Works: construction of new ablution facilities at Osborn Senior Secondary School.
Site: existing school premises.
Contract: JBCC Principal Building Agreement Series Edition 4.1, March 2005, with Preliminaries JBCC Series 2000, May 2005.
Bills of Quantities measured in accordance with the Standard System of Measuring Building Work, Seventh Edition.
Contractor to provide a 4 x 3m site office with concrete floor, lockable, with tables and chairs for meetings.
Contractor to provide a lockable container or structure for material storage with a concrete or steel floor.
Contractor to provide water, electricity, telephones, and toilet facilities on site.
Contractor to erect hoardings, safety screens, barriers, and access gates for public protection.
Contractor to provide one main notice board.
Contractor to record construction breaks and concrete pours on structural drawings and submit three sets of as-built drawings within 14 days after practical completion.
Contractor to maintain a Construction Instruction Book and Daily Record Book on site.
Contractor to provide weekly written labour and plant records to the principal agent.
Contractor to submit a method statement when required by the principal agent.
Contractor to exclude unauthorised persons from the site and provide shelter for any watchmen.
Contractor to remove all temporary works and make good any damage on completion.