ESKOM requires the supply and delivery of metallic piping and related cooling water system components for the west half station shutdown at camden power station in mpumalanga. Bids are lodged electronically only, through eskom's etendering portal, which cannot be entered without a csd number. Uploads are capped at 50mb per file and 900mb in total, and the bid is not lodged until the submission is finalised on the portal. The tender closes on 9 december 2026 at 10:00.
Key Requirements
Electronic submission only — bids are lodged on Eskom's eTendering portal at https://eTendering.eskom.co.za; uploading has replaced physical lodgement at Eskom tender offices.
CSD registration — a CSD number is required before the eTendering portal can be accessed, so a bid cannot be submitted without it.
Closing deadline — 9 December 2026 at 10:00; all documents must be uploaded and the submission finalised on the portal before this time.
Upload limits — no single file may exceed 50MB, and the combined size of all uploaded files may not exceed 900MB.
Finalisation — the bid is only lodged once Finalise and Close Submission is clicked; a confirmation email quoting the submission ID is issued and must be retained for later enquiries.
Portal access — register with an email address and a cellphone number in international format starting with +27, verify the emailed link, then log in with the one-time PIN sent to both the cellphone and email address.
System problems — difficulties with the Tender Bulletin, eTendering or OpenText must be raised with the buyer responsible for the published tender.
Document read. The full tender notice and its supporting documents are read end-to-end. Key sections, requirements, dates, and contact details are identified and pulled into a working summary you can act on.
Compliance review. The working summary is checked against South African procurement standards — PFMA, PPPFA, B-BBEE, CIDB, local content, and preferential procurement — so nothing critical is missed before you start your bid response.
Procurement Rules & Compliance ContextThis tender may be governed by South African public procurement rules covering fairness, transparency, preferential procurement, anti-corruption, administrative justice and access to information.
7 rules
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
Core procurement rules
These rules commonly apply to South African public-sector procurement.
7
Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
high
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Constitution of the Republic of South Africa, 1996 – Section 217
Act 108 of 1996 (s217)
high
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Eskom - Standard Conditions of Tender - 30 January 2025.pdf
Supply and delivery of cooling water system components — metallic piping — for the Camden west half station shutdown, for Eskom in Mpumalanga. The scope covers the supply and delivery of metallic piping components required during the west half station shutdown.
Supply and delivery of metallic piping components for the cooling water system, required for the Camden west half station shutdown, procured by Eskom in Mpumalanga.
Supply and delivery of cooling water system components — metallic piping — for the Camden West half station shutdown in Mpumalanga. Bidders must operate a quality management system conforming to ISO 9001 and comply with Eskom's Supplier Quality Management Specification 240-105658000 (QM 58, Revision 3).
Supply and delivery of metallic piping forming part of the cooling water system components for the Camden Power Station west half station shutdown, for Eskom in Mpumalanga. The procurement closes on 9 December 2026 at 10:00.
Supply and delivery of metallic piping components for the cooling water system at Eskom's Camden power station, required for the west half station shutdown in Mpumalanga. The tenderer must acknowledge and comply with Eskom's Supplier Quality Requirements as per specification 240-105658000 and ISO 9001.
Supply and delivery of metallic piping components for the cooling water system at Camden Power Station, required for the west half station shutdown. The contract is managed by Eskom and includes environmental compliance obligations.
Supply and delivery of cooling water system components — metallic piping — for the Camden west half station shutdown in Mpumalanga. Bidders must submit a Contract Quality Plan setting out how quality management will be applied across the contract, aligned to SANS 466:2005 Edition 1 and ISO 10005:2005 Edition 2.
Acknowledgement Form for Eskom SHE Rules and other Requirements.docx
Supply and delivery of cooling water system components, specifically metallic piping, for the Camden west half station shutdown, procured by Eskom in Mpumalanga. The contract includes strict compliance with Eskom's occupational health and safety (OHS) requirements and applicable South African legislation.
Supply and delivery of metallic piping components for the cooling water system, required for the Camden west half station shutdown, procured by Eskom in Mpumalanga.
240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsx
Supply and delivery of metallic piping components for the cooling water system at Camden power station, required for the west half station shutdown. The procurement is managed by Eskom in Mpumalanga, with a closing date of 9 December 2026 at 10:00.
Supply and delivery of metallic piping components — plate and slip-on flanges, seamless pipes, butt-weld elbows and equal tees — for the Camden Power Station West-side Half-Station Shutdown, which supports refurbishment and replacement of Main Cooling Water system piping. The components are procured against a fixed Bill of Materials of 16 stock-numbered line items for installation during the 2027 West HSSD.
Supply and delivery of cooling water system components — metallic piping — for the Camden west half station shutdown, for Eskom in Mpumalanga. Bids are submitted electronically through Eskom's eTendering portal rather than by physical delivery to an Eskom tender office.
Supply and delivery of metallic piping components, including flanges, pipes, elbows, and tees, for the Camden power station west half station shutdown. The contract is between Eskom Holdings SOC Ltd and a supplier, using the NEC3 Supply Short Contract (SSC3) form.
Eskom Generation Camden Power Station requires the supply and delivery of metallic piping components for the cooling water system as part of the Camden West Half-Station Shutdown. The contract is a once-off procurement with evaluation under the Preferential Procurement Policy Framework Act, including specific goals for B-BBEE and socio-economic development.
Supply and delivery of metallic piping components for the cooling water system at Camden Power Station's West Half-Station shutdown, scheduled for April 2027. The procurement is managed by Eskom and includes mandatory compliance with Eskom stock descriptions and material certification requirements.
240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP)-rev 3.docx
Supply and delivery of metallic piping components for the cooling water system at Eskom's Camden power station, specifically for the west half station shutdown in Mpumalanga. The procurement includes quality control planning, inspection, and testing requirements.
Eskom Supplier Integrity Pact - 02 June 2023 (1).pdf
Supply and delivery of metallic piping components for the cooling water system at Camden power station, required for the west half station shutdown. The procurement is managed by Eskom and is subject to the Eskom Supplier Integrity Pact, which bidders must accept and comply with.
Eskom requires the supply and delivery of metallic piping components for the cooling water system, specifically for the Camden west half station shutdown in Mpumalanga. The tender involves a confidentiality agreement that bidders must sign before receiving detailed information.
Supply and delivery of cooling water system components — metallic piping — for the Camden west half station shutdown, for Eskom in Mpumalanga, closing 9 December 2026 at 10:00. Work and supply for Eskom is governed by the Life Saving Rules standard (240-62196227, Rev 6), which applies to all Eskom employees, agents, consultants and contractors and carries a zero-tolerance stance on violations.
Supply and delivery of metallic piping forming part of the cooling water system components for the Camden Power Station west half station shutdown. The work is for Eskom in Mpumalanga.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Similar Tenders
Matched by category & region
Supplier Readiness Hub
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Bid-ready summary. The submission guidelines, evaluation criteria, technical, financial, and compliance sections are refined into professional, easy-to-scan prose. This is the final version you can rely on when preparing your bid or briefing your team.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Document read
Compliance review
Bid-ready summary
Purpose and applicability
The specification standardises vehicle safety requirements across Eskom to meet legislative and internal procedural obligations.
It sets the minimum vehicle-related specifications for Eskom and for contractors, subcontractors and third-party service providers carrying out work for or on behalf of Eskom, including the transport of Eskom and contractor employees.
It applies to vehicles and equipment across Eskom Holdings SOC Ltd, its divisions and subsidiaries, scheme vehicles, and any vehicle used for Eskom business purposes.
Divisions may add supplementary specifications provided they comply with OEM specifications and legislation and do not expose employees, contractors or the public to risk.
Where the specification does not cover a particular vehicle or attached equipment, the division must apply the relevant standard, regulation, code of practice or legislation.
Only newly purchased vehicles and new contracts must comply; existing vehicles are replaced on a phased basis under the Fleet Services replacement plan, and scheme and non-Eskom vehicles must comply when the specific vehicle is replaced.
The specification takes effect three months after the authorisation date.
Minimum vehicle safety specifications apply to all Eskom-owned vehicles and to any vehicle used for Eskom business, including contractor and subcontractor vehicles, scheme vehicles and private vehicles used for Eskom work, whether driven inside or beyond South Africa's borders.
Only newly purchased vehicles and new contracts must comply; vehicles already in service are replaced on a phased basis under the Fleet Services Department replacement plan.
The specification takes effect three months after its authorisation date.
Standard minimum equipment (all vehicles)
Euro NCAP 4 rating for models tested in South Africa or Europe.
Factory-fitted ABS, driver and passenger airbags, alarm/immobiliser, power steering, air conditioner and seatbelt reminder.
Tyres matching the manufacturer's specification for the intended application.
Two emergency warning triangles.
Daytime running lights, or dipped headlights switched on for daylight driving.
Reverse-park distance control sensor on Eskom-owned vehicles.
Reverse beeper on heavy commercial vehicles, buses, construction equipment and vehicles used on construction sites.
Emergency contact number label on the rear right-hand side, showing the operating unit's all-hours number and following corporate identity rules.
Vehicle-monitoring device and driver behaviour camera fitted to all Eskom-owned vehicles.
Hired or leased vehicles: Treasury Note B-class standard with airbags and ABS.
Private vehicles: at least two factory-fitted airbags and factory-fitted ABS.
Light delivery vehicles (under 3 500 kg)
Must meet the standard minimum equipment.
A roll bar for cab protection is required where a risk assessment shows a rollover risk, such as extensive gravel-road travel.
Heavy commercial vehicles (GVM above 3 500 kg, including above 16 000 kg and abnormal vehicles)
Must comply with the National Road Traffic Act and the standard minimum equipment, plus reverse lights, yellow reflective tape, anti-spray mud flaps, under-run protection to SANS 1055, chevron warning plates, a speed limit warning sign and applicable transport warning signs.
ABS, airbags, alarm/immobiliser and power steering are required where available in the market.
Tool boxes and other apparatus must be secured so they do not weaken the vehicle structure or create a risk in a rollover or collision.
Crew cabs may not be fitted.
Minibuses (up to 16 passengers)
SANS-approved three-point seatbelts on every seat; no fold-up or jockey seats.
Speed warning sign on the rear and yellow reflective tape.
Adjustable, partitioned driver's seat.
Tyres to the manufacturer's commercial specification; front axle tyres must be identical in make and model.
At least one emergency exit per 12 passengers.
Panel vans or goods-delivery vehicles may not be converted into minibuses.
A sign must indicate that the vehicle is equipped to carry passengers with disabilities.
Midi-buses (17 to 34 passengers) and buses (35 or more passengers)
SANS-approved seatbelts on every seat; no fold-up or jockey seats.
Speed warning sign on the rear and yellow reflective tape.
Adjustable driver's seat with a partitioned driver's compartment.
Tyres to the manufacturer's specification; front axle tyres must be identical in make and model.
At least two identified emergency exits per 12 passengers.
Anti-slip treads on steps.
Panel vans or goods-delivery vehicles may not be converted into midi-buses.
Vehicles carrying employees with disabilities should be wheelchair-friendly, with signage where the vehicle is designed for that purpose.
Trailers and caravans
Eskom-owned, rented and hired trailers and caravans must meet National Road Traffic Act requirements.
A trailer risk assessment and inspection governs compliance.
Construction vehicles
Must meet OHS Act Construction Regulation 23, the National Road Traffic Act, the Mine Health and Safety Act and the National Environmental Management Act.
Requirements include operator protection against falling material and overturning, acceptable design and construction, safe access and egress, signalling and control arrangements, an operator-activated acoustic warning device, an automatic reversing alarm, and telescoping whips with triangle flags for mining and construction sites.
Specialised vehicles
Golf carts, quad bikes, self-balancing scooters and similar units must meet the applicable OEM standard and Eskom Fleet Safety specifications.
Retrofitting and modifications
Elevated warning lights must be fitted where needed on LDVs, minibuses, midi-buses, buses, tractors and vehicles with canopies.
Modifications to Eskom-owned vehicles must follow the Fleet Management Policy, be certified safe by the manufacturer, be approved by the Fleet section, and be installed by the dealer or an approved fitment centre.
Methodology
Source: 3. Eskom Vehicle Safety Spec 32-345.pdf
Implementation approach
Only newly purchased vehicles and new contracts must meet the specification.
Vehicles already in service are replaced on a phased basis according to the Fleet Services Department's replacement plan, unless the business decides otherwise.
Scheme and non-Eskom vehicles must comply when the specific vehicle is replaced.
Divisions may set supplementary specifications that stay within OEM requirements and legislation without increasing risk to employees, contractors or the public.
Quality Management
Source: 3. Eskom Vehicle Safety Spec 32-345.pdf
Monitoring and audit
The operating or business unit audits compliance with the specification at least annually as part of its internal audit and review process.
Sustainability Systems OHS may carry out compliance inspections from time to time.
The Assurance and Forensic Department, or its delegate, audits all records at a frequency it determines.
Vehicle inspection sheets for the relevant vehicles support the process.
SANS 9001 quality management systems is listed as an informative reference.
Occupational Health and Safety Act, including the Construction Regulations
Mine Health and Safety Act
National Environmental Management Act
Administrative Adjudication of Road Traffic Offences Act (AARTO)
Standards
SANS 1055 — rear under-run protective devices
SANS 1563 — rollover protection strength for large passenger vehicle superstructures
SANS 9001 — quality management systems
SANS 39001 — road traffic safety management systems
SANS 45001 / ohsas 18001
Eskom internal documents
240-62582234 — OHS roles, responsibilities and statutory appointments
240-62946386 — vehicle and driver safety management procedure
32-109 — corporate identity policy
32-129 — managing the Eskom business vehicle scheme
32-136 — contractor health and safety requirements
Fleet Services technical specifications for the relevant vehicle types
Accountability
The section 16(2)-delegated employer and appointed responsible managers must ensure compliance in their designated areas.
Compliance is audited by the operating or business unit at least annually, by Sustainability Systems OHS on inspection, and by the Assurance and Forensic Department at a frequency it determines.
Health & Safety
Source: 3. Eskom Vehicle Safety Spec 32-345.pdf
OHS framework
The specification incorporates Eskom requirements, the National Road Traffic Act and the Construction Regulations under the Occupational Health and Safety Act.
The section 16(2)-delegated employer and appointed responsible managers are accountable for compliance in their designated areas, in line with Eskom's OHS roles and responsibilities standard (240-62582234).
Construction vehicles must meet OHS Act Construction Regulation 23, the National Road Traffic Act, the Mine Health and Safety Act and the National Environmental Management Act.
Construction vehicles require operator protection against falling material and overturning, safe access and egress, signalling and control arrangements, an operator-activated acoustic warning, an automatic reversing alarm, and telescoping whips with triangle flags on mining and construction sites.
Contractor health and safety requirements are set out in Eskom document 32-136.
SANS 45001 / OHSAS 18001 and SANS 39001 road traffic safety management systems are listed as informative references.
Camden Power Station is running a Half-Station Shutdown (HSSD) of its West-side units to inspect, refurbish and maintain the Main Cooling Water (CW) system, which is shared by all four West-side units.
Objective: refurbish or replace critical piping sections that cannot be accessed safely while the units are in operation.
This scope covers only the metallic piping components for the shutdown.
The station originally tried to procure all West-side HSSD spares as one turnkey project, but that approach was rejected through the sole-source steercom process.
The turnkey scope was split into several smaller procurement transactions, adding interfaces and schedule risk to the availability of spares before the outage.
Camden will not be ready to execute the West-side HSSD in December 2026 as shown in the outage listing; the planned start date must be reviewed and revised to allow time for procurement, manufacture, refurbishment and delivery.
Applicability: Eskom Camden Power Station, 2027 West-side Half-Station Shutdown.
Supply and delivery of replacement metallic piping components — flanges, pipes, elbows and tees — for the Camden Power Station West-side Half-Station Shutdown (HSSD), 2027.
The components form part of the Main Cooling Water (CW) system; the shutdown allows refurbishment or replacement of critical piping that cannot be reached while the units are running.
Delivery point: Camden Power Station.
No deviations from the specified technical requirements are permitted.
Bill of materials — stock no. / component / quantity
774634 — DN80 EN plate flange, slip-on type 01, P235GH, B1 raised face, PN10, EN 1092-1 — 10
774658 — DN100 EN plate flange, slip-on type 01, P235GH, B1 raised face, PN10, EN 1092-1 — 80
774797 — DN150 EN plate flange, slip-on type 01, P235GH, B1 raised face, PN10, EN 1092-1 — 100
774663 — DN200 EN plate flange, slip-on type 01, P235GH, B1 raised face, PN10, EN 1092-1 — 10
774665 — DN250 EN plate flange, slip-on type 01, P235GH, B1 raised face, PN10, EN 1092-1 — 48
774703 — DN450 (NPS 18) seamless equal tee, butt weld, ASTM A234 WPB, Standard wall (9.53 mm nominal), ASME B16.9 — 8
Supplier obligations
Verify the accuracy and completeness of Eskom's specifications and align them with Eskom internal standards and applicable international standards.
Confirm the full technical descriptions of all stock items and supply strictly in accordance with the applicable SAP stock descriptions and technical requirements.
Submit a detailed delivery schedule giving planned delivery dates for every item, and issue early warning notifications without delay for any deviation from the approved schedule.
Normative references
ISO 9001; EN 10204; Occupational Health and Safety Act of 1993.
Eskom 240-105658000 (Supplier Contract Quality Management Specification, QM-58) and 240-123801640 (Standard for Low Pressure Pipelines).
Drawing and documentation standards 240-76992014, 240-65459834, 240-54179170, 240-66920003 and 240-86973501.
Latest approved editions apply; any requirements introduced by later revisions must be met.
The supplier must verify the accuracy and completeness of Eskom's specifications and align them with Eskom internal standards and applicable international standards.
Every piping component must be supplied with an EN 10204 Type 3.1 inspection certificate in English.
Certification must be traceable to the heat number permanently marked or otherwise identifiable on each individual component.
Components supplied without the Type 3.1 certificate, without heat-number traceability, or with certification in a language other than English will be rejected.
Standards to comply with
ISO 9001 Quality Management Systems.
EN 10204 Metallic Products — Type of Inspection Documents.
Occupational Health and Safety Act of 1993 (OHSACT).
The Occupational Health and Safety Act of 1993 (OHSACT) is a normative reference for this scope. No further safety plan, HSE or site-safety requirements are specified.
DocumentE-Tendering Help Manual for supplier.pdfReview complete
Description
Source: E-Tendering Help Manual for supplier.pdf
The eTendering portal is Eskom's web-based channel for submitting tender documents, replacing physical delivery to Eskom tender offices. Suppliers must register on the portal, verify their email address, and pass one-time PIN verification on the registered cellphone number and email address before they can load a bid. Tenders are advertised on the Tender Bulletin, which carries the link to the portal. A CSD number is a prerequisite for portal access. Difficulties with the Tender Bulletin, eTendering or OpenText must be taken up with the buyer responsible for the tender. Eskom may also invite selected suppliers by email to bid privately on closed tenders that are not advertised on the Tender Bulletin.
Submission Guidelines
Source: E-Tendering Help Manual for supplier.pdf (TENDER)
Submission channel
Bids are lodged electronically through Eskom's eTendering portal at https://eTendering.eskom.co.za; uploading on the portal has replaced physical lodgement at Eskom tender offices.
Tenders are advertised on the Tender Bulletin at https://tenderbulletin.eskom.co.za, which links through to the eTendering portal.
A CSD number is required before the portal can be accessed.
Registration and login
Register on the portal with a valid email address and a cellphone number entered in international format starting with +27.
Registration must be verified by clicking the link emailed by the system; the verification email can be resent if it does not arrive.
Login uses the verified email address and password, followed by a one-time PIN sent to both the registered cellphone number and email address.
Uploading and finalising
Select the reference number, open the tender record, and start a new submission.
Give each file a name and classify it by type (technical, commercial, finance, and so on).
Maximum size per file: 50MB. Maximum combined size of all uploaded files: 900MB.
Upload every required document under the correct category and check the set is complete before finalising; the submission is only complete once it is finalised and closed.
If documents are still outstanding, the submission can be kept open instead of finalised.
A confirmation email listing the submitted files and quoting a submission ID is sent to the submitter; keep it for later enquiries.
System problems
Difficulties with the Tender Bulletin, eTendering or OpenText must be raised with the buyer responsible for the published tender.
Closed tenders
Eskom may email selected suppliers a private link to bid on closed tenders that are not published on the Tender Bulletin.
Browser
The portal supports most browsers; Microsoft Edge is recommended.
Compliance Requirements
Source: E-Tendering Help Manual for supplier.pdf (TENDER)
CSD registration
A CSD number is required before the eTendering portal can be accessed and a bid submitted.
Section
Source: E-Tendering Help Manual for supplier.pdf
Closed tenders
Eskom may identify suppliers that meet its selection and evaluation criteria and email them a private link to bid on tenders that are not advertised on the Tender Bulletin.
DocumentSupplier Declaration of Interest Template.docxReview complete
Description
Source: Supplier Declaration of Interest Template.docx
The document provided is the Eskom Supplier Declaration of Interest Template (form 240-59385360 Rev 3). It is a standard declaration form, not a full tender specification. The tender itself is for the supply and delivery of cooling water system components – metallic piping for the Camden west half station shutdown.
Submission Guidelines
Source: Supplier Declaration of Interest Template.docx (unknown)
Returnable documents:
Supplier Declaration of Interest Template (Eskom form 240-59385360 Rev 3): must be completed, signed under oath, and submitted with the bid. It declares any conflicts of interest, including Eskom employment, family or associate relationships with Eskom employees/directors, business courtesies exchanged in the last 12 months, and other work for Eskom or its related entities. A false declaration may result in action against the supplier or the signatory personally.
Evaluation Criteria
Source: Supplier Declaration of Interest Template.docx (unknown)
No evaluation criteria are stated in the document. The only requirement is the completion and submission of the Supplier Declaration of Interest as a returnable.
Technical Specifications
Source: Supplier Declaration of Interest Template.docx (unknown)
The tender is for the supply and delivery of cooling water system components – metallic piping for the Camden west half station shutdown. No further technical specifications are provided in the document.
Compliance Requirements
Source: Supplier Declaration of Interest Template.docx (unknown)
No specific compliance requirements are stated beyond the Supplier Declaration of Interest.
DocumentAcknowledgement Form for Eskom SHE Rules and other Requirements.docxReview complete
Description
Source: Acknowledgement Form for Eskom SHE Rules and other Requirements.docx
The tender is for the supply and delivery of cooling water system components, specifically metallic piping, for the Camden west half station shutdown. The document provided is an acknowledgement form for Eskom OHS legal and other requirements, which the supplier must sign to confirm understanding and compliance with Eskom's health and safety standards, the OHS specification, the Occupational Health and Safety Act 85 of 1993, and the Compensation for Occupational Diseases and Illnesses Act 130 of 1993.
Evaluation Criteria
Source: Acknowledgement Form for Eskom SHE Rules and other Requirements.docx (unknown)
Bidders must complete and sign the Annexure B Acknowledgement Form for Eskom OHS legal and other requirements, confirming understanding and compliance with the listed OHS documents. The form must be signed by an authorised person (CEO/Director/Managing Director) and witnessed by two witnesses. No other eligibility criteria are stated in the provided document.
Compliance Requirements
Source: Acknowledgement Form for Eskom SHE Rules and other Requirements.docx (unknown)
The contract covers fuel oil supply at Camden Power Station. The tender specifically requires the supply and delivery of metallic piping for the cooling water system during the west half station shutdown.
Bidders must comply with the referenced environmental and safety standards, including ISO 14001:2015, the National Environmental Management Act 107 of 1998, the National Environmental Management Waste Act 59 of 2008, the Hazardous Chemical and Substance Regulation, the Occupational Health and Safety Act No. 85 of 1993 and Regulations 19th Edition, Eskom SHEQ requirements, and EIA regulations screening and scoping. Returnable documents include:
Environmental Policy
Environmental Management Plan (with method statements for each activity)
Environmental Risk Assessment (aspects and impacts)
Proof of employee training on environmental risks
List of all waste streams (including packing material)
Waste management programme and housekeeping method statements
Recycling programme for all waste streams
Hazardous Substances and Material Register (or state 'no hazardous material' in the EMP)
Safety Data Sheets for each hazardous/chemical waste stream
Completed Camden Power Station Modification Environmental Impact Process form
Scope of work: Fuel oil contract at Camden Power Station. The tender is for the supply and delivery of cooling water system components – metallic piping for the Camden west half station shutdown. Environmental compliance requirements apply to the contract.
No specific compliance requirements stated beyond the environmental and safety standards listed in the evaluation criteria.
DocumentEskom - Standard Conditions of Tender - 30 January 2025.pdfReview complete
Important Dates
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)
Closing date: 9 December 2026 at 08:00 (SAST)
Compulsory site visit or clarification meeting: details stated in the Tender Data; attendance is compulsory and failure results in disqualification.
Contact Information
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)
Contact: Eskom Representative (as identified in the Invitation to Tender)
All communication must be directed to the Eskom Representative only, in writing, in English.
Submission address: as stated in the Tender Data (tender box at the tender office).
Service/delivery address: Camden Power Station, Mpumalanga (as per tender title).
Submission Guidelines
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)
Submission method: paper tender, original plus one (1) complete copy, each in a separate sealed package marked "ORIGINAL" and "COPY".
Outer package must be sealed, marked "Confidential", and show the Invitation to Tender number, the tenderer's name, physical address, email address and contact telephone number of the authorised signatory.
Tenders must be submitted in English, completed in ink (not pencil).
The Acknowledgement Form must be completed and submitted with the tender, stating whether the tender is for the whole or part of the scope.
The original tender must be signed by a person duly authorised to bind the tenderer.
No tender will be accepted after the closing date and time; proof of posting or courier dispatch does not count as delivery.
Eskom will not accept responsibility for misplacement or premature opening if the outer package is not sealed or the address/reference is incorrect.
Mandatory returnables must be submitted by the closing date and time; documents required for contract award must be provided before award.
All returnable documents must be fully completed; incomplete or unsigned documents may disqualify the tender.
Where an agent submits on behalf of a principal, an authenticated copy of the authority to act as agent must be included.
Tenderers must not alter or add to tender documents except to correct errors, and corrections must be initialled by all signatories; correction fluid or tape is not permitted.
Alternative tenders are allowed only if a main tender is also submitted and only if permitted by the Invitation to Tender.
Tenderers must not sub-contract 100% of the scope of work; such tenders are ineligible.
Tenderers must not be under any restriction to do business with Eskom or State-Owned Companies.
Failure to attend a compulsory site visit or clarification meeting results in disqualification.
Tenderers must check the Eskom Tender Bulletin and NT e-Tender Portal regularly for addenda and clarifications.
Evaluation Criteria
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)
Evaluation stages:
Basic compliance: tender must meet all basic compliance requirements stated in the Invitation to Tender; failure renders the tender non-responsive.
Mandatory returnables: tender must contain all mandatory documents and information by the closing date and time; otherwise disqualified.
Pre-qualification criteria: if stipulated, tenderers must comply; Eskom will not measure a criterion twice (no double dipping).
Functionality: if applicable, tenderers are scored against functionality criteria and must meet the minimum threshold stated in the Tender Data to proceed.
Financial analysis: Eskom assesses the financial risk of doing business with the tenderer; if risk is too high and no mitigating factors exist, the tenderer will not be considered for award.
Price evaluation: price is evaluated per the Tender Data, considering factors such as CPA, FOREX, commodity exposure, unconditional discounts, technical adjustment, PV and forecasted invoicing rates.
B-BBEE scoring: B-BBEE level is scored from the CSD report or certificate/affidavit provided.
Specific Goals: scored with reference to supporting documentation; failure to meet or submit proof results in zero points for Specific Goals within the 90/10 or 80/20 allocation.
Ranking: price score and Specific Goals score are added and suppliers ranked highest to lowest.
Arithmetical errors: if figures and words disagree, the amount in words prevails; Eskom will correct errors and the corrected total is binding unless the tenderer rejects the correction, in which case the tender is rejected.
Objective criteria may be used only as stipulated in the Invitation to Tender; functionality and B-BBEE scorecard elements may not be used as objective criteria.
Reverse e-auction may be used if indicated; if used, tenderers must submit a complete tender without prices.
Technical Specifications
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)
Scope: Supply and delivery of cooling water system components – metallic piping for the Camden West half station shutdown.
Location: Camden Power Station, Mpumalanga.
The tender is for the supply and delivery of metallic piping components as part of the cooling water system.
Tenderers must be able to supply the specified components and deliver them to the site.
All materials delivered to Eskom must be labelled in line with Eskom's labelling specifications.
The successful tenderer may be required to provide cataloguing information per item after contract award; if cataloguing is required, a line item must be included in the pricing schedule.
Financial Requirements
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)
Pricing:
Rates and prices must be in South African Rand unless otherwise instructed.
Prices must be fixed for the duration of the contract and not subject to price adjustment except as provided in the Invitation to Tender.
Include all duties, taxes (including VAT) and levies applicable 14 days prior to the closing date and time.
If a bill of quantities or pricing schedule applies, unit rates and line-item totals must be completed correctly; arithmetical errors will be corrected by Eskom.
If security for performance is required, the tenderer must indicate at least two (2) financial institutions it is likely to approach for the security; Eskom may reject unsuitable institutions.
Eskom will not compensate tenderers for any costs incurred in preparing or submitting a tender.
Insurance: Eskom's insurance may not cover the full extent required; tenderers should seek qualified advice.
Compliance Requirements
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf (TENDER)
Eligibility:
Must comply with eligibility criteria stated in the Tender Data and not be under any restriction to do business with Eskom or State-Owned Companies.
Must not sub-contract 100% of the scope of work.
CIDB:
If CIDB grading is stipulated as a qualification criterion, tenderers must be registered with CIDB at closing or be capable of being registered within 21 working days of closing.
Proof of CIDB registration is mandatory at closing; if only proof of application is available at closing, that must be submitted, and the actual CIDB printout must be submitted by contract award.
B-bbee:
If B-BBEE level is a pre-qualification criterion, proof (certificate, CSD number or CSD report) must be provided at closing; otherwise the tender is disqualified.
If sub-contracting to designated groups is a pre-qualification criterion, the sub-contractor's CSD number or B-BBEE certificate/affidavit must be provided at closing.
Fraudulent or expired B-BBEE documents lead to disqualification; for PPPFA point allocation, absence of valid B-BBEE proof results in zero points (not disqualification).
Legislative compliance:
Must comply with National Treasury Instruction Notes, CIDB Regulations, PPPFA Regulations, Amended B-BBEE Codes, COIDA, OHS Act, and Eskom's SHEQ requirements.
Sheq:
Must provide proof that safety, health, environmental and quality (SHEQ) systems, policies and capabilities are in place at closing and/or contract award; all SHEQ costs and personnel must be reflected in the tender.
SDL&I Undertaking:
Must be completed and submitted by no later than contract award; otherwise the tender will not be considered for award.
Designated materials and thresholds:
Information on designated materials and thresholds must be submitted no later than contract award; otherwise the tender will not be considered for award.
Misrepresentation:
Misrepresented or falsified information, certificates, affidavits or documents may lead to disqualification, reporting to the B-BBEE Commission, suspension from doing business with State-Owned Companies for up to 10 years, and possible imprisonment.
Contractual Terms
Source: Eskom - Standard Conditions of Tender - 30 January 2025.pdf
Briefing:
A site visit and/or clarification meeting may be stipulated as compulsory in the Tender Data.
Failure to attend a compulsory site visit or clarification meeting results in disqualification.
Details of the meeting(s) are stated in the Tender Data.
Tenderers are entitled to ask questions for clarity during the site visit or clarification meeting.
Document240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsxReview complete
Description
Source: 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsx
The tender is for the supply and delivery of cooling water system components – metallic piping for the Camden West half station shutdown. The document provided is a quality returnables template; detailed technical specifications are not included in this extract.
Submission Guidelines
Source: 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsx (unknown)
Returnable documents:
Form A: completed and signed.
The applicable category must be selected on the Cover tab (only one category).
The returnables template must be saved as PDF and signed, or signed and locked before sending.
Quality documentation required for the selected category must be submitted with the bid.
Evaluation Criteria
Source: 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsx (unknown)
Evaluation is based on a quality scorecard with weighted sections:
Section A (Quality Management System Requirements, ISO 9001): weight 25%.
Section B (Evidence of QMS in operation): weight 25%.
Section C (Contract Quality Plan): weight 20%.
Section D (Quality Control Plan / ITP): weight 20%.
Section E (User-defined additional requirements, including Form A): weight 10%.
Bidders must achieve scores in each section as evaluated. The scorecard is used to evaluate quality documentation submitted with the tender.
Technical Specifications
Source: 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsx (unknown)
The tender is for the supply and delivery of cooling water system components – metallic piping for the Camden West half station shutdown. The document provided is a quality returnables template; detailed technical specifications are not included in this extract.
Compliance Requirements
Source: 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.xlsx (unknown)
Bidders must comply with the quality requirements of the selected category, including submission of the required quality management system documentation, audit reports, and quality plans.
DocumentSDL&I.docxReview complete
Description
Source: SDL&I.docx
The tender is for the supply and delivery of cooling water system components – metallic piping for the Camden West Half-Station Shutdown at Camden Power Station. The contract is once-off. Specific goals (SDL&I) contribute up to 10/20 points under the preference point system, and the contract is awarded to the tenderer with the highest total points.
Submission Guidelines
Source: SDL&I.docx (unknown)
Returnable documents:
SBD 6.2 (Declaration for Local Production and Content) and Annex C (Local Content Declaration – Summary Schedule) are mandatory if applicable.
Proof of a subcontract agreement or a letter of intent to subcontract to designated suppliers (EME/QSE with at least 51% black ownership) is required.
Valid B-BBEE certificate (SANAS accredited), sworn affidavit, or CIPS affidavit as applicable.
Proof of ownership/shareholding (preferably CIPC documentation) with shareholding breakdown.
Certified ID copies of shareholders.
For trusts, consortia, or joint ventures, a consolidated B-BBEE certificate.
Proof of Disability (where applicable).
Eskom will not accept a sworn affidavit with an electronic signature.
Bidders failing to provide preference point documentation will not be disqualified but will score 0 for specific goals.
Evaluation Criteria
Source: SDL&I.docx (unknown)
Evaluation is based on the 90/10 or 80/20 preference point system. Price points are out of 90 (90/10 system) or 80 (80/20 system). Specific goals (SDL&I) contribute up to 10 points (90/10) or 20 points (80/20). The contract is awarded to the tenderer scoring the highest total points.
B-BBEE points (specific goals) are awarded as follows:
Level 1: 10 (90/10) / 20 (80/20)
Level 2: 9 / 18
Level 3: 6 / 14
Level 4: 5 / 12
Level 5: 4 / 8
Level 6: 3 / 6
Level 7: 2 / 4
Level 8: 1 / 2
Non-compliant: 0 / 0
SDL&I objectives (transformation, local procurement, jobs, skills development) do not form part of scoring, but commitments become contractual obligations. Tenderers who do not meet Eskom's SDL&I targets will not be disqualified.
Technical Specifications
Source: SDL&I.docx (unknown)
Supply and delivery of cooling water system components – metallic piping for the Camden West Half-Station Shutdown at Camden Power Station (Generation Business Unit). The scope is a once-off supply and delivery.
Financial Requirements
Source: SDL&I.docx (unknown)
Eskom will apply a penalty of 1% of the contract value for failure to meet SDL&I obligations. For the duration of the contract, Eskom will retain 1% of every invoice (excluding VAT) as security for the fulfilment of all SDL&I obligations. The retained amounts are released only upon full fulfilment of SDL&I obligations.
Compliance Requirements
Source: SDL&I.docx (unknown)
B-BBEE requirements:
Annual total revenue R10 million or less (EME): may submit a sworn affidavit.
Annual total revenue R50 million or less (QSE): must comply with all elements of the QSE scorecard relevant to the sector, unless at least 51% black-owned, in which case a sworn affidavit is required.
Annual total revenue above R50 million: must submit a valid B-BBEE certificate.
A valid B-BBEE certificate or sworn affidavit is a condition for contract award.
Local content:
Where a contract involves a combination of local and imported goods/services, the tender response must be separated into components as per the Price Schedule.
Local procurement content is total spending minus the imported component.
Subcontracting:
The tenderer must subcontract some of the scope to designated suppliers (EME/QSE with at least 51% black ownership). Designated suppliers must not be subsidiaries or have shares in the tenderer's company; preferably selected from local to site.
Skills development:
The recommended tenderer must skill two candidates of each skill type for the duration of the contract, with monthly progress demonstrated.
Bursaries must cover tuition and stipend.
Candidates must be from the Msukaligwa Municipality.
These targets exclude Eskom employees and registered learners.
The tenderer bears the full cost; Eskom makes no financial contribution.
DocumentEskom Supplier Integrity Pact - 02 June 2023 (1).pdfReview complete
Description
Source: Eskom Supplier Integrity Pact - 02 June 2023 (1).pdf
The Eskom Supplier Integrity Pact applies to Eskom Holdings SOC Ltd and its wholly owned subsidiaries, and to every existing and prospective supplier, consultant, contractor, sub-contractor and provider of goods or services, including those registered on the Eskom Vendor Database.
Purpose
Sets out the ethical conduct Eskom expects from suppliers and from its own employees and directors throughout procurement and contract execution.
Eskom commits to a procurement process aligned to South African law and to fairness, transparency, equity, cost effectiveness and competitiveness.
The pact supplements Eskom's other commercial and ethics policies, codes and procedures.
Obligation on bidders
Read the pact and complete, sign and submit the Integrity Declaration Form for every Eskom procurement.
Refrain from dishonesty, fraud, corruption, bad-faith tendering, under-pricing, collusion and bid rigging.
Integrity Declaration Form: must be read, completed, signed and submitted with every Eskom bid; it incorporates the Declaration of Fair Tendering Practices.
Non-Disclosure Agreement: required where the bidder will have access to Eskom confidential information.
Disqualification and sanction risks
Submitting false certifications, misrepresented information or forged documents.
Entering any dishonest or illegal agreement with other bidders.
Failing to disclose an interest or relationship with an Eskom employee or director.
Must be completed, signed and submitted with every Eskom bid; it includes a Declaration of Fair Tendering Practices.
Requires disclosure of any financial, personal or private interest, or any affiliation, that the bidder's owners, members, directors, partners or shareholders have with an Eskom employee or director.
A relationship that emerges after submission must also be disclosed to Eskom.
Non-Disclosure Agreement
Required where the bidder will access Eskom confidential information; disclosure needs the express consent of an authorised Eskom representative.
Conduct rules
No misrepresentation, false certification or forged documents; Eskom may audit submitted information.
No dishonest or illegal agreements or understandings with other bidders.
Business courtesies and gifts to Eskom employees or directors must not exceed R1500,00 and must not place the recipient under any obligation.
No bribe, gift, commission, fee or inducement may be offered to, or requested by, anyone involved in evaluating, adjudicating or negotiating the bid.
Sanctions
Misconduct may trigger Eskom's supplier discipline process, suspension from the Eskom Vendor Database, and referral of the supplier and its directors to National Treasury's List of Restricted Suppliers.
Contractual Terms
Source: Eskom Supplier Integrity Pact - 02 June 2023 (1).pdf
Supplier discipline
Eskom may investigate alleged misconduct, give the supplier an opportunity to make representations, then suspend the supplier from the Eskom Vendor Database or impose other sanctions.
Names of sanctioned suppliers and their directors may be forwarded to National Treasury for listing on the List of Restricted Suppliers.
Eskom's obligations
Eskom must treat all bidders fairly, transparently, equitably, cost-effectively and competitively.
Eskom employees and directors complete annual Declarations of Interest, plus a further declaration and an NDA where they are involved in a procurement.
An employee or director with any interest in a bid is excluded from its evaluation or negotiation.
Employees and directors may not accept money, gifts, favours or loans from bidders; gifts received in the ordinary course must be declared, recorded and authorised.
General
The pact is governed by South African law and remains in force until replaced.
It does not limit any civil or criminal proceedings that may arise.
The tender is for the supply and delivery of cooling water system components (metallic piping) for the Camden west half station shutdown. The document provided is a Contract Quality Plan (CQP) template that the supplier must complete and submit as part of the tender.
Technical Specifications
Source: 240-109253698 CQP Template.docx (unknown)
The supplier must prepare a Contract Quality Plan (CQP) that identifies and plans for meeting Eskom's quality management expectations for the supply and delivery of cooling water system components (metallic piping) for the Camden west half station shutdown.
The CQP must be based on the guidelines in SANS 466:2005 / ISO 10005:2005.
The CQP must cover, at minimum: scope of work, communication channels with Eskom, an organogram with QA/QC roles, interfacing documents (standards, codes, specifications), a list of suppliers and sub-suppliers, monitoring of sub-suppliers, items to be manufactured/refurbished/purchased, activities requiring QCP/ITP, special controls (e.g., welding, NDT), documented information to be submitted to Eskom, records control and retention, concession and non-conformance management, databook management, management of tools and equipment, dealing with customer property, product preservation, identification and traceability, and commissioning/post-delivery activities.
The CQP must include a risk register and method statements.
The CQP must be compiled by a representative of the tenderer (Rev 0 during tender evaluation) and approved by the owner of the organisation.
Eskom will review and accept the CQP after contract award.
Document240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP)-rev 3.docxReview complete
Technical Specifications
Source: 240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP)-rev 3.docx (unknown)
Deliverable
A completed Quality Control Plan / Inspection and Test Plan (QCP/ITP) covering the supply and delivery of cooling water system components — metallic piping — for the Camden West half station shutdown.
Document header to complete
Contract or order number, subcontractor order number, QCP number, revision number and date.
Scope of work, and the item, plant or material description.
Approval block
The plan is signed off by the contractor or supplier, the subcontractor where one is used, Eskom, and the Approved Inspection Authority (AIA) where one applies.
Activity schedule — one line per activity
Activity number and description or requirement, and the activity date.
Intervention point allocated to the supplier and to Eskom.
Category: statutory or non-statutory.
Inspection and test method, the controlling document, the acceptance criteria, and the records to be kept.
Inspection is carried out by the supplier's own team or by third-party inspection (TPI), and by Eskom's own team or TPI; AIA/NOBO involvement where applicable.
Intervention point legend
Hold Point; AP — document requires approval; IN — document for information only.
The contract is for the supply and delivery of metallic piping components for the west half station shutdown at Camden Power Station. The supplier is responsible for supplying all items strictly per the technical descriptions and requirements in Part C3. The purchaser provides permit entrance and assists with unloading; supplier provides own transport and delivers to Camden stores.
Important Dates
Source: NEC SSC3 - Metallic Piping Components.pdf (unknown)
Closing date: 9 December 2026 at 08:00 (from tender record).
Delivery date: 4 weeks from order placement.
Defects date: 26 weeks from delivery.
Assessment day: 5 days after delivery.
No briefing or site visit is mentioned.
Contact Information
Source: NEC SSC3 - Metallic Piping Components.pdf (unknown)
Registered office: Megawatt Park, Maxwell Drive, Sandton, Johannesburg
Telephone: +27 17 827 8045
Email: not stated
Delivery address: Camden Power Station, Piet Retief Road, Nucam, 2355
Submission Guidelines
Source: NEC SSC3 - Metallic Piping Components.pdf (unknown)
Returnable documents:
Form of Offer and Acceptance (C1.1): signed offer to perform the contract; includes the offered total price (excl. and incl. VAT) and validity period.
Contract Data provided by the Supplier (C1.2): completed supplier details and pricing data.
Price Schedule (C2.2): completed rates and prices for each item.
Schedule of Deviations: any agreed deviations from the tender documents, signed by both parties.
Submission method: not stated in the document. Closing time: 08:00 on 9 December 2026 (from tender record).
Evaluation Criteria
Source: NEC SSC3 - Metallic Piping Components.pdf (unknown)
No evaluation criteria (scoring, preference points, minimum qualifying score) are stated in the document. The contract is a NEC3 Supply Short Contract; award appears to be based on the offered price and compliance with the contract terms.
Technical Specifications
Source: NEC SSC3 - Metallic Piping Components.pdf (unknown)
Scope: Supply and delivery of metallic piping components for the west half station shutdown at Camden Power Station. The supplier is responsible for supplying all items strictly per the descriptions and technical requirements in Part C3.
Certification: Every item must be supplied with an EN 10204 Type 3.1 inspection certificate in English, traceable to the heat number permanently marked on the component. Items without this certification, without heat number traceability, or with certification not in English will be rejected.
Delivery requirements:
Supplier provides own transport to Camden Power Station.
Delivery times: 09:00–14:00 Monday to Thursday; 09:00–10:00 Friday; no deliveries on non-working days.
Deliveries to Camden stores (receiving); delivery note must be signed by Eskom Stores receiving personnel.
Goods must be packaged to prevent damage and clearly marked with description, quantity, order number.
Delivery vehicle must be roadworthy; driver must comply with Eskom cardinal rules (sober, seatbelt, hook up at heights, permit to work with risk assessment for loading/unloading).
Purchaser provides: permit entrance to Camden power station and assistance with unloading.
Quality Management
Source: NEC SSC3 - Metallic Piping Components.pdf
Quality requirements:
All piping components must be supplied with EN 10204 Type 3.1 inspection certificates in English.
Certification must be traceable to heat numbers permanently marked on components.
Components without required certification, without heat number traceability, or with certification not in English will be rejected.
A Quality Control Plan (QCP) is referenced (document specifying inspection activities, test methods, procedures, acceptance criteria).
Pricing Schedule
Source: NEC SSC3 - Metallic Piping Components.pdf
Pricing data:
Price Schedule (C2.2) lists 17 items (flanges, pipes, elbows, tees, and delivery transportation) with unit, quantity, rate, and price columns.
For each item, enter a rate and multiply by quantity to get price; or enter a lump sum if quantity not applicable.
Rates and prices include all work necessary to supply the item.
The offered total of the Prices (excl. VAT) is entered in the Form of Offer and Acceptance; VAT at 15% added.
Overheads and profit percentage on Defined Cost (clause 63.2) is to be completed by supplier (blank in document).
Financial Requirements
Source: NEC SSC3 - Metallic Piping Components.pdf (unknown)
Pricing: Complete the Price Schedule (C2.2) with rates and prices for each item; the total of the Prices (excl. VAT) is entered in the Form of Offer and Acceptance. Prices include all work necessary to supply the item.
Payment: Supplier assesses amount due and applies for payment with a tax invoice (core clause 50). Invoice must include supplier name/address, contract number/title, supplier VAT number, purchaser VAT number (4740101508), itemised amounts, and totals excl./incl. VAT. Invoices are processed after the assessment certificate is signed and after 5 working days from last signature (for Eskom SAP entries and GR number generation).
Interest on late payment: Zero.
Delay damages: 2% per day, maximum 10% of the affected component's price.
Liability: Supplier's liability for indirect/consequential loss is limited to zero; supplier not liable for loss/damage to purchaser's property beyond stated limits (amount not specified). Purchaser's liability for supplier's indirect/consequential loss is limited to R0.00.
Insurance: Supplier must provide insurance per Insurance Table A (loss/damage to goods, property liability, bodily injury, employee liability) from starting date until delivery and between delivery and defects date. Purchaser provides insurance per Insurance Table B (all risk, contract works, environmental, general/public liability, marine, motor, terrorism, cyber, nuclear).
No bid security, bonds, guarantees, or retention are stated.
Compliance Requirements
Source: NEC SSC3 - Metallic Piping Components.pdf (unknown)
No pre-qualification thresholds (e.g., CIDB grading, B-BBEE level, CSD registration) are stated in the document.
Contractual compliance obligations:
B-BBEE status change: notify purchaser within 7 days of any change; submit updated verification certificate within 30 days. If status decreases, purchaser may renegotiate or terminate.
Tax invoice: must include purchaser's VAT number 4740101508 and comply with VAT Act.
Cession/delegation/assignment: not allowed without purchaser's written consent.
Ethics: no coercive, collusive, corrupt, fraudulent, or obstructive actions; termination possible for such actions.
Nuclear liability: purchaser indemnifies supplier against nuclear damage (Koeberg) except for unlawful intent or unauthorised presence.
Asbestos: purchaser manages asbestos; supplier must follow asbestos regulations and may stop work if unsafe.
Health & Safety
Source: NEC SSC3 - Metallic Piping Components.pdf
Health and safety requirements:
Delivery drivers must comply with Eskom cardinal rules: be sober, buckle up, hook up at heights, and conduct a risk assessment for every activity (including loading/unloading).
Asbestos: purchaser ensures ambient air conforms to SA asbestos regulations (OEL 0.2 fibres/ml as 4-hour TWA; short-term 0.6 fibres/ml as 10-minute TWA). Supplier may perform parallel measurements at own expense. If asbestos identified, risk assessment and control measures; supplier's personnel may stop work and leave contaminated area until declared safe. Removal/disposal by registered asbestos contractor at purchaser's expense.
Environmental
Source: NEC SSC3 - Metallic Piping Components.pdf
Environmental requirements:
Asbestos management: purchaser manages asbestos and ACM per Eskom Asbestos Standard 32-303; removal/disposal by registered asbestos contractor at purchaser's expense, in line with SA legislation.
Contractual Terms
Source: NEC SSC3 - Metallic Piping Components.pdf
Contract: NEC3 Supply Short Contract (April 2013) with additional Z-clauses.
Key terms:
Delivery date: 4 weeks from order placement.
Defects date: 26 weeks from delivery.
Assessment day: 5 days after delivery.
Delay damages: 2% per day, max 10% of affected component.
Interest on late payment: zero.
Law of contract: Republic of South Africa.
Period for reply: 5 working days.
Premises: Camden Power Station.
Adjudicator: selected from ICE-SA Panel of Adjudicators; arbitration under Association of Arbitrators (Southern Africa) rules.
Additional conditions (Z-clauses):
Z1: No cession/delegation/assignment without purchaser's written consent; purchaser may cede to subsidiaries/divisions.
Z2: Supplier must notify purchaser within 7 days of any B-BBEE status change; submit updated certificate within 30 days; status decrease may lead to renegotiation or termination.
Z3: Waivers/relaxations do not constitute waiver of rights unless confirmed in writing.
Z4: Tax invoice must include purchaser's VAT number 4740101508; late invoice extends payment time; interest calculated from delayed date.
Z5: Purchaser's liability for supplier's indirect/consequential loss limited to R0.00.
Z6: Termination also if judicial management order granted against supplier.
Z7: If delay damages reach limit, purchaser may terminate.
Z8: Prohibited actions (coercive, collusive, corrupt, fraudulent, obstructive) may lead to termination; supplier must cooperate with investigations.
Z9: Insurance requirements as per Insurance Tables A (supplier) and B (purchaser).
Z10: Nuclear liability – purchaser indemnifies supplier against nuclear damage (Koeberg) except for unlawful intent or unauthorised presence.
Z11: Asbestos – purchaser manages asbestos; supplier must follow asbestos regulations; if asbestos identified, risk assessment and control measures; supplier may stop work until safe; removal/disposal by registered asbestos contractor at purchaser's expense.
Document240-68099512 Form A_Cat 3_ Rev 9.docxReview complete
Description
Source: 240-68099512 Form A_Cat 3_ Rev 9.docx
The tenderer must complete and sign the acknowledgement form to accept Eskom Supplier Quality Requirements as per specification 240-105658000 and ISO 9001 standard.
Submission Guidelines
Source: 240-68099512 Form A_Cat 3_ Rev 9.docx (unknown)
Returnable documents:
Form A (Cat 3, Rev 9): completed and signed acknowledgement of Eskom Supplier Quality Requirements per specification 240-105658000 and ISO 9001.
The form must indicate acceptance of Category 3 quality requirements and all applicable clauses.
Submission method and address: not stated in the document.
Evaluation Criteria
Source: 240-68099512 Form A_Cat 3_ Rev 9.docx (unknown)
The tenderer must complete and sign the acknowledgement form for Eskom Supplier Quality Requirements.
The tenderer must indicate acceptance of the applicable quality category (Category 3) and all applicable clauses.
The tenderer must comply with ISO 9001 standard clauses and quality principles.
Technical Specifications
Source: 240-68099512 Form A_Cat 3_ Rev 9.docx (unknown)
Supply and delivery of cooling water system components – metallic piping for Camden west half station shutdown.
The tenderer must acknowledge and accept Eskom Supplier Quality Requirements as per specification 240-105658000 and ISO 9001 standard.
Quality category applicable: Category 3 (refer to clause 3.5.4 of 240-105658000).
Post-contract award quality requirements apply: contract execution (clause 3.7.1) and supplier quality performance monitoring (clause 3.7.2).
Standard conditions apply: Eskom rights of access (3.8.1), rights to information (3.8.2), preservation (3.8.3), quality audits (3.8.4), management of nonconformities (3.8.5), and special processes (3.8.6).
ISO 9001 clauses 4 to 10 and quality principles 1 to 7 apply.
Compliance Requirements
Source: 240-68099512 Form A_Cat 3_ Rev 9.docx (unknown)
The tenderer must comply with ISO 9001 standard clauses and quality principles.
The tenderer must complete and sign the acknowledgement form for Eskom Supplier Quality Requirements.
The tender is for the supply and delivery of metallic piping components for the Camden West Half-Station Shutdown. The components are intended for incorporation into a piping system for conveyance, isolation, connection, support, or control of a fluid, including pipes, fittings, flanges, reducers, elbows, tees, branches, couplings, unions, caps, plugs, and other pressure-containing items. The scope is defined in the Scope of Work (CAM-WHSSD-2027-MPC, Rev. 3), Appendix A.
Declaration of Compliance with Eskom Stock Descriptions (M-1): on company letterhead, signed by the managing director, confirming all offered products comply with the Eskom stock descriptions in Appendix A of the Scope of Work (CAM-WHSSD-2027-MPC, Rev. 3), with no deviations or substitutions unless approved in writing by Eskom.
Declaration of Material Certification and Traceability (M-2): on company letterhead, signed by the managing director, confirming each component delivered to Camden Power Station will be accompanied by an EN 10204 Type 3.1 inspection certificate in English, and that each component will be permanently hard stamped with the heat number traceable to that certificate.
For digital submissions, each file must be clearly labelled with the relevant criteria designation (M-1, M-2, Q-1, Q-2, Q-3).
Disqualification risks:
Failing any mandatory criterion (M-1 or M-2) results in technical non-compliance and exclusion from further evaluation.
Scoring below 70% in the qualitative evaluation results in technical non-compliance.
Delivery schedule showing delivery in April 2027 or later is unacceptable.
Q-1 (50%): Technical compliance of offered piping components – submit a schedule covering all components in Appendix A, including manufacturer, component type, nominal size/DN, material standard and grade, schedule/wall thickness, pressure class/rating (flanges only), flange type and facing (flanges only), and applicable dimensional/manufacturing standard.
Q-2 (15%): Relevant supply experience – verifiable evidence of successful supply of carbon steel piping, flanges and/or fittings for power generation, petrochemical, mining, process plant or comparable industrial applications within the previous 5 years. Scoring: 0 (none), 2 (1 comparable contract/order), 4 (2 comparable), 5 (3 or more).
Q-3 (35%): Delivery schedule and lead-time commitment – submit a delivery schedule for each component showing manufacturing/procurement lead time and final delivery lead time to Camden Power Station, calculated from order placement. Delivery must be before April 2027 (the planned HSSD commencement). Delivery in April 2027 or later is non-compliant.
Scope: Supply and delivery of metallic piping components for the Camden West Half-Station Shutdown.
Components include pipes, fittings, flanges, reducers, elbows, tees, branches, couplings, unions, caps, plugs, and other pressure-containing or pressure-retaining piping items as specified in the Scope of Work (CAM-WHSSD-2027-MPC, Rev. 3), Appendix A.
Delivery location: Camden Power Station.
Each component must be accompanied by an EN 10204 Type 3.1 inspection certificate in English.
Each component must be permanently hard stamped with the applicable heat number, traceable to the inspection certificate.
The technical evaluation is conducted in two phases: Phase 1 (mandatory pass/fail) and Phase 2 (qualitative weighted scoring). Bidders must satisfy all mandatory criteria before proceeding to qualitative evaluation. Qualitative scoring uses a weighted scorecard with a minimum threshold of 70%.
Experience & Qualifications
Source: Metallic Piping Components_ TES.PDF
Bidders must provide verifiable evidence of relevant supply experience within the previous five years, demonstrating successful supply of carbon steel piping, flanges and/or fittings for power generation, petrochemical, mining, process plant, or comparable industrial piping applications. Acceptable evidence includes purchase orders, contracts, or customer reference letters. Scoring: 0 (none), 2 (1 comparable contract/order), 4 (2 comparable), 5 (3 or more).
Quality Management
Source: Metallic Piping Components_ TES.PDF
Each metallic piping component delivered to Camden Power Station must be accompanied by an EN 10204 Type 3.1 inspection certificate issued in English. Each component must be permanently hard stamped with the applicable heat number, and the heat number must correspond to and be fully traceable to the relevant inspection certificate.
Compliance with the Occupational Health and Safety Act (OHS-Act) is referenced.
Compliance with Eskom Procurement Policy (32-1034) is required.
Compliance with Eskom QM 58 Supplier Contract Quality Requirements Specification is required.
Compliance with Specification for Low Pressure Pipelines (240-123801640) is required.
Health & Safety
Source: Metallic Piping Components_ TES.PDF
Compliance with the Occupational Health and Safety Act (OHS-Act) is required. The tender references Eskom QM 58 Supplier Contract Quality Requirements Specification and the Specification for Low Pressure Pipelines.
Section
Source: Metallic Piping Components_ TES.PDF
Evaluation is in two phases: Phase 1 mandatory pass/fail (M-1 and M-2), Phase 2 qualitative weighted scoring (Q-1, Q-2, Q-3). Minimum qualifying score for Phase 2 is 70%. Weights: Q-1 50%, Q-2 15%, Q-3 35%.
DocumentAnnexure L-Authority to Submit a Tender.pdfReview complete
Submission Guidelines
Source: Annexure L-Authority to Submit a Tender.pdf (unknown)
Returnable documents: Annexure L – Authority to Submit a Tender (returnable schedule). The bidder must complete the certificate for its organisation type (company, close corporation, partnership, joint venture, or sole proprietor) or attach a certified copy of a company or organisation document providing the same information. The certificate must authorise the named signatory to sign all tender and contract documents on behalf of the bidder.
Evaluation Criteria
Source: Annexure L-Authority to Submit a Tender.pdf (unknown)
Bidders must be legally constituted entities (company, close corporation, partnership, joint venture, or sole proprietor) and must provide the relevant authorisation certificate as part of the tender submission.
Compliance Requirements
Source: Annexure L-Authority to Submit a Tender.pdf (unknown)
Joint venture bidders must attach a power of attorney signed by legally authorised signatories of all partners, and a copy of the joint venture agreement stating that all partners are jointly and severally liable for contract execution and that the lead partner is authorised to incur liabilities, receive instructions and payments, and be responsible for the entire execution of the contract.
The tender is for the supply and delivery of metallic piping components for the cooling water system at Camden Power Station, as part of the west half station shutdown. The work is classified as low risk for OHS purposes.
Valid Letter of Good Standing (COIDA or equivalent).
OHS policy signed by CEO, compliant with OHS Act Section 7.
If certified for an auditable OHS system, ISO 45001 certificate (or equivalent).
Health & Safety
Source: Tender evaluation Template Low Risk.pdf
Bidders must submit an OHS plan that addresses the specific OHS risks of the project and aligns with the health and safety specification. A Baseline OHS Risk Assessment (BRA) must be provided, including the methodology used for the risk assessment. A valid Letter of Good Standing (COIDA or equivalent) is required. The OHS policy must be signed by the CEO and comply with OHS Act Section 7. Alternatively, bidders certified for an auditable OHS system may submit an ISO 45001 certificate (or equivalent) instead of the OHS plan and BRA.
Sets the minimum quality requirements for existing and potential Eskom suppliers and the quality criteria for their selection, evaluation, vendor registration, management, monitoring, assessment and auditing.
Applies across Eskom divisions, subsidiaries, suppliers and sub-suppliers, and forms part of all Eskom RFI, RFQ and RFP documents and the resulting contracts for products and services.
Requires suppliers to develop, implement, maintain and continually improve a QMS based on ISO 9001.
Normative references: ISO 9001 and ISO 10005. Informative references include ISO 9000, ISO 10006, ISO 9004, Eskom SHEQ Policy 32-727, Eskom Procurement and Supply Chain Management Policy 32-1033 and Procedure 32-1034, the PPPFA, CIDB 1004, the List of Tender Returnables 240-12248652, IAEA Safety Standard GS-R-3.1 and SANS 10845-1.
The specification is a controlled document; downloaded copies are uncontrolled and the authorised version on Eskom's document management system governs.
Contract quality plan: must be submitted before the initial scope-of-work kick-off or pre-fabrication meeting and before manufacturing starts, whichever is earlier.
Coordination meetings: the supplier must give Eskom 14 days' advance notice before placing orders for items or equipment.
Returnable quality documentation — selected per the applicable quality category:
Form A (240-68099512, Tender and Contract Quality Requirements for Supplier Quality Management Specification 240-105658000/QM 58 and ISO 9001): must be completed, signed and returned with the tender to acknowledge and accept Eskom's supplier quality requirements.
Quality documentation for the category indicated in Form A, as listed in the List of Tender Returnables (240-12248652).
Only one quality category (1, 2, 3 or 4) applies to a procurement.
Category 1 returnables
Valid ISO 9001 (or equivalent QMS) certificate from an accredited certification body.
Latest internal and external management system audit reports, including nonconformities identified and the resulting remedial actions.
Draft contract quality plan specific to the scope of work, meeting ISO 10005.
Draft or example inspection and test plan (ITP) / quality control plan (QCP) from similar or previous work.
Documented information for control of externally provided processes, products and services.
Documented roles, responsibilities and authorities for the QMS.
Records of management review meetings (agenda, minutes, attendance registers, reports).
Category 2 returnables
Objective evidence of a developed, implemented and maintained ISO 9001 QMS: QMS manual or equivalent, quality policy, quality objectives, control of documented information, internal audit procedure, control of nonconforming outputs, and nonconformity and corrective action procedure.
Latest internal audit reports with nonconformities and remedial actions.
Draft contract quality plan per ISO 10005.
Example ITP or QCP from similar or previous work.
Documented information for control of externally provided processes, products and services.
Documented roles, responsibilities and authorities for the QMS.
Management review records.
Category 3 returnables
Objective evidence of a developed ISO 9001 QMS: QMS manual or equivalent, quality policy, quality objectives, control of documented information, internal audit procedure, control of nonconforming outputs, and nonconformity and corrective action procedure.
Draft contract quality plan per ISO 10005.
Example ITP or QCP.
Documented information for control of externally provided processes, products and services.
Documented roles, responsibilities and authorities for the QMS.
Category 4 returnables
Quality method statement based on ISO 9001 and specific to the scope of work.
Signed or approved quality policy.
Quality objectives.
Documented information for control of externally provided processes, products and services.
Documented roles, responsibilities and authorities specific to the project or scope of work.
An Eskom Quality representative selects the applicable quality requirements and completes Form A; the bidder must complete and sign Form A to acknowledge and accept them.
Quality requirements are classified into four categories; only one category applies per procurement and the applicable category is indicated in Form A.
The quality documentation required is determined by the applicable category and listed in the List of Tender Returnables (240-12248652).
Capability and capacity assessment
Eskom performs supplier and sub-supplier capability and capacity assessments before contract award where the scope provides products or services with high risk to operational sustainability, involves work on critical plant and equipment, supplies critical plant items or components, or involves special processes.
Eskom may request and perform assessments at sub-supplier facilities.
The main supplier remains accountable for the development and proper implementation of all sub-supplier quality programmes and QCPs/ITPs.
Supply and delivery of cooling water system components — metallic piping — for the Camden West Half Station shutdown.
The specification sets the minimum quality requirements for suppliers and sub-suppliers and forms part of Eskom RFI, RFQ and RFP documents and the resulting contracts.
Quality management system
Suppliers and sub-suppliers must develop, implement, maintain and continually improve a formal QMS conforming to the latest ISO 9001 or an applicable equivalent standard.
The QMS must include the documented information required by ISO 9001, such as a quality manual, quality plans, work procedures, work instructions, method statements and workflow documentation.
A valid ISO 9001 certificate from an accredited certification body is required unless specifically excluded for the applicable quality category.
The main supplier must inform Eskom of any proposed QMS or staff changes affecting quality before implementing them.
Contract quality plan (CQP)
Required where specified in the evaluation criteria or the list of tender returnables; must follow ISO 10005 and cover records management, material tests, positive material identification (PMI), material certification, access for inspection, final documentation and the final manufacturing data book before shipment.
Must cover special processes: welder qualification records (WQR), welding procedure specifications (WPS) and procedure qualification records (PQR), reviewed and accepted before manufacture starts.
Must cover special installation and fabrication procedures (post-weld heat treatment, tube rolling, coatings) reviewed and accepted before manufacture.
Must state equipment and material storage, preservation and maintenance instructions.
Must be submitted before the initial scope-of-work kick-off or pre-fabrication meeting and before manufacturing starts, whichever is earlier.
Eskom's CQP template (240-109253698) may be used where the supplier has no template.
Quality control plan / inspection and test plan (QCP/ITP)
Must cover all stages of manufacturing, fabrication, assembly and installation in chronological order, from contract review through material verification, manufacturing, final testing, commissioning, hand-over documentation and certification.
Must be reviewed and accepted by Eskom or its inspection agency before work starts, and must allow Eskom to insert hold and witness points.
Changes to an accepted QCP/ITP require Eskom's agreement before the affected activity starts.
Must record the Eskom contract number and title, supplier order number, area of works, work description, QCP/ITP number, sequence of operations, reference specifications and drawings, acceptance criteria with clause references, intervention points, and inspection and test records.
A separate QCP/ITP is required for each sub-supplier scope of work.
Once signed, ITPs and QCPs become addenda to the main contract.
Eskom's QCP/ITP template (240-109253302) may be used where the supplier has no template.
Plant item criticality
Level 1: failure affects personnel safety or health, causes an environmental incident, major production loss or major equipment damage, or covers safety, redundancy or protective devices or statutory equipment.
Level 2: failure impacts plant availability or reliability, or causes significant costs or secondary damage.
Level 3: failure does not affect safety, health, environment, cost, availability or reliability.
Special processes
Personnel performing special processes (NDE, welding, coating, heat treatment) whose results cannot be fully verified by later inspection must be suitably qualified and, where legally required, registered with statutory bodies.
Personnel must hold a certificate of competency through internal training and competency control or an accredited external provider (for example NDT) meeting SETA requirements.
Training needs of all personnel affecting quality must be identified, documented and implemented; training certificates must meet SETA requirements with unit standards and provider accreditation numbers.
Preservation
The supplier must run a preservation management programme covering valves, electrical motors and components, mechanical and rotating equipment, piping and fittings, instrumentation, flange faces, gaskets, coatings and insulation.
Special precautions include supplier-specified maintenance such as periodic shaft rotation, engine turnover and lubrication.
Preservation requirements must be documented in purchase orders, work authorisations and sub-supplier communications, and communicated to project logistics, construction management, quality and security.
Eskom must have free and unrestricted access to all preservation records.
The supplier must plan the quality-related activities and interfaces needed to control and meet Eskom's requirements.
The CQP must describe the equipment and locations where each activity takes place, identify the quality verification activity and stage, reference the procedures, standards and method statements used (with sections and pages), define acceptance criteria, list certifying and verifying documents using Eskom document numbering, identify the main supplier, sub-supplier and approved inspection authority, and provide for sign-off at each intervention point.
The QCP/ITP must list the sequence of operations including inspection and tests, reference the specification, drawing or procedure for each operation with the criticality risk rating, state acceptance criteria with clause references, and provide for intervention point acceptance by date and signature.
The QCP/ITP must cover materials certification, fabrication, in-process inspections, final acceptance tests, packaging, pre-shipment and transportation inspections, preservation, site acceptance tests, construction and erection, and pre-commissioning and commissioning tests.
Sub-suppliers must receive comprehensive, unambiguous inspection and testing protocols, including inspection checklists, report formats and content, report processing and retention, results tracking and nonconformity resolution, and, where applicable, FMECA and HAZOP reports.
The supplier must establish processes for formal assessment of sub-supplier inspection and testing programmes, with assessment scope and schedule developed in consultation with Eskom.
Outstanding procedural issues must be resolved before works are delivered.
The supplier must ensure sub-supplier QCPs/ITPs are prepared and that any changes are resubmitted to Eskom for review.
Where the supplier has no CQP or QCP/ITP template, the Eskom templates may be used as a guideline.
Personnel performing special processes (for example NDE, welding, coating, heat treatment) whose results cannot be fully verified by later inspection and test must be suitably qualified and, where legally required, registered with statutory bodies — for example radiographic workers conducting radiography.
Personnel performing special processes must hold a certificate of competency through the company's internal training and competency control procedures or an accredited external certification body (for example NDT) meeting SETA requirements.
Training needs of all personnel whose activities affect quality must be identified and documented, and the required training implemented; training certificates must meet SETA requirements with the unit standard completed and the service provider's accreditation number.
Welder records must be maintained by the sub-suppliers performing the work, and welders qualified to the specified codes of construction for the applicable procedures.
Supplier inspection personnel, including inspection agency personnel, must be competent and qualified for their inspection and testing assignments, mobilised in line with the Project Quality Personnel Qualification Specification.
Quality audits and related quality performance reviews must be carried out by trained, accredited and experienced personnel.
Suppliers and sub-suppliers must develop, implement, maintain and continually improve a formal QMS conforming to the latest ISO 9001 or an applicable equivalent standard.
The QMS must include the documented information required by ISO 9001, such as a quality manual, quality plans, work procedures, work instructions, method statements and workflow documentation.
A valid ISO 9001 certificate from an accredited certification body is required unless specifically excluded for the applicable quality category.
The QMS requirement applies equally to sub-suppliers whose scope covers design and development, manufacturing, maintenance, testing, storage, delivery, installation, commissioning or project management.
The main supplier must inform Eskom of proposed QMS or staff changes affecting quality before they are implemented.
Quality plans
Where required by the evaluation criteria or the list of tender returnables, every product, service and process must have a documented, implemented, reviewed and maintained contract quality plan and/or quality control plan (inspection and test plan).
Production and service provision must follow the agreed CQP and/or QCP/ITP.
The CQP addresses quality assurance elements; the QCP/ITP addresses quality control elements.
Sub-supplier CQPs must follow ISO 10005 and be submitted for supplier and Eskom review.
Quality control
The supplier must develop and implement processes to monitor, verify and document the quality of deliverables.
QCPs/ITPs must be prepared in chronological order from contract review through material verification, manufacturing, fabrication, assembly, final testing, commissioning, hand-over documentation and certification.
All applicable codes, standards and acceptance criteria must be available at the work location, in English and any workforce-appropriate language, with ongoing access for Eskom representatives.
The supplier must formally assess sub-supplier inspection and testing programmes, reviewing inspection reports and quality control documentation; assessment frequency depends on scope, criticality and performance.
Verification of purchased product compliance must obtain document return/review status before implementation.
Meetings
A quality kick-off meeting is held at the start of the contract and, if required, at the start of each subsequent phase.
The supplier must arrange coordination meetings with Eskom before placing orders for items or equipment, giving 14 days' advance notice.
Mandatory pre-inspection meetings are convened by Eskom or its inspection agency, attended by supplier and sub-supplier representatives including quality representatives, with records kept.
Eskom develops the meeting agenda in consultation with the supplier and keeps minutes.
Categories
Quality requirements are classified into four categories; only one applies per procurement and the applicable category is indicated in Form A.
Category 1 requires a valid ISO 9001 certificate, latest internal and external audit reports, a draft CQP, a draft or example ITP/QCP, documented control of externally provided processes, documented roles and responsibilities, and management review records.
Category 2 requires objective evidence of a developed, implemented and maintained ISO 9001 QMS, latest internal audit reports, a draft CQP, an example ITP/QCP, documented control of externally provided processes, documented roles and responsibilities, and management review records.
Category 3 requires objective evidence of a developed ISO 9001 QMS, a draft CQP, an example ITP/QCP, documented control of externally provided processes, and documented roles and responsibilities.
Category 4 requires a quality method statement based on ISO 9001, a signed quality policy, quality objectives, documented control of externally provided processes, and documented roles and responsibilities specific to the scope.
Templates
CQP template 240-109253698, QCP/ITP template 240-109253302 and method statement template 240-126469599 are available where the supplier has no equivalent.
Suppliers and sub-suppliers must hold a QMS conforming to the latest ISO 9001 or an applicable equivalent standard.
A valid ISO 9001 certificate from an accredited certification body is required unless specifically excluded for the applicable quality category.
Form A (240-68099512) must be completed, signed and returned with the tender.
Quality documentation must be submitted per the applicable category (1 to 4), as listed in the List of Tender Returnables (240-12248652).
Sub-suppliers
The main supplier is responsible for defining and managing the quality assurance and control elements of each sub-supplier's scope and for ensuring sub-supplier quality programmes meet Eskom requirements.
The main supplier must run a performance management programme for sub-suppliers covering QMS verification, audits and surveillances, assessment of CQPs and QCP reviews, nonconformity and defect management, inspection and test plans, and risk management.
Eskom may request and perform assessments at sub-supplier facilities.
Where the supplier's name changes, or through mergers, acquisitions or cessions, Eskom Quality must confirm the changed entity can still meet the contract requirements.
Capability and capacity
Eskom assesses supplier and sub-supplier capability and capacity before contract award for high-risk scopes, work on critical plant and equipment, supply of critical plant items or components, and special processes.
The Eskom SHEQ Policy (32-727) is an informative reference for this specification.
IAEA Safety Standard GS-R-3.1 (Application of the Management System for Facilities and Activities) is referenced.
Plant item criticality is classified by the consequence of failure: Level 1 items affect personnel safety or health, cause environmental incidents, major production loss or major equipment damage, or are safety, redundancy or protective devices or statutory equipment; Level 2 items impact plant availability or reliability or cause significant costs or secondary damage; Level 3 items do not affect safety, health, environment, cost, availability or reliability.
Personnel performing special processes such as radiography must be registered with statutory bodies where legally required.
The supplier must operate a documented preservation management programme for all physical assets not yet in operational use, including bulk materials, consumables, equipment systems and components.
The programme must cover review and tracking of compliance with Eskom and supplier engineering preservation requirements, and with sub-supplier preservation recommendations.
Prospective temporary and longer-term material storage sites must be evaluated against preservation expectations.
Preservation work plans must be developed and the execution performance of all parties providing transport, handling or storage services evaluated.
Material quality preservation plan preparation and execution must be overseen at all work locations.
A preservation records management process must be established in line with Eskom information management requirements, giving Eskom ready access to all records.
Preservation responsibilities must be clearly allocated within the project team and to sub-suppliers, and implemented at all scope-of-work locations.
Eskom must have free and unrestricted access to all preservation records for inspection and audit.
Preservation requirements must be documented in purchase orders, work authorisations and sub-supplier communications, and communicated to project logistics, construction management, quality and security.
Special precautions must address valves, electrical motors and components, mechanical and rotating equipment, piping and fittings, instrumentation, flange faces, gaskets, coatings and insulation, including supplier-specified maintenance such as periodic shaft rotation, engine turnover and lubrication.
Rights of access and information
Eskom holds rights of access and rights to information under the specification.
Eskom may appoint resident quality inspectors at supplier or sub-supplier premises and on site; the supplier must provide workspace at no cost.
Eskom may appoint any organisation as an approved inspection authority or inspection agency, and the supplier and its sub-suppliers may not obstruct, hinder or undermine that organisation's work.
Eskom may select intervention points on QCPs/ITPs and perform surveillance or audits.
Quality audits and nonconformities
Quality audits and related quality performance reviews must be carried out by trained, accredited and experienced personnel.
Nonconformities and nonconforming outputs identified by Eskom are managed under the specification.
Once signed, ITPs and QCPs become addenda to the main contract and may be reviewed at Eskom's discretion based on performance or other risks.
The standard sets out Eskom's five Life-Saving Rules and its zero-tolerance stance on the behaviours most likely to cause serious injury or death at work.
Purpose: to identify the five most prominent causes of serious injuries and fatalities within Eskom and to enforce zero tolerance for non-adherence, given the potential for serious injury or fatality.
Applicability: applies throughout Eskom Holdings SOC Limited, its divisions, subsidiaries and entities in which Eskom has a controlling interest, and to Eskom contractors, unless Sustainability Systems specifically exempts a business of a completely different nature.
Binds Eskom employees, agents, consultants, contractors (including vendors, suppliers, subcontractors, joint ventures and fixed-term contractors) and visitors.
Visitors who refuse to observe the rules may be instructed to leave Eskom premises immediately.
The rules complement existing safety practice and apply at all locations; they do not replace other safety requirements for work activities.
Reference: document 240-62196227, revision 6. Effective from the date of authorisation.
Compliance may be audited six months after implementation.
Definitions: a contractor is any juristic or natural person contracted directly or indirectly by Eskom to perform work or supply a service, product, equipment or material; work at height is work above a stable surface, or where a person is exposed to a fall, including access and egress that carries a fall risk; zero tolerance means severe consequences for a proscribed act, with no exception for extenuating circumstances.
Technical Specifications
Source: 20. Eskom life-saving rules.pdf (unknown)
Scope and applicability of the Life-Saving Rules standard
Applies at every Eskom site, and across Eskom Holdings SOC Limited, its divisions, subsidiaries and entities in which Eskom holds a controlling interest, as well as to Eskom contractors, unless Sustainability Systems grants a specific exemption for a business of a wholly different nature.
Binds Eskom employees, agents, consultants, contractors (including vendors, suppliers, subcontractors, joint ventures, principal contractors and fixed-term contractors) and visitors.
Visitors who refuse to observe the rules may be instructed to leave Eskom premises immediately.
The rules supplement existing safety practice and apply at all locations; they do not replace other safety requirements for work activities.
Reference: document 240-62196227, revision 6. Effective from the date of authorisation.
Compliance may be audited six months after implementation.
Monitoring: line management monitors compliance and reports analysis and trends through performance reporting.
Compliance Requirements
Source: 20. Eskom life-saving rules.pdf (unknown)
Contractor obligations
Every employee must sign confirmation that the Life-Saving Rules and the consequences of breaking them have been discussed with them and understood; the contractor must keep those records.
Employees may refuse to work in an unsafe situation, or where doing the work would require ignoring a Life-Saving Rule.
Only work the person is authorised to perform may be carried out.
The Life-saving Rule Acknowledgement Form (240-63942960) records the employee acknowledgement.
Applicable standards and legislation
ISO 9001 Quality Management Systems.
Occupational Health and Safety Act; National Road Traffic Act.
Eskom 32-136 Contractor Health and Safety Requirements; 32-37 Substance Abuse Procedure; 32-418 Working at Heights Standard; 36-681 Plant Safety Regulations; 32-848 Operating Regulations for High Voltage Systems; 32-1112 Disciplinary Code and 32-1113 Disciplinary Procedure; 240-44175132 PPE Specification; 240-100979499 PPE for Working at Heights Specification; 240-84733329 Medical Surveillance Procedure; 34-104 Earthing Standard.
Health & Safety
Source: 20. Eskom life-saving rules.pdf
Life-Saving Rules — zero tolerance
Rule 1 — Open, isolate, test, earth, bond and/or insulate before touch
No work on, around or near any electrical network, line or apparatus (whether charged or not) unless the person is trained and authorised as competent, holds a valid permit to work where one is required, has completed a pre-task risk assessment, applies the isolation sequence correctly for the task, has been shown by the authorised team leader that the apparatus is safe, and wears the appropriate PPE, including a face shield and insulated gloves for low-voltage work.
Rule 2 — Hook up at heights
Work at ground level is preferred wherever reasonably practicable.
No work at height where there is a fall risk unless the person is medically fit, a pre-task risk assessment has been completed, the person is trained as determined by that assessment, is secured while ascending and descending, and uses an Eskom-approved fall arrest system where applicable.
Rule 3 — Buckle up
Seat belts are mandatory for drivers, operators and passengers in all vehicles and equipment used for Eskom business; the driver must ensure all occupants are properly seated and belted.
Applies on any road or parking area, at any speed, in forward or reverse.
Rule 4 — Be sober
No person under the influence, or appearing to be under the influence, of alcohol or drugs may enter or remain on an Eskom site, conduct Eskom business, or drive or operate Eskom vehicles or equipment.
Any level of alcohol, or the presence of drugs, controlled substances or illegal substances that impairs or could impair mental or physical functioning, is prohibited regardless of when the substance was taken.
Rule 5 — Ensure you have a permit to work
Where an authorisation limitation exists, no work may proceed without the required Permit to Work, governed by the Plant Safety Regulations, the Operating Regulations for High Voltage Systems (ORHVS) or any other applicable permit regime.
Plant may not be returned to service until all permits on it are cancelled, unless permission is granted for a specific plant such as redundant systems.
Live work requires a live work declaration form completed by the authorised person responsible for safe execution of the work.
Consequences of a violation
A violation is treated as serious misconduct and triggers the Eskom Disciplinary Code and Procedure.
Where a contractor manager or supervisor allows a violation, Eskom may suspend the contractor's activities while deciding on an appropriate sanction.
Where a contractor employee is alleged to have violated a rule, the contractor must remove that employee from site immediately, investigate and start disciplinary action within five working days, and provide Eskom with a copy of the sanction afterwards.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Prevention and Combating of Corrupt Activities Act (PRECCA)
Act 12 of 2004
high
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Public Procurement Act, 2024 (PPA)
Act 28 of 2024
high
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Promotion of Access to Information Act (PAIA)
Act 2 of 2000
medium
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Promotion of Administrative Justice Act (PAJA)
Act 3 of 2000
medium
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
N2 Piet Retief Road - Nucam - Ermelo - 2355
Document-Backed
Recently Synced
Source Snapshot Available
AI Enhanced
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
23
Last checked
20 Nov 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Get deep intelligence on Manufacture of fabricated metal products, except machinery and equipment. Unlock full pricing strategies, bid frequency, and historical win rates.