This tender is for the appointment of a contractor to rehabilitate runway 0220 and taxiways at bram fischer international airport over a 24-month period. The work must be conducted airside with strict adherence to safety and operational procedures to ensure minimal disruption to airport activities. IT is intended for construction contractors with experience in working within active airport environments.
Key Requirements
The contract is for the rehabilitation of Runway 0220 and taxiways at Bram Fischer International Airport over 24 months.
All work must be programmed to minimise disruption to airside operations, with specific consideration for passenger safety and aircraft operations.
The Contractor must comply fully with the Occupational Health and Safety Act and all personnel working airside must complete a compulsory safety induction.
All workers must possess a valid ACSA Security Permit, and all vehicles and drivers require specific ACSA permits (Vehicle Permit and Airside Vehicle Operator Permit).
Work on or near runways and taxiways is restricted, generally requiring night work and subject to prior approval, with at least 14 days' notice needed for closures.
The Contractor must establish an approved radio communication system and have key personnel in direct radio contact with Fire & Rescue for emergencies and coordination.
A designated campsite is provided, but the Contractor must provide 24-hour security for it, subject to ACSA Security approval.
Contractor appointment for the construction of underground main water line and rehabilitation of service at bram fischer international airport for a period of 24 months.
Tenders in this industry often require registration with these bodies.
CIDB Registration
Construction Industry Development Board (CIDB) registration is mandatory for almost all public sector construction tenders. Ensure your grading matches the tender value.
Typical Documents
10 items
Company Registration (CIPC)
Tax Clearance Certificate
B-BBEE Certificate
CSD Registration
Company Profile
CIDB Registration Certificate
NHBRC Registration (if applicable)
Health & Safety Plan
Insurance Certificates
Previous Project Completion Certificates
Recommended Certifications
Having these can improve your winning chances: NHBRC Registration, ISO 9001:2015 (Quality Management), ISO 14001:2015 (Environmental Management), ISO 45001:2018 (Occupational Health & Safety), SACPCMP Registration, ECSA Registration
Review in progress · 0 of 3 documents being finalised
AI Document Analysis Stages
Document read. The full tender notice and its supporting documents are read end-to-end. Key sections, requirements, dates, and contact details are identified and pulled into a working summary you can act on.
Compliance review. The working summary is checked against South African procurement standards — PFMA, PPPFA, B-BBEE, CIDB, local content, and preferential procurement — so nothing critical is missed before you start your bid response.
DocumentCOTO BOQ .xlsxReview complete
Description
Source: COTO BOQ .xlsx
Important Dates
11 Jun
2026
PUBLICATION
Tender Published
Tender was published
24 Jul
2026
DEADLINE
Closing Date
Tender closing date
Procurement Rules & Compliance ContextThis tender may be governed by South African public procurement rules covering fairness, transparency, preferential procurement, anti-corruption, administrative justice and access to information.
11 rules
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
Core procurement rules
These rules commonly apply to South African public-sector procurement.
7
Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
high
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Constitution of the Republic of South Africa, 1996 – Section 217
Act 108 of 1996 (s217)
high
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Tender for construction of underground main water line and rehabilitation of service roads at Bram Fischer International Airport for Airports Company of South Africa, with a contract period of 24 months. The work includes civil engineering, mechanical installation, and stakeholder liaison components.
Contractor appointment for the rehabilitation of Runway 0220 and taxiways at Bram Fischer International Airport for a 24-month period. The tender includes strict airside operational procedures, security protocols, and coordination with airport authorities to ensure minimal disruption to airport operations.
Airports Company South Africa (ACSA) invites tenders for a 24-month contract to construct an underground main water line and rehabilitate service roads at Bram Fischer International Airport (BFIA). The tender uses a staged evaluation process, including mandatory criteria, functionality scoring (minimum 75/100), and a 90/10 price/preference system. The closing date is 24 July 2026 at 12:00 PM.
Win ACSA tenders with AI Matching Engine, airport-infrastructure intelligence, compliance analysis, and application support for aviation operations.
Similar Tenders
Matched by category & region
Supplier Readiness Hub
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
REQUEST FOR PROPOSAL FOR SUPPLY, INSTALLATION, COMMISSIONING, SUPPORT, MAINTENANCE, MONITORING, DECOMMISSIONING AND DISPOSAL OF DATA PROTECTION (BACKUP AND REPLICATION) AND DATA STORAGE (STORAGE ARRAY AND STORAGE NETWORKING) SERVICES FOR A PERIOD OF 60 MONTHS TO AIRPORTS COMPANY SOUTH AFRICA.
Based on 5 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
Bid-ready summary. The submission guidelines, evaluation criteria, technical, financial, and compliance sections are refined into professional, easy-to-scan prose. This is the final version you can rely on when preparing your bid or briefing your team.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Document read
Compliance review
Bid-ready summary
The tender is for the appointment of a contractor for the construction of an underground main water line and rehabilitation of service roads at Bram Fischer International Airport.
The primary document provided is a detailed Bill of Quantities (BOQ) spreadsheet, which forms the basis for pricing and defines the scope of work.
The BOQ is extensive and covers preliminaries, site establishment, traffic management, earthworks, and the installation of various services (water, sewer, ducts).
Evaluation Criteria
Source: COTO BOQ .xlsx (unknown)
Likely requires appropriate CIDB grading (based on references to CIDB 1-5+ in Section D), proven experience in airport infrastructure works, financial capacity to undertake the project, and compliance with health and safety and environmental regulations.
Technical Specifications
Source: COTO BOQ .xlsx (unknown)
Scope: Construction of an underground main water line and rehabilitation of service roads at Bram Fischer International Airport.
Duration: The extracted text refers to a period of 12 months, while the tender description states 24 months. Clarify the exact contract period.
Key work areas include:
Environmental management, including monitoring and a dedicated environmental officer.
Programming and reporting, including submission and updating of Scheme 1 Programme.
Submission address: Bram Fischer International Airport.
Evaluation Criteria
Source: Volume 5 Airside Manual.pdf (unknown)
Contractors must demonstrate experience with airport airside construction, ability to work within strict security and operational constraints, capacity to provide 24-hour site security, staff with valid security clearance, and proper insurance coverage. All personnel must complete ACSA security induction training and obtain necessary permits.
Technical Specifications
Source: Volume 5 Airside Manual.pdf (unknown)
Scope: Rehabilitation of Runway 0220 and taxiways at Bram Fischer International Airport over 24 months.
Key restrictions: Work must be programmed to minimise disruption to airside operations, with specific consideration for passenger safety and aircraft operations in apron areas.
Working times: General working hours are 08h00 to 17h00. Night work is allowed for crossings with live runways and taxiways, subject to arrangement with airport operations.
Access and movement: All construction traffic on the airside must be strictly controlled and channelled via approved routes. Access to runways and taxiways is limited to night work and subject to approval by the Airport Authority.
Communication: The Contractor must establish a radio communication system approved by Air Traffic Control (ATC). Contractor's Safety Managers and the Engineer's Representative must have radios to communicate directly with Fire & Rescue.
Site establishment: A designated campsite with water and electricity is provided. The Contractor must provide 24-hour security for the site camp, subject to ACSA Security approval.
Safety and inspections: A method statement for every closure must be submitted to the Airport Authority via the engineer before work commences. A final inspection by the Engineer's Representative and Fire & Rescue is required before reopening any runway or taxiway.
Methodology
Source: Volume 5 Airside Manual.pdf
Work within 50m of a runway edge or taxiway centreline must only be undertaken when the runway/taxiway is closed.
A request to close a specific taxiway or runway (via a NOTAM) must be submitted to the Engineer's Representative at least 14 days in advance. Late submissions may cause delays at the contractor's cost.
Key briefing points for personnel include: defined tasks and work area; permitted working hours and restrictions; procedures for when aircraft approach; communication protocols; and strict rules to avoid generating Foreign Object Damage (FOD).
Work sites must be clearly marked by day using approved cones or barriers at specified spacings.
Quality Management
Source: Volume 5 Airside Manual.pdf
The final construction programme must be submitted by the appointed contractor for approval by ACSA and the engineer.
All timelines are indicative and subject to change due to operational requirements (e.g., aircraft load factors, weather).
The Contractor must ensure the work area is clean and free of all Foreign Object Damage (FOD) material at the end of each shift.
Before reopening a runway or taxiway, the construction area must be cleared of all personnel, plant, and obstructions, with no loose material on the surface.
Prior to construction, the Contractor must arrange with airport authorities for a thorough inspection to locate all existing services using service detectors.
Compliance Requirements
Source: Volume 5 Airside Manual.pdf (unknown)
The Contractor must comply fully with the regulations of the Occupational Health and Safety Act.
All personnel working airside must complete a compulsory safety induction course.
All workers on site must possess a valid ACSA Security Permit. Where applicable, a cell phone permit and camera permit are also required.
All delivery and construction vehicles must have a valid ACSA Vehicle Permit, and all drivers must possess an Airside Vehicle Operator Permit (AVOP).
The Contractor must provide appropriate personal protective equipment (PPE) for all workers on site.
The Contractor is responsible for the cost of all permits and required training courses for its personnel and vehicles.
Health & Safety
Source: Volume 5 Airside Manual.pdf
The Contractor must comply with the Occupational Health and Safety Act and Regulations.
A dedicated Contractor's Safety Officer must be available. Responsibilities include: inspecting and recording all traffic accommodation features; ensuring removal of obstructions before sunrise; and being responsible for all traffic signs and barricades.
A liaison group with airport operations, safety, ATC, maintenance, and contractor representatives must be established to review progress and working practices.
All subcontractors must also comply with airside safety regulations, and the main contractor remains responsible for their compliance.
A method statement for every closure must be submitted to the Airport Authority via the engineer before work commences.
Before project commencement, a comprehensive safety briefing must be held for all personnel, covering tasks, work area marking, permitted hours, communication procedures, and actions in case of an accident.
All personnel must wear high-visibility clothing. A lookout and R/T communication with ATNS are required for 'ON/OFF' work conditions.
A Hot Work Permit is required for activities involving open flames (e.g., heating paver screeds). The permit must be carried on site and kept in the Site Safety File.
The Contractor must warn employees about aircraft jet blast and take measurements for compliance with noise exposure regulations.
Contractual Terms
Source: Volume 5 Airside Manual.pdf
This Volume 5 document is a Procedure Manual that forms part of the contract. It must be read in conjunction with Volumes 3 and 4.
The Contractor must not commence any work airside until fully conversant with this manual and it has been signed and implemented by the parties.
The Contractor has no right to claim for delays, standing time, or losses resulting from the cancellation of access permits due to security breaches. Any costs incurred by ACSA in rectifying a breach will be for the Contractor's account.
Permits are not transferable. Abuse of the permit system will lead to termination of further permit issuance.
The Contractor must submit a travel route plan to the Manager: Airside for movement between construction areas, spoil site, and campsite. No other routes are permitted.
As a condition for an Airside Vehicle Permit, the company must ensure all vehicles and drivers are covered by Contract Works, Public Liability, and SASRIA Special Risks insurance.
DocumentVolume 3 Tender and Contract.pdfReview complete
Important Dates
Source: Volume 3 Tender and Contract.pdf (TENDER)
Tender documents available from: Tuesday, 11 June 2026.
Compulsory briefing session: Thursday, 19 June 2026 at 09h00. Venue: Permit Office, Bram Fischer International Airport, 1 Old Thaba Nchu Road, Bloemfontein, 9300.
Non-compulsory site inspection: Thursday, 19 June 2026 from 13h00 to 15h00 (after briefing).
Programme for briefing day: Permits and registration 08h00-11h00, escort 11h00-11h30, briefing 11h30-12h30, site inspection 13h00-15h00. No access after 11h00.
Closing date for enquiries: Wednesday, 9 July 2026 at 12h00.
Tender closing date and time: Thursday, 24 July 2026 at 12h00 (South African Time).
Briefing Session
Source: Volume 3 Tender and Contract.pdf (TENDER)
Compulsory briefing session: 19 June 2026 at 09h00 at Permit Office, Bram Fischer International Airport, 1 Old Thaba Nchu Road, Bloemfontein, 9300.
Non-compulsory site inspection: follows briefing on same day from 13h00 to 15h00.
Programme: 08h00-11h00 permits and registration, 11h00-11h30 escort to training centre, 11h30-12h30 briefing, 13h00-15h00 site inspection. No access after 11h00.
Required for site inspection: ID/driver's license, safety boots, reflector vest, valid airside temporary permit (R35.00 ex VAT, card payment only, available at permit office 08h00-11h00).
Contact Information
Source: Volume 3 Tender and Contract.pdf (TENDER)
All tender enquiries and communications must be directed to the Employer's Agent: Patricia Nkambule (SCM Representative).
Physical submission address: Finance Office, Terminal Building, Bram Fischer International Airport, 1 Old Thaba Nchu Road, Bloemfontein, 9300.
Submission Guidelines
Source: Volume 3 Tender and Contract.pdf (TENDER)
Submit bids during working hours Monday to Friday. Ensure the Bid Register is completed and signed when depositing.
Submit one original and one copy, sealed in clearly marked envelopes indicating 'Original' and 'Copy', with tenderer's name, contact details, reference number, and description.
Also submit an electronic copy via email to [email protected], well-labelled per the returnables schedule.
Both physical and electronic submissions are mandatory. Physical submission takes precedence if there is a discrepancy.
Failure to submit physical documents before the closing time will result in disqualification.
Late bids will not be accepted. Ensure envelopes have a return address for return of late submissions.
Tenders may only be submitted on the issued tender documentation; no re-typing allowed.
Tender validity must be held for 12 weeks (84 days).
Returnable Documents
Source: Volume 3 Tender and Contract.pdf (TENDER)
Submit bids during working hours Monday to Friday.
Complete and sign the Bid Register upon submission.
Submit one original and one copy, sealed and marked, with tenderer details, reference number, and description.
Email electronic copy to [email protected], well-labelled per returnables schedule.
Both physical and electronic submissions are mandatory; physical takes precedence if discrepancy.
Failure to submit physical documents before closing time results in disqualification.
Use only issued tender documentation.
Evaluation Criteria
Source: Volume 3 Tender and Contract.pdf (TENDER)
Mandatory: 1) CIDB grading 8CE or higher. 2) Attendance at compulsory briefing session. 3) Submission of fully signed Form of Offer. Technical/Functional: 1) Minimum functionality score of 75/100 based on company experience (wet services and/or service roads) and key personnel experience. 2) Projects cited for experience must be completed, with a minimum value of R30 million (VAT inclusive) each. 3) Construction Manager must be professionally registered (Pr CM, Pr CPM, Pr Eng, Pr Tech, or Pr Techni). 4) Health & Safety Officer must be SACPCMP-registered (CHSO/CHSM). Compliance: 1) Tax compliance status. 2) B-BBEE certification or sworn affidavit for preference points. 3) Submission in accordance with all formatting and delivery instructions.
Technical Specifications
Source: Volume 3 Tender and Contract.pdf (TENDER)
Scope: Construction of underground main water line and rehabilitation of service roads at Bram Fischer International Airport.
Contract duration: 24 months.
Key standards and documents:
Volume 1: General Conditions of Contract for Construction Works (2015) published by SAICE.
Volume 2: Standard General and Technical Specifications for Civil Works (COTO or South African Road Authorities 2020).
Volume 3: Tendering procedures, returnable documents, agreements, pricing data, scope of work, site information.
Volume 4: Tender drawings.
Volume 5: Manual of Procedures for Working on the Airside.
CIDB requirement: Tenderers must have a contractor grading of 8CE or higher (combined for JV/consortium).
Relevant experience defined for evaluation: Wet Services (bulk water pipeline, reticulation, pump stations) and Service Roads (asphalt construction, rehabilitation, special maintenance).
Financial Requirements
Source: Volume 3 Tender and Contract.pdf (TENDER)
Pricing must be in Rand, fixed for contract duration, subject to contract price adjustment per GCC Clause 6.8.
Include all duties and taxes except VAT; show VAT separately as an addition.
Tenderers must provide rates and prices in the pricing schedule/bills of quantities.
Errors in pricing: line-item totals govern; gross decimal misplacements corrected; arithmetic errors corrected with tenderer confirmation.
Securities, bonds, guarantees, policies, and insurance certificates may be required before contract formation.
Compliance Requirements
Source: Volume 3 Tender and Contract.pdf (TENDER)
Tax Compliance: Submit SARS PIN or TCS certificate; if not available, provide CSD number. For consortia/JV/sub-contractors, each party must submit separately.
CIDB Registration: Active registration with grading 8CE or higher mandatory.
B-BBEE: Preference points awarded per PPPFA 90/10 system. Proof required via sworn affidavit or SANAS-accredited B-BBEE certificate (consolidated for JV). Specific goals include status levels (1-8) and ownership by black youth, women, disabled persons, and subcontracting to eligible EMEs/QSEs.
Professional Registrations: Construction Manager must be registered with SACPCMP (Pr CM/Pr CPM) or ECSA (Pr Eng/Pr Tech/Pr Techni). Health and Safety Officer must be registered with SACPCMP as CHSO or CHSM.
Foreign Suppliers: If not resident/branch/establishment/income/tax liable in RSA, tax registration not required.
Requirements
Source: Volume 3 Tender and Contract.pdf (TENDER)
Late bids will not be accepted and may be returned unopened if a return address is provided.
ACSA is not liable for late bids.
No telegraphic, telephonic, telex, facsimile, or email tender submissions accepted.
Sealing, addressing, delivery, opening, and assessment requirements are stated in the Tender Data.
Section
Source: Volume 3 Tender and Contract.pdf (TENDER)
All tender enquiries must be directed to Patricia Nkambule via email: [email protected].
Closing date for enquiries: 9 July 2026 at 12h00.
Telegraphic, telephonic, telex, facsimile, or email tender submissions are not accepted.
Bidders may not contact any other ACSA employee regarding this tender.
Contact with ACSA Business Unit representatives is only permitted after award approval or for pre-existing commercial relations unrelated to this tender.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.