Awarded Tender: Construction of sanitation facilities at zanokhanyo junior primary school eastern cape
Contract Awarded
This tender has been awarded to TPM DEVELOPERS for RΒ 6Β 138Β 858 00.
AwardedTMT-ECDOE-26/27-SAN60-CL30
Award Information
Award Value
RΒ 6Β 138Β 858 00
Winning Supplier
TPM DEVELOPERS
Type: GEN
Construction
Tender document for the construction of sanitation facilities at zanokhanyo junior primary school in eastern cape province under the sanitation 60 programme
Tender document for the construction of sanitation facilities at zanokhanyo junior primary school in eastern cape province under the sanitation 60 programme
What the tender required and what the award supports
Source material and existing AI analysis appear first. Supplier conclusions remain qualified by the evidence Tenders-SA holds.
Summary
This tender invites bids for the construction of new ablution facilities at zanokhanyo junior primary school in the eastern cape, under the sanitation 60 programme managed by the mvula trust. IT is a government contract requiring compliance with jbcc standards, strict health and safety regulations, and an 18-week completion timeline.
Review in progress Β· 1 of 2 document being finalised
AI Document Analysis Stages
Document read. The full tender notice and its supporting documents are read end-to-end. Key sections, requirements, dates, and contact details are identified and pulled into a working summary you can act on.
Compliance review. The working summary is checked against South African procurement standards β PFMA, PPPFA, B-BBEE, CIDB, local content, and preferential procurement β so nothing critical is missed before you start your bid response.
Review in progress
The information shown on this card is preliminary. Our procurement team is currently finalising the submission guidelines, evaluation criteria, technical specifications, financial requirements, and compliance sections so you have a clean, bid-ready summary to work from. Document being finalised: TMT-ECDoE-2627-SAN60-CL30 ZANOKHANYO JSS.pdf. You donβt need to refresh β this page will pick up the updated review automatically.
DocumentTMT-ECDoE-2627-SAN60-CL30 ZANOKHANYO JSS.pdfCompliance review in progress
Award analysis coverage
0 of 2 source documents fully reviewed. Unstated details are identified only after complete source review.
technical scope
28 sourced criteria
financial capacity
22 sourced criteria
pricing
6 sourced criteria
compliance returnables
34 sourced criteria
evaluation
14 sourced criteria
experience
2 sourced criteria
personnel
3 sourced criteria
equipment capacity
5 sourced criteria
delivery contract
5 sourced criteria
equity registrations
9 sourced criteria
What the buyer was looking for
1Inferred operational need
Submit a fully priced Bill of Quantities (BoQ) with all items individually priced; unpriced items will be deemed free of charge.
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.
Inferred from stored analysis; verify against the source document. No source document identifier is stored for this item.
Source: AI key requirements Β· requirements
Known supplier evidence
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
An award confirms appointment. It does not prove why a supplier was selected, that every qualification remains current, or that delivery was completed successfully.
Bid-ready summary. The submission guidelines, evaluation criteria, technical, financial, and compliance sections are refined into professional, easy-to-scan prose. This is the final version you can rely on when preparing your bid or briefing your team.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically β no action required from you.
Submit one tender offer only (as a single entity or joint venture member).
Deadline: Friday, 10 July 2026 at 12:00pm. Late submissions will not be accepted.
Submission method: Sealed envelope, clearly marked with Bid No. TMT-ECDOE-26/27-SAN60-CL30, deposited in the tender box at 69 Devereux Avenue, Vincent, East London. Fax/email submissions will be rejected.
Documents: Return all returnable documents (Part T2) completed in full, using non-erasable black ink. Submit original + required copies; sign the original where required.
Key returnables: CSD Registration Report (β€30 days old), CIDB print-out, COIDA/FEM Certificate, Completed Projects (T2.1.D), Current Projects declaration (T2.1.E), SBD 1/2/4/6.1, and risk assessment schedules (T2.3).
Non-compliance: Missing/incomplete data may render the tender non-responsive.
Scoring: 80/20 Preference Point System (80 points for price, 20 points for Specific Goals).
CIDB Grading: Minimum 4GB (valid on evaluation and award days). Joint ventures must comply with CIDB Regulation 25(6) Table 9 (e.g., 3x Grade 3 for Grade 4 JV).
Project Limits: Maximum 2 current projects under construction. Disqualification if: (a) >2 current projects, (b) awarded/considered for β₯2 other TMT projects, or (c) fails to declare current projects.
Risk Assessment: Mandatory minimum 14/20 points across 6 areas:
Scope: Construction of sanitation facilities at Zanokhanyo Junior Primary School (Eastern Cape) under the Sanitation 60 Programme.
CIDB Grading Requirement: 5 GB or higher for the project.
Contract Duration: 24 weeks from commencement to practical completion.
Penalties: R2,000/day for late completion (capped at 10% of contract value).
Key Personnel: Must include:
Contract Manager (3-year built environment qualification + 5 yearsβ building experience).
OHS Officer (SACPCMP-registered).
Foreman (5 yearsβ school sanitation/building experience).
Health & Safety: Comply with Part C3 (Health and Safety Specification, Contractorβs Report, Certificates of Compliance).
Subcontracting: 5% of construction value reserved for local SMMEs (participation) and local suppliers (material procurement). Pricing must cover SMME engagement, supervision, and profit.
Standards: CIDB Standard Conditions of Contract (August 2019) apply.
CSD Registration: Must be registered on Central Supplier Database on tender closure date. Submit report β€30 days old (48-hour grace period to update if expired).
CIDB Registration: Valid on evaluation and award days; submit print-out. Fraudulent registrations = disqualification + CIDB complaint.
COIDA/FEM: Certificate of Good Standing with Workmenβs Compensation Commissioner (valid on evaluation/award).
Works Description: Construction of new ablution facilities at Zanokhanyo Junior Primary School.
Site Description: Existing school premises with no work or installations by others.
Important Dates
Source: ZANOKHANYO PS UNPRICED BOQ.pdf (unknown)
Tender validity: 20 weeks from closing date.
Site possession date: To be advised by the Principal Agent.
Commencement: Must begin within 5 working days after site possession.
Practical completion: Intended within 18 weeks of commencement.
Penalty for non-completion: R2000 per calendar day, capped at 10% of the contract amount.
Contact Information
Source: ZANOKHANYO PS UNPRICED BOQ.pdf (unknown)
Employer and Principal Agent: The Mvula Trust.
Postal Address: 67 Devereux Avenue, Vincent, East London.
Physical Address: 67 Devereux Avenue, Vincent, East London.
Telephone: 043 726 2255.
Facsimile: 043 726 5967.
Submission Guidelines
Source: ZANOKHANYO PS UNPRICED BOQ.pdf (unknown)
Tenders must remain valid for 20 weeks from the closing date.
Submit a fully priced Bill of Quantities (BoQ) with each item priced individuallyβno lump sums.
Include a fully priced Health and Safety schedule with quantities inserted for each item.
Priced documents must be submitted within 5 working days of receiving the Letter of Appointment.
Unpriced items will be deemed free of charge; no claims for extras will be accepted.
Submit three sets of as-built drawings within 14 days after practical completion.
Returnable Documents
Source: ZANOKHANYO PS UNPRICED BOQ.pdf (unknown)
Fully priced Bill of Quantities and Health and Safety schedule with quantities inserted for each item.
Three sets of as-built drawings submitted within 14 days after practical completion.
General Preambles for Trades 2017 (ASAQS) apply; supplementary preambles take precedence.
Evaluation Criteria
Source: ZANOKHANYO PS UNPRICED BOQ.pdf (unknown)
Compliance with JBCC Series Edition 4.1 (March 2005) contract framework is mandatory.
Demonstrate capability to complete works within the 18-week timeline.
Proof of insurance capacity required: Contract Works (sum + 10%), SASRIA (sum + 20%), Public Liability (R5 million).
Experience with government contracts is required.
No payment guarantee will be provided (government contract).
Community Liaison Officer (CLO) costs must be included in Health and Safety pricing.
Tender validity period: 20 weeks from closing date.
Technical Specifications
Source: ZANOKHANYO PS UNPRICED BOQ.pdf (unknown)
Scope: Construction of new ablution facilities at Zanokhanyo Junior Primary School (existing school premises).
Contract Framework: JBCC Principal Building Agreement Series Edition 4.1 (March 2005) and Preliminaries Series 2000 (May 2005), both as amended by this tender.
Standards: General Preambles for Trades 2017 (ASAQS) apply; supplementary preambles take precedence.
Temporary Works: Contractor must provide all temporary works, services, and site facilities (water, electricity, telephones, ablutions).
Site Office: Provide a 4m x 3m lockable site office with concrete floor, windows, and meeting facilities.
Storage: Provide a lockable container or structure with a concrete or steel floor for material storage.
Documentation: Submit method statements, maintain construction instruction and daily record books, and provide weekly labour and plant records.
Materials: Use proprietary branded products strictly per manufacturer instructions; obtain written approval for alternatives.
Site Responsibilities: Inspect site, existing premises, and services; protect trees and adjoining properties.
Methodology
Source: ZANOKHANYO PS UNPRICED BOQ.pdf
Method Statement: Submit a method statement outlining construction methods, labour, and plant resources. Approval does not relieve the contractor of responsibility.
Site Records: Maintain a construction instruction book (A4 triplicate) and daily record book (A4 triplicate) on site. Entries must be signed and forwarded to the Principal Agent daily.
Reporting: Provide weekly labour and plant records in schedule form to the Principal Agent.
Work Order: Principal Agent may direct the order of execution and expedite sections; contractor must comply and provide additional resources at their own cost if required.
Temporary Works: Provide all temporary works, roads, services, and site accommodation. No guarantee is given for site conditions.
Site Office: Provide a 4m x 3m lockable site office with a concrete floor, windows, and meeting facilities.
Storage: Provide a lockable container or structure with a concrete or steel floor for material storage.
Cleanup: Remove all temporary works on completion and make good any damage to the Principal Agent's satisfaction.
Quality Management
Source: ZANOKHANYO PS UNPRICED BOQ.pdf
Site Inspection: Contractor is responsible for inspecting the site, existing premises, services, and protecting trees.
Submissions: Submit samples of materials, workmanship samples, and shop drawings as required.
Proprietary Products: Use branded products strictly per manufacturer instructions; obtain written approval for alternatives.
Pricing Schedule
Source: ZANOKHANYO PS UNPRICED BOQ.pdf
Individual Pricing: Price each item in the Bill of Quantities individuallyβno lump sums.
Unpriced Items: Will be deemed free of charge; no claims for extras will be accepted.
Preliminaries Categorization: If using Alternative A, categorize items as Fixed (F), Variable (V), or Time-related (T) in the rate column.
VAT: Provision for VAT is included in the Final Summary of the BoQ.
Financial Requirements
Source: ZANOKHANYO PS UNPRICED BOQ.pdf (unknown)
Pricing: Price each item in the Bill of Quantities individuallyβno lump sums.
Unpriced items: Deemed free of charge; no claims for extras will be entertained.
Preliminaries Adjustment: If using Alternative A, categorize items as Fixed (F), Variable (V), or Time-related (T) in the rate column.
VAT: Provision for VAT is included in the Final Summary of the BoQ.
Interim Payments: Off-site materials may be included in payment certificates only with an approved bank guarantee.
No Payment Guarantee: This is a government contract; no payment guarantee will be provided.
Contract Value Adjustment: CPAP will not be used for adjustments.
Compliance Requirements
Source: ZANOKHANYO PS UNPRICED BOQ.pdf (unknown)
Contract Type: State Contract under the Sanitation 60 Programme.
Legal Compliance: Adhere to the Occupational Health and Safety Act and Construction Regulations 2014.
Health and Safety: Provide a site-specific Health and Safety Plan, Health and Safety File, and employ a full-time Health and Safety Officer. Conduct induction training and supply first aid boxes.
Insurance: Contract Works (sum + 10%, deductible β€5%), SASRIA (sum + 20%), Public Liability (R5 million, deductible β€5%).
Waiver of Lien: Required.
Dispute Resolution: Mediation followed by litigation.
Applicable Law: Republic of South Africa.
Latent Defects: Includes water leakage unless proven to be a design defect or storm damage; defects must be attended to progressively during the liability period.
Community Liaison: Incorporate Community Liaison Officer (CLO) costs in pricing.
Health & Safety
Source: ZANOKHANYO PS UNPRICED BOQ.pdf
Compliance: Adhere to the Occupational Health and Safety Act and Construction Regulations 2014.
Documentation: Provide a site-specific Health and Safety Plan and File.
Personnel: Employ a full-time Health and Safety Officer for the entire construction period.
Training: Conduct induction training for all personnel and provide first aid boxes.
Barriers: Erect SANS-approved temporary barrier fencing (400m) with a double-swing vehicle gate (5.5m x 1.8m) and pedestrian gate (1.8m x 1.8m).
PPE: Supply personal protective equipment (reflective vests, hard hats, safety footwear, ear plugs, dust masks).
Health Monitoring: Cover costs for initial and exit medical examinations, noise monitoring, and audiograms.
Site Control: Exclude unauthorized persons; provide shelter for labour and watchmen.
Community Liaison: Incorporate Community Liaison Officer (CLO) costs in pricing.
Contractual Terms
Source: ZANOKHANYO PS UNPRICED BOQ.pdf
Principal Building Agreement: JBCC Series Edition 4.1 (March 2005), as amended by this tender.
Latent Defects: Includes water leakage unless proven to be a design defect or storm damage. Defects must be rectified progressively during the liability period.
Completion: Practical completion intended within 18 weeks; penalty of R2000 per calendar day for non-completion, capped at 10% of the contract amount.
Insurance: Contract Works (sum + 10%), SASRIA (sum + 20%), Public Liability (R5 million).
Dispute Resolution: Mediation followed by litigation.
Applicable Law: Republic of South Africa.
Section
Source: ZANOKHANYO PS UNPRICED BOQ.pdf (unknown)
CONTRACTING AND OTHER PARTIES (Clause 42.1). Employer: The Mvula Trust. Postal Address: 67 Devereux Avenue, Vincent, East London. Telephone: 043 726 2255. Facsimile: 043 726 5967. Physical address: 67 Devereux Avenue, Vincent, East London. Principal Agent: The Mvula Trust. Postal Address: 67 Devereux Avenue, Vincent, East London. Telephone: 043 726 2255. Facsimile: 043 726 5967. Physical address: 67 Devereux Avenue, Vincent, East London.
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
2Inferred operational need
Complete works within 18 weeks of commencement; penalties of R2000 per calendar day apply for delays, capped at 10% of the contract value.
Threshold: 18 weeks
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.
Inferred from stored analysis; verify against the source document. No source document identifier is stored for this item.
Source: AI key requirements Β· requirements
Known supplier evidence
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
3Inferred operational need
Include a fully priced Health and Safety schedule with quantities, a site-specific Health and Safety Plan, and a full-time Health and Safety Officer.
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.
Inferred from stored analysis; verify against the source document. No source document identifier is stored for this item.
Source: AI key requirements Β· requirements
Known supplier evidence
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
4Mandatory requirement
Tenders must remain valid for 20 weeks from the closing date (10 July 2026).
Threshold: 20 weeks
Why it matters: The source identifies this as a mandatory or eligibility condition for a compliant bid.
No source document identifier is stored for this item.
Source: AI key requirements Β· requirements
Known supplier evidence
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
5Inferred operational need
Works Description: Construction of new ablution facilities at Zanokhanyo Junior Primary School.
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.
Inferred from stored analysis; verify against the source document.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
11Inferred operational need
Method Statement: Submit a method statement outlining construction methods, labour, and plant resources. Approval does not relieve the contractor of responsibility.
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.
Inferred from stored analysis; verify against the source document.
Tenders-SA records other appointments with overlapping scope terms for TPM DEVELOPERS.
Qualified inference
Supported inference
The recorded history supports exposure to related scope, but does not establish the bid evidence submitted or current delivery capacity.
Related historical records suggest exposure; they do not prove bid contents, current capacity, or delivery.
12Mandatory requirement
Site Records: Maintain a construction instruction book (A4 triplicate) and daily record book (A4 triplicate) on site. Entries must be signed and forwarded to the Principal Agent daily.
Why it matters: The source identifies this as a mandatory or eligibility condition for a compliant bid.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
14Mandatory requirement
Work Order: Principal Agent may direct the order of execution and expedite sections; contractor must comply and provide additional resources at their own cost if required.
Why it matters: The source identifies this as a mandatory or eligibility condition for a compliant bid.
Tenders-SA records other appointments with overlapping scope terms for TPM DEVELOPERS.
Qualified inference
Supported inference
The recorded history supports exposure to related scope, but does not establish the bid evidence submitted or current delivery capacity.
Related historical records suggest exposure; they do not prove bid contents, current capacity, or delivery.
16Inferred operational need
Storage: Provide a lockable container or structure with a concrete or steel floor for material storage.
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.
Inferred from stored analysis; verify against the source document. Inferred from stored analysis; verify against the source document. No source document identifier is stored for this item.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
19Inferred operational need
Contract Framework: JBCC Principal Building Agreement Series Edition 4.1 (March 2005) and Preliminaries Series 2000 (May 2005), both as amended by this tender.
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.
Inferred from stored analysis; verify against the source document. No source document identifier is stored for this item.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
33Inferred operational need
VAT: Provision for VAT is included in the Final Summary of the BoQ.
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.
Inferred from stored analysis; verify against the source document. Inferred from stored analysis; verify against the source document. No source document identifier is stored for this item.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
51Inferred operational need
Community Liaison: Incorporate Community Liaison Officer (CLO) costs in pricing.
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.
Inferred from stored analysis; verify against the source document. Inferred from stored analysis; verify against the source document. No source document identifier is stored for this item.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
53Inferred operational need
Unpriced Items: Will be deemed free of charge; no claims for extras will be accepted.
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.
Inferred from stored analysis; verify against the source document. Inferred from stored analysis; verify against the source document. No source document identifier is stored for this item.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
56Mandatory requirement
**Subcontracting**: **5% of construction value** reserved for **local SMMEs** (participation) and **local suppliers** (material procurement). Pricing must cover SMME engagement, supervision, and profit.
Why it matters: The source identifies this as a mandatory or eligibility condition for a compliant bid.
No source document identifier is stored for this item.
Tenders-SA records other appointments with overlapping scope terms for TPM DEVELOPERS.
Qualified inference
Supported inference
The recorded history supports exposure to related scope, but does not establish the bid evidence submitted or current delivery capacity.
Related historical records suggest exposure; they do not prove bid contents, current capacity, or delivery.
70Inferred operational need
Health and Safety: Provide a site-specific Health and Safety Plan, Health and Safety File, and employ a full-time Health and Safety Officer. Conduct induction training and supply first aid boxes.
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.
Inferred from stored analysis; verify against the source document. No source document identifier is stored for this item.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
72Mandatory requirement
Latent Defects: Includes water leakage unless proven to be a design defect or storm damage; defects must be attended to progressively during the liability period.
Why it matters: The source identifies this as a mandatory or eligibility condition for a compliant bid.
No source document identifier is stored for this item.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
75Inferred operational need
**Submission method**: Sealed envelope, clearly marked with **Bid No. TMT-ECDOE-26/27-SAN60-CL30**, deposited in the tender box at **69 Devereux Avenue, Vincent, East London**. Fax/email submissions **will be rejected**.
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.
Inferred from stored analysis; verify against the source document. No source document identifier is stored for this item.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
76Inferred operational need
**Documents**: Return **all returnable documents** (Part T2) completed in full, using **non-erasable black ink**. Submit **original + required copies**; sign the original where required.
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.
Inferred from stored analysis; verify against the source document. No source document identifier is stored for this item.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
80Mandatory requirement
**CSD Registration**: Must be **registered on Central Supplier Database** on tender closure date. Submit **report β€30 days old** (48-hour grace period to update if expired).
Threshold: 30 days
Why it matters: The source identifies this as a mandatory or eligibility condition for a compliant bid.
No source document identifier is stored for this item.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
96Scored criterion
**Project Limits**: Maximum **2 current projects** under construction. **Disqualification** if: (a) >2 current projects, (b) awarded/considered for β₯2 other TMT projects, or (c) fails to declare current projects.
Threshold: Maximum **2 current projects** under construction
Why it matters: The source places this item in the evaluation criteria; the recorded weight or threshold is shown when available.
No source document identifier is stored for this item.
Tenders-SA records other appointments with overlapping scope terms for TPM DEVELOPERS.
Qualified inference
Supported inference
The recorded history supports exposure to related scope, but does not establish the bid evidence submitted or current delivery capacity.
Related historical records suggest exposure; they do not prove bid contents, current capacity, or delivery.
103Scored criterion
**Disqualification Triggers**: Poor past performance (>25% overrun), penalties/negative final accounts, unresolved defects, or fraudulent registrations.
Why it matters: The source places this item in the evaluation criteria; the recorded weight or threshold is shown when available.
No source document identifier is stored for this item.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
116Mandatory requirement
Latent Defects: Includes water leakage unless proven to be a design defect or storm damage. Defects must be rectified progressively during the liability period.
Why it matters: The source identifies this as a mandatory or eligibility condition for a compliant bid.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
118Inferred operational need
Dispute Resolution: Mediation followed by litigation.
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.
Inferred from stored analysis; verify against the source document. Inferred from stored analysis; verify against the source document. No source document identifier is stored for this item.
The linked award records TPM DEVELOPERS as appointed for this tender. Recorded contract value: 6138858 ZAR.
Qualified inference
Inference only
The successful bid likely addressed this expectation, but the submitted evidence and evaluation reason are unavailable.
The linked award confirms appointment only, not the submitted qualification or reason for selection.
119Inferred operational need
Applicable Law: Republic of South Africa.
Why it matters: This is a qualified operational interpretation of the stored scope, not a stated mandatory or scored criterion.