Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
Eskom Hendrina Power Station Pullens Hope - Pullenshope - Mpumalanga -
Organization Type
GOVERNMENT
Published
28 Oct 2026
OCDS Reference
ocds-9t57fa-176185
ESKOM requires the design and replacement of fuel oil flow meters at hendrina power station in mpumalanga over a 24-month period. Bidders must meet strict environmental compliance requirements, including an iso 14001-aligned ems file, a signed environmental management plan, and a minimum 80% score on the environmental evaluation checklist to be considered.
Environmental evaluation: Bidders must score at least 80% on the environmental checklist; outcomes may be qualified, not qualified, or qualified with condition.
EMS file: Must be aligned with ISO 14001:2015 and include policy, objectives, roles, communication, audits, emergency preparedness, monitoring, corrective action, and management review.
Environmental Management Plan: A signed, site-specific EMP must be submitted.
Site Environmental Representative: Must be appointed with a signed appointment letter.
Permits and licences: Certified copies of relevant environmental authorisations, permits, and licences (e.g., waste transporter, waste site licence) are required.
Documentation: Must provide method statements, procedures, work instructions, emergency preparedness plans (oil/chemical spill), hazardous substances register, Safety Data Sheets, approved Environmental Management Programme, waste register, and Waste Management Plan.
Training proof: Must provide proof of training for personnel performing significant activities (e.g., oil spill response).
Continue with tenders sharing this issuer, category, or province.
Browse categories with current opportunities in this area.
Compare tender activity across provinces.
Explore organisations currently publishing tenders.
Tools and research to help you assess opportunities.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Browse categories with current opportunities in this area.
Compare tender activity across provinces.
Explore organisations currently publishing tenders.
Tools and research to help you assess opportunities.
Date & Time
Thursday, 19 November 2026 - 10:00
Venue
Hendrina Power Station 1 Impala Street Pullenshope
Important: Attendance at this briefing session is mandatory. Bids from suppliers who do not attend may be disqualified.
Request for Bid(Open-Tender)
Eskom Hendrina Power Station Pullens Hope - Pullenshope - Mpumalanga -
Tenders in this industry often require registration with these bodies.
Recommended Certifications
Having these can improve your winning chances: Professional Engineering Technologist (Pr.Tech Eng), CESA Membership
AI Document Analysis Stages
Description
Source: 240-109253698 CQP Template 2021.docx28 Oct
2026
Tender Published
Tender was published
19 Nov
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Scope of Work- FUEL OIL INSTALLATION.pdf
Design and replacement of fuel oil flow meters at Hendrina Power Station over 24 months, including supply and installation of Coriolis mass flow meters, level measurement instruments, and a local monitoring system with HMI, plus integration with unit DCS systems.
E-Tenderers E-Tendering Training Acknowledgement Form.pdf
Design and replacement of fuel oil flow meters for a period of 24 months, procured by Eskom in Mpumalanga. The tender requires bidders to acknowledge completion of self-training on the e-Tendering solution via a standard form.
E-tendering Help Manual for supplier - 27 January 2025.pdf
Eskom requires the design and replacement of fuel oil flow meters at a site in Mpumalanga, with the contract running for 24 months. The tender is managed through Eskom's eTendering system, where bidders must register and upload their documents electronically.
Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdf
Design and replacement of fuel oil flow meters at Eskom's Hendrina Power Station over a 24-month period. The contract will be awarded as a single contract to one supplier.
SDLI Strategy Replace of Fuel Oil system.pdf
Design, supply, and replacement of fuel oil flow meters at Hendrina Power Station under a 24-month contract, with specific goals for B-BBEE preference points and additional Eskom SDL&I commitments.
Environmental Evaluation Checklist - template.pdf
Eskom Hendrina Power Station requires the design and replacement of fuel oil flow meters over a 24-month contract period. Bidders must meet an environmental evaluation threshold of 80% or above, providing an Environmental Management Plan, hazardous substance registers, and related environmental documentation.
Tender Technical Evaluation-Fuel Oil Flow Meters.pdf
Design and replacement of fuel oil flow meters at Hendrina Power Station over a 24-month period. The appointed contractor will provide detailed design, remove old equipment, supply and install Coriolis mass flow meters and level monitoring equipment, install a monitoring control panel, test and commission the system, train Eskom personnel, and provide maintenance strategy and documentation.
Supplier Evaluation Pack.pdf
Eskom requires the design and replacement of fuel oil flow meters over a 24-month period, with work to take place in Mpumalanga. Bidders must complete the PAYE questionnaire to determine their tax classification for service contracts with Eskom.
240-109253698 CQP Template 2021.docx
Eskom requires the design and replacement of fuel oil flow meters over a 24-month contract period, with the successful bidder expected to provide a contract quality plan that complies with SANS 466:2005 / ISO 10005:2005 and specifies all quality management arrangements for the work.
240-12248652_List of Tender Returnables_Cat 2_ Rev 7.xlsx
Eskom requires the design and replacement of fuel oil flow meters over a 24-month period, with the work located in Mpumalanga. Bidders must comply with a detailed quality management system evaluation based on ISO 9001:2015 and must submit forms and plans as specified in the tender documentation.
240-68099512 Form A_Cat 2_ Rev 9.docx
Design and replacement of fuel oil flow meters at Eskom power stations in Mpumalanga, under a 24-month contract. The successful bidder must comply with Eskom's Supplier Quality Requirements (specification 240-105658000) and ISO 9001, and will be subject to pre- and post-contract quality assessments.
380-136358 R0 - Quality Control Plan TEMPLATE.doc
Eskom requires the design and replacement of fuel oil flow meters at its Mpumalanga operations over a 24-month period. The work includes a Quality Control Plan (QCP) with defined hold, witness, review, and surveillance points, and involves Eskom maintenance personnel, system engineers, QA/QC personnel, and an Approved Inspection Authority (AIA).
Annexure B Eskom Acknowledgement Form for OHS Legal and Other Requirements - Rev 4.pdf
Design and replacement of fuel oil flow meters for a 24-month period at Eskom's Mpumalanga operations. The contract requires compliance with South African OHS legislation and Eskom's OHS requirements, with penalties for non-compliance.
240-77471651(HIGH RISK) (1).pdf
Eskom requires the design and replacement of fuel oil flow meters over a 24-month period at its Mpumalanga operations. The tender is classified as high risk for occupational health and safety (OHS), and bidders must submit a comprehensive OHS returnable pack as part of their offer.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
R 2 574 030
Range
Based on 8 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Eskom requires the design and replacement of fuel oil flow meters for a 24-month period. The supplier must provide a Contract Quality Plan that identifies and plans for meeting the client's and contract's quality expectations for the scope of work.
Technical Specifications
Source: 240-109253698 CQP Template 2021.docx (unknown)The tender concerns the design and replacement of fuel oil flow meters for a 24-month period. The successful supplier must provide a Contract Quality Plan (CQP) that addresses the client's and contract's quality management expectations, referencing the SANS 466:2005 / ISO 10005:2005 quality plan guidelines. The plan must cover, as applicable:
Description
Source: 240-12248652_List of Tender Returnables_Cat 2_ Rev 7.xlsxThe document is a mandatory returnable template: the List of Tender Returnables and the Supplier Quality Management tender evaluation scorecard. It defines how bidders must complete the returnables sheet and the quality management evaluation criteria for this Eskom tender. Bidders must select one applicable category on the cover tab, after which the applicable requirements are flagged.
Evaluation Criteria
Source: 240-12248652_List of Tender Returnables_Cat 2_ Rev 7.xlsx (unknown)The bid is evaluated on the Supplier Quality Management scorecard. Bidders must score points across five weighted sections.
Scoring sections and weights:
Section A offers two options; bidders are scored on the option they choose:
Section B requires documented roles and responsibilities, control of externally provided processes, an internal audit report with nonconformity and corrective action reports, and management review meeting records.
Section C requires a draft Contract Quality Plan specific to the scope, per ISO 10005.
Section D requires a QCP or ITP (Inspection and Test Plan) example or as per scope.
Section E requires a completed and signed Form A, plus any additional requirements per scope.
Evaluation is at the discretion of the PQA representatives; a minimum qualifying score is not stated.
Technical Specifications
Source: 240-12248652_List of Tender Returnables_Cat 2_ Rev 7.xlsx (unknown)The scope is the design and replacement of fuel oil flow meters for a period of 24 months. This document is an evaluation scorecard for the tender; the full scope of works is referenced in specification 240-105658000. Bidders must select the applicable category and submit according to the category requirements listed in the returnables sheet.
Compliance Requirements
Source: 240-12248652_List of Tender Returnables_Cat 2_ Rev 7.xlsx (unknown)Bidders must comply with the quality management system requirements (ISO 9001:2015) as detailed in the evaluation scorecard. Specific compliance evidence is listed under evaluation criteria. No other compliance requirements (e.g., CSD, tax, CIDB) are stated in this document.
Important Dates
Source: Supplier Evaluation Pack.pdf (unknown)Closing date: 19 November 2026 at 08:00 (Eskom).
Pack validity: 1 March 2026 to 28 February 2027, subject to tax legislation changes.
Contact Information
Source: Supplier Evaluation Pack.pdf (unknown)Eskom Group Tax (for PAYE pack submissions):
[No further contacts stated in the document.]
Submission Guidelines
Source: Supplier Evaluation Pack.pdf (unknown)Returnable documents:
Risk: If required affidavits or declarations are not signed, PAYE will be withheld from payments.
Evaluation Criteria
Source: Supplier Evaluation Pack.pdf (unknown)The evaluation determines the contractor's tax classification (independent contractor, personal service provider, labour broker, or dependent contractor), which governs PAYE withholding and IRP5 codes.
Classification tests ( Pack A for companies/CCs/trusts, Pack B for individuals):
Outcome determines PAYE withholding and the IRP5 code (3601 or 3616).
Technical Specifications
Source: Supplier Evaluation Pack.pdf (unknown)Purpose: The pack establishes whether a contractor supplying services to Eskom is an independent contractor, personal service provider, labour broker, or dependent contractor for PAYE purposes.
Applicable entities: Companies, close corporations, trusts (Evaluation Pack A) and individuals (Evaluation Pack B).
Classification determines tax treatment, including PAYE withholding and IRP5/IT3(a) codes.
Pricing Schedule
Source: Supplier Evaluation Pack.pdfPricing is not addressed in this pack. The pack only determines PAYE withholding based on the contractor's classification.
If a labour broker provides a valid IRP30 exemption certificate, no PAYE is withheld and an IT3(a) is issued; otherwise PAYE is withheld at individual tax rates until the certificate is provided.
Classification as a dependent contractor or personal service provider results in PAYE withheld and coded 3601 or 3616 on the IRP5.
Financial Requirements
Source: Supplier Evaluation Pack.pdf (unknown)PAYE implications based on classification:
Compliance Requirements
Source: Supplier Evaluation Pack.pdf (unknown)Mandatory: Complete and sign the applicable Supplier Evaluation Pack (A or B).
Required data: Contractor details including VAT registration, income tax registration, bank details, and authorised representative details.
Required affidavits/declarations (Appendices 1–9) depending on answers to the questionnaire. Signing each one confirms specific facts; failure to sign results in PAYE withholding.
Section
Source: Supplier Evaluation Pack.pdfAdditional evaluation criteria: The pack uses a structured questionnaire with tests (residence, employees, connected persons, 80% income, place/control, dominant impression) to assign a tax classification. The classification determines PAYE withholding and IRP5/IT3(a) codes.
Description
Source: Tender Technical Evaluation-Fuel Oil Flow Meters.pdfDesign and replacement of fuel oil flow meters at Hendrina Power Station over 24 months. Scope includes detailed design, removal of old equipment (including hazardous waste), supply and installation of Coriolis mass flow meters, level monitoring equipment, monitoring control panel with DCS integration, testing and commissioning, training of Eskom staff, maintenance strategy, and provision of documentation and drawings.
Submission Guidelines
Source: Tender Technical Evaluation-Fuel Oil Flow Meters.pdf (unknown)Returnable documents: evidence of hazardous-location electrical-contractor registration with the DoL, proof of ECSA professional registration for electrical/electronic and mechanical engineers or technologists (employed by the bidder), and a method statement and execution plan for design, installation, testing and commissioning. The Tender Returnable must be numbered and ordered as defined (e.g. 1.1.a). An undertaking is required that identified resources will not be changed after award. Where no information is offered for any qualitative criterion, no points will be scored.
Evaluation Criteria
Source: Tender Technical Evaluation-Fuel Oil Flow Meters.pdf (unknown)Minimum technical threshold: 70% weighted final score.
Qualitative criteria (total 100 points):
Mandatory criteria (pass/fail):
Technical Specifications
Source: Tender Technical Evaluation-Fuel Oil Flow Meters.pdf (unknown)Work is at Hendrina Power Station in Mpumalanga. Scope: design and replacement of fuel oil flow meters over a 24-month period.
References: NEC3 Term Service Contract (informative); ISO 9001 Quality Management Systems (informative); Generation Tender Technical Evaluation Procedure (normative).
Methodology
Source: Tender Technical Evaluation-Fuel Oil Flow Meters.pdfProvide a method statement and execution plan for design, installation, testing and commissioning. Must include: a) project organogram showing project team structure, b) resource schedule listing qualified personnel, c) project execution schedule, d) quality and commissioning plan. Scoring: all four items = 5 points, three items = 4, between one and three = 2, one or less = 0 (out of 10 total).
Experience & Qualifications
Source: Tender Technical Evaluation-Fuel Oil Flow Meters.pdfCompany capability and experience (40% of qualitative): at least 3 reference letters from traceable clients in the past 5-10 years for similar or related services.
Key personnel requirements:
CVs of key personnel must have experience comparable to the tender scope. An undertaking is required that key resources will not be changed after award.
Quality Management
Source: Tender Technical Evaluation-Fuel Oil Flow Meters.pdfQuality and commissioning plan is part of the method statement (item d) and is scored out of the 10-point scope-execution criterion. ISO 9001 is referenced as an informative standard.
Compliance Requirements
Source: Tender Technical Evaluation-Fuel Oil Flow Meters.pdf (unknown)Mandatory: proof of hazardous-location electrical contractor registration with DoL and certification that at least one individual is a Master Installation Electrician (MIE) under the OHS Act to issue a Certificate of Compliance (CoC).
Mandatory: ECSA professional registration for both an electrical/electronic engineer or technologist and a mechanical engineer or technologist, employed by the company, for design and document authorisation.
Unacceptable risks: no MIE to issue CoC; no ECSA-registered engineer to sign off designs; failure to understand scope and technical risks.
Health & Safety
Source: Tender Technical Evaluation-Fuel Oil Flow Meters.pdfWork is in a hazardous location. The company must have a Master Installation Electrician (MIE) registered under the OHS Act to issue a Certificate of Compliance for construction, testing and inspection of hazardous-location installation. The supervisor must hold a minimum N3 electrical certificate, 3 years' supervisory experience, and hazardous-location (HAZLOC) certification. Provide proof of supervision for HAZLOC installations via CV and certificates. Removal and handling of equipment includes hazardous waste.
Section
Source: Tender Technical Evaluation-Fuel Oil Flow Meters.pdfAdditional to the standard evaluation: minimum technical threshold of 70%. Scoring uses a 5-point scale (5 = compliant, 4 = compliant with acceptable qualifications, 2 = non-compliant, 0 = totally deficient). Unacceptable technical risks: no MIE to issue CoC, no ECSA-registered engineer for design sign-off, and failure to understand scope.
Description
Source: Scope of Work- FUEL OIL INSTALLATION.pdfThe tender is for the design, supply, installation, testing and commissioning of replacement fuel oil flow meters at Hendrina Power Station, part of the Fuel Oil Management System (FOMS). The work covers Units 2, 4, 5, 6, 7 and 10, and the North and South fuel oil offloading bays and plants.
Important Dates
Source: Scope of Work- FUEL OIL INSTALLATION.pdf (unknown)Closing date: 19 November 2026 at 10:00 (08:00 UTC). No briefing or site visit is stated.
Submission Guidelines
Source: Scope of Work- FUEL OIL INSTALLATION.pdf (unknown)Returnable forms (complete and sign all):
Submit with proof of CSD registration and a valid tax clearance.
Evaluation Criteria
Source: Scope of Work- FUEL OIL INSTALLATION.pdf (unknown)Evaluation basis not stated in the source document. Bidders must be CSD-registered and hold a valid tax clearance. Only contractors with proven experience in fuel oil monitoring systems will be considered; the bid must include a CV of relevant experience and references.
Technical Specifications
Source: Scope of Work- FUEL OIL INSTALLATION.pdf (unknown)Scope: design, supply, install, test and commission replacement fuel oil flow meters at Hendrina Power Station as part of the Fuel Oil Management System (FOMS).
Location: Units 2, 4, 5, 6, 7 and 10, plus the North and South fuel oil offloading bays and fuel oil plants.
Flow meter quantities:
Level measurement instruments (tanks):
Each tank capacity: 100 000 litres.
Work includes: remove and hand over old equipment, supply and install Coriolis mass flow meters, supply and install level monitoring equipment, monitor fuel oil consumption and delivery, install a control panel at the fuel oil plant, interface unit flow meters with each unit's DCS via 4-20 mA signals, provide a local HMI for outside plant monitoring, train Eskom personnel, and provide maintenance strategy, drawings, manuals and documentation.
Design and performance requirements:
Construction constraints:
Cabling standards: Eskom 240-64636794 (wiring and cable marking) and 240-70413291 (terminal blocks); concealed in trunking or conduit, tied at max 1.5 m intervals.
Manufacturing standards:
Testing and commissioning:
Handover:
Documentation: deliver as-built drawings and manuals in both hard and soft copy; soft copies in 'dgn' MicroStation format.
Quality Management
Source: Scope of Work- FUEL OIL INSTALLATION.pdfQuality Inspection Documentations must be generated for design, installation, commissioning and testing. The Eskom project manager and stakeholders must witness installation. Hold points are required for testing and commissioning.
Pricing Schedule
Source: Scope of Work- FUEL OIL INSTALLATION.pdfNo pricing schedule or pricing format is stated in the source document. The scope includes design, supply, installation, testing, commissioning, training and documentation.
Compliance Requirements
Source: Scope of Work- FUEL OIL INSTALLATION.pdf (unknown)Bidders must be registered on the CSD and hold a valid tax clearance.
Only contractors with proven experience in fuel oil monitoring systems will be considered; a CV of relevant experience and references must be submitted.
Installers must comply with the OHS Act and Eskom health and safety specifications.
All instruments supplied and installed must be Ex rated for zone 2 explosion group IIA.
Earthing must comply with Eskom standards 240-56872313 (Radio Station Earthing and Bonding) and 240-56356396 (Earthing and Lightning Protection).
Environmental compliance: system must comply with SANS 61000-1-2 for signal and electromagnetic radiation levels.
Health & Safety
Source: Scope of Work- FUEL OIL INSTALLATION.pdfAll work must comply with the OHS Act and Eskom health and safety specifications. Hot work permits are required for cutting and welding. All instruments must be Ex rated for zone 2, explosion group IIA. Earthing must follow Eskom standards.
Environmental
Source: Scope of Work- FUEL OIL INSTALLATION.pdfSignal, voltage and electromagnetic radiation levels must not be dangerous. System and components must comply with SANS 61000-1-2. Earthing must meet Eskom earthing and lightning protection standards.
Contractual Terms
Source: Scope of Work- FUEL OIL INSTALLATION.pdfContract period: 24 months. The specification forms part of the contractual documents. No other specific contractual terms (penalties, retention, guarantees) are stated in the source document.
Section
Source: Scope of Work- FUEL OIL INSTALLATION.pdfEvaluation criteria are not detailed in the source document. Bidders must be CSD-registered, hold a valid tax clearance, and have proven experience in fuel oil monitoring systems (submit CV and references).
Evaluation Criteria
Source: E-Tenderers E-Tendering Training Acknowledgement Form.pdf (unknown)The only stated requirement is submission of the completed E-Tendering Training Acknowledgement Form. No other eligibility criteria are stated in the document.
Important Dates
Source: Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdf (TENDER)Closing date: 19 November 2026 at 10:00
Tender validity: 12 weeks from closing date and time.
Compulsory clarification meeting / site visit: 06 November 2026 from 09:00 to 12:00, at Hendrina Power Station, 1 Impala Street, Pullenshope. Attendance is mandatory. Bidders must report by 08:30 for the mandatory safety induction. PPE required.
Clarification queries deadline: 12 November 2026 at 15:30 (5 working days before closing).
Contact Information
Source: Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdf (TENDER)Eskom Representative (SCM): Theo Vilakazi
Telephone: 013 296 3779
Email: [email protected]
Fraud and corruption reporting: 0800 11 2722, [email protected]
Submission address: Eskom E-tendering site via TenderBulletin (eskom.co.za)
Site visit venue: Hendrina Power Station, 1 Impala Street, Pullenshope
Submission Guidelines
Source: Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdf (TENDER)Submission method: Electronic only, via the Eskom E-tendering site (TenderBulletin at eskom.co.za).
No hard copies accepted; no zipped/compressed files allowed.
All documents must be in PDF format; each document upload limit is 500 MB, total submission limit is 4 GB.
Upload tender documents under the folders: Technical, Commercial, Financial, and Other.
The price list must be submitted in PDF.
If resubmitting, the latest version is accepted and prior submissions are null and void.
Ensure the submission status is marked as complete.
Returnable documents required at tender closing (disqualifiable if not submitted):
Returnables required at tender closing (non-disqualifiable, but must be submitted within 5 working days if requested):
Returnables required for evaluation (score zero if not submitted):
Disqualification risks:
Evaluation Criteria
Source: Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdf (TENDER)Evaluation stages:
Total score = Price points + Specific Goals points. Bidders ranked from highest to lowest.
Prices evaluated inclusive of VAT, corrected for arithmetical errors, excluding contingencies, and adjusted for variations. Unconditional discounts considered; conditional discounts applied at payment.
Contractual requirements (e.g., CSD registration, SHEQ, financial viability, CSI) are assessed after ranking and must be met before award; failure may result in non-responsive determination.
Technical Specifications
Source: Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdf (TENDER)Scope: Design and replacement of fuel oil flow meters at Hendrina Power Station, for a 24-month period.
Mandatory technical requirements:
Technical evaluation criteria (Annexure A):
Methodology
Source: Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdfMethodology requirements:
Experience & Qualifications
Source: Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdfKey personnel qualifications and scoring:
Quality Management
Source: Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdfQuality management system: Must comply with ISO 9001, either through valid certification (Option 1) or documented QMS compliant with ISO 9001 (Option 2).
Must provide evidence of QMS in operation (Tender Quality Requirements - Ref 240-105658000).
Draft Contract Quality Plan specific to scope (Ref ISO 10005).
Quality Control Plans (QCP/Checklist/ITP) as per Scope of Works (Ref ISO 10005).
CVs and qualifications of personnel for quality-related roles.
Pricing Schedule
Source: Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdfPricing must be submitted in PDF format via e-tendering.
Pricing schedule/BOQ is attached to tender documents; complete it in full.
Prices will be evaluated inclusive of VAT, corrected for arithmetical errors, and excluding contingencies. Unconditional discounts considered; conditional discounts applied at payment.
Prices scored out of 80 points.
Cataloguing: If required, pricing schedule must include a line item for cataloguing, which Eskom will pay for.
Reverse e-auction is not applicable.
Financial Requirements
Source: Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdf (TENDER)Payment terms: For contracts below R50 million (incl. VAT), Eskom pays within 30 days of receiving undisputed invoices. For contracts above R50 million, within 60 days.
Bid security: None stated, but if recommended tenderer is not financially suitable, Eskom may require a performance bond from an approved financial institution, or a Parent Company Guarantee. At least two approved financial institutions must be identified for the bond.
Financial viability: The recommended tenderer must submit latest approved annual financial statements (not draft or management accounts), including director's report, auditor's/reviewer's report, statement of financial position, comprehensive income, changes in equity, cash flows, and notes. For unincorporated JV or SPV, each partner must submit AFS. Public interest score and ITA34C required for non-audited South African entities.
Eskom may negotiate prices if tendered prices are not market-related.
Compliance Requirements
Source: Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdf (TENDER)CSD registration: Mandatory contractual requirement. Provide CSD number/report.
Tax compliance: Local tenderers must be on CSD or provide SARS e-filing PIN for verification; otherwise submit a certified copy of a tax clearance certificate. Foreign tenderers with a footprint in SA require tax clearance; those without a footprint only complete SBD 1.
CIDB grading: Required grade 6ME (Mechanical Engineering) or higher, or be capable of being registered within 21 working days from tender closing.
B-BBEE: Preference points claimed under SBD 6.1. Proof of B-BBEE status level (certificate or sworn affidavit) required. Failure to submit evidence results in zero points for that goal, not disqualification.
Employment Equity Act: If a designated employer, provide proof of compliance, including EE report submission.
OHS requirements (High Risk):
Quality requirements (Category 2):
Environmental requirements:
Contractual requirements (not evaluation criteria, but assessed after ranking):
Prohibition: Main contractors discouraged from subcontracting with subsidiaries (may be seen as fronting); must declare any such subcontracting.
Health & Safety
Source: Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdfOHS requirements for high-risk works:
Environmental
Source: Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdfEnvironmental management requirements:
Contractual Terms
Source: Invitation to Tender (ITT)-Fuel Oil Flow meters for a period of 24 months.pdfContract type: NEC3 Engineering and Construction Contract (ECC3), with main Option A (Priced contract with activity schedule).
Dispute resolution: Option W1.
Secondary options: X1 (Price adjustment for inflation), X2 (Changes in the law), X5 (Sectional Completion), X7 (Delay damages), X16 (Retention), X18 (Limitation of liability), and Z (Additional conditions).
Payment terms: For contracts below R50 million (incl. VAT), payment within 30 days of undisputed invoice; above R50 million, within 60 days.
Eskom may negotiate prices with preferred bidders if prices are not market-related.
Evaluation Criteria
Source: Environmental Evaluation Checklist - template.pdf (unknown)Bidders must score at least 80% on the environmental evaluation checklist to be considered. The outcome may be qualified, not qualified, or qualified with condition. Items assessed include:
Methodology
Source: Environmental Evaluation Checklist - template.pdfMethod statements for specific activities as per the contract are required.
Copies of procedures and work instructions must be provided.
Quality Management
Source: Environmental Evaluation Checklist - template.pdfQuality and environmental management system evidence required:
Compliance Requirements
Source: Environmental Evaluation Checklist - template.pdf (unknown)Site is Hendrina Power Station, Eskom.
Health & Safety
Source: Environmental Evaluation Checklist - template.pdfHealth and safety requirements:
Environmental
Source: Environmental Evaluation Checklist - template.pdfEnvironmental compliance:
Description
Source: E-tendering Help Manual for supplier - 27 January 2025.pdfThe provided document is an Eskom eTendering system user manual, not the tender specification for the fuel oil flow meters. It explains how to register on the system, upload bid documents, and finalise submissions. No scope details of the meter design/replacement work are given in this manual.
Important Dates
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)Closing date: 2026-11-19 (from tender record).
Closing time: 08:00 (from tender record).
Contact Information
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)System support: Contact the buyer responsible for the published tender for problems with TenderBulletin, eTendering, or OpenText systems.
System email (automated): [email protected]
Submission Guidelines
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)Submission Method: Upload electronically via the Eskom eTendering system at https://eTendering.eskom.co.za.
Registration: Bidders must register on the eTendering system before submission. A CSD number is required to access the system.
File upload: Each file must not exceed 50MB; total uploads must not exceed 900MB. Classify files appropriately (e.g. Technical, Commercial, Finance).
Finalisation: Verify all required documents are uploaded, then click 'Finalize Submission' to close. A submission ID is emailed; retain it for enquiries.
Closing time: Bids must be finalised before the closing time stated; late submissions are disqualified.
Evaluation Criteria
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)Evaluation method: Not detailed in the provided document. Bidders must meet the selection and evaluation criteria relevant to the tender.
Preference points: Not specified in this document.
Technical Specifications
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)Scope: Design and replacement of fuel oil flow meters.
Contract period: 24 months.
Location: Mpumalanga (Eskom).
No further technical detail is provided in this user manual.
Compliance Requirements
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)CSD registration: A valid CSD number is mandatory to access the eTendering system.
Description
Source: 240-68099512 Form A_Cat 2_ Rev 9.docxThe tender is for the design and replacement of fuel oil flow meters at Eskom, with a contract period of 24 months. The supplier must complete and sign the form to acknowledge acceptance of Eskom Supplier Quality Requirements.
Submission Guidelines
Source: 240-68099512 Form A_Cat 2_ Rev 9.docx (unknown)Returnable documents: the completed and signed Supplier Quality Requirements acknowledgement form (Form A) as per specification 240-105658000 and ISO 9001 Standard.
Submission method: electronic or physical as per tender instructions.
Closing time: 08:00 on 19 November 2026.
Evaluation Criteria
Source: 240-68099512 Form A_Cat 2_ Rev 9.docx (unknown)Bidder must select only one quality category; Category 2 is pre-selected as applicable.
Bidder must indicate whether a site assessment is applicable.
Bidder must accept and comply with all quality requirements of specification 240-105658000, including Eskom's rights of access, rights to information, preservation, quality audits, management of nonconformities, and special processes.
Bidder must confirm compliance with all ISO 9001 clauses and quality principles.
Technical Specifications
Source: 240-68099512 Form A_Cat 2_ Rev 9.docx (unknown)Contract scope: design and replacement of fuel oil flow meters for a period of 24 months.
The bidder must complete and sign the form to acknowledge and accept Eskom Supplier Quality Requirements.
The supplier must comply with specification 240-105658000 and ISO 9001 Standard.
Compliance Requirements
Source: 240-68099512 Form A_Cat 2_ Rev 9.docx (unknown)The bidder must complete and sign the Supplier Quality Requirements acknowledgement form.
The bidder must comply with all clauses of ISO 9001 and the quality principles listed in the form.
Description
Source: 380-136358 R0 - Quality Control Plan TEMPLATE.docThe document provided is a Quality Control Plan (QCP) template to be completed by the successful bidder. It identifies the project, contract, work order, and intervention points for quality approvals. No further scope details are present in the source.
Submission Guidelines
Source: 380-136358 R0 - Quality Control Plan TEMPLATE.doc (unknown)Returnable documents: a completed Quality Control Plan (QCP) template, as provided with the tender, is required. The QCP must detail inspection and approval intervention points for each activity.
Submission method and closing time follow the tender record (closing 19 November 2026 at 08:00).
Technical Specifications
Source: 380-136358 R0 - Quality Control Plan TEMPLATE.doc (unknown)The QCP template is structured around the Eskom project identification fields: project description, contract/order number, work order/QCP number, job/task description, area of works, drawing number and revision, and KKS/AKZ or item/plant/material reference.
Approval roles on the QCP include: Eskom Maintenance/Service Provider, Eskom System Engineer, QA/QC/QE Personnel, and Approved Inspection Authority (AIA). Each role is assigned intervention codes: H (Hold - cannot be waived), W (Witness - activity may proceed if notice/waiver given), R (Review), and S (Surveillance).
The QCP must list each activity with its applicable specification, procedure, or acceptance standard, and identify the responsible approver for each intervention point.
Compliance Requirements
Source: 380-136358 R0 - Quality Control Plan TEMPLATE.doc (unknown)No specific compliance requirements are stated beyond the submission of a completed QCP template.
Description
Source: Annexure B Eskom Acknowledgement Form for OHS Legal and Other Requirements - Rev 4.pdfThe tender involves the design and replacement of fuel oil flow meters, with a 24-month engagement period. The provided text contains only OHS acknowledgement requirements; no additional scope description is available.
Submission Guidelines
Source: Annexure B Eskom Acknowledgement Form for OHS Legal and Other Requirements - Rev 4.pdf (unknown)Returnable documents:
Disqualification risks:
Evaluation Criteria
Source: Annexure B Eskom Acknowledgement Form for OHS Legal and Other Requirements - Rev 4.pdf (unknown)Bidders must comply with the Occupational Health and Safety Act, 1993 and the Compensation for Occupational Injuries and Diseases Act, 1993.
Bidders must be able to provide testimonials/references and contact details of previous clients for similar work, if instructed.
No price/functionality scoring split or minimum qualifying score is stated in the available document.
Technical Specifications
Source: Annexure B Eskom Acknowledgement Form for OHS Legal and Other Requirements - Rev 4.pdf (unknown)The procurement is for the design and replacement of fuel oil flow meters for a period of 24 months. The extract provided is limited to OHS requirements; no further technical detail is available in the supplied text.
Contractor management obligations (if the bidder subcontracts):
Quality Management
Source: Annexure B Eskom Acknowledgement Form for OHS Legal and Other Requirements - Rev 4.pdfNo quality management plan or certification is specified. The available content addresses contractor and supplier management obligations: the main supplier must have a documented selection process covering competency, compliance and OHS performance; notify Eskom before appointing sub-contractors; ensure sub-contractors have the necessary resources and competencies; audit sub-contractor compliance; and manage non-conformances through agreed performance and penalty mechanisms.
Compliance Requirements
Source: Annexure B Eskom Acknowledgement Form for OHS Legal and Other Requirements - Rev 4.pdf (unknown)Legal compliance (mandatory):
Contractual penalties apply for non-compliance with statutory requirements or Eskom OHS requirements.
After contract award, the contractor must fully align its company processes to Eskom's OHS policies, procedures and standards.
Health & Safety
Source: Annexure B Eskom Acknowledgement Form for OHS Legal and Other Requirements - Rev 4.pdfBidders must comply with the Occupational Health and Safety Act, 1993 and the Compensation for Occupational Injuries and Diseases Act, 1993. After award, the contractor must align its processes to Eskom's OHS policies, procedures and standards. Non-compliance may attract contractual penalties. All employees must undergo relevant Eskom induction and their own company induction. The supplier is accountable for managing and overseeing sub-contractors and suppliers, including verifying their OHS compliance.
Evaluation Criteria
Source: 240-77471651(HIGH RISK) (1).pdf (unknown)The bidder must submit the OHS returnables listed in Annexure C1 (High Risk). Each returnable is assessed as Yes (submitted and compliant), No (not submitted), or N/A (not applicable). The OHS evaluation concludes with a recommendation of either 'Recommended' or 'Not Recommended'. The following documents must be submitted:
Experience & Qualifications
Source: 240-77471651(HIGH RISK) (1).pdfThe bidder must provide OHS competency documentation, including CVs and qualifications/certificates, listing the competencies required for the scope of work. The assessment considers the scope, risks, OHS plan, and applicability.
Compliance Requirements
Source: 240-77471651(HIGH RISK) (1).pdf (unknown)OHS compliance requirements for this high-risk tender:
Health & Safety
Source: 240-77471651(HIGH RISK) (1).pdfOHS tender returnables required for this high-risk scope:
Section
Source: 240-77471651(HIGH RISK) (1).pdfThe OHS evaluation uses Annexure C1 (High Risk). Each returnable is marked Y (yes), N (no), or N/A. The evaluator makes a recommendation of 'Recommended' or 'Not Recommended'. The annotated fields on the template include the Safety Officer's signature and designation.
Description
Source: SDLI Strategy Replace of Fuel Oil system.pdfHendrina Power Station requires the design and replacement of fuel oil flow meters for a period of 24 months (2 years).
Important Dates
Source: SDLI Strategy Replace of Fuel Oil system.pdf (TENDER)Closing date: 01 April 2023 (as listed in the document identifier effective date; the tender record lists closing date as 19 November 2026 at 08:00). The closing time for the tender is 08:00 according to the tender record.
Contact Information
Source: SDLI Strategy Replace of Fuel Oil system.pdf (TENDER)Business unit: Hendrina Power Station
No individual contact names, emails, or telephone numbers are provided in the document.
Evaluation Criteria
Source: SDLI Strategy Replace of Fuel Oil system.pdf (TENDER)Eskom Hendrina Power Station requires the design and replacement of fuel oil flow meters over a 24-month period. The contract is awarded to the bidder scoring the highest combined points for price and specific goals, in line with the PPPFA.
Preference point system:
B-BBEE preference points table (90/10 system, 80/20 system):
Preference point documentation:
Missing preference point documentation:
Objective criteria (Section 2):
CIDB Skills Development:
Technical Specifications
Source: SDLI Strategy Replace of Fuel Oil system.pdf (TENDER)Hendrina Power Station requires the design and replacement of fuel oil flow meters.
Scope:
Related components requiring local content:
Methodology
Source: SDLI Strategy Replace of Fuel Oil system.pdfSkills development methodology: Bidders are expected to participate in developing critical and scarce skills. They may involve SETA-accredited training providers. Skills development targets exclude Eskom employees and registered learners. Bidders bear the full cost of developing these skills; Eskom will not contribute financially. Bidders are advised to approach relevant SETAs for grants, subsidies, and incentives, and SARS for tax rebates earmarked for skills development.
Pricing Schedule
Source: SDLI Strategy Replace of Fuel Oil system.pdfPricing must be separated into local and imported components as per the Price Schedule. Local procurement content is total spending minus the imported component. Penalties of 1.5% of invoice amount or contract value apply for failure to meet SDL&I obligations. Eskom retains 1.5% of each invoice (excl. VAT) as security for SDL&I obligations until all obligations are fulfilled and reports submitted.
Financial Requirements
Source: SDLI Strategy Replace of Fuel Oil system.pdf (TENDER)Pricing should be submitted in the format of the tender's Price Schedule. Where a contract involves both local and imported goods or services, the tender response must separate the components as per the Price Schedule. Local procurement content is defined as total spending minus the imported component.
SDL&I penalties and retention:
Compliance Requirements
Source: SDLI Strategy Replace of Fuel Oil system.pdf (TENDER)B-BBEE requirements:
Sworn affidavit validity requirements:
Local content requirements:
Ownership documents required to claim preference points:
Health & Safety
Source: SDLI Strategy Replace of Fuel Oil system.pdfThis section does not contain health and safety requirements. It covers the validity requirements for sworn affidavits, which are listed under compliance.
Section
Source: SDLI Strategy Replace of Fuel Oil system.pdfThe contract is awarded to the bidder scoring the highest combined points for price and specific goals. The specific goal is B-BBEE status level. Points for specific goals are added to price points, and the total is rounded to two decimal places. The maximum points for specific goals are 10 under the 90/10 system or 20 under the 80/20 system. Refer to the preference point table in the evaluation criteria section.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 85 of 1993
Sets health and safety duties for contractors, employers and service providers working on public-sector sites.
Relevant because this tender appears to involve architectural, building design, or professional built-environment services.
Act 44 of 2000
Relevant where architectural work or professional building-design services may be required.
Relevant because this tender appears to involve architectural, building design, or professional built-environment services.
Act 103 of 1977
Relevant where building standards, renovations, maintenance or construction compliance may apply.
Relevant because this tender appears to involve architectural, building design, or professional built-environment services.
Address
Eskom Hendrina Power Station Pullens Hope - Pullenshope - Mpumalanga -
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
14
Last checked
29 Oct 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Learn how to submit a winning bid with these related articles
How consulting engineers, engineering firms, and multidisciplinary practices can win public sector infrastructure contracts in South Africa — from ECSA registration and CESA membership to fee proposals, QBS scoring, and building a winning tender response.
A practical guide to using the Tenders-SA Forensic Analysis workbench for supplier audits, department scans, pair analysis, and AI-generated case narratives to identify procurement irregularities.
How Tenders-SA built a forensic analysis workbench that detects procurement irregularities across 80+ indicators spanning 8 families — from market concentration and single-bidder patterns to OCPO restricted supplier cross-referencing and AI-generated case narratives.
How mechanical and electrical engineers, contractors, and consultants can win public sector contracts in South Africa — HVAC, plumbing, fire systems, electrical infrastructure, ECSA registration, CIDB ME designation, and tender documentation essentials.
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Architectural and engineering activities; technical testing and analysis. Unlock full pricing strategies, bid frequency, and historical win rates.