Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Status: Closed — No Longer Accepting Submissions
This tender closed on 26 February 2026. Submissions are no longer accepted. The tender lifecycle continues — check the awards section for updates.
Tender Type
RFI
Delivery Location
522 Impala Road - Johannesburg - Johannesburg - 2058
Organization Type
GOVERNMENT
Published
04 Feb 2026
Rand water is seeking information from qualified oems, epc contractors and system integrators on utility‑grade battery energy storage system (bess) solutions to support its bulk water pumping operations in gauteng. The aim is to reduce exposure to peak time‑of‑use electricity tariffs and to provide backup power during grid outages, while ensuring uninterrupted pumping.
AI Document Analysis Stages
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Review in progress
The information shown on this card is preliminary. Our procurement team is currently finalising the submission guidelines, evaluation criteria, technical specifications, financial requirements, and compliance sections so you have a clean, bid-ready summary to work from. Document being finalised: RFI BESS Final v1.pdf. You don’t need to refresh — this page will pick up the updated review automatically.
Important Dates
Source: RFI BESS Final v1.pdfContact Information
Source: RFI BESS Final v1.pdfBuyer Sourcing Manager – Sandisile Zulu, Tel: 011 682 0708, Email: [email protected]
Buyer Sourcing Manager – Tshepo Morare, Tel: 011 682 0708, Email: [email protected]
Submission address: Tender Box (by the main entrance), 522 Impala Road, Glenvista, 2058, South Africa.
Submission Guidelines
Source: RFI BESS Final v1.pdfTechnical Specifications
Source: RFI BESS Final v1.pdfCompliance Requirements
Source: RFI BESS Final v1.pdfNo explicit compliance requirements (e.g., CSD, tax, B‑BBEE, CIDB, CIPC, professional registrations) are stated in the RFI. Respondents should ensure standard Rand Water supplier compliance (CSD registration, tax compliance, B‑BBEE verification, CIDB registration where applicable) and be prepared to provide relevant certificates if requested during a later procurement stage.
Categories
RFI
522 Impala Road - Johannesburg - Johannesburg - 2058
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
RFI BESS Final v1.pdf
To download these documents and access AI-powered analysis, visit the main tender page.
Date & Time
Thursday, 26 February 2026 - 16:30
Venue
To follow
This briefing session took place during the tender period.
Rand Water is a Schedule 3B State Owned Entity (SOE) responsible for the abstraction,
Category: technical
treatment, and bulk supply of potable water to municipalities, industries, and mines across
Category: technical
Gauteng province mainly. The organisation operates one of the largest bulk water pumping
Category: technical
and distribution systems in the world, supplying water to an economic heartland that
Category: technical
accounts for a significant portion of South Africa’s gross domestic product.
Category: technical
The reliability and continuity of Rand Water’s pumping operations are therefore strategic to
Category: technical
national water security, economic stability, and public health. Rand Water’s pumping
Category: technical
infrastructure is highly energy-intensive, relying predominantly on large electrically driven
Category: technical
pump sets operating continuously to meet contractual demand obligations. These
Category: technical
operations are supplied through a combination of Eskom and Municipal electrical networks
Category: technical
and are subject to Time-of-Use (TOU) electricity tariffs, which impose significantly higher
Category: technical
operational costs.
Category: technical
Based on current measured data, Rand Water’s aggregated average electrical demand
Category: technical
across key pumping stations is approximately 271 MW, of which approximately 190 MW is
Category: technical
Eskom-supplied, and 81 MW is supplied through Municipal or alternative distributors. Major
Category: technical
energy-intensive stations include Zuikerbosch, Palmiet, Zwartkopjes, and Eikenhof, each
Category: technical
supporting critical bulk supply corridors within the Integrated Vaal River System.
Category: technical
In recent years, Rand Water has experienced increasing electricity cost escalation, driven
Category: technical
by:
Category: technical
• Rising Eskom tariffs under the Multi-Year Price Determination (MYPD) regime,
Category: technical
• Differential peak, standard, and off-peak tariff structures,
Category: technical
• Growing exposure to municipal electricity tariff variability, and
Category: technical
• Increasing emphasis on grid stability and demand management from electricity
Category: technical
suppliers.
Category: technical
Given the non-discretionary nature of water pumping, Rand Water has limited operational
Category: technical
flexibility to reduce or interrupt load during peak tariff windows without adversely affecting
Category: technical
water supply reliability. Consequently, Rand Water is pursuing technologies and system
Category: technical
architectures that enable energy cost optimisation without compromising pumping
Category: technical
continuity or hydraulic performance.
Category: technical
Battery Energy Storage Systems (BESS) have emerged globally as a mature and utility-
Category: technical
scale technology capable of:
Category: technical
• Shifting electrical energy consumption from peak to off-peak periods,
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
• Reducing exposure to peak electricity tariffs,
Category: technical
• Improving power quality and voltage support,
Category: technical
• Enhancing operational resilience and energy system flexibility.
Category: technical
However, the application of BESS within large-scale, mission-critical water pumping
Category: technical
systems introduces specific technical, operational, and safety considerations. These
Category: technical
include:
Category: technical
• Seamless parallel operation with grid supply,
Category: technical
• Zero-interruption pumping under all battery states of charge,
Category: technical
• Integration with high-power motors and variable speed drives,
Category: technical
• Compliance with South African grid codes and utility protection philosophies,
Category: technical
• Long-term reliability over lifecycles extending 15–20 years.
Category: technical
Rand Water has therefore issued this Request for Information (RFI) to obtain detailed
Category: technical
technical, commercial, and operational input from the market on utility-grade Battery
Category: technical
Energy Storage System solutions suitable for integration into its bulk water pumping
Category: technical
infrastructure. The information received will be used to:
Category: technical
• Assess feasible BESS architectures and deployment strategies (centralised and/or
Category: technical
distributed),
Category: technical
• Inform preliminary system sizing and configuration options,
Category: technical
• Identify risks, constraints, and enabling requirements,
Category: technical
• Support the development of a subsequent Request for Proposal (RFP) and business
Category: technical
case.
Category: technical
This RFI is not a commitment to procure, but an information-gathering exercise designed
Category: technical
to ensure that any future procurement is technically sound, commercially prudent, and
Category: technical
aligned with Rand Water’s mandate to deliver secure, sustainable, and cost-effective bulk
Category: technical
water services.
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
4. OVERVIEW OF THE REQUIREMENTS
Category: technical
4.1 Scope of Envisaged Packages/Main Activities
Category: technical
4.1.1 Envisage Package 1 – BESS for Shifting Demand from Peak to Off Peak
Category: technical
Package 1 envisages the design, supply, integration, and commissioning of a
Category: technical
grid-connected Battery Energy Storage System (BESS) configured primarily to
Category: technical
shift electrical energy demand from Eskom peak tariff periods to standard and
Category: technical
off-peak periods. The system shall operate in parallel with the existing electrical
Category: technical
supply and pumping infrastructure and be optimised to reduce Rand Water’s
Category: technical
exposure to high Time-of-Use (TOU) electricity tariffs associated with bulk water
Category: technical
pumping operations.
Category: technical
The BESS shall be engineered to discharge during defined peak tariff windows,
Category: technical
partially offsetting grid import to the pumping loads, and to charge during off-peak
Category: technical
and standard tariff periods without adversely impacting pump station operation,
Category: technical
motor performance, or power quality. Under no circumstances shall pumping be
Category: technical
interrupted or constrained due to battery charging, depletion of state-of-charge, or
Category: technical
system transitions. Seamless, automatic operation and fail-safe reversion to full
Category: technical
grid supply shall be inherent to the design.
Category: technical
This package shall include all associated power conversion equipment,
Category: technical
medium-voltage integration, automation, energy management systems (EMS),
Category: technical
protection, and balance-of-plant necessary to implement demand shifting in a
Category: technical
safe, reliable, and fully compliant manner. The proposed solution shall be scalable
Category: technical
and configurable to accommodate varying station demand profiles and shall be
Category: technical
capable of supporting long-term operation under Rand Water’s continuous
Category: technical
pumping duty cycle.
Category: technical
Important Note: Ideally Rand Water would prefer that the OEM provide this
Category: technical
system at their own capital cost, Rand Water would provide land, off-take and the
Category: technical
saving made from shifting load from peak to off-peak be shared.
Category: technical
4.1.2 Envisaged Package 2: BESS Providing Temporary Backup for Power Failures
Category: technical
Package 2 envisages the design, supply, integration, and commissioning of a
Category: technical
Battery Energy Storage System (BESS) configured to provide temporary electrical
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
backup during grid power supply interruptions, including unplanned outages,
Category: technical
network disturbances, and short-duration voltage or frequency events affecting
Category: technical
Eskom or municipal supplies.
Category: technical
The primary function of this BESS package is to maintain uninterrupted pumping
Category: technical
operations for a defined autonomies period following a loss or degradation of grid
Category: technical
supply, until normal supply is restored or auxiliary generation systems (where
Category: technical
applicable) are fully available. The BESS shall operate in an online,
Category: technical
parallel-connected configuration, capable of instantaneous response to supply
Category: technical
failure without inducing pump trips, motor protection activation, or hydraulic
Category: technical
transients.
Category: technical
The system shall include high-speed detection, automatic islanding and
Category: technical
re-synchronisation capability, and seamless transition back to grid-connected
Category: technical
operation once stable supply is restored. The BESS shall be compatible with large
Category: technical
synchronous and induction motors, variable speed drives (VSDs), and existing
Category: technical
station protection schemes. Under normal conditions, the system shall remain in
Category: technical
a standby or partial-charge state to ensure immediate availability for backup duty.
Category: technical
This package shall include all associated power conversion systems,
Category: technical
medium-voltage protection, control and automation, Energy Management System
Category: technical
(EMS) logic, safety systems, and balance-of-plant required to provide a reliable
MandatoryCategory: technical
and compliant temporary backup solution. The design shall consider defined
Category: technical
backup durations, priority load selection, black-out ride-through requirements, and
Category: technical
integration with any existing standby generation, while meeting applicable grid
Category: technical
codes, safety standards, and Rand Water operational requirements.
Category: technical
4.2 Current Electrical Load Profile (Baseline Data)
Category: technical
Respondents shall base their proposed technical solutions, system architectures, and
Category: technical
preliminary sizing assumptions on the measured average electrical demand profile
Category: technical
across Rand Water’s pumping stations, expressed as Average Megawatts (MW) per
Category: technical
month. This demand profile represents the current baseline electrical loading
Category: technical
associated with continuous bulk water pumping operations and is provided to support
Category: technical
realistic modelling of Battery Energy Storage System (BESS) demand-shifting and
Category: technical
backup-operational scenarios.
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
The demand profile includes pumping stations supplied directly by Eskom, as well as
Category: technical
stations supplied via municipal or alternative electricity distributors, as summarised
Category: technical
below.
Category: technical
Eskom-Supplied Stations
Category: technical
Station Average MW/month
Category: technical
Zuikerbosch 97.62 MW
Category: technical
Lethabo 9.89 MW
Category: technical
Zwartkopjes 27.25 MW
Category: technical
Palmiet 46.13 MW
Category: technical
BWD Pumping 9.59 MW
Category: technical
Total Eskom Supply 190.48 MW
Category: technical
Non-Eskom (Municipal) Supply
Category: technical
Station Average MW/month
Category: technical
Vereeniging – Emfuleni 26.89 MW
Category: technical
Eikenhof – City Power 35.90 MW
Category: technical
Mapleton – Ekurhuleni 13.05 MW
Category: technical
BWD Pumping – Emfuleni 1.87 MW
Category: technical
BWD Pumping – City Power 1.92 MW
Category: technical
BWD Pumping – Metsimaholo 1.28 MW
Category: technical
Total Other Supply 80.92 MW
Category: technical
The Grand Total Average Demand: 271.39 MW. These values provide an indicative
Category: technical
representation of Rand Water’s continuous electrical demand associated with bulk water
Category: technical
pumping operations and shall be used by respondents as the reference load profile for
Category: technical
evaluating BESS capacity, dispatch strategies, and system integration requirements.
Category: technical
Proposals may address station‐specific, regional, or portfolio‐wide BESS deployment
Category: technical
approaches, provided that the above demand data is clearly referenced and applied.
Category: technical
Important Note: The above electrical demand figures represent average monthly
Category: technical
consumption values and do not explicitly reflect instantaneous peak demand, transient
Category: technical
loading, or motor starting characteristics. Respondents are therefore required to clearly state,
MandatoryCategory: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
justify, and document all assumptions used in their modelling and design, particularly with
Category: technical
respect to:
Category: technical
• Peak‐to‐average load ratios
Category: technical
• Coincidence of electrical demand with Eskom Time‐of‐Use peak tariff windows
Category: technical
• Station simultaneity, operational diversity, and load aggregation factors
Category: technical
All such assumptions shall be explicitly identified in the RFI response and supported by sound
Category: technical
engineering rationale and applicable reference experience.
Category: technical
4.3 System Objective & Operational Philosophy
Category: technical
The primary objective of this initiative is the design and supply of a Battery Energy
Category: technical
Storage System (BESS) capable of partially or fully offsetting grid electricity
Category: technical
consumption during Time-of-Use peak tariff periods, while enabling effective load
Category: technical
shifting to standard and off-peak tariff periods. The BESS shall be engineered to
Category: technical
optimise Rand Water’s energy cost profile associated with bulk water pumping
Category: technical
operations, without negatively affecting operational performance, water delivery
Category: technical
obligations, or system reliability.
Category: technical
A mandatory operational constraint of the proposed system is that pumping operations
MandatoryCategory: technical
shall at no point be stopped, interrupted, or compromised because of battery charging
Category: technical
activities, full depletion of battery state-of-charge (including at 0% SOC), or any outage,
Category: technical
fault, or unavailability of the battery system. The BESS shall therefore be designed as
Category: technical
a parallel-operating system, interfacing continuously with the electrical grid and any
Category: technical
other available power sources, and shall incorporate fully automatic and seamless
Category: technical
transfer of electrical supply between sources.
Category: technical
The overall system architecture shall eliminate single points of failure and ensure that
Category: technical
no individual component failure, control transition, or protection event results in pump
Category: technical
tripping, inadvertent motor protection activation, or loss of hydraulic output. Continuous
Category: technical
pumping capability and stability of the water supply system shall take absolute
Category: technical
precedence over all energy management functions.
Category: technical
4.4 Bess Scope Of Supply
Category: technical
Respondents shall propose a fully engineered, utility-grade Battery Energy Storage
Category: technical
System (BESS) solution comprising all equipment, systems, and services required for
MandatoryCategory: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
safe, reliable, and continuous operation within Rand Water’s bulk water pumping
Category: technical
environment. The proposed solution shall be designed as an integrated system rather
Category: technical
than discrete components and shall be suitable for long-term operation under
Category: technical
continuous duty conditions typical of high-capacity pumping stations.
Category: technical
The Battery Energy Storage System shall consist of modular battery racks, containers,
Category: technical
or purpose-built buildings, arranged to allow scalability, redundancy, and
Category: technical
maintainability. Respondents shall propose appropriate battery chemistry options,
Category: technical
which may include lithium iron phosphate (LFP), nickel manganese cobalt (NMC),
Category: technical
sodium-ion, flow batteries, or equivalent proven technologies, together with clear
Category: technical
justification for suitability in terms of safety, lifecycle performance, and operating
Category: technical
conditions. The battery system shall include all necessary DC protection, isolation,
Category: technical
monitoring equipment, and a fully functional Battery Management System (BMS) to
Category: technical
ensure safe operation, fault detection, and effective life-cycle management.
Category: technical
The scope shall further include complete power conversion and electrical integration,
Category: technical
comprising grid-tied power conversion systems (PCS/inverters) suitably rated for the
Category: technical
intended duty, medium-voltage (MV) transformers, and MV switchgear with associated
Category: technical
protection systems. All cabling, busbars, earthing, and lightning protection systems
Category: technical
required for full integration shall be included. The BESS shall be synchronised with
MandatoryCategory: technical
existing MV busbars in a manner that ensures stable, parallel operation with the grid
Category: technical
and other power sources, while maintaining compliance with applicable grid codes and
Category: technical
protection philosophies.
Category: technical
An integrated automation, control, and energy management architecture shall be
Category: technical
provided. This shall include a robust Energy Management System (EMS) capable of
Category: technical
Time-of-Use (TOU)-based scheduling, peak shaving and load shifting, state-of-charge
Category: technical
management, and fail-safe and fallback logic to ensure continuous pumping under all
Category: technical
operating conditions. The system shall incorporate appropriate PLC and/or RTU
Category: technical
platforms, full SCADA integration with Rand Water’s existing control systems, and
Category: technical
facilities for secure remote monitoring and diagnostics.
Category: technical
The proposed solution shall also include all necessary balance-of-plant components,
Category: technical
including HVAC systems suitable for battery and power electronics environments, fire
Category: technical
detection and suppression systems compatible with the selected battery chemistry,
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
and all related civil works, foundations, structural enclosures, and access
Category: technical
infrastructure. Comprehensive access control, safety, and occupational health systems
Category: technical
shall be incorporated to ensure safe operation, maintenance, and compliance with
Category: technical
statutory and Rand Water safety requirements.
Category: technical
4.5 Performance & Sizing Requirements
Category: technical
Respondents shall propose Battery Energy Storage System (BESS) sizing and
Category: technical
configuration solutions based on Rand Water’s aggregate electrical demand of 271.39
Category: technical
MW across all the stations, and/or on station‐specific or regional deployment options,
Category: technical
such as a Zuikerbosch‐focused installation or clustered regional pump station
Category: technical
solutions. Proposals may address centralised, distributed, or hybrid deployment
Category: technical
strategies, provided that the approach is clearly defined and justified in relation to
Category: technical
demand profiles, operational constraints, and economic performance.
Category: technical
Each proposal shall clearly specify the rated power capacity (MW/MVA) of the BESS,
Category: technical
the usable energy capacity (MWh), and the intended duration of discharge during peak
Category: technical
tariff windows. Respondents shall further indicate the percentage of the total station
Category: technical
load or aggregate system load that the BESS is designed to supply during Eskom peak
Category: technical
periods. All sizing assumptions, diversity factors, and load allocation methodologies
Category: technical
shall be explicitly stated and supported by sound engineering principles.
Category: technical
Respondents are encouraged to submit multiple configuration options to enable
Category: technical
comparative evaluation. These may include, but are not limited to, a cost‐optimised
Category: technical
option focused on partial peak shaving, a performance‐optimised option targeting deep
Category: technical
peak avoidance and maximum tariff offset, and alternative architectures comparing
Category: technical
distributed versus centralised BESS deployment across the Rand Water network.
Category: technical
Each option shall include a brief description of its operational philosophy, benefits, and
Category: technical
limitations.
Category: technical
For the purposes of modelling and system design, respondents shall assume Eskom
Category: technical
Time‐of‐Use tariff structures that include distinct morning and evening peak periods.
Category: technical
The BESS shall be configured to discharge during these peak tariff windows and to
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
recharge during standard and off‐peak periods, in a manner that optimises energy cost
Category: technical
savings while preserving battery life and system availability. All proposed operating
Category: technical
strategies shall respect existing grid import limits, station electrical constraints, and
Category: technical
pumping operational requirements, and shall ensure continuous, uninterrupted
Category: technical
pumping at all times.
Category: technical
4.6 Reliability, Redundancy & Availability
Category: technical
The proposed Battery Energy Storage System (BESS) shall be designed to achieve a
Category: technical
minimum subsystem availability of not less than 98% on an annualised basis,
Category: technical
excluding scheduled maintenance. The system architecture shall prioritise operational
Category: technical
stability and shall ensure that transitions between operating modes, including charging,
Category: technical
discharging, standby, grid disturbances, or system faults, do not result in nuisance
Category: technical
tripping of pumps, motors, or variable speed drives (VSDs). All operating transitions
Category: technical
shall be seamless and fully coordinated with existing protection and control systems.
Category: technical
Where technically and economically justified, the design shall incorporate N+1
Category: technical
redundancy for critical components such as inverters, control systems, auxiliary power
Category: technical
supplies, cooling systems, and communications infrastructure. Respondents shall
Category: technical
clearly define the Mean Time to Repair (MTTR) for major system components and
Category: technical
describe maintenance strategies, spare‐parts philosophy, and service response
Category: technical
capabilities necessary to restore full system functionality within acceptable timeframes.
Category: technical
4.7 Power Quality & Grid Compliance
Category: technical
The BESS and all associated electrical equipment shall fully comply with the South
Category: technical
African Grid Code, Eskom interconnection requirements, and applicable NRS
Category: technical
standards, as well as any relevant municipal network codes where applicable. The
Category: technical
system shall be designed to operate within prescribed power quality limits, including
Category: technical
harmonic distortion limits in accordance with IEEE 519, applicable IEC 61000 series
Category: technical
standards, or approved local equivalents.
Category: technical
The BESS shall be capable of providing reactive power support and voltage regulation
Category: technical
at the point of connection to assist with network stability and power quality
Category: technical
management. Anti‐islanding protection shall be incorporated in accordance with utility
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
requirements, and the system shall demonstrate appropriate dynamic voltage and
Category: technical
frequency ride‐through capability to prevent undesirable disconnections during grid
Category: technical
disturbances or transient e
Category: technical
vents.
Category: technical
4.8 Safety, Environmental & Cyber Security
Category: technical
The proposed solution shall be designed and implemented in accordance with
Category: technical
internationally recognised battery safety standards, including IEC 62619, IEC 62933,
Category: technical
and, where applicable, evidence derived from UL 9540A testing or equivalent
Category: technical
fire‐propagation assessments. Fire detection and suppression systems shall be
Category: technical
specifically designed to suit the selected battery chemistry and enclosure
Category: technical
configuration, with due consideration given to thermal runaway prevention,
Category: technical
containment, and safe access for emergency response.
Category: technical
All work shall comply with the requirements of the Occupational Health and Safety Act
Category: technical
and all applicable environmental legislation, standards, and Rand Water safety
Category: technical
procedures. In addition, the BESS control, communication, and monitoring systems
Category: technical
shall incorporate appropriate cybersecurity measures aligned with IEC 62443
Category: technical
principles, including secure access control, system hardening, network segmentation,
Category: technical
monitoring, and audit functionality to protect against unauthorised access and cyber
Category: technical
threats.
Category: technical
4.9 INFORMATION REQUIRED FROM RESPONDENTS
MandatoryCategory: technical
4.9.1 Technical Submissions
Category: technical
Respondents shall submit comprehensive technical information describing the
Category: technical
proposed system solution. This shall include system architectures, single‐line
Category: technical
diagrams, and detailed descriptions of the Energy Management System (EMS)
Category: technical
control philosophy, including Time‐of‐Use (TOU) optimisation logic. Performance
Category: technical
modelling shall be provided using the 271.39 MW aggregate Rand Water electrical
Category: technical
demand baseline, together with supporting assumptions relating to load
Category: technical
distribution, diversity, and duty cycles. Respondents shall also provide battery
Category: technical
degradation, efficiency, and lifecycle modelling, as well as a description of the
Category: technical
intended approach to protection coordination studies and grid impact
Category: technical
assessments.
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
4.9.2 Commercial (ROM)
Category: technical
Respondents shall provide indicative, non‐binding Commercial information in the
Category: technical
form of Rough Order of Magnitude (ROM) estimates. This shall include preliminary
Category: technical
capital cost estimates, expected operations and maintenance costs, and projected
Category: technical
lifecycle costs. Indicative delivery, installation, and commissioning timelines shall
Category: technical
be stated, together with details of available warranty terms, performance
Category: technical
guarantees, and long‐term service and support offerings.
Category: technical
4.9.3 Experience & References
Category: technical
Respondents shall demonstrate relevant experience by providing details of at least
Category: technical
three (3) comparable utility‐scale BESS installations, preferably involving
Category: technical
high‐power industrial or critical‐infrastructure applications. Information on local
Category: technical
presence, technical support capabilities, and the ability to provide ongoing
Category: technical
operational and maintenance support within South Africa shall be included.
Category: technical
4.10 Key Emphasis for RFI Responses
Category: technical
In submitting RFI responses, respondents shall explicitly demonstrate how the
Category: technical
proposed BESS solution reduces Rand Water’s exposure to Eskom peak tariff
Category: technical
charges while ensuring that continuous pumping operations are preserved
Category: technical
under all conditions. Proposals shall further describe how the solution can be
Category: technical
scaled, replicated, or phased across Rand Water’s pump station portfolio, and
Category: technical
how technical, safety, and commercial risks are managed over the system
Category: technical
lifecycle. Respondents shall clearly indicate how the proposed solution remains
Category: technical
compliant, safe, and economically viable over an anticipated operating life of
Category: technical
15 to 20 years.
Category: technical
Rand Water further records that this RFI is not intended to restrict, limit or pre-
Category: technical
determine competition in any future procurement process. Information obtained
Category: technical
through this RFI will be used solely to inform internal planning, strategy
Category: technical
development, governance decision-making and the design of potential future
Category: technical
procurement processes.
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
Any future concession, energy trading, wheeling, asset development or asset
Category: technical
transfer arrangement will be subject to detailed feasibility assessments, value-
Category: technical
for-money analysis, legal and regulatory due diligence, and approval by Rand
Category: technical
Water.
Category: technical
Respondents are advised that any future implementation involving electricity
Category: technical
generation, energy storage, demand-side management, trading, wheeling or
Category: technical
grid-connected services may require approvals, registrations or licences from
Category: technical
the National Energy Regulator of South Africa (NERSA), Eskom, municipal
Category: technical
distributors and/or other regulatory authorities.
Category: technical
Rand Water makes no representation regarding the availability, timing or
Category: technical
certainty of such approvals. Any future procurement or implementation will be
Category: technical
conditional upon the successful attainment of all required regulatory consents.
MandatoryCategory: technical
5. PROFESSIONAL REQUIREMENTS INDEMNITY
Category: technical
Respondents must confirm that they maintain in-force, claims-made Professional Indemnity
MandatoryCategory: technical
(PI) insurance appropriate to energy trading/advisory services, with adequate limits,
Category: technical
suitable territorial/jurisdictional scope, no exclusions for core trading advisory/settlement
Category: technical
support, an unlimited or appropriate retroactive date, and a minimum 24-month run-off after
Category: technical
expiry. A broker/insurer letter confirming current cover, limits, retro date, main exclusions
Category: technical
and deductible(s), together with a 5-year loss history declaration, should accompany RFI
Category: technical
submissions. Final requirements will be confirmed at RFP/award stage and may include
Category: technical
additional insurances (e.g., Public Liability, Cyber).
Category: technical
Rand Water reserves the right to verify the validity, scope and adequacy of all insurance
Category: technical
cover submitted and to require additional insurance cover at a later stage, should a formal
Category: technical
procurement process be initiated.
Category: technical
6. MINIMUM SUBMISSION REQUIREMENTS
Category: technical
In addition to the above the expert consultant is required to provide RAND WATER
MandatoryCategory: technical
with the following:
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
• Respondents are requested to submit a comprehensive written response
Category: technical
to this Request for Information, addressing all sections and information
Category: technical
requirements outlined in the RFI.
Category: technical
• The response should be supported by relevant capability statements that
Category: technical
demonstrate the respondent’s experience, technical competence and
Category: technical
organisational capacity to provide energy trading services of a nature and
Category: technical
scale relevant to Rand Water.
Category: technical
• Respondents are encouraged to include illustrative non-confidential case
Category: technical
studies that highlight prior experience, operational approaches or
Category: technical
outcomes achieved for comparable clients, provided that such case
Category: technical
studies do not disclose commercially sensitive or client-identifying
Category: technical
information.
Category: technical
• In addition, respondents should complete and submit any compliance
Category: technical
checklists or questionnaires included as part of the RFI documentation, to
Category: technical
facilitate a consistent and efficient assessment of responses.
Category: technical
• Respondents must submit a signed declaration confirming the absence of
MandatoryCategory: technical
any actual, potential or perceived conflicts of interest in relation to this RFI
Category: technical
or any potential future engagement with Rand Water.
Category: technical
7. COST OF REQUEST FOR INFORMATION
Category: technical
Respondents are expected to fully acquaint themselves with the conditions,
Category: technical
requirements, and specifications of this RFI before submitting responses. Each
Category: technical
Respondent assumes all risks for resource commitment and expenses, direct or
Category: technical
indirect, of RFI preparation and participation throughout the RFI process. RAND
Category: technical
WATER is not responsible, directly, or indirectly, for any costs incurred by service
Category: technical
providers.
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
8. TERMS AND CONDITIONS
Category: technical
Respondents shall sign a Non-Disclosure Agreement (NDA) with RAND WATER so that they
Category: technical
can have access to additional information for this RFI.
Category: technical
RAND WATER reserves the right to.
Category: technical
✓ Verify any information contained in a response.
Category: technical
✓ Postpone, withdraw, amend, modify, or cancel the RFI process at any time,
Category: technical
without prior notice and without liability to compensate or reimburse any person
Category: technical
pursuant to such.
Category: technical
8.1 Submission of RFI Responses
Category: technical
▪ To facilitate the preparation of the RFI Response, Respondents may access the
Category: technical
following website where the Document can be downloaded:
Category: technical
https://www.randwater.co.za/availabletenders.php/.
Category: technical
▪ The RFI Response, must be submitted to RAND WATER before or on closing date
MandatoryCategory: technical
and time at the following address: Tender Box (by the main entrance), 522 Impala
Category: technical
Road, Glenvista by not later than the time and date of 16:30 on 26 February 2026.
Category: technical
▪ RFI Responses reaching RAND WATER later than the cut-off time and date
Category: technical
specified above may, in the RAND WATER’s sole discretion, be rejected without
Category: technical
further consideration.
Category: technical
▪ RFI Responses may be submitted prior to the cut-off time and date specified
Category: technical
above, however only complete RFI Responses will receive attention from the
Category: technical
RAND WATER.
Category: technical
▪ All costs incurred by a Respondent in connection with this Document and the
Category: technical
preparation of its RFI Responses shall be borne by the Respondent.
Category: technical
▪ Responses submitted by companies must be signed by a person or persons duly
MandatoryCategory: technical
authorised thereto in a form of a resolution so passed by the appropriate governing
Category: technical
structure or letter of Delegation by an authorised Official of such Company.
Category: technical
8.2 Language of the RFI Response
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
▪ The RFI Response and all documents forming part of it shall be in English.
Category: technical
▪ Any printed literature submitted with the RFI Response may be in another
Category: technical
language so long as it is accompanied by an English translation (made by an
Category: technical
accredited translator) of the entire document.
Category: technical
▪ All correspondence and any other documentation and oral communication
Category: technical
exchanged between the Respondent and the organisation shall be in English.
Category: technical
8.3 Further Information
Category: technical
▪ RAND WATER reserves the right to seek additional information from the
Category: technical
Respondent regarding its RFI Response, as it may, in its sole discretion,
Category: technical
determine, whether such information has been requested under this Document or
Category: technical
otherwise, and may require the Respondent to make oral presentations for
Category: technical
clarification purposes or to present supplementary information, in respect of its
Category: technical
RFI Response if so, required by the RAND WATER.
MandatoryCategory: technical
▪ The Respondent may, following the submission of a RFI Response, be requested
Category: technical
to engage with RAND WATER. Any meetings are likely to take place at RAND
Category: technical
WATER offices, which is at the following address: 522 Impala Road, Glenvista
Category: technical
2058, South Africa.
Category: technical
8.4 Contact with the Supply Chain Office
Category: technical
▪ All queries and requests for clarification in respect of this Document must be
MandatoryCategory: technical
addressed to the Supply Chain Office of Rand Water. E-mailed or oral requests
Category: technical
and queries addressed to persons other than a Supply Chain Official, at the
Category: technical
address, will not be entertained and will not receive a response. RAND WATER
Category: technical
will endeavour, in good faith, to respond to all reasonable written queries and
Category: technical
requests for clarification raised by the Respondent Rand Water will provide a final
Category: technical
response on clarifications by no later than ten (10) calendar days before the
Category: technical
closing date.
Category: technical
▪ The Respondent must give the name and contact details of the person whom it
MandatoryCategory: technical
appoints to undertake all contact with the SCM Office in its RFI Response.
Category: technical
▪ After the submission of its RFI Response, the Respondent may only communicate
Category: technical
with RAND WATER through such person and RAND WATER shall be entitled, at
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
its sole discretion, to disregard any communication from the Respondent, that
Category: technical
does not come from such contact person, and that does not go directly to the
Category: technical
Supply Chain Office.
Category: technical
8.5 Compliance, Ethics and Market Conduct
Category: technical
▪ Respondents warrant that their submissions are prepared independently and
Category: technical
without collusion, consultation, coordination or agreement with any other
Category: technical
respondent. Any conduct that may constitute collusive behaviour, anti-competitive
Category: technical
practices or market manipulation may result in exclusion from future procurement
Category: technical
processes and referral to the appropriate regulatory authorities.
Category: technical
▪ Respondents must comply with all applicable legislation, including the Protection
MandatoryCategory: technical
of Personal Information Act (POPIA), and confirm that any information submitted
Category: technical
has been lawfully obtained and may be shared with Rand Water for the purposes
Category: technical
of this RFI.
Category: technical
▪ Respondents acknowledge that Rand Water is a responsible party under POPIA
Category: technical
and confirm that any personal information submitted is limited to what is necessary
Category: technical
for the purposes of this RFI, has been lawfully obtained, and may be processed,
Category: technical
stored and retained by Rand Water in accordance with its information governance
Category: technical
policies.
Category: technical
8.6 Competition Law and Fair Market Conduct
Category: technical
▪ Respondents must comply with the Competition Act, 1998 (as amended), and
MandatoryCategory: technical
warrant that their participation in this RFI does not involve any form of collusion,
Category: technical
bid-rigging, price-fixing, market allocation, or exchange of competitively sensitive
Category: technical
information with any actual or potential competitor.
Category: technical
▪ Rand Water reserves the right to disqualify any respondent and to report any
Category: technical
suspected anti-competitive conduct to the Competition Commission of South
Category: technical
Africa.
Category: technical
8.7 Intellectual Property and Use of Information
Category: technical
▪ All intellectual property rights in pre-existing proprietary methodologies,
Category: technical
technologies, software and designs submitted by respondents shall remain vested
Category: technical
in the respondent.
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
▪ By submitting a response to this RFI, respondents grant Rand Water a royalty-
Category: technical
free, irrevocable, non-exclusive right to use, reproduce and analyse the
Category: technical
information contained in the submission for internal evaluation, planning,
Category: technical
governance and procurement development purposes.
Category: technical
▪ Rand Water shall not be restricted from developing its own specifications or
Category: technical
procuring similar solutions from third parties, provided that it does not unlawfully
Category: technical
disclose confidential proprietary information.
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
ANNEXURE A: CHECKLIST
Category: technical
This checklist is provided for information-gathering purposes only and does not constitute
Category: technical
evaluation criteria, minimum eligibility requirements or scoring mechanisms for any future
Category: technical
procurement process.
Category: technical
A. GENERAL SUBMISSION INFORMATION
Category: technical
☐ Company name and legal entity
Category: technical
☐ Company registration number and country of registration
Category: technical
☐ Physical and postal address
Category: technical
☐ Primary contact person (name, designation, email, telephone)
Category: technical
☐ Local South African presence (office, partners, service capability)
Category: technical
☐ BBBEE status level (if applicable)
Category: technical
☐ Declaration of interest and conflict of interest statement
Category: technical
B. PROPOSED SOLUTION OVERVIEW
Category: technical
☐ Executive summary of proposed BESS solution
Category: technical
☐ Description of proposed system architecture (centralised, distributed, or hybrid)
Category: technical
☐ Stations or regions addressed (aggregate/system-wide or station-specific)
Category: technical
☐ Alignment with RFI Packages:
Category: technical
☐ Package 1 – Peak to Off‐Peak Demand Shifting
Category: technical
☐ Package 2 – Temporary Backup During Power Failure
Category: technical
☐ Key assumptions and exclusions clearly stated
Category: technical
C. TECHNICAL COMPLIANCE & DESIGN
Category: technical
C1. Battery Energy Storage System
Category: technical
☐ Battery technology and chemistry proposed
Category: technical
☐ Battery configuration (racks, containers, buildings)
Category: technical
☐ Battery Management System (BMS) description
Category: technical
☐ DC protection, isolation, and monitoring approach
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
☐ Battery safety certifications (IEC 62619, IEC 62933, UL 9540A evidence)
Category: technical
C2. Power Conversion & Electrical Integration
Category: technical
☐ PCS/inverter ratings and configuration
Category: technical
☐ MV transformer specifications
Category: technical
☐ MV switchgear and protection philosophy
Category: technical
☐ Synchronisation approach with existing MV busbars
Category: technical
☐ Earthing, lightning protection, and cabling strategy
Category: technical
C3. Automation, Controls & EMS
Category: technical
☐ EMS control philosophy and operational modes
Category: technical
☐ TOU optimisation and scheduling logic
Category: technical
☐ Peak shaving and load shifting strategy
Category: technical
☐ SOC management and fail‐safe logic
Category: technical
☐ PLC/RTU architecture
Category: technical
☐ SCADA integration approach (protocols and signals)
Category: technical
☐ Remote monitoring and diagnostics capability
Category: technical
D. BESS SIZING & PERFORMANCE
Category: technical
☐ BESS sizing based on the 271.39 MW baseline clearly demonstrated
Category: technical
☐ Rated power capacity (MW and/or MVA) stated
Category: technical
☐ Usable energy capacity (MWh) stated
Category: technical
☐ Duration of peak‐period discharge defined
Category: technical
☐ Percentage of station/system load supplied during peak periods
Category: technical
☐ Multiple configuration options submitted (if applicable):
Category: technical
☐ Cost‐optimised option
Category: technical
☐ Performance‐optimised option
Category: technical
☐ Distributed vs centralised option
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
☐ Justification of peak‐to‐average assumptions
Category: technical
☐ Coincidence and diversity factors stated
Category: technical
E. RELIABILITY, AVAILABILITY & REDUNDANCY
Category: technical
☐ Availability target ≥98% stated
Category: technical
☐ Redundancy philosophy (N+1 or equivalent) defined
Category: technical
☐ No‐trip, bumpless transition strategy described
Category: technical
☐ Mean Time to Repair (MTTR) defined
Category: technical
☐ Maintenance philosophy and spare‐parts strategy
Category: technical
F. POWER QUALITY & GRID COMPLIANCE
Category: technical
☐ Compliance with South African Grid Code confirmed
Category: technical
☐ Compliance with Eskom and relevant municipal requirements confirmed
Category: technical
☐ Harmonic distortion compliance (IEEE 519 / IEC) demonstrated
Category: technical
☐ Reactive power and voltage support capability stated
Category: technical
☐ Anti‐islanding protection described
Category: technical
☐ Voltage and frequency ride‐through capability described
Category: technical
G. SAFETY, ENVIRONMENTAL & CYBER SECURITY
Category: technical
☐ Fire detection and suppression system design provided
Category: technical
☐ Environmental and thermal management strategy provided
Category: technical
☐ OHSA compliance confirmation
Category: technical
☐ Cybersecurity approach aligned with IEC 62443 principles
Category: technical
☐ Secure access, monitoring, and audit functionality
Category: technical
H. PERFORMANCE MODELLING & STUDIES
Category: technical
☐ Load and energy modelling provided
Category: technical
☐ TOU optimisation modelling results included
Category: technical
☐ Battery degradation and lifecycle performance modelling (15–20 years)
Category: technical
☐ Round‐trip efficiency stated
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
Form No: RW SCM 00073 F REQUEST FOR INFORMATION
Category: technical
Revision No: 01
Category: technical
Effective Date: 01 Jan 2026
Category: technical
☐ Grid impact and protection study approach outlined
Category: technical
I. COMMERCIAL INFORMATION (ROM)
Category: technical
☐ Capital cost estimate (ROM)
Category: technical
☐ Operations and maintenance cost estimate
Category: technical
☐ Lifecycle cost assumptions
Category: technical
☐ Delivery, installation, and commissioning timeline
Category: technical
☐ Warranty terms (equipment and performance)
Category: technical
☐ Long‐term service and support offerings
Category: technical
J. EXPERIENCE & REFERENCES
Category: technical
☐ At least three (3) comparable utility‐scale BESS references provided
Category: technical
☐ Reference project size, application, and year of commissioning stated
Category: technical
☐ Client contact details provided
Category: technical
☐ Local execution and support capability demonstrated
Category: technical
K. RISK & ASSUMPTIONS
Category: technical
☐ Key technical risks identified
Category: technical
☐ Mitigation strategies described
Category: technical
☐ Commercial and programme risks identified
Category: technical
☐ Clear listing of assumptions and exclusions
Category: technical
L. DECLARATION
Category: technical
☐ Confirmation that the submission is non‐binding
Category: technical
☐ Acknowledgement that this is an RFI and not a commitment to procure
Category: technical
☐ Authorised signatory and date
Category: technical
RW SCM 00073 F Rev No: 01 of 26
Category: technical
No specific requirements found
MandatoryCategory: compliance
04 Feb
2026
Tender Published
Tender was published
26 Feb
2026
Closing Date
Tender closing date
Pending
Awaiting Award of Contract
This tender has not yet been awarded. The contracting authority is expected to publish the award notice in due course.
26 Feb
2026
Submissions Closed
No further submissions were accepted after this date.
Organization
Rand WaterRand Water is the largest water utility in Africa, supplying bulk potable water to Gauteng and surrounding regions.
Contact Person
Sandisile Zulu
Phone
011-682-0708
Rand Water is the largest water utility in Africa, supplying bulk potable water to Gauteng and surrounding regions.
Matched by category & region
Learn how to submit a winning bid with these related articles
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 38 of 2000
Important for public-sector construction and infrastructure tenders that require contractor grading or construction procurement standards.
Relevant because this tender appears to involve engineering, technical design, maintenance, or regulated built-environment work.
Act 85 of 1993
Sets health and safety duties for contractors, employers and service providers working on public-sector sites.
Relevant because this tender appears to involve engineering, technical design, maintenance, or regulated built-environment work.
Act 46 of 2000
Relevant where professional engineering services or regulated engineering work may be required.
Relevant because this tender appears to involve engineering, technical design, maintenance, or regulated built-environment work.
Address
522 Impala Rd, Dikole Section, Johannesburg South, 2058, South Africa
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
1
Last checked
05 Jun 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Contact
011-682-0708[email protected]www.randwater.co.za522 Impala Rd, Dikole Section, Johannesburg South, 2058, South Africa
Key Personnel
Provinces Active
Industries
💡 Want more tendering tips and strategies?
Explore Our BlogMedian Estimate
R 5 821 875
Range
Based on CIDB grading. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.