, in similar fashion, anticipate transfer of support for tactical-level
responsibility between various subcontracted service providers.
3.8.3.16 Supplier engineering shall ensure that preservation requirements for scope of work
systems, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented and that preservation requirements are efficiently and
effectively communicated to project procurement, logistics, construction management,
quality, security, and other project functional areas, as required, for efficient and effective
implementation of preservation requirements. This shall take the form of a preservation
programme applicable to all systems, system components, equipment, materials, customer-
supplied materials, and other goods procured or managed under the scope of work.
3.8.3.17 The supplier’s preservation management programme shall clearly and unambiguously
address temporary, long-term, and in-transit preservation requirements, including, but not
limited to:
requirements for protection against, or insulation from, atmospheric conditions,
sunlight, temperature, soil, dust, humidity, salt spray, corrosive atmospheres, or
other physical environment conditions;
detailed procedures for application, use, monitoring, and maintenance of coatings,
coverings, fasteners, lines, and other components for internal and external weather
proofing;
requirements for electrical grounding or isolation;
requirements for internal or external environment creation, for example, inert gas
charging, heating, cooling, etc., inclusive of gas storage, electric power supply, etc.;
detailed procedures for initial set-up, charging, activation, and maintenance of
internal atmosphere generation, regeneration, monitoring, and relieving systems, for
example, inert gas management systems;
requirements for protection against, or insulation from, vibration or long-period
cyclical motion in transit, for example, wave-generated movement during sea
transport;
internal and external structural integrity protection, for example, internal and external
bracing, padding, framing, chocking, etc.;
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
support structure requirements, for example, stools, pads, or other devices,
substrates, or support required to ensure in-storage and in-transit stability of
systems, system components, equipment, and material, or other discrete units or
items;
provision for physical separation and/or barriers to prevent airborne or direct
transmittal of contaminants between work areas or between work areas and storage
areas, for example, prevention of carbon steel grinding or cutting debris impact on
stainless steel elements, airborne drift of blast aggregate into vessels or machinery,
etc.;
provision for, and final disposition of, temporary and longer-term storage or transit
required supports and related binding devices, for example, stools, stands, sea
fasteners, platforms, chocks, spacers, cabling, etc.;
provision of requirements for temporary work platforms or other support structures
required to ensure provision of preservation services, for example, provision of a
self-elevating work platform for periodic access to elevated fittings, gauges, man-
ways, etc.;
requirements for protection against, or insulation from, contact with other objects, for
example, padding or other protection for external tubing, fittings, or other impact-
sensitive structures or components;
clear physical delineation of temporary and longer-term storage areas supplemented
by hard and soft barriers, as required, to maintain a protective perimeter;
documented agreements with storage facility and transportation provider
management regarding security management, including, but not limited to, facility
access and egress control and control of access to project goods and materials
within facility boundaries or aboard vehicles or vessels; and
detailed procedures for inspection and testing to verify performance of preservation
procedures and to provide for timely notice and corrective action to maintain
preservation status.
3.8.3.18 The supplier’s preservation management programme scope shall encompass
management of preservation requirements, from initial transfer of ownership or management
responsibility to project scope of responsibility, through any period of temporary or longer-
term storage and through any period of transit, including transit for final delivery at point of
active use or installation.
3.8.3.19 The supplier’s preservation management programme shall clearly and unambiguously
address processes and procedures to ensure that storage and control of materials are
accomplished in accordance with manufacturer recommendations, specifications, and
project-specific requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3.20 The supplier’s preservation management programme shall incorporate special precautions
to address preservation and control of valves, electrical motors and components,
mechanical and rotating equipment, piping and fittings, instrumentation, flange faces,
gaskets, coatings, insulation, and other materials. Special precautions include, but are not
limited to, supplier-specified maintenance procedures related to engines, electric motors,
pumps, compressors, etc., such as periodic shaft rotation, engine turnover, lubrication, etc.
3.8.3.21 The supplier shall ensure that clear and unambiguous requirements for preservation of the
system, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented in purchase orders, work authorisations, and other
communications between the supplier and sub-suppliers.
3.8.3.22 Where sub-supplier expertise is utilised in determination of the preservation protocol,
supplier procurement processes shall ensure clear and unambiguous documentation of sub-
supplier input into preservation management programme requirements.
3.8.3.23 Supplier procurement shall ensure that preservation requirements for scope of work
systems, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented and that preservation requirements are efficiently and
effectively communicated to project logistics, construction management, quality, security,
and other project functional areas, as required, for efficient and effective implementation of
preservation requirements.
3.8.3.24 The supplier shall ensure comprehensive, clear, and unambiguous designation of sub-
supplier responsibility for execution of all preservation management programme elements,
including, but not limited to, all systems, processes, procedures, methods, ready access to
records, and provision of equipment, tools, or services essential to efficient and effective
execution of the preservation management programme.
3.8.3.25 The supplier shall ensure that preservation management programme responsibilities are
clearly and unambiguously defined within the project team and efficiently and effectively
implemented at all project scope of work locations. Inclusion of supplier and sub-supplier
scope of work in the development and implementation of a preservation management
programme shall be considered essential to efficient and effective preservation
management programme execution.
3.8.3.26 The supplier shall ensure clear and unambiguous designation of project team responsibility
for oversight and management of preservation management programme elements during
every stage of project development.
3.8.3.27 The supplier shall ensure that Eskom has free and unrestricted access to all preservation
records for inspection and audit.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.4 Quality Audits Related Conditions
3.8.4.1 The supplier shall maintain an accurate quality audit and related quality performance review
schedule and shall incorporate the current schedule as an attachment to the supplier CQP.
3.8.4.2 The supplier’s quality audit and related quality performance review schedule development
process shall be designed to incorporate consideration of information generated by
previously conducted audits and reviews, by input from project risk management evaluations
(risk register), or from Eskom or sub-supplier subject matter expertise.
3.8.4.3 Eskom reserves the right to oversee supplier audit programmes by participating in selected
audits as an observer and by assessing the supplier during key work stages. Eskom will
coordinate with the supplier to develop an oversight schedule aligned with the supplier’s
audit schedule.
3.8.4.4 Eskom will have the right to obtain access to any audit reports of audits performed by the
supplier reflected in the audit programme.
3.8.4.5 Eskom reserves the right to conduct independent quality audits, scheduled and
unscheduled, during all phases of the contract. The supplier shall provide all resources to
support these activities.
3.8.4.6 Eskom shall be given access at all reasonable times before, during, and after manufacture
and before delivery, construction, erection, and commissioning to measure, test, and inspect
the products and workmanship, as necessary, at the supplier’s premises and at Eskom sites.
3.8.4.7 The supplier shall obtain access for Eskom to measure, test, witness tests, and inspect
products that are being manufactured by any sub-supplier. This includes surveillances.
3.8.4.8 The assessments and audits shall be carried out on all new suppliers and their sub-
suppliers.
3.8.4.9 Eskom shall have the right to participate in, or request that, a technical investigation be
launched and conducted at the supplier’s and sub-suppliers’ premises or other sites when
risk to Eskom products or service deliverables is identified.
3.8.4.10 Qualification requirements for supplier and sub-supplier personnel engaged in conducting
quality audits and related quality performance reviews shall be defined in the supplier CQP
and shall be in compliance with the Project Quality Personnel Qualification Specification.
3.8.5 Management of Nonconformities and Nonconforming Outputs Identified by Eskom
3.8.5.1 Nonconformity reports raised by Eskom and issued against the supplier shall be investigated
by the supplier as a matter of urgency in order to determine the root cause, corrective action
measures, as required, with implementation time frames.
3.8.5.2 A formal response shall be prepared in respect of the defined criteria and submitted to
Eskom for its review, evaluation, and acceptance, within a maximum of 14 calendar days
from the date of issue of the nonconformity and should be aligned with the site
requirements/procedure.
3.8.5.3 Eskom may, at its discretion, request a response sooner and, in any case, before the
supplier proceeding with any pending/further intervention or corrective action, as may be
required by Eskom.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.5.4 Should Eskom or its inspection authority/agency identify any nonconforming products during
the conduct of its audits/surveillances/inspections, the supplier shall be deemed to be in
breach of contract and shall be held liable for any repair, rework, and/or associated
replacement costs. The supplier may, in such instances, also be held liable for the full costs
associated with the conducting of follow-up audits/surveillances/inspections.
3.8.5.5 The nature, magnitude, and/or frequency of nonconformity and inspection defect/rejection
reports raised by Eskom or its appointed inspection authority/agency shall form the basis of
any action to rescind/withdraw the supplier’s qualification status.
3.8.5.6 Nonconforming outputs identified by Eskom shall be documented via a NC Report and
issued to the suppliers via the contract communication protocol. The suppliers shall
investigate the matter and respond in writing to Eskom of disposition within the stated
contractual conditions.
Note: The dates for the disposition should align to contractual conditions.
3.8.5.7 Eskom shall identify repeat deficiencies as systematic failures of the supplier’s QMS and
shall notify the supplier of the trends. Eskom can initiate an internal audit to highlight the
system failures. The supplier with raise a Corrective Action Report and undertake Root
Cause Analysis. In such cases, QMS rectification and/ or update measures shall be taken
immediately.
3.8.5.8 Should the Supplier fail to respond and rectify nonconforming products within stipulated
contractual conditions. The Project Manager should apply contractual remedies in
accordance with Fidic/ NEC contract.
3.8.5.9 Repeated Nonconformities; if there are any identified repeat nonconformities from the same
supplier within a period of 6 months or less. This must then be escalated to the management
review committees of the BU/ OU/ Cluster/ or Divisions for adjudication. If not resolved, then
the matter must be escalated to the supplier review committee for recommendation.
3.8.6 Special Processes
The following requirements shall be applicable as well as additional requirements as specified in the
scope of work for the provision of the following special process services:
3.8.6.1 The supplier shall ensure that all processes which require that procedures be pre-qualified
or work methods and operators tested and qualified are controlled and all steps followed
before the work can commence.
3.8.6.2 This typically covers such activities as welding, non-destructive testing, special fabrication
techniques, coating, painting, etc.
3.8.6.3 All special processes (procedures and processes) shall be submitted for review and
acceptance by Eskom, accredited or certified agency. No work shall commence until these
are accepted.
3.8.6.4 Where applicable, a relevant Management System for the special process shall be certified
or approved by an accredited body and proof of certification shall be submitted to Eskom for
review. An example for this will be the Welding Management System based on ISO 3834.
3.8.6.5 Where samples are required for acceptance, these shall be submitted to Eskom for review
and acceptance.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.6.6 The supplier shall ensure that all operators are suitably qualified for these processes in
accordance with the procedures, processes and/ or applicable standards/ codes.
3.8.6.7 The records of qualification of procedures, processes and operators shall be maintained by
the supplier in accordance with the applicable procedure or code and these made available
to Eskom at all times.
This document has been seen and accepted by:
Name Designation
Kerseri Pather General Manager: Risk and Sustainability
Lenock Meyer Acting Senior Manager: Quality Management
Pamela Dondashe Middle Manager: Quality Assurance
Mandla Mkhwanazi Middle Manager: SHEQ Procurement and Supply Chain Management
Suzette Manthe Senior Advisor: Quality Performance and Planning
Lorna Ndlela Middle Manager: Eskom Document and Records Management
Date Rev. Compiler Remarks
October 2021 3 SA Sambo Specification was due for revision and in addition, to
align the requirements with the latest Eskom business
processes and systems.
October 2018 2 SA Sambo Specification reviewed to be aligned with the
requirements of ISO 9001:2015
March 2016 1 SA Sambo Specification was due for revision and also to
repackage the requirements and tender returnable
documents into four categories.
December 2011 0 A Hunter New document
The following people were involved in the development of this document:
Andrew Else
Bongi Tshabalala
Feziwe Mogamisi
Lesego Garegae
Patrick Thwane
Xolani Zuma
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Eskom Operational Quality Forum Members
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Evaluation Criteria
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Primary eligibility is contingent on the supplier's ability to meet the stringent quality management criteria. There is no explicit financial or experience threshold stated in the provided excerpt. However, eligibility is effectively determined by: 1) Possession of a QMS conforming to ISO 9001 (certification required for Category 1, documented evidence for others). 2) Willingness to submit all required tender returnables as specified in the 'List of Tender Returnables' document (240-12248652) for the applicable Category. 3) Acceptance of Eskom's standard conditions, including rights of access, information, and audit. 4) Capability to manage sub-suppliers in line with Eskom's requirements. Suppliers must complete and sign 'Form A' to acknowledge these requirements.
Section
Source: 240-105658000 Supplier Quality Management Specification (3).pdfSupplier Quality Management: Specification Unique Identifier: 240-105658000
The intention of this specification is to specify and describe the minimum quality requirements for all
existing and potential Eskom suppliers and define the quality criteria for the selection, evaluation,
implementation, and maintenance of a quality management system (QMS) that conforms to the
a quality management system (QMS) based on ISO 9001, which should form the basis for conformity
to Eskom quality requirements and continually adhere to them throughout the duration of a contract
[1] ISO 9001 Quality Management Systems – Requirements
[2] ISO 10005 Quality Management Systems – Guidelines for Quality Plans.
[3] ISO 9000 Quality Management Systems – Fundamentals and Vocabulary
[4] 32-727: Safety, Health, Environment, and Quality (SHEQ) Policy
[5] ISO 10006 Quality Management Systems – Guidelines for Quality Management in Projects
[6] ISO 9004 Quality Management – Quality of an Organisation – Guidance to Achieve Sustained
[9] PPPFA: Preferential Procurement Policy Framework Act, 2000 (Act No. )
[10] CIDB 1004: Best Practice Guideline A4: Evaluating Quality in Tender Submissions
[11] 240-12248652 Supplier Quality Management: List of Tender Returnables
2.3.2 Contract Quality Plan: a document of the supplier’s process for delivering the level of quality
required by the contract. It is a framework for the contractor’s process for delivering quality.
2.3.3 Hold Point: a predetermined stage in the quality control plan (QCP) beyond which work/
2.3.4 Intervention Points: those control points indicated by the various controlling bodies
inspection, hold points, surveillances, witnesses, reviews and verifications.
performing quality assurance/ quality control, monitoring, inspection and/ or expediting
Title: Supplier Quality Management: Document Identifier: 240-105658000
Functional Area: Quality Management
Quality Quality Manager Quality Risk and
Description
Source: 37-2 agreement form.docxThe tender is for the supply and delivery of sodium bicarbonate for DSI FGD Phase 2 testing at Majuba and Lethabo Power Stations for a period of three months.
Evaluation Criteria
Source: 37-2 agreement form.docx (unknown)Must be registered employer under OHS Act; must have authority to sign binding agreements; must accept SHE specifications as part of contractual obligations.
Technical Specifications
Source: 37-2 agreement form.docx (unknown)The tender is for the supply and delivery of sodium bicarbonate for DSI FGD Phase 2 testing at Majuba and Lethabo Power Stations for a period of three months.
Compliance Requirements
Source: 37-2 agreement form.docx (unknown)The bidder must sign a Section 37(2) Agreement under the Occupational Health and Safety Act, 1993 (Act 85 of 1993). This agreement confirms the bidder is an employer with duties under the Act and must comply with provided SHE specifications.
Description
Source: OHS Evaluation.docxScope: Supply and delivery of sodium bicarbonate for DSI FGD Phase 2 testing at Majuba and Lethabo Power Stations for a period of three (3) months.
Submission Guidelines
Source: OHS Evaluation.docx (unknown)Returnable Documents:
Evaluation Criteria
Source: OHS Evaluation.docx (unknown)Must demonstrate strong OHS compliance through documented systems and policies. Must have valid Letter of Good Standing (COIDA or equivalent). OHS policy must be signed by CEO and legally compliant. Must submit all required OHS documentation as per tender returnables list.
Compliance Requirements
Source: OHS Evaluation.docx (unknown)No specific requirements found
Submission Guidelines
Source: 240-126469599_Method Statement template final 18 Oct2021.docx (unknown)Returnable Documents: The document indicates a method statement template must be completed. Prepare a detailed method statement addressing: scope of work, objectives, customer focus, competency and training requirements, PPE, tools and equipment, leadership and values, risk management, process improvement, data analysis, and relationship management.
Evaluation Criteria
Source: 240-126469599_Method Statement template final 18 Oct2021.docx (unknown)Suppliers must demonstrate capability to meet the technical and managerial requirements outlined in the method statement, including relevant experience, competent personnel, appropriate infrastructure, and robust quality and risk management systems. Compliance with the detailed response format and submission by the closing date (August 14, 2026) is mandatory.
Technical Specifications
Source: 240-126469599_Method Statement template final 18 Oct2021.docx (unknown)The tender requires supply and delivery of sodium bicarbonate for DSI FGD Phase 2 testing at Majuba and Lethabo Power Stations for three months. The method statement template outlines detailed requirements: scope of work as per contract, SMART objectives, customer needs identification, human resources and training, PPE, tools and equipment, organizational mission/vision/values, risk management, process improvement, data analysis, and stakeholder/outsourcing management.
Important Dates
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdf (TENDER)Briefing Session
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdf (TENDER)Contact Information
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdf (TENDER)Submission Guidelines
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdf (TENDER)Returnable Documents
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdf (TENDER)Evaluation Criteria
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdf (TENDER)Tenderers must meet eligibility criteria: must not be from a country on international sanctions lists; must not submit more than one tender (except for system size limits); JV/consortium must have joint and several liability; must have no conflict of interest; must be signed by authorized persons; must not be restricted by National Treasury or on Tender Defaulters list; cannot subcontract 100% of the Scope of Work. Tenderers must not be under any restriction to do business with Eskom or State-Owned Companies.
Technical Specifications
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdf (TENDER)Quality Management
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdfPricing Schedule
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdfFinancial Requirements
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdf (TENDER)Compliance Requirements
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdf (TENDER)B-BBEE Requirements
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdf (TENDER)Health & Safety
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdfEnvironmental
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdf (TENDER)Contractual Terms
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdfRequirements
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdf (TENDER)Section
Source: E3286CXMWP_Invitation to Tender (ITT)_Sodium bicarbonate for DSI FGD Phase 2 testing at Majuba & Lethabo Power Stations_23 July 2026.pdfDescription
Source: 20260224_Sodium Bicarbonate _240-68099512 Form A_Cat 4_ Rev 9.docxContact Information
Source: 20260224_Sodium Bicarbonate _240-68099512 Form A_Cat 4_ Rev 9.docx (unknown)Submission Guidelines
Source: 20260224_Sodium Bicarbonate _240-68099512 Form A_Cat 4_ Rev 9.docx (unknown)Evaluation Criteria
Source: 20260224_Sodium Bicarbonate _240-68099512 Form A_Cat 4_ Rev 9.docx (unknown)Suppliers must have ISO 9001 certified quality management system. Must comply with Category 4 requirements of Eskom specification 240-105658000. Must have capability and capacity to supply sodium bicarbonate meeting technical specifications. Must accept Eskom's quality representative oversight and monitoring requirements. Must provide designated quality representative for contract execution.
Technical Specifications
Source: 20260224_Sodium Bicarbonate _240-68099512 Form A_Cat 4_ Rev 9.docx (unknown)Compliance Requirements
Source: 20260224_Sodium Bicarbonate _240-68099512 Form A_Cat 4_ Rev 9.docx (unknown)Description
Source: Acknowledgement Form for Eskom SHE Rules and other Requirements (1).docxThe supply and delivery of sodium bicarbonate for DSI FGD phase 2 testing at Majuba and Lethabo power stations for a period of three months.
Submission Guidelines
Source: Acknowledgement Form for Eskom SHE Rules and other Requirements (1).docx (unknown)The supplier/contractor/tenderer must submit the required documents, including the acknowledgement form for Eskom OHS legal and other requirements. Returnable documents include the signed acknowledgement form.
Evaluation Criteria
Source: Acknowledgement Form for Eskom SHE Rules and other Requirements (1).docx (unknown)Suppliers must have OHS management systems aligned with Eskom requirements, ability to manage subcontractors, previous experience in similar work (verifiable through references), and authorized signatory at CEO/Director/Managing Director level.
Technical Specifications
Source: Acknowledgement Form for Eskom SHE Rules and other Requirements (1).docx (unknown)The supplier/contractor/tenderer must comply with Eskom's OHS requirements, including the Eskom contractor Health and Safety requirements standards 32-136, OHS specification/requirements, Occupational Health and Safety Act 85 of 1993, and Compensation for Occupational Diseases and Illnesses Act 130 of 1993.
Compliance Requirements
Source: Acknowledgement Form for Eskom SHE Rules and other Requirements (1).docx (unknown)The supplier/contractor/tenderer must comply with Eskom's OHS requirements and ensure that all employees undergo the relevant Eskom induction and the company's induction. The main supplier is accountable for the management of its contractors/suppliers and must ensure that they comply with the applicable legal and Eskom requirements.
Submission Guidelines
Source: Acknowledgement Form Life-saving Rules.docx (unknown)Returnable Documents: The document does not specify submission details. Refer to the main tender document for submission address, deadline, and required forms.
Evaluation Criteria
Source: Acknowledgement Form Life-saving Rules.docx (unknown)Open to suppliers who can demonstrate understanding and implementation of Eskom's safety protocols. Must be willing to sign employee pledge forms and ensure all personnel comply with Life-Saving Rules Standard 240-62196227.
Technical Specifications
Source: Acknowledgement Form Life-saving Rules.docx (unknown)Scope: Supply and delivery of sodium bicarbonate for DSI FGD Phase 2 testing at Majuba and Lethabo Power Stations for three months.
Safety Requirements: All personnel must adhere to Eskom's Life-Saving Rules, which apply to contractors and anyone on site. A zero-tolerance stance is taken on violations.
Key Safety Rules:
Compliance: Adherence to safety rules is a condition for working on Eskom sites. Employees must sign a pledge to abide by the Life-Saving Rules (Standard 240-62196227).
Description
Source: E-tendering Help Manual for supplier - 27 January 2025 (1).docxeTendering system is a web-based system that allows suppliers bidding for various tenders advertised on Tender Bulletin system to “upload” their tender documents. Currently the tenderers or suppliers submit tender documents at various Eskom tender offices. eTendering system replaces the manual or physical submission of tender documents at various Eskom tender offices.
Submission Guidelines
Source: E-tendering Help Manual for supplier - 27 January 2025 (1).docx (unknown)To submit tender documents, click on “Add file” button and upload required tender documents. Give the file a name, select the listed file type, choose the file to upload, and then click on “Upload” button. Verify all required documents are uploaded before making ‘Final Submission’ by clicking on ‘Finalize Submission’ button. A file size cannot exceed 50MB and a total size of all uploaded files should not exceed 900MB.
Evaluation Criteria
Source: E-tendering Help Manual for supplier - 27 January 2025 (1).docx (unknown)Must have a Central Supplier Database (CSD) number. Must be registered on the eTendering system. Must comply with electronic submission procedures. For the specific tender, likely requires capability to supply sodium bicarbonate meeting technical specs (not detailed in this document) and deliver to specified power stations.
Technical Specifications
Source: E-tendering Help Manual for supplier - 27 January 2025 (1).docx (unknown)eTendering system is a web-based system that allows suppliers bidding for various tenders advertised on Tender Bulletin system to “upload” their tender documents. Currently the tenderers or suppliers submit tender documents at various Eskom tender offices. eTendering system replaces the manual or physical submission of tender documents at various Eskom tender offices.
Description
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdfImportant Dates
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Contact Information
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Submission Guidelines
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Returnable Documents
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Evaluation Criteria
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Tenderer must meet eligibility criteria in Tender Data; not under restriction to do business with Eskom/state-owned companies; cannot subcontract 100% of scope; must be registered with CIDB if required (or capable of registration within 21 days); must provide proof of SHEQ systems; must submit valid B-BBEE documentation; must attend compulsory site visit/clarification meeting if required.
Experience & Qualifications
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Quality Management
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdfPricing Schedule
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdfFinancial Requirements
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Compliance Requirements
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Health & Safety
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdfContractual Terms
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdfRequirements
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Section
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdfDescription
Source: 20260224_Sodium Bicarbonate_List of Tender Returnables_Cat 4_ Rev 7_signed.pdfImportant Dates
Source: 20260224_Sodium Bicarbonate_List of Tender Returnables_Cat 4_ Rev 7_signed.pdf (unknown)Contact Information
Source: 20260224_Sodium Bicarbonate_List of Tender Returnables_Cat 4_ Rev 7_signed.pdf (unknown)Submission Guidelines
Source: 20260224_Sodium Bicarbonate_List of Tender Returnables_Cat 4_ Rev 7_signed.pdf (unknown)Evaluation Criteria
Source: 20260224_Sodium Bicarbonate_List of Tender Returnables_Cat 4_ Rev 7_signed.pdf (unknown)Suppliers must have a documented Quality Management System complying with ISO 9001:2015 (certification not mandatory but system must comply). Must provide evidence of QMS in operation including defined roles/responsibilities and external provider controls. All tender returnables must be submitted as per document requirements.
Technical Specifications
Source: 20260224_Sodium Bicarbonate_List of Tender Returnables_Cat 4_ Rev 7_signed.pdf (unknown)Quality Management
Source: 20260224_Sodium Bicarbonate_List of Tender Returnables_Cat 4_ Rev 7_signed.pdfCompliance Requirements
Source: 20260224_Sodium Bicarbonate_List of Tender Returnables_Cat 4_ Rev 7_signed.pdf (unknown)Section
Source: 20260224_Sodium Bicarbonate_List of Tender Returnables_Cat 4_ Rev 7_signed.pdfDescription
Source: Technical Evaluation Criteria - Sodium Bicarb for DSI FGD Phase 2.pdfThe tender is for a once-off purchase of Sodium Bicarbonate. Bidders must submit a Product Information Sheet (Certificate of Analysis, Test Report, or Data Sheet) to ensure compliance with technical specifications.
Submission Guidelines
Source: Technical Evaluation Criteria - Sodium Bicarb for DSI FGD Phase 2.pdf (unknown)Evaluation Criteria
Source: Technical Evaluation Criteria - Sodium Bicarb for DSI FGD Phase 2.pdf (unknown)To be eligible for evaluation, tenderers must: 1) Submit the mandatory Product Information Sheet; 2) Achieve a minimum weighted final score of 70% in the qualitative technical evaluation. Failure to meet either criterion results in disqualification. The evaluation uses a scoring system (5, 4, 2, or 0 points) per criterion, with points mapped to percentage weightings.
Technical Specifications
Source: Technical Evaluation Criteria - Sodium Bicarb for DSI FGD Phase 2.pdf (unknown)Methodology
Source: Technical Evaluation Criteria - Sodium Bicarb for DSI FGD Phase 2.pdfBidders must provide a detailed method statement covering procurement, transportation, and storage of the product from order placement to delivery.
Experience & Qualifications
Source: Technical Evaluation Criteria - Sodium Bicarb for DSI FGD Phase 2.pdfQuality Management
Source: Technical Evaluation Criteria - Sodium Bicarb for DSI FGD Phase 2.pdfCompliance Requirements
Source: Technical Evaluation Criteria - Sodium Bicarb for DSI FGD Phase 2.pdf (unknown)Health & Safety
Source: Technical Evaluation Criteria - Sodium Bicarb for DSI FGD Phase 2.pdfCompliance with technical specifications is mandatory. Evidence must be provided via a Certificate of Analysis, Test Report, or Data Sheet.
Contractual Terms
Source: Technical Evaluation Criteria - Sodium Bicarb for DSI FGD Phase 2.pdfRequirements
Source: Technical Evaluation Criteria - Sodium Bicarb for DSI FGD Phase 2.pdf (unknown)Section
Source: Technical Evaluation Criteria - Sodium Bicarb for DSI FGD Phase 2.pdfTechnical evaluation is conducted in two stages: Mandatory Technical Evaluation (Gatekeeper) and Qualitative Technical Evaluation. A minimum threshold of 70% is required to pass the qualitative stage.
Evaluation Criteria
Source: Tender Environmental Requirements - DSI FGD - Feb 2026 .pdf (unknown)Bidders must meet environmental requirements and provide all three environmental documents. Compliance is determined by meeting the specified environmental requirements; non-compliance results from failing to meet these requirements.
Important Dates
Source: NEC3 SSC3 - Supply and Delivery of Sodium Bicarbonate for DSI FGD Phase 2 Research Test.pdf (unknown)No specific dates mentioned in the document.
Contact Information
Source: NEC3 SSC3 - Supply and Delivery of Sodium Bicarbonate for DSI FGD Phase 2 Research Test.pdf (unknown)Mrs Prudence, [email protected], +27 11 516 7994
Submission Guidelines
Source: NEC3 SSC3 - Supply and Delivery of Sodium Bicarbonate for DSI FGD Phase 2 Research Test.pdf (unknown)The Supplier includes the following information on each tax invoice: Name and address of the Supplier, The contract number and title, Supplier’s VAT registration number, The Purchaser’s VAT registration number, The total of the Price for each lump sum item in the Price Schedule or Batch Order which the Supplier has completed, Other amounts to be paid to the Supplier, Less amounts to be paid by or retained from the Supplier, The invoiced amount - excluding VAT, the VAT and including VAT. Purchasers to be paid according to Eskom’s payment terms which is 30 days after receipt of valid tax invoice. Invoices to be delivered to Eskom’s Document Centres.
Evaluation Criteria
Source: NEC3 SSC3 - Supply and Delivery of Sodium Bicarbonate for DSI FGD Phase 2 Research Test.pdf (unknown)Supplier must complete all contract data sections including company details, pricing schedule, and percentage for overheads/profit. Must comply with South African law and Eskom's additional Z-clauses covering B-BBEE, ethics, insurance, nuclear liability, and asbestos handling. Must provide valid tax invoices with Eskom's VAT number (4740101508). No subcontracting without written consent. Must have ISO 9001-compliant Quality Management System.
Technical Specifications
Source: NEC3 SSC3 - Supply and Delivery of Sodium Bicarbonate for DSI FGD Phase 2 Research Test.pdf (unknown)The required product is 120 000 kg (120 tonnes) of Sodium Bicarbonate (NaHCO3), material no. 0775797, with the following specifications: Particle Size Distribution: 90% of particles should be less than 60 μm, with 50% less than 30 μm, Purity: Minimum 99% purity, Moisture Content: Less than 0.5%, Bulk Density: ≈ 68 lbs/ft3 (1.09 g/cm3).
Financial Requirements
Source: NEC3 SSC3 - Supply and Delivery of Sodium Bicarbonate for DSI FGD Phase 2 Research Test.pdf (unknown)Payment Terms: payment terms which is 30 days after receipt of valid tax invoice. Invoices to be delivered to Eskom’s Document Centres.
Compliance Requirements
Source: NEC3 SSC3 - Supply and Delivery of Sodium Bicarbonate for DSI FGD Phase 2 Research Test.pdf (unknown)The Supplier is required to submit an updated verification certificate and necessary supporting documentation confirming the change in his B-BBEE status to the Purchaser within thirty days of the notification or as otherwise instructed by the Purchaser.
Health & Safety
Source: NEC3 SSC3 - Supply and Delivery of Sodium Bicarbonate for DSI FGD Phase 2 Research Test.pdfThe Purchaser manages asbestos and ACM according to the Standard. In the event that any asbestos is identified while Providing the Services, a risk assessment is conducted and if so required, with reference to possible exposure to an airborne concentration of above the AL for asbestos, immediate control measures are implemented and relevant air monitoring conducted in order to declare the area safe.
Environmental
Source: NEC3 SSC3 - Supply and Delivery of Sodium Bicarbonate for DSI FGD Phase 2 Research Test.pdfEnvironmental requirements: The Purchaser manages asbestos and ACM according to the Standard.
Section
Source: NEC3 SSC3 - Supply and Delivery of Sodium Bicarbonate for DSI FGD Phase 2 Research Test.pdfThe Supplier shall operate under an ISO 9001-compliant Quality Management System. A Contract Quality Plan (CQP) and Inspection and Test Plan (ITP), aligned to this specification, shall be submitted with the tender. All quality documentation shall be submitted to the Purchaser prior to delivery and injection. The Purchaser reserves the right to audit quality records and procedures at any stage during the Contract.
Description
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025 (1).docxSubmission Guidelines
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025 (1).docx (unknown)Evaluation Criteria
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025 (1).docx (unknown)Suppliers must be registered on Eskom's e-tendering system and complete mandatory e-tendering training. Must provide valid business registration, contact details, and authorized signatory.
Technical Specifications
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025 (1).docx (unknown)Contact Information
Source: Practice-Guide-01-of-2018-Determining-Validity-of-a-B-BBEE-Certificate.pdf (unknown)Evaluation Criteria
Source: Practice-Guide-01-of-2018-Determining-Validity-of-a-B-BBEE-Certificate.pdf (unknown)Technical Specifications
Source: Practice-Guide-01-of-2018-Determining-Validity-of-a-B-BBEE-Certificate.pdf (unknown)Methodology
Source: Practice-Guide-01-of-2018-Determining-Validity-of-a-B-BBEE-Certificate.pdfCompliance Requirements
Source: Practice-Guide-01-of-2018-Determining-Validity-of-a-B-BBEE-Certificate.pdf (unknown)B-BBEE Requirements
Source: Practice-Guide-01-of-2018-Determining-Validity-of-a-B-BBEE-Certificate.pdf (unknown)Health & Safety
Source: Practice-Guide-01-of-2018-Determining-Validity-of-a-B-BBEE-Certificate.pdfContractual Terms
Source: Practice-Guide-01-of-2018-Determining-Validity-of-a-B-BBEE-Certificate.pdfSets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
MAJUBA AND LETHABO POWER STATIONS - Mpumalanga and Free State - Volksrust and Viljoensdrif - 2095
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
16
Last checked
24 Jul 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Manufacture of chemicals and chemical products. Unlock full pricing strategies, bid frequency, and historical win rates.