Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
Gauteng - Vanderbijlpark - Vanderbijlpark - 1911
Organization Type
GOVERNMENT
Published
04 Sept 2026
OCDS Reference
ocds-9t57fa-169197
The refurbishment of the access road at kwagga substation in pretoria west, gauteng, involves converting a 342m long, 4m wide gravel road into an asphalt surfaced road, including cleaning and repairing drainage along the road. The contract is an nec3 engineering and construction contract (april 2013) option b (priced contract with bill of quantities) under the employer ntcsa. The most consequential requirement is that the contractor must have an ntcsa certified and authorised person available in each work area at all times, in accordance with ntcsa transmission standard TST32-136, given the high-voltage environment.
Scope: Refurbish the access road at Kwagga Substation from the main entrance to the feeder bays, converting 342m of 4m wide gravel road to asphalt, and clean and repair drainage along the road.
Contract type: NEC3 Engineering and Construction Contract (April 2013), Option B (priced contract with bill of quantities), with dispute resolution option W1 and secondary options X2, X5, X7, X16, X18 and Z.
Completion date: The whole of the works must be completed by 31 December 2027, with key dates including compliance by Feb 2027, site establishment by Mar 2027, scope completed by Oct 2027, and handover by Nov 2027.
Starting date and access: The starting date is 15 Feb 2027, and access to the site at Kwagga Substation is from Mar 2027.
Safety and personnel: The Contractor must have an NTCSA certified and authorised ORHVS person available on site at all times, and that person must hold a valid first aid level 2 certificate. All tools must have valid test certificates produced two weeks before site establishment.
Working hours: Work is limited to 08h00 to 16h00 on weekdays; weekend work only on request by NTCSA.
Environmental compliance: The Contractor must compile a complete environmental file, audited and approved by the Grid Environmental Department before commencement, and must sign off TRM-FM-0038 – NTCSA Holdings Transmission division contractor environmental compliance proforma.
Quality management: The supplier must submit objective evidence of a developed and implemented QMS that complies with ISO 9001:2015 or the latest applicable standard, and complete and sign Form A (Enquiry/Contract/Quality Requirements for QM 58 and ISO 9001).
Pricing: The contract is a re-measurement contract with a bill of quantities; the tendered total of the Prices is to be stated excluding VAT, with VAT at 15% added.
Bonds and guarantees: The Contractor must provide any required bond or guarantee in the form given in Part 1 of the contract data (document C1.3, Sureties); the Employer may withhold payment until the bond or guarantee is received and accepted.
Payment: Assessments are made by the 25th of each month, with payment within 30 days. Invoices must be sent in PDF to [email protected] and include the Employer's VAT registration number 4740101508.
Defects: The defects date is 52 weeks after Completion; defects requiring urgent attention must be corrected within 48 hours.
Delay damages: Secondary option X7 (delay damages) applies, but the amount is not stated in the provided text.
SD&L obligations: The Contractor must comply with SD&L (Socio-Economic Development and Local) obligations; failure to submit SD&L performance reports quarterly or meet contractual obligations results in a penalty of 2.5% of every invoice amount (excluding VAT).
Site facilities: No office, telephone or toilet facilities are available on site; the Contractor must provide his own, and no work may commence before toilet facilities are available.
Site security: Alcohol testing is conducted on all employees entering NTCSA premises; those testing positive will not be allowed on site. All vehicles must comply with the National Road Traffic Act, 1996.
As-built drawings: The Contractor must provide as-built drawings in dgn format within 14 days after Completion, and within five days after Completion for the access road as-built drawings.
Continue with tenders sharing this issuer, category, or province.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Wednesday, 07 October 2026 - 10:00
Venue
MS Team
All documents to be downloaded on ntcsa tender bulletin
Categories
Request for Bid(Open-Tender)
Gauteng - Vanderbijlpark - Vanderbijlpark - 1911
Tenders in this industry often require registration with these bodies.
Construction Industry Development Board (CIDB) registration is mandatory for almost all public sector construction tenders. Ensure your grading matches the tender value.
Recommended Certifications
Having these can improve your winning chances: NHBRC Registration, ISO 9001:2015 (Quality Management), ISO 14001:2015 (Environmental Management), ISO 45001:2018 (Occupational Health & Safety), SACPCMP Registration, ECSA Registration
AI Document Analysis Stages
Description
Source: SHEQ FOLDER.zip04 Sept
2026
Tender Published
Tender was published
07 Oct
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
NEC.zip
Eskom Holdings SOC Ltd is procuring the Central Grid Access Road Refurbishment Project for Rigi and Kwagga Substations in Gauteng. The tender closes on 07 Oct 2026 at 10:00 GMT and is governed by the NEC3 Engineering & Construction Contract Option B (re‑measurement, bill of quantities).
Technical.zip
SHEQ FOLDER.zip
string or null
BOQ.zip
ESKOM (National Transmission Company of South Africa) is procuring refurbishment of access roads at Kwagga and Rigi substations in Gauteng. The scope comprises earthworks, paving, drainage, and landscaping under NEC3 ECC Pricing Option B, with a closing date of 7 October 2026 at 10:00.
Commercial.zip
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubWe refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
The refurbishment of the access roads at Kwagga and Rigi Substations is required due to
the deterioration of the existing road surfaces. The proposed works will improve road
condition, enhance user safety and comfort, and extend the service life of the road
infrastructure.
Kwagga Substation
The existing gravel access road at Kwagga Substation has become worn over time and
requires refurbishment. The project involves upgrading the road from a gravel surface to an
asphalt-paved road to improve durability and reduce future maintenance requirements.
The road section to be refurbished extends from the main entrance gate of the substation to
the feeder bays within the NTCSA Kwagga Substation. The road is approximately 342 m
long and 4 m wide.
Rigi Substation
The access road at Rigi Substation has deteriorated significantly, with several sections
exhibiting potholes and surface failures. During rainfall, water accumulates in low-lying
areas, resulting in ponding that affects vehicle access and creates a safety hazard for
personnel and heavy vehicles operating within the substation.
The refurbishment works will cover the road section starting approximately 25 m outside the
substation access gate, extending through the station to the feeder bays, where the existing
asphalt road meets the concrete road. The works will also include the refurbishment of the
gravel road adjacent to the existing asphalt road, which provides access to the stores.
2.1 Scope of the EMPr
NB: This EMPr document only caters for the scope of work contained in it. Any activities
outside the given scope of work will need to be addressed through the correct process (i.e.,
method statements).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Projects/Service Providers
Revision: 3
Page:
2.1.1 Purpose
This EMPr has been compiled to address the potential environmental impact that might
occur during the Central Grid Access Road refurbishment project. This document serves as
the environmental specification to National Transmission Company South Africa (NTCSA)
personnel and Contractors with regards to addressing the environmental issues identified
prior to and during the construction phase. It is the responsibility of the Project Manager
(PM), Contractors and the Environmental Practitioners to ensure compliance with all the
environmental specifications in this document, Environmental Requirements for Contractors
and/or Suppliers as well as the relevant compliance obligations.
This EMPr should also ensure the sustainable management of the environment whilst
replacement works are undertaken. This EMPr must be viewed as a contract document to
which all NTCSA personnel and contractors involved should adhere to.
2.1.2 Applicability
This document shall apply to Transmission Project Delivery (TPD) and Contractors
contracted to work on the Central Grid Access Road Refurbishment for Kwagga and Rigi
Substations Project.
2.1.3 Effective date
N/a
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in
the following paragraphs.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Projects/Service Providers
Revision: 3
Page:
2.2.1 Normative
[1] ISO 9001 Quality Management Systems
[2] ISO 14001 Environmental Management System
[3] 240-180100134 Environmental Requirements for Contractors and /or Suppliers These
documents are indispensable for the application of this document, i.e., documents to be used
together with this document.
[4] Informative
[5] National Environmental Management Act, 1998 (NEMA) (Act No ), and all
amendments and supplementary listings and/or regulations.
[6] Environment Conservation Act, 1989 (ECA) (No ) and amendments.
[7] National Environmental Management: Waste Act, 2008 (NEMWA, Act ).
[8] National Environmental Management: Biodiversity Act, 2004 (NEM:BA) (Act No. )
and amendments.
[9] National Forest Act, 1998 (NFA) (No ).
[10] National Veld and Forest Fire Act, 1998 (Act No. ). Conservation of Agricultural
Resources Act, 1983 (CARA) (Act No. ) & amendments.
[11] National Heritage Resources Act, 1999 (Act ).
[12] National Water Act, 1998 (Act ).
[13] The Occupational Health and Safety Act, 1993 (Act No. ).
[14] The National Fencing Act, 1963 (Act No ) as amended by Act .
[15] The National Environmental Management: Protected Areas Act, 2003 (Act No. ) and
it’s Regulations.
[16] The National Environmental Management: Air Quality Act, 2004 (Act ).
[17] South African National Standard (SANS) 10228 – The identification and classification of
dangerous goods.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Projects/Service Providers
Revision: 3
Page:
2.3 Definitions
Include all definitions applicable to this document, in alphabetical order. Explain all terms used,
including documents, titles and departmental references that may cause confusion if not explained.
Definition Explanation
Construction work The erection, maintenance, alteration, renovation, repair, demolition
or dismantling of or addition to a building or any similar structure
The installation, erection, dismantling or maintenance of a fixed plant
where such work includes the risk of a person falling
The construction, maintenance, demolition or dismantling of any
bridge, dam, canal, road, railway, runway, sewer or water reticulation
system or any similar civil engineering structure
Contractor The Contractor has overall responsibility for ensuring that all work,
activities, and actions linked to the delivery of the contract, are in
line with the Environmental Management Programme and that
Method Statements are implemented as described
Works The works to be executed in terms of the Contract
2.4 Abbreviations
Provide explanations of terms and abbreviations including documents, titles and departmental
references that may cause confusion if not explained, and that are used in this document.
Abbreviation Explanation
CEO Contractor Environmental Officer
EMPr Environmental Management Programme
HCS Hazardous Chemical Substance
IAP Interested and Affected Parties
NEMA National Environmental Management Act, 1998 (Act No. )
NTCSA National Transmission Company South Africa
TPD Transmission Power Delivery
2.5 Roles and Responsibilities
Function roles and responsibilities
TPD Environmental To ensure that the Environmental Management
Practitioner Programme (EMPr) for the project is compiled and
approved.
To ensure that all conditions stipulated in the EMPr are
met.
To conduct audit, monitor or provide assurance before,
during and post construction.
TPD Project Ensure that implementation of EMPr is executed as
Manager/ Site planned.
Manager
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Projects/Service Providers
Revision: 3
Page:
Ensure that all stipulations within the EMPr are
communicated and adhered to by the Contractor.
Ensure that conditions in this EMPr are fulfilled before the
contractor occupies the site, during and post construction.
Contractor Ensures that all Sub-contractors (if any) working under the
Environmental Principal Contractor abide by the requirements of the
Officer (CEO) EMPr.
Be on site throughout the duration of the project and be
dedicated to the project.
Ensure all staff are aware of the environmental
requirements, conditions, and constraints with respect to
all their activities on site.
Implementing the environmental conditions, guidelines
and requirements as stipulated within the EMPr and
Method Statements
Attend and provide performance status at the project
progress and Environmental site meetings.
Facilitate and undertake corrective actions where non-
compliances are registered within the stipulated
timeframes.
Assist the TPD Environmental Practitioner in maintaining
all the site documentation.
Prepare site inspection reports and corrective action
reports for submission to TPD.
Contractor Project To provide all necessary supervision during the execution
Manager/ Site of the project. He/ She should be available on site all the
Manager time.
To appoint a suitably qualified and competent
Environmental Officer to monitor and report to the Project
Manager on the daily activities during the construction
phase.
To ensure that implementation is conducted in an
environmentally acceptable manner.
To fulfil all obligations as per the agreed contract.
To inform and educate all employees about the
environmental risks associated with the different activities
that should be avoided during the construction process
and lessen significant impacts to the environment.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Projects/Service Providers
Revision: 3
Page:
2.6 Process for Monitoring
All documents shall be kept on site and be available for monitoring purposes. Site
inspections by an Environmental Audit Team may require access to this documentation for
auditing purposes. The documentation shall be signed by all parties to ensure that such
documents are legal. Regular monitoring of site works by the CEO is imperative to ensure
that all problems encountered are solved punctually and amicably. When the CEO is not
available, the Site Supervisor shall keep abreast of all works to ensure no problems arise.
The following documentation shall be kept on site:
10.1. Site Diary
10.2. Complaints Register
10.3. Incidents and Non-Conformance Registers
10.4. Records of all remediation / rehabilitation activities
10.5. Copy of this Environmental Management Programme
10.6. Photographic record (before, during and post construction/ refurbishment)
10.7. Project specific Method Statements / Procedures
10.8. Inspections and Audit (monitoring and evaluation) Records
10.9. Waste Records
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Projects/Service Providers
Revision: 3
Page:
2.7 Related/Supporting Documents
Submission Form for Board and Exco Committees Executive Summary Additional Information – the
Central Grid Access Road Refurbishment for Kwagga and Rigi Substations Project
3.1 Geographical Site Location and Environmental Condition
Kwagga Substation
Kwagga Substation is in Kwaggastrand, Pretoria West, within City of Tshwane Gauteng Province,
South Africa and is close in Atteridgeville.
Rigi Substation
Rigi Substation is also located in The Emfuleni local municipality Gauteng Province, South Africa.
Between Sharpville and Boipatong just northeast of Vanderbijlpark.
Environmental Conditions
The Gauteng region experiences a temperate Highveld climate characterized by warm, wet summers
and cool, dry winters. Most rainfall occurs between October and March, with occasional heavy
thunderstorms that can result in localized flooding and ponding on deteriorated road surfaces. During
the dry winter months, unsealed gravel roads are prone to dust generation.
3.2 Public Involvement/ Participation Process
The potential environmental impacts associated with the proposed project are required to
be considered in compliance with the Environmental Impact Assessment (EIA) Regulations
of 2014 (As amended) published in Government Notice R982 to R985 on, in terms of
Chapter 5 of the National Environmental Management Act, 1998 (Act ) (as
amended). The above scope of work was assessed against the Listing Notices of the EIA
Regulations 2014 and the following is noted:
That the Project does not trigger EIA process as per the above-mentioned regulations.
The public may be involved if project/ activity triggers the requirements for any related
permits/ agreements e.g., water use licenses or heritage permits.
All the required replacement works will be done directly on the existing substation footprint;
therefore, the project would not trigger the EIA listed activities.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Projects/Service Providers
Revision: 3
Page:
3.3 Project Specific Scope of Work and Design
The scope of work in this project will cover the following:
The following civil works needs to be done for Kwagga Substations access road.
Refurbish 4m wide tar road
Clean open-cut drains and gutters that run next to the road
Conduct DCP and Troxler
The following civil works needs to be done for Rigi Substations access road.
Refurbish and construct 6m-9m wide tar road
Clean open-cut drains and gutters that run next to the road
Conduct DCP and CBR test
Place vegetation outside the gate of the substation
Construct cut-off drain outside the gate of the substation
This document has been seen and accepted by:
Name Designation
N/a
Note: Start with the latest Revision History in the first row and go backwards.
Date Rev. Compiler Remarks
July 2026 1 Bukelwa Masiza New document
The following people were involved in the development of this document:
N/a
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
Table 1: Project Specific Environmental Controls
This section specifies standard mitigation measures to be followed by the parties responsible for environmental management during
the construction of the Central Grid Access Road at Kwagga and Rigi project.
Note: An activity may have multiple aspects that might need to be looked at
No. Activity Aspect Impact Management Mitigation Measure Measurable Frequency of Responsible
Objective Targets Action Party
Contract and Enquiry to legal minimising included as part of the records stage Buyer/
programme requirements negative impacts tender documentation signed Environmental
and non- anticipated to thereby making it part of Practitioner
conformance to occur during the the enquiry document to
Declaration on other construction/ make the
Environmental requirements refurbishment recommendations and
Requirements and conditions phase. constraints, as set out in
Pro-forma. set out in the this document,
EMPr. enforceable under the
general conditions of
Ensure
contract. Project Manager environmental
awareness and
formalize A contractor shall
environmental acknowledge or complete
responsibilities Declaration on
and Environmental
implementation. Requirements Pro-forma
before commencement of
the works.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
A copy of this EMPr must During CEO
be always available at the construction/
works site. The Contractor refurbishment
shall ensure that all the
personnel on site, sub-
contractors and their
teams, suppliers, etc. are
familiar with and
understand the
specifications contained in
this EMPr.
Statements Project documents to legal minimising require method Method commenceme
requirements negative impacts statements may only Statements nt of activities
and non- anticipated to commence once the and relevant
conformance to occur during the method statements have documents. As and when
other construction/ been approved by the PM required
requirements refurbishment and NTCSA
and conditions phase. Environmental
set out in the Practitioner.
EMPr.
contractor shall provide Contractor
job-specific training on an Training
ad hoc basis when records
workers are engaged in
activities, which require
Method Statements.
that NTCSA Policies,
Guidelines and Standards
are consulted to ensure
that Method Statements
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
meet requirements as set
out in those documents.
demarcation demarcation of site contravention, minimising shall be consulted before take place commenceme
and and damage to negative impacts site demarcations and within the nt of
development the environment anticipated to development, including demarcated construction/
occur during the the camp site. area. refurbishment
construction/
refurbishment contained in this EMPr site
phase. must be adhered to and
considered when site As and when
demarcation and required
development takes place.
allowed outside the
demarcated area.
al Awareness Environmental understanding training and receive environmental impact commenceme
Training Awareness Training by workforce of awareness of awareness/ training. because of nt of
the construction/
responsibilities refurbishment onto site shall receive refurbishment refurbishment
in terms of this staff contribute to environmental activities is activities.
EMPr minimisation of awareness/training. minimised
the occurrence of through the
environmental development Legal environmental required
impact to the work of effective contravention, awareness/training shall
area. environmental damage to the be available as and when
awareness environment required.
training and private
and controls linked to the environmental
EMPr. awareness
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
aware of their individual staff.
roles and responsibilities
in achieving compliance
with the EMPr.
erect and maintain
information posters at key
locations on site.
Wastewater management
procedures.
conservation.
management procedures.
procedures.
-A record of all
environmental awareness
undertaken as part of the
EMPr must be available.
-Educate workers on the
dangers of open and/or
unattended fires.
Environmental
awareness/training should
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
include as a minimum the
following:
significant environmental
impacts, actual or
potential, related to their
work activities.
to be implemented when
carrying out specific
activities.
preparedness and
response procedures.
followed when
working near or within
sensitive areas.
management procedures.
conservation.
management procedures.
procedures.
-A record of all
environmental awareness
undertaken as part of the
EMPr must be available.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
-Educate workers on the
dangers of open and/or
unattended fires
-A staff attendance
registers of all staff to
have received
environmental awareness
training must be available
-Course material must be
available and presented
in appropriate languages
that all staff can
understand
Establishmen site camp environment by environmental method statement shall environment project
t unnecessary issues are taken be provided by the during site commences
clearing the into consideration contractor prior to any establishment
surface/ ground. in the planning onsite activity that is minimised
and construction includes the layout of the and the
of site construction camp in the development Land pollution/
establishment. form of a plan showing footprint are contamination.
the location of key kept to
infrastructure and demarcated
Chemical services (where development
pollution caused applicable), including but area.
by vehicle oils, not limited to offices,
grease or vehicle parking areas,
solvents stores, the workshop,
stockpile and lay down
areas, hazardous
materials storage areas
(including fuels), the
batching plant (if one is
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
located at the construction
camp), designated access
routes, equipment
cleaning areas, ablution
facilities, waste and
wastewater management;
construction camps must
be carefully considered
and approved by the
Substation/ Grid Team
and Tx. Projects Delivery
to ensure that the site
does not impact on
sensitive areas.
located where possible on
previously disturbed
areas.
camp shall be fenced
where necessary.
6 Environment Response to all Land, water Emergency
al types of pollution/ procedures are in Emergency Response situations are commenceme
emergencies environmental contamination. place to enable a Plan prior to the managed in nt
emergencies. rapid and commencement of the accordance
effective response proposed project. with the Chemical As and when
pollution caused to all types of
environmental must deal among other procedures. by vehicle oils,
emergencies. things with accidents grease or
solvents harsh weather conditions, Rapid and
disasters, wildlife effective
interactions, potential response to all
types of
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
spillages and fires in line environmental
with relevant legislation. emergencies.
aware of emergency
procedures as part of
environmental awareness
training.
authority shall be made
aware of a fire as soon as
it starts.
emergency necessary
mitigation measures to
contain the spill or leak
shall be implemented.
Chemical use and disposal of and water pollution of the provide method the CEO/ SHE
Substances hazardous pollution/ environment. statements for the environment. Representative
(incl. oil) substances contamination. “handling & storage of
hazardous chemical Minimise chances No litigation
substances”, “fire”, and Damage to the of transgression due to
“emergency spills environment. of the acts transgression
procedures”. controlling of pollution
pollution.
be confined to specific
and secured areas within
No complaints the contractor’s site, and
from in a way that does not
Interested & pose a danger of pollution
Affected even during times of high
Parties (I & rainfall. These areas must
APs). be imperviously bunded
with adequate
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
containment (at least 1.5 Method
times the volume of the statements
fuel) for potential spills or
leaks
of 10cm deep) must be
placed under all vehicles,
including plant and
equipment that stand for
more than 24 hours.
Vehicles suspected of
leaking must not be left
unattended, drip trays
must be utilised.
the drip trays will be
dependent on the vehicle
and must be large enough
to catch any
hydrocarbons that may
leak from the vehicle/plant
while stationery.
substances must be
contained in impermeable
containers for removal to
a licensed hazardous
Title: Supplier Quality Management: Document Identifier: 240-105658000
Alternative Reference QM 58
Number:
Area of Applicability: Eskom Holdings SOC Ltd
Functional Area: Procurement and Supply
Chain Management
Revision: 4
Total Pages: 30
Next Review Date: May 2030
Disclosure Controlled Disclosure
Classification:
Compiled by Supported by and Authorized by
Functional
Responsibility
Sipho A Sambo Bathusi Montwedi Gerhard Van Der Walt
Middle Manager Senior Manager General Manager
(Acting) (Acting)
Procurement and
Supplier Quality Procurement and Supply Chain
Management Supply Chain Management
ManagementProcurement and Corporate Services
Supply Chain Corporate Services
Management
Corporate Services
Date: 2026/05/26 Date: Date: 01 July 2026
EDC TN Formatted 15.10.2021/TR Formatted 22.10.2025
Template ID: 32-4 (Rev 13) Document template (for procedures, manuals, standards, instructions, etc.)
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
Content
. Introduction .................................................................................................................................................. 3
2.1 Scope ................................................................................................................................................. 3
2.1.1 Purpose .................................................................................................................................. 3
2.1.2 Applicability ............................................................................................................................ 3
2.1.3 Effective date ......................................................................................................................... 3
2.2 Normative/Informative References ..................................................................................................... 3
2.2.1 Normative ............................................................................................................................... 3
2.2.2 Informative ............................................................................................................................. 4
2.3 Definitions ........................................................................................................................................... 4
2.4 Abbreviations ...................................................................................................................................... 6
2.5 Roles and Responsibilities ................................................................................................................. 6
2.6 Process for Monitoring ....................................................................................................................... 7
2.7 Related/Supporting Documents ......................................................................................................... 7
3.1 Supplier and Sub-Supplier Quality Management System Requirements .......................................... 8
3.2 Quality Plan ........................................................................................................................................ 9
3.3 Contract Quality Plan ......................................................................................................................... 9
3.4 Quality Control Plan ......................................................................................................................... 11
4.1 Main Supplier and Sub-supplier Categories .................................................................................... 15
4.2 Main Supplier and Sub-supplier Capability and Capacity Assessment ........................................... 18
5.1. Contract Execution ............................................................................................................... 19
5.2. Supplier Quality Performance Monitoring Phase ................................................................. 20
5.3. Supplier Quality Audit .......................................................................................................... 21
6.1. Rights of Access ............................................................................................................... 21
6.2. Eskom Rights to Information ............................................................................................................ 22
6.3. Preservation ..................................................................................................................................... 23
6.4. Quality Audits Related Conditions .................................................................................................... 27
6.5. Management of Nonconformities and Nonconforming Outputs Identified by Eskom ...................... 27
6.6. Special Processes ............................................................................................................................ 28
Acceptance ................................................................................................................................................ 29
Revisions ................................................................................................................................................... 29
Development Team ................................................................................................................................... 30
Acknowledgements ................................................................................................................................... 30
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
The intention of this specification is to specify and describe the minimum quality requirements for all
existing and potential Eskom suppliers and define the quality criteria for the evaluation, selection,
supplier/ vendor registration, assessment, performance monitoring, and auditing of suppliers.
Eskom’s position is to partner with suppliers who fully demonstrate commitment to the development,
implementation, and maintenance of a quality management system (QMS) that conforms to the
requirements of ISO 9001 standard. The focus is to ensure suppliers establish and continually
improve their QMS and enhance service delivery, and customer satisfaction by implementing and
conforming to the standard.
2.1 Scope
2.1.1 Purpose
The purpose of this specification is to outline the requirements according to which suppliers shall
a quality management system (QMS) based on ISO 9001, which should form the basis for conformity
to Eskom quality requirements for various externally provided products, services and processes and
continual adherence throughout the duration of a contract.
2.1.2 Applicability
This specification shall apply throughout Eskom Holdings Limited divisions, its subsidiaries,
suppliers, and sub-suppliers and shall form part of all Eskom requests for information (RFI)/ requests
for quotation (RFQ)/ requests for proposal (RFP), including contracts for the procurement of products
and services.
2.1.3 Effective date
Date of authorisation of the specification
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
[1] ISO 9001 Quality Management Systems – Requirements
[2] ISO 10005 Quality Management Systems – Guidelines for Quality Plans.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
2.2.2 Informative
[3] ISO 9000 Quality Management Systems – Fundamentals and Vocabulary
[4] 32-727: Safety, Health, Environment, and Quality (SHEQ) Policy
[5] ISO 10006 Quality Management Systems – Guidelines for Quality Management in Projects
[6] ISO 9004 Quality Management – Quality of an Organisation – Guidance to Achieve Sustained
Success
[7] 32-1033: Eskom’s Procurement and Supply Chain Management Policy
[8] 32-1034: Eskom’s Procurement and Supply Chain Management Procedure
[9] PPPFA: Preferential Procurement Policy Framework Act, 2000 (Act No. )
[10] CIDB 1004: Best Practice Guideline A4: Evaluating Quality in Tender Submissions
[11] 240-12248652 Supplier Quality Management: List of Tender Returnable
[12] 240-168873697 Supplier Quality Management: Tender Evaluation Scorecard
[13] 240-125473040 Supplier Quality Management: Guideline for QM 58 Selection Criteria
[14] IAEA Safety Standard GS-R-3.1 Application of the Management System for Facilities and
Activities
[15] SANS 10845-1 Construction Procurement Part1: Processes, Methods and Procedures
2.3 Definitions
The vocabulary of ISO 9000 and the following definitions apply in the application of this specification.
2.3.1 Component: a constituent part of the product or sub-assembly of the product. The product
may comprise multiple individual components.
2.3.2 Contract Quality Plan: a document of the supplier’s process for delivering the level of quality
required by the contract. It is a framework for the contractor’s process for delivering quality.
Purpose of a CQP is to outline how the results defined in the specifications will be achieved.
2.3.3 Hold Point: a predetermined stage in the quality control plan (QCP) beyond which work/
manufacturing shall not proceed without the attendance of, and written authorisation of, an
Eskom representative or Eskom inspection agency, whichever is applicable.
2.3.4 Intervention Points: those control points indicated by the various controlling bodies
concerned with the implementation of a specific QCP/ ITP. These can be in the form of
inspection, hold points, surveillances, witnesses, reviews and verifications.
2.3.5 Inspection Agency: an organisation or person appointed by Eskom for the purpose of
performing quality assurance/ quality control, monitoring, inspection and/ or expediting
services.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
2.3.6 Level 1 Plant Items: equipment, whose failure has an effect on personnel safety and/ or
health, causes an environmental incident, cause a huge production loss or major equipment
damage. Equipment that are safety/ redundancy/ protective device or covered by statutory
regulations requirements.
2.3.7 Level 2 Plant Items: equipment, whose failure impacts plant availability and/or reliability,
causes significant costs or secondary damage.
2.3.8 Level 3 Plant Items: equipment that does not impact on personnel safety and/ or health,
environmental, cost, availability and/ or reliability of plant.
2.3.9 Nonconformity: a deficiency in material, composition, characteristic, or performance that
renders the quality of an item, component, or product unacceptable or indeterminate. The
term also covers a deficiency in, or deviation from/non-adherence to, the quality management
system requirements, prescribed production processes, and/or related documentation such
as procedures and instructions.
2.3.10 Quality Plan: specification of the actions, responsibilities and associated resources to be
applied to a specific object.
2.3.11 Quality Control Plan: a document specifying the activities to be inspected throughout the
execution of the project, inclusive of test methods, procedures, and acceptance criteria (This
term is equivalent to QIP and ITP).
NOTE: An Inspection and Test Plan (ITP) is a structured document that outlines the
necessary inspections and tests to ensure that a product or process meets specified quality
requirements and standards.
2.3.12 Requirement: the need or expectation that is stated, generally implied, or obligatory.
Requirements are generally specified in the purchase order and/or contract documentation
but may not be limited to these.
2.3.13 Primary Plant (Power Plant): primary plant include High Voltage equipment situated inside
the control room (breakers, bus-bars, CT’s, VT’s and transformers).
2.3.14 Secondary Plant (Control Plant): secondary plant includes all equipment used to control
and protect the HV equipment on the primary plant side. (Protection, metering, AC/DC and
tele-control).
2.3.15 Special Process: is any production or service process which generates products or services
which cannot be measured, monitored, or verified prior to delivery and use. This may include
welding processes or non-destructive techniques
2.3.16 Supplier: is a current or potential supplier, vendor, contractor, consultant, or service provider.
A supplier may be a natural or legal person and includes any employee acting within the
course and scope of his/her employment or any agent or manager acting for, or on behalf of,
or in the interests of, the person registered as supplier on the Eskom supplier database.
2.3.17 Sub-supplier: an organisation that provides a product/service to the supplier and/or that
enters into a subcontract and assumes some of the obligations of the supplier or prime
contractor.
2.3.18 Witness Point: a predetermined stage in the quality control plan where and inspection
activity will take place. Work may proceed, provided Eskom or its inspection agency has been
formally notified and confirmed that inspection is waived.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
2.4 Abbreviations
Abbreviation Explanation
AIA Approved Inspection Authority
CA Corrective Action
CFT Cross Functional Team
CQP Contract Quality Plan
FIDIC Federation Internationale Des Ingenieurs- Conseils
FMECA Failure Mode, Effects and Criticality Analysis
HAZOP Hazard and Operability Study
ISO International Organisation for Standardisation
ITP Inspection and Test Plan
NC Nonconformity
NDT / NDE Non-Destructive Testing / Non-Destructive Examination
PMI Positive Material Identification
QCP Quality Control Plan
QMS Quality Management System
PQP Project Quality Plan
RFI Request for Information
RFQ Request for Quotation
RFP Request for Proposal
SHEQ Safety, Health, Environment, and Quality
WPS Welding Procedure Specifications
WQR Welder’s Qualification Record
2.5 Roles and Responsibilities
The assigned Eskom Quality representative/ professional when part of a Cross Functional Team
(CFT) appointed to transact on externally provided products, services and processes shall select
applicable requirements for existing and potential Eskom suppliers using, 240-125473040 Supplier
Quality Management – Guideline for QM 58 Selection Criteria and Form A (Tender and Contract
Quality Requirements for Supplier Quality Management: Specification 240-105658000/ QM 58 and
Quality Requirements for ISO 9001 Standard).
The existing and/ or potential suppliers must complete, sign and return Form A with the other
returnables as listed in the List of Tender Returnable document (240-12248652). Other roles and
responsibilities for this standard are defined within the text of this specification.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
2.6 Process for Monitoring
The application of this specification throughout Eskom shall be audited as per the management
system audit schedule to review performance and effectiveness of this specification.
2.7 Related/Supporting Documents
The documents superseded by this specification: all divisional and business unit supplier quality
requirements standards and/or specifications.
2.7.1 Forms and templates:
[1] 240-68099512 Tender and Contract Quality Requirements for Supplier Quality Management
Specification 240-105658000/ QM 58 and Quality Requirements for ISO 9001 Standard (Form
A)
[2] 240-109253698 Template for a Typical Contract Quality Plan
[3] 240-109253302 Quality Control Plan/Inspection and Test Plan
[4] 240-126469599 Method Statement Template.
[5] 240-144723833 Quality Requirements Exemption Certificate
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
3.1 Supplier and Sub-Supplier Quality Management System Requirements
3.1.1 The supplier and sub-supplier shall develop, implement, maintain and improve a formal QMS
that conforms to the latest ISO 9001 standard or any applicable standard of QMS (latest
applicable revision) in accordance with the requirements of this specification.
3.1.2 Such a formal system shall consist of the appropriate documented information required by
ISO 9001, and may include a quality manual, quality plans, work procedures, work
instructions, method statements, workflow documentation, etc., as the case may be. This
requirement constitutes the most basic QMS requirements.
3.1.3 Unless specifically excluded from the quality list of tender returnables, as per the categories
of quality requirements (Category 1, 2, 3, or 4), such a QMS shall carry a valid ISO 9001
certificate from an accredited certification body, as indicated in the applicable Eskom
invitation (this requirement applies equally to both the supplier and any/ all manufacturing
third-party organisations mentioned above).
3.1.4 Unless specifically excluded in the quality list of tender returnable, as per the categories of
quality requirements (Category 1, 2, 3, or 4), the supplier shall have a fully developed,
documented, implemented, reviewed and maintained QMS that complies with the
requirements of ISO 9001 standard or any applicable standard of QMS. In the event that the
main supplier invariably requires the assistance of a sub-supplier in order to realise its own
supply obligations. The aforementioned requirement applies equally in all cases where any
such sub-supplier’s scope of responsibility includes the provision of any of the following
activities, namely, design and development, manufacturing, maintenance, testing, storage,
delivery, installation, commissioning, and project management, or in the cases the supplier’s
name changes, mergers, acquisitions and/ or cessions. Eskom Quality department must
ensure that the changed entity can still fulfil the requirements as set out in the contract
documentation.
3.1.5 Where a new product/ service introduced in Eskom, the requirements for such shall be in line
with available industry recommended practises (RP) or applicable codes (for example for
BESS, the RP UL 9540 or IEEE 1790) in the absence of SANS equivalent
3.1.6 Eskom reserves the right to request and perform necessary assessments at sub-supplier
facilities.
3.1.7 The main supplier shall be responsible for defining and managing the specific quality
assurance and control elements applicable to the respective sub-supplier’s scope of
work/supply and ensure that its sub-supplier(s) quality programmes support Eskom
requirements.
3.1.8 The supplier shall inform Eskom of any proposed changes to the QMS or staff that will affect
the quality system prior to implementation of these changes.
3.1.9 The main supplier shall develop and implement a performance management programme for
their sub-supplier. The programme shall include, but not limited to:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
3.2 Quality Plan
The information in this section constitutes the minimum requirements for a quality plan.
3.2.1 Where specified in the Evaluation Criteria and/ or quality list of tender returnables, as per the
categories of quality requirements (Category 1, 2, 3, or 4); all individual products, services
and processes shall have a documented, implemented, reviewed and maintained
contract/project quality plan and/or quality control plan (inspection and test plan).
3.2.2 Where specified in the evaluation criteria and/ or quality list of tender returnables. All
production and/ or service provision shall be carried out in accordance with a documented
and agreed contract/project quality plan (CQP) and/ or quality control plan (QCP)/ inspection
and test plan (ITP).
3.2.3 The supplier shall plan for the required quality-related activities and interfaces within the
supplier’s quality system in order to demonstrate its ability towards both controlling and
meeting specified Eskom requirements.
Note 1: Contract/ Project Quality Plan should address the quality assurance elements related to
the scope of work and/ or technical specification for the specified duration.
Note 2: Quality Control Plan (QCP)/ Inspection and Test Plan (ITP) should address the quality
control elements related to the scope of work and/ or technical specification.
3.3 Contract Quality Plan
The main supplier shall require sub-suppliers to submit project quality plans (PQPs)/ contract quality
plans (CQPs) and associated documentation in accordance with the requirements of project QMS
processes applicable to the sub-supplier’s scope of work.
The supplier shall, where applicable, based on scope of work criticality, ensure that procurement
documents clearly and unambiguously require sub-supplier submission of a sub-supplier CQP for
supplier and Eskom review.
The main supplier shall ensure that sub-supplier CQPs are developed and implemented in
accordance with the ISO 10005 Quality Management System Guidelines for Quality Plans and the
sub-contracted scope of work. In addition to the elements specified in ISO 10005, the supplier’s
and/ or sub-suppliers’ CQPs shall include the following (as applicable):
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
3.3.1 The management of records, including material tests, positive material identification (PMI)
testing, material certification, etc.
3.3.2 The provision for free and uninhibited access by the supplier and/or personnel at the time of
inspection.
3.3.3 The proposals for submission of final documentation, the final manufacturing data book, prior
to shipment.
3.3.4 The special processes related to welding: management of the welder’s qualification record
(WQR), welding procedure specifications (WPS), and procedures qualification records (PQR)
that will be used in the performance of work for supplier review and acceptance prior to
commencing manufacture. Welders shall be qualified to the specified Codes of Construction
for the applicable procedures. The requirements for qualification shall be specified by the
supplier, and welder records shall be maintained by sub-suppliers performing the work.
3.3.5 The special installation procedures and other required fabrication or manufacturing
procedures (that is, those required for post-weld heat treatment, tube rolling, coatings, etc.)
that will be used in the performance of work shall require supplier review and acceptance
prior to commencing manufacture.
3.3.6 The personnel carrying out special processes (for example, NDE, welding, coating, heat
treatment, etc.) where the results cannot be fully verified by subsequent inspection and test
shall be suitably qualified and, where applicable, registered with statutory bodies as legally
required, that is, as radiographic workers to conduct radiography. The requirements for the
qualification shall be specified, and personnel records shall be maintained in accordance with
the Project Quality Personnel Qualification Specification and, where applicable, legal
requirements.
3.3.7 The personnel required to perform special processes shall be certified competent through a
certificate of competency in accordance with the company’s training and development policies
or in line with applicable regulatory and statutory bodies requirements.
3.3.8 All personnel who perform activities that affect quality shall have their training needs identified
and documented. The required training shall be implemented in accordance with the
company’s training and development policies. All the training certificates shall meet the
applicable regulatory or statutory requirements in terms of having the unit standard /National
Qualification Framework (NQF) completed and the accreditation number of the service
providers.
3.3.9 Instructions and requirements for equipment and materials storage, preservation, and
maintenance, including identification of materials required for preservation and maintenance,
are to be provided sufficiently prior to receipt (prior to shipment or earlier) to ensure that
appropriate resources are available at the time of delivery.
3.3.10 Specific quality monitoring and verification activities are to be undertaken on the supplier’s
sub-suppliers by Eskom or it agent.
3.3.11 The CQP information shall include, but not limited to:
methods to be utilised to ensure quality.
generated.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
Cqp.
project.
3.3.12 The main supplier and sub-supplier CQPs shall comply with the Eskom Quality Requirements
Specifications and shall be submitted prior to the initial scope of work kick-off or initial pre-
fabrication meeting and prior to commencement of manufacturing, whichever is earlier.
3.3.13 The Eskom template for CQP provided shall be used as guideline, where the supplier does
not have a CQP template.
3.3.14 Competence and Qualification of Personnel managing quality shall be in line with applicable
qualification, certificates as deemed by the respectable company criteria.
3.3.15 Where personnel involved in the management of quality shall be noted to be lacking relevant
competences, Eskom shall request the removal of such personnel from the contract site
operations in respect to all activities and process that leads to conformity of product /services.
3.4 Quality Control Plan
The supplier shall develop, implement and maintain processes and procedures that efficiently and
effectively allows monitoring and verification of the scope of work activities, to outline specific
procedures; standards; and responsibilities for maintaining product or service quality.
The main supplier shall ensure that sub-supplier QCPs/ ITPs are prepared at a level of detail
sufficient to address all quality-control-related activities in a chronological order, from contract review
through materials verification, manufacturing, fabrication, assembly, final testing, commissioning,
hand-over documentation, and certification. In addition, the supplier shall ensure compliance with
the following requirements:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
3.4.1 All stages of manufacturing, fabrication, assembly and installation shall be controlled by a
supplier’s QCP/ ITP that clearly and unambiguously identifies the quality verifications to be
performed and special attention to controls related to critical products and services. The
intervention points and the inspection and tests methods to be applied are to be indicated
as per ISO 10005, Guidelines for Quality Plans.
3.4.2 QCP/ ITP shall be reviewed and accepted by an Eskom employer representative, its
inspection authority or agency, and they shall allow for the insertion of Eskom specific
requirements, including hold and witness points prior to the commencement of work.
3.4.3 Subsequent changes to the Eskom accepted QCP/ ITP shall require Eskom, its inspection
authority or agency’s agreement prior to the commencement of work involving an activity
affected by such changes.
3.4.4 The ITPs should cover materials certification, fabrication works, in-process inspections, final
acceptance tests, packaging and pre- shipment/ transportation, shipping/ transportation
inspections where contracted, preservation, site acceptance tests, construction and erection
works, and pre-commissioning and commissioning tests.
3.4.5 All sub-supplier QCP/ ITP activity shall be performed using an Eskom-accepted supplier
QCP/ ITP and be based on the sub-contracted scope of work.
3.4.6 All applicable codes, standards, and relevant acceptance criteria documents are available at
the work location, and Eskom representatives on site shall have on-going access to this
information. Workplace documentation shall be available in English and in any workforce-
appropriate language.
3.4.7 Where activities subject to inspection and test procedures are to be undertaken by a sub-
supplier, the QCP/ ITP shall make reference to this fact and shall include descriptive details
of the sub-supplier’s involvement. A separate QCP/ ITP shall be required for each sub-
supplier scope of work.
3.4.8 The supplier shall be ultimately accountable and responsible for the development and proper
implementation of all sub-supplier QCPs/ ITPs, including those reviewed or developed by
sub-suppliers.
3.4.9 Eskom reserves the right to select intervention points on QCPs/ ITPs for Eskom oversight of
selected functions and to perform surveillance or audits of the work.
3.4.10 Once signed, the ITPs and QCPs become addendums to the main contract. These ITPs can
be reviewed at Eskom’s discretion based on its assessment of the supplier’s performance or
other risks.
3.4.11 A QCP/ ITP shall contain the following information:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
with reference to the relevant criticality risk rating
international standard, with the relevant clause number for each operation
agency
intervention in the plan
indication of records to be provided to Eskom (as applicable)
3.4.12 The main supplier shall require sub-suppliers to submit QCPs/ ITPs and associated
documentation applicable to the sub-supplier scope of work. Any changes made to the QCP
after submission must be resubmitted to Eskom for further review. The supplier shall ensure
that all sub-supplier QCPs/ ITPs are in compliance with the Eskom Quality Requirements
Specifications, including, but not limited to, the following requirements:
will take place, including facility location(s)
performance of the activity, including specific reference to actual sections and pages of
procedures, standards, instructions, specifications, etc.
with specified requirements; documents are to be provided using the proper Eskom
document numbering requirements
inspection authority (AIA) and Eskom inspection activities defined in terms of witness, hold,
document review, and verification monitoring points and provision for sign-off of each of the
above-mentioned parties for each intervention point
inspectors
applicable), and Eskom prior to commencement of work
and package acceptance test, witness, and hold points
3.4.13 A quality kick-off meeting will be held at the start of the contract and, if required, at the start
of each subsequent phase.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
for items or equipment to ensure that all technical and commercial requirements are clear
and understood. Fourteen days’ advance notice of meetings shall be given to Eskom.
and qualified to perform inspection and testing assignments. Mobilisation of all such
personnel shall be in compliance with the Project Quality Personnel Qualification
Specification.
3.4.14 Where QCP/ ITP is applicable, the supplier shall ensure that sub-suppliers are provided with
comprehensive, clearly written, and unambiguous inspection and testing protocols, including
processes, procedures, and methods that shall include, but not be limited to, the following:
inspected
distribution, and report retention requirements
inspection and test processes, procedures, or methods and nonconformity identified in
inspection and test results
equipment and sub-systems (if applicable)
3.4.15 The supplier shall establish processes and procedures for formal assessment of sub-supplier
inspection and testing programmes. These shall include review of sub-supplier inspection
reports and other quality control documentation. Additional formal assessment of
manufacturing, fabrication, and assembly facility operations shall be conducted by the
supplier to ensure continuing suitability, adequacy, and effectiveness of the sub-supplier’s
inspection and testing programmes. Assessment frequency shall be established in
consideration of the sub-supplier scope of work, criticality of scope of work deliverables, and
performance information. The assessment scope and schedule shall be developed in
consultation with Eskom.
3.4.16 Supplier processes and procedures for verification of supplier and sub-supplier purchased
product compliance with specifications shall obtain document return/review status prior to
implementation.
3.4.17 The objective is to finalise any outstanding procedural or other issues before proceeding to
deliver the works.
3.4.18 Eskom, in consultation with the supplier, develops an agenda for the meeting, and Eskom will
keep minutes of these meetings.
3.4.19 Mandatory pre-inspection meetings will be convened by Eskom or its inspection agency or
AIA to be attended by the supplier’s and sub-supplier’s representatives, including their quality
representatives who will be involved in the works, and records are to be kept.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
3.4.20 Eskom reserves the right to appoint resident quality inspectors who can be based at the
supplier’s or sub-supplier’s premises and on site where the work is being performed. The
supplier is expected to provide workspace at no cost to Eskom for the inspector, as required.
3.4.21 Eskom may appoint any organisation it prefers to perform quality assurance and quality
control activities, either in the capacity as an AIA or inspection agency, on the works
contracted to the supplier, and the supplier or its sub-suppliers may not object, prevent,
hinder, undermine, circumvent, question, discredit, or in any way make it impossible for such
organisation to carry out its work on behalf of Eskom.
3.4.22 The Eskom template for QCP/ ITP provided shall be used as guideline, where the supplier
does not have a QCP/ ITP template.
The selected quality assessment criteria and Form A of this specification will be compiled and
completed by the assigned Eskom Quality representative/ professional who using the guideline 240125473040, shall select the suitable supplier quality requirements to be met.
Form A (Section A & Section E) of this specification must also be completed and signed by the
supplier responding to an Eskom invitation to tender, in order to acknowledge, accept and further
commit to comply with the Eskom Supplier Quality requirements as per this specification and ISO
9001 Standard or any additional quality requirements specific to the scope of work.
4.1 Main Supplier and Sub-supplier Categories
Eskom supplier quality requirements for all existing and potential suppliers and sub-suppliers are
classified into four categories (category 1, 2, 3 and 4). Suppliers must prepare and submit quality
documentation as per the tender selected category (indicated in Form A) using the list of tender
returnables document.
NOTE: Only one (1) category must be applicable per procurement process e.g. [Eskom requests for
information (RFI)/ requests for quotation (RFQ)/ requests for proposal (RFP), including contracts for
the procurement of products and services].
The following are the minimum returnable documentation for Categories 1 to 4:
4.1.1 Category 1: Quality Requirements
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
Automobile; ICT) of a QMS (the latest applicable revision). The QMS should drive the
supplier’s business management processes to ensure that all of Eskom’s requirements are
fully met on a consistent basis.
audit reports. The audit reports must include, if applicable, nonconformities identified, and
the resulting remedial actions (correction and/ or corrective action reports).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals,
procedures.
described in the tender documents. The plan must address the minimum requirements as
per ISO 10005.
plan (ITP) or quality control plan (QCP) on similar and/ or previous work done.
Processes, Products and Services.
meetings that include agenda, meeting minutes, attendance registers, reports, presentations,
etc.
Note 1: specific requirements per tender will be selected using the List of Tender Returnable
documents (240-12248652).
Note 2: any additional requirements specific to the scope of work can be included under Section E
(List of Tender Returnable documents (240-12248652)) and subsequently listed from E2 onwards.
4.1.2 Category 2: Quality Requirements
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
QMS that complies with ISO 9001 or any applicable standard of quality management system
(the latest applicable revision). The following documents (approved/ signed copies) shall be
submitted:
o Quality Management System manual or a documented information that have defines
and describes the QMS and its scope
o Quality Policy, aligned with the supplier’s strategic direction (documented
information)
o Quality Objectives (documented information)
o Control of documented information (both maintain and retain documented
information)
o Internal audit procedure (documented information)
o Control of nonconforming outputs (documented information)
o Nonconformity and Corrective action procedure (documented information)
The QMS should drive all the supplier’s business management processes to ensure that all of
Eskom’s requirements are fully met on a consistent basis.
The audit reports must include, if applicable, nonconformity identified, and the resulting
remedial actions (correction and/ or corrective action reports).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
described in the tender documents. The plan must address the minimum requirements as
per ISO 10005.
quality control plan (QCP) on similar or previous work done.
Processes, Products and Services.
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals,
procedures.
meetings that include agenda, meeting minutes, attendance registers, reports, presentations,
etc.
Note 1: specific requirements per tender will be selected using the List of Tender Returnable
documents (240-12248652).
Note 2: any additional requirements specific to the scope of work can be included under Section E
(List of Tender Returnable documents (240-12248652)) and subsequently listed from E2 onwards.
4.1.3 Category 3: Quality Requirements
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
9001 (or the latest applicable revision). The following documented information (approved/
signed copies) shall be submitted:
o Quality management system manual or a (documented information) that have
defines and describes the QMS and its scope
o Quality Policy, aligned with the supplier’s strategic direction (documented
information)
o Quality Objectives (documented information)
o Control of documented information (both maintain and retain documented
information)
o Internal audit procedure (documented information)
o Control of nonconforming outputs (documented information)
o Nonconformity and Corrective action procedure (documented information)
The QMS should drive all the supplier’s business management processes to ensure that all of
Eskom’s requirements are fully met on a consistent basis.
described in the tender documents. The plan must address the minimum requirements as
per ISO 10005.
quality control plan (QCP).
Processes, Products and Services.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals,
procedures.
Note 1: specific requirements per tender will be selected using the List of Tender Returnable
documents (240-12248652).
Note 2: any additional requirements specific to the scope of work can be included under Section E
(List of Tender Returnable documents (240-12248652)) and subsequently listed from E2 onwards.
4.1.4 Category 4: Quality Requirements
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
scope of work.
processes to ensure that all of Eskom’s requirements are fully met on a consistent basis.
strategic direction). (documented information)
Processes, Products and Services.
authorities, specific to the project/ scope of work/ technical requirements. Examples of
relevant documented information are; organization charts, job descriptions, work instructions,
duty statements, manuals, procedures.
Note 1: specific requirements per tender will be selected using the List of Tender Returnable
documents (240-12248652).
Note 2: any additional requirements specific to the scope of work can be included under Section E
(List of Tender Returnable documents (240-12248652)) and subsequently listed from E2 onwards.
4.2 Main Supplier and Sub-supplier Capability and Capacity Assessment
Supplier capability and capacity assessments shall be performed prior to contract award on potential
suppliers participating in Eskom Holdings procurement process to:
All sub-suppliers used by the main supplier/ contractor, performing work on Eskom critical plant
equipment, supplying commodities and providing specialised services shall be subjected to the
capability and capacity assessment.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
Critical plant includes the following:
All potential quality risks identified will be included in the assessment report provided for the tender
evaluation.
Note: Form A (Enquiry/ Contract/ Quality Requirements for Supplier Quality Management:
Specification 240-105658000/ QM 58 and ISO 9001) will be used to select and indicate whether
capability and capacity assessment will be conducted during the requirements setting phase of the
transaction.
5.1. Contract Execution
The supplier shall submit the following documents within 30 days (depending on the contract
duration) or as per stated timeline after the contract date, prior to the commencement of work, for
acceptance by Eskom:
Method statement before contract award. This shall be reviewed and signed off by Eskom
appointed employer agent within 30 days or as per stated timeline after contract award.
(Inspection and Test Plan) ITP(s) for review and acceptance by Eskom prior to the
commencement of any work, inclusive of subcontracted work, within 30 days or as per
stated timeline after contract award.
by Eskom within 30 days or as per stated timeline after the award of the tender. All supplier
and Eskom comments shall be resolved prior to commencing work.
considered when compiling CQPs and QCPs.
minimum of 7 working days prior to the activity being executed.
Note: These plans are to be compiled in line with Eskom’s requirements and will have to be
discussed with, and approved by, Eskom prior to any work commencing.
meetings shall be convened by Eskom with the supplier.
manager or his/her representative for the contract.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
during contract execution. The content of these reports shall be agreed by Eskom when
submitted to Eskom on a monthly basis.
5.2. Supplier Quality Performance Monitoring Phase
During the contract execution phase, suppliers shall be monitored by Eskom for performance on
quality-related aspects.
The outcomes of such monitoring will enable Eskom to take any appropriate actions pertaining to
the supplier.
The monitoring shall be carried out periodically by Eskom assigned employer agent at predetermined
intervals during the execution of a contract using agreed key performance indicators. The monitored
key performance areas include the following:
Subsequent key performance indicators associated with these areas will include the following:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
5.3. Supplier Quality Audit
5.3.1. Quality audits and related quality performance reviews are intended to provide an objective
evaluation of compliance with performance expectations defined in this specification, in the
supplier contract quality plan (CQP), and in any other project scope of work specification
such as contract document.
5.3.2. Quality audits and related quality performance reviews include, but are not limited to, any
quality or other project functional area audits, verification of compliance reviews, surveillance,
inspections, or other interim or final assessments of scope of work deliverables provided by
the supplier or sub-suppliers.
5.3.3. Quality audits and related quality performance reviews are intended to provide an objective
evaluation of compliance with performance expectations defined in this specification, in the
supplier contract quality plan (CQP), and in any other project scope of work specification.
5.3.4. Quality audits and related quality performance reviews include, but are not limited to, any
quality or other project functional area audits, verification of compliance reviews, surveillance,
inspections, or other interim or final assessments of scope of work deliverables provided by
the supplier or sub-suppliers.
5.3.5. Quality audits and related quality performance reviews shall be carried out by trained,
accredited, and experienced personnel in accordance with established documented
information for managing audits.
5.3.6. The supplier shall submit, for Eskom review, documented processes for conducting project
scope of work quality audits and related quality performance reviews. Supplier quality audits
and related quality performance review processes shall be designed to address evaluation
of progress towards completion of project functional area deliverables as well as final
deliverable quality.
5.3.7. The supplier shall provide a schedule of anticipated quality audits covering all functional
areas and related quality performance reviews at the time of first post-contract award CQP
submission.
6.1. Rights of Access
Eskom:
6.1.1. shall be granted electronic and hard-copy access to all quality plans, procedures,
documentation, and other quality records relating to the work, including, but not limited to,
data extracts;
6.1.2. reserves the right to review, inspect, and audit any or all parts of the supplier’s QMS, as well
as any documentation, materials, or equipment associated with the work, at any time or
project work location; and
6.1.3. reserves the right to carry out assessments and audits on all new suppliers and sub-
suppliers.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
The supplier:
6.1.4. shall support Eskom’s effort to monitor, verify, and/or witness any activities associated with
the work at any time;
6.1.5. shall cooperate with Eskom requests for documentation, records, and inspection and
witnessing. Eskom participation in audits, appraisals, assessment of plans, and verification
shall be conducted at no extra cost to Eskom;
6.1.6. shall ensure that a sub-supplier provides access to Eskom to all work procedures, records,
and supporting documentation through provision of access to view and photocopy, as
required, to support verification of scope of work requirements. Access shall include the
ability to photograph Eskom equipment, systems, system components, materials, etc.;
6.1.7. shall provide access to all quality-related information pertaining to activities performed by
itself or sub-suppliers, where Eskom might not have participated in the witnessing of their
quality assurance or control (this refers to inspections, audits, etc. performed by the supplier
on its own sub-suppliers);
6.1.8. shall allow Eskom to assess, audit, approve, or reject any sub-suppliers employed by
Eskom’s suppliers to assist with the product and/or service delivery to Eskom; and
6.1.9. shall ensure that the above requirements flow down to sub-suppliers.
6.2. Eskom Rights to Information
6.2.1. To expect that the works will be conducted in accordance with the contract between the
parties.
6.2.2. To have access to the supplier’s information as determined by applicable legislation.
6.2.3. Eskom reserves the right to oversee the supplier’s audit programmes by participating in
selected audits as an observer and by assessing the supplier during key work stages. Eskom
will coordinate with the supplier to develop an oversight schedule aligned with the supplier’s
audit schedule.
6.2.4. To obtain access to any audit reports of audits performed by the supplier reflected in the audit
programme.
6.2.5. To conduct independent quality audits during all phases of the contract, and the supplier shall
provide all resources to support these activities.
6.2.6. Eskom shall have the right to participate in, or request that, a technical investigation be
launched and conducted at the supplier’s and sub-suppliers’ premises or other sites when
risk to Eskom products or service deliverables is identified.
6.2.7. To participate in, and/or lead, investigations related to incidents involving its products.
6.2.8. To require from suppliers to be responsible for the cost of re-inspections.
6.2.9. To withhold payment from suppliers as a result of outstanding nonconformities, irrespective
of the agreed payment schedule and in accordance with the conditions of contract.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
6.2.10. Shall be granted electronic and hard-copy access to all quality plans, procedures,
documentation, and other quality records relating to the work, including, but not limited to,
data extracts.
6.2.11. Reserves the right to review, inspect, and audit any or all parts of the supplier’s QMS, as well
as any documentation, materials, or equipment associated with the work, at any time or
project work location.
6.2.12. Shall carry out assessments and audits on all new suppliers and sub-suppliers.
6.2.13. Reserves the right to appoint resident quality inspectors who can be based at the supplier’s
or sub-supplier’s premises and on site where the work is being performed.
6.2.14. Reserves the right to select intervention points within all developed supplier QCPs/ ITPs for
Eskom oversight of selected functions and to perform surveillance or audits of the work.
6.2.15. Shall be given access at all reasonable times before, during, and after manufacture and
before delivery, construction, erection, and commissioning to measure, test, and inspect the
products and workmanship, as necessary, at the supplier’s premises and at Eskom sites.
6.2.16. Reserves the right to suspend any pending deliveries by the issuing of a cease delivery
order at any time and for any portion of the work that is not being performed in accordance
with the specified/agreed requirements.
6.3. Preservation
The supplier shall develop and implement a comprehensive preservation programme consisting of
plans, processes, procedures and actions undertaken for the purpose of planning for and
maintenance of material deliverables quality. The supplier preservation programme scope includes,
but is not limited to, the following:
6.3.1. Engagement of personnel suitably qualified for oversight of, and (as required) direct
implementation of, preservation programme requirements.
6.3.2. Development and implementation of preservation programme training appropriate to work
need.
6.3.3. Eskom may make use of its appointed service provider tasked to provide a full suite of
services encompassing an online monitoring system and asset tracking during, but not limited
to the following stages: inspections, testing, shipping, transportation, storage, and
commissioning. The supplier is to enable full access during all of these stages in order to
allow the installation of the devices on Eskom-identified products and equipment, which
include the sub-supplier’s testing facilities, processing plant, and any other processes
deemed important towards effective and efficient quality control.
6.3.4. Eskom seeks cooperation between the supplier’s designers and those of Eskom’s service
provider in ensuring seamless installation of the device and other associated installations.
Moreover, there is also a need to integrate data flows and systems between Eskom and the
supplier. Further details are included in the Eskom specifications and works information.
6.3.5. Review and tracking of compliance with Eskom and supplier engineering specification of
preservation requirements.
6.3.6. Review and tracking of compliance with sub-supplier provided preservation requirements and
recommendations.
6.3.7. Evaluation of prospective temporary and longer-term material storage sites for consistency
with preservation programme expectations.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
6.3.8. Preservation work plan development and plan execution performance evaluation of all parties
engaged for provision of material transportation, handling, or storage services.
6.3.9. Oversight of material quality preservation plan preparation and plan execution performance
at all work locations.
6.3.10. Development of a preservation programme records management process, in compliance
with Eskom information management requirements, which comprehensively addresses
generation, maintenance, and ready access by Eskom to all preservation programme
records.
6.3.11. The supplier shall deploy a clearly defined documented programme providing for
identification of all physical asset pre-operation preservation of quality requirements. In this
reference, the term “physical assets” should be understood to include bulk materials,
including consumable items, equipment systems, system components, and any other
procured or supplied materials or equipment transferred to project control, but not deployed
for operational purposes.
6.3.12. Where the project responsibility for equipment and materials management has been formally
delegated, the supplier’s preservation programme shall ensure clear and unambiguous
communication of pre-operation preservation of goods quality requirements to sub-suppliers.
6.3.13. The supplier’s preservation programme shall clearly and unambiguously document
processes and procedures for efficient and effective monitoring of compliance with
programme requirements.
6.3.14. Compliance monitoring shall commence with ensuring comprehensive consideration of
preservation requirements in the engineering instruction and subsequent inclusion of said
instruction in procurement documentation and shall be applicable until such time as
equipment or materials have been incorporated in an operating or operational system or
structure.
6.3.15. Compliance evaluation frequency shall anticipate transfer of tactical-level responsibility for
management of preservation responsibilities between project functional areas, for example,
procurement to logistics, logistics to fabrication, fabrication to logistics, logistics to
construction, etc., and shall, in similar fashion, anticipate transfer of support for tactical-level
responsibility between various subcontracted service providers.
6.3.16. Supplier engineering shall ensure that preservation requirements for scope of work systems,
system components, equipment, materials, and other procured goods are clearly and
unambiguously documented and that preservation requirements are efficiently and effectively
communicated to project procurement, logistics, construction management, quality, security,
and other project functional areas, as required, for efficient and effective implementation of
preservation requirements. This shall take the form of a preservation programme applicable
to all systems, system components, equipment, materials, customer-supplied materials, and
other goods procured or managed under the scope of work.
6.3.17. The supplier’s preservation management programme shall clearly and unambiguously
address temporary, long-term, and in-transit preservation requirements, including, but not
limited to:
sunlight, temperature, soil, dust, humidity, salt spray, corrosive atmospheres, or
other physical environment conditions.
coverings, fasteners, lines, and other components for internal and external weather
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
proofing;
charging, heating, cooling, etc., inclusive of gas storage, electric power supply, etc.;
internal atmosphere generation, regeneration, monitoring, and relieving systems, for
example, inert gas management systems;
cyclical motion in transit, for example, wave-generated movement during sea
transport;
bracing, padding, framing, chocking, etc.;
substrates, or support required to ensure in-storage and in-transit stability of
systems, system components, equipment, and material, or other discrete units or
items;
transmittal of contaminants between work areas or between work areas and storage
areas, for example, prevention of carbon steel grinding or cutting debris impact on
stainless steel elements, airborne drift of blast aggregate into vessels or machinery,
etc.;
required supports and related binding devices, for example, stools, stands, sea
fasteners, platforms, chocks, spacers, cabling, etc.;
required to ensure provision of preservation services, for example, provision of a
self-elevating work platform for periodic access to elevated fittings, gauges, man-
ways, etc.;
example, padding or other protection for external tubing, fittings, or other impact-
sensitive structures or components;
by hard and soft barriers, as required, to maintain a protective perimeter;
management regarding security management, including, but not limited to, facility
access and egress control and control of access to project goods and materials
within facility boundaries or aboard vehicles or vessels; and
6.3.18. detailed procedures for inspection and testing to verify performance of preservation
procedures and to provide for timely notice and corrective action to maintain preservation
status.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
6.3.19. The supplier’s preservation management programme scope shall encompass management
of preservation requirements, from initial transfer of ownership or management responsibility
to project scope of responsibility, through any period of temporary or longer-term storage and
through any period of transit, including transit for final delivery at point of active use or
installation.
6.3.20. The supplier’s preservation management programme shall clearly and unambiguously
address processes and procedures to ensure that storage and control of materials are
accomplished in accordance with manufacturer recommendations, specifications, and
project-specific requirements.
6.3.21. The supplier’s preservation management programme shall incorporate special precautions
to address preservation and control of valves, electrical motors and components, mechanical
and rotating equipment, piping and fittings, instrumentation, flange faces, gaskets, coatings,
insulation, and other materials. Special precautions include, but are not limited to, supplier-
specified maintenance procedures related to engines, electric motors, pumps, compressors,
etc., such as periodic shaft rotation, engine turnover, lubrication, etc.
6.3.22. The supplier shall ensure that clear and unambiguous requirements for preservation of the
system, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented in purchase orders, work authorisations, and other
communications between the supplier and sub-suppliers.
6.3.23. Where sub-supplier expertise is utilised in determination of the preservation protocol, supplier
procurement processes shall ensure clear and unambiguous documentation of sub-supplier
input into preservation management programme requirements.
6.3.24. Supplier procurement shall ensure that preservation requirements for scope of work systems,
system components, equipment, materials, and other procured goods are clearly and
unambiguously documented and that preservation requirements are efficiently and effectively
communicated to project logistics, construction management, quality, security, and other
project functional areas, as required, for efficient and effective implementation of preservation
requirements.
6.3.25. The supplier shall ensure comprehensive, clear, and unambiguous designation of sub-
supplier responsibility for execution of all preservation management programme elements,
including, but not limited to, all systems, processes, procedures, methods, ready access to
records, and provision of equipment, tools, or services essential to efficient and effective
execution of the preservation management programme.
6.3.26. The supplier shall ensure that preservation management programme responsibilities are
clearly and unambiguously defined within the project team and efficiently and effectively
implemented at all project scope of work locations. Inclusion of supplier and sub-supplier
scope of work in the development and implementation of a preservation management
programme shall be considered essential to efficient and effective preservation management
programme execution.
6.3.27. The supplier shall ensure clear and unambiguous designation of project team responsibility
for oversight and management of preservation management programme elements during
every stage of project development.
6.3.28. The supplier shall ensure that Eskom has free and unrestricted access to all preservation
records for inspection and audit.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
6.4. Quality Audits Related Conditions
6.4.1. The supplier shall maintain an accurate quality audit and related quality performance review
schedule and shall incorporate the current schedule as an attachment to the supplier CQP.
6.4.2. The supplier’s quality audit and related quality performance review schedule development
process shall be designed to incorporate consideration of information generated by
previously conducted audits and reviews, by input from project risk management evaluations
(risk register), or from Eskom or sub-supplier subject matter expertise.
6.4.3. Eskom reserves the right to oversee supplier audit programmes by participating in selected
audits as an observer and by assessing the supplier during key work stages. Eskom will
coordinate with the supplier to develop an oversight schedule aligned with the supplier’s audit
schedule.
6.4.4. Eskom will have the right to obtain access to any audit reports of audits performed by the
supplier reflected in the audit programme.
6.4.5. Eskom reserves the right to conduct independent quality audits, scheduled and unscheduled,
during all phases of the contract. The supplier shall provide all resources to support these
activities.
6.4.6. Eskom shall be given access at all reasonable times before, during, and after manufacture
and before delivery, construction, erection, and commissioning to measure, test, and inspect
the products and workmanship, as necessary, at the supplier’s premises and at Eskom sites.
6.4.7. The supplier shall obtain access for Eskom to measure, test, witness tests, and inspect
products that are being manufactured by any sub-supplier. This includes surveillances.
6.4.8. The assessments and audits shall be carried out on all new suppliers and their sub-suppliers.
6.4.9. Eskom shall have the right to participate in, or request that, a technical investigation be
launched and conducted at the supplier’s and sub-suppliers’ premises or other sites when
risk to Eskom products or service deliverables is identified.
6.4.10. Qualification requirements for supplier and sub-supplier personnel engaged in conducting
quality audits and related quality performance reviews shall be defined in the supplier CQP
and shall be in compliance with the Project Quality Personnel Qualification Specification.
6.5. Management of Nonconformities and Nonconforming Outputs Identified by Eskom
6.5.1. Nonconformity reports raised by Eskom and issued against the supplier shall be investigated
by the supplier as a matter of urgency in order to determine the root cause, corrective action
measures, as required, with implementation time frames.
6.5.2. A formal response shall be prepared in respect of the defined criteria and submitted to Eskom
for its review, evaluation, and acceptance, within a maximum of 14 calendar days from the
date of issue of the nonconformity and should be aligned with the site
requirements/procedure.
6.5.3. Eskom may, at its discretion, request a response sooner and, in any case, before the supplier
proceeding with any pending/further intervention or corrective action, as may be required by
Eskom.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
6.5.4. Should Eskom or its inspection authority/agency identify any nonconforming products during
the conduct of its audits/surveillances/inspections, the supplier shall be deemed to be in
breach of contract and shall be held liable for any repair, rework, and/or associated
replacement costs. The supplier may, in such instances, also be held liable for the full costs
associated with the conducting of follow-up audits/surveillances/inspections.
6.5.5. The nature, magnitude, and/or frequency of nonconformity and inspection defect/rejection
reports raised by Eskom or its appointed inspection authority/agency shall form the basis of
any action to rescind/withdraw the supplier’s qualification status.
6.5.6. Nonconforming outputs identified by Eskom shall be documented via a NC Report and issued
to the suppliers via the contract communication protocol. The suppliers shall investigate the
matter and respond in writing to Eskom of disposition within the stated contractual conditions.
Note: The dates for the disposition should align to contractual conditions.
6.5.7. Eskom shall identify repeat deficiencies as systematic failures of the supplier’s QMS and
shall notify the supplier of the trends. Eskom can initiate an internal audit to highlight the
system failures. The supplier with raise a Corrective Action Report and undertake Root
Cause Analysis. In such cases, QMS rectification and/ or update measures shall be taken
immediately.
6.5.8. Should the Supplier fail to respond and rectify nonconforming products within stipulated
contractual conditions. The Project Manager should apply contractual remedies in
accordance with Fidic/ NEC contract.
6.5.9. Repeated Nonconformities, if there are any identified repeat nonconformities from the same
supplier within a period of 6 months or less. This must then be escalated to the management
review committees of the BU/ OU/ Cluster/ or Divisions for adjudication. If not resolved, then
the matter must be escalated to the supplier review committee for recommendation.
6.6. Special Processes
The following requirements shall be applicable as well as additional requirements as specified in the
scope of work for the provision of the following special process services:
6.6.1. The supplier shall ensure that all processes which require that procedures be pre-qualified
or work methods and operators tested and qualified are controlled and all steps followed
before the work can commence.
6.6.2. This typically covers such activities as welding, non-destructive testing, special fabrication
techniques, coating, painting, etc.
6.6.3. All special processes (procedures and processes) shall be submitted for review and
acceptance by Eskom, accredited or certified agency. No work shall commence until these
are accepted.
Where applicable, a relevant Management System for the special process shall be certified or
approved by an accredited body and proof of certification shall be submitted to Eskom for review.
An example for this will be the Welding Management System based on ISO 3834.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
6.6.4. The supplier shall ensure that all processes which require that procedures be pre-qualified
or work methods and operators tested and qualified are controlled and all steps followed
before the work can commence.
6.6.5. This typically covers such activities as welding, non-destructive testing, special fabrication
techniques, coating, painting, etc.
6.6.6. All special processes (procedures and processes) shall be submitted for review and
acceptance by Eskom, accredited or certified agency. No work shall commence until these
are accepted.
6.6.7. Where applicable, a relevant Management System for the special process shall be certified
or approved by an accredited body and proof of certification shall be submitted to Eskom for
review. An example for this will be the Welding Management System based on ISO 3834.
6.6.8. Where samples are required for acceptance, these shall be submitted to Eskom for review
and acceptance.
6.6.9. The supplier shall ensure that all operators are suitably qualified for these processes in
accordance with the procedures, processes and/ or applicable standards/ codes.
6.6.10. The records of qualification of procedures, processes and operators shall be maintained by
the supplier in accordance with the applicable procedure or code and these made available
to Eskom at all times.
This document has been seen and accepted by:
Name Designation
Portia Mngomezulu Group Executive: Corporate Services
Mpho Dire Chief Procurement Officer (Acting): Corporate Services
Bathusi Montwedi Senior Manager (Acting): Procurement and Supply Chain Management
Sanjiv Kalicharran Senior Manager (Acting): Risk and Sustainability - Quality Management
Rolland Ngugama Middle Manager: Risk and Sustainability - Quality Assurance
Pamela Dondashe Middle Manager: Risk and Sustainability - Quality Assurance
Date Rev. Compiler Remarks
Specification was due for revision and in addition, to
align the requirements with the latest Eskom business
October 2025 4 SA Sambo
processes and systems. Including updates on
numbering of the document.
October 2021 3 SA Sambo Specification was due for revision and in addition, to
align the requirements with the latest Eskom business
processes and systems.
October 2018 2 SA Sambo Specification reviewed to be aligned with the
requirements of ISO 9001:2015
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
Date Rev. Compiler Remarks
March 2016 1 SA Sambo Specification was due for revision and also to
repackage the requirements and tender returnable
documents into four categories.
December 2011 0 A Hunter New document
The following people were involved in the development of this document:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
B.2 Documented information for Control of Externally Provided Processes, Products and Services - Must include criteria for evaluation, selection,
Indicate with an
105658000 (x) as applicable
Specification or (-) if not
Applicable
Pre-contract award quality requirements x
(*Select Only Applicable Category). NB: Not more than one category must be selected. Also indicate
whether site assessment is applicable.
Category 1 (refer to clause 3.5.-105658000) -
Category 2 (refer to clause 3.5.-105658000) -
Category 3 (refer to clause 3.5.-105658000) X
Category 4 (refer to clause 3.5.-105658000) -
Main Supplier and Sub-supplier Capability and Capacity Assessment (refer to clause 3.-105658000) -
3 post-contract award(eskom)
Cell A2: Occupational Health and Safety Baseline Risk Assessment Substation ProjectsTemplate
The aim of the Health & Safety (H&S) specification is to provide principal contractor/s and suppliers
with:
compliance to legal and Eskom Holdings (NTCSA) H&S requirements.
contract.
NTCSA strives to exceed the minimum standards prevailing in the construction industry and requires
full commitment from all parties to be pro-active to achieve best H&S business practice.
This H&S Specification is intended for principal contractor and their contractors to develop a H&S
plan that meets the specified requirements.
2.1 Scope
This H&S specification sets out the minimum legal and NTCSA requirements for construction work
that is specific to the scope of work, site, and type of project.
2.2 Purpose
To indicate to principal contractor the H&S requirements on the project, upon which their planning
for the management of H&S will be based on and thus produce their H&S plan.
2.3 Applicability
This specification is only applicable to the project as mentioned on the first page, title all principal
contractors, contractors, service providers, suppliers and all the activities and processes carried out
for and on behalf of PD.
This specification shall be implemented from the date of approval.
Parties using this specification shall apply the most recent edition of the documents listed below.
3.1 Normative
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
Standards – SANS)
Note: only latest documents must be used and all pertinent OHS Regulation as per the scope of
works must be included. Remove this note prior authorising this specification.
3.2 Informative
[1] ISO 45001, Occupational Health and Safety Management Systems-Requirements
[2] ISO 9001, Quality Management Systems- Requirements
[3] Construction Regulations of 2014
[4] Council for the Built Environment Act
[5] Project and Construction Management Profession Act
Authorised person: a competent person who has been given permission in writing to perform
specific duties and responsibilities in terms of the Operating Regulations for High Voltage Systems.
Baseline risk assessment: (32-520) baseline operational risks refer to the H&S risks associated
with all standard processes, as well as routine and non-routine activities in the business.
Critical Lifts: (1) any lift weighing in excess of 20 tons, (2) any lift involving a crane suspended work
platform (man cage), (3) any lift over critical operating and/or process equipment and (4) any lift that
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
exceeds 85 % of the crane’s load chart (5) any lift that utilises more than one lifting device (Tandem
Lift).(6) Load transfers.(7) night lifting.
Eskom Holdings (NTCSA) Requirements: Eskom Holdings (NTCSA) requirements, which evolve
from directives, policies, standards, procedures, specifications, work instructions, guidelines, or
manuals.
Hazard identification: the identification and documenting of existing or expected hazards to the
health and safety of persons, which are normally associated with the type of construction work being
executed or to be executed.
Medical surveillance: a planned programme or periodic examination (which may include clinical
examinations, biological monitoring, or medical tests) of employees by an occupational health
practitioner or, in prescribed cases, by an occupational medicine practitioner.
Method Statement: is a written document detailing work procedures and sequences of operations.
On Site/Site: any workplace where the contractor or his employees perform construction related
work as agreed contractually with the client.
Planned Task Observation: an independent observation made during the planned period in which
the task is being executed.
Pre-Task Risk Assessment: a meeting held prior to the commencement of the day’s work with
relevant personnel (client representative included) associated with the task at hand.
Risk Assessment: a programme to determine any risk associated with any hazard at a construction
site in order to identify the steps needed to be taken to remove, reduce, or control such hazard.
H&S File: a file or other record in permanent form, containing the information on the H&S
management system during construction including all information relating to construction phase after
the handover to Client.
Safe Work Procedures: a series of specific steps that guide a worker through a task from start to
finish in a chronological order. Safe work procedures are designed to reduce the risk by minimizing
potential exposure.
Abbreviation Explanation
AIA Approved Inspection Authority
COIDA Compensation for Occupational Injuries and Diseases Act
CR Construction Regulations
DMR Driven Machinery Regulations
DSTI Daily Safety Task Instruction
EA Environmental Authorization
ECO Environmental Control Officer
FAS Fall Arrest Systems
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
Abbreviation Explanation
GSR General Safety Regulations
RHCA Regulations for Hazardous Chemical Agents, 2020
H&S Health and Safety
HIRA Hazard identification and risk assessment
HV High Voltage
LDV Light Delivery Vehicles
LMI Lifting Machine Inspector
LME Lifting Machine Entity
LTIR Lost Time Incident Rate
NEC New Engineering Contract
NEMA National Environmental Management Act
NTCSA National Transmission Company South Africa
NQF National Qualifications Framework
OHNP Occupational Health Nursing Practitioner
OHS Act Occupational Health and Safety Act No.
OHS Occupational Health and Safety
ORHVS Operating Regulations for High Voltage Systems
PPE Personal Protective Equipment
PTO Planned Task Observations
RSA Republic of South Africa
SANAS South African National Accreditation System
SANS South African National Standards
SACPCMP South African Council for the Project & Construction Management Professions
SAQA South African Qualifications Authority.
SDS Safety Data sheets
SHEQ Safety, Health, Environment Quality
SETA Skills Education Training Authorities
SWP Safe Work Procedure
PD Project Delivery
VFL Visible Felt Leadership
Manages the contract signed with the principal contractor and ensures that H&S specifications are
developed and issued with tender enquiries, and that the principal contractor’s H&S plan is approved
prior to commencement of work. He must ensure that applicable legal and other requirements are
complied with by the principal contractor and (if applicable) their contractors. The project manager,
thus takes the overall accountability of this project as
Is responsible for the overall management of the project design as well as ensuring the management
of the compliance of the completed works to the design during and after construction on site.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
Provides assurance, advice, and support to the project in the management of the H&S issues on the
project. They will also assist in the development of project’s H&S Specifications which will be issued
with enquiry documents, and that the principal contractor’s H&S plan is submitted; evaluated and
approved. They will be responsible for auditing and ensuring compliance to legal requirements. The
H&S Senior Advisor shall approve the principal contractor H&S plan in all projects that does not have
a CWP.
7.1 Visible Commitment
Visible commitment is essential in providing a safe work environment. managers, supervisors, and
employees at all levels must demonstrate their commitment by being proactively involved in the dayto-day operations, in particular H&S aspects of the project / contract.
A minimum of one (1) Visible Felt Leadership engagement (VFL) per month shall be conducted by
the contractor’s project manager. The contractor General Manager/Chief Executive or executive
representative shall one (1) VFL quarterly that shall be submitted to Client Project Manager.
7.2 Designers
The designer of a structure must comply with Construction Regulations 6 and ensure that cognizance
is taken of ergonomic design principles and foreseeable constructability health and safety risks
during construction and life cycle of the structure.
7.3 Principal Contractor’s Accountabilities
a. The principal contractor shall comply with provisions of Construction Regulations 7.
b. Where a principal contractor procures the services of a contractor, the principal
contractor shall first inform the client. Such contractor shall also comply with relevant
sections of this H&S specification.
c. The principal contractor must demonstrate how activities of various contractors will be
coordinated to mitigate the risks.
d. The principal contractor shall ensure that his/her H&S plan is approved by the client
before gaining access to site. The same principle will apply to its contractor, where he/she
shall approve his/her contractors H&S plan.
e. A comprehensive & updated list of all contractors on site, also indicating the type of work
being done.
f. The principal contractor shall coordinate, consolidate, and submit H&S performance and
that of contractors on the last day of each month to the client.
g. The principal contractor must ensure that their senior management conduct VFL, at least
once a quarter.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
h. The principal contractor must incorporate the client's induction into their induction and
induct their contractors before site access. The principal contractor shall keep all
induction material including registers.
a. The principal contractor shall comply with provisions of Construction Regulations 8.
b. The principal contractor shall appoint one (1) full-time competent construction manager
responsible for a single site. In a case where a construction manager is not available, an
alternate construction manager shall be appointed in writing for a specified duration.
c. Having considered the size of the site one or more assistant construction manager shall
be appointed in writing.
d. The principal contractor must, in writing, appoint one Full Time safety officer in
accordance with the requirements of Construction Regulations 8(5).
e. Construction supervisors and their assistance must be appointed in accordance with
Construction Regulations 8(7) & (8) respectively.
f. The appointed safety officer(s) shall be registered with SACPCMP.
The appointment of a registered or non-registered construction manager shall be
done in accordance with the provisions of the PD SACPCMP Registration Categories
attached on the Appendix A, annexure B.
Note: No construction work must commence or continue without a competent construction
manager(s), a supervisor(s), being on site.
This document is under revision control and is valid for the duration of the works and will be
amended, as and when necessary, as requirements are being amended and therefore it will be
required for the principal contractor and contractor’s H&S plan to be amended accordingly.
Conformance to this document shall be via regular safety inspections and by Monthly Audits.
9.1 Related/Supporting Documents
Annexure A – Eskom Holdings (NTCSA) SHEQ Policy Statement 32-727
Annexure B – 20241010 SACPCMP Registration Categories
Annexure C – Contractor Manpower Sourcing and Verification
Annexure D – Pre-Task Planning Template
Annexure E – Flash Report template
Annexure F – Portable Toilet Specification
Annexure G – Contractor OHS File Handover Record Template
Annexure H – PD Loading and Offloading
Annexure I – Tender Evaluation Criteria
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
Annexure J – Site Readiness Evaluation Criteria
Annexure K - Health and Safety Requirements Acknowledgement
Annexure L - Appointments and Competencies Guide_559-1762006876
Project Details
9.2 Scope of Work
The following civil works needs to be done for Kwagga Substations access road.
Refurbish 4m wide tar road
Clean open-cut drains and gutters that run next to the road
Conduct DCP and Troxler
The following civil works needs to be done for Rigi Substations access road.
Refurbish and construct 6m-9m wide tar road
Clean open-cut drains and gutters that run next to the road
Conduct DCP and CBR test
Place vegetation outside the gate of the substation
Construct cut-off drain outside the gate of the substation
Location: Kwagga and Riggi Substation
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
9.3 The Client Project Organogram:
Senior Manager
Projects
Harrish Mahabir
Programme Intergration Acting Senior Safety Risk Construction H&S
Manager Manager Advisor H&S Manager Agent
Ofhani Matsea Sandile Mokoena Linda Shabalala Lindiwe Masoeu N/A
Project Manager Project Scheduler H&S Officer
Lungi Mdletshe Nyamunzhedzi Musetsho Sherlley Mokone
Project Site Supervisor Cost Engineer Risk Advisor coordinator
Nanda Moonsamy
Wisani Mabaso Alfred Mashala N/A
Project Officer Quantity Survey
Rebone Mkhonto Kulani Maringaa
9.4 Principal Contractor Organogram
The principal contractor shall provide an organisational organogram related to this project, listing all
the levels of responsibility from the Chief Executive down to the supervisors responsible for the
project. The organogram must list the names of appointees and their roles and responsibilities
including the statutory requirements appointees. All organograms shall be updated timeously when
appointments are changed and filed in the project H&S file.
For the duration of the contract, the principal contractor shall ensure that competent persons are
appointed in writing in terms of the requirements of the OHS Act and its Regulations; and
or other statutory and Eskom Holdings (NTCSA) requirements and that all their appointees are made
aware of their accountabilities and responsibilities and have been suitably trained in terms of their
appointment.
The principal contractor shall notify in writing in a form similar to annexure 2 the relevant Provincial
Director (Labour Centre) of the Department of Employment and Labour of the intention to carry out
construction work as defined in the Construction Regulations 4, at least 7 days before construction
work is to be carried out. No construction work shall commence without a proof of submission of
such notification to the client.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
11.1 OHS Act Section 37 (2) (Legal) Agreement
a. An OHS section 37(2) agreement shall be signed between the client and the principal
contractor at the time of contract award.
b. The original copy of an OHS section 37(2) agreements shall be retained by the contractor
and a copy retained by the client project manager.
c. A copy of OHS section 37(2) agreement must form part of the respective contractor’s H&S
file.
11.2 CR 5(1)(k) Appointment
a. At contract award the principal contractor shall be appointed in writing by the PD Project
Manager for the construction site. Therefore, site access shall be granted once all the
contractual requirements are met.
b. A copy of CR 5(1)(k) appointment must form part of the respective contractor’s H&S file.
11.3 Designated employer, Sec 16(2) and other competencies appointments
The principal contractor shall ensure that a designated employer is appointed in writing for the for
the duration of the project.
The principal contractor shall ensure that competent persons are appointed in writing for OHS
statutory and non-statutory functions in line with their organisational structure. See Annexure L
The principal contractor shall ensure that the appointees understand their roles, responsibilities and
accountabilities. Copies of relevant appointments shall be kept on an OHS site safety file.
The scope of training shall include, but not limited to, the type of work being performed and the
relevant procedures. Where training is provided by the external service providers, the principal
contractor shall ensure that the service providers are accredited by SAQA or QCTO (Appropriate
qualifications and training registered in terms of the National Qualifications Framework Act No. ).
The principal contractor must demonstrate how he/she intends managing training/awareness within
their organisation including method of informing visitors and other persons entering the site about
hazards prevalent onsite.
Persons with foreign qualifications and registrations to convert these to equivalent local registrations
in that level or category (this shall be in accordance with SAQA and SETA requirements). The letter
from SAQA shall form part of the tender and site readiness submissions to PD.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
The principal contractor shall develop an OHS Policy authorised by their Chief Executives that states
overall OHS objectives and commitment to improving OHS performance and must be conspicuously
displayed and shared with all stakeholders.
The principal contractor shall comply with relevant legal and other requirements as part of the
contract. Expenses to the principal contractor, which result from such compliance, as well as any
site-specific requirements, will be for the principal contractors’ account.
Where the principal contractor appoints another contractor(s), the same roles, and responsibilities
in relation to the contractor as the client has in relation to the principal contractor shall apply.
The client reserves the right to stop work and issue a non-conformance report and/ Prohibition
notice(s) whenever H&S violations are observed from the principal contractors and their contractors,
after engaging and making both aware of such. Expenses incurred because of such work stoppage
and standing time shall be for the principal contractor’s account. Any nonconformances/findings/observations found during the audits/inspections on the contractor shall be
raised and discussed with the relevant principal contractor (with whom the contractor is contracted
with).
15.1 Legal and Other Requirements
The principal contractors shall comply with the relevant applicable legislation, specifications, and
standards in accordance with the scope of the project.
The principal contractor shall compile a legal register listing all applicable legislation and standards
that may have an impact on the scope of work that they are performing on the construction project.
The register shall be updated as and when there are amendments.
The Bill of Rights in the Constitution of the Republic of South Africa is clear on the rights of
children, especially when it comes to child labour. Child labour shall not be permitted in any of
NTCSA, PD sites.
The principal contractor shall develop a Risk Assessment in line with Construction Regulation 9 in
alignment to Eskom/NTCSA, 32-520 procedure.
Detailed Risk Assessment must be conducted to ensure that all the applicable scenarios are covered
and documented per site activities including practical controls. High Risk Activities
When the principal contractor and/or his/her contractors are working in an area where a high health
and safety hazard exists, the principal contractor shall:
a) Develop a SWP.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
b) Ensure that permanent and adequate supervision is available for the duration of the work
performed.
c) Work within visible earths (Standard Line Construction Method).
d) Ensure the use of safety standbys in areas of high-risk activities, and activities that fall within
the scope of the permit to work system.
e) Provide, erect and maintain the required barricading, lighting, flags, flashing lights, or other
safety control equipment to enable operations to proceed in a safe manner.
f) Maintain defined access ways, which are clear of obstructions, to allow for emergency vehicle
entry.
g) Provide any temporary protective shielding required for protecting nearby operations from
the construction activities, at their own cost.
a. To ensure the safety of workers, visitors and other persons who may be affected, the
operating regulations for high voltage systems shall apply during construction of high voltage
apparatus (construction of transmission/distribution lines) or working in live yard inside a
substation.
b. The principal contractor shall ensure that workers in prohibited areas inside a sub-station are
under supervision of an authorised person, under a work permit. When an authorised person
resigns from a company and is employed by another company, his authorisation shall expire
immediately.
c. The authorised person shall be present throughout the operations.
Reference: ORHVS, 240-114967625 and Power Delivery Operating Assessment,
Authorisation and Training Standard, 240-70413865.
The principal contractor shall ensure that the submitted tender adequately makes provision for the
cost of H&S.
Note: the costing for H&S must be itemised based on the overall scope of the project e.g.: resources,
provision of PPE, occupational hygiene, occupational health, etc.
The principal contractor shall not permit any person to enter the construction site where their health
and safety may be at risk. Notices at every entrance prohibiting the entry of unauthorised persons
shall be posted:
a. No one should enter the construction site without being inducted. The principal contractor
shall demonstrate how site access shall be manage on site.
b. Entering or leaving the site shall only take place at official access control points and may only
be done via the official designated walkways.
c. Where construction line is being constructed the principal contractor shall ensure that:
i). Members of the public are not allowed to be in the proximity where the activities are
being executed.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
ii). Domestic animals are managed not to be in the proximity where the activities are being
executed.
Symbolic safety signs shall comply with the requirements of SANS 1186.The display of the following
signage is mandatory:
a. The principal contractor sign shall be posted at their site offices and shall have the name
and contact details of the: Construction Supervisor; Health and Safety Manager/ Officer; First
Aider; Health and Safety Representative and Evacuation warden, Construction Health and
Safety Agent and Construction Permit (where applicable). Emergency numbers, principal
contractor name (including a logo), construction manager and contact number.
b. The Contractors shall provide signage in accordance with the scope and work area.
c. All safety and warning signs shall be always obeyed.
Site facilities shall be established and maintained by the principal contractor. The facilities include
but are not limited to the following (refer to OHS Act, Construction Regulations 30). See also
Annexure F for portable toilet specifications. The design of the toilet should not expose employees
to splashes of other people’s human waste.
Principal contractors shall in their H&S plan, factor how they would safeguard members of the public
against their activities during the project.
24.1 Life Saving Rules
The Eskom Holdings (NTCSA) Life Saving rules applies to NTCSA employees, agents, consultants,
contractors, and visitors. Visitors to NTCSA sites are expected to respect and comply with these
rules. Anyone who refuses to do so may be instructed to leave to leave NTCSA premises
immediately. Failure to adhere to these rules will be regarded a serious transgression, and it is
expected that the employer will take appropriate disciplinary action. The client also reserves the right
to suspend the contractor’s activities pending the outcome of such disciplinary processes.
These rules are enforced to prevent serious injury or loss of life among employee, labour broker or
contractor working in any area within Eskom Holdings (NTCSA) area.
The rules are:
Rule description of rule
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
Open, isolate, test, earth and create an equipotential zone
Before touch
To ensure a safe electrical work environment, no person may work/operate on, around
or near any electrical network, line or apparatus, electrically connected to the power
Rule 1
system and/or electrically charged and/or not electrically charged unless if trained,
authorised, competent and supervised. The equipotential zone is only applicable for
work being done on medium and high voltage apparatus.
(That is plant, any plant operating above 1000 V)
Hook up at height
Working at height means any work performed above a stable work surface or where a
person puts himself/herself in a position where he/she exposes himself/herself to a fall
Rule 2 from or into.
Working at height is a significant part of work in NTCSA and is regarded as a high-risk
activity, as a result, all precautions must be taken to prevent incidents while working at
height.
Buckle up
Where required, the proper wearing of seat belts for any driver, operator and passenger
Rule 3 is mandatory in all vehicles/equipment when driving and/or travelling for NTCSA
business purposes.
.
Be sober
No person who is under the influence or who appears to be under the influence of
Rule 4
intoxicating liquor or drugs will be permitted to enter or remain on a NTCSA site conduct
NTCSA business or drive/operate a vehicle/equipment for NTCSA business purposes.
Ensure that you have a permit to work
Rule 5 No person shall work without the required Permit to Work (PTW). This includes driver’s
license and other statutory permits
Ensure safe live working
To ensure safe live work: Each live worker shall ensure all live work basic principles are
adhered to, as outlined (for the method being used) in the High Voltage Live Working
Rule 6
Standard; Observe and maintain the Minimum Approach Distance; Only perform live
work and tasks that are authorised for and that are documented in the respective Task
Manual.
24.2 Smoking
Smoking is only permitted at designated areas in accordance with the requirements of the
smoking policy (32-1126: Eskom Holdings (NTCSA) Smoking Policy). Add to the appendix A.
24.3 Cellular Phones
A contractor shall develop and implement a risk-based cell phone policy for a particular
construction site. Cellular phones shall not be used in areas where their usage is prohibited.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
24.4 Fire Extinguishers
A Principal Contractor shall have a layout plan (site offices, laydown area) where fire-fighting
equipment is located. Fire extinguishers should be inspected monthly and be maintained annually
by a competent service provider. These records shall be kept in the project safety file.
24.5 Vehicles and Traffic Rules
a. The principal contractor shall ensure that the driver of the vehicle has a valid driver’s licence.
b. Principal contractor shall ensure that drivers and passengers wear seatbelts while travelling
in a motor vehicle.
c. No passengers shall be permitted to be transported at the back of trucks or light delivery
vehicles (LDV).
d. Passengers shall only be permitted to be transported at the back of such vehicles if fitted with
a specially designed crew cab with appropriate seating and seat belt per passenger, by the
manufacturer and manufacturer appointed fitment centre. The test certificate shall be
submitted for consideration to the client.
e. Where a vehicle licence condition stipulates the number of persons to be transported on the
vehicle, such number shall not be exceeded.
f. The principal contractor shall ensure that the vehicles are inspected daily and maintained
regularly as per the manufacture’s specification.
24.6 Substance and Drug Abuse Management
a. The principal contractor must develop a substance abuse management procedure to manage
substance abuse on site. The procedure shall be in line with the client substance abuse
management procedure were applicable. Eskom Holdings (NTCSA) Substance Abuse
Procedure 32-37.
b. All testing equipment shall be calibrated as per the manufacturer’s recommendation and the
calibration be available on the safety file.
c. The alcohol testers must be trained and appointed in writing.
The principal contractor shall conduct a daily pre-task risk assessment with employees involved with
the task, such as DSTI. This assessment will be the basis of daily pre-job briefings or toolbox talks
before work begins, highlighting critical steps from the SWP to ensure safety. Proof of
communication and confirmation of understanding will be recorded and kept at the job site during
execution. The signed pre-task risk assessment form shall be filed in the safety file.
Upon receipt of the task for the day, the principal contractor manager or his/her assignee the site
supervisor, shall perform a pre-task planning in accordance with Line Construction; Substation
Works and 559-1432317009 Rev 1, Pre-Task Planning Template, see, Annexure D.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
The principal contractor shall compile a project/ site-specific SWP for all the high-risk activities as
identified in the risk assessment and scope of work, which will be submitted to client. Proof that the
SWP’s are discussed with all employees on site should be available in the site safety file.
The construction manager / supervisor shall conduct Planned Task Observations (PTO).
PTOs shall be conducted in such a way that the employee is observed against the actual steps of
the safe work procedure (SWP)/ method statements and marked against compliance with each step.
This will assist in determining employee competence and compliance. Record shall be kept. The
findings raised on the PTOs must be addressed/discussed with all employees on site to ensure
conformance and adherence to safe work procedures and method statements.
The minimum items that must be in the PTO but not limited to:
a. Project name.
b. Title of the SWP, reference number and revision number.
c. Specific activity.
d. Steps.
e. Safety Steps.
f. Critical steps.
g. Follow-up action.
h. Observation conducted by (full name).
i. Designation (e.g., supervisor).
j. Individual/Team observed names.
k. Date of observation.
l. Signature.
Work at Elevated Positions and Roof Work
The Principal Contractor shall ensure that all work performed at elevated positions conform to
the requirements of the Construction Regulations, the relevant Unit Standard (US) and 32-418
(Working at Height Procedure).
assessments will be compiled, implemented, reviewed, and communicated to all employees
working at heights.
at intervals to be determined by the principal contractor, and taking into consideration:
a. Incident trend analysis, or new/revised technology.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
b. Changes to scope of work, changes to work methods/procedures/equipment, etc.
weather.
safety harness shall be worn when working at an elevated position. All FAS equipment in use
must meet the specifications outlined in the OHS Act and the following applicable standards:
a. SANS 50361:2003
b. SANS 50363:2003
c. SANS 50353-1:2003
d. SANS 50354:2003
e. Eskom Work at Heights Standard 32-418
f. Eskom Personal Protective Equipment (PPE) for Work-at-Heights Specification 240-
Working in elevated positions shall only be carried out under the supervision of a competent
person in accordance with US 229995.
possible:
a. Fall protection equipment shall comply with Unit Standards and other recognised
international standards.
b. The Principal Contractor and/or his contractor shall compile a fall protection equipment
inspection, testing and maintenance procedure (Refer to SANS 50365 and manufactures
requirements for safe use and for inspections).
the protection of persons working below. A drop zone shall be established with barricading and
necessary signs.
29.1 Ladders (Portable)
a) Ladders used on the site shall comply with the OHS Act and Regulations, the relevant
SANS standards, or other recognised international standards.
b) Damaged ladders shall be clearly marked and quarantined and removed from the project
site.
c) Prior to work being performed, an adequate risk assessment shall be conducted, and
work shall be conducted in accordance with General Safety Regulation 6 and 13A and
Construction Regulation 10 of the OHS Act
29.2 Training and authorization
a) Every employer shall ensure that no person engages in any activity in relation to work at
heights unless they are competent to do so.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
b) Only training providers that use competent training instructors and assessors who are
SETA-Accredited and SAQA-registered in terms of the relevant unit standards shall be
used.
c) All persons who work at heights or who are required to do rescue at heights shall receive
three days of Fall Arrest System (FAS) training and two days of rescue training in
accordance with the Unit standards 22998 and 229995.
d) The Contractor must ensure that all persons who work at heights and those who will be
required to do rescue at heights shall receive training according to the relevant unit
standards. As a minimum, individuals who work at height and are not responsible for
performing a rescue must undergo three days of FAS training (Unit Standard 229998)
and rescuers must further undergo two days rescue training in accordance with the Unit
Standard 229995. Rescuers must be appointed in writing for the site/project.
e) Official FAS training shall not have an expiry date on the certificate.
f) Only the training date shall be indicated on the certificate.
g) Official rescue training shall expire every three years from the date of issue.
h) The principal contractor shall ensure that there is a Level (insert level 2 or 3 depending
on the SoW and remoteness of the site) First Aider trained for every team working at
height. See Annexure L - all line construction First Aider shall be level 3
NB: All work at heights appointments and competency certificates shall be kept in the Health and
Safety File.
The principal contractors and contractors shall identify the occupational stressors which could
include exposure to chemical and biological hazards, noise, dust, vibration, heat, etc., to which any
person may be exposed because of his work activities.
30.1 Occupational Hygiene Management Program
Principal Contractors and contractors shall develop, implement, and maintain an occupational
hygiene management programme to ensure that the occupational hygiene stressors are identified
assessed (monitored) and controlled. The occupational hygiene programme shall include, but not
limited to the following elements:
a. Occupational health risk assessment as a foundation.
b. Occupational hygiene monitoring program. Monitoring shall be performed by a SANAS
accredited AIA.
c. Communication of occupational hygiene results and requirements.
d. Conduct awareness trainings and keep registers; and
e. Keep Occupational Hygiene surveys reports for a period of 40 years.
Where there are occupational hygiene stressors, principal contractors and contractors shall ensure
that occupation surveys are conducted to assess stressors. These programs may include but not
be limited to:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
a. Hearing Conservation Programme.
b. Heat and cold stress Management Program.
The principal contractors and contractors shall report to the Department of Employment and Labour
on occupational hygiene milestones (e.g., crystalline silica). Evidence of reporting and copies of
such reports shall be made available to the client senior advisor H&S / H&S officer.
Copies of all occupational hygiene surveys conducted by the principal contractor and contractor shall
be submitted to PD Management/Occupational Hygiene Practitioners for information and record
keeping.
The principal contractor shall provide and adhere to effective monitoring procedures. These
procedures shall include the planning, carrying out and recording of the results of the measurement
programme. This is to confirm the effectiveness of the implemented control measures, and the
results shall be made available to the Contracts Manager/Employer’s Representative on request.
Note: Principal contractors and contractors are responsible to measure and monitor all Occupational
Hygiene stressors as contemplated in the Occupational Health and Safety act 85 0f 1993.
30.2 Medical Surveillance Programme
The Principal Contractor and contractor shall ensure that their employees are registered on a
medical surveillance programme and are in possession of a valid medical fitness for duty certificate
specific to the construction work to be performed. The Fitness for duty certificate shall be in form of
Construction Regulation, Annexure 3, and be relevant to the type of work (risk based) that the
employee will be exposed to.
The principal contractor and contractors shall ensure that employees have undergone pre-entry
medical examination before starting work on site. No employee shall access site without a valid
medical fitness for duty certificate.
The principal contractor and contractors shall ensure that employees undergo a periodic medical
examination as and when a need arise.
The Principal Contractor and contractors shall ensure that employees undergo an exit medical
examination at the end of the project or when the service of the specific employee has been
terminated or has expired.
Note.: The client will only accept medical surveillances conducted by an Occupational Health
Practitioner who holds a qualification in occupational health and registered with Health Professions
Council of South Africa (HPCSA).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
30.3 Pre-Existing / Current Medical Condition
30.3.1 Disclosure of pre-existing injuries or medical conditions
A pre-existing condition as defined by the OHS Incident Management Definitions and Classification
Parameters Standard (240-131838225), is a medical condition/medical impairment as a result of an
incident arising out of, and in the course of employment, shall be considered:
a) Non-work-related if the incident arises solely because of a pre-existing medical
condition/medical impairment and if a worker without such a condition/medical impairment
would not have suffered such an incident; or
b) Work-related if the incident arises where the pre-existing condition/medical impairment may
have been a contributing factor.
Note 1: Principal contractors are to follow their own processes and procedures for classification. At
a minimum, the decision about the impact/implication of such pre-existing medical condition/medical
impairment must be confirmed by an occupational medicine practitioner (as defined in the OHS Act,
section 1).
Pre-existing medical conditions can include health issues such as cancer, diabetes, lupus,
depression, acne, hypertension, asthma, arthritis, ulcerative [Allergies] colitis etc or just about any
other health condition such as previous medical operational condition in any part of the body.
An injury are any old injuries that existed prior to the work injury that may or may not have fully
healed. Some workplace environments could aggravate pre-existing conditions even if they would
not necessarily have caused a new condition in an otherwise healthy individual. Examples may
include amongst others, traumatic injury worsening back pain, joint pain (condition), sore neck, knee
injuries etc.
30.3.2 A prospective employer / Supplier expectations/ duties
A prospective employer / supplier shall:
a) request a prospective worker to disclose all pre-existing injuries or medical conditions existing
during the period of the employment process that could reasonably be expected to be
aggravated by performing their employment related duties.
b) request disclosure in writing and this request must be accompanied by details of the nature
of the duties that are subject to the employment.
c) advise prospective workers that if they knowingly supply false or misleading information, they
will not be entitled to compensation or damages under the Compensation for Occupational
Injuries and Diseases Act, Act for any event that aggravates the non-disclosed
pre-existing injury or condition.
d) ensure that pre-existing or current condition is part of:
i). Individual employment contract. Because the contract defines the terms and
conditions of employment
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
ii). Included in the employment induction.
iii). Person Job Specification shall be developed to have a portion where the individual
when visiting the occupational medical practitioner, it has been completed by the
employer, employee and the medical practitioner can complete the document.
iv). The employee shall reveal any pre-existing or current medical condition to the
Occupational Medical Practitioner prior the assessment.
v). Part of toolbox talk at least monthly, and awareness conducted more often, and
vi). Records shall be kept.
30.3.3 A prospective contractor employee duty
A prospective employee must, where requested in writing by a prospective employer, disclose all
pre-existing injuries or medical conditions of which they are aware of, that could reasonably be
expected to be aggravated by performing the employment related duties. If the prospective
employee is engaged before making the disclosure (or being requested to make the disclosure),
his or her entitlement to compensation is unaffected.
However, if the prospective employee does not disclose pre-existing medical condition or injury,
this may have an impact on the future management of incidents in particular the work relatedness
or not of an incident which may be attributed or not to pre-existing conditions.
30.3.4 Key considerations for employers
Employers considering implementing changes to their employment conditions and processes in
relation to these amendments shall note:
a) it is the prospective employer's duty to request disclosure of pre-existing injuries or medical
conditions from prospective workers during the pre-employment, periodic and post
screening process, and such information shall be kept confidential.
b) when providing details of the nature of the duties that are subject to the employment, it is
important that this information is accurate and provides specific details of the nature of the
duties. The prospective employee must receive information that will enable them to make
an informed decision about whether their pre-existing injury or condition might be
aggravated by the duties.
c) if the Workers' Compensation Commissioner has previously provided a copy of the
employee's claims history summary the employer shall not:
i). disclose to anyone else the contents of or information contained in the
summary.
ii). give access to the document to anyone else.
iii). use the contents of or the information contained in the summary for any
purpose other than for the purposes of the employment process (penalties
apply).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
d) changes to employment conditions and processes should be made in consultation with the
employer's human resources or advisor and employee representative. Employers who may
have queries concerning equal employment condition and processes should seek
independent advice.
e) employers shall keep accurate records relating to this disclosure as this information will be
requested where applicable during the claim determination process.
f) The employer shall follow their own disciplinary procedure and share the outcome with the
client.
Note:
I. The employer shall ensure that the employees are not exposed or expected to execute
an activity that will exacerbate the pre-existing or current medical condition. Risk
assessment shall be conducted to determine the area where the individual shall be
expected to execute the duties.
II. The pre-existing or current medical condition shall be applicable to new or current
employees within a specific employer.
III. The employer shall manage all the pre-existing or current medical condition (this
include referrals medical conditions) as per legal requirements as all information shall
be kept private and confidential all the time.
30.4 Emergency Care
A list of emergency numbers (local emergency numbers and Eskom Holdings (NTCSA)
ER24(084 124/010 205 3400) numbers) shall be posted where it is visible in the office’s places such
as information H&S board, eating area etc. The principal contractor and contractor(s) shall ensure
that all employees are familiar with the emergency numbers. Where the principal contractor or/and
contractor(s) has established their own contract with a specific service provider, those numbers must
be part of the induction and be used in conjunction with local or Eskom Holdings (NTCSA) numbers.
The principal contractor must make clear to the employees that in any event one of the numbers
must be used or the combination to ensure that the life of the individual is preserved.
30.5 Employee Assistance Programs (EAP)
The contractor will engage the local clinics on HIV/AIDS Awareness programme. This will include
voluntary counselling and testing (VCT) of individuals, with chronic illnesses such as diabetes;
hypertension; HIV/AIDS awareness training. Ensure access to ongoing support for affected
individuals. The Contractor shall communicate the programme to all personnel.
30.6 Rehabilitation
The principal contractor and contractor(s) shall ensure rehabilitation of employees injured where
rehabilitation is required.
The treating Doctor/Hospital will recommend and refer. The principal contractor must comply with
recommendations, communicate with employee and provide transport according to the planned
appointment.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
The process shall continue until the rehabilitation of an employee is declared fit by the
Doctor/Hospital.
30.7 Compensation of Occupational Injuries and Diseases Act (COIDA)
The principal contractor and contractor(s) shall submit a valid letter of good standing with the
compensation fund or a licensed compensation insurer relevant for the construction sector.
a) The principal contractor shall provide a site-specific emergency preparedness and
response plan of which it shall include the specific activities being executed for site and
offices and submit this plan to the client for review.
b) The Emergency Preparedness Plans must be relevant to the scope of works and to the
prevailing surrounding environmental risks.
c) The principal contractor shall ensure that all the employees are fully conversant with this
plan.
d) The Principal Contractor shall plan, conduct emergency drills at specific intervals and
identify areas for improvement. The report shall be written and action plan where
applicable be developed and all the records shall be made available for inspection/audit
by the client and/or authorities.
e) When preparing worksite Emergency Preparedness Plans, cognisance must be made
as to the locality of the site and the response time for the emergency services. Where
sites are remote, contractor management shall ensure that enough employees are
trained in the various disciplines to be able to afford prompt response attention.
Contractors shall develop a fire safety procedure for the office/ campsite, which must meet the
requirements of the local authority fire department and Section 9 of the Environmental Regulations
for Workplaces.
The principal contractor must develop a comprehensive site layout plan with the following as a
Name list of all contractors’ employee on site:1 To be supplied to the Security In following format Department before
Important Dates
Source: SHEQ FOLDER.zip (unknown){"closingDate":"28 July 2026","briefingSession":"{"date":null,"time":null,"venue":"ion and confirmation of understanding will be recorded and kept at the job site during","is_compulsory":false}"}
Contact Information
Source: SHEQ FOLDER.zip (unknown){"name":null,"email":"[email protected]","phone":null,"department":null,"address":"his EMPr document only caters for the scope of work contained in it. Any activities"}
Evaluation Criteria
Source: SHEQ FOLDER.zip (unknown)string or null
Technical Specifications
Source: SHEQ FOLDER.zip (unknown)The refurbishment of the access roads at Kwagga and Rigi Substations is required due to
the deterioration of the existing road surfaces. The proposed works will improve road
condition, enhance user safety and comfort, and extend the service life of the road
infrastructure.
Kwagga Substation
The existing gravel access road at Kwagga Substation has become worn over time and
requires refurbishment. The project involves upgrading the road from a gravel surface to an
asphalt-paved road to improve durability and reduce future maintenance requirements.
The road section to be refurbished extends from the main entrance gate of the substation to
the feeder bays within the NTCSA Kwagga Substation. The road is approximately 342 m
long and 4 m wide.
Rigi Substation
The access road at Rigi Substation has deteriorated significantly, with several sections
exhibiting potholes and surface failures. During rainfall, water accumulates in low-lying
areas, resulting in ponding that affects vehicle access and creates a safety hazard for
personnel and heavy vehicles operating within the substation.
The refurbishment works will cover the road section starting approximately 25 m outside the
substation access gate, extending through the station to the feeder bays, where the existing
asphalt road meets the concrete road. The works will also include the refurbishment of the
gravel road adjacent to the existing asphalt road, which provides access to the stores.
2.1 Scope of the EMPr
NB: This EMPr document only caters for the scope of work contained in it. Any activities
outside the given scope of work will need to be addressed through the correct process (i.e.,
method statements).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Projects/Service Providers
Revision: 3
Page:
2.1.1 Purpose
This EMPr has been compiled to address the potential environmental impact that might
occur during the Central Grid Access Road refurbishment project. This document serves as
the environmental specification to National Transmission Company South Africa (NTCSA)
personnel and Contractors with regards to addressing the environmental issues identified
prior to and during the construction phase. It is the responsibility of the Project Manager
(PM), Contractors and the Environmental Practitioners to ensure compliance with all the
environmental specifications in this document, Environmental Requirements for Contractors
and/or Suppliers as well as the relevant compliance obligations.
This EMPr should also ensure the sustainable management of the environment whilst
replacement works are undertaken. This EMPr must be viewed as a contract document to
which all NTCSA personnel and contractors involved should adhere to.
2.1.2 Applicability
This document shall apply to Transmission Project Delivery (TPD) and Contractors
contracted to work on the Central Grid Access Road Refurbishment for Kwagga and Rigi
Substations Project.
2.1.3 Effective date
N/a
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in
the following paragraphs.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Projects/Service Providers
Revision: 3
Page:
2.2.1 Normative
[1] ISO 9001 Quality Management Systems
[2] ISO 14001 Environmental Management System
[3] 240-180100134 Environmental Requirements for Contractors and /or Suppliers These
documents are indispensable for the application of this document, i.e., documents to be used
together with this document.
[4] Informative
[5] National Environmental Management Act, 1998 (NEMA) (Act No ), and all
amendments and supplementary listings and/or regulations.
[6] Environment Conservation Act, 1989 (ECA) (No ) and amendments.
[7] National Environmental Management: Waste Act, 2008 (NEMWA, Act ).
[8] National Environmental Management: Biodiversity Act, 2004 (NEM:BA) (Act No. )
and amendments.
[9] National Forest Act, 1998 (NFA) (No ).
[10] National Veld and Forest Fire Act, 1998 (Act No. ). Conservation of Agricultural
Resources Act, 1983 (CARA) (Act No. ) & amendments.
[11] National Heritage Resources Act, 1999 (Act ).
[12] National Water Act, 1998 (Act ).
[13] The Occupational Health and Safety Act, 1993 (Act No. ).
[14] The National Fencing Act, 1963 (Act No ) as amended by Act .
[15] The National Environmental Management: Protected Areas Act, 2003 (Act No. ) and
it’s Regulations.
[16] The National Environmental Management: Air Quality Act, 2004 (Act ).
[17] South African National Standard (SANS) 10228 – The identification and classification of
dangerous goods.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Projects/Service Providers
Revision: 3
Page:
2.3 Definitions
Include all definitions applicable to this document, in alphabetical order. Explain all terms used,
including documents, titles and departmental references that may cause confusion if not explained.
Definition Explanation
Construction work The erection, maintenance, alteration, renovation, repair, demolition
or dismantling of or addition to a building or any similar structure
The installation, erection, dismantling or maintenance of a fixed plant
where such work includes the risk of a person falling
The construction, maintenance, demolition or dismantling of any
bridge, dam, canal, road, railway, runway, sewer or water reticulation
system or any similar civil engineering structure
Contractor The Contractor has overall responsibility for ensuring that all work,
activities, and actions linked to the delivery of the contract, are in
line with the Environmental Management Programme and that
Method Statements are implemented as described
Works The works to be executed in terms of the Contract
2.4 Abbreviations
Provide explanations of terms and abbreviations including documents, titles and departmental
references that may cause confusion if not explained, and that are used in this document.
Abbreviation Explanation
CEO Contractor Environmental Officer
EMPr Environmental Management Programme
HCS Hazardous Chemical Substance
IAP Interested and Affected Parties
NEMA National Environmental Management Act, 1998 (Act No. )
NTCSA National Transmission Company South Africa
TPD Transmission Power Delivery
2.5 Roles and Responsibilities
Function roles and responsibilities
TPD Environmental To ensure that the Environmental Management
Practitioner Programme (EMPr) for the project is compiled and
approved.
To ensure that all conditions stipulated in the EMPr are
met.
To conduct audit, monitor or provide assurance before,
during and post construction.
TPD Project Ensure that implementation of EMPr is executed as
Manager/ Site planned.
Manager
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Projects/Service Providers
Revision: 3
Page:
Ensure that all stipulations within the EMPr are
communicated and adhered to by the Contractor.
Ensure that conditions in this EMPr are fulfilled before the
contractor occupies the site, during and post construction.
Contractor Ensures that all Sub-contractors (if any) working under the
Environmental Principal Contractor abide by the requirements of the
Officer (CEO) EMPr.
Be on site throughout the duration of the project and be
dedicated to the project.
Ensure all staff are aware of the environmental
requirements, conditions, and constraints with respect to
all their activities on site.
Implementing the environmental conditions, guidelines
and requirements as stipulated within the EMPr and
Method Statements
Attend and provide performance status at the project
progress and Environmental site meetings.
Facilitate and undertake corrective actions where non-
compliances are registered within the stipulated
timeframes.
Assist the TPD Environmental Practitioner in maintaining
all the site documentation.
Prepare site inspection reports and corrective action
reports for submission to TPD.
Contractor Project To provide all necessary supervision during the execution
Manager/ Site of the project. He/ She should be available on site all the
Manager time.
To appoint a suitably qualified and competent
Environmental Officer to monitor and report to the Project
Manager on the daily activities during the construction
phase.
To ensure that implementation is conducted in an
environmentally acceptable manner.
To fulfil all obligations as per the agreed contract.
To inform and educate all employees about the
environmental risks associated with the different activities
that should be avoided during the construction process
and lessen significant impacts to the environment.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Projects/Service Providers
Revision: 3
Page:
2.6 Process for Monitoring
All documents shall be kept on site and be available for monitoring purposes. Site
inspections by an Environmental Audit Team may require access to this documentation for
auditing purposes. The documentation shall be signed by all parties to ensure that such
documents are legal. Regular monitoring of site works by the CEO is imperative to ensure
that all problems encountered are solved punctually and amicably. When the CEO is not
available, the Site Supervisor shall keep abreast of all works to ensure no problems arise.
The following documentation shall be kept on site:
10.1. Site Diary
10.2. Complaints Register
10.3. Incidents and Non-Conformance Registers
10.4. Records of all remediation / rehabilitation activities
10.5. Copy of this Environmental Management Programme
10.6. Photographic record (before, during and post construction/ refurbishment)
10.7. Project specific Method Statements / Procedures
10.8. Inspections and Audit (monitoring and evaluation) Records
10.9. Waste Records
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Projects/Service Providers
Revision: 3
Page:
2.7 Related/Supporting Documents
Submission Form for Board and Exco Committees Executive Summary Additional Information – the
Central Grid Access Road Refurbishment for Kwagga and Rigi Substations Project
3.1 Geographical Site Location and Environmental Condition
Kwagga Substation
Kwagga Substation is in Kwaggastrand, Pretoria West, within City of Tshwane Gauteng Province,
South Africa and is close in Atteridgeville.
Rigi Substation
Rigi Substation is also located in The Emfuleni local municipality Gauteng Province, South Africa.
Between Sharpville and Boipatong just northeast of Vanderbijlpark.
Environmental Conditions
The Gauteng region experiences a temperate Highveld climate characterized by warm, wet summers
and cool, dry winters. Most rainfall occurs between October and March, with occasional heavy
thunderstorms that can result in localized flooding and ponding on deteriorated road surfaces. During
the dry winter months, unsealed gravel roads are prone to dust generation.
3.2 Public Involvement/ Participation Process
The potential environmental impacts associated with the proposed project are required to
be considered in compliance with the Environmental Impact Assessment (EIA) Regulations
of 2014 (As amended) published in Government Notice R982 to R985 on, in terms of
Chapter 5 of the National Environmental Management Act, 1998 (Act ) (as
amended). The above scope of work was assessed against the Listing Notices of the EIA
Regulations 2014 and the following is noted:
That the Project does not trigger EIA process as per the above-mentioned regulations.
The public may be involved if project/ activity triggers the requirements for any related
permits/ agreements e.g., water use licenses or heritage permits.
All the required replacement works will be done directly on the existing substation footprint;
therefore, the project would not trigger the EIA listed activities.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Projects/Service Providers
Revision: 3
Page:
3.3 Project Specific Scope of Work and Design
The scope of work in this project will cover the following:
The following civil works needs to be done for Kwagga Substations access road.
Refurbish 4m wide tar road
Clean open-cut drains and gutters that run next to the road
Conduct DCP and Troxler
The following civil works needs to be done for Rigi Substations access road.
Refurbish and construct 6m-9m wide tar road
Clean open-cut drains and gutters that run next to the road
Conduct DCP and CBR test
Place vegetation outside the gate of the substation
Construct cut-off drain outside the gate of the substation
This document has been seen and accepted by:
Name Designation
N/a
Note: Start with the latest Revision History in the first row and go backwards.
Date Rev. Compiler Remarks
July 2026 1 Bukelwa Masiza New document
The following people were involved in the development of this document:
N/a
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd,
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
Table 1: Project Specific Environmental Controls
This section specifies standard mitigation measures to be followed by the parties responsible for environmental management during
the construction of the Central Grid Access Road at Kwagga and Rigi project.
Note: An activity may have multiple aspects that might need to be looked at
No. Activity Aspect Impact Management Mitigation Measure Measurable Frequency of Responsible
Objective Targets Action Party
Contract and Enquiry to legal minimising included as part of the records stage Buyer/
programme requirements negative impacts tender documentation signed Environmental
and non- anticipated to thereby making it part of Practitioner
conformance to occur during the the enquiry document to
Declaration on other construction/ make the
Environmental requirements refurbishment recommendations and
Requirements and conditions phase. constraints, as set out in
Pro-forma. set out in the this document,
EMPr. enforceable under the
general conditions of
Ensure
contract. Project Manager environmental
awareness and
formalize A contractor shall
environmental acknowledge or complete
responsibilities Declaration on
and Environmental
implementation. Requirements Pro-forma
before commencement of
the works.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
A copy of this EMPr must During CEO
be always available at the construction/
works site. The Contractor refurbishment
shall ensure that all the
personnel on site, sub-
contractors and their
teams, suppliers, etc. are
familiar with and
understand the
specifications contained in
this EMPr.
Statements Project documents to legal minimising require method Method commenceme
requirements negative impacts statements may only Statements nt of activities
and non- anticipated to commence once the and relevant
conformance to occur during the method statements have documents. As and when
other construction/ been approved by the PM required
requirements refurbishment and NTCSA
and conditions phase. Environmental
set out in the Practitioner.
EMPr.
contractor shall provide Contractor
job-specific training on an Training
ad hoc basis when records
workers are engaged in
activities, which require
Method Statements.
that NTCSA Policies,
Guidelines and Standards
are consulted to ensure
that Method Statements
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
meet requirements as set
out in those documents.
demarcation demarcation of site contravention, minimising shall be consulted before take place commenceme
and and damage to negative impacts site demarcations and within the nt of
development the environment anticipated to development, including demarcated construction/
occur during the the camp site. area. refurbishment
construction/
refurbishment contained in this EMPr site
phase. must be adhered to and
considered when site As and when
demarcation and required
development takes place.
allowed outside the
demarcated area.
al Awareness Environmental understanding training and receive environmental impact commenceme
Training Awareness Training by workforce of awareness of awareness/ training. because of nt of
the construction/
responsibilities refurbishment onto site shall receive refurbishment refurbishment
in terms of this staff contribute to environmental activities is activities.
EMPr minimisation of awareness/training. minimised
the occurrence of through the
environmental development Legal environmental required
impact to the work of effective contravention, awareness/training shall
area. environmental damage to the be available as and when
awareness environment required.
training and private
and controls linked to the environmental
EMPr. awareness
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
aware of their individual staff.
roles and responsibilities
in achieving compliance
with the EMPr.
erect and maintain
information posters at key
locations on site.
Wastewater management
procedures.
conservation.
management procedures.
procedures.
-A record of all
environmental awareness
undertaken as part of the
EMPr must be available.
-Educate workers on the
dangers of open and/or
unattended fires.
Environmental
awareness/training should
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
include as a minimum the
following:
significant environmental
impacts, actual or
potential, related to their
work activities.
to be implemented when
carrying out specific
activities.
preparedness and
response procedures.
followed when
working near or within
sensitive areas.
management procedures.
conservation.
management procedures.
procedures.
-A record of all
environmental awareness
undertaken as part of the
EMPr must be available.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
-Educate workers on the
dangers of open and/or
unattended fires
-A staff attendance
registers of all staff to
have received
environmental awareness
training must be available
-Course material must be
available and presented
in appropriate languages
that all staff can
understand
Establishmen site camp environment by environmental method statement shall environment project
t unnecessary issues are taken be provided by the during site commences
clearing the into consideration contractor prior to any establishment
surface/ ground. in the planning onsite activity that is minimised
and construction includes the layout of the and the
of site construction camp in the development Land pollution/
establishment. form of a plan showing footprint are contamination.
the location of key kept to
infrastructure and demarcated
Chemical services (where development
pollution caused applicable), including but area.
by vehicle oils, not limited to offices,
grease or vehicle parking areas,
solvents stores, the workshop,
stockpile and lay down
areas, hazardous
materials storage areas
(including fuels), the
batching plant (if one is
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
located at the construction
camp), designated access
routes, equipment
cleaning areas, ablution
facilities, waste and
wastewater management;
construction camps must
be carefully considered
and approved by the
Substation/ Grid Team
and Tx. Projects Delivery
to ensure that the site
does not impact on
sensitive areas.
located where possible on
previously disturbed
areas.
camp shall be fenced
where necessary.
6 Environment Response to all Land, water Emergency
al types of pollution/ procedures are in Emergency Response situations are commenceme
emergencies environmental contamination. place to enable a Plan prior to the managed in nt
emergencies. rapid and commencement of the accordance
effective response proposed project. with the Chemical As and when
pollution caused to all types of
environmental must deal among other procedures. by vehicle oils,
emergencies. things with accidents grease or
solvents harsh weather conditions, Rapid and
disasters, wildlife effective
interactions, potential response to all
types of
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
spillages and fires in line environmental
with relevant legislation. emergencies.
aware of emergency
procedures as part of
environmental awareness
training.
authority shall be made
aware of a fire as soon as
it starts.
emergency necessary
mitigation measures to
contain the spill or leak
shall be implemented.
Chemical use and disposal of and water pollution of the provide method the CEO/ SHE
Substances hazardous pollution/ environment. statements for the environment. Representative
(incl. oil) substances contamination. “handling & storage of
hazardous chemical Minimise chances No litigation
substances”, “fire”, and Damage to the of transgression due to
“emergency spills environment. of the acts transgression
procedures”. controlling of pollution
pollution.
be confined to specific
and secured areas within
No complaints the contractor’s site, and
from in a way that does not
Interested & pose a danger of pollution
Affected even during times of high
Parties (I & rainfall. These areas must
APs). be imperviously bunded
with adequate
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on
the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, © copyright Eskom Holdings
SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Projects/Service Providers Unique Identifier: 240-131566734
Revision: 3
Page:
containment (at least 1.5 Method
times the volume of the statements
fuel) for potential spills or
leaks
of 10cm deep) must be
placed under all vehicles,
including plant and
equipment that stand for
more than 24 hours.
Vehicles suspected of
leaking must not be left
unattended, drip trays
must be utilised.
the drip trays will be
dependent on the vehicle
and must be large enough
to catch any
hydrocarbons that may
leak from the vehicle/plant
while stationery.
substances must be
contained in impermeable
containers for removal to
a licensed hazardous
Title: Supplier Quality Management: Document Identifier: 240-105658000
Alternative Reference QM 58
Number:
Area of Applicability: Eskom Holdings SOC Ltd
Functional Area: Procurement and Supply
Chain Management
Revision: 4
Total Pages: 30
Next Review Date: May 2030
Disclosure Controlled Disclosure
Classification:
Compiled by Supported by and Authorized by
Functional
Responsibility
Sipho A Sambo Bathusi Montwedi Gerhard Van Der Walt
Middle Manager Senior Manager General Manager
(Acting) (Acting)
Procurement and
Supplier Quality Procurement and Supply Chain
Management Supply Chain Management
ManagementProcurement and Corporate Services
Supply Chain Corporate Services
Management
Corporate Services
Date: 2026/05/26 Date: Date: 01 July 2026
EDC TN Formatted 15.10.2021/TR Formatted 22.10.2025
Template ID: 32-4 (Rev 13) Document template (for procedures, manuals, standards, instructions, etc.)
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
Content
. Introduction .................................................................................................................................................. 3
2.1 Scope ................................................................................................................................................. 3
2.1.1 Purpose .................................................................................................................................. 3
2.1.2 Applicability ............................................................................................................................ 3
2.1.3 Effective date ......................................................................................................................... 3
2.2 Normative/Informative References ..................................................................................................... 3
2.2.1 Normative ............................................................................................................................... 3
2.2.2 Informative ............................................................................................................................. 4
2.3 Definitions ........................................................................................................................................... 4
2.4 Abbreviations ...................................................................................................................................... 6
2.5 Roles and Responsibilities ................................................................................................................. 6
2.6 Process for Monitoring ....................................................................................................................... 7
2.7 Related/Supporting Documents ......................................................................................................... 7
3.1 Supplier and Sub-Supplier Quality Management System Requirements .......................................... 8
3.2 Quality Plan ........................................................................................................................................ 9
3.3 Contract Quality Plan ......................................................................................................................... 9
3.4 Quality Control Plan ......................................................................................................................... 11
4.1 Main Supplier and Sub-supplier Categories .................................................................................... 15
4.2 Main Supplier and Sub-supplier Capability and Capacity Assessment ........................................... 18
5.1. Contract Execution ............................................................................................................... 19
5.2. Supplier Quality Performance Monitoring Phase ................................................................. 20
5.3. Supplier Quality Audit .......................................................................................................... 21
6.1. Rights of Access ............................................................................................................... 21
6.2. Eskom Rights to Information ............................................................................................................ 22
6.3. Preservation ..................................................................................................................................... 23
6.4. Quality Audits Related Conditions .................................................................................................... 27
6.5. Management of Nonconformities and Nonconforming Outputs Identified by Eskom ...................... 27
6.6. Special Processes ............................................................................................................................ 28
Acceptance ................................................................................................................................................ 29
Revisions ................................................................................................................................................... 29
Development Team ................................................................................................................................... 30
Acknowledgements ................................................................................................................................... 30
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
The intention of this specification is to specify and describe the minimum quality requirements for all
existing and potential Eskom suppliers and define the quality criteria for the evaluation, selection,
supplier/ vendor registration, assessment, performance monitoring, and auditing of suppliers.
Eskom’s position is to partner with suppliers who fully demonstrate commitment to the development,
implementation, and maintenance of a quality management system (QMS) that conforms to the
requirements of ISO 9001 standard. The focus is to ensure suppliers establish and continually
improve their QMS and enhance service delivery, and customer satisfaction by implementing and
conforming to the standard.
2.1 Scope
2.1.1 Purpose
The purpose of this specification is to outline the requirements according to which suppliers shall
a quality management system (QMS) based on ISO 9001, which should form the basis for conformity
to Eskom quality requirements for various externally provided products, services and processes and
continual adherence throughout the duration of a contract.
2.1.2 Applicability
This specification shall apply throughout Eskom Holdings Limited divisions, its subsidiaries,
suppliers, and sub-suppliers and shall form part of all Eskom requests for information (RFI)/ requests
for quotation (RFQ)/ requests for proposal (RFP), including contracts for the procurement of products
and services.
2.1.3 Effective date
Date of authorisation of the specification
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
[1] ISO 9001 Quality Management Systems – Requirements
[2] ISO 10005 Quality Management Systems – Guidelines for Quality Plans.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
2.2.2 Informative
[3] ISO 9000 Quality Management Systems – Fundamentals and Vocabulary
[4] 32-727: Safety, Health, Environment, and Quality (SHEQ) Policy
[5] ISO 10006 Quality Management Systems – Guidelines for Quality Management in Projects
[6] ISO 9004 Quality Management – Quality of an Organisation – Guidance to Achieve Sustained
Success
[7] 32-1033: Eskom’s Procurement and Supply Chain Management Policy
[8] 32-1034: Eskom’s Procurement and Supply Chain Management Procedure
[9] PPPFA: Preferential Procurement Policy Framework Act, 2000 (Act No. )
[10] CIDB 1004: Best Practice Guideline A4: Evaluating Quality in Tender Submissions
[11] 240-12248652 Supplier Quality Management: List of Tender Returnable
[12] 240-168873697 Supplier Quality Management: Tender Evaluation Scorecard
[13] 240-125473040 Supplier Quality Management: Guideline for QM 58 Selection Criteria
[14] IAEA Safety Standard GS-R-3.1 Application of the Management System for Facilities and
Activities
[15] SANS 10845-1 Construction Procurement Part1: Processes, Methods and Procedures
2.3 Definitions
The vocabulary of ISO 9000 and the following definitions apply in the application of this specification.
2.3.1 Component: a constituent part of the product or sub-assembly of the product. The product
may comprise multiple individual components.
2.3.2 Contract Quality Plan: a document of the supplier’s process for delivering the level of quality
required by the contract. It is a framework for the contractor’s process for delivering quality.
Purpose of a CQP is to outline how the results defined in the specifications will be achieved.
2.3.3 Hold Point: a predetermined stage in the quality control plan (QCP) beyond which work/
manufacturing shall not proceed without the attendance of, and written authorisation of, an
Eskom representative or Eskom inspection agency, whichever is applicable.
2.3.4 Intervention Points: those control points indicated by the various controlling bodies
concerned with the implementation of a specific QCP/ ITP. These can be in the form of
inspection, hold points, surveillances, witnesses, reviews and verifications.
2.3.5 Inspection Agency: an organisation or person appointed by Eskom for the purpose of
performing quality assurance/ quality control, monitoring, inspection and/ or expediting
services.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
2.3.6 Level 1 Plant Items: equipment, whose failure has an effect on personnel safety and/ or
health, causes an environmental incident, cause a huge production loss or major equipment
damage. Equipment that are safety/ redundancy/ protective device or covered by statutory
regulations requirements.
2.3.7 Level 2 Plant Items: equipment, whose failure impacts plant availability and/or reliability,
causes significant costs or secondary damage.
2.3.8 Level 3 Plant Items: equipment that does not impact on personnel safety and/ or health,
environmental, cost, availability and/ or reliability of plant.
2.3.9 Nonconformity: a deficiency in material, composition, characteristic, or performance that
renders the quality of an item, component, or product unacceptable or indeterminate. The
term also covers a deficiency in, or deviation from/non-adherence to, the quality management
system requirements, prescribed production processes, and/or related documentation such
as procedures and instructions.
2.3.10 Quality Plan: specification of the actions, responsibilities and associated resources to be
applied to a specific object.
2.3.11 Quality Control Plan: a document specifying the activities to be inspected throughout the
execution of the project, inclusive of test methods, procedures, and acceptance criteria (This
term is equivalent to QIP and ITP).
NOTE: An Inspection and Test Plan (ITP) is a structured document that outlines the
necessary inspections and tests to ensure that a product or process meets specified quality
requirements and standards.
2.3.12 Requirement: the need or expectation that is stated, generally implied, or obligatory.
Requirements are generally specified in the purchase order and/or contract documentation
but may not be limited to these.
2.3.13 Primary Plant (Power Plant): primary plant include High Voltage equipment situated inside
the control room (breakers, bus-bars, CT’s, VT’s and transformers).
2.3.14 Secondary Plant (Control Plant): secondary plant includes all equipment used to control
and protect the HV equipment on the primary plant side. (Protection, metering, AC/DC and
tele-control).
2.3.15 Special Process: is any production or service process which generates products or services
which cannot be measured, monitored, or verified prior to delivery and use. This may include
welding processes or non-destructive techniques
2.3.16 Supplier: is a current or potential supplier, vendor, contractor, consultant, or service provider.
A supplier may be a natural or legal person and includes any employee acting within the
course and scope of his/her employment or any agent or manager acting for, or on behalf of,
or in the interests of, the person registered as supplier on the Eskom supplier database.
2.3.17 Sub-supplier: an organisation that provides a product/service to the supplier and/or that
enters into a subcontract and assumes some of the obligations of the supplier or prime
contractor.
2.3.18 Witness Point: a predetermined stage in the quality control plan where and inspection
activity will take place. Work may proceed, provided Eskom or its inspection agency has been
formally notified and confirmed that inspection is waived.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
2.4 Abbreviations
Abbreviation Explanation
AIA Approved Inspection Authority
CA Corrective Action
CFT Cross Functional Team
CQP Contract Quality Plan
FIDIC Federation Internationale Des Ingenieurs- Conseils
FMECA Failure Mode, Effects and Criticality Analysis
HAZOP Hazard and Operability Study
ISO International Organisation for Standardisation
ITP Inspection and Test Plan
NC Nonconformity
NDT / NDE Non-Destructive Testing / Non-Destructive Examination
PMI Positive Material Identification
QCP Quality Control Plan
QMS Quality Management System
PQP Project Quality Plan
RFI Request for Information
RFQ Request for Quotation
RFP Request for Proposal
SHEQ Safety, Health, Environment, and Quality
WPS Welding Procedure Specifications
WQR Welder’s Qualification Record
2.5 Roles and Responsibilities
The assigned Eskom Quality representative/ professional when part of a Cross Functional Team
(CFT) appointed to transact on externally provided products, services and processes shall select
applicable requirements for existing and potential Eskom suppliers using, 240-125473040 Supplier
Quality Management – Guideline for QM 58 Selection Criteria and Form A (Tender and Contract
Quality Requirements for Supplier Quality Management: Specification 240-105658000/ QM 58 and
Quality Requirements for ISO 9001 Standard).
The existing and/ or potential suppliers must complete, sign and return Form A with the other
returnables as listed in the List of Tender Returnable document (240-12248652). Other roles and
responsibilities for this standard are defined within the text of this specification.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
2.6 Process for Monitoring
The application of this specification throughout Eskom shall be audited as per the management
system audit schedule to review performance and effectiveness of this specification.
2.7 Related/Supporting Documents
The documents superseded by this specification: all divisional and business unit supplier quality
requirements standards and/or specifications.
2.7.1 Forms and templates:
[1] 240-68099512 Tender and Contract Quality Requirements for Supplier Quality Management
Specification 240-105658000/ QM 58 and Quality Requirements for ISO 9001 Standard (Form
A)
[2] 240-109253698 Template for a Typical Contract Quality Plan
[3] 240-109253302 Quality Control Plan/Inspection and Test Plan
[4] 240-126469599 Method Statement Template.
[5] 240-144723833 Quality Requirements Exemption Certificate
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
3.1 Supplier and Sub-Supplier Quality Management System Requirements
3.1.1 The supplier and sub-supplier shall develop, implement, maintain and improve a formal QMS
that conforms to the latest ISO 9001 standard or any applicable standard of QMS (latest
applicable revision) in accordance with the requirements of this specification.
3.1.2 Such a formal system shall consist of the appropriate documented information required by
ISO 9001, and may include a quality manual, quality plans, work procedures, work
instructions, method statements, workflow documentation, etc., as the case may be. This
requirement constitutes the most basic QMS requirements.
3.1.3 Unless specifically excluded from the quality list of tender returnables, as per the categories
of quality requirements (Category 1, 2, 3, or 4), such a QMS shall carry a valid ISO 9001
certificate from an accredited certification body, as indicated in the applicable Eskom
invitation (this requirement applies equally to both the supplier and any/ all manufacturing
third-party organisations mentioned above).
3.1.4 Unless specifically excluded in the quality list of tender returnable, as per the categories of
quality requirements (Category 1, 2, 3, or 4), the supplier shall have a fully developed,
documented, implemented, reviewed and maintained QMS that complies with the
requirements of ISO 9001 standard or any applicable standard of QMS. In the event that the
main supplier invariably requires the assistance of a sub-supplier in order to realise its own
supply obligations. The aforementioned requirement applies equally in all cases where any
such sub-supplier’s scope of responsibility includes the provision of any of the following
activities, namely, design and development, manufacturing, maintenance, testing, storage,
delivery, installation, commissioning, and project management, or in the cases the supplier’s
name changes, mergers, acquisitions and/ or cessions. Eskom Quality department must
ensure that the changed entity can still fulfil the requirements as set out in the contract
documentation.
3.1.5 Where a new product/ service introduced in Eskom, the requirements for such shall be in line
with available industry recommended practises (RP) or applicable codes (for example for
BESS, the RP UL 9540 or IEEE 1790) in the absence of SANS equivalent
3.1.6 Eskom reserves the right to request and perform necessary assessments at sub-supplier
facilities.
3.1.7 The main supplier shall be responsible for defining and managing the specific quality
assurance and control elements applicable to the respective sub-supplier’s scope of
work/supply and ensure that its sub-supplier(s) quality programmes support Eskom
requirements.
3.1.8 The supplier shall inform Eskom of any proposed changes to the QMS or staff that will affect
the quality system prior to implementation of these changes.
3.1.9 The main supplier shall develop and implement a performance management programme for
their sub-supplier. The programme shall include, but not limited to:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
3.2 Quality Plan
The information in this section constitutes the minimum requirements for a quality plan.
3.2.1 Where specified in the Evaluation Criteria and/ or quality list of tender returnables, as per the
categories of quality requirements (Category 1, 2, 3, or 4); all individual products, services
and processes shall have a documented, implemented, reviewed and maintained
contract/project quality plan and/or quality control plan (inspection and test plan).
3.2.2 Where specified in the evaluation criteria and/ or quality list of tender returnables. All
production and/ or service provision shall be carried out in accordance with a documented
and agreed contract/project quality plan (CQP) and/ or quality control plan (QCP)/ inspection
and test plan (ITP).
3.2.3 The supplier shall plan for the required quality-related activities and interfaces within the
supplier’s quality system in order to demonstrate its ability towards both controlling and
meeting specified Eskom requirements.
Note 1: Contract/ Project Quality Plan should address the quality assurance elements related to
the scope of work and/ or technical specification for the specified duration.
Note 2: Quality Control Plan (QCP)/ Inspection and Test Plan (ITP) should address the quality
control elements related to the scope of work and/ or technical specification.
3.3 Contract Quality Plan
The main supplier shall require sub-suppliers to submit project quality plans (PQPs)/ contract quality
plans (CQPs) and associated documentation in accordance with the requirements of project QMS
processes applicable to the sub-supplier’s scope of work.
The supplier shall, where applicable, based on scope of work criticality, ensure that procurement
documents clearly and unambiguously require sub-supplier submission of a sub-supplier CQP for
supplier and Eskom review.
The main supplier shall ensure that sub-supplier CQPs are developed and implemented in
accordance with the ISO 10005 Quality Management System Guidelines for Quality Plans and the
sub-contracted scope of work. In addition to the elements specified in ISO 10005, the supplier’s
and/ or sub-suppliers’ CQPs shall include the following (as applicable):
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
3.3.1 The management of records, including material tests, positive material identification (PMI)
testing, material certification, etc.
3.3.2 The provision for free and uninhibited access by the supplier and/or personnel at the time of
inspection.
3.3.3 The proposals for submission of final documentation, the final manufacturing data book, prior
to shipment.
3.3.4 The special processes related to welding: management of the welder’s qualification record
(WQR), welding procedure specifications (WPS), and procedures qualification records (PQR)
that will be used in the performance of work for supplier review and acceptance prior to
commencing manufacture. Welders shall be qualified to the specified Codes of Construction
for the applicable procedures. The requirements for qualification shall be specified by the
supplier, and welder records shall be maintained by sub-suppliers performing the work.
3.3.5 The special installation procedures and other required fabrication or manufacturing
procedures (that is, those required for post-weld heat treatment, tube rolling, coatings, etc.)
that will be used in the performance of work shall require supplier review and acceptance
prior to commencing manufacture.
3.3.6 The personnel carrying out special processes (for example, NDE, welding, coating, heat
treatment, etc.) where the results cannot be fully verified by subsequent inspection and test
shall be suitably qualified and, where applicable, registered with statutory bodies as legally
required, that is, as radiographic workers to conduct radiography. The requirements for the
qualification shall be specified, and personnel records shall be maintained in accordance with
the Project Quality Personnel Qualification Specification and, where applicable, legal
requirements.
3.3.7 The personnel required to perform special processes shall be certified competent through a
certificate of competency in accordance with the company’s training and development policies
or in line with applicable regulatory and statutory bodies requirements.
3.3.8 All personnel who perform activities that affect quality shall have their training needs identified
and documented. The required training shall be implemented in accordance with the
company’s training and development policies. All the training certificates shall meet the
applicable regulatory or statutory requirements in terms of having the unit standard /National
Qualification Framework (NQF) completed and the accreditation number of the service
providers.
3.3.9 Instructions and requirements for equipment and materials storage, preservation, and
maintenance, including identification of materials required for preservation and maintenance,
are to be provided sufficiently prior to receipt (prior to shipment or earlier) to ensure that
appropriate resources are available at the time of delivery.
3.3.10 Specific quality monitoring and verification activities are to be undertaken on the supplier’s
sub-suppliers by Eskom or it agent.
3.3.11 The CQP information shall include, but not limited to:
methods to be utilised to ensure quality.
generated.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
Cqp.
project.
3.3.12 The main supplier and sub-supplier CQPs shall comply with the Eskom Quality Requirements
Specifications and shall be submitted prior to the initial scope of work kick-off or initial pre-
fabrication meeting and prior to commencement of manufacturing, whichever is earlier.
3.3.13 The Eskom template for CQP provided shall be used as guideline, where the supplier does
not have a CQP template.
3.3.14 Competence and Qualification of Personnel managing quality shall be in line with applicable
qualification, certificates as deemed by the respectable company criteria.
3.3.15 Where personnel involved in the management of quality shall be noted to be lacking relevant
competences, Eskom shall request the removal of such personnel from the contract site
operations in respect to all activities and process that leads to conformity of product /services.
3.4 Quality Control Plan
The supplier shall develop, implement and maintain processes and procedures that efficiently and
effectively allows monitoring and verification of the scope of work activities, to outline specific
procedures; standards; and responsibilities for maintaining product or service quality.
The main supplier shall ensure that sub-supplier QCPs/ ITPs are prepared at a level of detail
sufficient to address all quality-control-related activities in a chronological order, from contract review
through materials verification, manufacturing, fabrication, assembly, final testing, commissioning,
hand-over documentation, and certification. In addition, the supplier shall ensure compliance with
the following requirements:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
3.4.1 All stages of manufacturing, fabrication, assembly and installation shall be controlled by a
supplier’s QCP/ ITP that clearly and unambiguously identifies the quality verifications to be
performed and special attention to controls related to critical products and services. The
intervention points and the inspection and tests methods to be applied are to be indicated
as per ISO 10005, Guidelines for Quality Plans.
3.4.2 QCP/ ITP shall be reviewed and accepted by an Eskom employer representative, its
inspection authority or agency, and they shall allow for the insertion of Eskom specific
requirements, including hold and witness points prior to the commencement of work.
3.4.3 Subsequent changes to the Eskom accepted QCP/ ITP shall require Eskom, its inspection
authority or agency’s agreement prior to the commencement of work involving an activity
affected by such changes.
3.4.4 The ITPs should cover materials certification, fabrication works, in-process inspections, final
acceptance tests, packaging and pre- shipment/ transportation, shipping/ transportation
inspections where contracted, preservation, site acceptance tests, construction and erection
works, and pre-commissioning and commissioning tests.
3.4.5 All sub-supplier QCP/ ITP activity shall be performed using an Eskom-accepted supplier
QCP/ ITP and be based on the sub-contracted scope of work.
3.4.6 All applicable codes, standards, and relevant acceptance criteria documents are available at
the work location, and Eskom representatives on site shall have on-going access to this
information. Workplace documentation shall be available in English and in any workforce-
appropriate language.
3.4.7 Where activities subject to inspection and test procedures are to be undertaken by a sub-
supplier, the QCP/ ITP shall make reference to this fact and shall include descriptive details
of the sub-supplier’s involvement. A separate QCP/ ITP shall be required for each sub-
supplier scope of work.
3.4.8 The supplier shall be ultimately accountable and responsible for the development and proper
implementation of all sub-supplier QCPs/ ITPs, including those reviewed or developed by
sub-suppliers.
3.4.9 Eskom reserves the right to select intervention points on QCPs/ ITPs for Eskom oversight of
selected functions and to perform surveillance or audits of the work.
3.4.10 Once signed, the ITPs and QCPs become addendums to the main contract. These ITPs can
be reviewed at Eskom’s discretion based on its assessment of the supplier’s performance or
other risks.
3.4.11 A QCP/ ITP shall contain the following information:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
with reference to the relevant criticality risk rating
international standard, with the relevant clause number for each operation
agency
intervention in the plan
indication of records to be provided to Eskom (as applicable)
3.4.12 The main supplier shall require sub-suppliers to submit QCPs/ ITPs and associated
documentation applicable to the sub-supplier scope of work. Any changes made to the QCP
after submission must be resubmitted to Eskom for further review. The supplier shall ensure
that all sub-supplier QCPs/ ITPs are in compliance with the Eskom Quality Requirements
Specifications, including, but not limited to, the following requirements:
will take place, including facility location(s)
performance of the activity, including specific reference to actual sections and pages of
procedures, standards, instructions, specifications, etc.
with specified requirements; documents are to be provided using the proper Eskom
document numbering requirements
inspection authority (AIA) and Eskom inspection activities defined in terms of witness, hold,
document review, and verification monitoring points and provision for sign-off of each of the
above-mentioned parties for each intervention point
inspectors
applicable), and Eskom prior to commencement of work
and package acceptance test, witness, and hold points
3.4.13 A quality kick-off meeting will be held at the start of the contract and, if required, at the start
of each subsequent phase.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
for items or equipment to ensure that all technical and commercial requirements are clear
and understood. Fourteen days’ advance notice of meetings shall be given to Eskom.
and qualified to perform inspection and testing assignments. Mobilisation of all such
personnel shall be in compliance with the Project Quality Personnel Qualification
Specification.
3.4.14 Where QCP/ ITP is applicable, the supplier shall ensure that sub-suppliers are provided with
comprehensive, clearly written, and unambiguous inspection and testing protocols, including
processes, procedures, and methods that shall include, but not be limited to, the following:
inspected
distribution, and report retention requirements
inspection and test processes, procedures, or methods and nonconformity identified in
inspection and test results
equipment and sub-systems (if applicable)
3.4.15 The supplier shall establish processes and procedures for formal assessment of sub-supplier
inspection and testing programmes. These shall include review of sub-supplier inspection
reports and other quality control documentation. Additional formal assessment of
manufacturing, fabrication, and assembly facility operations shall be conducted by the
supplier to ensure continuing suitability, adequacy, and effectiveness of the sub-supplier’s
inspection and testing programmes. Assessment frequency shall be established in
consideration of the sub-supplier scope of work, criticality of scope of work deliverables, and
performance information. The assessment scope and schedule shall be developed in
consultation with Eskom.
3.4.16 Supplier processes and procedures for verification of supplier and sub-supplier purchased
product compliance with specifications shall obtain document return/review status prior to
implementation.
3.4.17 The objective is to finalise any outstanding procedural or other issues before proceeding to
deliver the works.
3.4.18 Eskom, in consultation with the supplier, develops an agenda for the meeting, and Eskom will
keep minutes of these meetings.
3.4.19 Mandatory pre-inspection meetings will be convened by Eskom or its inspection agency or
AIA to be attended by the supplier’s and sub-supplier’s representatives, including their quality
representatives who will be involved in the works, and records are to be kept.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
3.4.20 Eskom reserves the right to appoint resident quality inspectors who can be based at the
supplier’s or sub-supplier’s premises and on site where the work is being performed. The
supplier is expected to provide workspace at no cost to Eskom for the inspector, as required.
3.4.21 Eskom may appoint any organisation it prefers to perform quality assurance and quality
control activities, either in the capacity as an AIA or inspection agency, on the works
contracted to the supplier, and the supplier or its sub-suppliers may not object, prevent,
hinder, undermine, circumvent, question, discredit, or in any way make it impossible for such
organisation to carry out its work on behalf of Eskom.
3.4.22 The Eskom template for QCP/ ITP provided shall be used as guideline, where the supplier
does not have a QCP/ ITP template.
The selected quality assessment criteria and Form A of this specification will be compiled and
completed by the assigned Eskom Quality representative/ professional who using the guideline 240125473040, shall select the suitable supplier quality requirements to be met.
Form A (Section A & Section E) of this specification must also be completed and signed by the
supplier responding to an Eskom invitation to tender, in order to acknowledge, accept and further
commit to comply with the Eskom Supplier Quality requirements as per this specification and ISO
9001 Standard or any additional quality requirements specific to the scope of work.
4.1 Main Supplier and Sub-supplier Categories
Eskom supplier quality requirements for all existing and potential suppliers and sub-suppliers are
classified into four categories (category 1, 2, 3 and 4). Suppliers must prepare and submit quality
documentation as per the tender selected category (indicated in Form A) using the list of tender
returnables document.
NOTE: Only one (1) category must be applicable per procurement process e.g. [Eskom requests for
information (RFI)/ requests for quotation (RFQ)/ requests for proposal (RFP), including contracts for
the procurement of products and services].
The following are the minimum returnable documentation for Categories 1 to 4:
4.1.1 Category 1: Quality Requirements
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
Automobile; ICT) of a QMS (the latest applicable revision). The QMS should drive the
supplier’s business management processes to ensure that all of Eskom’s requirements are
fully met on a consistent basis.
audit reports. The audit reports must include, if applicable, nonconformities identified, and
the resulting remedial actions (correction and/ or corrective action reports).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals,
procedures.
described in the tender documents. The plan must address the minimum requirements as
per ISO 10005.
plan (ITP) or quality control plan (QCP) on similar and/ or previous work done.
Processes, Products and Services.
meetings that include agenda, meeting minutes, attendance registers, reports, presentations,
etc.
Note 1: specific requirements per tender will be selected using the List of Tender Returnable
documents (240-12248652).
Note 2: any additional requirements specific to the scope of work can be included under Section E
(List of Tender Returnable documents (240-12248652)) and subsequently listed from E2 onwards.
4.1.2 Category 2: Quality Requirements
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
QMS that complies with ISO 9001 or any applicable standard of quality management system
(the latest applicable revision). The following documents (approved/ signed copies) shall be
submitted:
o Quality Management System manual or a documented information that have defines
and describes the QMS and its scope
o Quality Policy, aligned with the supplier’s strategic direction (documented
information)
o Quality Objectives (documented information)
o Control of documented information (both maintain and retain documented
information)
o Internal audit procedure (documented information)
o Control of nonconforming outputs (documented information)
o Nonconformity and Corrective action procedure (documented information)
The QMS should drive all the supplier’s business management processes to ensure that all of
Eskom’s requirements are fully met on a consistent basis.
The audit reports must include, if applicable, nonconformity identified, and the resulting
remedial actions (correction and/ or corrective action reports).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
described in the tender documents. The plan must address the minimum requirements as
per ISO 10005.
quality control plan (QCP) on similar or previous work done.
Processes, Products and Services.
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals,
procedures.
meetings that include agenda, meeting minutes, attendance registers, reports, presentations,
etc.
Note 1: specific requirements per tender will be selected using the List of Tender Returnable
documents (240-12248652).
Note 2: any additional requirements specific to the scope of work can be included under Section E
(List of Tender Returnable documents (240-12248652)) and subsequently listed from E2 onwards.
4.1.3 Category 3: Quality Requirements
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
9001 (or the latest applicable revision). The following documented information (approved/
signed copies) shall be submitted:
o Quality management system manual or a (documented information) that have
defines and describes the QMS and its scope
o Quality Policy, aligned with the supplier’s strategic direction (documented
information)
o Quality Objectives (documented information)
o Control of documented information (both maintain and retain documented
information)
o Internal audit procedure (documented information)
o Control of nonconforming outputs (documented information)
o Nonconformity and Corrective action procedure (documented information)
The QMS should drive all the supplier’s business management processes to ensure that all of
Eskom’s requirements are fully met on a consistent basis.
described in the tender documents. The plan must address the minimum requirements as
per ISO 10005.
quality control plan (QCP).
Processes, Products and Services.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals,
procedures.
Note 1: specific requirements per tender will be selected using the List of Tender Returnable
documents (240-12248652).
Note 2: any additional requirements specific to the scope of work can be included under Section E
(List of Tender Returnable documents (240-12248652)) and subsequently listed from E2 onwards.
4.1.4 Category 4: Quality Requirements
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
scope of work.
processes to ensure that all of Eskom’s requirements are fully met on a consistent basis.
strategic direction). (documented information)
Processes, Products and Services.
authorities, specific to the project/ scope of work/ technical requirements. Examples of
relevant documented information are; organization charts, job descriptions, work instructions,
duty statements, manuals, procedures.
Note 1: specific requirements per tender will be selected using the List of Tender Returnable
documents (240-12248652).
Note 2: any additional requirements specific to the scope of work can be included under Section E
(List of Tender Returnable documents (240-12248652)) and subsequently listed from E2 onwards.
4.2 Main Supplier and Sub-supplier Capability and Capacity Assessment
Supplier capability and capacity assessments shall be performed prior to contract award on potential
suppliers participating in Eskom Holdings procurement process to:
All sub-suppliers used by the main supplier/ contractor, performing work on Eskom critical plant
equipment, supplying commodities and providing specialised services shall be subjected to the
capability and capacity assessment.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
Critical plant includes the following:
All potential quality risks identified will be included in the assessment report provided for the tender
evaluation.
Note: Form A (Enquiry/ Contract/ Quality Requirements for Supplier Quality Management:
Specification 240-105658000/ QM 58 and ISO 9001) will be used to select and indicate whether
capability and capacity assessment will be conducted during the requirements setting phase of the
transaction.
5.1. Contract Execution
The supplier shall submit the following documents within 30 days (depending on the contract
duration) or as per stated timeline after the contract date, prior to the commencement of work, for
acceptance by Eskom:
Method statement before contract award. This shall be reviewed and signed off by Eskom
appointed employer agent within 30 days or as per stated timeline after contract award.
(Inspection and Test Plan) ITP(s) for review and acceptance by Eskom prior to the
commencement of any work, inclusive of subcontracted work, within 30 days or as per
stated timeline after contract award.
by Eskom within 30 days or as per stated timeline after the award of the tender. All supplier
and Eskom comments shall be resolved prior to commencing work.
considered when compiling CQPs and QCPs.
minimum of 7 working days prior to the activity being executed.
Note: These plans are to be compiled in line with Eskom’s requirements and will have to be
discussed with, and approved by, Eskom prior to any work commencing.
meetings shall be convened by Eskom with the supplier.
manager or his/her representative for the contract.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
during contract execution. The content of these reports shall be agreed by Eskom when
submitted to Eskom on a monthly basis.
5.2. Supplier Quality Performance Monitoring Phase
During the contract execution phase, suppliers shall be monitored by Eskom for performance on
quality-related aspects.
The outcomes of such monitoring will enable Eskom to take any appropriate actions pertaining to
the supplier.
The monitoring shall be carried out periodically by Eskom assigned employer agent at predetermined
intervals during the execution of a contract using agreed key performance indicators. The monitored
key performance areas include the following:
Subsequent key performance indicators associated with these areas will include the following:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
5.3. Supplier Quality Audit
5.3.1. Quality audits and related quality performance reviews are intended to provide an objective
evaluation of compliance with performance expectations defined in this specification, in the
supplier contract quality plan (CQP), and in any other project scope of work specification
such as contract document.
5.3.2. Quality audits and related quality performance reviews include, but are not limited to, any
quality or other project functional area audits, verification of compliance reviews, surveillance,
inspections, or other interim or final assessments of scope of work deliverables provided by
the supplier or sub-suppliers.
5.3.3. Quality audits and related quality performance reviews are intended to provide an objective
evaluation of compliance with performance expectations defined in this specification, in the
supplier contract quality plan (CQP), and in any other project scope of work specification.
5.3.4. Quality audits and related quality performance reviews include, but are not limited to, any
quality or other project functional area audits, verification of compliance reviews, surveillance,
inspections, or other interim or final assessments of scope of work deliverables provided by
the supplier or sub-suppliers.
5.3.5. Quality audits and related quality performance reviews shall be carried out by trained,
accredited, and experienced personnel in accordance with established documented
information for managing audits.
5.3.6. The supplier shall submit, for Eskom review, documented processes for conducting project
scope of work quality audits and related quality performance reviews. Supplier quality audits
and related quality performance review processes shall be designed to address evaluation
of progress towards completion of project functional area deliverables as well as final
deliverable quality.
5.3.7. The supplier shall provide a schedule of anticipated quality audits covering all functional
areas and related quality performance reviews at the time of first post-contract award CQP
submission.
6.1. Rights of Access
Eskom:
6.1.1. shall be granted electronic and hard-copy access to all quality plans, procedures,
documentation, and other quality records relating to the work, including, but not limited to,
data extracts;
6.1.2. reserves the right to review, inspect, and audit any or all parts of the supplier’s QMS, as well
as any documentation, materials, or equipment associated with the work, at any time or
project work location; and
6.1.3. reserves the right to carry out assessments and audits on all new suppliers and sub-
suppliers.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
The supplier:
6.1.4. shall support Eskom’s effort to monitor, verify, and/or witness any activities associated with
the work at any time;
6.1.5. shall cooperate with Eskom requests for documentation, records, and inspection and
witnessing. Eskom participation in audits, appraisals, assessment of plans, and verification
shall be conducted at no extra cost to Eskom;
6.1.6. shall ensure that a sub-supplier provides access to Eskom to all work procedures, records,
and supporting documentation through provision of access to view and photocopy, as
required, to support verification of scope of work requirements. Access shall include the
ability to photograph Eskom equipment, systems, system components, materials, etc.;
6.1.7. shall provide access to all quality-related information pertaining to activities performed by
itself or sub-suppliers, where Eskom might not have participated in the witnessing of their
quality assurance or control (this refers to inspections, audits, etc. performed by the supplier
on its own sub-suppliers);
6.1.8. shall allow Eskom to assess, audit, approve, or reject any sub-suppliers employed by
Eskom’s suppliers to assist with the product and/or service delivery to Eskom; and
6.1.9. shall ensure that the above requirements flow down to sub-suppliers.
6.2. Eskom Rights to Information
6.2.1. To expect that the works will be conducted in accordance with the contract between the
parties.
6.2.2. To have access to the supplier’s information as determined by applicable legislation.
6.2.3. Eskom reserves the right to oversee the supplier’s audit programmes by participating in
selected audits as an observer and by assessing the supplier during key work stages. Eskom
will coordinate with the supplier to develop an oversight schedule aligned with the supplier’s
audit schedule.
6.2.4. To obtain access to any audit reports of audits performed by the supplier reflected in the audit
programme.
6.2.5. To conduct independent quality audits during all phases of the contract, and the supplier shall
provide all resources to support these activities.
6.2.6. Eskom shall have the right to participate in, or request that, a technical investigation be
launched and conducted at the supplier’s and sub-suppliers’ premises or other sites when
risk to Eskom products or service deliverables is identified.
6.2.7. To participate in, and/or lead, investigations related to incidents involving its products.
6.2.8. To require from suppliers to be responsible for the cost of re-inspections.
6.2.9. To withhold payment from suppliers as a result of outstanding nonconformities, irrespective
of the agreed payment schedule and in accordance with the conditions of contract.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
6.2.10. Shall be granted electronic and hard-copy access to all quality plans, procedures,
documentation, and other quality records relating to the work, including, but not limited to,
data extracts.
6.2.11. Reserves the right to review, inspect, and audit any or all parts of the supplier’s QMS, as well
as any documentation, materials, or equipment associated with the work, at any time or
project work location.
6.2.12. Shall carry out assessments and audits on all new suppliers and sub-suppliers.
6.2.13. Reserves the right to appoint resident quality inspectors who can be based at the supplier’s
or sub-supplier’s premises and on site where the work is being performed.
6.2.14. Reserves the right to select intervention points within all developed supplier QCPs/ ITPs for
Eskom oversight of selected functions and to perform surveillance or audits of the work.
6.2.15. Shall be given access at all reasonable times before, during, and after manufacture and
before delivery, construction, erection, and commissioning to measure, test, and inspect the
products and workmanship, as necessary, at the supplier’s premises and at Eskom sites.
6.2.16. Reserves the right to suspend any pending deliveries by the issuing of a cease delivery
order at any time and for any portion of the work that is not being performed in accordance
with the specified/agreed requirements.
6.3. Preservation
The supplier shall develop and implement a comprehensive preservation programme consisting of
plans, processes, procedures and actions undertaken for the purpose of planning for and
maintenance of material deliverables quality. The supplier preservation programme scope includes,
but is not limited to, the following:
6.3.1. Engagement of personnel suitably qualified for oversight of, and (as required) direct
implementation of, preservation programme requirements.
6.3.2. Development and implementation of preservation programme training appropriate to work
need.
6.3.3. Eskom may make use of its appointed service provider tasked to provide a full suite of
services encompassing an online monitoring system and asset tracking during, but not limited
to the following stages: inspections, testing, shipping, transportation, storage, and
commissioning. The supplier is to enable full access during all of these stages in order to
allow the installation of the devices on Eskom-identified products and equipment, which
include the sub-supplier’s testing facilities, processing plant, and any other processes
deemed important towards effective and efficient quality control.
6.3.4. Eskom seeks cooperation between the supplier’s designers and those of Eskom’s service
provider in ensuring seamless installation of the device and other associated installations.
Moreover, there is also a need to integrate data flows and systems between Eskom and the
supplier. Further details are included in the Eskom specifications and works information.
6.3.5. Review and tracking of compliance with Eskom and supplier engineering specification of
preservation requirements.
6.3.6. Review and tracking of compliance with sub-supplier provided preservation requirements and
recommendations.
6.3.7. Evaluation of prospective temporary and longer-term material storage sites for consistency
with preservation programme expectations.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
6.3.8. Preservation work plan development and plan execution performance evaluation of all parties
engaged for provision of material transportation, handling, or storage services.
6.3.9. Oversight of material quality preservation plan preparation and plan execution performance
at all work locations.
6.3.10. Development of a preservation programme records management process, in compliance
with Eskom information management requirements, which comprehensively addresses
generation, maintenance, and ready access by Eskom to all preservation programme
records.
6.3.11. The supplier shall deploy a clearly defined documented programme providing for
identification of all physical asset pre-operation preservation of quality requirements. In this
reference, the term “physical assets” should be understood to include bulk materials,
including consumable items, equipment systems, system components, and any other
procured or supplied materials or equipment transferred to project control, but not deployed
for operational purposes.
6.3.12. Where the project responsibility for equipment and materials management has been formally
delegated, the supplier’s preservation programme shall ensure clear and unambiguous
communication of pre-operation preservation of goods quality requirements to sub-suppliers.
6.3.13. The supplier’s preservation programme shall clearly and unambiguously document
processes and procedures for efficient and effective monitoring of compliance with
programme requirements.
6.3.14. Compliance monitoring shall commence with ensuring comprehensive consideration of
preservation requirements in the engineering instruction and subsequent inclusion of said
instruction in procurement documentation and shall be applicable until such time as
equipment or materials have been incorporated in an operating or operational system or
structure.
6.3.15. Compliance evaluation frequency shall anticipate transfer of tactical-level responsibility for
management of preservation responsibilities between project functional areas, for example,
procurement to logistics, logistics to fabrication, fabrication to logistics, logistics to
construction, etc., and shall, in similar fashion, anticipate transfer of support for tactical-level
responsibility between various subcontracted service providers.
6.3.16. Supplier engineering shall ensure that preservation requirements for scope of work systems,
system components, equipment, materials, and other procured goods are clearly and
unambiguously documented and that preservation requirements are efficiently and effectively
communicated to project procurement, logistics, construction management, quality, security,
and other project functional areas, as required, for efficient and effective implementation of
preservation requirements. This shall take the form of a preservation programme applicable
to all systems, system components, equipment, materials, customer-supplied materials, and
other goods procured or managed under the scope of work.
6.3.17. The supplier’s preservation management programme shall clearly and unambiguously
address temporary, long-term, and in-transit preservation requirements, including, but not
limited to:
sunlight, temperature, soil, dust, humidity, salt spray, corrosive atmospheres, or
other physical environment conditions.
coverings, fasteners, lines, and other components for internal and external weather
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
proofing;
charging, heating, cooling, etc., inclusive of gas storage, electric power supply, etc.;
internal atmosphere generation, regeneration, monitoring, and relieving systems, for
example, inert gas management systems;
cyclical motion in transit, for example, wave-generated movement during sea
transport;
bracing, padding, framing, chocking, etc.;
substrates, or support required to ensure in-storage and in-transit stability of
systems, system components, equipment, and material, or other discrete units or
items;
transmittal of contaminants between work areas or between work areas and storage
areas, for example, prevention of carbon steel grinding or cutting debris impact on
stainless steel elements, airborne drift of blast aggregate into vessels or machinery,
etc.;
required supports and related binding devices, for example, stools, stands, sea
fasteners, platforms, chocks, spacers, cabling, etc.;
required to ensure provision of preservation services, for example, provision of a
self-elevating work platform for periodic access to elevated fittings, gauges, man-
ways, etc.;
example, padding or other protection for external tubing, fittings, or other impact-
sensitive structures or components;
by hard and soft barriers, as required, to maintain a protective perimeter;
management regarding security management, including, but not limited to, facility
access and egress control and control of access to project goods and materials
within facility boundaries or aboard vehicles or vessels; and
6.3.18. detailed procedures for inspection and testing to verify performance of preservation
procedures and to provide for timely notice and corrective action to maintain preservation
status.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
6.3.19. The supplier’s preservation management programme scope shall encompass management
of preservation requirements, from initial transfer of ownership or management responsibility
to project scope of responsibility, through any period of temporary or longer-term storage and
through any period of transit, including transit for final delivery at point of active use or
installation.
6.3.20. The supplier’s preservation management programme shall clearly and unambiguously
address processes and procedures to ensure that storage and control of materials are
accomplished in accordance with manufacturer recommendations, specifications, and
project-specific requirements.
6.3.21. The supplier’s preservation management programme shall incorporate special precautions
to address preservation and control of valves, electrical motors and components, mechanical
and rotating equipment, piping and fittings, instrumentation, flange faces, gaskets, coatings,
insulation, and other materials. Special precautions include, but are not limited to, supplier-
specified maintenance procedures related to engines, electric motors, pumps, compressors,
etc., such as periodic shaft rotation, engine turnover, lubrication, etc.
6.3.22. The supplier shall ensure that clear and unambiguous requirements for preservation of the
system, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented in purchase orders, work authorisations, and other
communications between the supplier and sub-suppliers.
6.3.23. Where sub-supplier expertise is utilised in determination of the preservation protocol, supplier
procurement processes shall ensure clear and unambiguous documentation of sub-supplier
input into preservation management programme requirements.
6.3.24. Supplier procurement shall ensure that preservation requirements for scope of work systems,
system components, equipment, materials, and other procured goods are clearly and
unambiguously documented and that preservation requirements are efficiently and effectively
communicated to project logistics, construction management, quality, security, and other
project functional areas, as required, for efficient and effective implementation of preservation
requirements.
6.3.25. The supplier shall ensure comprehensive, clear, and unambiguous designation of sub-
supplier responsibility for execution of all preservation management programme elements,
including, but not limited to, all systems, processes, procedures, methods, ready access to
records, and provision of equipment, tools, or services essential to efficient and effective
execution of the preservation management programme.
6.3.26. The supplier shall ensure that preservation management programme responsibilities are
clearly and unambiguously defined within the project team and efficiently and effectively
implemented at all project scope of work locations. Inclusion of supplier and sub-supplier
scope of work in the development and implementation of a preservation management
programme shall be considered essential to efficient and effective preservation management
programme execution.
6.3.27. The supplier shall ensure clear and unambiguous designation of project team responsibility
for oversight and management of preservation management programme elements during
every stage of project development.
6.3.28. The supplier shall ensure that Eskom has free and unrestricted access to all preservation
records for inspection and audit.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
6.4. Quality Audits Related Conditions
6.4.1. The supplier shall maintain an accurate quality audit and related quality performance review
schedule and shall incorporate the current schedule as an attachment to the supplier CQP.
6.4.2. The supplier’s quality audit and related quality performance review schedule development
process shall be designed to incorporate consideration of information generated by
previously conducted audits and reviews, by input from project risk management evaluations
(risk register), or from Eskom or sub-supplier subject matter expertise.
6.4.3. Eskom reserves the right to oversee supplier audit programmes by participating in selected
audits as an observer and by assessing the supplier during key work stages. Eskom will
coordinate with the supplier to develop an oversight schedule aligned with the supplier’s audit
schedule.
6.4.4. Eskom will have the right to obtain access to any audit reports of audits performed by the
supplier reflected in the audit programme.
6.4.5. Eskom reserves the right to conduct independent quality audits, scheduled and unscheduled,
during all phases of the contract. The supplier shall provide all resources to support these
activities.
6.4.6. Eskom shall be given access at all reasonable times before, during, and after manufacture
and before delivery, construction, erection, and commissioning to measure, test, and inspect
the products and workmanship, as necessary, at the supplier’s premises and at Eskom sites.
6.4.7. The supplier shall obtain access for Eskom to measure, test, witness tests, and inspect
products that are being manufactured by any sub-supplier. This includes surveillances.
6.4.8. The assessments and audits shall be carried out on all new suppliers and their sub-suppliers.
6.4.9. Eskom shall have the right to participate in, or request that, a technical investigation be
launched and conducted at the supplier’s and sub-suppliers’ premises or other sites when
risk to Eskom products or service deliverables is identified.
6.4.10. Qualification requirements for supplier and sub-supplier personnel engaged in conducting
quality audits and related quality performance reviews shall be defined in the supplier CQP
and shall be in compliance with the Project Quality Personnel Qualification Specification.
6.5. Management of Nonconformities and Nonconforming Outputs Identified by Eskom
6.5.1. Nonconformity reports raised by Eskom and issued against the supplier shall be investigated
by the supplier as a matter of urgency in order to determine the root cause, corrective action
measures, as required, with implementation time frames.
6.5.2. A formal response shall be prepared in respect of the defined criteria and submitted to Eskom
for its review, evaluation, and acceptance, within a maximum of 14 calendar days from the
date of issue of the nonconformity and should be aligned with the site
requirements/procedure.
6.5.3. Eskom may, at its discretion, request a response sooner and, in any case, before the supplier
proceeding with any pending/further intervention or corrective action, as may be required by
Eskom.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
6.5.4. Should Eskom or its inspection authority/agency identify any nonconforming products during
the conduct of its audits/surveillances/inspections, the supplier shall be deemed to be in
breach of contract and shall be held liable for any repair, rework, and/or associated
replacement costs. The supplier may, in such instances, also be held liable for the full costs
associated with the conducting of follow-up audits/surveillances/inspections.
6.5.5. The nature, magnitude, and/or frequency of nonconformity and inspection defect/rejection
reports raised by Eskom or its appointed inspection authority/agency shall form the basis of
any action to rescind/withdraw the supplier’s qualification status.
6.5.6. Nonconforming outputs identified by Eskom shall be documented via a NC Report and issued
to the suppliers via the contract communication protocol. The suppliers shall investigate the
matter and respond in writing to Eskom of disposition within the stated contractual conditions.
Note: The dates for the disposition should align to contractual conditions.
6.5.7. Eskom shall identify repeat deficiencies as systematic failures of the supplier’s QMS and
shall notify the supplier of the trends. Eskom can initiate an internal audit to highlight the
system failures. The supplier with raise a Corrective Action Report and undertake Root
Cause Analysis. In such cases, QMS rectification and/ or update measures shall be taken
immediately.
6.5.8. Should the Supplier fail to respond and rectify nonconforming products within stipulated
contractual conditions. The Project Manager should apply contractual remedies in
accordance with Fidic/ NEC contract.
6.5.9. Repeated Nonconformities, if there are any identified repeat nonconformities from the same
supplier within a period of 6 months or less. This must then be escalated to the management
review committees of the BU/ OU/ Cluster/ or Divisions for adjudication. If not resolved, then
the matter must be escalated to the supplier review committee for recommendation.
6.6. Special Processes
The following requirements shall be applicable as well as additional requirements as specified in the
scope of work for the provision of the following special process services:
6.6.1. The supplier shall ensure that all processes which require that procedures be pre-qualified
or work methods and operators tested and qualified are controlled and all steps followed
before the work can commence.
6.6.2. This typically covers such activities as welding, non-destructive testing, special fabrication
techniques, coating, painting, etc.
6.6.3. All special processes (procedures and processes) shall be submitted for review and
acceptance by Eskom, accredited or certified agency. No work shall commence until these
are accepted.
Where applicable, a relevant Management System for the special process shall be certified or
approved by an accredited body and proof of certification shall be submitted to Eskom for review.
An example for this will be the Welding Management System based on ISO 3834.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
6.6.4. The supplier shall ensure that all processes which require that procedures be pre-qualified
or work methods and operators tested and qualified are controlled and all steps followed
before the work can commence.
6.6.5. This typically covers such activities as welding, non-destructive testing, special fabrication
techniques, coating, painting, etc.
6.6.6. All special processes (procedures and processes) shall be submitted for review and
acceptance by Eskom, accredited or certified agency. No work shall commence until these
are accepted.
6.6.7. Where applicable, a relevant Management System for the special process shall be certified
or approved by an accredited body and proof of certification shall be submitted to Eskom for
review. An example for this will be the Welding Management System based on ISO 3834.
6.6.8. Where samples are required for acceptance, these shall be submitted to Eskom for review
and acceptance.
6.6.9. The supplier shall ensure that all operators are suitably qualified for these processes in
accordance with the procedures, processes and/ or applicable standards/ codes.
6.6.10. The records of qualification of procedures, processes and operators shall be maintained by
the supplier in accordance with the applicable procedure or code and these made available
to Eskom at all times.
This document has been seen and accepted by:
Name Designation
Portia Mngomezulu Group Executive: Corporate Services
Mpho Dire Chief Procurement Officer (Acting): Corporate Services
Bathusi Montwedi Senior Manager (Acting): Procurement and Supply Chain Management
Sanjiv Kalicharran Senior Manager (Acting): Risk and Sustainability - Quality Management
Rolland Ngugama Middle Manager: Risk and Sustainability - Quality Assurance
Pamela Dondashe Middle Manager: Risk and Sustainability - Quality Assurance
Date Rev. Compiler Remarks
Specification was due for revision and in addition, to
align the requirements with the latest Eskom business
October 2025 4 SA Sambo
processes and systems. Including updates on
numbering of the document.
October 2021 3 SA Sambo Specification was due for revision and in addition, to
align the requirements with the latest Eskom business
processes and systems.
October 2018 2 SA Sambo Specification reviewed to be aligned with the
requirements of ISO 9001:2015
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 4
Page:
Date Rev. Compiler Remarks
March 2016 1 SA Sambo Specification was due for revision and also to
repackage the requirements and tender returnable
documents into four categories.
December 2011 0 A Hunter New document
The following people were involved in the development of this document:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced without the
expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
B.2 Documented information for Control of Externally Provided Processes, Products and Services - Must include criteria for evaluation, selection,
Indicate with an
105658000 (x) as applicable
Specification or (-) if not
Applicable
Pre-contract award quality requirements x
(*Select Only Applicable Category). NB: Not more than one category must be selected. Also indicate
whether site assessment is applicable.
Category 1 (refer to clause 3.5.-105658000) -
Category 2 (refer to clause 3.5.-105658000) -
Category 3 (refer to clause 3.5.-105658000) X
Category 4 (refer to clause 3.5.-105658000) -
Main Supplier and Sub-supplier Capability and Capacity Assessment (refer to clause 3.-105658000) -
3 post-contract award(eskom)
Cell A2: Occupational Health and Safety Baseline Risk Assessment Substation ProjectsTemplate
The aim of the Health & Safety (H&S) specification is to provide principal contractor/s and suppliers
with:
compliance to legal and Eskom Holdings (NTCSA) H&S requirements.
contract.
NTCSA strives to exceed the minimum standards prevailing in the construction industry and requires
full commitment from all parties to be pro-active to achieve best H&S business practice.
This H&S Specification is intended for principal contractor and their contractors to develop a H&S
plan that meets the specified requirements.
2.1 Scope
This H&S specification sets out the minimum legal and NTCSA requirements for construction work
that is specific to the scope of work, site, and type of project.
2.2 Purpose
To indicate to principal contractor the H&S requirements on the project, upon which their planning
for the management of H&S will be based on and thus produce their H&S plan.
2.3 Applicability
This specification is only applicable to the project as mentioned on the first page, title all principal
contractors, contractors, service providers, suppliers and all the activities and processes carried out
for and on behalf of PD.
This specification shall be implemented from the date of approval.
Parties using this specification shall apply the most recent edition of the documents listed below.
3.1 Normative
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
Standards – SANS)
Note: only latest documents must be used and all pertinent OHS Regulation as per the scope of
works must be included. Remove this note prior authorising this specification.
3.2 Informative
[1] ISO 45001, Occupational Health and Safety Management Systems-Requirements
[2] ISO 9001, Quality Management Systems- Requirements
[3] Construction Regulations of 2014
[4] Council for the Built Environment Act
[5] Project and Construction Management Profession Act
Authorised person: a competent person who has been given permission in writing to perform
specific duties and responsibilities in terms of the Operating Regulations for High Voltage Systems.
Baseline risk assessment: (32-520) baseline operational risks refer to the H&S risks associated
with all standard processes, as well as routine and non-routine activities in the business.
Critical Lifts: (1) any lift weighing in excess of 20 tons, (2) any lift involving a crane suspended work
platform (man cage), (3) any lift over critical operating and/or process equipment and (4) any lift that
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
exceeds 85 % of the crane’s load chart (5) any lift that utilises more than one lifting device (Tandem
Lift).(6) Load transfers.(7) night lifting.
Eskom Holdings (NTCSA) Requirements: Eskom Holdings (NTCSA) requirements, which evolve
from directives, policies, standards, procedures, specifications, work instructions, guidelines, or
manuals.
Hazard identification: the identification and documenting of existing or expected hazards to the
health and safety of persons, which are normally associated with the type of construction work being
executed or to be executed.
Medical surveillance: a planned programme or periodic examination (which may include clinical
examinations, biological monitoring, or medical tests) of employees by an occupational health
practitioner or, in prescribed cases, by an occupational medicine practitioner.
Method Statement: is a written document detailing work procedures and sequences of operations.
On Site/Site: any workplace where the contractor or his employees perform construction related
work as agreed contractually with the client.
Planned Task Observation: an independent observation made during the planned period in which
the task is being executed.
Pre-Task Risk Assessment: a meeting held prior to the commencement of the day’s work with
relevant personnel (client representative included) associated with the task at hand.
Risk Assessment: a programme to determine any risk associated with any hazard at a construction
site in order to identify the steps needed to be taken to remove, reduce, or control such hazard.
H&S File: a file or other record in permanent form, containing the information on the H&S
management system during construction including all information relating to construction phase after
the handover to Client.
Safe Work Procedures: a series of specific steps that guide a worker through a task from start to
finish in a chronological order. Safe work procedures are designed to reduce the risk by minimizing
potential exposure.
Abbreviation Explanation
AIA Approved Inspection Authority
COIDA Compensation for Occupational Injuries and Diseases Act
CR Construction Regulations
DMR Driven Machinery Regulations
DSTI Daily Safety Task Instruction
EA Environmental Authorization
ECO Environmental Control Officer
FAS Fall Arrest Systems
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
Abbreviation Explanation
GSR General Safety Regulations
RHCA Regulations for Hazardous Chemical Agents, 2020
H&S Health and Safety
HIRA Hazard identification and risk assessment
HV High Voltage
LDV Light Delivery Vehicles
LMI Lifting Machine Inspector
LME Lifting Machine Entity
LTIR Lost Time Incident Rate
NEC New Engineering Contract
NEMA National Environmental Management Act
NTCSA National Transmission Company South Africa
NQF National Qualifications Framework
OHNP Occupational Health Nursing Practitioner
OHS Act Occupational Health and Safety Act No.
OHS Occupational Health and Safety
ORHVS Operating Regulations for High Voltage Systems
PPE Personal Protective Equipment
PTO Planned Task Observations
RSA Republic of South Africa
SANAS South African National Accreditation System
SANS South African National Standards
SACPCMP South African Council for the Project & Construction Management Professions
SAQA South African Qualifications Authority.
SDS Safety Data sheets
SHEQ Safety, Health, Environment Quality
SETA Skills Education Training Authorities
SWP Safe Work Procedure
PD Project Delivery
VFL Visible Felt Leadership
Manages the contract signed with the principal contractor and ensures that H&S specifications are
developed and issued with tender enquiries, and that the principal contractor’s H&S plan is approved
prior to commencement of work. He must ensure that applicable legal and other requirements are
complied with by the principal contractor and (if applicable) their contractors. The project manager,
thus takes the overall accountability of this project as
Is responsible for the overall management of the project design as well as ensuring the management
of the compliance of the completed works to the design during and after construction on site.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
Provides assurance, advice, and support to the project in the management of the H&S issues on the
project. They will also assist in the development of project’s H&S Specifications which will be issued
with enquiry documents, and that the principal contractor’s H&S plan is submitted; evaluated and
approved. They will be responsible for auditing and ensuring compliance to legal requirements. The
H&S Senior Advisor shall approve the principal contractor H&S plan in all projects that does not have
a CWP.
7.1 Visible Commitment
Visible commitment is essential in providing a safe work environment. managers, supervisors, and
employees at all levels must demonstrate their commitment by being proactively involved in the dayto-day operations, in particular H&S aspects of the project / contract.
A minimum of one (1) Visible Felt Leadership engagement (VFL) per month shall be conducted by
the contractor’s project manager. The contractor General Manager/Chief Executive or executive
representative shall one (1) VFL quarterly that shall be submitted to Client Project Manager.
7.2 Designers
The designer of a structure must comply with Construction Regulations 6 and ensure that cognizance
is taken of ergonomic design principles and foreseeable constructability health and safety risks
during construction and life cycle of the structure.
7.3 Principal Contractor’s Accountabilities
a. The principal contractor shall comply with provisions of Construction Regulations 7.
b. Where a principal contractor procures the services of a contractor, the principal
contractor shall first inform the client. Such contractor shall also comply with relevant
sections of this H&S specification.
c. The principal contractor must demonstrate how activities of various contractors will be
coordinated to mitigate the risks.
d. The principal contractor shall ensure that his/her H&S plan is approved by the client
before gaining access to site. The same principle will apply to its contractor, where he/she
shall approve his/her contractors H&S plan.
e. A comprehensive & updated list of all contractors on site, also indicating the type of work
being done.
f. The principal contractor shall coordinate, consolidate, and submit H&S performance and
that of contractors on the last day of each month to the client.
g. The principal contractor must ensure that their senior management conduct VFL, at least
once a quarter.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
h. The principal contractor must incorporate the client's induction into their induction and
induct their contractors before site access. The principal contractor shall keep all
induction material including registers.
a. The principal contractor shall comply with provisions of Construction Regulations 8.
b. The principal contractor shall appoint one (1) full-time competent construction manager
responsible for a single site. In a case where a construction manager is not available, an
alternate construction manager shall be appointed in writing for a specified duration.
c. Having considered the size of the site one or more assistant construction manager shall
be appointed in writing.
d. The principal contractor must, in writing, appoint one Full Time safety officer in
accordance with the requirements of Construction Regulations 8(5).
e. Construction supervisors and their assistance must be appointed in accordance with
Construction Regulations 8(7) & (8) respectively.
f. The appointed safety officer(s) shall be registered with SACPCMP.
The appointment of a registered or non-registered construction manager shall be
done in accordance with the provisions of the PD SACPCMP Registration Categories
attached on the Appendix A, annexure B.
Note: No construction work must commence or continue without a competent construction
manager(s), a supervisor(s), being on site.
This document is under revision control and is valid for the duration of the works and will be
amended, as and when necessary, as requirements are being amended and therefore it will be
required for the principal contractor and contractor’s H&S plan to be amended accordingly.
Conformance to this document shall be via regular safety inspections and by Monthly Audits.
9.1 Related/Supporting Documents
Annexure A – Eskom Holdings (NTCSA) SHEQ Policy Statement 32-727
Annexure B – 20241010 SACPCMP Registration Categories
Annexure C – Contractor Manpower Sourcing and Verification
Annexure D – Pre-Task Planning Template
Annexure E – Flash Report template
Annexure F – Portable Toilet Specification
Annexure G – Contractor OHS File Handover Record Template
Annexure H – PD Loading and Offloading
Annexure I – Tender Evaluation Criteria
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
Annexure J – Site Readiness Evaluation Criteria
Annexure K - Health and Safety Requirements Acknowledgement
Annexure L - Appointments and Competencies Guide_559-1762006876
Project Details
9.2 Scope of Work
The following civil works needs to be done for Kwagga Substations access road.
Refurbish 4m wide tar road
Clean open-cut drains and gutters that run next to the road
Conduct DCP and Troxler
The following civil works needs to be done for Rigi Substations access road.
Refurbish and construct 6m-9m wide tar road
Clean open-cut drains and gutters that run next to the road
Conduct DCP and CBR test
Place vegetation outside the gate of the substation
Construct cut-off drain outside the gate of the substation
Location: Kwagga and Riggi Substation
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
9.3 The Client Project Organogram:
Senior Manager
Projects
Harrish Mahabir
Programme Intergration Acting Senior Safety Risk Construction H&S
Manager Manager Advisor H&S Manager Agent
Ofhani Matsea Sandile Mokoena Linda Shabalala Lindiwe Masoeu N/A
Project Manager Project Scheduler H&S Officer
Lungi Mdletshe Nyamunzhedzi Musetsho Sherlley Mokone
Project Site Supervisor Cost Engineer Risk Advisor coordinator
Nanda Moonsamy
Wisani Mabaso Alfred Mashala N/A
Project Officer Quantity Survey
Rebone Mkhonto Kulani Maringaa
9.4 Principal Contractor Organogram
The principal contractor shall provide an organisational organogram related to this project, listing all
the levels of responsibility from the Chief Executive down to the supervisors responsible for the
project. The organogram must list the names of appointees and their roles and responsibilities
including the statutory requirements appointees. All organograms shall be updated timeously when
appointments are changed and filed in the project H&S file.
For the duration of the contract, the principal contractor shall ensure that competent persons are
appointed in writing in terms of the requirements of the OHS Act and its Regulations; and
or other statutory and Eskom Holdings (NTCSA) requirements and that all their appointees are made
aware of their accountabilities and responsibilities and have been suitably trained in terms of their
appointment.
The principal contractor shall notify in writing in a form similar to annexure 2 the relevant Provincial
Director (Labour Centre) of the Department of Employment and Labour of the intention to carry out
construction work as defined in the Construction Regulations 4, at least 7 days before construction
work is to be carried out. No construction work shall commence without a proof of submission of
such notification to the client.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
11.1 OHS Act Section 37 (2) (Legal) Agreement
a. An OHS section 37(2) agreement shall be signed between the client and the principal
contractor at the time of contract award.
b. The original copy of an OHS section 37(2) agreements shall be retained by the contractor
and a copy retained by the client project manager.
c. A copy of OHS section 37(2) agreement must form part of the respective contractor’s H&S
file.
11.2 CR 5(1)(k) Appointment
a. At contract award the principal contractor shall be appointed in writing by the PD Project
Manager for the construction site. Therefore, site access shall be granted once all the
contractual requirements are met.
b. A copy of CR 5(1)(k) appointment must form part of the respective contractor’s H&S file.
11.3 Designated employer, Sec 16(2) and other competencies appointments
The principal contractor shall ensure that a designated employer is appointed in writing for the for
the duration of the project.
The principal contractor shall ensure that competent persons are appointed in writing for OHS
statutory and non-statutory functions in line with their organisational structure. See Annexure L
The principal contractor shall ensure that the appointees understand their roles, responsibilities and
accountabilities. Copies of relevant appointments shall be kept on an OHS site safety file.
The scope of training shall include, but not limited to, the type of work being performed and the
relevant procedures. Where training is provided by the external service providers, the principal
contractor shall ensure that the service providers are accredited by SAQA or QCTO (Appropriate
qualifications and training registered in terms of the National Qualifications Framework Act No. ).
The principal contractor must demonstrate how he/she intends managing training/awareness within
their organisation including method of informing visitors and other persons entering the site about
hazards prevalent onsite.
Persons with foreign qualifications and registrations to convert these to equivalent local registrations
in that level or category (this shall be in accordance with SAQA and SETA requirements). The letter
from SAQA shall form part of the tender and site readiness submissions to PD.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
The principal contractor shall develop an OHS Policy authorised by their Chief Executives that states
overall OHS objectives and commitment to improving OHS performance and must be conspicuously
displayed and shared with all stakeholders.
The principal contractor shall comply with relevant legal and other requirements as part of the
contract. Expenses to the principal contractor, which result from such compliance, as well as any
site-specific requirements, will be for the principal contractors’ account.
Where the principal contractor appoints another contractor(s), the same roles, and responsibilities
in relation to the contractor as the client has in relation to the principal contractor shall apply.
The client reserves the right to stop work and issue a non-conformance report and/ Prohibition
notice(s) whenever H&S violations are observed from the principal contractors and their contractors,
after engaging and making both aware of such. Expenses incurred because of such work stoppage
and standing time shall be for the principal contractor’s account. Any nonconformances/findings/observations found during the audits/inspections on the contractor shall be
raised and discussed with the relevant principal contractor (with whom the contractor is contracted
with).
15.1 Legal and Other Requirements
The principal contractors shall comply with the relevant applicable legislation, specifications, and
standards in accordance with the scope of the project.
The principal contractor shall compile a legal register listing all applicable legislation and standards
that may have an impact on the scope of work that they are performing on the construction project.
The register shall be updated as and when there are amendments.
The Bill of Rights in the Constitution of the Republic of South Africa is clear on the rights of
children, especially when it comes to child labour. Child labour shall not be permitted in any of
NTCSA, PD sites.
The principal contractor shall develop a Risk Assessment in line with Construction Regulation 9 in
alignment to Eskom/NTCSA, 32-520 procedure.
Detailed Risk Assessment must be conducted to ensure that all the applicable scenarios are covered
and documented per site activities including practical controls. High Risk Activities
When the principal contractor and/or his/her contractors are working in an area where a high health
and safety hazard exists, the principal contractor shall:
a) Develop a SWP.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
b) Ensure that permanent and adequate supervision is available for the duration of the work
performed.
c) Work within visible earths (Standard Line Construction Method).
d) Ensure the use of safety standbys in areas of high-risk activities, and activities that fall within
the scope of the permit to work system.
e) Provide, erect and maintain the required barricading, lighting, flags, flashing lights, or other
safety control equipment to enable operations to proceed in a safe manner.
f) Maintain defined access ways, which are clear of obstructions, to allow for emergency vehicle
entry.
g) Provide any temporary protective shielding required for protecting nearby operations from
the construction activities, at their own cost.
a. To ensure the safety of workers, visitors and other persons who may be affected, the
operating regulations for high voltage systems shall apply during construction of high voltage
apparatus (construction of transmission/distribution lines) or working in live yard inside a
substation.
b. The principal contractor shall ensure that workers in prohibited areas inside a sub-station are
under supervision of an authorised person, under a work permit. When an authorised person
resigns from a company and is employed by another company, his authorisation shall expire
immediately.
c. The authorised person shall be present throughout the operations.
Reference: ORHVS, 240-114967625 and Power Delivery Operating Assessment,
Authorisation and Training Standard, 240-70413865.
The principal contractor shall ensure that the submitted tender adequately makes provision for the
cost of H&S.
Note: the costing for H&S must be itemised based on the overall scope of the project e.g.: resources,
provision of PPE, occupational hygiene, occupational health, etc.
The principal contractor shall not permit any person to enter the construction site where their health
and safety may be at risk. Notices at every entrance prohibiting the entry of unauthorised persons
shall be posted:
a. No one should enter the construction site without being inducted. The principal contractor
shall demonstrate how site access shall be manage on site.
b. Entering or leaving the site shall only take place at official access control points and may only
be done via the official designated walkways.
c. Where construction line is being constructed the principal contractor shall ensure that:
i). Members of the public are not allowed to be in the proximity where the activities are
being executed.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
ii). Domestic animals are managed not to be in the proximity where the activities are being
executed.
Symbolic safety signs shall comply with the requirements of SANS 1186.The display of the following
signage is mandatory:
a. The principal contractor sign shall be posted at their site offices and shall have the name
and contact details of the: Construction Supervisor; Health and Safety Manager/ Officer; First
Aider; Health and Safety Representative and Evacuation warden, Construction Health and
Safety Agent and Construction Permit (where applicable). Emergency numbers, principal
contractor name (including a logo), construction manager and contact number.
b. The Contractors shall provide signage in accordance with the scope and work area.
c. All safety and warning signs shall be always obeyed.
Site facilities shall be established and maintained by the principal contractor. The facilities include
but are not limited to the following (refer to OHS Act, Construction Regulations 30). See also
Annexure F for portable toilet specifications. The design of the toilet should not expose employees
to splashes of other people’s human waste.
Principal contractors shall in their H&S plan, factor how they would safeguard members of the public
against their activities during the project.
24.1 Life Saving Rules
The Eskom Holdings (NTCSA) Life Saving rules applies to NTCSA employees, agents, consultants,
contractors, and visitors. Visitors to NTCSA sites are expected to respect and comply with these
rules. Anyone who refuses to do so may be instructed to leave to leave NTCSA premises
immediately. Failure to adhere to these rules will be regarded a serious transgression, and it is
expected that the employer will take appropriate disciplinary action. The client also reserves the right
to suspend the contractor’s activities pending the outcome of such disciplinary processes.
These rules are enforced to prevent serious injury or loss of life among employee, labour broker or
contractor working in any area within Eskom Holdings (NTCSA) area.
The rules are:
Rule description of rule
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
Open, isolate, test, earth and create an equipotential zone
Before touch
To ensure a safe electrical work environment, no person may work/operate on, around
or near any electrical network, line or apparatus, electrically connected to the power
Rule 1
system and/or electrically charged and/or not electrically charged unless if trained,
authorised, competent and supervised. The equipotential zone is only applicable for
work being done on medium and high voltage apparatus.
(That is plant, any plant operating above 1000 V)
Hook up at height
Working at height means any work performed above a stable work surface or where a
person puts himself/herself in a position where he/she exposes himself/herself to a fall
Rule 2 from or into.
Working at height is a significant part of work in NTCSA and is regarded as a high-risk
activity, as a result, all precautions must be taken to prevent incidents while working at
height.
Buckle up
Where required, the proper wearing of seat belts for any driver, operator and passenger
Rule 3 is mandatory in all vehicles/equipment when driving and/or travelling for NTCSA
business purposes.
.
Be sober
No person who is under the influence or who appears to be under the influence of
Rule 4
intoxicating liquor or drugs will be permitted to enter or remain on a NTCSA site conduct
NTCSA business or drive/operate a vehicle/equipment for NTCSA business purposes.
Ensure that you have a permit to work
Rule 5 No person shall work without the required Permit to Work (PTW). This includes driver’s
license and other statutory permits
Ensure safe live working
To ensure safe live work: Each live worker shall ensure all live work basic principles are
adhered to, as outlined (for the method being used) in the High Voltage Live Working
Rule 6
Standard; Observe and maintain the Minimum Approach Distance; Only perform live
work and tasks that are authorised for and that are documented in the respective Task
Manual.
24.2 Smoking
Smoking is only permitted at designated areas in accordance with the requirements of the
smoking policy (32-1126: Eskom Holdings (NTCSA) Smoking Policy). Add to the appendix A.
24.3 Cellular Phones
A contractor shall develop and implement a risk-based cell phone policy for a particular
construction site. Cellular phones shall not be used in areas where their usage is prohibited.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
24.4 Fire Extinguishers
A Principal Contractor shall have a layout plan (site offices, laydown area) where fire-fighting
equipment is located. Fire extinguishers should be inspected monthly and be maintained annually
by a competent service provider. These records shall be kept in the project safety file.
24.5 Vehicles and Traffic Rules
a. The principal contractor shall ensure that the driver of the vehicle has a valid driver’s licence.
b. Principal contractor shall ensure that drivers and passengers wear seatbelts while travelling
in a motor vehicle.
c. No passengers shall be permitted to be transported at the back of trucks or light delivery
vehicles (LDV).
d. Passengers shall only be permitted to be transported at the back of such vehicles if fitted with
a specially designed crew cab with appropriate seating and seat belt per passenger, by the
manufacturer and manufacturer appointed fitment centre. The test certificate shall be
submitted for consideration to the client.
e. Where a vehicle licence condition stipulates the number of persons to be transported on the
vehicle, such number shall not be exceeded.
f. The principal contractor shall ensure that the vehicles are inspected daily and maintained
regularly as per the manufacture’s specification.
24.6 Substance and Drug Abuse Management
a. The principal contractor must develop a substance abuse management procedure to manage
substance abuse on site. The procedure shall be in line with the client substance abuse
management procedure were applicable. Eskom Holdings (NTCSA) Substance Abuse
Procedure 32-37.
b. All testing equipment shall be calibrated as per the manufacturer’s recommendation and the
calibration be available on the safety file.
c. The alcohol testers must be trained and appointed in writing.
The principal contractor shall conduct a daily pre-task risk assessment with employees involved with
the task, such as DSTI. This assessment will be the basis of daily pre-job briefings or toolbox talks
before work begins, highlighting critical steps from the SWP to ensure safety. Proof of
communication and confirmation of understanding will be recorded and kept at the job site during
execution. The signed pre-task risk assessment form shall be filed in the safety file.
Upon receipt of the task for the day, the principal contractor manager or his/her assignee the site
supervisor, shall perform a pre-task planning in accordance with Line Construction; Substation
Works and 559-1432317009 Rev 1, Pre-Task Planning Template, see, Annexure D.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
The principal contractor shall compile a project/ site-specific SWP for all the high-risk activities as
identified in the risk assessment and scope of work, which will be submitted to client. Proof that the
SWP’s are discussed with all employees on site should be available in the site safety file.
The construction manager / supervisor shall conduct Planned Task Observations (PTO).
PTOs shall be conducted in such a way that the employee is observed against the actual steps of
the safe work procedure (SWP)/ method statements and marked against compliance with each step.
This will assist in determining employee competence and compliance. Record shall be kept. The
findings raised on the PTOs must be addressed/discussed with all employees on site to ensure
conformance and adherence to safe work procedures and method statements.
The minimum items that must be in the PTO but not limited to:
a. Project name.
b. Title of the SWP, reference number and revision number.
c. Specific activity.
d. Steps.
e. Safety Steps.
f. Critical steps.
g. Follow-up action.
h. Observation conducted by (full name).
i. Designation (e.g., supervisor).
j. Individual/Team observed names.
k. Date of observation.
l. Signature.
Work at Elevated Positions and Roof Work
The Principal Contractor shall ensure that all work performed at elevated positions conform to
the requirements of the Construction Regulations, the relevant Unit Standard (US) and 32-418
(Working at Height Procedure).
assessments will be compiled, implemented, reviewed, and communicated to all employees
working at heights.
at intervals to be determined by the principal contractor, and taking into consideration:
a. Incident trend analysis, or new/revised technology.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
b. Changes to scope of work, changes to work methods/procedures/equipment, etc.
weather.
safety harness shall be worn when working at an elevated position. All FAS equipment in use
must meet the specifications outlined in the OHS Act and the following applicable standards:
a. SANS 50361:2003
b. SANS 50363:2003
c. SANS 50353-1:2003
d. SANS 50354:2003
e. Eskom Work at Heights Standard 32-418
f. Eskom Personal Protective Equipment (PPE) for Work-at-Heights Specification 240-
Working in elevated positions shall only be carried out under the supervision of a competent
person in accordance with US 229995.
possible:
a. Fall protection equipment shall comply with Unit Standards and other recognised
international standards.
b. The Principal Contractor and/or his contractor shall compile a fall protection equipment
inspection, testing and maintenance procedure (Refer to SANS 50365 and manufactures
requirements for safe use and for inspections).
the protection of persons working below. A drop zone shall be established with barricading and
necessary signs.
29.1 Ladders (Portable)
a) Ladders used on the site shall comply with the OHS Act and Regulations, the relevant
SANS standards, or other recognised international standards.
b) Damaged ladders shall be clearly marked and quarantined and removed from the project
site.
c) Prior to work being performed, an adequate risk assessment shall be conducted, and
work shall be conducted in accordance with General Safety Regulation 6 and 13A and
Construction Regulation 10 of the OHS Act
29.2 Training and authorization
a) Every employer shall ensure that no person engages in any activity in relation to work at
heights unless they are competent to do so.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
b) Only training providers that use competent training instructors and assessors who are
SETA-Accredited and SAQA-registered in terms of the relevant unit standards shall be
used.
c) All persons who work at heights or who are required to do rescue at heights shall receive
three days of Fall Arrest System (FAS) training and two days of rescue training in
accordance with the Unit standards 22998 and 229995.
d) The Contractor must ensure that all persons who work at heights and those who will be
required to do rescue at heights shall receive training according to the relevant unit
standards. As a minimum, individuals who work at height and are not responsible for
performing a rescue must undergo three days of FAS training (Unit Standard 229998)
and rescuers must further undergo two days rescue training in accordance with the Unit
Standard 229995. Rescuers must be appointed in writing for the site/project.
e) Official FAS training shall not have an expiry date on the certificate.
f) Only the training date shall be indicated on the certificate.
g) Official rescue training shall expire every three years from the date of issue.
h) The principal contractor shall ensure that there is a Level (insert level 2 or 3 depending
on the SoW and remoteness of the site) First Aider trained for every team working at
height. See Annexure L - all line construction First Aider shall be level 3
NB: All work at heights appointments and competency certificates shall be kept in the Health and
Safety File.
The principal contractors and contractors shall identify the occupational stressors which could
include exposure to chemical and biological hazards, noise, dust, vibration, heat, etc., to which any
person may be exposed because of his work activities.
30.1 Occupational Hygiene Management Program
Principal Contractors and contractors shall develop, implement, and maintain an occupational
hygiene management programme to ensure that the occupational hygiene stressors are identified
assessed (monitored) and controlled. The occupational hygiene programme shall include, but not
limited to the following elements:
a. Occupational health risk assessment as a foundation.
b. Occupational hygiene monitoring program. Monitoring shall be performed by a SANAS
accredited AIA.
c. Communication of occupational hygiene results and requirements.
d. Conduct awareness trainings and keep registers; and
e. Keep Occupational Hygiene surveys reports for a period of 40 years.
Where there are occupational hygiene stressors, principal contractors and contractors shall ensure
that occupation surveys are conducted to assess stressors. These programs may include but not
be limited to:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
a. Hearing Conservation Programme.
b. Heat and cold stress Management Program.
The principal contractors and contractors shall report to the Department of Employment and Labour
on occupational hygiene milestones (e.g., crystalline silica). Evidence of reporting and copies of
such reports shall be made available to the client senior advisor H&S / H&S officer.
Copies of all occupational hygiene surveys conducted by the principal contractor and contractor shall
be submitted to PD Management/Occupational Hygiene Practitioners for information and record
keeping.
The principal contractor shall provide and adhere to effective monitoring procedures. These
procedures shall include the planning, carrying out and recording of the results of the measurement
programme. This is to confirm the effectiveness of the implemented control measures, and the
results shall be made available to the Contracts Manager/Employer’s Representative on request.
Note: Principal contractors and contractors are responsible to measure and monitor all Occupational
Hygiene stressors as contemplated in the Occupational Health and Safety act 85 0f 1993.
30.2 Medical Surveillance Programme
The Principal Contractor and contractor shall ensure that their employees are registered on a
medical surveillance programme and are in possession of a valid medical fitness for duty certificate
specific to the construction work to be performed. The Fitness for duty certificate shall be in form of
Construction Regulation, Annexure 3, and be relevant to the type of work (risk based) that the
employee will be exposed to.
The principal contractor and contractors shall ensure that employees have undergone pre-entry
medical examination before starting work on site. No employee shall access site without a valid
medical fitness for duty certificate.
The principal contractor and contractors shall ensure that employees undergo a periodic medical
examination as and when a need arise.
The Principal Contractor and contractors shall ensure that employees undergo an exit medical
examination at the end of the project or when the service of the specific employee has been
terminated or has expired.
Note.: The client will only accept medical surveillances conducted by an Occupational Health
Practitioner who holds a qualification in occupational health and registered with Health Professions
Council of South Africa (HPCSA).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
30.3 Pre-Existing / Current Medical Condition
30.3.1 Disclosure of pre-existing injuries or medical conditions
A pre-existing condition as defined by the OHS Incident Management Definitions and Classification
Parameters Standard (240-131838225), is a medical condition/medical impairment as a result of an
incident arising out of, and in the course of employment, shall be considered:
a) Non-work-related if the incident arises solely because of a pre-existing medical
condition/medical impairment and if a worker without such a condition/medical impairment
would not have suffered such an incident; or
b) Work-related if the incident arises where the pre-existing condition/medical impairment may
have been a contributing factor.
Note 1: Principal contractors are to follow their own processes and procedures for classification. At
a minimum, the decision about the impact/implication of such pre-existing medical condition/medical
impairment must be confirmed by an occupational medicine practitioner (as defined in the OHS Act,
section 1).
Pre-existing medical conditions can include health issues such as cancer, diabetes, lupus,
depression, acne, hypertension, asthma, arthritis, ulcerative [Allergies] colitis etc or just about any
other health condition such as previous medical operational condition in any part of the body.
An injury are any old injuries that existed prior to the work injury that may or may not have fully
healed. Some workplace environments could aggravate pre-existing conditions even if they would
not necessarily have caused a new condition in an otherwise healthy individual. Examples may
include amongst others, traumatic injury worsening back pain, joint pain (condition), sore neck, knee
injuries etc.
30.3.2 A prospective employer / Supplier expectations/ duties
A prospective employer / supplier shall:
a) request a prospective worker to disclose all pre-existing injuries or medical conditions existing
during the period of the employment process that could reasonably be expected to be
aggravated by performing their employment related duties.
b) request disclosure in writing and this request must be accompanied by details of the nature
of the duties that are subject to the employment.
c) advise prospective workers that if they knowingly supply false or misleading information, they
will not be entitled to compensation or damages under the Compensation for Occupational
Injuries and Diseases Act, Act for any event that aggravates the non-disclosed
pre-existing injury or condition.
d) ensure that pre-existing or current condition is part of:
i). Individual employment contract. Because the contract defines the terms and
conditions of employment
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
ii). Included in the employment induction.
iii). Person Job Specification shall be developed to have a portion where the individual
when visiting the occupational medical practitioner, it has been completed by the
employer, employee and the medical practitioner can complete the document.
iv). The employee shall reveal any pre-existing or current medical condition to the
Occupational Medical Practitioner prior the assessment.
v). Part of toolbox talk at least monthly, and awareness conducted more often, and
vi). Records shall be kept.
30.3.3 A prospective contractor employee duty
A prospective employee must, where requested in writing by a prospective employer, disclose all
pre-existing injuries or medical conditions of which they are aware of, that could reasonably be
expected to be aggravated by performing the employment related duties. If the prospective
employee is engaged before making the disclosure (or being requested to make the disclosure),
his or her entitlement to compensation is unaffected.
However, if the prospective employee does not disclose pre-existing medical condition or injury,
this may have an impact on the future management of incidents in particular the work relatedness
or not of an incident which may be attributed or not to pre-existing conditions.
30.3.4 Key considerations for employers
Employers considering implementing changes to their employment conditions and processes in
relation to these amendments shall note:
a) it is the prospective employer's duty to request disclosure of pre-existing injuries or medical
conditions from prospective workers during the pre-employment, periodic and post
screening process, and such information shall be kept confidential.
b) when providing details of the nature of the duties that are subject to the employment, it is
important that this information is accurate and provides specific details of the nature of the
duties. The prospective employee must receive information that will enable them to make
an informed decision about whether their pre-existing injury or condition might be
aggravated by the duties.
c) if the Workers' Compensation Commissioner has previously provided a copy of the
employee's claims history summary the employer shall not:
i). disclose to anyone else the contents of or information contained in the
summary.
ii). give access to the document to anyone else.
iii). use the contents of or the information contained in the summary for any
purpose other than for the purposes of the employment process (penalties
apply).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
d) changes to employment conditions and processes should be made in consultation with the
employer's human resources or advisor and employee representative. Employers who may
have queries concerning equal employment condition and processes should seek
independent advice.
e) employers shall keep accurate records relating to this disclosure as this information will be
requested where applicable during the claim determination process.
f) The employer shall follow their own disciplinary procedure and share the outcome with the
client.
Note:
I. The employer shall ensure that the employees are not exposed or expected to execute
an activity that will exacerbate the pre-existing or current medical condition. Risk
assessment shall be conducted to determine the area where the individual shall be
expected to execute the duties.
II. The pre-existing or current medical condition shall be applicable to new or current
employees within a specific employer.
III. The employer shall manage all the pre-existing or current medical condition (this
include referrals medical conditions) as per legal requirements as all information shall
be kept private and confidential all the time.
30.4 Emergency Care
A list of emergency numbers (local emergency numbers and Eskom Holdings (NTCSA)
ER24(084 124/010 205 3400) numbers) shall be posted where it is visible in the office’s places such
as information H&S board, eating area etc. The principal contractor and contractor(s) shall ensure
that all employees are familiar with the emergency numbers. Where the principal contractor or/and
contractor(s) has established their own contract with a specific service provider, those numbers must
be part of the induction and be used in conjunction with local or Eskom Holdings (NTCSA) numbers.
The principal contractor must make clear to the employees that in any event one of the numbers
must be used or the combination to ensure that the life of the individual is preserved.
30.5 Employee Assistance Programs (EAP)
The contractor will engage the local clinics on HIV/AIDS Awareness programme. This will include
voluntary counselling and testing (VCT) of individuals, with chronic illnesses such as diabetes;
hypertension; HIV/AIDS awareness training. Ensure access to ongoing support for affected
individuals. The Contractor shall communicate the programme to all personnel.
30.6 Rehabilitation
The principal contractor and contractor(s) shall ensure rehabilitation of employees injured where
rehabilitation is required.
The treating Doctor/Hospital will recommend and refer. The principal contractor must comply with
recommendations, communicate with employee and provide transport according to the planned
appointment.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01
HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx
Revision: 01
Page: of 39
The process shall continue until the rehabilitation of an employee is declared fit by the
Doctor/Hospital.
30.7 Compensation of Occupational Injuries and Diseases Act (COIDA)
The principal contractor and contractor(s) shall submit a valid letter of good standing with the
compensation fund or a licensed compensation insurer relevant for the construction sector.
a) The principal contractor shall provide a site-specific emergency preparedness and
response plan of which it shall include the specific activities being executed for site and
offices and submit this plan to the client for review.
b) The Emergency Preparedness Plans must be relevant to the scope of works and to the
prevailing surrounding environmental risks.
c) The principal contractor shall ensure that all the employees are fully conversant with this
plan.
d) The Principal Contractor shall plan, conduct emergency drills at specific intervals and
identify areas for improvement. The report shall be written and action plan where
applicable be developed and all the records shall be made available for inspection/audit
by the client and/or authorities.
e) When preparing worksite Emergency Preparedness Plans, cognisance must be made
as to the locality of the site and the response time for the emergency services. Where
sites are remote, contractor management shall ensure that enough employees are
trained in the various disciplines to be able to afford prompt response attention.
Contractors shall develop a fire safety procedure for the office/ campsite, which must meet the
requirements of the local authority fire department and Section 9 of the Environmental Regulations
for Workplaces.
The principal contractor must develop a comprehensive site layout plan with the following as a
Name list of all contractors’ employee on site:1 To be supplied to the Security In following format Department before
Compliance Requirements
Source: SHEQ FOLDER.zip (unknown)No specific requirements found
A site plan must indicate evacuation routes and emergency assembly point locations.
Zones for particular activities.
Cranes (including radii and capacities).
Site offices.
Welfare facilities.
Off-loading, temporary storage and storage areas (laydown areas).
Sub-contractor facilities were applicable.
Car parking including reverse parking. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30 File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01 HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx Revision: 01 Page: of 39
Access (must consider people with disability), entrances, security and access controls, temporary roads, and separate pedestrian routes.
Site hoardings and existing boundaries.
Temporary services (including electrical power, lighting, water distribution, drainage, information and communications technology, site security systems, and so on).
Location of fire extinguishers and first aid kits including blood spill kit where applicable.
Fire hazard The Contractor shall develop emergency protocols for dealing with fires, which may include a Fire Management Plan in accordance with the National Veld and Forest Fire Act (No ) and ensure that all staff is trained / informed in fire prevention. No area shall be denuded of vegetation to create firebreaks. Open fires are not allowed on site. The Contractor Environmental Officer shall ensure that in areas with a high fire danger rating, staff is informed of this. Smoking shall be restricted to designated areas or shall not be allowed, particularly in areas that have a high fire danger rating. Contractor shall ensure that adequate Fire Fighting equipment is available on site, particularly near hot work and/or where it is specifically identified as a requirement by either the landowner or during the risk assessment.
Environmental factors to H&S The principal contractor shall monitor dust and noise caused by mobile equipment, generators and other equipment during construction. Factors such as wind can often affect the intensity to which these impacts are experienced. To ensure that noise does not constitute a disturbance during construction activities. Dust suppression measures shall be in place to reduce the dust caused by the movement of heavy vehicles and other contractor activities in order not obscure visibility.
Signing off the contract No project shall be signed off before the client has assessed the activities completed in relation to health & safety outstanding issues.
Forums for Governance and Communication Governance and communication structures shall be established on site where project H&S matters shall be discussed. The agenda, minutes and attendance registers of H&S meetings shall be available. NOTE: These meetings do not replace or act as a substitute for the required statutory meetings. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30 File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01 HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx Revision: 01 Page: of 39 Statutory H&S Committees in terms of Section 19 and 20 and General Administrative Regulations 5 of the OHS Act and Eskom Holdings (NTCSA) requirements shall be established.
Construction Vehicles and Mobile Plant Construction vehicles and equipment shall comply with the relevant legal and other requirements like Construction Regulations 23, the National Road Traffic Act, the Mine Health and Safety Act, National Environmental Act and Eskom Holdings (NTCSA) Vehicle Safety Specification Procedure 240-62946386. The following requirements are applicable during operation of construction vehicles: A principal contractor shall ensure that construction vehicles and mobile plant are operated by persons with appropriate training, certified competent and in possession of proof of competency, and authorised in writing to operate those construction vehicles and mobile plant
Designated drivers shall be in possession of an appropriate valid driver’s licence for the class of vehicle operated. The driver’s license shall be kept by the person so authorised who shall produce such card on request.
All construction vehicle operators, flagman/banksman/signalman/pointsman shall wear visible PPE at identified high-risk construction sites and shall be visible to the operators during the day or night.
Heavy construction vehicle parking sites, driveways, or any site shall be designed in such a way that no reversing is required. Where reversing is unavoidable, it shall only be done in the presence of a flagman or a banksman.
The contractor shall develop a vehicle and pedestrian management plan.
Relevant traffic signs shall be displayed.
Reverse beepers shall be fitted on construction vehicles.
Drivers of construction vehicles and mobile plant shall have medical certificates of fitness to operate those construction vehicle and mobile plant, issued by an occupational health practitioner in the form of Annexure 3 of the Construction Regulations.
The speed limit within the bounds of the construction site shall be clearly stipulated and communicated to everyone and be part of the induction.
Drivers / operators shall not text or talk on cell phones or two-way radios while driving.
The Principal Contractor/ contractor shall ensure that employees do not: i). Ride on back of light delivery vehicles, cranes or other mobile plant equipment. ii). Leave vehicles unattended with the engine running. iii). When unattended, vehicles shall be locked, chock blocks fitted, and keys removed.
Vehicle shall be searched on the premises or when entering or leaving the premises.
The Principal Contractor/ contractor shall be responsible for the safety and security of his vehicles (including private vehicles) on the premises. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30 File name: Central Grid Access Road Kwagga and Riggi Substation _ C.TXA1293 _Rev 01 HEALTH AND SAFETY (H&S) SPECIFICATION Unique Identifier: 555xxxxxxxxx Revision: 01 Page: of 39
The Principal Contractor/ contractor shall maintain his vehicles in roadworthy condition with valid licenses. These vehicles shall be subject to inspection by the Client representative. Un- roadworthy vehicles shall not be allowed to site.
B-BBEE Minimum Level: 2
Section
Source: SHEQ FOLDER.zip[2] ISO 9001, Quality Management Systems- Requirements
Description
Source: BOQ.zipCell D2: NATIONAL TRANSMISSION COMPANY OF SOUTH AFRICA (ESKOM)
Cell D2: NATIONAL TRANSMISSION COMPANY OF SOUTH AFRICA (ESKOM)
Evaluation Criteria
Source: BOQ.zip (unknown)No eligibility criteria specified
Technical Specifications
Source: BOQ.zip (unknown)Cell D2: NATIONAL TRANSMISSION COMPANY OF SOUTH AFRICA (ESKOM)
Cell D2: NATIONAL TRANSMISSION COMPANY OF SOUTH AFRICA (ESKOM)
Compliance Requirements
Source: BOQ.zip (unknown)No specific requirements found
Description
Source: NEC.zipThe work involves repairing and resurfacing the access road at Kwagga Substation (Pretoria West) and Rigi Substation (Vanderbiljpark). The road is approximately 342m long and 4m wide, refurbished from gravel to asphalt. The Employer's objectives and purpose are to repair and resurface the access road from outside the station main gate until the station. The design includes standard civil works as part of the detail design. One-in-ten-year-return weather data is provided in Annexure A.
Submission Guidelines
Source: NEC.zip (unknown)Submit one fully completed original copy of the tender, signed, including the Schedule of Deviations (if any). The contract is NEC3 Engineering and Construction Contract (April 2013) Option B (re-measurement). The Bill of Quantities is a pricing document only. The Employer is NTCSA. Working hours are 08h00 to 16h00 weekdays; weekend work only on request. The Contractor must have an NTCSA certified and authorized person available in each work area. All tools must have valid test certificates produced two weeks before site establishment. The Contractor leaves site only after a written site instruction from an NTCSA site representative. Submit an organogram with updated CVs of key personnel within 7 days after contract award. Invoicing must include contractor and project manager names and addresses, contract number and title, contractor's VAT number, and employer's VAT number. All scope changes must be approved by the Project Manager. Bonds/guarantees must be provided in the form given in Part 1 of the contract data.
Evaluation Criteria
Source: NEC.zip (unknown)Not explicitly stated in the provided text.
Technical Specifications
Source: NEC.zip (unknown)| |
The Employer, identified in the Acceptance signature block, has solicited offers to enter into a contract for the procurement of:
Please read both the NEC3 Engineering and Construction Contract (April 2013) and the relevant parts of its Guidance Notes (ECC3-GN) in order to understand the implications of this Data which the tenderer is required to complete. An example of the completed Data is provided on pages 156 to 158 of the ECC3 (April 2013) Guidance Notes.
Clause 11 in NEC3 Engineering and Construction Contract (ECC3) Option B states:
1.2 Employer’s objectives and purpose of the works 5
Kwagga Substation is located in the Gauteng province, in Pretoria West ; Figure 1 below displays the locality map. The refurbishment of the access road at Kwagga Substation is designed for which this report includes the standard civil works as part of the detail design.
Annexure A: One-in-ten-year-return weather data obtained from SA Weather Bureau for [weather station]
Please read both the NEC3 Engineering and Construction Contract (April 2013) and the relevant parts of its Guidance Notes (ECC3-GN) in order to understand the implications of this Data which the tenderer is required to complete. An example of the completed Data is provided on pages 156 to 158 of the ECC3 (April 2013) Guidance Notes.
Clause 11 in NEC3 Engineering and Construction Contract (ECC3) Option B states:
1.2 Employer’s objectives and purpose of the works 5
Rigi Substation is located in the Gauteng province, in Vanderbiljpark; Figure 1 below displays the locality map. The refurbishment of the access road at Rigi Substation is designed for which this report includes the standard civil works as part of the detail design.
| |
Annexure A: One-in-ten-year-return weather data obtained from SA Weather Bureau for [weather station]
The Employer, identified in the Acceptance signature block, has solicited offers to enter into a contract for the procurement of:
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 38 of 2000
Important for public-sector construction and infrastructure tenders that require contractor grading or construction procurement standards.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 107 of 1998
Relevant where environmental authorisations, EIAs or environmental compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 85 of 1993
Sets health and safety duties for contractors, employers and service providers working on public-sector sites.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 103 of 1977
Relevant where building standards, renovations, maintenance or construction compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Address
Gauteng - Vanderbijlpark - Vanderbijlpark - 1911
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
5
Last checked
08 Sept 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Median Estimate
R 3 155 171
Range
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
Learn how to submit a winning bid with these related articles
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Construction. Unlock full pricing strategies, bid frequency, and historical win rates.