Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Quotation
Delivery Location
SOB Office Building - Cape Town International Airport - Cape Town -
Organization Type
GOVERNMENT
Published
07 Aug 2026
OCDS Reference
ocds-9t57fa-164949
Acsa cape town international airport requires the supply and delivery of aircraft extrication tools, including battery-operated cutters, spreaders, telescopic rams, floodlights, rescue straps, stabilisation struts, cribbing blocks, hazmat suits, and spill containment units. Bidders must submit a priced offer on the prescribed schedule by email before 12:00 on 21 august 2026, with all mandatory returnable documents, and the most consequential requirement is full compliance with nfpa 1960/EN 13204 for all cutting and spreading tools, which must weigh NO more than 21 kg each.
Submission deadline: 21 August 2026 at 12:00, by email only to [email protected]; late bids are not accepted.
Submission format: bids must be on official forms, split into at least four attachments of 4 MB each, and every page signed or stamped by an authorised person.
Mandatory returnable documents: SBD 3.3 (priced offer), SBD 4, SBD 6.1, Declaration of Interest and Politically Exposed Persons form, Confidentiality and Non-Disclosure Agreement, B-BBEE certificate or QSE/EME affidavit, tax PIN or CSD number, certificate of incorporation showing ownership split, CSD report, VAT questionnaire, and ACSA terms and conditions.
Technical compliance: all cutting and spreading tools must comply fully with NFPA 1960/EN 13204, have integrated LED lights, and weigh no more than 21 kg; batteries and chargers must be supplied.
Specific tool specifications: combi cutter minimum spreading width 405 mm (NFPA Class A7-B9-C7-D9-E9-F6), heavy-duty cutter NFPA Class A9-B9-C9-D9-E9-F7, spreader minimum spreading width 820 mm, telescopic rams with maximum extensions of 1500 mm, 1300 mm, and 750 mm.
Pricing: bidders must price only on the prescribed pricing schedule; failure to do so leads to disqualification, and prices must remain firm for 120 business days.
Preference points: 80/20 system applies (price 80 points, specific goals 20 points); B-BBEE levels and ownership categories (Black youth, Black women, people with disabilities) earn up to 5 points each, with proof required at submission.
Continue with tenders sharing this issuer, category, or province.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Friday, 21 August 2026 - 12:00
Venue
null
Categories
Request for Quotation
SOB Office Building - Cape Town International Airport - Cape Town -
Tenders in this industry often require registration with these bodies.
Recommended Certifications
Having these can improve your winning chances: RTMS (Road Transport Management System), ISO 28000 (Supply Chain Security), HACCP Certification (Food Transport)
AI Document Analysis Stages
Description
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdf07 Aug
2026
Tender Published
Tender was published
21 Aug
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdf
Supply and delivery of battery-operated aircraft extrication tools and related rescue equipment for the fire and rescue services at Cape Town International Airport, under RFQ 73191, with a 120-day validity period and an 80/20 preference point system.
To download these documents and access AI-powered analysis, visit the main tender page.
Organization
Airports Company South Africa (ACSA)Contact Person
Makhaya Jeremiah Mlenze
Phone
011-723-1400
Win ACSA tenders with AI Matching Engine, airport-infrastructure intelligence, compliance analysis, and application support for aviation operations.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubLearn how to submit a winning bid with these related articles
Median Estimate
R 1 870 000
Range
Based on 7 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Request for Quotation for the supply and delivery of aircraft extrication tools at Cape Town International Airport. RFQ 73191, issued 7 August 2026, closing 21 August 2026 at 12:00. No compulsory briefing and no site inspection.
Important Dates
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdf (RFQ)Closing — Friday, 21 August 2026 at 12:00.
Clarification deadline — requests for clarity may be made until 21 August 2026.
Compulsory briefing — none (N/A).
Site inspection — none (N/A).
Contact Information
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdf (RFQ)Bidding and technical enquiries — Makhaya J. Mlenze, Buyer, email [email protected].
Submission email — [email protected].
Restriction — bidders may not contact any ACSA employee other than the named buyer. After award, contact is only with ACSA Business Unit representatives.
Submission Guidelines
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdf (RFQ)Submission channel — email only, to [email protected], on or before 12:00 on 21 August 2026. Late bids are not accepted for consideration.
Format — bids must be submitted on the official forms provided, not re-typed, and in the prescribed format. Submissions must be split into at least four attachments of 4 MB each; one large attachment is not acceptable.
Signing — every page of the bid documents must be signed or stamped by a person authorised to act for the bidder, and proof of that authority (e.g. company resolution) must be submitted.
Disqualification risks — any mandatory returnable document omitted or unsigned; any change or alteration to the bid document; contacting any ACSA employee other than the named buyer; submitting after the closing time.
Returnable forms — SBD 3.3 (priced offer), SBD 4 (Bidder's Disclosure), SBD 6.1 (Preference Points Claim), Declaration of Interest and Politically Exposed Persons form, Confidentiality and Non-Disclosure Agreement, B-BBEE certificate or affidavit, tax PIN or CSD number, certificate of incorporation showing ownership split, CSD report, VAT questionnaire, and ACSA terms and conditions. All must be completed and signed.
Security — ACSA is a National Key Point; bidders may be subjected to security vetting and ACSA will not contract with a bidder that fails vetting.
Returnable Documents
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdf (RFQ)Mandatory returnable documents include: SBD 3.3 Priced offer, Declaration of Interest Form and Politically Exposed Persons, SBD 4 Bidder's Disclosure Form, SBD 6.1 Preference Points Claim Form, Confidentiality and Non-Disclosure Agreement, BEE Certificate and Scorecard or BBBEE QSE/EME Affidavit, Verifiable medical certificate of report as proof of disability (for preference claims), Tax Pin number (ACSA may not award to a bidder whose tax affairs have not been declared to be in order by SARS), Certificate of Incorporation of the bidding entity showing ownership split, Central Supplier Database Report (CSD), VAT Questionnaire, ACSA Terms and Conditions. Other returnable documents may be required at specific stages. Bidders must ensure all conditions, documents and information remain valid for the duration of the contract period.
Evaluation Criteria
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdf (RFQ)Preference point system — 80/20 system applies (contract value up to R50 million including taxes).
Points split — Price 80 points; Specific Goals / Preference 20 points; total 100.
Price formula — Ps = 80(1 - (Pt - Pmin)/Pmin), where Pt is the tender price under consideration and Pmin is the lowest acceptable tender price.
Specific goals — points awarded per the table: B-BBEE Level 1 = 5, Level 2 = 4.5, Level 3 = 4, Level 4 = 3, Level 5 = 2, Level 6 = 0.5, Level 7 = 0.3, Level 8 = 0.1; Black youth majority-owned = 5; Black women majority-owned = 5; majority owned by people with disabilities = 5; non-compliant contributor = 0.
Claiming preference — failure to submit proof or documentation for specific goals with the bid means those points are not claimed. ACSA may require substantiation of any preference claim at any time.
Disqualification — bidders on the Register for Tender Defaulters or List of Restricted Suppliers are automatically disqualified. Bidders must not have any conflict of interest with ACSA employees and must declare any politically exposed persons.
Technical Specifications
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdf (RFQ)Scope — supply and delivery of aircraft extrication tools for Cape Town International Airport.
Items and quantities:
All cutting and spreading tools must have integrated LED lights, weigh no more than 21 kg, and comply fully with NFPA 1960 / EN 13204. Batteries and chargers supplied.
Methodology
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdf (RFQ)Scope — supply and delivery of aircraft extrication tools. Items include battery-operated saws, cutters, spreaders and telescopic rams (with NFPA cutting class ratings and weight limits), floodlights, rescue straps, stabilisation struts, cribbing blocks, step chocks, Level A hazmat suits, fuel spill containment units and Vetter Magna Seals. All battery-operated tools must include batteries and chargers, have integrated LED lights, weigh no more than 21 kg, and comply with NFPA 1960 / EN 13204.
Pricing Schedule
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdfPricing — bidders must price only on the prescribed schedule (description, quantity, cost per unit, total, grand total). Failure to use the schedule disqualifies the bid. Disbursements reimbursed at actual cost with proof of expenses; other expenses must be specified and certified invoices checked.
Financial Requirements
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdf (RFQ)Pricing — bidders must price only on the prescribed pricing schedule (description, quantity, cost per unit, total, grand total). Failure to use the schedule makes the bid liable for disqualification.
Disbursements — reimbursed at actual cost; the successful bidder must provide proof of expenses. Other expenses (e.g. accommodation) must be specified and certified invoices will be checked.
Validity — prices must remain firm and valid for 120 business/working days from bid closing; changes only in exceptional circumstances.
Compliance Requirements
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdf (RFQ)Tax compliance — bidders must submit a SARS Tax Compliance Status (TCS) PIN, or a printed TCS certificate, or a CSD number if no TCS PIN is available. Each party in a consortium, joint venture or subcontracting arrangement must submit a separate TCS PIN / certificate / CSD number.
CSD — bidders must be registered on the Central Supplier Database and submit a CSD report.
B-BBEE — bidders must submit a B-BBEE certificate and scorecard, or a QSE/EME affidavit, to claim preference points.
Company registration — certificate of incorporation showing ownership split.
Declarations — SBD 4 (Bidder's Disclosure) declaring any directors or shareholders employed by the state; Declaration of Interest and Politically Exposed Persons form; SBD 6.1 (Preference Points Claim).
Disability — a verifiable medical certificate is required to claim preference points for disability.
Foreign suppliers — must complete the foreign supplier questionnaire; if not resident in South Africa and with no branch, permanent establishment, source of income or tax liability, they need not register for a SARS PIN.
Health & Safety
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdfEquipment safety — vehicle stabilisation struts must have a 4,500 kg capacity with a 2-in-1 safety factor; cribbing blocks and step chocks must be heavy-duty polyurethane. Hazmat suits must be Level A, reusable for airport environments, protecting against industrial chemicals, biological agents and toxic substances, and suitable for explosive areas and cryogenic substances with SCBA worn inside.
Contractual Terms
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdfValidity — prices must remain firm for 120 business/working days; changes only in exceptional circumstances.
ACSA rights — may award whole or part of the bid, split the award, negotiate with shortlisted bidders, award to a bidder other than the highest scorer where objective criteria allow, reject the lowest acceptable bid, or cancel the bid.
Confidentiality — ACSA will not disclose bidder information to third parties without written approval; bidders may not disclose bid information to third parties without ACSA approval, and any third party consulted must sign a confidentiality agreement returned with the bid.
Security — ACSA is a National Key Point; bidders may be security vetted and must comply with vetting to be contracted.
Contract — the successful bidder must have a fully completed and signed written contract post award.
Special Conditions
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdf (RFQ)Security vetting — ACSA is a National Key Point; bidders may be subjected to security vetting and ACSA will not contract with a bidder that fails vetting.
Section
Source: RFQ 73191_SUPPLY AND DELIVERY OF AIRCRAFT EXTRICATION TOOLS.pdf80/20 preference point system applies. Price 80 points, Specific Goals 20 points, total 100. Price scored by formula Ps = 80(1 - (Pt - Pmin)/Pmin). Specific goals points per B-BBEE status and ownership categories as tabled. Failure to submit proof for specific goals means those points are not claimed; ACSA may require substantiation of any claim.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 85 of 1993
Sets health and safety duties for contractors, employers and service providers working on public-sector sites.
Relevant because this tender appears to involve transport, fleet, logistics, public transport, vehicles, or road operations.
Act 5 of 2009
Relevant to public transport, fleet, logistics and subsidised transport service contracts.
Relevant because this tender appears to involve transport, fleet, logistics, public transport, vehicles, or road operations.
Act 93 of 1996
Relevant to roadworthiness, vehicle compliance and operator requirements in transport contracts.
Relevant because this tender appears to involve transport, fleet, logistics, public transport, vehicles, or road operations.
Address
SOB Office Building - Cape Town International Airport - Cape Town -
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
1
Last checked
07 Aug 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Air transport. Unlock full pricing strategies, bid frequency, and historical win rates.