Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
Tutuka Power Station - Standerton - Standerton - 2430
Organization Type
GOVERNMENT
Published
07 Aug 2026
OCDS Reference
ocds-9t57fa-164996
ESKOM is procuring the supply and delivery of stationery at tutuka power station in mpumalanga for a five-year period. Bidders must accept eskom's supplier quality requirements under specification 240-105658000 and iso 9001, with category 4 quality requirements indicated as applicable. The most consequential requirement is completing and signing the quality acknowledgement form, which commits the bidder to post-contract quality monitoring and audit obligations.
Quality category: Bidders must select and indicate Category 4 quality requirements as applicable on the Supplier Quality Requirements acknowledgement form.
Quality standard: Bidders must acknowledge and accept Eskom Supplier Quality Requirements per specification 240-105658000 and the ISO 9001 Standard.
Contract term: The contract is for the supply and delivery of stationery for a period of five years.
Delivery location: Stationery must be delivered to Tutuka Power Station in Mpumalanga.
Post-contract obligations: Bidders must accept post-contract award requirements including contract execution, supplier quality performance monitoring, Eskom rights of access and information, preservation, quality audits, management of nonconformities, and special processes.
Form completion: The tenderer's quality representative must complete and sign Section E of the acknowledgement form.
Closing deadline: Bids must be submitted by 25 August 2026 at 10:00.
Date & Time
Tuesday, 25 August 2026 - 10:00
Venue
null
Tenders are to be submitted electronically via ESKOM e-tendering site by the stipulated closing date and time.
Categories
Request for Bid(Open-Tender)
Tutuka Power Station - Standerton - Standerton - 2430
Recommended Certifications
Having these can improve your winning chances: SABS Product Certification, NRCS Certification
AI Document Analysis Stages
Contact Information
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.pdf (unknown)07 Aug
2026
Tender Published
Tender was published
25 Aug
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Eskom_Standard_Conditions_of_Tender_.pdf
Eskom is procuring the supply and delivery of stationery at Tutuka Power Station in Mpumalanga for a five-year period. The tender is governed by Eskom's Standard Conditions of Tender, which set out submission, evaluation, and contractual requirements.
240-77471499 Annexure B-Safety.docx
Eskom is procuring the supply and delivery of stationery at Tutuka Power Station in Mpumalanga for a five-year period. Bidders must acknowledge and comply with Eskom's Occupational Health and Safety (OHS) legal and other requirements, including the Occupational Health and Safety Act and the Compensation for Occupational Diseases and Illnesses Act.
Invitation to Tender (ITT) - Stationery ...pdf
Eskom is inviting tenders for the supply and delivery of stationery at Tutuka Power Station in Mpumalanga over a five-year period. The contract will be governed by the NEC3 Term Service Contract, with evaluation based on functionality (70% threshold), price (80 points), and specific goals (20 points).
TTES STATIONARY 25062026.pdf
Supply and delivery of stationery items on an as-and-when required basis for a period of five years to Tutuka Power Station, issued by Eskom in Mpumalanga. The tender follows an open enquiry process, with an 80/20 preference points system and a single contract for the whole of the works.
E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf
Eskom is procuring the supply and delivery of stationery at Tutuka Power Station in Mpumalanga for a five-year period. Bidders must submit their tender documents electronically through Eskom's eTendering system.
Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.pdf
Eskom is procuring the supply and delivery of stationery at Tutuka Power Station in Mpumalanga for a five-year period. The tender requires bidders to enter into a Non-Disclosure Agreement (NDA) with Eskom before receiving confidential information related to the project.
Declaration_of_Shareholding_or_Beneficiaries_Form.pdf
Eskom is procuring the supply and delivery of stationery at Tutuka Power Station in Mpumalanga for a five-year period. Bidders must complete the tender schedules, including a declaration of shareholding or beneficiaries.
240-77471499 Annexure B -Safety.pdf
Supply and delivery of stationery at Tutuka Power Station for a period of five years, issued by Eskom.
Life Saving-Rules.pdf
Eskom is procuring the supply and delivery of stationery at Tutuka Power Station in Mpumalanga over a five-year period. The document provided is Eskom's Life-Saving Rules standard, which sets out mandatory safety rules for all persons on Eskom sites, including contractors and visitors.
240-12248652_List of Tender Returnables_Cat 4_ Rev 7-Quality.xlsx
Eskom is procuring the supply and delivery of stationery at Tutuka Power Station in Mpumalanga for a five-year period. The tender includes a quality evaluation scorecard that assesses bidders' quality management systems, with specific requirements for ISO 9001 certification or equivalent evidence of an implemented QMS.
NEC3SC - Supply and Delivery of Stationery Revised Quantities -30-07-2026.pdf
Eskom is procuring the supply and delivery of stationery to Tutuka Power Station in Mpumalanga under a five-year, as-and-when-required contract, using the NEC3 Supply Contract (SC3) form.
Scope of Work for Stationery - 16 April 2026.pdf
Eskom is procuring the supply and delivery of stationery to Tutuka Power Station in Mpumalanga on an as-and-when-required basis for a five-year period. The contract covers a wide range of items including adhesive labels, paper, books, desktop stationery, filing and storage products, and presentation materials, with delivery triggered by purchase orders.
240-68099512 Form A_Cat 4_ Rev 9-Quality.docx
Eskom is procuring the supply and delivery of stationery at Tutuka Power Station in Mpumalanga for a five-year period. The tender includes acceptance of Eskom's Supplier Quality Requirements as per specification 240-105658000 and ISO 9001 standards.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
R 720 068
Range
Based on 10 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
{"name":null,"email":null,"phone":null,"department":null,"address":"................... a company incorporated under the laws of [insert"}
Evaluation Criteria
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.pdf (unknown)Bidders must be legally capable of entering into the Non-Disclosure Agreement (NDA) and must have the authority to sign it. The NDA does not create a business relationship or obligate either party to proceed with the tender.
Technical Specifications
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.pdf (unknown)provisions of this Agreement for any
purpose whatsoever other than the Project
Compliance Requirements
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.pdf (unknown)Bidders must sign the Non-Disclosure Agreement (NDA) with Eskom Holdings SOC Ltd. The NDA governs the handling of confidential information disclosed during the tender process.
Contractual Terms
Source: Non-Disclosure Agreement (NDA) Vendors Template - 02 September 2024.pdf (unknown)The Non-Disclosure Agreement (NDA) between Eskom Holdings SOC Ltd and the tenderer defines confidential information, obligations to protect and not disclose it, exclusions, return or destruction of materials, a term of three years after termination, breach remedies, amendments, enforcement, representations and warranties, entire agreement, governing law (South Africa), addresses and notices, severability, assignment, publicity, and interpretation rules.
Description
Source: 240-68099512 Form A_Cat 4_ Rev 9-Quality.docxBidders must complete and sign the form to acknowledge and accept Eskom Supplier Quality Requirements as per specification 240-105658000 and ISO 9001 Standard. The form requires selection of one quality category; Category 4 is indicated as applicable. Post-contract award requirements include contract execution, supplier quality performance monitoring, Eskom rights of access and information, preservation, quality audits, management of nonconformities, and special processes as per the referenced specification clauses.
Evaluation Criteria
Source: 240-68099512 Form A_Cat 4_ Rev 9-Quality.docx (unknown)Bidders must complete and sign the Supplier Quality Requirements acknowledgement form, selecting the applicable quality category. Category 4 is indicated as applicable. No other eligibility criteria are stated in the document.
Technical Specifications
Source: 240-68099512 Form A_Cat 4_ Rev 9-Quality.docx (unknown)Bidders must complete and sign the form to acknowledge and accept Eskom Supplier Quality Requirements as per specification 240-105658000 and ISO 9001 Standard. The form requires selection of one quality category; Category 4 is indicated as applicable. Post-contract award requirements include contract execution, supplier quality performance monitoring, Eskom rights of access and information, preservation, quality audits, management of nonconformities, and special processes as per the referenced specification clauses.
Compliance Requirements
Source: 240-68099512 Form A_Cat 4_ Rev 9-Quality.docx (unknown)Bidders must complete and sign the Supplier Quality Requirements acknowledgement form, accepting Eskom Supplier Quality Requirements per specification 240-105658000 and ISO 9001 Standard. The form requires selection of one quality category; Category 4 is indicated as applicable.
Description
Source: TTES STATIONARY 25062026.pdfThe tender is for the supply and delivery of stationery items on an 'as and when' required basis for a period of 5 years at Tutuka Power Station. The enquiry is for the whole of the works, resulting in a single contract, and is advertised locally. The 80/20 preference scoring system applies. Deliveries are once per month as per purchase order instructions, with occasional additional deliveries. Delivery times are Monday to Thursday not later than 15H00 and Friday before 11H00. A purchase order will be issued with required items and quantities. Upon delivery, a delivery note is requested for payment processing. Items not meeting the required specification will not be accepted, and a quality check is performed upon receipt.
Important Dates
Source: TTES STATIONARY 25062026.pdf (unknown)Closing date: 25 August 2026 at 10:00. No other dates (briefings, site visits, clarification deadlines) are stated in the document.
Submission Guidelines
Source: TTES STATIONARY 25062026.pdf (unknown)Returnable documents: reference letter(s) on client letterheads for similar stationery supply contracts, a letter of intent or existing agreement from the stationery supplier, and proof of ownership or lease of a fully enclosed (box-body) delivery vehicle. All documents must be valid and current as specified in the evaluation criteria. Bids must be submitted before the closing time; late submissions are disqualified. The tender is advertised locally and results in a single contract for the whole of the works. The 80/20 preference scoring system applies.
Evaluation Criteria
Source: TTES STATIONARY 25062026.pdf (unknown)Technical evaluation threshold: minimum weighted final score of 70% to be considered. Qualitative criteria (total 100%): 1) Reference letters (40% weight) — scoring: 5 points for 5+ years cumulative relevant experience, 4 points for 4 years, 2 points for 1–3 years, 0 points for less than 1 year or none. 2) Letter of intent from stationery supplier (40% weight) — 30% for a signed and stamped existing agreement (not older than 3 months) or letter of intent (not older than 1 month); 0% if none. 3) Delivery vehicle proof (20% weight) — 0 points for none, 4 points for one vehicle, 5 points for two or more. No mandatory technical criteria are specified. Evaluation process: submissions are rated against functional criteria, weightings applied, and tenders below the threshold eliminated. The 80/20 preference points system applies, so B-BBEE status will be scored under the preference points claim.
Technical Specifications
Source: TTES STATIONARY 25062026.pdf (unknown)Scope: supply and delivery of stationery items on an 'as and when' required basis for a period of 5 years at Tutuka Power Station. Deliveries: once per month as per purchase order instructions; occasionally more than once per month. Delivery times: Monday to Thursday not later than 15H00, Friday before 11H00. A purchase order will be issued with required items and quantities. Upon delivery, a delivery note is requested for payment processing. Items not meeting the required specification will not be accepted. Quality check to be performed upon receiving stationery items. The contract covers the whole of the works and results in a single contract.
Experience & Qualifications
Source: TTES STATIONARY 25062026.pdfBidders must provide reference letters on client letterheads for similar stationery supply contracts, demonstrating cumulative relevant experience. Scoring: 5 points for 5+ years, 4 points for 4 years, 2 points for 1–3 years, 0 points for less than 1 year or none. Each reference letter must confirm the description of the supplied stationery, the contract duration (start and completion dates), and successful completion. Acceptable technical risks include pandemic. Unacceptable technical risks include supplier failing to meet the standard and incorrect delivery. Unacceptable technical exceptions/conditions include lack of understanding the scope of work and poor controls (e.g., documents, records, transportation).
Compliance Requirements
Source: TTES STATIONARY 25062026.pdf (unknown)B-BBEE: The 80/20 preference scoring system applies, so bidders must submit a valid B-BBEE certificate or affidavit to claim preference points. No other compliance requirements (CSD, tax, CIDB, etc.) are stated in the document.
Section
Source: TTES STATIONARY 25062026.pdfTechnical evaluation threshold: minimum weighted final score of 70%. Qualitative criteria: 1) Reference letters (40% weight) — 5 points for 5+ years experience, 4 points for 4 years, 2 points for 1–3 years, 0 points for less than 1 year or none. 2) Letter of intent from stationery supplier (40% weight) — 30% for signed and stamped existing agreement (not older than 3 months) or letter of intent (not older than 1 month); 0% if none. 3) Delivery vehicle proof (20% weight) — 0 points for none, 4 points for one vehicle, 5 points for two or more. Evaluation process: rate submissions against functional criteria, apply weightings, calculate total functional score, and eliminate tenders below the minimum threshold. Acceptable technical risks include pandemic. Unacceptable technical risks include supplier failing to meet the standard and incorrect delivery. Unacceptable technical exceptions/conditions include lack of understanding the scope of work and poor controls.
Description
Source: Scope of Work for Stationery - 16 April 2026.pdf (unknown)Supply and delivery of stationery to Tutuka Power Station for a period of 5 years on an as and when required basis. The supplier is required to supply stationery items to Tutuka Power Station. Delivery to be on an as and when requested basis. A purchase order will be issued to the supplier with the required items. Upon delivery, a delivery note will be requested for processing of payment. No item delivered that is not on the required specification will be accepted. Quality check to be performed upon receiving of stationery items. This document is applicable to all Tutuka Power Station employees. The document will be effective after the day of approval.
Contact Information
Source: Scope of Work for Stationery - 16 April 2026.pdf (unknown){"name":null,"email":null,"phone":null,"department":"SIZE UNIT QTY NO","address":null}
Evaluation Criteria
Source: Scope of Work for Stationery - 16 April 2026.pdf (unknown)Bidders must be able to supply the full range of stationery items listed in the specification. Compliance with quality, safety, and environmental standards (ISO 9001, ISO 14001, OHSAS 18001/ISO 45001, HACCP) is required. Bidders must accept the terms regarding rejection of non-conforming goods, return of excess quantities at supplier's risk, and penalties for delays. No specific registration or certification is stated in the document.
Technical Specifications
Source: Scope of Work for Stationery - 16 April 2026.pdf (unknown)Supply and delivery of stationery to Tutuka Power Station for a period of 5 years on an as and when required basis.
Scope: The supplier is required to supply stationery items to Tutuka Power Station. Delivery to be on an as and when requested basis. A purchase order will be issued to the supplier with the required items. Upon delivery, a delivery note will be requested for processing of payment. No item delivered that is not on the required specification will be accepted. Quality check to be performed upon receiving of stationery items.
Item categories and quantities:
Quality Management
Source: Scope of Work for Stationery - 16 April 2026.pdf (unknown)Goods must conform with the quality, description, and other particulars stated in the bid documents and all specifications provided. Goods must be of satisfactory quality and fit for any intended use made known to the supplier, free from defects in materials and workmanship for a period of 6 months from the date of delivery. Goods must comply with all performance and other specifications and all applicable legislation. Goods must conform with all quality standards. Quality check to be performed upon receiving of stationery items. ISO 9001 Quality Management Systems is referenced.
Financial Requirements
Source: Scope of Work for Stationery - 16 April 2026.pdf (unknown)Pricing must be provided for the full range of stationery items listed in the specification, with quantities as stated. The contract is for a period of 5 years on an as and when required basis. Payment will be processed upon delivery and acceptance of goods. No charges for wrapping, packing, cartons, boxes, crating or containers unless specified in the Purchase Order.
Compliance Requirements
Source: Scope of Work for Stationery - 16 April 2026.pdf (unknown)No specific registration or certification is stated in the document. Bidders must comply with quality, safety, and environmental standards referenced: ISO 9001, ISO 14001, OHSAS 18001/ISO 45001, and HACCP.
Health & Safety
Source: Scope of Work for Stationery - 16 April 2026.pdf (unknown)OHSAS 18001:2007/ISO 45001:2018 Occupational Health and Safety Management systems is referenced as a normative standard. The contractor must ensure compliance to all requirements within this document and provide training and create awareness to their employees.
Environmental
Source: Scope of Work for Stationery - 16 April 2026.pdf (unknown)ISO 14001 (Environment) is referenced as an informative standard.
Contractual Terms
Source: Scope of Work for Stationery - 16 April 2026.pdf (unknown)Delivery must be made in accordance with the time stated in the Purchase Order. Time is of the essence; if the supplier fails to deliver, the customer may cancel the contract in whole or in part without liability, refuse subsequent deliveries, purchase substitute items elsewhere, and hold the supplier accountable for any loss and additional costs. The supplier must notify the customer in writing within 24 hours of any conditions impeding timely delivery, stating the likely duration and cause. Delays render the supplier liable for penalties. Goods must be properly packed and secured to reach their destination in good condition. No charge for wrapping, packing, cartons, boxes, crating or containers unless specified in the Purchase Order. The customer is not responsible for returning such materials. Goods must be delivered to the Delivery Place specified in the Purchase Order, subject to inspection and approval. Rejected goods not conforming to specification are returned at the supplier's risk and expense. The supplier must deliver exact quantities specified in the Purchase Order; the customer may reject incomplete deliveries and return excess quantities at the supplier's risk and expense.
Evaluation Criteria
Source: 240-77471499 Annexure B -Safety.pdf (unknown)Bidders must sign and submit Annexure B: Acknowledgement Form for Eskom OHS legal and other requirements (document 240-77471499 Rev 3). The form must be signed by an authorised person (CEO/Director/Managing Director) and witnessed by two witnesses.
Technical Specifications
Source: 240-77471499 Annexure B -Safety.pdf (unknown)appointment of contractors or suppliers for the commencement
of work
Health & Safety
Source: 240-77471499 Annexure B -Safety.pdf (unknown)Bidders must comply with the following OHS documents when working at or rendering a service to Eskom:
After contract award, the supplier must align its processes to Eskom's OHS requirements (policies, procedures, standards).
Penalties will be enforced on the main supplier for non-conformance to Eskom or statutory OHS requirements, including non-conformance by its contractors or suppliers.
All employees (contractors/suppliers) must undergo the relevant Eskom induction.
The main supplier must:
Eskom reserves the right to verify compliance and may instruct the contractor to provide copies of testimonials/references and contact details of clients (including Eskom) for whom the company has done previous similar work.
Contractual Terms
Source: 240-77471499 Annexure B -Safety.pdf (unknown)The main supplier must:
Description
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)The document is the Eskom eTendering System Suppliers Help Manual, which explains how suppliers register and submit bids electronically. It replaces physical submission at Eskom tender offices. Suppliers must register on the portal, verify their email, and use OTP for login. Tender documents are uploaded under categories such as technical, commercial, and finance. The system supports closed tenders, which are sent directly to selected suppliers via email.
Important Dates
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)The closing date for this tender is 25 August 2026 at 10:00. No other dates (briefings, site visits, clarification deadlines) are stated in the document.
Contact Information
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)For system problems with Tender Bulletin, eTendering, or OpenText, contact the buyer responsible for the published tender. No specific contact details are provided in the document.
Submission Guidelines
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)Bids must be submitted electronically through the Eskom eTendering system at https://eTendering.eskom.co.za. Access requires a valid CSD number and prior registration on the portal. During registration, a contact number with a plus prefix (e.g., +27) is required, and an OTP is sent to the cellphone and email for verification. Upload tender documents under the correct category (technical, commercial, finance). Each file must not exceed 50MB, and the total size of all uploaded files must not exceed 900MB. Finalise the submission by clicking 'Finalize Submission' and then 'Finalise and Close Submission'. A confirmation email with a submission ID is sent; retain it for future enquiries.
Evaluation Criteria
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)Bidders must have a valid CSD number to access the eTendering system. Registration on the eTendering portal is required. Closed tenders may be sent directly to suppliers who meet selection and evaluation criteria, but no specific scoring or thresholds are stated in the document.
Technical Specifications
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)The document is a user manual for the Eskom eTendering system, not a specification for stationery supply. It describes how to register, upload, and submit tender documents electronically. No technical specifications for the stationery (types, quantities, quality) are provided.
Compliance Requirements
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)A valid CSD number is required to access the eTendering system. Registration on the eTendering portal is mandatory, including providing a contact number with a plus prefix (e.g., +27). No other compliance requirements are stated.
Section
Source: E-tendering Help Manual for supplier - 27 January 2025A ANNEXURE L.pdf (TENDER)No specific evaluation criteria are provided in the document. It mentions that closed tenders are sent to suppliers who meet selection and evaluation criteria, but the criteria themselves are not detailed.
Evaluation Criteria
Source: Declaration_of_Shareholding_or_Beneficiaries_Form.pdf (unknown)Bidders must be authorised representatives of their organisation and must truthfully declare all shareholders or beneficiaries. Failure to disclose accurately may lead to disqualification.
Compliance Requirements
Source: Declaration_of_Shareholding_or_Beneficiaries_Form.pdf (unknown)Returnable form T2.2a (Declaration of Shareholding or Beneficiaries): bidders must list all shareholders or beneficiaries of their organisation and disclose whether any are employed by or close family members of Eskom employees. A false or incomplete declaration risks disqualification.
Evaluation Criteria
Source: 240-77471499 Annexure B-Safety.docx (unknown)Bidders must sign and submit the Acknowledgement Form (Annexure B) confirming understanding of Eskom OHS requirements. The form must be signed by an authorised person (CEO, Director, or Managing Director) and witnessed by two witnesses. Non-compliance with OHS requirements may result in penalties or termination.
Compliance Requirements
Source: 240-77471499 Annexure B-Safety.docx (unknown)Bidders must comply with Eskom OHS requirements, including Eskom contractor Health and Safety standards 32-136, the Occupational Health and Safety Act 85 of 1993, and the Compensation for Occupational Diseases and Illnesses Act 130 of 1993. After contract award, the supplier must align its processes to Eskom's OHS policies and procedures. The main supplier is accountable for managing its contractors and suppliers, ensuring they have adequate resources and competencies, and monitoring their OHS compliance through audits and assessments. Non-conformances may lead to penalties or termination.
Description
Source: Life Saving-Rules.pdf (unknown)The document is Eskom's Life-Saving Rules standard, not the tender specification. It applies to all Eskom employees, agents, consultants, contractors, and visitors at all Eskom sites. The rules enforce zero tolerance for behaviours with high probability of causing disability or fatality. Contractors are defined as any person or entity formally contracted by Eskom, including vendors, suppliers, agents, joint ventures, fixed-term contractors, principal contractors, and subcontractors.
Contact Information
Source: Life Saving-Rules.pdf (unknown){"name":null,"email":null,"phone":null,"department":"....................................................................... 5","address":null}
Evaluation Criteria
Source: Life Saving-Rules.pdf (unknown)Bidders must be contractors as defined by Eskom, which includes vendors, suppliers, agents, joint ventures, fixed-term contractors, principal contractors, and subcontractors. There is no specific eligibility criteria stated in the provided document beyond compliance with Eskom's Life-Saving Rules and the requirement to remove and discipline employees who violate them.
Technical Specifications
Source: Life Saving-Rules.pdf (unknown)Eskom and its subsidiaries will conduct business with respect and care for people to ensure that no
operating condition or urgency of service endangers the life of anyone or causes injury or damage
to the environment. Eskom is committed to preventing all work-related injuries. In fulfilling this
commitment to protect people, the environment and property, management will provide and
maintain a safe and healthy work environment, in accordance with industry standards and in
compliance with legislative requirements.
At-risk behaviour leads to incidents. Life-saving Rules are safety rules that have been created to
enforce zero tolerance for serious at-risk behaviours. These rules have been determined in terms
of the consequences of the behaviours they describe, that is, if a particular set of behaviours or
actions has a very high probability of causing disabilities or fatalities when performed.
The Eskom Life-saving Rules complement our existing safety best practices and are safety rules to
be followed at all locations.
The Life-saving Rules apply to all Eskom employees, agents, consultants, and contractors. Visitors
to Eskom should also respect and adhere to these rules as applicable and could be instructed to
leave the Eskom premises with immediate effect should they refuse to do so.
2.1 Scope
This standard shall apply at all Eskom sites with the intention to promote a safe working
environment for all Eskom employees, agents, consultants, and contractors. Visitors to Eskom
should also respect and adhere to these rules, as applicable.
2.1.1 Purpose
This standard clarifies the five most prominent causes of serious injuries and fatalities within
Eskom, and non-adherence to
these rules, due to the potential consequences of serious injury or fatality at the workplace.
2.1.2 Applicability
This standard shall apply throughout Eskom Holdings SOC Limited, its divisions, subsidiaries, and
entities wherein Eskom has a controlling interest and/or Eskom contractors, unless specifically
exempted by Sustainability Systems, where the business transacted may be of a completely
different nature to the core business of Eskom.
2.1.3 Effective date
This document will be effective from the date of authorisation.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Life Saving-Rules Unique Identifier: 240-62196227
Revision: 6
Page:
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
[1] ISO 9001 Quality Management Systems
[2] 32-37: Substance Abuse Procedure
[3] 32-95: Environmental, Occupational Health and Safety Incident Management Procedure
[4] 32-136 Contractor Health and Safety Requirements
[5] 32-345 Eskom Vehicle Safety Specification
[6] 32-407 Behavioural Safety Observations
[7] 32-418: Working at Heights Standard
[8] 32-477 Safety, Health and Environment Training and Development Procedure
[9] 32-520 Occupational Health and Safety Risk Assessment Procedure
[10] 32-524 Developing a SHE Specification
[11] 36-681: Plant Safety Regulations
[12] 32-726 SHE requirements for Eskom Commercial Process
[13] 32-727: Safety, Health, Environment and Quality Policy
[14] 32-848: Operating Regulations for High Voltage Systems
[15] 32-1112: Disciplinary Code
[16] 32-1113: Disciplinary Procedure
[17] 240-44175132 Eskom Personal Protective Equipment Specification
[18] 240-62946386: Vehicle and Driver Safety Management Procedure
[19] 240- Refusal to Work in an Unsafe Situation
Procedure
[20] 240-84733329: Medical Surveillance Procedure
[21] 240-100979499 Personal Protective Equipment for Working at Heights Specification
2.2.2 Informative
[22] National Road Traffic Act
[23] Occupational Health and Safety Act
[24] 34-104 Earthing Standard
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Life Saving-Rules Unique Identifier: 240-62196227
Revision: 6
Page:
2.3 Definitions
2.3.1 Contractor: Any person (juristic/individual) formally contracted (directly or indirectly) by
Eskom and who performs work; supplies a service, product, equipment or material for the
purposes of advancin
and third party contractors i.e. vendors, suppliers, agents, joint ventures, fixed term
contractors, principal contractors and subcontractors.
2.3.2 Life-saving Rule: Rules that, if not adhered to, have the potential to cause serious harm to
people. The consequences of a person knowingly and wilfully violating this rule will result in
a disciplinary process in accordance with the Eskom Disciplinary Code and Procedure.
2.3.3 Visitors: Any person who visits an Eskom site/office during working hours to attend a
meeting or for any reason whatsoever. This could include a minor.
2.3.4 Work at height: Means any work performed above a stable work surface or where a
person puts himself/herself in a position where he/she exposes himself/herself to a fall from
or into. Work at height is, as a result, work in any place (except a staircase in a permanent
workplace ), including a place at, above or below ground level, where a person could be
injured if he/she fell from that place. Access and egress that present a risk of fall can also
be classified as work at height.
2.3.5 Zero Tolerance: The standard that provides for the imposition of severe consequences for
a proscribed offence or behaviour without making exceptions for the extenuating
circumstances.
2.4 Abbreviations
Abbreviation Explanation
OHS Occupational Health and Safety
ORHVS Operational Regulations for High Voltage Systems
PPE Personal Protective Equipment
PSR Plant Safety Regulations
PTW Permit to Work
SHEQ Safety, health, environment and quality
2.5 Roles and Responsibilities
2.5.1 Sustainability Systems Department
The sustainability Systems Department shall:
a) Compile and review the Life-saving Rules for Occupational Health and Safety;
b) Develop awareness material;
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Life Saving-Rules Unique Identifier: 240-62196227
Revision: 6
Page:
c) Ensure that the rules are communicated throughout the business;
d) Ensure compliance is monitored; and
e) Ensure that violations and sanctions are consolidated and communicated by Sustainability
Systems to the organisation.
2.5.2 All Groups/Divisions/Operating Units/Business Units
The management at Group/Divisional/Operating Unit/Business Unit level shall be responsible for:
a) Implementing the Eskom Life-saving Rules in their Groups/Divisions/Operating
Units/Business Units.
b) Communicating to all their employees, contractors, contractor employees and visitors the
importance of compliance with the Eskom Life-saving Rules and the consequences of non-
compliance therewith. This includes communicating Life-saving Rules to all new
employees and new contractors.
c) Ensuring that the awareness material is made available, distributed and displayed at all
units.
d) Ensuring all employees sign confirmation that the rules have been discussed with them,
that they understand the rules and the consequences of violating these rules, and retain
copies thereof.
e) Investigating any violation of a Life-saving rule and initiate the disciplinary process within
five (5) working days.
f) Ensuring consistency in the application of appropriate sanctions on employees, contractors
and contractor employees.
2.5.3 All employees (Eskom and contractors)
a) Always observe and adhere to the Life-saving Rules.
b) Avoid taking shortcuts when executing tasks. Always do the right thing even when no-one
is watching.
c) Only perform work that you are authorised to do.
d) All employees to exercise the right to refuse to perform work in an unsafe situation, or when
required to ignore a Life-saving rule.
2.6 Process for Monitoring
Groups/Divisions/Operating Units/Business units are responsible for ensuring the understanding
of, and compliance with, Life-saving Rules. Line management shall monitor compliance and report
on analysis and trending through performance reporting. The amendments to the revised standard
shall be implemented with immediate effect and may be audited after a period of six (6) months
from date of implementation.
2.7 Related/Supporting Documents
[1] 240-62196227 - Life-saving Rules revision 5 (superseded).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Life Saving-Rules Unique Identifier: 240-62196227
Revision: 6
Page:
[2] 240 63942960 - Life-saving Rule Acknowledgement Form Document Content.
Life-saving Rules are safety rules that, if not adhered to, have the potential to cause serious harm
to people. The consequences of a person knowingly and wilfully violating these rules will result in a
disciplinary process in accordance with the Eskom Disciplinary Code and Procedure.
The o ZERO TOLERANCE
respect to behaviour resulting in serious risk to an individual at the workplace.
It must be noted that the content of this standard does not detract from the requirements for safe
behaviour for all other work-related activities or other safety requirements, but emphasises the
importance thereof.
3.1 Eskom Life-Saving Rules
3.1.1 Rule 1: open, isolate, test, earth, bond, and/or insulate before
Touch
With the aim to ensure a safe electrical work environment, no person may work/operate on, around
or near any electrical network, line or apparatus, electrically connected to the power system and/or
electrically charged and/or not electrically charged unless:
a) He/she is trained and authorised as competent for the task to be done;
b) There is a valid permit to work, where required;
c) A pre-task risk assessment to identify all risks and hazards has been conducted prior to any
work commencing;
d) He/she follows the requirements on OPEN, ISOLATE, TEST, EARTH, BOND and/or
INSULATE BEFORE TOUCH, correctly based on applicable/related standards, procedures
and outcome of risk assessment fit for the type of work or task to be performed;
e) The authorised person (team leader) has certified and physically shown all team members that
the apparatus is safe to work on;
f) He/she makes the specific electrical environment safe prior to performing the work; and
g) All the appropriate PPE (including face shield and insulated gloves for low voltage work) are
worn.
3.1.2 Rule 2: hook up at heights
Working at height is a significant part of work in Eskom Holdings and is regarded as a high-risk
activity, and as a result all precautions must be taken to prevent incidents while working at height.
Wherever reasonably practicable, preference must be given to the performance of work at ground
level as opposed to work in an elevated position. Where work in an elevated position is necessary,
the requirements in this document shall apply.
No person may work at height where there is a risk of falling unless:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Life Saving-Rules Unique Identifier: 240-62196227
Revision: 6
Page:
a) He/she is medically fit to work at height;
b) A pre-task risk assessment to identify all risks and hazards has been conducted prior to
commencing any work of this nature;
c) He/she is appropriately trained as determined by the risk assessment;
d) He/she is appropriately secured during ascending and descending; and
e) He/she is using an Eskom approved fall arrest system where applicable.
3.1.3 Rule 3: buckle up
Where required, the proper wearing of seat belts for any driver, operator and passenger is
mandatory in all vehicles/equipment when driving and/or travelling for Eskom business purposes.
The driver is obligated to ensure that he/she as well as all passengers are properly seated and
wearing their seatbelts at all times while being transported in the vehicle, as per Eskom
specifications.
Note: This rule is applicable on any road or parking lot, irrespective of the speed, and when the
vehicle moves in a forward or backward direction.
3.1.4 Rule 4: be sober
No person who is under the influence or who appears to be under the influence of intoxicating
liquor or drugs will be permitted to enter, or remain on an Eskom site or conduct Eskom business
or drive/operate a vehicle/equipment for Eskom business purposes.
This includes any level of alcohol or the presence of any drugs, controlled substances, and/or
illegal substances in the body that impairs or could impair mental and physical functioning,
irrespective of when the substance was used.
3.1.5 Rule 5: ensure that you have a permit to work
Where an authorisation limitation exists, no person shall work without the required Permit to Work
(PTW), which is governed by for example the:
a) Plant Safety Regulations; or
b) Operating Regulations for High Voltage Systems (ORHVS); or
c) Any other activity where a permit is required.
No plant is to be returned to service without the cancellation of all permits on that plant in
accordance with procedure, unless permission is granted for a particular plant to be returned to
service with permits still open, like in the case of redundant systems.
Note:
person, who is the person responsible for the safe execution of work according to relevant
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Life Saving-Rules Unique Identifier: 240-62196227
Revision: 6
Page:
standards and procedures. Outline the key principles or rules to support the implementation of the
standard statement.
3.2 Consequences of violating a Life-Saving Rule
In terms of general health and safety in Eskom, if any of the Life-saving Rules are violated, it will
be treated as a serious misconduct, and result in a disciplinary process in accordance with the
Eskom Disciplinary Code and Procedure.
It must be highlighted that Eskom takes a ZERO TOLERANCE stance to violation of these rules.
Depending on the circumstances, Eskom reserves the right, where a contractor
manager/supervisor allows the violation of a Lifewhile determining an appropriate sanction.
In the light of a contractor employee allegedly violating a Life-saving Rule, the contractor shall
immediately remove the employee from site and initiate the disciplinary process. The contractor
shall investigate any violation of a Life-saving Rule and initiate the disciplinary process within five
(5) working days of the violation. The contractor shall after the disciplinary process furnish Eskom
with a copy of the sanction.
This document has been seen and approved by:
Name Designation
Thava Govender Group Executive Generation and (Acting) Risk and Sustainability
Divisions
Kerseri Pather General Manager Sustainability Systems
Jace Naidoo Senior Manager Sustainability Systems OHS
Alex Stramrood Senior Manager Sustainability Systems OHS
Risk and Sustainability Members of the Risk and Sustainability Management Committee
Management Committee
HR Policies and Procedures Members of the HR Policies and Procedures Committee
Committee
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Life Saving-Rules Unique Identifier: 240-62196227
Revision: 6
Page:
Date Rev. Compiler Remarks
January 2017 6 A Stramrood
Updated the Purpose and
Applicability to specify that this
Standard is applicable to
contractors. Updated Normative
and Informative References.
Updated Definition section by
removing Agent and Consultant as
these have been incorporated into
the definition of Contractor.
Updated the definition of Work at
Height and Zero Tolerance.
Reviewed and updated the Roles
and Responsibilities section and
Process for Monitoring. Added
permit requirement to Rule 1,
updated Rule 2 - Removed the
as this is no longer a requirement
in terms of the Construction
Regulations, 2014 and updated
Rule 3 (for
example transporting people on
the back of trucks in a cabin)
Updated Consequences of
violating a Life-saving Rule with
regard to contractors.
October 2015 5 A Stramrood Revision date needed to be
extended. Content still valid and
same.
May 2012 4 S Govender Amended Section 3.6
Consequences of Violating a Life-
saving Rule to align with EXCO
decision.
March 2013 3 S Govender Changed Cardinal Rules to Life-
saving Rules, and amended
content to ensure better
understanding of the intent and
requirements.
September 2010 2 K Terblanche Content of Rev 1 was incorporated
into the new Policy template.
Content was revised and updated.
December 2008 1 K Terblanche Annexure 1: Acknowledgement of
Eskom Life-saving Rules of this
document was removed. The
references made to Annexure 1 in
paragraphs 3.5.2 and 3.8 were
also removed.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Life Saving-Rules Unique Identifier: 240-62196227
Revision: 6
Page:
Date Rev. Compiler Remarks
August 2008 0 K Terblanche The document with reference
number 32-421 was developed
and approved.
The following people were involved in the development of this document:
Alex Stramrood
Kerseri Pather
Loraine Smit
Marc Lebea
Mike Townsend
Nosipho Noveve
Sheryl Isaacs
Sivi Govender
SN Middel
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Compliance Requirements
Source: Life Saving-Rules.pdf (unknown)No specific requirements found
Health & Safety
Source: Life Saving-Rules.pdf (unknown)Violating a Life-Saving Rule is treated as serious misconduct and triggers a disciplinary process under the Eskom Disciplinary Code and Procedure. Eskom takes a zero-tolerance stance. Where a contractor employee violates a rule, the contractor must immediately remove the employee from site, investigate the violation, initiate disciplinary process within five working days, and provide Eskom with a copy of the sanction.
Description
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Eskom Holdings SOC Ltd invites tenders for the supply and delivery of stationery at Tutuka Power Station for a period of five (5) years.
Important Dates
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Closing date and time: 25 August 2026 at 10h00 (SAST).
Clarification queries: must be submitted in writing 7 working days before the tender submission deadline.
No compulsory meeting, site visit, or clarification meeting will be held.
Contact Information
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Eskom Representative: Moleboheng Radebe
All queries and clarifications must be addressed in writing to the Eskom Representative only.
Fraud and corruption reporting: 0800 11 2722 / [email protected]
Submission Guidelines
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Submission channel: electronic only via the Eskom E-tendering site (Eskom Tender Bulletin). No hard copies accepted. Upload documents under folders Technical, Commercial, Financial, and Other. All documents in PDF format; the price list must be in PDF and a copy in Excel. No zip/condensed files. If resubmitting, only the latest version is accepted; previous versions become null and void. Ensure the submission status is marked complete. Late tenders are not accepted. Upload size per document is 500 MB; total submission restricted to 4 GB.
Mandatory returnables (disqualifiable if missing or incomplete):
Returnables required at closing but non-disqualifiable (5 working days to remedy):
Returnables required for evaluation (score zero if not submitted):
Mandatory contractual requirement: proof of valid and current CSD registration.
Disqualification risks: missing mandatory returnables, unsigned forms, late submission, non-compliance with eligibility criteria, submitting more than one tender, conflict of interest, or subcontracting 100% of the scope.
Returnable Documents
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Mandatory returnables (disqualifiable): Authorisation Form (Annexure A), Acknowledgement Form (Annexure B), Tenderer's Particulars (Annexure C), Integrity Pact Declaration (Annexure D), CPA for local goods/services (Annexure E), SBD 6.2 Declaration Certificate for Local Production and Local Content (Annexures G1-G4), SBD 1 (Annexure H), SBD 4 Bidders Disclosure (Annexure J).
Non-disqualifiable returnables (5 working days to remedy): Tax Clearance Certificate (if applicable), Employment Equity compliance proof (if designated employer), NEC or other Contract completed in full, Pricing Schedule, additional documents (ECSA/SACPCMP/CVs/permits/licenses if applicable).
Returnables for evaluation: SBD 6.1 Preference Points Claim Form (Annexure I), Specific Goals evidence.
Mandatory contractual requirement: Proof of valid and current CSD Registration.
Additional contractual requirements: Safety (OHS risk assessment, SHE Plan, letter of good standing, OHS policy), Quality (Quality Method Statement, Quality Policy, Quality Objectives, QMS evidence), Environmental (waste management plan, environmental policy), Financial analysis (2 years comparative financial statements).
Evaluation Criteria
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Functionality (Technical) criteria: weight 100%, threshold 70%. Bidders failing the 70% threshold are disqualified.
Technical evaluation criteria (total 100%):
Price evaluation: prices inclusive of VAT, corrected for arithmetical errors, excluding contingencies, adjusted for variations, compared on Net Present Value. Unconditional discounts considered; conditional discounts not considered for evaluation but applied at payment. Prices scored out of 80 points.
Specific Goals: scored out of 20 points in accordance with PPPFA. Failure to submit evidence results in 0 points for that goal but not disqualification.
Ranking: 80/20 preferential point system; price + specific goals scores added and ranked highest to lowest.
Objective criteria: Local Procurement Content target 100%. Eskom may award to a tenderer other than the highest scoring if objective criteria justify.
Technical Specifications
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Scope: supply and delivery of stationery at Tutuka Power Station for a period of five (5) years.
Technical evaluation criteria (see evaluationCriteria for scoring):
Cataloguing: the successful tenderer may be required to provide cataloguing information per item after contract award and label all materials per Eskom's labelling specifications. If cataloguing is required, the pricing schedule must include a line item for cataloguing, which Eskom will pay for.
Methodology
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Risk analysis: Time risk (failure to deliver on time) mitigated by ordering with sufficient stock buffer; Cost risk (supplier funds) mitigated by monthly ordering; Scope risk (supplier not delivering batch orders) mitigated by enforcing NEC3 clauses; SHEQ risks (non-compliance) mitigated by induction, training, check sheets, verifying delivery notes; Supplier risk (not meeting mandatory requirements) mitigated by submitting all requirements; Other risks (non-compliance to NEC3) mitigated by exercising NEC clauses.
Experience & Qualifications
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Technical evaluation criteria: Bidders must submit reference letter(s) on client letterheads demonstrating relevant experience in supply of similar stationery. Scoring: 5 points for 5+ years cumulative experience, 4 points for 4 years, 2 points for 1-3 years, 0 points for less than 1 year. Also, letter of intent from supplier for stationery procurement, proof of existing agreement not older than 3 months, and proof of delivery vehicle ownership/lease.
Quality Management
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Quality requirements: Quality Method Statement based on scope, Quality Policy approved by top management, Quality Objectives approved by top management, documented information for roles/responsibilities, control of externally provided processes, products and services, Form A completed and signed.
Pricing Schedule
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Pricing schedule must be submitted in PDF and a copy in Excel format. The price list needs to be submitted in both formats.
If cataloguing is required, the pricing schedule must include a line item for cataloguing, which Eskom will pay for.
Prices evaluated inclusive of VAT, corrected for arithmetical errors, excluding contingencies, adjusted for variations, compared on Net Present Value. Unconditional discounts considered; conditional discounts applied at payment.
Financial Requirements
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Pricing schedule: must be submitted in PDF and a copy in Excel format. The price list must be submitted in both formats.
Payment terms: for contracts below R50,000,000 (including VAT), Eskom pays within 30 days of receipt of undisputed invoices. For contracts above R50,000,000 (including VAT), Eskom pays within 60 days.
Eskom reserves the right to negotiate with preferred bidders if tendered prices are not market-related.
Financial analysis: latest 2 years comparative financial statements required (audited/reviewed reports, directors' report, statement of financial position, comprehensive income, changes in equity, cash flows, notes). For close corporations: signed accounting officer's report, members' report, and similar statements. For joint ventures: signed JV agreement indicating percentage shareholding. For new entities (less than 1 year old): owner's 5-year tax returns and financial position. If a subsidiary's financials are consolidated into the holding company, a signed guarantee letter is required. Parent Company Guarantee or Performance Bond may be required on Eskom-approved templates.
Compliance Requirements
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Eligibility: bidders must not be under restriction to do business with Eskom or state-owned companies; must not have nationality of a sanctioned country; must not have conflict of interest; must not be on National Treasury restricted list or Tender Defaulters list; must not subcontract 100% of scope; must not submit more than one tender; JV/consortium must have joint and several liability.
Mandatory returnables (disqualifiable):
Returnables for evaluation:
Mandatory contractual requirement: proof of valid and current CSD registration.
Tax compliance: certified tax clearance certificate required if not on CSD or no SARS PIN. Foreign suppliers with no SA footprint complete SBD 1 but no tax proof required.
Employment Equity: designated employers must provide proof of compliance, including submission of EE report to the Department of Labour.
B-BBEE: proof of B-BBEE status level certificate (issued by authorised body) or sworn affidavit as per B-BBEE Codes of Good Practice.
Safety requirements: acknowledgement of Eskom's OHS legal and other requirements form, baseline OHS risk assessment, SHE Plan aligned with scope, valid letter of good standing, OHS policy signed by CEO.
Quality requirements: comply with ISO 9001; submit quality method statement, quality policy approved by top management, quality objectives, documented information for roles/responsibilities, control of externally provided processes/products/services, and Form A completed and signed.
Environmental requirements: acknowledgement of Eskom's SHE rules and requirements form, waste management plan (reduction, re-use, recycling, disposal), environmental induction, environmental (or SHE/SHEQ) policy signed by owner/CEO/MD, commitment to compliance and environmental duty of care.
Health & Safety
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Safety requirements: Acknowledgement of Eskom's OHS legal and other requirements form, Baseline OHS risk assessment, SHE Plan addressing project OHS risks, valid letter of good standing, OHS policy signed by CEO.
Environmental
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Environmental requirements: Acknowledgement of Eskom's SHE rules and requirements form, Waste management Plan (reduction, re-use, recycling, disposal), Environmental induction, Environmental (or SHE/SHEQ) policy signed by Company Owner/CEO/MD, commitment to compliance and environmental duty of care.
Contractual Terms
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Contract conditions: NEC3 Term Service Contract (TSC).
Mandatory contractual requirements: proof of CSD registration.
Additional contractual requirements (assessed after evaluation): SHEQ requirements, financial viability, and others. Failure to meet may result in non-responsiveness.
Payment terms: 30 days for contracts below R50m, 60 days for contracts above R50m.
Eskom may negotiate with preferred bidders if prices not market-related.
Subcontracting with subsidiaries discouraged and must be declared.
Requirements
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Eligibility criteria: tenderers must not be under any restriction to do business with Eskom or state-owned companies. Ineligible if: nationality of a country on international sanctions list; submitting more than one tender (except where size limits apply); JV/consortium without joint and several liability; conflict of interest; signed by non-authorised persons; restricted by National Treasury; on Tender Defaulters list; or subcontracting 100% of the scope. Eskom will disqualify tenderers not meeting eligibility criteria.
Section
Source: Invitation to Tender (ITT) - Stationery ...pdf (TENDER)Functionality requirements applicable. Technical Criteria weight 100%, threshold 70%. Tenderers failing 70% threshold disqualified.
Technical criteria (total 100%):
Prices scored out of 80 points. Specific Goals scored out of 20 points. Ranking by 80/20 system. Objective criteria: Local Procurement Content 100%. SBD 6.2 and Annex C are tender returnables.
Description
Source: Eskom_Standard_Conditions_of_Tender_.pdf (TENDER)Supply and delivery of stationery at Tutuka Power Station for a period of five (5) years. Specific items and quantities are defined in the specification and/or works information.
Important Dates
Source: Eskom_Standard_Conditions_of_Tender_.pdf (TENDER)Closing time:
Site visit / clarification meeting:
Clarification queries:
Addenda:
Contact Information
Source: Eskom_Standard_Conditions_of_Tender_.pdf (TENDER)Fraud and corruption reporting:
General communication:
Submission Guidelines
Source: Eskom_Standard_Conditions_of_Tender_.pdf (TENDER)Submission format:
Returnable documents:
Disqualification risks:
Evaluation Criteria
Source: Eskom_Standard_Conditions_of_Tender_.pdf (TENDER)Evaluation stages:
Preference points:
Other evaluation rules:
Technical Specifications
Source: Eskom_Standard_Conditions_of_Tender_.pdf (TENDER)Scope:
Quality Management
Source: Eskom_Standard_Conditions_of_Tender_.pdf (TENDER)Quality requirements:
Pricing Schedule
Source: Eskom_Standard_Conditions_of_Tender_.pdf (TENDER)Pricing format:
Arithmetical corrections:
Ranking:
Financial Requirements
Source: Eskom_Standard_Conditions_of_Tender_.pdf (TENDER)Pricing:
Arithmetical corrections:
Security for performance:
Insurance:
Costs:
Compliance Requirements
Source: Eskom_Standard_Conditions_of_Tender_.pdf (TENDER)Mandatory registrations and certificates:
Returnable forms:
Other compliance:
Contractual Terms
Source: Eskom_Standard_Conditions_of_Tender_.pdf (TENDER)Form of Agreement:
Requirements
Source: Eskom_Standard_Conditions_of_Tender_.pdf (TENDER)Misrepresentation:
Description
Source: NEC3SC - Supply and Delivery of Stationery Revised Quantities -30-07-2026.pdf (unknown)Supply and delivery of stationery to Tutuka Power Station for a period of five years, as and when required, under an NEC3 Supply Contract (SC3) between Eskom Holdings SOC Ltd and the Supplier.
Contact Information
Source: NEC3SC - Supply and Delivery of Stationery Revised Quantities -30-07-2026.pdf (unknown)The document does not provide a specific contact for this tender. The Supply Manager details are to be inserted in the Contract Data. The Purchaser is Eskom Holdings SOC Ltd, registered office at Megawatt Park, Maxwell Drive, Sandton, Johannesburg. The NEC3 Supply Contract guidance notes are available from Engineering Contract Strategies, Tel 011 803 3008, Fax 086 539 1902, www.ecs.co.za.
Submission Guidelines
Source: NEC3SC - Supply and Delivery of Stationery Revised Quantities -30-07-2026.pdf (unknown)Returnable documents: C1.1 Form of Offer and Acceptance, C1.2b Contract Data provided by the Supplier, and the completed Price Schedule (C2.2). The Offer is accepted by the Purchaser signing the Acceptance part of the Form of Offer and Acceptance and returning one copy, including the Schedule of Deviations, within the validity period. Bidders must complete the Contract Data Part Two with the tendered total of Prices and delivery dates. Any deviations from the tender documents must be recorded in the Schedule of Deviations; a covering letter is not part of the final contract. Bidders must arrange delivery of any securities, bonds, guarantees, proof of insurance and other documentation within two weeks of receiving the completed agreement. Failure to fulfil these obligations constitutes repudiation of the agreement. Alternative tenders require a separate copy of the Form of Offer and Acceptance.
Evaluation Criteria
Source: NEC3SC - Supply and Delivery of Stationery Revised Quantities -30-07-2026.pdf (unknown)The document does not specify a scoring split or preference point system. Bidders must complete the Contract Data Part Two, including the tendered total of Prices and delivery dates. Bidders must be able to provide required securities and guarantees. Bidders must comply with Eskom's additional conditions, including B-BBEE status change notification and ethics provisions. Bidders must be registered on the Central Supplier Database (CSD) and have a valid tax clearance, as is standard for Eskom tenders.
Technical Specifications
Source: NEC3SC - Supply and Delivery of Stationery Revised Quantities -30-07-2026.pdf (unknown)Scope: Supply and delivery of stationery to Tutuka Power Station as and when required, for a period of five years. The contract is an NEC3 Supply Contract (SC3). Goods are delivered to the main stores at Tutuka Power Station. The Supplier is responsible for transporting goods to the delivery place. The Supplier gives notice of delivery, checks packing and marking, contracts for transport, pays transport costs, and loads the goods; the Purchaser arranges access and unloads. Goods must be to the standard and quality accepted by the Purchaser and suitable for the purpose intended by the manufacturer. No compensation is payable if the Supplier arrives on site without prior arrangement. The Supplier must provide packing lists, invoices, delivery notes, test results and maintenance manuals. The Risk Register includes late deliveries, default during offloading, industrial actions, community strikes, and bad quality of goods.
Methodology
Source: NEC3SC - Supply and Delivery of Stationery Revised Quantities -30-07-2026.pdf (unknown)The document does not specify a methodology or execution plan beyond the general supply requirements. The Supplier must give notice of delivery, check packing and marking, contract for transport, pay transport costs, and load the goods. The Purchaser arranges access to the delivery place and unloads the goods. The Supplier must provide packing lists, invoices, delivery notes, test results and maintenance manuals.
Pricing Schedule
Source: NEC3SC - Supply and Delivery of Stationery Revised Quantities -30-07-2026.pdf (unknown)The pricing data includes pricing assumptions and the price schedule. The Prices are the amounts stated in the price column of the Price Schedule. The amount due is calculated based on lump sum items or quantities multiplied by rates. The Price Schedule is only a pricing document, not Goods Information. The tendering supplier should insert any additional items. The total of the Prices is assumed to be fully inclusive of everything necessary. The supplier must include costs for correction of defects. There is no adjustment to lump sum prices if quantities change, except through compensation events. The format of the price schedule: entries in the first four columns are made by the Purchaser or the tendering supplier. For lump sum items, the amount is entered in the Price column only. For rate-based items, the rate and quantity are entered to produce the Price. For time-based items, a unit of time and quantity are stated.
Financial Requirements
Source: NEC3SC - Supply and Delivery of Stationery Revised Quantities -30-07-2026.pdf (unknown)Pricing: The contract is a priced contract under NEC3 SC3. The Price Schedule (C2.2) lists items priced as lump sums or quantities multiplied by rates. The tendered total of Prices must be fully inclusive of everything necessary to provide the goods and services. The Supplier must include costs for correction of defects (core clause 43.1) as there is no compensation event for this unless the defect is due to a Supplier's risk. There is no adjustment to lump sum prices if quantities change; the only basis for a change is a compensation event per clause 60.1. Payment: The assessment interval is between the 26th day of each successive month. Payments are made within 4 weeks. The currency is South African Rand. Interest on late payments is at the publicly quoted prime rate of Standard Bank of South Africa (or LIBOR for other currencies). The Supplier must provide a tax invoice within one week of receiving a payment certificate; late submission extends the payment period. The Supplier's VAT number must be included on each invoice, and the Purchaser's VAT number is 4740101508. The Supplier's liability for indirect or consequential loss is limited to 50% of the contract value; total liability is limited to the total contract value. The end of liability date is 6 months after delivery of the whole of the goods and services. Delay damages for delivery are 2% of the purchase order value per day, capped at 10%. Low performance damages are replacement within 2 working days at contractor cost plus 2% of affected order value.
Compliance Requirements
Source: NEC3SC - Supply and Delivery of Stationery Revised Quantities -30-07-2026.pdf (unknown)Returnable forms: C1.1 Form of Offer and Acceptance (signed offer and acceptance), C1.2b Contract Data provided by the Supplier, and the Price Schedule (C2.2). B-BBEE: The Supplier must notify the Purchaser within seven days of any change in B-BBEE status, and submit an updated verification certificate within thirty days. If B-BBEE status decreases, the Purchaser may re-negotiate or terminate. Failure to notify may constitute a reason for termination. Joint ventures: members are jointly and severally liable; the key person with authority to bind the Supplier must be notified within two weeks of the Contract Date; composition may not be altered without consent. Ethics: The Supplier may not take any Prohibited Action (coercive, collusive, corrupt, fraudulent, obstructive); the Purchaser may terminate for such actions. Insurance: The Supplier must provide insurances stated in Insurance Table A; the Purchaser provides insurances in Insurance Table B. The Supplier must comply with all applicable health, safety and environmental laws and regulations. Asbestos provisions apply: the Purchaser manages asbestos according to its standard; the Supplier's personnel may stop work if asbestos is identified. The Supplier must be registered on the Central Supplier Database (CSD) and have a valid tax clearance, as is standard for Eskom tenders.
Health & Safety
Source: NEC3SC - Supply and Delivery of Stationery Revised Quantities -30-07-2026.pdf (unknown)The Supplier must take all reasonable precautions to maintain the health and safety of persons in and about the provision of the goods and execution of the services. The total of the Prices must include a sufficient amount for proper compliance with all applicable health and safety laws and regulations. The Supplier must comply with all applicable environmental laws and regulations. Asbestos provisions apply: the Purchaser ensures ambient air conforms to the prescribed South African standard for asbestos (OEL 0.2 fibres per ml as a 4-hour TWA, short-term 0.6 fibres per ml as a 10-minute TWA). The Purchaser manages asbestos and ACM according to its standard. If asbestos is identified, a risk assessment is conducted and immediate control measures implemented. The Supplier's personnel may stop work and leave the contaminated area until declared safe. Any removal and disposal of asbestos is done by a registered asbestos contractor instructed by the Purchaser at the Purchaser's expense.
Contractual Terms
Source: NEC3SC - Supply and Delivery of Stationery Revised Quantities -30-07-2026.pdf (unknown)Annexure A: Supply Requirements. The Supplier supplies goods in accordance with INCOTERMS 2010. The obligations of seller and buyer for the selected Incoterm determine costs, risks and insurance. The Supply Requirements include: no compensation if the Supplier arrives on site without prior arrangement; all goods delivered to the main stores; goods must be to the standard and quality accepted by the Purchaser; the Supplier is responsible for transporting goods to the delivery place (Tutuka Power Station); the Supplier gives notice of delivery, checks packing and marking, contracts for transport, pays transport costs, and loads the goods; the Purchaser arranges access to the delivery place and unloads the goods. The Supplier must provide packing lists, invoices, delivery notes, test results and maintenance manuals.
Section
Source: NEC3SC - Supply and Delivery of Stationery Revised Quantities -30-07-2026.pdf (unknown)The document does not specify evaluation criteria beyond the requirement to complete the Contract Data Part Two and provide required securities and guarantees. The Risk Register includes bad quality of goods as a risk.
Description
Source: 240-12248652_List of Tender Returnables_Cat 4_ Rev 7-Quality.xlsxThe tender is for the supply and delivery of stationery at Tutuka Power Station for a period of five years. The quality scorecard template requires bidders to select the applicable category (Category 4 is indicated as applicable) and complete the returnables tab accordingly. The scope of work is stationery supply and delivery.
Submission Guidelines
Source: 240-12248652_List of Tender Returnables_Cat 4_ Rev 7-Quality.xlsx (unknown)Returnable documents: bidders must complete and sign Form A. The tender pack includes a quality scorecard template with sections A to E; bidders must select the applicable category on the cover tab and complete the returnables tab accordingly. The completed template must be saved as PDF and signed, or signed and locked before sending to the buyer.
Evaluation Criteria
Source: 240-12248652_List of Tender Returnables_Cat 4_ Rev 7-Quality.xlsx (unknown)Quality evaluation is weighted across five sections: Section A (Quality Management System, 25%), Section B (Evidence of QMS in operation, 25%), Section C (Contract Quality Plan, 20%), Section D (Quality Control Plan, 20%), Section E (User defined additional requirements, 10%). For Section A, bidders may choose either Option 1 (valid ISO 9001 certificate with relevant scope, issued by an accredited authority) or Option 2 (evidence of an implemented QMS including a QMS manual, quality policy, quality objectives, and documented information for control of nonconforming outputs and corrective action). Section B requires documented information for defined roles, responsibilities and authorities, and for control of externally provided processes, products and services, plus audit reports and management review records. Section C requires a draft Contract Quality Plan specific to the scope of work. Section D requires a Quality Control Plan or Inspection and Test Plan for similar work. Section E requires Form A completed and signed, plus any other requirements per the scope.
Technical Specifications
Source: 240-12248652_List of Tender Returnables_Cat 4_ Rev 7-Quality.xlsx (unknown)The tender is for the supply and delivery of stationery at Tutuka Power Station for a period of five years. The quality scorecard template requires bidders to select the applicable category (Category 4 is indicated as applicable) and complete the returnables tab accordingly. The scope of work is stationery supply and delivery.
Compliance Requirements
Source: 240-12248652_List of Tender Returnables_Cat 4_ Rev 7-Quality.xlsx (unknown)Bidders must complete and sign Form A as part of the quality evaluation. No other compliance requirements (e.g., CSD registration, B-BBEE, CIDB grading) are stated in the provided document.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
Tutuka Power Station - Standerton - Standerton - 2430
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
13
Last checked
07 Aug 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Learn how to submit a winning bid with these related articles
Guide to printing tenders. From Annual Reports to Security Printing. Understanding the Government Printing Works (GPW) relationship and capacity requirements.
How small office supplies, stationery, and general goods suppliers use Joint Ventures to win government procurement contracts by combining inventory with B-BBEE credentials.
Office stationery tenders are a high-volume entry point for many SMEs. Learn how to source competitively, price effectively, and win these operational mandates.
Not every job is a 'tender.' Learn how to access the high-volume world of small orders (RFQs) and how to get invited to bid on jobs under R200k.
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Supplies: Stationery/Printing. Unlock full pricing strategies, bid frequency, and historical win rates.