C3.4.10 Site establishment
is however required to obtain approval of his choice of campsite from the Employer.
arrangements for water, telephone, and power connections with the relevant service
owners in the area.
as required. The Contractor may establish their own laboratory on site or may employ the
services of an independent commercial laboratory. Whatever method is used, the
necessary facilities as set out in the Project Specifications.
C3.4.11 Facilities provided by the contractor
a) Engineerβs Office
To be provided as stipulated in the schedule of quantities. The Engineerβs
Representative will be allowed free use of the Contractorβs facilities under this Contract,
as well as free use of survey equipment and survey assistants to carry out control work
of 42
Coega development corporation (pty) ltd
CONTRACT No. CDC/158/26
Construction works for expansion of the weidplas facility in zone 2 of the
as and when required.
b) Photographic Record of Work
USB drive. Photos will be in jpeg format of at least 48MP quality at 9:16 ratio. At least
25 photos should be captured each day.
shall take all the necessary steps and precautions to prevent the pollution of the
surrounding area by anyone in any way. These steps and precautions shall be to the
satisfaction of the Engineer and CDC.
b) Contractorβs Telephone
proper latrines in compliance with the relevant Municipal Sanitation General By-laws,
as well as CDCβs requirements. Latrines must be properly screened and secluded from
public view and their use shall be strictly enforced. The Contractor shall provide
chemical toilets (or other approved toilets). Soak-aways and septic tanks will not be
allowed on the site. Temporary latrines must be sited so that they are within reasonable
distance of the working place.
on the Works. All latrines shall be adequately ventilated, properly disinfected, and kept
in a clean condition.
of 42
Coega development corporation (pty) ltd
CONTRACT No. CDC/158/26
Construction works for expansion of the weidplas facility in zone 2 of the
d) Contract Name Board
to the Site, in a conspicuous place to be agreed upon by the Engineer, a Contract name
board as detailed in clause 3.1, Part AB of SANS 1200. The total cost for the
procurement and erection thereof will be deemed to be included in the schedule of
quantities.
e) Transport
document and the South African Road Traffic Signs Manual.
f) The Contractor shall submit proposals in connection with directional signs to the
g) The Contractor may not construct any deviations without the prior written approval from
the Engineer.
h) The Contractor shall be responsible for repairing any damage caused to infrastructure
and vegetation in the areas of construction. Failure to repair any damage will give the
Employer (CDC) the right to withhold payments due to the Contractor until repairs have
been made to the satisfaction of the Engineer and Employer. Any expenses incurred in
this regard will be for the Contractor's own account and the Employer will not be liable
for any payment in this regard.
i) The Contractor shall make provision for the coordination of work with other contractors
that may be operating in the project area that is outside the scope of this project.
C3.4.13 Permits and way leaves
been obtained before the commencement of works. The Contractor will at all times be
required to be in contact with the relevant service providers.
this permit. The Contractor must apply for this permit immediately at the start of the project.
C3.4.14 Construction in restricted areas
the exceptions described in this sub-clause, no additional payment will be made for work
done in restricted areas. In certain places, the width of the excavations adjacent to existing
of 42
Coega development corporation (pty) ltd
CONTRACT No. CDC/158/26
Construction works for expansion of the weidplas facility in zone 2 of the
road pavement layers may be reduced to as little as zero and the working space may be
confined.
cracks etc. before commencing with the works that may have a potential to damage
surrounding buildings and properties. Notes and photographs must be taken of each
structure surrounding the development, to record any existing defects prior to the
commencement of the works.
C3.4.17 Water for construction purposes, power supply and other
commencing with the works and must notify the Engineer of any discrepancy.
of 42
Coega development corporation (pty) ltd
CONTRACT No. CDC/158/26
Construction works for expansion of the weidplas facility in zone 2 of the
C3.4.19 Change in scope of the works
The Employer reserves the right to amend the quantities and scope of works (increase or
decrease quantities) prior to or during the Contract and the Contractor shall forfeit all claims
linked to loss of profits or consequential losses against the Employer in this regard.
C3.4.20 Survey requirements
The Contractor may only backfill pipe trenches on instruction by the Employerβs
invert level and position is captured and approved by the Engineer.
The Contractor shall be responsible for capturing a 5m wide tache strip survey of the surface
along the pipeline routes after commissioning.
person. It is imperative that the surveyor utilises the nearest survey control point and notifies
the Engineer thereof. The survey shall be done in WGS84 Lo25 projection. Survey of
pipelines, bends, specials, fittings, and chambers shall be captured to an accuracy of less
than 10mm by a Professionally Registered Surveyor.
prior to any as-built data being captured. The Employerβs Representative may request further
accuracy tests and verified calibration certificates during the Contract should they deem it
necessary.
Employerβs Representative and should any of the information provided be found to be
inaccurate or untrue, the Employerβs Representative reserves the right on behalf of the
survey all the works, at the Contractorβs expense. In this case a minimum of three quotations
is required from three independent engineering surveyors of the Employerβs choice and the
cost thereof will be deducted from money owed to the Contractor.
infrastructure under the Contract is shown on the as built survey.
A tacky survey of the completed works carried out in accordance with TMH11: Standard
- Each point shall be suitably coded and identifiable by the Engineer and shall be supplied