Bathal/Standerton Road - Tutuka Power Station - Standerton - 2340
Organization Type
GOVERNMENT
Published
23 Sept 2026
OCDS Reference
ocds-9t57fa-171429
ESKOM requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages, projects and commissioning work at tutuka power station in mpumalanga for five years. The contractor must lead the quality process, conduct daily toolbox talks, raise non-conformance reports, transfer skills to station employees and submit weekly quality reports. All work is done under permit, personnel need yearly induction and medical surveillance, and the contractor supplies sabs-approved PPE.
Contract period: 5 years at Tutuka Power Station, Mpumalanga.
Scope: co-ordinate, oversee and quality control maintenance, outage, project and commissioning activities; conduct daily toolbox talks; perform physical inspections; raise NCRs for non-compliance; submit weekly quality reports.
Skills transfer: contractor must transfer quality skills to Tutuka Power Station employees.
Permit to work: all work must be done under a permit to work.
Personnel compliance: all personnel must comply with Eskom rules and Life Saving rules, and have yearly induction and medical surveillance.
PPE: contractor must provide all PPE, which must be SABS approved.
Timesheets: must be logged and signed by the Services Manager and the contractor.
Continue with tenders sharing this issuer, category, or province.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Thursday, 08 October 2026 - 10:00
Venue
https://teams.microsoft.com/meet/31161431309269?p=7pGLAEq2mAT7adhz8s
Categories
Request for Quotation
Bathal/Standerton Road - Tutuka Power Station - Standerton - 2340
AI Document Analysis Stages
Submission Guidelines
Source: FOLDER SUBMISSION GUIDE.pdf (unknown)Submission folders guide:
Returnable documents: all required standard forms (SBD forms) must be completed and submitted as part of the tender pack.
23 Sept
2026
Tender Published
Tender was published
08 Oct
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdf
Eskom Holdings SOC Ltd requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and project-related activities at Tutuka Power Station in Mpumalanga for a period of five years. The contract will be governed by the NEC3 Term Service Contract and requires ISO 9001:2015 certification.
Annex-e_Local Content Declaration-Supporting Schedule to Annex C.pdf
Annex-d_Imports Declaration-Supporting schedule to Annex C.pdf
Annex-c_Local content Declaration-Summary Schedule.pdf
SHE Tender Evaluation Template (High risk) .pdf
Eskom requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station in Mpumalanga for a period of 5 years. The tender includes an OHS evaluation for high-risk work, requiring a comprehensive health and safety plan, risk assessment, and competency documentation.
Contractor Health and Safety.pdf
TSC - Quality Control Activities and Physical Inspections - 15092026.pdf
No summary available
ANNEXURE K E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf
Eskom requires control, co-ordination and performance of quality control activities and physical inspections on maintenance, outages and projects related activities at Tutuka Power Station for a period of 5 years.
240-68099512 Form A_Cat 1_ Rev 9.pdf
Eskom requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station in Mpumalanga for a period of 5 years. The tenderer must accept Eskom's Supplier Quality Requirements (specification 240-105658000) and ISO 9001 standard, and complete the quality requirements form as part of the bid.
Declaration_of_Shareholding_or_Beneficiaries_Form (1).pdf
Eskom requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and projects related activities at Tutuka Power Station in Mpumalanga for a period of 5 years.
Eskom_Standard_Conditions_of_Tender.pdf
Eskom requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station in Mpumalanga, for a period of 5 years. The tender is governed by Eskom's Standard Conditions of Tender and the Preferential Procurement Policy Framework Act (PPPFA), with evaluation based on price and specific goals.
Life Saving-Rules.pdf
Eskom requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station in Mpumalanga, for a period of five years. The contract covers quality assurance and inspection services across plant maintenance and project work.
FOLDER SUBMISSION GUIDE.pdf
Eskom requires a contractor to control, coordinate and perform quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station in Mpumalanga for a five-year period.
Authority to submit a tender (Returnable Schedule).pdf
Eskom requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station in Mpumalanga for a period of five years.
Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.pdf
Eskom requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and project-related activities at Tutuka Power Station in Mpumalanga, for a period of five years. The tender includes a PAYE questionnaire that bidders must complete to determine their tax classification for payments under the contract.
Annex B Acknowledgement Form for Eskom SHE Rules and other Requirements (3).pdf
Eskom requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station in Mpumalanga, for a period of 5 years. The successful bidder must comply with Eskom's OHS legal and other requirements, including the Occupational Health and Safety Act, Compensation for Occupational Injuries and Diseases Act, and Eskom's lifesaving rules.
E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf
Eskom requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station in Mpumalanga, for a period of five years. The tender is advertised on the Eskom Tender Bulletin and submissions must be made electronically via the eTendering system.
low risk Tender Evaluation form.pdf
Eskom requires a supplier to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and projects related activities at Tutuka Power Station in Mpumalanga for a period of 5 years.
Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.pdf
Eskom requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station in Mpumalanga for a five-year period. The tender is open to suppliers who must sign a Non-Disclosure Agreement before receiving confidential information.
240-12248652_List of Tender Returnables_Cat 1_ Rev 7.pdf
Eskom requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and project-related activities at Tutuka Power Station in Mpumalanga for a five-year period. The tender is evaluated primarily on quality management system compliance, contract quality planning, and inspection/test plan deliverables.
Annexure B.pdf
Eskom requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station in Mpumalanga for a five-year period. The contract includes strict compliance with Eskom's Safety, Health and Environment (SHE) rules and statutory requirements, with financial penalties for non-conformance.
Supplier Development Localisation Industrialisation (SDLI) Strategy -Quality control.pdf
Eskom requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outages and project-related activities at Tutuka Power Station for a five-year period. The contract is awarded under the 90/10 preferential procurement system, with up to 10 points for B-BBEE status and 90 for price, and includes mandatory SDL&I obligations covering transformation, local procurement, subcontracting, job creation and skills development.
Tender Technical Evaluation Strategy.pdf
Eskom seeks a contractor to control, coordinate and perform quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station in Mpumalanga for five years. The contract provides independent quality oversight to improve compliance, reduce rework, and ensure adherence to engineering standards. Tenderers must meet mandatory ISO 9001:2015 certification and score at least 70% in the technical evaluation to qualify.
Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx (1).pdf
Eskom requires a contractor to control, coordinate and perform quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station in Mpumalanga, under a five-year contract. The document supplied is the Eskom PAYE Questionnaire for service contracts, applicable to the 2026/2027 tax year, used to classify the contractor's tax status (independent contractor, personal service provider, labour broker, or dependent contractor) for withholding purposes.
Scope of Work.pdf
Eskom requires a contractor to control, co-ordinate and perform quality control activities and physical inspections on maintenance, outage, project and commissioning work at Tutuka Power Station in Mpumalanga for five years. The contractor will lead quality processes, conduct daily toolbox talks, raise non-conformance reports, and transfer skills to station staff, with all work performed under permit and in compliance with Eskom rules.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
R 6 063 472
Range
Based on 12 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Evaluation Criteria
Source: FOLDER SUBMISSION GUIDE.pdf (unknown)Evaluation is based on the submission folders. Bidders must be registered on the CSD and hold a valid tax clearance certificate. A valid B-BBEE certificate, COIDA registration, and company certificates are required in the Commercial folder. Financial statements, ITC34, and Public Interest Score must be submitted in the Finance folder. Technical evaluation criteria are included in the Technical folder.
Compliance Requirements
Source: FOLDER SUBMISSION GUIDE.pdf (unknown)Required compliance documents:
Health & Safety
Source: FOLDER SUBMISSION GUIDE.pdfSHEQ folder must include health & safety, environment, quality, and occupational hygiene documentation. This is part of the required submission folders.
Description
Source: Annex B Acknowledgement Form for Eskom SHE Rules and other Requirements (3).pdfThe document is an acknowledgement form for Eskom OHS legal and other requirements. It does not describe the scope of the tender itself.
Submission Guidelines
Source: Annex B Acknowledgement Form for Eskom SHE Rules and other Requirements (3).pdf (unknown)Returnable documents:
Submission method and address are not stated in this document.
Evaluation Criteria
Source: Annex B Acknowledgement Form for Eskom SHE Rules and other Requirements (3).pdf (unknown)Bidders must sign and submit the Acknowledgement Form for Eskom OHS legal and other requirements (Annexure B). No other evaluation criteria are stated in this document.
Technical Specifications
Source: Annex B Acknowledgement Form for Eskom SHE Rules and other Requirements (3).pdf (unknown)The main contractor/supplier must:
Compliance Requirements
Source: Annex B Acknowledgement Form for Eskom SHE Rules and other Requirements (3).pdf (unknown)OHS compliance:
Health & Safety
Source: Annex B Acknowledgement Form for Eskom SHE Rules and other Requirements (3).pdfOHS compliance summary:
Contractual Terms
Source: Annex B Acknowledgement Form for Eskom SHE Rules and other Requirements (3).pdfThe main contractor/supplier must:
Evaluation Criteria
Source: Tender Technical Evaluation Strategy.pdf (unknown)Technical evaluation uses a weighted score-card approach. The overall technical score is weighted 100% and a minimum weighted score of 70% is required to qualify for further evaluation.
Scoring method:
Evaluation weights:
Mandatory technical criterion:
Qualitative criteria (100% total):
Acceptable technical risks:
Unacceptable technical risks:
Acceptable exceptions/conditions:
Unacceptable exceptions/conditions:
Technical Specifications
Source: Tender Technical Evaluation Strategy.pdf (unknown)Eskom requires the control, co-ordination and performance of quality control activities and physical inspections on maintenance, outages (planned and unplanned) and project-related activities at Tutuka Power Station for a period of 5 years.
The contract provides independent quality oversight to improve compliance, reduce rework, improve outage execution quality, and ensure adherence to engineering standards.
Scope includes provision of resources to control, co-ordinate and perform quality control activities and physical inspections during maintenance, outages and projects.
Quality control services cover mechanical, electrical, control & instrumentation, civil and structural quality control, welding inspection, documentation control, material verification, inspection and test plan (ITP) implementation, non-conformance management, quality surveillance and final acceptance inspection for maintenance, planned and forced shutdowns, refurbishment and capital projects.
Methodology
Source: Tender Technical Evaluation Strategy.pdf (unknown)Technical proposal (25% of evaluation) must be a high-level technical proposal for execution of Quality Control Services covering: allocation of resources to respective departments, RFI acknowledgement and allocation of resources, streamlining of offsite inspections, and follow-through of nonconformances and review of remedies. Scoring is based on coverage of minimum items and further elaboration.
Quality Management
Source: Tender Technical Evaluation Strategy.pdfMandatory ISO 9001:2015 QMS certification is required, with a verifiable valid certificate covering the scope of quality control and inspection services as specified. The contract aims to provide independent quality oversight to improve compliance, reduce rework, improve outage execution quality, and ensure adherence to engineering standards.
Compliance Requirements
Source: Tender Technical Evaluation Strategy.pdf (unknown)Mandatory technical criterion:
No other compliance requirements (e.g., CSD, tax, B-BBEE, CIDB) are stated in this document.
Requirements
Source: Tender Technical Evaluation Strategy.pdf (unknown)Mandatory technical criterion: Valid ISO 9001:2015 QMS certificate with scope covering quality control and inspection services as specified. No other requirements are stated in this document.
Section
Source: Tender Technical Evaluation Strategy.pdfTechnical evaluation uses a weighted score-card approach. Minimum weighted score of 70% to qualify. Scoring: 5=100% compliant, 4=80% compliant with qualifications, 2=40% non-compliant, 0=0% totally deficient. Weights: Proven track record 25%, Team experience 50%, Technical proposal 25%. Acceptable risks: supplier worked on 2 similar projects; resources with 3-5 years experience. Unacceptable risks: inexperienced personnel, only 1 similar project. Acceptable exceptions: 50% of qualified resources initially. Unacceptable exceptions: zero experience in Quality Control.
Important Dates
Source: ANNEXURE K E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)Closing date: 27 January 2025 (time not stated)
Submission Guidelines
Source: ANNEXURE K E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)Returnable documents:
Evaluation Criteria
Source: ANNEXURE K E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)Submission of the fully completed E-Tendering Training Acknowledgement Form within the prescribed period is mandatory; failure to do so will render the tenderer non-responsive and disqualified from the procurement process.
Description
Source: 240-68099512 Form A_Cat 1_ Rev 9.pdfThe work involves control, co-ordination and performance of quality control activities and physical inspections on maintenance, outages and projects related activities at Tutuka Power Station, for a period of 5 years. The tenderer must select the applicable pre-contract award quality category (Category 1 applies) and indicate whether site assessment is applicable.
Contact Information
Source: 240-68099512 Form A_Cat 1_ Rev 9.pdf (unknown)Eskom Quality Representative:
Submission Guidelines
Source: 240-68099512 Form A_Cat 1_ Rev 9.pdf (unknown)Returnable documents:
Evaluation Criteria
Source: 240-68099512 Form A_Cat 1_ Rev 9.pdf (unknown)The tenderer must complete and sign Form A to acknowledge and accept Eskom Supplier Quality Requirements as per specification 240-105658000 and ISO 9001. The form indicates pre-contract award quality requirements (Category 1 selected) and post-contract award clauses. No scoring split, minimum qualifying score, or preference point system is stated.
Technical Specifications
Source: 240-68099512 Form A_Cat 1_ Rev 9.pdf (unknown)Scope: Control, co-ordination and performance of quality control activities and physical inspections on maintenance, outages and projects related activities at Tutuka Power Station.
Contract period: 5 years.
Quality requirements: The tenderer must comply with Eskom Supplier Quality Requirements (specification 240-105658000) and ISO 9001 standard.
Pre-contract award quality requirements: Category 1 applies (refer to clause 3.5 of 240-105658000). Only one category may be selected.
Post-contract award clauses (refer to clauses 3.7 and 3.8 of 240-105658000):
Methodology
Source: 240-68099512 Form A_Cat 1_ Rev 9.pdfThe ISO 9001 clauses applicable are: Context of the Organisation, Leadership, Planning, Support, Operation, Performance Evaluations, and Improvement. The quality principles applicable are: Customer focus, Leadership, Engagement of people, Process approach, Improvement, Evidence based decision making, and Relationship Management.
Quality Management
Source: 240-68099512 Form A_Cat 1_ Rev 9.pdfThe tenderer must complete and sign Form A to acknowledge and accept Eskom Supplier Quality Requirements (specification 240-105658000) and ISO 9001. The form indicates pre-contract award quality requirements (Category 1 selected), post-contract award clauses including contract execution, supplier quality performance monitoring, Eskom rights of access and information, preservation, quality audits, management of nonconformities, and special processes. It also lists applicable ISO 9001 clauses and quality principles.
Compliance Requirements
Source: 240-68099512 Form A_Cat 1_ Rev 9.pdf (unknown)The tenderer must complete and sign Form A to acknowledge and accept Eskom Supplier Quality Requirements (specification 240-105658000) and ISO 9001. No other compliance requirements are stated in the document.
Section
Source: 240-68099512 Form A_Cat 1_ Rev 9.pdfThe tenderer must complete and sign Form A to acknowledge and accept Eskom Supplier Quality Requirements (specification 240-105658000) and ISO 9001. The form indicates pre-contract award quality requirements (Category 1 selected) and post-contract award clauses. No scoring split or minimum qualifying score is stated.
Submission Guidelines
Source: low risk Tender Evaluation form.pdf (unknown)Returnable documents (all mandatory):
Evaluation Criteria
Source: low risk Tender Evaluation form.pdf (unknown)Evaluation is conducted by Eskom's/Client's OHS Representative using Annexure C 1 (OHS Tender Evaluation Template, Low risk work). The bidder is recommended or not recommended based on submission of the mandatory OHS documents.
Compliance Requirements
Source: low risk Tender Evaluation form.pdf (unknown)Mandatory OHS compliance:
Health & Safety
Source: low risk Tender Evaluation form.pdf (unknown)Mandatory OHS documents: signed acknowledgement of Eskom's OHS legal and other requirements (Annexure B), a Health and Safety Policy, and a valid Letter of Good Standing (COIDA or equivalent).
Section
Source: low risk Tender Evaluation form.pdfThe bid is evaluated using Annexure C 1 (OHS Tender Evaluation Template, Low risk work). The OHS Representative recommends or does not recommend the bidder based on submission of the mandatory OHS documents.
Description
Source: SHE Tender Evaluation Template (High risk) .pdfSupply and delivery of instrumentation: Inductively Coupled Plasma (ICP) and Ion Chromatography dual (low and high level) equipment for coal stations. The contract is for a period of 5 years at Tutuka Power Station.
Contact Information
Source: SHE Tender Evaluation Template (High risk) .pdf (unknown)No contact details are provided in the document.
Submission Guidelines
Source: SHE Tender Evaluation Template (High risk) .pdf (unknown)Returnable documents (all must be submitted):
Submission method: not specified in the document.
Disqualification risk: failure to submit any required returnable may result in disqualification.
Evaluation Criteria
Source: SHE Tender Evaluation Template (High risk) .pdf (unknown)Evaluation is based on the OHS Tender Evaluation Template (Annexure C1, high risk).
Each returnable is assessed as Yes (compliant), No (non-compliant), or Not Applicable.
Recommendation: Recommended or Not Recommended.
No scoring split or minimum qualifying score is stated.
Technical Specifications
Source: SHE Tender Evaluation Template (High risk) .pdf (unknown)Scope: supply and delivery of instrumentation, specifically Inductively Coupled Plasma (ICP) and Ion Chromatography dual (low and high level) equipment.
Location: Coal stations (Tutuka Power Station is the site per the tender record).
Contract period: 5 years (per tender record).
Experience & Qualifications
Source: SHE Tender Evaluation Template (High risk) .pdfOHS competency must be demonstrated through CVs and qualifications/certificates, listing the competencies required for the scope of work, risks, OHS plan, and applicability.
Financial Requirements
Source: SHE Tender Evaluation Template (High risk) .pdf (unknown)OHS costing must be detailed and broken down, not a lump sum.
Costing must be based on the overall scope of work/service to be performed; the scope of work and risk assessment may serve as a guideline.
Compliance Requirements
Source: SHE Tender Evaluation Template (High risk) .pdf (unknown)OHS compliance is mandatory:
No B-BBEE, CIDB, or CSD requirements are stated in the document.
Health & Safety
Source: SHE Tender Evaluation Template (High risk) .pdfThe OHS policy must comply with OHS Act Section 7.
Section
Source: SHE Tender Evaluation Template (High risk) .pdfEvaluation uses Annexure C1: OHS Tender Evaluation Template (High risk). Each returnable is marked Yes/No/Not Applicable, leading to a recommendation of Recommended or Not Recommended.
Description
Source: Eskom_Standard_Conditions_of_Tender.pdfThe scope is the control, co-ordination and performance of quality control activities and physical inspections on maintenance, outages and projects related activities at Tutuka Power Station for a period of 5 years. No further description is provided in this document.
Important Dates
Source: Eskom_Standard_Conditions_of_Tender.pdf (TENDER)Closing date: 8 October 2026 at 10:00 (SAST).
Compulsory site visit / clarification meeting: details (date, time, venue) are stated in the Tender Data; attendance is mandatory and failure to attend disqualifies the tender.
Clarification deadline: earlier than the closing time for clarification of queries (exact date/time not stated in the document).
Briefing Session
Source: Eskom_Standard_Conditions_of_Tender.pdf (TENDER)A site visit and/or clarification meeting may be compulsory. Details (date, time, venue) are stated in the Tender Data. Attendance is mandatory; failure to attend results in disqualification. The purpose is to familiarise bidders with the proposed work, services, supply and location, and to raise questions.
Contact Information
Source: Eskom_Standard_Conditions_of_Tender.pdf (TENDER)Fraud and corruption reporting (anonymous):
All tender communication must be directed to the Eskom Representative only, in writing, in English. The Eskom Representative's name and contact details are stated in the Tender Data (not provided in this document).
Submission Guidelines
Source: Eskom_Standard_Conditions_of_Tender.pdf (TENDER)Submission method: physical delivery to the designated tender box at the address stated in the Tender Data.
Required copies:
Packaging:
Returnable documents (all must be completed and submitted by the closing deadline):
Disqualification risks:
Evaluation Criteria
Source: Eskom_Standard_Conditions_of_Tender.pdf (TENDER)Evaluation stages:
Preference point system: 80/20 or 90/10 as per PPPFA (the document does not state which applies to this tender).
Arithmetical error correction:
Objective criteria: Eskom may award to a tenderer that did not score highest only under Section 2(1)(f) of the PPPFA, with objective criteria stipulated in the tender documents.
Designated materials: failure to meet DTIC local content requirements for designated materials renders the tender non-responsive.
Reverse e-auction: Eskom may use a reverse e-auction; if used, tenderers submit a complete tender without prices, and any included prices are disregarded.
Technical Specifications
Source: Eskom_Standard_Conditions_of_Tender.pdf (TENDER)Scope: Control, co-ordination and performance of quality control activities and physical inspections on maintenance, outages and projects related activities at Tutuka Power Station.
Contract period: 5 years.
Location: Tutuka Power Station, Mpumalanga.
No further technical specifications are provided in this document; refer to the Tender Data and the specification/works information.
Quality Management
Source: Eskom_Standard_Conditions_of_Tender.pdfQuality management is part of the SHEQ requirements. Bidders must provide reasonable proof that quality systems, policies and capabilities are in place at contract award. All quality-related costs and personnel must be reflected in the tender. No specific quality standards or certifications are stated in this document.
Pricing Schedule
Source: Eskom_Standard_Conditions_of_Tender.pdfPricing requirements:
Financial Requirements
Source: Eskom_Standard_Conditions_of_Tender.pdf (TENDER)Pricing format:
Insurance:
Security for performance:
Costs:
Payment terms: not stated in this document.
Compliance Requirements
Source: Eskom_Standard_Conditions_of_Tender.pdf (TENDER)Eligibility:
Legislative compliance:
Sheq:
CIDB:
B-bbee:
Contract Skills Development Goal (CSDG):
Contract Participation Goals (CPG):
Tax and CSD: compliance with NT instructions (CSD) is required; specific tax clearance details not stated in this document.
Health & Safety
Source: Eskom_Standard_Conditions_of_Tender.pdfHealth and safety requirements:
Contractual Terms
Source: Eskom_Standard_Conditions_of_Tender.pdfContract formation:
Eskom's rights:
Confidentiality:
Validity:
Disqualification:
Clarification:
Award notification:
Special Conditions
Source: Eskom_Standard_Conditions_of_Tender.pdf (TENDER)Special conditions:
Requirements
Source: Eskom_Standard_Conditions_of_Tender.pdf (TENDER)General requirements:
Section
Source: Eskom_Standard_Conditions_of_Tender.pdfAdditional evaluation criteria:
Description
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdfThe service is the control, co-ordination and performance of quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station, for a period of 5 years. The Affected Property is Tutuka Power Station.
Important Dates
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdf (unknown)Closing date: 8 October 2026 at 10:00 (from tender record).
No briefing session, site visit, or clarification deadline is stated in the document.
Contact Information
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdf (unknown)Enquiries:
Submission address: not stated.
Service location:
Tutuka Power Station
Mpumalanga
Submission Guidelines
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdf (unknown)Returnable documents:
Submission method and address: not stated in the document.
Disqualification risks:
Evaluation Criteria
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdf (unknown)No evaluation criteria (scoring, preference points, minimum qualifying score) are stated in the document.
The contract is a priced contract with price list (Option A) under NEC3 TSC3. Prices are derived from the price list, either as lump sums or as rates multiplied by expected quantities.
Low service damages (Option X17) apply, with the service level table in Appendix A.
Liability limitations (Option X18):
Technical Specifications
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdf (unknown)Scope: Control, co-ordination and performance of quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station.
Contract duration: 5 years (60 months).
Purpose: Provide competent Quality Control (QC) resources to perform independent quality inspections, surveillance, and testing in support of planned and unplanned outages, maintenance, and project activities. Verify that all work is executed in accordance with approved technical specifications, engineering standards, quality requirements, statutory and regulatory requirements, and approved procedures.
Plant areas covered (electrical quality inspections, all plant areas):
Core crew roles (per hour): Administrator, C&I Quality Inspector, Civil Quality Inspector, Electrical Quality Inspector, Mechanical Inspector, Quality Supervisor, Safety Officer, Welding Quality Supervisor, Welding Quality Inspector.
Additional resources (as and when required): C&I, Civil, Electrical, Welding Quality Inspectors.
Normal working hours averaged at 173 hours per month for the duration of the contract.
Home-to-work rate based on return trip between Tutuka Power Station and Standerton. Transport for Home-Work-Home (22 Seater) sourced from local taxi association.
Call-out and off-site inspection kilometres based on start and finish from Tutuka Power Station or Standerton.
Contractor must be ISO 9001:2015 QMS certified.
Risk register items include: industrial action, community unrest, health and safety incidents, unavailability of Quality Control Inspectors, delays in performing scheduled inspections, non-attendance at mandatory meetings/inspections/hold points/witness points, delays in close-out of Non-Conformance Reports, failure to comply with approved Quality Control Plans (QCPs), Inspection and Test Plans (ITPs), technical specifications, or Eskom procedures.
Methodology
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdf (unknown)Contractor submits a first plan for acceptance within 1 week of the Contract Date.
Contractor prepares forecasts of the final total of the Prices at intervals no longer than 4 weeks.
For Task Orders, Contractor submits a Task Order programme to the Service Manager within 24 hours of receiving the Task Order.
Experience & Qualifications
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdfKey personnel details and CVs must be provided in the Contract Data (C1.2b). The document does not specify minimum experience or qualification requirements for key personnel.
Quality Management
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdfContractor must be ISO 9001:2015 QMS certified.
Quality control activities must comply with approved Quality Control Plans (QCPs), Inspection and Test Plans (ITPs), technical specifications, and Eskom procedures.
Risks include delays in close-out of Non-Conformance Reports and failure to comply with approved plans.
Contractor remains liable for any non-conformance, omission or deficiency in quality control services, including inspections, testing, verification or certification, up to 52 weeks after the end of the service period, and must provide support, information, records, clarifications and technical assistance for investigations.
Pricing Schedule
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdfPrice list (C2.2) includes items for:
Pricing format: Option A – priced contract with price list. Items can be lump sums or rates multiplied by expected quantities. No adjustment to lump sums if quantity changes; only compensation events change the Prices.
Price adjustment for inflation (CPA) proposals must form part of tender returnables.
Financial Requirements
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdf (unknown)Pricing: Priced contract with price list (Option A). Prices are either lump sums or rates multiplied by expected quantities. No adjustment to lump sum items if quantity changes; only compensation events change the Prices.
Price adjustment for inflation (Option X1):
Payment:
Insurance (Contractor provides, per Insurance Table A):
Employer provides insurances per Insurance Table B (Assets All Risk, Contract Works, Environmental Liability, General and Public Liability, Transportation (Marine), Motor Fleet and Mobile Plant, Terrorism, Cyber Liability, Nuclear Material Damage and Business Interruption, Nuclear Material Damage Terrorism) – cover per policy documents.
No bid security, performance bond, or retention is stated in the document.
Compliance Requirements
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdf (unknown)ISO 9001:2015 QMS certification is mandatory.
B-bbee:
Security clearance:
POPIA compliance: Each party is an independent Responsible Party and must comply with POPIA when processing shared personal information.
No CSD registration, tax clearance, CIDB grading, or CIPC registration requirements are stated in the document.
Health & Safety
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdfContractor must take all reasonable precautions to maintain health and safety of persons in and about the execution of the service.
Employer may appoint the Contractor as Principal Contractor under the Construction Regulations 2014 (promulgated under the Occupational Health & Safety Act).
Contractor warrants that the total of the Prices includes sufficient amount for proper compliance with the Construction Regulations, all applicable health and safety laws, and the Employer's health and safety rules.
Contractor must comply with the Construction Regulations and all applicable health and safety laws, and ensure subcontractors, employees and others under its control do likewise.
Asbestos management:
Environmental
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdfContractor must comply with all applicable environmental laws and regulations and the Employer's environmental rules, guidelines and procedures, and ensure subcontractors, employees and others under its control do likewise.
Section
Source: TSC - Quality Control Activities and Physical Inspections - 15092026.pdfNo evaluation criteria (scoring, preference points, minimum qualifying score) are stated in the document. The contract is a priced contract with price list (Option A). Low service damages (Option X17) apply, with the service level table in Appendix A. Liability limitations (Option X18) as described in the main evaluation criteria section.
Submission Guidelines
Source: Declaration_of_Shareholding_or_Beneficiaries_Form (1).pdf (unknown)Returnable documents: Tender Schedule T2.2a No 8 – Declaration of Shareholding or Beneficiaries. The form must be completed, signed, and submitted with the bid. It requires disclosure of all shareholders or beneficiaries, their registration numbers, and shareholding percentages, and a declaration of any relationship (including close family members) with Eskom employees.
Evaluation Criteria
Source: Declaration_of_Shareholding_or_Beneficiaries_Form (1).pdf (unknown)Bidders must complete and submit the Declaration of Shareholding or Beneficiaries (T2.2a No 8). Bidders must disclose all shareholders or beneficiaries. Bidders must declare any relationship between shareholders or beneficiaries and Eskom employees, including close family members.
Compliance Requirements
Source: Declaration_of_Shareholding_or_Beneficiaries_Form (1).pdf (unknown)No specific requirements found
Description
Source: Life Saving-Rules.pdfEskom is committed to preventing all work-related injuries and will conduct business with respect and care for people to ensure that no operating condition or urgency of service endangers life or causes injury or damage to the environment. Management will provide and maintain a safe and healthy work environment in accordance with industry standards and legislative requirements. The Life-Saving Rules are safety rules created to enforce zero tolerance for serious at-risk behaviours that have a high probability of causing disabilities or fatalities. These rules complement existing safety best practices and apply at all Eskom locations.
Evaluation Criteria
Source: Life Saving-Rules.pdf (unknown)Bidders must be Eskom contractors or subcontractors and must comply with Eskom's Life-Saving Rules. Contractor employees must sign an acknowledgement of the Life-Saving Rules. Contractors must have processes to investigate and discipline violations within 5 working days. No specific pre-qualification criteria (e.g., CSD, B-BBEE, CIDB) are stated in the provided document.
Technical Specifications
Source: Life Saving-Rules.pdf (unknown)The Life-Saving Rules apply to all Eskom employees, agents, consultants, and contractors. Visitors to Eskom must also respect and adhere to these rules as applicable and could be instructed to leave the premises with immediate effect should they refuse to do so.
The five Life-Saving Rules are:
Health & Safety
Source: Life Saving-Rules.pdfThe five Life-Saving Rules are: 1) Open, isolate, test, earth, bond, and/or insulate before touch - no work on electrical networks without training, permit, risk assessment, and PPE. 2) Hook up at heights - no work at height without medical fitness, risk assessment, training, and fall arrest system. 3) Buckle up - seatbelts mandatory for all drivers, operators, and passengers in vehicles/equipment for Eskom business. 4) Be sober - no person under influence of alcohol or drugs may enter Eskom sites or conduct business. 5) Ensure that you have a permit to work - no work without required permit (e.g., Plant Safety Regulations, ORHVS). Violations result in disciplinary process, zero tolerance, and contractors must remove offending employees from site and initiate disciplinary process within 5 working days.
Section
Source: Life Saving-Rules.pdfNo additional evaluation criteria are stated beyond compliance with Eskom's Life-Saving Rules.
Submission Guidelines
Source: Annexure B.pdf (unknown)Returnable documents:
Evaluation Criteria
Source: Annexure B.pdf (unknown)Evaluation is not described in this document. The only stated requirement is that the signed acknowledgement form and compliance with the listed SHE documents are mandatory for the tender returnable.
Technical Specifications
Source: Annexure B.pdf (unknown)Scope of work is not described in this document. The document only covers SHE compliance obligations for work at Tutuka Power Station.
Quality Management
Source: Annexure B.pdfQuality management is not addressed in this document. The only related point is that financial penalties will be enforced on the main supplier for non-conformance to Eskom and/or statutory SHE requirements, and work stoppages due to SHE issues will not warrant financial compensation claims against Eskom.
Compliance Requirements
Source: Annexure B.pdf (unknown)Mandatory SHE compliance documents (as listed in Annexure B):
Health & Safety
Source: Annexure B.pdfMandatory SHE requirements for the tenderer:
Contractual Terms
Source: Annexure B.pdfContractor and supplier management obligations:
Description
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdfEskom invites tenders for control, co-ordination and performance of quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station for a period of 5 years. Tender number E3581GXMPTUT. Issue date 23 September 2026. Closing date 08 October 2026 at 10:00. Tender validity 120 days.
Important Dates
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdf (TENDER)Closing date: 08 October 2026 at 10:00 (SAST)
Clarification meeting (non-compulsory): 01 October 2026, 10:00–11:30, via MS Teams. Link: https://teams.microsoft.com/meet/31161431309269?p=7pGLAEq2mAT7adhz8s
Tender validity period: 120 days from closing date.
Contact Information
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdf (TENDER)Eskom Representative (for all queries and clarifications):
Fraud and corruption reporting:
Submission: via Eskom E-Tendering site (no physical address provided).
Submission Guidelines
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdf (TENDER)Submission method: electronic only via the Eskom E-Tendering site (Eskom Tender Bulletin). No hard copies accepted. Upload documents under folders: Technical, Commercial, Financial, Other. All documents in PDF format; price list in PDF and Excel. Upload size per document: 500 MB; total submission: 4 GB. No zip/compressed files. If resubmitting, the latest version is accepted; previous versions become null and void. Ensure submission status is marked complete.
Returnable forms (all must be completed, signed where required, and submitted by closing time):
Disqualification risks:
Returnable Documents
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdf (TENDER)Mandatory returnables (disqualifiable if missing): Annexure A (Authorisation), B (Acknowledgement), C (Tenderer's Particulars), D (Integrity Declaration), E (CPA for local goods/services), H (SBD 1), I (SBD 6.1 Preference Points), J (SBD 4 Bidders Disclosure).
Non-disqualifiable (5 working days to correct): Tax Evaluation Questionnaire, Employment Equity compliance proof, NEC contract, pricing schedule, CSD registration.
Prior to award: Safety, quality, environmental returnables, financial statements, tax clearance (if not on CSD).
Evaluation Criteria
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdf (TENDER)Evaluation stages:
Ranking: Price + Specific Goals = total score, ranked highest to lowest. Eskom may award to a tenderer other than the highest scorer if objective criteria justify.
Technical Specifications
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdf (TENDER)Scope: Control, co-ordination and performance of quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station.
Contract period: 5 years.
Key requirements:
Methodology
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdfTechnical Proposal must cover resource allocation, RFI acknowledgement, offsite inspection streamlining, nonconformance follow-through.
Experience & Qualifications
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdfReferences required with project details. Quality Supervisor: 5 years QA/QC, QC training, QMS/auditing knowledge. Mechanical Inspectors: knowledge of plants/items. Welding Inspectors: SAIW Level II or IIW, 3 years welding QC, ISO 9001:2015 and ISO3834.
Quality Management
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdfMandatory ISO 9001:2015 certificate with required scope. Conform to QM58 Category 4: Form A, quality method statement, quality policy, quality objectives, documented information for external processes.
Pricing Schedule
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdfPrices evaluated inclusive of VAT, corrected for errors, excluding contingencies, adjusted for variations, NPV comparison. Unconditional discounts considered. Prices scored out of 90.
Financial Requirements
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdf (TENDER)Payment terms:
Pricing:
Security:
Financial viability:
Compliance Requirements
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdf (TENDER)Mandatory:
Additional (assessed after evaluation, prior to award):
CIDB: Not applicable for this tender.
B-BBEE Requirements
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdf (TENDER)Specific Goals scored out of 10 points under PPPFA. Proof of B-BBEE status: certificate from authorised body, sworn affidavit per B-BBEE Codes, or other prescribed requirement.
Subcontracting/procurement spend on entities with minimum 51% black ownership encouraged. Target: 10% of local procurement content from Black Owned enterprises. Submit proposals for jobs created/retained in South Africa.
Health & Safety
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdfSafety returnables: Annexure B signed, baseline OHS risk assessment, SHE Plan, OHS cost breakdown, letter of good standing, OHS policy signed by CEO, SHE competency CVs/certificates.
Environmental
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdf (TENDER)Environmental returnables: signed acknowledgement of Eskom's SHE rules, waste management plan, environmental policy signed by CEO/MD.
Contractual Terms
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdfNEC3 Term Service Contract with options A, W1, X1, X2, X17, X18, X19, Z. Mandatory contractual requirement: CSD registration. Additional: SHEQ, financial viability. Failure to meet may render non-responsive.
Special Conditions
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdf (TENDER)Skills development: provide 24-month internships for unemployed candidates in Mechanical, Electrical, C&I Engineering. Tenderer bears full cost. Encouraged to procure from 51% black-owned entities (target 10%). Submit job creation proposals.
Requirements
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdf (TENDER)Eligibility criteria:
Mandatory returnables: Annexures A, B, C, D, E, H, I, J, and G1–G4 if applicable. Also CSD number, NEC contract, pricing schedule, ISO 9001:2015 certificate.
Section
Source: Invitation to Tender (ITT) E3581GXMPTUT - QC Control Contract.pdfFunctionality criteria (threshold 70%):
Price scored out of 90; Specific Goals (B-BBEE) scored out of 10. Ranking by total score. Objective criteria may justify award to non-highest scorer.
Submission Guidelines
Source: Authority to submit a tender (Returnable Schedule).pdf (TENDER)Returnable documents:
Evaluation Criteria
Source: Authority to submit a tender (Returnable Schedule).pdf (TENDER)Bidders must complete and sign the Authority to Submit a Tender (returnable schedule) with the certificate applicable to their entity type. For joint ventures, a joint venture agreement and power of attorney are required. For partnerships, signatures from all committing partners are required.
Compliance Requirements
Source: Authority to submit a tender (Returnable Schedule).pdf (TENDER)Joint ventures must provide a joint venture agreement that states all partners are jointly and severally liable for contract execution and that the lead partner is authorised to incur liabilities, receive instructions and payments, and is responsible for the entire execution of the contract. A power of attorney signed by legally authorised signatories of all partners must be attached.
Important Dates
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy -Quality control.pdf (TENDER)Closing date: 8 October 2026 at 10:00 (from tender record). No other dates stated in the document.
Contact Information
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy -Quality control.pdf (TENDER)Buyer: Frans Mametsa
Department: Majuba Power Station
Compiled by: Martin Mojela (Senior Advisor, Supplier Development, Localisation and Industrialisation)
Supported by: David Pule (Middle Manager, Supplier Development, Localisation and Industrialisation)
No email, telephone, or address provided in the document.
Submission Guidelines
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy -Quality control.pdf (TENDER)Returnable documents: SBD 6.2 (Declaration for Local Production and Content) and Annex C (Local Content Declaration-Summary Schedule) are returnable if applicable. All required preference point documents must be submitted with the bid. Submission method and address not stated in the document.
Evaluation Criteria
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy -Quality control.pdf (TENDER)Evaluation uses the 90/10 preference point system. Price scores out of 90; specific goals (B-BBEE status level) score out of 10. Points are added and rounded to two decimal places. Contract awarded to the highest scoring tenderer. Bidders failing to submit preference point documentation are not disqualified but score 0 out of 10 for specific goals and may only score out of 90 for price. Specific goal points by B-BBEE level: Level 1 = 10, Level 2 = 9, Level 3 = 6, Level 4 = 5, Level 5 = 4, Level 6 = 3, Level 7 = 2, Level 8 = 1, Non-compliant = 0.
Technical Specifications
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy -Quality control.pdf (TENDER)Scope: Control, co-ordination and performance of quality control activities and physical inspections on maintenance, outages and projects related activities at Tutuka Power Station.
Duration: 5 years.
Skills development targets (contractual obligations):
Candidates must be from all provinces and representative of South African demographics. Excludes Eskom employees and registered learners. Tenderer bears full cost; Eskom makes no financial contribution.
Methodology
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy -Quality control.pdfSkills development must be delivered directly or through the supply network. SETA-accredited training providers may be approached. Tenderers bear full cost of skills development; Eskom makes no financial contribution. Tenderers may access SETA grants, subsidies, incentives and SARS tax rebates for skills development.
Financial Requirements
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy -Quality control.pdf (TENDER)SDL&I penalty: 2.5% of contract value for failure to meet SDL&I obligations.
Retention: 2.5% of every invoice (excluding VAT) retained as security for SDL&I obligations, released only upon full fulfilment.
Pricing: Tender response must separate local and imported components as per the Price Schedule. Local procurement content is total spending minus imported component.
Compliance Requirements
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy -Quality control.pdf (TENDER)B-BBEE: Valid B-BBEE certificate (SANAS accredited), sworn affidavit, or CIPS affidavit required to claim preference points and is a condition for contract award.
Revenue thresholds: EME (≤ R10m) may submit sworn affidavit; QSE (≤ R50m) must comply with QSE scorecard unless at least 51% black owned; above R50m must submit valid B-BBEE certificate.
Preference point documents: Proof of ownership/shareholding (preferably CIPC documentation) with shareholding breakdown; certified ID copies of shareholders; proof of disability (where applicable); for trusts/consortia/JVs, consolidated B-BBEE verification certificate.
B-BBEE improvement plan: Must be submitted within 30 days of signing contract. Level 4 must achieve Level 3 by end of year one; Levels 5-8 or non-compliant must achieve Level 4 by end of year one, then improve one level each subsequent year.
Local content: Commodity is not a designated sector. SBD 6.2 and Annex C returnable if applicable.
Sworn affidavit validity: Must meet specific requirements (deponent name and ID, designation, enterprise name and address, ownership percentages, revenue, financial year end, status level, empowering supplier status, same signing date for deponent and Commissioner of Oaths, Commissioner cannot be employee or ex officio of enterprise).
B-BBEE Requirements
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy -Quality control.pdf (TENDER)Specific goals: Maximum 10 points based on B-BBEE status level under 90/10 system (Level 1 = 10, Level 2 = 9, Level 3 = 6, Level 4 = 5, Level 5 = 4, Level 6 = 3, Level 7 = 2, Level 8 = 1, Non-compliant = 0). To claim preference points, submit valid B-BBEE certificate (SANAS accredited), sworn affidavit, or CIPS affidavit; proof of ownership/shareholding (preferably CIPC); certified ID copies of shareholders; proof of disability where applicable; consolidated B-BBEE certificate for trusts/consortia/JVs. Bidders failing to provide documentation are not disqualified but score 0 out of 10 for specific goals and may only score out of 90 for price. Objective criteria: Commodity is not a designated sector. SBD 6.2 and Annex C returnable if applicable. Transformation: B-BBEE improvement or retention plan required within 30 days of contract signing. Level 4 must achieve Level 3 by end of year one; Levels 5-8 or non-compliant must achieve Level 4 by end of year one, then improve one level each subsequent year. Valid B-BBEE certificate or sworn affidavit is a condition for contract award. EME (≤ R10m) may submit sworn affidavit; QSE (≤ R50m) must comply with QSE scorecard unless at least 51% black owned; above R50m must submit valid B-BBEE certificate. Local procurement content: Eskom target 100%. Subcontracting: Eskom target 10% procurement from black-owned designated groups. Jobs: Tenderers must submit proposals for jobs created and retained. Skills development: 3 internships (Mechanical, Electrical, C&I) with 24-month programmes. Sworn affidavit validity: Must meet specific requirements including deponent name and ID, designation, enterprise name and address, ownership percentages, revenue, financial year end, status level, empowering supplier status, same signing date for deponent and Commissioner of Oaths, Commissioner cannot be employee or ex officio of enterprise.
Contractual Terms
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy -Quality control.pdf (TENDER)SDL&I obligations are contractual. Penalty of 2.5% of contract value for failure to meet SDL&I obligations. Eskom retains 2.5% of every invoice (excluding VAT) as security, released only upon full fulfilment. Quarterly reporting required. Eskom reviews reports within 30 days and notifies in writing if obligations not met. Corrective measures must be implemented before next report, failing which retention clauses invoked. SDL&I Implementation Schedule must be completed and returned to SDL&I representative for acceptance 28 days after contract award.
Section
Source: Supplier Development Localisation Industrialisation (SDLI) Strategy -Quality control.pdfSpecific goals: Maximum 10 points for B-BBEE status level under 90/10 system. Price scores out of 90. Bidders failing to provide preference point documentation score 0 out of 10 for specific goals and may only score out of 90 for price.
Description
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.pdfThe PAYE Questionnaire is a mandatory tax classification tool for contractors supplying services or labour to Eskom. It determines whether a contractor is an Independent Contractor, Personal Service Provider, Labour Broker, or Dependent Contractor for tax purposes. Contractors must complete the relevant evaluation pack (Pack A for companies/CCs/trusts, Pack B for individuals) and sign required affidavits and declarations.
Important Dates
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.pdf (unknown)The PAYE Questionnaire applies from 1 March 2025 to 28 February 2026.
Contact Information
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.pdf (unknown)Group Tax email: [email protected]
Submission Guidelines
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.pdf (unknown)Returnable documents:
Consequences:
Evaluation Criteria
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.pdf (unknown)The document does not specify a scoring or preference point system. The PAYE questionnaire determines tax classification (Independent Contractor, Personal Service Provider, Labour Broker, or Dependent Contractor) based on answers to residence, employee, income, place/control, and dominant impression tests. The classification affects whether PAYE is withheld and the IRP5/IT3(a) code used.
Technical Specifications
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.pdf (unknown)The document is a tax classification questionnaire, not a technical specification. It applies to contractors supplying services or labour to Eskom Holdings SOC Ltd and its subsidiaries (Eskom Rotek Industries, Eskom Enterprises, Escap, Eskom Finance Company, Eskom Foundation, Eskom National Transmission Company).
Pricing Schedule
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.pdfPAYE withholding rules:
Financial Requirements
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.pdf (unknown)PAYE withholding:
Compliance Requirements
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.pdf (unknown)No specific eligibility criteria (CSD, tax clearance, B-BBEE, CIDB) are stated. Contractors must complete the PAYE questionnaire truthfully and sign required appendices. Non-residents must sign Appendix 9.
Contractual Terms
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.pdf (unknown)Eskom accepts no liability for loss or damages arising from use of the pack. Contractors are responsible for the accuracy and completeness of information provided. The pack will not be automatically updated with changes in legislation.
Requirements
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.pdf (unknown)Contractors must complete the PAYE questionnaire truthfully and sign required appendices. Failure to sign required affidavits or declarations may result in PAYE being withheld from payments. Non-resident contractors must sign Appendix 9 and have their pack referred to Eskom's Group Tax Department.
Section
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.pdfThe document does not specify a scoring or preference point system. The PAYE questionnaire determines tax classification based on answers to residence, employee, income, place/control, and dominant impression tests.
Important Dates
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx (1).pdf (unknown)The pack applies from 1 March 2026 to 28 February 2027.
Contact Information
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx (1).pdf (unknown)Enquiries:
Submission:
Submission Guidelines
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx (1).pdf (unknown)Returnable documents:
Evaluation Criteria
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx (1).pdf (unknown)The pack determines your tax classification for PAYE purposes. Classification is based on your answers to the questionnaire:
Technical Specifications
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx (1).pdf (unknown)Purpose: to determine whether a contractor supplying services to Eskom is classified as an Independent Contractor, Personal Service Provider, Labour Broker, or Dependent Contractor for PAYE purposes.
Applies to: contractors supplying services to Eskom Holdings SOC Ltd and its subsidiaries (Eskom Rotek Industries, Eskom Enterprises, Escap, Eskom Finance Company, Eskom Foundation, Eskom National Transmission Company).
The questionnaire covers residence, employees, connected persons, income concentration, place of work and control, and a dominant impression test.
Pricing Schedule
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx (1).pdfPAYE withholding rules apply based on classification. If a valid IRP30 certificate is provided (labour broker), no PAYE is withheld and an IT3(a) with code 3617 is issued. Without it, PAYE is withheld at individual rates until the certificate is provided, and an IRP5 with code 3617 is issued.
Financial Requirements
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx (1).pdf (unknown)PAYE withholding:
Compliance Requirements
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx (1).pdf (unknown)No specific compliance requirements beyond completing the PAYE questionnaire and signing the required appendices.
Contractual Terms
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx (1).pdf (unknown)The contractor is responsible for the accuracy and completeness of all information provided. Eskom may withhold taxes, interest and penalties from payments if information is inaccurate. The contractor must notify Eskom of any changes to their status. Eskom accepts no liability for loss or damages arising from use of the pack.
Requirements
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx (1).pdf (unknown)Contractors must complete the applicable evaluation pack (A for companies/CCs/trusts, B for individuals) and answer all questions truthfully. Required appendices must be signed as directed; failure to do so results in PAYE being withheld.
Section
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx (1).pdfClassification is determined by the questionnaire answers, including residence, employees, connected persons, income concentration, place/control, and the Dominant Impression Test. The outcome determines whether PAYE is withheld and the IRP5 code used.
Description
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdfThe eTendering system is a web-based platform that allows suppliers to upload tender documents electronically, replacing manual submission at Eskom tender offices. Suppliers must register and verify their email and OTP before accessing the system. Access is available via the TenderBulletin public website or the eTendering website, and a CSD number is required.
Contact Information
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)For problems with the Tender Bulletin, eTendering, or OpenText systems, contact the buyer responsible for the published tender. No specific contact details are provided in the document.
Submission Guidelines
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)Submission is electronic only via the Eskom eTendering system at https://eTendering.eskom.co.za. Bidders must register on the portal and verify their email and cellphone with an OTP before access is granted. A CSD number is required to access the system.
Evaluation Criteria
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)No evaluation criteria specific to this tender are stated in the document. The document only describes the eTendering submission process.
Technical Specifications
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)The document is a user manual for the Eskom eTendering system, not a specification for the tender. It describes how suppliers upload tender documents electronically. No technical requirements for the quality control services are provided.
Methodology
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)Submission process steps: register on the eTendering portal, verify email and OTP, select the tender reference number, create a new submission, upload files under the correct categories (Technical, Commercial, Finance, etc.), and finalize the submission. File size limits: individual files max 50MB, total uploads max 900MB. After finalization, a confirmation email with the submission ID is sent.
Compliance Requirements
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)CSD (Central Supplier Database) number is required to access the eTendering system.
Special Conditions
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)A new functionality allows 'closed tenders' to be added, which are tenders not listed on TenderBulletin but sent directly to selected suppliers who meet the criteria. These suppliers receive a link via email to bid privately.
Description
Source: Scope of Work.pdfThe scope of work covers the control, co-ordination and performance of quality control activities and physical inspections on maintenance, outages and projects at Tutuka Power Station for a period of 5 years. Key responsibilities include co-ordinating and overseeing quality control, conducting daily toolbox talks, performing physical inspections, providing leadership on quality processes, transferring skills to station employees, determining inspection requirements, providing professional advice, raising NCRs for non-compliance, monitoring compliance with Eskom procedures and standards, and submitting weekly quality reports.
Evaluation Criteria
Source: Scope of Work.pdf (unknown)Contractor must comply with Eskom Life Saving rules and all station rules. All personnel must have yearly induction and medical surveillance. All PPE must be SABS approved. Work must be done under a permit to work. Timesheets must be signed by the Services Manager and the contractor.
Technical Specifications
Source: Scope of Work.pdf (unknown)Scope of work includes:
Quality Management
Source: Scope of Work.pdfThe contractor is responsible for quality control activities and physical inspections, including raising NCRs for non-compliance with quality procedures and processes, and monitoring compliance with Eskom procedures, standards, processes, and QCP requirements.
Compliance Requirements
Source: Scope of Work.pdf (unknown)All personnel who enter the station must abide by Eskom rules and regulations and comply with Eskom Life Saving rules. All work to be done under permit to work. Yearly induction and medical surveillance to be done for all personnel. All PPE to be provided by Contractor and must be SABS approved.
Requirements
Source: Scope of Work.pdf (unknown)All Eskom required training will be provided by Eskom. Timesheets must be logged and signed by the Services Manager and the contractor. All PPE must be provided by the contractor and must be SABS approved.
Contact Information
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.pdf (unknown)Eskom Holdings SOC Ltd
Megawatt Park, Maxwell Drive
Sunninghill ext. 3
Sandton
Postal: PO Box 1091, Johannesburg, 2000
No specific contact person, email, or telephone number is provided in the NDA.
Submission Guidelines
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.pdf (unknown)The provided document is a Non-Disclosure Agreement (NDA) template, not the full tender pack. It contains no submission instructions, returnable forms, or closing details. Bidders must sign the NDA as part of the tender process; the NDA must be signed by a duly authorised representative and witnessed. No other submission requirements are stated.
Evaluation Criteria
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.pdf (unknown)No evaluation criteria are stated in the provided document. The NDA does not describe how bids will be scored or any preference point system.
Technical Specifications
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.pdf (unknown)The document is an NDA template; it does not contain technical specifications, scope of work, quantities, or delivery locations for the tender.
Compliance Requirements
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.pdf (unknown)Bidders must be a legally incorporated company (or similar entity) able to enter into a binding agreement. The NDA must be signed by a duly authorised representative, with a witness. No other compliance requirements (e.g., CSD, tax, B-BBEE) are stated in the provided document.
Contractual Terms
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.pdfThe NDA governs the disclosure and use of confidential information between Eskom and the tenderer. Key obligations:
Description
Source: 240-12248652_List of Tender Returnables_Cat 1_ Rev 7.pdfThe tender covers quality control activities and physical inspections for maintenance, outages, and projects at Tutuka Power Station, for a 5-year period.
Important Dates
Source: 240-12248652_List of Tender Returnables_Cat 1_ Rev 7.pdf (TENDER)Closing date: 15 September 2026 (time not stated in the provided document).
Document issue date: 15 September 2026.
Contact Information
Source: 240-12248652_List of Tender Returnables_Cat 1_ Rev 7.pdf (TENDER)Eskom representative: Dimpho Mnisi (no email or telephone provided).
Submission Guidelines
Source: 240-12248652_List of Tender Returnables_Cat 1_ Rev 7.pdf (TENDER)Returnable documents:
Evaluation Criteria
Source: 240-12248652_List of Tender Returnables_Cat 1_ Rev 7.pdf (TENDER)Quality deliverables are evaluated against the following scored sections (each item scored 1 if compliant):
No minimum qualifying score is stated. No other evaluation criteria (price, functionality, preference points) are stated in the provided document.
Quality Management
Source: 240-12248652_List of Tender Returnables_Cat 1_ Rev 7.pdfForm A must be completed and signed as part of the quality requirements.
Compliance Requirements
Source: 240-12248652_List of Tender Returnables_Cat 1_ Rev 7.pdf (TENDER)ISO 9001 certification is required (see evaluation criteria).
No other compliance requirements (CSD, tax clearance, B-BBEE, CIDB) are stated in the provided document.
Section
Source: 240-12248652_List of Tender Returnables_Cat 1_ Rev 7.pdfScored quality sections as detailed in the main evaluation criteria. No additional criteria stated.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
Bathal/Standerton Road - Tutuka Power Station - Standerton - 2340
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
25
Last checked
23 Sept 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Learn how to submit a winning bid with these related articles
Win consulting, legal, accounting, and engineering service contracts with government. Learn registration requirements and proposal strategies.
Win government insurance, banking, actuarial, and financial consulting contracts. FSCA licensing requirements and tender strategies for financial service providers.
Master the art of the consulting bid. How to structure your methodology, price your services competitively, and score maximum evaluation points.
A professional guide for law firms to join the provincial and municipal legal panels in Gauteng, covering compliance, specialization, and bidding.
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Other service activities. Unlock full pricing strategies, bid frequency, and historical win rates.