Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
Arnot Power Station - Rietkuil - Mpumalanga - 1097
Organization Type
GOVERNMENT
Published
30 Jun 2026
OCDS Reference
ocds-9t57fa-160731
ESKOM is inviting open tenders for the full refurbishment, testing, and delivery of medium voltage motors at arnot power station in mpumalanga, under a 4-year contract. This tender is for suppliers capable of handling the complete scope of work, including compliance with eskom's standard conditions of tender and all applicable regulations.
Continue with tenders sharing this issuer, category, or province.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Monday, 20 July 2026 - 10:00
Venue
null
Request for Bid(Open-Tender)
Arnot Power Station - Rietkuil - Mpumalanga - 1097
Recommended Certifications
Having these can improve your winning chances: NERSA Registration, PV GreenCard (Solar Installation)
AI Document Analysis Stages
Review in progress
The information shown on this card is preliminary. Our procurement team is currently finalising the submission guidelines, evaluation criteria, technical specifications, financial requirements, and compliance sections so you have a clean, bid-ready summary to work from. Documents being finalised: Annexure B – Supplier Tender Receiving Acknowledgement Form..docx, Annexure D - Integrity Declaration Form.docx. You don’t need to refresh — this page will pick up the updated review automatically.
30 Jun
2026
Tender Published
Tender was published
20 Jul
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Annexure F - CPA (IG) Requirements for Foreign Goods and Services.docx
Eskom seeks a contractor for a 4-year contract to perform full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station in Mpumalanga. The tender includes detailed provisions for Contract Price Adjustment (CPA) for contracts exceeding 12 months and specific requirements for handling foreign goods/services and currency payments.
Declaration of Shareholding or Beneficiaries Form.pdf
Eskom invites tenders for a 4-year contract to refurbish, test, and deliver medium voltage motors at Arnot Power Station in Mpumalanga. The provided document is a declaration form requiring disclosure of company shareholders/beneficiaries and potential conflicts of interest with Eskom employees.
Annexure G - Tax Compliance Questionnaire for Foreign Suppliers (Manadatory for foreign suppliers to complete) - April 2024.docx
Tender for full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station for a 4-year period, issued by ESKOM in Mpumalanga. The document focuses on tax compliance requirements for foreign suppliers.
1. Form CPA - General.pdf
This document is Eskom's standard Contract Price Adjustment (CPA) form for a 4-year contract involving the refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station. The form details the mandatory methodology for calculating price adjustments over the contract term, protecting both parties from inflation and cost fluctuations. It is not the main tender specification but a critical financial/commercial annexure.
Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.docx
This document is a Non-Disclosure Agreement (NDA) template from Eskom for tenderers bidding on a 4-year contract for the full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station. The NDA establishes confidentiality obligations for sensitive information disclosed during the tender process, not the tender's technical or commercial specifications.
Scope of work and Technical Evaluation Criteria for the Refurbishment of Medium Voltage Motors__Rev 4_Signed.pdf
Eskom seeks a contractor for a 4-year contract to fully refurbish, test, and deliver medium voltage motors (185kW to 5800kW) for Arnot Power Station in Mpumalanga. The scope includes collection, comprehensive repair, testing, painting, and delivery of 18 specific motor types critical to plant operations.
Annexure B – Supplier Tender Receiving Acknowledgement Form..docx
Eskom seeks a contractor for a 4-year contract to fully refurbish, test, and deliver medium voltage motors at Arnot Power Station in Mpumalanga. The document provided is an acknowledgement form requiring bidders to confirm receipt and completeness of tender documents and to address cataloguing information.
Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdf
Eskom invites tenders for a 4-year contract for the full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station in Mpumalanga. The tender is open, uses a 90/10 scoring system (price 90 points, specific goals 10 points), and requires strict compliance with eligibility, functionality, and local content thresholds.
Annexure I - SBD 6.1 Preference Points Claim Form in terms of The PPR 2022.docx
Eskom tender for full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station for a 4-year period. The tender uses South Africa's preferential procurement system with either 80/20 or 90/10 scoring depending on final tender values.
Eskom Vehicle Safety Spec 32-345.pdf
This tender document outlines Eskom's vehicle safety specifications that apply to contractors performing work for Eskom, including the refurbishment of medium voltage motors at Arnot Power Station. The document details mandatory safety standards for all vehicle types used in Eskom operations.
E-Tenderers E-Tendering Training Acknowledgement Form.pdf
Eskom's tender for full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station in Mpumalanga over a 4-year period. The document provided is an E-Tendering Training Acknowledgement Form, which is a mandatory returnable document for tenderers to confirm they have completed required e-tendering training.
Annexure J - SBD 4 - Tenderer_s Disclosure.docx
Eskom seeks a contractor for the full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station in Mpumalanga under a 4-year contract. The tender includes a mandatory disclosure form (SBD 4) requiring declarations on conflicts of interest, state employment, and collusion.
2. B-BBEE_sworn Affidavit-Exempted Micro Enterprise.pdf
This tender document is a B-BBEE exemption affidavit form for ESKOM's 4-year contract for refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station. The document is not the full tender but a specific compliance form requiring sworn declaration of B-BBEE status as an Exempted Micro Enterprise.
2. B-BBEE_sworn Affidavit-Qualifying Smal Enterprise.pdf
ESKOM tender for full refurbishment, testing and delivery of medium voltage motors at Arnot Power Station in Mpumalanga Province for a 4-year period. The provided document excerpt focuses on B-BBEE compliance requirements, specifically a Sworn Affidavit for Qualifying Small Enterprises (QSE) with annual revenue between R10 million and R50 million. The tender closes on July 20, 2026.
Eskom Supplier Integrity Pact - 02 June 2023.pdf
This is Eskom's Supplier Integrity Pact document, not the full tender document. It outlines ethical and compliance requirements for suppliers participating in Eskom procurement processes, including a 4-year contract for refurbishing medium voltage motors at Arnot Power Station. The pact mandates integrity, transparency, and anti-corruption measures.
Eskom - Standard Conditions of Tender - 30 January 2025.pdf
Eskom is soliciting tenders for a 4-year contract for the full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station in Mpumalanga. The tender process is governed by Eskom's Standard Conditions of Tender, which emphasize fairness, transparency, and compliance with South African procurement regulations.
NEC3 Term Service Contract for MV Motors.pdf
Eskom Holdings SOC Ltd is tendering for a 48-month term service contract for the full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station in Mpumalanga. The contract is based on the NEC3 Term Service Contract (TSC3) framework, utilizing Option A (Priced contract with price list). The scope includes tasks such as transportation, electrical testing, and refurbishment of specific motor types (e.g., PA Fan Motors, Sluice Pump Motors). The closing date for submissions is July 20, 2026.
Eskom General Conditions of Purchase - 31 May 2024.pdf
Eskom General Conditions of Purchase document governing the tender for full refurbishment, testing and delivery of medium voltage motors at Arnot Power Station in Mpumalanga for a 4-year period. This document establishes the contractual framework between Eskom and suppliers, covering payment terms, delivery requirements, warranties, and legal obligations.
E-Tendering Help Manual for supplier.pdf
This document is not the actual tender specification but a user manual for Eskom's eTendering system. It provides instructions for suppliers on how to register, log in, and submit tender documents electronically for Eskom tenders, including the referenced tender for the refurbishment of medium voltage motors at Arnot Power Station.
Annexure D - Integrity Declaration Form.docx
Eskom invites tenders for a 4-year contract to provide comprehensive refurbishment, testing, and delivery services for medium voltage motors at Arnot Power Station in Mpumalanga. The tender closes on July 20, 2026.
Annexure G1-G4 - SBD 6.2 - Declaration Certificate for Local Production and Content for Designated Sectors - 14 March 2025.docx
This tender document from ESKOM requires the full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station in Mpumalanga for a 4-year period. The document focuses primarily on local content requirements, mandating compliance with designated sector thresholds and detailed declaration processes.
Annexure E - Contract Price Adjustment (CPA) Requirements for Local Goods and Services.docx
Eskom seeks a 4‑year contract to refurbish, test and deliver medium‑voltage motors at Arnot Power Station (Mpumalanga). The tender requires a fixed‑price component for the first year and a Contract Price Adjustment (CPA) formula for years 2‑4, with separate formulas for local and imported items, using only publicly published indices.
Supplier Declaration of Interest Template.docx
This tender, issued by Eskom in Mpumalanga, involves the full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station over a 4-year period. The document includes a Supplier Declaration of Interest, requiring applicants to disclose conflicts of interest, relationships with Eskom employees/directors, and any business courtesies exchanged.
SHE SPEC.pdf
This is an Occupational Health and Safety (OHS) specification document for a 60-month (5-year) contract for the total refurbishment, testing, and delivery of medium voltage motors (185kW to 5800kW) at Arnot Power Station. The document outlines Eskom's minimum OHS requirements that the main contractor and any appointed subcontractors must meet. It is not the full tender but a critical compliance component focusing on safety management systems, legislative adherence, and contractor responsibilities.
Tenderer - (SDLI) Strategy Setting - MV Motors.docx
Eskom is inviting tenders for the full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station in Mpumalanga over a 4-year period. The tender evaluates bids based on a 90/10 or 80/20 points system (price vs. specific goals like B-BBEE compliance). SDL&I (Socio-Economic Development and Localization & Industrialization) objectives are contractual obligations but not part of scoring. Key focus areas include B-BBEE improvement, local content, job creation, skills development, and subcontracting to designated groups.
3. Eskom Vehicle Safety Spec 32-345.pdf
This document is Eskom's Vehicle Safety Specification (32-345, Revision 5), not the tender document for the 'Full refurbishment, testing and delivery of medium voltage motors at Arnot Power Station'. It outlines mandatory safety standards for all vehicles used for Eskom business, including contractor vehicles. The tender closing date is July 20, 2026.
Eskom life-saving rules.pdf
This document is Eskom's Life-Saving Rules Standard (Revision 6), not the primary tender document. It outlines mandatory safety protocols that all contractors must follow when working on the 'Full refurbishment, testing and delivery of medium voltage motors at Arnot Power Station' tender. The rules enforce zero tolerance for high-risk behaviors to prevent fatalities and serious injuries.
Annexure C - Tenderer_s Particulars.docx
Eskom tender for the full refurbishment, testing and delivery of medium voltage motors at Arnot Power Station in Mpumalanga Province over a 4-year contract period. This Annexure C document outlines tenderer registration requirements, vendor particulars, and subcontracting disclosure obligations.
3. Eskom Waste Management Standard 32-245.pdf
This is not a tender document but Eskom's Safety, Health, Environment, and Quality (SHEQ) Policy. The provided tender information describes a future contract for motor refurbishment, but the document content is a corporate policy outlining Eskom's commitment to SHEQ principles, management systems, and a Zero Harm culture.
E-Tenderers' Training Acknoweldegement.pdf
This document is an E-Tendering Training Acknowledgement Form for a tender issued by Eskom for the full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station over a 4-year period. The tender closing date is July 20, 2026. The provided content is not the full tender specification but a mandatory administrative form that tenderers must complete and submit.
Annexure H - SBD 1 - Part A - Invitation to Bid and Part B - Terms and Conditions for Bidding.docx
ESKOM invites bids for a 4-year contract for full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station in Mpumalanga. The tender is governed by South African public procurement regulations and requires strict compliance with submission procedures and tax obligations.
3. Eskom life-saving rules.pdf
This document is Eskom's Life-Saving Rules Standard (Revision 6), not the full tender document. It outlines mandatory safety rules for all work at Eskom sites, including the Arnot Power Station tender. The rules enforce zero tolerance for behaviors with high potential for serious injury or fatality. The tender involves a 4-year contract for refurbishing medium voltage motors.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
R 12 869 512
Range
Based on 13 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Description
Source: 3. Eskom Vehicle Safety Spec 32-345.pdfImportant Dates
Source: 3. Eskom Vehicle Safety Spec 32-345.pdf (unknown)Submission Guidelines
Source: 3. Eskom Vehicle Safety Spec 32-345.pdf (unknown)Evaluation Criteria
Source: 3. Eskom Vehicle Safety Spec 32-345.pdf (unknown)Technical Specifications
Source: 3. Eskom Vehicle Safety Spec 32-345.pdf (unknown)Methodology
Source: 3. Eskom Vehicle Safety Spec 32-345.pdfQuality Management
Source: 3. Eskom Vehicle Safety Spec 32-345.pdfCompliance Requirements
Source: 3. Eskom Vehicle Safety Spec 32-345.pdf (unknown)Health & Safety
Source: 3. Eskom Vehicle Safety Spec 32-345.pdfSection
Source: 3. Eskom Vehicle Safety Spec 32-345.pdf (unknown)buses, tractors, and all vehicles fitted with canopies to ensure effective warning capabilities.
Contact Information
Source: NEC3 Term Service Contract for MV Motors.pdf (unknown)Submission Guidelines
Source: NEC3 Term Service Contract for MV Motors.pdf (unknown)Returnable Documents
Source: NEC3 Term Service Contract for MV Motors.pdf (unknown)Evaluation Criteria
Source: NEC3 Term Service Contract for MV Motors.pdf (unknown)Technical Specifications
Source: NEC3 Term Service Contract for MV Motors.pdf (unknown)Methodology
Source: NEC3 Term Service Contract for MV Motors.pdf (unknown)Experience & Qualifications
Source: NEC3 Term Service Contract for MV Motors.pdfQuality Management
Source: NEC3 Term Service Contract for MV Motors.pdfFinancial Requirements
Source: NEC3 Term Service Contract for MV Motors.pdf (unknown)Compliance Requirements
Source: NEC3 Term Service Contract for MV Motors.pdf (unknown)B-BBEE Requirements
Source: NEC3 Term Service Contract for MV Motors.pdf (unknown)Health & Safety
Source: NEC3 Term Service Contract for MV Motors.pdfEnvironmental
Source: NEC3 Term Service Contract for MV Motors.pdfContractual Terms
Source: NEC3 Term Service Contract for MV Motors.pdfRequirements
Source: NEC3 Term Service Contract for MV Motors.pdf (unknown)Description
Source: 3. Eskom life-saving rules.pdfEvaluation Criteria
Source: 3. Eskom life-saving rules.pdf (unknown)Technical Specifications
Source: 3. Eskom life-saving rules.pdf (unknown)Compliance Requirements
Source: 3. Eskom life-saving rules.pdf (unknown)Health & Safety
Source: 3. Eskom life-saving rules.pdfSection
Source: 3. Eskom life-saving rules.pdfDescription
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.docxThis is a Non-Disclosure Agreement (NDA) template between Eskom Holdings SOC Ltd (the Disclosing Party) and the supplier/tenderer (the Receiving Party). The NDA governs the confidentiality of information disclosed by Eskom to the supplier for the purpose of evaluating a potential business relationship or tender. The supplier must sign this NDA before receiving any confidential information related to the tender.
Submission Guidelines
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.docx (unknown)This document is a Non-Disclosure Agreement (NDA) template, not the full tender submission package. The NDA must be signed and returned as part of the tender returnables. Ensure the NDA is completed with the supplier's details, signed by a duly authorised representative (no lower than Procurement Senior Manager level for Eskom), and witnessed. The signed NDA must be submitted with the tender response. Failure to sign and return the NDA may result in disqualification as it is a prerequisite for receiving confidential information.
Evaluation Criteria
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.docx (unknown)The NDA itself does not state specific eligibility criteria for the tender (e.g., B-BBEE level, financial standing, technical capability). Those will be in the separate tender invitation documents. Eligibility to sign this NDA is implicitly granted to any company intending to submit a tender and receive Eskom's confidential information.
Technical Specifications
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.docx (unknown)The document is an NDA template and does not contain technical specifications for the motor refurbishment. Technical specifications for the full refurbishment, testing and delivery of medium voltage motors will be provided in the main tender documents, likely after the NDA is signed.
Compliance Requirements
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.docx (unknown)No specific compliance requirements are stated in this NDA. However, bidders must be registered on the National Treasury's Central Supplier Database (CSD) and comply with Eskom's general tender conditions. The NDA itself does not impose B-BBEE, CIDB, or tax compliance conditions.
Submission Guidelines
Source: E-Tenderers' Training Acknoweldegement.pdf (unknown)Mandatory returnable: Complete and submit the E-Tendering Training Acknowledgement Form. Failure to fully complete and submit within the prescribed period will result in disqualification.
Returnable Documents
Source: E-Tenderers' Training Acknoweldegement.pdf (unknown)Mandatory returnable: E-Tendering Training Acknowledgement Form.
Evaluation Criteria
Source: E-Tenderers' Training Acknoweldegement.pdf (unknown)Based solely on this document: Eligibility is contingent on submitting this fully completed mandatory form. The tenderer must be capable of using Eskom's E-Tendering system, as confirmed by this acknowledgement. Other standard eligibility criteria (e.g., B-BBEE status, financial standing, technical capability) are not detailed in this excerpt but would be in the main tender documents.
Technical Specifications
Source: E-Tenderers' Training Acknoweldegement.pdf (unknown)This document is an E-Tendering Training Acknowledgement Form. Bidders must complete self-training via the e-Tendering Noddy Guide, video, or a clarification meeting, and acknowledge their ability to operate the E-Tendering Solution.
Description
Source: Annexure G - Tax Compliance Questionnaire for Foreign Suppliers (Manadatory for foreign suppliers to complete) - April 2024.docxEvaluation Criteria
Source: Annexure G - Tax Compliance Questionnaire for Foreign Suppliers (Manadatory for foreign suppliers to complete) - April 2024.docx (unknown)Open to both local and foreign suppliers. Foreign suppliers must truthfully complete the questionnaire regarding their presence and tax obligations in South Africa. Suppliers must confirm understanding and truthfulness of responses with signature, designation, date, and company details.
Compliance Requirements
Source: Annexure G - Tax Compliance Questionnaire for Foreign Suppliers (Manadatory for foreign suppliers to complete) - April 2024.docx (unknown)Submission Guidelines
Source: Supplier Declaration of Interest Template.docx (unknown)Submit the completed Supplier Declaration of Interest form as a mandatory returnable document with your tender. The declaration must be signed by an authorised signatory (member, director, partner, etc.) of the bidding entity. Eskom reserves the right to take action against the supplier or the signatory personally if the declaration is found to be false.
Evaluation Criteria
Source: Supplier Declaration of Interest Template.docx (unknown)General
Exclusions
Compliance Requirements
Source: Supplier Declaration of Interest Template.docx (unknown)Bidders must complete and submit a detailed Supplier Declaration of Interest form. The declaration requires disclosure of any relationships with Eskom employees or directors that could constitute a conflict of interest. Required disclosures include: - Whether any person with an interest in the supplier (shareholder, director, etc.) is employed by or is a director of Eskom. - Whether any such person is a close family member or associate of an Eskom employee/director involved in the procurement. - Awareness of any close family or associate relationships between the supplier's representatives and Eskom personnel involved in the process. - Any exchange of business courtesies (gifts, favours, hospitality) with Eskom employees/directors in the last 12 months. - If acting as a consultant, details of other services currently being rendered to Eskom or its related entities.
Submission Guidelines
Source: Declaration of Shareholding or Beneficiaries Form.pdf (unknown)To submit your tender, you must complete and return the Declaration of Shareholding or Beneficiaries form (Tender Schedule T2.2a No 8) as a returnable document. Ensure all required information is accurately provided and the form is signed by an authorized representative.
Returnable Documents
Source: Declaration of Shareholding or Beneficiaries Form.pdf (unknown)You must submit a Declaration of Shareholding or Beneficiaries form (Tender Schedule T2.2a No 8). The form requires full disclosure of all individual and company shareholders/beneficiaries in your organisation, the authorized representative's declaration, a yes/no declaration on whether any shareholders/beneficiaries are Eskom employees or their close family members, and if yes, details of the Eskom employee's position and the nature of the shareholder's interest. The form must be signed by the authorized representative with their designation and date.
Evaluation Criteria
Source: Declaration of Shareholding or Beneficiaries Form.pdf (unknown)Bidders will be evaluated based on their legal authorization to submit the tender, full disclosure of all shareholders/beneficiaries, and declaration of any potential conflicts of interest with Eskom employees. The declaration must be signed by an authorized representative with their designation and date.
Technical Specifications
Source: Declaration of Shareholding or Beneficiaries Form.pdf (unknown)The Declaration of Shareholding or Beneficiaries form requires: the name, registration number, and authorized representative of your company or trust; a list of all shareholders/beneficiaries and their share percentages; a declaration of whether any shareholders/beneficiaries are employed by or are close family members of Eskom employees; and if yes, details of the Eskom employee's position and the shareholder's interest.
Compliance Requirements
Source: Declaration of Shareholding or Beneficiaries Form.pdf (unknown)No specific compliance requirements were found beyond the submission of the Declaration of Shareholding or Beneficiaries form.
Description
Source: Eskom life-saving rules.pdfEvaluation Criteria
Source: Eskom life-saving rules.pdf (unknown)Technical Specifications
Source: Eskom life-saving rules.pdf (unknown)Compliance Requirements
Source: Eskom life-saving rules.pdf (unknown)Health & Safety
Source: Eskom life-saving rules.pdfSection
Source: Eskom life-saving rules.pdfDescription
Source: Annexure C - Tenderer_s Particulars.docxThe tenderer must furnish the following particulars where applicable:
Evaluation Criteria
Source: Annexure C - Tenderer_s Particulars.docx (unknown)The tender document (Annexure C) does not specify evaluation criteria or scoring methodology. It only indicates that registration on the National Treasury's Central Supplier Database (CSD) is mandatory prior to award, and that tax compliance must be verified via SARS E-filing or a valid tax compliance certificate. Subcontractors must be disclosed with B-BBEE level and designated group verification if subcontracting is intended.
Technical Specifications
Source: Annexure C - Tenderer_s Particulars.docx (unknown)The tenderer must furnish the following particulars where applicable:
Compliance Requirements
Source: Annexure C - Tenderer_s Particulars.docx (unknown)The tenderer must meet the following compliance requirements:
Description
Source: Tenderer - (SDLI) Strategy Setting - MV Motors.docxScope: Full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station over a 4-year period.
Contact Information
Source: Tenderer - (SDLI) Strategy Setting - MV Motors.docx (unknown)Business Unit: Arnot Power Station.
Buyer: Lebohang Malema.
Submission Guidelines
Source: Tenderer - (SDLI) Strategy Setting - MV Motors.docx (unknown)Required returnable documents:
Note: Failure to provide documentation for preference points will not disqualify the bidder but limits scoring to 80/90 for price and 0/20 for specific goals.
Evaluation Criteria
Source: Tenderer - (SDLI) Strategy Setting - MV Motors.docx (unknown)Scoring system:
B-BBEE preference points (90/10 system):
SDL&I commitments:
Technical Specifications
Source: Tenderer - (SDLI) Strategy Setting - MV Motors.docx (unknown)Scope of work:
Financial Requirements
Source: Tenderer - (SDLI) Strategy Setting - MV Motors.docx (unknown)Payment and penalties:
Reporting:
Compliance Requirements
Source: Tenderer - (SDLI) Strategy Setting - MV Motors.docx (unknown)B-bbee:
Local Content:
Subcontracting:
Sworn Affidavit Validity:
Description
Source: 3. Eskom Waste Management Standard 32-245.pdfEskom’s SHEQ Policy (Document 32-727, Revision 4) outlines the following commitments:
Evaluation Criteria
Source: 3. Eskom Waste Management Standard 32-245.pdf (unknown)Bidders must demonstrate the following SHEQ eligibility criteria to qualify:
Technical Specifications
Source: 3. Eskom Waste Management Standard 32-245.pdf (unknown)The tender document does not specify technical requirements for motor refurbishment. However, the following SHEQ-related technical and operational standards apply:
Methodology
Source: 3. Eskom Waste Management Standard 32-245.pdfKey SHEQ management roles and definitions:
Quality Management
Source: 3. Eskom Waste Management Standard 32-245.pdfEskom’s quality management approach is aligned with international standards:
Compliance Requirements
Source: 3. Eskom Waste Management Standard 32-245.pdf (unknown)The document does not specify bidder compliance requirements (e.g., CSD, tax, B-BBEE, CIDB). However, the following SHEQ compliance obligations are implied for contractors:
Health & Safety
Source: 3. Eskom Waste Management Standard 32-245.pdfEskom’s health and safety commitments include:
Environmental
Source: 3. Eskom Waste Management Standard 32-245.pdfEskom’s environmental commitments under its Zero Harm goal include:
Description
Source: 1. Form CPA - General.pdfThe tender involves the supply and delivery of plant and equipment, which may be fully or partly manufactured or supplied from locally held imported stocks. The scope includes cost components for manufacture, transport, and installation/erection.
Evaluation Criteria
Source: 1. Form CPA - General.pdf (unknown)Tenderers must be able to comply with the Contract Price Adjustment (CPA) framework. Eligibility requires the capability to track and claim adjustments using agreed indices and provide documentary evidence (e.g., proof of transport method) as required. Supplier or 'in-house' indices are not acceptable.
Technical Specifications
Source: 1. Form CPA - General.pdf (unknown)The tender is for the full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station for a period of 4 years. The scope includes supply and delivery of plant and equipment, which may be fully or partly manufactured or supplied from locally held imported stocks. Installation and commissioning may be applicable.
Pricing Schedule
Source: 1. Form CPA - General.pdfThe tenderer must specify:
Financial Requirements
Source: 1. Form CPA - General.pdf (unknown)Complete the Contract Price Adjustment (CPA) form. Key requirements:
Compliance Requirements
Source: 1. Form CPA - General.pdf (unknown)The tender/contract price shall remain fixed where the period between the closing date of tenders and the contractual completion date is less than one year.
Description
Source: Scope of work and Technical Evaluation Criteria for the Refurbishment of Medium Voltage Motors__Rev 4_Signed.pdfEvaluation Criteria
Source: Scope of work and Technical Evaluation Criteria for the Refurbishment of Medium Voltage Motors__Rev 4_Signed.pdf (unknown)Technical Specifications
Source: Scope of work and Technical Evaluation Criteria for the Refurbishment of Medium Voltage Motors__Rev 4_Signed.pdf (unknown)Quality Management
Source: Scope of work and Technical Evaluation Criteria for the Refurbishment of Medium Voltage Motors__Rev 4_Signed.pdfSection
Source: Scope of work and Technical Evaluation Criteria for the Refurbishment of Medium Voltage Motors__Rev 4_Signed.pdfDescription
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdfScope: Full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station for a period of 4 years. Work includes repair, testing, and delivery of MV motors (up to 5800 kW), with mandatory compliance to Eskom’s technical and quality standards. Suppliers must demonstrate capability for vertical and horizontal mount motors.
Important Dates
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdf (RFP)Closing date and time: 20 July 2026 at 10h00. Tender validity period: 120 days from closing date. Clarification queries must be emailed to [email protected] at least 5 working days before the tender submission deadline. No clarification meeting will be held.
Contact Information
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdf (RFP)Eskom Representative: Lebohang Malema. Email: [email protected]. Phone: 013 297 9875. Submission address: Eskom e-tendering site (TenderBulletin.eskom.co.za). Fraud/corruption reporting: 0800 11 2722 or [email protected].
Submission Guidelines
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdf (RFP)Submit tenders electronically via the Eskom e-tendering site (TenderBulletin.eskom.co.za) by the closing date and time. No hard copies or zipped files are accepted. Each document must be in PDF format (max 500MB per file, total submission max 4GB). The pricing schedule must also be submitted in Excel format. Ensure the submission status is marked as 'complete'. Late submissions will not be accepted. If resubmitting, only the latest version will be considered. Mandatory returnables must be uploaded under the folders: Technical, Commercial, Financial, and Other. Failure to submit mandatory documents by the deadline will result in disqualification.
Evaluation Criteria
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdf (RFP)Evaluation is based on a 90/10 system: 90 points for pricing and 10 points for Specific Goals (PPPFA). Functionality requirements are mandatory with a 75% threshold; failure to meet this threshold results in disqualification. Pricing evaluation includes VAT, arithmetic error corrections, and adjustments for acceptable variations. Unconditional discounts are considered for evaluation. Specific Goals scoring requires evidence submission; failure to submit evidence results in 0 points for that goal. Tenderers are ranked from highest to lowest combined score. Objective criteria may justify awarding to a tenderer other than the highest scorer. Local content thresholds for designated commodities (e.g., MV Motors: 70%, Casting/Frame Fabrication: 100%) must be met in full.
Technical Specifications
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdf (RFP)Scope: Full refurbishment, testing, and delivery of medium voltage motors at Arnot Power Station for 4 years. Mandatory technical criteria include familiarity with refurbishment and repair of power station electric motors. Proof of ISO 9001:2015 certification for rewinding and quality standards is required. Load testing capacity for 11kV motors up to 5800 kW is mandatory. Suppliers must submit a Draft Contract Quality Plan, Quality Control Plan (QCP/ITP), and evidence of QMS compliance (e.g., ISO 9001 certification, audit reports, management review records). Local content requirements apply to designated commodities (e.g., MV Motors: 70%, Casting/Frame Fabrication: 100%).
Experience & Qualifications
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdfMandatory experience: Proof of 5 years’ experience in repairing and testing medium voltage induction motors (vertical and horizontal mount, up to 5800 kW). Required personnel: CVs for 3 motor winders (5% weight). Proof of transport capacity (up to 50 tons) or a service agreement with transport insurance (5% weight). Load testing capacity for 11kV motors up to 5800 kW is mandatory (30% weight).
Quality Management
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdfQuality Management System (QMS) requirements: Option 1: Valid ISO 9001 certification (4 points) with defined product/service scope, approved authority, international accreditation, and valid expiry date. Option 2: Documented QMS complying with ISO 9001 (0 points if not certified). Evidence of QMS in operation includes: organization chart, responsibility matrix, external provider control criteria, internal audit reports, certification audit reports (≤12 months old), and management review records. Draft Contract Quality Plan and Quality Control Plan (QCP/ITP) are mandatory. Compliance with ISO 9001:2015 for rewinding and certification is required.
Pricing Schedule
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdfPricing schedule must be completed and submitted in PDF and Excel format. Pricing is evaluated inclusive of VAT, corrected for arithmetic errors, and adjusted for acceptable variations. Unconditional discounts are considered for evaluation; conditional discounts are applied at payment. Pricing is scored out of 90 points. Bill of Quantities (BOQ) or activity schedules must exclude contingencies. Net Present Value (NPV) comparisons may be used for evaluation.
Financial Requirements
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdf (RFP)Payment terms: For contracts below R50,000,000 (incl. VAT), payment within 30 days of undisputed invoices. For contracts above R50,000,000 (incl. VAT), payment within 60 days. Pricing must be inclusive of VAT and exclude contingencies. Submit a completed pricing schedule in PDF and Excel format. Financial statements (audited or reviewed) are mandatory for contractual requirements. Annual financial statements must include: background, director’s report, auditor’s report, financial position, comprehensive income, equity changes, cash flows, and notes. Public Interest Score (for non-audited SA entities) and ITA34C copies (current & previous years) are required.
Compliance Requirements
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdf (RFP)Mandatory compliance: CSD registration (CSD number/report). Tax clearance certificate required for local tenderers and foreign tenderers with a SA footprint (SARS PIN verification). Foreign suppliers without a SA footprint must complete SBD1 but are exempt from tax compliance proof. B-BBEE status certificate or sworn affidavit is required. CIDB grading proof (if applicable) must be submitted at tender closing or within 21 working days. Employment Equity compliance proof (for designated employers) and COIDA certificate (for SA tenderers) are mandatory. Integrity Declaration Form (Annexure D) and Supplier Integrity Pact acknowledgment are required. SBD forms (SBD 1, SBD 4, SBD 6.1, SBD 6.2) must be completed and submitted. Joint ventures must provide a valid JV agreement and designated bank account details.
Health & Safety
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdfSHEQ compliance is mandatory. Suppliers must comply with: Occupational Health and Safety Act, Eskom SHEQ Policy (32-727), Emergency Preparedness Procedure, Eskom lifesaving rules, OHRVS regulations, PSR, working at height standards, lifting machinery regulations, Electrical Machinery/Installations requirements, Contractor Management Procedure, and Housekeeping standards. Required SHE returnables: Annexure B (SHE rules acknowledgment), Health and Safety Plan, health and safety costing (itemized), baseline OHS risk assessment, valid COIDA certificate (SA tenderers), letter of good standing, medical surveillance program, signed OHS policy, and proof of OHS competencies (e.g., electrical installer accreditation). Arnot Power Station’s Safety File approval is required before work commencement.
Environmental
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdfNo Environmental Impact Assessment (EIA) is required for this scope. Suppliers must comply with Eskom’s environmental policies and any applicable regulations as part of the SHEQ requirements.
Contractual Terms
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdfContract terms: NEC3 Term Service Contract applies. Payment terms: 30 days for contracts ≤ R50M (incl. VAT), 60 days for contracts > R50M (incl. VAT). Tender validity period: 120 days from closing date. Eskom reserves the right to negotiate with preferred bidders if prices are not market-related. Subcontracting with subsidiaries must be declared. Contractual requirements (e.g., SHEQ, financial viability) are assessed post-evaluation and must be met prior to award.
Section
Source: Invitation to Tender (ITT) MV Motors Rev. 28 - 21 April 2026.pdfFunctionality criteria (100% weight, 75% threshold) must be met to avoid disqualification. Pricing is scored out of 90 points, and Specific Goals (PPPFA) out of 10 points. Local content thresholds for designated commodities (e.g., MV Motors: 70%, Casting/Frame Fabrication: 100%) are mandatory. Failure to submit Specific Goals evidence results in 0 points for that goal but not disqualification. Ranking uses the 90/10 preferential point system. Objective criteria may override highest score for award.
Submission Guidelines
Source: Annexure B – Supplier Tender Receiving Acknowledgement Form..docx (unknown)This document is Annexure B (Supplier Tender Receiving Acknowledgement Form) and does not contain full submission guidelines. Key points from this form:
Evaluation Criteria
Source: Annexure B – Supplier Tender Receiving Acknowledgement Form..docx (unknown)No evaluation criteria are provided in this document. The form only confirms receipt and cataloguing obligations. Specific scoring methods, thresholds, or preference points are not detailed here. Refer to the main tender document for evaluation criteria.
Technical Specifications
Source: Annexure B – Supplier Tender Receiving Acknowledgement Form..docx (unknown)This document is an acknowledgement form and does not contain technical specifications. Scope, deliverables, standards, capacity requirements, or service levels for motor refurbishment are not included. Refer to the main tender document for technical details.
Compliance Requirements
Source: Annexure B – Supplier Tender Receiving Acknowledgement Form..docx (unknown)No compliance requirements are stated in this document. CSD, tax clearance, B-BBEE, CIDB, CIPC, professional registrations, or local content requirements are not mentioned. Refer to the main tender document for compliance obligations.
Submission Guidelines
Source: Annexure H - SBD 1 - Part A - Invitation to Bid and Part B - Terms and Conditions for Bidding.docx (unknown)Evaluation Criteria
Source: Annexure H - SBD 1 - Part A - Invitation to Bid and Part B - Terms and Conditions for Bidding.docx (unknown)Compliance Requirements
Source: Annexure H - SBD 1 - Part A - Invitation to Bid and Part B - Terms and Conditions for Bidding.docx (unknown)Description
Source: E-Tendering Help Manual for supplier.pdfContact Information
Source: E-Tendering Help Manual for supplier.pdf (TENDER)Submission Guidelines
Source: E-Tendering Help Manual for supplier.pdf (TENDER)Returnable Documents
Source: E-Tendering Help Manual for supplier.pdf (TENDER)Evaluation Criteria
Source: E-Tendering Help Manual for supplier.pdf (TENDER)Technical Specifications
Source: E-Tendering Help Manual for supplier.pdf (TENDER)Compliance Requirements
Source: E-Tendering Help Manual for supplier.pdf (TENDER)Requirements
Source: E-Tendering Help Manual for supplier.pdf (TENDER)Section
Source: E-Tendering Help Manual for supplier.pdfDescription
Source: Eskom Vehicle Safety Spec 32-345.pdfThis is Eskom's Vehicle Safety Specification document (32-345). Its purpose is to standardise vehicle safety specifications across Eskom and its contractors to comply with legislative and internal Eskom requirements. It applies throughout Eskom Holdings SOC Ltd, its divisions, subsidiaries, and any entity where Eskom has a controlling interest (including contractors). The document provides the minimum vehicle-related specifications that must be adhered to.
Contact Information
Source: Eskom Vehicle Safety Spec 32-345.pdf (unknown)The document lists the following groups and individuals as having accepted or contributed to the specification:
No direct contact details (email, phone, address) are provided for tender enquiries.
Evaluation Criteria
Source: Eskom Vehicle Safety Spec 32-345.pdf (unknown)The document does not define tender evaluation criteria. It references SANS 9001 as an informative standard only.
Technical Specifications
Source: Eskom Vehicle Safety Spec 32-345.pdf (unknown)This is Eskom's Vehicle Safety Specification (Document 32-345, Rev 5). It sets minimum safety standards for all vehicles used for Eskom business, including contractor vehicles.
Key requirements for bidders:
Methodology
Source: Eskom Vehicle Safety Spec 32-345.pdfFor implementation: Newly purchased vehicles and new contracts must comply immediately. Existing vehicles in the business will follow a phased replacement approach according to the Fleet Services Department's plan. Scheme and non-Eskom vehicles must comply when being replaced.
Compliance Requirements
Source: Eskom Vehicle Safety Spec 32-345.pdf (unknown)The specification mandates compliance with several legislative and Eskom standards, but does not list typical tender compliance documents (e.g., CSD, tax, B-BBEE).
Key referenced standards and acts:
Bidders must ensure all vehicles used for Eskom work meet these safety specifications and legislative requirements.
Health & Safety
Source: Eskom Vehicle Safety Spec 32-345.pdfThis is a comprehensive vehicle safety specification document. It mandates compliance with:
It details minimum safety specifications for all vehicle types (light vehicles, heavy commercial vehicles, minibuses, buses, construction vehicles, trailers) used for Eskom business. Key requirements include factory-fitted safety features (ABS, airbags), specific equipment (warning triangles, reflective tape, warning signs), and monitoring devices (VMDs, driver cameras). The purpose is to standardise safety specifications to protect Eskom employees, contractors, and the public.
Requirements
Source: Eskom Vehicle Safety Spec 32-345.pdf (unknown)The document is a compendium of vehicle safety requirements. Bidders must consult the full specification, but key points include:
Section
Source: Eskom Vehicle Safety Spec 32-345.pdfThe document references SANS 9001 Quality Management Systems as an informative standard, but does not define tender evaluation criteria.
Description
Source: SHE SPEC.pdfThis OHS specification lists the legislative and Eskom requirements that must be met by the contractor for the duration of the contract. The contractor is expected to develop an OHS plan that meets these requirements and all relevant applicable legislation. This document reflects minimum requirements and should not be construed as all-encompassing.
Evaluation Criteria
Source: SHE SPEC.pdf (unknown)Key eligibility is demonstrated through OHS compliance capability. Applicants must prove:
Technical Specifications
Source: SHE SPEC.pdf (unknown)The contract is for full refurbishment, testing, and delivery of Medium Voltage motors (185kW to 5800kW) at Arnot Power Station for a 60-month period.
Experience & Qualifications
Source: SHE SPEC.pdfThe main contractor and appointed contractors must have appropriate qualifications, certificates, and employees should always be under competent supervision.
Quality Management
Source: SHE SPEC.pdfQuality management is implied through requirements for tool and equipment inspections, record-keeping, and adherence to standards. Specific quality requirements are not detailed in this OHS document.
Compliance Requirements
Source: SHE SPEC.pdf (unknown)No specific requirements found
B-BBEE Minimum Level: 2
Health & Safety
Source: SHE SPEC.pdfThis is the primary focus of the document. Key requirements include:
Environmental
Source: SHE SPEC.pdfThe contractor must comply with environmental legislation, including the National Environmental Management Act. Waste must be disposed of promptly and stored temporarily in designated areas.
Contractual Terms
Source: SHE SPEC.pdfThe document includes sections on risk assessment, safe work procedures, fire equipment, flammable liquids, first aid, OHS communication, toolbox talks, and OHS training. These are contractual requirements for the duration of the project.
Section
Source: SHE SPEC.pdfThe OHS department will issue the Section 37(2) agreement to the project manager/end user who will facilitate signing by Eskom and contractor representatives. The contractor must be accountable for the quality and execution of their health and safety programme.
Important Dates
Source: Eskom General Conditions of Purchase - 31 May 2024.pdf (unknown)Closing date: 31 May 2024. No other dates (briefings, site visits, clarifications) are specified in the extracted document.
Contact Information
Source: Eskom General Conditions of Purchase - 31 May 2024.pdf (unknown)Email for fraud/corruption reporting: [email protected]. No SCM or technical contact details, phone numbers, or submission addresses are provided.
Submission Guidelines
Source: Eskom General Conditions of Purchase - 31 May 2024.pdf (unknown)Returnable documents are not specified in this document. Refer to the specific tender invitation or specification documents for submission details, required forms, and disqualification risks.
Evaluation Criteria
Source: Eskom General Conditions of Purchase - 31 May 2024.pdf (unknown)This document does not specify evaluation criteria. It is the general conditions of purchase. Evaluation criteria would be in the invitation to tender or specification documents.
Technical Specifications
Source: Eskom General Conditions of Purchase - 31 May 2024.pdf (unknown)Scope: Supply goods or execute works/services as described in the agreement. The agreement includes order documents, General Conditions of Purchase, specifications, schedules, and drawings approved by Eskom. Rejection: Eskom may reject goods if Supplier fails obligations, requiring replacement or re-work. For delivered goods, Eskom may return rejected goods at Supplier's risk and expense, with cost recovery. For works/services, Supplier must correct defects as indicated.
Pricing Schedule
Source: Eskom General Conditions of Purchase - 31 May 2024.pdfPrices or rates may include a price adjustment calculated per formula in the agreement.
Financial Requirements
Source: Eskom General Conditions of Purchase - 31 May 2024.pdf (unknown)Pricing and payment: Prices may include a price adjustment calculated per formula in the agreement. Payment can be in any currency, converted to ZAR at a single exchange rate. Eskom's CPA (IG) form must be completed. Payment within 30 days after receipt of a correct tax invoice. Eskom's VAT number (4740101508) must appear on the invoice.
Compliance Requirements
Source: Eskom General Conditions of Purchase - 31 May 2024.pdf (unknown)Statutory requirements: Supplier must adhere to all statutory requirements relevant to the agreement, governed by RSA law. No specific mention of CSD, tax, B-BBEE, CIDB, CIPC, or professional registrations.
Health & Safety
Source: Eskom General Conditions of Purchase - 31 May 2024.pdfDelivery means compliance at specified point/site by agreed date. Late delivery/completion may incur penalties. No payment if goods/services not provided as stated. Packaging and documentation requirements: Mark consignments with Supplier name and destination details, include packing note. Send advice note with transport details, weight, volume, dispatch point/date to Eskom. Send detailed tax invoice after delivery/completion. State agreement number on all communications. State if delivery cost included in price (deemed included if not stated). No payment for containers/packing unless otherwise stated. Acceptance subject to Eskom inspection/testing at any stage.
Contractual Terms
Source: Eskom General Conditions of Purchase - 31 May 2024.pdfThe agreement consists of order documents, General Conditions of Purchase, specifications, schedules, and drawings approved by Eskom. These conditions form the contract basis and are deemed accepted unless non-acceptance is indicated. No oral variations are allowed. Risk passes to Eskom upon proof of delivery and acceptance. Ownership passes upon payment or as otherwise stated. Entire agreement clause: No additions or variations are valid unless in writing and signed by both parties. Indemnity against negligence, infringement, defects. Warranty of fitness for purpose and defect-free for one year (unless otherwise stated). Assignment/subcontracting requires written consent. Statutory compliance required under RSA law. Breach and termination rights specified. Ethics commitment expected.
Submission Guidelines
Source: E-Tenderers E-Tendering Training Acknowledgement Form.pdf (unknown)Mandatory returnable: Fully complete and submit the E-Tendering Training Acknowledgement Form to Eskom within the prescribed period. Failure to do so will disqualify the bidder from the procurement process. The form must include: Business name/JV, contact person, landline, cellphone, email address, acknowledgment statement, authorized signature, designation, and date.
Returnable Documents
Source: E-Tenderers E-Tendering Training Acknowledgement Form.pdf (unknown)Mandatory returnable: E-Tendering Training Acknowledgement Form. Must include: Business name/JV, contact person, landline, cellphone, email address, acknowledgment statement, authorized signature, designation, and date.
Evaluation Criteria
Source: E-Tenderers E-Tendering Training Acknowledgement Form.pdf (unknown)All tenderers must be registered on Eskom's e-tendering system and complete mandatory e-tendering training. The form must be fully completed and submitted within prescribed period. Joint ventures must specify business structure.
Compliance Requirements
Source: E-Tenderers E-Tendering Training Acknowledgement Form.pdf (unknown)Self-training requirement: Bidder must acknowledge completion of e-Tendering training via the Noddy Guide, video, or clarification meeting. Non-compliance with this requirement will result in disqualification. Failure to fully complete and submit the E-Tendering Training Acknowledgement Form to Eskom within the prescribed period will render the bidder non-responsive and disqualified.
Description
Source: Annexure G1-G4 - SBD 6.2 - Declaration Certificate for Local Production and Content for Designated Sectors - 14 March 2025.docxSubmission Guidelines
Source: Annexure G1-G4 - SBD 6.2 - Declaration Certificate for Local Production and Content for Designated Sectors - 14 March 2025.docx (unknown)Evaluation Criteria
Source: Annexure G1-G4 - SBD 6.2 - Declaration Certificate for Local Production and Content for Designated Sectors - 14 March 2025.docx (unknown)Compliance Requirements
Source: Annexure G1-G4 - SBD 6.2 - Declaration Certificate for Local Production and Content for Designated Sectors - 14 March 2025.docx (unknown)Submission Guidelines
Source: 2. B-BBEE_sworn Affidavit-Qualifying Smal Enterprise.pdf (unknown)To submit, bidders must complete and return a sworn affidavit for B-BBEE Qualifying Small Enterprise. The affidavit must be signed and dated, and must include the required declarations and information.
Returnable Documents
Source: 2. B-BBEE_sworn Affidavit-Qualifying Smal Enterprise.pdf (unknown)The deponent must declare understanding of the affidavit contents and consent to the oath. The sworn affidavit is valid for 12 months from the date signed by the commissioner.
Evaluation Criteria
Source: 2. B-BBEE_sworn Affidavit-Qualifying Smal Enterprise.pdf (unknown)The evaluation criteria include the enterprise's B-BBEE level, with a minimum requirement of Level Two (at least 51% black owned) or Level One (100% black owned). The enterprise must also meet the definition of 'Black People' and 'Black Designated Groups' as defined in the Broad-Based Black Economic Empowerment Act.
Compliance Requirements
Source: 2. B-BBEE_sworn Affidavit-Qualifying Smal Enterprise.pdf (unknown)The compliance requirements include: B-BBEE Minimum Level: One; completion of a sworn affidavit declaring B-BBEE status as a Qualifying Small Enterprise; declaration of percentage Black Owned, percentage Black Female Owned, and percentage Black Designated Group Owned; provision of Black Designated Group breakdown percentages; and indication of B-BBEE level contributor.
B-BBEE Requirements
Source: 2. B-BBEE_sworn Affidavit-Qualifying Smal Enterprise.pdf (unknown)The definition of 'Black People' includes Africans, Coloureds, and Indians who are South African citizens by birth, descent, or naturalisation. The definition of 'Black Designated Groups' includes unemployed black people, black youth, black persons with disabilities, black people living in rural/underdeveloped areas, and black military veterans.
Requirements
Source: 2. B-BBEE_sworn Affidavit-Qualifying Smal Enterprise.pdf (unknown)The enterprise must have annual total revenue between R10,000,000.00 and R50,000,000.00 based on the latest financial year-end.
Description
Source: Annexure F - CPA (IG) Requirements for Foreign Goods and Services.docxSubmission Guidelines
Source: Annexure F - CPA (IG) Requirements for Foreign Goods and Services.docx (unknown)Evaluation Criteria
Source: Annexure F - CPA (IG) Requirements for Foreign Goods and Services.docx (unknown)Technical Specifications
Source: Annexure F - CPA (IG) Requirements for Foreign Goods and Services.docx (unknown)Financial Requirements
Source: Annexure F - CPA (IG) Requirements for Foreign Goods and Services.docx (unknown)Description
Source: Annexure I - SBD 6.1 Preference Points Claim Form in terms of The PPR 2022.docxThis document is the SBD 6.1 Preference Points Claim Form, a mandatory component of all tenders under the Preferential Procurement Regulations 2022. It provides general information and serves as the official claim form for preference points tied to specific goals.
Submission Guidelines
Source: Annexure I - SBD 6.1 Preference Points Claim Form in terms of The PPR 2022.docx (unknown)Submit the completed SBD 6.1 Preference Points Claim Form as part of your tender. This form is mandatory and must accompany all tender submissions.
Evaluation Criteria
Source: Annexure I - SBD 6.1 Preference Points Claim Form in terms of The PPR 2022.docx (unknown)Evaluation is open to all legal business structures, including: partnerships, joint ventures, close corporations, public companies, (Pty) Ltd companies, trusts, non-profit companies, and state-owned companies. Scoring follows the Preferential Procurement Regulations 2022. Points are awarded for: Price (80 or 90 points, depending on tender value) and Specific Goals (20 or 10 points). The applicable system (80/20 or 90/10) will be determined by the lowest/highest acceptable tender once submissions are received. Failure to submit required proof/documentation for specific goals will result in zero preference points for those goals.
Compliance Requirements
Source: Annexure I - SBD 6.1 Preference Points Claim Form in terms of The PPR 2022.docx (unknown)Mandatory compliance requirements: Submit the SBD 6.1 Preference Points Claim Form with your tender. Study the General Conditions, Definitions, and Directives of the Preferential Procurement Regulations 2022 before completing the form. The organ of state may require substantiation of preference claims at any time. Fraudulent claims or non-compliance may lead to: disqualification from the tender process, recovery of costs/losses/damages by the organ of state, contract cancellation, restriction from obtaining state business for up to 10 years, and criminal prosecution.
Description
Source: Annexure J - SBD 4 - Tenderer_s Disclosure.docxSubmission Guidelines
Source: Annexure J - SBD 4 - Tenderer_s Disclosure.docx (unknown)Please submit your tender to Eskom, complete the SBD 4 (Tenderer’s Disclosure) form, and declare any state employment, relationships with Eskom employees, and independent bidding status.
Evaluation Criteria
Source: Annexure J - SBD 4 - Tenderer_s Disclosure.docx (unknown)Tenderers must not be listed on the Register for Tender Defaulters or List of Restricted Suppliers. Must declare any state employment of directors/trustees/shareholders. Must disclose any relationships with Eskom employees. Must confirm independent bidding without collusion. Must certify all information as true under penalty of disqualification, investigation by Competition Commission/NPA, and potential blacklisting.
Compliance Requirements
Source: Annexure J - SBD 4 - Tenderer_s Disclosure.docx (unknown)Description
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Type of Invitation to Tender 1.4 An open Invitation to Tender will be advertised on Eskom’s Tender Bulletin and National Treasury (NT) e-Tender Portal and in any other media if so required. A closed Invitation to Tender, also known as procurement from multiple sources, will be sent directly to specific tenderers that Eskom has identified. A sole source and a single source are regarded as a tenderer that meets the requirements stated in the Eskom Procurement and Supply Chain Management Procedure 32-1034. Any addenda to an issued Invitation to Tender will be published or issued in the same way as the Invitation to Tender was and will form part of the Invitation to Tender documents.
Important Dates
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER){"closingTime":"2.2","briefingSession":"{"date":null,"time":null,"venue":"tend a site visit and/or clarification meeting that is stipulated as being","is_compulsory":true}"}
Contact Information
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER){"name":null,"email":null,"phone":null,"department":"Supply Chain Management","address":"g time 2.2 Ensure that Eskom has received the complete original tender and one (1) complete hard"}
Submission Guidelines
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)The document outlines standard Eskom tender submission rules. Key points:
Returnable Documents
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Tender closing time 2.2 Ensure that Eskom has received the complete original tender and one (1) complete hard copy of the original tender at the address and in the tender box or e-mail address specified in the Tender Data by no later than the closing date and time for tender submission. Proof of posting or of courier delivery does not equate to proof of delivery. Eskom will not accept a tender submitted by e-mail unless stated otherwise in the Tender Data. For E-tendering the tenderer must upload and finalize the tender via Eskom Tender bulletin site on the Eskom E- tendering page by no later than the closing date and time for tender submission. It remains the sole responsibility of the tenderer to ensure that the documents (PDF/Excel) are submitted and accessible for downloading/evaluation without any challenges as well as they are not corrupt or unreadable. It is the tenderer’s responsibility to ensure that their tenders documents are submitted/uploaded, and the submission is finalised before the closing date and time For E-tendering tenderers are not permitted to deposit a tender into the Eskom tender box only electronic submission via the Eskom Tender bulletin site on the Eskom E- tendering page will be accepted.
Evaluation Criteria
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Tenderer must meet eligibility criteria stated in the Tender Data, not be restricted from doing business with Eskom or State-Owned Companies, and cannot subcontract 100% of the work. Proof of B-BBEE status (certificate/affidavit/CSD report) is required. Where CIDB grading is stipulated, registration or proof of application is mandatory. Tenderers may be disqualified for misrepresentation, fronting, or fraudulent B-BBEE documentation.
Technical Specifications
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Supply Chain
Management Procedure 32-1034. Any addenda to an issued Invitation to Tender will be
published or issued in the same way as the Invitation to Tender was and will form part of the
Invitation to Tender documents.
Communication 1.5 Every communication between Eskom and a tenderer shall be made to or from the Eskom
Representative only, in w
Quality Management
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdfof a tenderer.
Cost of tendering 2.6 Accept that Eskom will not compensate the tenderer for any costs incurred in the preparation
and submission of a tender, including the costs of any testing necessary to demonstrate that
aspects of the tender satisfy the evaluation criteria, or the negotiation of any contract.
Submitting a tender 2.7 Check the Invitation to Tender documents on receipt and notify the Eskom representative of
any discrepancy or omitted documents. The Acknowledgement Form must be completed
and submitted with the tender and must clearly state if the tender is for the whole or part of
the works, services or supply identified in the specification and/or works information by
Pricing Schedule
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdfreasonable time for tenderers to make consequential adjustments to their tenders before
the closing date and time for submission.
In writing’ means hand-written, typed, type-written, printed or electronically made, and that
results in a permanent record.
Insurance 2.17 The extent (if any) of insurance provided by Eskom may not be for the full cover required in
the conditions of contract. The tenderer is advised to seek qualified advice regarding
insurance.
Pricing the tender 2.18 Include in the rates, prices, and the tendered total of the Prices all duties, taxes (including
VAT), and other levies payable by the tenderer if successful. Such duties, taxes and levies
are those applicable 14 (fourteen) days prior to the closing date and time for tender
submission.
2.19 Provide rates and Prices that are fixed for the duration of the contract and are not subject to
contract price adjustment except as provided for in the Invitation to Tender.
2.20 State the rates and Prices in South African Rand unless instructed otherwise in the Invitation
to Tender. The selected conditions of contract may provide for part payment in other
currencies. Therefore, submit Rates/Prices in Rands in accordance with the exchange rate
and base date as stipulated in the Invitation to tender.
Alterations to 2.21 May not make any alterations or additions to the tender documents, other than for purposes
documents of complying with instructions issued by the Eskom Representative or if necessary to correct
errors made by the tenderer. All such alterations shall be initialed by all signatories to the
tender. Corrections may not be made using correction fluid, correction tape or the like.
Alternative tenders 2.22 Submit alternative tenders only if a main tender is also submitted, and only if the submission
of alternative tenders is permitted by the Invitation to Tender. Accept that an alternative
tender may be based only on the criteria stated in the Tender Data.
Clarification and 2.23 Provide clarification and documents as may be required by the Eskom Representative
correction of Prices during the evaluation of tenders. However, documents identified as mandatory tender
after tender returnables that are required to be submitted at the closing date and time for tender
submission submission will not be requested and may not be submitted after the closing date and time.
phases, as this is regarded as ‘double dipping’.
Designated 3.12 Tenderers are also required to submit information on designated material and
materials and thresholds no later than contract award. If this information is not completed and
thresholds submitted as indicated in the Invitation to Tender, your tender will not be considered for
contract award
Functionality 3.13 If functionality is a criterion, tenderers will be scored against the functionality criteria and
requirements will be required meet the minimum threshold stated in the Tender Data to proceed to
further evaluation.
Financial analysis 3.14 Eskom has to determine the risk of doing business with a supplier who may pose a
(if applicable) financial risk to Eskom in the execution of the contract. During evaluation of a tenderer’s
financial statements, Eskom will attempt to identify mitigating factors or requirements for
the tenderer to meet, if such factors/requirements exist in the tender’s context. However,
should suitable mitigating factors not exist in the tender’s context or should mitigating
factors exist but be insufficient or if the risk is considered to be too high or should the
tenderer not agree with the mitigating factors, the tenderer will not be considered for
award.
Evaluation of Price 3.15 Evaluate the Price in accordance with the criteria/requirements in the Tender Data. Factors
such as CPA, FOREX, commodity exposure, unconditional discounts, technical
adjustment, PV and forecasted rates of invoicing are taken into account when determining
the evaluation Price.
Arithmetical errors 3.16 Check responsive tenders for arithmetical errors. If there is a discrepancy between an
amount in figures and the amount in words, the amount in words shall prevail.
Check the highest-ranked tenders for the following errors or omissions: -
(a) the misplacement of the decimal point in any unit rate; or
(b) omissions in completing the pricing schedule or bill of quantities, or
(c) arithmetical errors in line-item totals that are the result of the incorrect multiplication
of a unit rate and a quantity in a bill of quantities or schedule of prices; or
(d) arithmetical errors that are the result of the incorrect addition of the prices.
will request the tenderer to either confirm the prices as tendered or to accept the
corrected prices.
Where the tenderer elects to confirm the prices as tendered; Eskom will correct the error
as follows: -
(a) If a bill of quantities or pricing schedule applies and there is an error in the line-item
total that is the result of an error in multiplying the unit rate and the quantity, the line-
item total shall prevail, and the rate shall be corrected.
(b) Where there is a misplacement of the decimal point in the unit rate, the line-item total
as quoted shall prevail, and the unit rate shall be corrected.
(c) Where there is an error in the total of the prices that is the result either of other
corrections required by the checking process or in the tenderer’s addition of prices,
the total of the prices shall prevail, and the tenderer shall be asked to revise the
selected item prices (and their rates if a bill of quantities applies) to result in the
tendered total of the prices.
documentation by closing date and time of tender submission, the tenderer will not be
disqualified if otherwise evaluated as acceptable in all other criteria; however, the tenderer
will score zero points for Specific Goals within the 90/10 or 80/20 allocation of points.
Ranking of tenders 3.19 According to the PPPFA, Eskom will add the score for Pricing and the Specific Goals
together and rank the suppliers from the highest to the lowest.
Objective criteria 3.20 A contract may be awarded to a tenderer that did not score the highest points only in
accordance with Section 2(1) (f) of the Preferential Procurement Policy Framework Act,
must stipulate the Objective Criteria in the Invitation to Tender. Functionality and any
element of the B-BBEE scorecard may not be used as Objective Criteria.
Compliance Requirements
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)CSD report or as per certificate/affidavit provided
CSD number/CSD report) must be provided at the closing date and time for
CSD number or B-BBEE certificate/affidavit will need to be
B-BBEE Details: kom Representative and
Agreement to sign the contract documents.
Proof of authority 2.25 Where an agent submits a tender on behalf of a principal, an authenticated copy of the
to act as agent authority to act as an agent of the tenderer must be submitted as a tender returnable.
Compliance with 2.26 Comply with relevant legislation and regulatory instruments such as Instruction Notes issued
relevant legislation by National Treasury, CIDB Regulations for construction works; materials designated for local
(NT instructions, content and/or production by the dtic, PPPFA Regulations; Amended B-BBEE Codes, COIDA;
CIDB, PPPFA etc) OHS Act; Eskom’s requirements for Safety, Health, Environment and Quality (SHEQ) and any other
applicable legislation or regulatory instruments indicated in the Invitation to Tender.
Proof of Safety, 2.27 Tenderers are required to provide proof to the satisfaction of Eskom that safety, health,
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
Environment and closing date and time for tender submission stipulated in the Invitation to Tender and/or
Quality Contract Award. All costs and personnel associated with SHEQ must be reflected in the
requirements tender.
CIDB 2.28 Where the Tender Data has stipulated CIDB grading/s as a qualification criterion, tenderers
are required to be registered with the Construction Industry Development Board at the
closing date and time for submission of tenders or to be capable of being so registered
within twenty-one (21) working days from the closing date and time for submission of
tenders.
Where CIDB is applicable; proof of registration on CIDB is mandatory at the closing date
and time for tender submission. Should this not be received as stipulated
Health & Safety
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdftenderers that Eskom has identified. A sole source and a single source are regarded as a
tenderer that meets the requirements stated in the Eskom Procurement and Supply Chain
Management Procedure 32-1034. Any addenda to an issued Invitation to Tender will be
published or issued in the same way as the Invitation to Tender was and will form part of the
Proof of authority 2.25 Where an agent submits a tender on behalf of a principal, an authenticated copy of the
to act as agent authority to act as an agent of the tenderer must be submitted as a tender returnable.
Compliance with 2.26 Comply with relevant legislation and regulatory instruments such as Instruction Notes issued
relevant legislation by National Treasury, CIDB Regulations for construction works; materials designated for local
(NT instructions, content and/or production by the dtic, PPPFA Regulations; Amended B-BBEE Codes, COIDA;
CIDB, PPPFA etc) OHS Act; Eskom’s requirements for Safety, Health, Environment and Quality (SHEQ) and any other
applicable legislation or regulatory instruments indicated in the Invitation to Tender.
Proof of Safety, 2.27 Tenderers are required to provide proof to the satisfaction of Eskom that safety, health,
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
requirements tender.
CIDB 2.28 Where the Tender Data has stipulated CIDB grading/s as a qualification criterion, tenderers
are required to be registered with the Construction Industry Development Board at the
closing date and time for submission of tenders or to be capable of being so registered
within twenty-one (21) working days from the closing date and time for submission of
tenders.
Where CIDB is applicable; proof of registration on CIDB is mandatory at the closing date
and time for tender submission. Should this not be received as stipulated in the Invitation to
Tender; the tender will be disqualified. However, in the event that, at the closing date and
time for tender submission, only proof of application for registration on CIDB is available,
then this must be submitted by the closing date and time for tender submission, while the
actual proof of CIDB registration (printout from CIDB database) must be submitted by
contract award
Contract Skills 2.29 If the tenderer is awarded a contract, it, as Contractor, shall achieve in the performance of
Development Goal the contract the Contract Skills Development Goals (CSDG) established in the CIDB
(CSDG) Standard for Developing Skills through Infrastructure Contract (published in GN 1779,
Government Gazette No. April 2023)
that has a duration of 12 months or more, and to:
a contract of R5 million or more, in the case of a professional service or service contract
or an order issued in terms of such a contract; or
a CIDB grading designation of grade 7 or higher, in case of an engineering and
construction works, or design and build contract or an order issued in terms of such a
contract.
Contract 2.30 The Contractor shall achieve in the performance of the contract the Contract Participation
Participation Goals Goals (CPG) relating to the engagement of targeted enterprises as established in the CIDB
(CPG) standard for indirect targeting for enterprise development through Construction works
contracts (published in Government Gazette No. February 2013).
enterprises as established in the aforesaid standard applies to:
construction works contracts in the General Building (GB) and to Civil Engineering (CE)
classes of construction works;
construction works contracts of an estimated minimum project duration of 6 months; and
construction works contracts in which at least 25% of the main contract could reasonably
be expected to be subcontracted out in one or more of the following CIDB classes of
construction works:
Civil Engineering (CE)
Electrical Engineering Work (EB)
) General Building Works (GB)
) Mechanical Engineering (ME)
2.31 Eskom may disqualify a tender if it is found that the tenderer has misrepresented or
falsified any information, certificate, affidavit or document. Eskom will report any fraud
in relation to a tenderer’s B-BBEE certificate/affidavit, or evidence of ‘fronting’ as
defined in the B-BBEE Act , as amended, to the B-BBEE Commission. The
tenderer will be suspended from business with any State-Owned Company for up to 10
years and may even be sentenced to jail.
2.32 Tenderers are also required to complete fully and submit the SDL&I Undertaking
(annexure to the Invitation to Tender) by no later than contract award. If the SDL&I
Respond 3.1 Respond to a request for clarification that Eskom receives before the closing date for
clarification clarification or queries. Eskom’s responses will be published to all tenderers in the same
manner the Invitation to Tender documents were issued. It is the tenderers’ responsibility
to check the Eskom Tender Bulletin and NT e-Tender Portal regularly for updated
responses to clarifications.
Issue Addenda 3.2 If necessary and prior to the closing date and time for tender submission, amend, amplify, or
add to the Invitation to Tender documents by way of Addenda published in the same
platform that the Invitation to Tender was issued. It is the tenderers’ responsibility to
check the Eskom Tender Bulletin and NT e-Tender Portal regularly for Addenda.
electronically. The Eskom Representative will publish the names of all tenderers received
on the Eskom Tender Bulletin and NT e-Tender Portal.
Tender Prices 3.5 Eskom will announce the names of the tenderers. Prices may be announced if so, stated
in the Tender Data.
Non-disclosure 3.6 Unless required by law, Eskom will not disclose information relating to the evaluation and
comparison of tenders and recommendations for the award of a contract to tenderers or to
any other person not officially concerned with the tender process until after the tender
award.
Grounds for 3.7 Reject a tender if Eskom establishes that there is proof that the tenderer influenced the
rejection processing of tenders or the awarding of the contract, the existence of collusion and/or bid
rigging, and/or that the tenderer has participated in any fraudulent/illegal activity in
connection with the Invitation to Tender.
Clarification of a 3.8 Obtain clarification from a tenderer in respect of any matter in the tender that may not be
tender clear or that could give rise to ambiguity in a contract arising from this tender if the matter
were not to be clarified. A document that the Invitation to Tender identifies as a mandatory
tender returnable that is required to be submitted at the closing date and time for tender
submission will not be requested, but Eskom may seek clarity on it.
may utilise reverse e-auction in certain Enquiries. Where reverse e-auction will be utilised,
this will be indicated in the respective Invitation to Tender and the reverse e-auction
supporting documents will be issued in the Invitation to Tender. Tenderers will be required
to submit a complete tender that does not contain Prices. If a tenderer has included prices
in its tender, the prices will not be considered.
Acceptance of 3.22 Notify Eskom's acceptance to the successful tender before the expiry of the validity period
tender or agreed additional validity period. Inform the successful and unsuccessful tenderers only
once approval has been granted by the Eskom Adjudication Authority. For open tenders,
this notification must be published on the Eskom Tender Bulletin and NT e-Tender Portal
Prepare contract 3.23 Revise the contract documents issued by Eskom in the Invitation to Tender documents to
documents take account of:
Addenda issued during the tender period;
inclusion of returnables stipulated in the Invitation to Tender;
inclusion of changes agreed in contract negotiations; and
Other revisions or documents agreed to between Eskom and the successful
tenderer during negotiations,
Sign Form of 3.24 Arrange for authorised signatories of both parties to complete and sign the original and one
Contractual Terms
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdfincluding the Eskom Representative shall not be liable for any losses, claims or damages of
whatsoever nature or howsoever arising that may be sustained by a tenderer or any other
person as a result of its participation in the tender or from any amendment, termination or
suspension of the process set out in the Invitation to Tender or from its exclusion from
participating in the tender process at any point.
Eskom’s right to 1.7 Eskom reserves the right to enter into mandated negotiations with any, one or more selected
negotiate tenderer(s) in accordance with Eskom’s approved procurement policies and procedures.
240-62044728 Rev 12 Eskom Standard Identifier
Conditions of Tender Effective Date 01 February 2025
Review Date January 2030
Disclaimer 1.8 While Eskom takes all reasonable measures to ensure that all information contained in the
regarding accuracy tender documents is correct and complete, Eskom does not, however, make any
of tender representations or warranties, express or implied, as to the accuracy or completeness of
documents such information and Eskom expressly disclaims any, and all liability for such
representations, warranties or statements.
Tenderer’s 2. The tenderer shall comply with the following obligations when submitting a tender and shall:
Tender validity 2.12 Hold the tender(s) valid for acceptance by Eskom at any time within the validity period after
the closing date and time for tender submission. Extend the validity period for a specified
additional period if Eskom requests the tenderer to do so. A tenderer that agrees to extend
the validity of its tender will not be required or permitted to modify its tender. A tenderer that
does not agree to extend the validity of its tender will be excluded from further
consideration. Tenderers will be requested to extend the validity of their tenders until a
contract(s) have been concluded with one or more tenderers. A request that a tenderer
extend the validity of its tender is not a representation that the tender is an acceptable
tender or that Eskom will seek to negotiate or conclude a contract with the tenderer. If the
validity of tenders expires before contracts have been concluded, the procurement process
is deemed to have concluded without an award.
Confidentiality and 2. 13 Treat as confidential all matters that arise in connection with the procurement. Use and copy
copyright of the documents provided by Eskom only for the purpose of preparing and submitting a tender
documents in response to this Invitation to Tender.
Standardised 2.14 Obtain and familiarise themselves with, if required for the purposes of submitting a tender,
specifications and the latest revision of standardised specifications and/or other documents that have been
other publications incorporated by reference into the Invitation to Tender documents by reference.
Site visit and / or 2.15 Tenderers must attend a site visit and/or clarification meeting that is stipulated as being
clarification compulsory in order to familiarise themselves with the proposed work, services, supply,
meeting location or similar. Failure to attend a clarification meeting or site visit that is identified as
compulsory will result in disqualification from participation.
Details of the meeting(s) are stated in the Tender Data. Tenderers are entitled to ask
correction of errors as required above.
Evaluation of 3.17 Score the B-BBEE level as stated on the CSD report or as per certificate/affidavit provided.
B-BBEE If the B-BBEE level is a pre-qualification criterion; then the proof of the B-BBEE level
(certificate/CSD number/CSD report) must be provided at the closing date and time for
tender submission; or the tender will be disqualified. If sub-contracting to designated groups
pre-qualification criteria are utilized (selected/mandatory) in terms of the PPPFA
Regulation, then Eskom will apply the PPPFA requirements for sub-contractors’ B-BBEE
status and the sub-contractors’ CSD number or B-BBEE certificate/affidavit will need to be
provided at the closing date and time for tender submission. Should the
information/documents provided indicate that the level is in dispute (fraudulent/ expired)
then the tender will be disqualified.
However, for the purposes of PPPFA point allocation: if no B-BBEE certificate/affidavit is
provided at Tender closing date and time for tender submission, or the
information/documents provided are fraudulent or have expired; then the tenderer will not
be disqualified (if otherwise deemed to be responsive and acceptable in all other aspects)
but will score zero under PPPFA point allocation.
Evaluation of 3.18 Score the Specific Goals with reference to the supporting documentation in the tender. If a
Requirements
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)Eligibility 2.1 Submit a tender only if the tenderer (whether a single company or an incorporated or unincorporated joint venture or consortium) complies with the eligibility criteria stated in the Tender Data and the tenderer, or any of its principals, is not under any restriction to do business with Eskom or State-Owned Companies. Tenderers that Eskom finds to be ineligible will be disqualified. Tenderers are not permitted to sub-contract 100% of the scope of work (SOW). Any tender that is based on 100% sub-contracting will be deemed ineligible and will be disqualified.
Section
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdfare submitted and accessible for downloading/evaluation without any challenges as well as
It must be noted that Eskom will not measure a criterion twice in the different evaluation
Functionality 3.13 If functionality is a criterion, tenderers will be scored against the functionality criteria and
further evaluation.
(if applicable) financial risk to Eskom in the execution of the contract. During evaluation of a tenderer’s
Evaluation of Price 3.15 Evaluate the Price in accordance with the criteria/requirements in the Tender Data. Factors
the evaluation Price.
but will score zero under PPPFA point allocation.
Evaluation of 3.18 Score the Specific Goals with reference to the supporting documentation in the tender. If a
Specific Goals tenderer fails to meet Specific Goals and/or to submit the required proof/supporting
will score zero points for Specific Goals within the 90/10 or 80/20 allocation of points.
Ranking of tenders 3.19 According to the PPPFA, Eskom will add the score for Pricing and the Specific Goals
Objective criteria 3.20 A contract may be awarded to a tenderer that did not score the highest points only in
must stipulate the Objective Criteria in the Invitation to Tender. Functionality and any
element of the B-BBEE scorecard may not be used as Objective Criteria.
Reverse e-Auction 3.21 Reverse e-auction is an electronic system that utilises the 90/10 and 80/20 Price and
Preference point systems, and which is intended to achieve competitive pricing. Eskom
(NT instructions, content and/or production by the dtic, PPPFA Regulations; Amended B-BBEE Codes, COIDA;
CIDB, PPPFA etc) OHS Act; Eskom’s requirements for Safety, Health, Environment and Quality (SHEQ) and any other
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
Quality Contract Award. All costs and personnel associated with SHEQ must be reflected in the
However, for the purposes of PPPFA point allocation: if no B-BBEE certificate/affidavit is
Submission Guidelines
Source: 2. B-BBEE_sworn Affidavit-Exempted Micro Enterprise.pdf (unknown)Required returnable document: A sworn affidavit for B-BBEE Exempted Micro Enterprises must be completed, signed by an authorized representative (Member/Director/Owner), and commissioned by a Commissioner of Oaths. The affidavit remains valid for 12 months from the date of commissioning.
Returnable Documents
Source: 2. B-BBEE_sworn Affidavit-Exempted Micro Enterprise.pdf (unknown)Required returnable document: A sworn affidavit for B-BBEE Exempted Micro Enterprises. Must be signed by an authorized representative and commissioned by a Commissioner of Oaths. Valid for 12 months from the date of commissioning.
Evaluation Criteria
Source: 2. B-BBEE_sworn Affidavit-Exempted Micro Enterprise.pdf (unknown)Eligibility for using this form requires the bidder to: - Be an Exempted Micro Enterprise with annual total revenue ≤ R10,000,000. - Provide enterprise details: name, registration number, VAT number (if applicable), physical address, entity type, and nature of business. - Declare Black ownership, Black female ownership, and Black Designated Group ownership percentages. - Break down Black Designated Group ownership into: youth, disabled, unemployed, rural, and military veteran percentages. - Confirm the applicable B-BBEE level contributor (Level 1 for 100% Black owned, Level 2 for ≥51% Black owned, Level 4 for <51% Black owned).
Compliance Requirements
Source: 2. B-BBEE_sworn Affidavit-Exempted Micro Enterprise.pdf (unknown)B-BBEE compliance requirements: - Must be an Exempted Micro Enterprise with annual revenue ≤ R10,000,000. - Submit a sworn affidavit declaring: percentage of Black ownership, Black female ownership, and Black Designated Group ownership. - Provide a breakdown of Black Designated Group ownership into youth, disabled, unemployed, rural, and military veteran percentages. - Confirm B-BBEE level contributor (Level 1, 2, or 4 based on ownership). - Affidavit must be signed by an authorized representative and commissioned.
B-BBEE Requirements
Source: 2. B-BBEE_sworn Affidavit-Exempted Micro Enterprise.pdf (unknown)B-BBEE requirements for Exempted Micro Enterprises: - Annual revenue must be ≤ R10,000,000. - Submit a sworn affidavit declaring: percentage of Black ownership, Black female ownership, and Black Designated Group ownership. - Break down Black Designated Group ownership into: youth, disabled, unemployed, rural, and military veteran percentages. - Confirm B-BBEE level contributor: Level 1 (100% Black owned), Level 2 (≥51% Black owned), or Level 4 (<51% Black owned). - Affidavit must be signed by an authorized representative and commissioned by a Commissioner of Oaths.
Submission Guidelines
Source: Annexure D - Integrity Declaration Form.docx (unknown)Returnable documents are not specified in the available text. Bidders must obtain the full tender document to identify all required forms and submission instructions.
Evaluation Criteria
Source: Annexure D - Integrity Declaration Form.docx (unknown)Specific eligibility criteria are not detailed in the provided snippet. However, typical Eskom tenders require: Valid B-BBEE status, tax compliance, CIDB registration (if applicable), proof of financial stability, and relevant industry experience, especially with medium voltage electrical equipment. Bidders should consult the full tender document for exact requirements.
Technical Specifications
Source: Annexure D - Integrity Declaration Form.docx (unknown)The tender uses the standard Eskom Invitation to Tender (ITT) or Request for Proposal (RFP) template. Template details: File name 240-1142368630 (Rev 21); Template ID 240-43921804 (Rev 7) Header and Footer portrait template. No scope, deliverables, or standards are provided in the available text.
Compliance Requirements
Source: Annexure D - Integrity Declaration Form.docx (unknown)No specific compliance requirements are found in the available text. Bidders should expect standard Eskom requirements such as CSD registration, tax clearance, B-BBEE verification, and possibly CIDB grading for electrical works.
Contact Information
Source: Eskom Supplier Integrity Pact - 02 June 2023.pdf (unknown)For reporting unethical behaviour: Email Eskom Ethics office at [email protected] or Eskom Forensic at [email protected]. Toll-free hotline: 0800 11 27 22.
Submission Guidelines
Source: Eskom Supplier Integrity Pact - 02 June 2023.pdf (unknown)Returnable Documents: Integrity Declaration Form must be completed, signed, and submitted when participating in any Eskom procurement process. Suppliers must also complete a Non-Disclosure Agreement (NDA) if required.
Returnable Documents
Source: Eskom Supplier Integrity Pact - 02 June 2023.pdf (unknown)Integrity Declaration Form must be signed and submitted when participating in any Eskom procurement process. Non-Disclosure Agreement (NDA) may also be required.
Evaluation Criteria
Source: Eskom Supplier Integrity Pact - 02 June 2023.pdf (unknown)Supplier eligibility and evaluation criteria include: - Must be an existing or potential supplier (natural or juristic person) registered or seeking registration on Eskom's Vendor Database. - Must comply with all South African laws and Eskom's ethical standards. - Must disclose any conflicts of interest or relationships with Eskom employees/directors. - Must have a clean record with no history of misconduct in Eskom processes. - Must agree to the terms of the Integrity Pact and associated declarations, including fair tendering practices.
Technical Specifications
Source: Eskom Supplier Integrity Pact - 02 June 2023.pdf (unknown)This document is an Integrity Pact, not a technical specification. It outlines ethical obligations for suppliers participating in Eskom procurement processes, including motor refurbishment tenders.
Compliance Requirements
Source: Eskom Supplier Integrity Pact - 02 June 2023.pdf (unknown)Suppliers must: - Read, complete, sign, and submit the Integrity Declaration Form. - Avoid conflicts of interest and disclose any relationships with Eskom employees/directors. - Complete a Non-Disclosure Agreement (NDA) if required. - Not submit false or forged documents. - Adhere to ethical standards and reject improper practices. - Ensure business courtesies or gifts do not exceed R1500 and do not improperly influence recipients. - Avoid unethical or fraudulent dealings with Eskom employees/directors involved in evaluation, adjudication, or negotiation. - Not enter dishonest or illegal agreements with other tenderers.
Contractual Terms
Source: Eskom Supplier Integrity Pact - 02 June 2023.pdfThis Integrity Pact is governed by and interpreted in accordance with the laws of the Republic of South Africa. Actions stipulated are without prejudice to other civil or criminal proceedings. The Pact remains valid until replaced. If any provision is invalid, the remainder of the provisions stay valid.
Requirements
Source: Eskom Supplier Integrity Pact - 02 June 2023.pdf (unknown)Supplier obligations include: - Business courtesies or gifts must not harm Eskom's image, must not exceed R1500, and must not improperly influence recipients. - Avoid unethical or fraudulent dealings with Eskom employees/directors involved in evaluation, adjudication, or negotiation; no bribes, gifts, fees, commissions, or inducements may be offered or requested. - Do not enter dishonest or illegal agreements with other tenderers; complete the Integrity Declaration Form, which includes a Declaration of Fair Tendering Practices.
Description
Source: Annexure E - Contract Price Adjustment (CPA) Requirements for Local Goods and Services.docxScope: Contract Price Adjustment (CPA) requirements for local goods and services. Applies to the refurbishment, testing, and delivery of medium-voltage motors at Arnot Power Station over a 4-year period. Key focus: CPA conditions, fixed pricing, and index-based adjustments for long-term contracts.
Evaluation Criteria
Source: Annexure E - Contract Price Adjustment (CPA) Requirements for Local Goods and Services.docx (unknown)Bidders must: - Demonstrate capability to supply medium-voltage motor refurbishment services in South Africa. - Prove financial capacity to fulfill a 4-year contract. - Apply publicly published Contract Price Adjustment (CPA) indices as stipulated by Eskom. - Ensure compliance with Eskom’s procurement policies. - Submit all required signatures and documentation. - Avoid reliance on exchange-rate adjustments in CPA formulae. - Separate local and foreign cost escalations in CPA proposals. - Include the mandatory fixed-price portion (minimum 15% of total agreement value).
Technical Specifications
Source: Annexure E - Contract Price Adjustment (CPA) Requirements for Local Goods and Services.docx (unknown)Scope: Contract Price Adjustment (CPA) requirements for local goods and services related to the refurbishment, testing, and delivery of medium-voltage motors. Key points: - CPA applies to contracts exceeding 12 months. - Fixed pricing required for contracts of 12 months or less. - CPA not applicable in the first year for contracts longer than 12 months; applies from year two onwards.
Financial Requirements
Source: Annexure E - Contract Price Adjustment (CPA) Requirements for Local Goods and Services.docx (unknown)Pricing and Contract Price Adjustment (CPA) rules: - CPA may apply if the contract duration exceeds 12 months. - Fixed price offer required for contracts of 12 months or less. - For contracts longer than 12 months, CPA is not applicable for the first year; it applies from year two onwards. - Failure to propose CPA or submit a CPA formula results in pricing being considered fixed. - CPA formulae must be separate for local and foreign components; they cannot be combined. - Minimum 15% of the total agreement value must remain fixed when a CPA formula is applied. - Each CPA formula must total 100%. - Only official, publicly published indices may be used; no in-house indices allowed. - Eskom does not accept Rate of Exchange adjustments in CPA formulae. - Local indices may not be used for any imported component. - Base date for indices: month before the tender closing month. - For professional services, the preferred index is the country-specific CPI Headline index. - Eskom reserves the right to negotiate CPA terms during tender negotiations.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 4 of 2006
Relevant to electricity, generation, transmission, distribution and energy-service procurement.
Relevant because this tender appears to involve electricity, power supply, energy infrastructure, generators, or energy maintenance. Relevant because this tender appears to involve petroleum, oil, gas, fuel, or energy-resource services.
Act 107 of 1998
Relevant where environmental authorisations, EIAs or environmental compliance may apply.
Relevant because this tender appears to involve electricity, power supply, energy infrastructure, generators, or energy maintenance. Relevant because this tender appears to involve petroleum, oil, gas, fuel, or energy-resource services.
Act 85 of 1993
Sets health and safety duties for contractors, employers and service providers working on public-sector sites.
Relevant because this tender appears to involve electricity, power supply, energy infrastructure, generators, or energy maintenance. Relevant because this tender appears to involve petroleum, oil, gas, fuel, or energy-resource services.
Act 28 of 2002
Relevant to mineral resources, mining rights, prospecting and mining-related procurement.
Relevant because this tender appears to involve petroleum, oil, gas, fuel, or energy-resource services.
Act 40 of 2004
Relevant to regulated electricity, piped-gas and petroleum-pipeline activities.
Relevant because this tender appears to involve electricity, power supply, energy infrastructure, generators, or energy maintenance.
Address
Arnot Power Station - Rietkuil - Mpumalanga - 1097
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
32
Last checked
01 Aug 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Learn how to submit a winning bid with these related articles
How small office supplies, stationery, and general goods suppliers use Joint Ventures to win government procurement contracts by combining inventory with B-BBEE credentials.
How the Protection of Personal Information Act affects tender submissions, data handling, and supplier contracts with government. A practical POPIA compliance guide for South African tender bidders covering lawful processing, data subject rights, and consequences of non-compliance.
A meticulously organised tender submission can be the difference between a winning bid and one that hits the rejection pile. Learn how to package, structure, and present your tender response for maximum evaluator impact on South African government contracts.
How consulting engineers, engineering firms, and multidisciplinary practices can win public sector infrastructure contracts in South Africa — from ECSA registration and CESA membership to fee proposals, QBS scoring, and building a winning tender response.
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Electricity, gas, steam and air conditioning. Unlock full pricing strategies, bid frequency, and historical win rates.