Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
Vaaldam Road - Viljoensdrift - Viljoensdrift - 1930
Organization Type
GOVERNMENT
Published
15 Sept 2026
OCDS Reference
ocds-9t57fa-170518
This invitation to tender (ITT) is issued by ESKOM for the supply and delivery of goods and/or services as detailed in the tender data and price schedule. Tenders must be submitted electronically via the ESKOM e-tendering portal; NO hard copies will be accepted. The contract will be awarded on the 90/10 preference point system (for tenders above r50 million) or the 80/20 system (for tenders at or below r50 million), with points allocated for price and specific goals. Bidders must be registered on the central supplier database (csd) and must not be under any restriction to do business with ESKOM or state-owned companies. The tender includes mandatory contractual requirements, including proof of csd registration and a completed pricing schedule (in pdf and excel for e-tendering). Bidders must complete the standard sbd forms, including sbd 4 (declaration of interest) and sbd 6.1 (Preference points claim). Local procurement content requirements apply, and a penalty of 2.5% Of contract value may be imposed for failure to meet sdl&i obligations; ESKOM will retain 2.5% Of every invoice (excluding VAT) as security for sdl&i obligations. Tenders must be submitted in english and in south african rand. Late tenders will be returned unopened. Alternative tenders are not allowed. Prices will not be read out at tender opening. The tenderer must comply with all eligibility criteria and may not subcontract unless permitted. The closing date and time are as stated in the tender data (not provided in the extracted text).
Bidders must submit their tender electronically via the Eskom e-tendering portal; no hard copy will be accepted.
Bidders must be registered on the Central Supplier Database (CSD) and provide proof of CSD registration as a mandatory contractual requirement.
Bidders must not be under any restriction to do business with Eskom or any State-Owned Company.
Bidders must complete and submit the standard SBD forms, including SBD 4 (declaration of interest) and SBD 6.1 (preference points claim), as part of the tender.
The pricing schedule must be completed and submitted in PDF and Excel format (for e-tendering).
Tenders must be submitted in English and prices must be stated in South African Rand.
The tender will be evaluated using the 90/10 or 80/20 preference point system; bidders must claim specific goals points and may be required to submit evidence of their claims.
Date & Time
Friday, 09 October 2026 - 10:00
Venue
https://teams.microsoft.com/meet/334448949444663?p=jU7VdaOcNh612ybh28
Categories
Request for Bid(Open-Tender)
Vaaldam Road - Viljoensdrift - Viljoensdrift - 1930
Recommended Certifications
Having these can improve your winning chances: SABS Product Certification, NRCS Certification
AI Document Analysis Stages
Compliance Requirements
Source: Quality.zip (unknown)15 Sept
2026
Tender Published
Tender was published
09 Oct
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Quality.zip
Technical.zip
Safety.zip
No summary available
Commercial.zip
Eskom is procuring the supply and delivery of coal reference materials for Lethabo Power Station on an as-and-when-required basis over a 5-year period. The tender is open to eligible suppliers who must submit electronically via Eskom's e-tendering system by the closing date.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
R 1 193 700
Range
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
No document content found in ZIP archive
Important Dates
Source: Commercial.zip (TENDER){"closingDate":"17 June 2025","closingTime":"10:00 am","briefingSession":"{"date":"22 September 2026","time":"10:00 am","venue":"ion Date: 22 September 2026","is_compulsory":false}"}
Contact Information
Source: Commercial.zip (TENDER){"name":"MS teams","email":"[email protected]","phone":"016 457 5294","department":null,"address":"r which may be"}
Evaluation Criteria
Source: Commercial.zip (TENDER)Tenderers must meet the eligibility criteria in the Tender Data, including: not being under any restriction to do business with Eskom or State-Owned Companies; not having a conflict of interest; not being listed on National Treasury's Database of Restricted Suppliers or the Register for Tender Defaulters; not having been convicted of fraud or corruption in the past five years; and not being prohibited from doing business with any International Financial Development Agency. Tenderers must not submit more than one tender (unless as a JV with joint and several liability) and must not subcontract 100% of the scope of work. Tenderers must complete and submit the mandatory returnables, including the Integrity Declaration Form (Annexure D), SBD 1 (Annexure H), SBD 6.1 (Annexure I), and SBD 4 (Annexure J).
Technical Specifications
Source: Commercial.zip (TENDER)provisions above, please complete the table hereunder with all required
Annexure a – integrity declaration form)
information.
Full Name & Capacity/ Identity Confirm and provide Full Names & To your
Position within tenderer (e.g. Number details (including Capacity/Position of knowledge
employee/Director/member/ employee number) if Eskom employee/ is thi
supply identified in the
specification and/or works
payment terms initiative of Eskom, and its aim is to explore the extent to which Eskom can
benefit financially from either extending the supplier payment terms or offering an early
settlement discount.
payment terms, and further guidance will come on early settlement discounts. The document
provides an update on the thresholds on which the 60-day payment term is applicable and
provides guidance on compliance reporting and the applicability of the Policy.
Threshold
of VAT. This means that all contracts exceeding this threshold must be established on the
60-day payment term.
Applicability of policy
However, the Policy is applicable to contracts concluded between subsidiaries and their own
suppliers.
of an extended payment term must be applied as a lever.
Monitoring of compliance
Committee (“Cost Steerco”) on a monthly basis. Divisional Procurement Senior Managers shall
provide reasons for non-compliance to the oCPO on request and shall present these to the
Cost Steerco. This arrangement shall continue until the end of the 2022/23 financial year.
Compiled by: ms reshma maghoo
Contract advisor
Date: 28/9/2022
Guidance note: implementation of supplier payment term policy
Recommended: mr godfrey quickfall
Senior manager: contract management (acting)
Date: 2022-09-28
Supported: ms jainthree sankar
Chief procurement officer
DATE: 5 October 2022
Approved: mr calib cassim
Chief financial officer
DATE: 05 October 2022
Eskom Holdings SOC Ltd Reg No 2002/015527/30
3.15 Evaluation of Price Prices will be evaluated as follows:
schedule’
alternative tenders submitted; and
tender based on the tendered programme (if provided) and
prices, on the estimated effect of Price Adjustment Factors and
rate of exchange fluctuations (if applicable) and on other
evaluation parameters relating to uncertainty and risk, where
applicable.
purposes.
evaluation purposes but will be implemented when payment is
effected.
Prices will be scored out of [80/90] points
3.18 Evaluation of Specific Goals Specific goals will be scored out of [10/20] points in accordance with
the PPPFA.
If a tenderer fails to submit evidence of its points claim for a Specific
Goal, it will not be disqualified. However, it will be awarded 0 points
for that Specific Goal.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 64
File name: Invitation to Tender (ITT) - Supply and delivery of Coal Reference materials (003)
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 26
Identifier
Invitation to Tender
Effective Date 17 June 2025
Review Date June 2030
Clause Number from Standard
Tender Data
Conditions of Tender
Section 1: Specific Goals
A maximum of 10/20 points may be awarded to a tenderer for the specific goal specified for the tender.
The points scored for the specific goal must be added to the points scored for price and the total must be
rounded off to the nearest two decimal places. Subject to section 2(1)(f) of the Preferential Procurement
Policy Framework Act, the contract must be awarded to the tenderer scoring the highest points.
B-BBEE Status Level of Number of points Number of points
Contributor (80/20 system) (90/10 system)
1 20 10
2 18 9
3 14 6
4 12 5
5 8 4
6 6 3
7 4 2
8 2 1
Non-compliant contributor 0 0
NB: The following documents are required to claim preference points,
affidavit
breakdown
consolidated B-BBEE status level verification certificate.
Tenderer failing to provide documentation for the allocation of preference points will not be
disqualified, but’
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 64
File name: Invitation to Tender (ITT) - Supply and delivery of Coal Reference materials (003)
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 26
Identifier
Invitation to Tender
Effective Date 17 June 2025
Review Date June 2030
Clause Number from Standard
Tender Data
Conditions of Tender
Section 2: Objective criteria
N/a
Section 3: SDL&I Objectives in line with Reconstruction and Development Programme (RDP) Goals
Tenderers who complete and submit the objectives as required, but who do not meet Eskom’s targets,
will not be disqualified. SDL&I objectives do not form part of scoring but commitments will form part of
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 64
File name: Invitation to Tender (ITT) - Supply and delivery of Coal Reference materials (003)
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 26
Identifier
Invitation to Tender
Effective Date 17 June 2025
Review Date June 2030
Annexure a
Authorisation form
Indicate the status of the tenderer by ticking the appropriate box below.
A b c d e f
Company close partnership joint sole trust
Corporation venture proprietor
The tenderer must complete the appropriate certificate set out below for its category of organisation.
If the tenderer is a company, close corporation, joint venture, or trust the tenderer must attach a
certified copy the document that is proof of the contents of the certificate (resolution of the board of
directors of a company, members’ resolution of a close corporation, power of attorney in the case of
a joint venture, or resolution of the board of trustees of a trust).
Note further that, in addition to completing the relevant certificate for category of organisation, the
authorised representative of the tenderer is also required to complete and sign the table at the end of
this Authorisation Form.
A. Certificate for company
I,_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ , in my capacity as _ _ _ _ _ _ _ _ _ _ _ of the
board of directors of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, hereby
confirm that by resolution of the board taken on _ _ _ __ _ _ _ _ (date), Mr/Ms _ _ _ _ _ _ _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ , acting in his/her capacity of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, is
authorised to submit this tender on behalf of the company, and to sign all documents in connection
with this tender and any contract that may result from it on behalf of the company. A certified copy of
the resolution of the board is annexed to this Form.
Signed: Date:
Name: Position:
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 64
File name: Invitation to Tender (ITT) - Supply and delivery of Coal Reference materials (003)
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 26
Identifier
Invitation to Tender
Effective Date 17 June 2025
Review Date June 2030
B. Certificate for close corporation
I,_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ , in my capacity as member of _ _ _ _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, hereby confirm that by majority vote of the
members taken on _ _ _ __ _ _ _ _ (date), Mr/Ms _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ , acting
in his/her capacity of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, is authorised to submit this tender
on behalf of the close corporation, and to sign all documents in connection with this tender and any
contract that may result from it on behalf of the close corporation. A certified copy of the members’
resolution is annexed to this Form.
Signed: Date:
Name: Position:
C. Certificate for partnership
We, the undersigned, being the key partners in the business trading as _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ hereby authorise Mr/Ms _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, acting in his/her
capacity of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, to submit this tender on behalf of the partnership,
and to sign all documents in connection with the tender and any contract that may result from it on
behalf of the partnership.
Name Address Signature Date
NOTE: This certificate is required to be completed and signed by the full number of Partners
necessary to commit the Partnership. Attach additional pages if more space is required.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 64
File name: Invitation to Tender (ITT) - Supply and delivery of Coal Reference materials (003)
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 26
Identifier
Invitation to Tender
Effective Date 17 June 2025
Review Date June 2030
D. Certificate for Joint Venture
We, the undersigned, are submitting this tender offer in Joint Venture and hereby authorise Mr/Ms _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, an authorised signatory of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ , being the lead member in the Joint Venture, to sign all documents in connection
with the tender and any contract that may result from it on behalf of all the members in the Joint
Venture.
This authorisation is evidenced by the attached power of attorney signed by the legally authorised
signatories of all the members in the Joint Venture.
We attach to this Form a certified copy of the Joint Venture Agreement which incorporates a statement
that all members in the Joint Venture are liable jointly and severally for the execution of the contract,
a term that indicates which member will be the lead member, and terms that indicate the ratios
according to which work and payment will be divided amongst the members.
Name of JV member Address Authorised signature,
name and capacity
Lead member
Member
Member
Member
NOTE: This certificate is required to be completed and signed by all members of the joint
venture. Attach additional pages if more space is required.
E. Certificate for sole proprietor
I, _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, hereby confirm that I am the sole proprietor of the
business trading as _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Signed: Date:
Name: Position:
(Sole Proprietor)
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 64
File name: Invitation to Tender (ITT) - Supply and delivery of Coal Reference materials (003)
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 26
Identifier
Invitation to Tender
Effective Date 17 June 2025
Review Date June 2030
Certificate for trust
I,_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ , in my capacity as _ _ _ _ _ _ _ _ _ _ _ of the
board of trustees of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, hereby confirm
that by resolution of the board of trustees taken on _ _ _ __ _ _ _ _ (date), Mr/Ms _ _ _ _ _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ , acting in his/her capacity of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
_, is authorised to submit this tender on behalf of the trust and to sign all documents in connection
with this tender and any contract that may result from it on behalf of the trust. A certified copy of the
resolution of the board of trustees is annexed to this Form.
Signed: Date:
Name: Position:
NOTE: The table below must also be fully completed by all tenderers in addition to the
certificate that was selected and completed above.
Name of tenderer:
Full names of authorised signatory:
Designation and capacity:
Signature of authorised signatory
Date of signature:
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 64
File name: Invitation to Tender (ITT) - Supply and delivery of Coal Reference materials (003)
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 26
Identifier
Invitation to Tender
Effective Date 17 June 2025
Review Date June 2030
Annexure b
Acknowledgement form
We are in receipt of the Invitation to Tender/Proposal from Eskom Holdings SOC Ltd and
the following addenda issued by Eskom:
We confirm that the documentation received by us is: (Indicate by ticking the box)
Correct as stated in the Invitation to Tender / RFP Content List, and that each document is
complete.
Or: Incorrect or incomplete for the following reasons:
Cataloguing Acknowledgement:
Please select the relevant statement by ticking the appropriate box below:
Tender
Invitation to Tender in a previous contract/order [insert previous contract/order
number] __________
stated hereunder:
Manufacturer (OEM), is or is not [delete whichever is not applicable] in the position
to supply cataloguing information for items. We attach the letter from the OEM
confirming its position.
Invitation to Tender/Request for Proposal No: ____________________
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 64
File name: Invitation to Tender (ITT) - Supply and delivery of Coal Reference materials (003)
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 26
Identifier
Invitation to Tender
Effective Date 17 June 2025
Review Date June 2030
Name of Tenderer: ___________ _ _
Country of registration: _______________________________________
Full names of contact person: __________________________________
Contact details:
Tel (landline):
Cell phone:
e-mail address:
Name of tenderer:
Full names of authorised signatory:
Supply chain management system should
This declaration prove to be false.
.................................... .....................................................
Signature Date
.................................... ......................................................
Position Name of bidder
income-generating contracts)
of services, works or goods Stipulated minimum threshold
_______________________________ _______%
_______________________________ _______%
_______________________________ _______%
have any imported content?
(Tick applicable box)
Yes NO
3..1 If yes, the rate(s) of exchange to be used in this bid to calculate the local content as
prescribed in paragraph 1.5 of the general conditions must be the rate(s) published
by SARB for the specific currency at 12:00 on the date of advertisement of the bid.
The relevant rates of exchange information is accessible on www.reservebank.co.za
Indicate the rate(s) of exchange against the appropriate currency in the table below
(refer to Annex A of SATS 1286:2011):
Currency Rates of exchange
US Dollar
Pound Sterling
Euro
Yen
Other
NB: Bidders must submit proof of the SARB rate (s) of exchange used.
minimum threshold for local content the dtic must be informed accordingly in order for the
DTIC to verify and in consultation with the AO/AA provide directives in this regard.
Local content declara
supplying entity AND their company registration
number] ......................................................................., certify under oath that, to the best of my
knowledge, the information furnished herein is true and correct. I accept that Eskom reserves its right to
act against the supplier named above or me personally in terms hereof, should this declaration prove to be
false.
Eskom employees and directors that engage in private work
Financial Requirements
Source: Commercial.zip (TENDER)Payment Terms: payment terms as stipulated hereunder when
submitting tenders and concluding contracts with Eskom:
For contracts valued below R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed to paying
Suppliers within 30 days of receipt of undisputed invoices.
For contracts valued above R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed
Compliance Requirements
Source: Commercial.zip (TENDER)joint venture agreement which incorporates a statement that all partners are
No specific requirements found
ADDITIONAL CONTRACTUAL REQUIREMENTS √ SUPPORTING EVIDENCE Safety √ OCCUPATIONAL HEALTH AND SAFETY Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 64 File name: Invitation to Tender (ITT) - Supply and delivery of Coal Reference materials (003) Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 26 Identifier Invitation to Tender Effective Date 17 June 2025 Review Date June 2030 Reference Returnable From Suppliers at at ** closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable) to Tender Returnable Returnable Returnable Contractual requirements mean the service provider will submit the tender returnable during the tender close-out. The evaluation will take place once the mandatory and functionality evaluation have been completed. The service provider will be given only ONE opportunity to submit the outstanding documents within 7 working days. Failure to submit the outstanding documents within the stipulated time; may result in the tenderer being regarded as non- responsive and ineligible for contract award. These OHS requirements will form part of the procurement process and must be complied with prior to signing the contract (Note: these requirements are applicable to the tender phase only). The service provider shall comply with the OHS Safety file requirements which will be issued to the successful bidder, and no work may commence until the Safety file is approved by the Contract custodian together with the OHS professional of the respective site. The tenderer shall submit Safety Returnable as follows
Annexure B Is the acknowledgement of Eskom's OHS legal and other requirements form signed and submitted by the tenderer?
Health and Safety Plan The Safety plan (must address the project /scope of work OHS risk(s) and aligned with the health and safety specification or requirements) Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 64 File name: Invitation to Tender (ITT) - Supply and delivery of Coal Reference materials (003) Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 26 Identifier Invitation to Tender Effective Date 17 June 2025 Review Date June 2030 Reference Returnable From Suppliers at at ** closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable) to Tender Returnable Returnable Returnable
Baseline OHS Risk Assessment (BRA) and Health Risk Assessment (HRA) Identification, assessment, and management of Occupational hygiene and safety risks related to the scope of work. The methodology used for the risk assessment must be provided together with the BRA and HRA. 4.Valid Letter of Good Standing (COIDA or equivalent) 5.OHS policy signed by CEO The submitted policy must comply to OHS Act Section 7
OHS Competency (Consider scope of work, risks, OHS plan and applicability) CV’s and qualifications / certificates (List competencies required) e.g Risk assessor, Incident Investigator
Costing for Occupational hygiene and Safety Management Has the tenderer submitted a detailed costing for OHS (the cost should be broken down not provided as a lump sum).
Risk based Personal Protective Clothing
Medical assessment/ surveillance After contract award the contractor shall: Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 64 File name: Invitation to Tender (ITT) - Supply and delivery of Coal Reference materials (003) Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 26 Identifier Invitation to Tender Effective Date 17 June 2025 Review Date June 2030 Reference Returnable From Suppliers at at ** closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable) to Tender Returnable Returnable Returnable Note this requirement are for tender phase only. After the contract has been awarded the tenderer shall submit a safety file in each power station and work shall not commence until the safety file is approved by the respective site. Quality The Supplier must be Accredited by SANAS as a √ Reference Material Producer in accordance with ISO/IEC17034 for Coal Reference Materials and supply Coal reference materials as detailed in scope of work. Other safety/quality √ documents as required per scope of works Environmental No EIA needed, however, to ensure compliance to √ environmental requirements, ISO14001, Lethabo environmental procedures will be provided with tender documents. Due Audited Financial Statements of the tenderer for the N/A Diligence/financial previous 18 months, or to the extent that such analysis statements are not available, for the last year. In the case of a joint venture or special purpose vehicle (SPV) specially formed for this tender, audited financial statements for each participant in the JV / SPV must be submitted. Start-up enterprises formed within the last 12 months are not required to submit audited financial statements, but if successful in this Invitation to Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 64 File name: Invitation to Tender (ITT) - Supply and delivery of Coal Reference materials (003) Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 26 Identifier Invitation to Tender Effective Date 17 June 2025 Review Date June 2030 Reference Returnable From Suppliers at at ** closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable) to Tender Returnable Returnable Returnable Tender, they will be required to furnish statements for the first year once available. DOCUMENTS REQUIRED UNDER √ FUNCTIONALITY/TECHINICAL CRITERIA Compliance to Technical Specification for the supply and delivery of Coal Reference Materials will be evaluated on a YES or NO basis. (Gatekeeper). Description Returnable with the RFQ/tender YES/NO
The Supplier must supply reference be accredited
B-BBEE Minimum Level: 0
Points Allocation: 0 points
B-BBEE Details: Identifier
Invitation to Tender
Effective Date 17 June 2025
Review Date June 2030
Clause Number from Standard
Tender Data
Conditions of Tender
Section 1: Specific Goals
A maximum of 10/20 points may be awarded to a tenderer for the specific goal specified for the tender.
The points scored for the specific goal must be added to the points scored for price and the total must be
rounded off to the nearest two decimal places. Subject to section 2(1)(f) of the Preferential Procurement
Policy Framework Act, the contract must be awarded to the tenderer scoring the highest points.
B-BBEE Status Level of Number of points Number of points
Contributor (80/20 system) (90/10 system)
1 20 10
2 18 9
3 14 6
4 12 5
5 8 4
6 6 3
7 4 2
8 2 1
Non-compliant contributor 0 0
NB: The following documents are required to claim preference points,
affidavit
breakdown
consolidated B-BBEE status level verification certificate.
Tenderer failing to provide documentation for the allocation of preference points will not be
disqualified, but’
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in l
Section
Source: Commercial.zip1.1.9 *SBD 6.1 Preference Points Claim Form in terms of Annexure I Y
PPPFA 2022 regulations
1.1.11 Tax Evaluation questionnaire to determine whether a N/A
3.13 Functionality requirements Functionality requirements are applicable
functionality criteria
with ISO/IEC17034:2016 ISO/IEC17034:2016 for Coal Reference Materials.
3.15 Evaluation of Price Prices will be evaluated as follows
Section 1: Specific Goals
A maximum of 10/20 points may be awarded to a tenderer for the specific goal specified for the tender.
The points scored for the specific goal must be added to the points scored for price and the total must be
Policy Framework Act, the contract must be awarded to the tenderer scoring the highest points.
B-BBEE Status Level of Number of points Number of points
Contributor (80/20 system) (90/10 system)
NB: The following documents are required to claim preference points,
Tenderer failing to provide documentation for the allocation of preference points will not be
Quality The Supplier must be Accredited by SANAS as a √
ISO/IEC17034 for Coal Reference Materials and
Other safety/quality √
Functionality/techinical criteria
evaluation parameters relating to uncertainty and risk, where
evaluation purposes but will be implemented when payment is
Prices will be scored out of [80/90] points
Description
Source: Safety.zipThe scope is the supply and delivery of coal reference materials for a period of 5 years, on an as-and-when-required basis, at Lethabo Power Station. The contractor must retain a copy of the scope of work and comply with the OHS specification.
Important Dates
Source: Safety.zip (unknown){"briefingSession":"{"date":null,"time":null,"venue":"ion reports to the relevant management.","is_compulsory":false}"}
Contact Information
Source: Safety.zip (unknown){"name":null,"email":null,"phone":null,"department":null,"address":"aterials for a period of 5 years,"}
Submission Guidelines
Source: Safety.zip (unknown)Submit the tender to Eskom at Lethabo Power Station, Deneysville/Viljoensdrift Road, Private Bag X415, Vereeniging, 1930 SA. The closing date and time are not stated in the available text. Bids must be submitted in the required format; failure to complete and sign all returnable documents may lead to disqualification.
Evaluation Criteria
Source: Safety.zip (unknown)The evaluation criteria are not stated in the available text. However, compliance with the OHS specification is mandatory, and the contractor's OHS performance will be assessed. The contractor must provide method statements and task risk assessments for all work.
Technical Specifications
Source: Safety.zip (unknown)Eskom’s responsibility and commitment is to ensure a safe working environment is in line with its
Safety, Health, Environmental, and Quality (SHEQ) Policy and applicable legislative obligations.
This OHS specification is Eskom Generation's minimum requirements which are required to be
met for the duration of the contract period by contractors/suppliers and, where required, the
delivery organisation. The contractor is expected to develop an OHS plan that meets these
requirements as well as all the relevant applicable legislation that they conform to. Eskom in no
way assumes the contractor’s legal responsibilities and liabilities. The contractor is and remains
accountable for the quality and execution of their health and safety programme for their employees
and appointed contractor employees. This OHS specification reflects minimum requirements and
should not be construed as all-encompassing.
Note 1: All the requirements listed hereunder are in relation to the contract and do not supersede or
replace any organizational OHS requirements.
Where requirements listed are already in place, then the organizational requirements must be
taken cognisance of and listed in the respective OHS plans. If there are any additional Eskom
and/or legislative requirements listed in the OHS specification, then these must be addressed.
2.1 Scope
This OHS specification lists the legislative and Eskom requirements and, where applicable, any
requirements pertaining to local authorities, municipal by-laws, or environmental legislation that
must be met by the contractor.
2.1.1 Purpose
This document will provide a standardised approach to the compilation of OHS specifications
throughout Eskom Generation business for contracts, standards, and NEC 3.
2.1.2 Applicability
This OHS specification is applicable to any contracting organisation that intends to respond to
Eskom Generation's tender/enquiry with the intention of entering into a contract.
2.2 Normative/informative references
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
2.2.2 Informative
2.3 Definitions
Definition Explanation
Appointed contractor Means a contractor appointed by the Main contractor
Baseline risk assessment (32-520) baseline operational risks refer to the health and safety risks
associated with all standard processes and routine activities in the
business
Business unit (BU) (32-296) means any defined unit within the Eskom environment,
operating as a business under a particular cost-centre number. In the
context of this document and in terms of health and safety, any
reference to a BU includes a defined unit within any Eskom division and
its subsidiaries
Client (OHS Act) Eskom representative (Internal – Asset Owner), also referred
to as the contract administrator/custodian or agent or project manager
(as defined in the contract). He/she is the person responsible for
ensuring that the works or services are executed in terms of the
contract, as well as adherence to legislation pertaining to the contract.
Competent person (OHS Act) means any person having the knowledge, training,
experience, and qualifications, specific to the work or task being
performed, provided that, where appropriate, qualifications and training
are registered in terms of the South African Qualifications Authority Act,
1995 (Act No. )
Contractor (OHS Act) means an employer as defined in section 1 of the Act who
performs contracted work and includes Main contractors
Contract’s Manager/End Contract’s Manager/End User
User
Consultant means a person providing professional advice
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
Definition Explanation
Controlled disclosure controlled disclosure to external parties (either enforced by law or
discretionary)
Duty of care to the (32-136) anybody who causes or has caused or may cause significant
environment pollution or degradation of the environment must take reasonable
measures to prevent such pollution or degradation from occurring,
continuing, or recurring. If such harm to the environment is authorised
by law or cannot reasonably be avoided or stopped, such person must
minimise and rectify such pollution or degradation of the environment
Employee (OHS Act) means, subject to the provisions of subsection (2), any
person who is employed by or works for an employer and who receives
or is entitled to receive any remuneration or who works under the
direction or supervision of an employer or any other person
Employer (OHS Act) means, subject to the provisions of subsection (2), any
person who employs or provides work for any person and remunerates
that person or expressly or tacitly undertakes to remunerate him/her,
but excludes a TES (ex labour broker) as defined in section 1(1) of the
Labour Relations Act 1956 (Act No. )
Environment (32-94) means:
the land, water, and atmosphere of the earth;
micro-organisms and plant and animal life; and
any part or combination of (a) and (b) and the interrelationships among
and between them, and the physical, chemical, aesthetic, and cultural
properties and conditions of the foregoing that influence human health
and well-being
Eskom requirements Eskom requirements flowing from directives, policies, standards,
procedures, specifications, work instructions, guidelines, or manuals
Fall protection plan (OHS Act) means a documented plan of all risks relating to working from
an elevated position, considering the nature of work undertaken, and
setting out the procedures and methods to be applied in order to
eliminate the risk
Hazard (OHS Act) means a source of, or exposure to, danger
Hazard identification (OHS Act) means the identification and documenting of existing or
expected hazards to the health and safety of persons, which are
normally associated with the type of construction work being executed
or to be executed
Occupational Health and (OHS Act) means a file or other record in permanent form, containing
safety file the information required in relation to the contract.
Health and safety plan (OHS Act) means a document plan that addresses hazards identified
and includes safe work procedures to mitigate, reduce, or control
hazards identified
Occupational Health and (OHS Act) means a document specification of all health and safety
safety specification requirements pertaining to associated to a contract, so as to ensure the
health and safety of persons.
Occupational Health and means comprehensive health and safety requirements for a contract,
safety requirements project, site, and scope of work. This specification is intended to ensure
the health and safety of persons, both workers and the public, and the
duty of care to the environment. The health and safety requirements
must be specific to each contract, project, site, and scope of work
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
Definition Explanation
Lifesaving Rules (240-62196227) a rule that, if not adhered to, has the potential to cause
serious harm to people
Medical Certificate of fitness (OHS Act) means a certificate valid for one year, issued by an
occupational health practitioner, issued in terms of the regulations,
whom shall be registered with the Health Professions Council of South
Africa
Medical surveillance (OHS Act) means a planned programme or periodic examination (which
may include clinical examinations, biological monitoring, or medical
tests) of employees by an occupational health practitioner or, in
prescribed cases, by an occupational medicine practitioner
Method statement (OHS Act) means a written document detailing the key activities to be
performed in order to reduce, as reasonably as practicable, the hazards
identified in any risk assessment
National Enquiries/contracts sourcing of services providers/contractors at the divisional level and not
at BU level thorough tendering, request for price etc
Organisation may be defined as a group of individuals (large of small) that is
cooperating under the direction of executive leadership in
accomplishment of certain common objects
Pre-job meetings (34-227) means a meeting that is held prior to the commencement of
the day’s work and that is attended by all the relevant employees
associated with the work task
Main contractor (In the text of this document) Means an employer, as defined in section
1 of the OHS Act, who intends to tender for or has signed a contract
with Eskom for services rendered.
Provincial director (OHS Act) means the provincial director as defined in Regulation 1 of
the General Administrative Regulations under the Act
Responsible Manager Is a Manager of a department, section or operating/business unit who
has been appointed as part of the Eskom delegation of authority
process with the aim to assist the applicable 16(2) assigned person in
executing his/her duties in terms of the Occupational Health and Safety
Act
Risk assessment (OHS Act) means a programme to determine any risk associated with
any hazard at a construction site in order to identify the steps needed
to be taken to remove, reduce, or control such hazard.
Site (34-228) means an Eskom department, unit, complex, building, specific
project, work site, or the site where agents, clients, Main contractors,
contractors, suppliers, vendors, and service providers provide a service
to Eskom, directly or indirectly
Service provider any private person or legal entity that provides any service(s) to Eskom
for compensation
Subsidiary (32-94) an enterprise controlled by another (called the parent) through
the ownership of greater than 50% of its voting stock
Supplier (32-1034)means a natural or legal person who renders a service and
may include the following current or potential supplier vendor,
contractor, consultant
Task (34-227) a segment of work that requires a set of specific and distinct
actions for its completion
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
Definition Explanation
Toolbox talks (34-227) where the team leader, after conducting pre-task planning,
shares all the tasks at hand and discusses task allocation, the identified
risks, and the control measures with all his/her team members on site
before commencing a specific task and documenting the agreed
strategy. (This shall be done to ensure common understanding of the
tasks, risks, and control measures required.)
The Act (OHS Act) means the Occupational Health and Safety Act No. , as amended, and the Regulations thereto
Visitor any person visiting a workplace with the knowledge of, or under the
supervision of, an employer.
2.4 Abbreviations
Abbreviation Description
BU Business Unit
CE Chief Executive
COID Act Compensation for Occupational Injuries and Diseases Act
DMR Driven Machinery Regulations
DEL Department of Employment and Labour ( Inspection and Enforcement services
– Provincial office)
EP Emergency Preparedness
EAP Employee Assistance Program
ERfW Environmental Regulations for Workplaces
GAR General Administrative Regulations
GSR General Safety Regulations
HCS Hazardous Chemical Substances
LDV Light Delivery Vehicle
MSDS Material Safety Data Sheets
OHS Act Occupational Health and Safety Act and Regulations,
O&M Operating and Maintenance
LoG (COID) Letter of Good Standing
SABS South African Bureau Standard
SANS South African National Standard
2.5 Related/supporting documents
Section 37(2) of the OHS Act requires Eskom to sign an agreement and include it in the OHS file
for evaluation prior to the start of work. OHS department will issue the 37(2) agreement to the
project manager/end user who will facilitate the signing of the document by Eskom and contractor
representatives.
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
3.1 Scope of work
Supply and delivery of Coal Reference materials for a period of 5 years, on an as and when required
basis, at Lethabo Power Station
A copy of the scope of work must be retained by the contractor.
Note: The contractor who will be awarded this contract will be known as the “Main contractor”
and any contractor appointed by the Main contractor will be known as the “Appointed contractor"
3.2 Legal compliance
3.2.1 Section 37(2) (Legal) Agreement
A section 37(2) agreement must be signed between Eskom and the main contractor at the time of
submitting the safety file. The main contractor must ensure that a section 37(2) agreement is
compiled between the main contractor and all their appointed contractors for the contract. The
original copy of the section 37(2) agreement must be retained by the contractor, and a copy must
be retained by the responsible project manager/end user. A copy of all the agreements must form
part of the respective contractor’s OHS file.
3.2.2 Hazardous Work by Children (Child Labour)
The constitution of the Republic of South Africa, in the "Bill of Rights", is clear on the rights of
children, especially when it comes to:
moral, or social development and the Basic Conditions of Employment Act, Chapter six,
Section 43, "Prohibition of employment of children."
Before resorting to the use of child labour, due consideration must be given to the child's
constitutional rights. Where work is being performed which is not prohibited in terms of the
constitution, then such work must be conducted in terms of the OHS Act "Regulations on
Hazardous Work by Children in South Africa" with emphasis on paragraph 2: Purpose and
Interpretation. Eskom does not condone the use of child labour and, therefore, all effort must be
exercised, and child labour should not be used.
3.2.3 OHS Act
The main contractor and appointed contractors shall have an up-to-date copy of the OHS Act and
regulations which will be available to all employees.
3.2.4 Legislative Compliance
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
All contractors will comply with all the legislation pertaining to this contract being:
The Main contractor and all appointed contractors will comply with all the legislation pertaining to
this project being:
Rights).
3.3 ESKOM requirements
All contractors shall, before commencement of the project ensure that all their employees are
familiar with the relevant Eskom OHS documentation that is applicable to contract services.
3.4 Sheq policy
A SHEQ policy is a statement of intent and a commitment by the organization’s CE and senior
management in relation to the relevant OHS roles and responsibilities, the achievement of their
strategic objectives, and values of integrity, customer satisfaction, excellence, and innovation. The
main contractor and all appointed contractors, if not already in place, will be required to compile
an organisational SHEQ policy in line with their OHS responsibilities. The policy must be signed
by the organisation’s CE or the appointed assistant to the CE, OHS Act Section 16(2). The policy
must be displayed in a prominent place within the workplace. A copy of the policy must be filed in
the contractor's OHS files and attached as an annexure to the OHS Plan.
3.6 Coid
The Main contractor and all his/her appointed contractors shall be registered with an appropriate
employment compensation commissioner and have available a valid letter of good standing (LoG)
from such commissioner. The obligation lies with the contractors to ensure that the LoG remain
valid throughout the contract period. A copy of the LoG must be filed in the contractor OHS files.
3.7 Costing for OHS within the project
The costing for OHS must be itemised based on the overall scope of the project (i.e.) Training,
provision of PPE, safety equipment purchases etc.
'
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
3.8 Statutory appointments
The Main contractor and all appointed contractors must appoint competent workers who will
comply with the OHS Act for the duration of the contract. Before requiring appointees to accept an
appointment, the employer must ensure that they have received appropriate training and/or
information about their responsibilities. The relevant statutory appointments must be made in
compliance with the OHS Act's criteria, which include appointing a qualified individual to the
appropriate roles. The following should be included in the statutory appointments, but not limited
to:
3.8.1 Non statutory appointments
3.9 ESKOM life-saving rules
work for Eskom to do the same.
consultants, and contractors. Any Eskom employee or employee of a Main Contractor or appointed
contractor who fails to follow these rules would be deemed a serious violation. These rules are in
place to protect any employee, labour broker, or contractor working from significant injury or death.
the rules shall be obeyed by any contractor and their employees.
The rules are:
Rule description of rule
Open, isolate, test, earth, bond, and/or insulate before touch
Rule 1
( That is plant, any plant operating above 1000 V)
Hook up at heights
Rule 2 Working at height is defined as any work performed above a stable work surface or where a person puts
himself/herself in a position where he/she exposes himself/herself to a fall from or into.
Buckle up
Rule 3 No person may drive any vehicle on Eskom business and/or on Eskom premises:
Unless the driver and all passengers are wearing seat belts.
Be sober
Rule 4
No person is allowed to be under the influence of intoxicating liquor or drugs while on duty
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
Permit to work
Rule 5
Where an authorisation limitation exists, no person shall work without the required permit to work.
Ensure safe live working
Rule 6 All live work basic principles must be adhered to, as outlined (for the method being used) in the
High Voltage Live Working Standard for the respective Eskom division.
Rule 7
Use of cellphones on site
Site
Use of cell phones (either texting or talking) when walking or driving is strictly prohibited.
Specific
Eskom will take a zero-tolerance approach to these policies.
Noncompliance to Life-saving rules is regarded as a serious misconduct and will result in serious
disciplinary action, which may include dismissal.
This is to ensure that everyone who works on or visits an Eskom facility returns home to their
families safely.
3.10 Substance abuse
comes to workplace accidents and car driving. As a result, Eskom has the right to take
reasonable procedures to identify and prohibit drunk people from entering the company.
taking into account that this is an Eskom Life-saving Rule number 4: (BE SOBER"), and
anyone entering the Eskom site will be subjected to ad hoc alcohol testing if the BU has
self-alcohol testing equipment.
alcohol on a regular basis.
commencement of work.
3.11 Contractor organisational structure
3.11.1 Main Contractor Organogram
The Main contractor must provide an organisational organogram on the company’s letter head
related to this contract, depicting all the levels of responsibility from the CE down to the supervisors
responsible for the contract. List the relevant positions held, names of appointees, legal
appointments and the Organogram must be signed off by the company's 16(1) or 16 (2).
The Main contractor must ensure that all appointed contractors comply with this requirement. The
Main contractor is responsible for keeping copies of all the organograms’ as well as submitting
them with the OHS plan. All organograms shall be updated timeously when appointments are
changed.
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
This diagram must be kept up to date and filed in the project OHS files.
3.11.2 Appointed Contractor/s Organogram
on the company’s letter head, listing the reporting structure from their CE down to their
project supervisors. The diagram must list the names, positions held, any appointments
made and must be signed off by the company's 16(1) or 16 (2).
and a copy filed in the relevant project OHS files.
3.12 Roles and responsibilities
Commitment
Visible commitment is essential to providing a safe work environment. Managers, supervisors and
employees at all levels must demonstrate their commitment by being proactively involved in the
day to day operations, in particular the Occupational Health and Safety aspects of any project /
contract. Legislation requires that each employee must take reasonable care of themselves and
their fellow workers, from management level down to the lowest employee level.
Managers and Supervisors will be required to submit 4(four) BSO(Behavioural Safety Observation)
a month to Lethabo Safety Department @ [email protected]
The 16.1 is required to submit at least 1(one) VFL to Lethabo Safety Department @
3.12.1 Main contractors and appointed contractors
Note 1: Most of the roles and responsibilities listed apply to both Main contractors and any appointed
contractors. Where some of the listed do not apply to both, then the specific responsibilities will be
listed and titled. The contractors shall:
part of the OHS Act and Regulation 7 of the Construction Regulations.
their appointed contractors within their working area, as contemplated by section 37(2) of
the OHS Act;
including date of induction, relevant skills and licenses and be able to produce this list at
the request of the Eskom Project Manager.
responsibilities in terms of their appointment and that they advise and assist these
appointees in the execution of their duties.
complied with on all work sites.
participation and cooperation.
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
records must be kept for each work site.
Commissioner’s valid letter of good standing before the commencement of work and any
future renewal letters obtained during the contract for record-keeping purposes. The letter
of good standing shall reflect the name of the contractor’s company. Similarly, the Main
contractor must provide the Eskom project manager with all the valid letters of good
standing from their appointed contractors.
Commissioner’s valid letter of good standing before the commencement of work and any
future renewal letters obtained during the contract for record-keeping purposes. The letter
of good standing shall reflect the name of the contractor’s company.
trained in the health and safety aspects relating to such work and that the employees
understand the hazards associated with all other work being carried out on the project.
adhere to such procedures. Similarly (without removing the appointed contractors’
responsibilities), ensure that their appointed contractors and their employees are
conversant with all relevant work procedures and that they adhere to such procedures.
health;
for the cost of safety and health measures throughout the project.
health and safety of persons or a risk of degradation to the environment.
evaluate, and assess the appointed contractors OHS files. Only appoint contractors who
are competent to do work, have satisfied the OHS compliance requirements and satisfied
that the contractor has the necessary competencies and resources to perform the work
safely.
specified work throughout the contract period.
site for which such supervisor has been appointed for.
safety information or suspecting such information has been divulged, in the interests of
health and safety requirements.
contractor employees have transgressed any of the requirements of the health and safety
specification, safety and health plans, site rules or any other requirements.
include site or emerging risks. This should be done by a competent person appointed in
writing with a view to identify hazardous and potentially hazardous work operations.
the starting of any new task, irrespective of whether it is a repetitive task or not.
contract is in place and maintained.
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
person/man job specifications must be compiled and handed to the occupational health
practitioner.
employees, inspect such equipment regularly and ensure recipients of PPE are trained in
the proper use, care and where necessary, the maintenance of PPE;
they will be held responsible for the provision and wearing PPE.
investigators as and aligned with 32-95 requirements.
his/her approval prior to them commencing work.
3.12.2 Contractor site supervisor
Contractor Management and site supervisor requirements
The Contractor Section 16.1/16.2 must be trained in the following:
The contractor site supervisor must be trained in the following:
Person, Legal liability;
Must:
and Eskom project requirements;
Inspect all work done by the contractors to ensure adherence to Eskom’s standards and
Conduct follow-up inspections to ensure findings are closed out and preventative action
is in place.
the first instance and thereafter the Eskom project manager in the second instance
relating to procedure requirements, non-conformances identified, corrective actions,
audits and inspection schedules.
procedures, work instructions and safety regulations issued by Eskom:
inspection reports.
incident statistics report etc.
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
meetings.
perform the tasks assigned.
contractors deviate from safety requirements.
3.12.3 Contractor Health and Safety officer part time
The Safety Officer for this contract shall be full time on for the whole duration of this contract
The contractor health and Safety officer must be trained in the following:
National Diploma in Safety Management, which is a must have, HIRA, Incident
investigation training, Legal liability Training, Minimum work experience 3yrs,
3.13 RISK ASSESSMENT (refer to 32-520)
It is a legal requirement in terms of Section 8 (2)(d) of the OHS Act for an employer to carry out
risk assessments, to establish which risks and hazards are attached to the health and safety of
persons due to any work which is performed, any article or substance which is, handled, stored,
transported. A risk assessment is defined as an identification of the hazards present in the activity,
work, site, and an estimate of the extent of the risks involved, considering whatever precautions
are already being taken.
It is essentially a three-stage process:
Risk assessments are required to be maintained. This means that significant changes to a process
or activity, or any new process or activity should be subjected to a risk assessment and that if new
hazards become known during the work process, then these should also be subjected to risk
assessments. Risk assessments for long-term processes should be periodically reviewed and
updated. Method statements or written safe work procedures are an effective method as
information and record of the way jobs / tasks must be performed. Daily or issue based or task
specific or on the job risk assessments must be conducted at the place where work is to be
performed/ conducted to allow managers and employees to assess any inherent risks that could
have been overlooked during the initial risk assessment or any changes that might have occurred
in a period of absence. For example if a job / task is extended over a day or halted due to inclement
weather.
Guidelines for actual steps involved in a job/task specific risk assessment are:
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
procedures exist for ladders.
to rectify this shall be recorded, and safe working procedures drawn up.
nominated and duly assigned.
must be nominated.
for comment and approval.
Supervisor nominated as the responsible person; and the names of workmen who have
received instruction on the work content and the sequence of the activities listed in the
risk assessment shall be recorded, and their competence established. This instruction
shall be done through an interpreter if required and recorded on the Pre-Job Brief (Daily
Safe Task Instructions), with reference to applicable Risk Assessments.
Consequence criteria
Consequence rating Description
Quality Management
Source: Safety.zipDEL Department of Employment and Labour ( Inspection and Enforcement services
– Provincial office)
comes to workplace accidents and car driving. As a result, Eskom has the right to take
reasonable procedures to identify and prohibit drunk people from entering the company.
taking into account that this is an Eskom Life-saving Rule number 4: (BE SOBER"), and
anyone entering the Eskom site will be subjected to ad hoc alcohol testing if the BU has
self-alcohol testing equipment.
Person, Legal liability;
Must:
and Eskom project requirements;
specifications
is in place.
the first instance and thereafter the Eskom project manager in the second instance
relating to procedure requirements, non-conformances identified, corrective actions,
audits and inspection schedules.
procedures, work instructions and safety regulations issued by Eskom:
inspection reports.
incident statistics report etc.
o List of agenda items:
o Matters arising from previous minutes
o Matters arising from Contractor’s OHS meetings.
o Covid-19 compliance
o Audit results and feedback
o Review Health and Safety Representative Inspection Reports
o Review
Incident investigation reports
Non-Conformances
Announcements (near miss/injury/damage)
Follow up on recommendations made by the employer in incident
investigation reports
o Accident Prevention – Safety Promotion
Planned Job Observations
OHS Training
Protective clothing and equipment
Incident Announcements / Recall
o Forthcoming High hazard activities.
o Non-conformances.
o Housekeeping.
o Work permits.
least 30 (thirty) meters must be left clear between such a vehicle and such a machine.
ensure maintenance of satisfactory standards. The Main contractor shall document the
results of each inspection and shall maintain records for viewing.
3.27 Stacking and storage
used on the project. Such tools and equipment’s shall be subjected to regular inspections.
inspection themes will differ from month to month, and the deviation picked up will be immediately
addressed by the main contractor. These audits shall be attended by the contractor’s site manager
or his representative.
implementation of their OHS Plan on a yearly basis or when the scope of work changes. A
summary of the findings and the proposed corrective actions shall be submitted to Eskom project
manager within one week after completion of the audit. Where appointed contractors are audited
by the Main contractor a copy of the audit report shall be submitted to the appointed contractor
within 7 days of the audit.
3.33 Smoking
3.41 Non-conformance and compliance
in place) for issuing to contractors for transgressions. The procedure can include “quality”
related non-conformance issues. Similarly, appointed contractors must implement a non-
conformance procedure.
procedure will be for the offender to be called by the responsible project manager to
explain the non-conformance issued and what plan is in place to prevent a recurrence of
the non-conformance.
employees for the tasks being performed and/or to visitors; failure to enforce the wearing
of such PPE will be viewed as a transgression of the legislative and Eskom requirements.
3.43 OHS files
than one site per project, a file per site shall be kept at that site. Contractors may keep
additional files at their head office as additional records. The OHS file shall be maintained
by all the contractors on their project sites and shall be available on request for audit and
inspection purposes.
Compliance Requirements
Source: Safety.zip (unknown)The contractor must sign a Section 37(2) agreement with Eskom and with any appointed subcontractors. The contractor must provide a SHEQ policy, an organisational structure diagram, and a communication strategy for OHS issues. The site supervisor must be trained in legal liability, HIRA, and incident investigation. The contractor must ensure a medical surveillance programme is in place and maintain an OHS file for each work site. Cell phone use on site is restricted. Eskom's life-saving rules must be included in induction.
Health & Safety
Source: Safety.zip1 No injuries or health effects(near misses)
2 First-aid treatment case, and temporary discomfort case
3 Medical treatment case; occupational disease with reversible/non-permanent effect
4 Lost Time Injury. Irreversible health effects/occupational disease with permanent consequence
5 Fatality or life threatening health effects
6 Multiple fatalities
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
Likelihood criteria
Score Descriptor Safety and Environment Occupational Hygiene
Exposure Probability of exceeding OEL
▪ <5% probability
▪ occurrence requires
exceptional circumstances
1 Highly unlikely ▪ exceptionally unlikely, even in Rare(once a year) No exposure (or exposure < 10% of OEL)
the long-term future
▪ only occurs as a “100-year
event”
▪ >5% probability, or
▪ may occur but not anticipated,
Short periods of time, a few times per day / intermittent
2 Unlikely or Low exposure (<50% of OEL)
(once in 6, 3 or a month)
▪ could occur in “years to
decades”
▪ >20% probability, or
▪ may occur shortly but a distinct
3 Possible probability it will not, or Continuous for between 1 and 2 hours (often / weekly) Moderate exposure (chronic exposure > 50% of OEL or acute exposure >/-OEL
▪ could occur within “months to
year\s”
▪ >70% probability, or
▪ balance of probability it will
4 Likely Continuous for between 2 and 4 hours (frequent / daily) High exposure (chronic exposure > OEL, or exposure exceeding OEL-STEL)
occur, or
▪ could occur within “weeks to
months”
▪ 99% probability, or
5 Unavoidable ▪ impact is occurring now, or Continuous for 8 hour shift Very high exposure (chronic exposure > 2 x OEL or exposure exceeding OEL-C
▪ could occur within “days to
weeks”
Risk matrix
6 iii ii i i i
5 iii ii ii i i
4 iv iii ii i i
3 IV III II II I Consequences 2 IV IV III II II
1 iv iv iii iii iii
1 2 3 4 5
Likelihood
Priority Risk ranking Action required
I Very high Immediate action required
Strong mandatory action
II High
required
Action required, possibly at
III Medium
administrative level
IV Low Minor or no action required
3.14 Safe work procedures / method statements
There must be written safe work procedures for all activities, the safe work procedures must align
with the risk assessments. Method statements / written safe work procedure are control measures
used to prevent an incident from occurring during the execution of the project. A written safe work
procedure/ method statements provide guidance how to execute the task safely. A safe working
procedure should be written when: -
a. Designing a new job or task.
b. Changing jobs or task;
c. Introducing new equipment or substances; and
The safe working procedure should identify:
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
a. The supervisor for the task or job and the employees who will undertake the task;
b. The tasks that are to be undertaken that pose risks;
c. The equipment and substances that are used in these tasks;
d. The control measures that have been built into these tasks;
e. Any training or qualification needed to undertake the task;
f. The personal protective equipment to be worn;
g. J. Actions to be undertaken to address safety issues that may arise while undertaking
the task.
3.15 Fire equipment and maintenance
a. Be clearly labelled
b. Conspicuously numbered
c. Entered in a register
d. Inspected monthly by a competent person
Tested and serviced every 12 months.
Results entered in the register and signed by competent person.
Main Contractor/s and their appointed contractors must develop a communication strategy
outlining how they intend to communicate OHS issues to their staff, the mediums they will
employ and how they will measure the effectiveness of their OHS communication. Below
is a brief on how communication should take place. Where project meetings are
conducted on site, OHS shall be included as a standing agenda point and minutes of
these meetings shall be available on site at all times. Minutes of meeting must be compiled
and filed in the relevant OHS files. All employees shall have access to these minutes.
Attendance register shall be kept for all the health and safety meetings.
3.19.1 Statutory Health and Safety Committees
Section 19 of the OHS Act. Similarly, appointed contractors shall establish their own
statutory health and safety committee.
performed, training, upcoming work and OHS requirements, incidents and lessons
learned specific OHS problems, safety performance, action plans and other relevant OHS
issues. Listed below is a preferred agenda.
committees (Refer to Section 19 (2) (a) of the OHS Act).
Safety Representatives on that specific statutory health and safety committee. (Refer to
Section 19(2)(c) of the OHS Act)
medium to high risk work is involved, more frequent if required), and all appointed
members of the committee shall attend the meeting.
contractor and the project manager and the Inspector at DEL.
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
and 25 incidents and other notified serious incidents.
and shall keep record of all recommendations made by the committee.
current standards, procedures and practices.
statutory health and safety committees carry out their duties.
the contractor. The appointed chairperson must be competent to chair meetings and be
able to make informed decisions.
3.19.2 Non-statutory health and safety committees
within that worksite to assist with the communication of health and safety related matters
between the statutory health and safety committee and the workplace.
the same as the statutory safety committee
Representative is appointed or join Eskom monthly departmental meetings
3.19.2.1 Agenda
o List of agenda items:
o Matters arising from previous minutes
o Matters arising from Contractor’s OHS meetings.
o Covid-19 compliance
o Audit results and feedback
o Review Health and Safety Representative Inspection Reports
o Review
Incident investigation reports
Non-Conformances
Announcements (near miss/injury/damage)
Follow up on recommendations made by the employer in incident
investigation reports
o Accident Prevention – Safety Promotion
Planned Job Observations
OHS Training
Protective clothing and equipment
Incident Announcements / Recall
o Forthcoming High hazard activities.
o Non-conformances.
o Housekeeping.
o Work permits.
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
o Work procedures.
o Hazardous materials / substances.
o Fire Prevention
o Occupational Hygiene Assessments, Health Risks and Actions
o Security
o Rules, Instructions
o Public Safety
o Environmental Management
o Emergency Preparedness
o Statistics report
o Closure
3.19.2.2 Minutes and action items for all health and safety committee meetings
meetings.
minutes and shall be completed during the meeting.
be kept for the duration of the project or a minimum period of three years.
of the project or a minimum period of 12 months.
period of 12 months.
chairperson.
his/her recommendations and return the minutes to the relevant contractors chairperson
within 14 calendar days of the meeting.
3.20 Tool box talks / daily team talks / pre job meetings
personnel associated with the work task in attendance. The job, relevant procedures,
associated hazards, safety measures, i.e. the task risk assessments shall be discussed.
Each employee who attends the briefing shall sign an attendance list of that pre-job brief
form undertaking that they have an understanding of the tasks, risks and control measures
required.
not occur, then weekly tool box talks must be conducted. The toolbox talk topics will be
based on OHS issues pertaining to the project site. The topic and the contents shall be in
writing. Attendance registers with the topic listed shall be kept.
3.21 OHS training
the OHS training requirements and the costing of such requirements. Similarly, appointed
contractor must provide the same requirements when bidding with the Main contractor.
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
the relevant procedures. Additional to the requirements, will be that the Main contractor
and appointed contractors must have the appropriate qualifications, certificates and
employees should always be under competent supervision.
shall be given to those appointees prior to the acceptance of those appointments.
OHS plan, all affected staff shall undergo the applicable refresher training.
OHS file.
3.21.1 Main Contractor Induction training
The contractor is required to arrange with the Business Unit for its employees to attend induction
in order to be granted permission to access site.
their employees have undergone the Eskom OHS induction training prior to commencing
work on site.
indicate that they have received and understood the induction training.
medical examination and found fit for duty. A copy of the certificate of fitness must be kept
in the OHS file on site for the duration of the project.
3.21.2 Appointed Contractor induction training
The Main contractor shall ensure that all his / her employees and appointed contractor employees
undergo site-specific work induction with regard to the approved project OHS plan, hazards
prevalent on the work site, scope specific risk assessment, rules and regulations, and other related
aspects. The induction training should also include identification of sensitive features such as
wetlands/vlei areas, red data species, graves, etc.
3.21.3 Visitors to site induction
safety induction prior to being allowed access to site.
inducted. No visitors are permitted to undertake any work onsite, of any nature.
Induction training.
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
3.22 General training
The Main contractor will be required to ensure that before an employee commences work on the
project/site, the respective supervisor informs the employee of his scope of authority, the hazards
associated with work as well as the control measures to be taken. This will include man-job
specifications, the discussion of any task procedures or hazardous operational procedures to be
performed by the employee. The Main Contractor is to ensure that the supervisor has satisfied
himself that the employee understands the hazards associated with the work to be performed by
conducting task/job observations.
3.24 Site roads
equipment’s as well as roadways for ease of manoeuvrability of these vehicles.
vehicles traversing the sites.
3.25 Vehicle management
a. Their passengers wear seat belts whilst the vehicle is in motion.
b. Comply with all traffic road rules, safety, direction and speed signs.
c. Ensure that vehicle loads are properly secured prior to moving off.
d. Ensure that vehicles are not overloaded.
be services annually and inspected monthly. Drivers must be trained on how to use the
First aid box and fire extinguishers.
the back of the vehicle.
vehicle access to site.
must be valid at all times and this is applicable to yellow plant.
least 30 (thirty) meters must be left clear between such a vehicle and such a machine.
Vehicles which are not roadworthy will not be permitted to be used on site.
them. Precautions shall be taken to secure all loads properly. Loads projecting from
vehicles shall be securely loaded and in daytime a red flag and during darkness a red light
or red reflective material shall be attached to the extreme end of such projecting materials.
o Reverse alarm / beeper
o Yellow reflective tape
o Mud flaps
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
o Fire Extinguisher
o 2 Triangles
o First Aid Box
o Safety belts for every seat
o No fold-up or jockey seat
o Tyres
o License disc
o Driver have a Public Driving Permit
3.26 Housekeeping and order
vehicles for the duration of the project/contract.
temporarily in a designated waste area, awaiting disposal.
serious injuries/fatalities.
area immediately.
area of all materials, scrap, temporary buildings and building bases to the satisfaction of
the client/agent.
safety and cleanliness, anyone has the responsibility to bring it to the attention of the Main
contractor in the first instance and the Eskom project/contract manager in the second
instance.
appointed contractors to cease work until the area has been tidied up and made safe.
Neither additional costs nor extension of time to the contract shall be allowed because of
such a stoppage. Failure to comply with this requirement will result into site cleaning by
another cleaning contractor company at the cost of the Main contractor.
ensure maintenance of satisfactory standards. The Main contractor shall document the
results of each inspection and shall maintain records for viewing.
3.27 Stacking and storage
stacking and storage on site.
manager for authorisation to use such an area for stacking purposes. This is to prevent
haphazard arrangements.
carried out correctly and safely.
small on top.
3.28 Workplace signage and colour coding
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
name and contact details of the: contractor site/responsible manager; supervisors; Health
and Safety Manager/Practitioner; First Aider; Health and Safety Representative and
Evacuation warden.
indicated by means of a sign.
people of its use.
is prohibited and/or where alerting and cautioning passers-by to be aware of potential
dangers.
training and toolbox talks.
sign indicating the meaning of symbolic safety signs must be displayed.
3.29 Tools and equipment
is maintained in a good condition.
regularly inspected at least monthly or as required by legislation and risk assessments.
The equipment should be numbered or tagged so that it can be properly monitored and
inspected.
calibration documentation prior to being brought onto the project and the records shall
form part of the OHS plan. Maintenance calibration shall be undertaken in terms of the
manufacturer’s requirements.
manufacturer’s recommendations and legal requirements.
contractors for use on this project.
way unsuitable for the safe and satisfactory execution of the work for which it is intended,
the Eskom personnel shall advise the contractor in writing and the contractor shall
forthwith remove the item from site and replace it with a safe and adequate substitute.
Note: In such cases, the contractor shall not be entitled to extra payments or extensions
of time in respect of delay caused by Eskom’s instructions.
removed out of site immediately, locked away to prevent further use until such time as the
tool or piece of equipment has been repaired.
used on the project. Such tools and equipment’s shall be subjected to regular inspections.
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
3.32 Auditing
3.32.1 Approval and compliance of Main contractor OHS plan
The Contractor’s OHS Plan will be audited against compliance checklist so as to verify compliance
to the requirements of the Eskom OHS specifications. Once there is compliance only then will the
Main contractors OHS plan be approved by the project manager or an appointed Eskom contract
custodian. The implementation of the OHS Plan shall be assessed / audited by Eskom personnel
on a regular basis. This will include physical conditions evaluation.
3.32.2 Eskom OHS audits
Eskom shall evaluate all contractors’ OHS performance on an ongoing basis against the legal,
Eskom requirements, OHS specification and the contractors OHS plans.
Note: Eskom reserves the right to conduct unannounced audits on contractors
There will be yearly audits conducted by Eskom on the Main contractor/s and this main contractor
shall be expected to do the same on their contractor if one is appointed. Eskom through Safety
Risk Management shall conduct monthly inspections on the main contractor on monthly basis. This
inspection themes will differ from month to month, and the deviation picked up will be immediately
addressed by the main contractor. These audits shall be attended by the contractor’s site manager
or his representative.
If there are any findings / non-compliance identified as serious in these audits, an activity will be
stopped for that specific Main Contractor and appointed contractor. Refer to section on “Work
Stoppage” in this OHS Specification.
3.32.3 Contractor audits
Main Contractors are required to conduct internal audits on their appointed contractors on the
implementation of their OHS Plan on a yearly basis or when the scope of work changes. A
summary of the findings and the proposed corrective actions shall be submitted to Eskom project
manager within one week after completion of the audit. Where appointed contractors are audited
by the Main contractor a copy of the audit report shall be submitted to the appointed contractor
within 7 days of the audit.
3.33 Smoking
The national smoking policy must be observed, and smoking is permitted in designated areas only
(Eskom Smoking Procedure 32-36).
3.34 Cellular phones
The National Road Traffic Act requirements regarding the use of cellular phones must be observed,
when driving and or operating mobile equipment and or machinery. The personal use of cell
phones in the plant is prohibited unless it is an emergency or for work purpose. The use of cell
phone camera in the plant must be in line with the national key point Act and the Plant safety
regulation.
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
3.35 Occupational health, hygiene and rehabilitation
3.35.1 All contractors are required to develop an Occupational Health Risk assessment for all
occupational hygiene stressors employees are potentially exposed to. The health risk
assessment is intended to ensure that the risks to health are identified, controlled and managed.
All contractors will comply with all the legislation pertaining to this project scope being:
Physical Regulation, 2024
Noise Exposure Regulation,2024
Hazardous Chemical Agent, 2021.
Ergonomics Regulation,2019
Note: Eskom will only accept medical surveillances conducted by an Occupational Health Practitioner
who holds a qualification in occupational health.
employees have a medical surveillance program whereby their employees undergo entry,
periodic and exit medical fitness examinations.
address the hazards that the employees will be exposed to.
man job specification, which must indicate the description of work, list of hazards and
potential occupational exposure limits, physical hazards and required physical attributes.
site. This shall be maintained until completion of the contract.
employees have undergone pre-entry medical examination before starting work on the
contract.
who are issued with a conditional certificate of fitness.
fitness certificates as and when their employees leave the company.
3.39 Personal protective equipment requirements
maintenance and replacement of PPE for all his employees and appointed contractors on
site.
Specification Standard 240-44175132.
to be issued to employees performing the respective tasks.
additional PPE, a risk assessment must be done, in which such PPE requirements will be
determined and issued.
worksites.
contractor’s responsibility to provide the PPE.
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
with the relevant SANS standards.
be worn.
maintenance of PPE and keep the record.
3.40 Incident investigation & reporting
All incidents shall be investigated in terms of OHS Act General Administrative Regulations 8 and
9, using Eskom Procedure 32-95 OHS incident management as a reference, and where injuries
as contemplated in sections 24 and 25 have been sustained, be reported to the Department of
Employment and Labour.
Contractors shall use the Eskom Flash report or their own template to report incidents immediately
or before end of shift. The standard General Administrative Regulation Annexure 1 “Recording of
an Incident form” for all incident investigation reports. The objective of incident investigation, should
not only be a legal requirement, but should establish why and how the incident occurred and find
out the real root cause of the incident and to decide on precautionary measures that are required
to address the root cause to prevent any further recurrences of the same or similar incidents.
Eskom 32-95 Incident Management Procedure requires that the investigation be done within seven
days of the incident happening, then in 30 days the investigation results including safety measures
must have been populated on SAP EH&S. So the contractor shall adhere to all these requirements.
3.41 Emergency management
The art of emergency preparedness and response is to minimise the effects of any emergency and
to restore normal activities as soon as possible. The contractor must develop and align their own
Emergency response plan with Eskom’s to address any emergency which might arise at any given
point in time. The contractor to familiarise themselves with the Eskom emergency response plan
and procedure. Periodic emergency drills must be undertaken to test the effectiveness of their plan.
This must be recorded and provided on request.
3.41 Non-conformance and compliance
subject to discipline in terms of the Eskom Procurement and Supply Chain Management
Procedure.
in place) for issuing to contractors for transgressions. The procedure can include “quality”
related non-conformance issues. Similarly, appointed contractors must implement a non-
conformance procedure.
adhered to.
in not doing so; any recommendations made may not be implemented.
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
procedure will be for the offender to be called by the responsible project manager to
explain the non-conformance issued and what plan is in place to prevent a recurrence of
the non-conformance.
employees for the tasks being performed and/or to visitors; failure to enforce the wearing
of such PPE will be viewed as a transgression of the legislative and Eskom requirements.
3.43 OHS files
about the safety and health management system from inception, execution to completion
of works.
than one site per project, a file per site shall be kept at that site. Contractors may keep
additional files at their head office as additional records. The OHS file shall be maintained
by all the contractors on their project sites and shall be available on request for audit and
inspection purposes.
requirements/specification, legal and other requirements.
this OHS requirements /specification and the OHS plan.
partition must be labelled.
health and safety file to the project manager.
cumbersome, the older documentation must be archived in boxes which shall be correctly
labelled and be available for auditing purposes. The archived documentation must be
handed over at the completion of the project.
3.44 WORK STOP. Any person may stop any activity where an unsafe act or unsafe condition that poses or
may pose an imminent threat to the safety and health of an individual or create a risk of
degradation of the environment. This includes any unauthorised work or service
performed by, or legally or contractually non-compliant acts or omissions by, any
contractor contracted to work at that site.
performance related to the contractor’s works or services shall not warrant any financial
compensation claim lodged against Eskom where the contractor has not met the
requirements defined legally or contractually.
custodians.
3.45 Hours of work
The requirements of the Basic Conditions of Employment Act, Chapter Two “Regulation of Working
Time” must be adhered to. All contractors are required to maintain an accurate record of time
worked by each employee.
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
Template Identifier 240-43921804 Rev 6
Lethabo Power Station
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
3.45.1 Normal work
All work conducted on site shall fall within the legal requirements in accordance with the Basic
Conditions of Employment Act. Contractors will notify their Eskom Supervisor or project manager
of any work that needs to be performed after hours according to the agreed arrangements. (The
application needs to be submitted timeously). Where applicable, the notification should include
proof of application, for overtime, to the Department of Employment and Labour and /or the letter
of approval from the Department of Employment and Labour.
3.45.2 Night work
When night work is to be performed, the baseline risk assessment must be reviewed to include the
management of night work. Contractors shall provide sufficient lighting to enable the entire work
site to be illuminated to a degree that employees will not work in dark (un-illuminated) or dimly lit
areas. Care must be exercised as not to use few lights with high light intensives, as this will cause
night blindness.
If work is continuing from day light into night, at dusk, a tool box talk must be held where all
employees will be advised of the hazards of night work and the extra precautions which require to
be taken, i.e. poor housekeeping, stepping on uneven ground, stepping into holes etc.
3.45.3 Overtime
When overtime is required to be performed, the appointed contractors shall inform the Main
contractor of such action. The Main contractor shall inform the Eskom project manager of such
function and provide proof of exemption from the Department of Employment and labour.
Contractors shall be aware of the effects of human fatigue and regulate overtime accordingly. The
baseline risk assessment must be reviewed to include the management of overtime work.
3.46 Omissions from safety and health requirements specification
By drawing up this OHS specification Eskom has endeavoured to address the most critical aspects
relating to OHS issues in order to assist the contractor to adequately provide for the health and
safety of employees on site.
Should Eskom not have addressed all OHS aspects pertaining to the work that is tendered for, the
contractor needs to include it in the OHS plan and inform Eskom of such issues when signing the
contract.
3.47 Contractor performance monitoring
Contractor management is required to do the following as part of the continuous improvement
initiatives:
Business Unit Power Station General Managers meeting
Controlled disclosure
When downloaded from the Document Management System, this document is uncontrolled and the responsibility
rest with the user to ensure it is in line with the authorised version on the system
No part of this document may be reproduced without the expressed consent of the copyright holder,
Eskom Holdings SOC Ltd Req No 2002/015527/30.
of 31
. Introduction ......................................................................................................................... 4
2.1 Scope ....................................................................................................................................... 4
2.2 Normative/informative references ............................................................................ 4
2.3 Definitions ............................................................................................................................. 5
2.4 Abbreviations ...................................................................................................................... 8
2.5 Related/supporting documents ................................................................................... 8
3.1 Scope of work ..................................................................................................................... 9
3.2 Legal compliance ............................................................................................................... 9
3.3 ESKOM requirements ....................................................................................................... 10
3.4 Sheq policy ......................................................................................................................... 10
3.6 Coid ........................................................................................................................................ 10
3.7 Costing for OHS within the project ......................................................................... 10
3.8 Statutory appointments ............................................................................................... 11
3.9 ESKOM life-saving rules................................................................................................. 11
3.10 Substance abuse .............................................................................................................. 12
3.11 Contractor organisational structure ................................................................. 12
3.12 Roles and responsibilities ........................................................................................... 13
3.13 RISK ASSESSMENT (refer to 32-520) ..................................................................................... 16
3.14 Safe work procedures / method statements ....................................................... 18
3.15 Fire equipment and maintenance .............................................................................. 19
3.20 Tool box talks / daily team talks / pre job meetings ......................................... 21
3.21 OHS training ....................................................................................................................... 21
3.22 General training .............................................................................................................. 23
3.24 Site roads............................................................................................................................ 23
3.25 Vehicle management ........................................................................................................ 23
3.26 Housekeeping and order ............................................................................................... 24
3.27 Stacking and storage .................................................................................................... 24
3.28 Workplace signage and colour coding .................................................................. 24
3.29 Tools and equipment ....................................................................................................... 25
3.32 Auditing ................................................................................................................................ 26
3.33 Smoking ................................................................................................................................ 26
3.34 Cellular phones ............................................................................................................... 26
3.35 Occupational health, hygiene and rehabilitation .............................................. 27
3.39 Personal protective equipment requirements ................................................... 27
3.40 Incident investigation & reporting ........................................................................... 28
3.41 Emergency management ................................................................................................ 28
3.41 Non-conformance and compliance ........................................................................... 28
3.43 OHS files .............................................................................................................................. 29
3.44 Work stoppage.................................................................................................................. 29
3.45 Hours of work .................................................................................................................. 29
3.46 Omissions from safety and health requirements specification .................. 30
3.47 Contractor performance monitoring .................................................................... 30
3.48 Contract sign off ............................................................................................................ 31
3.49 ESKOM's RIGHT TO TERMINATE THE CONTRACT .............................................................. 31
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
Eskom’s responsibility and commitment is to ensure a safe working environment is in line with its
Safety, Health, Environmental, and Quality (SHEQ) Policy and applicable legislative obligations.
met for the duration of the contract period by contractors/suppliers and, where required, the
delivery organisation. The contractor is expected to develop an OHS plan that meets these
requirements as well as all the relevant applicable legislation that they conform to. Eskom in no
way assumes the contractor’s legal responsibilities and liabilities. The contractor is and remains
accountable for the quality and execution of their health and safety programme for their employees
and appointed contractor employees. This OHS specification reflects minimum requirements and
should not be construed as all-encompassing.
Note 1: All the requirements listed hereunder are in relation to the contract and do not supersede or
replace any organizational OHS requirements.
following paragraphs.
2.2.1 Normative
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
2.2.2 Informative
2.3 Definitions
Baseline risk assessment (32-520) baseline operational risks refer to the health and safety risks
associated with all standard processes and routine activities in the
business
Business unit (BU) (32-296) means any defined unit within the Eskom environment,
operating as a business under a particular cost-centre number. In the
context of this document and in terms of health and safety, any
reference to a BU includes a defined unit within any Eskom division and
its subsidiaries
Client (OHS Act) Eskom representative (Internal – Asset Owner), also referred
to as the contract administrator/custodian or agent or project manager
(as defined in the contract). He/she is the person responsible for
ensuring that the works or services are executed in terms of the
contract, as well as adherence to legislation pertaining to the contract.
Competent person (OHS Act) means any person having the knowledge, training,
experience, and qualifications, specific to the work or task being
performed, provided that, where appropriate, qualifications and training
are registered in terms of the South African Qualifications Authority Act,
1995 (Act No. )
Contractor (OHS Act) means an employer as defined in section 1 of the Act who
performs contracted work and includes Main contractors
Contract’s Manager/End Contract’s Manager/End User
Controlled disclosure controlled disclosure to external parties (either enforced by law or
discretionary)
Duty of care to the (32-136) anybody who causes or has caused or may cause significant
environment pollution or degradation of the environment must take reasonable
measures to prevent such pollution or degradation from occurring,
continuing, or recurring. If such harm to the environment is authorised
by law or cannot reasonably be avoided or stopped, such person must
minimise and rectify such pollution or degradation of the environment
Employee (OHS Act) means, subject to the provisions of subsection (2), any
person who is employed by or works for an employer and who receives
or is entitled to receive any remuneration or who works under the
direction or supervision of an employer or any other person
Employer (OHS Act) means, subject to the provisions of subsection (2), any
person who employs or provides work for any person and remunerates
that person or expressly or tacitly undertakes to remunerate him/her,
but excludes a TES (ex labour broker) as defined in section 1(1) of the
Labour Relations Act 1956 (Act No. )
Environment (32-94) means:
the land, water, and atmosphere of the earth;
micro-organisms and plant and animal life; and
any part or combination of (a) and (b) and the interrelationships among
and between them, and the physical, chemical, aesthetic, and cultural
properties and conditions of the foregoing that influence human health
and well-being
procedures, specifications, work instructions, guidelines, or manuals
Fall protection plan (OHS Act) means a documented plan of all risks relating to working from
an elevated position, considering the nature of work undertaken, and
setting out the procedures and methods to be applied in order to
eliminate the risk
Hazard (OHS Act) means a source of, or exposure to, danger
Hazard identification (OHS Act) means the identification and documenting of existing or
expected hazards to the health and safety of persons, which are
normally associated with the type of construction work being executed
or to be executed
Occupational Health and (OHS Act) means a file or other record in permanent form, containing
safety file the information required in relation to the contract.
Health and safety plan (OHS Act) means a document plan that addresses hazards identified
and includes safe work procedures to mitigate, reduce, or control
hazards identified
Occupational Health and (OHS Act) means a document specification of all health and safety
safety specification requirements pertaining to associated to a contract, so as to ensure the
health and safety of persons.
safety requirements project, site, and scope of work. This specification is intended to ensure
the health and safety of persons, both workers and the public, and the
duty of care to the environment. The health and safety requirements
must be specific to each contract, project, site, and scope of work
Lifesaving Rules (240-62196227) a rule that, if not adhered to, has the potential to cause
serious harm to people
Medical Certificate of fitness (OHS Act) means a certificate valid for one year, issued by an
occupational health practitioner, issued in terms of the regulations,
whom shall be registered with the Health Professions Council of South
Medical surveillance (OHS Act) means a planned programme or periodic examination (which
may include clinical examinations, biological monitoring, or medical
tests) of employees by an occupational health practitioner or, in
prescribed cases, by an occupational medicine practitioner
Method statement (OHS Act) means a written document detailing the key activities to be
performed in order to reduce, as reasonably as practicable, the hazards
identified in any risk assessment
has been appointed as part of the Eskom delegation of authority
process with the aim to assist the applicable 16(2) assigned person in
executing his/her duties in terms of the Occupational Health and Safety
Act
Risk assessment (OHS Act) means a programme to determine any risk associated with
any hazard at a construction site in order to identify the steps needed
to be taken to remove, reduce, or control such hazard.
Site (34-228) means an Eskom department, unit, complex, building, specific
project, work site, or the site where agents, clients, Main contractors,
contractors, suppliers, vendors, and service providers provide a service
to Eskom, directly or indirectly
Service provider any private person or legal entity that provides any service(s) to Eskom
for compensation
Subsidiary (32-94) an enterprise controlled by another (called the parent) through
the ownership of greater than 50% of its voting stock
Supplier (32-1034)means a natural or legal person who renders a service and
may include the following current or potential supplier vendor,
contractor, consultant
Task (34-227) a segment of work that requires a set of specific and distinct
actions for its completion
Toolbox talks (34-227) where the team leader, after conducting pre-task planning,
shares all the tasks at hand and discusses task allocation, the identified
risks, and the control measures with all his/her team members on site
before commencing a specific task and documenting the agreed
strategy. (This shall be done to ensure common understanding of the
tasks, risks, and control measures required.)
The Act (OHS Act) means the Occupational Health and Safety Act No. , as amended, and the Regulations thereto
Note: The contractor who will be awarded this contract will be known as the “Main contractor”
and any contractor appointed by the Main contractor will be known as the “Appointed contractor"
3.2 Legal compliance
3.2.1 Section 37(2) (Legal) Agreement
A section 37(2) agreement must be signed between Eskom and the main contractor at the time of
submitting the safety file. The main contractor must ensure that a section 37(2) agreement is
compiled between the main contractor and all their appointed contractors for the contract. The
original copy of the section 37(2) agreement must be retained by the contractor, and a copy must
be retained by the responsible project manager/end user. A copy of all the agreements must form
part of the respective contractor’s OHS file.
3.2.2 Hazardous Work by Children (Child Labour)
The constitution of the Republic of South Africa, in the "Bill of Rights", is clear on the rights of
children, especially when it comes to:
moral, or social development and the Basic Conditions of Employment Act, Chapter six,
Section 43, "Prohibition of employment of children."
constitutional rights. Where work is being performed which is not prohibited in terms of the
constitution, then such work must be conducted in terms of the OHS Act "Regulations on
Hazardous Work by Children in South Africa" with emphasis on paragraph 2: Purpose and
this project being:
Rights).
3.3 ESKOM requirements
familiar with the relevant Eskom OHS documentation that is applicable to contract services.
3.4 Sheq policy
A SHEQ policy is a statement of intent and a commitment by the organization’s CE and senior
management in relation to the relevant OHS roles and responsibilities, the achievement of their
strategic objectives, and values of integrity, customer satisfaction, excellence, and innovation. The
main contractor and all appointed contractors, if not already in place, will be required to compile
an organisational SHEQ policy in line with their OHS responsibilities. The policy must be signed
by the organisation’s CE or the appointed assistant to the CE, OHS Act Section 16(2). The policy
must be displayed in a prominent place within the workplace. A copy of the policy must be filed in
the contractor's OHS files and attached as an annexure to the OHS Plan.
3.6 Coid
employment compensation commissioner and have available a valid letter of good standing (LoG)
from such commissioner. The obligation lies with the contractors to ensure that the LoG remain
valid throughout the contract period. A copy of the LoG must be filed in the contractor OHS files.
3.7 Costing for OHS within the project
The costing for OHS must be itemised based on the overall scope of the project (i.e.) Training,
provision of PPE, safety equipment purchases etc.
'
comply with the OHS Act for the duration of the contract. Before requiring appointees to accept an
appointment, the employer must ensure that they have received appropriate training and/or
information about their responsibilities. The relevant statutory appointments must be made in
compliance with the OHS Act's criteria, which include appointing a qualified individual to the
appropriate roles. The following should be included in the statutory appointments, but not limited
to:
3.8.1 Non statutory appointments
3.9 ESKOM life-saving rules
Rule 2 Working at height is defined as any work performed above a stable work surface or where a person puts
himself/herself in a position where he/she exposes himself/herself to a fall from or into.
employees at all levels must demonstrate their commitment by being proactively involved in the
day to day operations, in particular the Occupational Health and Safety aspects of any project /
contract. Legislation requires that each employee must take reasonable care of themselves and
their fellow workers, from management level down to the lowest employee level.
Managers and Supervisors will be required to submit 4(four) BSO(Behavioural Safety Observation)
a month to Lethabo Safety Department @ [email protected]
The 16.1 is required to submit at least 1(one) VFL to Lethabo Safety Department @
3.12.1 Main contractors and appointed contractors
Note 1: Most of the roles and responsibilities listed apply to both Main contractors and any appointed
contractors. Where some of the listed do not apply to both, then the specific responsibilities will be
listed and titled. The contractors shall:
part of the OHS Act and Regulation 7 of the Construction Regulations.
their appointed contractors within their working area, as contemplated by section 37(2) of
the OHS Act;
including date of induction, relevant skills and licenses and be able to produce this list at
the request of the Eskom Project Manager.
responsibilities in terms of their appointment and that they advise and assist these
appointees in the execution of their duties.
complied with on all work sites.
participation and cooperation.
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
records must be kept for each work site.
Commissioner’s valid letter of good standing before the commencement of work and any
future renewal letters obtained during the contract for record-keeping purposes. The letter
of good standing shall reflect the name of the contractor’s company. Similarly, the Main
contractor must provide the Eskom project manager with all the valid letters of good
standing from their appointed contractors.
Commissioner’s valid letter of good standing before the commencement of work and any
future renewal letters obtained during the contract for record-keeping purposes. The letter
of good standing shall reflect the name of the contractor’s company.
trained in the health and safety aspects relating to such work and that the employees
understand the hazards associated with all other work being carried out on the project.
adhere to such procedures. Similarly (without removing the appointed contractors’
responsibilities), ensure that their appointed contractors and their employees are
conversant with all relevant work procedures and that they adhere to such procedures.
health;
for the cost of safety and health measures throughout the project.
health and safety of persons or a risk of degradation to the environment.
evaluate, and assess the appointed contractors OHS files. Only appoint contractors who
are competent to do work, have satisfied the OHS compliance requirements and satisfied
that the contractor has the necessary competencies and resources to perform the work
safely.
specified work throughout the contract period.
site for which such supervisor has been appointed for.
safety information or suspecting such information has been divulged, in the interests of
health and safety requirements.
contractor employees have transgressed any of the requirements of the health and safety
specification, safety and health plans, site rules or any other requirements.
include site or emerging risks. This should be done by a competent person appointed in
writing with a view to identify hazardous and potentially hazardous work operations.
the starting of any new task, irrespective of whether it is a repetitive task or not.
contract is in place and maintained.
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
person/man job specifications must be compiled and handed to the occupational health
practitioner.
employees, inspect such equipment regularly and ensure recipients of PPE are trained in
the proper use, care and where necessary, the maintenance of PPE;
they will be held responsible for the provision and wearing PPE.
investigators as and aligned with 32-95 requirements.
his/her approval prior to them commencing work.
3.12.2 Contractor site supervisor
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
meetings.
perform the tasks assigned.
contractors deviate from safety requirements.
3.12.3 Contractor Health and Safety officer part time
investigation training, Legal liability Training, Minimum work experience 3yrs,
3.13 RISK ASSESSMENT (refer to 32-520)
It is a legal requirement in terms of Section 8 (2)(d) of the OHS Act for an employer to carry out
risk assessments, to establish which risks and hazards are attached to the health and safety of
persons due to any work which is performed, any article or substance which is, handled, stored,
transported. A risk assessment is defined as an identification of the hazards present in the activity,
work, site, and an estimate of the extent of the risks involved, considering whatever precautions
are already being taken.
or activity, or any new process or activity should be subjected to a risk assessment and that if new
hazards become known during the work process, then these should also be subjected to risk
assessments. Risk assessments for long-term processes should be periodically reviewed and
updated. Method statements or written safe work procedures are an effective method as
information and record of the way jobs / tasks must be performed. Daily or issue based or task
specific or on the job risk assessments must be conducted at the place where work is to be
performed/ conducted to allow managers and employees to assess any inherent risks that could
have been overlooked during the initial risk assessment or any changes that might have occurred
in a period of absence. For example if a job / task is extended over a day or halted due to inclement
weather.
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
procedures exist for ladders.
to rectify this shall be recorded, and safe working procedures drawn up.
nominated and duly assigned.
must be nominated.
for comment and approval.
Supervisor nominated as the responsible person; and the names of workmen who have
received instruction on the work content and the sequence of the activities listed in the
risk assessment shall be recorded, and their competence established. This instruction
shall be done through an interpreter if required and recorded on the Pre-Job Brief (Daily
Safe Task Instructions), with reference to applicable Risk Assessments.
Health and Safety
1 No injuries or health effects(near misses)
with the risk assessments. Method statements / written safe work procedure are control measures
used to prevent an incident from occurring during the execution of the project. A written safe work
procedure/ method statements provide guidance how to execute the task safely. A safe working
procedure should be written when: -
a. Designing a new job or task.
b. Changing jobs or task;
c. Introducing new equipment or substances; and
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
a. The supervisor for the task or job and the employees who will undertake the task;
b. The tasks that are to be undertaken that pose risks;
c. The equipment and substances that are used in these tasks;
d. The control measures that have been built into these tasks;
e. Any training or qualification needed to undertake the task;
f. The personal protective equipment to be worn;
g. J. Actions to be undertaken to address safety issues that may arise while undertaking
the task.
3.15 Fire equipment and maintenance
a. Be clearly labelled
b. Conspicuously numbered
c. Entered in a register
d. Inspected monthly by a competent person
3.19.1 Statutory Health and Safety Committees
Section 19 of the OHS Act. Similarly, appointed contractors shall establish their own
statutory health and safety committee.
performed, training, upcoming work and OHS requirements, incidents and lessons
learned specific OHS problems, safety performance, action plans and other relevant OHS
issues. Listed below is a preferred agenda.
Safety Representatives on that specific statutory health and safety committee. (Refer to
Section 19(2)(c) of the OHS Act)
medium to high risk work is involved, more frequent if required), and all appointed
members of the committee shall attend the meeting.
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
and 25 incidents and other notified serious incidents.
statutory health and safety committees carry out their duties.
the contractor. The appointed chairperson must be competent to chair meetings and be
able to make informed decisions.
3.19.2 Non-statutory health and safety committees
within that worksite to assist with the communication of health and safety related matters
between the statutory health and safety committee and the workplace.
the same as the statutory safety committee
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
o Work procedures.
o Hazardous materials / substances.
o Fire Prevention
o Occupational Hygiene Assessments, Health Risks and Actions
o Security
o Rules, Instructions
o Public Safety
o Environmental Management
o Emergency Preparedness
o Statistics report
o Closure
3.19.2.2 Minutes and action items for all health and safety committee meetings
be kept for the duration of the project or a minimum period of three years.
of the project or a minimum period of 12 months.
his/her recommendations and return the minutes to the relevant contractors chairperson
within 14 calendar days of the meeting.
3.20 Tool box talks / daily team talks / pre job meetings
personnel associated with the work task in attendance. The job, relevant procedures,
associated hazards, safety measures, i.e. the task risk assessments shall be discussed.
undergo site-specific work induction with regard to the approved project OHS plan, hazards
prevalent on the work site, scope specific risk assessment, rules and regulations, and other related
aspects. The induction training should also include identification of sensitive features such as
wetlands/vlei areas, red data species, graves, etc.
3.21.3 Visitors to site induction
safety induction prior to being allowed access to site.
inducted. No visitors are permitted to undertake any work onsite, of any nature.
project/site, the respective supervisor informs the employee of his scope of authority, the hazards
associated with work as well as the control measures to be taken. This will include man-job
specifications, the discussion of any task procedures or hazardous operational procedures to be
performed by the employee. The Main Contractor is to ensure that the supervisor has satisfied
himself that the employee understands the hazards associated with the work to be performed by
conducting task/job observations.
3.24 Site roads
a. Their passengers wear seat belts whilst the vehicle is in motion.
b. Comply with all traffic road rules, safety, direction and speed signs.
c. Ensure that vehicle loads are properly secured prior to moving off.
d. Ensure that vehicles are not overloaded.
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
o Fire Extinguisher
o 2 Triangles
o First Aid Box
o Safety belts for every seat
o No fold-up or jockey seat
o Tyres
o License disc
o Driver have a Public Driving Permit
3.26 Housekeeping and order
safety and cleanliness, anyone has the responsibility to bring it to the attention of the Main
contractor in the first instance and the Eskom project/contract manager in the second
instance.
manager for authorisation to use such an area for stacking purposes. This is to prevent
haphazard arrangements.
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
name and contact details of the: contractor site/responsible manager; supervisors; Health
and Safety Manager/Practitioner; First Aider; Health and Safety Representative and
indicated by means of a sign.
sign indicating the meaning of symbolic safety signs must be displayed.
3.29 Tools and equipment
regularly inspected at least monthly or as required by legislation and risk assessments.
shall be expected to do the same on their contractor if one is appointed. Eskom through Safety
stopped for that specific Main Contractor and appointed contractor. Refer to section on “Work
Stoppage” in this OHS Specification.
3.32.3 Contractor audits
when driving and or operating mobile equipment and or machinery. The personal use of cell
phones in the plant is prohibited unless it is an emergency or for work purpose. The use of cell
phone camera in the plant must be in line with the national key point Act and the Plant safety
regulation.
Document Identifier LFMS048 Rev 00 OHS SPECIFICATION FOR
HIGH RISK Effective Date 2023/11/21
ACTIVITIES / SERVICES Review Date 2026/11/21
3.35 Occupational health, hygiene and rehabilitation
3.35.1 All contractors are required to develop an Occupational Health Risk assessment for all
occupational hygiene stressors employees are potentially exposed to. The health risk
assessment is intended to ensure that the risks to health are identified, controlled and managed.
Physical Regulation, 2024
Noise Exposure Regulation,2024
Hazardous Chemical Agent, 2021.
Ergonomics Regulation,2019
Note: Eskom will only accept medical surveillances conducted by an Occupational Health Practitioner
who holds a qualification in occupational health.
address the hazards that the employees will be exposed to.
man job specification, which must indicate the description of work, list of hazards and
potential occupational exposure limits, physical hazards and required physical attributes.
maintenance and replacement of PPE for all his employees and appointed contractors on
site.
Specification Standard 240-44175132.
additional PPE, a risk assessment must be done, in which such PPE requirements will be
determined and issued.
contractor’s responsibility to provide the PPE.
with the relevant SANS standards.
be worn.
maintenance of PPE and keep the record.
3.40 Incident investigation & reporting
All incidents shall be investigated in terms of OHS Act General Administrative Regulations 8 and
9, using Eskom Procedure 32-95 OHS incident management as a reference, and where injuries
as contemplated in sections 24 and 25 have been sustained, be reported to the Department of
or before end of shift. The standard General Administrative Regulation Annexure 1 “Recording of
an Incident form” for all incident investigation reports. The objective of incident investigation, should
not only be a legal requirement, but should establish why and how the incident occurred and find
out the real root cause of the incident and to decide on precautionary measures that are required
to address the root cause to prevent any further recurrences of the same or similar incidents.
Eskom 32-95 Incident Management Procedure requires that the investigation be done within seven
days of the incident happening, then in 30 days the investigation results including safety measures
must have been populated on SAP EH&S. So the contractor shall adhere to all these requirements.
3.41 Emergency management
to restore normal activities as soon as possible. The contractor must develop and align their own
Emergency response plan with Eskom’s to address any emergency which might arise at any given
point in time. The contractor to familiarise themselves with the Eskom emergency response plan
and procedure. Periodic emergency drills must be undertaken to test the effectiveness of their plan.
about the safety and health management system from inception, execution to completion
of works.
health and safety file to the project manager.
cumbersome, the older documentation must be archived in boxes which shall be correctly
labelled and be available for auditing purposes. The archived documentation must be
handed over at the completion of the project.
3.44 WORK STOP. Any person may stop any activity where an unsafe act or unsafe condition that poses or
may pose an imminent threat to the safety and health of an individual or create a risk of
degradation of the environment. This includes any unauthorised work or service
performed by, or legally or contractually non-compliant acts or omissions by, any
contractor contracted to work at that site.
employees will be advised of the hazards of night work and the extra precautions which require to
be taken, i.e. poor housekeeping, stepping on uneven ground, stepping into holes etc.
3.45.3 Overtime
baseline risk assessment must be reviewed to include the management of overtime work.
3.46 Omissions from safety and health requirements specification
relating to OHS issues in order to assist the contractor to adequately provide for the health and
safety of employees on site.
Environmental
Source: Safety.ziprequirements pertaining to local authorities, municipal by-laws, or environmental legislation that
must be met by the contractor.
2.1.1 Purpose
temporarily in a designated waste area, awaiting disposal.
serious injuries/fatalities.
Section
Source: Safety.zipEvaluation criteria are not explicitly stated, but compliance with the OHS specification is mandatory. The contractor's OHS management, including risk assessments and method statements, will be assessed.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
Vaaldam Road - Viljoensdrift - Viljoensdrift - 1930
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
4
Last checked
15 Sept 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Get deep intelligence on Supplies: General. Unlock full pricing strategies, bid frequency, and historical win rates.
Learn how to submit a winning bid with these related articles
💡 Want more tendering tips and strategies?
Explore Our Blog