TRANSNET rail infrastructure manager invites qualified contractors to submit quotations for the refurbishment of tanks at the homestead site in deal party, eastern cape. The scope includes sandblasting and repainting of tanks within the petroleum industry, with a compulsory site briefing and strict compliance requirements. Bidders must meet CIDB grading, functionality thresholds, and submit all required documentation electronically by the closing date.
Key Requirements
Attend the compulsory clarification meeting on 05 August 2026 at 11:00 at TFR Container Terminal, Deal Party; failure to attend leads to disqualification.
Submit electronically via the Transnet e-Tender Portal before 12:00 on 14 August 2026; late submissions are not accepted.
Hold a valid CIDB registration with grading designation 1CE or higher (or be capable of obtaining it before evaluation).
Achieve a minimum functionality score of 70 points, based on experience, method statement, delivery lead time, and key personnel.
Provide all required returnable documents, including tax clearance, B-BBEE certificate, CSD registration, and Workmen's Compensation Fund good standing.
Submit a detailed method statement covering all 7 specified items, including safety, risk assessment, and weather contingencies.
Provide CVs and qualifications for all 5 key personnel: Project Manager, Master/Electrician, SHE rep, Testing officer/Engineer/Technician, and Technical Supervisor.
Review in progress · 1 of 2 document being finalised
AI Document Analysis Stages
Document read. The full tender notice and its supporting documents are read end-to-end. Key sections, requirements, dates, and contact details are identified and pulled into a working summary you can act on.
Compliance review. The working summary is checked against South African procurement standards — PFMA, PPPFA, B-BBEE, CIDB, local content, and preferential procurement — so nothing critical is missed before you start your bid response.
Review in progress
The information shown on this card is preliminary. Our procurement team is currently finalising the submission guidelines, evaluation criteria, technical specifications, financial requirements, and compliance sections so you have a clean, bid-ready summary to work from. Document being finalised: RFQ - TANK REFURBISHMENT.pdf. You don’t need to refresh — this page will pick up the updated review automatically.
RFQRFQ - TANK REFURBISHMENT.pdfCompliance review in progress
Important Dates
03 Aug
2026
PUBLICATION
Tender Published
Tender was published
14 Aug
2026
DEADLINE
Closing Date
Tender closing date
Procurement Rules & Compliance ContextThis tender may be governed by South African public procurement rules covering fairness, transparency, preferential procurement, anti-corruption, administrative justice and access to information.
7 rules
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
Core procurement rules
These rules commonly apply to South African public-sector procurement.
7
Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
high
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Constitution of the Republic of South Africa, 1996 – Section 217
Act 108 of 1996 (s217)
high
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
This tender from Transnet SOC Ltd (Transnet Rail Infrastructure Manager) is for the refurbishment of a steel tank at the Deal Party Homestead Site in Gqeberha, Eastern Cape. The work includes repairs to the tank roof, shell, floor, foundation, nozzles, handrails, platforms, and stairways, as well as painting and installation of safety and venting systems. The contract is governed by the NEC3 TSC (Term Service Contract) and requires compliance with Transnet's Health and Safety and Environmental specifications. The closing date is 14 August 2026.
Transnet SOC Ltd is seeking quotations for the refurbishment of a tank at the Homestead Site in Deal Party, Eastern Cape. The tender is issued under the NEC3 Engineering and Construction Contract and requires a compulsory site briefing on 05 August 2026. Bids must be submitted electronically via the Transnet e-Tender Submission Portal by 12:00 PM on 14 August 2026. The evaluation will consider functionality (minimum 70 points), price, and preference points (80/20 system).
Secure Transnet tenders using AI Matching & Recommendations, logistics infrastructure intelligence, compliance analysis, and application support for rail, ports, and pipelines.
Similar Tenders
Matched by category & region
Supplier Readiness Hub
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Bid-ready summary. The submission guidelines, evaluation criteria, technical, financial, and compliance sections are refined into professional, easy-to-scan prose. This is the final version you can rely on when preparing your bid or briefing your team.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Document read
Compliance review
Bid-ready summary
Important Dates
Source: RFQ - TANK REFURBISHMENT.pdf (RFQ)
Compulsory Tender Clarification Meeting: 05 August 2026 at 11:00am, at TFR Container Terminal, Transnet Park, Ries Street, Deal Party. Duration approx. 2 hours. Site walk follows. Attendance is mandatory; latecomers will not be briefed.
Closing Date: 14 August 2026 at 12:00pm (noon).
Tender validity period: 12 weeks from closing date.
Register your company profile on the portal and log an intent to bid before uploading documents.
Upload your bid before 12:00pm on 14 August 2026. Late submissions will not be accepted.
Submit at least one day before closing to avoid internet/bandwidth issues. Max 30MB per upload; multiple uploads allowed.
Each company must submit under its own registered profile. No submissions on behalf of another company (except JV members using their own profile).
Mark documents with: Name of Tenderer, Contact person and details, Tender Number, and Tender Description. Mark for attention of Nosipho Matika ([email protected]).
Tender offers must be in English. No telephonic, telegraphic, facsimile, or e-mailed offers accepted.
No alternative tender offers will be considered.
Complete and submit all returnable schedules listed in T2.1, including the Certificate of Attendance (T2.1.1-01) signed at the compulsory briefing.
Ensure all required documents (e.g., tax clearance, B-BBEE, CIDB, CSD, WCF good standing) are attached.
Tender validity period is 12 weeks from closing date; may be extended if requested.
Do not include documents for any other tender in your submission.
Attend the compulsory clarification meeting; failure to attend leads to disqualification.
Evaluation Criteria
Source: RFQ - TANK REFURBISHMENT.pdf (RFQ)
Eligibility is assessed in three stages:
Stage One: Attendance at the compulsory clarification meeting (must be signed on attendance register).
Stage Two: CIDB registration with contractor grading designation of 1CE or higher (or capable of being registered before evaluation). For JVs, all members must be CIDB registered, lead partner at least one level below required, combined grading meets requirement, and signed JV agreement provided.
Stage Three: Functionality score of at least 70 points out of 100.
Method Statement (15%): Must cover all 7 specified items (technical quality, time minimisation, detailed method for fuel tank replacement, baseline risk assessment, tools/materials, weather remedial actions, safety of Transnet infrastructure/personnel). 7 items = 100%, 6 = 80%, 5 = 60%, 4 = 40%, 1-3 = 20%, none = 0%.
Delivery Lead Time Programme (20%): Delivery period ≤6 weeks = 100%, >6-7 = 80%, >7-8 = 60%, >8-9 = 40%, >9 = 20%, no submission = 0%.
Minimum Personnel Requirements (25%): Provide CVs and qualifications for all 5 key personnel (Project Manager, Master/Electrician, SHE rep, Testing officer/Engineer/Technician, Technical Supervisor). All 5 = 100%, 4 = 80%, 3 = 60%, 2 = 40%, 1 = 20%, none = 0%.
After functionality, evaluation proceeds with price and preference points using the 80/20 system (80 points price, 20 points preference).
Preference points: B-BBEE Level 1 or 2 = 6.67 points; 30% Black Women Owned = 6.67; 50% Black Youth Owned = 6.67; non-compliant or Level 3-8 = 0.
Tenderers must not be listed on Register of Tender Defaulters, Transnet restricted list, or National Treasury defaulters list. Must complete Compulsory Enterprise Questionnaire and have no conflicts of interest.
Transnet may conduct due diligence and risk analysis; reserves right to award to highest scorer unless objective criteria justify otherwise.
Technical Specifications
Source: RFQ - TANK REFURBISHMENT.pdf (RFQ)
Scope: Tank refurbishment for homestead site at Deal Party, Eastern Cape.
Work includes sand blasting and re-painting of tanks within the petroleum industry (as per experience requirement).
Contractor must provide a detailed method statement covering: technical quality approach, time minimisation during fuel tank replacement, step-by-step replacement of standby generator fuel tank, baseline risk assessment, tools and materials, remedial actions for weather changes, and safety of Transnet infrastructure and personnel.
Provide a delivery lead time programme (MS Project or Excel) showing procurement, installation, testing, and commissioning, including Bill of Quantity numbers, activity descriptions, start/finish dates, preceding activities, and time risk allowances.
Minimum key personnel: Project Manager, Master/Electrician, SHE rep, Testing officer/Engineer/Technician, Technical Supervisor. Attach CVs and qualifications. Valid ISO 9001 certification required.
Site visit/walk is part of the compulsory briefing; PPE required (safety shoes, high visibility vests). No PPE = no site access. Breathalyzer testing and ID checks apply. Firearms prohibited.
Contract will be NEC3 Engineering and Construction Contract.
Financial Requirements
Source: RFQ - TANK REFURBISHMENT.pdf (RFQ)
Pricing: Complete the Bill of Quantities (BoQ) as per pricing instructions. No alternative offers accepted.
Preference points: 80/20 system (80 points price, 20 points preference). Price includes all applicable taxes.
Tender validity: 12 weeks from closing date; may be extended.
Transnet may request audited financial statements for due diligence.
No payment terms or bonds specified in the document.
Transnet reserves right to go to open market if quoted rates are unreasonable.
Compliance Requirements
Source: RFQ - TANK REFURBISHMENT.pdf (RFQ)
Central Supplier Database (CSD): Must be registered on https://secure.csd.gov.za/ and provide supplier number and unique registration reference.
Tax: Valid Tax Clearance Certificate from SARS, and provide TCS PIN for verification.
B-BBEE: Valid B-BBEE certificate from SANAS-accredited verification agency, or sworn affidavit confirming annual turnover and black ownership. For JV, consolidated scorecard accepted.
CIDB: Must be registered with CIDB with grading designation 1CE or higher (or capable of being registered before evaluation). Provide CIDB CRS number.
Workmen's Compensation Fund: Letter of Good Standing from WCF (or separate letters for each JV member).
Other returnable documents: Authority to submit tender, Health and Safety Management, Risk Elements, Availability of equipment, Compulsory Enterprise Questionnaire (CIDB SFU Annexure G), Non-Disclosure Agreement, RFQ Declaration Form, Breach of Law declaration, Certificate of Acquaintance, Service Provider Integrity Pact, Supplier Code of Conduct, POPIA agreement, Insurance provided by Contractor.
Must not be listed on Register of Tender Defaulters or Transnet restricted list.
Must complete Compulsory Enterprise Questionnaire and have no conflicts of interest.
Must attend compulsory briefing and submit signed attendance certificate.
DocumentANNEXURE A - SOW.pdfReview complete
Description
Source: ANNEXURE A - SOW.pdf
The service involves tank refurbishment at Deal Party, Gqeberha (Halfweg Depot Loop 10). The scope includes repairs to the tank roof, roof nozzles, handrails, platforms, supports, access stairway, shell external and internal, shell nozzles, tank floor, and foundation. The work must be performed to API 650 and API 653 standards. The Employer's objective is to complete the installation of an underground suction line at Halfweg Loop 10 as soon as possible while maintaining high quality and safety standards without interfering with normal operations.
Roof: sand blast entire roof, supply and install normal and emergency venting systems with screen mesh per API 653, install anti-slip strip.
Roof nozzles: replace goose neck vent, repair corroded areas, fit new seal to dip hatch, tighten loose bolts on auto gauge nozzle.
Handrails/platforms/stairway: sand blast/wire brush, replace severely corroded staircases, repair corroded areas, remove cracked welds and weld reinforcement plates, install support structures anchored to foundation.
Shell external: sand blast entire shell, remove and replace non-conforming patch plates with rounded plates per API 653, conduct PMI test before welding, install data plates per API 650/653, install API-style name plate.
Shell nozzles: remedial grinding, replace threaded connections with welded per API 653, dye-pen test for pin-hole leaks, remove plugs from tell-tale holes, supply and install thermal relief system with isolation valves, supply and calibrate PRV set at 350 kPa, replace old ball valves with new ones, fit spiral wound gaskets, remove non-compliant drainpipe supports and install H-type supports, review and correct inlet nozzle misalignment, box up tank and install new graphite gasket on manhole.
Shell internal: remove non-conforming patch plates, prepare first strake and floor for painting, apply epoxy coating.
Tank floor: repair pitted areas ≥3mm by scab/overlay welding, install strike plate 200x200x6mm EN10025 S355JO under dipping location, trim water draw-off pipe per API 650, apply epoxy coating.
Foundation: grind/wire brush/grit blast and repair coating on floor projection plate, fill and compact voids with material at 45 degrees, ensure bottom-to-shell connection per API 650 5.1.2.7, re-install waterproof membrane, install dip hatch and striker plate per SANS 10131.
Painting: prepare tanks, spray paint external surfaces with oxide primer first coat, then two coats of silver aluminium paint.
Limits: no scope changes without project manager approval, install wear plates on ATG supports.
Handover: generate hand-over report with records of activities and technical details of materials used.
Contractor to supply all labour, tools, materials, scaffolding, platforms, safety harnesses, and site services (electricity, water, ablutions, fire protection, lighting).
Contractor responsible for site security and access control.
Contractor must leave site clean and tidy, no drain blockages or environmental contamination.
Protect existing services; repair any damage at own cost.
Comply with OHS Act and SANS 10089 Part 1-3 for Zone 1 area.
Working hours: Monday-Friday 07:30-16:00 (or as per Department of Labour/trade unions).
No fires on Transnet property.
No accommodation on site except security watchmen with written approval.
Methodology
Source: ANNEXURE A - SOW.pdf (unknown)
Technical requirements for tank refurbishment include specific tasks for roof, nozzles, handrails, shell, floor, foundation, and painting.
Must follow API 650 and API 653 standards.
Conduct PMI test before welding.
Use approved weld procedures and qualified welders.
Submit reviewed design drawings for inlet nozzle misalignment to Transnet Engineer for approval.
No scope changes without project manager approval.
Install wear plates on ATG supports.
Generate hand-over report with records of activities and technical details.
Plan to be submitted with tender showing critical path, logic diagrams, sequence of operations.
Plan shows duration in working days; work week Monday-Friday 07:30-16:00.
Show resource histogram with planned vs actual progress and remedial actions on each revised programme.
Progress reports and updates must be reliable, accurate, and timely.
Experience & Qualifications
Source: ANNEXURE A - SOW.pdf
Works must conform to current professional engineering practices, standards, and specifications.
Contractor and subcontractors must have suitably qualified supervisors in charge of project.
Furnish names, qualifications, and experience of supervisors.
Furnish names and addresses of all proposed subcontractors; subject to approval.
Provide organogram showing key people and lines of authority and communication.
Do not change project team without prior written approval of Service Manager.
Quality Management
Source: ANNEXURE A - SOW.pdf
Contractor must leave site and facilities clean, no drain blockages, no environmental contamination.
Service Manager may stop work until site is clean.
Contractor must protect existing services; repair any damage at own cost.
If unknown services encountered, advise Service Manager in writing within 24 hours.
Work on unknown services not covered by contract will be dealt with per NEC TSC compensation events procedure.
Completion: Contractor must do everything required by Completion Date; Service Manager certifies completion only when work is free of defects.
Contractor must institute a quality control system at own expense, provide experienced technical staff and equipment.
Submit Quality Management System documents: Quality Plan, Quality Policy, Index of Procedures.
Maintain a comprehensive register of documents generated during contract.
Service Manager indicates documents for information, review, or acceptance; Contractor must respond within period for reply.
Quality Plan outlines strategy, methodology, resource allocation, QA/QC coordination to meet standards.
Pricing Schedule
Source: ANNEXURE A - SOW.pdf (unknown)
Invoices must be addressed to Transnet SOC Limited.
Include Transnet's VAT No: 4720103177.
Include invoice number and Contractor's VAT number.
Contractor to bear all costs for site services (electricity, water, etc.) if provided by Employer, at Local Authority tariffs.
Contractor to cover all costs for health and safety requirements in tendered rates.
Compliance Requirements
Source: ANNEXURE A - SOW.pdf (unknown)
Must comply with Occupational Health and Safety Act, 1993 (as amended) and regulations.
Must comply with Transnet Health and Safety Specification TFR-ISM-RN-R&C-FM009.
Must provide letter of good standing from Compensation Commissioner (Section 80 of COIDA).
Must have valid safety inductions and medical certificates for all workers.
Must appoint a health and safety coordinator to liaise fortnightly with Service Manager.
Must finalize site-specific HIRA with Service Manager before work commences.
Must comply with substance abuse policy; Transnet may conduct substance abuse testing.
Must provide site-specific PPE for all workers.
Must comply with SANS 10089 Part 1-3 for Zone 1 area.
Must comply with TFR Standard Environmental Specification (SES).
Must provide quality management system documents including Quality Plan, Quality Policy, and Index of Procedures.
Must provide organogram of key people and not change project team without approval.
Must have suitably qualified supervisors and provide their details.
Must provide details of proposed subcontractors for approval.
Must comply with all health and safety clauses; non-compliance may be breach of contract.
Health & Safety
Source: ANNEXURE A - SOW.pdf
Comply with OHS Act and Transnet Health and Safety Specification TFR-ISM-RN-R&C-FM009.
Submit Health & Safety Program with tender.
Appoint health and safety coordinator to liaise fortnightly with Service Manager.
Contractor is an 'employer' under OHS Act and must fulfil obligations.
Provide particulars of any subcontractors; they must be aware of health and safety clauses.
Advise Service Manager of any hazardous situations.
Furnish letter of good standing from Compensation Commissioner (Section 80 of COIDA).
Submit documentary proof of procedural compliance and particulars of Health & Safety Program before commencement.
Health & Safety Program subject to Service Manager agreement; may order supplementary arrangements.
All health and safety clauses are integral; non-compliance may be breach.
Workers must have valid safety inductions and medical certificates.
Finalize site-specific HIRA with Service Manager on day of site handover; must be signed and accepted before work.
Substance abuse testing may be conducted; no person under influence allowed.
Ensure safety representative appointed and regular safety meetings held; minutes to Service Manager.
All costs for safety aspects to be covered in tendered rates.
Comply with SANS 10089 Part 1-3 for Zone 1 area.
Provide site-specific PPE for all workers.
Working hours per Department of Labour or trade unions; supply to Service Manager prior to commencement.
Keep daily records of people on site; available for inspection.
Ensure safe passage of traffic and workers around working areas.
Contractor excluded from Employer's Operational Areas adjacent to Affected Property.
Staff and equipment must remain within allocated fenced-off area.
Comply with TRIM operational safety requirements.
No accommodation on site except security watchmen with written approval.
Contractor to provide own security and access control.
Site access certificate to be issued and displayed.
Contractor to provide safe working access as approved by Service Manager.
Provide A4 triplicate books for Daily Diary and Site Instruction Book.
No fires on Transnet property.
Contractor to provide all tools, materials, water, electricity, etc.
Leave site clean and tidy.
Contractual Terms
Source: ANNEXURE A - SOW.pdf
Contractor and Service Manager to inspect immediate surroundings and record any damage before work starts.
Contractor must ensure no damage to adjoining property; negotiate permission to work on adjoining land if necessary.
Contractor to supply all labour, tools, materials, scaffolding, platforms, and safety harnesses.
Contractor responsible for maintenance, leasing, hiring, and insurance of equipment.
Contractor responsible for transport and safekeeping of equipment and materials; Transnet accepts no liability for safekeeping.
Fires strictly prohibited on Transnet property.
All health and safety clauses are integral part of contract; non-compliance may be breach of contract.
Contractor and employees must have valid safety inductions and medical certificates.
Insurance provided by Employer is contained in Contract Data – Part 1; procedures for claims from Service Manager.
Standard reporting forms will be provided to Contractor.
No additional requirements apply to TSC Clause 60 series.
Special Conditions
Source: ANNEXURE A - SOW.pdf (unknown)
Work to be carried out at Halfweg Depot Loop 10.
Contractor must ensure safe passage of traffic and workers.
Contractor excluded from Employer's Operational Areas adjacent to Affected Property.
Access routes allocated and coordinated by Service Manager.
Staff and equipment must remain within allocated fenced-off area.
Comply with TRIM operational safety requirements and provide PPE.
Conform to OHS Act and SANS 10089 Part 1-3 for Zone 1 area.
Working hours per Department of Labour or trade unions; supply to Service Manager.
Keep daily records of people on site.
Contractor must not interfere with other parties; work in liaison with Service Manager.
Obtain permission before erecting notice boards or using contract details in advertising.
No communication with media without written consent.
No equipment provided by Employer.
Contractor to make own arrangements for site services (electricity, water, ablutions, fire protection, lighting).
Provide and maintain portable latrines at own cost.
If Employer provides services, costs for meters, connections, usage to Contractor's account.
Suitable construction site provided free of charge; must be signposted and compliant.
Layout of construction site to be submitted for approval before erecting camp.
Contractor to arrange accommodation for labour; no accommodation on site except security watchmen with approval.
Contractor to provide security and access control.
No facilities required for Service Manager.
Contractor and Service Manager to inspect surroundings and record damage before work.
Contractor to ensure no damage to adjoining property; negotiate permission if necessary.
Contractor to supply all labour, tools, materials, scaffolding, platforms, safety harnesses.
Contractor responsible for maintenance, leasing, hiring, insurance of equipment.
Contractor responsible for transport and safekeeping of equipment and materials.
No liability accepted by Transnet for safekeeping of Contractor's materials.
Fires strictly prohibited.
Contractor to leave site clean and tidy.
Protect existing services; repair any damage at own cost.
Unknown services: advise Service Manager in writing within 24 hours.
Work on unknown services per NEC TSC compensation events procedure.
Provide A4 triplicate books for Daily Diary and Site Instruction Book.
Only Service Manager may issue site instructions.
Section
Source: ANNEXURE A - SOW.pdf
The Employer's objective is to achieve installation of underground suction line at Halfweg Loop 10 as soon as possible while maintaining highest quality and safety standards, without interfering with normal day-to-day operations. This implies evaluation may consider ability to complete work promptly and safely.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Level 200, Carlton Centre, 150 Commissioner St, Cbd, Johannesburg, 2001, South Africa
Document-Backed
Recently Synced
Source Snapshot Available
AI Enhanced
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
2
Last checked
03 Aug 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.