Tender Type
Request for Bid(Open-Tender)
Delivery Location
National transmission of south africa - Germiston - Gauteng - 1401
Organization Type
GOVERNMENT
Published
28 Oct 2026
OCDS Reference
ocds-9t57fa-176195
Eskom's national transmission company of south africa requires a supplier to procure, deliver, off-load, install, test, commission and hand over smart meters to the required standard and scope of work, with the work situated in gauteng. Bids close on 27 november 2026 at 08:00 and must be lodged electronically through the ntcsa etendering portal, as physical delivery to ESKOM tender offices is NO longer used. A valid csd number is a precondition for portal access, and uploads are capped at 50mb per file and 900mb in total.
Submission channel: bids are submitted electronically only, through the NTCSA eTendering portal at https://eTendering.eskom.co.za; tenders are advertised on the Tender Bulletin at https://tenderbulletin.ntcsa.co.za.
Closing: 27 November 2026 at 08:00; the portal stamps the submission with a date and time when Finalise Submission is clicked.
CSD registration: a valid CSD number is mandatory before the eTendering portal can be accessed or a bid submitted, and the number held on the supplier's registration must stay current.
Portal registration and login: suppliers must register with name, organisation, CSD number and cellphone number (plus prefix, e.g. +27), verify by email link, then log in with the registered email address, password and a one-time PIN sent to the registered cellphone and email.
Upload limits and filing: no single file may exceed 50MB and all uploaded files together may not exceed 900MB; each document must be filed under the correct category (technical, commercial or finance) before finalising.
Proof of submission: a confirmation email listing the submitted documents and a submission ID is issued once the submission is finalised, and it must be retained for any later enquiry; submitted bids remain viewable under My Submissions.
Scope of work: procurement, delivery, off-loading, installation, testing, commissioning and handover of smart meters to the stated standard and specification.
Continue with tenders sharing this issuer, category, or province.
Browse categories with current opportunities in this area.
Compare tender activity across provinces.
Explore organisations currently publishing tenders.
Tools and research to help you assess opportunities.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Browse categories with current opportunities in this area.
Compare tender activity across provinces.
Explore organisations currently publishing tenders.
Tools and research to help you assess opportunities.
Date & Time
Friday, 27 November 2026 - 10:00
Venue
null
Categories
Request for Bid(Open-Tender)
National transmission of south africa - Germiston - Gauteng - 1401
Tenders in this industry often require registration with these bodies.
Recommended Certifications
Having these can improve your winning chances: SAPVP Registration, REBOSA Membership
AI Document Analysis Stages
Description
Source: NTCSA Non-Disclosure Agreement (NDA) Vendors.docx28 Oct
2026
Tender Published
Tender was published
27 Nov
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
NTCSA_E-Tenderers E-Tendering Training Acknowledgement Form.docx
Supply, delivery, off-loading, installation, testing, commissioning and handover of smart meters meeting the required standards and specifications, procured by Eskom National Transmission Company of South Africa in Gauteng.
BOQ.pdf
Procurement, delivery, off-loading, installation, testing, commissioning and handover of smart meters and associated electrical metering infrastructure for Eskom National Transmission Company of South Africa in Gauteng. Pricing is by bill of quantities covering site preliminaries and general, and electrical installation of multifunction energy meters, current transformers, protection and enclosures.
NTCSA Non-Disclosure Agreement (NDA) Vendors.docx
Procurement, delivery, off-loading, installation, testing, commissioning and handover of smart meters built to the required standards and specifications for the National Transmission Company South Africa (NTCSA). The material supplied covers the non-disclosure agreement that a bidder must conclude with NTCSA before project information is shared.
SDL&I Input Meterbox Installation.pdf
Supply, delivery, off-loading, installation, testing, commissioning and handover of smart meters for Eskom National Transmission Company of South Africa, to meet specified standards and specifications. The project duration is stated as Seven (6) months, with work in Gauteng.
NTCSA_E-Tenderers E-Tendering Training Acknowledgement Form - Copy.docx
Supply, delivery, off-loading, installation, testing, commissioning and handover of smart meters to meet the standards and specifications set out in the scope of work. The contract is issued by Eskom National Transmission Company of South Africa in Gauteng.
20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdf
NTCSA requires the procurement, delivery, off-loading, installation, testing, commissioning and handover of smart meters to meet defined standards and specifications, executed as a full EPC-style metering installation across multiple buildings and metering points. The contract is let on the NEC3 Engineering Short Contract and is evaluated on an 80/20 preference point system with a mandatory functionality threshold of 70%.
NTCSA_E-tendering Help Manual for supplier.docx
Supply, delivery, off-loading, installation, testing, commissioning and handover of smart meters meeting the specified standards and scope of work. The contract is issued by Eskom National Transmission Company of South Africa for a Gauteng-based requirement.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubWe refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
This document is a confidentiality agreement between NTCSA and the bidder (the receiving party). It governs the disclosure and use of confidential information related to the project, including the procurement of smart meters.
Submission Guidelines
Source: NTCSA Non-Disclosure Agreement (NDA) Vendors.docx (unknown)Returnable documents: NTCSA non-disclosure agreement, completed by the bidder as the receiving party, stating its registered name, country of incorporation, registered address, and registration number. The NTCSA signatory must be no lower than an E-Band Manager.
Evaluation Criteria
Source: NTCSA Non-Disclosure Agreement (NDA) Vendors.docx (unknown)The bidder must be able to conclude the NTCSA non-disclosure agreement. No other evaluation criteria are provided in this document.
Technical Specifications
Source: NTCSA Non-Disclosure Agreement (NDA) Vendors.docx (unknown)NTCSA (the Disclosing Party) is a company incorporated under the laws of the Republic of South Africa, registration number 2021/539129/30, with registered office at Megawatt Park, Maxwell Drive, Sunninghill ext. 3, Sandton.
Submission Guidelines
Source: NTCSA_E-Tenderers E-Tendering Training Acknowledgement Form.docx (unknown)Mandatory returnable form:
Submission method: e-Tendering platform. Failure to fully complete and submit the form within the prescribed period renders the tenderer non-responsive and disqualified from the procurement process.
Evaluation Criteria
Source: NTCSA_E-Tenderers E-Tendering Training Acknowledgement Form.docx (unknown)Mandatory responsiveness requirement:
Compliance Requirements
Source: NTCSA_E-Tenderers E-Tendering Training Acknowledgement Form.docx (unknown)Reference number and business/JV name are required on the acknowledgement form.
Description
Source: BOQ.pdfThe works involve the procurement, delivery, off-loading, installation, testing, commissioning and handover of smart meters on site. The contractor must establish site facilities and complete the Bill of Quantities in line with the project technical specification.
Important Dates
Source: BOQ.pdf (unknown)Closing date: 27 November 2026 (time not stated in document). No briefing or site visit dates provided.
Contact Information
Source: BOQ.pdf (unknown)No contact information was found in the document.
Submission Guidelines
Source: BOQ.pdf (unknown)Submission method: not stated in the document.
Returnable documents: not specified; the Bill of Quantities must be completed using the project technical specification.
Evaluation Criteria
Source: BOQ.pdf (unknown)Evaluation criteria are not detailed in the provided document. The Bill of Quantities indicates pricing items but no scoring method or preference point system is stated.
Technical Specifications
Source: BOQ.pdf (unknown)Scope: Procure, deliver, off-load, install, test, commission and handover smart meters on site, in accordance with the technical specification and works information.
Electrical work (Bill No. 4) — supply and install:
Preliminaries (Bill No. 1) — contractor must provide:
Financial Requirements
Source: BOQ.pdf (unknown)Pricing: complete the Bill of Quantities with rates and amounts for each item. The contract sum is the estimated cost excluding VAT. No bond, guarantee, retention or payment terms are stated.
Compliance Requirements
Source: BOQ.pdf (unknown)No specific eligibility or compliance requirements (e.g., CSD, tax clearance, B-BBEE, CIDB) are stated in the provided document.
Health & Safety
Source: BOQ.pdfThe contractor must prepare a health and safety file and plan, provide medicals, PPE, police clearance, appoint a safety officer, and include these costs in the preliminaries.
Contractual Terms
Source: BOQ.pdfContract terms are not stated; only the requirement to supply and install wiring termination accessories and identification labels is listed as a bill item.
Section
Source: BOQ.pdfNo additional evaluation criteria are specified in the document.
Submission Guidelines
Source: NTCSA_E-Tenderers E-Tendering Training Acknowledgement Form - Copy.docx (unknown)Returnable documents:
Submission method: e-Tendering Solution.
Disqualification risks:
Evaluation Criteria
Source: NTCSA_E-Tenderers E-Tendering Training Acknowledgement Form - Copy.docx (unknown)Mandatory returnable:
Responsiveness: Tenderers not submitting the form fully and on time will be declared non-responsive and disqualified.
Bidders must confirm they have completed self-training via the e-Tendering Noddy Guide, video, or clarification meeting, and are able to operate the e-Tendering Solution.
Description
Source: NTCSA_E-tendering Help Manual for supplier.docxThe eTendering system is a web-based platform that replaces physical delivery of tender documents to Eskom tender offices. Suppliers upload their bids electronically instead of submitting them by hand.
Submission Guidelines
Source: NTCSA_E-tendering Help Manual for supplier.docx (unknown)Submission channel
Registration and access
Uploading a bid
System support
Compliance Requirements
Source: NTCSA_E-tendering Help Manual for supplier.docx (unknown)CSD registration
Description
Source: SDL&I Input Meterbox Installation.pdfThe work comprises the procurement, delivery, off-loading, installation, testing, commissioning, and handover of smart meters, to be carried out in accordance with the stated standard and specifications.
Contact Information
Source: SDL&I Input Meterbox Installation.pdf (TENDER)Contacts
(Additional contact details not provided in the document.)
Submission Guidelines
Source: SDL&I Input Meterbox Installation.pdf (TENDER)Returnable documents — all must be completed, signed and submitted with the bid:
Disqualification risks:
Evaluation Criteria
Source: SDL&I Input Meterbox Installation.pdf (TENDER)Evaluation is in two stages:
Failure to meet the objective criteria may result in the second-ranked tenderer being recommended for award.
Technical Specifications
Source: SDL&I Input Meterbox Installation.pdf (TENDER)Scope of work:
Project duration: Seven (6) months (as stated; note: the document says "Seven (6)" which is inconsistent, likely a typo — 6 months is the figure given in the text).
Compliance Requirements
Source: SDL&I Input Meterbox Installation.pdf (TENDER)Compliance requirements:
Contractual Terms
Source: SDL&I Input Meterbox Installation.pdfContractual obligations include:
Undertakings given in Section 2 are not scored but become contractual obligations once awarded.
Description
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdfThe tender is for the procurement, delivery, off-load, installation, testing, commissioning, and handover of smart meters to meet specified standards and technical requirements. The work is for NTCSA buildings/metering points. The contract is for the whole scope. Bidders must be registered with the Department of Employment and Labour as electrical contractors and hold CIDB grading 2EB or higher.
Important Dates
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdf (TENDER)Closing date: 27 November 2026
Closing time: 10h00
Tender validity: 12 weeks (90 days) from closing date.
Clarification queries deadline: 10 working days before tender submission deadline.
Clarification meeting: Not applicable.
Contact Information
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdf (TENDER)NTCSA Representative: Ofhani Masakona
Telephone: 013 297 9690
Email: [email protected]
1st Escalation – Procurement Manager: Magcino Zuma
Email: [email protected]
2nd Escalation – Middle Manager: Vongani Hlungwani
Email: [email protected]
Submission: Electronic via NTCSA Tender Bulletin site on Eskom E-tendering page.
Submission Guidelines
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdf (TENDER)Tenders must be submitted electronically via the NTCSA Tender Bulletin site on the Eskom E-tendering page. Documents must be uploaded under the Technical, Commercial, Financial, and other folders. All documents must be in PDF format; the price list must be submitted in both PDF and Excel format. The upload size per document is 500 megabytes, and total submission is restricted to 4 gigabytes. No zip or compressed files, no hard copies. If a tender is resubmitted, only the latest version is accepted; previous versions are null and void. Ensure the submission status is marked as complete. Late tenders will not be accepted.
Returnable forms required at tender closing (disqualifiable if not completed, signed if required, and submitted):
Other returnables (non-disqualifiable; if not submitted at closing, requested in writing, must be provided within 5 working days):
Disqualification risks:
Evaluation Criteria
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdf (TENDER)Evaluation follows a two-stage process. First, functionality (technical) is scored out of 100. A minimum threshold of 70% is required to proceed; bidders scoring below this are disqualified. Then, price and specific goals are scored under the 80/20 preference point system (for tenders up to R50 million).
Functionality scoring (out of 100):
Price scoring (out of 80 points):
Specific Goals scoring (out of 20 points) under PPPFA. Failure to submit evidence for a specific goal results in zero points for that goal but not disqualification.
Ranking: total score = price + specific goals, ranked highest to lowest.
Technical Specifications
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdf (TENDER)Scope: Procure, deliver, off-load, install, test, commission, and handover smart meters at NTCSA buildings/metering points, per the technical scope of work.
Mandatory technical criteria:
Quality and safety:
Functionality documents required (unless already submitted):
Methodology
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdfA method statement must be submitted as part of the functionality evaluation (20% weight). The method statement must demonstrate understanding of the full scope, including the installation sequence, CT and voltage wiring methodology, testing and commissioning approach, SHEQ requirements, and handover. Scoring: 5 marks for comprehensive method addressing all scope elements; 4 marks for most elements with minor omissions; 2 marks for generic or incomplete; 0 for none.
Experience & Qualifications
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdfThe bidder must demonstrate relevant experience: at least one successfully completed project involving installation, configuration, testing, and commissioning of energy meters within the past seven years, with verifiable client references. A detailed project organogram must be provided identifying key personnel and any outsourced resources. Key resource requirements: the registered person must be an Installation Electrician or Master Installation Electrician (no single-phase tester) with 5+ years relevant experience and must be a full-time employee of the company. At least 2 electrical artisans are required, each with an electrical trade test with minimum N4 qualification, at least 5 years relevant experience, and trained/authorised to work on low voltage installations (ORLVS). If artisans are subcontracted, a letter of intent between parties must be provided.
Quality Management
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdfBidders must submit a draft Inspection and Test Plan (ITP) and Quality Plan covering activities of the scope, demonstrating understanding of inspection and verification points (hold/witness points) for CT installation, CT ratio verification, polarity testing, voltage reference checks, meter configuration, Modbus/address settings, functional testing, and Certificate of Compliance (CoC) issuance. The bidder must comply with NTCSA's Supplier Quality Management Specification (240-105658000). The registered person is responsible for issuing the electrical certificate of compliance after inspection and testing.
Pricing Schedule
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdfThe pricing schedule/BOQ is attached to the tender and must be completed and submitted. Price list must be submitted in PDF and Excel format. Prices are evaluated inclusive of VAT, corrected for arithmetical errors, and excluding contingencies. Pricing will be scored out of 80 points under the 80/20 preference system.
Financial Requirements
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdf (TENDER)Pricing: Bidders must submit a pricing schedule/BOQ as attached to the tender (1.1.28). The price list must be submitted in PDF and Excel format. Prices are evaluated inclusive of VAT.
Payment terms: For contracts valued below R50,000,000 (including VAT), NTCSA commits to paying suppliers within 30 days of receipt of undisputed invoices.
Performance security: Not applicable.
Contractual requirements after award (not scoring criteria):
Note: The 80/20 preference point system applies to tenders with a rand value equal to or below R50 million.
Compliance Requirements
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdf (TENDER)Mandatory compliance:
Tax compliance:
Electrical contractor registration:
CIDB grading:
Employment Equity:
B-bbee:
Local content:
Additional contractual requirements (assessed after evaluation, prior to award):
Eligibility exclusions:
Health & Safety
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdfBidders must comply with NTCSA SHEQ requirements, including the NTCSA SHEQ Policy (32-727), the Contract and Contractor OHS Management specification, and the Draft SHE Specification for Smart Meters Installation. The bidder must submit a method statement addressing SHEQ considerations. South African tenderers must provide COIDA certificate of good standing or proof of application. The bidder must submit the required OHS tender returnables as listed (e.g., 32-95 rev 9, AM OHS Contractor Baseline risk assessment).
Environmental
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdfBidders must comply with the Transmission Environmental Requirements for Contractors/Suppliers standard (240-180100134) and the NTCSA SHEQ Policy. The smart meter installation has an Environmental Management Tender Returnable and an Environmental Requirements Proforma (240-180100154) that must be completed and submitted.
Contractual Terms
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdfThe contract will be subject to the NEC3 Engineering Short Contract. The contract is for the whole of the scope. The tender validity period is 12 weeks. NTCSA may extend the validity period; bidders agreeing to an extension may not modify their tender. The Form of Agreement will be signed by authorised signatories. Contractual requirements (CSD, financial viability, security vetting) are not evaluation criteria but are conditions for award; failure to meet them may render the bidder non-responsive.
Section
Source: 20261023_NTCSA Invitation_to_Tender_(ITT) Meter Installation.pdfThe evaluation process is as described in the main evaluationCriteria section. Additional details: For functionality, a minimum threshold of 70% is required to proceed to the next stage. Specific goals are scored out of 20 points; failure to submit evidence results in zero points for that goal but not disqualification. The 80/20 system applies for tenders with rand value equal to or below R50 million.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 4 of 2006
Relevant to electricity, generation, transmission, distribution and energy-service procurement.
Relevant because this tender appears to involve electricity, power supply, energy infrastructure, generators, or energy maintenance.
Act 107 of 1998
Relevant where environmental authorisations, EIAs or environmental compliance may apply.
Relevant because this tender appears to involve electricity, power supply, energy infrastructure, generators, or energy maintenance.
Act 85 of 1993
Sets health and safety duties for contractors, employers and service providers working on public-sector sites.
Relevant because this tender appears to involve electricity, power supply, energy infrastructure, generators, or energy maintenance.
Act 40 of 2004
Relevant to regulated electricity, piped-gas and petroleum-pipeline activities.
Relevant because this tender appears to involve electricity, power supply, energy infrastructure, generators, or energy maintenance.
Address
Lake Street, Germiston, Johanessburg, 1401, South Africa
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
7
Last checked
29 Oct 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Contact
011-629-5553[email protected]www.eskom.co.za/Pages/Landing.aspxLake Street, Germiston, Johanessburg, 1401, South Africa
Key Personnel
Median Estimate
R 691 734
Range
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
Get deep intelligence on Real estate activities. Unlock full pricing strategies, bid frequency, and historical win rates.
Learn how to submit a winning bid with these related articles
Guide to winning facilities management (FM) tenders in South Africa. Covers soft services, hard services, and integrated FM contracts for government buildings.
South Africa's energy revolution is gathering pace. Discover the massive opportunities for SMMEs in the renewable energy sector, from the Northern Cape's solar hubs to municipal wheeling projects.
Win renewable energy, Eskom, and municipal utilities contracts. IPP programmes, solar tenders, and power infrastructure opportunities.
A guide to winning government property valuation tenders in South Africa, covering MPRA requirements, municipal general valuation rolls, SACPVP registration, and objection handling.
💡 Want more tendering tips and strategies?
Explore Our Blog