Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
GARIEP HYDRO STATION - - Xhariep District Municipality -
Organization Type
GOVERNMENT
Published
04 Sept 2026
OCDS Reference
ocds-9t57fa-169074
ESKOM is procuring building and infrastructure maintenance services at the gariep hydro station on an as-and-when-required basis for five years. Bidders must hold a valid iso 9001-certified quality management system and submit the specified quality documentation, including form a, to be considered.
Bidders must complete, sign, and return Form A (Tender and Contract Quality Requirements for Supplier Quality Management Specification 240-105658000/QM 58 and ISO 9001) with the bid.
Bidders must hold a valid ISO 9001 certificate (or applicable QMS standard) from an accredited certification body, unless specifically excluded for the selected quality category.
Bidders must submit documented evidence of a developed, implemented, and maintained QMS, including internal and external audit reports with any nonconformities and remedial actions.
Depending on the quality category (1-4) indicated in Form A, bidders must submit a draft contract quality plan (per ISO 10005), an example inspection and test plan (ITP) or quality control plan (QCP), and documented information for control of externally provided processes, roles and responsibilities, and management review records.
Bidders must submit a quality method statement, quality policy, and quality objectives if the applicable category requires them.
Personnel performing special processes (e.g., NDT, welding) must be certified competent through accredited providers per SETA requirements, and training certificates must meet SETA requirements.
Eskom may perform supplier capability and capacity assessments prior to contract award for high-risk products, critical plant work, or special processes.
Continue with tenders sharing this issuer, category, or province.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Thursday, 08 October 2026 - 10:00
Venue
https://teams.microsoft.com/meet/359938769603162?p=2IKrfmeXGKd1stOCr2
Important: Attendance at this briefing session is mandatory. Bids from suppliers who do not attend may be disqualified.
Categories
Request for Bid(Open-Tender)
GARIEP HYDRO STATION - - Xhariep District Municipality -
Tenders in this industry often require registration with these bodies.
Construction Industry Development Board (CIDB) registration is mandatory for almost all public sector construction tenders. Ensure your grading matches the tender value.
Recommended Certifications
Having these can improve your winning chances: NHBRC Registration, ISO 9001:2015 (Quality Management), ISO 14001:2015 (Environmental Management), ISO 45001:2018 (Occupational Health & Safety), SACPCMP Registration, ECSA Registration
AI Document Analysis Stages
Description
04 Sept
2026
Tender Published
Tender was published
08 Oct
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Attachment 4 TSC3.pdf
Provision of building and infrastructure maintenance services at Eskom's Gariep Hydro Station (and other peaking sites) on an as-and-when-required basis for five years, under an NEC3 Term Service Contract (TSC3) with Task Orders.
Attachment 8 240-105658000 Supplier Quality Management Specification.pdf
Eskom is procuring building and infrastructure maintenance services at the Gariep Hydro Station on an as-and-when-required basis for a five-year contract. The tender is governed by Eskom's Supplier Quality Management specification, which mandates that bidders demonstrate a quality management system conforming to ISO 9001 and submit various quality-related documents as part of their bid.
Attachment 13 Eskom - Standard Conditions of Tender.pdf
Eskom is procuring building and infrastructure maintenance services at the Gariep Hydro Station on an as-and-when-required basis for a five-year period. The tender is an open invitation and will be evaluated under Eskom's standard conditions of tender, with compliance and eligibility criteria applying.
Attachment 3 Scope of work Building Maintenance.pdf
Provision of building and infrastructure maintenance services on an as-and-when-required basis for Eskom's Peaking power stations (Drakensberg, Ingula, Vanderkloof, Gariep, Port Rex, and Gourikwa) for a period of five years. The scope covers preventative, corrective, reactive, emergency, refurbishment, and minor construction services for buildings, civil infrastructure, utilities, and support facilities.
Attachment 5 Technical Evaluation.pdf
Eskom is procuring a five-year, as-and-when-required contract for building and infrastructure maintenance services at the Gariep Hydro Station (part of a broader Peaking Generation fleet contract covering six sites). The scope includes repairs to buildings, roofing, waterproofing, roads, civil infrastructure, plumbing, sewer systems, electrical building services, fencing, security infrastructure, and fire protection systems. Bidders must demonstrate relevant experience, submit detailed methodologies and quality control plans, and provide key personnel and plant resources.
Invitation to Tender ITT GARIEP.pdf
Eskom is procuring building and infrastructure maintenance services at the Gariep Hydro Station on an as-and-when-required basis for a five-year period. The contract will be governed by the NEC3 Term Service Contract (TSC3), and bidders must meet mandatory technical, safety, and quality requirements.
Attachment 1- Tax Evaluation questionnaire.pdf
Eskom is procuring building and infrastructure maintenance services at the Gariep Hydro Station on an as-and-when-required basis for a five-year period. The tender includes a detailed PAYE evaluation pack to determine the tax classification of the contractor (independent contractor vs. personal service provider) for withholding purposes.
Attachment 2 - E-Tendering Training Acknowledgement Form.pdf
Eskom is procuring building and infrastructure maintenance services at Gariep Hydro Station on an as-and-when-required basis for a five-year period. The document provided is solely an acknowledgement form confirming that the bidder has completed self-training on the e-Tendering solution, with no details on scope, pricing, or evaluation criteria.
Attachment 12 Supplier Declaration of Interest Template (1).pdf
Eskom is procuring building and infrastructure maintenance services at the Gariep Hydro Station on an as-and-when-required basis for a period of five years. The tender is issued by Eskom in the Free State province, with a closing date of 8 October 2026.
Attachment 9 Safety.pdf
Eskom is procuring building and infrastructure maintenance services at the Gariep Hydro Station on an as-and-when-required basis for a five-year period. The tender is issued by Eskom in the Free State province, with a closing date of 8 October 2026.
Attachment 14 SDLI Strategy.pdf
Provision of building and infrastructure maintenance services at Gariep Hydro Station on an as-and-when-required basis for a period of five (5) years, issued by Eskom in the Free State. The contract duration is 60 months, and the tender includes specific goals for B-BBEE preference points, mandatory local content requirements for designated sectors, and a compulsory CIDB skills development goal.
Attachment 7 240-68099512 Form A_Cat 3_ Rev 9.docx
Provision of building and infrastructure maintenance services at Gariep Hydro Station on an as-and-when-required basis for a period of five years, issued by Eskom in the Free State.
Attachment 10 Peaking OHS Baseline risk assessment - Rev.6 2025.04.30.xlsx
ESKOM is procuring building and infrastructure maintenance services at the Gariep Hydro Station on an as-and-when-required basis for a period of five (5) years. The tender is issued by ESKOM in the Free State province, with a closing date of Thu Oct 08 2026 10:00:00 GMT+0000. The document content provided consists of Occupational Health and Safety Baseline Risk Assessment templates for Sere Wind Farm and Small Hydros, which are not directly related to the tender specification.
Attachment 6 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsx
The document is a tender evaluation scorecard for the provision of building and infrastructure maintenance services at the Gariep Hydro Station, issued by Eskom for a period of five years. It details the quality management system requirements, including ISO 9001 certification or evidence of an operational QMS, and provides weighted scoring criteria across five sections for evaluating tender submissions.
Attachment 11 Non-Disclosure Agreement (NDA) Generic Template - 06 August 2024.pdf
Provision of building and infrastructure maintenance services at Eskom's Gariep Hydro Station on an as-and-when-required basis for a five-year period.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
R 4 727 112
Range
Based on 3 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
This is a supplier quality management specification (240-105658000, revision 3) that applies to all Eskom suppliers and sub-suppliers. It defines minimum quality requirements for selection, evaluation, vendor registration, management, monitoring, assessment, and auditing of suppliers. The specification is part of all Eskom procurement processes, including RFIs, RFQs, RFPs, and contracts.
Contact Information
Source: Attachment 8 240-105658000 Supplier Quality Management Specification.pdf (unknown)Supply Chain Management (department only; no named contact, email, phone, or address provided in the document).
Submission Guidelines
Source: Attachment 8 240-105658000 Supplier Quality Management Specification.pdf (unknown)Returnable documents: Form A (Tender and Contract Quality Requirements for Supplier Quality Management Specification 240-105658000/QM 58 and ISO 9001) must be completed, signed, and returned with the bid. Other returnables are listed in the List of Tender Returnables (240-12248652). Depending on the quality category (1-4) selected for this tender, returnables may include: a valid ISO 9001 certificate, internal and external audit reports, a draft contract quality plan, an example inspection and test plan (ITP) or quality control plan (QCP), documented information for control of externally provided processes, roles and responsibilities, management review records, quality policy, quality objectives, and a quality method statement.
Returnable Documents
Source: Attachment 8 240-105658000 Supplier Quality Management Specification.pdf (unknown)Suppliers must complete and sign Form A (Tender and Contract Quality Requirements) and submit it with other returnables listed in the List of Tender Returnables (240-12248652). Depending on the category, returnables include ISO 9001 certificate, audit reports, draft contract quality plan, example ITP/QCP, documented information for control of externally provided processes, roles/responsibilities, management review records, quality policy, quality objectives, and quality method statement.
Evaluation Criteria
Source: Attachment 8 240-105658000 Supplier Quality Management Specification.pdf (unknown)Quality requirements are classified into four categories (1, 2, 3, 4); only one category applies per procurement. The applicable category is indicated in Form A and determines the exact returnable documentation. Bidders must complete and sign Form A to acknowledge and accept Eskom's supplier quality requirements. The supplier must have a formal quality management system (QMS) conforming to ISO 9001. Unless excluded, a valid ISO 9001 certificate from an accredited certification body is required. The latest internal and external audit reports must be submitted, including any nonconformities and remedial actions. Supplier capability and capacity assessments may be performed prior to contract award for high-risk products, critical plant work, or special processes.
Technical Specifications
Source: Attachment 8 240-105658000 Supplier Quality Management Specification.pdf (unknown)This specification applies to all Eskom divisions, subsidiaries, suppliers, and sub-suppliers, and forms part of all Eskom RFIs, RFQs, RFPs, and contracts for products and services. The supplier must develop, implement, maintain, and continually improve a QMS based on ISO 9001. The QMS must include documented information such as a quality manual, quality plans, work procedures, work instructions, and method statements. The supplier must inform Eskom of any proposed changes to the QMS or staff affecting the quality system. The main supplier is responsible for managing sub-supplier quality assurance and control, including performance management programmes covering QMS verification, audits, CQP/QCP reviews, nonconformity management, inspection and test plans, and risk management. Where specified, all products, services, and processes must have a documented contract quality plan (CQP) and/or quality control plan (QCP)/inspection and test plan (ITP). CQPs must comply with ISO 10005 and be submitted prior to the initial kick-off or pre-fabrication meeting. QCPs/ITPs must be reviewed and accepted by Eskom, allow for hold and witness points, and become addendums to the contract once signed. A quality kick-off meeting is held at contract start; coordination meetings require 14 days' notice. Mandatory pre-inspection meetings are convened by Eskom. Eskom may appoint resident quality inspectors and any inspection agency; the supplier must provide workspace at no cost and may not obstruct the agency's work.
Methodology
Source: Attachment 8 240-105658000 Supplier Quality Management Specification.pdfThe supplier must develop and implement processes to monitor, verify, and document quality of deliverables. This includes preparing QCPs/ITPs at a level of detail sufficient to address all quality-control-related activities in chronological order, from contract review through materials verification, manufacturing, fabrication, assembly, final testing, commissioning, hand-over documentation, and certification. The supplier must also establish processes for formal assessment of sub-supplier inspection and testing programmes, and for verification of purchased product compliance.
Experience & Qualifications
Source: Attachment 8 240-105658000 Supplier Quality Management Specification.pdfPersonnel performing special processes must be certified competent through internal training or external certification bodies (e.g., NDT) as per SETA requirements. Training needs must be identified and documented, with certificates meeting SETA requirements. Quality control inspectors must be qualified per Project Quality Personnel Qualification Specification.
Quality Management
Source: Attachment 8 240-105658000 Supplier Quality Management Specification.pdfThe supplier must develop, implement, maintain, and continually improve a QMS conforming to ISO 9001. The QMS must include documented information such as quality manual, quality plans, work procedures, and method statements. A valid ISO 9001 certificate is required unless excluded. The supplier must submit audit reports, a draft contract quality plan (per ISO 10005), and an example ITP/QCP. QCPs/ITPs must be reviewed and accepted by Eskom, with hold and witness points. A quality kick-off meeting is held at contract start; coordination meetings require 14 days' notice. Mandatory pre-inspection meetings are convened by Eskom.
Compliance Requirements
Source: Attachment 8 240-105658000 Supplier Quality Management Specification.pdf (unknown)ISO 9001 certification (or applicable QMS standard) from an accredited certification body is required unless specifically excluded. The supplier must submit documented evidence of a developed, implemented, and maintained QMS. Internal and external audit reports must be provided. Personnel performing special processes must be certified competent (e.g., NDT) through accredited providers per SETA requirements; training certificates must meet SETA requirements. Quality control inspectors must be qualified per the Project Quality Personnel Qualification Specification. B-BBEE minimum level 1 is stated (no further details in the document).
Health & Safety
Source: Attachment 8 240-105658000 Supplier Quality Management Specification.pdfThe specification references Eskom's Safety, Health, Environment, and Quality (SHEQ) Policy (32-727) and IAEA Safety Standard GS-R-3.1. No specific health and safety requirements are detailed in this document.
Contractual Terms
Source: Attachment 8 240-105658000 Supplier Quality Management Specification.pdfStandard conditions include Eskom's rights of access to supplier facilities and information, rights to oversee audit programmes, and preservation requirements. Nonconformities must be managed per contractual conditions, with repeated nonconformities escalated to management review committees. Special processes require qualified operators and maintained qualification records. The supplier must ensure preservation requirements are documented and communicated, and Eskom has free access to preservation records.
Section
Source: Attachment 8 240-105658000 Supplier Quality Management Specification.pdfQuality requirements are categorised into four levels (1-4). The applicable category is indicated in Form A and determines the returnable documentation. Bidders must complete and sign Form A to accept Eskom's quality requirements. A valid ISO 9001 certificate is required unless excluded. Audit reports, draft contract quality plan, example ITP/QCP, and documented information for control of externally provided processes must be submitted as per the category.
Evaluation Criteria
Source: Attachment 5 Technical Evaluation.pdf (unknown)Bidders must attend the compulsory virtual clarification meeting (attendance register is the mandatory evidence). Bidders must meet all mandatory technical criteria on tender closing; failure results in disqualification. Bidders must achieve a minimum overall technical score of 70% on qualitative criteria. Acceptable risks include subcontracting specialist trades (roofing, waterproofing, fire protection, access control) and hiring/leasing specialised plant, provided proof of availability is demonstrated. Unacceptable risks include: inability to demonstrate relevant experience, lack of access to minimum plant/equipment, reliance entirely on subcontractors without management capability, no emergency response capability, or methodology presenting unacceptable quality/safety/operational risks. Unacceptable exceptions include: not covering the full scope, limiting emergency maintenance responsibility, reducing quality control/inspection/testing requirements, proposing personnel who do not meet minimum qualifications, or response times not meeting Works Information requirements.
Technical Specifications
Source: Attachment 5 Technical Evaluation.pdf (unknown)Peaking Generation operates a diverse portfolio of power stations comprising Drakensberg Power Station,
Ingula Pumped Storage Scheme, Gariep Power Station, Vanderkloof Power Station, Port Rex Power
Station and Gourikwa Power Station. The buildings, civil infrastructure, utilities and associated support
facilities at these stations are critical to safe, reliable and efficient power generation operations. Over time,
these assets are subjected to deterioration arising from ageing, environmental exposure, operational use,
water ingress, corrosion, structural defects, drainage failures and normal wear and tear.
The purpose of the Building and Infrastructure Maintenance contract is to provide planned, preventative,
corrective, reactive and emergency building and infrastructure maintenance services on an “as and when
required” basis across the six Peaking Generation sites for a period of five (5) years. The scope includes
maintenance and repair of buildings, roofing and waterproofing systems, roads and civil infrastructure,
plumbing and sewer systems, electrical building services, fencing and security infrastructure, fire
protection systems, and associated facilities required to maintain asset integrity and operational readiness.
This Technical Evaluation Strategy has been developed to assess tenderers’ capability, experience,
resources and technical understanding to successfully execute the required services across multiple
geographically dispersed sites. The evaluation process is intended to identify contractors who possess the
necessary technical competence, organisational capacity, appropriately qualified personnel, plant and
equipment resources, and proven maintenance experience to deliver the services safely, efficiently and in
accordance with Eskom standards, applicable legislation, relevant SANS requirements and contract
obligations.
The strategy defines the mandatory and qualitative technical evaluation criteria, evaluation methodology,
technical scoring framework, responsibilities of the Tender Evaluation Team (TET), and acceptable
technical risks and qualifications to be considered during the evaluation process. The objective is to ensure
the appointment of technically capable contractors who can effectively support the long-term maintenance,
reliability and sustainability of building and infrastructure assets across the Peaking Generation fleet.
2.1 Scope
The scope of this document is to define the tender technical evaluation strategy for a 5-year maintenance
contract for Gourikwa, Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof Power Station buildings
and associated infrastructure. The Tender Technical Evaluation Strategy defines the following with regards
to the project.
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
Technical Evaluation Strategy for the Provision of
Unique Identifier: 167A/20886-A Building and Infrastructure Maintenance at Gourikwa,
Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof Revision: 1
Power Station for a Period of Five (5) Years Page:
2.1.1 Purpose
The purpose of this tender technical evaluation strategy is to define the Mandatory Evaluation Criteria,
Qualitative Evaluation Criteria and TET member responsibilities for tender technical evaluation. The
technical evaluation strategy serves as basis for the tender technical evaluation process.
2.1.2 Applicability
This document applies to all Tenderers responding to the enquiry and members of the Tender Evaluation
Team responsible for the technical evaluation.
2.2 Normative/informative references
Parties using this document shall apply the most recent edition of the documents listed in the following
paragraphs.
2.2.1 Normative
[1] 240-168966153: Generation Tender Technical Evaluation Procedure
[2] ISO 9001 Quality Management Systems
[3] 240-53716726: Technical Scoring Form
2.2.2 Informative
[4] 167A/20886: Scope of work for Building & Infrastructure Maintenance Services on an 'As and When
Required' Basis for Eskom Peaking.
2.3 Definitions
Definition Description
Tender A tender refers to an open or closed competitive
request for quotations/ prices against a clearly
defined scope/ specification.
2.3.1 Classification
Controlled Disclosure: Controlled Disclosure to external parties (either enforced by law, or discretionary).
2.4 Abbreviations
Abbreviation Description
A&A Auxiliary & Ancillaries
CV Curriculum Vitae
DB Distribution Board(s)
ISO International Organization for Standardization
N/A Not Applicable
QCP Quality Control Plan
SANS South African National Standards
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
Technical Evaluation Strategy for the Provision of
Unique Identifier: 167A/20886-A Building and Infrastructure Maintenance at Gourikwa,
Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof Revision: 1
Power Station for a Period of Five (5) Years Page:
Abbreviation Description
SoW Scope of Work
SEM System Engineering Manager
TET Tender Evaluation Team
2.5 Roles and responsibilities
As per 240-168966153: Generation Tender Technical Evaluation Procedure for Generation.
2.6 Process for monitoring
N/a
2.7 Related/supporting documents
N/a
3.1 Technical evaluation threshold
Technical evaluation will be conducted using a weighted scorecard. Tenderers must achieve a minimum
overall score of 70% to be considered technically acceptable.
Mandatory Technical Evaluation Criteria are gatekeepers and will be evaluated on a Yes/No basis. These
criteria are not scored. Failure to meet any mandatory criterion will result in disqualification and the tender
will not proceed to the qualitative evaluation stage.
Qualitative Technical Evaluation Criteria will be applied only to tenderers that meet all mandatory criteria.
These criteria are weighted according to their relative importance, and a minimum weighted score of 70%
is required for the tender to be considered technically acceptable.
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
Technical Evaluation Strategy for the Provision of
Unique Identifier: 167A/20886-A Building and Infrastructure Maintenance at Gourikwa,
Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof Revision: 1
Power Station for a Period of Five (5) Years Page:
Table 1: Qualitative Evaluation Criteria Scoring Guideline
Score percentage description
5 100 compliant
4 80 compliant with associated qualifications
o Acceptable technical risk(s) AND/OR
o Acceptable exceptions AND/OR
o Acceptable conditions.
2 40 non-compliant
0 0 totally deficient or non-responsive
Note 1: The scoring table does not allow for scoring of 1 and 3.
Note 2: Foreseen acceptable and unacceptable risk(s), exceptions and conditions shall be
unambiguously defined in the relevant Tender Technical Evaluation Strategy.
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
3.2 Mandatory technical evaluation criteria
Tenderers shall submit all documentation and evidence as specified below. These criteria shall be evaluated on a compliance basis
(Yes/No).
Failure to meet any mandatory requirement shall result in disqualification from further evaluation.
Tenderers who do not meet all mandatory criteria shall not proceed to the technical (qualitative) evaluation stage.
3.2.1 Mandatory Technical Evaluation Criteria on Tender Closing
Table 2 defines the Mandatory Technical Evaluation Criteria on Tender Closing.
Table 2: Mandatory Technical Evaluation Criteria on Tender Closing
Mandatory Technical Criteria Description Evidence Motivation for use of Criteria
which will be conducted virtually via Microsoft Teams. Attendance register site conditions, access requirements,
Physical attendance at site is not required. operational constraints and geographical
spread of the contract.
3.3 Qualitative technical evaluation criteria
Tenderers who meet all mandatory criteria shall be evaluated against the Qualitative Technical Evaluation Criteria, as defined below.
Evaluation shall be based on a weighted scoring system and a minimum threshold score of 70% must be achieved to be considered
technically acceptable.
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
Table 3 defines all Qualitative Technical Evaluation Criteria to be submitted by the Contractor by the tender closing date. Should the
Contractor fail to submit these criteria by the tender closing date, the Contractor will score zero for each of the criterion stipulated in the
table below.
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
Table 3: Qualitative Technical Evaluation Criteria
Qualitative Technical Criteria Description Reference to Technical Criteria Weighting Criteria Sub
Specification / Tender Returnable (%) Weighting
(%)
1.1 Contractor Experience: Works Information 70.00
The Tenderer shall submit evidence of successfully completed building
and infrastructure maintenance projects completed within the last ten
(10) years.
Projects should include one or more of the following:
Building maintenance
Roofing and waterproofing
Civil infrastructure
Roads and pavements
Plumbing services
Electrical building services
Security infrastructure
Fire protection systems
For each project submitted, the Tenderer shall provide:
Project name
Client name
Brief description of the scope of work
Contract value
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
Contract duration (start and completion dates)
Project location
Percentage of work undertaken by the Tenderer (where applicable)
Acceptable evidence shall include:
Completion certificates
Contract award letters
Purchase orders/work orders
Appointment letters
Signed completion reports or
Practical completion certificates
1.2 Client References: Works Information 15.00
The Tenderer shall provide client references for similar building and
infrastructure maintenance projects successfully completed.
A minimum of three (3) client references shall be submitted.
Each reference shall include:
Client organisation
Contact person's name
Telephone number and/or email address
Project description
Contract value
Contract duration
Date of completion
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
1.3 Multi-Site Maintenance Experience: Works Information 15.00
Experience on geographically dispersed sites/ multiple sites.
2.1 Building Maintenance Method Statement: Works Information 35.00
Methodology as defined in the SoW for:
Roofing
Waterproofing
Painting
Doors and windows
Flooring and ceilings
Building fabric repairs
2.2 Civil Infrastructure Methodology: Works Information 30.00
Methodology as defined in the SoW for:
Roads
Stormwater systems & Drainage structure
Culverts
Potholes
Concrete repairs
2.3 Plumbing and Sewer Methodology: Works Information 15.00
Methodology as defined in the SoW for:
Sewer blockages and backflow
Reticulation repairs
Manholes
Water systems
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
2.4 Electrical and Security Infrastructure Methodology: Works Information 15.00
Methodology as defined in the SoW for:
Lighting
Distribution boards
Gate motors
Access control systems
Security infrastructure
2.5 Emergency Maintenance Strategy: Works Information 5.00
The Tenderer must demonstrate:
Callout capability
Response process
Escalation matrix
Availability of resources
3.1 Civil & Building Quality Control Plan: Works Information 60.00
The Tenderer submits QCP’s for all activities showing:
Activities
Inspection points
Hold points
Witness points
Check sheets
Records.
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
3.2 Electrical & Security Infrastructure Quality Control Plan: Information 20.00
The Tenderer submits QCP’s for all activities showing:
Activities
Inspection, Hold & Witness points
Check sheets & Records
3.3 Inspection & Test Strategy: 20.00
Tenderer demonstrates understanding of:
Inspection requirements
Testing requirements
Handover requirements
Defect management
4.1 Resource: Key Personnel: Works Information 50.00
The tenderer must provide CVs for all key staff needed for the
maintenance work. This includes:
Contract Manager
Supervisor
Electrician with Wireman’s License
Plumber
Building/Civil Artisan
Scaffold Supervisor/Inspector
Rope Access Supervisor/Technician
All personnel must have minimum of three (3) years’ experience
relevant to the works.
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
4.2 Plant & Equipment: 25.00
Plant list covering as a minimum:
Vehicles
Compaction equipment
Concrete tools
Drain cleaning equipment
Pressure cleaning equipment
Electrical testing equipment
Fall protection equipment
Access equipment required for execution of repair works
The Tenderer shall provide proof of ownership, availability or valid
lease/hire agreements for key plant and access equipment.
4.3 Organogram and Resource Deployment: 25.00
The Tenderer demonstrates via the organogram:
Head Office support
Site support
Multi-site resource deployment
Escalation structure
Total: 100.00
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
3.4 Qualitative technical criteria – scoring measures
Table 4: Qualitative Technical Evaluation Criteria – Scoring Measures
Civil & Structural Technical Criteria
Criteria Qualitative Technical Criteria Description Criteria Sub
No Weighting Range Score
(%)
1.1 Contractor Experience: No experience submitted or experience not related 0
to building and infrastructure maintenance works. The Tenderer shall submit evidence of successfully completed building
and infrastructure maintenance projects completed within the last ten Less than three similar projects submitted and/or 2
(10) years. limited scope similarity.
Projects should include one or more of the following:
Three similar projects submitted covering most 4
Four or more similar projects submitted covering 5
Civil infrastructure building, civil, roads, plumbing, electrical, security
Roads and pavements and fire protection maintenance works.
Plumbing services 70.00
Electrical building services
Security infrastructure
Fire protection systems
For each project submitted, the Tenderer shall provide:
Project name
Client name
Brief description of the scope of work
Contract value
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
Contract duration (start and completion dates)
Project location
Percentage of work undertaken by the Tenderer (where
applicable)
Acceptable evidence shall include:
Completion certificates
Contract award letters
Purchase orders/work orders
Appointment letters
Signed completion reports or
Practical completion certificates
1.2 Client References: No references submitted. 0
The Tenderer shall provide client references for similar building and Less than three references submitted and/or 2
infrastructure maintenance projects successfully completed. incomplete information provided.
Three acceptable references submitted with all 4
A minimum of three (3) client references shall be submitted. required information.
Each reference shall include:
Four or more acceptable references submitted with 5
Client organisation 15.00 all required information and directly relevant scope.
Contact person's name
Telephone number and/or email address
Project description
Contract value
Contract duration
Date of completion
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
Acceptable evidence shall include:
Client reference letters
Signed client performance evaluations
Completion certificates containing client contact details
Client satisfaction/performance reports
1.3 Multi-Site Maintenance Experience: No evidence of multi-site maintenance experience. 0
Tenderer shall demonstrate experience in executing building and Experience limited to a single site or limited 2
infrastructure maintenance works across geographically dispersed evidence of multi-site execution.
sites under a single contract or multiple concurrent contracts.
Evidence demonstrates successful execution of 4 Multiple work areas within the same facility shall not be considered
maintenance works across 2-3 geographically multi-site experience. The Tenderer must demonstrate experience
dispersed sites concurrently. across two or more geographically separate facilities or locations.
The Tenderer shall provide evidence in the form of: Evidence demonstrates successful execution of 5
maintenance works across 4 or more
geographically dispersed sites concurrently.
Purchase orders
Contract award letters 15.00
Completion certificates
Signed client performance reports
The evidence shall clearly indicate:
Number of sites serviced
Geographical spread of the sites
Scope of maintenance works performed
Whether the sites were serviced concurrently
Contract Duration
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
Building Maintenance Method Statement: 2.1 No method statement submitted or non-compliant. 0
Methodology as defined in the SoW for:
Method statement addresses less than 50% of 2
Method statement addresses all listed activities and 5
2.2 Civil Infrastructure Methodology: No method statement submitted or non-compliant. 0
Methodology as defined in the SoW for: Method statement addresses less than 50% of 2
Roads required activities.
Stormwater systems & Drainage structure 30.00 Method statement addresses at least 75% of the 4
Culverts listed activities.
Potholes Method statement addresses all listed activities and 5
Concrete repairs includes execution methodology, quality controls
and safety controls for each activity.
2.3 Plumbing and Sewer Methodology: No method statement submitted or non-compliant. 0
Methodology as defined in the SoW for: Method statement addresses less than 50% of 2
Sewer blockages required activities.
Reticulation repairs 15.00 Method statement addresses at least 75% of the 4
Manholes listed activities.
Sewer backflow Method statement addresses all listed activities and 5
Water systems including sewer blockages, reticulation repairs,
manholes, sewer backflow and water systems.
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
2.4 Electrical and Security Infrastructure Methodology: No method statement submitted or non-compliant. 0
Methodology as defined in the SoW for: Method statement addresses less than 50% of 2
Lighting required activities.
Distribution boards 15.00 Method statement addresses at least 75% of the 4
Gate motors listed activities.
Access control systems Method statement addresses all listed activities and 5
Security infrastructure includes execution methodology, quality controls
and safety controls for each activity.
2.5 Emergency Maintenance Strategy: No emergency maintenance strategy submitted. 0
The Tenderer must demonstrate: Strategy submitted but missing one or more of the 2
commitments, escalation matrix, or resource
allocation plan.
Strategy includes a documented call-out procedure, 4
defined response time commitments, escalation
matrix, and identified resources available for
emergency maintenance.
5.00
Strategy includes all requirements for a score of 4, 5
and additionally provides:
24/7 call-out availability
Response time commitments for different
incident priorities
emergency response
and contacts
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
3.1 Civil & Building Quality Control Plan (QCP): No QCP submitted. 0
The Tenderer submits QCP’s for all activities showing: QCP addresses fewer than three required 2
Activities elements.
Inspection, Hold & Witness points 60.00 QCP addresses at least three required elements. 4
Check sheets
QCP addresses all required elements: activities, 5
records.
3.2 Electrical & Security Infrastructure Quality Control Plan (QCP): No QCP submitted. 0
The Tenderer submits QCP’s for all activities showing: QCP addresses fewer than three required 2
Activities elements.
Inspection, Hold & Witness points 20.00 QCP addresses at least three required elements. 4
Check sheets
QCP addresses all required elements: activities, 5
records.
3.3 Inspection & Test Strategy: No inspection and test strategy submitted. 0
Tenderer demonstrates understanding of: Strategy submitted but addresses only 1 or 2 of the 2
requirements, handover requirements, or defect
management process.
20.00 Strategy addresses at least 3 of the required 4
elements and provides documented procedures for
implementation.
Strategy addresses all 4 required elements and 5
includes documented inspection activities, test
procedures and acceptance criteria, handover
requirements, and a defined defect management
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
process with responsibilities and close-out
requirements.
4.1 Resource: Key Personnel: Key personnel not submitted or major omissions 0
identified. CVs for all key staff needed for the maintenance work. This includes:
positions and/or one or more proposed personnel
do not meet the minimum qualification or
50.00 CVs submitted for at least 75% of the required 4
minimum of three (3) years' relevant experience.
All personnel must have minimum of three (3) years’ experience CVs submitted for 100% of the required positions. 5
relevant to the works. All personnel meet the minimum qualification
requirements and have a minimum of three (3)
years' relevant experience.
4.2 Plant & Equipment: No plant and equipment schedule submitted. 0
Plant list covering as a minimum: Plant and equipment schedule submitted but 2
equipment categories.
includes at least 75% of the minimum required
equipment categories.
Plant and equipment schedule submitted and 5
includes all minimum required equipment
but not limited to:
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
o Scaffolding systems
o Mobile scaffolding towers
o Mobile elevated work platforms (MEWPs)
o Man-lifts/cherry pickers
o Ladders
o Rope access/abseiling equipment.
The Tenderer shall provide proof of ownership, availability or valid
lease/hire agreements for key plant and access equipment.
4.3 Organogram and Resource Deployment: No organogram submitted. 0
The Tenderer demonstrates via the organogram: Organogram addresses only 1 or 2 of the following: 2
resource deployment, Escalation structure.
requirements.
Comprehensive organisational structure 5
demonstrating head office support, site support,
multi-site management capability, resource
deployment strategy and escalation structure.
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
3.5 Tet member responsibilities
Key: X = Mandatory; O = Optional
Table 5: TET Member Responsibilities
Mandatory Criteria TET 1 TET 2 TET 3 TET 4 TET 5 TET 6 TET 7 TET 8 TET 9
1 x x x x x x x x o
Qualitative Criteria TET 1 TET 2 TET 3 TET 4 TET 5 TET 6 TET 7 TET 8 TET 9
1.1 X x x x o
1.2 X x x x o
1.3 X x x x o
2.1 X x x x o
2.2 X x x x o
2.3 X x x x o
2.4 X x x x
2.5 X x x x x x x x o
3.1 X x x x o
3.2 X x x x
3.3 X x x x x x x x o
4.1 X x x x x x x x o
4.2 X x x x o
4.3 X x x x x x x x o
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1 Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
3.6 Foreseen acceptable / unacceptable qualifications
3.6.1 Risks
Table 6: Acceptable Technical Risks
Risk Description
Contractor subcontracts plant and machine operators with relevant skills, experience and competency certificates.
Contractor utilises specialist subcontractors for roofing, waterproofing, fire protection systems, access control systems or security infrastructure, provided
that the subcontractors possess the required experience and qualifications.
Certain specialised plant and equipment are hired or leased, provided proof of availability can be demonstrated upon request.
Contractor shares resources between multiple sites provided adequate resource planning and service delivery capability are demonstrated.
Table 7: Unacceptable Technical Risks
Risk Description
Contractor or subcontractor cannot demonstrate the required experience relevant to the allocated scope of work.
Contractor does not have access to the minimum plant, equipment or specialist tools required to execute the works.
Contractor relies entirely on subcontractors for execution of the core scope of works without demonstrating management and supervision capability.
Contractor cannot demonstrate an emergency response capability for urgent and breakdown maintenance work.
Contractor's methodology presents unacceptable quality, safety or operational risks to Eskom facilities.
3.6.2 Exceptions / Conditions
Table 8: Acceptable Technical Exceptions / Conditions
Risk Description
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa,
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
demonstrated.
Table 9: Unacceptable Technical Exceptions / Conditions
Risk Description
Tenderer proposal does not cover the full scope of building and infrastructure maintenance services.
Tenderer qualifies or limits responsibility for emergency maintenance and breakdown response services.
Tenderer proposes reduced quality control, inspection or testing requirements contrary to the Works Information.
Tenderer proposes personnel who do not meet the minimum qualifications, competencies or experience requirements.
Tenderer's proposed response times do not meet the requirements defined in the Works Information.
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the
system.
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
Building and Infrastructure Maintenance at Gourikwa, Revision: 1
Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof Page:
Power Station for a Period of Five (5) Years
Controlled disclosure
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
Methodology
Source: Attachment 5 Technical Evaluation.pdf (unknown)Technical evaluation will be conducted using a weighted scorecard. Tenderers must achieve a minimum threshold score of 70% to be considered. Mandatory Technical Evaluation Criteria are gatekeepers and will be evaluated on a Yes/No basis. Failure to meet any mandatory criterion will result in disqualification. Qualitative Technical Evaluation Criteria will be applied only to tenderers that meet all mandatory criteria. Scoring measures include: Contractor Experience (35%), Building & Civil Maintenance Methodology (35%), Quality Management (15%), and Resource: Key Personnel (15%). Detailed scoring guidelines are provided in Table 4.
Experience & Qualifications
Source: Attachment 5 Technical Evaluation.pdf. Introduction ...................................................................................................................................................... 3
2.1 Scope .............................................................................................................................................................. 3
2.1.1 Purpose ..................................................................................................................................................... 4
2.1.2 Applicability................................................................................................................................................ 4
2.2 Normative/informative references .................................................................................................. 4
2.2.1 Normative .................................................................................................................................................. 4
2.2.2 Informative ................................................................................................................................................. 4
2.3 Definitions .................................................................................................................................................... 4
2.3.1 Classification ............................................................................................................................................. 4
2.4 Abbreviations .............................................................................................................................................. 4
2.5 Roles and responsibilities .................................................................................................................... 5
2.6 Process for monitoring ........................................................................................................................ 5
2.7 Related/supporting documents ......................................................................................................... 5
3.1 Technical evaluation threshold ....................................................................................................... 5
3.2 Mandatory technical evaluation criteria .................................................................................... 7
3.2.1 Mandatory Technical Evaluation Criteria on Tender Closing .................................................................... 7
3.3 Qualitative technical evaluation criteria .................................................................................... 7
3.4 Qualitative technical criteria – scoring measures................................................................ 15
3.5 Tet member responsibilities ............................................................................................................... 23
3.6 Foreseen acceptable / unacceptable qualifications............................................................. 24
3.6.1 Risks ........................................................................................................................................................ 24
3.6.2 Exceptions / Conditions ........................................................................................................................... 24
2.1 Scope
The scope of this document is to define the tender technical evaluation strategy for a 5-year maintenance
contract for Gourikwa, Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof Power Station buildings
and associated infrastructure. The Tender Technical Evaluation Strategy defines the following with regards
to the project.
5 100 compliant
4 80 compliant with associated qualifications
o Acceptable technical risk(s) AND/OR
o Acceptable exceptions AND/OR
o Acceptable conditions.
2 40 non-compliant
0 0 totally deficient or non-responsive
Note 1: The scoring table does not allow for scoring of 1 and 3.
Note 2: Foreseen acceptable and unacceptable risk(s), exceptions and conditions shall be
unambiguously defined in the relevant Tender Technical Evaluation Strategy.
Specification / Tender Returnable (%) Weighting
(%)
1.1 Contractor Experience: Works Information 70.00
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
1.3 Multi-Site Maintenance Experience: Works Information 15.00
maintenance work. This includes:
Contract Manager
Supervisor
Electrician with Wireman’s License
Plumber
Building/Civil Artisan
Scaffold Supervisor/Inspector
Rope Access Supervisor/Technician
All personnel must have minimum of three (3) years’ experience
relevant to the works.
(%)
1.1 Contractor Experience: No experience submitted or experience not related 0
to building and infrastructure maintenance works. The Tenderer shall submit evidence of successfully completed building
and infrastructure maintenance projects completed within the last ten Less than three similar projects submitted and/or 2
(10) years. limited scope similarity.
Three similar projects submitted covering most 4
Four or more similar projects submitted covering 5
Civil infrastructure building, civil, roads, plumbing, electrical, security
Roads and pavements and fire protection maintenance works.
Plumbing services 70.00
Electrical building services
Security infrastructure
Fire protection systems
Client reference letters
Signed client performance evaluations
Completion certificates containing client contact details
Client satisfaction/performance reports
1.3 Multi-Site Maintenance Experience: No evidence of multi-site maintenance experience. 0
Tenderer shall demonstrate experience in executing building and Experience limited to a single site or limited 2
infrastructure maintenance works across geographically dispersed evidence of multi-site execution.
sites under a single contract or multiple concurrent contracts.
Evidence demonstrates successful execution of 4 Multiple work areas within the same facility shall not be considered
maintenance works across 2-3 geographically multi-site experience. The Tenderer must demonstrate experience
dispersed sites concurrently. across two or more geographically separate facilities or locations.
The Tenderer shall provide evidence in the form of: Evidence demonstrates successful execution of 5
maintenance works across 4 or more
geographically dispersed sites concurrently.
Purchase orders
Contract award letters 15.00
Completion certificates
Signed client performance reports
Revision: 1Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
process with responsibilities and close-out
requirements.
4.1 Resource: Key Personnel: Key personnel not submitted or major omissions 0
identified. CVs for all key staff needed for the maintenance work. This includes:
positions and/or one or more proposed personnel
do not meet the minimum qualification or
50.00 CVs submitted for at least 75% of the required 4
minimum of three (3) years' relevant experience.
All personnel must have minimum of three (3) years’ experience CVs submitted for 100% of the required positions. 5
relevant to the works. All personnel meet the minimum qualification
requirements and have a minimum of three (3)
years' relevant experience.
4.2 Plant & Equipment: No plant and equipment schedule submitted. 0
Plant list covering as a minimum: Plant and equipment schedule submitted but 2
equipment categories.
includes at least 75% of the minimum required
equipment categories.
Plant and equipment schedule submitted and 5
includes all minimum required equipment
but not limited to:
Revision: 1 Port Rex, Ingula, Drakensberg, Gariep & Vanderkloof
Power Station for a Period of Five (5) Years Page:
3.6 Foreseen acceptable / unacceptable qualifications
3.6.1 Risks
Table 6: Acceptable Technical Risks
that the subcontractors possess the required experience and qualifications.
Quality Management
Source: Attachment 5 Technical Evaluation.pdf (unknown)Quality Management criteria include: Civil & Building Quality Control Plan (QCP) with inspection points, Electrical & Security Infrastructure QCP with Inspection, Hold & Witness points, and Inspection & Test Strategy covering inspection requirements, testing requirements, handover requirements, and defect management. Tenderers must submit these by tender closing date; failure results in zero score for each criterion.
Compliance Requirements
Source: Attachment 5 Technical Evaluation.pdf (unknown)Completion certificates
Completion certificates containing client contact details
Appointment letters
proof of ownership, availability or valid
Special Conditions
Source: Attachment 5 Technical Evaluation.pdf (unknown)Tenderers must demonstrate emergency response capability for urgent and breakdown maintenance work. Subcontractors must possess required experience and qualifications. Alternative equipment, materials, or maintenance methods may be proposed if equivalence or superiority is demonstrated. Additional quality control measures exceeding specified requirements are acceptable. Tenderers must not qualify or limit responsibility for emergency maintenance and breakdown response services.
Section
Source: Attachment 5 Technical Evaluation.pdfTechnical Evaluation StrategyTitle: Unique Identifier: 167A/20886-A
Template Identifier: 240-53716769 Tender Technical Evaluation Strategy Template (Rev 2) (Next Review Date July 2027)
Technical Evaluation Strategy for the Provision of
Technical Evaluation Strategy for the Provision of Unique Identifier: 167A/20886-A
ender technical evaluation. The
technical evaluation strategy serves as basis for the tender technical evaluation process.
This document applies to all Tenderers responding to the enquiry and members of the Tender Evaluation
Team responsible for the technical evaluation.
[1] 240-168966153: Generation Tender Technical Evaluation Procedure
[2] ISO 9001 Quality Management Systems
QCP Quality Control Plan
TET Tender Evaluation Team
As per 240-168966153: Generation Tender Technical Evaluation Procedure for Generation.
3.1 Technical evaluation threshold
Technical evaluation will be conducted using a weighted scorecard. Tenderers must achieve a minimum
overall score of 70% to be considered technically acceptable.
Mandatory Technical Evaluation Criteria are gatekeepers and will be evaluated on a Yes/No basis. These
criteria are not scored. Failure to meet any mandatory criterion will result in disqualification and the tender
will not proceed to the qualitative evaluation stage.
Qualitative Technical Evaluation Criteria will be applied only to tenderers that meet all mandatory criteria.
Description
Source: Attachment 1- Tax Evaluation questionnaire.pdfProvision of building and infrastructure maintenance services at Gariep Hydro Station on an as-and-when-required basis for a period of five (5) years.
Important Dates
Source: Attachment 1- Tax Evaluation questionnaire.pdf (unknown){"closingDate":"1 March 2022"}
Evaluation Criteria
Source: Attachment 1- Tax Evaluation questionnaire.pdf (unknown)Bidders must be residents of South Africa (or non-residents must sign Appendix 9). They must complete the evaluation pack accurately and sign all required affidavits and declarations. Failure to sign required appendices may result in PAYE being withheld from payments. Bidders must not have connected persons rendering services to Eskom unless disclosed. Bidders must not receive more than 80% of income from a single client unless declared. Bidders must not be subject to Eskom's control or supervision unless declared.
Technical Specifications
Source: Attachment 1- Tax Evaluation questionnaire.pdf (unknown)The Fourth Schedule to the Income Tax Act (“the Act”) requires that Employees' Tax must be
withheld from "remuneration" paid by an "Employer" to an "Employee". This tool is intended to establish
whether an Individual, Close Corporation, Company or Trust should be classified as an Independent
Contractor, Personal Service Provider, Labour Broker or a Dependent Contractor, and the tax
consequences of such classification.
This Pack is applicable ONLY to Contractors who supply Eskom Holdings SOC Ltd (“Eskom”) and its
subsidiaries with services or Individual Contractors providing Eskom with labour.
The Contractor or its duly authorised representative must declare that all questions have been answered
truthfully.
Answering the questions will direct you to your next step.
Please note:
This Pack is based on tax legislation for the 2022/2023 tax year and is subject to change.
In the questions, any references to "you" refers to the Contractor.
In the questions, the term Contractor is used interchangeably with Individual/CC/Company/Trust.
Definitions as per the Income Tax Act are included in Appendix 10.
Any reference to “Eskom” refers to Eskom Holdings SOC Ltd and its subsidiaries:
Eskom Rotek Industries SOC Ltd
Eskom Enterprises SOC (Pty) Ltd
Escap SOC (Pty) Ltd
Eskom Finance Company SOC (Pty) Ltd
Eskom Foundation NPC
National Transmission Company SA
The Pack is based on legislation and case law applicable to the 2022/2023 tax year. We therefore
recommend that, if it is used outside of this period, you should first consult with your representative in
Eskom to refer it to Eskom’s Corporate Tax Department in Megawatt Park.
When you return the completed Pack; i.e. the signed summary sheet and signed affidavits to Eskom,
please copy Group Tax on Email address: [email protected]
The Contractor or its duly Authorised Representative acknowledges and accepts that:
ease of reading.
this Pack;
Disclaimer
Applicable to the 2022/2023 Tax Years
Eskom accepts no liability whatsoever for any loss or damages whatsoever and howsoever incurred, or
suffered, resulting, or arising, from the use of this Pack.
Contractor type
Supplier category
Please complete the following questionnaire for:
Company/Close Corporation/Trusts - EVALUATION PACK A on .
Individuals - EVALUATION PACK B on .
Applicable to the 2022/2023 Tax Years
Evaluation pack a
(To determine whether a Company, Close Corporation (CC) or Trust is a Personal
Service Provider)
Fields marked with an Asterisk (*) must be completed
Contractor’s details for a company or close corporation or
Trust
Contractor’s Name* Vendor No.
Duly Authorised Representative Name Representative Surname
Capacity Representative ID No.*
Representative Passport No. (if no RSA ID) Country of Passport Issue
VAT Registration No. Income Tax Registration No.*
CO/CC/Trust Registration No.* E-Mail Address
Telephone Number* Fax Number
Contractor’s Physical Business Address*
Unit No
Complex Name
Street Number
Street Name
Suburb
City/Town
Postal Code
Contractor’s Postal Business Address*
Same as above (Mark with an X)
Address TYPE (Delete where not applicable) P O Box/Private Bag/Street Address
P O Box/Private Bag/Street NUMBER
Street Name
Suburb
Town
Postal Code
Contractor’s Bank Details*
Account Number Bank Name
Branch Name Branch Number
Name of Account Holder Account Type (Delete where not applicable)
Current/ Savings/ Transmission/Credit Card/Bond
Account
Account Holder Relationship*
i.e. own, joint or 3rd party Own/Joint/3rd Party
Applicable to the 2022/2023 Tax Years
Please answer the following questions by marking the appropriate column with an
"X".
The term “You” will refer to the Company/CC/Trust in this Questionnaire.
Question 1(i)
Are you a Resident of the Republic of South Africa in terms of the Income Tax Act?
(Refer to Appendix 10 for the definition of a resident).
If the answer is Yes, go to Question 2(i).
If the answer is No:
Eskom to refer it to Eskom Group Tax Department in Megawatt Park.
Question 2(i)
Do you employ 3 (three) or more persons (excluding shareholders or members or
beneficiaries of the Company/CC/Trust)?
If the answer is Yes, go to Question 2(ii).
If the answer is No, go to Question 3(i).
Question 2(ii)
Are these employees employed:
If the answer is Yes, go to Question 2(iii).
If the answer is No, go to Question 3(i).
Question 2(iii)
Are the above 3 employees connected to the shareholders or the members or the
beneficiaries of the Company/CC/Trust?
If the answer is Yes, go to Question 3(i).
If the answer is No:
from your payments.
from your payments.
Corporation/Trust” at the end of the Evaluation Pack.
Applicable to the 2022/2023 Tax Years
Question 3(i)
Will/are any person who is a Connected person in relation to the Company/CC/Trust
render services personally to Eskom on behalf of the Company/CC/Trust? (Refer to
Appendix 10 for the definition of a Connected person).
If the answer is Yes, go to Question 4(i).
If the answer is No:
from your payments.
from your payments.
Corporation/Trust” at the end of the evaluation Pack.
Question 4(i)
During the current year of assessment:
received either directly or indirectly, from:
the definition of an Associated institution)
If the answer is Yes:
Corporation/Trust” at the end of the evaluation Pack.
If the answer is No:
from your payments.
Question 5(i)
Must your duties be performed /are your duties performed mainly (more than 50%) at
the premises of Eskom,
And
Will you be subject /are you subject to Eskom’s control or supervision as to the
manner in which your duties are to be performed?
If the answer is Yes to BOTH questions:
Corporation/Trust” at the end of the evaluation Pack.
If the answer is No:
from your payments.
Applicable to the 2022/2023 Tax Years
Question 6(i)
Do/will the payments by Eskom for services payable with reference to output or
certain agreed results, e.g. payment (be it a fixed fee or an hourly rate) be only due if
and when a specific deliverable has been completed?
Question 6(ii)
Does/Will Eskom have the contractual right to control the tools or equipment, staff,
raw materials, routines, patents or technology used in the provision of the services?
Question 6(iii)
Are you/will you prohibited from rendering services to any other employers/clients
during the period of service to Eskom?
Question 6(iv)
Do/will you have the right to sub-contract work?
Question 6(v)
Are you personally or will you personally be at risk for the quality of the work done or
to be done (risk for poor quality; time over-runs, project not producing income)?
Question 6(vi)
Are/will you or the person rendering the service be obliged to be present and perform
the work at Eskom regardless of whether work is available or not?
Question 6(vii)
Is Eskom’s business or will Eskom’s business be critical to your financial/economic
survival?
Question 6(viii)
Does/will your position form part of Eskom’s organisational structure?
Question 6(ix)
Does/will Eskom provide you with any of the following:
Question 6(x)
Does/will Eskom provide you with an office?
Question 6(xi)
Does/will Eskom provide you with any equipment, tools, stationery and material?
Please go to the next section to establish your tax status.
Applicable to the 2022/2023 Tax Years
To establish your tax status, you need to summarise the “Yes” and “No” as
answered on Question 6(i) to 6(xi) in the column below:
Question Yes No
6(i) Independent PSP
6(ii) PSP Independent
6(iii) PSP Independent
6(iv) Independent PSP
6(v) Independent PSP
6(vi) PSP Independent
6(vii) PSP Independent
6(viii) PSP Independent
6(ix) PSP Independent
6(x) PSP Independent
6(xi) PSP Independent
Decision
Independent
Psp
If you have answered “PSP” to any of the following questions 6 (i), 6(iii), 6(v), 6(vi),
6(ix);
or
If you have answered more than 50% “PSP” to questions 6(ii), 6(iv), 6(vii), 6(viii),
6(x), 6(xi):
and will be coded as 3601 on your IRP5 certificate.
Corporation/Trust” at the end of the evaluation Pack.
Alternatively:
If you have already signed Appendix 7 on Questions 4 or 5:
disclosed on the IRP5 for payments received.
If you have not signed Appendix 7 on Questions 4 or 5:
from your payments.
Corporation/Trust” at the end of the evaluation Pack.
Applicable to the 2022/2023 Tax Years
Summary for ID No. Vendor No:
Company/Close Corporation/Trust Summary
Please sign
he
following
Questions Answer Appendix
(Appendices
)
1(i) Are you a Resident of the Republic of South Africa in terms of the Income
Tax Act?
2(i) Do you employ 3 (three) or more persons (excluding shareholders or
members or beneficiaries of the Company/CC/Trust and connected
persons in relation to the shareholder or member or beneficiaries)?
2(i ) Are these employees employed on a full time basis and are they engaged
in the business of the Company/CC/Trust?
2(iii) Are the above 3 employees connected to the shareholders or the members
or beneficiaries of the Company/CC/Trust?
3(i) Will/are any person who is a Connected person in relation to the
Company/CC/Trust render services personally to Eskom on behalf of the
Compa y/CC Trust?
4(i) During the current year of assessment will more than 80% of your income
or is it likely that more than 80% of your income will consist of amounts
received either directly or indirectly from any one client, or an Associated
institution in relation to that client?
5(i) Must your duties be performed / are your duties performed mainly (more
than 50%) at the premises of Eskom AND will you be /are you subject to
Eskom’s control or supervision as to the manner in which your duties are
performed or to the hours of work?
6( ) Do/will the payments by Eskom for services payable with reference to
output or certain agreed results, e.g. payment (be a fixed fee or an hourly
rate) be only due if and when a specific deliverable has been completed?
6(ii) Does/Will Eskom have the contractual right to control the tools or
equipment, staff, raw materials, routines, patents or technology used in the
provision of the services?
6(iii) Are you/will you prohibited from rendering services to any other
employers/clients during the period of service to Eskom?
6(iv) Do/will you have the right to sub-contract work?
6(v) Are you personally or will you personally be at risk for the quality of the
work done or to be done (risk for poor quality; time over-runs, project not
producing income)?
6(vi) Are/will you or the person rendering the service be obliged to be present
and perform the work at Eskom regardless of whether work is available or
not?
6(vii) Is Eskom’s business or will Eskom’s business be critical to your
financial/economic survival?
6(viii) Does/will your position form part of Eskom’s organisational structure?
6(ix) Does/will Eskom provide you with any of the following:
Pension fund / Provident fund / Retirement Annuity Fund; medical aid,
leave of any nature, salary increases, bonuses or any allowances.
6(x) Does/will Eskom provide you with an office?
6(xi) Does/will Eskom provide you with any equipment, tools, stationery and
material?
Tax Status
Particulars of person acting as representative of the company/close
Corporation/trust
I, the undersigned, confirm that the information provided above is accurate, and that the Company/CC/Trust will,
while contracted to Eskom, inform Eskom of any changes that take place pertaining to the information provided
above. Eskom shall be entitled to withhold from any payments to be made to the Company/CC/Trust, any taxes,
interest and penalties that it may be required to pay to SARS as a result of the above information being inaccurate.
Representative's Full Names Capacity Contact No.
Signature Date
Applicable to the 2022/2023 Tax Years
Evaluation pack b
(To determine whether an Individual is a Dependent Contractor)
Fields marked with an Asterisk (*) must be completed
Contractor’s details for an individual*
Trading Name* Vendor No.
First Names* Initials*
Surname* ID Number*
Passport No. (if no RSA ID) Country of Passport Issue
VAT Registration No. Income Tax Registration No.*
Date of Birth* E-Mail Address
Telephone Number* Fax Number
Contractor’s Physical Business Address*
Unit No
Complex Name
Street Number
Street Name
Suburb
City/Town
Postal Code
Contractor’s Postal Business Address*
Same as above (Mark with an X)
Address TYPE (Delete where not applicable) P O Box/Private Bag/Street Address
P O Box/Private Bag/Street NUMBER
Street Name
Suburb
Town
Postal Code
Contractor’s Bank Details*
Account Number Bank Name
Branch Name Branch Number
Name of Account Holder Account Type (Delete where not applicable)
Current/ Savings/ Transmission/Credit Card/Bond
Account
Account Holder Relationship*
i.e. own, joint or 3rd party Own/Joint/3rd Party
Applicable to the 2022/2023 Tax Years
Please answer the following questions by marking the appropriate column with an
"X".
Question 1(i)
Do/will you provide Eskom with a service or people?
If the answer is “Service”:
PAYE will be withheld from your payments.
If the answer is “People”, go to Question 2(i).
Question 2(i)
Do you provide Eskom with People and will these people be paid by you?
If the answer is Yes, go to Question 2(ii).
If the answer is No, go to Question 3(i).
Question 2(ii)
Are you in possession of an IRP30 exemption certificate which is valid for the period
under review?
If the answer is Yes:
from your payments.
provided, PAYE will be withheld from your payments until such time
the IRP30 certificate is provided.
Pack.
If the answer is No:
IRP30 certificate is provided.
Pack.
Question 3(i)
Are you a Resident of the Republic of South Africa in terms of the Income Tax Act?
(Refer to Appendix 10 for the definition of a Resident).
If the answer is Yes, go to Question 4(i).
If the answer is No:
Eskom to refer it to Eskom Group Tax Department in Megawatt.
Applicable to the 2022/2023 Tax Years
Question 4(i)
Do you employ:
If the answer is Yes, go to Question 4(ii).
If the answer is No, go to Question 5(i).
Question 4(ii)
Are these employees employed:
If the answer is Yes, go to Question 4(iii).
If the answer is No, go to Question 5(i).
Question 4(iii)
Are any of these employees Connected persons in respect of the Individual, e.g.
spouse, parent, adoptive parent, child, grandparent, cousin, etc.? (Refer to
Appendix 10 for the definition of Connected person).
If the answer is Yes, go to Question 5(i).
If the answer is No:
from your payments.
withheld from your payments.
Pack.
Question 5(i)
Must your duties be performed mainly (i.e. more than 50%) at premises of Eskom?
If the answer is Yes, go to Question 5(ii).
If the answer is No, go to Question 5(ii).
Question 5(ii)
Will you be /are you subject to Eskom’s control or supervision as to the manner in
which your duties are to be performed or as to the hours of work?
If the answers in both Questions 5(1) and 5(ii) are Yes:
If the answer is No:
from your payments.
Applicable to the 2022/2023 Tax Years
Question 6(i)
Do/will the payments by Eskom for services payable with reference to output or
certain agreed results, e.g. payment (be it a fixed fee or an hourly rate) be only due
if and when a specific deliverable has been completed?
Question 6(ii)
Does/Will Eskom have the contractual right to control the tools or equipment, staff,
raw materials, routines, patents or technology used in the provision of the services?
Question 6(iii)
Are you/will you prohibited from rendering services to any other employers/clients
during the period of service to Eskom?
Question 6(iv)
Do/will you have the right to sub-contract work?
Question 6(v)
Are you personally / will you personally be at risk for the quality of the work done or
to be done (risk for poor quality; time over-runs, project not producing income)?
Question 6(vi)
Are/will you or the person rendering the service be obliged to be present and
perform the work at Eskom regardless of whether work is available or not?
Question 6(vii)
Is Eskom’s business or will Eskom’s business be critical to your financial/economic
survival?
Question 6(viii)
Does/will your position form part of Eskom’s organisational structure?
Question 6(ix)
Does/will Eskom provide you with any of the following:
Question 6(x)
Does/will Eskom provide you with an office?
Question 6(xi)
Does/will Eskom provide you with any equipment, tools, stationery and material?
Please go to the next section to establish your tax status.
Applicable to the 2022/2023 Tax Years
To establish your tax status, you need to summarise the “Yes” and “No” as
answered on Question 6(i) to 6(xi) in the column below:
Question Yes No
6(i) Independent Employee
6(ii) Employee Independent
6(iii) Employee Independent
6(iv) Independent Employee
6(v) Independent Employee
6(vi) Employee Independent
6(vii) Employee Independent
6(viii) Employee Independent
6(ix) Employee Independent
6(x) Employee Independent
6(xi) Employee Independent
Decision
Independent
Psp
If you have answered “Employee” to any of the following questions 6 (i), 6(iii), 6(v),
6(vi), 6(ix);
or
If you have answered more than 50% “Employee” to questions 6(ii), 6(iv), 6(vii),
6(viii), 6(x), 6(xi):
Alternatively:
If you have already signed Appendix 7 on Questions 5:
disclosed on the IRP5 for payments received.
If you have not signed Appendix 7 on Questions 5:
withheld from your payments.
Corporation/Trust” at the end of the evaluation Pack.
Applicable to the 2022/2023 Tax Years
Summary for ID No. Vendor No:
Company/Close Corporation/Trust Summary
Please si n
the following
Pricing Schedule
Source: Attachment 1- Tax Evaluation questionnaire.pdfthe non-deduction is 07.
until such time that a valid IRP30 certificate is provided to Eskom.
Labour Broker Individual N/A X IRP5 / IT3(a) 3617 A
tax rates
Dependent Contractor Individual X X IRP5 / IT3(a) 3601 or “A” for
tax rates 3616 Individual
“E” for
Compliance Requirements
Source: Attachment 1- Tax Evaluation questionnaire.pdf (unknown)No specific requirements found
Health & Safety
Source: Attachment 1- Tax Evaluation questionnaire.pdfCompany/close corporation/trust ..................................................................... 11
Evaluation pack b....................................................................................................................... 12
Contractor’s details for an individual* ..................................................................... 12
Question 1(i) .............................................................................................................................. 13
Question 2(i) .............................................................................................................................. 13
Question 2(ii) ............................................................................................................................. 13
Question 3(i) .............................................................................................................................. 13
Question 4(i) .............................................................................................................................. 14
Question 4(ii) ............................................................................................................................. 14
Question 4(iii) ............................................................................................................................ 14
Question 5(i) .............................................................................................................................. 14
Question 5(ii) ............................................................................................................................. 14
Question 6(i) .............................................................................................................................. 15
Question 6(ii) ............................................................................................................................. 15
Question 6(iii) ............................................................................................................................ 15
Question 6(iv) ............................................................................................................................ 15
Question 6(v) ............................................................................................................................. 15
Question 6(vi) ............................................................................................................................ 15
Question 6(vii) ........................................................................................................................... 15
Question 6(viii)........................................................................................................................... 15
Question 6(ix) ............................................................................................................................ 15
Question 6(x) ............................................................................................................................. 15
Question 6(xi) ............................................................................................................................ 15
Particulars of individual .............................................................................................. 17
Applicable to the 2022/2023 Tax Years
Appendix 1 ....................................................................................................................................... 18
Three or more full - time employees who are not connected persons . 18
Appendix 2 ....................................................................................................................................... 19
ESKOM ...................................................................................................................................... 19
Appendix 3 ....................................................................................................................................... 20
And/or shall not be controlled or supervised by ESKOM ............................. 20
Appendix 4 ....................................................................................................................................... 21
Affidavit confirming that not more than eighty percent (80 %) of income
Is or is likely to be received from any one client ............................................. 21
Appendix 5 ....................................................................................................................................... 22
Opposed to people ........................................................................................................... 22
Appendix 6 ....................................................................................................................................... 23
Declaration by ........................................................................................................................ 23
That the contractor is a labour broker ................................................................... 23
Appendix 7 ....................................................................................................................................... 24
Declaration by ........................................................................................................................ 24
Provider ................................................................................................................................ 24
Appendix 8 ....................................................................................................................................... 25
Declaration by ........................................................................................................................ 25
That the contractor is an independent supplier or contractor .................. 25
Appendix 9 ....................................................................................................................................... 26
Declaration by ........................................................................................................................ 26
That the contractor is a non-resident of the republic of south africa .... 26
Appendix 10 ..................................................................................................................................... 27
Definitions as per the income tax act, NO. , as amended. ................... 27
“Connected Person” .................................................................................................................. 27
"Associated Institution", in relation to any single employer, ...................................................... 28
"Labour Broker" ......................................................................................................................... 28
"Personal Service Provider” ...................................................................................................... 28
"Remuneration" ......................................................................................................................... 28
“Resident” .................................................................................................................................. 29
Applicable to the 2022/2023 Tax Years
Introduction
The Fourth Schedule to the Income Tax Act (“the Act”) requires that Employees' Tax must be
withheld from "remuneration" paid by an "Employer" to an "Employee". This tool is intended to establish
whether an Individual, Close Corporation, Company or Trust should be classified as an Independent
Definitions as per the Income Tax Act are included in Appendix 10.
Any reference to “Eskom” refers to Eskom Holdings SOC Ltd and its subsidiaries:
Eskom Rotek Industries SOC Ltd
Eskom Enterprises SOC (Pty) Ltd
Escap SOC (Pty) Ltd
Eskom Finance Company SOC (Pty) Ltd
Eskom Foundation NPC
National Transmission Company SA
The Pack is based on legislation and case law applicable to the 2022/2023 tax year. We therefore
recommend that, if it is used outside of this period, you should first consult with your representative in
Eskom to refer it to Eskom’s Corporate Tax Department in Megawatt Park.
When you return the completed Pack; i.e. the signed summary sheet and signed affidavits to Eskom,
please copy Group Tax on Email address: [email protected]
ease of reading.
this Pack;
Question 1(i)
Are you a Resident of the Republic of South Africa in terms of the Income Tax Act?
(Refer to Appendix 10 for the definition of a resident).
If the answer is Yes, go to Question 2(i).
Sign Appendix 9. Submit The Pack to your contractor representative in
Sign Appendix 1. If the Affidavit is not signed, PAYE will be withheld
from your payments.
from your payments.
Corporation/Trust” at the end of the Evaluation Pack.
Applicable to the 2022/2023 Tax Years
render services personally to Eskom on behalf of the Company/CC/Trust? (Refer to
Appendix 10 for the definition of a Connected person).
If the answer is Yes, go to Question 4(i).
from your payments.
from your payments.
Corporation/Trust” at the end of the evaluation Pack.
Question 4(i)
Corporation/Trust” at the end of the evaluation Pack.
from your payments.
Go to Question 5(i).
Sign Appendix 7. PAYE will be withheld from your payments.
Go to Question 6(i) to determine the correct disclosure code on the IRP5.
Sign “Particulars of person acting as representative of the Company/Close
Corporation/Trust” at the end of the evaluation Pack.
from your payments.
Applicable to the 2022/2023 Tax Years
Psp
If you have answered “PSP” to any of the following questions 6 (i), 6(iii), 6(v), 6(vi),
6(ix);
or
If you have answered more than 50% “PSP” to questions 6(ii), 6(iv), 6(vii), 6(viii),
6(x), 6(xi):
and will be coded as 3601 on your IRP5 certificate.
Corporation/Trust” at the end of the evaluation Pack.
If you have already signed Appendix 7 on Questions 4 or 5:
disclosed on the IRP5 for payments received.
If you have not signed Appendix 7 on Questions 4 or 5:
from your payments.
Corporation/Trust” at the end of the evaluation Pack.
Applicable to the 2022/2023 Tax Years
(Appendices
)
1(i) Are you a Resident of the Republic of South Africa in terms of the Income
Tax Act?
2(i) Do you employ 3 (three) or more persons (excluding shareholders or
members or beneficiaries of the Company/CC/Trust and connected
persons in relation to the shareholder or member or beneficiaries)?
2(i ) Are these employees employed on a full time basis and are they engaged
in the business of the Company/CC/Trust?
2(iii) Are the above 3 employees connected to the shareholders or the members
or beneficiaries of the Company/CC/Trust?
3(i) Will/are any person who is a Connected person in relation to the
Question 1(i)
Do/will you provide Eskom with a service or people?
If the answer is “Service”:
Complete and sign Appendix 5 Affidavit. If the Affidavit is not signed,
Sign Appendix 6. If the Agreement is not signed, PAYE will be withheld
from your payments.
provided, PAYE will be withheld from your payments until such time
the IRP30 certificate is provided.
No further questions must be answered.
Sign the “Particulars of Individual” Section at the end of the Evaluation
Sign Appendix 6. PAYE will be withheld from your payments.
PAYE will be withheld from your payments until such time the valid
IRP30 certificate is provided.
Question 3(i)
Are you a Resident of the Republic of South Africa in terms of the Income Tax Act?
(Refer to Appendix 10 for the definition of a Resident).
If the answer is Yes, go to Question 4(i).
spouse, parent, adoptive parent, child, grandparent, cousin, etc.? (Refer to
Appendix 10 for the definition of Connected person).
If the answer is Yes, go to Question 5(i).
from your payments.
withheld from your payments.
Question 5(i)
Must your duties be performed mainly (i.e. more than 50%) at premises of Eskom?
If the answer is Yes, go to Question 5(ii).
If the answer is No, go to Question 5(ii).
Question 5(ii)
Will you be /are you subject to Eskom’s control or supervision as to the manner in
which your duties are to be performed or as to the hours of work?
If the answers in both Questions 5(1) and 5(ii) are Yes:
Sign Appendix 7. PAYE will be withheld from your payments.
Go to Question 6(i) to determine the correct disclosure code on the IRP5.
Sign the “Particulars of Individual” at the end of the Evaluation Pack.
Sign Appendix 3. If the Affidavit is not signed, PAYE will be withheld
from your payments.
Applicable to the 2022/2023 Tax Years
Psp
If you have answered “Employee” to any of the following questions 6 (i), 6(iii), 6(v),
6(vi), 6(ix);
or
If you have answered more than 50% “Employee” to questions 6(ii), 6(iv), 6(vii),
6(viii), 6(x), 6(xi):
If you have already signed Appendix 7 on Questions 5:
disclosed on the IRP5 for payments received.
If you have not signed Appendix 7 on Questions 5:
withheld from your payments.
Corporation/Trust” at the end of the evaluation Pack.
Applicable to the 2022/2023 Tax Years
Applicable to the 2022/2023 Tax Years
Appendix 1
Thus signed and sworn to before me at ______________on this day
Of __________20.
Thus signed and sworn to before me at ______________on this day
Of __________20.
Applicable to the 2022/2023 Tax Years
Appendix 3
Thus signed and sworn to before me at ______________on this day
Of __________20.
Applicable to the 2022/2023 Tax Years
Appendix 4
Affidavit confirming that not more than eighty percent (80 %) of
Thus signed and sworn to before me at ______________on this day
Of __________20.
Applicable to the 2022/2023 Tax Years
Appendix 5
Thus signed and sworn to before me at ______________on this day
Of __________20.
Applicable to the 2022/2023 Tax Years
Appendix 6
Applicable to the 2022/2023 Tax Years
Appendix 7
Applicable to the 2022/2023 Tax Years
Appendix 8
Applicable to the 2022/2023 Tax Years
Appendix 9
Applicable to the 2022/2023 Tax Years
Appendix 10
rendering any such service, other than any employee who is a shareholder or member of the
company or trust or is a connected person in relation to such person;
"Remuneration"
means -
any amount of income which is paid or is payable to any person by way of any salary, leave pay, wage,
overtime pay, bonus, gratuity, commission, fee, emolument pension, superannuation allowance, retiring
allowance or stipend, whether in cash or otherwise and whether or not in respect of services rendered,
including-
a) any amount referred to in paragraph (a), (c), (cA),(d), (e), (eA) or (f) of the definition of "gross
income" in section one of this Act;
any amount required to be included in such person's gross income under paragraph (i) of that definition;
Applicable to the 2022/2023 Tax Years
bA) ...
but not including-
ii) any amount paid or payable in respect of services rendered or to be rendered by any person
(other than a person who is not a resident or an employee contemplated in paragraph (b), (c),
(d) (e) or (f)of the definition of "employee") in the course of any trade carried on by him
independently of the person by whom such amount is paid or payable and of the person to
whom such services have been or are to be rendered: Provided that for the purposes of this
paragraph a person shall not be deemed to carry on a trade independently as aforesaid if the
services are required to be performed mainly at the premises of the person by whom such
amount is paid or payable or of the person to whom such services were or are to be rendered
and the person who rendered or will render the services is subject to the control or supervision
of any other person as to the manner in which his or her duties are performed or to be
performed or as to his hours of work. Provided further that a person will be deemed to be
carrying on a trade independently as aforesaid if he throughout the year of assessment employs
three or more employees who are on a full time basis engaged in the business of such person
of rendering any such service, other than any employee who is a connected person in relation to
such person;
iii) ...
“Resident”
means any-
(a) natural person who is-
(i) ordinarily resident in the Republic; or
(ii) not at any time during the relevant year of assessment ordinarily resident in the Republic, if that
person was physically present in the Republic-
a) for a period or periods exceeding 91 days in aggregate during the relevant year of
assessment, as well as for a period or periods exceeding 91 days in aggregate during each
of the five years of assessment preceding such year of assessment; and
b) for a period or periods exceeding 915 days in aggregate during those five preceding years
of assessment,
in which case that person will be a resident with effect from the first day of that relevant year of
assessment: Provided that-
(A) a day shall include a part of a day, but shall not include any day that a person is in transit
through the Republic between two places outside the Republic and that person does not
formally enter the Republic through a “port of entry” as contemplated in section 9 (1) of the
Immigration Act, 2002 (Act No. ), or at any other place as may be permitted by
the Director General of the Department of Home Affairs or the Minister of Home Affairs in
terms of that Act; and
(B) where a person who is a resident in terms of this subparagraph is physically outside the
Republic for a continuous period of at least 330 full days immediately after the day on
which such person ceases to be physically present in the Republic, such person shall be
deemed not to have been a resident from the day on which such person so ceased to be
physically present in the Republic; or
(b) person (other than a natural person) which is incorporated, established or formed in the Republic or
which has its place of effective management in the Republic,
but does not include any person who is deemed to be exclusively a resident of another country for
purposes of the application of any agreement entered into between the governments of the Republic
and that other country for the avoidance of double taxation;
Applicable to the 2022/2023 Tax Years
Section
Source: Attachment 1- Tax Evaluation questionnaire.pdfEvaluation pack a......................................................................................................................... 6
Are you personally or will you personally be at risk for the quality of the work done or
to be done (risk for poor quality; time over-runs, project not producing income)?
Corporation/Trust” at the end of the evaluation Pack.
Important Dates
Source: Attachment 12 Supplier Declaration of Interest Template (1).pdf (unknown){"closingDate":"01 February 2015"}
Contact Information
Source: Attachment 12 Supplier Declaration of Interest Template (1).pdf (unknown){"name":null,"email":null,"phone":null,"department":"s, Eskom Divisions, Eskom","address":"e/s of Contact person/s and contact details"}
Submission Guidelines
Source: Attachment 12 Supplier Declaration of Interest Template (1).pdf (unknown)Returnable documents: The Supplier Declaration of Interest (form 240-59385360 Rev 3) must be completed, signed and submitted with the tender. The declaration must be certified under oath by the signatory. No other submission instructions are provided in this attachment.
Evaluation Criteria
Source: Attachment 12 Supplier Declaration of Interest Template (1).pdf (unknown)Bidders must complete and submit the Supplier Declaration of Interest (form 240-59385360 Rev 3). The declaration requires certification under oath that the information provided is true and correct. Bidders must disclose any Eskom employees or directors holding an interest in the supplier, any close family or associate relationships with Eskom employees or directors participating in the procurement, any business courtesies given or received in the last 12 months, and, for consultants, any other services currently rendered to Eskom business units, divisions, subsidiaries, suppliers of primary energy, strategic commodity suppliers, and key industrial customers.
Technical Specifications
Source: Attachment 12 Supplier Declaration of Interest Template (1).pdf (unknown)supplying entity AND their company registration
number] ..........................................................................., certify under oath that, to the best of my
knowledge, the information furnished herein is true and correct. I accept that Eskom reserves its right to act
against the supplier named above or me personally in terms hereof, should this declaration prove to be false.
Eskom employees and directors that engage in private work
Compliance Requirements
Source: Attachment 12 Supplier Declaration of Interest Template (1).pdf (unknown)The Supplier Declaration of Interest (form 240-59385360 Rev 3) must be completed and submitted as a returnable. The declaration must be certified under oath. Bidders must disclose any conflicts of interest, including Eskom employees or directors holding an interest, family or associate relationships, business courtesies in the last 12 months, and other services rendered by consultants. Eskom reserves the right to act against the supplier or signatory if the declaration proves false.
Health & Safety
Source: Attachment 12 Supplier Declaration of Interest Template (1).pdfEffective Date 01 February 2015
Review Date November 2026
I, the undersigned [insert full name of signatory]...................................................., in my capacity as
[insert capacity, i.e., member, director, partner, etc.] ...................................................... of the
supplier [insert registered full legal name of the supplying entity AND their company registration
number] ..........................................................................., certify under oath that, to the best of my
knowledge, the information furnished herein is true and correct. I accept that Eskom reserves its right to act
against the supplier named above or me personally in terms hereof, should this declaration prove to be false.
Evaluation Criteria
Source: Attachment 10 Peaking OHS Baseline risk assessment - Rev.6 2025.04.30.xlsx (unknown)No eligibility criteria specified
Technical Specifications
Source: Attachment 10 Peaking OHS Baseline risk assessment - Rev.6 2025.04.30.xlsx (unknown)Cell A3: Occupational Health and Safety Baseline risk assessment template
Important Dates
Source: Attachment 11 Non-Disclosure Agreement (NDA) Generic Template - 06 August 2024.pdf (unknown){"closingDate":"06 August 2024"}
Evaluation Criteria
Source: Attachment 11 Non-Disclosure Agreement (NDA) Generic Template - 06 August 2024.pdf (unknown)Bidders must submit a signed Non-Disclosure Agreement (NDA) for each employee involved in the tender. The NDA must be signed by an Eskom employee no lower than an E-Band Manager. No other eligibility criteria are stated in the provided document.
Technical Specifications
Source: Attachment 11 Non-Disclosure Agreement (NDA) Generic Template - 06 August 2024.pdf (unknown)Provision Of Building and Infrastructure Maintenance
Contractual Terms
Source: Attachment 11 Non-Disclosure Agreement (NDA) Generic Template - 06 August 2024.pdf3.1 The employee agrees and undertakes that:
3.1.1 during the period of his or her involvement in Group Commercial
project/s, or
3.1.2 if he or she is no longer involved in Group Commercial project/s but
is still in the employ of Eskom, or
3.1.3 if he or she has left the employ of Eskom, or
3.1.4 he or she shall not disclose to any other person, including third
parties, or make use for his or her benefit, or that of any other person,
whether directly or indirectly, any confidential information of Eskom
or the companies regarding the project/s without the prior written
consent of Eskom. Eskom shall provide the employee with a list of
employees who have signed confidentiality Agreements regarding the
project/s and the employee shall only grant access to the confidential
information to these employees.
3.2 The employee agrees and undertakes to protect Eskom’s confidential information
and to handle and store the confidential information in such a way as to prevent
any unauthorised disclosure.
3.3 The obligation to maintain the confidentiality of the information will not apply to the
information excluded by clause 2.2 above.
6.3 No contract varying, adding to, deleting from or cancelling this Agreement, and no
waiver of any right under this Agreement, will be effective unless reduced to writing
and signed by or on behalf of the parties.
6.4 The granting of any indulgence by a party under this Agreement will not constitute
a waiver of any rights by the grantor or prevent or adversely affect the exercise by
the grantor of any existing or future right of the grantor.
6.5 In the event that the employee should breach the provisions of this Agreement and
fail to remedy such breach within seven (7) calendar days from date of a written
notice to do so, then Eskom shall be entitled to invoke all remedies available to it
in law.
6.6 This Agreement replaces any non-disclosure and confidentiality Agreement
previously signed by the employee in respect of the project/s.
6.7 In the event of any one or more of the provisions of this Agreement being held for
any reason to be invalid, illegal or unenforceable in any respect, such invalidity,
illegality or unenforceability shall not affect any other provision of this Agreement,
and this Agreement shall be construed as if such invalid, illegal or unenforceable
provisions were not a part of this Agreement, and this Agreement shall be carried
out as nearly as possible in accordance with its original terms and intent.
Description
Source: Attachment 6 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsxProvision of building and infrastructure maintenance services at Gariep Hydro Station on an as-and-when-required basis for a period of five years.
Submission Guidelines
Source: Attachment 6 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsx (unknown)Submit the completed and signed tender documents, including all returnable schedules, in a sealed envelope marked with the tender number and description. Ensure all required forms are fully completed, signed, and dated. Late, faxed, or emailed submissions will not be accepted. The tender must be delivered to the specified address before the closing date and time.
Evaluation Criteria
Source: Attachment 6 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsx (unknown)Evaluation will be based on functionality (quality management) and price. The quality management evaluation will assess the submitted documents against the criteria in Sections A to E, with weightings of 0.25 for Section A, 0.25 for Section B, 0.2 for Section C, 0.2 for Section D, and 0.1 for Section E. Only bidders achieving a minimum threshold for functionality will proceed to price evaluation. The 80/20 preference point system may apply.
Technical Specifications
Source: Attachment 6 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsx (unknown)Cell D3: Type 1 in the block to select the applicable type of Category
Description
Source: Attachment 9 Safety.pdfThis attachment is a safety procedure, not a scope description. It applies to all Eskom sites and covers employees, contractors, agents, consultants, and temporary workers. The procedure aims to promote a safe working environment and zero harm.
Important Dates
Source: Attachment 9 Safety.pdf (unknown){"closingDate":"21 October 2022"}
Evaluation Criteria
Source: Attachment 9 Safety.pdf (unknown)No specific eligibility criteria (e.g., CSD registration, tax clearance, B-BBEE level, CIDB grading) are stated in the provided document.
Technical Specifications
Source: Attachment 9 Safety.pdf (unknown)Eskom is committed to health and safety excellence, which forms an integral part of its operations.
Eskom and its subsidiaries will conduct business with respect and care for people to ensure that no
operating condition or urgency of service endangers the life of anyone or causes injury or damage
to the environment.
Although the Bill of Rights entrenched in the South African Constitution makes no specific reference
to health and safety in the workplace, the rights relevant to health and safety in the workplace include
the right to life, the right to a safe and healthy environment, and labour rights.
Employees have a duty to take reasonable care of their health and safety and the health and safety
of other persons, to cooperate with the employer, to carry out lawful orders, to report unsafe
situations and incidents, and engage in a manner following the behavioural safety observations
elements (SMAT), which will ensure that unsafe behaviour does not continue or repeat itself.
The aim of this Procedure is to ensure that an environment is created that promotes Zero Harm by
empowering employees and contractors to take responsibility for their own safety and that of others.
2.1 Scope
This Procedure shall apply to all Eskom sites with the intention of promoting a safe working
environment for all Eskom employees (permanent, non-permanent, employees placed by a
Temporary Employee Services provider (TES), learners, and bursary students), agents, consultants,
and contractors.
2.1.1 Purpose
This Procedure clarifies Eskom’s intention to ensure that no one is exposed to unsafe conditions or
is in a position, with respect to any behaviour, that can result in serious risk at the workplace.
2.1.2 Applicability
This Procedure shall apply throughout Eskom Holdings SOC Ltd divisions and subsidiaries.
2.1.3 Effective date
1 July 2015.
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
[1] Occupational Health and Safety Act .
[2] 32-727: Eskom, Safety, Health, Environment and Quality Policy.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Employees’ Right of Refusal to Work in an Unique Identifier: 240-43848327
Unsafe Situation Procedure Revision: 1
Page:
[3] 32-407 Behavioural Observation Procedure.
2.2.2 Informative
[4] DPC 34-846: Operating Regulations for High-voltage Systems.
[5] GGR 0992: Plant Safety Regulations (Low-voltage Regulations).
[6] GGR 0568: Pulverised Fuel Firing Regulations.
[7] ISO 9001 Quality Management Systems.
[8] NEMA 107: National Environmental Management Act.
[9] MHSA: Mine Health and Safety Act.
2.3 Definitions
2.3.1 Absolute (or strict) requirement: A requirement designed for a safe working environment,
which means that the particular duty must be complied with, irrespective of cost or likelihood
of injury.
2.3.2 Unsafe situation: Any situation involving an unsafe act from an individual or an unsafe
condition.
2.3.3 Safety rules: Rules designed to prevent accidents and injuries when followed.
2.3.4 Contractor: Any employer formally contracted (directly or indirectly) by Eskom and who
performs work or supplies a service, product, equipment, or material for the purposes of
advancing Eskom’s business and other interests. This includes personal
contractors/consultants and third-party contractors (vendors, suppliers, agents, joint
ventures, principal contractors and subcontractors).
2.3.5 Suppliers: Any person or organisation that supplies any product, equipment, or material;
and this includes courier services.
2.3.6 Agents: Any person who acts as a representative for Eskom (as the client), as defined in
the OHS Act. (With specific reference to the Construction Regulations).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Employees’ Right of Refusal to Work in an Unique Identifier: 240-43848327
Unsafe Situation Procedure Revision: 1
Page:
2.3.7 Joint ventures: An entity formed through a decision and agreement to work together
between two or more persons, parties, and/or organisations to undertake an economic
activity together and which entity is managed by means of this agreement. The parties
agree to create a new entity by both contributing equity, and they then share in the
revenues, expenses, and control of the enterprise.
2.3.8 Treat: to apply/administer a process to improve or remedy a risk/hazard/unsafe condition(s)
or situation(s).
2.3.9 Mitigate: to control/prevent a hazard from causing harm and to reduce a risk/hazard/unsafe
condition(s) or situation(s).
2.3.10 Eliminate: to remove/eradicate a risk/hazard/unsafe condition(s) or situation(s).
2.3.11 Workplace: Any premises or place where a person performs work in the course of his
employment.
2.3.12 Behavioural Safety Observation (SMAT): Technique use to assess and address the
actual safe and unsafe behaviours of people in the workplace; as well as workplace
conditions - which are caused by the actions or non-actions of employees, contractors or
their supervisors.
2.4 Abbreviations
Abbreviation Explanation
BU Business Unit
EDC Eskom Documentation Centre
ExCo Executive Committee
H&S Health and safety
OH&S Occupational Health and Safety
OU Operating Unit
TES Temporary Employee Services
SMAT Safety Management Audit Technique
2.5 Roles and Responsibilities
2.5.1 The Risk and Sustainability Division (OHS): The OHS Department shall review the
Procedure every five years or as required by the OHS Steering Committee.
2.5.2 Group and divisional executives: Group and divisional executives are responsible for
ensuring adherence to this procedure within their respective groups/divisions.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Employees’ Right of Refusal to Work in an Unique Identifier: 240-43848327
Unsafe Situation Procedure Revision: 1
Page:
2.5.3 Operating units/ Business units: The management at Business Unit level shall be
responsible for:
importance of compliance with this Procedure; and the consequences of non-compliance.
This includes communicating duty of care and refusal to perform an unsafe task to all new
employees and new contractors;
duty of care and refusal to perform an unsafe task; and
2.6 Process for Monitoring
Compliance with the requirements of this Procedure has to be audited by the Operating/Business
Unit,
Service Function and/or Strategic function at least annually as part of an internal review process. All
records have to be audited by Assurance and Forensics Department or any person appointed by it
to do so, on its behalf, at its discretion and at a frequency determined by it.
The focus areas of such monitoring will include the following:
2.7 Related/Supporting Documents
2.7.1 Refusal to work in an unsafe workplace. (Unique identifier 240-53716047).
3.1 General
The employer has the duty to inform each person of his or her right to refuse unsafe work, which
includes that every employee shall, at work:
a) take reasonable care of his or her own health and safety and that of any other person who may
be affected by his or her acts or omissions;
b) co-operate in order to enable that any duty or requirement, including absolute (or strict)
requirements imposed on the employer in order to achieve a safe workplace, are performed and
complied with;
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Employees’ Right of Refusal to Work in an Unique Identifier: 240-43848327
Unsafe Situation Procedure Revision: 1
Page:
c) carry out any lawful order given to him or her and obey the health and safety rules and procedures
laid down by his or her employer or by anyone authorised to do so by the employer in the interest
of health and safety;
d) if any situation that is unsafe or unhealthy comes to his or her attention, as soon as practicable
take immediate preventative and corrective action and report such situation to his or her
employer or to the health and safety representative for his or her workplace or section thereof,
as the case may be, who shall, in turn, report it to the employer; and
e) exercise the duty so as not to interfere with, damage, misuse or intentionally or recklessly
interfere with anything that is provided in the interest of health or safety.
3.2 Standard Procedure for when an Employee Exercises his or her Right of Refusal to
Work in the case of an Unsafe Work Situation
Where an employee is directed, required, or instructed to perform a task in relation to equipment, a
machine, device, thing, or physical condition and he or she reasonably believes in good faith that
the:
a) equipment, machine, device, or thing; or
b) physical condition of the workplace;
c) is in contravention of any health and safety requirement, may endanger, endangers, causes an
undue hazard, or may cause an undue hazard to his or her health and safety, (collectively
referred to as an unsafe work condition) or those of his or her co-worker or any person, such an
employee has the right to refuse to perform such a task until such time as it has been corrected
and made safe.
d) The employee may refuse to return to perform such a task until the unsafe work condition(s)
has/have been mitigated, treated or eliminated.
e) An employee cannot refuse to work when high-risk work condition(s) and processes form part
of his or her normal contractual duties, where following approved safe work procedures will
ensure a safe working environment. (Example: a live line worker involved in live line work
following safe work procedures).
f) Should any employee at any time reasonably believe, in good faith, that the performance of work
or a task is unsafe, the following procedures shall apply:
Stage 1:
condition or unsafe act. The supervisor shall give the situation immediate attention.
available, the applicable health and safety representative the reasons for believing that the
work to be performed is unsafe. The employee has the right to invite his/her union
representative.
The employee(s) shall remain in a safe place.
The supervisor shall investigate the unsafe situation together with the applicable employee
and the applicable health and safety representative responsible for that particular area.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Employees’ Right of Refusal to Work in an Unique Identifier: 240-43848327
Unsafe Situation Procedure Revision: 1
Page:
outline the corrective actions in order to mitigate/treat/eliminate the unsafe situation.
Alternatively, if it is found that the perceived threat is unfounded, the supervisor shall give a
clearance notice to the employee, co-signed by the applicable employee, indicating that the
identified perceived threat has been thoroughly investigated and that the situation has been
declared to be safe. (See form referenced in Paragraph 2.7.1.)
threat to employees or any other person, only qualified and properly instructed employees or
persons will be permitted to correct such unsafe condition. Every possible effort must be
made to control the hazard while this is being done.
employee shall return to work. If the issue has not been resolved, proceed to the following
stage.
Stage 2:
The manager of that section or, if not readily available, any other person with the necessary
knowledge, skills, and experience who understands the task and associated risks must then
review the risk assessment and mitigation plans and, where necessary, make changes to further
reduce/treat/eliminate the risk. If the issue is resolved and the appropriate corrective action has
been taken, the employee shall return to work.
If the issue has not been resolved, then the work will be considered as unsafe and cannot
continue until the applicable Responsible Manager (BU/OU Manager) have introduced all steps
to ensure the work place is safe as defined in the Occupational Health and Safety Act, Eskom’s
policies, procedures and best practices.
Stage 3:
In a case, wherein, the employee is still unsatisfied or refuses to acknowledge the resolution of the
threat, the matter shall be brought to the OU/BU Manager for resolution. If the matter cannot be
resolved internally, the OU/BU Manager shall immediately notify the Provincial Inspector at the
Department of Employment and Labour.
3.3 Participation by Subject-Matter Specialist
If a supervisor requests that a subject-matter specialist should participate in the resolution of an
issue, the BU Responsible Manager:
a) must ensure the appointment of the appropriate subject-matter specialist to enter the workplace
for the purpose of participating;
b) must give every reasonable assistance necessary to enable participation by the subject-matter
specialist; and
c) shall:
i.ensure that the necessary steps are taken to make the workplace healthy and safe; and
ii. jointly advise the employees of the steps that are being taken
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Employees’ Right of Refusal to Work in an Unique Identifier: 240-43848327
Unsafe Situation Procedure Revision: 1
Page:
3.4 Report
The supervisor, together with the subject-matter specialist (if applicable), must prepare a report as
stipulated in form referenced in Paragraph 2.7.1, which must be tabled and discussed at the next
Statutory Health and Safety Committee meeting. The chairperson of the Health and Safety
Committee must enter the refusal to work into the register and ensure that all events involving any
person exercising his or her right of refusal to work in unsafe situations have been recorded in the
minutes of the Health and Safety Committee.
3.5 Victimisation Prohibited
Employees who exercise their right to refuse to work in accordance with the steps set out in this
Procedure are protected by the Occupational Health and Safety Act. Therefore, no employer or
person acting on behalf of an employer shall:
a) dismiss or threaten to dismiss an employee;
b) discipline or suspend or threaten to discipline or suspend an employee;
c) impose any penalty on an employee; or
d) intimidate or coerce an employee
Solely because the employee has acted in compliance with the applicable requirements set out in
this Procedure.
Notwithstanding this, any employee who without good reason refuses to work and who fails to follow
this Procedure may be dealt with in terms of Eskom’s applicable policies and procedures.
This document has been seen and accepted by:
Name Designation
M Moahlodi Senior Manager-
Phillip Mashego Senior Manager Human Resources
OHS Steering Committee
Date Rev. Compiler Remarks
October 2022 2 S Mqanto Stage 3 of reporting added
June 2015 1 SN Middel Confirmed still valid. Revision date
updated
August 2013 0 SN Middel
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Employees’ Right of Refusal to Work in an Unique Identifier: 240-43848327
Unsafe Situation Procedure Revision: 1
Page:
The following people were involved in the development of this document:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Standard
Title: Eskom Personal Protective Document Identifier: 240-44175132
Equipment (PPE)
Alternative Reference N/A
Number:
Area of Applicability: Eskom Holdings SOC Ltd
Functional Area: Occupational Health and
Safety
Revision: 2
Total Pages: 56
Next Review Date: March 2028
Disclosure Controlled Disclosure
Classification:
Compiled by Functional Responsibility Authorized by
Ntokozo Ngubane Miranda Moahlodi Kerseri Pather
Senior Advisor OHS Senior Manager OHS General Manager
Risk and Sustainability Risk and Sustainability Risk and Sustainability
Date: 05 April 2023 Date: 10 April 2023 Date: 10 April 2023
Document Template 32-4 Revision 7
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
Content
. Introduction ............................................................................................................................... 4
2.1 Scope ............................................................................................................................... 4
2.1.1 Purpose ................................................................................................................. 4
2.1.2 Applicability ........................................................................................................... 4
2.1.3 Effective Date ........................................................................................................ 5
2.2 Normative/Informative References ................................................................................... 5
2.2.1 Normative .............................................................................................................. 5
2.2.2 Informative............................................................................................................. 6
2.3 Definitions ........................................................................................................................ 6
2.4 Abbreviations ................................................................................................................... 7
2.5 Roles and Responsibilities ............................................................................................... 8
2.6 Process for Monitoring ...................................................................................................... 9
3.1 General ............................................................................................................................ 9
3.2 General Garments or Work Wear Specification .............................................................. 11
3.3 Minimum Standard Specifications for Boiler Suits/Overalls - One Piece (Figure 2 on
diagram: drg.10332 SANS 434) and two piece (Figure 4 on diagram: drg.15289da on
SANS 434) work wear suits ........................................................................................... 12
3.4 Minimum Standard Specifications for Dust Coats ........................................................... 16
3.5 Minimum Standard Specifications for Shirts ................................................................... 17
3.6 Minimum Standard Specifications for Ladies Shirts And Pants ...................................... 18
3.7 Minimum Standard Specifications Thermal Jackets (Winter Jackets) ............................ 19
3.8 Minimum Standard Specifications for Rain Protection (Rain Suits) ................................. 20
3.9 Minimum Standard Specifications for Chemical Protection (Chemical Suits) .................. 20
3.10 Minimum Standard Specifications for Reflective Vests and Bibs .................................. 21
3.11 Minimum Standard Specifications for Cold Weather Protection ................................... 22
3.12 Minimum Standard Specifications for Aprons ................................................................ 23
3.13 Minimum Standard Specifications for Head Protection ................................................. 23
3.14 Minimum Standard Specifications for Eye/Face Protection ............................................. 25
3.15 Minimum Standard Specifications for Hearing Protection .............................................. 28
3.16 Minimum Standard Specifications for Foot Protection .................................................... 28
3.17 Minimum Standard Specifications for Hand and Arm Protection .................................... 31
3.18 Minimum Standard Specifications for Skin Protection ..................................................... 32
3.19 Minimum Standard Specifications for Respirators ...................................................... 34
3.20 Minimum Standard Specifications for Protective Clothing for Users of Hand-Held Chain
Saws ......................................................................................................................... 36
3.21 Minimum Standard Specifications for Tog Bags ............................................................. 36
4.1 Head Protection .............................................................................................................. 37
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
4.2 Eye/Face Protection – Goggles, Eyeglasses, Welding Helmets, and Face Shields ........ 39
4.3 Hearing Protection .......................................................................................................... 40
4.4 Foot Protection ............................................................................................................... 40
4.5 Garments (Clothing) ....................................................................................................... 42
4.6 Chemical Protection ...................................................................................................... 44
4.7 Reflective Vests and Bibs ............................................................................................... 45
4.8 Hand and Arm Protection ............................................................................................... 45
4.9 Respirators and Dust Masks........................................................................................... 46
4.10 Cold-Weather Protection (Freezer Wear) ....................................................................... 46
4.11 Skin Protection ............................................................................................................... 47
4.12 Tog Bags ........................................................................................................................ 47
Acceptance ............................................................................................................................. 47
Revisions ................................................................................................................................ 48
Development Team ................................................................................................................ 48
Acknowledgements ................................................................................................................ 48
Annex A – Personal Protective Clothing – Standard Sizes ............................................................ 49
Annex B – Standard Nomenclature for Stitches, Seams and Stitching (Informative) ..................... 52
Annex C – Material Specification for T006 (Shirts) and all Garment Labels .......................... 53
Annex D – Flame Retardant Retro Reflective Material Sewing on Garments ................................ 54
Annex E – For Rain Wear Sizes and Chemical Chart Specs ......................................................... 55
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
The Occupational Health and Safety Act places an obligation on employers and/or users
of machinery to evaluate all the risks attached to any condition or situation that may arise from their
activities and to which persons at work may be exposed to and to take necessary steps to make
such condition or situation safe.
Where it is not possible to do so, the employer shall, free of charge, provide and maintain, in a good
and clean condition, safety equipment and facilities and ensure that any person exposed to any such
condition or situation is rendered safe. The employer is required to instruct or train his/her employees
in the proper use, maintenance, and limitations of the safety equipment and facilities provided and
to document such training. This document was compiled to provide minimum requirements for
generic Personal Protective Equipment (PPE) to be used in Eskom and its subsidiaries and how to
care for it. This in turn will ensure the protection of the health and safety of Eskom employees and
compliance with the relevant legal requirements.
2.1 Scope
2.1.1 Purpose
The purpose of this document is to prescribe the minimum requirements for generic Personal
Protective Equipment used in Eskom and provide guidance with regards to the process for the
selection, use, care, and maintenance of personal protective equipment (PPE).
This standard does not cover the requirements for specialised work such as Live Work, Fall Arrest
Systems and any other specialised equipment that is not included herein. The requirements for
specialised work disciplines are covered in their respective standards and/or specifications.
In the case where a particular PPE requirement is not covered in this standard, the onus is on the
Division/OU/Cluster/ BU to ensure that all safety requirements are complied with in accordance with
the relevant standards, regulations, or codes of practices for that specific PPE requirement.
2.1.2 Applicability
This document shall apply throughout Eskom Holdings SOC Limited divisions and subsidiaries.
The Operating/Business Units or Clusters may determine additional PPE requirements to suit their
own needs or working conditions, provided that the minimum requirements as set out in this
specification are met as well as the relevant legislation. Such additional requirements should not
expose the employee to any risk. This can be determined through a comprehensive activity-related
OHS risk assessment.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
2.1.3 Effective Date
This document will be effective from the day of authorization. Implementation of this document shall
be monitored after a period of six months from the authorisation date to allow the business to properly
transition to new requirements.
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
[1] Occupational Health and Safety Act No. .
[2] 240-62196227 Eskom Life-saving Rules.
[3] 240-62582234 OHS Roles and Responsibilities and Statutory Appointments.
[4] 240-43848327 Employees’ Right of Refusal to Work in Unsafe Situations.
[5] 32-245 Eskom Waste Management Standard.
[6] 32-520 Occupational Health and Safety Risk Assessment Procedure.
[7] SANS ISO 9001:2015 Quality Management Systems.
[8] SANS ISO 9001 Quality Management Systems.
[9] SANS 416 Chemical resistant gloves.
[10] SANS 434 Boiler Suits and Work Wear suits.
[11] SANS 1362 Sewing threads.
[12] SANS 1387-4, 6, 7 Woven cotton and similar apparel fabrics.
[13] SANS 1397 Industrial Safety Helmet.
[14] SANS 1400 Equipment (including oculars) for eye, face and neck protection against non-ionizing
radiation arising during welding and similar operations - Welding helmets, hand shields, goggles,
and welding spectacles.
[15] SANS 1404 Eye-protectors for industrial and non-industrial use.
[16] SANS 1423-1 Performance requirements for textile fabrics of low flammability.
[17] SANS 1451-1 Hearing protectors Part 1 Earmuffs.
[18] SANS 1451-2 Hearing protectors Part 2 Ear plugs.
[19] SANS 1451-3 Hearing protectors Part 3 Earmuffs attached to an industrial safety helmet.
[20] SANS 1822 Slide (zip) fasteners.
[21] SANS 10101 Standard nomenclature for stitches, seams, and stitching.
[22] SANS 50136 Respiratory protective devices – Full face masks - Requirements, testing, marking
[23] SANS 50140 Respiratory protective devices – Half masks and quarter masks – Requirements,
testing and marking.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
[24] SANS 50142 Respiratory protective devices – Mouthpiece assemblies - Requirements, testing
and marking.
[25] SANS 50143 Respiratory protective devices – Particle filters - Requirements, testing and
marking.
[26] SANS 50149 Respiratory protective devices – Filtering half masks to protect against particles –
Requirements, testing, marking.
[27] SANS 50381-2 Protective clothing for users of hand-held chain saws Part 2: Test methods for
leg protectors.
[28] SANS 50381-5 Protective clothing for users of hand-held chain saws Part 5: Requirements for
leg protectors.
[29] SANS 50471 High-visibility warning clothing for professional use - Test methods and
requirements.
[30] 240-47859177 Generation Policy on the Control of Clean Conditions When Working on
Generators.
2.2.2 Informative
[31] 32-109 Brand Architecture and Corporate Identity Policy.
[32] 32-288 Policy Procurement and Supply Chain Management Standard.
[33] 32-599 Standard Procurement and Supply Chain Management Standard.
[34] 32-727SHEQ Policy.
2.3 Definitions
2.3.1 Danger: Anything that may cause injury or damage to persons or property.
2.3.2 Employee: Any person who is employed by or works for an employer and who receives or
is entitled to receive any remuneration or who works under direction or supervision of an
employer or any other person.
2.3.3 Hazard: A potential source of harm or a source of, or exposure to, danger.
2.3.4 Hem: Free edge of a garment that is folded over and sewn down.
2.3.5 Lining: Layer of fabric sewn to the inside of a garment to give the garment a neat finish.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
2.3.6 PPE-Free Zone: An area of a work site where employees are not required to wear certain
types of PPE. This includes offices and walkways.
2.3.7 Pleat: A feature on a garment that makes provision for extra ease and formed by folding
fabric onto itself.
2.3.8 Risk Assessment: Overall process of hazard identification, risk analysis, and risk evaluation.
2.3.9 Seam: Joint consisting of a sequence of stitches uniting material or materials.
2.3.10 Syce: An armhole (or occasionally, a leg hole) in tailoring or dressmaking.
2.3.11 Yoke: Part of a shirt or jacket that is positioned at the shoulder area and joined to the lower
section with a seam.
2.4 Abbreviations
Abbreviation Explanation
ATPV Arc Thermal Performance Value
BS British Standard
BU Business Unit
Cal/cm2 Calories per square centimetre
dB Decibel
EN European Norms
g/m2 Grams per square meter
MAG Metal active gas (welding)
MIG Metal inert gas (welding)
MSDS Material safety data sheet
NRR Noise reduction rate
OU Operating Unit
OHS Act The Occupational Health and Safety Act, Act .
PPE Personal Protective Equipment
PU Polyurethane
PVC Polyvinyl chloride
SABS South African Bureau of Standards
SANS South African National Standard
SNR Signal to noise rate
TIG Tungsten inert gas welding
PPE Personal Protective Equipment
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
2.5 Roles and Responsibilities
2.5.1 Duties of Employer/Line Managers
PPE is identified as a control measure.
risk assessment document and the relevant PPE Matrix.
on the usage of any PPE is provided to all the applicable employees before its use. This shall
include the limitations of identified/specific work wear/accessory.
the employees are exposed to by ensuring that risk assessments are performed before
identification of PPE.
issued with the required personal protective equipment and makes proper use thereof.
cannot be eliminated or mitigated by the issuing of PPE.
contaminants, such as HBAs and HCAs, it becomes the responsibility of the employer to
clean the PPE.
2.5.2 Duties of Employees
Employees shall:
injury where required to.
modify any PPE issued.
emergencies and overtime.
by risk assessment, procedures, or any relevant requirements.
where the possibility exists that cleaning and maintenance will result in the spread of
contaminants. Then it becomes the responsibility of the employer.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
constraints shall approach their employer, through their health and safety representative or
manager, occupational health practitioner, or occupational hygienist, to arrange for specially
manufactured PPE to be purchased (for example, outsize shoes or boiler suits/overalls).
should not be shared with other employees.
responsibility of the issuer to ensure that it is properly cleaned or disinfected before storage
and use.
manufacturer’s specification.
2.5.3 OHS Department
The OHS Department shall:
2.6 Process for Monitoring
Compliance to this document shall be monitored and audited by the SHEQ department and Line
management. Where possible SHEQ department and/or line managers shall inspect procured PPE
to ensure compliance with this document and risk assessments.
3.1 General
3.1.1 Minimum Requirements
All PPE shall meet the following minimum requirements:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
adequate protection and reduce exposure to the specific hazards in the workplace.
specifications for the identified PPE.
depend on the condition of the equipment due to wear and tear or as specified by the
Responsible manager. (Each business unit to enforce their own site-specific
procedure/process).
3.1.2 Issuing of PPE
charge.
assessment and exposure assessment results.
needs shall be determined by the risk assessment.
every three months or according to guidance from the manufacturer or applicable legislation
or standards and codes.
schedule based on risk assessment and operational needs.
3.1.3 Replacement of PPE
items or based on fair wear and tear based on use and operational requirements.
items of PPE. Old clothing handed in shall be disfigured or cut up to prevent further use (that
is, wearing or using for exchange).
Standard (32-245). It is encouraged that waste management principles, such as reuse or
recycle, be adopted before disposal.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
appropriate Eskom disciplinary procedures shall be followed.
with Eskom. These items shall remain Eskom’s property and responsibility. The responsible
line manager shall monitor this process within the scope of the existing processes for the
issuing and replacement of PPE.
3.1.4 Special Circumstances
Employees who cannot perform their duties due to physical, medical, or ergonomic constraints that
prevent them from using appropriate protective equipment may be permitted to purchase specially
manufactured equipment (in terms of the Eskom procurement process), provided that a written
document from a specialist on such constraints is submitted to the employer via the health and safety
representative, Occupational health practitioner, Occupational Hygiene Practitioner, or manager.
3.1.5 PPE-Free Zones
that PPE is not a requirement in that area, and it is safe to be in that work area without
wearing PPE.
3.2 General Garments or Work Wear Specification
shall be free from defect that affect their appearance or may affect their serviceability (or
both) and free from marks, spots and stains incurred during the manufacturing process.
stitching shall be free of twists, pleats, and puckers and shall be sufficiently extensible to
obviate seams cracking and undue shrinkage in use.
tacked.
activities, garments without reflective strips shall be worn. This shall be supported by a proper
risk assessment.
the composition of these garments.
given in 5.3.1.2 (see figure 6(a) and figure 6(b)) of SANS 434.
the fabric confirming that the fabric complies with the SANS and EN specifications,
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
3.3 Minimum Standard Specifications for Boiler Suits/Overalls - One Piece (Figure 2 on
diagram: drg.10332 SANS 434) and two piece (Figure 4 on diagram: drg.15289da on
SANS 434) work wear suits
SANS 1387-4, material type of D59, flame retardant finish that complies with SANS 1423–1,
class C category 1.
polyester/viscose fabric in accordance with SANS 1387-3 and shall have acid resistant finish.
Pantone 19_6110TC.
Must be intact front and back of garments.
fabric with which the slide fastener is used.
Corporate Identity.
accordance with Eskom’s Corporate Identity.
sleeves’ circumference on the inner upper arm, and reflective strips on both legs at the knee
height , with an exception for conditions stated in 3.2. bullet point 5.
NB: Chemical (bottle green) boiler suits are acid treated only and are not flame treated.
3.3.1 Minimum Standard Specifications for Boiler Suits/Overalls (One Piece)
One Piece Boiler suits/overalls shall be in accordance with SANS 434.
at waist level.
at waist level.
least 80 mm and the steps shall be of width at least 35 mm.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
be turned in and stitched. Fly front shall fasten with a slide fastener as per SANS 1822 Figure
4 two-way fastener type A.
of the pocket with pencil pocket. Pocket mouths shall be finished with a hem that is deep
enough to accommodate the attachment of a fastening and shall be adequately secured.
with two rows of stitching of at least 2 mm and a maximum 10 mm respectively.
securely bar-tacked.
patternmaking practice.
acceptable patternmaking practice and at least 60 mm from the waist seam.
shall have an inside patch pocket of outer material.
depth of the breast pocket and shall be positioned at the centre front end of breast pocket.
buttonhole.
the ends.
least 10 mm above the pocket mouth and securely tacked at each end.
follows: If four-hole plastics buttons are used, a shirt type buttonhole may be used.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
3.3.2 Minimum Standard Specifications Boiler Suits/Overalls (Two Piece)
3.3.2.1 Minimum Standard Specifications for Pants (chemical and flame)
accordance with SANS 1387-4, Material Type D 59- flame retardant SANS 1423-1 class C
category 1.
polyester/viscose fabric in accordance with SANS 1387-3 and shall have acid resistant finish.
two-piece Personal Protective Clothing).
pocket.
front and one (1) button on the front of the waistband and a plain bottom.
chemical treated pants.
embroidered on the right back pocket.
material.
accordance with Eskom’s Corporate Identity.
conditions stated in 3.2. bullet point 5.
3.3.2.2 Minimum Standard Specifications for Clean Condition Pants
4, flame retardant class C category 1.
cord 10mm cotton belt string for fastening and without zip on the front no metal attachments.
Eskom’s Corporate Identity.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
with Eskom’s Corporate Identity.
on the inner upper leg.
3.3.2.3 Minimum Standard Specifications for Jackets (chemical and flame)
finished.
hem.
patternmaking and garment construction practice.
for chemical treated jackets.
40 mm and the full depth of the breast pocket and shall be positioned at the centre front end
of breast pocket.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
button and buttonhole.
ends.
mm above the pocket mouth and shall be securely tacked at each end; the bottom of a jacket
shall be finished with a plain hem.
3.3.2.4 Minimum Standard Specifications for Clean Condition Jacket
1387-4, Flame Retardant class C category 1.
accordance with Eskom’s Corporate Identity.
with Eskom’s Corporate Identity.
circumference on the inner upper arm.
3.4 Minimum Standard Specifications for Dust Coats
SANS 1457.
40 mm and the full depth of the breast pocket and shall be positioned at the centre front end
of breast pocket.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
top.
width at least 10 mm, shall be securely sewn in with the collar at the back neck on the inside.
width at least 15 mm.
and Zero Harm identification shall appear on the right side of the sleeve and shall be in
accordance with Eskom’s Corporate Identity.
3.5 Minimum Standard Specifications for Shirts
flame-retardant finish that complies with SANS 1423-1, class C category 1.
separate the cuff with button closure of non-conductive buttons. Sleeve opening bound with
binding.
accordance with Eskom’s Corporate Identity.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
3.6 Minimum Standard Specifications for Ladies Shirts And Pants
3.6.1 Ladies Shirts
with a flame-retardant finish that complies with SANS 1423-1, class C category 1.
conductive.
accordance with Eskom’s Corporate Identity.
3.6.2 Ladies Pants
SANS 1387-4, Material Type D59, flame retardant SANS 1423-1, class C category 1.
front and one (1) button on the front of the waistband and a plain bottom.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
embroidered on the right back pocket of the pants.
material.
accordance with Eskom’s Corporate Identity.
conditions stated in 3.2. bullet point 5.
3.7 Minimum Standard Specifications Thermal Jackets (Winter Jackets)
flammable material, the inner material shall be a tartan lining, 100% cotton of a darkish colour,
with the outer covering be pre-shrunk 100% soft woven fabric in accordance with SANS
1387-4, Material Type D59, flame retardant. (SANS 1423-1), class C category 1.
bellows type with a side entry into another separate pocket and shall be 22 cm deep and 21
cm wide.
conductive press studs.
well as a non-conductive zip complying with SANS 1822 and be intact front and back.
the size can be adjusted.
(Pantone 19_3920 as per corporate colour code.
inner upper arms.
accordance with Eskom’s Corporate Identity.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Personal Protective Equipment (PPE) Unique Identifier: 240-44175132
Revision: 2
Page:
3.8 Minimum Standard Specifications for Rain Protection (Rain Suits)
the face side 100% polyester, plain weave with 170 threads per square inch and coated with
a water-resistant coating.
to 50kN/m2). The lining to be 80% polyester and 20% cotton. All sizing benchmark to SANS
434 see size chart Annexure E for rain wear and chemical chart specification.
press-studs and shall comply with SANS 1822 type 5(auto lock alloy sliders).
rain entering the sleeve.
upper arm, reflective strips on both legs above the knees
accordance with Eskom’s Corporate Identity.
the front and on the back.
shall be 150 mm high.
3.9 Minimum Standard Specifications for Chemical Protection (Chemical Suits)
Coated Polyester, Tear strength weft 40N and warp 30N, burst strength weft 655N/50mm,
warp1232N/50mm, and coating adhesive 15N/50mm.
16 by 14.5.
rainwear.
welded.
resistant press-studs and shall comply with SANS 1822 type 5(auto lock alloy sliders).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Quality Management
Source: Attachment 9 Safety.pdfPPE must meet minimum standards and be suitable, fit for purpose, and kept in good condition. Compliance is monitored by SHEQ departments and line management, with inspections of procured PPE.
Health & Safety
Source: Attachment 9 Safety.pdfEskom's Personal Protective Equipment (PPE) Standard (240-44175132) prescribes minimum requirements for generic PPE used across Eskom and its subsidiaries. It covers the selection, use, care, and maintenance of PPE, including specifications for garments (boiler suits, dust coats, shirts, thermal jackets, rain suits, chemical suits, reflective vests, cold weather protection, aprons), head protection, eye/face protection, hearing protection, foot protection, hand/arm protection, skin protection, respirators, and protective clothing for chain saw users. The standard mandates that PPE be supplied free of charge, be suitable and fit for purpose, and be issued based on risk assessments. It details employer duties (conduct risk assessments, provide training, ensure proper use) and employee duties (attend training, sign for PPE, maintain and report issues). Monitoring and auditing by SHEQ departments and line management are required.
Environmental
Source: Attachment 9 Safety.pdfThe procedure references the National Environmental Management Act (NEMA 107) and the Eskom Waste Management Standard (32-245). Old or damaged PPE must be disposed of according to the Eskom Waste Standard, with reuse or recycling encouraged before disposal.
Contractual Terms
Source: Attachment 9 Safety.pdfPPE and clothing must be issued free of charge. Losses due to negligence may lead to disciplinary action. Eskom-branded PPE must be returned on termination of employment and remains Eskom's property.
Important Dates
Source: Attachment 13 Eskom - Standard Conditions of Tender.pdf (TENDER){"closingTime":"2.2","briefingSession":"{"date":null,"time":null,"venue":"tend a site visit and/or clarification meeting that is stipulated as being","is_compulsory":true}"}
Contact Information
Source: Attachment 13 Eskom - Standard Conditions of Tender.pdf (TENDER){"name":null,"email":null,"phone":null,"department":"Supply Chain Management","address":"g time 2.2 Ensure that Eskom has received the complete original tender and one (1) complete hard"}
Evaluation Criteria
Source: Attachment 13 Eskom - Standard Conditions of Tender.pdf (TENDER)Functionality
Tenders are evaluated on functionality as specified in the Invitation to Tender.
Price
Price is evaluated; prices must be in South African Rand.
Preferences
B-BBEE status contributes to preference points under the PPPFA.
Other
CIDB registration status may be considered; objective criteria may not include functionality or B-BBEE elements.
Technical Specifications
Source: Attachment 13 Eskom - Standard Conditions of Tender.pdf (TENDER)Supply Chain
Management Procedure 32-1034. Any addenda to an issued Invitation to Tender will be
published or issued in the same way as the Invitation to Tender was and will form part of the
Invitation to Tender documents.
Communication 1.5 Every communication between Eskom and a tenderer shall be made to or from the Eskom
Representative only, in w
Quality Management
Source: Attachment 13 Eskom - Standard Conditions of Tender.pdfof a tenderer.
Cost of tendering 2.6 Accept that Eskom will not compensate the tenderer for any costs incurred in the preparation
and submission of a tender, including the costs of any testing necessary to demonstrate that
aspects of the tender satisfy the evaluation criteria, or the negotiation of any contract.
Submitting a tender 2.7 Check the Invitation to Tender documents on receipt and notify the Eskom representative of
any discrepancy or omitted documents. The Acknowledgement Form must be completed
and submitted with the tender and must clearly state if the tender is for the whole or part of
the works, services or supply identified in the specification and/or works information by
Pricing Schedule
Source: Attachment 13 Eskom - Standard Conditions of Tender.pdfreasonable time for tenderers to make consequential adjustments to their tenders before
the closing date and time for submission.
In writing’ means hand-written, typed, type-written, printed or electronically made, and that
results in a permanent record.
Insurance 2.17 The extent (if any) of insurance provided by Eskom may not be for the full cover required in
the conditions of contract. The tenderer is advised to seek qualified advice regarding
insurance.
Pricing the tender 2.18 Include in the rates, prices, and the tendered total of the Prices all duties, taxes (including
VAT), and other levies payable by the tenderer if successful. Such duties, taxes and levies
are those applicable 14 (fourteen) days prior to the closing date and time for tender
submission.
2.19 Provide rates and Prices that are fixed for the duration of the contract and are not subject to
contract price adjustment except as provided for in the Invitation to Tender.
2.20 State the rates and Prices in South African Rand unless instructed otherwise in the Invitation
to Tender. The selected conditions of contract may provide for part payment in other
currencies. Therefore, submit Rates/Prices in Rands in accordance with the exchange rate
and base date as stipulated in the Invitation to tender.
Alterations to 2.21 May not make any alterations or additions to the tender documents, other than for purposes
documents of complying with instructions issued by the Eskom Representative or if necessary to correct
errors made by the tenderer. All such alterations shall be initialed by all signatories to the
tender. Corrections may not be made using correction fluid, correction tape or the like.
Alternative tenders 2.22 Submit alternative tenders only if a main tender is also submitted, and only if the submission
of alternative tenders is permitted by the Invitation to Tender. Accept that an alternative
tender may be based only on the criteria stated in the Tender Data.
Clarification and 2.23 Provide clarification and documents as may be required by the Eskom Representative
correction of Prices during the evaluation of tenders. However, documents identified as mandatory tender
after tender returnables that are required to be submitted at the closing date and time for tender
submission submission will not be requested and may not be submitted after the closing date and time.
phases, as this is regarded as ‘double dipping’.
Designated 3.12 Tenderers are also required to submit information on designated material and
materials and thresholds no later than contract award. If this information is not completed and
thresholds submitted as indicated in the Invitation to Tender, your tender will not be considered for
contract award
Functionality 3.13 If functionality is a criterion, tenderers will be scored against the functionality criteria and
requirements will be required meet the minimum threshold stated in the Tender Data to proceed to
further evaluation.
Financial analysis 3.14 Eskom has to determine the risk of doing business with a supplier who may pose a
(if applicable) financial risk to Eskom in the execution of the contract. During evaluation of a tenderer’s
financial statements, Eskom will attempt to identify mitigating factors or requirements for
the tenderer to meet, if such factors/requirements exist in the tender’s context. However,
should suitable mitigating factors not exist in the tender’s context or should mitigating
factors exist but be insufficient or if the risk is considered to be too high or should the
tenderer not agree with the mitigating factors, the tenderer will not be considered for
award.
Evaluation of Price 3.15 Evaluate the Price in accordance with the criteria/requirements in the Tender Data. Factors
such as CPA, FOREX, commodity exposure, unconditional discounts, technical
adjustment, PV and forecasted rates of invoicing are taken into account when determining
the evaluation Price.
Arithmetical errors 3.16 Check responsive tenders for arithmetical errors. If there is a discrepancy between an
amount in figures and the amount in words, the amount in words shall prevail.
Check the highest-ranked tenders for the following errors or omissions: -
(a) the misplacement of the decimal point in any unit rate; or
(b) omissions in completing the pricing schedule or bill of quantities, or
(c) arithmetical errors in line-item totals that are the result of the incorrect multiplication
of a unit rate and a quantity in a bill of quantities or schedule of prices; or
(d) arithmetical errors that are the result of the incorrect addition of the prices.
will request the tenderer to either confirm the prices as tendered or to accept the
corrected prices.
Where the tenderer elects to confirm the prices as tendered; Eskom will correct the error
as follows: -
(a) If a bill of quantities or pricing schedule applies and there is an error in the line-item
total that is the result of an error in multiplying the unit rate and the quantity, the line-
item total shall prevail, and the rate shall be corrected.
(b) Where there is a misplacement of the decimal point in the unit rate, the line-item total
as quoted shall prevail, and the unit rate shall be corrected.
(c) Where there is an error in the total of the prices that is the result either of other
corrections required by the checking process or in the tenderer’s addition of prices,
the total of the prices shall prevail, and the tenderer shall be asked to revise the
selected item prices (and their rates if a bill of quantities applies) to result in the
tendered total of the prices.
documentation by closing date and time of tender submission, the tenderer will not be
disqualified if otherwise evaluated as acceptable in all other criteria; however, the tenderer
will score zero points for Specific Goals within the 90/10 or 80/20 allocation of points.
Ranking of tenders 3.19 According to the PPPFA, Eskom will add the score for Pricing and the Specific Goals
together and rank the suppliers from the highest to the lowest.
Objective criteria 3.20 A contract may be awarded to a tenderer that did not score the highest points only in
accordance with Section 2(1) (f) of the Preferential Procurement Policy Framework Act,
must stipulate the Objective Criteria in the Invitation to Tender. Functionality and any
element of the B-BBEE scorecard may not be used as Objective Criteria.
Compliance Requirements
Source: Attachment 13 Eskom - Standard Conditions of Tender.pdf (TENDER)CSD report or as per certificate/affidavit provided
CSD number/CSD report) must be provided at the closing date and time for
CSD number or B-BBEE certificate/affidavit will need to be
B-BBEE Details: kom Representative and
Agreement to sign the contract documents.
Proof of authority 2.25 Where an agent submits a tender on behalf of a principal, an authenticated copy of the
to act as agent authority to act as an agent of the tenderer must be submitted as a tender returnable.
Compliance with 2.26 Comply with relevant legislation and regulatory instruments such as Instruction Notes issued
relevant legislation by National Treasury, CIDB Regulations for construction works; materials designated for local
(NT instructions, content and/or production by the dtic, PPPFA Regulations; Amended B-BBEE Codes, COIDA;
CIDB, PPPFA etc) OHS Act; Eskom’s requirements for Safety, Health, Environment and Quality (SHEQ) and any other
applicable legislation or regulatory instruments indicated in the Invitation to Tender.
Proof of Safety, 2.27 Tenderers are required to provide proof to the satisfaction of Eskom that safety, health,
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
Environment and closing date and time for tender submission stipulated in the Invitation to Tender and/or
Quality Contract Award. All costs and personnel associated with SHEQ must be reflected in the
requirements tender.
CIDB 2.28 Where the Tender Data has stipulated CIDB grading/s as a qualification criterion, tenderers
are required to be registered with the Construction Industry Development Board at the
closing date and time for submission of tenders or to be capable of being so registered
within twenty-one (21) working days from the closing date and time for submission of
tenders.
Where CIDB is applicable; proof of registration on CIDB is mandatory at the closing date
and time for tender submission. Should this not be received as stipulated
Health & Safety
Source: Attachment 13 Eskom - Standard Conditions of Tender.pdftenderers that Eskom has identified. A sole source and a single source are regarded as a
tenderer that meets the requirements stated in the Eskom Procurement and Supply Chain
Management Procedure 32-1034. Any addenda to an issued Invitation to Tender will be
published or issued in the same way as the Invitation to Tender was and will form part of the
Proof of authority 2.25 Where an agent submits a tender on behalf of a principal, an authenticated copy of the
to act as agent authority to act as an agent of the tenderer must be submitted as a tender returnable.
Compliance with 2.26 Comply with relevant legislation and regulatory instruments such as Instruction Notes issued
relevant legislation by National Treasury, CIDB Regulations for construction works; materials designated for local
(NT instructions, content and/or production by the dtic, PPPFA Regulations; Amended B-BBEE Codes, COIDA;
CIDB, PPPFA etc) OHS Act; Eskom’s requirements for Safety, Health, Environment and Quality (SHEQ) and any other
applicable legislation or regulatory instruments indicated in the Invitation to Tender.
Proof of Safety, 2.27 Tenderers are required to provide proof to the satisfaction of Eskom that safety, health,
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
requirements tender.
CIDB 2.28 Where the Tender Data has stipulated CIDB grading/s as a qualification criterion, tenderers
are required to be registered with the Construction Industry Development Board at the
closing date and time for submission of tenders or to be capable of being so registered
within twenty-one (21) working days from the closing date and time for submission of
tenders.
Where CIDB is applicable; proof of registration on CIDB is mandatory at the closing date
and time for tender submission. Should this not be received as stipulated in the Invitation to
Tender; the tender will be disqualified. However, in the event that, at the closing date and
time for tender submission, only proof of application for registration on CIDB is available,
then this must be submitted by the closing date and time for tender submission, while the
actual proof of CIDB registration (printout from CIDB database) must be submitted by
contract award
Contract Skills 2.29 If the tenderer is awarded a contract, it, as Contractor, shall achieve in the performance of
Development Goal the contract the Contract Skills Development Goals (CSDG) established in the CIDB
(CSDG) Standard for Developing Skills through Infrastructure Contract (published in GN 1779,
Government Gazette No. April 2023)
that has a duration of 12 months or more, and to:
a contract of R5 million or more, in the case of a professional service or service contract
or an order issued in terms of such a contract; or
a CIDB grading designation of grade 7 or higher, in case of an engineering and
construction works, or design and build contract or an order issued in terms of such a
contract.
Contract 2.30 The Contractor shall achieve in the performance of the contract the Contract Participation
Participation Goals Goals (CPG) relating to the engagement of targeted enterprises as established in the CIDB
(CPG) standard for indirect targeting for enterprise development through Construction works
contracts (published in Government Gazette No. February 2013).
enterprises as established in the aforesaid standard applies to:
construction works contracts in the General Building (GB) and to Civil Engineering (CE)
classes of construction works;
construction works contracts of an estimated minimum project duration of 6 months; and
construction works contracts in which at least 25% of the main contract could reasonably
be expected to be subcontracted out in one or more of the following CIDB classes of
construction works:
Civil Engineering (CE)
Electrical Engineering Work (EB)
) General Building Works (GB)
) Mechanical Engineering (ME)
2.31 Eskom may disqualify a tender if it is found that the tenderer has misrepresented or
falsified any information, certificate, affidavit or document. Eskom will report any fraud
in relation to a tenderer’s B-BBEE certificate/affidavit, or evidence of ‘fronting’ as
defined in the B-BBEE Act , as amended, to the B-BBEE Commission. The
tenderer will be suspended from business with any State-Owned Company for up to 10
years and may even be sentenced to jail.
2.32 Tenderers are also required to complete fully and submit the SDL&I Undertaking
(annexure to the Invitation to Tender) by no later than contract award. If the SDL&I
Respond 3.1 Respond to a request for clarification that Eskom receives before the closing date for
clarification clarification or queries. Eskom’s responses will be published to all tenderers in the same
manner the Invitation to Tender documents were issued. It is the tenderers’ responsibility
to check the Eskom Tender Bulletin and NT e-Tender Portal regularly for updated
responses to clarifications.
Issue Addenda 3.2 If necessary and prior to the closing date and time for tender submission, amend, amplify, or
add to the Invitation to Tender documents by way of Addenda published in the same
platform that the Invitation to Tender was issued. It is the tenderers’ responsibility to
check the Eskom Tender Bulletin and NT e-Tender Portal regularly for Addenda.
electronically. The Eskom Representative will publish the names of all tenderers received
on the Eskom Tender Bulletin and NT e-Tender Portal.
Tender Prices 3.5 Eskom will announce the names of the tenderers. Prices may be announced if so, stated
in the Tender Data.
Non-disclosure 3.6 Unless required by law, Eskom will not disclose information relating to the evaluation and
comparison of tenders and recommendations for the award of a contract to tenderers or to
any other person not officially concerned with the tender process until after the tender
award.
Grounds for 3.7 Reject a tender if Eskom establishes that there is proof that the tenderer influenced the
rejection processing of tenders or the awarding of the contract, the existence of collusion and/or bid
rigging, and/or that the tenderer has participated in any fraudulent/illegal activity in
connection with the Invitation to Tender.
Clarification of a 3.8 Obtain clarification from a tenderer in respect of any matter in the tender that may not be
tender clear or that could give rise to ambiguity in a contract arising from this tender if the matter
were not to be clarified. A document that the Invitation to Tender identifies as a mandatory
tender returnable that is required to be submitted at the closing date and time for tender
submission will not be requested, but Eskom may seek clarity on it.
may utilise reverse e-auction in certain Enquiries. Where reverse e-auction will be utilised,
this will be indicated in the respective Invitation to Tender and the reverse e-auction
supporting documents will be issued in the Invitation to Tender. Tenderers will be required
to submit a complete tender that does not contain Prices. If a tenderer has included prices
in its tender, the prices will not be considered.
Acceptance of 3.22 Notify Eskom's acceptance to the successful tender before the expiry of the validity period
tender or agreed additional validity period. Inform the successful and unsuccessful tenderers only
once approval has been granted by the Eskom Adjudication Authority. For open tenders,
this notification must be published on the Eskom Tender Bulletin and NT e-Tender Portal
Prepare contract 3.23 Revise the contract documents issued by Eskom in the Invitation to Tender documents to
documents take account of:
Addenda issued during the tender period;
inclusion of returnables stipulated in the Invitation to Tender;
inclusion of changes agreed in contract negotiations; and
Other revisions or documents agreed to between Eskom and the successful
tenderer during negotiations,
Sign Form of 3.24 Arrange for authorised signatories of both parties to complete and sign the original and one
Contractual Terms
Source: Attachment 13 Eskom - Standard Conditions of Tender.pdfincluding the Eskom Representative shall not be liable for any losses, claims or damages of
whatsoever nature or howsoever arising that may be sustained by a tenderer or any other
person as a result of its participation in the tender or from any amendment, termination or
suspension of the process set out in the Invitation to Tender or from its exclusion from
participating in the tender process at any point.
Eskom’s right to 1.7 Eskom reserves the right to enter into mandated negotiations with any, one or more selected
negotiate tenderer(s) in accordance with Eskom’s approved procurement policies and procedures.
240-62044728 Rev 12 Eskom Standard Identifier
Conditions of Tender Effective Date 01 February 2025
Review Date January 2030
Disclaimer 1.8 While Eskom takes all reasonable measures to ensure that all information contained in the
regarding accuracy tender documents is correct and complete, Eskom does not, however, make any
of tender representations or warranties, express or implied, as to the accuracy or completeness of
documents such information and Eskom expressly disclaims any, and all liability for such
representations, warranties or statements.
Tenderer’s 2. The tenderer shall comply with the following obligations when submitting a tender and shall:
Tender validity 2.12 Hold the tender(s) valid for acceptance by Eskom at any time within the validity period after
the closing date and time for tender submission. Extend the validity period for a specified
additional period if Eskom requests the tenderer to do so. A tenderer that agrees to extend
the validity of its tender will not be required or permitted to modify its tender. A tenderer that
does not agree to extend the validity of its tender will be excluded from further
consideration. Tenderers will be requested to extend the validity of their tenders until a
contract(s) have been concluded with one or more tenderers. A request that a tenderer
extend the validity of its tender is not a representation that the tender is an acceptable
tender or that Eskom will seek to negotiate or conclude a contract with the tenderer. If the
validity of tenders expires before contracts have been concluded, the procurement process
is deemed to have concluded without an award.
Confidentiality and 2. 13 Treat as confidential all matters that arise in connection with the procurement. Use and copy
copyright of the documents provided by Eskom only for the purpose of preparing and submitting a tender
documents in response to this Invitation to Tender.
Standardised 2.14 Obtain and familiarise themselves with, if required for the purposes of submitting a tender,
specifications and the latest revision of standardised specifications and/or other documents that have been
other publications incorporated by reference into the Invitation to Tender documents by reference.
Site visit and / or 2.15 Tenderers must attend a site visit and/or clarification meeting that is stipulated as being
clarification compulsory in order to familiarise themselves with the proposed work, services, supply,
meeting location or similar. Failure to attend a clarification meeting or site visit that is identified as
compulsory will result in disqualification from participation.
Details of the meeting(s) are stated in the Tender Data. Tenderers are entitled to ask
correction of errors as required above.
Evaluation of 3.17 Score the B-BBEE level as stated on the CSD report or as per certificate/affidavit provided.
B-BBEE If the B-BBEE level is a pre-qualification criterion; then the proof of the B-BBEE level
(certificate/CSD number/CSD report) must be provided at the closing date and time for
tender submission; or the tender will be disqualified. If sub-contracting to designated groups
pre-qualification criteria are utilized (selected/mandatory) in terms of the PPPFA
Regulation, then Eskom will apply the PPPFA requirements for sub-contractors’ B-BBEE
status and the sub-contractors’ CSD number or B-BBEE certificate/affidavit will need to be
provided at the closing date and time for tender submission. Should the
information/documents provided indicate that the level is in dispute (fraudulent/ expired)
then the tender will be disqualified.
However, for the purposes of PPPFA point allocation: if no B-BBEE certificate/affidavit is
provided at Tender closing date and time for tender submission, or the
information/documents provided are fraudulent or have expired; then the tenderer will not
be disqualified (if otherwise deemed to be responsive and acceptable in all other aspects)
but will score zero under PPPFA point allocation.
Evaluation of 3.18 Score the Specific Goals with reference to the supporting documentation in the tender. If a
Section
Source: Attachment 13 Eskom - Standard Conditions of Tender.pdfare submitted and accessible for downloading/evaluation without any challenges as well as
It must be noted that Eskom will not measure a criterion twice in the different evaluation
Functionality 3.13 If functionality is a criterion, tenderers will be scored against the functionality criteria and
further evaluation.
(if applicable) financial risk to Eskom in the execution of the contract. During evaluation of a tenderer’s
Evaluation of Price 3.15 Evaluate the Price in accordance with the criteria/requirements in the Tender Data. Factors
the evaluation Price.
but will score zero under PPPFA point allocation.
Evaluation of 3.18 Score the Specific Goals with reference to the supporting documentation in the tender. If a
Specific Goals tenderer fails to meet Specific Goals and/or to submit the required proof/supporting
will score zero points for Specific Goals within the 90/10 or 80/20 allocation of points.
Ranking of tenders 3.19 According to the PPPFA, Eskom will add the score for Pricing and the Specific Goals
Objective criteria 3.20 A contract may be awarded to a tenderer that did not score the highest points only in
must stipulate the Objective Criteria in the Invitation to Tender. Functionality and any
element of the B-BBEE scorecard may not be used as Objective Criteria.
Reverse e-Auction 3.21 Reverse e-auction is an electronic system that utilises the 90/10 and 80/20 Price and
Preference point systems, and which is intended to achieve competitive pricing. Eskom
(NT instructions, content and/or production by the dtic, PPPFA Regulations; Amended B-BBEE Codes, COIDA;
CIDB, PPPFA etc) OHS Act; Eskom’s requirements for Safety, Health, Environment and Quality (SHEQ) and any other
Health, environmental and quality (SHEQ) systems, policies and capabilities are in place at the
Quality Contract Award. All costs and personnel associated with SHEQ must be reflected in the
However, for the purposes of PPPFA point allocation: if no B-BBEE certificate/affidavit is
Contact Information
Source: Attachment 2 - E-Tendering Training Acknowledgement Form.pdf (unknown){"name":"__________________________________________________________","email":null,"phone":null,"department":null,"address":null}
Submission Guidelines
Source: Attachment 2 - E-Tendering Training Acknowledgement Form.pdf (unknown)Returnable documents: Annexure 1 – E-Tendering Training Acknowledgement Form, completed and signed, confirming the bidder has undergone self-training on the E-Tendering Solution and is able to operate it.
Description
Source: Attachment 3 Scope of work Building Maintenance.pdfThe purpose of this Scope of Work (SoW) is to define the requirements for the provision of building
and infrastructure maintenance services on an "as and when required" basis for the Peaking Power
Stations listed below:
This SoW provides preventative, corrective, reactive, emergency, refurbishment, and minor
construction services to ensure that all buildings, civil infrastructure, utilities and support facilities
remain safe, functional, reliable, compliant, and fit-for-purpose throughout the contract period.
The scope has been developed using the requirements contained in Buildings and Structures
System Health Report for Peaking Power Stations. The SOW is intended to address both routine
maintenance requirements and the identified asset health risks across the stations. Particular focus
will be placed on defects associated with water ingress, waterproofing failures, deteriorated building
finishes, drainage deficiencies, roofing defects, flooring failures, structural deterioration, sewage
infrastructure defects, access systems and building envelope degradation.
2.1 Scope
2.1.1 Purpose
The purpose of this document is to provide a standardized maintenance framework for building and
infrastructure assets across Drakensberg, Ingula, Vanderkloof, Gariep, Port Rex and Gourikwa
Power Stations.
The objective is to:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
2.1.2 Applicability
This Scope of Work applies to:
located at:
2.1.3 Effective date
This document becomes effective upon approval and implementation.
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
2.2.1 Normative
[1] Occupational Health and Safety Act (Act )
[2] Construction Regulations 2014
[3] SANS 10400 National Building Regulations
[4] Eskom Safety, Health and Environmental Standards
[5] Eskom Civil Engineering Standards
[6] Eskom Maintenance Strategy for Civil Plant
[7] ISO 9001 Quality Management Systems
[8] Applicable Municipal By-laws
[9] Applicable SANS Standards.
2.2.2 Informative
[10] I Buildings System Health Report for Peaking Power Stations
[11] Station Audit Reports
[12] Original Building Designs and Drawings.
2.3 Definitions
Definition Description
Corrective Maintenance Maintenance undertaken to restore an asset after a defect or failure.
Reactive Maintenance Maintenance undertaken after notification of a fault.
Work required immediately to eliminate safety, environmental or
Emergency Maintenance
operational risks.
Defect A condition impairing safety, functionality, appearance or reliability.
2.4 Abbreviations
Abbreviation Explanation
OHS Occupational Health & Safety
PPE Personal Protective Equipment
CoC Certificate of Compliance
SANS South African National Standards
UPS Uninterrupted Power Supply
SHR System Health Report
PM Preventative Maintenance
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
2.5 Roles and Responsibilities
Role Responsibility
Asset Management Asset integrity management and technical reviewers
Civil & Structural infrastructure inspections, assessments, and
Civil Engineering Team
monitoring
Engineering Manager Approval of scope, assessments, and recommendations
System Engineer Technical review of Civil & Structural infrastructures
2.6 Process for Monitoring
Monitoring shall include:
2.7 Related/Supporting Documents
Refer to Section 2.2.
3.1 General Building Maintenance
The SoW makes provision for the Contractor to provide:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
Work shall be performed upon instruction from the Service Manager.
Unless a different period is agreed upon for a specific Task Order, the Contractor responds to and
completes work within the following minimum timeframes, measured from moment of notification by
the Service Manager as per Table 1 below:
Table 1: Timeframes for Maintenance Categories
Category Response Time (on site) Completion Target
Emergency Maintenance 2 hours Risk eliminated/made
safe same day;
permanent repair per
agreed programme
Reactive Maintenance 48 hours 10 working days, or
per accepted
programme for larger
repairs
Corrective Maintenance By agreed Task Order date Per accepted
programme in the
Task Order
Planned Maintenance Not applicable Per frequency in
Table 2
As a minimum, Planned Maintenance is as per Table 2.
Table 2: Planned Maintenance Schedule
Area Activity Frequency
Buildings – General Cleaning 6 Monthly
Roads Cleaning 6 monthly
Building – Roofing Silver coating (where applicable) Annually
Buildings – Gutters & Downpipes Cleaning 6 monthly
Stormwater Drainage Cleaning Annually
(before rainy season)
Drainage (Powerhouse & Building) Cleaning 6 monthly
Sewage Treatment Plant Cleaning, infrastructure repairs Annually
(Drakensberg PS) where required
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
3.2 Building Envelope and Structural Repairs
3.2.1 Roofing and Waterproofing
The Contractor is required to execute the following services:
The Contractor notes the works includes the following areas as a minimum:
3.2.2 Walls, Masonry and Concrete
The Contractor is required to:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
3.2.3 Painting and Corrosion Protection
The scope includes but is not limited to:
The Contractor ensures that all works are executed in compliance with the manufacturer's
specifications.
3.3 Doors, Windows and Access Systems
The Contractor, as a minimum executes the following:
Specific focus shall be placed on damaged external doors and access doors identified at
Gourikwa and Drakensberg PS.
3.4 Flooring and Ceilings
The Contractor is required, as a minimum, to:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
Attention shall be given to:
Room.
The Contractor notes that the heaving tiles within the power stations are to be removed and floors
replaced with an epoxy coating system.
3.5 Plumbing, Water and Sewer Systems
The Contractor is required, as a minimum, to:
Particular focus is required to address:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
3.6 Electrical Building Services
The Contractor is required, as a minimum, to:
3.7 Roads and Civil Infrastructure
The Contractor is required, as a minimum, to:
(see Technical Service Requirements, Section 3.16)
require, where concrete road/apron pavements exist
waterproofing and drainage)
The Contractor performs routine maintenance as per Table 2 above.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
3.8 Fencing, Gates and Security Infrastructure
The Contractor is required, as a minimum, to:
Repair and/ or replace perimeter and electric fencing system components
Repair and/ or replace gate motors
Repair and/ or replace sliding gates
Repair and/ or replace security barriers
Repair access automation systems
Repair and/ or replace security doors
3.9 Fire Protection Infrastructure
The Contractor is required, as a minimum, to:
Service fire extinguishers
Service hose reels
Repair fire doors
Repair fire signage
Maintain fire detection devices
Repair associated building fire protection systems
The Contractor is to note that the stations have existing Fire Detection and Protection service
contracts, and any services related to fire detection and protection will be adhoc.
3.10 Defect Specific Work
The Contractor as a minimum, executes the defect specific services stated below.
3.10.1 Drakensberg PS
The Contractor as a minimum, executes the following defect specific services:
Water ingress
Roof sheet damage
Ceiling defects
Building waterproofing
Floor defects
Overhead crane/ crawl beams
3.10.2 Ingula PS
The Contractor as a minimum, executes the following defect specific services:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
Building envelope degradation
Power and control cables rerouting
Removal of redundant cable racks
3.10.3 Gariep PS
The Contractor as a minimum, executes the following defect specific services:
Roof waterproofing failures
Building cladding, where required
Effluent spillages
Floor tile failures
Building corrosion
3.10.4 Vanderkloof PS
The Contractor as a minimum, executes the following defect specific services:
Water ingress
Waterproofing deterioration
Floor covering defects
Concrete deterioration
3.10.5 Port Rex PS
The Contractor as a minimum, executes the following defect specific services:
Water ingress
Building envelope deterioration.
3.10.6 Gourikwa PS
The Contractor as a minimum, executes the following defect specific services:
Water ingress
Roof defects
Damaged doors
Sewer defects
Cracked walls and deteriorated finishes
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
4.1 Leak Detection, Roof Inspection and Roof Waterproofing
The Contractor is required to investigate, assess, repair and maintain roofing systems, waterproofing
systems and associated rainwater disposal infrastructure to eliminate water ingress and maintain
the weather-tight integrity of buildings. Particular emphasis shall be placed on defects identified in
the Buildings System Health Report, including water ingress at Drakensberg, Gariep, Ingula,
Vanderkloof, Port Rex and Gourikwa Power Stations.
The Contractor as a minimum, will:
systems and rainwater disposal systems to determine the source of water ingress.
contribute to water ingress.
Assess roof slopes and identify areas where ponding or pooling water occurs.
Verify the adequacy of gutter and downpipe sizing relative to roof catchment areas.
Submit a detailed inspection report containing findings, photographic evidence, root cause
analysis and proposed remedial measures for acceptance by the Service Manager.
leak-free.
components.
in accordance with Eskom corrosion protection specifications.
and submit the required test documentation.
Provide workmanship and material guarantees for all roof repair and waterproofing works.
Notify the Employer of any additional urgent defects identified during inspections.
Where an existing waterproofing system is to be replaced:
system by more than 10%.
registered Professional Structural Engineer/ Technologist to:
o Conduct a structural assessment
o Perform structural calculations
o Confirm the adequacy of the existing structure
o Produce a structural assessment report and methodology statement
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
before implementation.
The service includes as a minimum:
Inspection and leak detection
Roof waterproofing
Roof sheeting repairs
Roof tile repairs
Flashing repairs
Fascia board repairs
Barge board repairs
Roof sealing
Gutter replacement
Downpipe replacement
Roof coating systems
Local repairs to exposed roof support elements
The Contractor:
height.
Investigates water ingress pathways before any repair work is undertaken.
Ensures that wet, unstable or unsound substrates are not concealed without treatment and
acceptance.
existing roofing system.
Applies waterproofing systems strictly in accordance with manufacturer specifications.
Supplies all product data sheets, technical specifications and warranty certificates.
Notes that all major roof replacement, structural modifications and asbestos-containing
roofing systems are excluded from ordinary maintenance works and are only conducted
following specific instruction by the Employer.
Notwithstanding the above, the Contractor submits detailed:
Method Statements.
Quality Control Plans (QCPs).
Inspection and Test Plans (ITPs).
Product Specifications.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
for acceptance by the Service Manager before commencement of any roofing or waterproofing
works.
4.2 Painting and Corrosion Protection
The Contractor undertakes painting, coating and corrosion protection works for buildings and
associated infrastructure.
The scope includes, as a minimum:
Internal and External walls
Ceilings
Structural steel
Doors and Door frames
Window frames
Gates and Fencing
Gutters and Downpipes
Fascia boards and Barge boards
Exposed steelwork
Roof support structures
For repainting works, the Contractor ensures:
otherwise specified.
Unless otherwise instructed by the Service Manager, colours shall match Eskom Corporate Identity
requirements and generally consist of:
Plascon Inspired Y1-C2-3 (Pale Linen);
Plascon Inspired Y2-D2-3 (Veldrift);
Plascon Inspired Y2-D2-2 (Stone Wash);
Plascon Inspired Y2-D2-1 (Waxen Tint).
The Contractor is required to:
Obtain approved colour swatches from an approved supplier.
Ensure compliance with Eskom Corporate Identity Standards.
Submit product data sheets and Safety Data Sheets (SDS) prior to commencement.
Assess substrate conditions and identify causes of coating failure.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
The Contractor ensures that surface preparation includes:
Removal of loose paint and rust
Removal of oil and grease
Removal of mould and biological growth
Surface cleaning
Feathering of existing paint edges
Repair of defective surfaces
The Contractor further ensures:
Adjacent surfaces and equipment are protected
Covers, handles and removable fittings are removed where practical
Reinstatement is completed upon completion of the works
Coating application shall comply with manufacturer specifications relating to:
o Coverage rates
o Surface preparation
o Film thickness
o Overcoating intervals
o Environmental conditions
o Uniform in appearance
o Fully bonded
o Free of defects
o Free of contamination
o Applied to the specified coating thickness
Notwithstanding the above, the Contractor submits detailed:
Method Statements.
Quality Control Plans (QCPs).
Inspection and Test Plans (ITPs).
Product Specifications.
Material Data Sheets.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
for acceptance by the Service Manager before commencement of any painting works.
4.2.1 Machine Hall Crane beam – Drakensberg PS
The service includes as a minimum:
Overhead crane crawl beams
Crane rails
Rail clips
Rail fixing systems
Rail support structures
Crane girders
Crane access walkways
Structural steel supporting crane systems
Corrosion resulting from continuous water ingress from bedrock seepage is causing deterioration of
rail fixings, rail support systems, concrete channels, and structural steel components.
The Contractor is required, as a minimum, to:
Identify seepage and water ingress points.
Assess corrosion caused by continuous wetting.
Design and install water diversion measures.
Install bunds, drains and containment systems where required.
Repair water-damaged concrete.
Seal leakage pathways where practical.
Water ingress and pooling currently create the ideal conditions for crevice corrosion and accelerated
deterioration of the rail fixing components.
4.2.1.1 Crane Rail Corrosion Repairs
The Contractor is required to:
Inspect all crane rail systems,
Perform condition assessments,
Conduct dimensional checks,
Assess rail alignment,
Assess rail fastening systems and
Assess supporting concrete beams and channels.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
Works may include:
Rail clip replacement,
Rail fixing replacement,
Fastener replacement,
Structural steel repair,
Corrosion rehabilitation,
Reinstatement of rail alignment and
Concrete rehabilitation.
4.2.1.2 Concrete Rehabilitation
The Contractor repairs:
Spalled concrete.
Delaminated concrete.
Cracked concrete.
Water damaged concrete.
Corrosion affected concrete adjacent to steelwork.
Refer to Section 4.3.1 for repair specifications.
4.3 Walls, Masonry and Concrete
The service includes as a minimum, repair of:
Cracked walls
Water-damaged walls
Masonry defects
Concrete defects
Penetrations
Damp walls
Plaster failures
Retaining wall defects
Building envelope deterioration
The Contractor:
Assesses whether defects are structural or non-structural.
Assesses whether movement is active or dormant.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
Identifies any relationship between cracking and water ingress.
Reports structural defects to the Service Manager before repairs commence.
The Contractor removes all loose and unsound materials to a sound substrate and ensure
compatibility of repair materials with existing construction.
Major structural repairs, underpinning and structural strengthening remain outside the ordinary
maintenance scope and requires separate engineering instructions. The service includes local nonstructural repair of plaster, masonry, cracks, water-damaged finishes, penetrations, retaining-wall
finishes and concrete identified in a Task Order.
The Contractor assesses whether cracking or movement is active, structural or associated with water
ingress and reports suspected structural distress before repair.
Loose and unsound material is removed to a sound substrate. Exposed reinforcement is treated
using an accepted repair system.
Repair mortar, plaster, brick and block are compatible and properly bonded, cured and finished.
Structural design, significant reinforcement repair, underpinning and major retaining-wall work
require separate engineering scope and instruction.
4.3.1 General Concrete Repairs
The Contractor repairs concrete defects including:
Spalling
Cracking
Corrosion damage
Exposed reinforcement
Delamination
Loss of concrete cover
The Contractor:
Saw-cuts repair perimeters to a minimum depth of 10 mm.
Removes defective concrete to sound material.
Avoids damaging existing reinforcement.
Creates dovetailed repair edges where required.
Cleans and treats corroded reinforcement.
Removes all debris and dust before repair.
Saturates substrates where required by manufacturer specifications.
Apply approved repair mortars in accordance with manufacturer specifications.
Cure repairs for a minimum of seven days where specified.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
Where repair depths exceed 100 mm:
subject to acceptance by the Supervisor.
4.3.2 Crack Repairs
The Contractor assess and classify all cracks as:
Structural or non-structural
Moving or non-moving
The selected repair methodology will be appropriate to the crack classification and subject to Service
Manager acceptance.
Typical repair methods include:
Epoxy injection
Cementitious grout injection
Flexible sealant repairs
Crack routing and sealing
Surface treatment systems
The Contractor repairs all cracks greater than 0.2 mm wide unless instructed otherwise by the
Service Manager.
For dormant cracks, the Contractor:
Open a groove approximately 20–30 mm wide and up to 50 mm deep.
Cleans and prepares the crack.
Fills using an approved repair system.
For dry cracks on horizontal surfaces, the Contractor:
Forms a V-shaped groove approximately 10 mm deep.
Cleans the crack thoroughly.
Fills by capillary action with low-viscosity epoxy resin.
Removes excess material after curing.
Grinds and finishes the surface to match surrounding concrete.
The Contractor ensures all repaired cracks provide:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
Durability
Long-term serviceability
Structural integrity where applicable
Notwithstanding the above, the Contractor submits detailed:
Method Statements.
Quality Control Plans (QCPs).
Inspection and Test Plans (ITPs).
Product Specifications.
Material Data Sheets.
for acceptance by the Service Manager before commencement of any concrete works.
4.4 Doors, Windows and Access Systems
The service includes the inspection, maintenance, repair, replacement and installation of doors,
windows, frames, glazing, ironmongery, roller shutter doors, access control systems and associated
building access infrastructure.
The Contractor performs maintenance on:
External and internal doors
Security doors
Fire-rated doors
Roller shutter doors
Aluminium doors and windows
Timber doors and frames
Steel doors and frames
Window glazing systems
Blinds and window tinting
Door closers
Panic bars and emergency exit mechanisms
Hinges, locks and latches
Access control systems
Magnetic locking systems
Electric strikes
Door seals and weather strips
The Contractor:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
Assesses all defective components and submit recommendations to the Service Manager.
Repairs or replaces damaged doors, door frames and associated hardware.
Repairs damaged aluminium window and door systems.
Replaces broken or cracked glazing with equivalent safety glazing where required.
Repairs damaged hinges, rollers, closers and locking mechanisms.
Repairs or replaces weather strips and seals to prevent air and water ingress.
Ensures all windows and doors operate freely and close correctly.
Repairs damaged access control components.
Adjusts and tests magnetic locks and electric strikes.
Repairs roller shutter doors and associated motors.
Maintains the integrity of fire-rated doors and emergency exit systems.
For glazing repairs, the Contractor ensures:
Glass complies with applicable SANS requirements.
Safety glazing is utilised where required.
Existing tinting and shading characteristics are matched as closely as practicable.
For access systems:
The Contractor verifies correct operation of all access systems after completion.
Security settings and programming are only changed following approval by the Service
Manager.
facility.
Notwithstanding the above, the Contractor submits detailed:
Method Statements.
Quality Control Plans (QCPs).
Inspection and Test Plans (ITPs).
Product Specifications.
Material Data Sheets.
for acceptance by the Service Manager before commencement of any of the works.
4.5 Flooring and Ceilings
The service includes maintenance, repair and replacement of flooring systems, suspended ceilings,
raised access floors and associated finishes.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
The Contractor performs repairs to:
Floor Tiles (Ceramic, Porcelain etc.),
Concrete floors,
Timber floors,
Vinyl floors,
Epoxy flooring,
Carpets,
Raised access flooring systems,
Suspended ceilings,
Ceiling grids,
Ceiling boards,
Bulkheads,
Cornices, and
Access panels.
The Contractor:
Investigates root causes of floor failures before undertaking repairs,
Assesses defects resulting from movement, moisture, vibration, settlement or water ingress,
Replaces damaged flooring with materials matching existing finishes where reasonably
practicable,
Repairs loose, cracked, lifting or broken tiles,
Repairs damaged timber flooring systems,
Replaces damaged carpets and vinyl flooring,
Removes trip hazards, and
Repairs floor levels where localized settlement has occurred.
For raised floors, the Contractor:
Inspects support pedestals and framing systems,
Replaces unstable floor panels, and
Ensures floor loading capacities are maintained.
The Contractor notes that the raised floor in the Control Room (Drakensberg PS) is to be
replaced with new.
For ceiling works, the Contractor:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
Replaces water-damaged ceiling finishes,
Repairs ceiling suspension systems,
Reinstates access panels and service openings, and
Matches existing ceiling systems.
All flooring and ceiling materials shall be installed in accordance with manufacturer's specifications.
Notwithstanding the above, the Contractor submits detailed:
Method Statements,
Quality Control Plans (QCPs),
Inspection and Test Plans (ITPs),
Product Specifications, and
Material Data Sheets.
for acceptance by the Service Manager before commencement of any ceiling and flooring works.
4.5.1 Control Room – Drakensberg PS
The Contractor is required to replace the raised modular floor panels with panels of the same
dimensions as existing - 600mm × 600mm. The finished product must be a continuous floor finish
with no uneven surfaces that could pose a safety hazard. The Contractor must submit specifications
of the new floor which should be in accordance with the latest Eskom Standards for the Ergonomic
Design of Power Station Control Suites.
The panels are to consist of cementitious infill and as per the latest standard, the floors should have
a grey/ beige colour to match with the overall colour basis of the room. The floor colour should not
be completely plain but have a varying effect to reduce the impact of dirt.
The floor material should be hard-wearing, sound-deadening floor material and have antistatic
properties which is also advisable when using computer equipment.
The flooring product can be used as sheeting for large spaces or cut to fit onto computer flooring. If
required, inlays can be made with different colours to create a pattern on the floor, and it
recommended that the product utilised is linoleum or similar approved.
To define the operator’s workspace more clearly, darker overlays can be positioned around the
operator’s desk. This overlay will typically be charcoal black, to minimise wear and tear and dirt
appearance. The overlays can be removed for cleaning and easily replaced later. The overlays must
have a bevelled edge to reduce unevenness for chair castors.
The Contractor is to submit a sample of the floor panels prior to start of the work for acceptance by
the Service Manager.
4.5.1.1 Steel under Structure/sub-structure
The under-structure system and the interfaces to the panels shall be such that the floor shall remain
sturdy and firm no matter how many panels are removed for work to be carried out. The sub floor
should be structurally strong enough to support the raised access floor and the environment it
supports. The Contractor further confirms the final floor loading capabilities on refurbishment.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
4.5.1.2 Ceiling
The ceiling panels in the Control Room are aging and have water damage. The full extent of the
scope will be determined and accepted by the Service Manager once the Contractor has inspected
and submitted a detailed refurbishment plan.
The extent of work therefore required for the refurbishment of the ceiling is as follows:
been previously accepted by the Service Manager and is in accordance with relevant
Eskom and regulatory standards.
provided by the Contractor to the Service Manager for acceptance.
Equipment Room with new.
material that may cause harm and/ or skin irritation. The Contractor assesses the material
prior to commencement of work and plans the refurbishment accordingly. Where the
material is confirmed to contain asbestos, the Contractor ensures assessment, handling,
removal and disposal is carried out by a contractor accredited and registered in terms of
OHS Act to handle such material. All waste material is subsequently disposed safely and at
a designated landfill site.
panels and associated supporting aluminium frames and brackets. The ceiling must match
the existing. Depending on the condition and extent of damage to the ceiling, the Employer
may opt to replace the complete suspended ceiling which is generally white and comprises
of suspended acoustic boards/tiles.
4.5.1.3 Access Floor
The access floor panels are to be structurally rigid isotopic or linear assemblies fabricated entirely
from non-combustible components and shall consist of a dead flat full-hard steel top sheet,
resistance-welded to a steel bottom section of irregular or regular domed formation. The exterior and
interior surfaces of the access floor panel shall be protected from corrosion by a process of cleaning
and dip phosphate. The core interior of the panel shall be filled with a non-combustible cementitious
compound which will support no less than 90% of the top surface of the panel. The exterior surface
of the panel shall be coated with an epoxy coated finish.
For a freestanding system the access floor panels shall provide for positive engagement with the
pedestal at all four corners.
For a system in which the panels are screwed down at their corners the access floor panel shall be
provided with four corrosion resistant captured fasteners. The fasteners shall bolt through the panel
and clamp the panel to the pedestal’s heads. The panels shall be able to be removed by releasing
the four fasteners. A more suitable solution is advisable instead of boards for the ceiling area. The
Contractor is to make a proposal, which should be accepted and approved prior to installation, or
replace the existing boards with a more suitable material.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
4.5.1.4 Under Structure
The under-structure system consists of a steel or aluminium factory assembled pedestal head and
base which shall be surface treated and have a corrosion-resistant finish. This assembly shall be
capable of supporting a minimum load of 22.5 kN.
The maximum depth of the access floor panel and the pedestal assembly shall not exceed assembly
over a range of 50 mm (25 mm up 25 mm down) without rotation of the pedestal head.
The nut shall have an anti-rotation and vibration-proof feature.
For a freestanding system the pedestal head shall have locating studs on which the access floor
panels positively locate as well as locating tabs and ridges which positively position and self-align
the pedestal head with access floor panel.
For a system in which the panels are screwed down at their corners the pedestals head shall have
four threaded holes to accept the panel fasteners as well as locating tabs and ridges which positively
position and self-align the pedestal head with the access floor panel.
For both the free standing and the screw-down the access floor head rests on a conductive plastic
gasket.
For a stringer system the pedestal head shall be designed to receive Snap-On or bolt on stringers.
Stringers shall be manufactured from a minimum of 20-gauge steel channel section with a Snap-On
attachment to the pedestal.
Each stringer shall be surface treated and have a corrosion-resistant finish and be provided with a
factory-applied and conductive bonded gasket on the top surface.
The design of all under structure systems and their interfaces to the panels shall be such that the
floor shall remain sturdy and firm no matter how many panels are removed for work to be carried out
under the access floor.
4.5.1.5 Finishes
The raised access floor shall be finished with one of the following finishes:
panel for use in a Snap-On stringer or free-standing system.
crack or split or come away from the edge of the panel.
600mm × 600mm vinyl tiles adhered to the full surface of the access floor panel for use in a
Snap-on stringer or freestanding system.
4.5.1.6 Loading Performance Specifications
Type of Load Panel Grade
Type 1 Type 2 Type 3
Concentrated load on a 25 mm × 25 mm area: 2.7 kN 4.5 kN 5.5 kN
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
Maximum deflection on top surface 2.00 mm 2.00 mm 2.00 mm
(Not to increase when load is applied continuously
for 24 hours)
0.25 mm × 3 0.25 mm × 3 0.25 mm × 3
Maximum permanent set on top surface
Safety factor = design load
(Failure shall be ductile and not sudden)
Uniformly distributed load per m2: 9.0 kN 13.5 kN 16.5 kN
Maximum deflection on underside 1.00 mm 1.00 mm 1.00 mm
Maximum permanent set on underside 0.25 mm 0.25 mm 0.25 mm
Rolling loads:
Under rolling load test conditions edge to edge
deflection between loaded and unloaded panels
shall not exceed 2.00mm and maximum permanent
set shall not exceed 0.50mm (bolt on top surface for
all rolling load tests)
75mm Ø × 24mm wide hard plastic wheel 3.5 kN 4.9 kN 6.0 kN
Number of passes 10 10 10
150mm Ø × 50mm wide hard plastic wheel 2.7 kN 3.5 kN 4.5 kN
Number of passes 20 000 20 000 20 000
20 mm Ø ×75mm wide hard plastic wheel 2.25 kN 2.25 kN 2.25 kN
Number of passes 40 000 250 000 500 000
Impact:
Load dropped onto an area of 25 mm × 25 mm 0.43 kN 0.43 kN 0.43 kN
Maximum permanent set 1.50mm 1.50mm 1.50mm
Pedestal assembly:
Axial load 22.5 kN 22.5 kN 22.5 kN
Horizontal force applied at a height of 300mm from
the sub-floor after the adhesive has cured - 10 kg 10 kg 10 kg
minimum resistance
4.5.2 Floor Tiles (Underground Works – Machine Hall and Valve Hall) – Drakensberg &
Gariep PS
The Contractor is required to remove the existing heaved floor tiles in the Machine Hall and Valve
Hall in the underground powerhouse complex at Drakensberg and Gariep Power Station.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Scope of work for Building & Infrastructure Unique Identifier: 167A/20886
Maintenance Services on an 'As and When Required'
Revision: 1.0Basis for Eskom Peaking
Page:
The Contractor supplies all labour, supervision, materials, consumables, equipment and accessories
required for the removal of the existing floor tiles and the subsequent preparation and application of
a heavy-duty epoxy floor coating system to concrete floor surfaces.
The epoxy flooring system is to be suitable for industrial (power station) applications.
4.5.2.1 Surface Assessment
Prior to commencement of the works, the Contractor:
A condition assessment report together with the proposed coating system is submitted to the Service
Manager for acceptance before commencement of the works.
4.5.2.2 Surface Preparation
Surface preparation is considered critical to the success of the system.
The Contractor:
o Diamond grinding/ Shot blasting/ Scarifying or Mechanical abrasion.
The prepared substrate is to ne structurally sound, dry, free of dust and contaminants and provide
an open textured surface suitable for bonding.
All surface preparation is to comply with the coating manufacturer's specifications.
4.5.2.3 Concrete Repairs
Prior to application of the coating, the Contractor repairs concrete defects such as cracks, spalling,
surface defects, voids and honeycombing.
Repairs are to be undertaken using an approved epoxy repair mortar or cementitious repair materials
compatible with the proposed coating system.
All repairs are to be completed and cured in accordance with manufacturer's recommendations
before the coating system is applied.
4.5.2.4 Epoxy Coating System
Unless otherwise specified in the Task Order, the epoxy coating system consists of:
o Solvent-free or low VOC epoxy primer
o Applied to prepared concrete surfaces
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Submission Guidelines
Source: Attachment 3 Scope of work Building Maintenance.pdf (unknown)Returnable Documents:
Evaluation Criteria
Source: Attachment 3 Scope of work Building Maintenance.pdf (unknown)Bidders must comply with the Occupational Health and Safety Act, Construction Regulations 2014, SANS 10400, and Eskom Safety, Health and Environmental Standards. The contractor must submit method statements, quality control plans, inspection and test plans, and product data sheets for acceptance. No specific pre-qualification thresholds (e.g., CIDB grading, B-BBEE level) are stated in the provided document.
Technical Specifications
Source: Attachment 3 Scope of work Building Maintenance.pdf (unknown)The purpose of this Scope of Work (SoW) is to define the requirements for the provision of building and infrastructure maintenance services on an "as and when required" basis for the Peaking Power Stations listed below:
Services include preventative, corrective, reactive, emergency, refurbishment, and minor construction to keep buildings, civil infrastructure, utilities and support facilities safe, functional, reliable, compliant, and fit-for-purpose throughout the contract period.
Maintenance categories and response times:
Monitoring shall include monthly contract review meetings, defect tracking, quality inspections, system health monitoring, service level monitoring, annual review of contract performance, and reporting on outstanding and completed defects.
For water ingress, the Contractor must inspect roof slopes, identify ponding or pooling areas, inspect HVAC ducts and roof penetrations, and submit a detailed inspection report with photographic evidence, root cause analysis, and proposed remedial measures for acceptance by the Service Manager.
For structural assessments, the Contractor must engage a Structural Engineer/Technologist to conduct a structural assessment, perform structural calculations, confirm the adequacy of the existing structure, and produce a structural assessment report and methodology statement.
For concrete repairs, the Contractor must submit inspection reports with root cause analysis and carry out approved repairs. For depths greater than 100mm, use micro-concrete. Surface preparation must remove loose coatings, dirt, grease, and mechanically prepare (diamond grinding, shot blasting, scarifying).
Structural modifications and asbestos-containing roofing systems are excluded from ordinary maintenance works and are only conducted following specific instruction by the Employer.
Methodology
Source: Attachment 3 Scope of work Building Maintenance.pdf (unknown)Technical service requirements for leak detection, roof inspection and roof waterproofing: inspect roofs, gutters, flashings, waterproofing; assess roof slopes and ponding; verify gutter sizing; submit inspection reports with root cause analysis; carry out approved repairs; clean and repaint gutters; perform flood/rain penetration testing per SANS 10400-K; provide guarantees; notify of urgent defects. For replacement waterproofing, ensure dead load does not exceed existing by more than 10%, otherwise engage ECSA registered engineer for structural assessment. Submit method statements, QCPs, ITPs, product specs, material data sheets before work.
Quality Management
Source: Attachment 3 Scope of work Building Maintenance.pdfRevision: 1.0Eskom Peaking
Page:
Content . Introduction ............................................................................................................................... 4
2.1 Scope ............................................................................................................................... 4
2.1.1 Purpose ................................................................................................................. 4
2.1.2 Applicability ........................................................................................................... 5
2.1.3 Effective date ......................................................................................................... 5
2.2 Normative/Informative References ................................................................................... 5
2.2.1 Normative .............................................................................................................. 6
2.2.2 Informative............................................................................................................. 6
2.3 Definitions ........................................................................................................................ 6
2.4 Abbreviations ................................................................................................................... 6
2.5 Roles and Responsibilities ............................................................................................... 7
2.6 Process for Monitoring ...................................................................................................... 7
2.7 Related/Supporting Documents ........................................................................................ 7
3.1 General Building Maintenance .......................................................................................... 7
3.2 Building Envelope and Structural Repairs......................................................................... 9
3.2.1 Roofing and Waterproofing .................................................................................... 9
3.2.2 Walls, Masonry and Concrete ................................................................................ 9
3.2.3 Painting and Corrosion Protection ....................................................................... 10
3.3 Doors, Windows and Access Systems ........................................................................... 10
3.4 Flooring and Ceilings ...................................................................................................... 10
3.5 Plumbing, Water and Sewer Systems ............................................................................ 11
3.6 Electrical Building Services ............................................................................................ 12
3.7 Roads and Civil Infrastructure ........................................................................................ 12
3.8 Fencing, Gates and Security Infrastructure ..................................................................... 13
3.9 Fire Protection Infrastructure .......................................................................................... 13
3.10 Defect Specific Work ...................................................................................................... 13
3.10.1 Drakensberg PS .................................................................................................. 13
3.10.2 Ingula PS ............................................................................................................. 13
3.10.3 Gariep PS ............................................................................................................ 14
3.10.4 Vanderkloof PS ................................................................................................... 14
3.10.5 Port Rex PS ......................................................................................................... 14
3.10.6 Gourikwa PS ....................................................................................................... 14
4.1 Leak Detection, Roof Inspection and Roof Waterproofing .............................................. 15
4.2 Painting and Corrosion Protection .................................................................................. 17
4.2.1 Machine Hall Crane beam – Drakensberg PS ..................................................... 19
4.3 Walls, Masonry and Concrete ......................................................................................... 20
4.3.1 General Concrete Repairs ................................................................................... 21
2.7 Related/Supporting Documents
Refer to Section 2.2.
3.1 General Building Maintenance
Planned maintenance
Corrective maintenance
Reactive maintenance
Emergency maintenance
Minor refurbishment works
Minor construction works
Condition assessments
Inspection services
Repair and replacement of defective components
Repair and/ or replace lighting systems
Repair and/ or replace socket outlets
Repair and/ or replace distribution boards
Repair and/ or replace earth leakage units
Repair access control power supplies
Reroute power and control cables
Repair and/ or replace gate motor electrical systems
Repair UPS systems
Perform testing
Issue CoCs where required
3.7 Roads and Civil Infrastructure
4.1 Leak Detection, Roof Inspection and Roof Waterproofing
systems and rainwater disposal systems to determine the source of water ingress.
contribute to water ingress.
Assess roof slopes and identify areas where ponding or pooling water occurs.
Verify the adequacy of gutter and downpipe sizing relative to roof catchment areas.
Submit a detailed inspection report containing findings, photographic evidence, root cause
analysis and proposed remedial measures for acceptance by the Service Manager.
leak-free.
components.
in accordance with Eskom corrosion protection specifications.
and submit the required test documentation.
Provide workmanship and material guarantees for all roof repair and waterproofing works.
Notify the Employer of any additional urgent defects identified during inspections.
Inspection and leak detection
Roof waterproofing
Roof sheeting repairs
Roof tile repairs
Flashing repairs
Fascia board repairs
Barge board repairs
Roof sealing
Gutter replacement
Downpipe replacement
Roof coating systems
Local repairs to exposed roof support elements
Method Statements.
Quality Control Plans (QCPs).
Inspection and Test Plans (ITPs).
Product Specifications.
Method Statements.
Quality Control Plans (QCPs).
Inspection and Test Plans (ITPs).
Product Specifications.
Material Data Sheets.
Method Statements.
Quality Control Plans (QCPs).
Inspection and Test Plans (ITPs).
Product Specifications.
Material Data Sheets.
for acceptance by the Service Manager before commencement of any concrete works.
4.4 Doors, Windows and Access Systems
Method Statements.
Quality Control Plans (QCPs).
Inspection and Test Plans (ITPs).
Product Specifications.
Material Data Sheets.
for acceptance by the Service Manager before commencement of any of the works.
4.5 Flooring and Ceilings
Method Statements,
Quality Control Plans (QCPs),
Inspection and Test Plans (ITPs),
Product Specifications, and
Material Data Sheets.
for acceptance by the Service Manager before commencement of any ceiling and flooring works.
4.5.1 Control Room – Drakensberg PS
provided by the Contractor to the Service Manager for acceptance.
Only accepted and approved repair work is executed thereafter.
It is recommended that the Contractor replaces the entire ceiling panel in the Control and
Inspects the existing concrete substrate
Identifies moisture ingress, if any
Identifies cracking, delamination and spalling
Identifies contamination from oils, grease or chemicals
Measures floor levels where required
Performs moisture content testing where recommended by the coating manufacturer.
Health & Safety
Source: Attachment 3 Scope of work Building Maintenance.pdfRevision: 1.0Eskom Peaking
Page:
4.3.2 Crack Repairs ...................................................................................................... 22
4.4 Doors, Windows and Access Systems ........................................................................... 23
4.5 Flooring and Ceilings ...................................................................................................... 24
4.5.1 Control Room – Drakensberg PS ........................................................................ 26
4.5.2 Floor Tiles (Underground Works – Machine Hall and Valve Hall) –
Drakensberg & Gariep PS ................................................................................... 29
4.6 Plumbing, Water and Sewer Systems ............................................................................ 34
4.7 Electrical Building Services ............................................................................................ 35
4.8 Roads and Civil Infrastructure ........................................................................................ 37
4.8.1 Layerworks and Compaction for Patch Repairs ................................................... 38
4.8.2 Concrete Pavement Repairs ................................................................................ 38
4.9 Stormwater Drains and Culverts Cleaning – Access Roads............................................ 39
4.10 Survey Work ................................................................................................................... 39
4.11 Fencing, Gates and Security Infrastructure ..................................................................... 40
4.12 Fire Protection Infrastructure .......................................................................................... 40
4.13 Contractor’s Procurement of Plant and Materials ............................................................ 41
Acceptance ............................................................................................................................. 41
Revisions ................................................................................................................................ 42
Development Team ................................................................................................................ 42
Acknowledgements ................................................................................................................ 42
Appendix A – Applicable Standards .............................................................................................. 43
maintenance requirements and the identified asset health risks across the stations. Particular focus
will be placed on defects associated with water ingress, waterproofing failures, deteriorated building
finishes, drainage deficiencies, roofing defects, flooring failures, structural deterioration, sewage
infrastructure defects, access systems and building envelope degradation.
Revision: 1.0Basis for Eskom Peaking
Page:
2.2.1 Normative
[1] Occupational Health and Safety Act (Act )
[2] Construction Regulations 2014
[3] SANS 10400 National Building Regulations
[4] Eskom Safety, Health and Environmental Standards
[5] Eskom Civil Engineering Standards
[6] Eskom Maintenance Strategy for Civil Plant
[7] ISO 9001 Quality Management Systems
[8] Applicable Municipal By-laws
[9] Applicable SANS Standards.
2.2.2 Informative
[10] I Buildings System Health Report for Peaking Power Stations
[11] Station Audit Reports
[12] Original Building Designs and Drawings.
2.3 Definitions
completes work within the following minimum timeframes, measured from moment of notification by
the Service Manager as per Table 1 below:
Table 1: Timeframes for Maintenance Categories
Category Response Time (on site) Completion Target
Emergency Maintenance 2 hours Risk eliminated/made
safe same day;
permanent repair per
agreed programme
Reactive Maintenance 48 hours 10 working days, or
per accepted
programme for larger
repairs
Repair roof leaks
Replace damaged roof sheeting
Replace roof tiles
Repair flashings
Repair roof waterproofing systems
Screeding roof slabs
Repair roof penetrations
Repair damaged cladding
Repair or replace gutters
Repair or replace downpipes
Perform roof cleaning
Repair and/ or replace doors
Repair and/ or replace door frames
Repair and/ or replace locks and ironmongery
Repair and/ or replace emergency exit systems
Repair and/ or replace roller shutter doors
Replace glazing and broken windows
Repair and/ or replace blinds
Repair and/ or replace weather seals
Repair and/ or replace floor finishes
Replace damaged carpets
Repair timber floors
Repair and/ or replace raised flooring systems
Repair and/ or replace anti-slip strips
Install ramps, where required.
Service fire extinguishers
Service hose reels
Repair fire doors
Repair fire signage
Maintain fire detection devices
Repair associated building fire protection systems
Water ingress
Roof sheet damage
Ceiling defects
Building waterproofing
Floor defects
Overhead crane/ crawl beams
3.10.2 Ingula PS
Water ingress
Roof defects
Damaged doors
Sewer defects
Cracked walls and deteriorated finishes
Revision: 1.0Basis for Eskom Peaking
Page:
for acceptance by the Service Manager before commencement of any roofing or waterproofing
works.
4.2 Painting and Corrosion Protection
Obtain approved colour swatches from an approved supplier.
Ensure compliance with Eskom Corporate Identity Standards.
Submit product data sheets and Safety Data Sheets (SDS) prior to commencement.
Assess substrate conditions and identify causes of coating failure.
Adjacent surfaces and equipment are protected
Covers, handles and removable fittings are removed where practical
Reinstatement is completed upon completion of the works
Coating application shall comply with manufacturer specifications relating to:
o Coverage rates
o Surface preparation
o Film thickness
o Overcoating intervals
o Environmental conditions
o Uniform in appearance
o Fully bonded
o Free of defects
o Free of contamination
o Applied to the specified coating thickness
maintenance scope and requires separate engineering instructions. The service includes local nonstructural repair of plaster, masonry, cracks, water-damaged finishes, penetrations, retaining-wall
finishes and concrete identified in a Task Order.
Forms a V-shaped groove approximately 10 mm deep.
Cleans the crack thoroughly.
Fills by capillary action with low-viscosity epoxy resin.
Removes excess material after curing.
Grinds and finishes the surface to match surrounding concrete.
External and internal doors
Security doors
Fire-rated doors
Roller shutter doors
Aluminium doors and windows
Timber doors and frames
Steel doors and frames
Window glazing systems
Blinds and window tinting
Door closers
Panic bars and emergency exit mechanisms
Hinges, locks and latches
Access control systems
Magnetic locking systems
Electric strikes
Door seals and weather strips
Revision: 1.0Basis for Eskom Peaking
Page:
Assesses all defective components and submit recommendations to the Service Manager.
Repairs or replaces damaged doors, door frames and associated hardware.
Repairs damaged aluminium window and door systems.
Replaces broken or cracked glazing with equivalent safety glazing where required.
Repairs damaged hinges, rollers, closers and locking mechanisms.
Repairs or replaces weather strips and seals to prevent air and water ingress.
Ensures all windows and doors operate freely and close correctly.
Repairs damaged access control components.
Adjusts and tests magnetic locks and electric strikes.
Repairs roller shutter doors and associated motors.
Maintains the integrity of fire-rated doors and emergency exit systems.
Glass complies with applicable SANS requirements.
Safety glazing is utilised where required.
Existing tinting and shading characteristics are matched as closely as practicable.
All repairs preserve the safety, security, waterproofing and operational performance of the
facility.
raised access floors and associated finishes.
Investigates root causes of floor failures before undertaking repairs,
Assesses defects resulting from movement, moisture, vibration, settlement or water ingress,
Replaces damaged flooring with materials matching existing finishes where reasonably
practicable,
Repairs loose, cracked, lifting or broken tiles,
Repairs damaged timber flooring systems,
Replaces damaged carpets and vinyl flooring,
Removes trip hazards, and
Repairs floor levels where localized settlement has occurred.
Revision: 1.0Basis for Eskom Peaking
Page:
Replaces water-damaged ceiling finishes,
Repairs ceiling suspension systems,
Reinstates access panels and service openings, and
Matches existing ceiling systems.
dimensions as existing - 600mm × 600mm. The finished product must be a continuous floor finish
with no uneven surfaces that could pose a safety hazard. The Contractor must submit specifications
of the new floor which should be in accordance with the latest Eskom Standards for the Ergonomic
required, inlays can be made with different colours to create a pattern on the floor, and it
recommended that the product utilised is linoleum or similar approved.
To define the operator’s workspace more clearly, darker overlays can be positioned around the
operator’s desk. This overlay will typically be charcoal black, to minimise wear and tear and dirt
appearance. The overlays can be removed for cleaning and easily replaced later. The overlays must
have a bevelled edge to reduce unevenness for chair castors.
from non-combustible components and shall consist of a dead flat full-hard steel top sheet,
resistance-welded to a steel bottom section of irregular or regular domed formation. The exterior and
interior surfaces of the access floor panel shall be protected from corrosion by a process of cleaning
and dip phosphate. The core interior of the panel shall be filled with a non-combustible cementitious
compound which will support no less than 90% of the top surface of the panel. The exterior surface
of the panel shall be coated with an epoxy coated finish.
floor shall remain sturdy and firm no matter how many panels are removed for work to be carried out
under the access floor.
4.5.1.5 Finishes
Safety factor = design load
(Failure shall be ductile and not sudden)
Uniformly distributed load per m2: 9.0 kN 13.5 kN 16.5 kN
Maximum deflection on underside 1.00 mm 1.00 mm 1.00 mm
Maximum permanent set on underside 0.25 mm 0.25 mm 0.25 mm
Load dropped onto an area of 25 mm × 25 mm 0.43 kN 0.43 kN 0.43 kN
Maximum permanent set 1.50mm 1.50mm 1.50mm
Important Dates
Source: Attachment 14 SDLI Strategy.pdf (TENDER){"closingDate":"01 April 2023"}
Submission Guidelines
Source: Attachment 14 SDLI Strategy.pdf (TENDER)Submit the completed tender documents, including all required forms and schedules, to the address and by the date and time specified in the tender documentation. Ensure all sections are fully completed and signed. Late submissions will not be accepted.
Returnable Documents
Source: Attachment 14 SDLI Strategy.pdf (TENDER)NOTE: SBD 6.2 Declaration Form and Annex C (Local Content Declaration-Summary Schedule) are therefore mandatory and must be tender returnables if applicable.
Evaluation Criteria
Source: Attachment 14 SDLI Strategy.pdf (TENDER)Price (90/10 or 80/20 system) plus preference points for B-BBEE status level and specific goals. Specific goals include local production and content thresholds for designated sectors (e.g., valves and actuators 70%, pumps and medium voltage motors 70%). SDL&I commitments are evaluated and monitored.
Technical Specifications
Source: Attachment 14 SDLI Strategy.pdf (TENDER)4 ce/gb
Possible training initiatives in relation to the applicable CSDG%:
Skill type / Occupation Eskom target Entry Level Output
1 National ECSA
Diploma/ Candidate
Graduate in Civil Engineering Equivalent Registered
NOTE: Failure by the Contractor/Service Provider/Supplier to meet the CIDB CSDG mandatory %
will render their tender non-responsive. The above-mentioned Skills are a guideline. The actual
skills/trade type may be negotiated. However, expenditure of 0.375% of the Acceptable Contract
Confidential
Quality Management
Source: Attachment 14 SDLI Strategy.pdf (TENDER)Section 5: Reporting and Monitoring
Pricing Schedule
Source: Attachment 14 SDLI Strategy.pdftender response must be separated into its components as per the Price Schedule included with
the tender documents. Local procurement content is total spending minus the imported
component.
Financial Requirements
Source: Attachment 14 SDLI Strategy.pdf (TENDER)No specific financial requirements stated beyond pricing per the Price Schedule. Penalty of 1.5% of contract value for failure to meet SDL&I obligations. Retention of 1.5% of each invoice (excluding VAT) as security for SDL&I obligations.
Compliance Requirements
Source: Attachment 14 SDLI Strategy.pdf (TENDER)Proof of ownership / shareholding (preferably CIPC documentation) inclusive of shareholding
for the fulfilment of all SDL&I Obligations. The retained amounts shall only be released to the
B-BBEE Minimum Level: 0
Points Allocation: 20 points
B-BBEE Details: for Bidders Review Date April 2026
Description/ Scope of Work Provision of Building Maintenance at Gariep Hydro Station
Duration of the Project 60 Months
Section 1: Specific Goals
A maximum of 10/20 points may be awarded to a tenderer for the specific goal specified for the tender.
The points scored for the specific goal must be added to the points scored for price and the total must
be rounded off to the nearest two decimal places. Subject to section 2(1)(f) of the Preferential
Procurement Policy Framework Act, the contract must be awarded to the tenderer scoring the highest
points.
B-BBEE Status Level of Number of points Number of points
Contributor (90/10 system) (80/20 system)
1 10 20
2 9 18
3 6 14
4 5 12
5 4 8
6 3 6
7 2 4
8 1 2
Non-compliant contributor 0 0
NB: The following documents are required to claim preference points,
CIPC affidavit
breakdown
Tenderer failing to provide documentation for the allocation of preference points will not be
disqualified, but’
Section 2: Objective criteria
The inclusion of objective criteria is not mandatory but a condition for contract award. If the tenderer
does not meet objective criteria; it may lead to the second-ranked tenderer being recommended for
award.
Confidential
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with
B-BBEE Requirements
Source: Attachment 14 SDLI Strategy.pdf (TENDER)2.1 Designated Sectors When applicable the following stipulated minimum threshold for Local Production and Content must be achieved in full by the tenderer YES NO a) Is this Commodity or part of it a Designated ☐ ☐ Sector? Please indicate below Designated Components Commodity Components Local Content Steel Products and Steel 100% Cement Cement 100% Electrical and Telecom Cables Cables 90% Valves and Actuators Valves 70% Pumps and Medium Voltage Motors 70%
Health & Safety
Source: Attachment 14 SDLI Strategy.pdfensure their validity:
authorised to depose of an affidavit. (Mark the applicable option).
business address.
as per Statement 004, the percentage of black beneficiaries must be reflected. (No blank spaces to be left).
management account. (Mark the applicable option).
(Financial year end to be stipulated by day/month/year).
supplier status.
the presence of the Commissioner of Oath. Furthermore the Commissioner must also sign and stamp)
commission a sworn affidavit in which they have an interest.
Name of tenderer: ........................................
Tenderer representative: ...............................
Representative signature: .............................
Date: ........................................................
Contractual Terms
Source: Attachment 14 SDLI Strategy.pdf (TENDER)NOTE: Failure by the Contractor/Service Provider/Supplier to meet the CIDB CSDG mandatory % will render their tender non-responsive. The above-mentioned Skills are a guideline. The actual skills/trade type may be negotiated. However, expenditure of 0.375% of the Acceptable Contract Amount in accordance with the CIDB CSDG is a Condition for Contract Award.
Section
Source: Attachment 14 SDLI Strategy.pdfSection 1: Specific Goals
A maximum of 10/20 points may be awarded to a tenderer for the specific goal specified for the tender.
The points scored for the specific goal must be added to the points scored for price and the total must
B-BBEE Status Level of Number of points Number of points
Contributor (90/10 system) (80/20 system)
NB: The following documents are required to claim preference points,
Tenderer failing to provide documentation for the allocation of preference points will not be
Valves and Actuators Valves 70%
Pumps and Medium Voltage Motors 70%
Description
Source: Attachment 4 TSC3.pdf (unknown)PROVISION OF BUILDING AND INFRASTRUCTURE MAINTENANCE SERVICES ON AN 'AS AND WHEN REQUIRED' BASIS AT ESKOM PEAKING SITES FOR A PERIOD OF FIVE YEARS. The service is building and infrastructure maintenance services on an 'as and when required' basis at Eskom Peaking Sites for a period of five years, including planned, preventative, corrective, reactive and emergency maintenance instructed through Task Orders.
Contact Information
Source: Attachment 4 TSC3.pdf (unknown){"name":null,"email":"[email protected]","phone":"011 803 3008","department":null,"address":"n the conditions of contract identified"}
Submission Guidelines
Source: Attachment 4 TSC3.pdf (unknown)Returnable Documents: C1.1 Form of Offer and Acceptance 3, C1.1 Form of Offer & Acceptance, By the representative of the tenderer, deemed to be duly authorised, signing this part of this Form of Offer, This Offer may be accepted by the Employer by signing the Acceptance part of this Form of Offer and
Evaluation Criteria
Source: Attachment 4 TSC3.pdf (unknown)Bidders must complete the Form of Offer and Acceptance (C1.1) and provide Contract Data Part Two (C1.2b). Must submit pricing data (C2.2 price list). Must comply with B-BBEE requirements and notify Eskom of any change in B-BBEE status. Must not cede, delegate or assign rights without written consent. Must comply with ethics provisions (no corrupt, fraudulent, collusive, coercive or obstructive actions). Must be registered with CIDB (registration number required on the Offer form). Must provide securities, bonds, guarantees and proof of insurance as required. Must comply with all applicable laws including health, safety and environmental regulations.
Experience & Qualifications
Source: Attachment 4 TSC3.pdf2 Name:
3 Available from Engineering Contract Strategies Tel 011 803 3008 Fax 086 5391902 or www.ecs.co.za
Part c1 agreements and contract data of 71 c.1.3 Proforma quarantees
ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________
Provision of building and infrastructure maintenance services on an 'as and when required' basis at ESKOM peaking
Sites for a period of five years
Job
Responsibilities:
CV's (and further key person's data including
CVs) are in .
A Priced contract with price list
11.2(12) The price list is in
11.2(19) The tendered total of the Prices is Not applicable, tendered rates contained in C2.2
Part c1 agreements and contract data of 71 c.1.3 Proforma quarantees
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Provision of building and infrastructure maintenance services on an 'as and when required' basis at ESKOM peaking
Sites for a period of five years
Part 2: pricing data
TSC3 Option A
Document Title No of
reference pages
C2.1 Pricing assumptions: Option A 4
C2.2 The price list 10
Part c2 pricing data of 71 tsc3 option a
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Provision of building and infrastructure maintenance services on an 'as and when required' basis at ESKOM peaking
Sites for a period of five years
C2.1 Pricing assumptions: Option A
How the service is priced
The contract uses main Option A: Priced contract with price list together with secondary Option X19: Task
Order.
The Price List in C2.2 is a schedule of tendered rates, lump sums and percentages used for pricing work
instructed through Task Orders and for the contract-level items expressly identified in the Price List.
No Employer quantities are stated in the Price List at tender stage. The Tenderer completes the applicable
Rate, Lump Sum or Fee fields in the Price List.
The inclusion of an item in the Price List does not constitute an instruction to carry out the work and does not
guarantee any minimum quantity, frequency, duration, number of Task Orders or value of work during the
service period.
Except for contract-level items expressly identified in the Price List, the Contractor is paid only for work
instructed through a Task Order and Provided in accordance with the Service Information and the applicable
Task Order.
Pricing of Task Orders
When a Task Order is prepared, the applicable work is priced using the tendered rates and percentages
contained in C2.2.
The priced list for a Task Order identifies, as applicable:
a. the relevant Price List item number and description;
b. the applicable unit;
c. the quantity, duration or other measurable unit applicable to the Task;
d. the applicable tendered rate; and
e. the resulting Price.
Where an applicable tendered rate exists, the Price for the item is calculated by multiplying the applicable
quantity or duration by the tendered rate.
Where an instructed item is not covered by an applicable tendered rate or Cost-Plus item, the item is priced
and assessed in accordance with Option X19 and the applicable provisions of the conditions of contract.
No work outside an issued Task Order is payable merely because a rate for that work appears in the Price
List.
Part c2 pricing data of 71 c2.1 Option a pricing assumptions
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Provision of building and infrastructure maintenance services on an 'as and when required' basis at ESKOM peaking
Sites for a period of five years
Function of the Price List
Information in the Price List is not Service Information.
The Contractor Provides the Service in accordance with:
a. the conditions of contract;
b. the Service Information;
c. Annexure C3.1-E: Engineering Technical Scope and Requirements;
d. the applicable drawings and technical information;
e. the Accepted Plan;
f. the accepted Task Order programme;
g. accepted quality and technical submissions; and
h. the applicable Task Order.
The descriptions in the Price List are pricing descriptions and do not prescribe the Contractor’s method,
sequence, number of personnel, resource allocation, Equipment, working-hour arrangements or
Subcontracting arrangements.
The Contractor determines the resources required to Provide the Service and remains responsible for
complying with all requirements of the contract.
Rates
Unless the Price List expressly states otherwise, each tendered rate includes everything necessary and
incidental to complete the item described in accordance with the contract, including, as applicable:
a. labour and employment-related costs;
b. normal supervision associated with carrying out the activity;
c. administration and coordination associated with the activity;
d. ordinary hand tools and Equipment normally required for the activity;
e. ordinary personal protective equipment;
f. ordinary consumables associated with the activity;
g. preparation, protection, housekeeping and ordinary reinstatement associated with the activity;
h. Task-specific Method Statements, Quality Control Plans and Inspection and Test Plans required for the
activity;
i. applicable inspections, testing, commissioning, records, certificates and warranties;
j. Contractor overheads; and
k. profit.
An item is not paid more than once.
Where a composite activity rate is used, the Contractor is not additionally paid for labour, supervision,
Equipment, travel, consumables, Plant and Materials or other resources already included in that activity rate
Part c2 pricing data of 71 c2.1 Option a pricing assumptions
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Provision of building and infrastructure maintenance services on an 'as and when required' basis at ESKOM peaking
Sites for a period of five years
unless the applicable Task Order expressly identifies the resource as separately payable and the Price List
permits separate payment.
A cost which is included in one tendered rate is not recovered again through another Price List item, Cost-
Plus item, labour rate, Equipment rate, mobilisation item or other pricing mechanism
Separately payable labour, supervision and Equipment
Labour, management, supervision and Contractor’s Equipment rates stated in the Price List are used only
where the applicable resource is expressly identified as separately payable in the relevant Task Order.
These rates may be used for variable, additional or unforeseen work for which an appropriate composite
activity rate is not available.
A labour, supervision or Equipment rate is not separately payable where the applicable cost is already
included in a composite activity rate or another Price List item.
Labour rates are paid only for actual authorised productive time, or other time expressly identified as payable
in the Task Order, supported by the records required by the Service Information.
Normal supervision associated with carrying out an activity is included in the applicable activity or labour rate
unless the Task Order expressly identifies a dedicated supervisory, management, technical, health and
safety or quality resource as separately payable.
Contractor’s Equipment rates apply only where the Equipment is expressly identified as separately payable
in the Task Order.
Unless the applicable Price List item states otherwise, an Equipment rate includes the cost of providing,
operating, maintaining, inspecting and controlling the Equipment for the authorised period of use.
Ordinary hand tools and Equipment normally required by a person to carry out an activity are included in the
applicable activity or labour rate and are not separately payable
Travel, accommodation and subsistence
The station-specific mobilisation rate includes the travel and transport expressly stated under the
mobilisation-rate basis and is not paid again under another Price List item.
Accommodation and subsistence are separately payable only where:
a. applicable rates are stated in the Price List;
b. the relevant Task Order expressly identifies them as separately payable; and
c. the authorised number of persons and period are stated or subsequently accepted by the Service
Manager.
Accommodation and subsistence are not payable merely because the Contractor elects to deploy personnel
who reside away from the applicable Peaking site.
Part c2 pricing data of 71 c2.1 Option a pricing assumptions
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Provision of building and infrastructure maintenance services on an 'as and when required' basis at ESKOM peaking
Sites for a period of five years
Additional travel, accommodation, subsistence or mobilisation arising from the Contractor’s own resource
planning, replacement of personnel, procurement arrangements, correction of Defects, failure of Contractor’s
Equipment or failure to complete an instructed attendance is not separately payable.
A cost included in a mobilisation rate, activity rate, labour rate or other Price List item is not recovered again
as travel, accommodation or subsistence
Application of Cost-Plus items
A Cost-Plus item is used only where the required Plant and Materials, part, spare or specialist external
service:
a. is required for an instructed Task;
b. is not already included in an applicable tendered rate; and
c. has been accepted by the Service Manager for procurement under the applicable Cost-Plus item,
except where prior acceptance is impracticable due to an authorised Emergency Maintenance Task.
The applicable Direct Fee or Subcontracted Fee is applied to the accepted net cost excluding VAT and after
deduction of all discounts, rebates, credits and similar benefits.
No additional Fee, handling charge, procurement charge, administration charge or other markup is added to
a cost already subject to the applicable Direct Fee or Subcontracted Fee.
Labour, supervision, Contractor’s Equipment, mobilisation, travel, accommodation, subsistence or other
resources which are separately payable under another Price List item are not included again in the Cost-Plus
calculation.
A cost already included in another tendered rate is not recoverable again through a Cost-Plus item.
Price adjustment
Option X1 applies to the tendered rates, lump sums and other adjustable Prices in the Price List in
accordance with the Contract Data.
Option X1 does not apply to verified net supplier, Subcontractor or third-party costs reimbursed under a
Cost-Plus item because those costs are assessed using the accepted current net cost.
The tendered Direct Fee and Subcontracted Fee percentages applied to Cost-Plus items remain the
percentages tendered unless changed in accordance with the conditions of contract.
.
Part c2 pricing data of 71 c2.1 Option a pricing assumptions
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Provision of building and infrastructure maintenance services on an 'as and when required' basis at ESKOM peaking
Sites for a period of five years
C2.2 the price list
Tendered Rate /
Item Category Description Unit
Fee (R excl. VAT)
Contract Preparation and submission of the first overall service plan Lump
A1
requirements required by the Service Information. Sum
Contract Preparation and submission of the initial contract Quality Lump
A2
requirements Plan required by the Service Information. Sum
Initial contract health, safety and access documentation Per
Contract
A3 required before Providing the Service, including applicable Power
Qualifications:
Experience:
2 Name:
3 Available from Engineering Contract Strategies Tel 011 803 3008 Fax 086 5391902 or www.ecs.co.za
Part c1 agreements and contract data of 71 c.1.3 Proforma quarantees
ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________
Qualifications:
Experience:
CV's (and further key person's data including
CVs) are in .
Quality Management
Source: Attachment 4 TSC3.pdfassistance that the Employer is able to provide for the purpose of contesting any such
claim or action.
Z13.10.3 Should it be held in any such action that any such protected rights have been infringed, as
definitely stated by a judgment of the court before which the action is brought, the
incidental to complete the item described in accordance with the contract, including, as applicable:
a. labour and employment-related costs;
b. normal supervision associated with carrying out the activity;
c. administration and coordination associated with the activity;
d. ordinary hand tools and Equipment normally required for the activity;
e. ordinary personal protective equipment;
f. ordinary consumables associated with the activity;
g. preparation, protection, housekeeping and ordinary reinstatement associated with the activity;
h. Task-specific Method Statements, Quality Control Plans and Inspection and Test Plans required for the
activity;
i. applicable inspections, testing, commissioning, records, certificates and warranties;
j. Contractor overheads; and
k. profit.
C1 inspection report, photographic evidence where authorised, No.
waterproofing
root-cause assessment and proposed remedial measures.
Pricing Schedule
Source: Attachment 4 TSC3.pdfContents: No of
pages
Part C1 Agreements & Contract Data 17
Part C2 Pricing Data 14
Part C3 Scope of Work 35
CONTRACT No. [Insert at award stage]
Tsc3 of 71 cover page
ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER _________
Value Added Tax @ 15% is
The offered total of the amount due inclusive of VAT is1 Rates Based
(in words) Rates Based
Part C1 Agreements and Contract Data, (which includes this Form of Offer and Acceptance)
Part C2 Pricing Data
Part C3 Scope of Work: Service Information
and drawings and documents (or parts thereof), which may be incorporated by reference into the above
listed Parts.
11.2(12) The price list is in
11.2(19) The tendered total of the Prices is Not applicable, tendered rates contained in C2.2
Part c1 agreements and contract data of 71 c.1.3 Proforma quarantees
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Part 2: pricing data
TSC3 Option A
reference pages
C2.1 Pricing assumptions: Option A 4
C2.2 The price list 10
Part c2 pricing data of 71 tsc3 option a
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
C2.1 Pricing assumptions: Option A
The Price List in C2.2 is a schedule of tendered rates, lump sums and percentages used for pricing work
instructed through Task Orders and for the contract-level items expressly identified in the Price List.
Part c2 pricing data of 71 c2.1 Option a pricing assumptions
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
a. the conditions of contract;
b. the Service Information;
c. Annexure C3.1-E: Engineering Technical Scope and Requirements;
d. the applicable drawings and technical information;
e. the Accepted Plan;
f. the accepted Task Order programme;
g. accepted quality and technical submissions; and
h. the applicable Task Order.
The descriptions in the Price List are pricing descriptions and do not prescribe the Contractor’s method,
sequence, number of personnel, resource allocation, Equipment, working-hour arrangements or
Part c2 pricing data of 71 c2.1 Option a pricing assumptions
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Labour, management, supervision and Contractor’s Equipment rates stated in the Price List are used only
where the applicable resource is expressly identified as separately payable in the relevant Task Order.
a. applicable rates are stated in the Price List;
b. the relevant Task Order expressly identifies them as separately payable; and
c. the authorised number of persons and period are stated or subsequently accepted by the Service
who reside away from the applicable Peaking site.
Part c2 pricing data of 71 c2.1 Option a pricing assumptions
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Option X1 applies to the tendered rates, lump sums and other adjustable Prices in the Price List in
accordance with the Contract Data.
Option X1 does not apply to verified net supplier, Subcontractor or third-party costs reimbursed under a
percentages tendered unless changed in accordance with the conditions of contract.
.
Part c2 pricing data of 71 c2.1 Option a pricing assumptions
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
A16 call-out
mobilisation – Station, including arrangements necessary to meet the
Part c2 pricing data of 71 c2.2 Option a pricing list
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
C6 Screed roof slab to required falls or repair local roof screed. m2
waterproofing
C7 Roofing / Repair and seal roof penetration. No.
Part c2 pricing data of 71 c2.2 Option a pricing list
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
E6 crane m3
deterioration.
infrastructure
F1 Walls / Repair damaged plaster, including preparation and m2
Part c2 pricing data of 71 c2.2 Option a pricing list
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
I3 Repair or replace valve. No.
water / sewer
Part c2 pricing data of 71 c2.2 Option a pricing list
Financial Requirements
Source: Attachment 4 TSC3.pdf (unknown)Payment Terms: payment certificate from the Service Manager in terms of core
clause 51.1, the Contractor provides the Employer with a tax invoice in accordance with the
Employer's procedures stated in the Service Information, showing the amount due for payment
equal to that stated in the payment certificate.
Z7.2 If the Contractor does not provide a tax invoice in the form and
Compliance Requirements
Source: Attachment 4 TSC3.pdf (unknown)statutory appointments and safety-file documentation. Station Contract Final contract close-out and handover of required records, A4 close-out requirements warranties, certificates and Employer-provided items. Mobilisation – Mobilisation to Drakensberg Power Station for a Planned, A5 call-out Drakensberg Corrective or Reactive Maintenance Task. Emergency Emergency Maintenance mobilisation to Drakensberg A6 mobilisation – Power Station, including arrangements necessary to meet call-out Drakensberg the contractual emergency response requirement. Mobilisation – Mobilisation to Ingula Pumped Storage Scheme for a A7 call-out Ingula Planned, Corrective or Reactive Maintenance Task. Emergency Emergency Maintenance mobilisation to Ingula Pumped A8 mobilisation – Storage Scheme, including arrangements necessary to call-out Ingula meet the contractual emergency response requirement. Mobilisation – Mobilisation to Vanderkloof Power Station for a Planned, A9 call-out Vanderkloof Corrective or Reactive Maintenance Task. Emergency Emergency Maintenance mobilisation to Vanderkloof A10 mobilisation – Power Station, including arrangements necessary to meet call-out Vanderkloof the contractual emergency response requirement. Mobilisation – Mobilisation to Gariep Power Station for a Planned, A11 call-out Gariep Corrective or Reactive Maintenance Task. Emergency Emergency Maintenance mobilisation to Gariep Power A12 mobilisation – Station, including arrangements necessary to meet the call-out Gariep contractual emergency response requirement. Mobilisation – Mobilisation to Port Rex Power Station for a Planned, A13 call-out Port Rex Corrective or Reactive Maintenance Task. Emergency Emergency Maintenance mobilisation to Port Rex Power A14 mobilisation – Station, including arrangements necessary to meet the call-out Port Rex contractual emergency response requirement. Mobilisation – Mobilisation to Gourikwa Power Station for a Planned, A15 call-out Gourikwa Corrective or Reactive Maintenance Task. Emergency Emergency Maintenance mobilisation to Gourikwa Power A16 call-out mobilisation – Station, including arrangements necessary to meet the PART C2 PRICING DATA OF 71 C2.2 OPTION A PRICING LIST ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________ PROVISION OF BUILDING AND INFRASTRUCTURE MAINTENANCE SERVICES ON AN 'AS AND WHEN REQUIRED' BASIS AT ESKOM PEAKING SITES FOR A PERIOD OF FIVE YEARS Gourikwa contractual emergency response requirement. Condition assessment and inspection of a building or Inspection / B1 defined infrastructure area, including findings and No.
B-BBEE Details: authority to bind
the Contractor on their behalf.
Z2.3 The Contractor does not alter the composition of the joint venture, consortium or other
unincorporated grouping of two or more persons without the consent of the Employer having
been given to the Contractor in writing.
Part c1 agreements and contract data of 71 c.1.2A Contract data part 1
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Provision of building and infrastructure maintenance services on an 'as and when required' basis at ESKOM peaking
Sites for a period of five years
Z3 Change of Broad Based Black Economic Empowerment (B-BBEE) status
Z3.1 Where a change in the Contractor’s legal status, ownership or any other change to his business
composition or business dealings results in a change to the Contractor’s B-BBEE status, the
Contractor notifies the Employer within seven days of the change.
Z3.2 The Contractor is required to submit an updated verification certificate and necessary
supporting documentation confirming the change in his B-BBEE status to the Service Manager
within thirty days of the notification or as otherwise instructed by the Service Manager.
Z3.3 Where, as a result, the Contractor’s B-BBEE status has decreased since the Contract Date the
Employer may either re-negotiate this contract or alternatively, terminate the Contractor’s
obligation to Provide the Service.
Z3.4 Failure by the Contractor to notify the Employer of a change in its B-BBEE status may
constitute a reason for termination. If the Employer terminates in terms of this clause, the
procedures on termination are P1, P2 and P4 as stated in clause 92, and the amount due is A1
and A3 as stated in clause 93.
Z4 Confidentiality
Z4.1 The Contractor does not disclose or make any information arising from or in c
Health & Safety
Source: Attachment 4 TSC3.pdfsignature of Date
witness
Note: If a tenderer wishes to submit alternative tenders, use another copy of this Form of Offer and
including planned, preventative, corrective,
reactive and emergency maintenance instructed
through Task Orders.
11.2(14) The following matters will be included in
the Risk Register
concealed services/incomplete asset
information;
11.2(15) The Service Information is in Part C3: Scope of Work, C3.1 Employer’s
Service Information, including Annexure C3.1-E:
service period, requires the prior written consent of the Service Manager. All rights in and to all
such images vests exclusively in the Employer.
Z4.5 The Contractor ensures that all his subcontractors abide by the undertakings in this clause.
Z5 Waiver and estoppel: Add to core clause 12.3:
Z5.1 Any extension, concession, waiver or relaxation of any action stated in this contract by the
not give rise to an estoppel unless the Parties agree otherwise and confirm such agreement in
writing.
Z6 Health, safety and the environment: Add to core clause 27.4
Part c1 agreements and contract data of 71 c.1.2A Contract data part 1
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Z6.1 The Contractor undertakes to take all reasonable precautions to maintain the health and safety
of persons in and about the execution of the service. Without limitation the Contractor:
provided for under the Construction Regulations 2014 (promulgated under the Occupational
Health & Safety Act ) (“the Construction Regulations”) for the Affected Property;
proper compliance with the Construction Regulations, all applicable health & safety laws
and regulations and the health and safety rules, guidelines and procedures provided for in
this contract and generally for the proper maintenance of health & safety in and about the
execution of the service; and
regulations published in GNR February 2002, under the Occupational Health and Safety
Act, 1993 (Act ) (“Asbestos Regulations”). The OEL for asbestos is 0.2 regulated
asbestos fibres per millilitre of air as a 4-hour TWA, averaged over any continuous period of four
hours, and the short term exposure limit of 0.6 regulated asbestos fibres per millilitre of air as a 10-
minute TWA, averaged over any 10 minutes, measured in accordance with HSG248 and
monitored according to HSG173 and OESSM.
Z14.2 Upon written request by the Contractor, the Employer certifies that these conditions prevail. All
measurements and reporting are effected by an independent, competent, and certified
occupational hygiene inspection body, i.e. a SANAS accredited and Department of Employment
and Labour approved AAIA. The Contractor may perform Parallel Measurements and related
control measures at the Contractor’s expense. For the purposes of compliance the results
generated from Parallel Measurements are evaluated only against South African statutory limits as
detailed in clause Z14.1. Control measures conform to the requirements stipulated in the AAIA-
approved asbestos work plan.
Z14.3 The Employer manages asbestos and ACM according to the Standard.
Z14.4 In the event that any asbestos is identified while Providing the Services, a risk assessment is
conducted and if so required, with reference to possible exposure to an airborne concentration of
Part c1 agreements and contract data of 71 c.1.2A Contract data part 1
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
statement however other clauses may also use the same data.
selected. Click on the form field once and type in the data. Otherwise complete by hand and in ink.
unless the Task Order expressly identifies a dedicated supervisory, management, technical, health and
safety or quality resource as separately payable.
Contractor’s Equipment rates apply only where the Equipment is expressly identified as separately payable
in the Task Order.
service:
a. is required for an instructed Task;
b. is not already included in an applicable tendered rate; and
c. has been accepted by the Service Manager for procurement under the applicable Cost-Plus item,
except where prior acceptance is impracticable due to an authorised Emergency Maintenance Task.
A3 required before Providing the Service, including applicable Power
requirements
statutory appointments and safety-file documentation. Station
C3 compatible replacement sheeting, fixings, laps and local m2
waterproofing
weatherproofing.
G7 m2
windows / applicable safety requirements.
Part c2 pricing data of 71 c2.2 Option a pricing list
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Environmental
Source: Attachment 4 TSC3.pdfguidelines and procedures otherwise provided for under this contract and ensures that his
Subcontractors, employees and others under the Contractor’s direction and control,
likewise observe and comply with the foregoing.
Z6.2 The Contractor, in and about the execution of the service, complies with all applicable
environmental laws and regulations and rules, guidelines and procedures otherwise provided
for under this contract and ensures that his Subcontractors, employees and others under the
Contractor’s direction and control, likewise observe and comply with the foregoing.
Z7 Provision of a Tax Invoice and interest. Add to core clause 51
Z7.1 Within one week of receiving a payment certificate from the Service Manager in terms of core
clause 51.1, the Contractor provides the Employer with a tax invoice in accordance with the
if applicable.
Z14.6 The Contractor continues to Provide the Services, without additional control measures presented,
on presentation of Safe Levels. The contractually agreed dates to Provide the Services, including
the Completion Date, are adjusted accordingly. The contractually agreed dates are extended by
the notification periods required by regulations 3 and 21 of the Asbestos Regulations, 2001.
Z14.7 Any removal and disposal of asbestos, asbestos containing materials and waste, is done by a
registered asbestos contractor, instructed by the Employer at the Employer’s expense, and
conducted in line with South African legislation.
Part c1 agreements and contract data of 71 c.1.2A Contract data part 1
ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________
Contractual Terms
Source: Attachment 4 TSC3.pdfLoss of or damage caused by The replacement cost where not covered by the
the Contractor to the Employer’s insurance.
Employer’s property
The Employer’s policy deductible as at Contract
Date, where covered by the Employer’s insurance.
Loss of or damage to Plant and The replacement cost where not covered by the
Materials Employer’s insurance.
The Employer’s policy deductible as at Contract
Date, where covered by the Employer’s insurance.
Loss of or damage to The replacement cost where not covered by the
Equipment Employer’s insurance.
The Employer’s policy deductible as at Contract
Date, where covered by the Employer’s insurance.
The Contractor’s liability for Loss of or damage to property
loss of or damage to property The replacement cost
(except the Employer’s
property, Plant and Materials
and Equipment) and liability for Bodily injury to or death of a person
bodily injury to or death of a The amount required by the applicable law.
person (not an employee of the
Contractor) arising from or in
connection with the
Contractor’s Providing the
Service
Liability for death of or bodily The amount required by the applicable law
injury to employees of the
Contractor arising out of and in
the course of their employment
in connection with this contract
Z __12.2 Replace core clause 86 with the following:
Insurance 86
by the
Employer
86.1 The Employer provides the insurances stated in the Insurance Table B
Part c1 agreements and contract data of 71 c.1.2A Contract data part 1
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Provision of building and infrastructure maintenance services on an 'as and when required' basis at ESKOM peaking
Sites for a period of five years
Insurance table b
Insurance against or name Minimum amount of cover or minimum lim
of policy of indemnity
Assets All Risk Per the insurance policy document
Contract Works insurance Per the insurance policy document
Environmental Liability Per the insurance policy document
General and Public Liability Per the insurance policy document
Transportation (Marine) Per the insurance policy document
Motor Fleet and Mobile Plant Per the insurance policy document
Terrorism Per the insurance policy document
Cyber Liability Per the insurance policy document
Nuclear Material Damage and Per the insurance policy document
Business Interruption
Nuclear Material Damage Per the insurance policy document
Terrorism
Z13 Intellectual Property – Eskom owning Intellectual Property
“Intellectual means (a) patents, trade marks, service marks, rights in designs, trade names, trade secrets, know
Property” copyrights and topography rights, in each case whether registered or not; (b) applications for registrat
any of them; (c) rights under licences and consents in relation to any of them; (d) all forms of protection
similar nature or having equivalent or similar effect to any of them which may subsist anywhere in the wo
“Backgroun means any and all Intellectual Property rights that are not Foreground Intellectual Property,
d Intellectual and are owned or controlled by the relevant party or licensed to the relevant party prior to
Property" or outside of the services but required for the purposes of the services .
“Foreground means all Intellectual Property rights and other matter capable of being the subject of
Intellectual intellectual property rights that is conceived, first reduced to practice or writing or
Property” developed in whole or in substantial part in the course of the execution of the services
and rights which are developed substantially as a result of the services . Any services
that will be developed, changed, modified and/or improved specifically for the Purposes will
be Foreground Intellectual Property. Any data or any other information relating to
Employer’s proprietary information generated from the use of the Contractor’s Background
Intellectual Property.
Z13.1 The Contractor retains ownership of all Background Intellectual Property rights made by or
on behalf of the Contractor as part of the services in information or material it uses in
carrying out the services .
Z13.2 All Foreground Intellectual Property rights, contained in any developed materials which are
created by the Contractor or on behalf of the Contractor, for the purposes of and in support
of the execution of the services (Employer’s IP) vest with the Employer.
Z13.3 Any data or any other information relating to Employer’s proprietary information generated
from the use of the Contractor’s Background Intellectual Property, the copyright therein
shall be owned by the Employer.
Z13.4 The Contractor acknowledges that all rights, title, and interest in and to the Foreground
Intellectual Property that may result or originate from or be developed in execution of the
services vests in the Employer and that the Contractor has no claim of any nature in and to
Part c1 agreements and contract data of 71 c.1.2A Contract data part 1
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Provision of building and infrastructure maintenance services on an 'as and when required' basis at ESKOM peaking
Sites for a period of five years
the Foreground Intellectual Property.
Z13.5 The Contractor ensures that a copyright notice is incorporated or embossed or labelled on
the Foreground Intellectual Property, where the Employer is reflected as the owner of the
Foreground Intellectual Property.
Z13.6 The Contractor is obliged to provide Foreground Intellectual Property manufacturing
documents, designs, processes and/or specifications to the Employer before/on the
completion date.
Z13.7 The Contractor procures that each Sub-Contractor executes all and any services , and
takes all and any other actions as may be required, in order to give effect to this
Agreement.
Z13.8 The Employer retains all Background Intellectual Property rights in all documents made by
or on behalf of the Employer including all documents and requirements provided prior to or
during the execution of the services . The Contractor does not, without the written
consent, of the Employer, copy, use or issue to a third party any of the Employer’s
Background Intellectual Property documents and requirements except for the purposes of
executing the services .
Z13.9 Either party procures that any third party executes confidentiality undertakings not to
disclose to any other third parties, any of the Employer’s Background Intellectual Property
and IP documents and requirements at all, in respect of the Employer, or the Background
Intellectual Property, in respect of the Contractor.
Z13.10 Third Party Claims:
Z13.10.1 In the event of any claims being made or actions brought against the Employer, on the
ground that the Contractor infringed any patent, trade mark or copyright, the Contractor is
notified thereof and at its own expense, conducts all negotiations in consultation with the
Employer for the settlement of the claim and litigation that may arise from such alleged
infringement, provided that the Employer will not bear any financial burden or losses.
Z13.10.2 Save where the Contractor fails to take over the conduct of the negotiation or litigation
within a reasonable time of the notification of the alleged infringement, the Employer does
not make any admission which might be prejudicial to the Contractor’s position. The
Employer, at the request and the cost of the Contractor affords it all reasonable technical
assistance that the Employer is able to provide for the purpose of contesting any such
claim or action.
Z13.10.3 Should it be held in any such action that any such protected rights have been infringed, as
definitely stated by a judgment of the court before which the action is brought, the
Contractor, at its own expense and in consultation with the Employer, either:
a. procures for Employer the right to continue to use the affected item or design, or
b. replaces the said affected item or design with a non-infringing item, or
c. provides a design of equivalent quality or modify such affected item or design so as
to make it non-infringing without affecting the quality.
Z13.10.4 Notwithstanding anything contained in this contract, the foregoing sets forth the entire
responsibility of Contractor with respect to claims relating to infringement.
Z13.10.5 Where it is alleged that the Employer has committed an infringement as intended vis-à-vis
the Contractor as set out in the third party intellectual property infringement clause, the
Employer has the same rights and obligations as the Contractor, mutatis mutandis, as
regards such alleged infringement.
Z13.10.6 The Contractor herewith indemnifies the Employer and undertakes to keep the Employer
indemnified against all claims of whatsoever nature, real or imagined, which may be made
against the Employer arising from the infringement of any third party intellectual property
rights.
Part c1 agreements and contract data of 71 c.1.2A Contract data part 1
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Provision of building and infrastructure maintenance services on an 'as and when required' basis at ESKOM peaking
Sites for a period of five years
Z14 Asbestos
For the purposes of this Z-clause, the following definitions apply:
AAIA means approved asbestos inspection authority.
ACM means asbestos containing materials.
AL means action level, i.e. a level of 50% of the OEL, i.e. 0.1 regulated asbestos fibres
per ml of air measured over a 4 hour period. The value at which proactive actions is
required in order to control asbestos exposure to prevent exceeding the OEL.
Ambient Air means breathable air in area of work with specific reference to breathing zone, which
is defined to be a virtual area within a radius of approximately 30cm from the nose
inlet.
Compliance means compliance sampling used to assess whether or not the personal exposure of
Monitoring workers to regulated asbestos fibres is in compliance with the Standard’s requirements
for safe processing, handling, storing, disposal and phase-out of asbestos and
asbestos containing material, equipment and articles.
OEL means occupational exposure limit.
Parallel means measurements performed in parallel, yet separately, to existing measurements
Measurements to verify validity of results.
Safe Levels means airborne asbestos exposure levels conforming to the Standard’s requirements
for safe processing, handling, storing, disposal and phase-out of asbestos and
asbestos containing material, equipment and articles.
Standard means the Employer’s Asbestos Standard 32-303: Requirements for Safe Processing,
Handling, Storing, Disposal and Phase-out of Asbestos and Asbestos Containing
Material, Equipment and Articles.
SANAS means the South African National Accreditation System.
TWA means the average exposure, within a given workplace, to airborne asbestos fibres,
normalised to the baseline of a 4 hour continuous period, also applicable to short term
exposures, i.e. 10-minute TWA.
Z14.1 The Employer ensures that the Ambient Air in the area where the Contractor will Provide the
Services conforms to the acceptable prescribed South African standard for asbestos, as per the
regulations published in GNR February 2002, under the Occupational Health and Safety
Act, 1993 (Act ) (“Asbestos Regulations”). The OEL for asbestos is 0.2 regulated
asbestos fibres per millilitre of air as a 4-hour TWA, averaged over any continuous period of four
hours, and the short term exposure limit of 0.6 regulated asbestos fibres per millilitre of air as a 10-
minute TWA, averaged over any 10 minutes, measured in accordance with HSG248 and
monitored according to HSG173 and OESSM.
Z14.2 Upon written request by the Contractor, the Employer certifies that these conditions prevail. All
measurements and reporting are effected by an independent, competent, and certified
occupational hygiene inspection body, i.e. a SANAS accredited and Department of Employment
and Labour approved AAIA. The Contractor may perform Parallel Measurements and related
control measures at the Contractor’s expense. For the purposes of compliance the results
generated from Parallel Measurements are evaluated only against South African statutory limits as
detailed in clause Z14.1. Control measures conform to the requirements stipulated in the AAIA-
approved asbestos work plan.
Z14.3 The Employer manages asbestos and ACM according to the Standard.
Z14.4 In the event that any asbestos is identified while Providing the Services, a risk assessment is
conducted and if so required, with reference to possible exposure to an airborne concentration of
Part c1 agreements and contract data of 71 c.1.2A Contract data part 1
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Provision of building and infrastructure maintenance services on an 'as and when required' basis at ESKOM peaking
Sites for a period of five years
above the AL for asbestos, immediate control measures are implemented and relevant air
monitoring conducted in order to declare the area safe.
Z14.5 The Contractor’s personnel are entitled to stop working and leave the contaminated area forthwith
until such time that the area of concern is declared safe by either Compliance Monitoring or an
AAIA approved control measure intervention, for example, per the emergency asbestos work plan,
if applicable.
Z14.6 The Contractor continues to Provide the Services, without additional control measures presented,
on presentation of Safe Levels. The contractually agreed dates to Provide the Services, including
the Completion Date, are adjusted accordingly. The contractually agreed dates are extended by
the notification periods required by regulations 3 and 21 of the Asbestos Regulations, 2001.
Z14.7 Any removal and disposal of asbestos, asbestos containing materials and waste, is done by a
registered asbestos contractor, instructed by the Employer at the Employer’s expense, and
conducted in line with South African legislation.
Part c1 agreements and contract data of 71 c.1.2A Contract data part 1
ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________
Provision of building and infrastructure maintenance services on an 'as and when required' basis at ESKOM peaking
Sites for a period of five years
C1.2 Contract Data
Part two - Data provided by the Contractor
[Instructions to the contract compiler: (delete this notes before issue to tenderers with an enquiry)
Whenever a cell is shaded in the left hand column it denotes this data is optional and would be required in
relation to the option selected. In the event that the option is not required select and delete the whole row.]
Notes to a tendering contractor:
Guidance Notes (TSC3-GN)3 in order to understand the implications of this Data which the tenderer
is required to complete.
statement however other clauses may also use the same data.
selected. Click on the form field once and type in the data. Otherwise complete by hand and in ink.
Completion of the data in full, according to Options chosen, is essential to create a complete contract.
Clause Statement Data
10.1 The Contractor is (Name):
Address
Tel No.
Fax No.
11.2(8) The direct fee percentage is Direct Fee as stated in Contract Data Part Two
%
The subcontracted fee percentage is Subcontracted Fee as stated in Contract Data
Part Two. %
11.2(14) The following matters will be included in
the Risk Register
11.2(15) The Service Information for the
Contractor’s plan is in:
21.1 The plan identified in the Contract Data is
contained in:
24.1 The key people are:
1 Name:
Job:
Responsibilities:
of Deviations (if any), contact the Employer’s agent (whose details are given in the Contract Data) to arrange
the delivery of any securities, bonds, guarantees, proof of insurance and any other documentation to be
provided in terms of the conditions of contract identified in the Contract Data at, or just after, the date this
agreement comes into effect. Failure to fulfil any of these obligations in accordance with those terms shall
constitute a repudiation of this agreement.
clauses and the clauses for main Option:
A: Priced contract with price list
dispute resolution Option W1: Dispute resolution procedure
and secondary Options
X1: Price adjustment for inflation
X2 Changes in the law
X17: Low service damages
X19: Task Order
Z: Additional conditions of contract
of the NEC3 Term Service Contract April
20132 (tsc3)
10.1 The Employer is (name): Eskom Holdings SOC Ltd (reg no:
2002/015527/30), a state owned company
incorporated in terms of the company laws of
the Republic of South Africa
51.1 The currency of this contract is the South African Rand
51.2 The period within which payments are
made is Four (4) weeks after the assessment date.
51.4 The interest rate is the publicly quoted prime rate of interest
(calculated on a 365 day year) charged by from
time to time by the Standard Bank of South
Africa Limited (as certified, in the event of any
dispute, by any manager of such bank, whose
appointment it shall not be necessary to prove)
for amounts due in Rands and
(ii) the LIBOR rate applicable at the time for
amounts due in other currencies. LIBOR is the
6 month London Interbank Offered Rate quoted
under the caption “Money Rates” in The Wall
no rate is quoted for the currency in question
then the rate for United States Dollars, and if no
such rate appears in The Wall Street Journal
then the rate as quoted by the Reuters Monitor
Money Rates Service (or such service as may
replace the Reuters Monitor Money Rates
Service) on the due date for the payment in
question, adjusted mutatis mutandis every 6
months thereafter (and as certified, in the event
of any dispute, by any manager employed in the
foreign exchange department of The Standard
dispute to him. (see www.ice-sa.org.za). If the
Z3.2 The Contractor is required to submit an updated verification certificate and necessary
supporting documentation confirming the change in his B-BBEE status to the Service Manager
within thirty days of the notification or as otherwise instructed by the Service Manager.
Z3.3 Where, as a result, the Contractor’s B-BBEE status has decreased since the Contract Date the
Employer may either re-negotiate this contract or alternatively, terminate the Contractor’s
obligation to Provide the Service.
Z3.4 Failure by the Contractor to notify the Employer of a change in its B-BBEE status may
constitute a reason for termination. If the Employer terminates in terms of this clause, the
procedures on termination are P1, P2 and P4 as stated in clause 92, and the amount due is A1
and A3 as stated in clause 93.
Z4 Confidentiality
Z4.1 The Contractor does not disclose or make any information arising from or in connection with
this contract available to Others. This undertaking does not, however, apply to information
which at the time of disclosure or thereafter, without default on the part of the Contractor, enters
the public domain or to information which was already in the possession of the Contractor at the
time of disclosure (evidenced by written records in existence at that time). Should the
Contractor disclose information to Others in terms of clause 25.1, the Contractor ensures that
the provisions of this clause are complied with by the recipient.
Z4.2 If the Contractor is uncertain about whether any such information is confidential, it is to be
regarded as such until notified otherwise by the Service Manager.
Z4.3 In the event that the Contractor is, at any time, required by law to disclose any such information
which is required to be kept confidential, the Contractor, to the extent permitted by law prior to
disclosure, notifies the Employer so that an appropriate protection order and/or any other action
can be taken if possible, prior to any disclosure. In the event that such protective order is not,
or cannot, be obtained, then the Contractor may disclose that portion of the information which it
is required to be disclosed by law and uses reasonable efforts to obtain assurances that
confidential treatment will be afforded to the information so disclosed.
Z4.4 The taking of images (whether photographs, video footage or otherwise) of the Affected
the event, he is not entitled to a change in the Prices.
Z9 Employer’s limitation of liability
Z9.1 The Employer’s liability to the Contractor for the Contractor’s indirect or consequential loss is
limited to R0.00 (zero Rand)
Z9.2 The Contractor’s entitlement under the indemnity in 82.1 is provided for in 60.1(12) and the
Employer’s liability under the indemnity is limited to compensation as provided for in core
clause 63 and X19.11 if Option X19 Task Order applies to this contract.
Termination: Add to core clause 91.1, at the second main bullet point, fourth sub-bullet
Z10
point, after the words "against it":
Part c1 agreements and contract data of 71 c.1.2A Contract data part 1
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
appropriate action to prevent or remedy the situation, without limiting any other rights or
remedies the Employer has. It is not required that the Committing Party had to have been
found guilty, in court or in any other similar process, of such Prohibited Action before the
Employer can terminate the Contractor’s obligation to Provide the Services for this reason.
Z11.3 If the Employer terminates the Contractor’s obligation to Provide the Services for this reason,
the amounts due on termination are those intended in core clauses 92.1 and 92.2.
Z11.4 A Committing Party co-operates fully with any investigation pursuant to alleged Prohibited
Z12 Insurance
Z 12.1 Replace core clause 83 with the following:
Insurance cover 83
83.1 When requested by a Party, the other Party provides certificates from his insurer
or broker stating that the insurances required by this contract are in force.
Part c1 agreements and contract data of 71 c.1.2A Contract data part 1
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
83.2 The Contractor provides the insurances stated in the Insurance Table A from the
starting date until the earlier of Completion and the date of the termination
certificate.
the Contractor to the Employer’s insurance.
Employer’s property
The Employer’s policy deductible as at Contract
Date, where covered by the Employer’s insurance.
Materials Employer’s insurance.
The Employer’s policy deductible as at Contract
Date, where covered by the Employer’s insurance.
Equipment Employer’s insurance.
The Employer’s policy deductible as at Contract
Date, where covered by the Employer’s insurance.
The Contractor’s liability for Loss of or damage to property
loss of or damage to property The replacement cost
(except the Employer’s
property, Plant and Materials
and Equipment) and liability for Bodily injury to or death of a person
bodily injury to or death of a The amount required by the applicable law.
person (not an employee of the
Contractor) arising from or in
connection with the
Contractor’s Providing the
the course of their employment
in connection with this contract
Z __12.2 Replace core clause 86 with the following:
Insurance 86
by the
86.1 The Employer provides the insurances stated in the Insurance Table B
Part c1 agreements and contract data of 71 c.1.2A Contract data part 1
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
Transportation (Marine) Per the insurance policy document
Z13 Intellectual Property – Eskom owning Intellectual Property
“Intellectual means (a) patents, trade marks, service marks, rights in designs, trade names, trade secrets, know
Property” copyrights and topography rights, in each case whether registered or not; (b) applications for registrat
any of them; (c) rights under licences and consents in relation to any of them; (d) all forms of protection
similar nature or having equivalent or similar effect to any of them which may subsist anywhere in the wo
“Backgroun means any and all Intellectual Property rights that are not Foreground Intellectual Property,
d Intellectual and are owned or controlled by the relevant party or licensed to the relevant party prior to
Property" or outside of the services but required for the purposes of the services .
“Foreground means all Intellectual Property rights and other matter capable of being the subject of
Property” developed in whole or in substantial part in the course of the execution of the services
and rights which are developed substantially as a result of the services . Any services
that will be developed, changed, modified and/or improved specifically for the Purposes will
be Foreground Intellectual Property. Any data or any other information relating to
Employer’s proprietary information generated from the use of the Contractor’s Background
Z13.1 The Contractor retains ownership of all Background Intellectual Property rights made by or
on behalf of the Contractor as part of the services in information or material it uses in
carrying out the services .
Z13.2 All Foreground Intellectual Property rights, contained in any developed materials which are
created by the Contractor or on behalf of the Contractor, for the purposes of and in support
of the execution of the services (Employer’s IP) vest with the Employer.
Z13.3 Any data or any other information relating to Employer’s proprietary information generated
from the use of the Contractor’s Background Intellectual Property, the copyright therein
shall be owned by the Employer.
Z13.4 The Contractor acknowledges that all rights, title, and interest in and to the Foreground
the Foreground Intellectual Property.
Z13.5 The Contractor ensures that a copyright notice is incorporated or embossed or labelled on
the Foreground Intellectual Property, where the Employer is reflected as the owner of the
Z13.6 The Contractor is obliged to provide Foreground Intellectual Property manufacturing
documents, designs, processes and/or specifications to the Employer before/on the
completion date.
Z13.7 The Contractor procures that each Sub-Contractor executes all and any services , and
takes all and any other actions as may be required, in order to give effect to this
Z13.8 The Employer retains all Background Intellectual Property rights in all documents made by
or on behalf of the Employer including all documents and requirements provided prior to or
during the execution of the services . The Contractor does not, without the written
consent, of the Employer, copy, use or issue to a third party any of the Employer’s
executing the services .
Z13.9 Either party procures that any third party executes confidentiality undertakings not to
disclose to any other third parties, any of the Employer’s Background Intellectual Property
and IP documents and requirements at all, in respect of the Employer, or the Background
a. procures for Employer the right to continue to use the affected item or design, or
b. replaces the said affected item or design with a non-infringing item, or
c. provides a design of equivalent quality or modify such affected item or design so as
to make it non-infringing without affecting the quality.
Z13.10.4 Notwithstanding anything contained in this contract, the foregoing sets forth the entire
responsibility of Contractor with respect to claims relating to infringement.
Z13.10.5 Where it is alleged that the Employer has committed an infringement as intended vis-à-vis
the Contractor as set out in the third party intellectual property infringement clause, the
regards such alleged infringement.
Z13.10.6 The Contractor herewith indemnifies the Employer and undertakes to keep the Employer
indemnified against all claims of whatsoever nature, real or imagined, which may be made
against the Employer arising from the infringement of any third party intellectual property
rights.
Part c1 agreements and contract data of 71 c.1.2A Contract data part 1
ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________
guarantee any minimum quantity, frequency, duration, number of Task Orders or value of work during the
service period.
Section
Source: Attachment 4 TSC3.pdf (unknown)Service Manager: Rowan Francis, Address: 15 Pasita Street, Rosenberg, Durbanville, 7550, e-mail: [email protected]
Important Dates
Source: Invitation to Tender ITT GARIEP.pdf (TENDER){"closingDate":"04 September 2026","closingTime":"10h00","briefingSession":"{"date":"14 September 2026","time":"11:00","venue":"ion A compulsory Microsoft Teams meeting with representatives of","is_compulsory":true}"}
Briefing Session
Source: Invitation to Tender ITT GARIEP.pdf (TENDER)A compulsory Microsoft Teams clarification meeting will take place on 14 September 2026 at 11:00. Join link: https://teams.microsoft.com/meet/359938769603162?p=2IKrfmeXGKd1stOCr2, Meeting ID: 359 938 769 603 162, Passcode: 3nk97Bd9. Tenderers must confirm attendance with the Eskom Representative. Failure to attend will result in disqualification.
Contact Information
Source: Invitation to Tender ITT GARIEP.pdf (TENDER){"name":"Ms. Zodidi","email":"[email protected]","phone":null,"department":null,"address":"r which may be"}
Returnable Documents
Source: Invitation to Tender ITT GARIEP.pdf (TENDER)Mandatory tender returnables include: Annexure A Authorisation Form, Annexure B Acknowledgement Form, Annexure C Tenderer's Particulars, Annexure D Integrity Pact Declaration, Annexure E CPA for local goods/services, Annexure G1-G4 (SBD 6.2 local content declaration, only if designated materials are included), Annexure H SBD 1, Annexure I SBD 6.1, Annexure J SBD 4. Also: electronic copy of tender in PDF, tax clearance certificate, proof of CSD registration, proof of CIDB grading (or within 21 working days), completed NEC3 Term Service Contract, completed pricing schedule, quality and safety returnables. JVs must submit a joint venture agreement confirming rights, obligations, profit sharing and joint and several liability, and a designated bank account in the name of the JV.
Evaluation Criteria
Source: Invitation to Tender ITT GARIEP.pdf (TENDER)Bidders must meet eligibility criteria: no restrictions from Eskom or State-Owned Companies, no conflict of interest, not on National Treasury restricted list or Tender Defaulters list, not restricted by Eskom, and must not subcontract 100% of scope. Must attend compulsory clarification meeting. Must have valid CIDB grading of 4CE or 4GB or higher (or JV with combined grading). Must be registered on CSD. Must provide tax clearance (if not on CSD or no SARS PIN). Must submit all mandatory returnables at closing or be disqualified. Must meet mandatory technical criteria and achieve 70% functionality threshold. For specific goals, must submit valid B-BBEE certificate or sworn affidavit, proof of ownership, ID copies, and disability proof if claiming points.
Technical Specifications
Source: Invitation to Tender ITT GARIEP.pdf (TENDER)Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
compulsory clarification attendance site conditions, access requirements,
meeting, which will be register operational constraints and geographical
conducted virtually via Microsoft spread of the contract.
Teams. Physical attendance at
site is not required.
Tenderers who meet all mandatory criteria shall be evaluated against the Qualitative Technical Evaluation
Criteria, as defined below.
Evaluation shall be based on a weighted scoring system and a minimum threshold score of 70% must be
achieved to be considered technically acceptable.
The table below defines all Qualitative Technical Evaluation Criteria to be submitted by the Contractor by
the tender closing date. Should the Contractor fail to submit these criteria by the tender closing date, the
Contractor will score zero for each of the criterion stipulated in the table below.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
3.15 Evaluation of Price Prices will be evaluated as follows:
schedule’
alternative tenders submitted; and
tender based on the tendered programme (if provided) and
prices, on the estimated effect of Price Adjustment Factors and
rate of exchange fluctuations (if applicable) and on other
evaluation parameters relating to uncertainty and risk, where
applicable.
purposes.
evaluation purposes but will be implemented when payment is
effected.
Prices will be scored out of 80/90 points
3.18 Evaluation of Specific Goals Specific goals will be scored out of 20/10 points in accordance with
the PPPFA.
If a tenderer fails to submit evidence of its points claim for a Specific
Goal, it will not be disqualified. However, it will be awarded 0 points
for that Specific Goal.
3.19 Ranking of tenders Tenderers will be ranked by applying the preferential point scoring for
the 80/20 OR 90/10 system. Eskom will add the score from Pricing
and Specific Goals together and rank the suppliers from the highest
to the lowest.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
A maximum of 20/10 points may be awarded to a tenderer for the
specific goal specified for the tender. The points scored for the specific
goal must be added to the points scored for price and the total must
be rounded off to the nearest two decimal places. Subject to section
2(1)(f) of the Preferential Procurement Policy Framework Act, the
contract must be awarded to the tenderer scoring the highest points.
NB: The following documents are required to claim preference points:
verification agency / sworn affidavit / CIPC affidavit
documentation) inclusive of shareholding breakdown
Tenderer failing to provide documentation for the allocation of
preference points will not be disqualified, but:
3.20 Objective Criteria Objective criteria are not applicable.
(if applicable)
3.21 Reverse e-auction Reverse e-auction is not applicable.
(if applicable)
Contractual Requirements Mandatory Contractual Requirements that must be included in all
tenders is the following: -
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
Additional Contractual Requirements that may be included if
applicable:
(financial analysis is compulsory as a contractual requirement
for CIDB-related transactions from R30 000 excluding VAT);
and/or
SDL&I Objectives in line with Reconstruction and Development
Programme (RDP) Goals
Refer to the attached SDL&I Strategy (Attachment 14).
3.24 Sign form of Agreement/ The conditions of the contract will be the NEC3 – Term Service
Contractual Conditions Contract (TSC3).
2.28 CIDB Requirements (where CIDB Requirements are applicable.
applicable for Engineering and
Construction Works Contracts) 1. It is estimated that tenderers must have a Construction
Industry Development Board (CIDB) contractor grading of
4CE OR 4GB OR Higher.
Or;
Joint ventures are eligible to submit tenders provided that: -
2.every member of the Joint venture (JV) is registered with the
Cibd.
OR 3GB*class of construction work; or not lower than one level
below the required grading designation in the class of works
construction works under consideration and possesses the required
recognition status;
accordance with the CIBD regulations is equal to 4CE OR 4GB or
higher
than a contractor grading designation determined in
accordance with the sum tendered for a or CE OR GB* class of
construction work or a value determined in accordance
with Regulations 25 (1B) or 25 (7A) of the CIBD
Regulations.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
[ Please note that only those tenderers that are registered with
the Construction Industry Development Board or are capable of
being so registered within twenty-one (21) working days from
the closing date for submission of tenders in a contractor
grading designation as stipulated in the tender data and
determined in accordance with the best estimated value of the
scope of works are eligible to submit tenders.
2.29 Contract Skills Development Contract Skills Development Goals (CSDG) is applicable.
Goals (CSDG)
2.30 Contract Participation Goals Contract Participation Goals is not applicable.
Please note:
Tenderers are requested to bear in mind Eskom's standard payment terms as stipulated hereunder when
submitting tenders and concluding contracts with Eskom:
For contracts valued below R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed to paying
Suppliers within 30 days of receipt of undisputed invoices.
For contracts valued above R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed to paying
suppliers within 60 days of receipt of undisputed invoices.
Eskom reserves the right to negotiate with preferred bidders after a competitive bidding process or price
quotations should the tendered prices not be market-related.
Main contractors/ suppliers are discouraged from subcontracting with their subsidiary companies as this
may be interpreted as subcontracting with themselves and / or using their subsidiaries for fronting.
Where a main contractor subcontracts with a subsidiary, this must be declared in its tender documents.
A report containing a list of potential sub-contractors may be drawn by accessing the following link:
“proof of B-BBEE status level of contributor” means-
(a) the B-BBEE status level certificate issued by an authorised body or person; or
(b) a sworn affidavit as prescribed by the B-BBEE Codes of Good Practice; or
(c) any other requirement prescribed in terms of the Broad-Based Black Economic Empowerment Act
1.3 Tender returnables
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
The tenderer must submit the returnable set out hereunder as part of its tender at the stipulated deadline.
Note the following: -
These returnables are required to be completed, signed (if required on the returnable) and submitted with
the tender at Tender closing date and time. If not completed, signed (if required on the returnable) and/or
submitted by tender closing, the tenderer will be disqualified.
** Returnable required at Tender closing (non-disqualifiable): -
These returnables are required to be completed, signed (if required on the returnable) and submitted with
Tender at Tender closing date and time; however, if not submitted by Tender closing, or submitted with
incomplete information or without a required signature, the Procurement Practitioner will, in writing,
request the tenderer to submit the returnable within 5 working days. If the returnable is not completed,
signed if required and/or received by the Procurement Practitioner within 5 working days of the request,
the tenderer will be disqualified.
The 5 working days period does not apply to CIDB proof of grading. Refer to the returnable table the
prescribed period for CIDB proof of grading.
These returnables are required to be submitted at tender closing date and time. These returnables will
not be requested by the Procurement Practitioner. A tenderer that does not submit the required returnable
at stipulated deadline or submits an incomplete returnable; will not be disqualified but will score zero.
Returnable required prior to Contract Award.
Returnables that are mandatory for contract award must be submitted prior to award, completed if
completion is a requirement and signed if signature is a requirement.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Reference Returnable From Suppliers
required closing required closing. required Contract
to
Tender (disqualifiable)* Tender prior at at Returnable Returnable (Non-disqualifiable) Returnable
Basic Compliance Electronic copy of the tender in a PDF format. The √
price list needs to be submitted in PDF (The upload
size per document is 500 megabytes and total
submission is restricted to 4 gigabytes).
Annexure A Authorisation Form √
Annexure B Acknowledgement Form √
Annexure C Tenderers Particulars √
Annexure D Integrity Pact Declaration form √
Annexure E CPA for local goods/services (if applicable) √
Annexure F CPA(IG) for imported goods/services (if applicable) N/A
Annexure G1-G4 SBD 6.2 -Declaration certificate for local production √
and content and Annexures G2,G3,G4 [only applicable
where designated materials are included]
Annexure H SBD 1- to be completed and submitted by all √
(applicable for all tenderers.
suppliers including
Foreign suppliers)
PPPFA 2022 regulations
Annexure J SBD 4 – Bidders Disclosure √
Reverse e-auction N/A
training
acknowledgement
form (if applicable)
E-tendering Help √
Manual
acknowledgement
form (If applicable)
Additional Letter of intent to form a JV/consortium or Valid joint √
Documents required venture agreement confirming the rights and
in the event of JV: - obligations of each of the joint venture partners and
their profit-sharing ratios.
Separate written confirmation that the joint venture will √
operate as a single business entity (incorporated) for
the duration of the contract or this may be included as
an obligation within the JV agreement.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Reference Returnable From Suppliers
required closing required closing. required Contract
to
Tender (disqualifiable)* Tender prior at at Returnable Returnable (Non-disqualifiable) Returnable
Details and confirmation of a single designated bank √
account in the name of the JV and independent of the
individual JV partners, as set out in the joint venture
agreement.
(Valid BBBEE specific goals will not result in its disqualification.
Certificate or Sworn The tenderer will, however, be scored zero for
Affidavit) Specific Goals for purposes of PPPFA scoring and
ranking.
Tax Clearance A certified copy of a tax clearance certificate is √
Certificates required from foreign tenderers (with a footprint in
South Africa but that are not registered on CSD and
have not provided a SARS pin number) and local
tenderers (that have not provided their SARS e-filing
PIN number for verification by Eskom and/or their
CSD profile / CSD number).
Foreign suppliers with no footprint in South Africa must
complete the SBD1 document; however, no proof of
tax compliance is required.
Tax Evaluation Evaluation questionnaire to determine whether a √
Questionnaire (if company, close corporation (CC) or Trust is a personal
services contract service provider for purposes of PAYE
and was included as
annexure)
Compliance with To the extent that the tenderer falls within the definition √
Employment Equity of a “designated Employer” as contemplated in the
Act Employment Equity Act , the tenderer is
required to furnish the Employer with proof of
compliance with the Employment Equity Act, including
proof of submission of the Employment Equity report
to the Department of Labour. (South African tenderers
only)
CIDB (where Valid proof of the required CIDB grading designation √
applicable) for the main contractor; JV and /or sub-contractor as
may be required in the tender data at tender closing
deadline or within 21 working days from the closing
date of submission of tenders if this is agreed with the
Employer
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 68
File name: Invitation to Tender ITT GARIEP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Identifier
Invitation to Tender
Effective Date 07 April 2026
Review Date April 2031
Reference Returnable From Suppliers
required closing required closing. required Contract
to
Tender (disqualifiable)* Tender prior at at Returnable Returnable (Non-disqualifiable) Returnable
NEC or other NEC or other Contract, completed. √
Contract
Pricing schedule Completed pricing schedule (Included in the NEC3 √
Term Services Contract)
Additional √
documents required
(Ecsa/
SACPCMP/CVs/
permits/licenses/
specific registration
documents
(if applicable to
scope of work)
Mandatory contractual requirements
SUPPORTING EVIDENCE [applicable to all
tenders]
Mandatory CSD Registration (CSD number/CSD Report) √
Contractual
Methodology
Source: Invitation to Tender ITT GARIEP.pdf (TENDER)Tenders must include a Technical Evaluation Criteria (Attachment 5) submission, covering methodology and technical approach. The tenderer must submit all required documentation and evidence as specified in the technical criteria.
Experience & Qualifications
Source: Invitation to Tender ITT GARIEP.pdf (TENDER)Tenderers must submit documentation proving their technical experience and qualifications, including: CVs of key personnel, company profiles, and evidence of past projects. Specific requirements are detailed in the Technical Evaluation Criteria (Attachment 5).
Quality Management
Source: Invitation to Tender ITT GARIEP.pdf (TENDER)Quality requirements: Category 3 Quality Criteria listing all Tender Returnables (Attachment 6), Form A Category 3 Rev 9 (Attachment), and Supplier Quality Management specification 240-105658000 (previously QM 58) for reference.
Pricing Schedule
Source: Invitation to Tender ITT GARIEP.pdftender training
1.1.16 CIDB Contract Skills Development Goals (CSDG) Y
(if applicable) refer to SDL&I Attachment 14
1.1.17 Contract Participation Goals (CPG) N/A
(if applicable)
1.1.18 Scope of Work Attachment 3 Y
1.1.19 NEC3 Term Service Contract (TSC3) Attachment 4 Y
1.1.20 Completed pricing schedule (Included in the NEC3 Refer to NEC Y
Term Services Contract)
1.1.21 Technical Evaluation Criteria Attachment 5
1.1.22 Quality Requirements: Y
Goal, it will not be disqualified. However, it will be awarded 0 points
for that Specific Goal.
3.19 Ranking of tenders Tenderers will be ranked by applying the preferential point scoring for
the 80/20 OR 90/10 system. Eskom will add the score from Pricing
and Specific Goals together and rank the suppliers from the highest
to the lowest.
Pricing schedule Completed pricing schedule (Included in the NEC3 √
Term Services Contract)
Additional √
documents required
(Ecsa/
Compliance Requirements
Source: Invitation to Tender ITT GARIEP.pdf (TENDER)ADDITIONAL CONTRACTUAL REQUIREMENTS SUPPORTING EVIDENCE [where applicable and as stipulated under tender Data] Safety COIDA - Original certificate of good standing or proof √ of application issued by the Compensation Fund (COID) or a licensed compensation insurer (South African tenderers only) Quality Quality Requirements: √
Category 3 Quality Criteria Listing all Tender Returnables
Form A Category 3 Rev 9
Supplier Quality Management specification 240-105658000 (previously QM 58) for reference only Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 68 File name: Invitation to Tender ITT GARIEP Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Identifier Invitation to Tender Effective Date 07 April 2026 Review Date April 2031 Reference Returnable From Suppliers required closing required closing. required Contract to Tender (disqualifiable)* Tender prior at at Returnable Returnable (Non-disqualifiable) Returnable Other safety/quality Safety Requirements: √ documents as required per scope
Annexure C1 High Risk OHS Tender
Points Allocation: 10 points
B-BBEE Details: 7 April 2026
Review Date April 2031
Clause Number from Standard
Tender Data
Conditions of Tender
A maximum of 20/10 points may be awarded to a tenderer for the
specific goal specified for the tender. The points scored for the specific
goal must be added to the points scored for price and the total must
be rounded off to the nearest two decimal places. Subject to section
2(1)(f) of the Preferential Procurement Policy Framework Act, the
contract must be awarded to the tenderer scoring the highest points.
NB: The following documents are required to claim preference points:
verification agency / sworn affidavit / CIPC affidavit
documentation) inclusive of shareholding breakdown
Tenderer failing to provide documentation for the allocation of
preference points will not be disqualified, but:
3.20 Objective Criteria Objective criteria are not applicable.
(if applicable)
3.21 Reverse e-auction Reverse e-auction is not applicable.
(if applicable)
Contractual Requirements Mandatory Contractual Requirements that must be included in all
tenders is the following: -
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Es
Health & Safety
Source: Invitation to Tender ITT GARIEP.pdfAttachment 8 240-105658000 (previously QM 58) for
reference only
1.1.23 Safety Requirements: Attachment 9 Y
Form_240-77471499
Effective Date 07 April 2026
Review Date April 2031
Number Description Annexure Attached (Y /
N / n/a)
Evaluation
Peaking Rev3
the Workplace
32-95 Occupational Health and Safety
240-62946386 Driver and Vehicle Safety
Eskom Personal Protective Equipment (PPE)
PPE Non-Compliance Memo
Occupational Health and Safety Risk
applicable:
(financial analysis is compulsory as a contractual requirement
for CIDB-related transactions from R30 000 excluding VAT);
and/or
SUPPORTING EVIDENCE [where applicable and
as stipulated under tender Data]
Safety COIDA - Original certificate of good standing or proof √
of application issued by the Compensation Fund
(COID) or a licensed compensation insurer (South
African tenderers only)
Quality Quality Requirements: √
required closing required closing. required Contract
to
Tender (disqualifiable)* Tender prior at at Returnable Returnable (Non-disqualifiable) Returnable
Other safety/quality Safety Requirements: √
documents as
required per scope
of works Form_240-77471499
Evaluation
Peaking Rev3
the Workplace
32-95 Occupational Health and Safety
240-62946386 Driver and Vehicle Safety
Eskom Personal Protective Equipment (PPE)
PPE Non-Compliance Memo
Occupational Health and Safety Risk
Contractual Terms
Source: Invitation to Tender ITT GARIEP.pdfsanctions list. A tenderer shall be found to have the nationality
of a country if the tenderer is a national or is constituted,
incorporated, or registered and operates in conformity with the
provisions of the laws of that country. This criterion shall also
apply to the determination of the nationality of proposed
subcontractors or suppliers for any part of the Contract including
related services.
individually or as a partner in a joint venture (JV) or consortium,
except on an E-Tendering system where there is a limit size
(The upload size per document is 500 megabytes and total
submission is restricted to 4 gigabytes).
submitting tenders and concluding contracts with Eskom:
For contracts valued below R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed to paying
Suppliers within 30 days of receipt of undisputed invoices.
For contracts valued above R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed to paying
suppliers within 60 days of receipt of undisputed invoices.
Special Conditions
Source: Invitation to Tender ITT GARIEP.pdf (TENDER)Eskom's standard payment terms: For contracts below R50 million including VAT, Eskom pays within 30 days of receipt of undisputed invoices. For contracts above R50 million, within 60 days. Eskom reserves the right to negotiate with preferred bidders if tendered prices are not market-related. Main contractors are discouraged from subcontracting with subsidiary companies; if they do, this must be declared. Proof of B-BBEE status level contributor is required for preference points.
Requirements
Source: Invitation to Tender ITT GARIEP.pdf (TENDER)Eligibility criteria: Tenderers must not be under restriction from doing business with Eskom or State-Owned Companies; must not have nationality of a sanctioned country; must not submit more than one tender; JV/consortium must state joint and several liability; must not have a conflict of interest; tenders must be signed by authorised persons; must not be restricted by National Treasury, on the Tender Defaulters list, or restricted by Eskom; must not subcontract 100% of the scope of work. CIDB Requirements: Tenderers must have a CIDB contractor grading of 4CE or 4GB or higher. JVs must register every member, the lead partner must have a grading of 3CE or 3GB, and combined grading must equal 4CE or 4GB or higher. Ineligible tenderers will be disqualified.
Section
Source: Invitation to Tender ITT GARIEP.pdf (TENDER)Eskom Representative: Sinazo Sizani, Tel: 021 941 5763, E-mail: [email protected]. Procurement Manager: Ms. Zodidi Mavume.
Description
Source: Attachment 7 240-68099512 Form A_Cat 3_ Rev 9.docxThe tenderer must complete and sign the acknowledgement form to accept Eskom Supplier Quality Requirements as per specification 240-105658000 and ISO 9001.
Evaluation Criteria
Source: Attachment 7 240-68099512 Form A_Cat 3_ Rev 9.docx (unknown)Bidders must complete and sign the Eskom Supplier Quality Requirements acknowledgement form, accepting the requirements of specification 240-105658000 and ISO 9001. The form requires selection of a pre-contract award quality category; Category 3 (per clause 3.5.4) is indicated as applicable. No other evaluation criteria are stated in the provided document.
Technical Specifications
Source: Attachment 7 240-68099512 Form A_Cat 3_ Rev 9.docx (unknown)The tenderer must acknowledge and accept Eskom Supplier Quality Requirements as per specification 240-105658000 and ISO 9001. The form covers pre-contract award quality requirements, post-contract award quality monitoring, and standard conditions including Eskom rights of access and information, preservation, quality audits, management of nonconformities, and special processes. The tenderer must indicate applicability of ISO 9001 clauses and quality principles.
Compliance Requirements
Source: Attachment 7 240-68099512 Form A_Cat 3_ Rev 9.docx (unknown)Bidders must complete and sign the Eskom Supplier Quality Requirements acknowledgement form, accepting specification 240-105658000 and ISO 9001. No other compliance requirements (e.g., CSD, tax, B-BBEE, CIDB) are stated in the provided document.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 38 of 2000
Important for public-sector construction and infrastructure tenders that require contractor grading or construction procurement standards.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 107 of 1998
Relevant where environmental authorisations, EIAs or environmental compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 85 of 1993
Sets health and safety duties for contractors, employers and service providers working on public-sector sites.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 103 of 1977
Relevant where building standards, renovations, maintenance or construction compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Address
GARIEP HYDRO STATION - - Xhariep District Municipality -
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
15
Last checked
08 Sept 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Learn how to submit a winning bid with these related articles
How established construction firms use Joint Ventures with EMEs and QSEs to meet B-BBEE preferential procurement targets and access set-aside contracts.
Everything South African construction contractors need to know about how procurement officers verify cidb grades: what gauteng contractors must ensure is correct — april 2026 update — covering CIDB grading certificate, NHBRC registration (residential), step-by-step processes, common disqualification mistakes, and how Tenders-SA.org helps you find and win relevant contracts in Gauteng.
A practical guide for small and medium building contractors on winning government tenders for schools, clinics, housing, and municipal buildings in South Africa.
How small and medium construction contractors use Joint Ventures to combine CIDB grades, win larger infrastructure projects, and grow beyond their current grading ceiling.
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Construction. Unlock full pricing strategies, bid frequency, and historical win rates.