Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
Nelson Mandela Drive. - Lephalale - Lephalale - 0555
Organization Type
GOVERNMENT
Published
28 Oct 2026
OCDS Reference
ocds-9t57fa-176192
ESKOM requires a contractor to review the approved design, install, produce as-built drawings, and commission an automatic fixed fire detection and protection system for the unit 2-6 diesel generators at matimba power station in limpopo. The new system must integrate with the existing station fire system, which is fed by fire pumps from the outside plant services building. Bidders must hold CIDB level 4sf or higher and employ ecsa-registered engineers across mechanical, civil, and c&i disciplines, and must achieve a minimum technical score of 80% to be considered compliant.
Mandatory CIDB registration: Bidder must be registered with the Construction Industry Development Board at Level 4SF or above; proof of registration must be submitted.
Mandatory ECSA registration: All design engineers (Mechanical, Civil, and C&I) must be professionally registered with ECSA; valid certification must be provided.
Technical threshold: The minimum weighted final technical score is 80%; bids below this are non-compliant.
Qualitative scoring: Criteria are scored 0, 2, 4, or 5 (no 1 or 3); weightings are: contractor fire protection experience 30%, mechanical technologist/engineer CV 10%, method statement 10%, C&I method statement 10%, C&I key resource 15%, civil contractor experience 12.5%, civil engineer CV 12.5%.
Unacceptable exception: Bidders with no previous track record of successfully completed similar projects will be disqualified.
Scope deliverables: The work includes design review, installation, as-built drawings, and commissioning of the fire detection and protection system for Units 2-6, tied into the existing station fire system.
B-BBEE: Minimum Level 4 is required (per compliance requirements).
Continue with tenders sharing this issuer, category, or province.
Browse categories with current opportunities in this area.
Compare tender activity across provinces.
Explore organisations currently publishing tenders.
Tools and research to help you assess opportunities.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Browse categories with current opportunities in this area.
Compare tender activity across provinces.
Explore organisations currently publishing tenders.
Tools and research to help you assess opportunities.
Date & Time
Friday, 20 November 2026 - 10:00
Venue
https://teams.microsoft.com/meet/3804203620432627?p=dXsmngXEuGKiKOz0XY
Important: Attendance at this briefing session is mandatory. Bids from suppliers who do not attend may be disqualified.
Categories
Request for Bid(Open-Tender)
Nelson Mandela Drive. - Lephalale - Lephalale - 0555
Tenders in this industry often require registration with these bodies.
Recommended Certifications
Having these can improve your winning chances: CA(SA) - Chartered Accountant, PMI-PMP (Project Management Professional), Prince2 Practitioner, Six Sigma Certification
AI Document Analysis Stages
Description
28 Oct
2026
Tender Published
Tender was published
20 Nov
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
001.pdf
Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdf
Eskom requires a contractor to review the design, supply, install, test and commission automatic fixed fire detection and protection systems for the diesel generators and associated day tanks at Units 2, 3, 4, 5 and 6 at Matimba Power Station in Limpopo. The work includes mechanical, civil, C&I, painting, bunding, a fire barrier between Units 2 and 3, integration with the existing fire protection and detection systems, and provision of as-built documentation and training.
007.pdf
005.pdf
003.pdf
240-12248652_List of Tender Returnables_Cat 3_ Rev 7.docx
Eskom requires a contractor to design, supply, install, and commission fire protection systems for diesel generators at Matimba Power Station, covering Units 2 to 6. The tender includes quality management system requirements, a contract quality plan, and a quality control plan, with evaluation based on compliance with ISO 9001 and project-specific quality deliverables.
F240044 REV3 ENVIRONMENTAL EVALUATION LOW RISK ACTIVITY (5).xlsx
ESKOM requires fire protection for the diesel generators of Units 2-6 at Matimba Power Station in Limpopo. The work is classified as a low-risk environmental activity, and bidders must submit an environmental policy, an aspects and impacts register, and a method statement, scoring at least 90% on the environmental evaluation.
Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdf
Eskom requires the design review, supply, installation, testing and commissioning of automatic fixed fire detection and protection systems for the diesel generators and associated day tanks at Units 2, 3, 4, 5 and 6 of Matimba Power Station in Limpopo. The work includes mechanical, civil, C&I and training components, with the system to be integrated into the existing fire protection and detection network.
Annexure B (Acknowledgement of SHE requirements).docx
Eskom requires fire protection for diesel generators at Matimba Power Station, Units 2-6, in Limpopo. The contract includes strict compliance with Eskom's OHS standards and statutory requirements, with penalties for non-conformance.
240-109253302 Quality Control Plan Inspection and Test Plan QCP ITP - Copy.docx
Procurement of fire protection works for the diesel generators on Units 2-6 at Matimba Power Station, owned by Eskom, located in Limpopo province.
NEC ECC3 Unit 2-6 Diesel Generator Fire Protection Project.docx
Eskom requires the supply, installation, testing, commissioning and handover of automatic fixed fire protection and detection systems for the diesel generators and their associated 1,000-litre diesel day tanks for Units 2, 3, 4, 5 and 6 at Matimba Power Station in Limpopo. The contract is an NEC3 Engineering and Construction Contract (Option A, lump sum with activity schedule) and includes design, documentation, KKS codification, labelling, health and safety compliance, and environmental management obligations.
U2-6.pdf
Eskom requires a contractor for the design, installation, and commissioning of fire protection systems for diesel generators at Matimba Power Station (Units 2-6). The scope includes mechanical, control and instrumentation, and civil works, with a mandatory CIDB grading of 4SF or higher and a technical evaluation threshold of 80%.
240-109253698 Template for a Typical Contract Quality Plan.docx
Eskom requires a Contract Quality Plan (CQP) from suppliers bidding for the Matimba Power Station Unit 2-6 Diesel Generator Fire Protection contract. The CQP must detail how the supplier will meet quality management requirements, referencing SANS 466:2005 / ISO 10005:2005, and cover aspects such as scope of work, communication, sub-supplier management, inspection and testing, documentation control, and post-delivery activities.
Tender Technical Evaluation Strategy - Unit 2 - 6 Diesel Generator Fire Protection System 20260622.pdf
Eskom requires the review of an approved design, installation, production of as-built drawings and commissioning of automatic fixed fire detection and protection systems for the diesel generators on Units 2-6 at Matimba Power Station in Limpopo. The new fire system will tie into the existing station fire system supplied by water from fire pumps in the outside plant services building.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
R 1 676 700
Range
Based on 21 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Matimba Power Station relies on diesel generators for backup power to the units and the station during blackouts, and for black-start operation. The generators run on 24-hour standby; each unit has its own generator plus one for the station, giving seven on site. They are installed at 0 m level outside and on the southern side of the turbine building at units 2 to 6, each with an associated diesel day tank of about 1 000 l.
The work is to deliver a fully functional automatic fixed fire protection and detection system for the unit 2, 3, 4, 5 and 6 diesel generators and their day tanks. It covers design review, supply and installation, procurement and fabrication of plant and material, delivery and storage on site, all structural, civil, builders, plumbing, drainage, mechanical, electrical and C&I work, painting, bund construction, a fire barrier between units 2 and 3, integration with the existing fire protection system, scaffolding, connection of pressure/flow switches to the existing detection system for control room and EOD alarms, KKS numbering of standard components, and commissioning and testing.
Technical Specifications
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdf (unknown)Purpose
Site conditions
Scope of work
Design requirements
Sprinkler and pipework
Civil works
Control and instrumentation
Testing and commissioning
As-built documentation to be submitted on completion
Training
Quality Management
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdfQuality control plans (QCPs) must be submitted to the employer for review and approval before any work begins.
The contractor must supply welding procedures, welder qualifications, non-destructive testing reports, coating inspection reports, material certificates and hydrostatic test certificates.
Updated as-built drawings reflecting all modifications, valve locations and elevations must be handed over in both hard copy and electronic format.
Commissioning records, test reports, as-built drawings, compliance certificates and operation and maintenance manuals must be submitted for review, witnessing and final acceptance.
Compliance Requirements
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdf (unknown)Applicable standards
Quality requirements
Health & Safety
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdfThe Occupational Health and Safety Act, 1993 applies to the works.
The installation must comply with the fire protection and life safety standards named in the specification: NFPA 850, NFPA 13, NFPA 15, SANS 10287, SANS 1128-2, SANS 10139 and Eskom standards 240-54937450, 240-54937448 and 240-54937439.
Description
Source: 240-109253698 Template for a Typical Contract Quality Plan.docxThe document is a blank Contract Quality Plan (CQP) template that the successful bidder must complete and maintain. It requires the bidder to plan how it will meet quality management expectations for the contract, based on SANS 466:2005 and ISO 10005:2005.
Key obligations the template imposes on the bidder once awarded:
The template also requires signatures and approvals from the bidder (compiled by a representative, approved by the owner) and from Eskom (reviewed by Project Coordinator/Site Engineer/QC, accepted by Contract Manager/End User/Project Manager). The scope-of-work category must be marked: design, manufacturing, supply and delivery/transportation, construction/installation/maintenance, commissioning, professional services, or other.
Submission Guidelines
Source: 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.docx (unknown)Returnable documents for the Category 3 quality evaluation
Evaluation Criteria
Source: 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.docx (unknown)Category 3 quality requirements — each listed deliverable scores 1 point where provided (Apply = 1).
Section A — Quality Management System (ISO 9001): 6 points
Section B — Evidence of QMS in operation: 2 points
Section C — Contract Quality Plan: 1 point
Section D — Quality Control Plan: 1 point
Section E — Additional requirements: 1 point
Total available: 11 points.
Technical Specifications
Source: 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.docx (unknown)Scope: fire protection for the diesel generators serving Units 2 to 6 at Matimba Power Station, Limpopo.
Quality deliverables must address:
Compliance Requirements
Source: 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.docx (unknown)Quality management system
Submission Guidelines
Source: 240-109253302 Quality Control Plan Inspection and Test Plan QCP ITP - Copy.docx (unknown)Returnable Documents: The tender document provided does not specify returnable forms; however, the standard Eskom tender pack typically requires completion of the Quality Control Plan (QCP) with inspection and test plan (ITP) as applicable. No specific submission method or address is stated.
Technical Specifications
Source: 240-109253302 Quality Control Plan Inspection and Test Plan QCP ITP - Copy.docx (unknown)Scope of Work: Fire protection for diesel generators in Units 2-6 at Matimba Power Station. The QCP/ITP template indicates that the contractor/supplier must provide a Quality Control Plan covering inspection and test activities, with intervention points (hold, witness, document review, surveillance, verification), inspection and test methods (visual, microscopy, NDT, dye penetrant, magnetic particle, etc.), acceptance criteria, and controlling documents. Records must be maintained for all activities.
Compliance Requirements
Source: 240-109253302 Quality Control Plan Inspection and Test Plan QCP ITP - Copy.docx (unknown)No specific compliance requirements are stated in the provided document. Standard Eskom requirements (CSD registration, tax clearance, B-BBEE) are not mentioned in the extract.
Description
Source: NEC ECC3 Unit 2-6 Diesel Generator Fire Protection Project.docxThe Employer, identified in the Acceptance signature block, solicits offers to enter into a contract for the procurement of Unit 2-6 Diesel Generator Fire Protection. The work is for Matimba Power Station.
Submission Guidelines
Source: NEC ECC3 Unit 2-6 Diesel Generator Fire Protection Project.docx (unknown)Returnable documents: signed Form of Offer and Acceptance (NEC ECC3), including any Schedule of Deviations. No deviations are valid unless recorded in the Schedule. Submission method and address are not stated in the document.
Evaluation Criteria
Source: NEC ECC3 Unit 2-6 Diesel Generator Fire Protection Project.docx (unknown)No evaluation criteria stated in the document
Technical Specifications
Source: NEC ECC3 Unit 2-6 Diesel Generator Fire Protection Project.docx (unknown)Scope: supply, installation, testing, commissioning and handover of automatic fixed fire protection and detection systems, including all associated works, for diesel generators and their day tanks for Units 2, 3, 4, 5 and 6 at Matimba Power Station.
Diesel generators are located at the 0 m level on the southern exterior of the turbine building. Each unit has a dedicated diesel day tank with approximately 1000 litres capacity.
The systems must comply with safety and statutory regulations and Eskom requirements.
Contract type: NEC3 Engineering & Construction Contract (ECC3), Option A (lump sum with activity schedule). Work is priced as lump-sum activities; only completed activities are assessed for payment.
The Contractor is responsible for design where required by the Employer's design requirements.
Comprehensive documentation is required: engineering, operating, maintenance and training documentation, submitted electronically and in hard copy, in British English, and in PDF and editable format.
The Contractor must apply the KKS codification system to all plant, equipment, components and documents, and obtain KKS certificates prior to commissioning.
As-built drawings and operating manuals must be submitted upon completion.
The Contractor must prepare a Configuration Management Plan using ISO 10007 as a reference.
The Contractor must prepare and submit monthly Master Document Lists to the Employer.
Financial Requirements
Source: NEC ECC3 Unit 2-6 Diesel Generator Fire Protection Project.docx (unknown)Secondary Options X4 (parent company guarantee), X13 (performance bond), X14 (advance payment to the Contractor) and X16 (retention) require bonds or guarantees in the form set out in the Works Information. Guarantees must be issued on the bank's letterhead without any change to the text or format.
The Contractor may provide a Retention Money Guarantee. If accepted, the Project Manager will not assess retention.
The Contractor must guarantee its ASGI-SA obligations by providing an ASGI-SA Guarantee.
Pricing: NEC3 Option A lump sum, priced via an activity schedule. No adjustment for quantity changes; change only through compensation events.
Compliance Requirements
Source: NEC ECC3 Unit 2-6 Diesel Generator Fire Protection Project.docx (unknown)The Contractor is deemed the Employer under the Occupational Health and Safety Act 85 of 1993 for its activities and must comply with all regulations.
A written mandatory agreement under Section 37(2) of OHSA and the Construction Regulations must be concluded with Eskom before commencing work.
A Health and Safety File must be compiled, including: health and safety policy, appointments, risk assessments, safe work procedures, emergency plan, fall protection plan, notification to the Department of Labour, induction program, medical fitness certificates, weekly SHE inspections, PPE records, accident reporting system, and tool/equipment checks.
A valid COIDA letter of good standing is required for site access.
Compliance with Employer's Safety Health and Environmental Specification 240-149136837 and SHE Requirements Procedure (32-726) is required.
Eskom Life-Saving Rules (240-62196227) apply; violations are treated as serious misconduct with zero tolerance.
Workers must be medically fit (certificate valid one year), have police clearance, be inducted on site, and wear applicable PPE.
An Environmental Management Plan and various environmental documents (method statement, asbestos risk assessment, waste management plan, emergency preparedness and response plan) must be submitted and approved before construction starts.
Compliance with NEMA and NEMWA is required.
CSD registration and a valid tax clearance certificate are required.
B-BBEE requirements apply under the preferencing scheme.
A registered safety officer and experienced KKS practitioners are required.
Description
Source: F240044 REV3 ENVIRONMENTAL EVALUATION LOW RISK ACTIVITY (5).xlsxEnvironmental evaluation of a low risk activity at Matimba Power Station, assessed against three criteria: a signed environmental policy statement (10 points), an Aspects and Impacts Register aligned to the scope of work (70 points) and a Method Statement demonstrating execution of the scope (20 points). A minimum weighted final score of 90% is required. Low risk activities are those with minimal environmental impact, such as once-off deliveries.
Submission Guidelines
Source: F240044 REV3 ENVIRONMENTAL EVALUATION LOW RISK ACTIVITY (5).xlsx (unknown)Documents required for the environmental evaluation of this low risk activity:
Each document is scored separately; a document that is not submitted scores zero for its criterion.
Evaluation Criteria
Source: F240044 REV3 ENVIRONMENTAL EVALUATION LOW RISK ACTIVITY (5).xlsx (unknown)Environmental evaluation of a low risk activity, scored out of 100 with a minimum qualifying score of 90%.
Scoring split:
Minimum qualifying score: 90% of the weighted total.
Technical Specifications
Source: F240044 REV3 ENVIRONMENTAL EVALUATION LOW RISK ACTIVITY (5).xlsx (unknown)Environmental evaluation of a low risk activity at Matimba Power Station.
Low risk activity defined as work with minimal environmental impact, such as once-off deliveries.
Deliverables assessed:
Compliance Requirements
Source: F240044 REV3 ENVIRONMENTAL EVALUATION LOW RISK ACTIVITY (5).xlsx (unknown)Environmental compliance and duty of care commitments must be covered by a signed policy statement.
Environmental aspects and impacts arising from the scope of work must be identified, assessed and mitigated through a submitted Aspects and Impacts Register.
A Method Statement demonstrating execution of the scope of work must be submitted.
Applicable evaluation template: Environmental Evaluation Low Risk Activity, document F/240/044, revision 3, effective 8 August 2024, review date 8 August 2027.
Description
Source: Annexure B (Acknowledgement of SHE requirements).docxThe document is the Annexure B acknowledgement form covering Eskom OHS legal and other requirements. It commits the bidder to comply with the listed OHS documents, ensures all employees undergo induction, and holds the main supplier accountable for managing its contractors and suppliers.
Evaluation Criteria
Source: Annexure B (Acknowledgement of SHE requirements).docx (unknown)Bidders must sign and submit Annexure B (Acknowledgement Form for Eskom OHS legal and other requirements) as part of the bid. The form must be signed by an authorised person (CEO, Director, or Managing Director) and witnessed by two witnesses. Signing confirms understanding of and commitment to comply with the Eskom and statutory OHS requirements listed. Penalties will be enforced on the main supplier for any non-conformance to these OHS requirements, whether by the supplier, its contractors, or its subcontractors.
Technical Specifications
Source: Annexure B (Acknowledgement of SHE requirements).docx (unknown)The work involves diesel generator fire protection for Matimba Power Station Units 2-6. This annexure specifies the OHS obligations bidders must acknowledge and comply with during contract execution. The supplier must ensure all employees undergo Eskom induction. The main supplier is accountable for managing its contractors and suppliers, including demonstrating selection criteria, notifying Eskom before appointing them, ensuring adequate resources and competencies, and monitoring OHS compliance through audits and assessments. Eskom may request testimonials or references from previous clients, including Eskom, for similar work.
Compliance Requirements
Source: Annexure B (Acknowledgement of SHE requirements).docx (unknown)Bidders must comply with the following documents when working at or rendering a service to Eskom: Eskom contractor Health and Safety requirements standard 32-136; the OHS specification/requirements provided with the tender; the Occupational Health and Safety Act 85 of 1993; and the Compensation for Occupational Diseases and Illnesses Act 130 of 1993. After contract award, the supplier must align its processes with Eskom's OHS policies, procedures, and standards. Penalties apply for non-conformance. Eskom may verify compliance and request reference details.
Description
Source: Tender Technical Evaluation Strategy - Unit 2 - 6 Diesel Generator Fire Protection System 20260622.pdfThe project covers the review of the approved design, installation, as-built drawings, and commissioning of an automatic fixed fire detection and protection system for Unit 2–6 diesel generators at Matimba Power Station. The system must connect to the existing fire water supply from the outside plant services building.
Submission Guidelines
Source: Tender Technical Evaluation Strategy - Unit 2 - 6 Diesel Generator Fire Protection System 20260622.pdf (unknown)Returnable documents:
Evaluation Criteria
Source: Tender Technical Evaluation Strategy - Unit 2 - 6 Diesel Generator Fire Protection System 20260622.pdf (unknown)Technical evaluation threshold:
Mandatory criteria (pass/fail):
Qualitative criteria (scored 0–5, no scores 1 or 3 allowed):
Unacceptable exception:
Technical Specifications
Source: Tender Technical Evaluation Strategy - Unit 2 - 6 Diesel Generator Fire Protection System 20260622.pdf (unknown)Scope of work:
Experience & Qualifications
Source: Tender Technical Evaluation Strategy - Unit 2 - 6 Diesel Generator Fire Protection System 20260622.pdfExperience and personnel qualification requirements:
Compliance Requirements
Source: Tender Technical Evaluation Strategy - Unit 2 - 6 Diesel Generator Fire Protection System 20260622.pdf (unknown)Important Dates
Source: U2-6.pdf (RFP)Closing date: 20 November 2026 at 10h00 (Eskom E-tendering site)
Compulsory clarification meeting: 5 November 2026 at 10h00 via Microsoft Teams (meeting link provided; attendance is mandatory, otherwise disqualification)
Tender validity period: 90 days from closing date
Clarification queries deadline: 5 working days before tender submission deadline
Contact Information
Source: U2-6.pdf (RFP)Eskom Representative:
Procurement Manager:
Submissions: Eskom E-tendering site (https://etendering.eskom.co.za)
Fraud hotline: 0800 11 2722 / [email protected]
Submission Guidelines
Source: U2-6.pdf (RFP)Electronic submission only via the Eskom E-tendering site (https://etendering.eskom.co.za).
Upload under folders: Technical, Commercial, Financial, and other.
All documents in PDF format; the price list in PDF and a copy in Excel. No zip/compressed files. No hard copies.
Upload size limit: 500 MB per document, 4 GB total. On resubmission, only the latest version is accepted; ensure the submission status shows as complete.
Mandatory returnables (disqualifying if omitted or unsigned):
Non-disqualifiable returnable: if submitted late or incomplete, the bidder has 5 working days from written request to correct; otherwise disqualified. CIDB grading proof has a separate prescribed period.
Late submissions are not accepted.
Evaluation Criteria
Source: U2-6.pdf (RFP)Evaluation stages: (1) Basic compliance, (2) Functionality (technical) scoring, (3) Price (80 points), (4) Specific Goals / B-BBEE (20 points), (5) Contractual requirements check before award.
Functionality: minimum weighted final score of 80% required. Criteria and weights:
Price: scored out of 80 points. Prices are evaluated inclusive of VAT, corrected for arithmetical errors, excluding contingencies, adjusted for variations, compared on Net Present Value. Unconditional discounts count; conditional discounts applied at payment.
Specific Goals (20 points) per PPPFA 80/20 system. If evidence for a claimed goal is not submitted, 0 points are awarded for that goal but the bid is not disqualified.
Ranking: Price score + Specific Goals score, highest total wins.
Objective criteria: only locally produced goods/services with minimum local content thresholds are considered. Material thresholds: Pipes 100%, Valves 70%, Cables 90%. SBD 6.2 and supporting annexures are returnable.
Eskom may award to a tenderer other than the highest scorer if justified by objective criteria.
Technical Specifications
Source: U2-6.pdf (RFP)Scope: Fire protection for Diesel Generators at Matimba Power Station, Units 2-6. Work includes replacement and/or design, installation, and commissioning of fire protection systems.
Mandatory technical criteria:
Qualitative technical criteria (for functionality scoring):
Methodology
Source: U2-6.pdfMethod statements are part of functionality scoring:
Environmental method statement: must demonstrate how the scope of work will be executed with full understanding of the project (20 points, environmental).
Experience & Qualifications
Source: U2-6.pdfContractor experience (fire protection): minimum 1-2 similar projects; 5+ for full marks. For each reference project, provide: title and scope description, start/end dates, signed completion certificate(s), client names and contact details.
Personnel:
Qualification requirements for key personnel are part of mandatory technical criteria (ECSA registration for all discipline engineers).
Quality Management
Source: U2-6.pdfQuality management is scored as a contractual requirement (Annexure B, Category 3). Sections:
A. QMS Manual/ISO 9001: documented QMS manual, quality policy approved by top management, quality objectives, control of documented information (ISO 9001:2015 clauses 7.5, 8.7, 10.2). Score 6.
B. Evidence of QMS in operation: organisation chart/responsibility matrix including quality function; documented information for control of externally provided processes, products, services (supplier evaluation, selection, performance monitoring, re-evaluation). Score 2.
C. Draft Contract Quality Plan (CQP) specific to scope, showing how consistency of design is ensured and how experienced resources are allocated. Score 1.
D. Quality Control Plan (QCP) / Inspection and Test Plan (ITP) as per scope; methodologies for installation to ensure compliance with designs and Employer's requirements. Score 1.
E. User-defined: Form A completed and signed; other customer-specific requirements. Score 1.
Total quality score: 11.
Minimum weighted final score for environmental requirements is 90% (see environmental section).
Pricing Schedule
Source: U2-6.pdfPricing must be submitted in PDF and Excel (BOQ/pricing schedule). Prices are scored out of 80 points under the 80/20 system. Evaluation: inclusive of VAT, corrected for arithmetic errors, excluding contingencies, adjusted for variations, NPV comparison. Unconditional discounts count; conditional discounts not for evaluation but applied at payment.
If cataloguing is required, include a line item for it; Eskom pays for cataloguing.
Financial Requirements
Source: U2-6.pdf (RFP)Pricing: quoted inclusive of VAT; bill of quantities/pricing schedule required, in PDF and Excel.
No bid security or performance bond mentioned.
Payment terms: Eskom pays within 30 days for contracts below R50 million (incl. VAT), and within 60 days for contracts above R50 million (incl. VAT), from receipt of undisputed invoices.
Cataloguing: if required, the pricing schedule must include a line item for cataloguing; Eskom pays for it.
CSDG: Contract Skills Development Goals apply (CIDB) for contracts of R5 million or more, or grade 7+; the recommended supplier must submit CSDG documentation after award.
Compliance Requirements
Source: U2-6.pdf (RFP)CSD registration: mandatory contractual requirement.
Tax compliance status: required (form included).
B-BBEE: proof of B-BBEE status level (SBD 6.1) is required for preference points; acceptable evidence is a B-BBEE certificate from an authorised body, a sworn affidavit per the Codes of Good Practice, or other prescribed requirement.
CIDB grading: 4SF or higher, mandatory technical criterion.
ECSA professional registration: for all discipline engineers.
Local content: minimum thresholds for Pipes (100%), Valves (70%), Cables (90%) - SBD 6.2 and annexures required.
SHEQ requirements (Annexure B): OHS acknowledgement, health and safety plan, detailed OHS costing (not lump sum), baseline risk assessment, valid COIDA letter of good standing, OHS policy signed by CEO, OHS competency CVs/certificates.
Environmental policy and aspects/impacts register.
Fraud and corruption: reportable to 0800 11 2722.
Health & Safety
Source: U2-6.pdfSHEQ requirements (Annexure B) include:
Contractual requirement: SHEQ requirements are contractual (not evaluation criteria) and must be met before award.
Environmental
Source: U2-6.pdfEnvironmental requirements (scored, minimum 90% threshold):
Total weight score: 100.
Contractual Terms
Source: U2-6.pdfContract conditions: NEC ECC contract. Tender validity 90 days.
Eligibility: bidders must not be on any international sanctions list, not on Tender Defaulters or National Treasury restriction lists, not Eskom-restricted, no conflict of interest, and not submit more than one tender. JV/consortium must have joint and several liability. Subcontracting 100% of the scope is disallowed.
Payment terms: 30 days for contracts below R50m (incl. VAT), 60 days above R50m.
Eskom may negotiate with preferred bidders if prices not market-related.
Subcontracting with subsidiary companies is discouraged; must be declared if used.
CSDG: applicable; recommended supplier submits Targeted Enterprise Declaration Affidavit, interim and completion reports.
B-BBEE proof: certificate, sworn affidavit, or other prescribed requirement.
Description
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdfMatimba Power Station has seven diesel generators used for backup power and black start operation; each unit has its own generator and there is one for the station. The scope is to provide a fully functional automatic fixed fire protection and detection system for the diesel generators at Units 2, 3, 4, 5 and 6 and their associated day tanks. The diesel generators are located on the 0m level, outside and on the southern side of the turbine building. Each day tank holds approximately 1,000 litres of diesel. The system must comply with NFPA and SANS standards, and be integrated with the existing fire protection and detection systems.
Important Dates
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdf (unknown)Closing: 20 November 2026 at 10:00 (local time, as per tender record). No briefing or site visit dates are stated in the document.
Contact Information
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdf (unknown)Document compiled by: Sizwe Buthelezi, Fire Protection System Engineer (contact details not stated).
Technical contact (as per document): Gift Nkuna, Auxiliary Engineering Manager (contact details not stated).
No SCM or procurement contact is listed in the document. Submission address not stated.
Submission Guidelines
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdf (unknown)Submission method: not stated in the document. The tender is an open request for bid from Eskom. Bidders should consult the full tender pack for the submission address, closing procedure and returnable forms. The technical specification requires the contractor to submit, for approval, quality control plans (QCPs), welding procedures, welder qualifications, NDT reports, coating inspection reports, material certificates, hydrostatic test certificates, and as-built drawings in hard copy and electronic format.
Evaluation Criteria
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdf (unknown)The document provides no evaluation criteria, scoring method, preference point system, or minimum qualifying score. Compliance with the referenced technical standards and quality requirements is mandatory for acceptance. The contractor must comply with the Occupational Health and Safety Act, 1993 (Act No. 85 of 1993), and adhere to ISO 9001 and ISO 14001.
Technical Specifications
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdf (unknown)Scope: design review, supply, installation, testing and commissioning of an automatic fixed fire protection and detection system for diesel generators and day tanks at Matimba Power Station, Units 2, 3, 4, 5 and 6.
Location: Diesel generators are on the 0m level, outside and on the southern side of the turbine building, at Units 2–6. Each diesel generator has an associated day tank of approximately 1,000 litres.
Designed system (per the specification):
Work includes:
Mechanical requirements:
Civil works:
C&I works:
Testing and commissioning:
Documentation deliverables (as-built design):
Training:
Quality Management
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdfThe contractor must have a quality system in place. All Quality Control Plans (QCPs) must be submitted to the employer for review and approval before any work starts. The contractor must provide welding procedures, welder qualifications, non-destructive testing reports, coating inspection reports, material certificates, and hydrostatic test certificates. Updated as-built drawings reflecting all modifications, valve locations and elevations must be submitted in both hard copy and electronic format. The work must comply with ISO 9001.
Pricing Schedule
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdfPricing format is not stated. The specification requires a complete bill of materials as part of the as-built documentation, but no pricing schedule, rates, or payment terms are provided.
Financial Requirements
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdf (unknown)No financial requirements are stated in the document. No bid security, bonds, guarantees, retention, payment terms, or turnover thresholds are mentioned.
Compliance Requirements
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdf (unknown)Compliance with the following is mandatory:
Health & Safety
Source: Matimba Power Station - Unit 2-6 Diesel Generator Fixed Fire Protection Technical Specification (003).pdfThe contractor must comply with the Occupational Health and Safety Act, 1993 (Act No. 85 of 1993). The specification also references the Eskom Manual for fire protection of coal-fired power stations (N.PMZ 45-392). No specific safety plans or HSE site requirements are detailed in the document.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
Nelson Mandela Drive. - Lephalale - Lephalale - 0555
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
14
Last checked
29 Oct 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Learn how to submit a winning bid with these related articles
Win consulting, legal, accounting, and engineering service contracts with government. Learn registration requirements and proposal strategies.
Comprehensive guide to Institute of IT Professionals South Africa membership. Certification levels, requirements for ICT professionals, and how IITPSA membership enhances credibility for SITA and government IT tenders.
A strategic guide to getting listed on government consultancy, legal, and engineering panels. Learn why panels are the gateway to steady public sector work.
Master the art of the consulting bid. How to structure your methodology, price your services competitively, and score maximum evaluation points.