Petrosa invites registered and approved suppliers to tender for the technical assessment, repair, and replacement of the gas suppression system at its mossel bay refinery. The 36-month contract requires electronic submission via the petrosa e-procurement portal, with pre-qualification limited to BBBEE level 4 contributors or eme/qse entities. A mandatory scope clarification meeting and site inspection are scheduled for 20 july 2026.
Key Requirements
Must be a registered and approved supplier on the PetroSA database and the National Treasury Central Supplier Database.
Meet pre-qualification: BBBEE Level 4 contributor or an EME/QSE; provide a valid BBBEE certificate and improvement plan.
Attend the mandatory scope clarification meeting and site inspection on 20 July 2026 (RSVP by 17 July 2026 with attendee names and ID numbers).
Provide pricing as per the CBA total annual cost summary with a complete breakdown in the draft service agreement.
Comply with subcontracting rules: minimum 30% subcontracting to a 51% black-owned EME/QSE for contracts above R30 million; any subcontracting >25% requires a signed agreement and equal/higher BBBEE status.
Consent to due diligence checks and declare independent bid determination; fronting is prohibited and leads to disqualification.
Professional Services & Consulting Industry Profile
Regulatory Bodies
SAICA
Tenders in this industry often require registration with these bodies.
Typical Documents
5 items
Company Registration (CIPC)
Tax Clearance Certificate
B-BBEE Certificate
CSD Registration
Company Profile
Recommended Certifications
Having these can improve your winning chances: CA(SA) - Chartered Accountant, PMI-PMP (Project Management Professional), Prince2 Practitioner, Six Sigma Certification
Review in progress · 0 of 4 documents being finalised
AI Document Analysis Stages
Document read. The full tender notice and its supporting documents are read end-to-end. Key sections, requirements, dates, and contact details are identified and pulled into a working summary you can act on.
Compliance review. The working summary is checked against South African procurement standards — PFMA, PPPFA, B-BBEE, CIDB, local content, and preferential procurement — so nothing critical is missed before you start your bid response.
RFQHOW TO SUBMIT A TENDER OR QUOTATION.pdfReview complete
Description
Source: HOW TO SUBMIT A TENDER OR QUOTATION.pdf
Important Dates
14 Jul
2026
PUBLICATION
Tender Published
Tender was published
30 Jul
2026
DEADLINE
Closing Date
Tender closing date
Procurement Rules & Compliance ContextThis tender may be governed by South African public procurement rules covering fairness, transparency, preferential procurement, anti-corruption, administrative justice and access to information.
7 rules
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
Core procurement rules
These rules commonly apply to South African public-sector procurement.
7
Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
high
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Constitution of the Republic of South Africa, 1996 – Section 217
Act 108 of 1996 (s217)
high
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
PetroSA is soliciting tenders for technical assessment and repair/replacement of gas suppression systems at its Mossel Bay refinery. The tender process is conducted through an online portal with specific submission steps, including document review, questionnaire completion, pricing submission, and document attachment. The closing date is July 30, 2026.
PetroSA seeks a qualified Automatic Gas Suppression Specialist Company to assess, repair, and/or replace two non-functional gas suppression systems at their Mosel Bay refinery admin building: a decommissioned CO2 system (Document Control) and a non-functional FM-200 system (IT Server Room). Work includes mandatory site inspection, compliance audit (SANS 369, SANS 10139, NFPA 2001), detailed reporting, replacement proposals with integration, commissioning, and updated drawings. Closing date: 30 July 2026.
PetroSA invites registered and approved suppliers to tender for technical assessment and repair/replacement of gas suppression system at PetroSA Refinery in Mossel Bay. The 36-month contract requires electronic submission via E-Procurement Portal by 30 July 2026 11:00. A mandatory scope clarification meeting and site inspection is scheduled for 20 July 2026.
This document outlines PetroSA's two-phase supplier registration process for the 'Technical Assessment and Repair/Replacement of Gas Suppression System at PetroSA Refinery in Mosel Bay' tender. It is not the tender specification itself, but a mandatory pre-qualification step. The tender closes on July 30, 2026.
Win PetroSA tenders with AI Discovery, oil-and-gas intelligence, compliance analysis, and structured support for refinery and offshore contracts.
Similar Tenders
Matched by category & region
Supplier Readiness Hub
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Bid-ready summary. The submission guidelines, evaluation criteria, technical, financial, and compliance sections are refined into professional, easy-to-scan prose. This is the final version you can rely on when preparing your bid or briefing your team.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Document read
Compliance review
Bid-ready summary
Contact person details are available on the submission system screens.
Contact Information
Source: HOW TO SUBMIT A TENDER OR QUOTATION.pdf (RFQ)
Contact person details are displayed on the top screen of each step in the online submission system.
Submission Guidelines
Source: HOW TO SUBMIT A TENDER OR QUOTATION.pdf (RFQ)
Submission is via an online system. Follow these steps:
Log in with username, user code, and password.
Navigate to 'Tenders and Quotations'. Tenders have reference numbers starting with CTT; quotations start with AHT.
View line item specifications if needed before tendering.
Accept the terms and conditions.
Open all attached documents in Step 3 to proceed.
Complete the tender questionnaire in Step 4 and submit your response.
In Step 5, enter your price in the 'Response Price' field and lead time in the 'Lead Time' field, then save.
Attach required documents in Step 6 by browsing, uploading, and saving files.
Submit your tender in Step 7.
After submission, you can view a supplier submission report.
Important note: If you change your price after submission, you must resubmit the entire tender; otherwise, no tender is recorded.
Returnable Documents
Source: HOW TO SUBMIT A TENDER OR QUOTATION.pdf (RFQ)
No specific returnable documents are listed; follow the online submission process to attach required files.
Evaluation Criteria
Source: HOW TO SUBMIT A TENDER OR QUOTATION.pdf (RFQ)
No explicit eligibility criteria are stated in the provided document. However, applicants must be registered on the procurement portal and capable of complying with the submission process. The tender type (CTT vs. AHT) may imply different qualification requirements based on contract duration.
Technical Specifications
Source: HOW TO SUBMIT A TENDER OR QUOTATION.pdf (RFQ)
Line item specifications for materials can be viewed in the system before tendering. Use the 'View Line Item Specification' button.
Financial Requirements
Source: HOW TO SUBMIT A TENDER OR QUOTATION.pdf (RFQ)
Pricing must be entered in the 'Response Price' field in the online system. Lead time must be provided in the 'Lead Time' field.
Section
Source: HOW TO SUBMIT A TENDER OR QUOTATION.pdf
The evaluation uses a system-driven evaluation criteria questionnaire. Bidders must also complete a separate tender questionnaire.
DocumentAnnexure A1-Scope of Work.pdfReview complete
Description
Source: Annexure A1-Scope of Work.pdf
The tender is for the technical assessment and repair/replacement of gas suppression systems at the PetroSA refinery in Mossel Bay.
Purpose:
To appoint a qualified and certified Automatic Gas Suppression Specialist Company.
Perform site inspections of two fixed gas suppression systems in the PetroSA administrative building:
FM-200 system at the Admin IT Computer Centre.
CO2 Fire Suppression System at the Admin Document Control Department.
Provide technical and commercial proposals.
Repair and/or replace the existing systems or components.
Equipment List:
1 CO2 suppression system.
1 FM-200 Automatic Gas Suppression System.
2 Fire Panels.
Background:
Existing systems are non-functional with known equipment failures and obsolete components.
CO2 system is decommissioned due to severe corrosion and deterioration of cylinders and piping.
FM-200 system is non-functional due to a defective fire control panel.
Scope of Services:
Site Audit and Assessment:
Conduct physical inspections.
Verify configuration, operational status, coverage, and compliance with standards (e.g., SANS 369, SANS 10139, NFPA 2001).
Identify obsolete equipment, coverage gaps, and integration status.
Documentation Review:
Review drawings and highlight discrepancies.
Deliverables – Audit Report:
Must include condition assessment (graded Good/Fair/Poor/Critical), technical assessment, risks, and recommended actions.
Required Proposals:
Submit proposals for replacing faulty systems with current generation systems.
Retain functional infrastructure.
Include integration, commissioning plan, and updated drawings.
Costing Requirements:
Detailed Bill of Quantities.
Include equipment, installation, labour, engineering, design, commissioning costs.
Optional maintenance/service agreements.
Lead times and project duration.
Quote in South African Rand.
Include Standard Safety File for site visits (specifications to be provided by PetroSA).
Site Visit:
A compulsory site clarification meeting and inspection will be conducted.
Important Dates
Source: Annexure A1-Scope of Work.pdf (TENDER)
Closing date: 30 June 2026.
A compulsory site clarification meeting and inspection will be conducted (date and time not specified).
Evaluation Criteria
Source: Annexure A1-Scope of Work.pdf (TENDER)
Qualified and certified Automatic Gas Suppression Specialist Company with expertise in CO2 and FM-200 systems, knowledge of SANS 369, SANS 10139, NFPA 2001, ability to integrate with existing fire panels, and compliance with PetroSA safety file requirements. Must attend mandatory site visit.
Technical Specifications
Source: Annexure A1-Scope of Work.pdf (TENDER)
The tender is to appoint a qualified and certified Automatic Gas Suppression Specialist Company.
Scope includes:
Perform site inspections of two fixed gas suppression systems at the PetroSA administrative building:
FM-200 system at the Admin IT Computer Centre.
CO2 Fire Suppression System at the Admin Document Control Department.
Provide technical and commercial proposals.
Repair and/or replace the existing systems or components.
Key equipment involved:
1 CO2 suppression system.
1 FM-200 Automatic Gas Suppression System.
2 Fire Panels.
Background:
Existing systems are non-functional with equipment failures and obsolete components.
CO2 system is decommissioned due to severe corrosion and deterioration.
FM-200 system is non-functional due to a defective fire control panel.
Detailed Scope of Services:
Site Audit and Assessment:
Conduct physical inspections of both installations.
Verify system configuration, operational status, coverage adequacy, and compliance with standards (e.g., SANS 369, SANS 10139, NFPA 2001).
Identify obsolete equipment, gaps in coverage, and integration status with fire panels.
Documentation Review:
Review drawings and highlight discrepancies between as-built and actual installations.
Deliverables – Audit Report:
Must include a condition assessment (graded Good/Fair/Poor/Critical), technical assessment, identified risks and critical failures, and recommended corrective actions.
Required Proposals:
Submit proposals for replacement of faulty, obsolete, or decommissioned systems with current generation systems.
Retain functional existing infrastructure where viable.
Include integration with existing systems, commissioning and testing plan, and updated drawings.
Costing Requirements:
Provide a detailed Bill of Quantities.
Include equipment, installation, labour, engineering, design, and commissioning costs.
Optional maintenance/service agreements.
State lead times and project duration.
All costs must be quoted in South African Rand.
Include any Standard Safety File required for site visits (exact specifications will be provided by PetroSA).
Site Visit:
A compulsory site clarification meeting and inspection will be conducted.
Quality Management
Source: Annexure A1-Scope of Work.pdf
Perform site inspections of the two fixed gas suppression systems.
Provide technical and commercial proposals.
Repair and/or replace existing systems or components.
Conduct physical inspections of both installations.
Deliver an audit report including condition assessment (graded Good/Fair/Poor/Critical), technical assessment, identified risks, and recommended corrective actions.
Submit proposals for replacement of faulty systems with current generation systems, retaining functional infrastructure, and including integration, commissioning plan, and updated drawings.
Financial Requirements
Source: Annexure A1-Scope of Work.pdf (TENDER)
Provide a detailed Bill of Quantities.
Include equipment costs, installation and labour costs, engineering and design costs, and commissioning costs.
Optional maintenance/service agreements may be included.
State lead times and project duration.
All costing must be quoted in South African Rand.
Include any Standard Safety File required for site visits (exact specifications will be provided by PetroSA).
Health & Safety
Source: Annexure A1-Scope of Work.pdf
Include any Standard Safety File that is required to visit the site (exact specifications will be provided by PetroSA).
A compulsory site clarification meeting and inspection will be conducted.
Requirements
Source: Annexure A1-Scope of Work.pdf (TENDER)
Vendors must submit proposals for the replacement of legacy/non-operational systems, including replacement of faulty systems with current generation components, retaining functional infrastructure, and covering integration, commissioning and testing plan, and updated drawings.
PetroSA Database Administrators (accreditation/B-BBEE vetting): Phone 021 928 4731. Ask for the Tender Consultant (details on the online tender).
Submission Guidelines
Source: Supplier Self Registration.pdf (unknown)
This document describes the PetroSA supplier self-registration process, not the tender submission process. To participate in PetroSA tenders, suppliers must first complete this two-phase registration:
For assistance, contact CSD National Support: 012 406 9222 or [email protected].
Phase 2 – PetroSA Portal Registration:
Login at the PetroSA supplier portal using Username: MAAA..., User Code: MAAA..., Password: newuser.
For login assistance, contact support: 012 663 8815 or [email protected].
Change password on first login.
Click "Registration" link to start the 7-step registration wizard.
Complete each step; mandatory fields turn the step indicator green.
Step 6: Local suppliers must complete B-BBEE information and save.
Upload required documents via "Manage Attachments": click "Clear", enter description (e.g., "BEE certificate 2018"), upload file, click "Save". Repeat for each document.
Step 7: Declare conflict of interest (Yes/No) and save.
After submission, the Database Administrator vets and verifies the information.
If your accreditation status prevents online tendering or B-BBEE status is not vetted, contact PetroSA on 021 928 4731 and advise the Tender Consultant (contact on the online tender).
Returnable Documents
Source: Supplier Self Registration.pdf (unknown)
Document upload procedure for registration:
After Step 6, scroll to the bottom to see the list of required documents applicable to you.
Click "Manage Attachments" (top left).
For each document: click "Clear", enter a description in the Description field (e.g., "BEE certificate 2018"), click "Upload", select file from your directory, click "Open" (or double-click), then click "Save".
A "saved successfully" message appears; the document record shows at the bottom.
When uploading multiple documents, click "Clear" before each new upload.
Typical documents: B-BBEE certificate, company profile, and any other applicable certificates.
Evaluation Criteria
Source: Supplier Self Registration.pdf (unknown)
Eligibility is contingent on successful completion of the two-phase registration and vetting process. Key criteria include: a valid CSD registration, provision of accurate BEE status (for local suppliers), and submission of all required documentation. Suppliers must also ensure their accreditation status (e.g., BEE) does not preclude them from tendering online.
Technical Specifications
Source: Supplier Self Registration.pdf (unknown)
This document does not contain technical specifications for the gas suppression system tender. It only covers the document upload process during supplier registration:
After completing Step 6, scroll to the bottom to view the list of required documents.
Click "Manage Attachments" (top left) to upload each document.
For each document: click "Clear", enter a description (e.g., "BEE certificate 2018"), select file from your directory, click "Open" (or double-click), then click "Save".
A "saved successfully" message confirms upload; the document appears in the list at the bottom.
When uploading multiple documents, click "Clear" before each new upload.
Compliance Requirements
Source: Supplier Self Registration.pdf (unknown)
Registration compliance requirements:
B-BBEE Information: Local suppliers must complete the required B-BBEE fields in Step 6 of the registration wizard and save.
Conflict of Interest Declaration: In Step 7, declare whether a conflict of interest exists (Yes – provide declaration; No – confirm).
Document Submission: Upload all applicable supporting documents (e.g., B-BBEE certificate, company profile) via the attachment function.
CSD Registration: Phase 1 requires valid registration on the Central Supplier Database (www.csd.gov.za).
Vetting: All submitted information is vetted and verified by the Database Administrator before the supplier is accredited.
B-BBEE Requirements
Source: Supplier Self Registration.pdf (unknown)
B-BBEE compliance during registration:
Local suppliers must complete the required B-BBEE information fields in Step 6 of the registration wizard.
After entering details, click "Save". A "saved successfully" message confirms.
B-BBEE certificate must be uploaded as a supporting document via the attachment function (describe as e.g., "BEE certificate 2018").
The Database Administrator vets B-BBEE status; if not vetted, contact PetroSA on 021 928 4731.
Requirements
Source: Supplier Self Registration.pdf (unknown)
Conflict of interest declaration requirement:
In Step 7 of the registration wizard, indicate whether you have a conflict of interest.
If Yes: select "Yes" indicator and type the declaration.
If No: select "No" indicator.
Click "Save" to proceed.
This declaration is mandatory to complete registration.
Ensure you are a registered and approved PetroSA supplier to access the portal.
Submit all required documentation: Tender Notice, PetroSA Standard Terms and Conditions, Draft Service Agreement, Supplier’s BBBEE Proposal, National Industrial Participation Programme (SBD5 Form), General Requirements for Suppliers, and Occupational Health General Conditions and Guidelines.
Check for tender bulletins on the PetroSA procurement website before submission.
Tenders not submitted electronically by the closing date and time will not be considered.
Returnable Documents
Source: Quotation Notice.pdf (TENDER)
logging on to the procurement website www.procurement.petrosa.com and selecting the ‘Login to Access Tenders/Quotes tab’ and logging on to the E Procurement Portal.
Evaluation Criteria
Source: Quotation Notice.pdf (TENDER)
Supplier must be registered and approved on PetroSA Supplier Database. Must meet pre-qualification: BBBEE Level 4 contributor OR EME/QSE. Must attend mandatory scope clarification meeting/site inspection. Must submit all required documentation. No fronting allowed. For contracts above R30 million, minimum 30% subcontracting to 51% black-owned EME/QSE required.
Technical Specifications
Source: Quotation Notice.pdf (TENDER)
Scope: Technical assessment and repair/replacement of the gas suppression system at the PetroSA refinery in Mossel Bay.
Detailed scope of service and pricing requirements are in Sections 4 and 5 of the Draft Service Agreement.
Suppliers must comply with PetroSA's General Requirements for Suppliers and Occupational Health General Conditions and Guidelines for Contractors.
Mandatory site inspection required to understand local conditions and scope.
Experience & Qualifications
Source: Quotation Notice.pdf
Suppliers must be technically competent. If using a sister company, provide full proof of competency and service distribution.
Quality Management
Source: Quotation Notice.pdf
A mandatory site inspection and scope clarification meeting is required to understand the work and local conditions.
Pricing Schedule
Source: Quotation Notice.pdf
Submit prices as per the CBA total annual cost summary with a complete breakdown.
Detailed pricing requirements are in the draft services agreement.
Financial Requirements
Source: Quotation Notice.pdf (TENDER)
Submit prices as per the CBA total annual cost summary in the draft services agreement.
Provide a complete price breakdown.
Non-compliance with pricing format may lead to disqualification.
Compliance Requirements
Source: Quotation Notice.pdf (TENDER)
Supplier must be registered and approved on the PetroSA supplier database.
Registration on the National Treasury Central Supplier Database (CSD) is required.
Upload a POPI Statement/Notice/Policy to your PetroSA online registration.
Submit a BBBEE improvement plan with your tender.
Pre-qualification requirement: BBBEE Level 4 contributor, or an EME/QSE.
Maintain a valid B-BBEE certificate; expired certificates result in no preference points.
Declare tender submission is independent (Certificate of Independent Bid Determination SBD 9).
Consent to a due diligence check by PetroSA on legal, empowerment, technical, and financial status.
Subcontracting rules: If subcontracting >25%, submit a sub-contracting agreement. For subcontracts >25% to non-EMEs, the subcontractor must have equal or higher B-BBEE status.
Minimum 30% subcontracting to a 51% black-owned EME/QSE is required for contracts above R30 million.
Fronting is prohibited and will lead to disqualification and possible blacklisting.
B-BBEE Requirements
Source: Quotation Notice.pdf (TENDER)
Submit a BBBEE improvement plan.
Pre-qualification requires BBBEE Level 4 or EME/QSE status.
Maintain a valid B-BBEE certificate.
Subcontracting rules affect B-BBEE points.
Minimum 30% subcontracting to a 51% black-owned EME/QSE for large contracts.
Fronting is prohibited and will be investigated.
Health & Safety
Source: Quotation Notice.pdf
Compliance with PetroSA's Occupational Health General Conditions and Guidelines for Contractors is mandatory.
A whistleblower facility is available for reporting fraud.
Contractual Terms
Source: Quotation Notice.pdf
Contract period: 36 months.
Supplier consents to a due diligence check by PetroSA.
Any award is subject to a written contract or official purchase order.
PetroSA reserves the right to withdraw, reissue, or divide the tender scope.
PetroSA is not obliged to accept the lowest tender and reserves the right not to award.
Requirements
Source: Quotation Notice.pdf (TENDER)
The registered PetroSA supplier must submit the tender.
If subcontracting >25%, submit a sub-contracting agreement.
Joint ventures must provide full details on services, payment, liabilities, and management.
Agents cannot submit on behalf of holding companies and vice versa.
Section
Source: Quotation Notice.pdf
Points allocated per the Preferential Procurement Regulations 2024.
Two systems apply: 80/20 for contracts up to R50 million, 90/10 for contracts above R50 million.
Points awarded for Price and B-BBEE Status Level.
PetroSA may conduct a reverse auction with shortlisted suppliers.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.