Skip to main content
    Design, Engineering, Design Verification/Validation, Material and Equipment Procurement, Quality Management, Factory Inspection/Testing, Transport and Delivery to Site, Site Inspection, Construction, Installation, Interfacing of Control and Protection Systems (Existing and New), Testing And Commissioning, Project Management, Training, Supervision and Interface Management with other parties and all associated works and services until final completion of the work package of the 400kV,500MVar Dynamic Reactive Compensator at Aries Substation in the Northern Cape. (Awarded) | Contract Award