ESKOM seeks a contractor to design, supply, install and commission replacement drive systems for the submerged scraper conveyor (ssc) at matimba power station in limpopo, over a 38-month period. The project involves replacing the existing ssc drives, which have reached end-of-life and fail without notice grate risk to plant operation. The works include drive design and supply, installation, safety and environmental provisions, and testing and commissioning. Bidders must provide qualified personnel in mechanical, electrical and c&i engineering as specified, and will be evaluated on mandatory criteria (ecsa registration) and qualitative criteria covering company experience, key personnel experience and the proposed solution.
Valid ECSA registration for all mechanical, electrical and C&I discipline engineers performing design work (mandatory).
Provide a drive solution including CAD 3D model, bill of materials, and technical specification.
Key personnel: Mechanical registered engineer or technologist (ECSA) - 2–3 years design experience gets 2 points; 4–6 years gets 4 points; 5+ years gets 5 points.
Site Manager: 2–3 years relevant experience gets 2 points; 4–5 years gets 4 points; 6+ years gets 5 points.
Mechanical Fitter: 2–4 years gets 2 points; 4–6 years gets 4 points; 7+ years gets 5 points.
Quality Control Inspector: 2–3 years gets 2 points; 4–5 years gets 4 points; 6+ years gets 5 points.
C&I Engineer/Technologist: ECSA registered with 1–2 years project experience gets 2 points; 3–4 years gets 4 points; 5+ years gets 5 points.
Qualitative criteria weightings apply to the above and to the completeness of the drive solution.
Contract duration: 38 months at Matimba Power Station, Limpopo.
Closing date: 15 September 2026 at 10:00.
Continue with tenders sharing this issuer, category, or province.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Tuesday, 15 September 2026 - 10:00
Venue
Matimba Power Station Lapa Auditorium
Important: Attendance at this briefing session is mandatory. Bids from suppliers who do not attend may be disqualified.
Categories
Request for Bid(Open-Tender)
Generation Division - Lephalale - Lephalale - 0555
Tenders in this industry often require registration with these bodies.
Construction Industry Development Board (CIDB) registration is mandatory for almost all public sector construction tenders. Ensure your grading matches the tender value.
Recommended Certifications
Having these can improve your winning chances: NHBRC Registration, ISO 9001:2015 (Quality Management), ISO 14001:2015 (Environmental Management), ISO 45001:2018 (Occupational Health & Safety), SACPCMP Registration, ECSA Registration
AI Document Analysis Stages
Review in progress
The information shown on this card is preliminary. Our procurement team is currently finalising the submission guidelines, evaluation criteria, technical specifications, financial requirements, and compliance sections so you have a clean, bid-ready summary to work from. Documents being finalised: 240-12248652_List of Tender Returnables_Cat 1_ Rev 7.docx, SUPPLI~1.DOC. You don’t need to refresh — this page will pick up the updated review automatically.
24 Aug
2026
Tender Published
Tender was published
15 Sept
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
SUPPLI~1.DOC
240-12248652 (Rev 7)_List of Tender Returnables-EDC Formatted LTN 03.02.2022.pdf
ESKOM is procuring a 38-month SSC Drive Replacement Project at Matimba Power Station in Limpopo. The tender requires bidders to demonstrate a certified ISO 9001 quality management system and provide a contract quality plan, quality control plan, and related quality documentation.
NEC for SSC Drive Gearbox Replacement Contract .doc
The tender is for the SSC Drive Replacement Project at Matimba Power Station, which includes the removal and replacement of the SSC drives on all six units with new hydraulic drive systems. The project is expected to take 38 months to complete.
E-tendering Help Manual for supplier - 27 January 2025.docx
ESKOM is procuring a 38-month SSC Drive Replacement Project at Matimba Power Station in Limpopo. The tender is managed through the eTendering system, which replaces physical document submission.
240-109253698 Template for a Typical Contract Quality Plan.docx
A Contract Quality Plan (CQP) template aligned to SANS 466/ISO 10005 is required for the SSC Drive Replacement Project at Matimba Power Station, to be executed over 38 months. The template is a mandatory document that the successful supplier must complete to demonstrate how quality requirements for the contract will be met, covering scope, processes, controls, documentation and records.
240-68~1.PDF
Eskom is procuring an SSC Drive Replacement Project at Matimba Power Station in Limpopo, with a contract duration of 38 months. The tender requires bidders to comply with Eskom's quality requirements, including ISO 9001 standards, and to complete a pre-contract award quality assessment.
Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf
Eskom is procuring a contractor for the SSC Drive Replacement Project at Matimba Power Station in Limpopo, with a contract duration of 38 months. The tender includes specific goals for B-BBEE preference points, mandatory subcontracting for contracts above R30 million, and SDL&I obligations covering transformation, local procurement, jobs, and skills development.
Scope of work.pdf
Analysis completed but response format was invalid
E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.docx
ESKOM is procuring a 38-month SSC Drive Replacement Project at Matimba Power Station in Limpopo. The tender requires bidders to complete e-tendering training and submit an acknowledgement form to be considered responsive.
ITT for SSC Drive replacement for a period of 38 months.pdf
Eskom is procuring a contractor to replace the SSC drives at Matimba Power Station in Limpopo over a 38-month period. The contract will be governed by the NEC conditions and requires a CIDB grading of 7ME or higher, with mandatory subcontracting of at least 30% of the contract value to designated groups.
240-12248652_List of Tender Returnables_Cat 1_ Rev 7.docx
Eskom is procuring a contractor for the SSC Drive Replacement Project at Matimba Power Station in Limpopo, with a contract period of 38 months. The scope focuses on quality management requirements, including ISO 9001 certification, operational quality management systems, and project-specific quality and control plans.
Tender Technical Evaluation Strategy - SSC Drives Gearbox Replacement 20260629.pdf
ESKOM is procuring a contractor to design and install replacement gearboxes for the Submerged Scraper Conveyor (SSC) drives at Matimba Power Station, Limpopo, over a 38-month period. The existing PIV gearboxes have high failure rates, long lead times, and are at end of life. The tender includes mandatory and qualitative technical evaluation criteria, with a minimum weighted technical score of 70%.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubLearn how to submit a winning bid with these related articles
Median Estimate
R 37 794 947
Range
Based on 12 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Description
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.docx (unknown)Business name/JV is required.
Submission Guidelines
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.docx (unknown)Returnable Documents: E-Tenderers' E-Tendering Training Acknowledgement Form must be fully completed and submitted to Eskom within the prescribed period. Failure to do so will disqualify the tenderer.
Evaluation Criteria
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.docx (unknown)Submission of the fully completed E-Tenderers' E-Tendering Training Acknowledgement Form is mandatory.
Technical Specifications
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.docx (unknown)Business name/JV is required.
Compliance Requirements
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.docx (unknown)No specific requirements found
Evaluation Criteria
Source: 240-12248652 (Rev 7)_List of Tender Returnables-EDC Formatted LTN 03.02.2022.pdf (TENDER)The tender is evaluated on Category 1: Quality Requirements Deliverables, with each requirement scored 1 point. Section A (Quality Management System Requirements, ISO 9001 certificate) scores 4 points: A.1 Product/Service Scoping on ISO 9001 certificate defined and relevant; A.2 Certificate by Approved and Authorized certification authority; A.3 Certification Authority has Recognized International Accreditation; A.4 Validity (expiry date) of certificate. Section B (Evidence of QMS in operation, Ref 240-105658000) scores 5 points: B.1 Documented information for defined roles, responsibilities and authorities (organization chart and responsibility matrix including quality management function/role, Clause 5.3 ISO 9001:2015); B.2 Documented information for Control of Externally Provided Processes, Products and Services (criteria for evaluation, selection, monitoring performance, re-evaluation of external providers, Clause 8.4 ISO 9001:2015); B.3 Latest copy of an internal management system audit report (with Nonconformity, Correction and/or Corrective Action Reports, including Objective, Scope, Criteria and outcomes, Clause 9.2 ISO 9001:2015); B.4 Latest copy of an internal management system audit report not older than 12 months (with Nonconformity, Correction and/or Corrective Action Reports); B.5 Records of Management Review meetings (minutes, attendance etc.). Section C (Draft Contract Quality Plan specific to the scope of works, Ref ISO 10005) scores 1. Section D (Quality Control Plan / Checklist / ITP as per Scope of Works, Ref ISO 10005) scores 1. Section E (Draft/Example of Inspection and Test Plan or Quality Control Plan for similar work) scores 1.
Technical Specifications
Source: 240-12248652 (Rev 7)_List of Tender Returnables-EDC Formatted LTN 03.02.2022.pdf (TENDER)The tender is for a project (reference E - not specified in document) requiring a Supplier Quality Management system. Bidders must submit documented information as defined in ISO 9001:2015, including an organization chart and responsibility matrix covering the quality management function, and control of externally provided processes, products and services (Clause 8.4). Bidders must provide latest internal management system audit report (Clause 9.2) and records of management review meetings. A Draft Contract Quality Plan is required per ISO 10005. Also required: latest copy of internal management system audit report (with Nonconformity, Correction and/or Corrective Action Reports) including Objective, Scope, Criteria and outcomes. A Quality Control Plan / Inspection and Test Plan (ITP) as per Scope of Works is required.
Quality Management
Source: 240-12248652 (Rev 7)_List of Tender Returnables-EDC Formatted LTN 03.02.2022.pdf (TENDER)Quality Management System (QMS) requirements per ISO 9001:2015:
Section
Source: 240-12248652 (Rev 7)_List of Tender Returnables-EDC Formatted LTN 03.02.2022.pdf (TENDER)Section A Score Option 1 4
SECTION B : Evidence of QMS in operation (Tender Quality Requirements -Ref 240-105658000)
not limited to quality management function/role) 1
B.2 Documented information for Control of Externally Provided Processes, Products and Services - Must include criteria for evaluation, selection,
monitoring of performance, and re-evaluation of external providers (Clause 8.4 of ISO 9001:2015)
Section B Score 5
SECTION C: Contract Quality Plan Requirements (Ref 240-105658000 and 240-109253698).
Draft Contract Quality Plan specific to the scope of work as described in the tender documents (Ref ISO 10005)
NB! Draft Contract/Project Quality Plan has important QA deliverables 1
Section C Score 1
SECTION D: Quality Control Plan Requirements (Ref 240-105658000 or 240-109253302)
QCP /Checklist/ ITP (Quality Control Plans) as per Scope of Works (Ref ISO 10005)
NB! Draft/ Example of an Inspection and Test Plan (ITP) or Quality Control Plan (QCP) on similar and/ or previous work done 1
Section D Score 1
Section E Score 1
Supplier Quality Management: Revision 7
Category 1 : Quality Requirements Deliverables to be evaluated indicator = 1
SECTION A : Quality Management System Requirements ISO 9001
Valid certification of Quality Management System by an ISO accredited body
QCP /Checklist/ ITP (Quality Control Plans) as per Scope of Works (Ref IS
Evaluation Criteria
Source: 240-12248652_List of Tender Returnables_Cat 1_ Rev 7.docx (unknown)Quality requirements are evaluated in five sections, each with a deliverable indicator of 1 (pass/fail per item).
Total quality score is 12 points; bidders must score on all deliverables to pass the quality evaluation.
Technical Specifications
Source: 240-12248652_List of Tender Returnables_Cat 1_ Rev 7.docx (unknown)The project is the replacement of SSC (static starter/soft starter?) drives at Matimba Power Station, with a contract period of 38 months. The scope includes ensuring consistency of design and philosophies across all units during implementation, and managing installation practices to comply with detailed designs and the Employer's requirements. A Contract Quality Plan and Quality Control Plan are required as part of the quality deliverables.
Compliance Requirements
Source: 240-12248652_List of Tender Returnables_Cat 1_ Rev 7.docx (unknown)Bidders must hold a valid ISO 9001 Quality Management System certificate issued by an accredited certification body, with the certificate's scope covering the relevant product/service and the certification authority having recognised international accreditation. The certificate must be current (not expired). Bidders must also complete and sign Form A as a returnable requirement.
Description
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)SSC Drive Replacement Project at Matimba Power Station for a period of 38 months. Tender number E3401GXMPMAT. Eskom Holdings SOC Ltd invites tenders for this project.
Important Dates
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP){"closingDate":"07 April 2026","closingTime":"10h00","briefingSession":"{"date":"02 September 2026","time":"10H00","venue":"ion A compulsory clarification meeting/site visit with representatives","is_compulsory":true}"}
Briefing Session
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)A compulsory clarification meeting/site visit will take place on 02 September 2026 at 10H00 at Matimba Power Station Lapa Auditorium. Tenderers must confirm their intention to attend with the Eskom Representative. Tenderers that do not attend this mandatory meeting will be disqualified.
Contact Information
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP){"name":null,"email":"[email protected]","phone":"011 800 3720","department":null,"address":"r which"}
Returnable Documents
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)Mandatory returnables at tender closing include: Authorisation Form (Annexure A), Acknowledgement Form (Annexure B), Tenderer's Particulars (Annexure C), Integrity Pact Declaration (Annexure D), CPA for local goods/services (Annexure E), CPA(IG) for imported goods/services (Annexure F), SBD 6.2 Declaration Certificate for Local Production and Content (Annexures G1-G4), SBD 1 (Annexure H), SBD 6.1 Preference Points Claim Form (Annexure I), SBD 4 Bidders Disclosure (Annexure J), Tax Evaluation questionnaire, and E-tendering Help Manual acknowledgement. Additional documents required include JV agreements, tax clearance certificates, proof of compliance with Employment Equity Act, CIDB grading proof, NEC or other Contract, and pricing schedule.
Evaluation Criteria
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)Bidders must meet the eligibility criteria in the Tender Data, including not being under any restriction to do business with Eskom or State-Owned Companies, not having a conflict of interest, and not being on the Tender Defaulters list or restricted by National Treasury. Bidders must not submit more than one tender (except as part of a JV with joint and several liability) and must not subcontract 100% of the scope. Mandatory returnables at closing (disqualifiable) include Annexure A (Authorisation Form), Annexure B (Acknowledgement Form), Annexure C (Tenderer's Particulars), Annexure D (Integrity Pact Declaration), Annexure E (CPA for local goods/services), Annexure F (CPA for foreign goods/services if applicable), Annexure G1-G4 (SBD 6.2 and local content declarations), Annexure H (SBD 1), Annexure I (SBD 6.1 Preference Points Claim), Annexure J (SBD 4 Bidders Disclosure), and the E-tendering Help Manual acknowledgement. Bidders must be registered on CSD (CSD number/report) prior to award. Tax clearance certificate required if not on CSD or no SARS pin. CIDB grading proof required at closing. Bidders must attend the compulsory clarification meeting. Local content threshold for switching devices is 5%. Mandatory subcontracting of 30% to designated groups is a condition of award.
Technical Specifications
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)d. Method statement
Document must demonstrate understanding of the project
as a whole, and methodology ow the activity will be
executed/conducted to minimize or prevent pollution to the
environment.
The supplier shall prepare a method statement for the works, entailing all process to be undertaken,
identifying environmental aspects and impacts related to the tasks and their mitigation measures.
e. Waste Management
The supplier shall prepare a document /process flow/strategy for management of waste to emanate from
the work activities, e.g., scrap metal/cut-off rebar’s and wield rods.
The supplier shall adopt and implement a zero liquid effluent discharge (ZLED) policy throughout their
processes.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 62
File name: Invitation to Tender (ITT) for SSC Drive Replacement Project
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
f. Emergency preparedness and response plan
The supplier shall provide an environmental incidents management process/procedure for the project.
g. Hazardous and chemical substances plan
The Hazardous Chemical substance handling and spill management procedure must also be submitted.
Quality Requirements
Category 1: Quality Requirements Deliverables to be evaluated indicator = 1
Apply =1
SECTION A: Quality Management System A.1 Product / Service Scoping on ISO 9001 1
Requirements ISO 9001 certificate is defined and relevant
A.2 Certificate by Approved and Authorized 1
Valid certification of Quality Management certification authority
System by an ISO accredited body A.3 Certification Authority has Recognized 1
International Accreditation
A.4 Validity (expiry date) of certificate 1
Section A Score 4
SECTION B: Evidence of QMS in B.1 Documented information for defined roles,
operation (Tender Quality Requirements responsibilities and authorities - Organization
chart and Responsibility matrix 1
(Ref 240-105658000)
(Clause 5.3 of ISO 9001:2015)
B.2 Documented information for Control of
Externally Provided Processes, Products and
Services - Must include criteria for evaluation,
selection, monitoring of performance, and re- 1
evaluation of external providers
(Clause 8.4 of ISO 9001:2015)
B.3 Latest copy of an internal management
system audit report (with Nonconformity,
Correction and/ or Corrective Action Reports) -
Report must include but not limited to 1
Objective, Scope, Criteria and outcomes of the
audit.
(Clause 9.2 of ISO 9001:2015)
B.4 Latest copy of a certification management
system audit report not older than 12 months
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 62
File name: Invitation to Tender (ITT) for SSC Drive Replacement Project
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
(with Nonconformity, Correction and/ or
Corrective Action Reports)
B.5 Records of Management Review meetings
(minutes, attendance registers e.t.c)
Section B Score 5
SECTION C: Contract Quality Plan (CQP) NB! Draft Contract/Project Quality Plan has 1
Requirements (Ref 240-105658000 and important QA deliverables
240-109253698).
A provisional Contract Quality Plan (CQP) for
Draft Contract Quality Plan specific to the the project. The CQP provide a comprehensive
scope of work as described in the tender strategy to demonstrate how consistency of
documents (Ref ISO 10005) design and philosophies across all the units
during the overall project implementation will be
ensured. Clearly identify roles, responsibilities
and expectations throughout the project and the
tenderer to demonstrate correct allocation of
experienced resources throughout the project
period.
Section C Score 1
SECTION D: Quality Control Plan NB! Draft/ Example of an Inspection and Test 1
Requirements (Ref 240-105658000 or 240- Plan (ITP) or Quality Control Plan (QCP) on
QCP /Checklist/ ITP (Quality Control Plans)
as per Scope of Works (Ref ISO 10005) A provisional QCP for the project. The QCP
provide a comprehensive Quality control
process, to ensure world-class engineering
practice will be achieved during the
implementation of the project, by others to be
overseen by the tenderer as well as any
subcontractors forming part of the project.
Methodologies must be provided to
demonstrate how installation practices will be
managed and carried out to ensure compliance
to the details designs and the Employer’s
requirements.
Section D Score 1
SECTION E: User defined additional E.1 Form A is completed and signed. 1
Requirements & miscellaneous (Ref 240-
Section E Score 1
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 62
File name: Invitation to Tender (ITT) for SSC Drive Replacement Project
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
3.24 Sign form of Agreement/ The conditions of the contract will be the NEC
Contractual Conditions
2.28 CIDB Requirements (where CIDB Requirements are applicable
applicable for Engineering and
Construction Works Contracts) 1. It is estimated that tenderers must have a Construction
Industry Development Board (CIDB) contractor grading of
7ME or high
Or;
Joint ventures are eligible to submit tenders provided that: -
the CIBD.
the ...6ME...... or higher *class of construction work; or
not lower than one level below the required grading
designation in the class of works construction works under
consideration and possesses the required recognition
status;
accordance with the CIBD regulations is equal to or higher
than a contractor grading designation determined in
accordance with the sum tendered for a or ............*
class of construction work or a value determined in
accordance with Regulations 25 (1B) or 25 (7A) of the
CIBD Regulations.
2.29 Contract Skills Development
Goals (CSDG) is not
applicable
2.30 Contract Participation Goals is
not applicable
Please note:
Tenderers are requested to bear in mind Eskom's standard payment terms as stipulated hereunder when
submitting tenders and concluding contracts with Eskom:
For contracts valued below R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed to paying
Suppliers within 30 days of receipt of undisputed invoices.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 62
File name: Invitation to Tender (ITT) for SSC Drive Replacement Project
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
For contracts valued above R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed to paying
suppliers within 60 days of receipt of undisputed invoices.
Eskom reserves the right to negotiate with preferred bidders after a competitive bidding process or price
quotations should the tendered prices not be market-related.
Main contractors/ suppliers are discouraged from subcontracting with their subsidiary companies as this
may be interpreted as subcontracting with themselves and / or using their subsidiaries for fronting.
Where a main contractor subcontracts with a subsidiary, this must be declared in its tender documents.
A report containing a list of potential sub-contractors may be drawn by accessing the following link:
“proof of B-BBEE status level of contributor” means-
(a) the B-BBEE status level certificate issued by an authorised body or person; or
(b) a sworn affidavit as prescribed by the B-BBEE Codes of Good Practice; or
(c) any other requirement prescribed in terms of the Broad-Based Black Economic Empowerment Act
1.3 Tender returnables
The tenderer must submit the returnable set out hereunder as part of its tender at the stipulated deadline.
Note the following: -
These returnables are required to be completed, signed (if required on the returnable) and submitted with
the tender at Tender closing date and time. If not completed, signed (if required on the returnable) and/or
submitted by tender closing, the tenderer will be disqualified.
** Returnable required at Tender closing (non-disqualifiable): -
These returnables are required to be completed, signed (if required on the returnable) and submitted with
Tender at Tender closing date and time; however, if not submitted by Tender closing, or submitted with
incomplete information or without a required signature, the Procurement Practitioner will, in writing,
request the tenderer to submit the returnable within 5 working days. If the returnable is not completed,
signed if required and/or received by the Procurement Practitioner within 5 working days of the request,
the tenderer will be disqualified.
The 5 working days period does not apply to CIDB proof of grading. Refer to the returnable table the
prescribed period for CIDB proof of grading.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 62
File name: Invitation to Tender (ITT) for SSC Drive Replacement Project
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
These returnables are required to be submitted at tender closing date and time. These returnables will
not be requested by the Procurement Practitioner. A tenderer that does not submit the required returnable
at stipulated deadline or submits an incomplete returnable; will not be disqualified but will score zero.
Returnable required prior to Contract Award.
Returnables that are mandatory for contract award must be submitted prior to award, completed if
completion is a requirement and signed if signature is a requirement.
Reference Returnable From Suppliers at at **
closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable)
to Tender Returnable Returnable Returnable
Basic Compliance Electronic copy of the tender in a PDF format. The √
price list needs to be submitted in PDF and a copy in
excel format (The upload size per document is 500
megabytes and total submission is restricted to 4
gigabytes)
Annexure A Authorisation Form √
Annexure B Acknowledgement Form √
Annexure C Tenderers Particulars √
Annexure D Integrity Pact Declaration form √
Annexure E CPA for local goods/services (if applicable) √
Annexure F CPA(IG) for imported goods/services (if applicable) √
Annexure G1-G4 SBD 6.2 -Declaration certificate for local production √
and content and Annexures G2,G3,G4 [only
applicable where designated materials are
included]
Annexure H SBD 1- to be completed and submitted by all √
(applicable for all tenderers.
suppliers including
Foreign suppliers)
PPPFA 2022 regulations
Annexure J SBD 4 – Bidders Disclosure √
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 62
File name: Invitation to Tender (ITT) for SSC Drive Replacement Project
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Reference Returnable From Suppliers at at **
closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable)
to Tender Returnable Returnable Returnable
Reverse e-auction
training
acknowledgement
form (if applicable)
E-tendering Help √
Manual
acknowledgement
form (If applicable)
Additional Letter of intent to form a JV/consortium or Valid joint √
Documents required venture agreement confirming the rights and
in the event of JV: - obligations of each of the joint venture partners and
their profit-sharing ratios.
Separate written confirmation that the joint venture will √
operate as a single business entity (incorporated) for
the duration of the contract or this may be included as
an obligation within the JV agreement.
Details and confirmation of a single designated bank √
account in the name of the JV and independent of the
individual JV partners, as set out in the joint venture
agreement.
specific goals will not result in its disqualification.
The tenderer will, however, be scored zero for
Specific Goals for purposes of PPPFA scoring and
ranking.
Tax Clearance A certified copy of a tax clearance certificate is √
Certificates required from foreign tenderers (with a footprint in
South Africa but that are not registered on CSD and
have not provided a SARS pin number) and local
tenderers (that have not provided their SARS e-filing
PIN number for verification by Eskom and/or their
CSD profile / CSD number).
Foreign suppliers with no footprint in South Africa must
complete the SBD1 document; however, no proof of
tax compliance is required.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 62
File name: Invitation to Tender (ITT) for SSC Drive Replacement Project
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Reference Returnable From Suppliers at at **
closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable)
to Tender Returnable Returnable Returnable
Tax Evaluation Evaluation questionnaire to determine whether a √
Questionnaire (if company, close corporation (CC) or Trust is a personal
services contract service provider for purposes of PAYE
and was included as
annexure)
Compliance with To the extent that the tenderer falls within the definition √
Employment Equity of a “designated Employer” as contemplated in the
Act Employment Equity Act , the tenderer is
required to furnish the Employer with proof of
compliance with the Employment Equity Act, including
proof of submission of the Employment Equity report
to the Department of Labour. (South African tenderers
only)
CIDB (where Valid proof of the required CIDB grading designation √
applicable) for the main contractor; JV and /or sub-contractor as
may be required in the tender data at tender closing
deadline
NEC or other NEC or other Contract, completed. √
Contract
Pricing schedule Completed pricing schedule (if not already submitted √
in the NEC or other Contract).
For e-tendering price schedule needs to be submitted
in PDF (The Cross Functional Team
Mandatory contractual requirements
SUPPORTING EVIDENCE [applicable to all
tenders]
Mandatory CSD Registration (CSD number/CSD Report) √
Contractual
Methodology
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)The supplier shall prepare a method statement for the works, entailing all processes to be undertaken, identifying environmental aspects and impacts related to the tasks and their mitigation measures.
Quality Management
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)Quality requirements include: ISO 9001 certificate by an accredited body, documented information for roles and responsibilities, control of externally provided processes, internal management system audit report, certification audit report not older than 12 months, records of management review meetings, a provisional Contract Quality Plan (CQP), a draft Inspection and Test Plan (ITP) or Quality Control Plan (QCP), and completed Form A.
Pricing Schedule
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)Effective Date 07 April 2026
Review Date April 2031
Number Description Annexure Attached (Y /
N / n/a)
1.1.12 Reverse e-auction training acknowledgement form (if N/A
applicable)
1.1.13 Reverse e-auction process (if applicable) N/A
1.1.14 E-tendering Help Manual acknowledgement form Attached
1.1.15 E-tendering Help Manual for supplier Attached
1.1.16 CIDB Contract Skills Development Goals (CSDG) N/A
1.1.17 Contract Participation Goals (CPG) N/A
(if applicable)
1.1.18 Scope of Work Y
1.1.19 NEC or other Contract Y
1.1.20 Pricing Schedule/BOQ (if not contained in Contract) NEC attached Y
meeting is mandatory/compulsory, then tenderers must attend
such meeting. Tenderers that do not attend such
mandatory/compulsory meeting will be disqualified and will not
be evaluated.
2.16 Seeking clarification The tenderer will notify Eskom of any clarifications required before the
closing time for clarification queries, which is [7] working days before
the deadline for tender submission.
2.22 Alternative tenders Alternative tenders are not allowed.
2.33 Cataloguing The successful tenderer may be required to provide the cataloguing
information per item after contract award and will need to ensure that
all materials delivered to Eskom are labelled in line with Eskom’s
labelling specifications as may be stipulated by Eskom. Where
cataloguing is a requirement, the Pricing Schedule must also include
a line item for cataloguing, which tenderers are required to quote for.
Goal, it will not be disqualified. However, it will be awarded 0 points
for that Specific Goal.
3.19 Ranking of tenders Tenderers will be ranked by applying the preferential point scoring for
the 80/20 system. Eskom will add the score from Pricing and Specific
Pricing schedule Completed pricing schedule (if not already submitted √
in the NEC or other Contract).
Compliance Requirements
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)ADDITIONAL CONTRACTUAL REQUIREMENTS SUPPORTING EVIDENCE Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 62 File name: Invitation to Tender (ITT) for SSC Drive Replacement Project Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Identifier Invitation to Tender Effective Date 07 April 2026 Review Date April 2031 Reference Returnable From Suppliers at at ** closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable) to Tender Returnable Returnable Returnable Safety COIDA - Original certificate of good standing or proof √ of application issued by the Compensation Fund (COID) or a licensed compensation insurer (South African tenderers only) Quality Attached √ Other safety/quality Attached √ documents as required per scope of works Environmental Attached √ Due
A signed copy of the public interest score (only applicable to South African entities that are not audited) o Giving the actual score o Indicating whether the company is owner managed or not o Confirming whether the annual financial statements were externally prepared or not. Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 62 File name: Invitation to Tender (ITT) for SSC Drive Replacement Project Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Identifier Invitation to Tender Effective Date 07 April 2026 Review Date April 2031 Reference Returnable From Suppliers at at ** closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable) to Tender Returnable Returnable Returnable
Copies of the ITA34C for the current & previous years of assessment (only applicable to South African entities that are not audited)
For unincorporated JV or a SPV, each partner in the JV or a SPV must submit its annual financial statements including all items listed above. DOCUMENTS REQUIRED UNDER FUNCTIONALITY/TECHINICAL CRITERIA Functionality/Technical Technical Evaluation Criteria attached √ [required for evaluation /scoring] Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 62 File name: Invitation to Tender (ITT) for SSC Drive Replacement Project Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Identifier Invitation to Tender Effective Date 07 April 2026 Review Date April 2031 ANNEXURE A AUTHORISATION FORM Indicate the status of the tenderer by ticking the appropriate box below. A B C D E F COMPANY CLOSE PARTNERSHIP JOINT SOLE TRUST CORPORATION VENTURE PROPRIETOR The tenderer must complete the appropriate certificate set out below for its category of organisation. If the tenderer is a company, close corporation, joint venture, or trust the tenderer must attach a certified copy the document that is proof of the contents of the certificate (resolution of the board of directors of a company, members’ resolution of a close corporation, power of attorney in the case of a joint venture, or resolution of the board of trustees of a trust). Note further that, in addition to completing the relevant certificate for category of organisation, the authorised representative of the tenderer is also required to complete and sign the table at the end of this Authorisation Form.
Certificate for company I,_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ , in my capacity as _ _ _ _ _ _ _ _ _ _ _ of the board of directors of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, hereby confirm that by resolution of the board taken on _ _ _ __ _ _ _ _ (date), Mr/Ms _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ , acting in his/her capacity of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, is authorised to submit this tender on behalf of the company, and to sign all documents in connection with this tender and any contract that may result from it on behalf of the company. A certified copy of the resolution of the board is annexed to this Form. Signed: Date: Name: Position: Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 62 File name: Invitation to Tender (ITT) for SSC Drive Replacement Project Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Identifier Invitation to Tender Effective Date 07 April 2026 Review Date April 2031
Certificate for close corporation I,_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ , in my capacity as member of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, hereby confirm that by majority vote of the members taken on _ _ _ __ _ _ _ _ (date), Mr/Ms _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ , acting in his/her capacity of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, is authorised to submit this tender on behalf of the close corporation, and to sign all documents in connection with this tender and any contract that may result from it on behalf of the close corporation. A certified copy of the members’ resolution is annexed to this Form. Signed: Date: Name: Position
Certificate for partnership We, the undersigned, being the key partners in the business trading as _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ hereby authorise Mr/Ms _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, acting in his/her capacity of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, to submit this tender on behalf of the partnership, and to sign all documents in connection with the tender and any contract that may result from it on behalf of the partnership. Name Address Signature Date NOTE: This certificate is required to be completed and signed by the full number of Partners necessary to commit the Partnership. Attach additional pages if more space is required. Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 62 File name: Invitation to Tender (ITT) for SSC Drive Replacement Project Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Identifier Invitation to Tender Effective Date 07 April 2026 Review Date April 2031
Certificate for Joint Venture We, the undersigned, are submitting this tender offer in Joint Venture and hereby authorise Mr/Ms _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, an authorised signatory of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ , being the lead member in the Joint Venture, to sign all documents in connection with the tender and any contract that may result from it on behalf of all the members in the Joint Venture. This authorisation is evidenced by the attached power of attorney signed by the legally authorised signatories of all the members in the Joint Venture. We attach to this Form a certified copy of the Joint Venture Agreement which incorporates a statement that all members in the Joint Venture are liable jointly and severally for the execution of the contract, a term that indicates which member will be the lead member, and terms that indicate the ratios according to which work and payment will be divided amongst the members. Name of JV member Address Authorised signature, name and capacity Lead member Member Member Member NOTE: This certificate is required to be completed and signed by all members of the joint venture. Attach additional pages if more space is required.
Certificate for sole proprietor I, _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, hereby confirm that I am the sole proprietor of the business trading as _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ Signed: Date: Name: Position:(Sole Proprietor) Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 62 File name: Invitation to Tender (ITT) for SSC Drive Replacement Project Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Identifier Invitation to Tender Effective Date 07 April 2026 Review Date April 2031
Certificate for trust I,_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ , in my capacity as _ _ _ _ _ _ _ _ _ _ _ of the board of trustees of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, hereby confirm that by resolution of the board of trustees taken on _ _ _ __ _ _ _ _ (date), Mr/Ms _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ , acting in his/her capacity of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, is authorised to submit this tender on behalf of the trust and to sign all documents in connection with this tender and any contract that may result from it on behalf of the trust. A certified copy of the resolution of the board of trustees is annexed to this Form. Signed: Date: Name: Position: NOTE: The table below must also be fully completed by all tenderers in addition to the certificate that was selected and completed above. Name of tenderer: Full names of authorised signatory: Designation and capacity: Signature of authorised signatory Date of signature: Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 62 File name: Invitation to Tender (ITT) for SSC Drive Replacement Project Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Identifier Invitation to Tender Effective Date 07 April 2026 Review Date April 2031 ANNEXURE B ACKNOWLEDGEMENT FORM We are in receipt of the Invitation to Tender/Proposal from Eskom Holdings SOC Ltd and the following addenda issued by Eskom: We confirm that the documentation received by us is: (Indicate by ticking the box) Correct as stated in the Invitation to Tender / RFP Content List, and that each document is complete. Or: Incorrect or incomplete for the following reasons: Cataloguing Acknowledgement: Please select the relevant statement by ticking the appropriate box below
We agree to provide the cataloguing information as described in the Invitation to Tender
We have already supplied Eskom with the cataloguing information pertaining to this Invitation to Tender in a previous contract/order [insert previous contract/order number] __________
We do not intend to provide the required cataloguing information for the reasons stated hereunder:
We are a Distributor/Importer/Agent and our Principal, being the Original Equipment Manufacturer (OEM), is or is not [delete whichever is not applicable] in the position to supply cataloguing information for items. We attach the letter from the OEM confirming its position. Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 62 File name: Invitation to Tender (ITT) for SSC Drive Replacement Project Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Identifier Invitation to Tender Effective Date 07 April 2026 Review Date April 2031 Invitation to Tender/Request for Proposal No: ____________________ Name of Tenderer: ___________ _ _ Country of registration: _______________________________________ Full names of contact person: __________________________________ Contact details: Tel (landline): Cell phone: e-mail address: Name of tenderer: Full names of authorised signatory
Points Allocation: 10 points
B-BBEE Details: der (ITT) for SSC Drive Replacement Project
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
rural or underdeveloped area or townships.
NOTE 1: Tenderers shall submit the following mandatory returnable
for Subcontracting:
company registration documents (CK and B-BBEE certificate
or sworn affidavit) or
letters from the tenderer to the sub-contractors, stating the
intent to sub-contract. The Tenderer should sign both
documents and the Sub-contractor(s) earmarked.
Potential scope to be subcontracted and/or outsourced:
Skills type Intake Outcome
Hydraulics Diploma/ On job Training
Technician N Diploma
Mechanical Diploma/ On job Training
Technician N Diploma
3.21 Reverse e-auction Reverse e-auction is not applicable
(if applicable)
Contractual Requirements
Mandatory Contractual Requirements that must be included in all tenders is the following: -
Additional Contractual Requirements that may be included if applicable:
.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on
B-BBEE Requirements
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)This tender concerns a service with designated materials. Only locally produced goods or services with a stipulated minimum threshold for Local Production and Content will be considered. The material threshold for switching devices is 5%. Mandatory subcontracting is a condition of award for contracts above R30 million. Tenderers shall subcontract a minimum of 30% of the contract value to designated groups, such as an EME or QSE which is 51% owned by black people living in rural or underdeveloped areas. Proof of B-BBEE status level is required.
Health & Safety
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)Health and Safety Plan
✓ Must address the project /scope of work OHS
risk(s)and aligned with the health and safety
specification or requirements)
Costing for Health and Safety management
✓ Has the tenderer submitted detailed costing for
OHS (the cost should be broken down not provided
as a lump sum).
work/service to be performed.
as a guideline.
✓ Letter of Good Standing (COIDA or equivalent)
Baseline OHS Risk Assessment (BRA)
✓ Identification, assessment and management of
OHS risks related to the scope of work. The
methodology used for the risk assessment must be
provided together with the BRA
OHS policy signed by CEO
✓ The submitted policy must comply to OHS Act
Section 7
OHS Competency
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 62
File name: Invitation to Tender (ITT) for SSC Drive Replacement Project
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
✓ (Consider scope of work, risks, OHS plan and
applicability) CV’s and qualifications / certificates
(List competencies required)
.
Safety Requirements
✓ Must address the project /scope of work OHS
risk(s)and aligned with the health and safety
specification or requirements)
✓ Has the tenderer submitted detailed costing for
OHS (the cost should be broken down not provided
as a lump sum).
work/service to be performed.
as a guideline.
✓ Letter of Good Standing (COIDA or equivalent)
Baseline OHS Risk Assessment (BRA)
✓ Identification, assessment and management of
methodology used for the risk assessment must be
provided together with the BRA
f. Emergency preparedness and response plan
g. Hazardous and chemical substances plan
Effective Date 07 April 2026
Review Date April 2031
Reference Returnable From Suppliers at at **
closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable)
to Tender Returnable Returnable Returnable
Safety COIDA - Original certificate of good standing or proof √
of application issued by the Compensation Fund
(COID) or a licensed compensation insurer (South
African tenderers only)
Quality Attached √
Other safety/quality Attached √
documents as
required per scope
of works
Environmental Attached √
Due
Environmental
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)a. Appointment of the Environmental Officer
With at least three (3) years related environmental
management experience with Qualification (i.e., National
Diploma/Degree/Btech in Environmental Management).
b. Environmental Policy
The policy statement should commit to:
Environmental compliance and
Duty of care or pollution prevention commitment
c. Aspect and impact register
Environmental Aspects & Impacts Register must identify,
assess and provides controls/ mitigations for impacts as per
✓ (Consider scope of work, risks, OHS plan and
applicability) CV’s and qualifications / certificates
(List competencies required)
Environmental Requirements:
a. Appointment of the Environmental Officer
With at least three (3) years related environmental
management experience with Qualification (i.e., National
Diploma/Degree/Btech in Environmental Management).
b. Environmental Policy
assess and provides controls/ mitigations for impacts as per
scope of work
d. Method statement
identifying environmental aspects and impacts related to the tasks and their mitigation measures.
e. Waste Management
Contractual Terms
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)sanctions list. A tenderer shall be found to have the nationality
of a country if the tenderer is a national or is constituted,
incorporated, or registered and operates in conformity with the
provisions of the laws of that country. This criterion shall also
apply to the determination of the nationality of proposed
subcontractors or suppliers for any part of the Contract including
related services.
individually or as a partner in a joint venture (JV) or consortium,
except on an E-Tendering system where there is a limit size
(The upload size per document is 500 megabytes and total
submission is restricted to 4 gigabytes).
submitting tenders and concluding contracts with Eskom:
For contracts valued below R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed to paying
Suppliers within 30 days of receipt of undisputed invoices.
Effective Date 07 April 2026
Review Date April 2031
For contracts valued above R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed to paying
suppliers within 60 days of receipt of undisputed invoices.
Special Conditions
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)The tender is for the whole of the contract. Alternative tenders are not allowed. The successful tenderer may be required to provide cataloguing information. The tender validity period is 12 weeks. Tenders must be submitted electronically via the Eskom E-tendering site. The latest version of the tender submitted will be accepted. Tenderers must ensure the submission status is indicated as complete.
Requirements
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)Eligibility criteria: Tenderers must not be under any restriction to do business with Eskom or State-Owned Companies. Tenderers are ineligible if they have the nationality of a country on international sanctions lists, submit more than one tender, have a conflict of interest, are restricted by National Treasury, are on the Tender Defaulters list, are restricted by Eskom, or sub-contract 100% of the Scope of Work. Tenders signed by non-authorised persons are also ineligible. Tenderers must have a CIDB contractor grading of 7ME or higher, or meet JV grading requirements.
Section
Source: ITT for SSC Drive replacement for a period of 38 months.pdf (RFP)1.1.9 *SBD 6.1 Preference Points Claim Form in terms of Annexure I Y
PPPFA 2022 regulations
1.1.11 Tax Evaluation questionnaire to determine whether a
3.13 Functionality requirements Functionality requirements are applicable
Tenderers who do not meet the threshold for functionality scoring will
The following criteria will be applicable for this transaction under functionality criteria
3.15 Evaluation of Price Prices will be evaluated as follows
evaluation parameters relating to uncertainty and risk, where
evaluation purposes but will be implemented when payment is
Prices will be scored out of 90 points
3.18 Evaluation of Specific Goals Specific goals will be scored out of 10 points in accordance with the
If a tenderer fails to submit evidence of its points claim for a Specific
Goal, it will not be disqualified. However, it will be awarded 0 points
the 80/20 system. Eskom will add the score from Pricing and Specific
Quality Requirements
Category 1: Quality Requirements Deliverables to be evaluated indicator = 1
SECTION A: Quality Management System A.1 Product / Service Scoping on ISO 9001 1
Valid certification of Quality Management certification authority
Section A Score 4
operation (Tender Quality Requirements responsibilities and authorities - Organization
Services - Must include criteria for evaluation,
evaluation of external providers
Compliance Requirements
Source: SUPPLI~1.DOC (unknown)No document content found in ZIP archive
Description
Source: Scope of work.pdf (unknown)of the works ......................................................................................................................... 6
1.1 Executive overview ................................................................................................................................................ 6
1.2 Employer’s objectives and purpose of the works .................................................................................................. 6
1.3 Interpretation and terminology ............................................................................................................................... 6
1.3.1 List of Definitions .......................................................................................................................... 6
1.3.2 List of Abbreviations ..................................................................................................................... 7
2 Management and start up. ...................................................................................................................... 8
2.1 Management meetings ...................................................................................................
Submission Guidelines
Source: Scope of work.pdf (unknown)The Employer's Design section provides drawings for the SSC drive replacement project at Matimba Power Station. Works are for the design, supply, installation, testing and commissioning of the replacement of the SSC (Submerged Scraper Conveyor) drive of Unit 5? ensure proposal aligns with Eskom standards. Contractors are required to follow Matimba’s Permit to Work System and Health and Safety specifications. Part C3 of the Scope of Work consists of the Works Information and Part C3 ECC3 cover page. The Employer will provide standard Site Regulations.
Evaluation Criteria
Source: Scope of work.pdf (unknown)Unable to extract eligibility criteria
Technical Specifications
Source: Scope of work.pdf (unknown)The scope includes the replacement of the SSC drive at Matimba Power Station. Objectives include standardisation of the drive system with those at other Eskom power stations, specifically Matimba's SSV Collins. The Employer's design includes Mechanical Design, Electrical Design, and Control and Instrumentation (C&I) Design for the SSC system. C&I design is based on the Teleperm ME system. Drive types are referenced (e.g., PIV, Vickers Hardness HV), with components measured in mm, Nm, kW, Hz. The Employer’s design is described, including the SSC process description, mechanical design, electrical design, and control and instrumentation design in the Works Information.
Methodology
Source: Scope of work.pdf (unknown)The purpose of the program and planning is to define the Employers requirements for the time, cost and resource planning and control when using the NEC contract.
Financial Requirements
Source: Scope of work.pdf (unknown)Payment Terms: payment certificate from the Service Manager in terms of core clause 51.1, the
Contractor provides the Employer with a tax invoice showing the amount due for payment equal to that stated
in the Service Manager’s payment certificate.
The Contractor shall address the tax invoice to:
Matimba Power Station, P.O Box 215, Lephalale, 0555 and include on each invoice the fo
Compliance Requirements
Source: Scope of work.pdf (unknown)e Employer’s VAT registration number 4740101508.
Health & Safety
Source: Scope of work.pdf (unknown)3.7.1 Documentation Synopsis ............................................................................................................ 45
3.7.2 As Built Drawings and Documents ............................................................................................. 45
4 Procurement ........................................................................................................................................... 46
4.1 Minimum requirements of people employed on the Site ..................................................................................... 46
4.2 Subcontracting..................................................................................................................................................... 46
4.2.1 List of Proposed Sub-Contractors .............................................................................................. 46
5 Construction .......................................................................................................................................... 47
5.1 Facilities provided by the Contractor ................................................................................................................... 47
5.2 Temporary works, Site services & construction constraints ................................................................................ 47
5.2.1 Employer’s Site entry and security control, permits, and Site regulations ................................. 47
5.2.2 Restrictions to access on Site, roads, walkways and barricades ............................................... 48
5.2.3 Health and safety facilities on Site .............................................................................................. 48
5.2.4 Publicity and progress photographs ........................................................................................... 48
5.2.5 Contractor’s Equipment .............................................................................................................. 48
5.2.6 Equipment provided by the Employer ........................................................................................ 49
5.2.7 Site services and facilities .......................................................................................................... 49
5.3 Completion, testing, commissioning and correction of Defects .......................................................................... 49
5.3.1 Sectional Completion .................................................................................................................. 49
5.3.2 Completion of the Whole of the Works ....................................................................................... 49
5.3.3 Maintenance Spares ................................................................................................................... 50
5.3.4 Commissioning Spares ............................................................................................................... 50
5.3.5 Performance tests after Completion ........................................................................................... 50
Pre-testing check sheet and Preparation .................................................................................................. 50
6 List of drawings ..................................................................................................................................... 52
6.1 Drawings issued by the Employer ....................................................................................................................... 52
C3.2 Contractor’s Works Information .......................................................................................................... 54
Part c3: scope of work 5 c3 ecc3 cover page
ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER _____________
electrical and C&I panels shall be done by the Contractor.
2.3 Health and safety risk management
2.3.1 General
Specifications for Contractors (PA/270/003) attached to the Invitation to Tender. This procedure will be
handed over during tender enquiry and will enable the successful Tenderers to compile a Health & Safety
plan that has to be approved by the Employer prior to commencement of work.
Employer’s site regulations as stipulated in Form PA/270/003, covering the following:
2.3.2 Matimba Permit to Work System
The Contractor will ensure that he/she is informed of all the requirements of Eskom’s Plant Safety
2.3.3 SHE documentation required from the Contractor at tender
performance, should the Contractor not provide this information it will be assumed that it does not exist:
2.3.3.1 Health and Safety Plan (Construction Regulations)
file should be compiled in line with attached healthy and safety file guideline index.
2.3.3.2 Occupational Health and Safety Act 1993, Section 37
employ only people who have been duly authorized in terms thereof and who have received sufficient
safety training to ensure that they can comply therewith.
provisions of the Act, Regulations or Safety and Operating Procedures.
premises relevant to this contract.
whenever he is required to do so.
this contract, in terms of the Act and Regulations and shall advise the Safety Officer of any changes
thereto.
found to commit any unlawful act or any unsafe working practice or is found to be not authorized or
qualified in terms of the Act.
unsafe working procedures or conditions or any non-compliance with the Act, Regulations and
walkways. All equipment is packed neatly without interference to access. All excess scaffolding material is
removed from working areas after the scaffolding has been erected. Scrap bins are available on the zerometer level and emptied daily by the Employer.
2.3.5 Barricading
Access to danger zones is done using handrail type guards of at least 1,2 meters high, able to block access
to the danger zone. Symbolic safety signs depicting “Danger” and “No entry” are attached to the guards.
2.3.6 Scaffolding
2.3.7 Hazardous Waste
handled in accordance with the minimum requirements for the Handling and Disposal of hazardous waste in
terms of Government Legislation as proclaimed by the Department of Water Affairs and Forestry 1994 Ref.:
BN0621-16296-5. (A copy of this document is available at the Power Station for reference purposes).
Part c3: scope of work 13 c3 ecc3 cover page
ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER _____________
and work instructions
quality and the integration of such with prescribed contract communication channels
Part c3: scope of work 15 c3 ecc3 cover page
ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER _____________
Note: The meeting is chaired by the Project Manager.
Outage meetings are held daily at 08H00 during outages and must be attended by the Contractor to review
previous days’ activities and plan details and progress for the next period. An attendance registers and
minutes are kept monitoring attendance and details discussed during these meetings. The Contractor’s senior
staff and supervisors attend these meetings with input from their staff to enable up to date feedback to the
3 Engineering and the Contractor’s design
3.1 Employer’s design
3.1.1 SSC Process description
Coarse ash, from the boiler, falls into a bath of water contained by the SSC’s top trough structure, which
quenches the hot ash. The quenched ash is then conveyed to the front of the SSC by scrapers connected to
a chain driven system. Part of the water is removed from the ash on the dewatering slope of the SSC. The dewatered ash is then transferred by discharge chute onto one of two Coarse Ash Conveyors (CAC).
SSC performs the functions of Boiler Bottom Ash (BBA) collection, dewatering of BBA, and provides a
controlled rate of BBA discharge onto downstream plant. The SSC’s top trough correctly filled with water
working in conjunction with the dipper plates provides boiler sealing by preventing air ingress into the boiler
via the SSC.
3.1.2 Mechanical Design
SSCs are currently driven by an electro-mechanical drive system which consists of an 18,5kW electrical
motor directly connected to 3 reduction gearboxes. The output of the three-reduction gearbox is connected to
a rack and pinion gear assembly which is linked by a chain. The SSC’s drive shaft is directly connected to the
pinion gear to provide drive torque to the SSC system. This drive assembly is supplied by PIV Gearboxes and
Drives and produces 75 000 Nm of torque. The speed of the drive shaft can be varied using a variable speed
gearbox in accordance with the ash production in the boiler. The maximum drive speed of the SSC is applied
during backlog recovery conditions, refer to drawing 058/39872 in Table 13.
Figure 1: 3 gearboxes aligned to develop torque (Mechanical drive)
from losing tension and bundling under the guide idlers during operation. The chain is guided with in the SSC
by a number of idlers. Submerged idler wheels are used in the upper trough of the machines and require
adequate sealing designs to prevent water leakage from the upper trough to the outer environment. The
rotation of the idlers downstream of the tension station is monitored by the revolution of the controllers. This
device detects a breakage in the two chain strands.
Part c3: scope of work 26 c3 ecc3 cover page
ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER _____________
Furthermore station 11 is equipped with 3 DI and 2 DO modules whilst station 12 is equipped 5 DO modules.
motor and first reduction box. The variable gearbox has an internal hydraulic drive mechanism equipped with
an electric servo motor HDA10 AA001 (also called speed variator) with maximum and minimum speed limit
switches i.e., PIV Slip monitor relay located inside the variable speed gearbox. The speed of the SSC
conveyor chain is varied by actuating the servo unit from either locally from the IO remote panel or the unit
control room. This is done manually by the local or remote operator and is based on the unit operating load
conditions. This functionality needs to be automated in the new drive design.
The variable gearbox is also equipped with a tacho generator HDA10 CS002 which provides the feedback of
the variable speed system output to the control room in unit of percentages. The interface is via transducer
module located inside the IO remote panel. The transducer is powered through 220VAC source internal to
remote IO panel. The correct functioning of the conveyor chain is monitored through the SSC speed switch
HDA10 CS001 located on the front-end bottom chain wheel shaft as well as a slip clutch monitors HDA10
CS101/102.
The IO remote panel is equipped with push buttons (PB) related to the operation of the variable speed-box.
Table 5: IO remote panel is equipped with push buttons
Environmental
Source: Scope of work.pdf (unknown)2.4 Environmental constraints and management
Matimba has an Environmental Policy, PP/240/001, to which the Contractor and his employees must adhere.
the legal register applicable to his area of responsibility, the aspect register and the Matimba procedures
(applicable to the Contractor’s area of responsibility) and to familiarize themselves on such procedures, within
30 days from the date of commencement of work at Matimba, to assist the Contractor and his/her employees
to prevent pollution and to comply with legislative requirements. Copies of the above-mentioned documents
shall be obtained from the Project Manager or Environmental Officer on the first day prior to commencement
of work at Matimba. The Contractor shall submit proof to the Environmental Officer of Matimba that he and his
employees has done all the necessary training on procedures and Policies supplied to them and that they do
understand the contents of the procedures, registers and policies and will adhere to them at all times.
designated storage area
hazardous waste disposal certificate is submitted to the Project Manager.
materials are moved to allocated sites. No scrap shall be stored in the Contractor’s yard. Scrap is to be
cleared from Site daily.
contract.
Part c3: scope of work 14 c3 ecc3 cover page
ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER _____________
Contractual Terms
Source: Scope of work.pdf (unknown)2.5.8 Quality Records .......................................................................................................................... 17
2.6 Programming constraints .................................................................................................................................... 18
2.6.1 Purpose ...................................................................................................................................... 18
2.6.2 General ....................................................................................................................................... 18
2.6.3 Updated Bar Chart ...................................................................................................................... 21
2.6.4 Plant Outages ............................................................................................................................. 21
2.6.5 Site Programme Updating and Monitoring During Outages ....................................................... 21
2.6.6 Contractor’s Management, Supervision and Key People ........................................................... 22
2.7 Invoicing and payment ........................................................................................................................................ 22
2.8 Insurance provided by the Employer ................................................................................................................... 22
2.9 Contract change management ............................................................................................................................ 22
2.10 Provision of bonds and guarantees ..................................................................................................................... 22
2.11 Training workshops and technology transfer ...................................................................................................... 23
2.11.1 General ....................................................................................................................................... 23
2.11.2 Training Categories .................................................................................................................... 23
2.11.3 Training Documentation ............................................................................................................. 23
2.11.4 Operating, Maintenance and Engineering Training Manuals ..................................................... 23
2.11.5 Participation of Employer’s Staff ................................................................................................. 24
3 Engineering and the Contractor’s design ........................................................................................... 25
3.1 Employer’s design ............................................................................................................................................... 25
3.1.1 SSC Process description ............................................................................................................ 25
3.1.2 Mechanical Design ..................................................................................................................... 25
3.1.3 Electrical Design ......................................................................................................................... 27
3.1.4 Control and Instrumentation Design ........................................................................................... 27
3.1.5 Teleperm ME .............................................................................................................................. 27
3.1.6 SSC Operation............................................................................................................................ 30
3.2 Parts of the works which the Contractor is to design .......................................................................................... 31
3.2.1 General ....................................................................................................................................... 31
The general scope related to the SSC drive replacement project include but not limited to the following:31
3.2.2 SSC Mechanical Design ............................................................................................................. 33
3.2.3 Electrical System Design ............................................................................................................ 35
3.2.4 Control and Instrumentation System Design .............................................................................. 36
3.3 Operating description .......................................................................................................................................... 42
3.4 Technical risk assessments ................................................................................................................................ 44
3.4.1 HAZOP Studies .......................................................................................................................... 44
3.4.2 FMEA (Failure Mode and Effect Analysis) ................................................................................. 44
3.4.3 Fire Protection Requirements ..................................................................................................... 44
3.4.4 Safety Signs ................................................................................................................................ 45
3.5 Other requirements of the contractor’s design .................................................................................................... 45
3.6 Procedure for submission and acceptance of Contractor’s design ..................................................................... 45
3.7 As-built drawings, operating manuals and maintenance schedules ................................................................... 45
Part c3: scope of work 4 c3 ecc3 cover page
ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER _____________
listed above. It may be required that the person be based at the Contractor’s offices full time. The Contractor
will then be required to include allocated codes to all other designs and related documentation. It is also the
responsibility of the Contractor to consistently apply the KKS codes throughout the rest of the technical
documentation which shall include, but not limited to:
The Contractor shall ensure that all documentation is coded (as per the codes assigned by the technician)
prior submission to the Employer for review.
Part c3: scope of work 10 c3 ecc3 cover page
ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER _____________
2.8 Insurance provided by the Employer.
As per NEC insurance cover clause 80.1
2.9 Contract change management.
2.10 Provision of bonds and guarantees.
The form in which a bond or guarantee required by the conditions of contract (if any) is to be provided by the
Contractor is given in Part 1 Agreements and Contract Data, document C1.3, Sureties.
does not affect the Employer’s right to termination stated in this contract.
2.11 Training workshops and technology transfer
2.11.1 General
Requirements
Source: Scope of work.pdf (unknown)The Contractor shall implement and maintain a quality management system that as a minimum meets the requirements of Generation Standard GGS 0462 Quality Management for Engineering and Construction Works.
Section
Source: Scope of work.pdf (unknown)System, are trained and on successful completion of Matimba’s authorization / evaluation process will be
conditions. This functionality needs to be automated in the new drive design.
2.5 Quality assurance requirements.......................................................................................................................... 15
2.5.1 Quality Management System ..................................................................................................... 15
2.5.2 Quality Documents Submitted with the Tender .......................................................................... 15
2.5.3 Quality Documents Submitted after the Contract Date .............................................................. 15
2.5.4 Contract Quality Management Plan Requirement ...................................................................... 15
2.5.5 Quality Control Plan .................................................................................................................... 16
2.5.8 Quality Records .......................................................................................................................... 17
Important Dates
Source: 240-68~1.PDF (unknown){"closingDate":"08 June 2026"}
Submission Guidelines
Source: 240-68~1.PDF (unknown)Submit the completed Form 240-68099512 (Rev 9) Tender & Contract Quality Requirements for 240-105658000, with the Tenderer's Quality Representative section signed and dated.
The form requires the tenderer to indicate applicability (-) to ISO 9001 clauses 4 through 10 and quality principles 1 through 7.
The form also includes a section for the tenderer's quality representative name, designation, date, and signature.
Evaluation Criteria
Source: 240-68~1.PDF (unknown)Bidders must complete Form A (Document 240-68099512 Rev 9) and select Category 1 for pre-contract award quality requirements. No other eligibility criteria (e.g., CSD registration, B-BBEE level, CIDB grading, tax clearance) are stated in the provided document.
Technical Specifications
Source: 240-68~1.PDF (unknown)Section (tenderer)
Clauses of 240- clause description indicate with an
105658000 (x) as applicable
Specification or (-) if not
Applicable
Clause 3 pre-contract award quality requirements x
(*Select Only Applicable Category). NB: Not more than one category must be selected. Also indicate
whether site assessment is applicable.
Category 1 (refer to clause 3.5.-105658000) X
CLAUSE 4 Category 2 (refer to clause 3.5.-105658000) -
Category 3 (refer to clause 3.5.-105658000) -
Category 4 (refer to clause 3.5.-105658000) -
Main Supplier and Sub-supplier Capability and Capacity Assessment (refer to clause 3.-105658000)
Post-contract award (ESKOM)
Methodology
Source: 240-68~1.PDF (unknown)CLAUSE 4 Context of the Organisation X PRINCIPLE 1 Customer focus X
CLAUSE 5 Leadership X PRINCIPLE 2 Leadership X
CLAUSE 6 Planning X PRINCIPLE 3 Engagement of people X (ESKOM)
C CLAUSE 7 Support X PRINCIPLE 4 Process approach X
CLAUSE 8 Operation X PRINCIPLE 5 Improvement X
CLAUSE 9 Evidence based decision
Performance Evaluations X PRINCIPLE 6 X SECTION making
CLAUSE 10 Improvement X PRINCIPLE 7 Relationship Management X
Quality Management
Source: 240-68~1.PDF (unknown)REQUIREMENTS FOR 240-105658000 AND Effective
January 2022
QUALITY REQUIREMENTS FOR ISO 9001 Date
STANDARD Review Date January 2027
Eskom Rights of Access (refer to clause 3.8.-105658000) X
Eskom Rights to Information (refer to clause 3.8.-105658000) X
Preservation (refer to clause 3.8.-105658000) X CLAUSE 6
Quality Audits Related Conditions (refer to clause 3.8.-105658000) X
Management of Nonconformities and Nonconforming Outputs Identified by Eskom (refer to clause 3.8.-
Special processes (refer to clause 3.8.-105658000) x
Clauses of iso iso 9001 standard indicate with an quality iso 9001 standard indicate with an
9001 standard clause description (x) as applicable principles principle description (x) as applicable
Or (-) if not or (-) if not
line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written
consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 2
File name: 240-68099512 (Rev 9) Form A Tender & Contract Quality Requirements for 240-105658000 and Quality Requirements for ISO 9001
REQUIREMENTS FOR 240-105658000 AND Effective
January 2022
QUALITY REQUIREMENTS FOR ISO 9001 Date
STANDARD Review Date January 2027
line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written
consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 2
File name: 240-68099512 (Rev 9) Form A Tender & Contract Quality Requirements for 240-105658000 and Quality Requirements for ISO 9001
Section
Source: 240-68~1.PDF (unknown)Rd indicate with an quality iso 9001 standard indicate with an
Performance Evaluations X PRINCIPLE 6 X SECTION making
Eskom’s quality
SECTION (ESKOM) Andani Muthelo Quality Officer 08 June 2026
File name: 240-68099512 (Rev 9) Form A Tender & Contract Quality Requirements for 240-105658000 and Quality Requirements for ISO 9001
TENDER & CONTRACT QUALITY Identifier
QUALITY REQUIREMENTS FOR ISO 9001 Date
Clause 3 pre-contract award quality requirements x
Supplier Quality Performance Monitoring Phase (refer to clause 3.7.-105658000) X
Quality Audits Related Conditions (refer to clause 3.8.-105658000) X
Clauses of iso iso 9001 standard indicate with an quality iso 9001 standard indicate with an
Description
Source: Tender Technical Evaluation Strategy - SSC Drives Gearbox Replacement 20260629.pdf (unknown)The tender is for the replacement of Submerged Scraper Conveyor (SSC) Drives Gearbox at Matimba Power Station. The SSCs are used for boiler bottom ash (BBA) and slag removal, as well as furnace sealing. The current drives have a high failure rate, long lead time, and have reached the end of their life cycle.
Evaluation Criteria
Source: Tender Technical Evaluation Strategy - SSC Drives Gearbox Replacement 20260629.pdf (unknown)Mandatory: valid ECSA certification for all design engineers. Qualitative criteria: Company's capacity to execute works (40%) includes related experience (5+ hydraulic drives projects for full marks). Method statements (25%) include mechanical, electrical, C&I works. Project schedule (5%). Minimum technical score: 70%. Acceptable risks: experience related to other plant system hydraulic drives. Unacceptable risks: exclusions of scope specified in employer's requirements. Exceptions: accept deviation with technical qualification; deviation without technical qualification not accepted.
Technical Specifications
Source: Tender Technical Evaluation Strategy - SSC Drives Gearbox Replacement 20260629.pdf (unknown)Matimba Power Station is designed to have the SSC employed underneath the boiler for the purpose of
boiler bottom ash (BBA) and slag removal, as well as furnace sealing. SSCs are driven by an input gearbox
which is directly connected to the first reduction gearbox, the variable speed drive links these gearboxes
to the electric motor. This drive assembly is supplied by PIV Gearboxes and Drives and produces 75 000
Nm of torque.
The failure rate of these drives is high and has resulted in UCLF being incurred by the station. Secondly,
these drives have a long lead time resulting in the plant running at risk when spares are exhausted, and a
failure occurs. Finally, these drives have reached the end of their life cycle, usually failing with no notice
and the condition monitoring systems onsite struggle to obtain accurate readings.
2.1 Scope
The scope in this Tender Technical Evaluation Strategy covers the technical requirements that will be
applied during the technical evaluations phase of the tender to guide in evaluating the proposals received
from the market to appoint the suitable contractor to design and install submerged scraper conveyor drives
gearbox replacement.
Technical Evaluation Strategy (TTES) defines the following with regards to this works:
2.1.1 Purpose
The purpose of this tender technical evaluation strategy is to define the Qualitative Evaluation Criteria and
TET member responsibilities for tender technical evaluation. The technical evaluation strategy serves as
basis for the tender technical evaluation process.
2.1.2 Applicability
This document applies to the Matimba Power Station Submerged Scraper Conveyor (SSC) Drives
Gearbox Replacement.
2.2 Normative/informative references
Parties using this document shall apply the most recent edition of the documents listed in the following
paragraphs.
2.2.1 Normative
[1] 240-48929482: Tender Technical Evaluation Procedure
[2] ISO 9001 Quality Management Systems.
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
Tender Technical Evaluation Strategy - Submerged Scraper
Conveyor (SSC) Drives Gearbox Replacement. Revision: 2.0
Page:
2.2.2 Informative
[3] 240-53716726: Tender Technical Evaluation Scoring Form Template.
2.3 Definitions
2.3.1 Classification
Controlled Disclosure: Controlled Disclosure to external parties (either enforced by law, or discretionary).
2.4 Abbreviations
Abbreviation Description
BBA Boiler Bottom Ash
ISO International Organization for Standards
PIV Positive Infinitely Variable
QCP Quality control plan
SSC Submerged Scrapper Conveyor
TET Technical evaluation Team
TTES Tender technical evaluation strategy
UCLF Unplanned capability loss factor
2.5 Roles and responsibilities
The Technical Evaluation Team (TET) will be responsible for setting up the technical evaluation criteria
and evaluating the bidding candidates’ submissions. The TET will perform their duty as prescribed and
dictated by the guidelines of the Eskom’s Tender Evaluation Procedure with the intent of appointing a
competent contractor to execute the works.
Below are some of the key roles and responsibilities as prescribed in the Tender Technical Evaluation
Procedure:
staff, in their respective areas understand and adhere to this procedure.
Technical Evaluation Team (TET): The delegated engineers/technical specialists who
are responsible to review and evaluate technical aspects of the tender documentation as
per the Tender Technical Evaluation Strategy.
2.6 Process for monitoring
The TET will perform their evaluations and provide their recommendations as per the Eskom’s Tender
Evaluation Procedure.
2.7 Related/supporting documents
Not Applicable
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
Tender Technical Evaluation Strategy - Submerged Scraper
Conveyor (SSC) Drives Gearbox Replacement. Revision: 2.0
Page:
3.1 Technical evaluation threshold
The minimum weighted final score (threshold) required for a tender to be considered from a technical
perspective is 70%.
3.2 Tet members
Table 1: TET Members
TET number TET Member Name Designation
TET 1 Sizwe Buthelezi Mechanical Engineer
TET 2 David Du Plessis Mechanical Engineer
TET 3 Wandile Mjuqu Electrical System Engineer
TET 4 Boleo Lesejane Electrical System Engineer
TET 5 Vukani Gebashe C&I System Engineer
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
Tender Technical Evaluation Strategy - Submerged Scraper
Conveyor (SSC) Drives Gearbox Replacement. Revision: 2.0
Page:
3.3 Manadatory technical evaluation criteria
Table 2: Mandatory Technical Evaluation Criteria
Mandatory Technical Criteria Reference to Technical Specification / Tender Motivation for use of Criteria
Description Returnable
Provide valid ECSA certification. 1. All (Mechanical, Electrical and C&I) Design Integrity (requirement for all individuals
discipline engineers are required to be
performing engineering design work).
professionally recognised/registered
engineer/technologist with ECSA.
Tender Technical Evaluation Strategy - Submerged Scraper
Conveyor (SSC) Drives Gearbox Replacement. Revision: 2.0
Page:
3.4 Qualitative technical evaluation criteria
Table 3: Qualitative Technical Evaluation Criteria
Qualitative Technical Reference to Technical Specification / Tender Criteria Weighting Criteria Sub
Criteria Description Returnable (%) Weighting
(%)
execute the works
1.1 Related The contractor must have successfully completed Proof submitted indicating 5 or more 5 40
Experience projects of similar scope of work. In the case of Joint successfully completed hydraulic drives
venture, a letter of agreement and clearly indicate all projects.
the details.
Proof submitted indicating 3 to 4 4
Proof to be submitted as follows: successfully completed hydraulic drives
Proof submitted indicating 1 to 2 2
projects.
Not submitted, Experience not relevant 0
or satisfactory.
Tender Technical Evaluation Strategy - Submerged Scraper
Conveyor (SSC) Drives Gearbox Replacement. Revision: 2.0
Page:
2.1 2.1.1 Method statement clearly demonstrate Method Statement(s) demonstrates 5 15
compliance with the full scope of works as good understanding of the scope of
detailed in the works information. Method work and meet technical
statement must include but not limited: requirement(s), safety, and
environment.
model, schematics, technical Method statement(s) has partial 4
specification, and bill of material. limitation
/partial understanding of the scope
of work.
Testing and commissioning
Method Statements lack details and 2
does not meet technical
requirement(s),safety and
environment.
No method statement submitted. 0
2.1.2 Provide CV’s and qualification of Key Mechanical registered engineer or 5
Resources personnel for electrical works. Technologist with 7 or more years
design experience.
Mechanical registered engineer or 4
Technologist with 4 to 6 years design
Technologist with a 2 to 3 years
design experience.
No submission or not relevant 0
Methodology
Source: Tender Technical Evaluation Strategy - SSC Drives Gearbox Replacement 20260629.pdf (unknown)Method statement detailing how the work 4
will be executed showing a thorough
understanding of C&I Scope of the works.
Method statement detailing a high-level 2
Experience & Qualifications
Source: Tender Technical Evaluation Strategy - SSC Drives Gearbox Replacement 20260629.pdf (unknown)The contractor must have successfully completed projects of similar scope of work. The key resources personnel must have relevant experience and qualifications, such as ECSA certification.
Quality Management
Source: Tender Technical Evaluation Strategy - SSC Drives Gearbox Replacement 20260629.pdf (unknown)paragraphs.
2.2.1 Normative
[1] 240-48929482: Tender Technical Evaluation Procedure
[2] ISO 9001 Quality Management Systems.
Method Statements lack details and 2
does not meet technical
requirement(s),safety and
environment.
No method statement submitted. 0
2.1.2 Provide CV’s and qualification of Key Mechanical registered engineer or 5
Resources personnel for electrical works. Technologist with 7 or more years
design experience.
Mechanical registered engineer or 4
Technologist with 4 to 6 years design
Technologist with a 2 to 3 years
design experience.
No submission or not relevant 0
experience
Conveyor (SSC) Drives Gearbox Replacement. Revision: 2.0
Page:
Quality Control Inspector with 6 or 5
more years relevant experience.
Quality Control Inspector with 4 to 5 4
years relevant experience.
Quality Control Inspector with 2 to 3 2
years relevant experience.
No submission or not relevant 0
experience
Rigger with a minimum of 6 or more 5 2
years relevant experience.
Rigger with 4 to 5 years relevant 4
experience.
Rigger with 2 to 3 years relevant 2
experience.
No submission or not relevant 0
experience
2.2 Electrical works 2.2.1 Method statement clearly demonstrate Method Statement(s) demonstrates good 5
compliance with the full scope of works as understanding of the scope of work.
detailed in the works information. Method
statement must include but not limited:
Concept/Basic Design, electrical connection The method statement submitted explains 4
diagram and electrical interface. how some of the activities on the scope 5
will be executed but not all of them.
The method statement provided is not 2
applicable to the scope or refers to other
work or work done in the past.
No method statement submitted. 0
Compliance Requirements
Source: Tender Technical Evaluation Strategy - SSC Drives Gearbox Replacement 20260629.pdf (unknown)key personnel CVs and 5
key personnel CVs and 4
key personnel CVs and 2
B-BBEE Minimum Level: 2
Health & Safety
Source: Tender Technical Evaluation Strategy - SSC Drives Gearbox Replacement 20260629.pdf (unknown)TET 1 Sizwe Buthelezi Mechanical Engineer
TET 2 David Du Plessis Mechanical Engineer
TET 3 Wandile Mjuqu Electrical System Engineer
TET 4 Boleo Lesejane Electrical System Engineer
TET 5 Vukani Gebashe C&I System Engineer
Conveyor (SSC) Drives Gearbox Replacement. Revision: 2.0
Page:
2.1 2.1.1 Method statement clearly demonstrate Method Statement(s) demonstrates 5 15
compliance with the full scope of works as good understanding of the scope of
detailed in the works information. Method work and meet technical
statement must include but not limited: requirement(s), safety, and
environment.
model, schematics, technical Method statement(s) has partial 4
specification, and bill of material. limitation
/partial understanding of the scope
of work.
Conveyor (SSC) Drives Gearbox Replacement. Revision: 2.0
Page:
Site Manager with 6 or more years 5
relevant experience.
Site Manager with 4 to 5 years 4
relevant experience.
Site Manager with 2 to 3 years 2
3 relevant experience.
No submission or not relevant 0
experience
Safety Officer with 6 or more years 5
relevant experience.
Safety Officer with 4 to 5 years 4 2
relevant experience.
Safety Officer with 2 to 3 years 2
relevant experience.
No submission or not relevant 0
experience
Qualified Mechanical Fitter with 7 or 5
more years relevant experience.
Qualified Mechanical Fitter with 4 4 2
to 6 years relevant experience.
Qualified Mechanical Fitter with 2 2
to 4 years relevant experience.
No submission or not relevant 0
experience
Requirements
Source: Tender Technical Evaluation Strategy - SSC Drives Gearbox Replacement 20260629.pdf (unknown)The Technical Evaluation Team (TET) will evaluate the tenders based on the Qualitative Technical Evaluation Criteria, which includes company capacity, method statements, CVs and qualifications of key resources, and project schedule. The minimum weighted final score required for a tender to be considered from a technical perspective is 70%.
Section
Source: Tender Technical Evaluation Strategy - SSC Drives Gearbox Replacement 20260629.pdf (unknown)Title: Tender Technical Evaluation
Tender Technical Evaluation Strategy - Submerged Scraper
TET member responsibilities for tender technical evaluation. The technical evaluation strategy serves as
basis for the tender technical evaluation process.
[1] 240-48929482: Tender Technical Evaluation Procedure
[2] ISO 9001 Quality Management Systems.
[3] 240-53716726: Tender Technical Evaluation Scoring Form Template.
QCP Quality control plan
TET Technical evaluation Team
TTES Tender technical evaluation strategy
The Technical Evaluation Team (TET) will be responsible for setting up the technical evaluation criteria
dictated by the guidelines of the Eskom’s Tender Evaluation Procedure with the intent of appointing a
Below are some of the key roles and responsibilities as prescribed in the Tender Technical Evaluation
Technical Evaluation Team (TET): The delegated engineers/technical specialists who
per the Tender Technical Evaluation Strategy.
The TET will perform their evaluations and provide their recommendations as per the Eskom’s Tender
Evaluation Procedure.
Description
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf (TENDER)construction and Development
Programme (RDP) Goals
Tenderers who complete and submit the objectives as required, but who do not meet Eskom’s
targets, will not be disqualified. SDL&I objectives do not form part of scoring but commitments will
form part of contractual obligations
Transformation rema
Important Dates
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf (TENDER)Closing date: Not explicitly stated in the provided text. The document mentions 'Compulsory Briefing Session' but no date/time is given. The effective date of the SDL&I strategy is 1 February 2023, but this is not the tender deadline. No other dates are provided.
Contact Information
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf (TENDER)Buyer: Kamogelo Mahlangu, Matimba Power Station. No direct contact details (phone/email) are provided in the source.
Submission Guidelines
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf (TENDER)Tenderers must submit the completed SBD forms and supporting documentation as specified in the tender document. The required forms include the preference points claim (SBD 6.1) with valid B-BBEE certificate or sworn affidavit, proof of ownership/shareholding, and certified ID copies. For subcontracting, the subcontracting agreement with designated groups must be submitted. Failure to provide documentation for preference points may result in zero points for specific goals.
Evaluation Criteria
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf (TENDER)Evaluation is based on the 90/10 or 80/20 preference point system. A maximum of 10 points (under 90/10 system) or 20 points (under 80/20 system) may be awarded for B-BBEE status level: Level 1: 10/20, Level 2: 9/18, Level 3: 6/14, Level 4: 5/12, Level 5: 4/8, Level 6: 3/6, Level 7: 2/4, Level 8: 1/2, Non-compliant: 0. Points for specific goals are added to price points, and the contract is awarded to the highest total. For subcontracting, a minimum of 30% of the contract value must be subcontracted to designated groups for contracts above R30 million.
Technical Specifications
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf (TENDER)Scope of work: Supply and delivery of a Synchronous Condenser (SC) for Matimba Power Station. The work includes the supply, delivery, and off-loading of the synchronous condenser, which is a large electrical machine (approximately 40-ton machine). The equipment must be new, unused, and of the exact type specified. Detailed specifications are in the technical schedule.
Methodology
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf (TENDER)through their supply network. In certain cases, the SETA’s accredited training providers can be
approached to participate in developing critical and scarce skills.
Note: That these targets for skills development candidates categorically exclude Eskom
employees and registered learners. The tenderers are required to take full responsibility
for the total cost of developing the requisite skills, and Eskom shall not make any
financial contribution towards the fulfilment of this obligation. Tenderers also are
advised to approach their relevant SETAs to access grants, subsidies, and incentives
as well as South African Revenue Services for tax rebates that are earmarked for skills
development initiatives
Section 3: SDL&I Penalty and Performance Security
Eskom will apply a penalty of 2% the Contract Value for failure to meet SDL&I obligations.
For the duration of the contract, Eskom will retain 2% of every invoice (excluding VAT) as security for
the fulfilment of all SDL&I Obligations. The retained amounts shall only be released to the Contractor
upon fulfilment of all SDL&I obligations by the contractor.
Pricing Schedule
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf (TENDER)tender response must be separated into its components as per the Price Schedule included with
the tender documents. Local procurement content is total spending minus the imported
component.
Financial Requirements
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf (TENDER)No specific financial thresholds or guarantees are stated. Tenderers should refer to the pricing schedule and provide pricing as required.
Compliance Requirements
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf (TENDER)Valid B-BBEE certificate issued by a SANAS accredited verification agency, or sworn affidavit, or CIPS affidavit. Proof of ownership/shareholding (preferably CIPC documentation) including shareholding breakdown. Certified ID copies of all shareholders. For subcontracting: a minimum of 30% subcontracting to designated groups as per the Preferential Procurement Regulations. Tenderers must be compliant with the Preferential Procurement Policy Framework Act.
B-BBEE Requirements
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf (TENDER)Specific Goals: A maximum of 10/20 points may be awarded for the specific goal. Points scored for the specific goal are added to price points, and the total is rounded to two decimal places. Subject to section 2(1)(f) of the Preferential Procurement Policy Framework Act, the contract is awarded to the tenderer scoring the highest points. B-BBEE status levels correspond to points as follows: Level 1: 10 (90/10) or 20 (80/20); Level 2: 9 or 18; Level 3: 6 or 14; Level 4: 5 or 12; Level 5: 4 or 8; Level 6: 3 or 6; Level 7: 2 or 4; Level 8: 1 or 2; Non-compliant: 0 or 0. To claim preference points, tenderers must provide: a valid B-BBEE certificate from a SANAS accredited verification agency, sworn affidavit, or CIPS affidavit; proof of ownership/shareholding (preferably CIPC documentation) with shareholding breakdown; certified ID copies of shareholders; proof of disability where applicable; and for trusts, consortia, or joint ventures, a consolidated B-BBEE status level verification certificate. Deponent electrical signatures are not accepted. Tenderers failing to provide documentation for preference points are not disqualified but may only score points out of 90/80 for price and score 0 points out of 10/20 for specific goals.
Health & Safety
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf (TENDER)ensure their validity:
authorised to depose of an affidavit. (Mark the applicable option).
business address.
as per Statement 004, the percentage of black beneficiaries must be reflected. (No blank spaces to be left).
management account. (Mark the applicable option).
(Financial year end to be stipulated by day/month/year).
supplier status.
the presence of the Commissioner of Oath. Furthermore the Commissioner must also sign and stamp)
commission a sworn affidavit in which they have an interest.
Compiled by: Levious Mocheko Supported by: David Pule
................................... ...................................
Contractual Terms
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf (TENDER)Reporting and Monitoring: The suppliers shall on a quarterly basis submit a report to Eskom in accordance with the Data Collection Template on their compliance with the SDL&I obligations described above. Eskom shall review the SDL&I reports submitted by the suppliers within 30 days of receipt of the reports and notify the suppliers in writing if their SDL&I obligations have not been met. Upon notification by Eskom that the suppliers have not met their SDL&I obligations, the suppliers shall be required to implement corrective measures to meet those SDL&I obligations before the commencement of the following report, failing which Retention clauses shall be invoked. Every contract shall be accompanied by the SDL&I Implementation Schedule, which must be completed by the suppliers and returned to the SDL&I representative for acceptance 28 days after contract award. This will be used as a reference document for monitoring, measuring and reporting on the supplier's progress in delivering on their stated SDL&I commitments.
Section
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy SSC Drive Replacement 1.pdf (TENDER)Section 1: Specific Goals
A maximum of 10/20 points may be awarded to a tenderer for the specific goal specified for the
tender. The points scored for the specific goal must be added to the points scored for price and the
scoring the highest points.
B-BBEE Status Level of Number of points Number of points
Contributor (90/10 system) (80/20 system)
NB: The following documents are required to claim preference points,
Tenderer failing to provide documentation for the allocation of preference points will not be
Description
Source: 240-109253698 Template for a Typical Contract Quality Plan.docx (unknown)Contract Quality Plan template assist the supplier to identify and plan for meeting client's/ contract expectations/requirements for quality management
Submission Guidelines
Source: 240-109253698 Template for a Typical Contract Quality Plan.docx (unknown)Completed Contract Quality Plan must be submitted as part of the bid response. The document serves as a template to be completed by the tenderer, identifying how the supplier will meet the client's/contract expectations for quality management.
Evaluation Criteria
Source: 240-109253698 Template for a Typical Contract Quality Plan.docx (unknown)No explicit evaluation criteria, eligibility thresholds, or returnable forms are stated in the document.
Technical Specifications
Source: 240-109253698 Template for a Typical Contract Quality Plan.docx (unknown)The scope of work must be described in full (as per the NEC/FIDIC works information). The Contract Quality Plan must include: an organogram showing roles and responsibilities including QA/QC functions; communication channels between supplier and Eskom; an index of interfacing documents (processes, standards, codes and specifications); a list of suppliers/sub-suppliers and their monitoring; descriptions of products/processes requiring special controls (e.g. welding, NDT); documented information to be submitted to Eskom; control of documented information; concession and non-conformance management; databook and operation & maintenance manual management; working tools and equipment; handling of customer property; product preservation; identification and traceability; and commissioning and post-delivery activities.
Description
Source: NEC for SSC Drive Gearbox Replacement Contract .doc (unknown)The document is the NEC3 Engineering and Construction Contract (April 2013) template for the SSC Drive Gearbox Replacement Contract at Matimba Power Station. It comprises Part C1 (Agreements & Contract Data), Part C2 (Pricing Data), Part C3 (Scope of Work), and Part C4 (Site Information). The contract is for a 38-month period (36 months to completion plus defects period). The scope covers replacement of SSC drives on all six units with new hydraulic drive systems, including mechanical, electrical, C&I, and structural modifications. The contract uses Option A (Priced contract with Activity Schedule) with secondary Options X1, X2, X5, X7, X16, X17, X18, and additional conditions Z1–Z12. No tender-specific submission guidelines, evaluation criteria, or returnable forms are contained in this contract template; those would be in the separate tender enquiry / invitation to tender documents.
Important Dates
Source: NEC for SSC Drive Gearbox Replacement Contract .doc (unknown)Contract start date: November 2026 (linked to plant outage). Completion date for the whole of the works: 36 months after contract start date. Defects date: 52 weeks after completion of the whole of the works. First programme submission: within 2 weeks of the Contract Date. Revised programmes at intervals no longer than 2 weeks. Defect correction period: 7 days. Assessment interval for payment: between the 25th day of each successive month. No tender closing date, briefing, or site visit dates are provided in the document.
Contact Information
Source: NEC for SSC Drive Gearbox Replacement Contract .doc (unknown)Employer: Eskom Holdings SOC Ltd (Reg No. 2002/015527/30), Registered office at Megawatt Park, Maxwell Drive, Sandton, Johannesburg. Project Manager: Appointed Project Manager, Matimba Power Station, Nelson Mandela Drive, Lephalale 0555. Supervisor: Appointed Supervisor, Matimba Power Station, Nelson Mandela Drive, Lephalale 0555. No email, telephone, or fax numbers are provided for the Project Manager or Supervisor.
Submission Guidelines
Source: NEC for SSC Drive Gearbox Replacement Contract .doc (unknown)Submission method and address: not stated in the document. The document is the NEC3 contract template (Part C1–C4) that will be completed at award stage. No tender-specific returnable forms, closing time, or submission channel are provided in the extracted text.
Evaluation Criteria
Source: NEC for SSC Drive Gearbox Replacement Contract .doc (unknown)No evaluation criteria, scoring split, minimum qualifying thresholds, or preference point system are stated in the document. The document contains contract data, scope of work, and pricing assumptions only.
Technical Specifications
Source: NEC for SSC Drive Gearbox Replacement Contract .doc (unknown)Scope: Replacement of SSC (Submerged Scraper Conveyor) drive gearboxes on all six units at Matimba Power Station with new hydraulic drive systems over a 38-month period. Key work areas: SSC hydraulic drive installation, hydraulic drive motor installation, power pack cabinet installation and positioning, drive shaft modification, drive shaft bearings installation, SSC head end structural modifications for torque arm, Control and Instrumentation design, Electrical power supply design. Contractor design responsibilities: SSC Mechanical Design, Electrical System Design, Control and Instrumentation System Design. Required technical risk assessments: HAZOP Studies, FMEA (Failure Mode and Effect Analysis), Fire Protection Requirements, Safety Signs. Documentation standards: Eskom procedures 240-66920003, 240-65459834, 240-54179170, 240-53114026, 240-53113685, 240-86973501. Drawings in Micro Station (DGN) format and scanned PDF; no TIFF, AutoCAD, or other formats. Plant coding per Eskom KKS Coding Manual; Contractor to manufacture and install KKS coded equipment labels per Matimba P.S. KKS Plant Labelling Guideline (240-62937990). Subcontracting: list of proposed sub-contractors required. Sectional completion and completion of whole works defined. Maintenance and commissioning spares required. Performance tests after completion with pre-testing check sheet.
Financial Requirements
Source: NEC for SSC Drive Gearbox Replacement Contract .doc (unknown)Contract type: NEC3 Option A – Priced contract with Activity Schedule. Price adjustment for inflation (Option X1) applies with base date 1 month before contract start; proportions: Labour 36% (SEIFA Table C-3(a)), Material 30% (SEIFA Table E-A cold rolled), Transport 14% (SEIFA Table L-2(a)), Metal Prices 5% (SEIFA Table F-Zinc), Fixed 15% (non-adjustable). Delay damages (Option X7): R80 000.00 per day for complete works as per Scope of Work and for remainder of works. Retention (Option X16): retention free amount R0.00; retention percentage not specified in extracted text. Limitation of liability (Option X18): Contractor's liability for indirect or consequential loss limited to R1 000 000.00; Employer's liability for Contractor's indirect or consequential loss limited to R0.00. End of liability: 3 years after defects date for latent defects; otherwise per Prescription Act No. 68 of 1969. Payment currency: South African Rand. Payment period: depends on supplier vendor status with Eskom. Contractor must provide tax invoice within one week of payment certificate; must include Eskom VAT number 4740101508. Insurance: Employer provides insurance per Format A, B, or Dx (value-dependent) per policies at http://www.eskom.co.za/Tenders/InsurancePoliciesProcedures/Pages/EIMS_Policies_.From_1_April_2014_To_31_March_2015.aspx. Contractor must provide additional insurances: minimum limit for property damage and third-party bodily injury – whatever Contractor deems necessary in addition to Employer's cover; for employee injury – per COIDA Act No. 130 of 1993 and common law liability with limit not less than R500 000. Pro forma ASGI-SA Guarantee required as security. Contractor to provide hourly rates for design staff and percentage for design overheads in Contract Data Part 2.
Compliance Requirements
Source: NEC for SSC Drive Gearbox Replacement Contract .doc (unknown)Health and safety: Contractor must comply with Matimba Power Station Health & Safety Specifications for Contractors (PA/270/003), OHS Act 85 of 1993, Construction Regulations 2014, Eskom & Matimba No Smoking Policy. All staff must undergo Safety Induction by Matimba Risk Management Department. Contractor's supervisors involved in Permit to Work System must be trained and authorised as Responsible Persons. At tender: Health and Safety Plan (Construction Regulations) required. After award: Health and Safety Plan filed in Health and Safety File per attached guideline index; Occupational Health and Safety Act Section 37 compliance. Environmental: Contractor must comply with all applicable environmental laws, regulations, and contract-specific rules, guidelines, and procedures; ensure subcontractors and employees do likewise. Quality: Quality Management System required; Quality Documents submitted with tender and after Contract Date; Contract Quality Management Plan and Quality Control Plan required; access to Contractor and subcontractor premises for inspection; inspection and testing per contract; quality records maintained. B-BBEE: Contractor must notify Employer within 7 days of any change in B-BBEE status; submit updated verification certificate and supporting documentation within 30 days; decrease in B-BBEE status may lead to renegotiation or termination. Ethics: No illegal or corrupt practices; termination grounds if Contractor or JV member found guilty by competent court/body. Confidentiality: No disclosure of contract information; prior written consent required for images of works; all rights in images vest in Employer; subcontractors bound by same. Joint ventures: joint and several liability; notify key person with binding authority within 2 weeks of Contract Date; no alteration of JV composition without Employer written consent. Cession/delegation/assignment: Contractor may not cede, delegate, or assign without Employer written consent; Employer may cede to subsidiaries or divisions on written notice. Tax: Contractor (if SA registered) must comply with VAT Act No. 89 of 1991 and include Eskom VAT number 4740101508 on invoices. Insurance: as per financial requirements. Dispute resolution: Option W1 – Adjudicator from ICE-SA panel; if no agreement, appointed by Arbitration Foundation of Southern Africa; tribunal is Arbitration per latest Association of Arbitrators (Southern Africa) rules; place of arbitration: South Africa.
Description
Source: E-tendering Help Manual for supplier - 27 January 2025.docxThe document provided is a general eTendering system user manual for Eskom suppliers. It describes how to register and upload bids on the Eskom eTendering portal, not the specific tender content. Bidders must have a CSD number to access the system. OTP verification is sent to both cellphone and email during login. To access this tender, suppliers must register on the eTendering portal (https://eTendering.eskom.co.za), log in, and upload their documents before submission closes. The manual notes that closed tenders may be sent directly to selected suppliers via email link rather than listed on TenderBulletin.
Important Dates
Source: E-tendering Help Manual for supplier - 27 January 2025.docx (unknown)The closing date and time for this tender is 15 September 2026 at 10:00 (SAST).
Submission Guidelines
Source: E-tendering Help Manual for supplier - 27 January 2025.docx (unknown)Bids must be submitted electronically via Eskom's eTendering system at https://eTendering.eskom.co.za. Registration and login require a valid CSD number and email verification. An OTP is sent to the registered cellphone and email for authentication. Tender documents are uploaded to the eTendering portal; a Tender Bulletin publication (https://tenderbulletin.eskom.co.za) serves as the public listing. Once uploaded and finalised, the submission is timestamped and an email confirmation with the submission ID is sent. Bidders should contact the buyer responsible for the tender if they experience problems with the system.
Evaluation Criteria
Source: E-tendering Help Manual for supplier - 27 January 2025.docx (unknown)Access to the eTendering system requires a CSD number. Registration details must be verified via email and OTP. No other eligibility criteria are stated in the document.
Technical Specifications
Source: E-tendering Help Manual for supplier - 27 January 2025.docx (unknown)None of the source documents provided contain any project-specific specification details for the SSC Drive Replacement at Matimba Power Station. The only supplied document is Eskom's eTendering Help Manual for suppliers, covering the web-based upload process only.
Compliance Requirements
Source: E-tendering Help Manual for supplier - 27 January 2025.docx (unknown)Suppliers must be registered on Central Supplier Database (CSD) to gain access to the eTendering system. Access to the eTendering portal requires registration and verified email address. Bidders must register on the eTendering system at https://eTendering.eskom.co.za with a CSD number. An OTP for verification is sent to both cellphone and email address.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 38 of 2000
Important for public-sector construction and infrastructure tenders that require contractor grading or construction procurement standards.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 107 of 1998
Relevant where environmental authorisations, EIAs or environmental compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 85 of 1993
Sets health and safety duties for contractors, employers and service providers working on public-sector sites.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 103 of 1977
Relevant where building standards, renovations, maintenance or construction compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Address
Generation Division - Lephalale - Lephalale - 0555
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
12
Last checked
24 Aug 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Construction. Unlock full pricing strategies, bid frequency, and historical win rates.