Tender Type
Request for Bid(Open-Tender)
Delivery Location
Ogies Bethal Road - Kriel - Kriel - 2271
Organization Type
GOVERNMENT
Published
14 Jul 2026
OCDS Reference
ocds-9t57fa-162304
ESKOM invites tenders for the refurbishment of the generator circuit breaker (gcb) compressor plant control circuit at kriel power station units 1 & 4, for a 12-month period. This tender is aimed at qualified electrical contractors with experience in mv and lv switchgear maintenance and project execution.
Date & Time
Friday, 07 August 2026 - 10:00
Venue
MS Teams /Site visit
Categories
Request for Bid(Open-Tender)
Ogies Bethal Road - Kriel - Kriel - 2271
14 Jul
2026
Tender Published
Tender was published
07 Aug
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
NEC GCB.pdf
Eskom seeks a contractor for a 12-month refurbishment project of the Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Kriel Power Station Units 1 & 4. The contract uses the NEC3 Engineering and Construction Contract (Option A) and involves replacing electrical panels, pressure switches, water traps, gauges, and cabling for two compressors (A & B) while maintaining operational pressure.
Median Estimate
R 264 960
Range
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
Learn how to submit a winning bid with these related articles
Your meticulously crafted General sector tender submission can be disqualified for a single, seemingly minor compliance oversight. The reality for South African contractors is that technical competence is no longer sufficient; it is underpinned by a non-negotiable framework of documentary compliance. This regulatory guide: mastering CSD and BBBEE compliance for general sector tenders in south africa provides a comprehensive, step-by-step breakdown of the mandatory registrations and certificates you must secure and present. We detail the precise requirements for CSD, BBBEE, SARS TCS, CIPC, and COIDA, explaining their function within the procurement ecosystem governed by the PFMA and PPPFA. Learn the actionable steps to prepare your business, avoid the most common disqualifying errors, and leverage technology to streamline your compliance process for successful bidding in 2026 and beyond.
Everything South African general contractors need to know about how to write a winning tender proposal without an in-house bid team in gauteng — covering CSD, BBBEE, step-by-step processes, common disqualification mistakes, and how Tenders-SA.org helps you find and win relevant contracts in Gauteng.
This definitive guide provides General sector contractors with the precise, actionable steps required to achieve and maintain CSD and BBBEE compliance for South African public tenders in 2026. Authored by Dr. Sarah Mokwena, a Legal Compliance Specialist, it meticulously walks through the regulatory framework, mandatory registrations, and the critical documentation needed to avoid disqualification. We dissect the common, costly errors made during submission and provide a clear checklist to ensure your bid is responsive and competitive. Learn how to navigate the Central Supplier Database, validate your BBBEE status, and integrate compliance into your tender preparation process.
A meticulous legal compliance guide for South African SMEs and General contractors navigating the 2026 procurement landscape. This case study-driven analysis provides a regulatory intelligence deep dive into the mandatory frameworks of CSD (Central Supplier Database), BBBEE (Broad-Based Black Economic Empowerment), SARS Tax Compliance, CIPC registration, and COIDA. It outlines the precise, actionable steps contractors must take to achieve compliance, highlights common disqualification pitfalls in tender submissions, and explains how integrated tools like Tenders-SA.org can streamline the process. The guide serves as an essential evergreen resource for any business seeking to compete effectively for public sector contracts in the General sector.
💡 Want more tendering tips and strategies?
Explore Our BlogAI Document Analysis Stages
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Review in progress
The information shown on this card is preliminary. Our procurement team is currently finalising the submission guidelines, evaluation criteria, technical specifications, financial requirements, and compliance sections so you have a clean, bid-ready summary to work from. Documents being finalised: CIDB Ann G Compulsory Enterprise Questionnaire_.pdf, 17. RT284 Annex C Local Content Declaration - Summary Schedule.pdf, 18. RT284 Annex D Imported Content Declaration.pdf and 2 more. You don’t need to refresh — this page will pick up the updated review automatically.
Important Dates
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown){"closingDate":"17 October 2021"}
Contact Information
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown){"name":null,"email":null,"phone":null,"department":"Supply Chain Management","address":null}
Evaluation Criteria
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Supplier Quality Management: Specification Unique Identifier: 240-105658000
The intention of this specification is to specify and describe the minimum quality requirements for all
existing and potential Eskom suppliers and define the quality criteria for the selection, evaluation,
implementation, and maintenance of a quality management system (QMS) that conforms to the
a quality management system (QMS) based on ISO 9001, which should form the basis for conformity
to Eskom quality requirements and continually adhere to them throughout the duration of a contract
[1] ISO 9001 Quality Management Systems – Requirements
[2] ISO 10005 Quality Management Systems – Guidelines for Quality Plans.
[3] ISO 9000 Quality Management Systems – Fundamentals and Vocabulary
[4] 32-727: Safety, Health, Environment, and Quality (SHEQ) Policy
[5] ISO 10006 Quality Management Systems – Guidelines for Quality Management in Projects
[6] ISO 9004 Quality Management – Quality of an Organisation – Guidance to Achieve Sustained
[9] PPPFA: Preferential Procurement Policy Framework Act, 2000 (Act No. )
[10] CIDB 1004: Best Practice Guideline A4: Evaluating Quality in Tender Submissions
[11] 240-12248652 Supplier Quality Management: List of Tender Returnables
2.3.2 Contract Quality Plan: a document of the supplier’s process for delivering the level of quality
required by the contract. It is a framework for the contractor’s process for delivering quality.
2.3.3 Hold Point: a predetermined stage in the quality control plan (QCP) beyond which work/
2.3.4 Intervention Points: those control points indicated by the various controlling bodies
inspection, hold points, surveillances, witnesses, reviews and verifications.
performing quality assurance/ quality control, monitoring, inspection and/ or expediting
Title: Supplier Quality Management: Document Identifier: 240-105658000
Functional Area: Quality Management
Quality Quality Manager Quality Risk and
Technical Specifications
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Title: Supplier Quality Management: Document Identifier: 240-105658000
Alternative Reference QM 58
Number:
Area of Applicability: Eskom Holdings SOC Ltd
Functional Area: Quality Management
Revision: 3
Total Pages: 28
Next Review Date: October 2024
Disclosure Controlled Disclosure
Classification:
Compiled by Supported by Functional Authorized by
Responsibility
SA Sambo P Dondashe L Meyer K Pather
Chief Advisor Middle Manager Acting Senior General Manager
Quality Quality Manager Quality Risk and
Management Management Management Sustainability
Date: 15/10/2021 Date: 15/10/2021 Date: 15/10/2021 Date: 17 October 2021
EDC TN Formatted 15.10.2021
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Content
. Introduction ............................................................................................................................... 3
2.1 Scope ............................................................................................................................... 3
2.1.1 Purpose ................................................................................................................. 3
2.1.2 Applicability ........................................................................................................... 3
2.1.3 Effective date ......................................................................................................... 3
2.2 Normative/Informative References ................................................................................... 3
2.2.1 Normative .............................................................................................................. 3
2.2.2 Informative............................................................................................................. 3
2.3 Definitions ........................................................................................................................ 4
2.4 Abbreviations ................................................................................................................... 5
2.5 Roles and Responsibilities ............................................................................................... 6
2.6 Process for Monitoring ...................................................................................................... 6
2.7 Related/Supporting Documents ........................................................................................ 6
3.1 Supplier and Sub-Supplier Quality Management System Requirements .......................... 7
3.2 Quality Plan ...................................................................................................................... 8
3.3 Contract Quality Plan........................................................................................................ 8
3.4 Quality Control Plan ....................................................................................................... 10
3.5 Pre-Contract Award: Quality Requirement ...................................................................... 13
3.6 Main Supplier and Sub-supplier Capability and Capacity Assessment ........................... 16
3.7 Post-Contract Award ...................................................................................................... 17
3.7.1 Contract Execution .............................................................................................. 17
3.7.2 Supplier Quality Performance Monitoring Phase ................................................. 18
3.7.3 Supplier Quality Audit .......................................................................................... 18
3.8 Standard Conditions ....................................................................................................... 19
3.8.1 Rights of Access .................................................................................................. 19
3.8.2 Eskom Rights to Information ................................................................................ 20
3.8.3 Preservation ........................................................................................................ 21
3.8.4 Quality Audits Related Conditions ....................................................................... 25
3.8.5 Management of Nonconformities and Nonconforming Outputs Identified by
Eskom ................................................................................................................. 25
3.8.6 Special Processes ............................................................................................... 26
Acceptance ............................................................................................................................. 27
Revisions ................................................................................................................................ 27
Development Team ................................................................................................................ 27
Acknowledgements ................................................................................................................ 28
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The intention of this specification is to specify and describe the minimum quality requirements for all
existing and potential Eskom suppliers and define the quality criteria for the selection, evaluation,
vendor registration, management, monitoring, assessment and auditing of suppliers. Eskom’s
position is to partner with suppliers who fully demonstrate commitment to the development,
implementation, and maintenance of a quality management system (QMS) that conforms to the
requirements of ISO 9001 standard. The priority is to encourage suppliers to continually improve
their QMS and enhance service delivery by implementing and conforming to the standard.
2.1 Scope
2.1.1 Purpose
The purpose of this specification is to outline the requirements according to which suppliers shall
develop,
implement,
maintain, and
continually improve
a quality management system (QMS) based on ISO 9001, which should form the basis for conformity
to Eskom quality requirements and continually adhere to them throughout the duration of a contract
2.1.2 Applicability
This specification shall apply throughout Eskom Holdings Limited divisions, its subsidiaries,
suppliers, and sub-suppliers and shall form part of all Eskom requests for information (RFI)/ requests
for quotation (RFQ)/ requests for proposal (RFP), including contracts for the procurement of products
and services.
2.1.3 Effective date
Date of authorisation of the specification
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
[1] ISO 9001 Quality Management Systems – Requirements
[2] ISO 10005 Quality Management Systems – Guidelines for Quality Plans.
2.2.2 Informative
[3] ISO 9000 Quality Management Systems – Fundamentals and Vocabulary
[4] 32-727: Safety, Health, Environment, and Quality (SHEQ) Policy
[5] ISO 10006 Quality Management Systems – Guidelines for Quality Management in Projects
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
[6] ISO 9004 Quality Management – Quality of an Organisation – Guidance to Achieve Sustained
Success
[7] 32-1033: Eskom’s Procurement and Supply Chain Management Policy
[8] 32-1034: Eskom’s Procurement and Supply Chain Management Procedure
[9] PPPFA: Preferential Procurement Policy Framework Act, 2000 (Act No. )
[10] CIDB 1004: Best Practice Guideline A4: Evaluating Quality in Tender Submissions
[11] 240-12248652 Supplier Quality Management: List of Tender Returnables
[12] IAEA Safety Standard GS-R-3.1 Application of the Management System for Facilities and
Activities
[13] SANS 10845-1 Construction Procurement Part1: Processes, Methods and Procedures
2.3 Definitions
The vocabulary of ISO 9000 and the following definitions apply in the application of this specification.
2.3.1 Component: a constituent part of the product or sub-assembly of the product. The product
may comprise multiple individual components
2.3.2 Contract Quality Plan: a document of the supplier’s process for delivering the level of quality
required by the contract. It is a framework for the contractor’s process for delivering quality.
Purpose of a CQP is to outline how the results defined in the specifications will be achieved.
2.3.3 Hold Point: a predetermined stage in the quality control plan (QCP) beyond which work/
manufacturing shall not proceed without the attendance of, and written authorisation of, an
Eskom representative or Eskom inspection agency, whichever is applicable.
2.3.4 Intervention Points: those control points indicated by the various controlling bodies
concerned with the implementation of a specific QCP/ ITP. These can be in the form of
inspection, hold points, surveillances, witnesses, reviews and verifications.
2.3.5 Inspection Agency: an organisation or person appointed by Eskom for the purpose of
performing quality assurance/ quality control, monitoring, inspection and/ or expediting
services.
2.3.6 Level 1 Plant Items: equipment, whose failure has an effect on personnel safety and/ or
health, causes an environmental incident, cause a huge production loss or major equipment
damage. Equipment that are safety/ redundancy/ protective device or covered by statutory
regulations requirements.
2.3.7 Level 2 Plant Items: equipment, whose failure impacts plant availability and/or reliability,
causes significant costs or secondary damage.
2.3.8 Level 3 Plant Items: equipment that does not impact on personnel safety and/ or health,
environmental, cost, availability and/ or reliability of plant.
2.3.9 Nonconformity: a deficiency in material, composition, characteristic, or performance that
renders the quality of an item, component, or product unacceptable or indeterminate. The
term also covers a deficiency in, or deviation from/non-adherence to, the quality management
system requirements, prescribed production processes, and/or related documentation such
as procedures and instructions.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
2.3.10 Quality Plan: specification of the actions, responsibilities and associated resources to be
applied to a specific object.
2.3.11 Quality Control Plan: a document specifying the activities to be inspected throughout the
execution of the project, inclusive of test methods, procedures, and acceptance criteria (This
term is equivalent to QIP and ITP).
2.3.12 Requirement: the need or expectation that is stated, generally implied, or obligatory.
Requirements are generally specified in the purchase order and/or contract documentation,
but may not be limited to these.
2.3.13 Primary Plant (Power Plant): primary plant include High Voltage equipment situated inside
the control room (breakers, bus-bars, CT’s, VT’s and transformers).
2.3.14 Secondary Plant (Control Plant): secondary plant includes all equipment used to control
and protect the HV equipment on the primary plant side. (Protection, metering, AC/DC and
tele-control).
2.3.15 Special Process: is any production or service process which generates products or services
which cannot be measured, monitored, or verified prior to delivery and use.
2.3.16 Supplier: is a current or potential supplier, vendor, contractor, consultant, or service provider.
A supplier may be a natural or legal person and includes any employee acting within the
course and scope of his/her employment or any agent or manager acting for, or on behalf of,
or in the interests of, the person registered as supplier on the Eskom supplier database.
2.3.17 Sub-supplier: an organisation that provides a product/service to the supplier and/or that
enters into a subcontract and assumes some of the obligations of the supplier or prime
contractor.
2.3.18 Witness Point: a predetermined stage in the quality control plan where and inspection
activity will take place. Work may proceed, provided Eskom or its inspection agency has been
formally notified and confirmed that inspection is waived.
2.4 Abbreviations
Abbreviation Explanation
AIA Approved Inspection Authority
CA Corrective Action
CQP Contract Quality Plan
FIDIC Federation Internationale Des Ingenieurs- Conseils
FMECA Failure Mode, Effects and Criticality Analysis
HAZOP Hazard and Operability Study
ISO International Organisation for Standardisation
ITP Inspection and Test Plan
NC Nonconformity
NDT Non Destructive Testing
PMI Positive Material Identification
QCP Quality Control Plan
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Abbreviation Explanation
QMS Quality Management System
PQP Project Quality Plan
RFI Request for Information
RFQ Request for Quotation
RFP Request for Proposal
SHEQ Safety, Health, Environment, and Quality
SETA Skills Education Training Authorities
WPS Welding procedure specifications
WQR Welder’s Qualification Record
2.5 Roles and Responsibilities
Eskom Quality representative/ professional will select applicable requirements for existing and
potential Eskom suppliers using Form A (Tender and Contract Quality Requirements for Supplier
Quality Management: Specification 240-105658000/ QM 58 and Quality Requirements for ISO 9001
Standard).
The existing and/ or potential suppliers must complete, sign and return Form A with the other
returnable as listed in the List of Tender Returnable document (240-12248652). Other roles and
responsibilities for this standard are defined within the text of this specification.
2.6 Process for Monitoring
The application of this specification throughout Eskom shall be audited as per the management
system audit schedule.
2.7 Related/Supporting Documents
The documents superseded by this specification: all divisional and business unit supplier quality
requirements standards and/or specifications.
Forms and templates:
[1] 240-68099512 Tender and Contract Quality Requirements for Supplier Quality Management
Specification 240-105658000/ QM 58 and Quality Requirements for ISO 9001 Standard (Form
A)
[2] 240-109253698 Template for a Typical Contract Quality Plan
[3] 240-109253302 Quality Control Plan/Inspection and Test Plan
[4] 240-126469599 Method Statement Template.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The quality assessment criteria and Form A of this specification will be selected and completed by
an Eskom Quality representative/ professional who will identify the applicable supplier quality
requirements to be met.
Form A of this specification must also be completed and signed by the supplier responding to an
Eskom invitation to tender, in order to acknowledge and accept Eskom Supplier Quality requirements
as per this specification and ISO 9001 Standard or any additional quality requirements specific to
the scope of work.
3.1 Supplier and Sub-Supplier Quality Management System Requirements
3.1.1 The supplier and sub-supplier shall develop, implement, maintain and improve a formal QMS
that conforms to the latest ISO 9001 standard or any applicable standard of QMS (latest
applicable revision) and in accordance with the requirements of this specification.
3.1.2 Such a formal system shall consist of the appropriate documented information required by
ISO 9001 and may include a quality manual, quality plans, work procedures, work
instructions, method statements, work flow documentation, etc., as the case may be. This
requirement constitutes the most basic QMS requirements.
3.1.3 Unless specifically excluded from the quality list of tender returnable, as per the categories of
quality requirements (Category 1, 2, 3, or 4), such a QMS shall carry a valid ISO 9001
certificate from an accredited certification body, as indicated in the applicable Eskom
invitation (this requirement applies equally to both the supplier and any/ all manufacturing
third-party organisations mentioned above).
3.1.4 Unless specifically excluded in the quality list of tender returnable, as per the categories of
quality requirements (Category 1, 2, 3, or 4), the supplier shall have a fully developed,
documented, implemented, reviewed and maintained QMS that complies with the
requirements of ISO 9001 standard or any applicable standard of QMS. In the event that the
main supplier invariably requires the assistance of a sub-supplier in order to realise its own
supply obligations. The aforementioned requirement applies equally in all cases where any
such sub-supplier’s scope of responsibility includes the provision of any of the following
activities, namely, design and development, manufacturing, maintenance, testing, storage,
delivery, installation, commissioning, and project management, or in the cases the supplier
name changes, mergers, acquisitions and/ or cessions. Eskom Quality department must
ensure that the changed entity can still fulfil the requirements as set out in the contract
documentation.
3.1.5 Eskom reserves the right to request and perform necessary assessments at sub-supplier
facilities.
3.1.6 The main supplier shall be responsible for defining and managing the specific quality
assurance and control elements applicable to the respective sub-supplier’s scope of
work/supply and ensure that its sub-supplier(s) quality programmes support Eskom
requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.1.7 The supplier shall inform Eskom of any proposed changes to the QMS or staff that will affect
the quality system prior to implementation of these changes.
3.1.8 The main supplier shall develop and implement a performance management programme for
their sub-supplier. The programme shall include, but not limited to:
Verification of the QMS
Audits and surveillances
Regular assessment of the CQPs and reviews of QCPs.
NC and Defect Management
Inspection and test plans
Risk management
3.2 Quality Plan
The information in this section constitutes the minimum requirements for a quality plan.
3.2.1 Where specified in the Evaluation Criteria and/ or quality list of tender returnables , as per the
categories of quality requirements (Category 1, 2, 3, or 4); all individual products, services
and processes shall have a documented, implemented, reviewed and maintained contract
quality plan and/or quality control plan (inspection and test plan).
3.2.2 Where specified in the evaluation criteria and/ or quality list of tender returnables. All
production and/ or service provision shall be carried out in accordance with a documented
and agreed contract quality plan (CQP) and/ or quality control plan (QCP)/ inspection and test
plan (ITP).
3.2.3 The supplier shall plan for the required quality-related activities and interfaces within the
supplier’s quality system in order to demonstrate its ability towards both controlling and
meeting specified Eskom requirements.
Note 1: Contract Quality Plan should address the quality assurance elements related to the scope
of work and/ or technical specification.
Note 2: Quality Control Plan (QCP)/ Inspection and Test Plan (ITP) should address the quality
control elements related to the scope of work and/ or technical specification.
3.3 Contract Quality Plan
The main supplier shall require sub-suppliers to submit project quality plans (PQPs)/ contract quality
plans (CQPs) and associated documentation in accordance with the requirements of project QMS
processes applicable to the sub-supplier’s scope of work.
The supplier shall, where applicable, based on scope of work criticality, ensure that procurement
documents clearly and unambiguously require sub-supplier submission of a sub-supplier CQP for
supplier and Eskom review.
The main supplier shall ensure that sub-supplier CQPs are developed and implemented in
accordance with the ISO 10005 Quality Management System Guidelines for Quality Plans. In
addition to the elements specified in ISO 10005, the supplier’s and/ or sub-suppliers’ CQPs shall
include the following (as applicable):
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.3.1 The management of records, including material tests, positive material identification (PMI)
testing, material certification, etc.
3.3.2 The provision for free and uninhibited access by the supplier and/or personnel at the time of
inspection.
3.3.3 The proposals for submission of final documentation, the final manufacturing data book, prior
to shipment.
3.3.4 The special processes related to welding: management of the welder’s qualification record
(WQR), welding procedure specifications (WPS), and procedures qualification records (PQR)
that will be used in the performance of work for supplier review and acceptance prior to
commencing manufacture. Welders shall be qualified to the specified Codes of Construction
for the applicable procedures. The requirements for qualification shall be specified by the
supplier, and welder records shall be maintained by sub-suppliers performing the work.
3.3.5 The special installation procedures and other required fabrication or manufacturing
procedures (that is, those required for post-weld heat treatment, tube rolling, coatings, etc.)
that will be used in the performance of work shall require supplier review and acceptance
prior to commencing manufacture. The personnel carrying out special processes (for
example, NDE, welding, coating, heat treatment, etc.) where the results cannot be fully
verified by subsequent inspection and test shall be suitably qualified and, where applicable,
registered with statutory bodies as legally required, that is, as radiographic workers to conduct
radiography. The requirements for the qualification shall be specified, and personnel records
shall be maintained in accordance with the Project Quality Personnel Qualification
Specification and, where applicable, legal requirements.
3.3.6 The personnel required to perform special processes shall be certified competent through a
certificate of competency in accordance with the company’s internal training management
and competency control procedures or an external certification body (for example, NDT)
through an accredited service provider as per Skills Education Training Authorities (SETA)
requirements.
3.3.7 All personnel who perform activities that affect quality shall have their training needs identified
and documented. The required training shall be implemented in accordance with the
company’s training management and competency control procedures. All the training
certificates shall meet the SETA requirements in terms of having the unit standard completed
and the accreditation number of the service providers.
3.3.8 Instructions and requirements for equipment and materials storage, preservation, and
maintenance, including identification of materials required for preservation and maintenance,
are to be provided sufficiently prior to receipt (prior to shipment or earlier) to ensure that
appropriate resources are available at the time of delivery.
3.3.9 Specific quality monitoring and verification activities are to be undertaken on the supplier’s
sub-suppliers by Eskom or it agent.
3.3.10 The CQP information need to include, but not limited to:
Spells out the aspects of the QMS to be applied within a specific Eskom project, and the
methods to be utilised to ensure quality.
Outline the resources, the communication channels, applicable documents and records to be
generated.
Management Authority and Responsibility from both supplier and client need to outline in the
Cqp.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
List of documents and records that will be used and submitted during the execution of the
project.
Communications channels should include contact person and contact details
Monitoring & measurement procedures for activities need to be indicated.
3.3.11 The main supplier and sub-supplier CQPs shall comply with the Eskom Quality Requirements
Specifications and shall be submitted prior to the initial scope of work kick-off or initial pre-
fabrication meeting and prior to commencement of manufacturing, whichever is earlier.
3.3.12 The Eskom template for CQP provided shall be used as guideline, where the supplier does
not have a CQP template.
3.4 Quality Control Plan
The supplier shall develop and implement processes and procedures that efficiently and effectively
monitor, verify and document the quality of the scope of work for deliverables.
The main supplier shall ensure that sub-supplier QCPs/ ITPs are prepared at a level of detail
sufficient to address all quality-control-related activities in a chronological order, from contract review
through materials verification, manufacturing, fabrication, assembly, final testing, commissioning,
hand-over documentation, and certification. In addition, the supplier shall ensure compliance with
the following requirements:
3.4.1 All stages of manufacturing, fabrication, assembly and installation shall be controlled by a
supplier’s QCP/ ITP that clearly and unambiguously identifies the quality verifications to be
performed and special attention to controls related to critical products and services.
3.4.2 QCP/ ITP shall be reviewed and accepted by Eskom, its inspection authority or agency, and
they shall allow for the insertion of Eskom specific requirements, including hold and witness
points prior to the commencement of work.
3.4.3 Subsequent changes to the Eskom accepted QCP/ ITP shall require Eskom, its inspection
authority or agency’s agreement prior to the commencement of work involving an activity
affected by such changes.
3.4.4 The ITPs should cover materials certification, fabrication works, in-process inspections, final
acceptance tests, packaging and pre- shipment/ transportation, shipping/ transportation
inspections where contracted, preservation, site acceptance tests, construction and erection
works, and pre-commissioning and commissioning tests.
3.4.5 All sub-supplier QCP/ ITP activity shall be performed using an Eskom-accepted supplier
Qcp/ itp.
3.4.6 All applicable codes, standards, and relevant acceptance criteria documents are available at
the work location, and Eskom representatives on site shall have on-going access to this
information. Workplace documentation shall be available in English and in any workforce-
appropriate language.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.4.7 Where activities subject to inspection and test procedures are to be undertaken by a sub-
supplier, the QCP/ ITP shall make reference to this fact and shall include descriptive details
of the sub-supplier’s involvement. A separate QCP/ ITP shall be required for each sub-
supplier scope of work.
3.4.8 The supplier shall be ultimately accountable and responsible for the development and proper
implementation of all sub-supplier QCPs/ ITPs, including those reviewed or developed by
sub-suppliers.
3.4.9 Eskom reserves the right to select intervention points on QCPs/ ITPs for Eskom oversight of
selected functions and to perform surveillance or audits of the work.
3.4.10 Once signed, the ITPs and QCPs become addendums to the main contract. These ITPs can
be reviewed at Eskom’s discretion based on its assessment of the supplier’s performance or
other risks.
3.4.11 A QCP/ ITP shall contain the following information:
Eskom contract number and title
The supplier’s order number
Identification of the area of works/contract
Description of the work, with components, item number, and activity date
QCP/ITP unique number
A list of the sequence of operations, including inspection and tests
The identification of the specification, drawing number, or procedure for each operation,
with reference to the relevant criticality risk rating
The acceptance criteria, with reference to the technical specification, in-house, national, or
international standard, with the relevant clause number for each operation
The inspection and test activities that the supplier has nominated for its intervention points
Provision for the inclusion of intervention points nominated by Eskom and/or its authority/
agency
Provision for intervention point acceptance by date and signature for all parties having
intervention in the plan
Inspection and test records to be generated by the supplier for each operation and an
indication of records to be provided to Eskom (as applicable)
3.4.12 The main supplier shall require sub-suppliers to submit QCPs/ ITPs and associated
documentation applicable to the sub-supplier scope of work. Any changes made to the QCP
after submission must be resubmitted to Eskom for further review. The supplier shall ensure
that all sub-supplier QCPs/ ITPs are in compliance with the Eskom Quality Requirements
Specifications, including, but not limited to, the following requirements:
Clear and unambiguous description of the equipment and location(s) at which each activity
will take place, including facility location(s)
Identification of quality verification activity and stage
The details of reference documents, procedures, or method statements to be utilised in
performance of the activity, including specific reference to actual sections and pages of
procedures, standards, instructions, specifications, etc.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Definition of acceptance criteria
Listing of certifying or verifying documents generated to provide evidence of compliance
with specified requirements; documents are to be provided using the proper Eskom
document numbering requirements
Identification of main supplier and sub-supplier (where applicable) third-party/approved
inspection authority (AIA) and Eskom inspection activities defined in terms of witness, hold,
document review, and verification monitoring points and provision for sign-off of each of the
above-mentioned parties for each intervention point
Qualification requirements for quality control inspectors, including any third-party/AIA
inspectors
Listing of all proposed test procedures
Acceptance criteria for each inspection or test in alignment with specified tolerances
A section for signed acceptance of the QC/ITP by the supplier, sub-supplier (where
applicable), and Eskom prior to commencement of work
Inspection or testing intervention points, including, but not limited to, factory acceptance test
and package acceptance test, witness, and hold points
3.4.13 A quality kick-off meeting will be held at the start of the contract and, if required, at the start
of each subsequent phase.
The supplier shall arrange coordination meetings with Eskom prior to placement of orders
for items or equipment to ensure that all technical and commercial requirements are clear
and understood. Fourteen days’ advance notice of meetings shall be given to Eskom.
Supplier inspection personnel, including inspection agency personnel, shall be competent
and qualified to perform inspection and testing assignments. Mobilisation of all such
personnel shall be in compliance with the Project Quality Personnel Qualification
Specification.
3.4.14 Where QCP/ ITP is applicable, the supplier shall ensure that sub-suppliers are provided with
comprehensive, clearly written, and unambiguous inspection and testing protocols, including
processes, procedures, and methods that shall include, but not be limited to, the following:
Requirements for inspection checklists and inspection assignments, with lists of items to be
inspected
An inspection and testing report format, report content, schedule for report processing and
distribution, and report retention requirements
Inspection and test report results response tracking (log) and resolution of nonconformity in
inspection and test processes, procedures, or methods and nonconformity identified in
inspection and test results
Associated Failure Mode, Effects and Criticality Analysis (FMECA) reports relating to the
equipment and sub-systems (if applicable)
Hazard and Operability Study (HAZOP) report, as applicable
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.4.15 The supplier shall establish processes and procedures for formal assessment of sub-supplier
inspection and testing programmes. These shall include review of sub-supplier inspection
reports and other quality control documentation. Additional formal assessment of
manufacturing, fabrication, and assembly facility operations shall be conducted by the
supplier to ensure continuing suitability, adequacy, and effectiveness of the sub-supplier’s
inspection and testing programmes. Assessment frequency shall be established in
consideration of the sub-supplier scope of work, criticality of scope of work deliverables, and
performance information. The assessment scope and schedule shall be developed in
consultation with Eskom.
3.4.16 Supplier processes and procedures for verification of supplier and sub-supplier purchased
product compliance with specifications shall obtain document return/review status prior to
implementation.
3.4.17 The objective is to finalise any outstanding procedural or other issues before proceeding to
deliver the works.
3.4.18 Eskom, in consultation with the supplier, develops an agenda for the meeting, and Eskom will
keep minutes of these meetings.
3.4.19 Mandatory pre-inspection meetings will be convened by Eskom or its inspection agency or
AIA to be attended by the supplier’s and sub-supplier’s representatives, including their quality
representatives who will be involved in the works, and records are to be kept.
3.4.20 Eskom reserves the right to appoint resident quality inspectors who can be based at the
supplier’s or sub-supplier’s premises and on site where the work is being performed. The
supplier is expected to provide workspace at no cost to Eskom for the inspector, as required.
3.4.21 Eskom may appoint any organisation it prefers to perform quality assurance and quality
control activities, either in the capacity as an AIA or inspection agency, on the works
contracted to the supplier, and the supplier or its sub-suppliers may not object, prevent,
hinder, undermine, circumvent, question, discredit, or in any way make it impossible for such
organisation to carry out its work on behalf of Eskom.
3.4.22 The Eskom template for QCP/ ITP provided shall be used as guideline, where the supplier
does not have a QCP/ ITP template.
3.5 Pre-Contract Award: Quality Requirement
3.5.1 Main Supplier and Sub-supplier Categories
Eskom supplier quality requirements for all existing and potential suppliers and sub-suppliers are
classified into four categories (category 1, 2, 3 and 4). Suppliers must prepare and submit quality
documentation as per the tender selected category (indicated in Form A) using the list of tender
returnables document.
NOTE: Only one (1) category must be applicable per procurement process e.g. [Eskom requests for
information (RFI)/ requests for quotation (RFQ)/ requests for proposal (RFP), including contracts for
the procurement of products and services].
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The following are the minimum returnable documentation for Categories 1 to 4:
3.5.2 Category 1: Quality Requirements
The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
The supplier shall submit a valid copy of ISO 9001 or any applicable certificate of a QMS (the
latest applicable revision). The QMS should drive the supplier’s business management
processes to ensure that all of Eskom’s requirements are fully met on a consistent basis.
The supplier shall submit the latest copy of the management system internal and external
audit reports. The audit reports must include, if applicable, nonconformity identified, and the
resulting remedial actions (correction and/ or corrective action reports).
The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
Where applicable; the supplier shall submit a draft, or an example of an inspection and test
plan (ITP) or quality control plan (QCP) on similar and/ or previous work done.
The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
The supplier shall submit documented information retained (records) of management review
meetings that include agenda, meeting minutes, attendance registers, reports, presentations,
etc.
Note: specific requirements per tender will be selected using the List of Tender Returnable
documents (240-12248652).
3.5.3 Category 2: Quality Requirements
The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
The supplier shall submit objective evidence of a developed, implemented and maintained QMS
that complies with ISO 9001 or any applicable standard of quality management system (the latest
applicable revision). The following documents (approved/ signed copies) shall be submitted:
Quality Management System manual or a documented information that have defines and
describes the QMS and its scope
Quality Policy, aligned with the supplier’s strategic direction (documented information)
Quality Objectives (documented information)
Control of documented information (both maintain and retain documented information )
Internal audit procedure (documented information)
Control of nonconforming outputs (documented information)
Nonconformity and Corrective action procedure (documented information)
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The QMS should drive all the supplier’s business management processes to ensure that all of
Eskom’s requirements are fully met on a consistent basis.
The supplier shall submit the latest copy of the management system internal audit reports. The
audit reports must include, if applicable, nonconformity identified, and the resulting remedial
actions (correction and/ or corrective action reports).
The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
Where applicable; the supplier shall submit an example of inspection and test plan (ITP) or
quality control plan (QCP) on similar or previous work done.
The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
The supplier shall submit documented information retained (records) of management review
meetings that include agenda, meeting minutes, attendance registers, reports, presentations,
etc.
Note: specific requirements per tender will be selected using the List of Tender Returnable
document (240-12248652).
3.5.4 Category 3: Quality Requirements
The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
The supplier shall submit objective evidence of a developed QMS that complies with ISO 9001
(or the latest applicable revision). The following documented information (approved/ signed
copies) shall be submitted:
o Quality management system manual or a (documented information) that have
defines and describes the QMS and its scope
o Quality Policy, aligned with the supplier’s strategic direction (documented
information)
o Quality Objectives (documented information)
o Control of documented information (both maintain and retain documented
information )
o Internal audit procedure (documented information)
o Control of nonconforming outputs (documented information)
o Nonconformity and Corrective action procedure (documented information)
The QMS should drive all the supplier’s business management processes to ensure that all of
Eskom’s requirements are fully met on a consistent basis.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
Where applicable; the supplier shall submit an example inspection and test plan (ITP) or
quality control plan (QCP).
The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
NB: specific requirements per tender will be selected using the List of Tender Returnables
document (240-12248652).
3.5.5 Category 4: Quality Requirements
The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
The supplier shall submit a quality method statement based on ISO 9001 and specific to the
scope of work.
The quality method statement should address all the supplier’s business management
processes to ensure that all of Eskom’s requirements are fully met on a consistent basis.
The supplier shall submit a signed/ approved quality policy (aligned with the supplier’s strategic
direction). (documented information)
The supplier shall submit a copy of quality objectives. (documented information)
The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
The supplier shall submit a copy of the documented information for roles, responsibilities and
authorities, specific to the project/ scope of work/ technical requirements. Examples of relevant
documented information are; organization charts, job descriptions, work instructions, duty
statements, manuals, procedures.
Note: specific requirements per tender will be selected using the List of Tender Returnables
document (240-12248652).
3.6 Main Supplier and Sub-supplier Capability and Capacity Assessment
Supplier capability and capacity assessments shall be performed prior to contract award on potential
suppliers participating in Eskom Holdings procurement process to:
provide products and services with high risk to operational sustainability
work on critical plant and equipment
supply of critical plant items or components
provide special processes
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
All sub-suppliers used by the main supplier/ contractor, performing work on Eskom critical plant
equipment, supplying commodities and providing specialised services shall be subjected to the
capability and capacity assessment.
Critical plant includes the following:
Generation Level 1 & 2 plant
Transmission and Distribution Power Plant & Control Plant
Mega Projects
All potential quality risks identified will be included in the assessment report provided for the tender
evaluation.
Note: Form A (Enquiry/ Contract/ Quality Requirements for Supplier Quality Management:
Specification 240-105658000/ QM 58 and ISO 9001) will be used to select and indicate whether
capability and capacity assessment will be conducted.
3.7 Post-Contract Award
3.7.1 Contract Execution
The supplier shall submit the following documents within 30 days or as per stated timeline after the
contract date, prior to the commencement of work, for acceptance by Eskom:
The supplier shall complete a QCP before contract award. This shall be reviewed and
signed off by Eskom within 30 days or as per stated timeline after contract award.
The supplier shall complete a quality control plan and ITP(s) for review and acceptance by
Eskom prior to the commencement of any work, inclusive of subcontracted work, within 30
days or as per stated timeline after contract award.
The sub-supplier QCP/ ITP shall be submitted for review and comment by the supplier and
by Eskom within 30 days or as per stated timeline after the award of the tender. All supplier
and Eskom comments shall be resolved prior to commencing work.
The equipment lists and an indication of pressurised components and systems.
Note: These plans are to be compiled in line with Eskom’s requirements and will have to be
discussed with, and approved by, Eskom prior to any work commencing.
Correspondence shall be directed to the project manager, and periodic quality review
meetings shall be convened by Eskom with the supplier.
The mandatory quality review meetings are to be convened by the nominated project quality
manager or his/her representative for the contract.
Monthly quality performance and management reports are to be prepared by the supplier
during contract execution. The content of these reports shall be agreed by Eskom when
submitted to Eskom on a monthly basis.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.7.2 Supplier Quality Performance Monitoring Phase
During the contract execution phase, suppliers shall be monitored by Eskom for performance on
quality-related aspects.
The outcomes of such monitoring will enable Eskom to take any appropriate actions pertaining to
the supplier.
The monitoring shall be carried out periodically by Eskom or at predetermined intervals during the
execution of a contract using agreed key performance indicators. The monitored key performance
areas include the following:
CQP and QCP /ITP
Delivery
Design
Cost
Management system
Subsequent key performance indicators associated with these areas will include the following:
Nonconformity monitoring
Audit and assessment evaluation scoring
Management system compliance and accreditation
Achievement of delivery targets as per contractual agreements
Process improvements
Correction and corrective action response and closure
3.7.3 Supplier Quality Audit
3.7.3.1 Quality audits and related quality performance reviews are intended to provide an objective
evaluation of compliance with performance expectations defined in this specification, in the
supplier contract quality plan (CQP), and in any other project scope of work specification.
3.7.3.2 Quality audits and related quality performance reviews include, but are not limited to, any
quality or other project functional area audits, assessments, verification of compliance
reviews, surveillance, inspections, or other interim or final assessments of scope of work
deliverables provided by the supplier or sub-suppliers
3.7.3.3 Quality audits and related quality performance reviews are intended to provide an objective
evaluation of compliance with performance expectations defined in this specification, in the
supplier contract quality plan (CQP), and in any other project scope of work specification.
3.7.3.4 Quality audits and related quality performance reviews include, but are not limited to, any
quality or other project functional area audits, assessments, verification of compliance
reviews, surveillance, inspections, or other interim or final assessments of scope of work
deliverables provided by the supplier or sub-suppliers.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.7.3.5 Quality audits and related quality performance reviews shall be carried out by trained,
accredited, and experienced personnel in accordance with procedures documented in the
Cqp.
3.7.3.6 The supplier shall submit, for Eskom review, documented processes for conducting project
scope of work quality audits and related quality performance reviews. Supplier quality audits
and related quality performance review processes shall be designed to address evaluation
of progress towards completion of project functional area deliverables as well as final
deliverable quality.
3.7.3.7 The supplier shall provide a schedule of anticipated quality audits covering all functional
areas and related quality performance reviews at the time of first post-contract award CQP
submission.
3.8 Standard Conditions
3.8.1 Rights of Access
Eskom:
3.8.1.1 shall be granted electronic and hard-copy access to all quality plans, procedures,
documentation, and other quality records relating to the work, including, but not limited to,
data extracts;
3.8.1.2 reserves the right to review, inspect, and audit any or all parts of the supplier’s QMS, as well
as any documentation, materials, or equipment associated with the work, at any time or
project work location; and
3.8.1.3 reserves the right to carry out assessments and audits on all new suppliers and sub-
suppliers.
The supplier:
3.8.1.4 shall support Eskom’s effort to monitor, verify, and/or witness any activities associated with
the work at any time;
3.8.1.5 shall cooperate with Eskom requests for documentation, records, and inspection and
witnessing. Eskom participation in audits, appraisals, assessment of plans, and verification
shall be conducted at no extra cost to Eskom;
3.8.1.6 shall ensure that a sub-supplier provides access to Eskom to all work procedures, records,
and supporting documentation through provision of access to view and photocopy, as
required, to support verification of scope of work requirements. Access shall include the
ability to photograph Eskom equipment, systems, system components, materials, etc.;
3.8.1.7 shall provide access to all quality-related information pertaining to activities performed by
itself or sub-suppliers, where Eskom might not have participated in the witnessing of their
quality assurance or control (this refers to inspections, audits, etc. performed by the supplier
on its own sub-suppliers);
3.8.1.8 shall allow Eskom to assess, audit, approve, or reject any sub-suppliers employed by
Eskom’s suppliers to assist with the product and/or service delivery to Eskom; and
3.8.1.9 shall ensure that the above requirements flow down to sub-suppliers.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.2 Eskom Rights to Information
3.8.2.1 To expect that the works will be conducted in accordance with the contract between the
parties.
3.8.2.2 To have access to the supplier’s information as determined by applicable legislation.
3.8.2.3 Eskom reserves the right to oversee the supplier’s audit programmes by participating in
selected audits as an observer and by assessing the supplier during key work stages.
Eskom will coordinate with the supplier to develop an oversight schedule aligned with the
supplier’s audit schedule.
3.8.2.4 To obtain access to any audit reports of audits performed by the supplier reflected in the
audit programme.
3.8.2.5 To conduct independent quality audits during all phases of the contract, and the supplier
shall provide all resources to support these activities.
3.8.2.6 Eskom shall have the right to participate in, or request that, a technical investigation be
launched and conducted at the supplier’s and sub-suppliers’ premises or other sites when
risk to Eskom products or service deliverables is identified.
3.8.2.7 To participate in, and/or lead, investigations related to incidents involving its products.
3.8.2.8 To require from suppliers to be responsible for the cost of re-inspections.
3.8.2.9 To withhold payment from suppliers as a result of outstanding nonconformities, irrespective
of the agreed payment schedule and in accordance with the conditions of contract.
3.8.2.10 Shall be granted electronic and hard-copy access to all quality plans, procedures,
documentation, and other quality records relating to the work, including, but not limited to,
data extracts.
3.8.2.11 Reserves the right to review, inspect, and audit any or all parts of the supplier’s QMS, as
well as any documentation, materials, or equipment associated with the work, at any time or
project work location.
3.8.2.12 Shall carry out assessments and audits on all new suppliers and sub-suppliers.
3.8.2.13 Reserves the right to appoint resident quality inspectors who can be based at the supplier’s
or sub-supplier’s premises and on site where the work is being performed.
3.8.2.14 Reserves the right to select intervention points within all developed supplier QCPs/ ITPs
for Eskom oversight of selected functions and to perform surveillance or audits of the work.
3.8.2.15 Shall be given access at all reasonable times before, during, and after manufacture and
before delivery, construction, erection, and commissioning to measure, test, and inspect the
products and workmanship, as necessary, at the supplier’s premises and at Eskom sites.
3.8.2.16 Reserves the right to suspend any pending deliveries by the issuing of a cease delivery
order at any time and for any portion of the work that is not being performed in accordance
with the specified/agreed requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3 Preservation
The supplier shall develop and implement a comprehensive preservation programme consisting of
plans, processes, procedures and actions undertaken for the purpose of planning for and
maintenance of material deliverables quality. The supplier preservation programme scope includes,
but is not limited to, the following:
3.8.3.1 Engagement of personnel suitably qualified for oversight of, and (as required) direct
implementation of, preservation programme requirements.
3.8.3.2 Development and implementation of preservation programme training appropriate to work
need.
3.8.3.3 Eskom may make use of its appointed service provider tasked to provide a full suite of
services encompassing an online monitoring system and asset tracking during, but not
limited to the following stages: inspections, testing, shipping, transportation, storage, and
commissioning. The supplier is to enable full access during all of these stages in order to
allow the installation of the devices on Eskom-identified products and equipment, which
include the sub-supplier’s testing facilities, processing plant, and any other processes
deemed important towards effective and efficient quality control.
3.8.3.4 Eskom seeks cooperation between the supplier’s designers and those of Eskom’s service
provider in ensuring seamless installation of the device and other associated installations.
Moreover, there is also a need to integrate data flows and systems between Eskom and the
supplier. Further details are included in the Eskom specifications and works information.
3.8.3.5 Review and tracking of compliance with Eskom and supplier engineering specification of
preservation requirements.
3.8.3.6 Review and tracking of compliance with sub-supplier provided preservation requirements
and recommendations.
3.8.3.7 Evaluation of prospective temporary and longer-term material storage sites for consistency
with preservation programme expectations.
3.8.3.8 Preservation work plan development and plan execution performance evaluation of all
parties engaged for provision of material transportation, handling, or storage services.
3.8.3.9 Oversight of material quality preservation plan preparation and plan execution performance
at all work locations.
3.8.3.10 Development of a preservation programme records management process, in compliance
with Eskom information management requirements, which comprehensively addresses
generation, maintenance, and ready access by Eskom to all preservation programme
records.
3.8.3.11 The supplier shall deploy a clearly defined documented programme providing for
identification of all physical asset pre-operation preservation of quality requirements. In this
reference, the term “physical assets” should be understood to include bulk materials,
including consumable items, equipment systems, system components, and any other
procured or supplied materials or equipment transferred to project control, but not deployed
for operational purposes.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3.12 Where the project responsibility for equipment and materials management has been
formally delegated, the supplier’s preservation programme shall ensure clear and
unambiguous communication of pre-operation preservation of goods quality requirements
to sub-suppliers.
3.8.3.13 The supplier’s preservation programme shall clearly and unambiguously document
processes and procedures for efficient and effective monitoring of compliance with
programme requirements.
3.8.3.14 Compliance monitoring shall commence with ensuring comprehensive consideration of
preservation requirements in the engineering instruction and subsequent inclusion of said
instruction in procurement documentation and shall be applicable until such time as
equipment or materials have been incorporated in an operating or operational system or
structure.
3.8.3.15 Compliance evaluation frequency shall anticipate transfer of tactical-level responsibility for
management of preservation responsibilities between project functional areas, for example,
procurement to logistics, logistics to fabrication, fabrication to logistics, logistics to
construction, etc., and shall, in similar fashion, anticipate transfer of support for tactical-level
responsibility between various subcontracted service providers.
3.8.3.16 Supplier engineering shall ensure that preservation requirements for scope of work
systems, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented and that preservation requirements are efficiently and
effectively communicated to project procurement, logistics, construction management,
quality, security, and other project functional areas, as required, for efficient and effective
implementation of preservation requirements. This shall take the form of a preservation
programme applicable to all systems, system components, equipment, materials, customer-
supplied materials, and other goods procured or managed under the scope of work.
3.8.3.17 The supplier’s preservation management programme shall clearly and unambiguously
address temporary, long-term, and in-transit preservation requirements, including, but not
limited to:
requirements for protection against, or insulation from, atmospheric conditions,
sunlight, temperature, soil, dust, humidity, salt spray, corrosive atmospheres, or
other physical environment conditions;
detailed procedures for application, use, monitoring, and maintenance of coatings,
coverings, fasteners, lines, and other components for internal and external weather
proofing;
requirements for electrical grounding or isolation;
requirements for internal or external environment creation, for example, inert gas
charging, heating, cooling, etc., inclusive of gas storage, electric power supply, etc.;
detailed procedures for initial set-up, charging, activation, and maintenance of
internal atmosphere generation, regeneration, monitoring, and relieving systems, for
example, inert gas management systems;
requirements for protection against, or insulation from, vibration or long-period
cyclical motion in transit, for example, wave-generated movement during sea
transport;
internal and external structural integrity protection, for example, internal and external
bracing, padding, framing, chocking, etc.;
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
support structure requirements, for example, stools, pads, or other devices,
substrates, or support required to ensure in-storage and in-transit stability of
systems, system components, equipment, and material, or other discrete units or
items;
provision for physical separation and/or barriers to prevent airborne or direct
transmittal of contaminants between work areas or between work areas and storage
areas, for example, prevention of carbon steel grinding or cutting debris impact on
stainless steel elements, airborne drift of blast aggregate into vessels or machinery,
etc.;
provision for, and final disposition of, temporary and longer-term storage or transit
required supports and related binding devices, for example, stools, stands, sea
fasteners, platforms, chocks, spacers, cabling, etc.;
provision of requirements for temporary work platforms or other support structures
required to ensure provision of preservation services, for example, provision of a
self-elevating work platform for periodic access to elevated fittings, gauges, man-
ways, etc.;
requirements for protection against, or insulation from, contact with other objects, for
example, padding or other protection for external tubing, fittings, or other impact-
sensitive structures or components;
clear physical delineation of temporary and longer-term storage areas supplemented
by hard and soft barriers, as required, to maintain a protective perimeter;
documented agreements with storage facility and transportation provider
management regarding security management, including, but not limited to, facility
access and egress control and control of access to project goods and materials
within facility boundaries or aboard vehicles or vessels; and
detailed procedures for inspection and testing to verify performance of preservation
procedures and to provide for timely notice and corrective action to maintain
preservation status.
3.8.3.18 The supplier’s preservation management programme scope shall encompass
management of preservation requirements, from initial transfer of ownership or management
responsibility to project scope of responsibility, through any period of temporary or longer-
term storage and through any period of transit, including transit for final delivery at point of
active use or installation.
3.8.3.19 The supplier’s preservation management programme shall clearly and unambiguously
address processes and procedures to ensure that storage and control of materials are
accomplished in accordance with manufacturer recommendations, specifications, and
project-specific requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3.20 The supplier’s preservation management programme shall incorporate special precautions
to address preservation and control of valves, electrical motors and components,
mechanical and rotating equipment, piping and fittings, instrumentation, flange faces,
gaskets, coatings, insulation, and other materials. Special precautions include, but are not
limited to, supplier-specified maintenance procedures related to engines, electric motors,
pumps, compressors, etc., such as periodic shaft rotation, engine turnover, lubrication, etc.
3.8.3.21 The supplier shall ensure that clear and unambiguous requirements for preservation of the
system, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented in purchase orders, work authorisations, and other
communications between the supplier and sub-suppliers.
3.8.3.22 Where sub-supplier expertise is utilised in determination of the preservation protocol,
supplier procurement processes shall ensure clear and unambiguous documentation of sub-
supplier input into preservation management programme requirements.
3.8.3.23 Supplier procurement shall ensure that preservation requirements for scope of work
systems, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented and that preservation requirements are efficiently and
effectively communicated to project logistics, construction management, quality, security,
and other project functional areas, as required, for efficient and effective implementation of
preservation requirements.
3.8.3.24 The supplier shall ensure comprehensive, clear, and unambiguous designation of sub-
supplier responsibility for execution of all preservation management programme elements,
including, but not limited to, all systems, processes, procedures, methods, ready access to
records, and provision of equipment, tools, or services essential to efficient and effective
execution of the preservation management programme.
3.8.3.25 The supplier shall ensure that preservation management programme responsibilities are
clearly and unambiguously defined within the project team and efficiently and effectively
implemented at all project scope of work locations. Inclusion of supplier and sub-supplier
scope of work in the development and implementation of a preservation management
programme shall be considered essential to efficient and effective preservation
management programme execution.
3.8.3.26 The supplier shall ensure clear and unambiguous designation of project team responsibility
for oversight and management of preservation management programme elements during
every stage of project development.
3.8.3.27 The supplier shall ensure that Eskom has free and unrestricted access to all preservation
records for inspection and audit.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.4 Quality Audits Related Conditions
3.8.4.1 The supplier shall maintain an accurate quality audit and related quality performance review
schedule and shall incorporate the current schedule as an attachment to the supplier CQP.
3.8.4.2 The supplier’s quality audit and related quality performance review schedule development
process shall be designed to incorporate consideration of information generated by
previously conducted audits and reviews, by input from project risk management evaluations
(risk register), or from Eskom or sub-supplier subject matter expertise.
3.8.4.3 Eskom reserves the right to oversee supplier audit programmes by participating in selected
audits as an observer and by assessing the supplier during key work stages. Eskom will
coordinate with the supplier to develop an oversight schedule aligned with the supplier’s
audit schedule.
3.8.4.4 Eskom will have the right to obtain access to any audit reports of audits performed by the
supplier reflected in the audit programme.
3.8.4.5 Eskom reserves the right to conduct independent quality audits, scheduled and
unscheduled, during all phases of the contract. The supplier shall provide all resources to
support these activities.
3.8.4.6 Eskom shall be given access at all reasonable times before, during, and after manufacture
and before delivery, construction, erection, and commissioning to measure, test, and inspect
the products and workmanship, as necessary, at the supplier’s premises and at Eskom sites.
3.8.4.7 The supplier shall obtain access for Eskom to measure, test, witness tests, and inspect
products that are being manufactured by any sub-supplier. This includes surveillances.
3.8.4.8 The assessments and audits shall be carried out on all new suppliers and their sub-
suppliers.
3.8.4.9 Eskom shall have the right to participate in, or request that, a technical investigation be
launched and conducted at the supplier’s and sub-suppliers’ premises or other sites when
risk to Eskom products or service deliverables is identified.
3.8.4.10 Qualification requirements for supplier and sub-supplier personnel engaged in conducting
quality audits and related quality performance reviews shall be defined in the supplier CQP
and shall be in compliance with the Project Quality Personnel Qualification Specification.
3.8.5 Management of Nonconformities and Nonconforming Outputs Identified by Eskom
3.8.5.1 Nonconformity reports raised by Eskom and issued against the supplier shall be investigated
by the supplier as a matter of urgency in order to determine the root cause, corrective action
measures, as required, with implementation time frames.
3.8.5.2 A formal response shall be prepared in respect of the defined criteria and submitted to
Eskom for its review, evaluation, and acceptance, within a maximum of 14 calendar days
from the date of issue of the nonconformity and should be aligned with the site
requirements/procedure.
3.8.5.3 Eskom may, at its discretion, request a response sooner and, in any case, before the
supplier proceeding with any pending/further intervention or corrective action, as may be
required by Eskom.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.5.4 Should Eskom or its inspection authority/agency identify any nonconforming products during
the conduct of its audits/surveillances/inspections, the supplier shall be deemed to be in
breach of contract and shall be held liable for any repair, rework, and/or associated
replacement costs. The supplier may, in such instances, also be held liable for the full costs
associated with the conducting of follow-up audits/surveillances/inspections.
3.8.5.5 The nature, magnitude, and/or frequency of nonconformity and inspection defect/rejection
reports raised by Eskom or its appointed inspection authority/agency shall form the basis of
any action to rescind/withdraw the supplier’s qualification status.
3.8.5.6 Nonconforming outputs identified by Eskom shall be documented via a NC Report and
issued to the suppliers via the contract communication protocol. The suppliers shall
investigate the matter and respond in writing to Eskom of disposition within the stated
contractual conditions.
Note: The dates for the disposition should align to contractual conditions.
3.8.5.7 Eskom shall identify repeat deficiencies as systematic failures of the supplier’s QMS and
shall notify the supplier of the trends. Eskom can initiate an internal audit to highlight the
system failures. The supplier with raise a Corrective Action Report and undertake Root
Cause Analysis. In such cases, QMS rectification and/ or update measures shall be taken
immediately.
3.8.5.8 Should the Supplier fail to respond and rectify nonconforming products within stipulated
contractual conditions. The Project Manager should apply contractual remedies in
accordance with Fidic/ NEC contract.
3.8.5.9 Repeated Nonconformities; if there are any identified repeat nonconformities from the same
supplier within a period of 6 months or less. This must then be escalated to the management
review committees of the BU/ OU/ Cluster/ or Divisions for adjudication. If not resolved, then
the matter must be escalated to the supplier review committee for recommendation.
3.8.6 Special Processes
The following requirements shall be applicable as well as additional requirements as specified in the
scope of work for the provision of the following special process services:
3.8.6.1 The supplier shall ensure that all processes which require that procedures be pre-qualified
or work methods and operators tested and qualified are controlled and all steps followed
before the work can commence.
3.8.6.2 This typically covers such activities as welding, non-destructive testing, special fabrication
techniques, coating, painting, etc.
3.8.6.3 All special processes (procedures and processes) shall be submitted for review and
acceptance by Eskom, accredited or certified agency. No work shall commence until these
are accepted.
3.8.6.4 Where applicable, a relevant Management System for the special process shall be certified
or approved by an accredited body and proof of certification shall be submitted to Eskom for
review. An example for this will be the Welding Management System based on ISO 3834.
3.8.6.5 Where samples are required for acceptance, these shall be submitted to Eskom for review
and acceptance.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.6.6 The supplier shall ensure that all operators are suitably qualified for these processes in
accordance with the procedures, processes and/ or applicable standards/ codes.
3.8.6.7 The records of qualification of procedures, processes and operators shall be maintained by
the supplier in accordance with the applicable procedure or code and these made available
to Eskom at all times.
This document has been seen and accepted by:
Name Designation
Kerseri Pather General Manager: Risk and Sustainability
Lenock Meyer Acting Senior Manager: Quality Management
Pamela Dondashe Middle Manager: Quality Assurance
Mandla Mkhwanazi Middle Manager: SHEQ Procurement and Supply Chain Management
Suzette Manthe Senior Advisor: Quality Performance and Planning
Lorna Ndlela Middle Manager: Eskom Document and Records Management
Date Rev. Compiler Remarks
October 2021 3 SA Sambo Specification was due for revision and in addition, to
align the requirements with the latest Eskom business
processes and systems.
October 2018 2 SA Sambo Specification reviewed to be aligned with the
requirements of ISO 9001:2015
March 2016 1 SA Sambo Specification was due for revision and also to
repackage the requirements and tender returnable
documents into four categories.
December 2011 0 A Hunter New document
The following people were involved in the development of this document:
Andrew Else
Bongi Tshabalala
Feziwe Mogamisi
Lesego Garegae
Patrick Thwane
Xolani Zuma
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Eskom Operational Quality Forum Members
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Quality Management
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)equipment, supplying commodities and providing specialised services shall be subjected to the capability and capacity assessment. Generation Level 1 & 2 plant Transmission and Distribution Power Plant & Control Plant Mega Projects
Special Conditions
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)3.8.1 Rights of Access
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
240-109253698 CQP Template 2021.docx
This document is a Contract Quality Plan template for the refurbishment of Kriel PS Generator Circuit Breaker Compressor Plant Control Circuit at Units 1 & 4 over 12 months. It outlines the required quality management framework, not the full tender. Bidders must use this template to demonstrate their quality processes.
Technical evaluation strategy.pdf
Eskom is seeking a contractor for the refurbishment of Generator Circuit Breaker (GCB) Compressor Plant Control Circuits at Units 1 & 4 of Kriel Power Station over a 12-month period. The tender uses a two-stage technical evaluation: mandatory gatekeeper criteria (pass/fail) followed by weighted qualitative criteria (minimum 75% threshold). The work involves electrical maintenance services for overhaul of compressor controls on MV/LV switchgear.
Eskom - Standard Conditions of Tender - 30 January 2025 (1).pdf
17. RT284 Annex C Local Content Declaration - Summary Schedule.pdf
CIDB Ann G Compulsory Enterprise Questionnaire_.pdf
18. RT284 Annex D Imported Content Declaration.pdf
18kV Breaker Compressor Controls Scope.pdf
ESKOM seeks a contractor for the refurbishment of Generator Circuit Breaker (GCB) Compressor Plant Control Circuits at Kriel Power Station Units 1 & 4. The 12-month project involves engineering, design, manufacturing, factory acceptance testing, delivery, installation, site acceptance testing, and commissioning of new electrical control panels for Compressor A and B, including replacement of pressure switches, water traps, pressure gauges, and associated cabling. Work must be performed sequentially to maintain plant availability.
240-68099512 Form A_Cat 3_ Rev 9.docx
This is a tender for the refurbishment of the Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 of Kriel Power Station, issued by Eskom. The contract duration is 12 months. The document is a Supplier Quality Requirements form that tenderers must complete and sign, indicating their compliance with Eskom's specification 240-105658000 and the ISO 9001 standard.
CIDB Standard Conditions of Tender Ann C.pdf
E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf
Tender for refurbishment of Kriel PS Generator Circuit Breaker Compressor Plant Control Circuit at Units 1 & 4 over 12 months, requiring mandatory e-tendering training acknowledgement submission.
safety file checklist.docx
Eskom tender for refurbishment of Kriel Power Station Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a 12-month period. The document provided is primarily an OHS/Health & Safety compliance assessment checklist that contractors must complete to demonstrate regulatory compliance before/during contract execution.
E-tendering Help Manual for supplier - 27 January 2025.pdf
This document is not the actual tender specification but rather Eskom's eTendering System User Manual. It provides instructions for suppliers on how to register, log in, and electronically submit tender documents, including for the 'Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4' tender. The tender itself closes on August 7, 2026.
She Requirements high risk.docx
Eskom tender for refurbishment of Kriel Power Station's Generator Circuit Breaker Compressor Plant Control Circuit at Units 1 & 4 over 12 months, with strong emphasis on occupational health and safety compliance.
240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP) rev 2.docx
This document outlines the Quality Control Plan (QCP) for the refurbishment of the Generator Circuit Breaker Compressor Plant Control Circuit at Units 1 & 4 of Kriel Power Station. The tender is issued by ESKOM for a 12-month contract. The document is a framework specifying inspection, testing, and approval protocols rather than the full tender scope of work.
RER0371 - Environmental Evaluation-Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a period of 12 months.pdf
ESKOM tender for refurbishment of Kriel Power Station's Generator Circuit Breaker Compressor Plant Control Circuit at Units 1 & 4 over 12 months. The document is an Environmental Evaluation Form requiring comprehensive environmental management documentation and certifications.
CIDB SBD9 SCM_certificate_independent_bid_determination.pdf
This document is the SBD 9 Certificate of Independent Bid Determination, a mandatory declaration form for bidders on an Eskom tender for the 12-month refurbishment of the Generator Circuit Breaker Compressor Plant Control Circuit at Kriel Power Station Units 1 & 4. Its primary purpose is to prevent collusive bidding by requiring a sworn statement that the bid was prepared independently.
240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsx
Eskom tender for refurbishment of Kriel Power Station Generator Circuit Breaker Compressor Plant Control Circuit at Units 1 & 4 over 12 months. This is a Category 3 tender requiring documented Quality Management System compliance with ISO 9001 standards, with evaluation weighted across five quality sections.
Hazard list signed.pdf
Tender for refurbishment of Kriel Power Station Generator Circuit Breaker Compressor Plant Control Circuit at Units 1 & 4 over 12 months. Focus on safety compliance with extensive hazard management.
Eskom Supplier Integrity Pact - 02 June 2023 (2).pdf
This document is an Eskom Supplier Integrity Pact, not the main tender document. It outlines ethical and compliance requirements for suppliers participating in Eskom procurement processes. The pact mandates integrity, prohibits corruption and conflicts of interest, and requires the signing of an Integrity Declaration Form as part of the tender submission for the 'Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4'.
CIDB SBD4 SCM_declaration_interest.pdf
ESKOM tender for refurbishment of Kriel Power Station Generator Circuit Breaker Compressor Plant Control Circuit at Units 1 & 4 over 12 months. The document provided is SBD 4 - Declaration of Interest form requiring disclosure of relationships with state employees involved in bid evaluation.
she spec refurbishment of Kriel PS Generator circuit breaker signed.pdf
Eskom Kriel Power Station tender for refurbishment of Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for 12 months. This document is the OHS Specification (Template R, High Risk) outlining mandatory health, safety, and environmental requirements for contractors.
240-105658000 Supplier Quality Management Specification (3).pdf
19. RT284 Annex E Local Content Declaration - Supporting Schedule to Annex C.pdf
Annexure B.docx
This is an Eskom OHS (Occupational Health and Safety) Acknowledgement Form (Annexure B) that forms part of a tender for the refurbishment of Kriel Power Station Generator Circuit Breaker Compressor Plant Control Circuit at Units 1 & 4 for 12 months. The form requires contractors/suppliers to acknowledge understanding and compliance with Eskom's OHS legal requirements, standards, policies, and procedures.
Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.xls
The document appears to be a corrupted or incorrectly processed Excel/VBA project file related to a tender for the 'Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a period of 12 months' issued by ESKOM. The core tender information is minimal, but the bulk of the content consists of garbled VBA macro code, sheet names, and project metadata, suggesting the file is a complex, macro-enabled workbook for managing a contractor application or evaluation process, not the tender specification itself.
Eskom General Conditions of Purchase - 31 May 2024 (3).pdf
Eskom tender for refurbishment of Kriel Power Station Generator Circuit Breaker Compressor Plant Control Circuit at Units 1 & 4 over 12 months. The document outlines general purchase conditions governing supplier obligations, payment terms, delivery, acceptance, warranties, and legal requirements.
Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx.doc
This document is not the main tender specification but a PAYE Questionnaire for service contracts with Eskom. It is used to determine the tax classification of contractors (Independent Contractor, Personal Service Provider, Labour Broker, or Dependent Contractor) for the 2026/2027 tax year, to establish whether Employees' Tax (PAYE) must be withheld from payments. The tender title indicates the actual work is 'Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a period of 12 months,' but the provided content is solely the tax compliance form.
Invitation to Tender GCB.pdf
Eskom invites tenders for the refurbishment of Kriel Power Station Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a 12-month period. Tender E2192GXMPKRIR closes on 07 August 2026 at 10h00. Compulsory clarification meeting on 28 July 2026 via MS Teams and site visit on 29 July 2026 at Kriel Power Station. CIDB grading 7EP required. Functionality evaluation with 70% minimum threshold. Local content target 100%. CSDG 0.25%. Submission via Eskom E-tendering portal only.
To download these documents and access AI-powered analysis, visit the main tender page.
Organization
EskomContact Person
Sibusiso Sithole
Phone
011-800-6223
[email protected]
Address
Ogies Bethal Road - Kriel - Kriel - 2271
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
29
Last checked
14 Jul 2026
AI status
Enhanced
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Eskom is South Africa's primary electricity supplier, managing generation, transmission, and distribution.
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubEvaluation Criteria
Source: safety file checklist.docx (unknown)Contractor must be a legally registered entity with valid COIDA registration (letter of good standing), ability to appoint qualified competent persons for all specified high-risk activities per OHS Act and regulations, proven capability to develop and implement Health & Safety Plans, risk assessments, and safe work procedures for electrical/mechanical refurbishment work in operational power station environment, compliance with Eskom-specific procedures (32-95, 32-345, 32-418, 32-520, 32-726), and capacity to maintain comprehensive safety documentation and records for 12-month duration.
Technical Specifications
Source: safety file checklist.docx (unknown)The document is a safety file checklist, not a technical specification for the tender. It details contractor safety management requirements for Eskom sites. Key points for bidders:
Compliance Requirements
Source: safety file checklist.docx (unknown)The document is a safety compliance checklist. Key legal and registration requirements for bidders:
Description
Source: 240-68099512 Form A_Cat 3_ Rev 9.docxTenderer must complete and sign the form to acknowledge and accept Eskom Supplier Quality Requirements as per 240-105658000 Specification and ISO 9001 Standard. This includes adherence to all applicable clauses and quality principles outlined in the specification and standard.
Submission Guidelines
Source: 240-68099512 Form A_Cat 3_ Rev 9.docx (unknown)Returnable Documents: Tenderer must complete and sign the form to acknowledge and accept Eskom Supplier Quality Requirements as per 240-105658000 Specification and ISO 9001 Standard.
Evaluation Criteria
Source: 240-68099512 Form A_Cat 3_ Rev 9.docx (unknown)To be eligible, tenderers must: 1) Be capable of meeting the 'Category 3' pre-contract award quality requirements as defined in clause 3.5.4 of specification 240-105658000. 2) Have a quality management system aligned with ISO 9001:2015. 3) Accept Eskom's stipulated rights and conditions for quality oversight and audits. 4) Provide details of their appointed Quality Representative.
Technical Specifications
Source: 240-68099512 Form A_Cat 3_ Rev 9.docx (unknown)Tenderer must comply with Eskom Supplier Quality Requirements as per 240-105658000 Specification and ISO 9001 Standard. Key clauses include: Pre-Contract Award Quality Requirements (Category 3 applies), Contract Execution, Supplier Quality Performance Monitoring Phase, Eskom Rights of Access, Rights to Information, Preservation, Quality Audits, and Management of Nonconformities.
Compliance Requirements
Source: 240-68099512 Form A_Cat 3_ Rev 9.docx (unknown)Compliance with Eskom Supplier Quality Requirements (240-105658000 Specification) and ISO 9001 Standard is mandatory. Quality principles such as Customer Focus, Leadership, Engagement of People, Process Approach, Improvement, Evidence-Based Decision Making, and Relationship Management must be adhered to.
Description
Source: Eskom Supplier Integrity Pact - 02 June 2023 (2).pdfContact Information
Source: Eskom Supplier Integrity Pact - 02 June 2023 (2).pdf (unknown)Submission Guidelines
Source: Eskom Supplier Integrity Pact - 02 June 2023 (2).pdf (unknown)Returnable Documents
Source: Eskom Supplier Integrity Pact - 02 June 2023 (2).pdf (unknown)Evaluation Criteria
Source: Eskom Supplier Integrity Pact - 02 June 2023 (2).pdf (unknown)The pact applies to all existing and potential suppliers (natural or juristic persons) doing or seeking to do business with Eskom. Key eligibility condition is adherence to this Integrity Pact and its ethical standards. Suppliers must be registered or registerable on the Eskom Vendor Database.
Technical Specifications
Source: Eskom Supplier Integrity Pact - 02 June 2023 (2).pdf (unknown)Compliance Requirements
Source: Eskom Supplier Integrity Pact - 02 June 2023 (2).pdf (unknown)Contractual Terms
Source: Eskom Supplier Integrity Pact - 02 June 2023 (2).pdfSpecial Conditions
Source: Eskom Supplier Integrity Pact - 02 June 2023 (2).pdf (unknown)Description
Source: NEC GCB.pdfContact Information
Source: NEC GCB.pdf (unknown)Returnable Documents
Source: NEC GCB.pdf (unknown)Evaluation Criteria
Source: NEC GCB.pdf (unknown)Contractor must be a legal entity able to enter a contract under South African law. Must have, or be able to obtain, necessary site access permits and safety file approval. Must comply with Broad-Based Black Economic Empowerment (B-BBEE) requirements; any degradation of status allows Eskom to renegotiate or terminate. If a joint venture, parties are jointly and severally liable. Contractor cannot cede/delegate/assign rights without Eskom's written consent. CIDB registration may be applicable (as indicated in the Offer form).
Technical Specifications
Source: NEC GCB.pdf (unknown)Experience & Qualifications
Source: NEC GCB.pdfQuality Management
Source: NEC GCB.pdfPricing Schedule
Source: NEC GCB.pdfFinancial Requirements
Source: NEC GCB.pdf (unknown)Compliance Requirements
Source: NEC GCB.pdf (unknown)B-BBEE Requirements
Source: NEC GCB.pdf (unknown)Health & Safety
Source: NEC GCB.pdfEnvironmental
Source: NEC GCB.pdfContractual Terms
Source: NEC GCB.pdfRequirements
Source: NEC GCB.pdf (unknown)Section
Source: NEC GCB.pdfDescription
Source: Invitation to Tender GCB.pdfImportant Dates
Source: Invitation to Tender GCB.pdf (RFP)Contact Information
Source: Invitation to Tender GCB.pdf (RFP)Submission Guidelines
Source: Invitation to Tender GCB.pdf (RFP)Evaluation Criteria
Source: Invitation to Tender GCB.pdf (RFP)Tenderers must: not be restricted from doing business with Eskom or State-Owned Companies; not have nationality of sanctioned countries; not submit more than one tender; if JV/consortium, agreement must state joint and several liability; no conflict of interest; tender signed by authorized persons; not on National Treasury restricted list or Tender Defaulters list; not restricted by Eskom; not subcontract 100% of scope. Must have CIDB grading 7EP or higher. Must attend compulsory clarification meeting and site visit. Must provide proof of registration as electrical contractor with Department of Employment and Labour. Must demonstrate 5 executed MV/LV switchgear projects with references and signed QCP reports.
Technical Specifications
Source: Invitation to Tender GCB.pdf (RFP)Methodology
Source: Invitation to Tender GCB.pdfExperience & Qualifications
Source: Invitation to Tender GCB.pdfQuality Management
Source: Invitation to Tender GCB.pdfPricing Schedule
Source: Invitation to Tender GCB.pdfFinancial Requirements
Source: Invitation to Tender GCB.pdf (RFP)Compliance Requirements
Source: Invitation to Tender GCB.pdf (RFP)Health & Safety
Source: Invitation to Tender GCB.pdfEnvironmental
Source: Invitation to Tender GCB.pdfContractual Terms
Source: Invitation to Tender GCB.pdfSection
Source: Invitation to Tender GCB.pdfImportant Dates
Source: Eskom - Standard Conditions of Tender - 30 January 2025 (1).pdf (TENDER){"closingTime":"2.2","briefingSession":"{"date":null,"time":null,"venue":"tend a site visit and/or clarification meeting that is stipulated as being","is_compulsory":true}"}
Briefing Session
Source: Eskom - Standard Conditions of Tender - 30 January 2025 (1).pdf (TENDER)Site visit and / or clarification meeting 2.15 Tenderers must attend a site visit and/or clarification meeting that is stipulated as being compulsory in order to familiarise themselves with the proposed work, services, supply, location or similar. Failure to attend a clarification meeting or site visit that is identified as compulsory will result in disqualification from participation. Details of the meeting(s) are stated in the Tender Data. Tenderers are entitled to ask
Returnable Documents
Source: Eskom - Standard Conditions of Tender - 30 January 2025 (1).pdf (TENDER)Eskom may also request that an additional copy of the original tender is submitted in an electronic format.
Evaluation Criteria
Source: Eskom - Standard Conditions of Tender - 30 January 2025 (1).pdf (TENDER)are submitted and accessible for downloading/evaluation without any challenges as well as
It must be noted that Eskom will not measure a criterion twice in the different evaluation
Functionality 3.13 If functionality is a criterion, tenderers will be scored against the functionality criteria and
further evaluation.
(if applicable) financial risk to Eskom in the execution of the contract. During evaluation of a tenderer’s
Evaluation of Price 3.15 Evaluate the Price in accordance with the criteria/requirements in the Tender Data. Factors
the evaluation Price.
but will score zero under PPPFA point allocation.
Evaluation of 3.18 Score the Specific Goals with reference to the supporting documentation in the tender. If a
Specific Goals tenderer fails to meet Specific Goals and/or to submit the required proof/supporting
will score zero points for Specific Goals within the 90/10 or 80/20 allocation of points.
Ranking of tenders 3.19 According to the PPPFA, Eskom will add the score for Pricing and the Specific Goals
Objective criteria 3.20 A contract may be awarded to a tenderer that did not score the highest points only in
must stipulate the Objective Criteria in the Invitation to Tender. Functionality and any
element of the B-BBEE scorecard may not be used as Objective Criteria.
Reverse e-Auction 3.21 Reverse e-auction is an electronic system that utilises the 90/10 and 80/20 Price and
Preference point systems, and which is intended to achieve competitive pricing. Eskom
(NT instructions, content and/or production by the dtic, PPPFA Regulations; Amended B-BBEE Codes, COIDA;
CIDB, PPPFA etc) OHS Act; Eskom’s requirements for Safety, Health, Environment and Quality (SHEQ) and any other
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
Quality Contract Award. All costs and personnel associated with SHEQ must be reflected in the
However, for the purposes of PPPFA point allocation: if no B-BBEE certificate/affidavit is
Technical Specifications
Source: Eskom - Standard Conditions of Tender - 30 January 2025 (1).pdf (TENDER)Supply Chain
Management Procedure 32-1034. Any addenda to an issued Invitation to Tender will be
published or issued in the same way as the Invitation to Tender was and will form part of the
Invitation to Tender documents.
Communication 1.5 Every communication between Eskom and a tenderer shall be made to or from the Eskom
Representative only, in w
Quality Management
Source: Eskom - Standard Conditions of Tender - 30 January 2025 (1).pdfof a tenderer.
Cost of tendering 2.6 Accept that Eskom will not compensate the tenderer for any costs incurred in the preparation
and submission of a tender, including the costs of any testing necessary to demonstrate that
aspects of the tender satisfy the evaluation criteria, or the negotiation of any contract.
Submitting a tender 2.7 Check the Invitation to Tender documents on receipt and notify the Eskom representative of
any discrepancy or omitted documents. The Acknowledgement Form must be completed
and submitted with the tender and must clearly state if the tender is for the whole or part of
the works, services or supply identified in the specification and/or works information by
Pricing Schedule
Source: Eskom - Standard Conditions of Tender - 30 January 2025 (1).pdfreasonable time for tenderers to make consequential adjustments to their tenders before
the closing date and time for submission.
In writing’ means hand-written, typed, type-written, printed or electronically made, and that
results in a permanent record.
Insurance 2.17 The extent (if any) of insurance provided by Eskom may not be for the full cover required in
the conditions of contract. The tenderer is advised to seek qualified advice regarding
insurance.
Pricing the tender 2.18 Include in the rates, prices, and the tendered total of the Prices all duties, taxes (including
VAT), and other levies payable by the tenderer if successful. Such duties, taxes and levies
are those applicable 14 (fourteen) days prior to the closing date and time for tender
submission.
2.19 Provide rates and Prices that are fixed for the duration of the contract and are not subject to
contract price adjustment except as provided for in the Invitation to Tender.
2.20 State the rates and Prices in South African Rand unless instructed otherwise in the Invitation
to Tender. The selected conditions of contract may provide for part payment in other
currencies. Therefore, submit Rates/Prices in Rands in accordance with the exchange rate
and base date as stipulated in the Invitation to tender.
Alterations to 2.21 May not make any alterations or additions to the tender documents, other than for purposes
documents of complying with instructions issued by the Eskom Representative or if necessary to correct
errors made by the tenderer. All such alterations shall be initialed by all signatories to the
tender. Corrections may not be made using correction fluid, correction tape or the like.
Alternative tenders 2.22 Submit alternative tenders only if a main tender is also submitted, and only if the submission
of alternative tenders is permitted by the Invitation to Tender. Accept that an alternative
tender may be based only on the criteria stated in the Tender Data.
Clarification and 2.23 Provide clarification and documents as may be required by the Eskom Representative
correction of Prices during the evaluation of tenders. However, documents identified as mandatory tender
after tender returnables that are required to be submitted at the closing date and time for tender
submission submission will not be requested and may not be submitted after the closing date and time.
phases, as this is regarded as ‘double dipping’.
Designated 3.12 Tenderers are also required to submit information on designated material and
materials and thresholds no later than contract award. If this information is not completed and
thresholds submitted as indicated in the Invitation to Tender, your tender will not be considered for
contract award
Functionality 3.13 If functionality is a criterion, tenderers will be scored against the functionality criteria and
requirements will be required meet the minimum threshold stated in the Tender Data to proceed to
further evaluation.
Financial analysis 3.14 Eskom has to determine the risk of doing business with a supplier who may pose a
(if applicable) financial risk to Eskom in the execution of the contract. During evaluation of a tenderer’s
financial statements, Eskom will attempt to identify mitigating factors or requirements for
the tenderer to meet, if such factors/requirements exist in the tender’s context. However,
should suitable mitigating factors not exist in the tender’s context or should mitigating
factors exist but be insufficient or if the risk is considered to be too high or should the
tenderer not agree with the mitigating factors, the tenderer will not be considered for
award.
Evaluation of Price 3.15 Evaluate the Price in accordance with the criteria/requirements in the Tender Data. Factors
such as CPA, FOREX, commodity exposure, unconditional discounts, technical
adjustment, PV and forecasted rates of invoicing are taken into account when determining
the evaluation Price.
Arithmetical errors 3.16 Check responsive tenders for arithmetical errors. If there is a discrepancy between an
amount in figures and the amount in words, the amount in words shall prevail.
Check the highest-ranked tenders for the following errors or omissions: -
(a) the misplacement of the decimal point in any unit rate; or
(b) omissions in completing the pricing schedule or bill of quantities, or
(c) arithmetical errors in line-item totals that are the result of the incorrect multiplication
of a unit rate and a quantity in a bill of quantities or schedule of prices; or
(d) arithmetical errors that are the result of the incorrect addition of the prices.
will request the tenderer to either confirm the prices as tendered or to accept the
corrected prices.
Where the tenderer elects to confirm the prices as tendered; Eskom will correct the error
as follows: -
(a) If a bill of quantities or pricing schedule applies and there is an error in the line-item
total that is the result of an error in multiplying the unit rate and the quantity, the line-
item total shall prevail, and the rate shall be corrected.
(b) Where there is a misplacement of the decimal point in the unit rate, the line-item total
as quoted shall prevail, and the unit rate shall be corrected.
(c) Where there is an error in the total of the prices that is the result either of other
corrections required by the checking process or in the tenderer’s addition of prices,
the total of the prices shall prevail, and the tenderer shall be asked to revise the
selected item prices (and their rates if a bill of quantities applies) to result in the
tendered total of the prices.
documentation by closing date and time of tender submission, the tenderer will not be
disqualified if otherwise evaluated as acceptable in all other criteria; however, the tenderer
will score zero points for Specific Goals within the 90/10 or 80/20 allocation of points.
Ranking of tenders 3.19 According to the PPPFA, Eskom will add the score for Pricing and the Specific Goals
together and rank the suppliers from the highest to the lowest.
Objective criteria 3.20 A contract may be awarded to a tenderer that did not score the highest points only in
accordance with Section 2(1) (f) of the Preferential Procurement Policy Framework Act,
must stipulate the Objective Criteria in the Invitation to Tender. Functionality and any
element of the B-BBEE scorecard may not be used as Objective Criteria.
Compliance Requirements
Source: Eskom - Standard Conditions of Tender - 30 January 2025 (1).pdf (TENDER)CSD report or as per certificate/affidavit provided
CSD number/CSD report) must be provided at the closing date and time for
CSD number or B-BBEE certificate/affidavit will need to be
B-BBEE Details: kom Representative and
Agreement to sign the contract documents.
Proof of authority 2.25 Where an agent submits a tender on behalf of a principal, an authenticated copy of the
to act as agent authority to act as an agent of the tenderer must be submitted as a tender returnable.
Compliance with 2.26 Comply with relevant legislation and regulatory instruments such as Instruction Notes issued
relevant legislation by National Treasury, CIDB Regulations for construction works; materials designated for local
(NT instructions, content and/or production by the dtic, PPPFA Regulations; Amended B-BBEE Codes, COIDA;
CIDB, PPPFA etc) OHS Act; Eskom’s requirements for Safety, Health, Environment and Quality (SHEQ) and any other
applicable legislation or regulatory instruments indicated in the Invitation to Tender.
Proof of Safety, 2.27 Tenderers are required to provide proof to the satisfaction of Eskom that safety, health,
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
Environment and closing date and time for tender submission stipulated in the Invitation to Tender and/or
Quality Contract Award. All costs and personnel associated with SHEQ must be reflected in the
requirements tender.
CIDB 2.28 Where the Tender Data has stipulated CIDB grading/s as a qualification criterion, tenderers
are required to be registered with the Construction Industry Development Board at the
closing date and time for submission of tenders or to be capable of being so registered
within twenty-one (21) working days from the closing date and time for submission of
tenders.
Where CIDB is applicable; proof of registration on CIDB is mandatory at the closing date
and time for tender submission. Should this not be received as stipulated
B-BBEE Requirements
Source: Eskom - Standard Conditions of Tender - 30 January 2025 (1).pdf (TENDER)Contract Participation Goals (CPG) 2.30 The Contractor shall achieve in the performance of the contract the Contract Participation Goals (CPG) relating to the engagement of targeted enterprises as established in the CIDB standard for indirect targeting for enterprise development through Construction works contracts (published in Government Gazette No. February 2013). The requirements of a contract participation goal relating to the engagement of targeted enterprises as established in the aforesaid standard applies to: construction works contracts in the General Building (GB) and to Civil Engineering (CE) classes of construction works; construction works contracts of an estimated minimum project duration of 6 months; and construction works contracts in which at least 25% of the main contract could reasonably be expected to be subcontracted out in one or more of the following CIDB classes of construction works: Civil Engineering (CE) Electrical Engineering Work (EB) ) General Building Works (GB) ) Mechanical Engineering (ME)
Health & Safety
Source: Eskom - Standard Conditions of Tender - 30 January 2025 (1).pdftenderers that Eskom has identified. A sole source and a single source are regarded as a
tenderer that meets the requirements stated in the Eskom Procurement and Supply Chain
Management Procedure 32-1034. Any addenda to an issued Invitation to Tender will be
published or issued in the same way as the Invitation to Tender was and will form part of the
Proof of authority 2.25 Where an agent submits a tender on behalf of a principal, an authenticated copy of the
to act as agent authority to act as an agent of the tenderer must be submitted as a tender returnable.
Compliance with 2.26 Comply with relevant legislation and regulatory instruments such as Instruction Notes issued
relevant legislation by National Treasury, CIDB Regulations for construction works; materials designated for local
(NT instructions, content and/or production by the dtic, PPPFA Regulations; Amended B-BBEE Codes, COIDA;
CIDB, PPPFA etc) OHS Act; Eskom’s requirements for Safety, Health, Environment and Quality (SHEQ) and any other
applicable legislation or regulatory instruments indicated in the Invitation to Tender.
Proof of Safety, 2.27 Tenderers are required to provide proof to the satisfaction of Eskom that safety, health,
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
requirements tender.
CIDB 2.28 Where the Tender Data has stipulated CIDB grading/s as a qualification criterion, tenderers
are required to be registered with the Construction Industry Development Board at the
closing date and time for submission of tenders or to be capable of being so registered
within twenty-one (21) working days from the closing date and time for submission of
tenders.
Where CIDB is applicable; proof of registration on CIDB is mandatory at the closing date
and time for tender submission. Should this not be received as stipulated in the Invitation to
Tender; the tender will be disqualified. However, in the event that, at the closing date and
time for tender submission, only proof of application for registration on CIDB is available,
then this must be submitted by the closing date and time for tender submission, while the
actual proof of CIDB registration (printout from CIDB database) must be submitted by
contract award
Contract Skills 2.29 If the tenderer is awarded a contract, it, as Contractor, shall achieve in the performance of
Development Goal the contract the Contract Skills Development Goals (CSDG) established in the CIDB
(CSDG) Standard for Developing Skills through Infrastructure Contract (published in GN 1779,
Government Gazette No. April 2023)
that has a duration of 12 months or more, and to:
a contract of R5 million or more, in the case of a professional service or service contract
or an order issued in terms of such a contract; or
a CIDB grading designation of grade 7 or higher, in case of an engineering and
construction works, or design and build contract or an order issued in terms of such a
contract.
Contract 2.30 The Contractor shall achieve in the performance of the contract the Contract Participation
Participation Goals Goals (CPG) relating to the engagement of targeted enterprises as established in the CIDB
(CPG) standard for indirect targeting for enterprise development through Construction works
contracts (published in Government Gazette No. February 2013).
enterprises as established in the aforesaid standard applies to:
construction works contracts in the General Building (GB) and to Civil Engineering (CE)
classes of construction works;
construction works contracts of an estimated minimum project duration of 6 months; and
construction works contracts in which at least 25% of the main contract could reasonably
be expected to be subcontracted out in one or more of the following CIDB classes of
construction works:
Civil Engineering (CE)
Electrical Engineering Work (EB)
) General Building Works (GB)
) Mechanical Engineering (ME)
2.31 Eskom may disqualify a tender if it is found that the tenderer has misrepresented or
falsified any information, certificate, affidavit or document. Eskom will report any fraud
in relation to a tenderer’s B-BBEE certificate/affidavit, or evidence of ‘fronting’ as
defined in the B-BBEE Act , as amended, to the B-BBEE Commission. The
tenderer will be suspended from business with any State-Owned Company for up to 10
years and may even be sentenced to jail.
2.32 Tenderers are also required to complete fully and submit the SDL&I Undertaking
(annexure to the Invitation to Tender) by no later than contract award. If the SDL&I
Respond 3.1 Respond to a request for clarification that Eskom receives before the closing date for
clarification clarification or queries. Eskom’s responses will be published to all tenderers in the same
manner the Invitation to Tender documents were issued. It is the tenderers’ responsibility
to check the Eskom Tender Bulletin and NT e-Tender Portal regularly for updated
responses to clarifications.
Issue Addenda 3.2 If necessary and prior to the closing date and time for tender submission, amend, amplify, or
add to the Invitation to Tender documents by way of Addenda published in the same
platform that the Invitation to Tender was issued. It is the tenderers’ responsibility to
check the Eskom Tender Bulletin and NT e-Tender Portal regularly for Addenda.
electronically. The Eskom Representative will publish the names of all tenderers received
on the Eskom Tender Bulletin and NT e-Tender Portal.
Tender Prices 3.5 Eskom will announce the names of the tenderers. Prices may be announced if so, stated
in the Tender Data.
Non-disclosure 3.6 Unless required by law, Eskom will not disclose information relating to the evaluation and
comparison of tenders and recommendations for the award of a contract to tenderers or to
any other person not officially concerned with the tender process until after the tender
award.
Grounds for 3.7 Reject a tender if Eskom establishes that there is proof that the tenderer influenced the
rejection processing of tenders or the awarding of the contract, the existence of collusion and/or bid
rigging, and/or that the tenderer has participated in any fraudulent/illegal activity in
connection with the Invitation to Tender.
Clarification of a 3.8 Obtain clarification from a tenderer in respect of any matter in the tender that may not be
tender clear or that could give rise to ambiguity in a contract arising from this tender if the matter
were not to be clarified. A document that the Invitation to Tender identifies as a mandatory
tender returnable that is required to be submitted at the closing date and time for tender
submission will not be requested, but Eskom may seek clarity on it.
may utilise reverse e-auction in certain Enquiries. Where reverse e-auction will be utilised,
this will be indicated in the respective Invitation to Tender and the reverse e-auction
supporting documents will be issued in the Invitation to Tender. Tenderers will be required
to submit a complete tender that does not contain Prices. If a tenderer has included prices
in its tender, the prices will not be considered.
Acceptance of 3.22 Notify Eskom's acceptance to the successful tender before the expiry of the validity period
tender or agreed additional validity period. Inform the successful and unsuccessful tenderers only
once approval has been granted by the Eskom Adjudication Authority. For open tenders,
this notification must be published on the Eskom Tender Bulletin and NT e-Tender Portal
Prepare contract 3.23 Revise the contract documents issued by Eskom in the Invitation to Tender documents to
documents take account of:
Addenda issued during the tender period;
inclusion of returnables stipulated in the Invitation to Tender;
inclusion of changes agreed in contract negotiations; and
Other revisions or documents agreed to between Eskom and the successful
tenderer during negotiations,
Sign Form of 3.24 Arrange for authorised signatories of both parties to complete and sign the original and one
Contractual Terms
Source: Eskom - Standard Conditions of Tender - 30 January 2025 (1).pdfincluding the Eskom Representative shall not be liable for any losses, claims or damages of
whatsoever nature or howsoever arising that may be sustained by a tenderer or any other
person as a result of its participation in the tender or from any amendment, termination or
suspension of the process set out in the Invitation to Tender or from its exclusion from
participating in the tender process at any point.
Eskom’s right to 1.7 Eskom reserves the right to enter into mandated negotiations with any, one or more selected
negotiate tenderer(s) in accordance with Eskom’s approved procurement policies and procedures.
240-62044728 Rev 12 Eskom Standard Identifier
Conditions of Tender Effective Date 01 February 2025
Review Date January 2030
Disclaimer 1.8 While Eskom takes all reasonable measures to ensure that all information contained in the
regarding accuracy tender documents is correct and complete, Eskom does not, however, make any
of tender representations or warranties, express or implied, as to the accuracy or completeness of
documents such information and Eskom expressly disclaims any, and all liability for such
representations, warranties or statements.
Tenderer’s 2. The tenderer shall comply with the following obligations when submitting a tender and shall:
Tender validity 2.12 Hold the tender(s) valid for acceptance by Eskom at any time within the validity period after
the closing date and time for tender submission. Extend the validity period for a specified
additional period if Eskom requests the tenderer to do so. A tenderer that agrees to extend
the validity of its tender will not be required or permitted to modify its tender. A tenderer that
does not agree to extend the validity of its tender will be excluded from further
consideration. Tenderers will be requested to extend the validity of their tenders until a
contract(s) have been concluded with one or more tenderers. A request that a tenderer
extend the validity of its tender is not a representation that the tender is an acceptable
tender or that Eskom will seek to negotiate or conclude a contract with the tenderer. If the
validity of tenders expires before contracts have been concluded, the procurement process
is deemed to have concluded without an award.
Confidentiality and 2. 13 Treat as confidential all matters that arise in connection with the procurement. Use and copy
copyright of the documents provided by Eskom only for the purpose of preparing and submitting a tender
documents in response to this Invitation to Tender.
Standardised 2.14 Obtain and familiarise themselves with, if required for the purposes of submitting a tender,
specifications and the latest revision of standardised specifications and/or other documents that have been
other publications incorporated by reference into the Invitation to Tender documents by reference.
Site visit and / or 2.15 Tenderers must attend a site visit and/or clarification meeting that is stipulated as being
clarification compulsory in order to familiarise themselves with the proposed work, services, supply,
meeting location or similar. Failure to attend a clarification meeting or site visit that is identified as
compulsory will result in disqualification from participation.
Details of the meeting(s) are stated in the Tender Data. Tenderers are entitled to ask
correction of errors as required above.
Evaluation of 3.17 Score the B-BBEE level as stated on the CSD report or as per certificate/affidavit provided.
B-BBEE If the B-BBEE level is a pre-qualification criterion; then the proof of the B-BBEE level
(certificate/CSD number/CSD report) must be provided at the closing date and time for
tender submission; or the tender will be disqualified. If sub-contracting to designated groups
pre-qualification criteria are utilized (selected/mandatory) in terms of the PPPFA
Regulation, then Eskom will apply the PPPFA requirements for sub-contractors’ B-BBEE
status and the sub-contractors’ CSD number or B-BBEE certificate/affidavit will need to be
provided at the closing date and time for tender submission. Should the
information/documents provided indicate that the level is in dispute (fraudulent/ expired)
then the tender will be disqualified.
However, for the purposes of PPPFA point allocation: if no B-BBEE certificate/affidavit is
provided at Tender closing date and time for tender submission, or the
information/documents provided are fraudulent or have expired; then the tenderer will not
be disqualified (if otherwise deemed to be responsive and acceptable in all other aspects)
but will score zero under PPPFA point allocation.
Evaluation of 3.18 Score the Specific Goals with reference to the supporting documentation in the tender. If a
Requirements
Source: Eskom - Standard Conditions of Tender - 30 January 2025 (1).pdf (TENDER)Tenderer’s Obligations 2. The tenderer shall comply with the following obligations when submitting a tender and shall:
Section
Source: Eskom - Standard Conditions of Tender - 30 January 2025 (1).pdf (TENDER)Seek clarification 2.16 While preparing their tenders and prior to submission, tenderers are entitled to seek clarification in respect of the Invitation to Tender documents. A request for clarification or query must be addressed, in writing, to the Eskom Representative identified in the Invitation to Tender document. No request or query may be addressed to any other Eskom official other
Description
Source: RER0371 - Environmental Evaluation-Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a period of 12 months.pdfImportant Dates
Source: RER0371 - Environmental Evaluation-Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a period of 12 months.pdf (unknown)Evaluation Criteria
Source: RER0371 - Environmental Evaluation-Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a period of 12 months.pdf (unknown)Contractors must provide all required environmental documentation, demonstrate top management commitment to environmental protection, comply with legal requirements, and show capability to manage environmental aspects of the project. Specific certificates required for waste transportation and dangerous goods handling.
Technical Specifications
Source: RER0371 - Environmental Evaluation-Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a period of 12 months.pdf (unknown)Methodology
Source: RER0371 - Environmental Evaluation-Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a period of 12 months.pdfCompliance Requirements
Source: RER0371 - Environmental Evaluation-Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a period of 12 months.pdf (unknown)Environmental
Source: RER0371 - Environmental Evaluation-Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a period of 12 months.pdfSection
Source: RER0371 - Environmental Evaluation-Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a period of 12 months.pdfDescription
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.xlsThis will save your file. Please select the correct folder.
Evaluation Criteria
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.xls (unknown)Explicit eligibility criteria are not present in the analyzable text. The document structure implies a distinction between different 'Contractor Types' (possibly 'A' and 'B' packages), requiring specific information sets. General criteria would need to be sourced from the official, uncorrupted tender documents.
Technical Specifications
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.xls (unknown)This will save your file. Please select the correct folder.
Compliance Requirements
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.xls (unknown)No specific requirements found
Description
Source: 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsxThe tender requires refurbishment of the Kriel Power Station Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a period of 12 months. Bidders must select the applicable category (Category 1, 2, 3, or 4) by typing '1' in the relevant block on the 'Cover' tab of the provided template.
Submission Guidelines
Source: 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsx (unknown)Submit the following returnable documents as per the selected category: Form A, ISO 9001:2015 certificate, internal and external management system audit reports (including Nonconformity, Correction, and Corrective Action Reports), Draft Contract Quality Plan (CQP) and Inspection and Test Plan (ITP) as per Scope of Works (Ref ISO 10005), and information for defined roles, responsibilities, and authorities. Save the completed template in PDF, sign, and preferably lock the sheet before submission. Ensure the print area fits to 1 page.
Evaluation Criteria
Source: 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsx (unknown)Category 3 eligibility: Must have implemented Quality Management System with internal audit reports, draft Contract Quality Plan and Inspection Test Plan per scope, and defined roles/responsibilities. No ISO certification required but must demonstrate ISO 9001 compliance through documentation. Must complete and sign Form A.
Compliance Requirements
Source: 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsx (unknown)Compliance with ISO 9001:2015 is mandatory. Required documents include: Valid ISO 9001:2015 certification (Option 1) OR evidence of QMS in operation (Option 2) such as QMS Manual, Quality Policy, Quality Objectives, and documented information for control of nonconforming outputs, corrective actions, and internal audits. Additional requirements include internal and external management system audit reports with Nonconformity, Correction, and Corrective Action Reports.
Submission Guidelines
Source: CIDB Ann G Compulsory Enterprise Questionnaire_.pdf (unknown)Returnable documents are required. No further submission details are provided in the extracted content.
Compliance Requirements
Source: CIDB Ann G Compulsory Enterprise Questionnaire_.pdf (unknown)Insufficient searchable text - AI extraction recommended
Submission Guidelines
Source: 18. RT284 Annex D Imported Content Declaration.pdf (unknown)Returnable Documents: Not specified in the provided text.
Description
Source: Annexure B.docxThis annexure requires the supplier/contractor/tenderer to acknowledge understanding and compliance with Eskom’s OHS legal and other requirements as a prerequisite for working at or rendering services to Eskom.
Submission Guidelines
Source: Annexure B.docx (unknown)Returnable Documents: Signed acknowledgement form confirming understanding of Eskom OHS legal and other requirements.
Evaluation Criteria
Source: Annexure B.docx (unknown)Not explicitly stated in this document excerpt. However, implied requirements include: proven ability to comply with Eskom OHS standards, experience with similar high-voltage electrical/refurbishment work at power stations, capacity to manage sub-contractor OHS compliance, and willingness to accept penalty clauses for safety violations. Full eligibility criteria would be in the main tender document.
Compliance Requirements
Source: Annexure B.docx (unknown)Mandatory compliance with the following OHS requirements:
Additional obligations:
Submission Guidelines
Source: CIDB SBD9 SCM_certificate_independent_bid_determination.pdf (TENDER)Returnable Documents: SBD 9 - Certificate of Independent Bid Determination must be completed and submitted with the bid.
Returnable Documents
Source: CIDB SBD9 SCM_certificate_independent_bid_determination.pdf (TENDER)Mandatory returnable document: SBD 9 - Certificate of Independent Bid Determination. This form must be completed, signed, and submitted with your bid. Failure to submit a true and complete certificate will result in disqualification.
Evaluation Criteria
Source: CIDB SBD9 SCM_certificate_independent_bid_determination.pdf (TENDER)While this specific document does not list technical or financial pre-qualification criteria, it establishes a fundamental legal eligibility condition: the bidder must be able to truthfully complete this anti-collusion certificate. Bidders involved in joint ventures or consortia are permitted to have internal communications, but any communication with entities outside their own venture regarding the bid is prohibited.
Compliance Requirements
Source: CIDB SBD9 SCM_certificate_independent_bid_determination.pdf (TENDER)The SBD 9 Certificate of Independent Bid Determination must be completed and submitted with the bid. This is a mandatory declaration to prevent bid-rigging.
Contractual Terms
Source: CIDB SBD9 SCM_certificate_independent_bid_determination.pdfThe SBD 9 Certificate of Independent Bid Determination must be completed and submitted with the bid to prevent bid-rigging.
Description
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx.docRefurbishment of Kriel Power Station (PS) Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for a period of 12 months.
Contact Information
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx.doc (unknown)Group Tax Department at Megawatt Park. Email: [email protected]
Evaluation Criteria
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx.doc (unknown)The primary eligibility relates to tax status: contractors must be South African residents (non-residents require special handling). Companies/CCs/Trusts employing three or more full-time, non-connected persons may be exempt from PAYE. Individuals providing 'services' (not 'people') are assessed differently. Compliance with South African Income Tax Act definitions (e.g., 'Connected Person', 'Personal Service Provider') is mandatory.
Compliance Requirements
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx.doc (unknown)Bidders must complete the PAYE Questionnaire for Service Contracts to Eskom Group of Companies. This includes:
Description
Source: Technical evaluation strategy.pdfContact Information
Source: Technical evaluation strategy.pdf (unknown)Returnable Documents
Source: Technical evaluation strategy.pdf (unknown)4.1 Tenderer shall provide test equipment calibration certificates for all test equipment used.
Evaluation Criteria
Source: Technical evaluation strategy.pdf (unknown)Eligible tenderers must be registered electrical contractors with the Department of Employment and Labour, have proven track record of at least 5 successfully completed MV/LV switchgear maintenance projects (with references from national/international clients), and have at least 5 signed-off QCP reports from previous projects. All key personnel must meet minimum qualification and experience requirements as specified. Tenderers must achieve minimum 75% weighted technical score after passing all mandatory criteria.
Technical Specifications
Source: Technical evaluation strategy.pdf (unknown)Methodology
Source: Technical evaluation strategy.pdfExperience & Qualifications
Source: Technical evaluation strategy.pdfQuality Management
Source: Technical evaluation strategy.pdfCompliance Requirements
Source: Technical evaluation strategy.pdf (unknown)Health & Safety
Source: Technical evaluation strategy.pdfRequirements
Source: Technical evaluation strategy.pdf (unknown)Section
Source: Technical evaluation strategy.pdfSubmission Guidelines
Source: CIDB SBD4 SCM_declaration_interest.pdf (TENDER)Returnable Documents:
Returnable Documents
Source: CIDB SBD4 SCM_declaration_interest.pdf (TENDER)You must submit the completed SBD 4 Declaration of Interest form with your bid.
Evaluation Criteria
Source: CIDB SBD4 SCM_declaration_interest.pdf (TENDER)All legal persons including state employees may bid, but must declare any relationships with state employees involved in evaluation/adjudication. State employees must provide proof of authority for outside remunerative work. Failure to provide required declarations or providing false information may result in disqualification or contract action.
Compliance Requirements
Source: CIDB SBD4 SCM_declaration_interest.pdf (TENDER)No specific requirements found.
Requirements
Source: CIDB SBD4 SCM_declaration_interest.pdf (TENDER)False declarations may lead to action under Paragraph 23 of the General Conditions of Contract.
Section
Source: CIDB SBD4 SCM_declaration_interest.pdfThe evaluation and adjudication process involves persons who are involved in the evaluation and/or adjudication of the bid.
Description
Source: 18kV Breaker Compressor Controls Scope.pdfEvaluation Criteria
Source: 18kV Breaker Compressor Controls Scope.pdf (unknown)Not explicitly stated in the provided scope document. Typically for ESKOM tenders: valid CIDB grading (likely 6EP or higher for electrical work), proven experience in high-voltage switchgear/control systems, ISO 9001 certification, ability to manufacture and test control panels off-site, qualified personnel for installation/commissioning at operational power station, and compliance with Eskom's safety and security requirements.
Technical Specifications
Source: 18kV Breaker Compressor Controls Scope.pdf (unknown)Wire new panel off-site.
Deliver new panel to site.
Remove old panel while Compressor B is running manually.
Install new panel.
Supply and install eight new pressure switches, five new water traps, eight new pressure gauges.
Supply and install cabling to auxiliaries (pressure switches, water traps, interconnected panels).
Commission the panel.
Test operation on auto and manual modes.
Wire new panel off-site.
Deliver new panel to site.
Remove old panel while Compressor A is running manually.
Install new panel.
Supply and install eight new pressure switches, five new water traps, eight new pressure gauges.
Supply and install cabling to auxiliaries.
Commission the panel.
Test operation on auto and manual modes.
Methodology
Source: 18kV Breaker Compressor Controls Scope.pdf (unknown)Quality Management
Source: 18kV Breaker Compressor Controls Scope.pdfSection
Source: 18kV Breaker Compressor Controls Scope.pdfDescription
Source: She Requirements high risk.docxScope of work: Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4.
Submission Guidelines
Source: She Requirements high risk.docx (unknown)Returnable Documents:
Evaluation Criteria
Source: She Requirements high risk.docx (unknown)Valid Letter of Good Standing (COIDA or equivalent), OHS policy signed by CEO complying with legal requirements, demonstrated OHS competencies through CVs, and ability to provide detailed OHS costing breakdown. All OHS returnable documents must be submitted as specified.
Technical Specifications
Source: She Requirements high risk.docx (unknown)Scope of work: Refurbishment of Kriel PS Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4.
Description
Source: 240-109253698 CQP Template 2021.docxThe tender is for the refurbishment of the Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 at Kriel Power Station for a 12-month period. The document provided is a template for a Contract Quality Plan (CQP), which the supplier must complete to demonstrate how they will manage quality to meet Eskom's requirements.
Evaluation Criteria
Source: 240-109253698 CQP Template 2021.docx (unknown)Not explicitly stated in this template document. Eligibility would be defined in the main tender documents. This template indicates that bidders must have a robust QMS capable of meeting the outlined quality planning requirements, including managing sub-suppliers, documented processes, and compliance with referenced standards.
Technical Specifications
Source: 240-109253698 CQP Template 2021.docx (unknown)The tender requires a Contract Quality Plan (CQP). The plan must detail how the supplier will meet Eskom's quality expectations. Key elements to include are:
Description
Source: E-tendering Help Manual for supplier - 27 January 2025.pdfImportant Dates
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)Contact Information
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)Submission Guidelines
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)Returnable Documents
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)Evaluation Criteria
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)The primary eligibility criterion specified in this document is that the supplier must have a CSD number. The manual also implies eligibility to bid on the specific Kriel PS tender requires successful registration and access to the eTendering portal.
Technical Specifications
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)Quality Management
Source: E-tendering Help Manual for supplier - 27 January 2025.pdfCompliance Requirements
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)Section
Source: E-tendering Help Manual for supplier - 27 January 2025.pdfEvaluation Criteria
Source: 240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP) rev 2.docx (unknown)Specific eligibility criteria (e.g., company registration, B-BBEE status, financial standing) are not detailed in this excerpt. This document focuses on technical and quality compliance. Applicants must refer to the full tender documentation for formal eligibility requirements. However, the ability to implement and adhere to the prescribed Quality Control Plan, including interaction with multiple inspection authorities, is implicitly required.
Technical Specifications
Source: 240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP) rev 2.docx (unknown)Scope: Refurbishment of Kriel Power Station (PS) Generator Circuit Breaker (GCB) Compressor Plant Control Circuit at Units 1 & 4 for 12 months.
Quality Control Plan (QCP) or Inspection Test Plan (ITP) Requirements:
Important Dates
Source: Eskom General Conditions of Purchase - 31 May 2024 (3).pdf (unknown)Closing date: 07 August 2026 at 10:00 (SAST).
Contact Information
Source: Eskom General Conditions of Purchase - 31 May 2024 (3).pdf (unknown)Fraud/corruption reporting: [email protected] or 0800 11 2722.
Submission Guidelines
Source: Eskom General Conditions of Purchase - 31 May 2024 (3).pdf (unknown)Submit the following returnable documents as part of your bid:
Disqualification risks:
Evaluation Criteria
Source: Eskom General Conditions of Purchase - 31 May 2024 (3).pdf (unknown)Suppliers must accept Eskom's General Conditions of Purchase (deemed acceptance if not objected); must be financially stable (bankruptcy or financial prejudice can lead to termination); must comply with South African law and jurisdiction; must not subcontract without Eskom's written consent; must adhere to Eskom's ethical standards.
Technical Specifications
Source: Eskom General Conditions of Purchase - 31 May 2024 (3).pdf (unknown)Scope: Supply goods or execute works/services as described in the agreement, including specifications, schedules, and drawings approved by Eskom.
Quality and compliance:
Quality Management
Source: Eskom General Conditions of Purchase - 31 May 2024 (3).pdfQuality control and rejection:
Pricing Schedule
Source: Eskom General Conditions of Purchase - 31 May 2024 (3).pdfPricing structure:
Financial Requirements
Source: Eskom General Conditions of Purchase - 31 May 2024 (3).pdf (unknown)Pricing and payment:
Compliance Requirements
Source: Eskom General Conditions of Purchase - 31 May 2024 (3).pdf (unknown)Statutory and legal compliance:
Description
Source: Hazard list signed.pdfThe document is a hazard checklist identifying risks associated with the refurbishment work, including:
Evaluation Criteria
Source: Hazard list signed.pdf (unknown)Contractors must have proven experience in power plant refurbishment, particularly with generator circuit breaker systems and compressor plants. Must demonstrate robust safety management systems and compliance with ESKOM safety standards. Experience with hazardous environments and pressure systems essential.
Technical Specifications
Source: Hazard list signed.pdf (unknown)The document lists various technical hazards and safety considerations relevant to the refurbishment work:
Compliance Requirements
Source: Hazard list signed.pdf (unknown)The document identifies various health, safety, and environmental hazards that must be managed:
Health & Safety
Source: Hazard list signed.pdf (unknown)The hazard checklist identifies specific health and safety risks:
Contact Information
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)Contact details must be provided on the acknowledgement form: Business name/JV, Contact Person, Tel (landline), Cellphone, and E-mail address.
Submission Guidelines
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)Mandatory returnable document: E-Tendering Training Acknowledgement Form.
Returnable Documents
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)Mandatory returnable: E-Tendering Training Acknowledgement Form.
Evaluation Criteria
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)Tenderers must demonstrate completion of e-tendering training and ability to operate the E-Tendering Solution. Form must be fully completed with all required information including business name, contact details, and authorized signature.
Technical Specifications
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)Tenderers must complete the E-Tendering Training Acknowledgement Form.
Special Conditions
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)The E-Tendering Training Acknowledgement Form is mandatory.
Section
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)Provide contact details on the acknowledgement form: Contact Person, Tel (landline), Cellphone, and E-mail address.
Description
Source: she spec refurbishment of Kriel PS Generator circuit breaker signed.pdfContact Information
Source: she spec refurbishment of Kriel PS Generator circuit breaker signed.pdf (unknown)Evaluation Criteria
Source: she spec refurbishment of Kriel PS Generator circuit breaker signed.pdf (unknown)Contractor must be a legally registered entity compliant with Occupational Health and Safety Act 1993, Compensation for Occupational Injuries and Diseases Act, and National Environmental Management Act. Must have valid COID Letter of Good Standing, competent workforce with relevant qualifications registered with SAQA, ability to meet Eskom's Life-Saving Rules and substance abuse requirements, and capacity to maintain comprehensive OHS documentation for 12-month duration at Kriel Power Station.
Methodology
Source: she spec refurbishment of Kriel PS Generator circuit breaker signed.pdfExperience & Qualifications
Source: she spec refurbishment of Kriel PS Generator circuit breaker signed.pdfQuality Management
Source: she spec refurbishment of Kriel PS Generator circuit breaker signed.pdfCompliance Requirements
Source: she spec refurbishment of Kriel PS Generator circuit breaker signed.pdf (unknown)Health & Safety
Source: she spec refurbishment of Kriel PS Generator circuit breaker signed.pdfEnvironmental
Source: she spec refurbishment of Kriel PS Generator circuit breaker signed.pdfContractual Terms
Source: she spec refurbishment of Kriel PS Generator circuit breaker signed.pdfSection
Source: she spec refurbishment of Kriel PS Generator circuit breaker signed.pdfData conflicts
None detected
Get deep intelligence on Services: General. Unlock full pricing strategies, bid frequency, and historical win rates.