Works description: construction of new ablution facilities at Gumzana Secondary School.
Site: the existing school premises.
Contract period: 18 weeks from possession of site.
Commencement: within 5 working days of taking possession.
Contract form: JBCC Series Edition 4.1, March 2005, with Preliminaries JBCC Series 2000, May 2005.
Bills of quantities: measured in accordance with the Standard System of Measuring Building Work, Seventh Edition.
Contractor to provide site office (4x3m), lockable storage container, and temporary services (water, electricity, telecommunications, ablutions) at own cost.
Contractor to erect temporary fencing: 300m of 1.8m high SANS approved weld mesh with green shade netting, plus vehicle and pedestrian gates.
Contractor to provide as-built drawings (three sets) within 14 days after practical completion.
Contractor to maintain site records: construction instruction book, daily record book, weekly labour and plant records.
Contractor to provide a method statement when required by the Principal Agent.
Contractor to provide a full-time Health and Safety Officer for the entire construction period.
Contractor to provide induction training, first aid boxes, PPE (reflective vests, hard hats, protective footwear, ear plugs, dust masks), medical examinations (baseline and exit), and noise monitoring (noise zones, audiograms).
Costs must include a Community Liaison Officer (CLO).