Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Quotation
Delivery Location
OR Tambo International Airport - Cape Town International Airport - Kempton Park -
Organization Type
GOVERNMENT
Published
18 Sept 2026
OCDS Reference
ocds-9t57fa-170945
Procurement of construction works at an airport under a nec3 priced contract with bill of quantities, including design responsibility, site access 14 hours daily, and a r100 million professional indemnity insurance requirement. The most consequential consideration is the mandatory r100 million pi cover and the employer's right to terminate for convenience with payment of a1 amount.
Continue with tenders sharing this issuer, category, or province.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Friday, 16 October 2026 - 12:00
Venue
Ms Teams On Line
Categories
Request for Quotation
OR Tambo International Airport - Cape Town International Airport - Kempton Park -
Tenders in this industry often require registration with these bodies.
Construction Industry Development Board (CIDB) registration is mandatory for almost all public sector construction tenders. Ensure your grading matches the tender value.
Recommended Certifications
Having these can improve your winning chances: NHBRC Registration, ISO 9001:2015 (Quality Management), ISO 14001:2015 (Environmental Management), ISO 45001:2018 (Occupational Health & Safety), SACPCMP Registration, ECSA Registration
AI Document Analysis Stages
Important Dates
Source: CIDB Bid document_RFQ 73933.pdf (TENDER)18 Sept
2026
Tender Published
Tender was published
16 Oct
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdf
Airports Company South Africa requires the refurbishment of passenger loading bridge wheels at OR Tambo International Airport, under an NEC3 Engineering and Construction Contract (Option B: Priced contract with bill of quantities). The contract runs for 12 months with a completion date of 30 March 2028, and includes sectional completion, delay damages, and extensive additional conditions.
CIDB Bid document_RFQ 73933.pdf
Refurbishment of passenger loading bridge wheels at OR Tambo International Airport, including new bearings, flange bearings, variable speed gear motors, and glass tunnel panels. The contract is issued by Airports Company South Africa (ACSA) and is subject to the Preferential Procurement Policy Framework Act, 2000.
To download these documents and access AI-powered analysis, visit the main tender page.
Win ACSA tenders with AI Matching Engine, airport-infrastructure intelligence, compliance analysis, and application support for aviation operations.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
R 1 983 750
Range
Based on 21 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Closing date: 16 October 2026 at 12h00 (South African time).
Contact Information
Source: CIDB Bid document_RFQ 73933.pdf (TENDER)Enquiries (bidding procedure and technical):
Submission email: [email protected]
Submission Guidelines
Source: CIDB Bid document_RFQ 73933.pdf (TENDER)Submission method: email only, to [email protected]. Bids sent to any other address will not be considered.
Evaluation Criteria
Source: CIDB Bid document_RFQ 73933.pdf (TENDER)Evaluation stages:
Technical Specifications
Source: CIDB Bid document_RFQ 73933.pdf (TENDER)Scope: Refurbishment of passenger loading bridge wheels at OR Tambo International Airport.
Financial Requirements
Source: CIDB Bid document_RFQ 73933.pdf (TENDER)Pricing: Fixed prices, no contract price adjustments or foreign fluctuations. Rates and prices remain fixed and binding for the full contract duration.
Compliance Requirements
Source: CIDB Bid document_RFQ 73933.pdf (TENDER)CIDB: Contractor grading of 4ME or higher (mandatory).
Description
Source: NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdfRefurbishment of Passenger Loading Bridges at OR Tambo International Airport for a period of 12 months. The works are Refurbishment for Passengers Loading Bridges at OR Tambo International Airport. The completion date for the whole of the works is 30 March 2028. The starting date is 01 November 2026.
Important Dates
Source: NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdf (unknown)Closing date: 16 October 2026 at 12:00
Starting date: 01 November 2026
Completion date for whole of works: 30 March 2028
Defects date: 52 weeks after Completion of the whole of the works
No briefing or site visit dates are stated.
Contact Information
Source: NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdf (unknown)Employer: Airports Company South Africa SOC Limited (reg. no: 1993/004149/06)
Address: O R Tambo International Airport, ACSA Admin. Building, 3rd Floor North Wing Offices, Kempton Park, 1627
Project Manager: TBA (same address)
Supervisor: TBA (same address)
Insurance contact:
Submission Guidelines
Source: NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdf (unknown)Returnable documents:
Submission method: not stated in the document. Closing time: 12:00 on 16 October 2026 (from tender record).
Disqualification risks:
Evaluation Criteria
Source: NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdf (unknown)Evaluation method not stated in the document. The contract is a priced contract with bill of quantities (NEC3 main Option B). No preference point system (80/20 or 90/10) is mentioned. No minimum qualifying score is stated.
Technical Specifications
Source: NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdf (unknown)Scope: Refurbishment of Passenger Loading Bridges (PLBs) at OR Tambo International Airport.
Contract period: 12 months.
Works to be done one PLB at a time; commissioning and testing per PLB.
Site access: 14 hours, 7 days a week.
The Employer is not willing to take over the works before the Completion Date.
The Contractor must submit a first programme within 2 weeks of the Contract Date, and revised programmes at intervals no longer than 2 weeks.
The period for reply is 1 week.
The law of the contract is the law of the Republic of South Africa; language is English.
Quality Management
Source: NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdfThe Contractor must implement and maintain a quality management system as stated in the Works Information.
A quality plan must be submitted for acceptance within 2 weeks of the Contract Date.
The Project Manager may instruct correction of any failure to comply with the quality plan; such instruction is not a compensation event.
Financial Requirements
Source: NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdf (unknown)Pricing: Priced contract with bill of quantities, measured in accordance with the 6th edition of the Standard System of Measuring Building Works (ASAQS), amended as stated in Part C2.1 Pricing Assumptions.
Payment: Assessments between the 20th day of each successive month; payments made within 5 weeks.
Performance bond: unconditional, on-demand, from an accepted bank or insurer, in the form in Annexure B. Must remain valid until end of contract period; if it expires earlier, must be extended four weeks prior to expiry, otherwise the Employer may claim the full amount and retain as cash security.
Delay damages: PLB handover R5,000 per day; Commissioning and Testing R3,000 per day; whole of works 0.05% of contract value per day, up to 10% maximum.
Limitation of liability: Neither party liable for indirect or consequential loss; Contractor's total liability limited to total losses incurred and/or repairs to damages caused, with excluded matters listed.
Insurance: Employer arranges Contract Works, Public Liability (R100,000,000), Lateral Support (R50,000,000), SASRIA (R500,000,000 aggregate), and Professional Indemnity (R25,000,000 aggregate, shared across ACSA contracts). Contractor must familiarise itself with these policies and may arrange additional cover at its own cost.
Compliance Requirements
Source: NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdf (unknown)No specific eligibility or pre-qualification requirements (e.g., CSD, tax clearance, B-BBEE, CIDB) are stated in the document.
The Contractor must comply with the Compensation for Occupational Injuries and Diseases Act No. 130 of 1993 and common law liability for people falling outside the scope of the Act.
The Contractor must implement a quality management system and submit a quality plan for acceptance within 2 weeks of the Contract Date.
Safety file approval is a key date condition.
Health & Safety
Source: NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdfSafety file approval is a key date condition.
The Contractor must comply with the Compensation for Occupational Injuries and Diseases Act No. 130 of 1993 and common law liability for people falling outside the scope of the Act.
Environmental
Source: NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdf (unknown)Weather data for compensation events: cumulative rainfall, number of days with rainfall more than 10 mm, number of days with minimum air temperature less than 0 degrees Celsius, and number of days with snow lying at 09:00 South African Time, recorded at OR Tambo International Airport, supplied by the National Weather Bureau of SA, with assumed values for ten-year return weather data in Annexure A.
Contractual Terms
Source: NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdfContract form: NEC3 Engineering and Construction Contract (April 2013) with main Option B (Priced contract with bill of quantities), dispute resolution Option W1, and secondary options X5 (Sectional Completion), X7 (Delay damages), X15 (Limitation of liability for design), X18 (Limitation of liability), X20 (Key performance indicators), and additional conditions Z1 to Z24.
Key terms:
Special Conditions
Source: NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdf (unknown)The Employer is not willing to take over the works before the Completion Date.
Access to the site is available 14 hours, 7 days a week.
The Contractor must submit a first programme within 2 weeks of the Contract Date, and revised programmes at intervals no longer than 2 weeks.
The period for reply is 1 week.
The law of the contract is the law of the Republic of South Africa, and the language is English.
Section
Source: NEC 3 ECC Contract - Refurbishment of PLB wheels at ORTIA Rev 2.pdfNo evaluation criteria are stated in the document. The contract is a priced contract with bill of quantities; no scoring or preference point system is mentioned.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 38 of 2000
Important for public-sector construction and infrastructure tenders that require contractor grading or construction procurement standards.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 107 of 1998
Relevant where environmental authorisations, EIAs or environmental compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 85 of 1993
Sets health and safety duties for contractors, employers and service providers working on public-sector sites.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 103 of 1977
Relevant where building standards, renovations, maintenance or construction compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Address
OR Tambo International Airport - Cape Town International Airport - Kempton Park -
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
2
Last checked
23 Sept 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Learn how to submit a winning bid with these related articles
How established construction firms use Joint Ventures with EMEs and QSEs to meet B-BBEE preferential procurement targets and access set-aside contracts.
Everything South African construction contractors need to know about how procurement officers verify cidb grades: what gauteng contractors must ensure is correct — april 2026 update — covering CIDB grading certificate, NHBRC registration (residential), step-by-step processes, common disqualification mistakes, and how Tenders-SA.org helps you find and win relevant contracts in Gauteng.
A practical guide for small and medium building contractors on winning government tenders for schools, clinics, housing, and municipal buildings in South Africa.
How small and medium construction contractors use Joint Ventures to combine CIDB grades, win larger infrastructure projects, and grow beyond their current grading ceiling.
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Specialised construction activities. Unlock full pricing strategies, bid frequency, and historical win rates.