Works description: Construction of new ablution facilities at Zinyosini Senior Secondary School.
Site: existing school premises.
No work or installations by others.
Contract period: 18 weeks to practical completion.
Penalty for non-completion: R 2,000.00 per calendar day, capped at 10% of contract amount.
Contract works insurance: contract sum plus 10%, deductible not exceeding 5% per claim.
SASRIA insurance: contract sum plus 20%.
Public liability insurance: R 5 million, deductible not exceeding 5% per claim.
Contractor to provide a 4 x 3m site office with concrete floor, lockable, with tables and chairs.
Contractor to provide a lockable storage container with concrete or steel floor.
Contractor to provide water, electricity, telephones, and ablution facilities on site.
Contractor to erect hoardings, safety screens, barriers, and access gates for public protection.
Contractor to provide one main notice board.
Contractor to record construction breaks and concrete pours on structural drawings.
Contractor to maintain site instruction book, daily record book, and weekly labour and plant records.
Contractor to submit as-built drawings (three sets) within 14 days after practical completion.
Contractor to produce a method statement when required by the Principal Agent.
Contractor to exclude unauthorised persons from site and provide shelter for labour if needed.
Contractor to remove all temporary works and make good any damage on completion.