Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
Cape Town International Airport Southern Office Block Building - Airport Industria - Cape Town - 7490
Organization Type
GOVERNMENT
Published
19 Aug 2026
OCDS Reference
ocds-9t57fa-166159
Airports company south africa seeks a contractor for a 60-month term service contract to maintain airside and landside pavements at cape town international airport under nec3 option a (priced activity schedule). The single most consequential requirement is the mandatory annual submission of a compliant b-bbee certificate; failure constitutes a material breach allowing contract cancellation.
Closing date and time: 2026-10-01 14:00 (per tender record; not in this document volume).
Submission method and address: not stated in this volume; full tender pack must be consulted.
Mandatory returnable documents: Form of Offer and Acceptance (C1.1), Contract Data Parts C1.2a (Employer) and C1.2b (Contractor with key personnel CVs), Occupational Health and Safety Agreement (C1.3, OHS 040), Pricing Data (Part C2), Annexure C (low service damages), Annexure D (S37(2) appointment), and likely standard forms SBD 4, SBD 6.1, SBD 8, SBD 9, and Authority to Sign / Board Resolution.
Eligibility thresholds: annual compliant B-BBEE certificate (Z18.1) — failure is a material breach; CSD registration and valid SARS tax clearance/tax pin (standard government practice, not explicit in this volume); CIDB grading not specified in this volume — bidder must verify from full tender pack; CIPC registration; compliance with OHS Act, Construction Regulations 2014, and COID Act.
Key personnel: CVs required for Contract Manager, Supervisor/Technician, and Health & Safety Officer; full-time dedicated H&S resource mandatory for projects with 5+ people on site.
Pricing and payment: NEC3 Option A Priced Activity Schedule (Price List in Part C2); Price Adjustment per Option X1; assessment interval 15th of each month; payment within 4 weeks; currency ZAR; interest at Nedbank prime rate.
Insurance and securities: Contractor provides insurance per Insurance Clauses in joint names covering Contractor's risks from starting date until Defects Certificate; minimum indemnity for employee injury/death as prescribed by COID Act; performance bond/guarantee requirements not stated in this volume.
Contract duration and dates: 60 months from starting date (date of contract signing by ACSA); defects date 12 months after Completion; revised programmes every 2 weeks; compensation event notification 4 weeks; Service Manager requires Employer written consent for scope/design changes ≥10% or completion extensions >30 days.
Continue with tenders sharing this issuer, category, or province.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Thursday, 01 October 2026 - 14:00
Venue
Cape Town International Airport Southern Office Block Building Ground floor Reception area
Important: Attendance at this briefing session is mandatory. Bids from suppliers who do not attend may be disqualified.
Refer to bid document
Categories
Request for Bid(Open-Tender)
Cape Town International Airport Southern Office Block Building - Airport Industria - Cape Town - 7490
AI Document Analysis Stages
Review in progress
The information shown on this card is preliminary. Our procurement team is currently finalising the submission guidelines, evaluation criteria, technical specifications, financial requirements, and compliance sections so you have a clean, bid-ready summary to work from. Document being finalised: 1. CIA RFP 7897-2025 Bid Document.pdf. You don’t need to refresh — this page will pick up the updated review automatically.
19 Aug
2026
Tender Published
Tender was published
01 Oct
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
1. CIA RFP 7897-2025 Bid Document.pdf
The Airports Company of South Africa is procuring a 60-month term contract for the maintenance of airside and landside pavements at Cape Town International Airport. The contract includes the maintenance of runways, taxiways, aprons, and other areas.
2. CIA RFP 7897-2025 NEC 3 Contract.pdf
A 60-month term service contract for the maintenance of airside and landside pavements at Cape Town International Airport, using the NEC3 Term Service Contract (Option A: Priced contract with Activity Schedule). The contract is issued by the Airports Company of South Africa (ACSA) and covers routine and reactive pavement works within the airport's landside and airside precincts.
To download these documents and access AI-powered analysis, visit the main tender page.
Organization
Airports Company South Africa (ACSA)Contact Person
Mogammad Kamaal Allom
Phone
011-723-1400
Win ACSA tenders with AI Matching Engine, airport-infrastructure intelligence, compliance analysis, and application support for aviation operations.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubLearn how to submit a winning bid with these related articles
Median Estimate
R 2 992 000
Range
Based on SITA benchmarks. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Important Dates
Source: 1. CIA RFP 7897-2025 Bid Document.pdf (RFQ)Issue date: 20 August 2026
Compulsory briefing session: 9 September 2026 at 10:30 (attendance register must be signed; only entities on the register receive addenda and may submit tenders)
Closing date for queries: 16 September 2026 at 15:00
Tender closing date and time: 1 October 2026 at 14:00
Public opening of tenders: 5 October 2026 at 12:00
Tender validity period: 12 weeks (84 days) from closing date
Contact Information
Source: 1. CIA RFP 7897-2025 Bid Document.pdf (RFQ)SCM / Procurement enquiries: Kamaal Allom, email [email protected], telephone 021 937 1368
Technical enquiries: same contact (Kamaal Allom)
All communication during tender period must be directed to ACSA Supply Chain Department via the above email
Submission address: Tender box, Cape Town International Airport, Southern Office Block Building, Ground floor reception area, Procurement Office
Submission Guidelines
Source: 1. CIA RFP 7897-2025 Bid Document.pdf (RFQ)Submission method: one original and one copy in printed format, plus an electronic copy on USB flash drive, all sealed in separate packages marked "ORIGINAL" and "COPY" with the tenderer's name, contact details, tender reference CIA7897/2025/RFP and tender description. Deliver to the tender box at Cape Town International Airport, Southern Office Block Building, Ground floor reception area, Procurement Office during working hours Monday to Friday. Complete the Bid Deposit Register when depositing. Late bids will not be accepted. Telegraphic, telephonic, telex, facsimile and e-mailed tenders are not accepted. All returnable documents must be completed in full and signed in non-erasable ink. The Form of Offer and Acceptance (NEC C1.1) must be completed and signed. Authority to sign (board resolution) must be submitted.
Evaluation Criteria
Source: 1. CIA RFP 7897-2025 Bid Document.pdf (RFQ)Four-stage evaluation:
Stage 1 – Responsiveness test: compliance with conditions of tender, fully completed and signed, responsive to all requirements.
Stage 2 – Mandatory administration criteria: (a) CIDB contractor grading 5CE or higher, valid and active; (b) attendance at compulsory site briefing with signed attendance register; (c) complete and correct submission of NEC C1.1 Form of Offer and Acceptance.
Stage 3 – Functionality evaluation (minimum 68/100 points to proceed):
Stage 4 – Price and Preference (80/20 PPPFA): 80 points for price (formula Ps = 80(1-(Pt-Pmin)/Pmin)), 20 points for specific goals. Specific goals: B-BBEE status level (Level 1 = 5, Level 2 = 4.5, Level 3 = 4, Level 4 = 3, Level 5 = 2, Level 6 = 0.5, Level 7 = 0.3, Level 8 = 0.1, non-compliant = 0); black youth majority-owned = 5; black women majority-owned = 5; majority owned by people with disabilities = 5. Proof required: original or certified copy of valid sworn affidavit or SANAS-accredited B-BBEE certificate; JV requires consolidated SANAS certificate.
Technical Specifications
Source: 1. CIA RFP 7897-2025 Bid Document.pdf (RFQ)Scope: five-year term service contract for maintenance and repairs of airside and landside pavements at Cape Town International Airport.
Airside: runways, taxiways, aprons, all service roads – address all concrete and asphalt pavement deformations, planned and unplanned maintenance.
Landside: all roads, car rental facilities, parking areas including long-stay parking.
Contractor must effectively address reinforced concrete and flexible (asphalt) pavement maintenance.
Required plant and equipment: asphalt milling machine, paver, pneumatic roller (16t), steel roller (6.5-13t), dump truck, painting equipment, bakkies.
Equipment age limits: vehicles ≤7 years, non-motorised ≤10 years, specialised motor ≤12 years.
Key personnel: Contracts Manager (min 9 years experience, BSc/BTech Civil Engineering NQF 7), Site Foreman/Supervisor (min 6 years experience, National Diploma NQF 6), Health & Safety Officer (min 4 years experience, National Diploma in Safety/Environmental Management or SAMTRAC).
Emergency and holiday work commitment required.
All rates and prices fixed for the full 60-month contract duration (no contract price adjustments, foreign fluctuations).
Financial Requirements
Source: 1. CIA RFP 7897-2025 Bid Document.pdf (RFQ)Pricing: fixed rates and prices for the full 60-month contract duration; no contract price adjustments, foreign fluctuations or escalation. VAT shown separately. Rates and prices in Rand. Pricing schedules/activity schedules to be completed (Part C2).
Securities, bonds, guarantees, policies and certificates of insurance required as per contract data (Appendix 3: Insurance Requirements) – to be submitted for employer's acceptance before contract formation.
Tender validity: 12 weeks (84 days).
No cost of tendering reimbursement.
Compliance Requirements
Source: 1. CIA RFP 7897-2025 Bid Document.pdf (RFQ)Mandatory:
Description
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdfTerm service contract for Maintenance of Airside & Landside Pavements works at Cape Town International Airport (CTIA): 60-month term contract. Tender No: CIA RFQ 7897-2025. Project Number: CIA RFQ 7896-2025. Employer: Airports Company South Africa SOC Limited (Reg: 1993/004149/30), applicable at CTIA, 3rd Floor ACSA Southern Office Block, CTIA 7525. Service Manager: Senior Civil Technician, same address, Tel: 021 937 1200. Works: Maintenance of Airside & Landside pavements as detailed in Scope of Work Part C3. Risk Register includes: Availability of As-Built information, Access to Site, Statutory approvals and ACSA approvals, Site Constraints and Constructability, Notification of Claims, Financial and Procurement. Service Information in Part C3. Site Information in Part C4. Site boundary: CTIA Landside and Airside Precinct. Working areas: CTIA Landside and Airside Precinct.
Important Dates
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdf (RFQ)Closing date and time: not stated in this document volume (tender record indicates 2026-10-01T14:00:00Z). Mandatory briefing or site visit: not stated in this volume. Contract start date: on signing of the contract by ACSA (Clause 30.1). Contract duration: 60 months from starting date (Clause 30.2). Defects date: 12 months after Completion of the whole works (Clause 42.2). Assessment interval: 15th day of each successive month (Clause 50.1). Payment period: 4 weeks (Clause 51.2). Contractor submits revised programmes at intervals no longer than 2 weeks (Clause 32.2). Compensation event notification period: 4 weeks (Z17.1). Task Order programme submission period: as stated in Contract Data (X19.5).
Contact Information
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdf (RFQ)Employer: Airports Company South Africa SOC Limited, 3rd Floor ACSA Southern Office Block, Cape Town International Airport, 7525. Service Manager: Senior Civil Technician, same address, Telephone: 021 937 1200, E-mail: TBC. Adjudicator panel: Adv. Ghandi Badela (+27 11 282 3700, [email protected]), Mr. Errol Tate Pr. Eng. (+27 11 262 4001, [email protected]), Adv. Saleem Ebrahim (+27 11 535-1800, [email protected]), Mr. Sebe Msutwana Pr. Eng. (+27 11 442 8555, [email protected]), Mr. Sam Amod ([email protected]), Adv. Sias Ryneke SC (083 653 2281, [email protected]), Mr. Emeka Ogbugo (+27 12 349 2027, [email protected]). Adjudicator nominating body: Chairman of Johannesburg Advocate's Bar Council. Arbitrator panel: same contacts. Arbitration place: Johannesburg, South Africa. Arbitration rules: Rules for the Conduct of Arbitrations 2013 Edition, 7th Edition, Association of Arbitrators (Southern Africa).
Submission Guidelines
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdf (RFQ)Submission method and address are not stated in the provided document. The Form of Offer and Acceptance (Part C1.1) must be completed, signed and returned with the Schedule of Deviations (if any). The following returnable documents are required: Form of Offer and Acceptance (Part C1.1), Contract Data Part C1.2a (Employer's data) and Part C1.2b (Contractor's data including key personnel CVs), Occupational Health and Safety Agreement (Part C1.3, OHS 040), Pricing Data (Part C2), and any Annexures referenced (Annexure C for low service damages, Annexure D for S37(2) appointment). Standard National Treasury forms likely required but not explicitly listed in this volume: SBD 4 (Declaration of Interest), SBD 6.1 (Preference Points Claim), SBD 8 (Declaration of Past SCM Practices), SBD 9 (Certificate of Independent Bid Determination), and Authority to Sign / Board Resolution. All returnable schedules must be fully completed and signed. Disqualification risks: unsigned or omitted returnable forms; late submission (closing time not specified in this volume).
Evaluation Criteria
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdf (RFQ)Evaluation methodology, scoring split (price vs functionality), minimum qualifying thresholds, and preference point system (80/20 or 90/10) are not stated in the provided document. The contract uses NEC3 Term Service Contract with Main Option A (Priced contract with Activity Schedule). Mandatory eligibility requirements inferred from contract clauses: annual submission of a compliant B-BBEE certificate (Z18.1) — failure is a material breach; registration on the National Treasury Central Supplier Database (CSD) and valid SARS tax clearance (standard government practice, not explicitly stated in this volume); CIDB grading not stated in this volume — bidders must verify from full tender pack. Key personnel CVs required for Contract Manager, Supervisor/Technician, and Health & Safety Officer. Compliance with OHS Act, Construction Regulations 2014, and COID Act is mandatory. No functionality scoring criteria or weightings are disclosed in this volume.
Technical Specifications
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdf (RFQ)Scope: Maintenance of Airside & Landside pavements works at Cape Town International Airport (CTIA) for a 60-month term contract. Works fully detailed in Scope of Work Part C3 (Service Information) and Site Information Part C4. Site boundary: CTIA Landside and Airside Precinct. Working areas: CTIA Landside and Airside Precinct. Risk Register items: Availability of As-Built information, Access to Site, Statutory approvals and ACSA approvals, Site Constraints and Constructability, Notification of Claims, Financial and Procurement. Task Order process: Service Manager issues Task Order with detailed work description, priced list of items from Price List, start/completion dates, delay damages, total prices. Contractor submits Task Order programme for acceptance within stated period; no work starts until instructed; no Task Order issued after service period end. Contractor submits revised programmes at intervals no longer than 2 weeks. Compensation event notification reduced to 4 weeks. Service Manager requires Employer written consent for design/scope/Works changes ≥10% or Completion Date extension >30 days. Measurement and payment per COTO Standard Specification for Road and Bridge Works for State Authorities, 2020 edition, as amended in Scope of Works. Units of measurement: metric (%, h, ha, km, m, m2, m3, No., Prov sum, PC Sum, R/only, sum, t, W/day). Definitions: Unit, Quantity, Rate, Amount, Lump Sum, Provisional Sum, Prime Cost Sum, hr (60 minutes), Day (9 hours).
Methodology
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdf (RFQ)Task Order process: Service Manager issues Task Order with detailed work description, priced list, start/completion dates, delay damages, total prices. Contractor submits Task Order programme for acceptance within stated period. Contractor does not start Task work until instructed. No Task Order issued after service period end. Contractor submits revised programmes at intervals no longer than 2 weeks. Compensation event notification: 4 weeks (reduced from 8 weeks). Service Manager requires Employer written consent for design/scope/Works changes ≥10% or Completion Date extension >30 days. Measurement and payment per COTO Standard Specification for Road and Bridge Works for State Authorities, 2020 edition, as amended in Scope of Works.
Experience & Qualifications
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdfContractor's Key People required: CVs to be appended to Tender Schedule. Positions: Contract Manager, Supervisor/Technician, Health & Safety Officer. For each: Name, Job Title, Responsibility, Qualifications, Experience. Full-time dedicated Health & Safety resource required for projects with 5+ people, based on site for duration. Competent persons appointed per Section 16(2) OHS Act with relevant training. All employees trained on health and safety aspects and hazards; operators of materials/machinery/equipment properly trained.
Quality Management
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdfDisallowed Cost definition (Z2.2) includes: costs not justified by accounts/records; costs not payable to Subcontractor/supplier per their contract; costs incurred due to Contractor not following acceptance/procurement procedures in Service Information, not complying with quality plan procedures, not giving required early warning; costs of correcting Defects after Completion; Defects from non-compliance with Service Information constraints; Defects from lack of reasonable skill/care/diligence in Equipment design; Defects from non-compliance with quality plan; previously corrected Defects; unused Plant/Materials (after reasonable wastage); unused resources (after reasonable availability/utilisation); adjudication/tribunal preparation and conduct costs. Contractor warrants Services results fit for intended purpose (Z4). Quality plan compliance is a condition for cost allowance.
Pricing Schedule
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdfPricing per Part C2 Pricing Data. Price list as detailed in Part C2. Contractor prepares forecasts of final total Prices at intervals no longer than 2 weeks. Price Adjustment per Option X1: Base Date Index (B) latest available before base date; Latest Index (L) latest available before assessment date; Price Adjustment Factor = sum of proportions × (L-B)/B for each index. Price adjustment included in each amount due. Low service damages per Annexure C. Task Order includes priced list of items from Price List, delay damages, total Prices for Task. Units of measurement: metric (%, h, ha, km, m, m2, m3, No., Prov sum, PC Sum, R/only, sum, t, W/day). Definitions: Unit, Quantity, Rate, Amount, Lump Sum, Provisional Sum, Prime Cost Sum, hr (60 minutes), Day (9 hours). Measurement and payment per COTO Standard Specification for Road and Bridge Works for State Authorities, 2020 edition, as amended in Scope of Works.
Financial Requirements
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdf (RFQ)Pricing: NEC3 TSC Option A — Priced contract with Activity Schedule (Price List). Price List as detailed in Part C2 Pricing Data. Contractor prepares forecasts of final total Prices at intervals no longer than 2 weeks. Price Adjustment per Option X1: Base Date Index (B) latest available before base date; Latest Index (L) latest available before assessment date; Price Adjustment Factor = sum of proportions × (L-B)/B for each index; price adjustment included in each amount due. Low service damages per Annexure C. Task Order includes priced list from Price List, delay damages, total Prices for Task. Currency: South African Rand. Assessment interval: 15th day of each month. Payment period: 4 weeks. Interest rate: Nedbank prime lending rate. Insurance: Employer provides insurances per Insurance Clauses; Contractor provides insurance per Insurance Clauses in joint names, covering Contractor's risks from starting date until Defects Certificate or termination. Minimum limit of indemnity for employee injury/death: as prescribed by COID Act. Performance bond / guarantee requirements not stated in this volume. No financial capacity or turnover thresholds disclosed.
Compliance Requirements
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdf (RFQ)Mandatory compliance requirements from contract clauses: Annual submission of a compliant B-BBEE certificate (Z18.1) — failure is a material breach allowing contract cancellation. Occupational Health and Safety Agreement (OHS 040) per Section 37(2) of OHS Act and Construction Regulation 5.1(k) must be signed before work commences. Contractor must appoint competent persons per Section 16(2) OHS Act; full-time dedicated H&S resource required for projects with 5+ people; baseline risk assessment by competent person before work; risk register review when scope changes; medical emergency response procedure submitted prior to work; employee training on hazards and equipment; strict supervision and discipline; unsafe condition reporting within 48 hours (24 hours if Client responsibility); permit-to-work compliance; health and safety committee establishment regardless of employee count; monthly H&S meetings; COID Act good standing letter required before work; incident reporting per Section 24 OHS Act; PPE compliance; 14-day notice to remedy non-compliance. Construction Regulations 2014 compliance mandatory. Environmental compliance: all applicable environmental laws, regulations, rules, guidelines and procedures (Z21.3). Standard government requirements not explicitly stated in this volume but typically required: CSD registration, valid SARS tax clearance/tax pin, CIDB grading (grade not specified), CIPC registration. Returnable forms: Form of Offer and Acceptance (C1.1), Contract Data (C1.2a & C1.2b), OHS Agreement (C1.3), Pricing Data (C2), key personnel CVs, Annexure C (low service damages), Annexure D (S37(2) appointment). Likely standard forms: SBD 4, SBD 6.1, SBD 8, SBD 9, Authority to Sign / Board Resolution.
B-BBEE Requirements
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdf (RFQ)Contractor shall annually present a compliant B-BBEE Certificate. Failure to adhere is a material breach, sanction may be contract cancellation (Z18.1).
Health & Safety
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdfOccupational Health and Safety Agreement (OHS 040) per Section 37(2) of OHS Act and Construction Regulation 5.1(k). Objectives: compliance with OHS Act, COID Act, Construction Regulations 2014. Mandatary (Contractor) undertakes: reporting to Client before work commencement and scope changes; warranty of compliance with OHS Act; baseline risk assessment by competent person before work; risk register review when scope changes; medical emergency response procedure submitted prior to work; appointment of competent persons per Section 16(2) OHS Act; full-time dedicated H&S resource for projects with 5+ people; employee training on hazards and equipment use; strict supervision and discipline; unsafe condition reporting within 48 hours (24 hours if Client responsibility); cooperation with Client inquiries; provision of checklists/inspection registers; development of mitigation measures and safe work procedures including lock-out/tag-out; permit-to-work compliance; health and safety committee establishment regardless of employee count; monthly H&S meetings; COID Act good standing letter required before work; incident reporting per Section 24 OHS Act; Client right to investigate incidents; permit-to-work notification; PPE compliance; 14-day notice to remedy non-compliance; indemnification of Client against claims; authorised signatory per Section 16.2 OHS Act. Contractor accepts potential appointment as Principal Contractor per Construction Regulations (Z21.2.1).
Environmental
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdfContractor complies with all applicable environmental laws, regulations, rules, guidelines and procedures under contract; ensures Subcontractors, employees and others under Contractor's direction comply (Z21.3). Site hygiene: reasonably practicable level of hygiene and cleanliness; no loose materials left lying about; work site cleared of waste material regularly and on completion. Hazardous substances transport: compliance with Hazardous Substances Act. Permit management: work requiring permit not performed prior to approved permit; Mandatary notifies Client of work for permit issuance.
Contractual Terms
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdfNEC3 Term Service Contract (TSC 3) with Main Option A: Priced contract with Activity Schedule. Dispute resolution Option W1. Secondary Options: X1 Price Adjustment, X2 Changes in the law, X17 Low service damages, X18 Limitation of liability, X19 Task Order, Z Additional conditions of contract. Law of contract: Republic of South Africa. Language: English. Period of reply: 7 business days. Starting date: on signing of contract by ACSA. Completion date: 60 months from starting date. Defects date: 12 months after Completion. Defects correction period: as determined by Service Manager per incident. Assessment interval: 15th day of each month. Currency: South African Rand. Payment period: 4 weeks. Interest rate: Nedbank prime lending rate. Insurance: Employer provides insurances per Insurance Clauses; Contractor provides insurance per Insurance Clauses in joint names. Minimum limit of indemnity for employee injury: as prescribed by COID Act. Adjudicator: appointed from panel (Adv. Ghandi Badela, Mr. Errol Tate, Adv. Saleem Ebrahim, Mr. Sebe Msutwana, Mr. Sam Amod, Adv. Sias Ryneke SC, Mr. Emeka Ogbugo). Adjudicator nominating body: Chairman of Johannesburg Advocate's Bar Council. Tribunal: Arbitration per Rules for Conduct of Arbitrations 2013 Edition, 7th Edition, Association of Arbitrators (Southern Africa). Arbitration place: Johannesburg, South Africa. Arbitrator selection: from Panel of Arbitrators by Chairman of Johannesburg Advocates Bar Council. Price Adjustment Factor: based on Base Date Index and Latest Index. Low service damages: per Annexure C. Limitation of liability: Contractor's indirect/consequential loss limited to nil; loss/damage to Employer's property limited to total cost of incurred losses/repairs; defects liability limited to total cost of incurred losses/repairs; total direct liability unlimited except excluded matters (property damage, delay damages, defects liability, insurance liability, third party injury/property, IP infringement). Task Order: includes detailed description, priced list, start/completion dates, delay damages, total prices. Task Order programme submitted within period stated in Contract Data. Additional Z clauses: Z1 waiver/estoppel, Z2 Disallowed Cost definition, Z4 service warranty, Z5 termination for business rescue, Z7 Employer's liability for indirect loss limited to R0.00, Z8 cession/delegation/assignment with Employer consent, Z9 joint/several liability for JV, Z10 ethics/anti-corruption, Z11 confidentiality, Z12 Employer step-in rights, Z13 liens/encumbrances, Z14 intellectual property, Z16 dispute resolution panels, Z17 compensation event notification reduced to 4 weeks, Z18 annual B-BBEE certificate requirement, Z19 Service Manager requires Employer consent for design/scope changes >10% or completion extension >30 days, Z20 OHS Act Section 37(2) delegation, Z21 health/safety/environment compliance including Construction Regulations 2014.
Section
Source: 2. CIA RFP 7897-2025 NEC 3 Contract.pdfNo evaluation criteria, scoring methodology, or preference point system disclosed in this document volume. Mandatory eligibility: annual B-BBEE certificate (Z18.1), OHS Act and Construction Regulations 2014 compliance, key personnel CVs for Contract Manager, Supervisor/Technician, Health & Safety Officer. Standard requirements (CSD, tax clearance, CIDB) not explicitly stated but typically apply.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
Cape Town International Airport Southern Office Block Building - Airport Industria - Cape Town - 7490
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
2
Last checked
19 Aug 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Services: Civil. Unlock full pricing strategies, bid frequency, and historical win rates.