The airports company of south africa is procuring the refurbishment of the terminal building roof at chief dawid stuurman international airport in the eastern cape. Bidders must hold a CIDB contractor grading of 3gb or higher and achieve at least 70 out of 100 functionality points to qualify for price and preference evaluation under the 80/20 split. The most consequential requirement is the mandatory CIDB grading, which will determine whether an sme can bid at all.
Mandatory: Bidders must hold a CIDB contractor grading of 3GB or higher.
Mandatory: A fully completed and signed form of offer must be submitted.
Functionality threshold: Bidders must score at least 70 out of 100 points on functionality to proceed to price and preference evaluation (80/20 split).
Company experience (max 50 points): Provide proof of similar completed projects within the past 10 years (2016 to date) – five or more projects = 50 points, three to four = 40 points, fewer than three or untraceable references = 0 points.
Project principal (max 30 points): Must hold a Quantity Surveying or Civil Engineering qualification at NQF level 7 or higher, with 5+ years post-qualification experience = 30 points, 3–4 years = 20 points, less than 3 years = 0 points.
Project supervisor (max 20 points): Must hold a Quantity Surveying, Building, or Civil Engineering qualification at NQF level 6 or higher, with 5+ years post-qualification experience = 20 points, 3–4 years = 10 points, less than 3 years = 0 points.
Proof of completed projects must be submitted as project completion certificates or reference letters with traceable contact details and client signature; appointment letters will not earn points.
Continue with tenders sharing this issuer, category, or province.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Friday, 28 August 2026 - 13:00
Venue
Information desk, Chief Dawid Stuurman Airport
None.
Categories
Request for Quotation
Allister Miller Dr - Walmer - Gqeberha - 6070
Tenders in this industry often require registration with these bodies.
Construction Industry Development Board (CIDB) registration is mandatory for almost all public sector construction tenders. Ensure your grading matches the tender value.
Recommended Certifications
Having these can improve your winning chances: NHBRC Registration, ISO 9001:2015 (Quality Management), ISO 14001:2015 (Environmental Management), ISO 45001:2018 (Occupational Health & Safety), SACPCMP Registration, ECSA Registration
AI Document Analysis Stages
Review in progress
The information shown on this card is preliminary. Our procurement team is currently finalising the submission guidelines, evaluation criteria, technical specifications, financial requirements, and compliance sections so you have a clean, bid-ready summary to work from. Document being finalised: RFQ_16806_TERMINAL BUILDING ROOF REFURBISHMENT.pdf. You don’t need to refresh — this page will pick up the updated review automatically.
07 Aug
2026
Tender Published
Tender was published
28 Aug
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
RFQ_16806_TERMINAL BUILDING ROOF REFURBISHMENT.pdf
This tender is for the refurbishment of the terminal building roof at Chief Dawid Stuurman International Airport, issued by Airports Company South Africa (ACSA). The project requires a CIDB contractor grading of 3GB or higher. The tender process includes a non-compulsory briefing and site inspection, and the evaluation will follow a multi-stage process including functionality, price, and preference points (80/20 system). The contract will be fixed-price with no adjustments, and the successful bidder must comply with all tax and insurance requirements.
NEC 3 ECC - Roof Refurb (1).pdf
This tender is for the refurbishment of the terminal building roof at Chief Dawid Stuurman International Airport, issued by the Airports Company of South Africa (ACSA). The contract is based on the NEC3 Engineering and Construction Contract (ECC) with Main Option B (Priced contract with Bill of Quantities). The project duration is 6 months from contract signing, with a defects date 52 weeks after completion. The contractor will be responsible for providing the works, including design (lead designer required), and must comply with strict health, safety, and insurance requirements. The tender includes a Form of Offer and Acceptance, Contract Data, and various Z-clauses that modify the standard NEC3 conditions.
CDSIA ROOF REPAIRS DQ - Functionality (2) criteria final.pdf
This tender is for the refurbishment of the terminal building roof at Chief Dawid Stuurman International Airport, issued by the Airports Company of South Africa (ACSA). The evaluation process includes mandatory requirements, functionality (technical ability based on company experience and key personnel qualifications), and then price and B-BBEE (80/20 split). Bidders must achieve a minimum of 70 out of 100 functionality points to proceed to the next stage.
To download these documents and access AI-powered analysis, visit the main tender page.
Win ACSA tenders with AI Matching Engine, airport-infrastructure intelligence, compliance analysis, and application support for aviation operations.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubLearn how to submit a winning bid with these related articles
Median Estimate
R 2 510 966
Range
Based on 16 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Important Dates
Source: RFQ_16806_TERMINAL BUILDING ROOF REFURBISHMENT.pdf (TENDER)Closing date: 28 August 2026 at 13:00 (South African Time). Non-compulsory briefing and site inspection: 14 August 2026 at 12:00 (midday) at the Information Desk, Chief Dawid Stuurman International Airport. Attendees must bring an ID document or driver's licence, safety boots and a reflector vest; a permit fee applies. Closing date for enquiries: 21 August 2026. Tender documents available from 07 August 2026.
Contact Information
Source: RFQ_16806_TERMINAL BUILDING ROOF REFURBISHMENT.pdf (TENDER)Bidding procedure enquiries: Joseph Rulash, telephone 011 409 3943, email [email protected]. The Employer's Agent is Joseph Rulash. All communication during the tender period must go to ACSA's Supply Chain Department, not the Principal Agent. Tender box location: Administrator Office, Aeropark Office Complex, Block A, 1st Floor, Allister Miller Drive, Walmer, Eastern Cape, South Africa (P O Box 5787, Walmer, Gqeberha, 6065).
Submission Guidelines
Source: RFQ_16806_TERMINAL BUILDING ROOF REFURBISHMENT.pdf (TENDER)Bids must be delivered to the Tender Box at the Administrator Office, Aeropark Office Complex, Block A, 1st Floor, Allister Miller Drive, Walmer, Eastern Cape, before 13:00 on 28 August 2026. Submit during working hours Monday to Friday. The Bid Register must be completed by the person depositing the bid. The bid document and contract document must be completed in full and returned with all supporting information. Tenders may only be submitted on the official tender documentation issued. Submit an original plus one copy and an electronic version on a USB flash drive, with packages marked "ORIGINAL" and "COPY". The outer package must show the employer's address and the bidder's return address. Late bids will be returned unopened. Telephonic, telegraphic, telex, facsimile and email tenders will not be accepted. The tender offer must remain valid for 12 weeks (84 days) after closing. Returnable documents include SBD 1 (Invitation to Bid), the completed contract document (Appendix 1), and the pricing schedules. Proof of authority to sign (e.g. company resolution) must be submitted. Bids must be signed in non-erasable ink; alterations must be initialled. Alternative bids will not be considered. Bidders may not contact ACSA employees other than the listed contact person during the tender period.
Evaluation Criteria
Source: RFQ_16806_TERMINAL BUILDING ROOF REFURBISHMENT.pdf (TENDER)Eligibility: Only tenderers with a CIDB contractor grading of 3GB or higher may submit. Evaluation stages: Stage 1 tests responsiveness; Stage 2 checks mandatory administration criteria (fully completed and signed form of offer, CIDB grading); Stage 4 evaluates functionality with a minimum threshold of 70 out of 100 points to proceed; Stage 5 applies the 80/20 preference point system for bids up to R50 million. Price scoring uses the formula Ps = 80(1 - (Pt - Pmin)/Pmin). Preference points (maximum 20) are awarded for B-BBEE status levels and specific goals: Level 1 (5 points), Level 2 (4.5), Level 3 (4), Level 4 (3), Level 5 (2), Level 6 (0.5), Level 7 (0.3), Level 8 (0.1). Additional 5 points each for black youth majority-owned, black women majority-owned, and majority-owned by people with disabilities. Non-compliant contributors score 0. Proof of preference claims must be submitted (sworn affidavit or SANAS-accredited B-BBEE certificate; JVs need a consolidated certificate). Failure to submit proof results in zero preference points but not disqualification. The contract is awarded to the highest scoring bidder unless objective criteria justify otherwise.
Technical Specifications
Source: RFQ_16806_TERMINAL BUILDING ROOF REFURBISHMENT.pdf (TENDER)The scope is the refurbishment of the terminal building roof at Chief Dawid Stuurman International Airport. The detailed scope of work is provided in Part C3 (Works Information / Scope of Work) and site information in Part C4. The contract is subject to the CIDB Standard Conditions of Tender (Annex C of the CIDB Standard for Uniformity in Construction Procurement, 8 August 2019). Prices are fixed for the contract duration with no price adjustments. The successful bidder must complete the Occupational Health and Safety Agreement and provide insurance as specified in the contract data.
Financial Requirements
Source: RFQ_16806_TERMINAL BUILDING ROOF REFURBISHMENT.pdf (TENDER)Prices must be stated in Rand, include all duties, taxes (except VAT) and levies applicable 14 days before closing, with VAT shown separately. Rates and prices are fixed and not subject to adjustment. The contract is not subject to price adjustments or foreign fluctuations. The bidder may be required to submit securities, bonds, guarantees, policies and certificates of insurance before contract formation. The employer does not compensate tenderers for costs of preparing bids.
Compliance Requirements
Source: RFQ_16806_TERMINAL BUILDING ROOF REFURBISHMENT.pdf (TENDER)CIDB contractor grading of 3GB or higher is mandatory. Tax compliance: bidders must submit a SARS Tax Compliance Status (TCS) PIN or a printed TCS certificate; if not available, a CSD number must be provided. Joint ventures and sub-contractors must each submit separate TCS/CSD documentation. Bidders must be registered on the Central Supplier Database (CSD) or provide a CSD number. B-BBEE: preference points are claimed via SBD 6.1 (Preference Points Claim) with proof of B-BBEE status (SANAS-accredited certificate or sworn affidavit). SBD 4 (Declaration of Interest) and SBD 9 (Certificate of Independent Bid Determination) are required. Proof of authority to sign (company resolution) must be submitted. Foreign suppliers must complete the foreign supplier questionnaire. Bidders must not be under restrictions from doing business with ACSA, must have legal capacity, and must not be insolvent or under business rescue.
Description
Source: NEC 3 ECC - Roof Refurb (1).pdfThe works comprise the refurbishment of the terminal building roof at Chief Dawid Stuurman International Airport. The contract is governed by the NEC3 Engineering and Construction Contract, April 2013. The site is the terminal building roof. The Works Information is in Part C3 and Site Information in Part C4. The law of the contract is the law of the Republic of South Africa; the language is English. The period of reply is seven days. The period of retention is six months following completion or earlier termination.
Contact Information
Source: NEC 3 ECC - Roof Refurb (1).pdf (unknown)Employer: Airports Company South Africa SOC Limited, Chief Dawid Stuurman International Airport, Aeropark Office Complex, Block A, 1st Floor, Alister Miller Drive, Walmer, Gqeberha, Eastern Cape. Telephone: +27 41 507 7362. Project Manager: Zuzokuhle Mbanjwa, at the same address. Supervisor: to be confirmed.
Submission Guidelines
Source: NEC 3 ECC - Roof Refurb (1).pdf (unknown)Returnable documents: the completed Form of Offer and Acceptance (Part C1.1) with the offered total price in words and figures, the Schedule of Deviations (if any), and the completed Contract Data Part C1.2b. Pricing must be submitted in the Pricing Data (Part C2). Key personnel CVs must be appended to the tender schedule. The offer must remain valid for the period stated in the Tender Data. Within two weeks of receiving the accepted contract, the contractor must arrange delivery of any securities, bonds, guarantees, proof of insurance and other documentation required by the contract; failure to do so constitutes repudiation. Unless the contractor notifies the employer in writing within five working days of receiving the completed agreement of any reason it cannot accept the contents, the agreement becomes binding.
Evaluation Criteria
Source: NEC 3 ECC - Roof Refurb (1).pdf (unknown)No explicit evaluation criteria or scoring split are stated in the document. The contract is a priced contract with a bill of quantities (NEC3 Main Option B), so price forms the basis of the contract, but no preference point system or minimum qualifying thresholds are specified.
Technical Specifications
Source: NEC 3 ECC - Roof Refurb (1).pdf (unknown)Works: refurbishment of the terminal building roof at Chief Dawid Stuurman International Airport. Site boundaries: the terminal building roof. The Works Information is in Part C3 (Scope of Work) and Site Information in Part C4. The contractor must provide the works in accordance with the Works Information and warrants the results will be fit for their intended purpose. The contractor must satisfy itself, before the contract date, as to the completeness, sufficiency and accuracy of all information and drawings provided. The contractor is responsible for correct setting out of the works; any errors in positioning must be rectified at the contractor's own cost. The contractor must employ a lead designer with proof of qualifications. The contractor must submit a first (preliminary) programme with the tender, and revised programmes at intervals no longer than four weeks. The employer provides access to all as-built information and existing services, and to relevant engineering, operational and maintenance personnel of ACSA, upon signing of the contract.
Experience & Qualifications
Source: NEC 3 ECC - Roof Refurb (1).pdfThe contractor must provide CVs of key personnel appended to the tender schedule, including name, responsibilities, qualifications and experience. The contractor must employ a lead designer with proof of qualifications. The completion date for the whole of the works is six months from the date of contract signing by ACSA. The risk register will include availability of as-built information, access to site, progress versus programme, and cash flow management. The employer provides access to all as-built information and existing services, and to relevant engineering, operational and maintenance personnel of ACSA, upon signing of the contract.
Quality Management
Source: NEC 3 ECC - Roof Refurb (1).pdfThe contractor must provide a quality policy statement and quality plan within four weeks of the contract date. The defects date is 52 weeks after completion of the whole of the works. The defects correction period is two weeks. If the employer cannot use the works due to a defect arising after completion and before the defects date, the defects date is delayed by the period of non-use; if part of the works is replaced, the defects date for that part is delayed accordingly, but the extension cannot exceed twice the period between completion and the original defects date.
Pricing Schedule
Source: NEC 3 ECC - Roof Refurb (1).pdfThe contract is a priced contract with a bill of quantities (NEC3 Main Option B). Pricing data is in Part C2. The offered total of the prices inclusive of VAT must be stated in the Form of Offer and Acceptance, in words and figures. The offered prices are as stated in the pricing schedule. Payment assessments occur every four weeks on the 20th day of each successive month, with payment within four to six weeks after receipt of the tax invoice. The currency is South African Rand. Retention is 10% of the prices, with 50% released at practical completion and the remaining 50% after the defects period.
Financial Requirements
Source: NEC 3 ECC - Roof Refurb (1).pdf (unknown)Pricing: the contract is a priced contract with a bill of quantities (NEC3 Main Option B); pricing data is in Part C2. The offered total of the prices inclusive of VAT must be stated in the Form of Offer and Acceptance. Payment: assessments every four weeks, on the 20th day of each successive month; payment within four to six weeks after receipt of the tax invoice. Currency: South African Rand. Interest on late payment: prime lending rate of Nedbank Bank as determined from time to time. Retention: 10% of the prices, with 50% released at practical completion and the remaining 50% after the defects period. Performance bond: unconditional, on-demand, provided by a bank accepted by the project manager and employer, for the amount stated in the contract data; must remain valid until the end of the contract period, and if it expires earlier the contractor must extend it four weeks before expiry or the employer may claim the full amount as cash security. Delay damages: 1% per week up to a maximum of 10% of the contract value. Limitation of liability: neither party is liable for indirect or consequential loss; the employer's liability to the contractor for indirect or consequential loss is limited to R0.00. The contractor's total liability for all matters is limited to the total of losses incurred and/or repairs to damages caused, excluding certain matters (loss of or damage to employer's property, delay damages, defects liability, insurance liability, damage to third party property, death or injury, IP infringement).
Compliance Requirements
Source: NEC 3 ECC - Roof Refurb (1).pdf (unknown)Occupational Health and Safety: the contractor must sign the OHS agreement under Section 37(2) of the OHS Act and Construction Regulation 5.1(k) before any work commences. The contractor must be an employer in its own right with duties under the OHS Act and Construction Regulations. Insurance: the contractor must ensure all employees are covered under the COID Act and provide a letter confirming good standing with the Compensation Fund or licensed insurer before starting work. The contractor must maintain public liability insurance and any other cover required by the subcontract agreement. The contractor must submit safety documentation, including a copy of the written Construction Manager appointment under Construction Regulation 8, seven days before work commences. The contractor must comply with all laws relating to bribery and corruption, including the Prevention and Combating of Corrupt Activities Act. The contractor must not cede, delegate or assign any rights or obligations without the employer's written consent. If the contractor is a joint venture or consortium, members are jointly and severally liable, and the contractor must notify the project manager and employer of the key person authorised to bind it within one week of the contract date.
Health & Safety
Source: NEC 3 ECC - Roof Refurb (1).pdfThe contractor must sign the Occupational Health and Safety Agreement under Section 37(2) of the OHS Act and Construction Regulation 5.1(k) before any work commences. The contractor is an employer in its own right with duties under the OHS Act and Construction Regulations. Requirements include: ensuring employees are covered under the COID Act and providing a letter of good standing with the Compensation Fund or licensed insurer; maintaining public liability insurance; conducting a baseline risk assessment by a competent person before work starts; appointing competent persons trained in OHS; providing and enforcing PPE use; reporting incidents to the Provincial Director of the Department of Labour and to the client; obtaining permits for work requiring them; prohibiting alcohol and intoxicating substances on site; and submitting safety documentation, including the written Construction Manager appointment under Construction Regulation 8, seven days before work commences. Only a duly authorised representative appointed under Section 16.2 of the OHS Act may sign the agreement, with signing power designated in writing by the CEO. Non-compliance may lead to immediate cancellation of the contract.
Contractual Terms
Source: NEC 3 ECC - Roof Refurb (1).pdfInsurance: the employer effects Principal Controlled Insurance (PCI) in joint names of the employer, contractor and relevant subcontractors, including Contract Works, Public Liability (R100,000,000 per occurrence), Removal of Lateral Support Liability (R50,000,000), Contract Works SASRIA (R500,000,000 aggregate), Aviation Liability (R2,000,000,000 per occurrence), and Design & Construct Professional Indemnity (R25,000,000 aggregate, shared across all ACSA contracts). The contractor must familiarise itself with the policy terms and comply with all conditions. The contractor must maintain its own insurances as required, including COID cover and public liability. The contractor must provide a letter confirming good standing with the Compensation Fund or licensed insurer before starting work. The insurances are in joint names and provide cover for events at the contractor's risk from the starting date until the defects certificate or termination certificate is issued.
Section
Source: NEC 3 ECC - Roof Refurb (1).pdfNo evaluation criteria are stated in the document. The quality policy statement and quality plan must be provided within four weeks of the contract date.
Contact Information
Source: CDSIA ROOF REPAIRS DQ - Functionality (2) criteria final.pdf (unknown){"name":null,"email":null,"phone":null,"department":null,"address":"es rendered, value of contract,"}
Evaluation Criteria
Source: CDSIA ROOF REPAIRS DQ - Functionality (2) criteria final.pdf (unknown)Mandatory requirements: bidders must hold a CIDB contractor grading of 3GB or higher and submit a fully completed and signed form of offer.
Functionality evaluation is scored out of 100 points; bidders must achieve at least 70 points to proceed to price and preference evaluation under the 80/20 split.
Company Experience (maximum 50 points):
Project Principal Qualification and Experience (maximum 30 points):
Project Supervisor Qualification and Experience (maximum 20 points):
Similar projects are defined as building roof refurbishment, roof waterproofing, construction of concrete roofs, roof extension and alterations, and construction of new buildings with concrete roofs.
Proof of completed projects must be submitted as project completion certificates or reference letters with traceable contact details and client signature. Appointment letters will not earn points.
Technical Specifications
Source: CDSIA ROOF REPAIRS DQ - Functionality (2) criteria final.pdf (unknown)The scope covers terminal building roof refurbishment at Chief Dawid Stuurman International Airport. Similar projects include building roof refurbishment, roof waterproofing, construction of concrete roofs, roof extension and alterations, and construction of new buildings with concrete roofs.
Experience & Qualifications
Source: CDSIA ROOF REPAIRS DQ - Functionality (2) criteria final.pdfProject Supervisor Qualification and Experience: Proof of qualification(s) and experience in the form of a comprehensive CV. Project Supervisor shall obtain Quantity Surveying or Building or Civil Engineering qualification with minimum NQF level 6 qualification. Experience should be in relation to built environment projects. Scoring: Project Supervisor with 5 or more years of experience post NQF 6 qualification = 20 points; 3 to 4 years of experience post NQF 6 qualification = 10 points; less than 3 years of experience, irrelevant experience, or no submission = 0 points.
Compliance Requirements
Source: CDSIA ROOF REPAIRS DQ - Functionality (2) criteria final.pdf (unknown)CIDB contractor grading of 3GB or higher is mandatory.
A fully completed and signed form of offer is required.
B-BBEE preference points will be evaluated under the 80/20 split after functionality threshold is met.
Section
Source: CDSIA ROOF REPAIRS DQ - Functionality (2) criteria final.pdfFunctionality evaluation includes Company Experience and Key Personnel Qualification and Experience. Total points allocated shall be 100. Bidders must achieve minimum of 70 points out of 100 to be eligible for further evaluation on Price and Preference (80/20 split).
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 38 of 2000
Important for public-sector construction and infrastructure tenders that require contractor grading or construction procurement standards.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 107 of 1998
Relevant where environmental authorisations, EIAs or environmental compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 85 of 1993
Sets health and safety duties for contractors, employers and service providers working on public-sector sites.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 103 of 1977
Relevant where building standards, renovations, maintenance or construction compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Address
Allister Miller Dr - Walmer - Gqeberha - 6070
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
3
Last checked
07 Aug 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Services: Building. Unlock full pricing strategies, bid frequency, and historical win rates.