Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
tender Office - tender Office - tender Office - 0000
Organization Type
GOVERNMENT
Published
19 Nov 2026
OCDS Reference
ocds-9t57fa-178953
ESKOM requires the supply of metallurgical replicas for outages on an 'as and when required' basis for a period of five years at kusile power station. Bidders must comply with eskom's supplier quality management specification (qm 58), which mandates a formal iso 9001-compliant quality management system and submission of category-specific quality documentation. The most consequential consideration is the quality category (1–4) selected by ESKOM, which determines the exact returnable documents and the depth of qms evidence required.
Closing date and time: 7 December 2026 at 08:00.
Bidders must complete and sign Form A (240-68099512) acknowledging acceptance of Eskom's Supplier Quality Management Specification (240-105658000/QM 58) and ISO 9001 requirements.
Bidders must submit the List of Tender Returnables (240-12248652) and all quality documentation required for the applicable category (1, 2, 3, or 4) as indicated in Form A.
Category 1 requires a valid ISO 9001 certificate, internal and external audit reports, a draft contract quality plan per ISO 10005, an example ITP/QCP, and documented information for control of externally provided processes, roles, and management reviews.
Category 2 requires objective evidence of a developed, implemented, and maintained ISO 9001-compliant QMS, including manual, quality policy, objectives, procedures, and audit reports.
Category 3 requires objective evidence of a developed ISO 9001-compliant QMS with core documented information, plus a draft contract quality plan and example ITP/QCP.
Category 4 requires a quality method statement based on ISO 9001, a signed quality policy, quality objectives, and documentation for control of externally provided processes and roles.
A Contract Quality Plan (CQP) must be submitted before the initial scope of work kick-off or pre-fabrication meeting, whichever is earlier.
Quality Control Plans (QCP/ITP) must be reviewed and accepted by Eskom before work commences; once signed, they become addendums to the main contract.
A quality kick-off meeting is held at contract start; coordination meetings with Eskom require 14 days' advance notice.
Mandatory pre-inspection meetings are convened by Eskom or its inspection agency; attendance by supplier and sub-supplier representatives is required.
Bidders must implement a documented preservation management programme for physical assets, with special precautions for valves, motors, piping, instrumentation, and other items.
Eskom reserves the right to assess sub-supplier facilities and to appoint resident quality inspectors at the supplier's premises at no cost to Eskom.
B-BBEE minimum level 1 is indicated, but no supporting detail is present in the document.
Continue with tenders sharing this issuer, category, or province.
Browse categories with current opportunities in this area.
Compare tender activity across provinces.
Explore organisations currently publishing tenders.
Tools and research to help you assess opportunities.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Browse categories with current opportunities in this area.
Compare tender activity across provinces.
Explore organisations currently publishing tenders.
Tools and research to help you assess opportunities.
Date & Time
Monday, 07 December 2026 - 10:00
Venue
MS TEAMS refer to tender document for the link
Categories
Request for Bid(Open-Tender)
tender Office - tender Office - tender Office - 0000
Tenders in this industry often require registration with these bodies.
Recommended Certifications
Having these can improve your winning chances: Good Manufacturing Practice (GMP), SABS Product Certification, NRCS Certification
AI Document Analysis Stages
Contact Information
Source: Replicas KUS-20250797 Kusile Power Station Environmental Specification Rev 1_.pdf (unknown)19 Nov
2026
Tender Published
Tender was published
07 Dec
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
240-68099512 Form A_Cat 2_ Rev 9.docx
Eskom requires metallurgical replicas for outages on an as-and-when-required basis for five years at Kusile Power Station in Mpumalanga. The contract covers the supply of metallurgical replica services during planned and unplanned outages, with the successful bidder required to comply with Eskom's Supplier Quality Requirements (specification 240-105658000) and ISO 9001.
Supplier risk category.docx
Metallurgical replicas for outages on an as-and-when-required basis over five years at Kusile Power Station. The scope covers outage and plant maintenance work, which Eskom categorises as high occupational health and safety risk. Bidders must meet Eskom's OHS returnable requirements before work can be undertaken.
KUS-20260765 Kusile Power Station TES Metallurgical Replicas for Outages as and when required for a 5 year period Rev 2 (002).pdf
Eskom requires metallurgical replication services at Kusile Power Station on an "as and when required" basis during outages, for a period of five years. The work covers replication on HP pipework and boiler components, and on turbine and generator components. Bidders are screened against mandatory criteria and then scored on a weighted technical evaluation with a 70% minimum qualifying threshold.
240-88542869 Replica Lifting Service Provider Management Standard (Rev 3).pdf
Eskom Generation requires metallurgical replica lifting services on an as-and-when-required basis for a five-year period at Kusile Power Station. The service involves taking metallographic replicas of high-temperature high-pressure components, and bidders must be approved under Eskom's Replica Lifting Supplier Management Standard.
Unpriced Cost Estimate Report For Metallurgical Replicas for Outages as and when required at Kusile Power Station.xlsx
Provision of metallurgical replica services, including personnel, consumables, tools, and reporting, on an as-and-when-required basis during outages at Kusile Power Station over a five-year period.
559-667439824 Generation Quality Control Plan Template 18Nov.docx
Provision of metallurgical replicas on an as-and-when-required basis for outages over a five-year period at Kusile Power Station, Mpumalanga.
240-161639691 Kusile Power Station Metallurgical Replicas for Outages as and when required Rev 2 (003) (003).pdf
Eskom requires a suitably qualified and well-established service provider to perform metallurgical replication at Kusile Power Station on an as-and-when-required basis over a five-year period. The work covers main steam, hot reheat and cold reheat pipework, plus any other plant area nominated by the employer, and must align with the station's outage programme.
Replicas KUS-20250797 Kusile Power Station Environmental Specification Rev 1_.pdf
Eskom requires metallurgical replicas for outages on an "as and when required" basis at Kusile Power Station over a five-year period. The work is governed by the station's environmental specification, which sets the minimum environmental management, reporting and record-keeping obligations the contractor must meet throughout the contract.
Invitation to Tender.pdf
Eskom requires metallurgical replica services for outages on an as-and-when-required basis for five years at Kusile Power Station. The contract will be an NEC3 Term Service Contract (TSC3).
20210603_communication_Labour Taxation Questionnaire.pdf
Provision of metallurgical replicas on an as-and-when-required basis for outages over a five-year period at Kusile Power Station, Mpumalanga.
E-Tenderers E-Tendering Training Acknowledgement Form.pdf
Eskom requires metallurgical replicas for outages on an as-and-when-required basis for a five-year period at Kusile Power Station in Mpumalanga. Bidders must acknowledge e-tendering training via a mandatory form to be considered responsive.
240-12248652_List of Tender Returnables_Cat 2_ Rev 7.pdf
ESKOM requires the provision of metallurgical replicas for outages on an "as and when required" basis at Kusile Power Station over a five-year period. Bidders must submit a set of quality management returnables, which are scored against a defined schedule covering ISO 9001 compliance, evidence of QMS in operation, a draft Contract Quality Plan, a Quality Control Plan or ITP, and user-defined requirements.
240-77471499 Annexure B (002).docx
Eskom requires metallurgical replicas for outages on an as-and-when-required basis over five years at Kusile Power Station. Bidders must acknowledge and comply with Eskom's occupational health and safety legal and other requirements, and carry accountability for the OHS conduct of their own contractors and suppliers.
Non-Disclosure Agreement (NDA) Vendors.pdf
Provision of metallurgical replicas for outages on an 'as and when required' basis for a period of five years at Kusile Power Station, under a Non-Disclosure Agreement with Eskom.
KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdf
Metallurgical replicas for outages at Kusile Power Station, provided on an as-and-when-required basis over a five-year contract period. The work is classified as high risk and is governed by Kusile Power Station's OHS specification, which sets the safety file, appointment, training, supervision and compliance obligations the successful contractor must meet.
E-tendering Help Manual for supplier - 27 January 2025.pdf
Provision of metallurgical replicas on an as-and-when-required basis for outages over a five-year period at Kusile Power Station, Mpumalanga.
Eskom Standard Conditions of Tender - January 2023.pdf
Eskom requires metallurgical replicas to be supplied for outages at Kusile Power Station on an "as and when required" basis over a five-year period. The work is contracted on demand rather than as a single defined scope, with prices fixed for the duration of the contract.
Labour Taxation Questionnaire.pdf
Eskom requires metallurgical replicas for outages on an 'as and when required' basis for a period of five years at Kusile Power Station in Mpumalanga. The tender includes a PAYE evaluation questionnaire (Appendix H) that bidders must complete.
240-75114345 Standard for Metallographic Replication Applicable to Turbine and Generator Components (Rev 3).pdf
Eskom requires a service provider to perform metallographic replication on turbine and generator components at Kusile Power Station on an as-and-when-required basis for a five-year period. The work must comply with Eskom's Standard for Metallographic Replication (240-75114345), which specifies personnel approvals, surface preparation, etching, replica handling, and quality control procedures.
Supplier Development Localisation Market.pdf
Eskom requires metallurgical replica services on an as-and-when-required basis for outages at Kusile Power Station over a five-year period. The contract will be awarded under the 90/10 preferential procurement system, with specific goals contributing up to 10 points.
Contractor basline risk assessment.pdf
Eskom requires metallurgical replicas for outages on an as-and-when-required basis for five years at Kusile Power Station in Mpumalanga. The tender includes a comprehensive occupational health and safety baseline risk assessment covering activities such as cleaning conveyors, conditioner unblocking, ash and gypsum conveying, coal handling, and general administrative work.
240-109253698 CQP Template 2021.docx
Metallurgical replicas are required for outages on an as-and-when-required basis at Kusile Power Station for five years. Bidders must prepare a Contract Quality Plan addressing quality management, inspection and test planning, supplier control, records, non-conformance and post-delivery activities.
NEC3.pdf
Eskom Holdings SOC Ltd requires the provision of metallurgical replicas on an “as and when” required basis at Kusile Power Station, under a five-year (60-month) NEC3 Term Service Contract (TSC3). Work is released through Task Orders against a priced price list, with prices fixed for the first 12 months and CPI-based adjustment from the second year.
240-105658000 Supplier QM Spec Rev 3-QM 58.pdf
Metallurgical replicas for outages at Kusile Power Station are required on an "as and when required" basis over a five-year period. Eskom applies its Supplier Quality Management Specification (240-105658000 / QM 58), which requires bidders to demonstrate an ISO 9001-aligned quality management system and to submit the quality documentation applicable to the category Eskom selects for this procurement.
To download these documents and access AI-powered analysis, visit the main tender page.
Organization
EskomWin Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
R 806 400
Range
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Environmental contacts:
No email or telephone numbers are provided in this document.
Submission Guidelines
Source: Replicas KUS-20250797 Kusile Power Station Environmental Specification Rev 1_.pdf (unknown)Returnable documents:
Submission method and closing time are not stated in this document.
Evaluation Criteria
Source: Replicas KUS-20250797 Kusile Power Station Environmental Specification Rev 1_.pdf (unknown)Compliance with the environmental specification is assessed during tender evaluation, ad-hoc inspections, and internal audits.
Technical Specifications
Source: Replicas KUS-20250797 Kusile Power Station Environmental Specification Rev 1_.pdf (unknown)The contract is for metallurgical replicas for outages at Kusile Power Station, on an as-and-when-required basis for five years.
The scope of work is detailed in document 240-161639691; the contractor must retain a copy.
Environmental protection covers noise pollution, gaseous emissions, odours, liquid and solid waste separation and collection, spillage clean-up, and rehabilitation of contaminated areas.
Quality Management
Source: Replicas KUS-20250797 Kusile Power Station Environmental Specification Rev 1_.pdfNon-conformance and incident reports must include the cause and proposed corrective/preventive actions.
Eskom Kusile will issue non-conformances for deviations from its procedures or environmental requirements.
The Environmental Department conducts regular audits; where non-conformances are recorded, the contractor must submit an action plan for correction or prevention.
Good housekeeping must be maintained at laydown and working areas.
Compliance Requirements
Source: Replicas KUS-20250797 Kusile Power Station Environmental Specification Rev 1_.pdf (unknown)The contractor must have a documented and implemented environmental management system, including an environmental policy, operational procedures, and an aspects/impacts register.
Employees must be inducted on environmental requirements before work commences, with proof retained.
Trained and competent personnel must be appointed in writing to implement environmental requirements.
Hazardous substances must be stored in bunded areas with 110% capacity; SDS must be kept onsite.
All waste must be stored in marked containers, disposed of at permitted sites, and records including safe disposal certificates maintained.
Spills and incidents must be reported immediately to the Supervisor and Environmental Officer(s).
Environmental incidents must be reported within 24 hours and investigated within 24 hours with Kusile Environmental representation.
A SHE policy signed by the CEO or top management must be displayed and communicated to all employees.
Environmental objectives must be developed for each financial year and communicated to employees.
Emergency response plans must be developed and periodic emergency drills undertaken.
Health & Safety
Source: Replicas KUS-20250797 Kusile Power Station Environmental Specification Rev 1_.pdfA SHE policy signed by the CEO or top management must be displayed and communicated to all employees, with proof of communication retained.
Hazardous substances must be stored in bunded areas with 110% capacity; SDS must be kept onsite; oil spill kits must be kept near storage areas.
Emergency response plans must be developed, and periodic emergency drills must be undertaken and recorded.
Employees must be inducted on environmental requirements before work commences.
Environmental
Source: Replicas KUS-20250797 Kusile Power Station Environmental Specification Rev 1_.pdfThe contractor must comply with Eskom's Zero Liquid Effluent Discharge policy through reuse and recycling.
All waste must be stored in marked containers, disposed of at permitted sites, and records including safe disposal certificates maintained.
Spills and incidents must be reported immediately; clean-up and rehabilitation must follow Kusile's Oil/Chemical spillage process (240-110383662).
Oils must be stored in bunded areas or impermeable tanks; disposal certificates must be submitted to the Environmental Department.
An environmental aspect and impact register must be prepared, including mitigations, an aspect rating matrix, and communication to employees.
Environmental incidents must be reported within 24 hours and investigated within 24 hours with Kusile Environmental representation.
Hazardous substances must be stored in bunded areas (110% capacity), with SDS kept onsite and registers maintained.
Waste must not be mixed or burned; no waste stored on the ground; recycling initiatives must be implemented; waste removal requires Environmental Department authorisation.
The contractor must develop environmental objectives for each financial year, including significant aspects, and communicate them to employees.
Environmental improvement opportunities must be identified, considering significant aspects.
Emergency response plans must be developed, and periodic emergency drills undertaken.
A SHE policy must be displayed and communicated to all employees.
Records to be kept onsite include: site-specific Environmental Management Plan, aspects/impacts register, incident registers and investigation reports, non-conformance register, public complaints register, waste disposal register, hazardous substances registers and SDS, audit reports, inspection records, environmental training matrix, proof of environmental awareness, proof of SHEQ policy communication, and emergency drill reports.
Description
Source: NEC3.pdfProvision of metallurgical replicas on an 'as and when' required basis for a 5-year period at Kusile Power Station. The contract is a term service contract for outages, covering site establishment, resources, consumables, equipment, and occupational hygiene surveys.
Contact Information
Source: NEC3.pdf (unknown)Service Manager (not named in the document):
Employer's registered office:
General Manager (for Employer): Christopher Nani
Submission Guidelines
Source: NEC3.pdf (unknown)Returnable documents:
Submission method: not stated in the document.
Closing time: not stated in the document.
Evaluation Criteria
Source: NEC3.pdf (unknown)Evaluation is based on the NEC3 Term Service Contract (TSC3) Option A (priced contract with price list).
The tenderer must complete the Form of Offer and Acceptance and Contract Data Part 2.
A decrease in the Contractor's B-BBEE status after the Contract Date may lead to re-negotiation or termination.
The Contractor must be able to comply with the Construction Regulations 2014 where appointed as Principal Contractor, and with the Employer's Asbestos Standard 32-303.
No specific scoring split or minimum qualifying score is stated in the document.
Technical Specifications
Source: NEC3.pdf (unknown)Provision of metallurgical replicas on an 'as and when' required basis for a 5-year period at Kusile Power Station.
The service includes:
Experience & Qualifications
Source: NEC3.pdfKey personnel requirements (from price list):
Quality Management
Source: NEC3.pdfQuality requirements are implied through the need for qualified personnel (e.g., NDT Level 1 training, metallurgical engineering qualifications) and adherence to the Employer's standards. No explicit quality management system or certification is stated in the document.
Pricing Schedule
Source: NEC3.pdfPricing is per TSC3 Option A (priced contract with price list). The price list includes items for preliminaries (site establishment, PPE, safety file, medicals, training), resources (labour hours for various roles), consumables (grinding papers, replica film, glass slides, chemicals, etc.), equipment (grinders, microscopes, cameras), and occupational hygiene surveys. Prices are in Rands. Lump sum items are not adjusted if quantities change; only compensation events can change lump sum prices. Rates multiplied by expected quantities determine the Price for items with quantities.
Financial Requirements
Source: NEC3.pdf (unknown)Pricing: Option A (priced contract with price list). Prices are derived from a list of items, each priced as a lump sum or as expected quantity multiplied by a rate.
Payment terms:
Insurance:
Liability:
Low service damages (X17): limited to 10% of Task Order value; daily percentages apply for various failures (e.g., 5% per day for delaying other contractors, 2% per day for other delays).
Compliance Requirements
Source: NEC3.pdf (unknown)B-BBEE: Minimum Level 2 (stated in currentAnalysis).
CIDB: Tenderer's CIDB registration number must be stated in the Form of Offer and Acceptance.
Health and safety:
Ethics: No coercive, collusive, corrupt, fraudulent, or obstructive actions.
Confidentiality: No disclosure of contract information without consent; images of the Affected Property require prior written consent.
Joint ventures: If a JV, parties are jointly and severally liable; notify Service Manager of key person within two weeks of Contract Date.
Health & Safety
Source: NEC3.pdfHealth and safety obligations:
Environmental
Source: NEC3.pdfEnvironmental obligations:
Section
Source: NEC3.pdfNo additional evaluation criteria beyond those in the standard evaluationCriteria section. The document does not specify a scoring split or minimum qualifying score.
Evaluation Criteria
Source: Non-Disclosure Agreement (NDA) Vendors.pdf (unknown)Bidders must be able to enter into a binding Non-Disclosure Agreement (NDA) with Eskom. The NDA requires the receiving party to be a legal entity with capacity to contract. No other eligibility criteria are stated in the provided document.
Technical Specifications
Source: Non-Disclosure Agreement (NDA) Vendors.pdf (unknown)Provision for Pulse Jet Fabric Filter (PJFF) and smokestack maintenance scope of work on a fulltime basis for a period of five (5) years.
Contractual Terms
Source: Non-Disclosure Agreement (NDA) Vendors.pdfThe NDA governs the disclosure of confidential information between Eskom and the receiving party. Key obligations include: the receiving party must keep all disclosed information confidential and use it only for the project; may share it only with its representatives on a need-to-know basis; must protect it with at least a reasonable standard of care; must return or destroy all confidential material upon request within 7 business days; and must indemnify Eskom against losses from unauthorised use or disclosure. The NDA does not create any obligation to enter into a business relationship. It remains in force for 3 years after termination of the relationship. Breach must be remedied within 7 business days of written notice, failing which Eskom may seek legal remedies. The agreement is governed by South African law.
Evaluation Criteria
Source: Labour Taxation Questionnaire.pdf (unknown)Bidders must complete and submit the Contractors' PAYE Evaluation Questionnaire (Appendix H). The questionnaire determines whether the bidder is a labour broker or personal services company, which affects tax treatment. Bidders must answer all questions relevant to their circumstances. If classified as a labour broker, a valid, original or certified copy of an IRP30 for the current tax year must be supplied within 30 days.
Compliance Requirements
Source: Labour Taxation Questionnaire.pdf (unknown)Bidders must complete the Contractors' PAYE Evaluation Questionnaire (Appendix H) as part of the bid. The questionnaire asks about the entity's structure, income sources, and relationship with Eskom, including whether the entity is a labour broker or personal services company, and whether it has been classified as such by SARS or any other client.
Section
Source: Labour Taxation Questionnaire.pdfBidders must complete and submit the Contractors' PAYE Evaluation Questionnaire (Appendix H). The questionnaire is used to assess whether the bidder is a labour broker or personal services company, which affects tax treatment.
Description
Source: Contractor basline risk assessment.pdfThe document is a baseline risk assessment template for Kusile Power Station, covering activities such as cleaning conveyors and chutes, conditioner unblocking, ash handling, coal stockpile construction, and administrative work. It lists hazards, risks, controls, and responsible managers.
Evaluation Criteria
Source: Contractor basline risk assessment.pdf (unknown)Bidders must comply with the Occupational Health and Safety Baseline Risk Assessment template and relevant legal requirements (OHS Act, GSR, ERW). No specific pre-qualification criteria such as CSD registration, B-BBEE level, or CIDB grading are stated in the provided document.
Technical Specifications
Source: Contractor basline risk assessment.pdf (unknown)The document is a baseline risk assessment template for Kusile Power Station. It lists activities, hazards, associated risks, consequences, existing controls, control owners, and legal requirements. Key activities include:
Quality Management
Source: Contractor basline risk assessment.pdfThe document references Eskom procedures (e.g., Procedure 32-285, Procedure 32-520) and management instructions (e.g., 240-85246142, 240-85428463) as controls. It includes requirements for medical surveillance, ergonomic surveys, equipment inspections, and toolbox talks. No specific quality management standards beyond these are stated.
Compliance Requirements
Source: Contractor basline risk assessment.pdf (unknown)No specific compliance requirements found in the provided document.
Health & Safety
Source: Contractor basline risk assessment.pdfThe document is an Occupational Health and Safety Baseline Risk Assessment template for Kusile Power Station. It requires identification of hazards, associated risks, consequences, existing controls (preventative and reactive), control owners, and legal requirements. Key hazards include fly ash exposure, defective hand tools, slippery surfaces, elevated positions, rotating equipment, vibrations, extreme weather, noise, sharp rotating equipment, suspended materials, tight locking pins, moving conveyor belts, dust, faulty machinery, wet material, poor visibility, moving machinery, congestion, over suppression, excessive coal dust, water seepage, poor visibility, diesel fumes, burns from hot components, machine rollover, and ergonomic issues. Controls include PPE (dust masks, hearing protection, safety boots, gloves, full body harness, safety goggles, reflector jackets), safety signs, pre-job briefs, pre-job inspections, toolbox talks, job observations, incident reporting, medical surveillance, plant inspections, SMAT, planned task observations, barricading, warning signs, 5m following distance, 2m clearance from machines, speed limits, dust suppression, and continuous assessment of traffic routing. Legal requirements include OHS Act s8(2)(c), OHS Act s8(2)e, GSR 2, ERW 3 & 4, and various Eskom procedures. The template is to be reviewed every 2 years, with revision date 30-Apr-25.
Submission Guidelines
Source: E-Tenderers E-Tendering Training Acknowledgement Form.pdf (unknown)Returnable documents:
Evaluation Criteria
Source: E-Tenderers E-Tendering Training Acknowledgement Form.pdf (unknown)Submission of the fully completed E-Tenderers' E-Tendering Training Acknowledgement Form is mandatory. Failure to submit it within the prescribed period will result in disqualification.
Description
Source: 240-161639691 Kusile Power Station Metallurgical Replicas for Outages as and when required Rev 2 (003) (003).pdfKusile Power Station is outsourcing metallurgical replica services on an as-and-when-required basis to a suitably qualified and well-established contractor. The service covers metallurgical replication for outages, supporting the station's performance targets of 85% EAF, 10% PCLF and 5% UCLF. The scope applies throughout Kusile Power Station and is effective upon authorization.
Evaluation Criteria
Source: 240-161639691 Kusile Power Station Metallurgical Replicas for Outages as and when required Rev 2 (003) (003).pdf (unknown)Technical Specifications
Source: 240-161639691 Kusile Power Station Metallurgical Replicas for Outages as and when required Rev 2 (003) (003).pdf (unknown)Quality Management
Source: 240-161639691 Kusile Power Station Metallurgical Replicas for Outages as and when required Rev 2 (003) (003).pdfQuality requirements are governed by the following normative references:
The service provider must comply with the Standard for Non-Destructive Testing (240-83539994); deviations will lead to withdrawal of Eskom approval. The metallurgist must conduct pre-analysis of replicas and ensure good quality. The service provider must produce a final report within 30 working days after completion of the works.
Compliance Requirements
Source: 240-161639691 Kusile Power Station Metallurgical Replicas for Outages as and when required Rev 2 (003) (003).pdf (unknown)Health & Safety
Source: 240-161639691 Kusile Power Station Metallurgical Replicas for Outages as and when required Rev 2 (003) (003).pdfThe service provider must comply with the employer's Environmental, Health and Safety standards, policies and procedures. The Occupational Health and Safety Act (OHS Act) applies. The service provider must also comply with the Kusile Power Station Integrated Risk Management Work Instruction (240-134567773).
Section
Source: 240-161639691 Kusile Power Station Metallurgical Replicas for Outages as and when required Rev 2 (003) (003).pdfThe document describes the applicable plant areas, scope of work, standards, quality, requirements, specifications, terms and conditions, and the criteria to qualify for the tender. Bidders must be suitably qualified and well-established contractors. The employer will assess intended service providers for compliance against standard 240-83539994 and relevant minimum EN ISO code requirements for each method intended for use on site.
Important Dates
Source: Eskom Standard Conditions of Tender - January 2023.pdf (TENDER)Closing date: 7 December 2026 at 08:00 (SAST).
Compulsory site visit / clarification meeting: details (date, time, venue) are stated in the Tender Data. Attendance is mandatory; failure to attend disqualifies the tender.
Clarification queries: must be submitted to the Eskom Representative before the closing time for clarification of queries (date/time not stated in this document).
Contact Information
Source: Eskom Standard Conditions of Tender - January 2023.pdf (TENDER)All communication must be directed to the Eskom Representative in writing (English), in a format that can be read, copied and recorded.
Contact details (name, email, telephone) are not stated in this document.
Submission address: as stated in the Tender Data (not provided in this document).
Submission Guidelines
Source: Eskom Standard Conditions of Tender - January 2023.pdf (TENDER)Submission method: sealed hard copy only — original plus one complete hard copy of the original, each in its own package marked "ORIGINAL" and "COPY". An additional soft copy may be required. Tenders must be in English, completed in ink, and signed. The outer package must be sealed, marked "CONFIDENTIAL", and show only the Eskom address and the Invitation to Tender number. Late tenders are returned unopened; proof of posting or courier delivery is not accepted. Tenders submitted telephonically or by email are not accepted unless stated in the Tender Data.
Returnable documents — all must be completed, signed and submitted by the closing deadline:
Disqualification risks:
Evaluation Criteria
Source: Eskom Standard Conditions of Tender - January 2023.pdf (TENDER)Evaluation stages:
Arithmetical errors: amounts in words govern over figures. Eskom corrects errors in line item totals, unit rates and totals; the tenderer must accept corrections or the tender may be rejected.
Objective criteria: a contract may be awarded to a non-highest scorer only under Section 2(1)(f) of the PPPFA, with objective criteria stipulated in the tender documents. Functionality and contractual requirements cannot be used as objective criteria.
Reverse e-auction: Eskom reserves the right to use reverse e-auction where indicated; in such cases tenders are submitted without prices and any included prices are disregarded.
Technical Specifications
Source: Eskom Standard Conditions of Tender - January 2023.pdf (TENDER)Scope: supply of metallurgical replicas for outages on an "as and when required" basis for a period of five (5) years at Kusile Power Station.
Specific quantities, technical standards, service levels and delivery locations are not stated in this document — refer to the Tender Data and specification.
Quality Management
Source: Eskom Standard Conditions of Tender - January 2023.pdfSHEQ systems: bidders must provide reasonable proof that safety, health, environmental and quality systems, policies and capabilities are in place at contract award. All costs and personnel associated with SHEQ must be reflected in the tender.
Quality of tender: tenders must be complete, in English, and signed. Corrections must be initialled by all signatories; correction fluid or tape is not permitted.
Pricing Schedule
Source: Eskom Standard Conditions of Tender - January 2023.pdfPricing format: rates and prices in South African Rand, fixed for the contract duration, including all duties, taxes (including VAT) and levies applicable 14 days before the tender submission deadline.
Arithmetical errors: amounts in words govern; Eskom corrects errors in line item totals, unit rates and totals; the tenderer must accept corrections or the tender may be rejected.
Specific Goals: if a bidder fails to meet Specific Goals or submit proof by closing, it is not disqualified but receives 80/90 points for Price and zero for Specific Goals.
Financial Requirements
Source: Eskom Standard Conditions of Tender - January 2023.pdf (TENDER)Pricing:
Insurance: Eskom's insurance (if any) may not cover the full risk; bidders should obtain qualified advice.
Security for performance: where required, bidders must name at least two financial institutions they would approach for the security; Eskom may reject unsuitable institutions.
Arithmetical corrections: Eskom may correct errors; the corrected total becomes binding if the tenderer accepts it.
Compliance Requirements
Source: Eskom Standard Conditions of Tender - January 2023.pdf (TENDER)Eligibility:
Statutory compliance:
SHEQ: bidders must provide reasonable proof that safety, health, environmental and quality systems, policies and capabilities are in place at contract award; associated costs and personnel must be reflected in the tender.
CIDB (if applicable): proof of registration is mandatory at the closing deadline. If only proof of application is available at closing, it must be submitted by closing, with the actual CIDB registration printout submitted by contract award.
B-BBEE: a fraudulent certificate/affidavit or fronting will be reported to the B-BBEE Commissioner.
Contract Skills Development Goal (CSDG): applicable to works exceeding R60 million with contract duration 12 months or more, or professional services exceeding R5 million with duration 12 months or more.
Contract Participation Goals (CPG): applicable to Grade 7-9 General Building and Civil Engineering contracts of 6 months or more, where at least 25% of the main contract is expected to be sub-contracted; at least 5% contract participation goal must be achieved.
Health & Safety
Source: Eskom Standard Conditions of Tender - January 2023.pdfCompliance: bidders must comply with COIDA, the OHS Act, and Eskom's SHEQ requirements.
SHEQ proof: reasonable proof of SHEQ systems, policies and capabilities must be provided at contract award; costs and personnel must be included in the tender.
CSDG: Contract Skills Development Goal applies to works exceeding R60 million with duration 12 months or more, or professional services exceeding R5 million with duration 12 months or more.
CPG: Contract Participation Goals apply to Grade 7-9 GB and CE contracts of 6 months or more where at least 25% of the main contract is sub-contracted; at least 5% contract participation goal must be achieved.
Contractual Terms
Source: Eskom Standard Conditions of Tender - January 2023.pdfCommunication: all communication between Eskom and tenderers must be in writing, in English, and directed to the Eskom Representative. Eskom is not responsible for non-receipt of communications.
Eskom's rights: Eskom may accept or reject any variation, deviation or alternative tender, accept the whole or part of a tender, and cancel the tender process at any time before contract formation. Eskom is not liable for any losses or damages arising from participation, amendment, termination or suspension of the process.
Negotiation: Eskom reserves the right to enter into mandated negotiations with selected tenderers.
Tender validity: tenders must remain valid for acceptance within the validity period stated in the Tender Data; Eskom may request an extension, and a tenderer agreeing to the extension may not modify its tender. If validity lapses without extension, the procurement process cannot continue.
Confidentiality: all matters arising in connection with the tender are confidential; Eskom documents may be used only for preparing and submitting the tender.
Standardised specifications: bidders must obtain the latest revisions of standardised specifications referenced in the enquiry.
Contract formation: the successful tenderer must check the final draft contract and sign the Form of Agreement.
Section
Source: Eskom Standard Conditions of Tender - January 2023.pdfFunctionality: if applicable, bidders must meet the minimum threshold stated in the Tender Data; only those meeting it proceed.
Financial risk: Eskom assesses financial risk and may disqualify if risk is too high and no sufficient mitigating factors exist.
Price evaluation: according to criteria in the Tender Data, considering CPA, FOREX, commodity increases, discounts, NPV and forecasted invoicing rates.
Specific Goals: scored on evidence; failure results in 80/90 points for Price and zero for Specific Goals.
Ranking: price and Specific Goals scores added, ranked highest to lowest.
Objective criteria: may be used only under Section 2(1)(f) of PPPFA, with criteria stipulated in the tender documents; functionality and contractual requirements cannot be used.
Reverse e-auction: Eskom may use reverse e-auction where indicated; tenders submitted without prices, any included prices disregarded.
Description
Source: 240-77471499 Annexure B (002).docxThis is an Eskom OHS acknowledgement form (Annexure B) for coal and limestone sampling at Kusile Power Station on an as-and-when-required basis for five years. The supplier must acknowledge and comply with Eskom OHS legal and other requirements, including the listed standards and acts.
Submission Guidelines
Source: 240-77471499 Annexure B (002).docx (unknown)Returnable documents:
Evaluation Criteria
Source: 240-77471499 Annexure B (002).docx (unknown)Signing of the OHS acknowledgement form by the CEO, director or managing director is a precondition of contracting, with acceptance that the supplier is accountable for OHS compliance across its contractors and suppliers at all tiers.
Technical Specifications
Source: 240-77471499 Annexure B (002).docx (unknown)Scope: Coal and limestone sampling at Kusile Power Station on an as-and-when-required basis for a period of five (5) years.
The supplier must comply with, but is not limited to:
After contract award, the supplier is responsible for fully aligning its processes to Eskom's OHS requirements (policies, procedures, standards).
Penalties will be enforced on the main supplier for non-conformances relating to Eskom or statutory OHS requirements, including those of its contractors or suppliers.
All employees (contractors/suppliers) must undergo the relevant Eskom induction and the company's induction.
The main supplier must:
Eskom reserves the right to verify compliance and may instruct the contractor to provide copies of testimonials/references and contact details of clients (including Eskom) for whom similar work was previously done.
Compliance Requirements
Source: 240-77471499 Annexure B (002).docx (unknown)OHS compliance as detailed in the technical specifications is mandatory. The supplier must acknowledge and commit to these requirements by signing Annexure B.
Description
Source: 559-667439824 Generation Quality Control Plan Template 18Nov.docxThe document is a Quality Control Plan (QCP) template for metallurgical replica work during outages at Kusile Power Station. After completing the Databook, an authorised copy must be sent to the site Documentation Control Centre for archiving and uploading to OpenText (Records Management).
Technical Specifications
Source: 559-667439824 Generation Quality Control Plan Template 18Nov.docx (unknown)The tender covers metallurgical replicas for outages on an "as and when required" basis for five years at Kusile Power Station. The document provided is a Quality Control Plan (QCP) template. After completing the Databook, an authorised copy must be sent to the site Documentation Control Centre for archiving and uploading to OpenText (Records Management).
Description
Source: Supplier risk category.docxThe document is a guideline for categorising services by risk level (high, medium, low) for occupational health and safety purposes. It lists examples of works and services in each category, such as installation of equipment, outage work, line construction, maintenance, transportation, manufacturing and supply, and various services. The list is not exhaustive; a risk assessment must be conducted for services not listed.
Evaluation Criteria
Source: Supplier risk category.docx (unknown)COID registration is mandatory for all contractors and suppliers.
If a letter of good standing is not submitted, the following alternatives are accepted for tender purposes:
International suppliers:
Joint ventures:
Supplier registration:
Technical Specifications
Source: Supplier risk category.docx (unknown)The document provides a guideline for categorising services by risk level (high, medium, low) for OHS purposes. It lists examples of works and services in each category, such as installation of equipment, outage work, line construction, maintenance, transportation, manufacturing and supply, and various services. The list is not exhaustive; a risk assessment must be conducted for services not listed.
Compliance Requirements
Source: Supplier risk category.docx (unknown)OHS requirements are applicable to both local and international companies.
Description
Source: 240-109253698 CQP Template 2021.docxThe tender is for the supply of metallurgical replicas for outages on an as-and-when-required basis for a period of five years at Kusile Power Station. The document provided is a Contract Quality Plan (CQP) template that the successful supplier must complete and maintain.
Technical Specifications
Source: 240-109253698 CQP Template 2021.docx (unknown)The tender is for the supply of metallurgical replicas for outages on an as-and-when-required basis for a period of five years at Kusile Power Station. The document provided is a Contract Quality Plan (CQP) template that the successful supplier must complete and maintain. The CQP must address:
Compliance Requirements
Source: 240-109253698 CQP Template 2021.docx (unknown)The CQP template references SANS 466:2005 / ISO 10005:2005 for quality plans. The supplier must comply with the quality management requirements of the contract, including maintaining a Quality Management System (QMS) and submitting the CQP for Eskom approval. No specific B-BBEE, CIDB, or other compliance thresholds are stated in the provided document.
Important Dates
Source: KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdf (unknown)No briefing session or site visit dates are stated in the document.
Contact Information
Source: KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdf (unknown)No contact details are stated in the document.
Submission Guidelines
Source: KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdf (unknown)Returnable documents: The OHS specification requires the following to be submitted with the bid:
Disqualification risks:
Evaluation Criteria
Source: KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdf (unknown)Preconditions to bid and to start work:
Required competencies:
Technical Specifications
Source: KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdf (unknown)Scope of work:
Key requirements:
Methodology
Source: KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdfA written method statement signed by the Kusile Contract Manager and the appointed contractor is required, detailing how the activity will be carried out. Safe work procedures and method statements must be developed and followed.
Experience & Qualifications
Source: KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdfThe main contractor and appointed contractors must have appropriate qualifications and certificates. Employees must always be under competent supervision. Specific competency requirements are detailed for health and safety representatives, supervisors, and safety officers.
Quality Management
Source: KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdfQuality management includes adherence to the SHEQ Policy and applicable legislative obligations. The contractor must maintain an OHS file containing incident investigation reports, non-conformances, announcements (near miss/injury/damage), and follow-up on recommendations. Accident prevention measures include planned job observations, OHS training, protective clothing and equipment, and incident announcements/recall.
Pricing Schedule
Source: KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdfOHS costs must be itemised in the bill of quantities as per the OHS Act and its regulations, in line with the scope of work. This includes training, PPE, and safety equipment purchases.
Financial Requirements
Source: KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdf (unknown)OHS costs must be itemised in the bill of quantities as per the OHS Act and its regulations, in line with the scope of work. This includes training, provision of PPE, and safety equipment purchases.
Compliance Requirements
Source: KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdf (unknown)B-BBEE Minimum Level: 6
Statutory appointments required:
Non-statutory appointments required:
Other compliance requirements:
Health & Safety
Source: KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdfThe OHS specification covers extensive requirements including: legal compliance, Kusile Power Station requirements, OHS policy, Covid-19 policy, COID registration, costing for OHS, statutory appointments, Eskom Life-Saving Rules, substance abuse, contractor organisational structure, roles and responsibilities, risk assessment, safe work procedures/method statements, fire equipment, hazardous chemical agents management, first aid, OHS communication, toolbox talks, OHS training, general training, site establishment, site roads, vehicle management, housekeeping, stacking and storage, signage, tools and equipment, ladders, scaffolding, auditing, smoking, cellular phones, occupational health and hygiene, working at heights, confined spaces, barricading, PPE, incident investigation, emergency management, non-conformance, OHS files, work stoppage, hours of work, and contractor performance monitoring.
Environmental
Source: KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdfThe contractor must comply with the National Environmental Management Act and the Environment Conservation Act. Duty of care to the environment requires taking reasonable measures to prevent pollution or degradation, and to minimise and rectify any such harm. Site induction must include identification of sensitive features such as wetlands/vlei areas, red data species, and graves.
Contractual Terms
Source: KUS-20260703 Kusile Power Station OHS Specification For Metallurgical Replicas (003).pdfThe contract is for a period of five years. The contractor must comply with all OHS requirements. Kusile Power Station reserves the right to terminate the contract for non-compliance. Contractor performance is monitored against KPIs. The contractor must have appropriate qualifications and certificates, and employees must be under competent supervision.
Contact Information
Source: 240-12248652_List of Tender Returnables_Cat 2_ Rev 7.pdf (TENDER)Eskom representative: Basetsana Pule
Date issued: 04-Jun-26
Submission Guidelines
Source: 240-12248652_List of Tender Returnables_Cat 2_ Rev 7.pdf (TENDER)Returnable documents (Category 2 – Quality Requirements):
Evaluation Criteria
Source: 240-12248652_List of Tender Returnables_Cat 2_ Rev 7.pdf (TENDER)Quality returnables are evaluated against the tender returnables schedule. The bidder must satisfy either Option 1 or Option 2 for Section A, plus Sections B to E. Scores are allocated per item (each item = 1 point).
No minimum qualifying score is stated.
Technical Specifications
Source: 240-12248652_List of Tender Returnables_Cat 2_ Rev 7.pdf (TENDER)Provision of metallurgical replicas for outages at Kusile Power Station.
Contract period: five (5) years, on an as-and-when-required basis.
Scope includes quality management deliverables as per specification 240-105658000.
Compliance Requirements
Source: 240-12248652_List of Tender Returnables_Cat 2_ Rev 7.pdf (TENDER)Quality management system compliance is mandatory:
Section
Source: 240-12248652_List of Tender Returnables_Cat 2_ Rev 7.pdfQuality returnables are scored per the schedule. Section A offers two options: Option 1 (ISO 9001 certificate) scores 4 points; Option 2 (documented QMS) scores 7 points. Section B (evidence of QMS in operation) scores 4 points. Section C (draft Contract Quality Plan) scores 1 point. Section D (draft ITP/QCP) scores 1 point. Section E (Form A completed and signed) scores 2 points. No minimum qualifying score is stated.
Description
Source: 240-88542869 Replica Lifting Service Provider Management Standard (Rev 3).pdfEskom requires metallographic replication services for outages on an 'as and when required' basis for a period of five years at Kusile Power Station. The service involves taking metallographic replicas on HP Pipework and Turbine components. Service providers must be approved by Eskom's Physical Metallurgy and Structural Integrity section. The standard applies throughout Eskom Holdings SOC Limited Generation Power Plants.
Important Dates
Source: 240-88542869 Replica Lifting Service Provider Management Standard (Rev 3).pdf (unknown)Closing date: 7 December 2026 at 08:00 (from tender record).
No briefing or site visit dates are stated in the document.
Contact Information
Source: 240-88542869 Replica Lifting Service Provider Management Standard (Rev 3).pdf (unknown)No specific contact details are provided in the document.
Submission Guidelines
Source: 240-88542869 Replica Lifting Service Provider Management Standard (Rev 3).pdf (unknown)Returnable documents — all must be submitted to the Physical Metallurgy and Structural Integrity section for approval:
Disqualification risks:
Evaluation Criteria
Source: 240-88542869 Replica Lifting Service Provider Management Standard (Rev 3).pdf (unknown)Approval process for new companies:
Existing companies:
Withdrawal of approval:
Technical Specifications
Source: 240-88542869 Replica Lifting Service Provider Management Standard (Rev 3).pdf (unknown)Scope: Metallographic replication services for outages on an 'as and when required' basis for a period of five years at Kusile Power Station.
Experience & Qualifications
Source: 240-88542869 Replica Lifting Service Provider Management Standard (Rev 3).pdfExperience and qualifications:
Quality Management
Source: 240-88542869 Replica Lifting Service Provider Management Standard (Rev 3).pdfQuality management requirements:
Compliance Requirements
Source: 240-88542869 Replica Lifting Service Provider Management Standard (Rev 3).pdf (unknown)ISO 9001 Quality Management Systems compliance is required (normative reference).
No other specific compliance requirements (CSD, tax, B-BBEE, CIDB) are stated in the document.
Health & Safety
Source: 240-88542869 Replica Lifting Service Provider Management Standard (Rev 3).pdfHealth and safety requirements:
Section
Source: 240-88542869 Replica Lifting Service Provider Management Standard (Rev 3).pdfAdditional evaluation criteria:
Description
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdfThis document is Eskom's Supplier Quality Management Specification (240-105658000, QM 58, Revision 3). It sets out the minimum quality requirements for all existing and potential Eskom suppliers, defining criteria for selection, evaluation, vendor registration, management, monitoring, assessment and auditing. The specification applies to all Eskom divisions, subsidiaries, suppliers and sub-suppliers, and forms part of all RFIs, RFQs, RFPs and contracts for products and services. Suppliers must develop, implement, maintain and continually improve a QMS based on ISO 9001.
Important Dates
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdf (unknown)Closing date: 7 December 2026 at 08:00 (from tender record).
No other dates (briefings, site visits, clarification deadlines) are stated in this document.
Contact Information
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdf (unknown)No contact names, emails, telephone numbers, or submission addresses are stated in this document.
Submission Guidelines
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdf (unknown)Returnable documents (all must be completed, signed and submitted):
Submission method and closing time are not stated in this document.
Evaluation Criteria
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdf (unknown)Quality category selection: Eskom's Quality representative selects one of four categories (1, 2, 3 or 4) for this procurement, indicated in Form A. Only one category applies.
Supplier capability and capacity assessment: performed before contract award where the work carries high risk to operational sustainability, involves critical plant and equipment, supplies critical plant items or components, or provides special processes.
Preference point system (80/20 or 90/10) and minimum qualifying scores are not stated in this document.
Technical Specifications
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdf (unknown)Scope: Supply of metallurgical replicas for outages on an 'as and when required' basis for a period of five (5) years at Kusile Power Station.
Quality management system requirements:
Contract Quality Plan (CQP):
Quality Control Plan (QCP)/Inspection and Test Plan (ITP):
Quality kick-off meeting:
Preservation management programme:
Methodology
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdfMethod statements and execution plans:
Experience & Qualifications
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdfQuality audits and related quality performance reviews must be carried out by trained, accredited, and experienced personnel in accordance with documented procedures.
Quality Management
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdfQuality management system requirements:
Quality Control Plan (QCP)/Inspection and Test Plan (ITP):
Quality kick-off and pre-inspection meetings:
Pricing Schedule
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdfNo pricing schedule, rates, bill of quantities, or payment schedules are stated in this document.
Financial Requirements
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdf (unknown)No pricing format, bid security, bonds, guarantees, retention, payment terms, or financial capacity thresholds are stated in this document.
Compliance Requirements
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdf (unknown)ISO 9001 certification: required unless excluded by the applicable quality category (see submission guidelines).
B-BBEE: Minimum level 1 is indicated in the analysis, but no supporting detail is present in the document.
CSD registration, tax clearance, CIDB grading, CIPC registration, and local content requirements are not stated in this document.
Health & Safety
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdfReferences to SHEQ Policy (32-727) and IAEA Safety Standard GS-R-3.1 are listed as informative references. No specific health and safety requirements are stated in this document.
Contractual Terms
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdfPreservation management programme obligations:
Section
Source: 240-105658000 Supplier QM Spec Rev 3-QM 58.pdfQuality categories 1 to 4 determine the minimum returnable quality documentation. Only one category applies per procurement, selected by Eskom's Quality representative and indicated in Form A. Supplier capability and capacity assessments are performed before contract award for high-risk work, critical plant, or special processes.
Description
Source: Supplier Development Localisation Market.pdfThe tender is for the supply of metallurgical replicas for outages at Kusile Power Station on an as-and-when-required basis for a period of five years. The document focuses on Supplier Development, Localisation and Industrialisation (SDL&I) objectives, including transformation, local procurement, black-owned spend, job creation, and skills development.
Contact Information
Source: Supplier Development Localisation Market.pdf (unknown)Buyer: Charmaine Silaule
Business unit: Kusile Power Station
Evaluation Criteria
Source: Supplier Development Localisation Market.pdf (unknown)Preference point system: 90/10 or 80/20, with specific goals (B-BBEE status level) awarded up to 10 points (90/10) or 20 points (80/20). Points for price and specific goals are added and rounded to two decimal places; contract awarded to highest total.
B-BBEE points table (status level -> points for 90/10, 80/20):
Documents required to claim preference points:
If B-BBEE documentation is not provided, the bidder is not disqualified but:
SDL&I objectives (transformation, local procurement, black-owned spend, jobs, skills development) do not form part of scoring but commitments become contractual obligations.
Technical Specifications
Source: Supplier Development Localisation Market.pdf (unknown)Scope: Supply of metallurgical replicas for outages on an as-and-when-required basis.
Location: Kusile Power Station.
Contract duration: 5 years.
SDL&I objectives (commitments become contractual obligations):
Methodology
Source: Supplier Development Localisation Market.pdfSDL&I objectives: Tenderers must submit proposals for local procurement content (target 100%), procurement from black-owned enterprises (target 12%), jobs created/retained, and skills development. These commitments become contractual obligations. Tenderers must submit an SDL&I Implementation Schedule within 28 days after contract award. Quarterly reporting on SDL&I compliance is required using Eskom's Data Collection Template. Eskom reviews reports within 30 days; if obligations not met, corrective measures must be implemented before the next report, failing which retention clauses are invoked.
Pricing Schedule
Source: Supplier Development Localisation Market.pdfTender response must separate local and imported components as per the Price Schedule. Local procurement content is total spending minus imported component.
Financial Requirements
Source: Supplier Development Localisation Market.pdf (unknown)SDL&I penalty: 2% of contract value for failure to meet SDL&I obligations.
Retention: Eskom retains 2% of every invoice (excluding VAT) as security for SDL&I obligations; released only upon full fulfilment.
Pricing: Tender response must separate local and imported components as per the Price Schedule.
Compliance Requirements
Source: Supplier Development Localisation Market.pdf (unknown)B-BBEE evidence required (see evaluation criteria).
Sworn affidavit validity requirements:
B-BBEE improvement milestones (contractual):
Valid B-BBEE certificate or sworn affidavit is a condition for contract award.
Health & Safety
Source: Supplier Development Localisation Market.pdfSkills development targets include a Safety Officer role requiring SAMTRACK qualification. No other health and safety requirements are stated in the document.
Section
Source: Supplier Development Localisation Market.pdfSpecific goals (B-BBEE status level) award up to 10/20 points. Points for price and specific goals are added; contract awarded to highest total. Bidders failing to provide B-BBEE documentation score 0 for specific goals but are not disqualified.
Description
Source: 240-68099512 Form A_Cat 2_ Rev 9.docxThe procurement is for metallurgical replicas for outages on an "as and when required" basis for a period of five (5) years at Kusile Power Station. The tenderer must acknowledge and accept Eskom Supplier Quality Requirements as per specification 240-105658000 and ISO 9001.
Submission Guidelines
Source: 240-68099512 Form A_Cat 2_ Rev 9.docx (unknown)Returnable documents:
Evaluation Criteria
Source: 240-68099512 Form A_Cat 2_ Rev 9.docx (unknown)Quality acknowledgement is mandatory:
Technical Specifications
Source: 240-68099512 Form A_Cat 2_ Rev 9.docx (unknown)Scope: Metallurgical replicas for outages on an "as and when required" basis for a period of five (5) years at Kusile Power Station.
Quality requirements:
Compliance Requirements
Source: 240-68099512 Form A_Cat 2_ Rev 9.docx (unknown)Quality compliance:
Description
Source: 240-75114345 Standard for Metallographic Replication Applicable to Turbine and Generator Components (Rev 3).pdfThe procurement is for metallurgical replicas for outages on an 'as and when required' basis for a period of five years at Kusile Power Station. The work involves in-situ metallographic replication on turbine and generator components to assess creep damage or cracking. The service provider must be approved by Eskom's Physical Metallurgy and Structural Integrity CoE and comply with Eskom Standard 240-75114345.
Important Dates
Source: 240-75114345 Standard for Metallographic Replication Applicable to Turbine and Generator Components (Rev 3).pdf (unknown)Closing date: 7 December 2026 at 08:00.
No briefing session or site visit is stated in the source document.
Contact Information
Source: 240-75114345 Standard for Metallographic Replication Applicable to Turbine and Generator Components (Rev 3).pdf (unknown)No contact information is stated in the source document.
Submission Guidelines
Source: 240-75114345 Standard for Metallographic Replication Applicable to Turbine and Generator Components (Rev 3).pdf (unknown)Returnable documents: none specified in the source document.
Submission method: not stated in the source document.
Submission address: not stated in the source document.
Closing time: 08:00 on 7 December 2026 (from tender record).
Evaluation Criteria
Source: 240-75114345 Standard for Metallographic Replication Applicable to Turbine and Generator Components (Rev 3).pdf (unknown)Bidders must be an approved service provider for metallographic replication on Eskom turbine and generator components, with approval from the Physical Metallurgy and Structural Integrity CoE.
Personnel must be individually approved by Eskom at the required levels: Preparation Technician, Wall Thickness Technician, Replication Technician, Replica Supervisor.
The Replica Supervisor must be a Metallurgical Engineer or Technologist.
Compliance with Eskom Standard 240-75114345 and applicable Eskom NDT Personnel Approval (NPA) standard is required.
All quality control must be done at a magnification of 400/500:1 by the supervisor.
Replicas must be delivered to the designated Eskom office (Rosherville or Middelburg) with correct transmittal sheets and wall thickness readings.
Technical Specifications
Source: 240-75114345 Standard for Metallographic Replication Applicable to Turbine and Generator Components (Rev 3).pdf (unknown)Scope: in-situ metallographic replication on Eskom turbine and generator components, using a thin plastic film to non-destructively duplicate the microstructure to assess creep damage or cracking.
Applicable to highly stressed, critical, and long-lead-time components, including inside surfaces where creep is suspected.
Replica film: acetate film, 30-50 micron thickness.
Minimum evaluable film size: 10 mm x 40 mm.
Weld replicas must show at least 15 mm parent metal and 10 mm weld metal.
Replication depths: turbine rotor/blades and generator components: 0.3 mm maximum; steam chests, casings, valves: 0.5-0.8 mm (low alloy), 0.5-1.0 mm (X20 with WT < 25 mm), 1.0-1.5 mm (X20 with WT > 25 mm), 0.3-0.5 mm on previously replicated areas; generator coil retaining rings: not more than 0.2 mm in an area not greater than 30 x 30 mm.
No replication on landing areas, pull faces in serrations, or areas affecting mechanical functionality.
Wall thickness measurements must be taken before and after replication and recorded on transmittal sheets.
Etchants: 3-5% Nital for low alloy steels; Vilella's reagent for X20 and P91; mixed acids or Marble's reagent for stainless steel (with Site Metallurgist approval); specific etchants for coil retaining rings.
Replicas must be lifted immediately after polishing and etching; no breaks until replica is lifted.
Post-replication cleaning: remove all polishing and etching consumables; clean with methanol and acetone; light grind with 400 grit paper and clean with alcohol.
Replicas must be correctly labelled and transmitted with transmittal sheets and wall thickness readings.
Delivery: replicas must be handed over to Rosherville or Middelburg offices not later than 7:00 am on day 3 after lifting (day 2 if ready).
Replicas dropped off at Security Office will only be checked and signed off when received by the Functional Administrator or Site Metallurgist.
Experience & Qualifications
Source: 240-75114345 Standard for Metallographic Replication Applicable to Turbine and Generator Components (Rev 3).pdfPersonnel must be approved by Eskom at the following levels:
Supervisor presence is mandatory at the beginning and completion of an inspection activity.
Quality Management
Source: 240-75114345 Standard for Metallographic Replication Applicable to Turbine and Generator Components (Rev 3).pdfQuality control must be performed at a magnification of 400/500:1 by the supervisor.
Replicas must meet quality standards: no scratches, correct etching (no under- or over-etching), minimum film size 10 mm x 40 mm, at least 15 mm parent metal and 10 mm weld metal visible on weld replicas, correct labelling, and complete transmittal forms with wall thickness readings.
The service provider must ensure replica quality is acceptable to Eskom and the Original Equipment Manufacturer (OEM).
The ESMQR monitors performance through quality spot checks; the service provider must also conduct its own spot checks and share results with the ESMQR.
Round robin studies are conducted yearly to ensure high-quality replica evaluation.
Replicas that are rejected due to quality issues must be re-taken at the service provider's own cost.
Compliance Requirements
Source: 240-75114345 Standard for Metallographic Replication Applicable to Turbine and Generator Components (Rev 3).pdf (unknown)Must be an approved service provider for metallographic replication on Eskom turbine and generator components, with approval from the Physical Metallurgy and Structural Integrity CoE.
Personnel must be individually approved by Eskom at the required levels.
Compliance with Eskom Standard 240-75114345 and applicable Eskom NDT Personnel Approval (NPA) standard.
In-house procedures must be approved by the Eskom Metallographic Quality Representative (ESMQR); in case of disputes, the Eskom standard prevails.
Health & Safety
Source: 240-75114345 Standard for Metallographic Replication Applicable to Turbine and Generator Components (Rev 3).pdfThe work area must always be clean and safe.
Replication must be carried out on a clean area, and the replicated area must be left dry and free from contaminants.
Swab etching in critical areas must contain all chemicals on the replicated area, and the area must be cleaned and dried with acetone and polished with 1000 grit to leave it free of etchant or rust marks.
Work instructions must be prepared for sensitive areas (rotor bodies, rotor attachments, generator clean areas) to prevent contamination and excessive grinding.
Contractual Terms
Source: 240-75114345 Standard for Metallographic Replication Applicable to Turbine and Generator Components (Rev 3).pdfThe service provider must provide a list of all areas replicated with wall thickness measurements taken before and after replication.
If the service provider uses an in-house procedure, it must be approved by the ESMQR. In case of disputes, the Eskom standard prevails.
Description
Source: Invitation to Tender.pdfThe tender is for the supply and delivery of metallurgical replicas for outages on an 'as and when required' basis for a period of five (5) years at Kusile Power Station. The contract will be governed by the NEC3 Term Service Contract (TSC3).
Important Dates
Source: Invitation to Tender.pdf (RFP)Closing date: 07 December 2026 at 10h00
Clarification meeting (non-compulsory): 25 November 2026 at 09h00 via MS Teams
Clarification queries deadline: 5 working days before the tender closing date
Contact Information
Source: Invitation to Tender.pdf (RFP)Eskom Representative:
Procurement Manager (signatory of ITT):
Fraud and corruption reporting:
Clarification meeting (MS Teams):
Submission Guidelines
Source: Invitation to Tender.pdf (RFP)Submission method: electronic only, via the Eskom E-Tendering site (Eskom Tender Bulletin). No hard copies accepted. Upload documents in PDF format under folders Technical, Commercial, Financial, and Other. The price list must be in PDF and a copy in Excel format. Upload size per document is 500 MB; total submission restricted to 4 GB. No zip/compressed files. If resubmitting, the latest version is accepted and previous submissions become null and void. Ensure the submission status is marked complete.
Returnable forms (all must be completed, signed where required, and submitted by closing time unless noted otherwise):
Disqualification risks:
Evaluation Criteria
Source: Invitation to Tender.pdf (RFP)Evaluation stages:
Contractual requirements (CSD registration, SHEQ, financial viability) are assessed after evaluation and ranking, prior to award. Failure to meet them may render the bidder non-responsive.
Technical Specifications
Source: Invitation to Tender.pdf (RFP)Scope: Supply and delivery of metallurgical replicas for outages on an 'as and when required' basis for a period of five (5) years at Kusile Power Station.
Key details:
Pricing Schedule
Source: Invitation to Tender.pdfPricing schedule must be completed and submitted (if not already in the NEC contract). For e-tendering, submit in PDF and Excel format. The schedule must include a line item for cataloguing if required. Prices are evaluated inclusive of VAT and corrected for arithmetical errors. Unconditional discounts count for evaluation; conditional discounts applied at payment.
Financial Requirements
Source: Invitation to Tender.pdf (RFP)Payment terms:
Security for performance:
Pricing:
Compliance Requirements
Source: Invitation to Tender.pdf (RFP)Mandatory contractual requirements (assessed after evaluation, prior to award):
Additional contractual requirements (if applicable):
Other compliance:
Health & Safety
Source: Invitation to Tender.pdfSHEQ requirements may apply as additional contractual requirements. South African tenderers must submit a COIDA certificate of good standing or proof of application from the Compensation Fund or a licensed compensation insurer. Quality, safety, and environmental documents are required as per the scope of works.
Contractual Terms
Source: Invitation to Tender.pdfEligibility: bidders must not be under any restriction to do business with Eskom or State-Owned Companies, must not have nationality of a country on international sanctions lists, must not submit more than one tender (except as part of a JV/consortium), must not have a conflict of interest, must not be signed by non-authorised persons, must not be restricted by National Treasury or on the Tender Defaulters list, and must not subcontract 100% of the scope of work.
Security: if a performance bond or demand guarantee is required, the tenderer must select at least two (2) financial institutions from Eskom's approved list.
Tender opening: no public opening; tenders downloaded electronically. Prices not read out.
Payment terms: 30 days for contracts below R50 million (incl. VAT); 60 days for contracts above R50 million (incl. VAT).
Eskom reserves the right to negotiate with preferred bidders if prices are not market-related.
Section
Source: Invitation to Tender.pdfFunctionality threshold: minimum weighted final score of 70% required for technical consideration. Price scored out of 80 or 90 points; Specific Goals scored out of 20 or 10 points under PPPFA. Ranking is by combined price and specific goals scores. Failure to submit evidence for a specific goal results in 0 points for that goal but not disqualification.
Description
Source: 20210603_communication_Labour Taxation Questionnaire.pdfThe tender is for metallurgical replicas for outages on an "as and when required" basis for a period of five (5) years at Kusile Power Station. The provided document is a labour taxation questionnaire, not a technical description.
Submission Guidelines
Source: 20210603_communication_Labour Taxation Questionnaire.pdf (unknown)Returnable documents:
Evaluation Criteria
Source: 20210603_communication_Labour Taxation Questionnaire.pdf (unknown)Bidders must complete and submit the PAYE Evaluation Questionnaire (Appendix H). The questionnaire determines whether the bidder is classified as a labour broker or personal services company for tax purposes. Bidders must answer all questions accurately and provide the required registration numbers.
Technical Specifications
Source: 20210603_communication_Labour Taxation Questionnaire.pdf (unknown)The tender is for metallurgical replicas for outages on an "as and when required" basis for a period of five (5) years at Kusile Power Station. The document provided is a labour taxation questionnaire, not the technical specification. No technical details are available in the source text.
Compliance Requirements
Source: 20210603_communication_Labour Taxation Questionnaire.pdf (unknown)Bidders must complete the Contractors' PAYE Evaluation Questionnaire (Appendix H) and provide registration numbers (ID, company, CC or trust, VAT, PAYE). If classified as a labour broker, bidders must supply a valid, original or certified copy of an IRP30 for the current tax year within 30 days.
Section
Source: 20210603_communication_Labour Taxation Questionnaire.pdfBidders must complete the Contractors' PAYE Evaluation Questionnaire (Appendix H) and provide the required registration numbers. If classified as a labour broker, bidders must supply a valid, original or certified copy of an IRP30 for the current tax year within 30 days.
Description
Source: E-tendering Help Manual for supplier - 27 January 2025.pdfThe document is the Eskom eTendering System Suppliers Help Manual. It explains how suppliers register and submit tender documents electronically. Key points:
Important Dates
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)Closing date: 7 December 2026 at 08:00 (from tender record).
No other dates are stated in the document.
Submission Guidelines
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)Submission method: online via the Eskom eTendering system at https://eTendering.eskom.co.za.
Evaluation Criteria
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)No evaluation criteria are stated in the provided document. The document is a user manual for the eTendering system, not the tender specification.
Technical Specifications
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)The document is a user manual for the Eskom eTendering system. It does not contain technical specifications for the tender.
Compliance Requirements
Source: E-tendering Help Manual for supplier - 27 January 2025.pdf (TENDER)Bidders must have a valid CSD (Central Supplier Database) number to access the eTendering system.
Description
Source: Unpriced Cost Estimate Report For Metallurgical Replicas for Outages as and when required at Kusile Power Station.xlsxThe tender is for the supply of metallurgical replica services for outages at Kusile Power Station, on an as-and-when-required basis, for a period of five years. The scope includes site establishment, provision of qualified personnel, consumables, tools and equipment, documentation, and occupational hygiene surveys.
Technical Specifications
Source: Unpriced Cost Estimate Report For Metallurgical Replicas for Outages as and when required at Kusile Power Station.xlsx (unknown)Scope: Supply of metallurgical replica services for outages on an as-and-when-required basis for five years at Kusile Power Station.
The pricing schedule covers six main items:
Key personnel requirements (normal time hours shown):
Quantities for consumables include: grinding papers (4,320 sheets per grit), replica film (18,000 pieces), glass slides (18,000 pieces), diamond paste (72 tubes per micron), acetone (360 units), etchants (36-72 units), and various safety items.
Tools include portable grinders, mini angle grinders, flexible shaft grinders, hand files, portable metallurgical microscope (up to 500x), digital microscope camera (min 5 MP), LED ring light, applicator tools, and tweezers.
Financial Requirements
Source: Unpriced Cost Estimate Report For Metallurgical Replicas for Outages as and when required at Kusile Power Station.xlsx (unknown)Pricing schedule is an unpriced cost estimate; bidders must complete rates and amounts for each line item.
The final summary totals all six items to a total amount excluding VAT.
No bid security, guarantees, retention, or payment terms are stated in the provided document.
Compliance Requirements
Source: Unpriced Cost Estimate Report For Metallurgical Replicas for Outages as and when required at Kusile Power Station.xlsx (unknown)No explicit compliance requirements (CSD, tax, B-BBEE, CIDB) are stated in the provided document.
Personnel must meet specified qualifications and experience as listed in the technical specifications.
Description
Source: KUS-20260765 Kusile Power Station TES Metallurgical Replicas for Outages as and when required for a 5 year period Rev 2 (002).pdfMetallurgical replication services for outages at Kusile Power Station, supplied on an as-and-when-required basis over a five-year period.
Evaluation approach
Submission Guidelines
Source: KUS-20260765 Kusile Power Station TES Metallurgical Replicas for Outages as and when required for a 5 year period Rev 2 (002).pdf (unknown)Returnable technical evidence (assessed at the mandatory gate):
Disqualification:
Evaluation Criteria
Source: KUS-20260765 Kusile Power Station TES Metallurgical Replicas for Outages as and when required for a 5 year period Rev 2 (002).pdf (unknown)Evaluation stages
Qualitative criteria and weights
Technical Evaluation Team
Technical Specifications
Source: KUS-20260765 Kusile Power Station TES Metallurgical Replicas for Outages as and when required for a 5 year period Rev 2 (002).pdf (unknown)Scope
Systems covered
Governing Eskom standards
Methodology
Source: KUS-20260765 Kusile Power Station TES Metallurgical Replicas for Outages as and when required for a 5 year period Rev 2 (002).pdfEvaluation method
Team responsibilities
Experience & Qualifications
Source: KUS-20260765 Kusile Power Station TES Metallurgical Replicas for Outages as and when required for a 5 year period Rev 2 (002).pdfPersonnel
Company experience
Plant approvals
Quality Management
Source: KUS-20260765 Kusile Power Station TES Metallurgical Replicas for Outages as and when required for a 5 year period Rev 2 (002).pdfQuality and technical standards referenced
Application
Compliance Requirements
Source: KUS-20260765 Kusile Power Station TES Metallurgical Replicas for Outages as and when required for a 5 year period Rev 2 (002).pdf (unknown)B-bbee
Mandatory technical compliance (pass/fail)
Consequence
Section
Source: KUS-20260765 Kusile Power Station TES Metallurgical Replicas for Outages as and when required for a 5 year period Rev 2 (002).pdfWeighted qualitative scoring, total 100%
Minimum qualifying technical score
Gatekeeping
Scoring detail
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
tender Office - tender Office - tender Office - 0000
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
24
Last checked
20 Nov 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Learn how to submit a winning bid with these related articles
Made in SA: Explore the strategic importance of localization in manufacturing tenders and learn how your fabrication SMME can qualify for high-value industrial contracts.
A masterguide to the legal and policy frameworks that mandate the use of South African products in Gauteng's government procurement.
A guide for local manufacturers to secure contracts for school uniforms, hospital linens, and protective clothing for Gauteng's public sector.
Win government goods supply contracts including furniture, stationery, uniforms, and equipment. Local content requirements and NRCS certification explained.
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Manufacturing. Unlock full pricing strategies, bid frequency, and historical win rates.