This tender, issued by SANRAL, seeks consulting engineering services for a community development project and small contractor training and development along the r56 section 2 (km 0 to km 30) in steynsburg, eastern cape. The scope includes survey work, road safety audits, and compliance with technical and legal standards such as tmh11 and spluma.
Key Requirements
Survey work must comply with TMH11 version 3.0 (April 2017), including Chapters 1, 2, 3, and 12, and relevant sections for topographical, borrow pit, quarry, and structural surveys.
Road Safety Audits must follow the South African Road Safety Audit Manual (May 2012), with a minimum of 3 audits for new projects and 2 for upgrading projects.
The Road Safety Audit Team must include a registered Team Leader with 10+ years of experience and recognized training, along with at least two additional qualified members.
All survey work must be conducted by or under the supervision of a registered surveyor as per TMH11 Chapter 1.18.
Compliance with municipal spatial planning and land use management provisions (SPLUMA) is mandatory, with non-compliance issues requiring written notification and rectification.
Digital deliverables may include CAD drawings (Microstation/AutoCAD) and DTMs in specified formats, with hard copy or digital A0-size drawings as required.
Closing date for submissions is 21 August 2026 at 12:00.
CONSULTING ENGINEERING SERVICES FOR COMMUNITY DEVELOPMENT PROJECT AND SMALL CONTRACTOR TRAINING AND DEVELOPMENT IN STEYNSBURG ALONG R56 SECTION 2 FROM (KM 0) TO (KM 30
Tender context
Return to this tenderβs issuing organisation, province, or category.
Consulting engineering services for community development project and small contractor training and development in steynsburg along r56 section 2 from (km 0) to (km 30
Review in progress Β· 0 of 2 documents being finalised
AI Document Analysis Stages
Document read. The full tender notice and its supporting documents are read end-to-end. Key sections, requirements, dates, and contact details are identified and pulled into a working summary you can act on.
Compliance review. The working summary is checked against South African procurement standards β PFMA, PPPFA, B-BBEE, CIDB, local content, and preferential procurement β so nothing critical is missed before you start your bid response.
Procurement Rules & Compliance ContextThis tender may be governed by South African public procurement rules covering fairness, transparency, preferential procurement, anti-corruption, administrative justice and access to information.
10 rules
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
Core procurement rules
These rules commonly apply to South African public-sector procurement.
7
Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
high
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Constitution of the Republic of South Africa, 1996 β Section 217
Act 108 of 1996 (s217)
high
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
South African National Roads Agency Soc Limited (SANRAL)
OCDS Verified Google
Secure SANRAL tenders with AI Tender Discovery, road-infrastructure intelligence, compliance analysis, and application support for construction and engineering.
Similar Tenders
Matched by category & region
Supplier Readiness Hub
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Based on 3 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
Bid-ready summary. The submission guidelines, evaluation criteria, technical, financial, and compliance sections are refined into professional, easy-to-scan prose. This is the final version you can rely on when preparing your bid or briefing your team.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically β no action required from you.
Project Scope: Consulting engineering services for a community development project and small contractor training and development in Steynsburg along R56 Section 2 (km 0 to km 30).
Key Objectives:
Provide engineering services to support community development and contractor training initiatives.
Ensure compliance with SANRAL standards, including TMH11 for survey work and the South African Road Safety Audit Manual for safety audits.
Facilitate capacity development in road safety and engineering practices through structured audits and training programs.
Road Safety Audit Focus:
Proactive tool to reduce road safety risks without waiting for crash data.
Aims to create a forgiving, self-explaining road environment that meets the needs of all users.
Capacity development is a priority, with SANRAL leading efforts to train and accredit Road Safety Auditors.
Audits are mandatory for New Facilities and Upgrading Projects, with optional stages for other project types.
Scope: Consulting engineering services for community development project and small contractor training and development in Steynsburg along R56 Section 2 (km 0 to km 30).
Survey Requirements:
Survey must comply with TMH11 version 3.0 (April 2017), specifically Chapters 1, 2, 3, and 12, which are relevant to all surveys.
Topographical surveys must adhere to TMH11 Sections 6.1, 6.2, 6.6, 6.7, 6.8, and 6.9 where applicable.
Survey areas must be clearly indicated on a photo/Google image or attached as Annexure A.
Existing road surveys must show start and end points on a photo/Google image.
Borrow pit and quarry surveys must comply with TMH11 Sections 6.5.1, 6.5.2, and 6.5.3.
Site surveys for structures (bridges, culverts, gantries) must follow TMH11 Sections 6.4.1 to 6.4.5 and 8.7.1 to 8.7.6.
Structural surveys for existing structures must comply with TMH11 Chapter 14 and Section 8.7.
Monitoring surveys (structures, slopes, surfaces) must follow TMH11 Chapter 9.
Permanent survey control must be established as per TMH11 Chapter 5 if required.
Digital CAD drawings may be required in Microstation or AutoCAD formats.
DTMs may be required in Microstation TIN, AutoCAD TIN, Model Maker, or Civil Designer formats.
Hard copy or digital drawings in A0 size may be required.
Ground survey detail and DTMs may need to be spliced into photogrammetric/LiDAR surveys (TMH11 Section 6.8).
Field and office check surveys may be required (TMH11 Chapter 13).
Compliance certificate must be submitted on completion (TMH11 Section 1.13 and Annexure 23).
Survey must be undertaken by a registered surveyor or under the supervision of a registered Partner/Director of a survey organization (TMH11 Chapter 1.18).
Road Safety Audit Requirements:
Road Safety Audits must be conducted for New Facilities and Upgrading Projects (Strengthening and Improvement).
Minimum of 3 audits for New Projects, 2 for Upgrading Projects (Strengthening or Improvement).
Audit stages include Feasibility/Preliminary Design, Preliminary/Draft Design, Detail Design, Construction (optional), and Pre-opening (optional).
Road Safety Audit Team must include a Team Leader and at least two additional members.
Team Leader must be a Registered Professional Engineer or Technologist with ECSA (or equivalent), with 10+ years in Road Safety Design, Traffic/Transportation Engineering, or Geometric Design, and must have completed a recognized Road Safety Audit course (5 CPD points) within the last 5-8 years.
Team Members must have a Diploma/Degree in Engineering or equivalent, 3+ years of experience in relevant fields, and must have completed a recognized Road Safety Audit course (5 CPD points).
Engineering Service Provider (Main Consultant) must develop the Scope of Works for the Audit Team, recommend team composition, request quotations, and manage the audit process.
Audit process includes Project Information Review, Site Inspections, producing Audit Reports, Completion Meetings, Response Reports, and implementing design changes.
Close-out procedure requires formal sign-off by SANRAL Project Manager on responses to audit findings.
Non-compliance with municipal spatial planning and land use management provisions (e.g., building lines, FAR restrictions, zoning) must be reported in writing and rectified or condoned.
SANRAL is exempt from certain provincial planning approvals (LUPA sections 36(1) and 38(1)) for subdivisions and consolidations under this agreement.
Municipality must publish a notice of exemption within 60 days of agreement signature (LUPA section 43).
SANRAL may apply for additional exemptions under LUPA section 53(3) if required.
Project-Specific Compliance:
Survey work must be conducted by or under the supervision of a registered surveyor (TMH11 Chapter 1.18).
Road Safety Audits must follow the South African Road Safety Audit Manual (May 2012) as adopted by SANRAL.
Public participation and intergovernmental consultation processes must align with SPLUMA and SANRAL Act requirements.
Land development applications submitted by SANRAL must include a list of approvals sought, motivation, this agreement, and annexures.
Certificate of Compliance and Authorisation must be issued by the Municipality within 10 days of request, following approval of the land development application.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Kuisis St, Val-De-Grace, Pretoria, 0184, South Africa
Document-Backed
Recently Synced
Source Snapshot Available
AI Enhanced
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
2
Last checked
29 Jul 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Get deep intelligence on Architectural and engineering activities; technical testing and analysis. Unlock full pricing strategies, bid frequency, and historical win rates.