Scope: completion contract for the Department of Education Water & Sanitation Programme for Schools at Emvubukazi Junior Secondary School, Harry Gwala District. The works are described in the Scope of Works (C3.1) and the Bills of Quantities (C2.3).
CIDB grading: 3GB or higher.
Contract period: 6 calendar months, including all non-working days, public holidays and year-end breaks.
Defects liability period: 12 months from the Certificate of Completion. Latent defect period: 5 years after the Final Approval Certificate.
Practical completion: whole of the works within 6 months; penalty for late completion is 0.04% of the Contract Price per calendar day, rounded to the nearest R10.
Documentation required before commencement (within 14 calendar days after notice from the Employer): Health and Safety Plan, chosen Guarantee, insurance, cash flow, priced Bill of Quantities, and programme of work (programme within 10 calendar days).
Contractor must commence works within 7 calendar days of the Commencement Date; site possession given within 10 calendar days after fulfilling conditions.
Contract Price Adjustment Provisions (CPAP) apply where the construction period exceeds 6 months and the contract exceeds R1,000,000.00; work group WG 180 (domestic buildings) or WG 181 (commercial/industrial).
Subcontractors must be registered with the CIDB with active status at tender submission.
EPWP requirements apply (Annexures 9β15), including scope of works, NYS specifications, employment agreements, attendance registers, data collection tools and proforma organogram.
HIV/AIDS awareness specification and compliance report are part of the scope (C3.2, C3.3).