Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
Maxwell Drive, Eskom Megawatt Park - Sunninghill - Sandton - 2157
Organization Type
GOVERNMENT
Published
28 Aug 2026
OCDS Reference
ocds-9t57fa-167465
ESKOM real estate is establishing a panel contract for multidisciplinary construction minor works at three corporate sites: eric, mwp, and eal. The scope covers electrical, control and instrumentation, architectural, mechanical, and civil works, including manufacture, construction, installation, and commissioning. The contract runs on an as-and-when-required basis for three years, and bidders must meet stringent she compliance requirements, including a valid compensation commissioner's letter of good standing and a site-specific she plan.
B-BBEE minimum level: 6.
Contractor must provide a valid Compensation Commissioner's letter of good standing before commencement, reflecting the company name and nature of business aligned to the scope.
Contractor must develop and submit a site-specific SHE Plan meeting the SHE Specification, all applicable legislation, and Eskom requirements, for approval before work starts.
Contractor must comply with the OHS Act, Construction Regulations, SANS standards, and Eskom SHE/OHS procedures and policies.
A Section 37(2) legal agreement is required.
Contractor must appoint competent staff and a SHE practitioner, and maintain employee records including inductions, skills, and licences.
Contractor must compile and hand over a consolidated health and safety file to the Eskom Project Manager on completion.
Contractor must notify the Provincial Director of the Department of Employment and Labour for construction work falling within Regulation 4 of the Construction Regulations.
Contractor must stop any work that poses a threat to health and safety or the environment.
Continue with tenders sharing this issuer, category, or province.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Monday, 28 September 2026 - 10:00
Venue
https://teams.microsoft.com/meet/352990567945534?p=45r URKRmbbix8VKoyz
Categories
Request for Bid(Open-Tender)
Maxwell Drive, Eskom Megawatt Park - Sunninghill - Sandton - 2157
Tenders in this industry often require registration with these bodies.
Construction Industry Development Board (CIDB) registration is mandatory for almost all public sector construction tenders. Ensure your grading matches the tender value.
Recommended Certifications
Having these can improve your winning chances: NHBRC Registration, ISO 9001:2015 (Quality Management), ISO 14001:2015 (Environmental Management), ISO 45001:2018 (Occupational Health & Safety), SACPCMP Registration, ECSA Registration
AI Document Analysis Stages
Description
Source: Technical Spec.pdf (unknown)28 Aug
2026
Tender Published
Tender was published
28 Sept
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdf
Eskom is procuring a panel of contractors for renovations and refurbishment works at its Megawatt Park, Eskom Academy of Learning, and Eskom Research Innovation Centre campuses, on an as-and-when-required basis over three years. The contract is an NEC3 Engineering and Construction Contract, priced per task order, with a start date of 1 November 2026.
20260703_Cat2- Quality Req _ ERE Renovations and Refurbishment .pdf
Eskom is procuring a panel contract for renovations and refurbishment works at its Megawatt Park (MWP), Eskom Academy of Learning (EAL), and Eskom Research Innovation Centre (ERIC) campuses, on an as-and-when-required basis for three years. The tender includes quality management system requirements and evaluation criteria.
20260630_GFD_ERE_Minor Works_EAL,ERIC,MWP.xlsx
Provision for the Renovations and Refurbishment panel Contract at Megawatt Park (MWP), Eskom Academy of Learning (EAL) and Eskom Research Innovation Centre (ERIC) Campuses on an "as and when required basis" for a period of three (03) years.
Technical Spec.pdf
This is the Employer's technical specification (unique reference 363-ERE-AABZ28-SP0004-18) governing construction work and plant installation on Eskom Real Estate properties. It sets out the scope, standards, management arrangements)Skip. It covers weekly and ad hoc meeting requirements, and refers to the OHS Act for health and safety compliance.
Invitation to Tender (ITT).pdf
Eskom is procuring a panel of contractors for renovations and refurbishment work at three Gauteng campuses (Megawatt Park, Eskom Academy of Learning, and Eskom Research Innovation Centre) on an as-and-when-required basis for three years. The contract will be awarded to the six highest-scoring technically compliant bidders, with individual task orders issued under an NEC Engineering and Construction Contract.
20260630_Spec_GFD_ERE_Coporate Sites_Minor works Spec_Rev01.pdf
Analysis completed but response format was invalid
Environmental Requirements- Multidisciplinary Construction Scope for Minor Works.pdf
Eskom is procuring a panel contract for renovation and refurbishment works at its Megawatt Park, Eskom Academy of Learning, and Eskom Research Innovation Centre campuses, on an as-and-when-required basis over three years. The contract requires contractors to comply with environmental management standards, including ISO 14001 compliance and the development of project-specific environmental, waste, and emergency preparedness plans.
240-77471651 Annexure C 1.pdf
Analysis completed but response format was invalid
240-105658000 Supplier Quality Management Specification (3).pdf
Eskom is establishing a panel contract for renovations and refurbishment works at three Gauteng campuses — Megawatt Park (MWP), Eskom Academy of Learning (EAL) and Eskom Research Innovation Centre (ERIC) — on an as-and-when-required basis for three years. The tender is governed by Eskom's Supplier Quality Management specification, which sets out quality management system requirements, quality plans, and inspection and test plans that bidders must comply with.
20260703_ Form A Cat2_ ERE Renovations and Refurbish.pdf
Eskom is procuring a panel contract for renovations and refurbishment works at its Megawatt Park (MWP), Eskom Academy of Learning (EAL), and Eskom Research Innovation Centre (ERIC) campuses, on an as-and-when-required basis over a three-year period. The tender includes a quality management requirement aligned with ISO 9001, with specific clauses covering pre-contract award quality, supplier capability and performance, and post-contract execution.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
R 2 479 688
Range
Based on 21 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Purpose: set standard technical requirements for minor construction works at Eskom Real Estate properties, both new and existing.
Contract based on NEC conditions.
Contractor responsibilities: engineering (where required), procurement, installation, quality control, commissioning, and spares.
Applicability: Eskom Real Estate only.
Normative references: ISO 9001, Construction Regulations 2014, Eskom SHEQ Policy, OHS Act, National Building Regulations, SANS 10400, SANS 10142-1, SANS 10114, SANS 204, SANS 10389, SANS 10139, SANS 50054, SANS 10287, and various Eskom standards.
Definitions: acceptance, commissioning, equipment, HAZLOC, IP rating, luminaire, switchboard, switchgear, type test.
Contact Information
Source: Technical Spec.pdf (unknown){"name":null,"email":null,"phone":"011 800 2714","department":"s for lighting, switches, conduits etc, shall be as per 240-55714363","address":"ssioning, of all equipment, instrumentation, controllers, wiring, and associated"}
Evaluation Criteria
Source: Technical Spec.pdf (unknown)No eligibility criteria specified
Technical Specifications
Source: Technical Spec.pdf (unknown)Scope: Renovations and refurbishment of Eskom Real Estate properties at Megawatt Park (MWP), Eskom Academy of Learning (EAL), and Eskom Research and Innovation Centre (ERIC) campuses, on an as-and-when-required basis for three years.
Works include: engineering (design where required), procurement, installation, quality control, commissioning, and spares supply.
Disciplines: architectural, electrical, control and instrumentation, civil, and mechanical engineering.
Specific installations: power supply cables, distribution boards, miniature circuit breakers, lighting, junction boxes, conduits, busbars, switchgear assemblies, ceilings, tiles, vinyl flooring, laminated timber flooring, HVAC and split units, fire detection and protection systems.
Security systems at all campuses: access control (biometrics and card readers), pedestrian turnstiles, CCTV surveillance, intruder detection, high security fences (concrete palisade and welded mesh), security perimeter lighting, control rooms (video walls and workstations). X-ray machines and metal detectors at MWP only.
Standards: comply with SANS 10142-1 (wiring), SANS 10114 (lighting), SANS 204 (energy efficiency), SANS 10400 (national building regulations), SANS 10139 and SANS 50054 (fire detection), SANS 10287 (sprinklers), and Eskom standards (e.g., 240-55714363 lighting, 240-56356396 earthing).
Quality: execute per approved Method Statement and Quality Control Plan (QCP)/Inspection and Test Plan (ITP).
Commissioning: provide commissioning requirements, competent persons for on-site advice and supervision.
Spares: provide comprehensive spares list, single-unit replacement cost, and recommended min/max stock based on lead time, turnaround, and failure rate.
As-built drawings, operating manuals, and maintenance schedules required.
Certificate of Compliance required for electrical installations after verification testing.
Methodology
Source: Technical Spec.pdf (unknown)Contractor must submit a single Project Implementation Plan (PIP) covering entire scope.
If conflict of method or approach, adopt the specification/recommendation/regulation with most accurate conditions; submit details of conflicts and adopted provisions to Employer.
Employer does not assume responsibility for completeness or accuracy of surveys/analysis of existing infrastructure.
Employer's review and commentary on Contractor's documentation does not absolve Contractor of liability.
Contractor must validate and assume responsibility for scope and accuracy of Employer-provided data.
Contractor must plan and execute additional site investigations as needed.
Quality Management
Source: Technical Spec.pdf (unknown)Quality control: execute per approved Method Statement and QCP/ITP.
Quality assurance documents required: List of Tender Returnable/Quality Requirement Document (240-12248652), Form A (240-68099512), QM 58 (240-105658000), Contract Quality Plan (240-109253698), QCP/ITP (240-109253302).
Quality documentation includes manufacturing, construction, commissioning, testing, operating, maintenance, handover, decommissioning, health and safety, and quality plans.
Electrical installations: full verification testing per SANS 10142-1; at least 12 types of tests; results recorded on Inspection and Test Report (ITR); Certificate of Compliance required.
Luminaires: samples must meet photometric requirements per Eskom standard 240-55714363; rejected if they fail.
MCCBs: comply with Eskom standard 240-56227516.
Trenching: LV cable burial depth 500 mm, width 450 mm per SANS 10142-1.
Earthing: TN-S system; comply with SANS 10142-1, SANS 1063, and Eskom earthing standard.
Financial Requirements
Source: Technical Spec.pdf (unknown)Bonds/guarantees: form and requirements per Part 1 Agreements and Contract Data, document C1.3. Payment may be withheld until required bond/guarantee is received and accepted.
Invoicing: must include contractor name and address, project manager name, contract number and title, contractor VAT number, employer VAT number 4740101508, description of service per price list, total excluding VAT, VAT, and total including VAT.
Insurance: provided by the Employer (contact Cluster Manager, Eskom Insurance Management Services).
Compliance Requirements
Source: Technical Spec.pdf (unknown)Comply with Occupational Health and Safety Act and Construction Regulations 2014.
Comply with Eskom SHEQ Policy (32-727).
Comply with National Building Regulations and SANS 10400.
Quality management: ISO 9001 / SANS 9001.
Environmental: comply with National Environmental Management Act, 1998; report environmental incidents within 24 hours.
Fire protection: comply with SANS 10139, SANS 50054, SANS 10287, and Eskom fire standards.
Electrical: comply with SANS 10142-1 and Eskom earthing/lightning standards.
Returnable quality documents: List of Tender Returnable/Quality Requirement Document (240-12248652), Form A (240-68099512), QM 58 (240-105658000), Contract Quality Plan (240-109253698), QCP/ITP (240-109253302).
Health & Safety
Source: Technical Spec.pdf (unknown)Comply with Occupational Health and Safety Act and Construction Regulations 2014.
Comply with Eskom SHEQ Policy (32-727).
Health and safety risk management required.
All necessary regulatory health and safety procedures for the works must be followed.
Environmental incidents must be reported to Employer within 24 hours.
Employer may suspend works if safety or environmental measures are inadequate.
Environmental
Source: Technical Spec.pdf (unknown)Comply with National Environmental Management Act, 1998.
Environmental Impact Assessments (EIAs) and Environmental Management Plans (EMPs) required where applicable.
Contractor responsible for keeping work area clean of environmental waste.
All environmental incidents reported to Employer within 24 hours and recorded in Environmental Incident register.
Employer may suspend works if environmental protection measures are not adequately implemented.
Comply with all applicable environmental legislation and conditions of environmental approvals.
Contractual Terms
Source: Technical Spec.pdf (unknown)Contract based on NEC conditions.
Contractor responsible for design (where required) and must validate Employer-provided data.
Contractor must plan and execute additional site investigations if needed.
Discrepancies between Employer documentation and Contractor's perception must be resolved.
Contractor must submit a single Project Implementation Plan (PIP) covering entire scope.
Bonds/guarantees: per Part 1 Agreements and Contract Data, document C1.3.
Payment may be withheld until required bond/guarantee is received.
Insurance provided by Employer.
Contractor must keep records of defined cost, payments, and compensation events.
Employer may suspend works if environmental protection measures are inadequate.
Confidentiality: Contractor's work for Employer is confidential; no disclosure without consent.
Description
Source: 20260703_Cat2- Quality Req _ ERE Renovations and Refurbishment .pdf (TENDER)The tender is for a panel contract for renovations and refurbishment at three Eskom campuses: Megawatt Park (MWP), Eskom Academy of Learning (EAL), and Eskom Research Innovation Centre (ERIC), on an 'as and when required' basis for three years.
Contact Information
Source: 20260703_Cat2- Quality Req _ ERE Renovations and Refurbishment .pdf (TENDER)Eskom representative: Bongi Tshabalala (named in the document). No contact details provided.
Submission Guidelines
Source: 20260703_Cat2- Quality Req _ ERE Renovations and Refurbishment .pdf (TENDER)Returnable documents for Category 2 (Quality Requirements) must be submitted with the tender. Required items include: a valid ISO 9001 certificate (Option 1) or documented QMS evidence (Option 2), evidence of QMS in operation, a draft Contract Quality Plan, a draft Inspection and Test Plan (ITP) or Quality Control Plan (QCP), and a completed and signed Form A. All documents must be provided as per the tender requirements.
Evaluation Criteria
Source: 20260703_Cat2- Quality Req _ ERE Renovations and Refurbishment .pdf (TENDER)Evaluation under Category 2 (Quality Requirements) uses a scoring system where each applicable item scores 1 point. Section A (QMS) offers two options: Option 1 (valid ISO 9001 certification) scores up to 4 points; Option 2 (documented QMS) scores up to 7 points. Section B (Evidence of QMS in operation) scores up to 4 points. Section C (Contract Quality Plan) scores 1 point. Section D (ITP/QCP) scores 1 point. Section E (Form A) scores 1 point. Bidders must meet the quality requirements to be evaluated.
Technical Specifications
Source: 20260703_Cat2- Quality Req _ ERE Renovations and Refurbishment .pdf (TENDER)The tender covers renovations and refurbishment panel contract at Megawatt Park (MWP), Eskom Academy of Learning (EAL), and Eskom Research Innovation Centre (ERIC) campuses, on an 'as and when required' basis for three years. Quality requirements include: documented information for control of externally provided processes, products and services (Clause 8.4 of ISO 9001:2015), including criteria for evaluation, selection, monitoring of performance, and re-evaluation of external providers.
Quality Management
Source: 20260703_Cat2- Quality Req _ ERE Renovations and Refurbishment .pdf (TENDER)Quality management requirements include: a valid ISO 9001 certificate (Option 1) or documented QMS (Option 2) with quality policy, objectives, control of documented information, control of nonconforming outputs, corrective action, and internal audit. Evidence of QMS in operation includes organization chart, responsibility matrix, control of external providers, internal audit report, and management review records. A draft Contract Quality Plan and a draft ITP/QCP are required. Form A must be completed and signed.
Compliance Requirements
Source: 20260703_Cat2- Quality Req _ ERE Renovations and Refurbishment .pdf (TENDER)Bidders must comply with the quality management system requirements as per Category 2. This includes either holding a valid ISO 9001 certificate (with relevant scope, issued by an approved and accredited certification authority) or demonstrating documented compliance with ISO 9001 clauses. Submission of the required quality documents is mandatory for evaluation.
Section
Source: 20260703_Cat2- Quality Req _ ERE Renovations and Refurbishment .pdf (TENDER)Quality evaluation scoring: Section A (QMS) Option 1 scores up to 4 points (valid ISO 9001 certification); Option 2 scores up to 7 points (documented QMS). Section B (Evidence of QMS in operation) scores up to 4 points. Section C (Contract Quality Plan) scores 1 point. Section D (ITP/QCP) scores 1 point. Section E (Form A) scores 1 point. Each applicable item scores 1 point.
Submission Guidelines
Source: 20260703_ Form A Cat2_ ERE Renovations and Refurbish.pdf (unknown)Returnable document: Form A (Tender & Contract Quality Requirements for ISO 9001) must be completed, signed by the tenderer's quality representative, and submitted with the bid. The form requires marking each applicable quality clause with an X (or - if not applicable) and selecting only one category (Category 2 is indicated as applicable).
Evaluation Criteria
Source: 20260703_ Form A Cat2_ ERE Renovations and Refurbish.pdf (unknown)No explicit evaluation criteria are stated in the provided document. The only requirement is completion of the quality declaration form (Form A) and compliance with the ISO 9001 quality clauses as indicated. No CSD registration, tax clearance, B-BBEE level, CIDB grading, or other pre-qualification thresholds are mentioned.
Technical Specifications
Source: 20260703_ Form A Cat2_ ERE Renovations and Refurbish.pdf (unknown)The tender is for renovations and refurbishment panel contract at Megawatt Park (MWP), Eskom Academy of Learning (EAL) and Eskom Research Innovation Centre (ERIC) campuses on an 'as and when required basis' for a period of three (03) years. The document indicates Category 2 quality requirements apply (refer to clause 3.5 of specification 240-105658000). Main Supplier and Sub-supplier Capability and Capacity Assessment is applicable.
Methodology
Source: 20260703_ Form A Cat2_ ERE Renovations and Refurbish.pdf (unknown)The document lists ISO 9001 standard clauses (Context of the Organisation, Leadership, Planning, Support, Operation, Performance Evaluations, Improvement) and quality principles (Customer focus, Leadership, Engagement of people, Process approach, Improvement, Evidence based decision making, Relationship Management) that are marked as applicable. The tenderer must indicate applicability of each with an X or - as applicable.
Quality Management
Source: 20260703_ Form A Cat2_ ERE Renovations and Refurbish.pdf (unknown)The tender requires compliance with Eskom's quality requirements for ISO 9001 standard (document 240-105658000). The tenderer must indicate applicability of each quality clause with an X or - as applicable. Category 2 is selected (refer to clause 3.5 of specification 240-105658000). Main Supplier and Sub-supplier Capability and Capacity Assessment is applicable. Post-contract award requirements include contract execution, supplier quality performance monitoring, Eskom rights of access, rights to information, preservation, quality audits, management of nonconformities, and special processes.
Description
Source: 20260630_GFD_ERE_Minor Works_EAL,ERIC,MWP.xlsx (unknown)The document is an Occupational Health and Safety Baseline Risk Assessment template for Eskom Real Estate, Design and Engineering department. It covers activities such as maintenance of air-conditioning systems, replacement of light features/bulbs, maintenance of lifts and escalators, maintenance of electricity distribution boards, construction work site activities, diesel storage, maintenance activities, and office work environment tasks. The template requires identifying hazards, assessing risks, and listing controls.
Evaluation Criteria
Source: 20260630_GFD_ERE_Minor Works_EAL,ERIC,MWP.xlsx (unknown)Bidders must be able to perform renovations and refurbishment work on an as-and-when-required basis across the Megawatt Park, Eskom Academy of Learning, and Eskom Research Innovation Centre campuses. The document does not specify additional eligibility criteria such as CSD registration, tax clearance, B-BBEE level, CIDB grading, or other pre-qualifications.
Technical Specifications
Source: 20260630_GFD_ERE_Minor Works_EAL,ERIC,MWP.xlsx (unknown)The document provides an Occupational Health and Safety Baseline Risk Assessment template. It lists activities such as maintenance of air-conditioning systems, replacement of light features/bulbs, maintenance of lifts and escalators, maintenance of electricity distribution boards, construction work site activities, diesel storage, maintenance activities, and office work environment tasks. For each activity, hazards, risks, existing controls, risk priority ratings, and additional controls are identified. The template requires listing specific activities, indicating routine or non-routine, identifying hazards, associated risks, exposed groups, risk owners, exposure patterns, possible consequences, existing controls, risk priority ratings, additional controls, monitoring mechanisms, control owners, legal requirements, target dates, current status, and IRM reference numbers.
Compliance Requirements
Source: 20260630_GFD_ERE_Minor Works_EAL,ERIC,MWP.xlsx (unknown)The document references the OHS Act (Act No 85 of 1993) and SANS standards (e.g., SANS 1545, SANS 53015) as legal and other requirements for the risk assessment. No other compliance requirements are specified.
Description
Source: Environmental Requirements- Multidisciplinary Construction Scope for Minor Works.pdf (unknown)The document is an environmental requirements checklist for a multidisciplinary construction scope for minor works. It lists four mandatory environmental management documents: policy, EMP, waste management plan, and emergency preparedness plan.
Evaluation Criteria
Source: Environmental Requirements- Multidisciplinary Construction Scope for Minor Works.pdf (unknown)Compliance with ISO 14001:2015 is required; certification is not mandatory but compliance is. The contractor must have an environmental policy signed by a senior company member. No other eligibility criteria (e.g., CIDB grading, B-BBEE, tax clearance) are stated in the provided document.
Technical Specifications
Source: Environmental Requirements- Multidisciplinary Construction Scope for Minor Works.pdf (unknown)The contractor must develop and implement the following environmental documents for the multidisciplinary construction scope for minor works:
Compliance Requirements
Source: Environmental Requirements- Multidisciplinary Construction Scope for Minor Works.pdf (unknown)No specific compliance requirements beyond the environmental documents listed in technical specifications.
Environmental
Source: Environmental Requirements- Multidisciplinary Construction Scope for Minor Works.pdf (unknown)Emergency Preparedness Plan: Must be developed and implemented to effectively respond to environmental incidents such as wildfires, fuel spills, and adverse weather conditions.
Contact Information
Source: 240-77471651 Annexure C 1.pdf (unknown)Eskom OHS Representative (designation and signature required on the evaluation template). No name, email, phone, or submission address stated in this document.
Submission Guidelines
Source: 240-77471651 Annexure C 1.pdf (unknown)Returnable OHS documents (Annexure C 1, high-risk template) — all must be signed and submitted with the tender:
Disqualification risks:
Evaluation Criteria
Source: 240-77471651 Annexure C 1.pdf (unknown)OHS tender evaluation (high risk) is a gate/qualification stage: the tenderer is recommended or not recommended based on submission of all OHS returnables. No scoring split or minimum qualifying score is stated in this annexure.
Technical Specifications
Source: 240-77471651 Annexure C 1.pdf (unknown)Scope of work: renovations and refurbishment panel contract at Megawatt Park (MWP), Eskom Academy of Learning (EAL) and Eskom Research Innovation Centre (ERIC) campuses, on an 'as and when required' basis for three (03) years. The OHS requirements must address the project/scope OHS risks and align with the health and safety specification.
Experience & Qualifications
Source: 240-77471651 Annexure C 1.pdf (unknown)OHS competency must be demonstrated considering the scope of work, risks, OHS plan and applicability. Submit CVs and qualifications/certificates listing the competencies required.
Financial Requirements
Source: 240-77471651 Annexure C 1.pdf (unknown)OHS costing must be detailed and broken down, not a lump sum, and based on the overall scope of work/service to be performed. The scope of work and risk assessment may serve as a guideline.
Compliance Requirements
Source: 240-77471651 Annexure C 1.pdf (unknown)Returnables:
Health & Safety
Source: 240-77471651 Annexure C 1.pdf (unknown)Mandatory OHS returnables:
Section
Source: 240-77471651 Annexure C 1.pdf (unknown)OHS evaluation is a pass/fail gate: the tenderer is marked 'Recommended' or 'Not Recommended' based on submission of all OHS returnables. No scoring weights or minimum scores are stated.
Description
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)This is the Supplier Quality Management Specification (240-105658000, Revision 3) for Eskom Holdings SOC Ltd. It defines minimum quality requirements for selection, evaluation, vendor registration, management, monitoring, assessment, and auditing of all existing and potential suppliers and sub-suppliers across all Eskom divisions and subsidiaries. The specification forms part of all RFIs, RFQs, RFPs, and contracts for procurement of products and services. It is a controlled disclosure document effective from authorisation date (17 October 2021) with next review due October 2024.
Important Dates
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Document revision date: 17 October 2021. Next review date: October 2024. No tender-specific closing date, briefing, or site visit dates are stated in this specification.
Contact Information
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Eskom Quality representative/professional selects applicable requirements using Form A. No specific SCM or technical contact names, emails, or phone numbers are provided in this specification.
Submission Guidelines
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Returnable documents: Suppliers must complete and sign Form A (Tender and Contract Quality Requirements for Supplier Quality Management Specification 240-105658000/QM 58 and ISO 9001) and submit it with the other returnables listed in the List of Tender Returnables document (240-12248652). The applicable quality category (1, 2, 3, or 4) is indicated in Form A by the Eskom Quality representative. Suppliers must prepare and submit quality documentation according to the selected category. Where specified in the evaluation criteria, each product, service, or process must have a documented, implemented, reviewed, and maintained Contract Quality Plan and/or Quality Control Plan (Inspection and Test Plan).
Evaluation Criteria
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Quality requirements are classified into four categories (Category 1, 2, 3, or 4). Only one category applies per procurement process, as indicated in Form A. Suppliers must prepare and submit quality documentation according to the selected category using the List of Tender Returnables. Where specified in the evaluation criteria, each product, service, or process must have a documented, implemented, reviewed, and maintained Contract Quality Plan and/or Quality Control Plan (Inspection and Test Plan).
Technical Specifications
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Scope: This specification defines minimum quality requirements for all existing and potential Eskom suppliers and sub-suppliers, applicable across all Eskom divisions, subsidiaries, and procurement processes (RFI, RFQ, RFP, contracts).
QMS Requirements: Suppliers must develop, implement, maintain, and continually improve a Quality Management System (QMS) conforming to ISO 9001 (latest revision). The QMS must include documented information such as Quality Manual, Quality Policy, Quality Objectives, control of documented information, internal audit procedure, control of nonconforming outputs, and nonconformity/corrective action procedure.
Special Processes: Welding, NDE, coating, heat treatment, and other special processes require qualified personnel and documented procedures (WPS, PQR, WQR) reviewed and accepted before manufacture. Personnel must be certified competent per SETA requirements or internal procedures.
Contract Quality Plan (CQP): Must address ISO 10005 elements plus management of records (material tests, PMI, certifications), free access for Eskom inspection, final documentation submission before shipment, special process management, personnel qualification, storage/preservation instructions, and sub-supplier monitoring. CQPs must be submitted before kick-off or manufacturing commencement.
Quality Control Plan (QCP)/Inspection and Test Plan (ITP): Must cover all stages from contract review through commissioning, include hold/witness points, acceptance criteria, inspection records, and be accepted by Eskom or its inspection agency before work starts. Separate QCP/ITP required for each sub-supplier scope.
Preservation: Supplier must implement a preservation management programme covering valves, motors, rotating equipment, piping, instrumentation, flanges, gaskets, coatings, insulation, and other materials. Requirements documented in purchase orders and work authorisations. Eskom must have free access to preservation records.
Nonconformity Management: Supplier must establish processes for nonconformity identification, correction, corrective action, and defect management. Eskom reserves rights to access, audit, and appoint resident inspectors at supplier/sub-supplier premises at no cost to Eskom.
Sub-supplier Management: Main supplier responsible for defining and managing sub-supplier quality assurance/control, performance management programme (QMS verification, audits, CQP/QCP reviews, NC management, ITPs, risk management), and ensuring sub-supplier QCPs/ITPs comply with Eskom requirements.
Methodology
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Preservation Work Plan: Supplier must develop and execute a preservation work plan including clear descriptions of equipment and locations, identification of quality verification activities and stages, and reference to relevant procedures or method statements. Supplier must review and track compliance with Eskom and sub-supplier preservation requirements, evaluate storage sites, and manage preservation records in compliance with Eskom information management requirements.
Quality Planning: Contract Quality Plans must address quality assurance elements per ISO 10005 plus Eskom-specific requirements. Quality Control Plans/Inspection and Test Plans must address quality control elements in chronological order from contract review through commissioning, including hold/witness points, acceptance criteria, and inspection records.
Method Statements: Special installation, fabrication, and manufacturing procedures (post-weld heat treatment, tube rolling, coatings, etc.) require supplier review and acceptance before manufacture. Eskom provides templates for CQP (240-109253698), QCP/ITP (240-109253302), and Method Statement (240-126469599) as guidelines where supplier lacks own templates.
Experience & Qualifications
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Quality audits and quality performance reviews must be carried out by trained, accredited, and experienced personnel in accordance with documented procedures. Personnel performing special processes (NDE, welding, coating, heat treatment, etc.) must be suitably qualified and, where applicable, registered with statutory bodies (e.g., radiographic workers for radiography). Welder qualification records (WQR), welding procedure specifications (WPS), and procedure qualification records (PQR) must be managed and maintained. All personnel affecting quality must have identified training needs, implemented training per company procedures, and certificates meeting SETA requirements (unit standard completed, accredited provider number).
Quality Management
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)QMS Framework: Suppliers must develop, implement, maintain, and continually improve a QMS based on ISO 9001 (latest revision). The QMS must include Quality Manual, Quality Policy (aligned with strategic direction), Quality Objectives, control of documented information (maintain and retain), internal audit procedure, control of nonconforming outputs, and nonconformity/corrective action procedure.
Special Processes: Welding, NDE, coating, heat treatment, and other special processes require qualified personnel and documented procedures (WPS, PQR, WQR) reviewed and accepted before manufacture. Personnel must be certified competent per SETA requirements or internal procedures. Training certificates must meet SETA requirements (unit standard completed, accredited provider).
Documentation Management: Supplier must manage records including material tests, PMI testing, material certifications. Final manufacturing data book must be submitted before shipment. Workplace documentation must be available in English and workforce-appropriate languages.
Sub-supplier Quality Management: Main supplier must develop and implement performance management programme covering QMS verification, audits/surveillances, CQP/QCP reviews, NC/defect management, inspection/test plans, and risk management. Main supplier accountable for all sub-supplier QCPs/ITPs.
Change Control: Supplier must inform Eskom of any proposed QMS or staff changes affecting quality prior to implementation.
Quality Audits: Must be carried out by trained, accredited, and experienced personnel per documented procedures. Eskom reserves right to audit sub-supplier facilities.
Compliance Requirements
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Mandatory Standards: ISO 9001 (Quality Management Systems – Requirements), ISO 10005 (Guidelines for Quality Plans).
Referenced Standards: ISO 9000, ISO 10006, ISO 9004, Eskom SHEQ Policy (32-727), IAEA GS-R-3.1, PPPFA, CIDB Best Practice Guideline A4, SANS 10845-1, Eskom Procurement and Supply Chain Management Policy (32-1033) and Procedure (32-1034).
Forms: Form A (240-68099512) must be completed and signed. List of Tender Returnables (240-12248652) defines specific returnables per tender.
Certification: Valid ISO 9001 certificate from accredited certification body required unless excluded by quality category. Internal and external audit reports with nonconformities and remedial actions must be submitted.
Sub-supplier Compliance: Main supplier must ensure sub-suppliers meet applicable QMS requirements, especially for design, manufacturing, maintenance, testing, storage, delivery, installation, commissioning, and project management scopes.
Change Notification: Supplier must inform Eskom of any proposed QMS or staff changes affecting quality prior to implementation.
Health & Safety
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)The specification references Eskom's Safety, Health, Environment and Quality (SHEQ) Policy (document 32-727) and the IAEA Safety Standard GS-R-3.1 for application of the management system. Suppliers must comply with these standards as applicable. No further health and safety requirements are detailed in this specification.
Contractual Terms
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Preservation Management: Supplier must implement a preservation programme covering valves, electrical motors, mechanical/rotating equipment, piping, instrumentation, flange faces, gaskets, coatings, insulation, and other materials. Requirements must be documented in purchase orders and work authorisations. Sub-supplier input must be documented. Requirements must be communicated to logistics, construction, quality, security, and other project areas. Supplier must clearly define sub-supplier preservation responsibilities. Eskom must have free and unrestricted access to all preservation records for inspection and audit.
Rights of Access: Eskom reserves right of free and uninhibited access to supplier and sub-supplier premises for inspection, audit, and monitoring. Eskom may appoint resident quality inspectors at supplier/sub-supplier premises; supplier must provide workspace at no cost to Eskom.
Eskom Rights to Information: Eskom may request and review all quality-related documentation and records.
Nonconformity Management: Supplier must manage nonconformities and nonconforming outputs identified by Eskom. Eskom may appoint any organisation as Approved Inspection Authority (AIA) or inspection agency; supplier may not object or hinder their work.
Contract Addendums: Once signed, ITPs and QCPs become addendums to the main contract and can be reviewed at Eskom's discretion.
Quality Kick-off Meetings: Mandatory at contract start and each subsequent phase. 14 days' advance notice required. Pre-inspection meetings convened by Eskom or its agency must be attended by supplier/sub-supplier quality representatives.
Section
Source: 240-105658000 Supplier Quality Management Specification (3).pdf (unknown)Quality requirements are categorised into four categories (1, 2, 3, or 4). Only one category applies per procurement process, as indicated in Form A by the Eskom Quality representative. Suppliers must prepare and submit quality documentation per the selected category using the List of Tender Returnables (240-12248652). Where specified in the evaluation criteria, each product, service, or process must have a documented Contract Quality Plan and/or Quality Control Plan (Inspection and Test Plan). Category 1 requires ISO 9001 certificate, audit reports, draft CQP, example ITP/QCP, control of externally provided processes, roles/responsibilities documentation, and management review records. Category 2 requires objective evidence of implemented QMS (manual, policy, objectives, procedures), audit reports, draft CQP, example ITP/QCP, control of externally provided processes, roles/responsibilities, and management review records. Category 3 requires objective evidence of developed QMS (manual, policy, objectives, procedures), draft CQP, example ITP/QCP, control of externally provided processes, and roles/responsibilities. Category 4 requires quality method statement based on ISO 9001, signed quality policy, quality objectives, control of externally provided processes, and project-specific roles/responsibilities.
Description
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdfConstruction Contract
ESKOM HOLDINGS SOC Ltd (Reg No. 2002/015527/30)
Between
and
Provision for the Renovations and Refurbishment panel
for Contract at Megawatt Park (MWP), Eskom Academy of
Learning (EAL) and Eskom Research Innovation Centre (ERIC)
Campuses on an “as and when required basis” for a period of
three (03) years.
Content:
Part C1 Agreements & Contract Data
Part C2 Pricing Date
Part C3 Scope of Work
Important Dates
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdf (unknown)Base date for inflation indices: 01 December 2025. Tendered prices fixed for first 12 months, then subject to escalation. Completion date: 36 months from contract start. Defects date: 12 months (52 weeks) from completion per house, per activity schedule. Defect correction period: 7 days after notification (long lead items 6-10 weeks). Payment assessment interval: 25th of each month. Payment within 30 days after assessment and tax invoice.
Contact Information
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdf (unknown)Employer: Eskom Holdings SOC Ltd (reg no: 2002/015527/30), a state-owned company. Employer's VAT number: 4740101508. Dispute resolution: Adjudicator from ICE-SA Panel; if no agreement, appointed by AFSA; arbitration under Association of Arbitrators (Southern Africa) rules, place South Africa.
Submission Guidelines
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdf (unknown)Submit the completed Form of Offer and Acceptance (Part C1.1) with the Schedule of Deviations, if any. The tenderer must contact the Employer's agent within two weeks of receiving the completed agreement to arrange delivery of securities, bonds, guarantees, proof of insurance, and other documentation. Failure to fulfil these obligations constitutes repudiation. The agreement comes into effect when the tenderer receives a fully completed signed copy. The tenderer has five working days to notify the Employer in writing of any reason for non-acceptance. Alternative tenders require a separate copy of the Form of Offer and Acceptance.
Evaluation Criteria
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdf (unknown)Low performance damages: R 2,000 per day for each incident, up to a maximum of 10 days, for: non-compliance with Safety file/plan requirements (if not approved within 1 week from submission, deemed approved); failure to revise the Programme as agreed; Quality Control Plan not submitted per schedule and delays activity start; quality non-compliance where Contractor fails to notify Employer or fails to comply with approved witness points on Quality Control Plans; reworks done three times or more.
Technical Specifications
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdf (unknown)Contract for renovations and refurbishment at Megawatt Park (MWP), Eskom Academy of Learning (EAL), and Eskom Research Innovation Centre (ERIC) campuses, on an 'as and when required basis' for three years. Works Information in Part C3; Site Information in Part C4. Contractor provides works in accordance with Works Information, not Bill of Quantities. Bill of Quantities is only a pricing document under NEC3 ECC Option B.
Methodology
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdfasbestos work plan, if applicable.
Z15.6 The Contractor continues to Provide the Services, without additional control measures
presented, on presentation of Safe Levels. The contractually agreed dates to Provide the
Experience & Qualifications
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdf2 Name:
Job
Responsibilities:
CV's (and further key persons data including CVs)
are appended to Tender Schedule entitled .
2 Available from Engineering Contract Strategies Tel 011 803 3008, Fax 011 803 3009 or see www.ecs.co.za
11.2(3) The completion date for the whole of the
works is
11.2(14) The following matters will be included in the
Risk Register
11.2(19) The Works Information for the Contractor’s
design is in:
31.1 The programme identified in the Contract Data
is
B Priced contract with bill of quantities
A Priced contract with activity schedule
As per price schedule
11.2(20) The activity schedule is in (in figures)
11.2(30) The tendered total of the Prices is (in words), excluding VAT
Note “SCC” means Schedule of Cost Components starting
Data for Schedules of Cost Components on , and “SSCC” means Shorter Schedule of Cost
Components starting on of ECC3 (April 2013).
A Priced contract with activity schedule Data for the Shorter Schedule of Cost Components
Part 2: pricing data
ECC3 Option B
Document Title No of
reference pages
C2.1 Pricing assumptions: Option B
C2.2 The Bill of quantities
C2.1 Pricing assumptions: Option B
How work is priced and assessed for payment
Clause 11 in NEC3 Engineering and Construction Contract (ECC3) Option B states:
Identified and 11
defined terms 11.2 (21) The Bill of Quantities is the bill of quantities as changed in accordance with this
contract to accommodate implemented compensation events and for accepted
quotations for acceleration.
(28) The Price for Work Done to Date is the total of
the quantity of the work which the Contractor has completed for each item in the Bill
of Quantities multiplied by the rate and
a proportion of each lump sum which is the proportion of the work covered by the item
which the Contractor has completed.
Completed work is work without Defects which would either delay or be covered by
immediately following work.
(31) The Prices are the lump sums and the amounts obtained by multiplying the rates
by the quantities for the items in the Bill of Quantities.
This confirms that Option B is a re-measurement contract and the bill comprises only items measured using quantities
and rates or stated as lump sums. Value related items are not used. Time related items are items measured using
rates where the rate is a unit of time.
Function of the Bill of Quantities
Clause 55.1 in Option B states, “Information in the Bill of Quantities is not Works Information or Site Information”. This
confirms that specifications and descriptions of the work or any constraints on how it is to be done are not included in
the Bill, but in the Works Information. This is further confirmed by Clause 20.1 which states, “The Contractor Provides
the Works in accordance with the Works Information”. Hence the Contractor does not Provide the Works in accordance
with the Bill of Quantities. The Bill of Quantities is only a pricing document.
Guidance before pricing and measuring
Employers preparing tenders or contract documents, and tendering contractors are advised to consult the sections
dealing with the bill of quantities in the NEC3 Engineering and Construction Contract Guidance Notes before preparing
the bill of quantities or before entering rates and lump sums into the bill.
There is no general provision in Option B for payment for materials on Site before incorporation into the works. If
secondary Option X14 Advanced payment has not been used then the tendering contractor may obtain the same effect
by inserting appropriate items in the method related charges where the method of measurement allows, or
alternatively making allowance in the rates of the bill of quantities for the financing of Plant and Materials until they
are incorporated in the works.
When compensation events arise, the default position is that the Bill of Quantities is not used to calculate the cost
effect of the event. Defined Cost and the resulting Fee is used and Defined Cost includes all components of cost which
the Contractor is likely to incur, including so called P & G items. Rates and lump sums from the Bill of Quantities, or
from any other source, may be used instead of Defined Cost and the Fee only if the Contractor and Project Manager
agree. If they are unable to agree, then Defined Cost plus Fee is used.
Measurement and payment
Symbols
The units of measurement described in the Bill of Quantities are metric units abbreviated as follows:
[add or delete as required]
Abbreviation Unit
% percent
h hour
ha hectare
kg kilogram
kl kilolitre
km kilometre
km-pass kilometre-
pass
kPa kilopascal
kW kilowatt
l litre
m metre
mm millimetre
m2 square metre
m2-pass square metre
pass
m3 cubic metre
m3-km cubic metre-
kilometre
MN meganewton
MN.m meganewton-
metre
MPa megapascal
No. number
sum Lump sum
t tonne
(1000kg)
General assumptions
made in the quantities for waste.
work, risks, liabilities, obligations, overheads, profit and everything necessary as incurred or required by the
Contractor in carrying out or providing that item.
quantities.
amount of work to be done. The quantities of work assessed and certified for payment by the Project Manager
at each assessment date will be used for determining payments due.
identifying the items. Detail regarding the extent of the work entailed under each item is provided in the
Works Information.
Departures from the method of measurement
Amplification of or assumptions about measurement items
The following is provided to assist in the interpretation of descriptions given in the method of measurement. In the
event of any ambiguity or inconsistency between the statements in the method of measurement and this section, the
interpretation given in this section shall be used.
Qualifications:
Experience:
2 Name:
Qualifications:
Experience:
CV's (and further key persons data including CVs)
are appended to Tender Schedule entitled .
2 Available from Engineering Contract Strategies Tel 011 803 3008, Fax 011 803 3009 or see www.ecs.co.za
11.2(3) The completion date for the whole of the
works is
11.2(14) The following matters will be included in the
Quality Management
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdfdiscovered on reasonable inspection by the Employer
or the Supervisor
X19 Task Order
X19.5 The Contractor submits a Task Order 5 working days of receiving the Task
programme to the Service Manager within Order
before the defects date, without requiring any inspection
not ordinarily carried out by the Employer or the
the reasonable inspection, this does not place a
greater responsibility on the Employer or the Supervisor to
have discovered the Defect.
occupational hygiene inspection body, i.e. a SANAS accredited and Department of Employment
and Labour approved AAIA. The Contractor may perform Parallel Measurements and related
control measures at the Contractor’s expense. For the purposes of compliance the results
generated from Parallel Measurements are evaluated only against South African statutory limits
as detailed in clause Z15.1. Control measures conform to the requirements stipulated in the
Pricing Schedule
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdfPricing is 'as per Task order' under Option B (priced contract with bill of quantities). Price adjustment for inflation (Option X1): base date for indices is 01 December 2025; proportions linked to indices: Material – Insulation 20% (Table O–2), Material – Ceiling boards 30% (Table G–2(A)), Material – Wiring 10% (Table G–2(A)), Material – Paint 3% (Table M–6), Labour 15% (Table C3 – AHPE), Overheads 4% (Table D–2), Transport 3% (Table L2–A), Fixed 15% non-adjustable. Tendered prices fixed for first 12 months, then subject to escalation.
Financial Requirements
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdf (unknown)Payment: Contractor provides tax invoice within one week of payment certificate, showing amount due equal to certificate. If tax invoice delayed, payment time extended by delay period. Interest on late payment at prime rate (Standard Bank) on 365-day year. Retention: 5% (50% paid at completion, 50% after defects period). Delay damages: 1% of total price per activity, capped at 5% of contract price. Low performance damages: R2,000 per day per incident, capped at 2% of contract price. Price adjustment for inflation: proportions linked to indices as specified (Material – Insulation 20%, Material – Ceiling boards 30%, Material – Wiring 10%, Material – Paint 3%, Labour 15%, Overheads 4%, Transport 3%, Fixed 15% non-adjustable).
Compliance Requirements
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdf (unknown)B-BBEE: Contractor must notify Employer within 7 days of any change in B-BBEE status; submit updated verification certificate within 30 days; if status decreases, Employer may re-negotiate or terminate. Failure to notify may constitute termination. Health and safety: Contractor to take all reasonable precautions; may be appointed Principal Contractor under Construction Regulations 2014; prices include sufficient amount for compliance; comply with all applicable health & safety laws. Asbestos: Employer ensures ambient air conforms to asbestos OEL (0.2 fibres/ml as 4-hour TWA, short-term 0.6 fibres/ml as 10-minute TWA); measurements by SANAS accredited AAIA; Contractor may perform parallel measurements; if asbestos identified, risk assessment and control measures; Contractor personnel may stop work and leave contaminated area; removal by registered asbestos contractor at Employer's expense. Security: Contractor and subcontractors implement risk and security management; provide criminal verification record security clearance certificates for each person accessing Employer's premises, issued by SAPS-accredited screening company, no older than four weeks, valid for access; Employer may require updated certificates every 26-52 weeks. Confidentiality: Receiving Party must not disclose information without prior written consent; images of works require prior written consent. Joint ventures: If Contractor is a joint venture, consortium, or unincorporated grouping, members are jointly and severally liable; notify Project Manager of key person with authority to bind within two weeks; cannot alter composition without Employer's written consent.
Health & Safety
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdfHealth and safety requirements: Contractor to take all reasonable precautions to maintain health and safety; may be appointed as Principal Contractor under Construction Regulations 2014; prices include sufficient amount for compliance with health & safety laws; comply with Construction Regulations and applicable laws; ensure subcontractors comply. Asbestos management: Employer ensures ambient air conforms to asbestos OEL (0.2 fibres/ml as 4-hour TWA, short-term 0.6 fibres/ml as 10-minute TWA); measurements by SANAS accredited AAIA; Contractor may perform parallel measurements; if asbestos identified, risk assessment and control measures; Contractor personnel may stop work and leave contaminated area; removal/disposal by registered asbestos contractor at Employer's expense.
Environmental
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdfContractor to comply with all applicable environmental laws and regulations, and ensure subcontractors comply.
Contractual Terms
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdfDispute resolution: Adjudicator selected from ICE-SA Panel of Adjudicators; if no agreement, appointed by AFSA; tribunal is arbitration under Association of Arbitrators (Southern Africa) rules; place of arbitration is South Africa.
Section
Source: NEC ECC3 Renovation and Refurbishment for minor works at EALMWP and ERIC.pdfR 2,000 per day For every incident where a Quality Control
R 2,000 per day For every incident of quality non
days approved witness points on Quality Control
Description
Source: Invitation to Tender (ITT).pdf (TENDER)The tender is for a panel contract for renovations and refurbishment at three Eskom campuses (Megawatt Park, Eskom Academy of Learning, and Eskom Research Innovation Centre) on an as-and-when-required basis for three years. The contract is open to all eligible tenderers. The tender documents are free of charge. The tender must be for the whole contract; alternative tenders are not allowed.
Important Dates
Source: Invitation to Tender (ITT).pdf (TENDER)Closing date and time: 28 September 2026 at 10h00 (SAST).
Non-compulsory clarification meeting: 10 September 2026 at 10h00 (SAST) via Microsoft Teams (link provided).
Clarification queries deadline: 5 working days before tender submission deadline.
Tender validity period: 90 days from closing date.
Contact Information
Source: Invitation to Tender (ITT).pdf (TENDER)Eskom Representative: Dakalo Mugadi, Tel: 011 629 8234, E-mail: [email protected].
Fraud/corruption reporting: 0800 11 2722 / [email protected].
Submission: via Eskom e-Tendering system (https://etendering.eskom.co.za).
Submission Guidelines
Source: Invitation to Tender (ITT).pdf (TENDER)Submit electronically via the Eskom e-Tendering system at https://etendering.eskom.co.za by the closing date and time. All documents must be in PDF format; the price list must also be submitted in Excel format. Upload size per document is 500 MB, total submission limited to 4 GB. No zip/condensed files, no hard copies. If resubmitting, only the latest version is accepted; previous submissions become null and void. Late tenders are not accepted. Ensure the submission status is marked complete. Returnable forms (all must be completed, signed where required, and submitted at closing):
Disqualification risks: missing or unsigned returnables, late submission, submitting more than one tender, conflict of interest, tenders signed by non-authorised persons, being on National Treasury restricted or Tender Defaulters list, subcontracting 100% of scope.
Evaluation Criteria
Source: Invitation to Tender (ITT).pdf (TENDER)Functionality/technical evaluation is applicable and weighted at 80%. Price evaluation is not applicable at this stage; it will be undertaken at the Task Order stage. Evaluation of specific goals (e.g., B-BBEE) is also not applicable at this stage; will be undertaken at Task Order stage. Tenders will be ranked by technical scores; the six highest-scoring tenderers will proceed (refer to attached technical evaluation criteria). Tenderers who do not meet the functionality threshold will be disqualified. Contractual requirements (e.g., quality, safety) are not evaluation criteria but are assessed after evaluation and ranking.
Technical Specifications
Source: Invitation to Tender (ITT).pdf (TENDER)Scope: Provision of renovations and refurbishment panel contract at Megawatt Park (MWP), Eskom Academy of Learning (EAL), and Eskom Research Innovation Centre (ERIC) campuses on an 'as and when required basis' for a period of three (03) years. The contract is for the whole of the contract; alternative tenders are not allowed. The successful tenderer may be required to provide cataloguing information per item after award and label materials per Eskom specifications. Pricing schedule must include a line item for cataloguing if required. Refer to attached Scope of Work and NEC or other Contract for detailed deliverables.
Methodology
Source: Invitation to Tender (ITT).pdf (TENDER)Tenders will be opened electronically; there will be no public opening. Prices will not be read out. Basic compliance with the ITT requires meeting all eligibility criteria and submitting all required returnables. The tender must be for the whole contract; alternative tenders are not allowed.
Quality Management
Source: Invitation to Tender (ITT).pdf (TENDER)Quality requirements: Either a valid ISO 9001:2015 certificate OR a QMS manual and related documented information (quality policy, objectives, control of documented information, control of nonconforming outputs, corrective action, internal audit, organization chart, responsibility matrix, control of externally provided processes, internal audit report, management review records). Contract Quality Plan (Ref 240-105658000 and 240-109253698) and Quality Control Plan (Ref 240-105658000 or 240-109253302) are required. Professional certifications required: Project Management Certification registered with SACPCMP as safety officer; Plumbing Trade certificate and PIRB registration; SAQCC HVAC Gas B6; SAQCC fire detection, protection, and gas at level 2.
Pricing Schedule
Source: Invitation to Tender (ITT).pdf (TENDER)Pricing schedule/BOQ must be submitted in PDF and Excel format. The price list must include a line item for cataloguing if required. The pricing schedule is not evaluated at this stage; it will be evaluated at the Task Order stage. Payment terms: 30 days for contracts below R50 million (incl. VAT), 60 days for contracts above R50 million (incl. VAT).
Financial Requirements
Source: Invitation to Tender (ITT).pdf (TENDER)Payment terms: For contracts valued below R50,000,000 (including VAT), Eskom pays within 30 days of receipt of undisputed invoices. For contracts valued above R50,000,000 (including VAT), Eskom pays within 60 days of receipt of undisputed invoices. No performance security is required (N/A). Tender validity period: 90 days. Pricing schedule/BOQ must be submitted in PDF and Excel format. Audited financial statements for the previous 18 months (or last year if not available) are required; for JV/SPV, each participant must submit. Start-up enterprises formed within the last 12 months are exempt but must furnish statements for the first year once available.
Compliance Requirements
Source: Invitation to Tender (ITT).pdf (TENDER)Eligibility: Tenderer must not be under any restriction to do business with Eskom or State-Owned Companies; must not have nationality of a country on international sanctions lists; must not submit more than one tender; JV/consortium agreement must state joint and several liability; must not have conflict of interest; must not be restricted by National Treasury or on Tender Defaulters list; must not subcontract 100% of scope.
B-BBEE: Minimum level 2. Proof of B-BBEE status level contributor (certificate, sworn affidavit, or other prescribed).
Safety: COIDA - original certificate of good standing or proof of application (South African tenderers only).
Quality: Option 1: valid ISO 9001:2015 certificate; OR Option 2: QMS manual, quality policy, quality objectives, control of documented information, control of nonconforming outputs, corrective action, internal audit, organization chart, responsibility matrix, control of externally provided processes, internal audit report, management review records. Also Contract Quality Plan (Ref 240-105658000 and 240-109253698) and Quality Control Plan (Ref 240-105658000 or 240-109253302).
Safety documents: Annexure B of works, Health and Safety plan/OHS manual, H&S costing, Baseline SHE Risk assessment, valid letter of good standing (LOGs), signed SHE policy, proof of SHE competency.
Environmental: Company environmental policy (integrated or non-integrated with safety) committing to compliance with environmental legislation, pollution prevention, continual improvement.
Professional registrations: Project Management Certification registered with SACPCMP as a safety officer; Plumbing Trade certificate and registered with PIRB as licenced plumber; SAQCC HVAC Gas B6; SAQCC fire detection at level 2; SAQCC fire protection at level 2; SAQCC fire gas at level 2.
Returnable forms: SBD 1, SBD 4, SBD 6.1, SBD 6.2 (if applicable), Authorisation Form, Acknowledgement Form, Tenderer's Particulars, Integrity Declaration Form, Tax Evaluation questionnaire.
Health & Safety
Source: Invitation to Tender (ITT).pdf (TENDER)Safety requirements: COIDA certificate of good standing or proof of application (South African tenderers only). Other safety documents: Annexure B of works, Health and Safety plan/OHS manual, H&S costing, Baseline SHE Risk assessment, valid letter of good standing (LOGs), signed SHE policy, proof of SHE competency. SHEQ requirements and SDL&I requirements may apply. Financial viability (financial statements) may be assessed.
Environmental
Source: Invitation to Tender (ITT).pdf (TENDER)Environmental requirements: Company environmental policy (can be integrated with safety) committing to compliance with environmental legislation, pollution prevention, and continual improvement. A project-specific Environmental Management Plan (EMP) must be developed identifying environmental aspects and impacts (e.g., waste, noise, dust) and outlining mitigation measures, monitoring procedures, and responsibilities. The EMP will be reviewed and approved before project commencement. A Waste Management Plan must be developed to ensure waste is handled and disposed in compliance with SHEQ standard, National Environmental Management Waste Act, and relevant bylaws. An Emergency Preparedness Plan must be developed to respond to environmental incidents (e.g., wildfires, fuel spills, adverse weather).
Contractual Terms
Source: Invitation to Tender (ITT).pdf (TENDER)The contract will be for the whole of the contract. Tenderers must not have a conflict of interest. JV/consortium agreements must state joint and several liability. Subcontracting 100% of the scope is not allowed. Payment terms: Eskom pays within 30 days for contracts below R50 million (incl. VAT) and within 60 days for contracts above R50 million (incl. VAT). No performance security is required. The successful tenderer may be required to provide cataloguing information and label materials per Eskom specifications.
Section
Source: Invitation to Tender (ITT).pdf (TENDER)Functionality/technical criteria are weighted at 80%. Price is not evaluated at this stage; it will be evaluated at the Task Order stage. Specific goals (e.g., B-BBEE) are also not evaluated at this stage. Tenders are ranked by technical scores; the six highest-scoring tenderers proceed. Refer to attached technical evaluation criteria for details. Contractual requirements (quality, safety) are assessed after evaluation and ranking.
Description
Source: 20260630_Spec_GFD_ERE_Coporate Sites_Minor works Spec_Rev01.pdf (unknown)Multidisciplinary construction minor works at Eskom corporate sites (ERIC, MWP and EAL). Project addresses: 1 Maxwell Drive, Sunninghill, Sandton, 2157; Dale Road, P/Bag X13, Midrand; Lower Germiston Road, Heriotdale, Johannesburg South, 2094. Work includes electrical, control and instrumentation, architectural, mechanical, and civil works.
Important Dates
Source: 20260630_Spec_GFD_ERE_Coporate Sites_Minor works Spec_Rev01.pdf (unknown){"closingDate":"02 July 2026"}
Contact Information
Source: 20260630_Spec_GFD_ERE_Coporate Sites_Minor works Spec_Rev01.pdf (unknown){"name":null,"email":null,"phone":null,"department":null,"address":"PECIFICATION Effective November 2023"}
Evaluation Criteria
Source: 20260630_Spec_GFD_ERE_Coporate Sites_Minor works Spec_Rev01.pdf (unknown)Unable to extract eligibility criteria
Technical Specifications
Source: 20260630_Spec_GFD_ERE_Coporate Sites_Minor works Spec_Rev01.pdf (unknown)Scope: Multidisciplinary construction minor works at Eskom corporate sites — ERIC, MWP, and EAL campuses. Work includes electrical systems, control and instrumentation, architectural, mechanical, and civil works, encompassing manufacture, construction, installation, and commissioning. Project addresses: 1 Maxwell Drive, Sunninghill, Sandton, 2157; Dale Road, P/Bag X13, Midrand; Lower Germiston Road, Heriotdale, Johannesburg South, 2094. Contract is on an 'as and when required' basis for three years.
Quality Management
Source: 20260630_Spec_GFD_ERE_Coporate Sites_Minor works Spec_Rev01.pdf (unknown)Quality records must be maintained in accordance with legislative and Eskom requirements. SHE-related problems must be discussed with contractor management timeously, and non-conformances, corrective actions, audits, and inspection schedules must be addressed.
Compliance Requirements
Source: 20260630_Spec_GFD_ERE_Coporate Sites_Minor works Spec_Rev01.pdf (unknown)B-BBEE minimum level: 6. Contractor must provide a valid Compensation Commissioner's letter of good standing before commencement. Contractor must develop a site-specific SHE Plan meeting the SHE Specification, all applicable legislation, and Eskom requirements. Contractor must comply with the OHS Act, Construction Regulations, SANS standards, and Eskom SHE/OHS procedures and policies. Section 37(2) legal agreement required. Contractor must be registered and in good standing with the Compensation Fund. Contractor must appoint competent staff and a SHE practitioner. Contractor must maintain employee records and compile a consolidated health and safety file. Contractor must notify the Provincial Director for certain construction work. Contractor must stop work that poses a threat to health and safety or the environment.
Health & Safety
Source: 20260630_Spec_GFD_ERE_Coporate Sites_Minor works Spec_Rev01.pdf (unknown)Contractor must prepare a site-specific SHE baseline risk assessment and SHE specification. SHE specification must be included in tender documents. Principal contractor must be registered and in good standing with the Compensation Fund. Written appointment of principal contractor required. Principal contractor is accountable for health and safety of employees and subcontractors. Must notify Provincial Director for certain construction work. Must maintain employee records and compile and hand over a consolidated health and safety file. Must provide certified letters of good standing. Must appoint competent staff and coordinate appointed contractors. Must stop work that poses a threat to health and safety or the environment. Must comply with Eskom Life-saving Rules, substance abuse policy, access and security control, PPE requirements, working at heights requirements, fire equipment and maintenance, first aid, SHE communication systems, toolbox talks, SHE training, housekeeping, signage, tools and equipment, auditing, smoking and cellular phone restrictions, occupational health and hygiene, incident investigation, emergency management, waste management, and SHE file requirements. Hours of work: normal work, night work, and overtime as per specification.
Environmental
Source: 20260630_Spec_GFD_ERE_Coporate Sites_Minor works Spec_Rev01.pdf (unknown)Environmental Management Plan must be implemented during the life cycle of the project, preferably forming part of Eskom's Environmental Management System. Negative environmental impacts must be addressed.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 38 of 2000
Important for public-sector construction and infrastructure tenders that require contractor grading or construction procurement standards.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 107 of 1998
Relevant where environmental authorisations, EIAs or environmental compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 85 of 1993
Sets health and safety duties for contractors, employers and service providers working on public-sector sites.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 103 of 1977
Relevant where building standards, renovations, maintenance or construction compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Address
Maxwell Drive, Eskom Megawatt Park - Sunninghill - Sandton - 2157
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
10
Last checked
28 Aug 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Learn how to submit a winning bid with these related articles
A practical guide for small and medium building contractors on winning government tenders for schools, clinics, housing, and municipal buildings in South Africa.
How established construction firms use Joint Ventures with EMEs and QSEs to meet B-BBEE preferential procurement targets and access set-aside contracts.
Everything South African construction contractors need to know about how procurement officers verify cidb grades: what gauteng contractors must ensure is correct — april 2026 update — covering CIDB grading certificate, NHBRC registration (residential), step-by-step processes, common disqualification mistakes, and how Tenders-SA.org helps you find and win relevant contracts in Gauteng.
How small and medium construction contractors use Joint Ventures to combine CIDB grades, win larger infrastructure projects, and grow beyond their current grading ceiling.
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Construction of buildings. Unlock full pricing strategies, bid frequency, and historical win rates.