Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Proposal
Delivery Location
Mqikela Secondary School - - Mqikela Secondary School -
Organization Type
GOVERNMENT
Published
29 Sept 2026
OCDS Reference
ocds-9t57fa-172057
ESKOM is procuring the supply, installation, testing, commissioning, and handover of a ground-mounted photovoltaic (pv) system with a battery energy storage system (bess) at mqikela senior secondary school in the eastern cape. Bidders must submit a complete set of environmental management documents, each scored pass/fail (0 or 1) against the environmental tender evaluation & scoring card (annexure c1). The most consequential consideration is that every required environmental document must be submitted and satisfy the minimum content requirements, as any missing or non-compliant document results in a score of 0 and may lead to the bidder not being recommended.
Closing date: 21 October 2026 at 10:00 (submission method and address not stated in the available document).
Environmental documentation: Submit all required documents listed in Annexure C1, each scored 0 or 1; a score of 0 (missing or non-compliant) may disqualify the bidder.
Environmental Policy: Must be signed by the CEO/Director, dated and version controlled, and include commitments to environmental protection, compliance, continual improvement, and pollution reduction.
Environmental Management Programme (EMP): Must be project/site specific, addressing significant aspects and impacts (e.g., oil spillage), SWOT risks (e.g., cutting protected trees without permits), and area-specific risks such as working in protected areas, wetlands, or requiring permits for indigenous tree removal.
Waste Management Plan: Must describe expected waste streams (batteries, paper, offcuts, concrete waste), pollution prevention, and waste minimisation (reuse, recycle, reduce).
Environmental Emergency Preparedness & Response Plan: Must list possible emergencies (chemical spillages, air pollution, bee/snake encounters), response approach, drills on specified timeframes, and stakeholder contact details.
Environmental Competency Training: Provide evidence of an environmental training matrix, schedule, and documented proof that staff have received training.
Declaration: Environmental and Social (ES) Past Performance Form must be signed and dated.
Reference documents: Bidders must comply with SHEQ Policy (32-727) and SHE Requirements for Eskom Commercial Processes (32-726).
Bidders should read ISO 14001:2015 for detailed environmental management system requirements and definitions.
Continue with tenders sharing this issuer, category, or province.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Wednesday, 21 October 2026 - 10:00
Venue
https://teams.microsoft.com/meet/33122886310099?p=qFfTtteLVSFKbdAkxd
Important: Attendance at this briefing session is mandatory. Bids from suppliers who do not attend may be disqualified.
Categories
Request for Proposal
Mqikela Secondary School - - Mqikela Secondary School -
Tenders in this industry often require registration with these bodies.
Construction Industry Development Board (CIDB) registration is mandatory for almost all public sector construction tenders. Ensure your grading matches the tender value.
Recommended Certifications
Having these can improve your winning chances: NHBRC Registration, ISO 9001:2015 (Quality Management), ISO 14001:2015 (Environmental Management), ISO 45001:2018 (Occupational Health & Safety), SACPCMP Registration, ECSA Registration
AI Document Analysis Stages
Description
29 Sept
2026
Tender Published
Tender was published
21 Oct
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Ground-mounted PV with BESS Specification Mqikela Senior Secondary School - 27-08-2026_signed 31Aug26.pdf
Supply, installation, testing, commissioning and handover of a ground-mounted photovoltaic (PV) system with battery energy storage (BESS) at Mqikela Senior Secondary School in the Eastern Cape. The system comprises 32 x 640W monocrystalline modules (20.46 kWp), a 20kW three-phase hybrid inverter, and a 40kWh lithium iron phosphate battery, housed in an outdoor integrated ESS. The plant will supply the school's loads, provide backup during grid outages, and export excess energy to the Eskom grid.
Supplier Quality Management_Returnables Latest.pdf
Eskom requires the supply, installation, testing, commissioning and handover of a ground-mounted PV with BESS system at Mqikela Senior Secondary School and Freemantle Boy’s High School in the Eastern Cape, including material and service warranty on the complete installation for a set period and other services detailed in the URS. Bidders must submit quality management returnables covering ISO 9001 QMS evidence, QMS in operation, a draft Contract Quality Plan, an ITP/QCP, and Form A. The quality deliverables are scored under Category 3.
NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdf
Eskom Holdings SOC Ltd requires the supply, installation, testing, commissioning and handover of a PV system with battery energy storage (BESS) at Mqikela Senior Secondary School in the Eastern Cape. The contract is let under the NEC3 Engineering and Construction Contract (April 2013), main Option B (priced contract with bill of quantities), dispute resolution Option W1, and secondary Options X2, X7, X16, X18 and Z1–Z15. Note that the tender title refers to a ground-mounted system while the contract documents and drawings describe a rooftop PV installation; bidders should confirm the configuration with the Employer before pricing.
Environmental Tender Evaluation criteria -.xlsx
Supply, installation, testing, commissioning and handover of a ground-mounted photovoltaic (PV) system with battery energy storage system (BESS) for Mqikela Senior Secondary School in the Eastern Cape.
Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdf
Eskom Holdings SOC Ltd invites tenders for the supply, installation, testing, commissioning, and handover of a ground-mounted photovoltaic (PV) system with battery energy storage (BESS) at Mqikela Senior Secondary School in the Eastern Cape. The contract will be based on the NEC3 Engineering and Construction Contract (ECC3).
240-109253698 CQP Template 2021.pdf
A ground-mounted photovoltaic system with battery energy storage is to be supplied, installed, tested, commissioned, and handed over for Mqikela Senior Secondary School in the Eastern Cape. ESKOM is the procuring organization, and bidders must submit a completed Contract Quality Plan as part of their response.
240-105658000 SUPPLIER QUALITY MANAGEMENT SPEC REV4 FINAL 2026.pdf
ESKOM is procuring the supply, installation, testing, commissioning, and handover of a ground-mounted photovoltaic (PV) system with battery energy storage (BESS) at Mqikela Senior Secondary School in Eastern Cape.
240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP)-rev 3.pdf
Eskom requires the supply, installation, testing, commissioning, and handover of a ground-mounted photovoltaic (PV) system with battery energy storage (BESS) at Mqikela Senior Secondary School in the Eastern Cape. The work includes a Quality Control Plan / Inspection and Test Plan (QCP/ITP) that must be approved by Eskom and relevant authorities.
Eskom - Standard Conditions of Tender (February 2022).pdf
Eskom requires the supply, installation, testing, commissioning, and handover of a ground-mounted photovoltaic (PV) system with battery energy storage (BESS) at Mqikela Senior Secondary School in the Eastern Cape. The tender is governed by Eskom's Standard Conditions of Tender, which set out strict submission, compliance, and evaluation requirements.
240-68099512 Form A Rev 10.pdf
Supply, installation, testing, commissioning, and handover of a ground-mounted PV with BESS system at Mqikela Senior Secondary School and Freemantle Boy's High School, Eastern Cape, for Eskom.
SHE SPECIFICATIONS FOR THE PV BESS SCHOOLS PROJECT.pdf
Eskom requires the supply, installation, testing, commissioning, and handover of a ground-mounted photovoltaic (PV) system with a Battery Energy Storage System (BESS) at Mqikela Senior Secondary School in the Eastern Cape. The contract is governed by Eskom's SHE Specification DXSHEQSF0036 Rev 2, which sets mandatory safety, health, and environmental requirements for the PV & BESS Schools Project.
Copy of Copy of Technical Schedule A B - Customer PV Schools(21-05-2026).xlsx
Eskom requires the supply, installation, testing, commissioning and handover of a ground-mounted photovoltaic system with battery energy storage at Mqikela Senior Secondary School in the Eastern Cape. The solution must meet Eskom Standard 240-171000418 (Major Equipment Requirements for Distribution Solar PV and BESS) and Eskom Specification 240-171000566 (User Requirement Specification for Residential Solar PV and BESS), with all deviations declared.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubWe refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
The project is to establish a ground-mounted PV system with battery backup at Mqikela Senior Secondary School. Objectives: reduce Eskom's carbon footprint, provide continuous supply during grid loss, provide renewable electricity for own consumption, export excess solar energy to the grid, and support future peak energy shaving. The system will supplement own consumption and use PV as primary source with grid as backup.
Submission Guidelines
Source: Ground-mounted PV with BESS Specification Mqikela Senior Secondary School - 27-08-2026_signed 31Aug26.pdf (unknown)Returnable documents: completed technical evaluation criteria, priced BOQ and BOM, BESS specifications, calculated solar DC and AC peak power per PGC, final power network diagram, final logic diagrams, basic project schedule, details of modes of operation, and risk mitigations. All statutory, regulatory and municipal applications and sign-offs are the Contractor's responsibility. The Contractor must provide a Certificate of Compliance (CoC) for all electrical works and as-built drawings upon completion. The Contractor must have the PV installation approved by personnel with Green Card certification.
Evaluation Criteria
Source: Ground-mounted PV with BESS Specification Mqikela Senior Secondary School - 27-08-2026_signed 31Aug26.pdf (unknown)Bidders must be registered on the Central Supplier Database (CSD) and have a valid tax clearance (SARS TCS or tax pin). Bidders must have ECSA-registered engineers for sign-offs and personnel with Green Card certification for PV installation. Bidders must comply with all statutory, regulatory and municipal requirements. Bidders must provide a Certificate of Compliance (CoC) for all electrical works. Bidders must submit all required returnable forms as specified in the tender pack (e.g., SBD forms, pricing schedules, declaration of interest, preference points claim, etc.). Bidders must have the capacity to provide a minimum 12-month base warranty and transfer all OEM guarantees to Eskom.
Technical Specifications
Source: Ground-mounted PV with BESS Specification Mqikela Senior Secondary School - 27-08-2026_signed 31Aug26.pdf (unknown)Scope: Supply, installation, testing, commissioning and handover of a ground-mounted PV with BESS system at Mqikela Senior Secondary School, Eastern Cape. The system must provide continuous supply during grid loss, use PV as primary source with grid backup, export excess energy to the grid, and support future peak shaving.
Key components and metrics:
Installation requirements:
Site: GPS 31°22'33.99"S, 29°35'44.06"E, Mqikela Senior Secondary School, Eastern Cape. Includes office block (A) and classrooms (B-H).
Cabling: AC LV cabling 2 x 50mm2 from each PGC to inverters, 1 x 50mm2 from inverter load output to PGC. All cabling in ducts/trays/piping. 110mm HDPE ducts with draw-wire for communications.
Energy metering: Two meters per PGC (bi-directional on grid, uni-directional on load side), class 0.5 CT 300/5A, Eskom approved, communication via modem.
Safety: Earthing, disconnection/isolation, surge protection, earth leakage, reverse current protection, shielding of comms cables, physical security, redundant safety devices, emergency shutdown controls.
Operating: Minimal user intervention, no full-time operator, full local control and monitoring, secure remote monitoring, detailed operating procedure required.
Warranty: Minimum 12 months base warranty, all OEM guarantees transferred to Eskom, workmanship warranty minimum 12 months, availability warranty at least 98%, 24-hour response time to faults.
Methodology
Source: Ground-mounted PV with BESS Specification Mqikela Senior Secondary School - 27-08-2026_signed 31Aug26.pdf (unknown)Modes of operation: Seamless and automatic islanding and synchronisation to and from the grid. User-configurable prioritisation of PV energy to essential loads or battery storage first. Export excess energy up to a specified power limit. Use of LV/MV connected CTs for export control. Programmable scheduled grid charge/discharge with at least six time-periods per day. Load shaving up to 100% of BESS peak AC discharge rate.
Key design constraints: All PGCs and PUCs at three phases. Support 100% unbalanced load. Equipment installed at identified locations. Contractor responsible for design and implementation of new cables. Equipment environmentally rated (outdoor IP65, indoor IP21). UV and corrosion protection. No single failure causes widespread loss. Appropriate protection devices. OEM guidelines followed. Compliance with latest standards. Neutral colour for enclosures. Metrics are minimum usable amounts. Final PGCs determined after review.
Execution: Site assessment, verify drawings, identify cable routing, verify main circuit breaker size. Mount 32640Wp modules portrait on ground-mounted structure facing north. Wire 4mm2 DC cables to combiner box and inverter. Install bidirectional meter next to transformer. Wire 50mm2 AC cables from meter to disconnector and inverter, and from inverter to AC distribution board. Wire 16mm2 from new AC DB to grid's main AC DB. Wire 4mm2 from new AC DB to office and classrooms B-H separately. Install 150A three-phase 4-pole automatic changeover switch. Test and commission. Provide CoC and as-built drawings. Supply and install 19L AVD Lithex Portable Fire Extinguisher.
Site acceptance testing: Tests include system full capacity, system round trip efficiency, sustained maximum power output, sustained charging current/power, insulation resistance, soil resistance, output voltage, output frequency, solar DC input to AC output efficiency, PV module open-circuit voltage, short-circuit current, operating current, resistance to earth, insulation testing.
Training: Provide overview of entire solar and battery storage system, including key components such as solar panels, inverters, batteries, and monitoring systems. Training sessions: 2 sessions for generic design/system overview/hardware (up to 10 attendees), 1 session for network administration (responsible teacher and caretaker), 1 session for operation and maintenance (responsible teacher and caretaker).
Quality Management
Source: Ground-mounted PV with BESS Specification Mqikela Senior Secondary School - 27-08-2026_signed 31Aug26.pdfCompliance with codes and standards: General - SANS 10142-1, SANS 10142-1-2, NRS 097-2-1, Grid Connection Code for RPPs. Electrical - PV modules per IEC 61215, IEC 61646, IEC 61730, IEC 61701, IEC 62716, IEC 60891, IEC 61829, IEC 61853, IEC 60068-2-78, IEC 60068-2-21, IEC 61345, IEC 62093, IEC 62548; Inverters per IEC 62093, SANS 62109-1, IEC 62109-2, IEC 62116, SANS 60730-1, IEC 61683, SANS 61000-6-2/3/4, IEC 61727, IEC 60364-7-712, IEC 62103; Storage per 240-170000103; Cabling per IEC 62053, 240-56227443; Earthing/lightning/surge per 240-56356396, IEC 60364-4-41, SANS 10292, SANS 10199, SANS 61312-3, SANS 10313, SANS 10200, NRS 039, IEC 61009; Metering per 240-56227589, 240-56359083, D-DT-1000; Performance monitoring per IEC 61724, IEC 61683, IEC 60364-6, IEC 62446, ISO 9845-1, ISO 9847, ISO 9060, ISO/TR 9901, IEC 61725. Control and instrumentation per IEC 61724, IEC 61850-7, IEC 62381, IEC 62382, IEC 62337, EIA/TIA 568/569/607, TIA/EIA 485, TSB-89-A, SANS 10142-1, SANS 10340-1/2, SANS 60794-1-1/2, SANS 61312, SABS 1411, SANS 60947-7-1/2, SANS 60429, 240-56227443, 240-56355754, 240-56355815, 240-56355731, 240-56355541, 32-373, 240-55410927, 240-79669677, 240-64038621. Civil per Southern African Steel Construction Handbook, SANS 10160-1/3, SANS 10162-1, SANS 10160, SANS 121, SANS 2001-CS1, SANS 1921-3, SANS 1200H, SANS 1200HC, 240-56364535, 240-56364545.
Pricing Schedule
Source: Ground-mounted PV with BESS Specification Mqikela Senior Secondary School - 27-08-2026_signed 31Aug26.pdfPricing: Priced BOQ (Bill of Quantities) and BOM (Bill of Materials) required, detailing individual inverters, BESS/batteries, PV modules, integration equipment, communication systems, metering, major cables, structural works, etc. No specific pricing format or payment schedule stated.
Financial Requirements
Source: Ground-mounted PV with BESS Specification Mqikela Senior Secondary School - 27-08-2026_signed 31Aug26.pdf (unknown)Pricing: Priced BOQ (Bill of Quantities) and BOM (Bill of Materials) required, detailing individual inverters, BESS/batteries, PV modules, integration equipment, communication systems, metering, major cables, structural works, etc. No bid security, bonds, guarantees, retention or payment terms are stated in the document.
Compliance Requirements
Source: Ground-mounted PV with BESS Specification Mqikela Senior Secondary School - 27-08-2026_signed 31Aug26.pdf (unknown)CSD registration required. Valid tax clearance (SARS TCS or tax pin) required. ECSA-registered engineers required for sign-offs. Green Card certification required for PV installation approval. Certificate of Compliance (CoC) required for all electrical works. Compliance with all statutory, regulatory and municipal requirements, including local municipality applications. Compliance with SANS, IEC, NRS and Eskom standards as listed in the specification.
Health & Safety
Source: Ground-mounted PV with BESS Specification Mqikela Senior Secondary School - 27-08-2026_signed 31Aug26.pdfSafety requirements: Earthing of electrical and electronic equipment to a reference earth point. Disconnection and isolation mechanisms between all current-carrying conductors of the PV source. Surge protection, earth leakage protection, reverse current detection/protection and circuit breakers. Shielding of all data communication and signal cables. Physical security measures and locking mechanisms to prevent unauthorised access. Redundant / dual in-line safety devices such as interlocks, dead-grid-safety-locks. Emergency shutdown controls suitably located and accessible. All statutory and mandatory safety requirements, including fire protection systems, electrical fire, safety, incident response and security protocols must be strictly adhered to. Excavations must be kept covered or barricaded to prevent injury. Contractor must notify Clerk of Works upon completion of excavations for pole foundations.
Environmental
Source: Ground-mounted PV with BESS Specification Mqikela Senior Secondary School - 27-08-2026_signed 31Aug26.pdfEnvironmental requirements: Equipment must be environmentally rated for locations (outdoor IP65, indoor IP21). Outdoor equipment must be rated for UV exposure and highly corrosive conditions. Excavated material must be disposed of in borrow pits or suitable places indicated by the Employer's environmental representative. Backfilling and reinstatement of surfaces must be done to original state, with compacted crown protruding 50mm above natural ground level to allow for erosion. Compliance with SANS 10198-8 for trench bedding and backfill.
Contractual Terms
Source: Ground-mounted PV with BESS Specification Mqikela Senior Secondary School - 27-08-2026_signed 31Aug26.pdfWarranties: All OEM guarantees and warranties of equipment and material shall be transferred to Eskom. The solution shall be offered with a minimum of 12 months base warranty where the Contractor warrants that the furnished equipment and materials and the completed project are fit for the purpose of producing and storing electricity in accordance with the requirements. Workmanship warranty minimum 12 months after handover. Performance warranty: capacity, availability (at least 98%), and efficiency guaranteed. Contractor must respond to faults within 24 hours, provide written solution within two weeks, and replace faulty equipment. Manufacturer or representative must have trained support staff within the province.
Section
Source: Ground-mounted PV with BESS Specification Mqikela Senior Secondary School - 27-08-2026_signed 31Aug26.pdfTechnical evaluation criteria must be completed and submitted. Bidders must demonstrate compliance with the technical requirements. No specific scoring split or minimum qualifying score stated.
Description
Source: Copy of Copy of Technical Schedule A B - Customer PV Schools(21-05-2026).xlsxThe tender is for the supply, installation, testing, commissioning, and handover of a ground-mounted PV with BESS system at Mqikela Senior Secondary School in the Eastern Cape. The technical evaluation process is detailed in the document, with mandatory and functional criteria.
Submission Guidelines
Source: Copy of Copy of Technical Schedule A B - Customer PV Schools(21-05-2026).xlsx (unknown)Submission method: complete all orange-shaded 'Tenderer's response' / 'B-schedule' columns in the technical schedule, with references to supporting documentation. All submitted documents must be in English. List all deviations to referenced standards (including direct and indirect references) in the '3. Deviations' sheet. Tenderers that do not meet mandatory requirements will not be further evaluated.
Evaluation Criteria
Source: Copy of Copy of Technical Schedule A B - Customer PV Schools(21-05-2026).xlsx (unknown)Evaluation is in three stages:
Technical Specifications
Source: Copy of Copy of Technical Schedule A B - Customer PV Schools(21-05-2026).xlsx (unknown)Scope: supply, installation, testing, commissioning, and handover of a ground-mounted PV with BESS system at Mqikela Senior Secondary School, Eastern Cape.
Major equipment required:
Key technical requirements (from Schedule A):
Compliance Requirements
Source: Copy of Copy of Technical Schedule A B - Customer PV Schools(21-05-2026).xlsx (unknown)No specific compliance requirements beyond the mandatory technical criteria listed in the evaluation criteria. The document does not state CSD, tax, B-BBEE, CIDB, or other compliance requirements.
Description
Source: Environmental Tender Evaluation criteria -.xlsxThe document is an environmental tender evaluation and scoring card (Annexure C1) used to assess whether the supplier submitted the required environmental documentation as specified in the enquiry, and whether that documentation complies with the specified requirements. The project involves the supply, installation, testing, commissioning, and handover of a ground-mounted PV with BESS system at Mqikela Senior Secondary School in the Eastern Cape.
Evaluation Criteria
Source: Environmental Tender Evaluation criteria -.xlsx (unknown)Environmental evaluation scoring card (Annexure C1) used to assess the supplier's submitted environmental documentation against specified requirements. Each criterion is scored 0 or 1: 0 = document not submitted or does not satisfy minimum requirements; 1 = document submitted and content satisfies minimum requirements. The tender submission score sheet, including criteria weighting, is authorised by the relevant senior manager and issued with the enquiry for technical evaluation. Bidders must ensure all required environmental documents are submitted and meet the stated requirements to be recommended.
Technical Specifications
Source: Environmental Tender Evaluation criteria -.xlsx (unknown)The project involves the supply, installation, testing, commissioning, and handover of a ground-mounted photovoltaic (PV) system with Battery Energy Storage System (BESS) at Mqikela Senior Secondary School in the Eastern Cape. The environmental evaluation focuses on the following required documents and evidence:
Note: Bidders should read ISO 14001:2015 for detailed information on environmental management system requirements and definitions.
Compliance Requirements
Source: Environmental Tender Evaluation criteria -.xlsx (unknown)Bidders must submit the required environmental documentation as specified in the enquiry, and the documentation must comply with the specified requirements. The evaluation is based on the Environmental Tender Evaluation & Scoring Card (Annexure C1). Reference documents include SHEQ Policy (32-727) and SHE Requirements for the Eskom Commercial Processes (32-726).
Description
Source: 240-68099512 Form A Rev 10.pdfSupply, installation, testing, commissioning and handover of a ground-mounted PV system with BESS at Freemantle Boy's High School and Mqikela Senior Secondary School in the Eastern Cape, including a material and service warranty on the completed installation for a set period and other services detailed in URS specification 240-105658000.
Submission Guidelines
Source: 240-68099512 Form A Rev 10.pdf (unknown)Returnable form
Technical Specifications
Source: 240-68099512 Form A Rev 10.pdf (unknown)Scope
Pre-contract award quality category
Post-contract award quality phases
Quality Management
Source: 240-68099512 Form A Rev 10.pdfPre-contract award
Post-contract award
Standard conditions (clause 6)
ISO 9001 alignment
Compliance Requirements
Source: 240-68099512 Form A Rev 10.pdf (unknown)Quality compliance
Contractual Terms
Source: 240-68099512 Form A Rev 10.pdfContract execution applies after award under clause 5 of 240-105658000.
The contract carries a material and service warranty on the complete installation for a set period, as set out in the URS specification.
Contact Information
Source: Supplier Quality Management_Returnables Latest.pdf (TENDER)Eskom representative: Bulelani Flekisi (date issued 09/09/2026)
Submission Guidelines
Source: Supplier Quality Management_Returnables Latest.pdf (TENDER)Returnable documents: Form A must be completed and signed. All quality-related returnables listed in the Supplier Quality Management document must be submitted.
Evaluation Criteria
Source: Supplier Quality Management_Returnables Latest.pdf (TENDER)Quality requirements are evaluated as Category 3 deliverables with an indicator value of 1. The evaluation covers:
Technical Specifications
Source: Supplier Quality Management_Returnables Latest.pdf (TENDER)Scope: Supply, installation, testing, commissioning, and handover of a ground-mounted PV with BESS system at Freemantle Boy's High School and Mqikela Senior Secondary School. Includes warranty (material and service) on the complete installation for a set period and other services as detailed in the URS.
Quality Management
Source: Supplier Quality Management_Returnables Latest.pdf (TENDER)Form A must be completed and signed.
Compliance Requirements
Source: Supplier Quality Management_Returnables Latest.pdf (TENDER)Quality Management System requirements per ISO 9001:2015. Bidders must provide objective evidence of a documented QMS that complies with ISO 9001 (Option 2). Specific documentation required includes QMS manual, quality policy, quality objectives, control of documented information, control of nonconforming outputs, nonconformity and corrective action, internal audit, organization chart and responsibility matrix, and control of externally provided processes.
Contractual Terms
Source: Supplier Quality Management_Returnables Latest.pdfWarranty (material and service) on the complete installation for a set period, as detailed in the URS.
Section
Source: Supplier Quality Management_Returnables Latest.pdfQuality requirements evaluated as Category 3 deliverables. Sections A-E with scores as listed.
Description
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdfEskom requires the supply, installation, testing, commissioning, and handover of a ground-mounted PV with BESS system at Mqikela Senior Secondary School in the Eastern Cape. Tender number E3619DXECOU.
Important Dates
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdf (TENDER)Closing date: 21 October 2026 at 10:00 SAST
Compulsory clarification meeting: 07 October 2026 at 10:30 via MS Teams
Attendance is mandatory; non-attendance leads to disqualification.
Clarification queries deadline: 2 working days before tender closing.
Tender validity period: 120 days from closing date.
Briefing Session
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdf (TENDER)Compulsory clarification meeting via MS Teams on 07 October 2026 at 10:30. Link: https://teams.microsoft.com/meet/33122886310099?p=qFfTtteLVSFKbdAkxd, Meeting ID: 331 228 863 100 99, Passcode: TG32Tz7C. Attendance is mandatory; non-attendance leads to disqualification.
Contact Information
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdf (TENDER)Eskom Representative (SCM):
Fraud and corruption reporting:
Submission portal: https://www.eskom.co.za/tenders/
Submission Guidelines
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdf (TENDER)Submission method: electronic only via the Eskom E-Tendering site at https://www.eskom.co.za/tenders/.
Returnable forms (all must be completed, signed where required, and submitted at closing unless noted):
Disqualification risks:
Evaluation Criteria
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdf (TENDER)Evaluation stages:
Preference system: 80/20 (price 80, specific goals 20). If uncertain, the lowest acceptable tender determines the applicable system.
Price evaluation details:
Specific goals: failure to submit evidence results in 0 points for that goal, not disqualification.
SHEQ and SDL&I requirements are evaluated; one opportunity is given to correct or submit outstanding items within a stipulated time.
Technical Specifications
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdf (TENDER)Scope: Supply, installation, testing, commissioning, and handover of a ground-mounted PV with BESS system at Mqikela Senior Secondary School, Eastern Cape.
Mandatory technical requirements (must be met or tender is not evaluated):
Local content thresholds (designated sectors):
Methodology
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdfMethodology requirements are embedded in the mandatory technical requirements: provide complete design documentation for 2 previously completed PV/BESS installation projects in the last 3 years, including SLD, PV array layout, string configuration, mounting structure specs, BOM, datasheets, container layout, and feasibility study report. Also provide a quality method statement based on scope (using Eskom template ref 240-126469599).
Quality Management
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdfQuality requirements (Category 3):
Pricing Schedule
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdfPricing schedule/BOQ must be submitted in PDF and Excel format. The price list must also be in Excel. Completed NEC pricing and Contract Data Part 2 are required. If cataloguing is required, include a line item for cataloguing. Prices are evaluated inclusive of VAT, corrected for arithmetical errors, excluding contingencies, and adjusted for variations. Unconditional discounts considered; conditional discounts applied at payment.
Financial Requirements
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdf (TENDER)Pricing format: completed pricing schedule/BOQ in PDF and Excel; also completed NEC pricing and Contract Data Part 2.
Security for performance: if a performance bond or demand guarantee is required, the tenderer must select at least two financial institutions from the Eskom-approved list.
Payment terms:
Financial statements: submit recent 2 years' financial statements for financial analysis, including:
Statements must be valid within 18 months after year end (per Companies Act S(30)).
Compliance Requirements
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdf (TENDER)Mandatory contractual requirement (prior to award): proof of CSD registration.
Tax compliance:
B-BBEE: proof of B-BBEE status level contributor (certificate, sworn affidavit, or other prescribed proof) is required for preference points.
Employment Equity Act: designated employers must provide proof of compliance, including submission of the EE report to the Department of Labour.
CIDB: proof of grading 2EP PE required (for engineering and construction works).
Local content: SBD 6.2 and Annexures G1–G4 mandatory; DTIC exemption letter if thresholds cannot be met; delegation of authority if signatory not in executive authority.
SHEQ requirements (evaluated, one opportunity to correct):
B-BBEE Requirements
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdf (TENDER)Local content thresholds for designated sectors: Solar PV mounting structures 90%, Inverters 40%, Fabricated steel products 100%, Electrical and telecoms cables 90%, Industrial lithium battery 50%.
Mandatory returnables for contract award: SBD 6.2 Local Content Declaration Certificate, Annexure C Local Content Declaration Summary Schedule, DTIC exemption letter if thresholds cannot be met, and delegation of authority letter if signatory is not in executive authority.
B-BBEE proof: certificate, sworn affidavit, or other prescribed proof required for preference points.
Health & Safety
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdfSafety requirements (evaluated; one opportunity to correct):
Environmental
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdfEnvironmental requirements (evaluated; one opportunity to correct):
Contractual Terms
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdfContract will be the NEC3 Engineering and Construction Contract (ECC3).
Mandatory contractual requirement: proof of CSD registration on contract award.
Tender validity period: 120 days from closing date.
Alternative tenders are not allowed.
Security for performance: if required, tenderer must select at least two Eskom-approved financial institutions.
Cataloguing may be required after award; pricing schedule must include a line item for cataloguing.
Payment terms: 30 days for contracts below R50 million, 60 days for above (incl. VAT).
Eskom reserves the right to negotiate with preferred bidders if prices are not market-related.
Main contractors are discouraged from subcontracting with subsidiaries; must declare if doing so.
Special Conditions
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdf (TENDER)Tender validity period: 120 days from closing date. Alternative tenders not allowed. Security for performance required – select at least two Eskom-approved financial institutions. Cataloguing may be required after award. Payment terms: 30 days for contracts below R50 million, 60 days for above. Eskom reserves right to negotiate with preferred bidders. Main contractors discouraged from subcontracting with subsidiaries; must declare if doing so.
Requirements
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdf (TENDER)Eligibility: tenderer (or JV/consortium) must not be under restriction to do business with Eskom or State-Owned Companies; must not have nationality of a sanctioned country; must not submit more than one tender; JV/consortium must be jointly and severally liable; must not have conflict of interest; must be signed by authorised persons; must not be restricted by National Treasury, on Tender Defaulters list, or restricted by Eskom; must not subcontract 100% of scope.
Mandatory technical requirements: as listed in technical specifications.
Section
Source: Invitation to Tender (ITT) Provision for the Supply installation testing commissioning handover of a Ground-mounted PV with BESS at Mqikela.pdfFunctionality: weighted score-card approach; minimum overall weighted score of 80% to technically qualify. Prices scored out of 80 points; specific goals scored out of 20 points. 80/20 preference system applies. Prices evaluated inclusive of VAT, corrected for arithmetical errors, excluding contingencies, adjusted for variations, NPV comparison, unconditional discounts considered.
Description
Source: 240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP)-rev 3.pdfThe document is an Eskom Quality Control Plan / Inspection and Test Plan (QCP/ITP) template. It is a blank form to be completed by the bidder for the specific contract. It does not contain any tender-specific scope, quantities, or requirements.
Technical Specifications
Source: 240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP)-rev 3.pdf (unknown)The document is a blank Eskom Quality Control Plan / Inspection and Test Plan (QCP/ITP) template. It defines the framework for quality control and inspection activities but contains no tender-specific scope, quantities, or requirements.
Key elements of the template:
Quality Management
Source: 240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP)-rev 3.pdfThe document is a blank Quality Control Plan / Inspection and Test Plan (QCP/ITP) template. It requires the bidder to complete a plan that defines:
Compliance Requirements
Source: 240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP)-rev 3.pdf (unknown)The document is an Eskom-controlled template. It states that when downloaded from the document management system, the document is uncontrolled and the user is responsible for ensuring it aligns with the authorised version. No specific compliance requirements for this tender are stated.
Description
Source: Eskom - Standard Conditions of Tender (February 2022).pdfThis document is the Eskom Standard Conditions of Tender (Rev 12, effective 01 February 2025). It sets out the general rules for tendering to Eskom. Specific details for this tender (scope, quantities, locations, evaluation criteria, etc.) are provided in the Invitation to Tender and Tender Data, which are not included in this document.
Important Dates
Source: Eskom - Standard Conditions of Tender (February 2022).pdf (TENDER)Closing date: 21 October 2026 at 10:00 (SAST).
Briefing Session
Source: Eskom - Standard Conditions of Tender (February 2022).pdf (TENDER)Tenderers must attend compulsory site visits and/or clarification meetings as stipulated in the Tender Data.
Contact Information
Source: Eskom - Standard Conditions of Tender (February 2022).pdf (TENDER)All communication must be directed to the Eskom Representative only, in writing, in English.
Submission Guidelines
Source: Eskom - Standard Conditions of Tender (February 2022).pdf (TENDER)Submission method: e-tendering via the Eskom Tender Bulletin site on the Eskom E-tendering page. Paper submissions are not permitted for e-tendering.
Evaluation Criteria
Source: Eskom - Standard Conditions of Tender (February 2022).pdf (TENDER)Evaluation stages:
Technical Specifications
Source: Eskom - Standard Conditions of Tender (February 2022).pdf (TENDER)Scope: Supply, installation, testing, commissioning, and handover of a ground-mounted PV with BESS system at Mqikela Senior Secondary School, Eastern Cape.
Experience & Qualifications
Source: Eskom - Standard Conditions of Tender (February 2022).pdf (TENDER)Tenderers must comply with eligibility criteria, including any CIDB grading requirements.
Quality Management
Source: Eskom - Standard Conditions of Tender (February 2022).pdfTenderers must provide proof to Eskom's satisfaction that safety, health, environmental, and quality (SHEQ) systems, policies, and capabilities are in place at the closing date and/or contract award.
Pricing Schedule
Source: Eskom - Standard Conditions of Tender (February 2022).pdfTenderers must include in rates, prices, and tendered total all duties, taxes (including VAT), and other levies payable.
Financial Requirements
Source: Eskom - Standard Conditions of Tender (February 2022).pdf (TENDER)Pricing:
Security for performance:
Insurance:
Financial analysis:
Compliance Requirements
Source: Eskom - Standard Conditions of Tender (February 2022).pdf (TENDER)Eligibility:
CIDB:
B-bbee:
Sheq:
Legislation:
Other:
B-BBEE Requirements
Source: Eskom - Standard Conditions of Tender (February 2022).pdf (TENDER)Eskom will score the B-BBEE level as stated on the CSD report or certificate/affidavit.
Contractual Terms
Source: Eskom - Standard Conditions of Tender (February 2022).pdfEskom is not liable for any losses, claims, or damages sustained by tenderers as a result of participation in the tender process.
Special Conditions
Source: Eskom - Standard Conditions of Tender (February 2022).pdf (TENDER)Eskom may accept or reject any variation, deviation, or alternative tender, and may cancel the tender at any time before contract conclusion.
Requirements
Source: Eskom - Standard Conditions of Tender (February 2022).pdf (TENDER)Tenderers must comply with eligibility criteria stated in the Tender Data, must not be under any restriction to do business with Eskom or State-Owned Companies, and must not subcontract 100% of the scope of work.
Section
Source: Eskom - Standard Conditions of Tender (February 2022).pdfEskom will determine basic compliance before detailed evaluation. Tenders failing basic compliance are non-responsive.
Quality Management
Source: 240-109253698 CQP Template 2021.pdfThe supplier must prepare a Contract Quality Plan (CQP) in line with SANS 466:2005 / ISO 10005:2005. The plan must cover: scope of work, communication channels for quality issues, an organogram with roles and responsibilities (including QA/QC functions), an index of interfacing documents, a list of suppliers and sub-suppliers, monitoring of suppliers, interface of sub-suppliers with the supplier's QMS, items to be manufactured/refurbished/purchased, QCP/ITP requirements, special controls for processes like welding and NDT, documented information to be submitted to Eskom, records control and retention, concession and non-conformance management, databook management, tools and equipment management, customer property handling, product preservation, identification and traceability, and commissioning and post-delivery activities.
Important Dates
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdf (unknown)Closing date: 21 October 2026 at 10:00 (from tender record).
Key dates (from contract data, conditions to be met):
Access dates:
Programme submission:
Defects date: 52 weeks after completion of the whole of the works.
Defect correction period: 2 weeks upon notification of defect.
Contact Information
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdf (unknown)Project Manager:
Supervisor:
Employer:
Submission Guidelines
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdf (unknown)Returnable documents:
Evaluation Criteria
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdf (unknown)No evaluation criteria (price/functionality split, minimum qualifying score, preference point system) are stated in the contract documents.
Bidders must be able to obtain the insurances required under Insurance Table A before the starting date.
Joint ventures, consortia and other unincorporated groupings are accepted and are jointly and severally liable for performance; the key person authorised to bind the grouping must be notified to the Project Manager within 2 weeks of the contract date, and the composition of the grouping may not change without the Employer's written consent.
The Contractor's key persons (with job, responsibilities, qualifications and experience) must be named in Contract Data Part 2, and that part must also record fee percentages, working areas, the programme, the bill of quantities reference and the Schedules of Cost Components data.
Technical Specifications
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdf (unknown)The works are the supply, installation, testing, commissioning and handover of a ground-mounted PV with BESS system at Mqikela Senior Secondary School (also referred to as Rooftop PV with BESS in the contract documents).
The site boundaries are within the servitude of Enoch Mqikela Secondary School boundaries project.
Works Information is in Part C3: Scope of Work; Site Information is in Part C4: Site Information.
The contract is a re-measurement contract (NEC3 Option B) priced against a bill of quantities.
The bill of quantities includes civil works items such as:
Time-related charges in the bill include:
Methodology
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdfThe Contractor must submit a first programme for acceptance within 2 weeks of the contract date. The starting date is the date of contract award. The Contractor submits revised programmes at intervals no longer than 2 weeks. The Employer is not willing to take over the works before the Completion Date.
Key dates and conditions to be met:
Experience & Qualifications
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdfThe Contractor's key persons must be named in Contract Data Part 2, with job, responsibilities, qualifications and experience. CVs (and further key persons data including CVs) are appended to a Tender Schedule (title to be completed).
Pricing Schedule
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdfPricing format: NEC3 Option B – Priced contract with bill of quantities. The bill comprises items measured using quantities and rates, or stated as lump sums. The Prices are the lump sums and amounts obtained by multiplying rates by quantities. The Price for Work Done to Date is the total of the quantity of work completed for each item multiplied by the rate, plus a proportion of each lump sum completed.
Method of measurement: as stated in Part C2.1, Pricing Assumptions.
General assumptions:
Bill of quantities includes civil works items (excavations, site clearance, ESS slab/foundation, yard stone, excess material removal, weed killer) and time-related charges (site establishment, supervision, security, plant and equipment, health and safety measures, transport).
Payment terms:
Retention: free amount NIL, retention percentage 10%.
Delay damages: 0.1% of Contract Value per day, up to a limit not exceeding 10% of Contract Value.
Financial Requirements
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdf (unknown)Pricing format: NEC3 Option B – Priced contract with bill of quantities. The bill comprises items measured using quantities and rates, or stated as lump sums. The Prices are the lump sums and amounts obtained by multiplying rates by quantities.
Payment terms:
Retention:
Delay damages:
Tax invoice:
Insurance (Insurance Table A – Contractor provides):
Insurance Table B – Employer provides: Assets All Risk, Contract Works, Environmental Liability, General and Public Liability, Transportation (Marine), Motor Fleet and Mobile Plant, Terrorism, Cyber Liability, Nuclear Material Damage and Business Interruption, Nuclear Material Damage Terrorism – all per the insurance policy document.
Limitation of liability:
Employer's limitation of liability:
Compliance Requirements
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdf (unknown)No minimum CIDB grading, B-BBEE level, CSD registration or tax clearance requirement is stated in the contract documents.
A field for the tenderer's CIDB registration number (if applicable) appears on the Form of Offer and Acceptance.
Bidders must be able to obtain the insurances required under Insurance Table A before the starting date.
A Contractor registered in South Africa under the Companies Act must comply with the Value Added Tax Act and quote the Employer's VAT number on invoices.
Joint ventures, consortia and other unincorporated groupings are accepted and are jointly and severally liable for performance; the key person authorised to bind the grouping must be notified to the Project Manager within 2 weeks of the contract date, and the composition of the grouping may not change without the Employer's written consent.
The Contractor's key persons (with job, responsibilities, qualifications and experience) must be named in Contract Data Part 2, and that part must also record fee percentages, working areas, the programme, the bill of quantities reference and the Schedules of Cost Components data.
B-BBEE Requirements
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdf (unknown)B-BBEE requirements (Z3):
Health & Safety
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdfThe Contractor must take all reasonable precautions to maintain the health and safety of persons in and about the execution of the works. The Employer may appoint the Contractor as the "Principal Contractor" under the Construction Regulations 2014 (promulgated under the Occupational Health & Safety Act). The Contractor warrants that the total of the Prices includes a sufficient amount for proper compliance with the Construction Regulations, all applicable health & safety laws and regulations, and the health and safety rules, guidelines and procedures provided for in the contract. The Contractor must comply with the Construction Regulations and all applicable health & safety laws and regulations, and must ensure that its subcontractors, employees and others under its direction and control likewise comply.
Asbestos requirements (Z15):
Environmental
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdfThe Contractor must comply with all applicable environmental laws and regulations and rules, guidelines and procedures provided for in the contract, and must ensure that its subcontractors, employees and others under its direction and control likewise comply.
Asbestos requirements (Z15):
Contractual Terms
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdfThe conditions of contract are the NEC3 Engineering and Construction Contract, April 2013 (ECC3), with main Option B (Priced contract with bill of quantities), dispute resolution Option W1, and secondary Options X2 (Changes in the law), X7 (Delay damages), X16 (Retention), X18 (Limitation of liability), and Z (Additional conditions of contract). The law of the contract is the law of the Republic of South Africa. The language is English. The period for reply is 5 working days.
Key terms:
Additional conditions Z1 to Z15 always apply:
Section
Source: NEC3 ECC FOR MQIKELA SSS PV SOLAR GROUND MOUNT.pdfNo evaluation criteria (price/functionality split, minimum qualifying score, preference point system) are stated in the contract documents. The contract is a re-measurement contract (NEC3 Option B) priced against a bill of quantities. The Contractor must submit a first programme for acceptance within 2 weeks of the contract date, and revised programmes at intervals no longer than 2 weeks. The Employer is not willing to take over the works before the Completion Date.
Description
Source: 240-105658000 SUPPLIER QUALITY MANAGEMENT SPEC REV4 FINAL 2026.pdfThis is Eskom's Supplier Quality Management specification (QM 58, revision 4). It defines minimum quality requirements for all Eskom suppliers, covering evaluation, selection, registration, assessment, performance monitoring, and auditing. Suppliers must maintain a QMS conforming to ISO 9001. The specification applies to all RFIs, RFQs, RFPs, and contracts. It includes requirements for quality plans, contract quality plans, quality control plans, supplier categories (1-4), pre-contract award requirements, post-contract execution, performance monitoring, audits, and standard conditions.
Contact Information
Source: 240-105658000 SUPPLIER QUALITY MANAGEMENT SPEC REV4 FINAL 2026.pdf (unknown)No specific contact details are provided in this document.
Submission Guidelines
Source: 240-105658000 SUPPLIER QUALITY MANAGEMENT SPEC REV4 FINAL 2026.pdf (unknown)Returnable documents (all must be completed, signed and submitted):
Disqualification risks:
Evaluation Criteria
Source: 240-105658000 SUPPLIER QUALITY MANAGEMENT SPEC REV4 FINAL 2026.pdf (unknown)Evaluation is based on the Supplier Quality Management specification (QM 58).
Technical Specifications
Source: 240-105658000 SUPPLIER QUALITY MANAGEMENT SPEC REV4 FINAL 2026.pdf (unknown)Scope: Supply, installation, testing, commissioning and handover of a ground-mounted PV with BESS system at Mqikela Senior Secondary School, Eastern Cape.
Quality management requirements:
Methodology
Source: 240-105658000 SUPPLIER QUALITY MANAGEMENT SPEC REV4 FINAL 2026.pdfPreservation work plan development and execution:
Quality Management
Source: 240-105658000 SUPPLIER QUALITY MANAGEMENT SPEC REV4 FINAL 2026.pdfQuality management system requirements:
Pricing Schedule
Source: 240-105658000 SUPPLIER QUALITY MANAGEMENT SPEC REV4 FINAL 2026.pdfNo pricing schedule details are provided in this document.
Financial Requirements
Source: 240-105658000 SUPPLIER QUALITY MANAGEMENT SPEC REV4 FINAL 2026.pdf (unknown)No specific financial requirements (bid security, guarantees, retention, payment terms) are stated in this document.
Compliance Requirements
Source: 240-105658000 SUPPLIER QUALITY MANAGEMENT SPEC REV4 FINAL 2026.pdf (unknown)Quality compliance:
Other compliance:
Health & Safety
Source: 240-105658000 SUPPLIER QUALITY MANAGEMENT SPEC REV4 FINAL 2026.pdfThe specification references Eskom's Safety, Health, Environment, and Quality (SHEQ) Policy (32-727) and IAEA Safety Standard GS-R-3.1. No additional health and safety requirements are detailed in this document.
Contractual Terms
Source: 240-105658000 SUPPLIER QUALITY MANAGEMENT SPEC REV4 FINAL 2026.pdfPreservation management programme requirements:
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 38 of 2000
Important for public-sector construction and infrastructure tenders that require contractor grading or construction procurement standards.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 107 of 1998
Relevant where environmental authorisations, EIAs or environmental compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 85 of 1993
Sets health and safety duties for contractors, employers and service providers working on public-sector sites.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 103 of 1977
Relevant where building standards, renovations, maintenance or construction compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Address
Mqikela Secondary School - - Mqikela Secondary School -
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
12
Last checked
30 Sept 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Median Estimate
R 560 204
Range
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
Get deep intelligence on Construction. Unlock full pricing strategies, bid frequency, and historical win rates.
Learn how to submit a winning bid with these related articles
💡 Want more tendering tips and strategies?
Explore Our Blog