KUSILE POWER STATION - WITBANK - EMALAHLENI/VICTOR KHANYE - 1035
Organization Type
GOVERNMENT
Published
17 Nov 2026
OCDS Reference
ocds-9t57fa-178506
Summary
ESKOM requires a contract quality plan (cqp) for the kusile smart plant digitalisation and artificial intelligence project, structured against SANS 466:2005 and iso 10005:2005. The plan must cover quality management across the full contract scope, including organogram, interfacing documents, sub-supplier management, inspection and test plans, special controls, records, non-conformance, databook, tools, customer property, preservation, traceability and post-delivery support. Bidders submit the cqp at revision 0 during tender evaluation, approved by the owner of the bidding organisation, and revise to revision 1 after contract signature. The most consequential consideration is that the cqp must be complete and specific to the scope, as IT forms part of the bid and will be reviewed by ESKOM.
Key Requirements
CQP structure: must follow SANS 466:2005 and ISO 10005:2005, covering all 20 sections from scope of work to commissioning and post-delivery activities.
Scope of work: full description as per the NEC or FIDIC contract document must be included.
Organogram: must show QA and QC functions, designations, roles, responsibilities and qualifications, including who verifies work versus who performs it.
Sub-supplier management: list all suppliers and sub-suppliers, selection criteria, and how their performance will be monitored after award.
Inspection and test: identify all products/processes requiring QCP/ITP (offsite and onsite) and describe special controls for welding, NDT/NDE and other coded processes.
Records and databook: describe how records are controlled, retained and disposed of, and provide a databook index and operating and maintenance manual if applicable.
Approval and revision: CQP must be compiled by the tenderer's representative at Revision 0 during tender evaluation, approved by the owner of the bidding organisation, and revised to Revision 1 after contract signature; Eskom review and acceptance occur only after award.
KUSILE POWER STATION - WITBANK - EMALAHLENI/VICTOR KHANYE - 1035
Information & Communication Technology Industry Profile
Critical Requirements
POPIA Compliance
Regulatory Bodies
IITPSA
Tenders in this industry often require registration with these bodies.
Typical Documents
9 items
Company Registration (CIPC)
Tax Clearance Certificate
B-BBEE Certificate
CSD Registration
Company Profile
ISO 27001 Certificate (if applicable)
Technical Certifications
Solution Architecture Documents
Reference Letters
Recommended Certifications
Having these can improve your winning chances: IITPSA Membership, ISO 27001 (Information Security Management), ISO 20000 (IT Service Management), CISSP
Document read. The full tender notice and its supporting documents are read end-to-end. Key sections, requirements, dates, and contact details are identified and pulled into a working summary you can act on.
Compliance review. The working summary is checked against South African procurement standards — PFMA, PPPFA, B-BBEE, CIDB, local content, and preferential procurement — so nothing critical is missed before you start your bid response.
DocumentSmart Plant Digitilisation SHE Spec .pdfReview complete
Description
Source: Smart Plant Digitilisation SHE Spec .pdf
Important Dates
17 Nov
2026
PUBLICATION
Tender Published
Tender was published
29 Jan
2027
DEADLINE
Closing Date
Tender closing date
Procurement Rules & Compliance ContextThis tender may be governed by South African public procurement rules covering fairness, transparency, preferential procurement, anti-corruption, administrative justice and access to information.
7 rules
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
Core procurement rules
These rules commonly apply to South African public-sector procurement.
7
Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
high
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Constitution of the Republic of South Africa, 1996 – Section 217
Act 108 of 1996 (s217)
high
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
A Contract Quality Plan template for the Kusile Smart Plant Digitalisation and Artificial Intelligence Project in Mpumalanga, requiring the supplier to plan how quality expectations of the contract will be met, with reference to SANS 466:2005 / ISO 10005:2005. Bids close on 29 January 2027 at 10:00.
The department requires the procurement of the Kusile Smart Plant Digitalisation and Artificial Intelligence Project for Eskom in Mpumalanga, with submissions closing on 29 January 2027 at 10:00. The provided document is the authorisation form that tenderers must complete and sign to authorise an individual to submit the tender and sign documents on behalf of the entity.
Procurement of the Kusile Smart Plant Digitalisation and Artificial Intelligence Project for Eskom at Kusile Power Station, Mpumalanga. The contract is an NEC3 Engineering & Construction Contract; the material provided covers only the securities required under it, namely the pro forma Performance Bond (Secondary Option X13) and Retention Money Guarantee (Secondary Option X16).
Annexure A - Technical Evaluation Criteria_Rev6.xlsx
Eskom requires a single supplier or integrated consortium to deliver the Kusile Smart Plant Digitalisation and Artificial Intelligence project across five pillars: network and infrastructure, intelligent inspection and digital integration, digital twin interface, paperless operations with SAP integration, and digitisation of plant documents. The project demands a comprehensive Primavera P6 schedule, full compliance with mandatory enterprise integration and IP ownership requirements, and achievement of at least 75% per pillar in functional evaluation.
Procurement of the Kusile Smart Plant digitalisation and artificial intelligence project for ESKOM in Mpumalanga. Bidders are required to submit a digitalisation and AI solution to enhance the plant's operations.
Eskom requires the supply and implementation of a smart plant digitalisation and artificial intelligence solution for the Kusile power station in Mpumalanga, delivered under a quality-managed contract aligned to Eskom specification 240-105658000 and ISO 9001.
Eskom requires the design, execution, commissioning, handover and training for the Kusile Power Station Smart Plant Digitalisation and Artificial Intelligence Project, delivered in five execution pillars at Kusile Power Station in Mpumalanga under an NEC3 ECC3 Option A priced contract with an activity schedule.
240-77471651 Annexure C 1 (3) High risk tender 2026.docx
The procurement covers the Kusile Smart Plant Digitalisation and Artificial Intelligence Project, covering digitalisation and artificial intelligence for the Kusile plant. The procuring organisation is Eskom.
Eskom requires a contractor to deliver the Kusile Smart Plant Digitalisation and Artificial Intelligence Project at Kusile Power Station in Mpumalanga, under an NEC3 Engineering and Construction Contract (April 2013) Option A priced contract with activity schedule. Bidders submit their offer by completing Contract Data Part 2, which fixes the contractor's identity, fee percentages, key personnel, programme, activity schedule and tendered total of the Prices.
Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.doc
Eskom requires a contractor to deliver the Kusile Smart Plant Digitalisation and Artificial Intelligence project in Mpumalanga. The appointed supplier must complete a PAYE classification questionnaire and supporting affidavits so Eskom can determine whether payments are subject to employee's tax withholding.
Smart plant digitalisation and artificial intelligence works at the Kusile Power Station in Mpumalanga, procured by Eskom Holdings SOC Ltd. Bids close on 29 January 2027 at 10:00 (South Africa Standard Time). The work is let under the NEC3 Engineering and Construction Contract, with the terms set out across Parts C1 to C4.
Eskom requires the supply of a smart plant digitalisation and artificial intelligence solution for the Kusile power station in Mpumalanga. The bid is subject to the Preferential Procurement Regulations, 2017 local production and content regime for designated sectors.
240-77433139 Annexure A supplier risk category.docx
Eskom is procuring the Kusile Smart Plant Digitalisation and Artificial Intelligence Project in Mpumalanga. The tender includes detailed occupational health and safety (OHS) requirements that vary by supplier risk category, with mandatory COID compliance and OHS evaluation for supplier registration.
Eskom requires the Kusile Smart Plant Digitalisation and Artificial Intelligence project, delivered in Mpumalanga. Bidders must submit a completed Contractors' PAYE Evaluation Questionnaire (Appendix H), which establishes whether they supply labour to Eskom, whether they operate as a labour broker or personal services company, and the degree of Eskom control and supervision over their work.
Eskom requires the design, implementation, and integration of advanced digital technologies at Kusile Power Station across five technology pillars delivered in two phases: Phase 1 covers Network & Infrastructure, Intelligent Inspection and Digital Integration, and Digital Twin Interface; Phase 2 covers Paperless Operations with SAP PM/MM integration and Digitization of Existing Plant Documents and Data Books.
Eskom requires the supply of a smart plant digitalisation and artificial intelligence solution for the Kusile power station in Mpumalanga. The scope covers the implementation of digital and AI capabilities for the plant.
Supplier Declaration of Interest Template (1).docx
Digitalisation and artificial intelligence services for the Kusile Smart Plant project in Mpumalanga, procured by Eskom. The closing date is 29 January 2027 at 10:00 South African Standard Time.
Eskom requires the delivery of a smart plant digitalisation and artificial intelligence project for the Kusile power station in Mpumalanga. The scope covers the supply and implementation of digitalisation and AI capability at the plant.
C3 1 ECC3 Employers Works Information_SPP_29.09.2026.docx
Procurement of the Kusile Smart Plant Digitalisation and Artificial Intelligence Project is required for implementation at Kusile Power Station. The works cover a governed digital foundation for real-time and near-real-time data access, paperless field execution, AI-assisted inspection, controlled document retrieval, auditability and technology transfer. The project is intended to support operational efficiency, safety, compliance, data-driven decision-making and knowledge preservation at the strategic coal-fired station.
Supplier Evaluation Pack Template for 01 March 2025 to 29 February 2026.xls
Eskom is procuring the Kusile Smart Plant Digitalisation and Artificial Intelligence Project in Mpumalanga. The submission appears to be managed through an Excel-based workbook with multiple sheets for contractor information, appendices, and definitions, protected with a password.
The procurement is for the design, execution, commissioning, handover, and training of the Kusile Power Station Smart Plant Digitalisation and Artificial Intelligence Project. Eskom Holdings Soc Ltd is the employer, and the contract is structured under the NEC3 Engineering & Construction Contract (Part C1: Agreements & Contract Data). Bids must be submitted by 29 January 2027 at 10:00.
559-667439824 Generation Quality Control Plan Template 18Nov.docx
Supply and delivery of digitalisation and artificial intelligence solutions for the Kusile Smart Plant under the Kusile Smart Plant Digitalisation and Artificial Intelligence Project. The procuring entity is Eskom in Mpumalanga, with a bid closing date of 29 January 2027 at 10:00. Project execution requires strict adherence to a Quality Control Plan (QCP) and archival of the Databook on OpenText.
KUS-20260973 Kusile Power Station Tender Technical Evaluation Strategy for Kusile Smart Plant Digitalisation and AI FINAL.pdf
Eskom requires a service provider to design, implement and integrate a Smart Plant digital ecosystem at Kusile Power Station across five technology pillars: network and infrastructure, intelligent inspection and digital interaction, digital twin interface integration, paperless operations, and digitisation of existing plant documents and data books. The solution must interoperate with the existing EPRI Program 224 Digital Twin and the existing ERP system.
Eskom requires a supplier to deliver the Kusile Smart Plant Digitalisation and Artificial Intelligence project, with the supplier bound to Eskom's Supplier Quality Management specification (240-105658000 / QM 58, Revision 3) and ISO 9001-based quality management throughout the contract.
Design, procurement, implementation, integration, testing, training and handover of five integrated technology pillars at Kusile Power Station: network and infrastructure, intelligent inspection and digital integration, a digital twin interface, paperless operations integrated with SAP PM/MM, and digitisation of existing plant documents and data books. The work is procured by Eskom under enquiry C.GKU1150 and is delivered in two sequential phases, with the awarded bidder designated the Main contractor and any subcontractor an Appointed contractor.
Digitalisation and artificial intelligence services for the Kusile Smart Plant are being procured by Eskom. The procurement is located in Mpumalanga, with bids closing on 29 January 2027 at 10:00.
Digitalisation and artificial intelligence works for the Kusile smart plant in Mpumalanga. Eskom procures the project under an NEC3 Engineering and Construction Contract Option A. Payment is made only for completed activities priced as lump sums on an Activity Schedule.
240-12248652_Catergory 2 List of Tender Returnables Rev 7.pdf
The department requires the procurement of the Kusile Smart Plant Digitalisation and Artificial Intelligence Project for a period of three years. Bidders must submit comprehensive quality management documentation, including a draft contract quality plan and a draft inspection and test plan, with submissions closing on 29 January 2027 at 10:00.
E-Tenderers E-Tendering Training Acknowledgement Form.pdf
The Kusile Smart Plant Digitalisation and Artificial Intelligence Project is being procured by Eskom in Mpumalanga, with bids closing on 29 January 2027 at 10:00 South Africa Standard Time. Participation runs through Eskom's e-Tendering Solution, and the e-Tendering training acknowledgement is a mandatory returnable.
The procurement covers the Kusile Smart Plant Digitalisation and Artificial Intelligence Project. The requirements concern smart plant digitalisation and artificial intelligence. The procuring authority is Eskom in Mpumalanga.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Similar Tenders
Matched by category & region
Supplier Readiness Hub
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
Bid-ready summary. The submission guidelines, evaluation criteria, technical, financial, and compliance sections are refined into professional, easy-to-scan prose. This is the final version you can rely on when preparing your bid or briefing your team.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Document read
Compliance review
Bid-ready summary
Eskom requires delivery of the Kusile Smart Plant Digitalisation and Artificial Intelligence project — a phased, five-pillar digitalisation programme covering network and infrastructure, intelligent inspection and digital integration, a digital twin interface, paperless operations integrated with SAP PM/MM, and digitisation of existing plant documents and data books. The contractor must meet the Kusile OHS specification as a minimum for the contract duration and remains solely accountable for its own and its appointed contractors' health and safety performance.
Contact Information
Source: Smart Plant Digitilisation SHE Spec .pdf (unknown)
Eskom contacts
Dorothy Mbonane — Eskom Contract's Manager
Mapuleng Kobo — Eskom Health and Safety Manager
Nkhetheni Ramukosi — Eskom Safety Officer
Project address
Kusile Power Station
R45 Kendal/Balmoral Road
Haartebeesfontein farm
Technical Specifications
Source: Smart Plant Digitilisation SHE Spec .pdf (unknown)
Scope of work
Design, procurement, implementation, integration, testing, training and handover of five integrated technology pillars, delivered in sequential phases.
Phase 1
Pillar 1: Network and infrastructure.
Pillar 2: Intelligent inspection and digital integration.
Pillar 3: Digital twin interface.
Phase 2
Pillar 4: Paperless operations (digitised routine work management) integrated with SAP PM/MM.
Pillar 5: Digitisation of existing plant documents and data books.
Deliverables
All hardware, software, professional services and training required for full operational capability.
Costing and deliverables to be phased.
Scope defined in the NEC contract; the contractor must retain a copy.
Support
Ongoing operational support beyond the initial three-month post-go-live period is excluded and handled under separate service level agreements.
Site
Kusile Power Station, R45 Kendal/Balmoral Road, Haartebeesfontein farm.
Methodology
Source: Smart Plant Digitilisation SHE Spec .pdf
Method statements
Safe work procedures and method statements must be prepared for the activities, addressing the hazards identified in the risk assessment.
Experience & Qualifications
Source: Smart Plant Digitilisation SHE Spec .pdf
Competency and training
Appoint competent staff with the knowledge, training, experience and qualifications for the task.
Training must cover the type of work and relevant procedures; employees must work under competent supervision.
Statutory and Eskom-recommended appointees must be trained before accepting appointment.
The main contractor must meet the same training requirements when bidding, and ensure appointed contractors do too.
Quality Management
Source: Smart Plant Digitilisation SHE Spec .pdf
Organogram
The main contractor must submit a signed organogram on company letterhead showing the chain of responsibility from the CE to contract supervisors, listing positions, names and legal appointments, signed by the 16(1) or 16(2) appointee.
Appointed contractors must provide equivalent organograms to the main contractor.
Organograms must be updated when appointments change and filed in the project OHS file.
Substance abuse
0% alcohol and drug tolerance; ad hoc testing on site.
Contractors may run their own testing; results marked confidential and kept on the employee's file.
All workers must sign the life-saving rules pledge before starting work.
Roles
Contractors carry accountability for the safety of their employees and appointed contractors, keep an employee record (induction, skills, licences), coordinate appointed contractors, and stop unsafe work.
Financial Requirements
Source: Smart Plant Digitilisation SHE Spec .pdf (unknown)
OHS costing
All OHS costs must be itemised on the bill of quantities, covering safety training, PPE, safety equipment and medical surveillance.
Compliance Requirements
Source: Smart Plant Digitilisation SHE Spec .pdf (unknown)
OHS compliance (contract stage)
Comply with the OHS Act and Regulations, NEMA, National Water Act, Environment Conservation Act, National Road Traffic Act, COID Act and applicable SANS standards.
Keep an up-to-date copy of the OHS Act and regulations available to all employees.
Sign a Section 37(2) agreement with Eskom at submission of the safety file, and with all appointed contractors.
Register with the Compensation Commissioner and hold a valid Letter of Good Standing for the full contract period.
Compile and sign an organisational SHEQ policy compliant with OHS Act Section 7 and ISO 45001:2018 clause 5.2.
Appoint statutory and non-statutory competent persons (16.2 appointee, first aiders, incident investigator, risk assessor, safety officer, working-at-heights and fall-protection planners, among others).
Maintain an OHS file per work site and a medical surveillance programme for the contract duration.
No child labour.
Zero-tolerance life-saving rules and 0% alcohol/drug tolerance apply.
Health & Safety
Source: Smart Plant Digitilisation SHE Spec .pdf
OHS specification (minimum requirements)
The contractor must develop an OHS plan meeting this specification and all applicable legislation; Eskom does not assume the contractor's legal liabilities.
SHEQ policy
Signed by the CE or 16(2) appointee, displayed in the workplace, filed in the OHS file and annexed to the OHS plan; compliant with OHS Act Section 7 and ISO 45001:2018 clause 5.2.
Coid
Valid Letter of Good Standing from the Compensation Commissioner, kept valid for the contract and filed in the OHS file.
Life-saving rules (zero tolerance)
Isolate, test, earth and bond before touching plant above 1000 V.
Fall protection when working at height.
Seat belts for all vehicle occupants.
Be sober — 0% alcohol and drugs.
Valid permit to work where required.
Safe live working.
No reversing without a spotter or flagman.
Breach is serious misconduct, potentially dismissal.
Risk and medical
Baseline risk assessment reviewed by a competent person before work; daily pre-task risk assessments documented.
Medical surveillance programme maintained for the contract.
Safe work procedures and method statements for identified hazards.
OHS file per work site.
Working environment
Requirements cover working at heights, confined spaces, scaffolding, hazardous chemical agents, fire equipment, first aid, PPE, housekeeping, stacking and storage, vehicle management, site roads, signage, and emergency management.
Environmental
Source: Smart Plant Digitilisation SHE Spec .pdf
Environmental duty of care
Comply with NEMA, the Environment Conservation Act, the National Water Act and applicable municipal by-laws.
Anyone causing or likely to cause pollution must take reasonable measures to prevent, minimise and rectify it.
Contractual Terms
Source: Smart Plant Digitilisation SHE Spec .pdf
Statutory appointments
The main contractor and appointed contractors must appoint competent persons in line with the OHS Act, after confirming they have the training and information needed for the role.
Required statutory appointments include: incident investigator (GAR 9(2)); first aiders (GSR 3(4), first aid unit standard 119567); 16.2 appointee (legal liability and OHS Act training); portable gas container inspector (Pressure Equipment Regulations 11 and 12); competent person for stacking and storage (GSR 8(a)).
Non-statutory appointments
Site supervisor (OHS Act and legal liability, HIRA, supervisory safety, planned job observation), risk assessor (HIRA), safety officer, working-at-heights planner, hazardous chemical agent coordinator, fall protection planner, emergency planning coordinator, health and safety committee chairperson, fire equipment inspector, and vehicle and mobile plant inspector.
DocumentSupplier Declaration of Interest Template (1).docxReview complete
Submission Guidelines
Source: Supplier Declaration of Interest Template (1).docx (unknown)
Returnable form
Eskom Supplier Declaration of Interest (file 240-59385360, Rev 3) must be completed, signed and submitted with the bid.
The declaration covers conflicts of interest, Eskom private work, close family or associate connections, business courtesies, and other services provided to Eskom by consultants.
Evaluation Criteria
Source: Supplier Declaration of Interest Template (1).docx (unknown)
Mandatory returnable
The signed Supplier Declaration of Interest must be included with the bid.
False declarations may lead to action against the supplier or the signatory.
Compliance Requirements
Source: Supplier Declaration of Interest Template (1).docx (unknown)
Conflict-of-interest compliance
Bidders must disclose whether they or any interested person are employed by Eskom or serve as an Eskom director.
Bidders must disclose close family or associate relationships with Eskom employees or directors who may participate in the procurement.
Bidders must disclose business courtesies given or received from Eskom employees or directors during the previous 12 months.
Consultants must list other services currently rendered to Eskom business units, divisions, subsidiaries, primary energy suppliers, strategic commodity suppliers or key industrial customers.
DocumentC3 1 ECC3 Employers Works Information_SPP_29.09.2026.docxReview complete
Description
Source: C3 1 ECC3 Employers Works Information_SPP_29.09.2026.docx
General scope
The project digitises Kusile Power Station through smart plant and AI capabilities.
It establishes secure industrial connectivity, intelligent inspection, Digital Twin integration, mobile work management, EDMS document control and governed analytics.
It supports paperless field execution, predictive maintenance, technical document control, decision support and sustainable internal capability.
The Contractor must provide design, supply, construction, testing, commissioning, training and knowledge transfer for the digital ecosystem.
Submission Guidelines
Source: C3 1 ECC3 Employers Works Information_SPP_29.09.2026.docx (unknown)
Returnable tender items
Organogram: project team, key personnel, reporting lines, responsibilities and communication lines.
Designated subcontracting: Letters of Intent from proposed subcontractors for eligible works, including Preliminaries and General and cabling-related packages.
B-BBEE: supporting documentation required by the Invitation to Tender.
Responsiveness risk
Missing Letters of Intent for designated subcontracting may make the bid non-responsive on that requirement.
Evaluation Criteria
Source: C3 1 ECC3 Employers Works Information_SPP_29.09.2026.docx (unknown)
Mandatory evaluation and responsiveness points
Designated-area subcontracting: minimum 15% of contract value.
B-BBEE: compliance with Invitation to Tender requirements and supporting evidence.
Subcontractor commitment: Letters of Intent for identified designated-area works; omission may render the bid non-responsive.
Technical Specifications
Source: C3 1 ECC3 Employers Works Information_SPP_29.09.2026.docx (unknown)
Scope
Smart plant digitalisation and artificial intelligence project at Kusile Power Station.
Station comprises six generating units of about 800 MW each, with total installed capacity of 4 800 MW.
The works create a governed digital environment for real-time and near-real-time data access, paperless field work, AI-assisted inspection, controlled document retrieval, auditability and technology transfer.
Strategic outcomes
Improve operational efficiency, reliability and predictive maintenance through integrated data, Digital Twin interfaces, intelligent inspection and SAP PM/MM maintenance workflows.
Strengthen safety, security and compliance through AI-enabled inspection, real-time monitoring, cyber-secure deployment, POPIA-aligned data handling and auditable evidence.
Provide trusted data flows across operational, maintenance, EDMS, inspection, dashboard and analytics systems.
Deliver scalable, resilient, standards-based private cloud, network, storage and integration infrastructure using open standards, documented APIs and anti-lock-in design.
Register, risk-assess, validate, monitor and revalidate AI capabilities under responsible AI governance, with human accountability, model provenance, lifecycle evidence and incident escalation.
Preserve knowledge and transfer skills through structured training, handover, documentation and an AI apprenticeship programme.
Design and engineering
Contractor designs the works to Functional Specification KUS-20251198 and acts as Design Authority under Design Review Procedure 240-53113685.
Design submissions must include drawings, calculations and reports; Employer review does not transfer design responsibility.
Plant and documentation must use KKS coding to at least breakdown level 3, unless otherwise approved, and labels or nameplates must meet Eskom Standard 240-71432150.
Contractor provides all plant, equipment, tools, temporary works, materials and resources needed for completion.
As-built drawings must reflect final works across disciplines and be provided in DGN/DWG and PDF/native CAD formats, with hard copy where required.
Operating and maintenance manuals must meet SANS 6750 and include manufacturer data, drawings, safety instructions, operating procedures, maintenance schedules, troubleshooting, storage instructions and spare parts lists.
Procurement and testing
Contractor procures, transports, stores, protects and installs plant and materials, and ensures suppliers and subcontractors comply with contract requirements.
Priced spare parts schedules must include descriptions, part numbers, unit rates, stock quantities and technical data.
Inspection and Test Plans, factory inspections, Factory Acceptance Tests, performance tests and Site Acceptance Tests are required before delivery, commissioning and completion.
Employer must receive at least 3 working days' notice for factory, off-site or witness tests.
No plant or materials may be dispatched without required inspections or written acceptance; failed items must be rectified and retested.
Employer witnessing does not transfer responsibility for equipment functionality.
Construction and site controls
Site access requires prior notification, security gate reporting, induction, permits, Worker Register registration and valid identification.
All personnel must follow Eskom Lifesaving Rules, OHS Act 85 of 1993, Construction Regulations, plant-specific risk assessments and permit-to-work requirements.
Normal working hours are Monday to Thursday 07:00 to 16:30 and Friday 07:00 to 12:00; overtime needs prior approval and authorised timesheets.
Weekly timesheets must be submitted for verification and retained for audit.
Contractor must protect existing underground services, scan before excavation, obtain excavation permits, control water and comply with SANS 1200 series and SANS 2001 BE1.
Contractor must control noise, dust, water and waste, manage temporary works, remove equipment promptly and keep working areas safe.
Hook-ups to existing plant require permits, isolations and coordination with the Employer and Others.
Photographs may not be used externally without written approval; progress photographs must be kept and provided as required.
Employer and Contractor facilities
Employer may provide water, electricity, waste disposal facilities and access to available site facilities such as canteens, subject to availability and site rules.
Contractor must provide PPE, site offices, parking, lighting, water storage, material storage, first-aid and firefighting equipment, ablution facilities, temporary fencing or access control and staff transport.
Programme, training and handover
Programme must be submitted in Primavera P6 or MS Project and show start date, access dates, key dates, completion date, sequencing, float, time risk allowances, health and safety provisions and training or knowledge transfer.
Contractor must embed Employer-nominated personnel in workstreams and provide access to plants where similar technologies are deployed.
Training must include mentoring, workshops, configuration walkthroughs, design reviews, model management, troubleshooting, system administration and train-the-trainer.
Learning pathways must cover executives, managers, engineers, technicians, operators, maintenance staff, ICT specialists, data analysts and system administrators.
Structured knowledge transfer must continue for at least 12 months during implementation and include post-go-live support and shadowing with measurable handover acceptance criteria.
Financial Requirements
Source: C3 1 ECC3 Employers Works Information_SPP_29.09.2026.docx (unknown)
Payment and invoicing
Tax invoice due within one week of receiving the Project Manager's payment certificate.
Invoice addressed to Eskom Holdings SOC Ltd and must include contractor and Project Manager names and addresses, contract number and title, contractor VAT number, Employer VAT number 4740101508, service description per Price List, amount excluding VAT, VAT amount and total including VAT.
Send invoice to [email protected] after confirming it matches the payment certificate.
Bonds and guarantees
Governed by C1 3 ECC3 Proforma Guarantees.
Insurance
Employer-provided insurance is as stated in the Contract Data.
Compliance Requirements
Source: C3 1 ECC3 Employers Works Information_SPP_29.09.2026.docx (unknown)
Contract and compliance
NEC3 ECC Option A applies; contractual communications and change management must use NEC3 ECC forms or letters.
B-bbee
Comply with B-BBEE requirements in the Invitation to Tender and submit supporting documentation.
Designated subcontracting and labour
Subcontract at least 15% of contract value to enterprises from designated areas.
Provide Letters of Intent for identified designated-area subcontract works, including Preliminaries and General and cabling-related packages.
Labour utilisation from designated areas will be communicated at the clarification meeting; bidders must provide for compliance.
SHEQ and site legal compliance
Develop and implement a SHEQ Plan and comply with OHS Specification KUS-20260463.
Appoint OHS personnel in writing as required by OHS Act 85 of 1993 and Factories Regulations.
Comply with Construction Regulations, Eskom Lifesaving Rules, site induction, permits, Worker Register and plant-specific risk assessments.
Data, AI and intellectual property
Align with Eskom ownership, data sovereignty, AI lifecycle governance, audit traceability, cyber-secure deployment, human accountability and structured knowledge transfer.
Register, risk-assess, validate, monitor and revalidate AI capabilities under Responsible AI governance.
Handle data in line with POPIA.
Subcontractors
Contractor remains responsible for selection, appointment, management and performance of subcontractors; subcontractors must comply with scope and contract conditions.
Kusile Power Station OHS baseline risk assessment: revision 5, dated 30 April 2025, under procedure 32-520.
Assessed activities include conveyor and chute cleaning, conditioner unblocking, ash and gypsum conveying, ash dump operations, mobile plant and vehicle movements, coal stockpiling and offloading, weighbridge operations, water and wastewater treatment, sampling, laboratory work and general administrative work.
Each activity records hazard identification, consequence and likelihood rating, existing controls, additional preventative and reactive controls, control owner, legal or other requirements, and medical surveillance where applicable.
OHS legal and other references include Occupational Health and Safety Act sections 8(2)(c) and 8(2)(e), General Safety Regulation 2, ERW 3 and 4, work instructions 240-85246142 and 240-85428463, medical surveillance procedure 32-285 and risk assessment procedure 32-520.
OHS baseline risk assessment: revision 5, dated 30 April 2025; refers to procedure 32-520.
The assessment records hazards, possible consequences, existing controls, additional preventative and reactive controls, control owner, legal or other requirements and priority.
Controls include elimination, substitution, engineering controls, administrative controls and PPE.
Medical surveillance, incident reporting, defect reporting, plant inspections, planned task observations, SMAT, toolbox talks and pre-job briefs are listed.
Specific OHS references include OHS Act sections 8(2)(c) and 8(2)(e), GSR 2, ERW 3 and 4, work instructions 240-85246142 and 240-85428463, and medical surveillance procedure 32-285.
Screen cleaning and removal of sludge to waste skips require respiratory protection and controls for biological agents and water-borne pathogens; medical surveillance under procedure 32-285 and defect reporting apply.
Works: design, execution, commissioning, handover and training for the Kusile Power Station Smart Plant Digitalisation and Artificial Intelligence Project.
Contract pack is split into four parts:
Part C1 — Agreements and Contract Data: form of offer and acceptance (C1.1), contract data supplied by the employer (C1.2a), contract data to be supplied by the contractor (C1.2b), proforma guarantees (C1.3).
Part C2 — Pricing Data.
Part C3 — Scope of Work.
Part C4 — Site Information.
Contract number: to be allocated.
Detailed scope, quantities, deliverables and site particulars are carried in Parts C3 and C4.
Contract form: NEC3 Engineering and Construction Contract (ECC3), Part C1 (Agreements and Contract Data).
Employer: Eskom Holdings SOC Ltd, registration number 2002/015527/30.
Contractor: registration number to be inserted in the agreement.
Contractor's contract data: to be completed by the bidder at C1.2b; C1.2a is completed by the employer.
DocumentAuthorisation Form.pdfReview complete
Submission Guidelines
Source: Authorisation Form.pdf (unknown)
Returnable document
The Authorisation Form (Eskom form 240-15811258) must be completed, signed by the tenderer's authorised representative, and submitted with the bid, together with the certificate and supporting resolution that match the tenderer's legal form.
Compliance Requirements
Source: Authorisation Form.pdf (unknown)
Authorisation of signatory
The tenderer must indicate its legal category: company, close corporation, joint venture, sole proprietor or partnership.
The individual signing the tender must be legally empowered to bind the organisation, and this authority must be evidenced.
Proof of authority to sign (attach the certificate for the chosen category)
Company: board resolution authorising the named signatory, with a certified copy attached.
Close corporation: members' resolution passed by majority vote, with a certified copy attached.
Joint venture: power of attorney signed by the authorised signatories of all members.
Partnership: authorisation signed by all partners required to commit the partnership.
Sole proprietor: declaration confirming sole ownership of the business.
Joint venture additional requirements
Attach the JV Agreement, which must record joint and several liability of all members, identify the lead member, and set out the ratios for dividing work and payment.
Signatory details (all tenderers)
Complete the signatory table: tenderer name, full names of the authorised signatory, designation and capacity, signature and date.
DocumentSBD 6.1.pdfReview complete
Submission Guidelines
Source: SBD 6.1.pdf (TENDER)
Returnable forms (complete, sign and submit with the bid):
SBD 6.1 Preference Points Claim Form: records the B-BBEE status level claimed, any subcontracting and the bidder's company particulars; signing commits the bidder to the truth of those claims.
Proof of B-BBEE status level of contributor must accompany the bid; if it is not submitted, no B-BBEE preference points are claimed.
The purchaser may require substantiation of any preference claim before adjudication or at any time afterwards.
Evaluation Criteria
Source: SBD 6.1.pdf (TENDER)
Preference points (SBD 6.1):
Points are awarded for price and B-BBEE status level of contributor; the combined total must not exceed 100.
80/20 system applies to requirements up to R50 million (tax included); 90/10 applies above R50 million. The form does not indicate which system applies to this bid (left blank).
Price points: maximum 80 (80/20) or 90 (90/10), calculated against the lowest acceptable bid price.
B-BBEE proof: certificate from an authorised body, sworn affidavit as prescribed by the B-BBEE Codes, or other requirement under the B-BBEE Act.
Subcontracting disclosure, if any portion is subcontracted: percentage of the contract, subcontractor name, B-BBEE status level, EME/QSE status and designated-group category (black people, youth, women, people with disabilities, rural or underdeveloped areas and townships, cooperatives, military veterans).
Company particulars: name, VAT registration number, company registration number, type of company, principal business activities, classification (manufacturer, supplier, professional service provider, other service provider) and years in business.
Consequences of fraudulent or unsubstantiated claims: disqualification, recovery of costs, losses or damages, cancellation of the contract with damages, recommendation to National Treasury for restriction from state business for up to 10 years, and criminal prosecution.
Section
Source: SBD 6.1.pdf
Preference point claim (SBD 6.1):
Points are awarded only for price and B-BBEE status level of contributor; total must not exceed 100.
Price points: Ps = 80 x (1 - (Pt - Pmin)/Pmin) under the 80/20 system, or Ps = 90 x (1 - (Pt - Pmin)/Pmin) under the 90/10 system, where Pt is the bid price and Pmin the lowest acceptable bid price.
Points claimed must be substantiated by proof of B-BBEE status level of contributor.
Document240-77471499 Annexure B 2026.docxReview complete
Description
Source: 240-77471499 Annexure B 2026.docx
Annexure B is an acknowledgement form for Eskom OHS legal and other requirements. It requires the bidder to confirm receipt and understanding of the listed OHS documents and to accept responsibility for compliance and the consequences of non-compliance.
Submission Guidelines
Source: 240-77471499 Annexure B 2026.docx (unknown)
Returnable document
Annexure B: Acknowledgement Form for Eskom OHS legal and other requirements, signed by an authorised person, confirming that the bidder has obtained and understands the OHS requirements and accepts the consequences of non-compliance.
Compliance Requirements
Source: 240-77471499 Annexure B 2026.docx (unknown)
OHS legal and contractual compliance
Bidders must comply with Eskom contractor Health and Safety requirements standards 32-136, any OHS specification or requirements provided, the Occupational Health and Safety Act 85 of 1993, and the Compensation for Occupational Diseases and Illnesses Act 130 of 1993.
After contract award, the supplier must align its processes with Eskom OHS policies, procedures and standards.
Penalties may be enforced against the main supplier for OHS non-conformance by the main supplier or its contractors/suppliers.
All contractor/supplier employees must complete the relevant Eskom induction and the supplier's induction.
The main supplier must demonstrate its contractor/supplier selection process and criteria, notify Eskom before appointing contractors/suppliers, ensure they have adequate resources and competencies, and remain accountable for their OHS compliance.
The main supplier must monitor contractors/suppliers through OHS audits and assessments, provide grounds for termination of contractor/supplier work, and manage non-conformances through performance and penalty processes.
Eskom may verify compliance and request testimonials, references and client contact details for similar previous work.
DocumentC1 2a ECC3 Data by Employer_SPP_29.09.2026.docxReview complete
Important Dates
Source: C1 2a ECC3 Data by Employer_SPP_29.09.2026.docx (unknown)
Contract milestones
Starting date: 01 April 2027.
Access to site: Contract Date, at Kusile Power Station.
First programme for acceptance: within 3 weeks of the Contract Date.
Revised programmes: at intervals no longer than 2 weeks.
Completion date for the whole of the works: to be confirmed.
Key dates (conditions to be met)
Project Plan submitted for acceptance: 3 weeks after the project kick-off meeting in the key dates table, 4 weeks after kick-off in the sectional completion table.
Safety File submitted for Employer approval: 4 weeks after the project kick-off meeting in the key dates table, 6 weeks after kick-off in the sectional completion table.
Final detailed design submitted for approval: per the accepted project plan.
Pillar 1 to Pillar 5 execution completion: per the accepted project plan.
Technology transfer and training: per the accepted project plan.
Defects
Defects date: 52 weeks after sectional completion.
Defect correction period: 2 days after notification of a defect.
Contact Information
Source: C1 2a ECC3 Data by Employer_SPP_29.09.2026.docx (unknown)
No contact names, email addresses or telephone numbers are recorded for the Project Manager or Supervisor.
Technical Specifications
Source: C1 2a ECC3 Data by Employer_SPP_29.09.2026.docx (unknown)
Scope
Design, execution, commissioning, handover and training for the Kusile Power Station Smart Plant Digitalisation and Artificial Intelligence project.
Site: Kusile Power Station, R545 Balmoral/Kendal Road, Haartebeesfontein Farm, Witbank.
Works Information: Part 3, Scope of Work, together with all documents and drawings it references.
Site Information: Part 4.
Delivery structure
Works are split into five execution pillars, each with its own completion milestone.
Sectional completion applies, with separate completion dates for the project plan, safety file, final detailed design, each of the five pillars, and technology transfer and training.
Technology transfer and training is a defined deliverable, not an add-on.
Contractor obligations
Submit a first programme within 3 weeks of the Contract Date and revised programmes at least every 2 weeks.
Compile and manage a risk register, starting with a risk identification and assessment meeting held after contract award.
Respond to communications within 24 hours during outages and emergencies, and within 3 working days during normal operations.
Correct notified defects within 2 days.
Contract framework
NEC3 Engineering and Construction Contract, April 2013, main Option A (priced contract with activity schedule).
Secondary options: W1 dispute resolution, X1 price adjustment for inflation, X2 changes in law, X3 multiple currencies, X5 sectional completion, X7 delay damages, X13 performance bond, X16 retention, X18 limitation of liability, plus additional conditions Z1 to Z17.
Governing law: Republic of South Africa. Contract language: English. Currency: South African Rand.
Financial Requirements
Source: C1 2a ECC3 Data by Employer_SPP_29.09.2026.docx (unknown)
Payment
Assessment interval: monthly, measured to the 25th day of each successive month.
Payment period: 30 calendar days after both parties sign the assessment and a valid tax invoice is received.
Eskom policy for contracts valued above R50 000 000 including VAT: payment term of 60 days. Bidders must price and plan on this basis.
Late payment interest: publicly quoted prime rate of Standard Bank of South Africa, calculated on a 365-day year.
Securities and deductions
Performance bond: 10% of the total contract value.
Retention: 5% of each payment certificate value.
Delay damages
Project Plan milestone: 0.01% of Total Prices per day.
Safety file, final detailed design, Pillar 1 to Pillar 5 and technology transfer and training: 0.02% of Total Prices per week.
Remainder of the works: 0.1% of Total Prices per day.
Total delay damages capped at 10% of Total Prices.
Price adjustment
Contract price adjustment applies 16 months after the base date.
Base date for indices: one month before the tender closing date.
Non-adjustable proportion: 0.15 of the price adjustment factor.
Liability
Liability for indirect or consequential loss: R0.00.
Liability for loss or damage to Employer property per event: limited to the applicable insurance deductibles.
Total liability: limited to the Total Prices, except for design defects arising before the defects certificate, manufacturing and fabrication defects outside site, property damage, death or injury, and intellectual property infringement, which are uncapped.
End of liability: 5 years after the defects date for latent defects; otherwise the date prescription applies under the Prescription Act 68 of 1969.
Compliance Requirements
Source: C1 2a ECC3 Data by Employer_SPP_29.09.2026.docx (unknown)
B-bbee
The contractor must notify the Employer within 7 days of any change to its B-BBEE status.
An updated verification certificate and supporting documents must reach the Project Manager within 30 days of that notification.
A drop in B-BBEE status entitles the Employer to renegotiate or terminate; failure to notify is itself grounds for termination.
Contractor structure
Joint ventures, consortia and other unincorporated groupings carry joint and several liability.
The grouping must name the person authorised to bind it to the Project Manager within 2 weeks of the Contract Date.
The composition of a grouping may not change without the Employer's written consent.
Contract administration
No cession, delegation or assignment of rights or obligations without the Employer's written consent. The Employer may transfer its own rights to Eskom subsidiaries or restructured electricity supply entities on written notice.
All information arising from the contract is confidential; where status is uncertain, information is treated as confidential until the Project Manager decides otherwise.
Lawful disclosure compelled by law requires prior notice to the Employer so a protective order can be sought.
Dispute resolution
Adjudication through a person selected from the ICE-SA Division panel of the South African Institution of Civil Engineering; if the parties cannot agree, ICE-SA appoints.
Arbitration seat: Johannesburg, under the Association of Arbitrators (Southern Africa) rules; the Association's chairman selects the arbitrator if the parties cannot agree.
DocumentE-Tenderers E-Tendering Training Acknowledgement Form.pdfReview complete
Submission Guidelines
Source: E-Tenderers E-Tendering Training Acknowledgement Form.pdf (unknown)
Mandatory returnable: E-Tendering Training Acknowledgement Form.
The form must be fully completed and submitted to the procuring entity within the prescribed period.
Failure to submit the completed form on time renders the tenderer non-responsive and disqualifies it from the procurement process.
Evaluation Criteria
Source: E-Tenderers E-Tendering Training Acknowledgement Form.pdf (unknown)
Responsiveness requirement: failure to fully complete and submit the E-Tendering Training Acknowledgement Form within the prescribed period renders the tenderer non-responsive and disqualifies it from the procurement process.
Compliance Requirements
Source: E-Tenderers E-Tendering Training Acknowledgement Form.pdf (unknown)
E-Tendering capability: the tenderer must confirm that it has completed self-training using the e-Tendering Noddy Guide, video, or a clarification meeting and can operate the E-Tendering Solution.
Mandatory acknowledgement: a fully completed E-Tendering Training Acknowledgement Form must be submitted within the prescribed period.
Consequence: failure to fully complete and submit the form renders the tenderer non-responsive and disqualifies it from the procurement process.
DocumentAnnexure A - Technical Evaluation Criteria_Rev6.xlsxReview complete
Description
Source: Annexure A - Technical Evaluation Criteria_Rev6.xlsx
Kusile Smart Plant Digitalisation and Artificial Intelligence — a multi-workstream programme to convert the Kusile power station into a smart plant.
Scope spans engineering and operational systems, digital platforms, data infrastructure, digital-twin capability, analytics and AI.
Delivered through five pillars:
Pillar 1, Network & Infrastructure: the connectivity foundation for all other technologies.
Pillar 2, Intelligent Inspection & Digital Integration: sensing, AI analytics, the IOC and collaboration tools.
Pillar 3, Digital Twin Interface: interoperability with the existing EPRI Program 224 Digital Twin.
Pillar 4, Paperless Operations: mobile maintenance with SAP PM/MM integration.
Pillar 5, Document & Data Book Digitisation: scanning, OCR and an EDMS.
Delivery must be coordinated and controlled against the approved scope, budget, quality requirements and agreed timelines.
Submission Guidelines
Source: Annexure A - Technical Evaluation Criteria_Rev6.xlsx (unknown)
Technical returnable
The technical evaluation workbook (Annexure A) is the returnable; every sheet must be completed.
Each requirement line needs a supplier compliance statement, a reference (file, page and section) and any justification or motivation the criterion calls for.
Disqualification risks
Not fully meeting any single mandatory requirement ends the bid at the evaluation stage.
Sheets left incomplete, or responses submitted without the required references and motivations.
Evaluation Criteria
Source: Annexure A - Technical Evaluation Criteria_Rev6.xlsx (unknown)
Functional evaluation — three gates, all of which must be passed to proceed
Gate 1: full compliance with every mandatory requirement.
Gate 2: a score of at least 75% of the maximum available for each individual pillar.
Gate 3: qualifying bidders must present a successfully implemented, operational equivalent solution already in deployment.
Failing any gate results in disqualification.
Technical scoring split (100 points total)
Schedule: 5%
Pillar 1 (Network & Infrastructure): 35%
Pillar 2 (Intelligent Inspection & Digital Integration): 20%
Pillar 3 (Digital Twin Interface): 10%
Pillar 4 (Paperless Operations): 15%
Pillar 5 (Document & Data Book Digitisation): 15%
Qualitative scoring scale (applied per requirement)
5 = 100% Compliant: meets the requirement with no foreseen technical risk.
4 = 80% Compliant with qualifications: meets it with acceptable risk, exceptions or conditions.
2 = 40% Non-compliant: fails the requirement, or carries unacceptable risk, exceptions or conditions.
0 = 0% Totally deficient or non-responsive.
Requirement priorities
Each line is graded Show Stopper, Critical, Important or Nice to Have, which drives its weighting.
Award approach
Eskom prefers to appoint a single supplier but may split the award across one or more suppliers.
Preference goes to bids where Pillars 1, 2 and 4 are delivered by one supplier, for an integrated solution with clear accountability.
A supplier bidding a single pillar carries all integration work and cost needed to fit the other pillars and the overall solution.
Technical Specifications
Source: Annexure A - Technical Evaluation Criteria_Rev6.xlsx (unknown)
Scope — five pillars of the Kusile smart-plant digitalisation
Pillar 1, Network & Infrastructure: industrial-grade wireless network, secure backhaul, cybersecurity aligned to IEC 62443, and a private-cloud platform (compute, storage, networking) with high availability and disaster recovery.
Pillar 2, Intelligent Inspection & Digital Integration: sensing devices, AI analytics, the intelligent inspection system and Intelligent Operations Centre (IOC); plus smart safety helmets, video/voice collaboration and intelligent meeting terminals.
Pillar 3, Digital Twin Interface: standardised, low-latency interoperability with the existing Digital Twin built under EPRI Program 224.
Pillar 4, Paperless Operations: a mobile-first maintenance application with two-way SAP PM/MM integration and digital outage management, covering the full routine work-management cycle from work-order creation to close-out.
Pillar 5, Document & Data Book Digitisation: scanning, OCR, metadata tagging, quality assurance and an Enterprise Document Management System (EDMS).
Pillar 1 detailed requirements (each line graded Show Stopper / Critical / Important)
Industrial access network
Industrial switches: PoE++, minimum 8 x Gigabit Ethernet and 4 x 10 Gigabit optical ports; -40 to +75 degrees C, IP40; MRP/ERPS/SEP ring protocols with failover under 20 ms.
Outdoor access points: 1/2.5 GE port with PoE+/PoE++ and MACsec plus a 10GE SFP+ port; IP68, -40 to +70 degrees C; 802.11a/b/g/n/ac/ax/be with aggregate throughput of at least 6.45 Gbps; terminal eavesdropping protection; directional and omni antenna options.
Access switches: at least 24 x 2.5GE Base-T and 8 x 25GE SFP28 ports, PoE++ up to 90 W; power-loss alarm on AC failure; MACsec, VXLAN and RIP/OSPF/IS-IS/BGP.
Aggregation and core
Aggregation switches: MACsec, at least 28 x 10GE SFP+ and 6 x 40/100GE QSFP28 ports; 1+1 redundant power; G.8032 ERPS and M-LAG.
Core chassis switches: dual control units, dual fans and dual power; at least 48 x 10/100/1000BASE-T, 48 x SFP+ and 32 x 40GE QSFP+ ports; switching capacity of at least 8 Tbps; VXLAN; RIP/OSPF/IS-IS/BGP.
Wireless access controller: manages at least 3,000 APs with forwarding of at least 50 Gbps; 802.11n/ac/ax/be; pluggable power modules.
Data centre switching
Spine switches: at least 128 x 100GE ports with at least 32 x 100G QSFP28 transceivers; hardware-based BFD at 3.3 ms; telemetry; VXLAN and BGP EVPN. Breakout cables do not count toward the port minimums.
Core switches: at least 64 x 100GE ports with at least 24 x 100G transceivers; same BFD, telemetry and VXLAN/EVPN requirements.
Leaf switches: at least 8 x 100GE and 48 x 25GE ports with at least 6 x 100G transceivers.
BMC switches: at least 48 x GE RJ45 and 4 x 10GE ports.
Network management
Visualises physical, logical and application topologies; telemetry-based health checks; single-node deployment with authentication and provisioning; rogue-AP/terminal detection (WIDS/WIPS); configuration comparison; role-based administration; RRM/FTM self-optimisation; GIS-based operations.
Must run on-premises inside Eskom's environment; public-cloud hosting or operation is not accepted.
Capacity, redundancy and integration
Support at least 500 concurrent devices: at least 100 handheld maintenance devices, more than 50 IP cameras, more than 200 IoT sensors and at least 150 access points or Wi-Fi devices.
Dual backhaul with automatic failover and a self-healing mesh topology.
Integrate with the plant's existing network, Wi-Fi and monitoring/supervisory systems via a secure interconnection interface and a dedicated integration channel.
Cybersecurity
Zero-trust security architecture across the network.
Border firewall: threat-protection throughput of at least 14 Gbps (FW/SA/IPS/AV, Enterprise Mix); at least 2 x 100GE, 2 x 40GE, 8 x 25GE and 20 x 10GE ports; at least 50,000,000 concurrent connections and 160,000 security policies.
Backhaul and microwave
Minimum aggregate backhaul of 1 Gbps with QoS prioritisation.
Point-to-point microwave: fully outdoor, 7 to 38 GHz, switching capacity of at least 60 Gbps, dual RF ports with carrier aggregation, XPIC.
Software licensing
Network management software and firewall security software (IDS/IPS), each with a valid three-year licence.
Cloud servers (minimum specifications)
Management node servers x3: 2 x 64-core CPUs, 24 x 64 GB RAM, 2 x 25GE, 2 x 960 GB SSD system disks and 8 x 7.68 TB NVMe data disks.
Network node servers x2: 2 x 48-core CPUs, 16 x 32 GB RAM, 6 x 10GE, 2 x 480 GB SSD.
BMS server: 2 x 64-core CPUs, 16 x 32 GB RAM, 4 x 10GE, 2 x 480 GB SSD and 6 x 1.8 TB SAS.
Virtual machines (minimum vCPU / RAM): CNKI 72 / 192 GB; IOC 64 / 128 GB; Intelligent Inspection 32 / 64 GB; VMS 224 / 448 GB; ISDP 128 / 480 GB; Historian data-warehouse x3 96 / 1024 GB; Master Data x2 96 / 512 GB; ETL 40 / 512 GB; Async Data Transformation 40 / 512 GB; Orchestration 64 / 512 GB; Performance Monitoring x2 32 / 128 GB; RabbitMQ x2 64 / 512 GB; API Gateway 20 / 64 GB; API Authentication 64 / 128 GB; API Analytical 40 / 128 GB. Each VM has 4 x 10GE interfaces and a 960 GB SSD system disk (200 GB for the historian, master-data, ETL, transformation, orchestration, monitoring, RabbitMQ and API servers).
Private cloud management software
Service catalogue with per-tenant visibility; self-service VM and storage management; SDN/VPC management (VPN, software load balancing, security groups, network ACLs, EIP, Direct Connect, VPC endpoints); Layer-2 bridging for VPC subnets; private CloudDNS (A/AAAA/CNAME/MX/TXT/SRV/PTR/NS/SOA); RBAC and multi-tenant authorisation.
Cloud storage
Bid brand must be a Gartner Peer Insights Customers' Choice for Primary Storage, with a current Voice of the Customer screenshot as evidence.
Symmetric active-active architecture; SAN/NAS/S3 convergence on a single controller; scalable to at least 32 controllers; non-disruptive upgrade and rollback.
Two controllers, at least 192 cores total at 2.6 GHz or higher, at least 1.5 TB L1 cache, dual-port enterprise NVMe SSDs, at least 200 TB usable.
RAID-TP tolerating three simultaneous disk failures; up to 60,000 snapshots per LUN and 1,000,000 per system, 3-second snapshot interval, secure SAN snapshots with 1 day to 20 year protection; built-in ransomware detection.
Video management and storage
Clustered platform for more than 10,000 video channels; IOC northbound integration; fibre-optic/optical-video alarm linkage with PTZ auto-direction and GIS mapping; configurable alarm linkage and handling; recording slicing into 20 segments over at least 30 days; third-party analytics alarm support.
Video storage: two 32-core processors at 2.6 GHz or higher, at least 64 GB RAM, dual 1.92 TB SAS SSD in RAID 1, 4 x GE and 4 x 10GE ports, at least 2,780 TB of video capacity.
DocumentC1 2b ECC3 Data by Contractor_SPP_29.09.2026.docxReview complete
Technical Specifications
Source: C1 2b ECC3 Data by Contractor_SPP_29.09.2026.docx (unknown)
Contract form
NEC3 Engineering and Construction Contract (April 2013), Option A: priced contract with activity schedule.
Contractor information required
Contractor name, address, telephone number and fax number.
Direct fee percentage and subcontracted fee percentage.
Working areas.
Key persons: name, job, responsibilities, qualifications, experience and CVs.
Completion date for the whole of the works.
Matters to be included in the Risk Register.
Works Information for the Contractor's design.
Activity schedule.
Shorter Schedule of Cost Components data, including people overheads, design overheads, equipment adjustment, other equipment rates and design hourly rates.
Financial Requirements
Source: C1 2b ECC3 Data by Contractor_SPP_29.09.2026.docx (unknown)
Pricing information required
Tendered total of the Prices, in figures and words, excluding VAT.
Direct fee percentage and subcontracted fee percentage.
People overheads percentage.
Design overheads percentage.
Adjustment percentage for equipment in the published list.
Rates for other equipment, with size or capacity.
Hourly rates for Defined Cost of design outside the Working Areas, by employee category.
Categories of design employees whose travelling expenses to and from the Working Areas are included in Defined Cost.
Compliance Requirements
Source: C1 2b ECC3 Data by Contractor_SPP_29.09.2026.docx (unknown)
Contract completion
The NEC3 Contract Data Part 2 must be completed in full according to the options selected.
Key-person CVs must be appended to the tender schedule.
Incomplete contract data may prevent a complete contract from being formed.
Procurement: Kusile Power Station Smart Plant Digitalisation and Artificial Intelligence Project, let by Eskom Holdings SOC Ltd as a works contract under the ECC3 conditions.
Contract structure:
Part C1 — Agreements and Contract Data, including the Form of Offer and Acceptance.
Prices are submitted under Part C2 (Pricing Data).
The offer must state the total price excluding VAT, VAT charged at 15%, and the total price including VAT.
Post-award security:
Within two weeks of receiving the signed agreement, the contractor must arrange delivery of all securities, bonds, guarantees and proof of insurance required by the contract.
Failing to provide these is treated as repudiation of the agreement.
CIDB: Where the tenderer is CIDB-registered, its CIDB registration number must be quoted.
DocumentEskom Standard Conditions of Tender.pdfReview complete
Contact Information
Source: Eskom Standard Conditions of Tender.pdf (TENDER)
Enquiries
Contact: Eskom Representative identified in the enquiry documents
Method: written communication only
Restriction: bidders may not direct queries to any other Eskom official
Clarifications
Requests must allow Eskom reasonable time to respond before the closing date
Eskom will publish anonymised queries and responses on the original advertising platforms
Submission Guidelines
Source: Eskom Standard Conditions of Tender.pdf (TENDER)
Submission
Channel: paper delivery to the Eskom tender box or other submission point stated in the tender data; fax or email is acceptable only where expressly permitted.
Copies: submit one complete original and one complete paper copy; mark the packages ORIGINAL and COPY; any required electronic copy must be separate and marked ELECTRONIC COPY.
Packaging: each inner package must show the Eskom submission address, invitation number, bidder name, physical address, email address and contact number of the authorised signatory; seal all packages in an outer package marked Confidential with the same details.
Completion: submit in English, complete in ink, sign the original, and initial any alterations.
Returnables: all evaluation returnables must be received by the closing deadline; award returnables must be provided before award; every form and schedule must be fully completed.
Acknowledgement Form: include it and state whether the bid is for the whole or only part of the required works, services or supply.
Agent bids: include an authenticated authority if an agent submits for a principal.
Disqualification risks: late receipt, missing original or copy, unsigned original, missing mandatory returnables, non-compliance with basic requirements, or failure to meet designated-material thresholds.
Evaluation Criteria
Source: Eskom Standard Conditions of Tender.pdf (TENDER)
Evaluation
Basic compliance: Eskom first checks whether the bid meets the enquiry's basic requirements; failure makes the bid non-responsive.
Mandatory returnables: missing mandatory documents or information by the deadline results in disqualification.
Designated materials: failure to meet stipulated local-content or designated-material requirements results in disqualification.
Functionality: where functionality applies, bidders are scored and must reach the minimum threshold stated in the tender data to continue.
Financial risk: Eskom may exclude a bidder if financial risk is too high or if required mitigating factors are absent, insufficient or not accepted.
Price: price is assessed under the enquiry's rules, taking account of CPA, FOREX, commodity increases, discounts, NPV and forecast invoicing.
Specific goals: these are scored from supporting evidence; missing evidence does not by itself disqualify an otherwise acceptable bid but earns zero specific-goal points.
Preference system: price and specific goals are combined under the 80/20 or 90/10 preference-point system and bids are ranked from highest to lowest.
Objective criteria: a lower-ranked bid may be awarded only where objective criteria are stated in the enquiry; functionality and B-BBEE scorecard elements cannot be used as objective criteria.
Reverse e-auction: where used, the written bid must contain no prices; any prices included will be disregarded.
Arithmetical errors: Eskom may correct errors; where figures and words differ, the written amount controls; the corrected total binds the bidder once accepted.
Pricing Schedule
Source: Eskom Standard Conditions of Tender.pdf
Pricing schedule
Prices must include all applicable duties, taxes and levies, including VAT, based on the rates applicable 14 days before closing.
Rates are fixed for the contract period unless the enquiry permits adjustment.
Prices must be in Rand unless otherwise instructed.
If a pricing schedule or bill of quantities is used, Eskom will correct arithmetical errors; the tenderer may confirm original prices or accept corrections.
If figures and words differ, the written amount controls.
Eskom may seek clarification of rates but this cannot change the substance of the bid except to correct arithmetical errors.
If cataloguing applies, a separate cataloguing line item must be priced.
Financial Requirements
Source: Eskom Standard Conditions of Tender.pdf (TENDER)
Financial
Pricing basis: rates and prices must include all duties, taxes, levies and VAT applicable 14 days before the closing date.
Price validity: prices are fixed for the contract duration unless the enquiry allows adjustment.
Currency: South African Rand unless the enquiry states otherwise.
Security: if a performance bond or demand guarantee is required, the bidder must identify at least two Eskom-approved financial institutions it may approach.
Insurance: Eskom's insurance may not cover the full risk required by the contract; bidders should obtain independent advice.
Cost recovery: Eskom does not pay bid preparation, testing or negotiation costs.
Cataloguing: if required, the pricing schedule must include a cataloguing line item; Eskom pays for cataloguing.
Financial risk: award may be refused if financial risk is unacceptable or mitigating conditions are not agreed.
Compliance Requirements
Source: Eskom Standard Conditions of Tender.pdf (TENDER)
Compliance
Eligibility: bidder and its principals must not be restricted from doing business with Eskom or state-owned companies.
CIDB: where a CIDB grade is required, registration must be held at closing or achievable within 21 working days after closing.
Legislation: compliance is required with National Treasury instructions, CIDB regulations, local-content/designated-material rules, PPPFA regulations, the amended B-BBEE Codes, COIDA, the OHS Act and Eskom SHEQ requirements.
SHEQ proof: bidders must provide satisfactory proof of safety, health, environmental and quality systems, policies and capabilities, with related costs and personnel included in the bid.
Construction goals: awarded contractors must meet CIDB Contract Skills Development Goals and Contract Participation Goals where applicable.
Agent authority: an authenticated agent authority is required where an agent submits for a principal.
Compulsory sessions: attendance at any site visit or clarification meeting designated as compulsory is mandatory; non-attendance leads to disqualification.
Integrity: misrepresentation or falsified documents may lead to disqualification; B-BBEE fraud or fronting is reported to the B-BBEE Commission.
Health & Safety
Source: Eskom Standard Conditions of Tender.pdf
Health and safety
Compliance with the OHS Act and Eskom's safety, health, environment and quality requirements is mandatory.
Bidders must prove that SHEQ systems, policies and capabilities are in place.
SHEQ costs and personnel must be included in the tender price.
Contractual Terms
Source: Eskom Standard Conditions of Tender.pdf
Contractual terms
Eskom may accept or reject variations, deviations or alternative bids, cancel the process, or negotiate with selected bidders.
Eskom is not liable for bidder losses arising from participation, suspension, amendment or termination of the process.
Tenders must remain valid for the stated period and be extended if requested; refusal to extend excludes the bidder.
Procurement information and documents must be kept confidential and used only for bid preparation.
Compulsory site visits or clarification meetings must be attended; failure leads to disqualification.
Clarification requests must be in writing to the Eskom Representative and allow reasonable response time.
If performance security is required, the bidder must select at least two approved financial institutions.
Section
Source: Eskom Standard Conditions of Tender.pdf
Additional evaluation considerations
Functionality scoring must be passed before further evaluation.
Financial statements may be assessed for risk and mitigating conditions.
Price may be adjusted for CPA, FOREX, commodity changes, discounts, NPV and invoicing profile.
Specific goals require documentary proof; lack of proof scores zero.
Combined price and specific-goal scores determine ranking under 80/20 or 90/10.
Reverse e-auction may require a price-free written submission.
Document240-68099512 Form A_Cat 2_ Rev 9.docxReview complete
Description
Source: 240-68099512 Form A_Cat 2_ Rev 9.docx
The submission is a supplier quality requirements acknowledgement: by completing and signing Form A, the tenderer confirms acceptance of Eskom specification 240-105658000 and the ISO 9001 standard.
Submission Guidelines
Source: 240-68099512 Form A_Cat 2_ Rev 9.docx (unknown)
Returnable form
Form A (Supplier Quality Requirements acknowledgement): must be completed and signed by the tenderer to accept Eskom's supplier quality requirements under specification 240-105658000 and the ISO 9001 standard.
Section E of the form: the tenderer's nominated quality representative must be named, with designation, date and signature.
Only one pre-contract award quality category may be marked on the form; selecting more than one is not permitted.
The form must also indicate whether a site assessment applies.
Compliance Requirements
Source: 240-68099512 Form A_Cat 2_ Rev 9.docx (unknown)
Quality management
Acceptance of Eskom specification 240-105658000 supplier quality requirements is a pre-contract award condition.
Pre-contract award category applied: Category 2 (clause 3.5.3 of 240-105658000).
A quality management system aligned to ISO 9001 is required, covering clauses 4 to 10: context of the organisation, leadership, planning, support, operation, performance evaluation and improvement.
The seven ISO 9001 quality principles apply: customer focus, leadership, engagement of people, process approach, improvement, evidence-based decision making and relationship management.
Post-contract award obligations
Contract execution (clause 3.7.1) and the supplier quality performance monitoring phase (clause 3.7.2) apply.
Eskom rights of access and rights to information, preservation, quality audit conditions, management of nonconformities and special process conditions apply (clauses 3.8.1 to 3.8.6).
The tenderer must nominate a quality representative with name, designation, date and signature.
DocumentSupplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.docReview complete
Contact Information
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.doc (unknown)
Non-resident contractors: sign Appendix 9 only and route the pack through the Eskom contractor representative for referral to the Group Tax Department at Megawatt Park; no further questions are answered.
Individuals who supply people and hold a valid IRP30 exemption certificate: sign Appendix 6 and provide the certificate.
Individuals who supply people without a valid IRP30 certificate: sign Appendix 6 and accept that PAYE is withheld until the certificate is produced.
Evaluation Criteria
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.doc (unknown)
Classification outcome
Pack A (company, close corporation or trust) tests residence, employee numbers, connected-person services, the 80% single-client income test, place and control, and the dominant impression test.
Pack B (individual) tests service versus people, the people test, residence, employee numbers, place and control, and the dominant impression test.
Personal service provider outcome: a PSP answer to any of questions 6(i), 6(iii), 6(v), 6(vi) or 6(ix), or PSP answers to more than half of questions 6(ii), 6(iv), 6(vii), 6(viii), 6(x) and 6(xi).
Where that outcome applies, Appendix 7 must be completed and signed and PAYE is withheld, disclosed under code 3601 on the IRP5.
Where Appendix 7 was already signed at question 4 or 5, code 3616 is the applicable IRP5 disclosure code.
Where Appendix 7 was not signed at question 4 or 5, Appendix 8 must be signed instead.
Financial Requirements
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.doc (unknown)
Tax withholding
PAYE is withheld from payments where a required affidavit or declaration is not signed.
Eskom may deduct from payments any tax, interest or penalty it becomes liable for to SARS because information supplied in the pack was inaccurate.
Individuals supplying people without a valid IRP30 exemption certificate have PAYE withheld until the certificate is provided.
Compliance Requirements
Source: Supplier Evaluation Pack Template for 01 March 2025 to 28 February 2026.doc (unknown)
Applicability
Applies to contractors supplying services, or individuals supplying labour, to Eskom Holdings SOC Ltd and its subsidiaries: Eskom Rotek Industries, Eskom Enterprises, Escap, Eskom Finance Company, Eskom Foundation and the National Transmission Company South Africa.
Pack valid for the 2025/2026 tax year, 1 March 2025 to 28 February 2026, and based on the Income Tax Act 58 of 1962 and case law for that year.
Companies, close corporations and trusts complete Pack A; individuals complete Pack B.
The contractor or an authorised representative must declare that every answer is true.
Company, CC or trust details required: registration number, income tax number, representative ID number, physical and postal business address, and bank details.
Declarations (signed only where the answers direct)
Appendix 1: three or more full-time employees who are not connected persons.
Appendix 2: no connected person renders services personally to Eskom.
Appendix 3: services not performed mainly at Eskom and not under Eskom control or supervision.
Appendix 4: not more than 80% of income from one client or an associated institution.
Appendix 5: an individual supplies a service rather than people.
Appendix 6: labour broker declaration, with a valid IRP30 certificate where applicable.
Appendix 7: dependent contractor or personal service provider declaration.
Appendix 8: independent supplier or contractor declaration.
Appendix 9: non-resident declaration.
Appendix 10: definitions under the Income Tax Act.
Source: Standard Bidding Document (SDB) 4_Annexure A.doc (unknown)
Returnable form
SBD 4 (Declaration of Interest): must be completed and signed; bidder must disclose state employment, relationships with persons employed by the procuring institution, and interests in related enterprises.
Disqualification risks
A false or incomplete declaration disqualifies the bid.
Bidders listed in the Register for Tender Defaulters or the List of Restricted Suppliers are automatically disqualified.
Document240-77433139 Annexure A supplier risk category.docxReview complete
Description
Source: 240-77433139 Annexure A supplier risk category.docx
General scope
The procurement concerns OHS risk categorisation for Eskom services and works.
Activities are grouped into high, medium and low risk, with examples for each category.
Any service not listed requires a project-specific risk assessment involving the responsible OHS functionary.
The requirements apply to local and international suppliers.
Contact Information
Source: 240-77433139 Annexure A supplier risk category.docx (unknown)
Contact
Name: Diane Maunatlala
Team: Development Team
Submission Guidelines
Source: 240-77433139 Annexure A supplier risk category.docx (unknown)
Returnable OHS documents
Annexure B: bidder must complete, sign and submit acknowledgement of Eskom OHS rules and requirements.
High-risk work: submit OHS plan/manual, H&S costing, baseline OHS risk assessment, valid COID letter of good standing or equivalent, signed OHS policy and proof of OHS competency.
Medium-risk work: submit OHS plan/manual, baseline OHS risk assessment, H&S management costing, proof of OHS competency, valid COID letter of good standing or equivalent and signed OHS policy; an OHSAS 18001 certificate with a valid letter of good standing may be accepted.
Low-risk work: submit OHS plan/manual, baseline OHS risk assessment, valid COID letter of good standing or equivalent and signed OHS policy; an OHSAS 18001 certificate with a valid letter of good standing may be accepted.
Joint ventures: show the joint venture name on submitted documents or provide each member's COID letter.
Evaluation Criteria
Source: 240-77433139 Annexure A supplier risk category.docx (unknown)
OHS evaluation
Suppliers must undergo an OHS evaluation to be registered on the Eskom vendor database.
The evaluation requires a baseline OHS risk assessment and a valid COID letter of good standing, or an OHS tender evaluation report.
COID registration and compliance are preconditions for supplier registration.
Technical Specifications
Source: 240-77433139 Annexure A supplier risk category.docx (unknown)
Scope and risk categorisation
Services and works are classified by occupational health and safety risk as high, medium or low.
Bidders must apply the risk category that matches the scope; if a service is not listed, the project manager, project leader, contract manager or end-user must conduct a risk assessment with the responsible OHS functionary.
OHS requirements apply to local and international companies.
High-risk examples
Construction and installation: equipment installation, outage work, line construction, work at heights, demolition, excavation, blasting, scaffolding, building or modification of infrastructure, lifting equipment, support work, rigging, tunnelling, batch plant, explosive power tools, civil work, modification of plant or similar structures, road construction, mobile plant, storage facilities for waste, fuel, oil, vehicles or hazardous substances.
Maintenance: live line work, plant maintenance, line maintenance, ashing including emergency ashing, coal lashing, PF leaks, boiler maintenance, transformer maintenance, electrical switching, crane operation, refurbishment, sandblasting, cleaning of dams.
Transportation: employee transportation, coal transportation, goods transportation including abnormal or high-risk loads, hazardous chemical and dangerous goods transportation, equipment transportation, driving, heavy-duty transport and rigging, waste transportation including hazardous and medical waste.
Manufacturing, supply and delivery to Eskom premises or sites: conductors, scaffolding, MV motors, handling of transmission or distribution poles, fuel, oil and hazardous substances.
Services: security, consulting not office-based where engineers work on site or individuals have access to plant, events management involving erection of stages and equipment, industrial cleaning, aviation chartering, vegetation management, tree felling, bush clearing.
Other works: cleaning up spills and site rehabilitation depending on scale, diving or work in or around water where drowning risk exists, light-bulb crushing, working at ash dams, working with asbestos, working with radioactive materials, waste disposal.
Medium-risk examples
Vehicle maintenance, disconnection and reconnection of customers, transportation of low-risk goods, emergency services, fire and emergency equipment maintenance, technical consulting on Eskom sites, consultants installing electronic equipment in offices and at sites such as phones, computers and screens.
Low-risk examples
Office-based labour broking or staff provision, cleaning not conducted at heights, gardening or landscaping, supply, delivery and maintenance of electronic equipment such as iPads, phones, computers, laptops and screens, waste disposal.
Supply, transportation and delivery to Eskom premises or sites of consumables, stationery and printing, catering.
Services performed on Eskom premises or sites: admin-based consulting and auditing, professional services, training and coaching or mentoring, event management consulting, planning and logistics, cleaning of offices and ablution facilities, meter reading.
Financial Requirements
Source: 240-77433139 Annexure A supplier risk category.docx (unknown)
OHS costing
Bidders must include OHS management costs in the pricing or bill of quantities.
OHS costing must reflect the scope of work and associated risk and may include PPE, OHS training, OHS professionals, first aid equipment, ablution facilities, safety signs, safety campaigns or interventions, OHS equipment or instruments, and medical examinations.
Insurance alternative
A company without employees may submit an insurance letter covering accidental death and disability to a minimum value of R500 000 instead of a COID letter of good standing.
Compliance Requirements
Source: 240-77433139 Annexure A supplier risk category.docx (unknown)
COID and OHS compliance
COID registration and compliance are required; the bidder must provide a valid letter of good standing from the Compensation Fund or a licensed compensation insurer, reflecting the company name, or an acceptable mutual association insurance policy covering the full potential COID liability.
A certificate of exemption from the Department of Labour may exempt a bidder from the COID letter requirement.
If a letter of good standing is not submitted, acceptable alternatives may include an insurance letter equivalent to COID, proof of assessment by the Compensation Commissioner and proof of payment, or an equivalent document for international suppliers.
International suppliers must provide an equivalent COID document from their country of origin; if the supplier has offices in South Africa and employs South African citizens, a South African COID certificate is required.
Joint ventures must reflect the joint venture name on submitted documents or submit each company's COID letter.
OHS returnables
Annexure B acknowledgement must be signed and submitted.
A signed OHS policy, baseline OHS risk assessment, OHS plan or manual, proof of OHS competency and, where applicable, H&S costing are required according to the risk category.
OHSAS 18001 certification may be accepted with a valid letter of good standing for certain risk categories.
Safety professionals may need SACPCMP registration, indicating part-time or full-time status where applicable.
The bidder must submit a Contract Quality Plan demonstrating how quality will be planned and controlled for the Kusile smart plant digitalisation and artificial intelligence project.
The plan is the supplier's statement of the standards, quality practices, resources and processes applied to this specific contract.
It must be built on the SANS 466:2005 and ISO 10005:2005 guidance for quality plans.
It must cover the full scope of work, the QA and QC organisation, sub-supplier management, inspection and test planning, non-conformance handling, records and databook control, and post-delivery support.
Revision 0 accompanies the bid; Revision 1 is issued after contract signature.
The bidder must prepare a CQP setting out how quality will be managed across the contract scope, structured against SANS 466:2005 and ISO 10005:2005.
Scope of work: full description of the works information as defined in the NEC or FIDIC contract document.
Communication: named supplier representatives and contact details, and the channels used for quality documentation, minutes, fixed contract meetings and weekly progress reporting.
Organogram: designations, roles and outputs, including the QA and QC functions, personnel qualifications, and who verifies work versus who performs it.
Interfacing documents: the supplier's core processes, work instructions, policies, procedures, industry standards, specifications and drawings applicable to the scope.
Suppliers and sub-suppliers: materials and components to be purchased, outsourced or specialised activities, selection criteria, and how their performance will be monitored after award.
Sub-supplier QMS interface: how sub-supplier quality systems and procedures integrate with the supplier's own.
Item register: items to be manufactured, refurbished or purchased, with descriptions, production schedule and whether produced in-house or outsourced.
Inspection and test: which products and processes need a QCP/ITP, both offsite and onsite, and how inspection compliance will be monitored.
Special controls: processes governed by manufacturing or fabrication codes, such as welding and NDT/NDE, with the quality control activities applied to each deliverable.
Documented information submitted to Eskom: method statements, inspection reports, signed QCPs, technical assurance reports, warranty and material certificates, dimensional and test reports.
Records: how records are identified, completed, retained and disposed of, using an indexed and cross-referenced filing system.
Non-conformance: processes for concessions, defects, repair and rework, and inspection management.
Databook: databook index and operating and maintenance manual, including review and acceptance, and purchase orders for quality-critical items.
Tools and equipment: list of tools and equipment used on the contract, with calibration, maintenance or test status for each.
Customer property: process flow for handling customer property per the current ISO 9001 requirement.
Product preservation: process flow covering identification, handling, contamination control, packaging, storage, transport and protection.
Identification and traceability: methods applied to scope activities affected by statutory and regulatory requirements.
Commissioning and post-delivery: warranty period and conditions, customer satisfaction measurement, technical support, defect correction period and retention funds.
CQP administration
Compiled by the tenderer's representative at Revision 0 during tender evaluation, then revised to Revision 1 after contract signature.
Approved by the owner of the bidding organisation.
Eskom review and acceptance, and the commencement and completion dates, are completed only after award.
The scope category must be indicated: design, manufacturing, supply and delivery, construction/installation/maintenance, commissioning, professional services or other.
Document559-667439824 Generation Quality Control Plan Template 18Nov.docxReview complete
Description
Source: 559-667439824 Generation Quality Control Plan Template 18Nov.docx
Quality Control Plan template for Eskom maintenance and project work
A controlled Eskom pro-forma (template ID 240-43921898, Rev 9) used to raise, approve, revise and close out a Quality Control Plan for a defined scope of work.
Structure of the form:
Approval-for-use header block capturing unit/area, project or outage ID, component, QCP number, functional location, date, task/SOW, section, responsible party, contract/order number and revision number.
Preparer details and a separate review-and-approval block.
Revision/addendum register for tracking changes after approval.
Activity schedule listing each activity, its specification or acceptance standard, the assigned intervention points, and signature and date columns for the service provider, employer representative, system engineer and QA/QC.
Final acceptance block signed off after work execution, feeding the record into the databook.
Documentation Control Centre receipt block recording the receiving officer, signature, date and OpenText upload date.
The document is a blank controlled template: it defines the recording, witnessing and sign-off discipline the appointed service provider must follow on site.
Submission Guidelines
Source: 559-667439824 Generation Quality Control Plan Template 18Nov.docx (unknown)
Document submission
Completed Quality Control Plans and databooks go to the site Documentation Control Centre, not to a tender or SCM address.
An authorised (signed) copy is required; the centre will not archive an unsigned version.
The receiving Documentation Control Centre officer or senior clerk records name and surname, signature, date, and the date the record was uploaded to OpenText (Records Management).
Technical Specifications
Source: 559-667439824 Generation Quality Control Plan Template 18Nov.docx (unknown)
Quality Control Plan (QCP) requirement
Each maintenance, outage or project task must be controlled by a QCP raised against the specific unit or area, project/outage/maintenance ID, component, functional location, task or scope-of-work reference, and section.
Every plan must carry a unique QCP number, revision number, contract or order number and date, and must identify whether the responsible party is the service provider or Eskom Maintenance.
The plan must name its preparer with designation and signature, and must pass a documented review and approval before it is used.
Changes to an approved plan must be captured in a revision/addendum register showing the QCP number, the revision added, name, signature, designation and date.
Activity control
Work is scheduled as numbered activities, each tied to a stated specification, procedure or acceptance standard.
Each activity is assigned intervention points from a fixed legend: I (inspection), S (surveillance), R (review), W (witness), H (hold), V (verification) and E (executor).
Sign-off must be recorded, with signature and date, by the service provider executor, the service provider QC representative, the employer representative, the system engineer and QA/QC.
Hold points are stop points: the activity may not proceed until the required signature and date are entered against it.
Inspection records and remarks must be referenced against each activity.
Close-out
Final acceptance after work execution requires signatures from the service provider, employer representative, system engineer, QC representative or technician, and QA/QC before the record is accepted into the databook.
Compliance Requirements
Source: 559-667439824 Generation Quality Control Plan Template 18Nov.docx (unknown)
Quality assurance obligations
A QCP must be prepared, reviewed and approved before the related work is executed.
Every activity must cite the governing specification, procedure or acceptance standard against which it will be judged.
Hold points must be honoured as mandatory stops, with the authorising signature and date recorded before work continues.
Final acceptance into the databook requires all five sign-off roles: service provider, employer representative, system engineer, QC representative or technician, and QA/QC.
Once the databook is complete, an authorised copy of the form must be lodged with the site Documentation Control Centre for archiving and upload to OpenText (Records Management).
Appendix H covers whether the bidder supplies labour to Eskom, whether it acts as a labour broker, and whether services are rendered through a company, close corporation or trust.
Submission Guidelines
Source: Labour Taxation Questionnaire.pdf (unknown)
Returnable form
Appendix H (Contractors’ PAYE Evaluation Questionnaire) must be completed by the bidder.
The bidder’s representative must sign and date the form.
Compliance Requirements
Source: Labour Taxation Questionnaire.pdf (unknown)
Tax and labour compliance
Appendix H requires the bidder to provide vendor details: vendor name, vendor number, registration number (ID, company, CC or trust), VAT registration number and PAYE registration number.
The bidder must mark an X for each answer and respond to every question relevant to its circumstances.
Labour broker and PAYE disclosures
State whether the bidder will receive payment from Eskom for supplying people or labour.
If the bidder is a labour broker, state whether it can provide an original or certified IRP30 for the current tax year within 30 days.
State whether services will be rendered through a company, close corporation or trust.
Disclose whether services are provided personally by shareholders, members, beneficiaries or relatives.
State whether the entity employs four or more full-time employees, excluding shareholders, members, beneficiaries and relatives.
Disclose any training supplied or paid for by Eskom, including its nature and extent.
State whether the bidder may choose its own tools, equipment, staff, raw materials, routines, patents and technology.
Disclose any tools or equipment supplied or paid for by Eskom and describe them.
State whether more than 80% of the entity’s income during the financial year is received or anticipated from services relating to Eskom.
State whether Eskom controls or prescribes the bidder’s working hours.
Disclose any control or supervision by Eskom and describe its nature.
Disclose whether the contract contains employment-contract features, such as job titles, reporting structures, fixed working hours, employment benefits or performance bonuses, excluding bonuses and penalties for early or late delivery.
State whether the contract allows payment even if no work is done.
Disclose any previous classification by SARS or another client as a labour broker or personal services company, and explain any change in circumstances.
Representative declaration
The representative must confirm that the information is accurate and undertake to notify Eskom of any changes while receiving payment.
Provide the representative’s full names, capacity, contact number, signature and date.
Section
Source: Labour Taxation Questionnaire.pdf
Appendix H is used for contractors’ PAYE evaluation.
The pro forma bonds and guarantees are provided for convenience and are to be treated as part of the Works Information of the NEC3 Engineering & Construction Contract.
Document position: Part C1 (Agreements and Contract Data), section C1.3, of the Kusile Power Station Smart Plant Digitalisation and Artificial Intelligence Project contract pack.
The bond or guarantee must be reproduced exactly on the provider's letterhead, with no change to the text or format, and completed with the required details.
The completed document must be given to the Employer within the time stated in the contract.
Performance Bond pro forma: letterhead of the Contractor's Parent Company.
Retention Money Guarantee pro forma: letterhead of the Bank providing the guarantee.
Contract Data Part 1 includes Secondary Option X13 (Performance Bond); each listed secondary option requires a bond or guarantee in the form set out in the Works Information.
Secondary Option X16 (Retention) is not used with Option F.
The pro forma bonds and guarantees are treated as part of the Works Information.
Performance Bond (Option X13): demand guarantee; the Bank holds the Guaranteed Sum at Eskom's disposal and pays on written demand received before the Expiry Date.
Retention Money Guarantee (Option X16, where it applies): once Eskom receives and accepts it in the exact form stated, the Project Manager is instructed not to assess any retention.
Guaranteed Sum: amount left blank in the pro formas; no figure or percentage is stated.
Expiry Date: the date the Defects Certificate is issued under the contract.
Demand mechanics
Performance Bond demand: written, at the Bank's address, signed for Eskom by a Group Executive, Divisional Executive, Senior General Manager, General Manager or delegate; must state the amount claimed and that it is payable under the contract.
Retention Money Guarantee demand: signed by a director of Eskom or authorised delegate; must state the amount claimed and that the Contractor failed to rectify defects for which it is responsible, or that the amount is payable under the contract.
Bank position
Liability is as principal, not surety; absolute on a compliant demand; limited to the Guaranteed Sum; not delayed by any dispute between Eskom and the Contractor.
The guarantee is irrevocable until expiry, personal to Eskom, non-negotiable and non-transferable; a liquid document; claims after expiry are invalid.
Eskom may cede its rights under the guarantee to a third party where the contract permits.
Eskom's supplier quality specification (240-105658000, alternative reference QM 58, revision 3) sets the minimum quality requirements for existing and prospective suppliers and the criteria used to select, evaluate, register, monitor, assess and audit them. It applies across Eskom divisions, subsidiaries, suppliers and sub-suppliers and forms part of every RFI, RFQ, RFP and contract for products or services. Eskom's stated position is to work with suppliers that demonstrate commitment to a QMS conforming to ISO 9001 and that keep improving it.
Form A (240-68099512, Tender and Contract Quality Requirements): completed and signed by the bidder to acknowledge and accept Eskom's supplier quality requirements and the applicable ISO 9001 requirements.
Returnables are selected per tender from the List of Tender Returnables (240-12248652) according to the quality category marked in Form A.
Only one quality category (1 to 4) applies to each RFI, RFQ, RFP or contract.
Submission timing
A draft Contract Quality Plan, and where applicable an example Inspection and Test Plan or Quality Control Plan from similar or previous work, must accompany the bid.
The Contract Quality Plan and QCP/ITP must reach Eskom before the scope kick-off or pre-fabrication meeting and before manufacturing begins, whichever is earlier.
Any change to an accepted QCP/ITP must be resubmitted for Eskom review before the affected activity starts.
Coordination meetings with Eskom before orders are placed require 14 days' advance notice.
Workplace documentation must be available in English and in any language suited to the workforce.
Quality requirements are set per tender: an Eskom quality representative selects the applicable requirements in Form A and the List of Tender Returnables, and the bidder responds against the single category marked there.
Category 1
Signed Form A.
Valid ISO 9001 (or equivalent QMS) certificate from an accredited certification body.
Latest internal and external management system audit reports, including nonconformities and the resulting corrective actions.
Draft contract quality plan specific to the scope, meeting ISO 10005.
Draft or example ITP/QCP from similar or previous work.
Documented information for control of externally provided processes, products and services.
Documented roles, responsibilities and authorities (organograms, job descriptions, work instructions, procedures).
Records of management review: agenda, minutes, attendance registers, reports.
Category 2
Signed Form A.
Objective evidence of a developed, implemented and maintained ISO 9001-conforming QMS: QMS manual or scope document, quality policy, quality objectives, control of documented information, internal audit procedure, control of nonconforming outputs, nonconformity and corrective action procedure.
Latest internal audit reports with nonconformities and remedial actions.
Draft contract quality plan to ISO 10005.
Example ITP/QCP.
Control of externally provided processes documentation.
Roles and responsibilities documentation.
Management review records.
Category 3
Signed Form A.
Objective evidence of a developed ISO 9001-conforming QMS with the same core documented information as Category 2.
Draft contract quality plan to ISO 10005.
Example ITP/QCP.
Control of externally provided processes documentation.
Roles and responsibilities documentation.
Category 4
Signed Form A.
Quality method statement based on ISO 9001 and specific to the scope of work.
Signed quality policy.
Quality objectives.
Control of externally provided processes documentation.
Roles, responsibilities and authorities documentation specific to the project.
No scoring formula, weighting or minimum qualifying score is stated.
Applies to every Eskom RFI, RFQ, RFP and contract for products and services, across Eskom divisions, subsidiaries, suppliers and sub-suppliers.
Suppliers and sub-suppliers must develop, implement, maintain and continually improve a QMS conforming to the latest ISO 9001 and keep it in place for the contract duration.
The main supplier is accountable for its sub-suppliers' quality performance and must run a sub-supplier programme covering QMS verification, audits and surveillances, CQP and QCP review, nonconformity and defect management, inspection and test plans, and risk management.
Eskom may assess sub-supplier facilities.
Contract Quality Plan
Required where the evaluation criteria or returnables list calls for it; must follow ISO 10005.
Must cover records and material testing (including positive material identification and material certification), free access for inspection, final documentation and the manufacturing data book before shipment, welding controls (WQR, WPS, PQR), special installation and fabrication procedures, storage and preservation instructions, and Eskom or agent monitoring of sub-suppliers.
Must set out the QMS elements applied to the project, resources, communication channels and named contacts, documents and records to be produced, management authority and responsibility on both sides, and monitoring and measurement methods.
Quality Control Plan / ITP
Must cover every manufacturing, fabrication, assembly and installation stage in chronological order, from contract review through material verification, final testing, commissioning and handover.
Must be accepted by Eskom or its inspection agency before work starts and must allow Eskom to insert hold and witness points.
Must carry the Eskom contract number and title, the supplier order number, the area of works, the work description with item numbers and activity dates, a unique QCP/ITP number, the sequence of operations, referenced specifications, drawings or procedures with criticality rating, acceptance criteria with clause references, intervention points, sign-off provision for every party, and the inspection and test records to be generated.
A separate QCP/ITP is required for each sub-supplier scope of work.
Once signed, the ITP and QCP become addenda to the contract.
Special processes
Welding, NDT, coating and heat treatment personnel must be suitably qualified and, where the law requires it, registered with the relevant statutory body.
Welding procedures and welder qualifications must be reviewed and accepted before manufacture starts.
Personnel certificates must meet SETA requirements, showing the completed unit standard and the provider's accreditation number.
Preservation
A documented preservation programme is required for bulk materials, consumables, equipment, systems and components held before operation, covering valves, motors, rotating equipment, piping, instrumentation, flange faces, gaskets, coatings and insulation, including periodic shaft rotation, engine turnover and lubrication.
Preservation requirements must be written into purchase orders and work authorisations and communicated to logistics, construction, quality and security functions.
Eskom must have unrestricted access to all preservation records.
Method statements and work procedures referenced in the QCP/ITP must identify the equipment and facility location for each activity and cite the specific sections and pages of the procedures, standards, instructions and specifications used.
The preservation programme must cover review and tracking of compliance with Eskom and supplier engineering specifications and with sub-supplier recommendations, evaluation of temporary and longer-term storage sites, performance evaluation of transport, handling and storage providers, oversight of preservation plan preparation and execution at all work locations, and a records management process giving Eskom ready access.
A documented programme must identify the pre-operation preservation requirements for all physical assets, including bulk materials, consumables, equipment, systems and components transferred to project control but not yet in operation.
Welders must be qualified to the codes of construction for the applicable procedures.
Welder qualification records, welding procedure specifications and procedure qualification records must be reviewed and accepted before manufacture starts.
Welder records are kept by the sub-suppliers performing the work.
Special processes
Personnel carrying out NDT, welding, coating or heat treatment, where results cannot be verified by later inspection, must be suitably qualified and, where the law requires it, registered with the relevant statutory body, such as radiographic workers.
Certificates of competency must come from the supplier's internal training and competency control process or from an accredited external provider meeting SETA requirements.
Training needs for all quality-affecting activities must be identified, documented and met; training certificates must show the completed unit standard and the provider's accreditation number.
Inspection and audit personnel
Quality control inspectors, including third-party and approved inspection authority inspectors, must meet the qualification requirements set in the QCP/ITP.
Quality audits and quality performance reviews must be carried out by trained, accredited and experienced personnel.
A Contract Quality Plan is required where the evaluation criteria or returnables list calls for it, and must follow ISO 10005 plus the additional elements set out in the specification.
A Quality Control Plan or Inspection and Test Plan must control all manufacturing, fabrication, assembly and installation stages, in chronological order, from contract review to handover and certification.
The QCP/ITP must be accepted by Eskom or its inspection agency before work starts and must allow Eskom to insert hold and witness points.
A separate QCP/ITP is required for each sub-supplier scope of work, and the main supplier remains accountable for all of them.
Meetings
A quality kick-off meeting is held at contract start and, where required, at the start of each subsequent phase.
Coordination meetings must be held with Eskom before orders are placed for items or equipment; 14 days' advance notice is required.
Mandatory pre-inspection meetings are convened by Eskom or its inspection agency and attended by supplier and sub-supplier representatives, including quality representatives; records are kept.
Monitoring and audit
The supplier must formally assess sub-supplier inspection and testing programmes, review their inspection reports and quality control documentation, and audit their facilities at a frequency set by scope criticality and performance.
Assessment scope and schedule are developed in consultation with Eskom.
Verification of purchased product compliance must be documented and reviewed before implementation.
Nonconformities and nonconforming outputs identified by Eskom are managed under the specification's standard conditions.
Documentation
Applicable codes, standards and acceptance criteria must be available at the work location and accessible to Eskom representatives on an ongoing basis.
Workplace documentation must be in English and in any language appropriate to the workforce.
ISO 9001 certification from an accredited certification body is required unless the returnables list excludes it for the applicable category.
Where certification is excluded, a documented, implemented and maintained ISO 9001-conforming QMS is still required.
The same QMS requirements apply to any sub-supplier performing design, manufacturing, maintenance, testing, storage, delivery, installation, commissioning or project management, and continue to apply after name changes, mergers, acquisitions or cessions.
The supplier must notify Eskom before changing its QMS or quality staff in a way that affects the quality system.
Personnel
Special-process personnel must hold certificates of competency; NDT and similar certification must come from an accredited provider meeting SETA requirements.
Radiographic workers must be registered with the statutory body.
Quality control inspectors, including third-party and approved inspection authority inspectors, must meet the qualification requirements set in the QCP/ITP.
Quality audits must be performed by trained, accredited and experienced personnel.
Eskom oversight
Eskom may appoint an inspection agency or approved inspection authority, and the supplier and its sub-suppliers may not obstruct, hinder or discredit that organisation's work.
Eskom may place resident quality inspectors at supplier or sub-supplier premises and on site; the supplier must provide workspace at no cost.
Mandatory pre-inspection meetings are convened by Eskom or its inspection agency and must be attended by supplier and sub-supplier representatives, including their quality representatives.
The supplier must run a documented preservation management programme for all physical assets transferred to project control but not yet in operation, including bulk materials, consumables, equipment, systems and components.
Preservation requirements must be recorded in purchase orders, work authorisations and communications with sub-suppliers, and passed to logistics, construction management, quality and security.
Sub-supplier responsibility for each element of the programme must be clearly allocated, including access to records and provision of equipment, tools and services.
Responsibility for oversight of the programme must be assigned within the project team at every stage and implemented at all work locations.
Eskom rights
Eskom has free and unrestricted access to all preservation records for inspection and audit.
Eskom may select intervention points on QCPs and ITPs and perform surveillance or audits of the work.
Eskom may appoint resident quality inspectors at supplier or sub-supplier premises and on site, and the supplier must provide workspace at no cost.
Eskom may appoint any organisation as an approved inspection authority or inspection agency, and the supplier and its sub-suppliers may not object to, prevent, hinder, circumvent or discredit that organisation.
Signed ITPs and QCPs become addenda to the main contract and may be reviewed at Eskom's discretion based on performance or risk.
Changes
The supplier must inform Eskom before implementing changes to its QMS or quality staff that affect the quality system.
Changes to an Eskom-accepted QCP/ITP require Eskom's agreement before the affected activity starts.
Quality requirements are chosen per procurement by an Eskom quality representative using Form A and the List of Tender Returnables; exactly one of the four categories applies to each RFI, RFQ, RFP or contract.
Before award, Eskom may run a supplier capability and capacity assessment where the supplier provides products or services carrying high operational risk, works on critical plant and equipment, supplies critical plant items or components, or performs special processes.
No scoring formula, weighting or minimum qualifying score is stated.
DocumentC2 ECC3 Pricing Data Option A_SPP_29.09.2026.docxReview complete
Description
Source: C2 ECC3 Pricing Data Option A_SPP_29.09.2026.docx
Project and pricing description
Project: Kusile Power Station Smart Plant Digitalisation and Artificial Intelligence Project.
Pricing framework: The pricing data is prepared under NEC3 ECC3 Option A.
Activity Schedule: The contractor must base its offer on the Activity Schedule provided in the relevant annexure.
Lump-sum activities: Each activity in the schedule is priced as a lump sum and is linked to the programme.
Works information: The Activity Schedule does not define the works; the contractor must provide the works in accordance with the Works Information.
Risk and defects: The priced activities must cover all work necessary and incidental to provide the works, including correction of defects not caused by an employer's risk.
Submission Guidelines
Source: C2 ECC3 Pricing Data Option A_SPP_29.09.2026.docx (unknown)
Pricing submission
Pricing basis: The offer must use the Activity Schedule supplied in the annexure named KUSILE POWER STATION SMART PLANT DIGITILISATION NEC PRICING SCHEDULE.
Deviations: Any proposed deviation, exclusion, omission, addition, inclusion or amendment to the Activity Schedule must be clearly identified in the tender submission.
Pricing of deviations: Each deviation must be separately detailed with the corresponding rates and prices and must be fully priced as part of the offer.
Technical Specifications
Source: C2 ECC3 Pricing Data Option A_SPP_29.09.2026.docx (unknown)
Contract and pricing structure
Contract form: NEC3 Engineering and Construction Contract, ECC3 Option A.
Work breakdown: The work must be divided into activities in the Activity Schedule.
Pricing method: Each activity must be priced as a lump sum.
Payment basis: Only completed activities are assessed for payment at each assessment date; no part payment is made if an activity is not completed by that date.
Document status: The Activity Schedule is a pricing document only and does not contain Works Information or Site Information.
Delivery obligation: The contractor must provide the works in accordance with the Works Information.
Programme link: The bidder must show how each Activity Schedule item relates to the operations on each programme submitted for acceptance.
Scope coverage: Priced activities must include everything necessary and incidental to provide the works and correct defects not caused by an employer's risk.
Financial Requirements
Source: C2 ECC3 Pricing Data Option A_SPP_29.09.2026.docx (unknown)
Pricing and payment
Pricing format: Lump-sum prices for each activity in the Activity Schedule.
Payment trigger: Payment is assessed only for completed activities at each assessment date.
Incomplete activities: No part payment is made for an activity that is not completed by the assessment date.
Completed activity: An activity is completed only when it is free of defects that would delay or be covered by immediately following work.
Price adjustment: The lump-sum price is not adjusted if the actual amount or quantity of work within an activity differs from the tender estimate, unless a compensation event applies.
Document240-12248652_Catergory 2 List of Tender Returnables Rev 7.pdfReview complete
Description
Source: 240-12248652_Catergory 2 List of Tender Returnables Rev 7.pdf
Quality requirements for the Kusile Smart Plant Digitalisation and Artificial Intelligence Project over 3 years.
Bidders must show a compliant quality management system, either certified to ISO 9001 or supported by documented QMS evidence.
Evidence must show the QMS is operating, including roles, external provider controls, internal audit results and management review records.
Bidders must provide a draft contract quality plan and a draft inspection and test plan or quality control plan for the scope of work.
Form A must be completed and signed.
Contact Information
Source: 240-12248652_Catergory 2 List of Tender Returnables Rev 7.pdf (TENDER)
Contact
Name: Veronica Mpe
Role: Eskom representative
Submission Guidelines
Source: 240-12248652_Catergory 2 List of Tender Returnables Rev 7.pdf (TENDER)
Returnable quality documents
QMS certification route: valid ISO 9001 certificate from an accredited body, with current validity and relevant product/service scope.
QMS documentation route: QMS manual or equivalent, quality policy, quality objectives, document control, control of nonconforming outputs, corrective action, and internal audit evidence.
QMS operation evidence: organisation chart and responsibility matrix, external provider controls, latest internal audit report with nonconformities/corrective actions, and management review records.
Draft contract/project quality plan aligned to scope and ISO 10005.
Draft inspection and test plan or quality control plan covering all scope-of-work activities.
Completed and signed Form A.
Evaluation Criteria
Source: 240-12248652_Catergory 2 List of Tender Returnables Rev 7.pdf (TENDER)
Quality evaluation
Category 2 quality deliverables are scored.
Section A: QMS requirement, either Option 1 certified ISO 9001 for 4 points or Option 2 documented QMS for 7 points.
Section B: evidence of QMS in operation for 4 points.
Section C: draft contract quality plan for 1 point.
Section D: draft inspection and test plan or quality control plan for 1 point.
Section E: completed Form A for 1 point.
Technical Specifications
Source: 240-12248652_Catergory 2 List of Tender Returnables Rev 7.pdf (TENDER)
Quality scope
Applies to the Kusile Smart Plant Digitalisation and Artificial Intelligence Project for a 3-year period.
Bidders must provide quality management evidence relevant to the scope of work.
The draft contract quality plan and inspection or test plan must address all scope-of-work activities.
Controls for externally provided processes, products and services must cover evaluation, selection, performance monitoring and re-evaluation.
Compliance Requirements
Source: 240-12248652_Catergory 2 List of Tender Returnables Rev 7.pdf (TENDER)
Compliance requirements
Quality management system: valid ISO 9001 certification from an accredited body, or documented QMS evidence covering the specified ISO 9001:2015 clauses.
The certificate must be current, issued by a recognised certification authority, and cover the relevant product or service scope.
Form A must be completed and signed.
Quality plans must align with ISO 10005 and the tender scope.
Section
Source: 240-12248652_Catergory 2 List of Tender Returnables Rev 7.pdf
Quality scoring
Section A: 4 points for a valid ISO 9001 certificate, or 7 points for documented QMS evidence.
Section B: 4 points for evidence of QMS operation.
Section C: 1 point for a draft contract quality plan.
Section D: 1 point for a draft inspection and test plan or quality control plan.
Section E: 1 point for completed Form A.
DocumentSBD 1 - Converted.docx.pdfReview complete
Technical Specifications
Source: SBD 1 - Converted.docx.pdf (TENDER)
Scope
Procurement of the Kusile Smart Plant digitalisation and artificial intelligence project.
Compliance Requirements
Source: SBD 1 - Converted.docx.pdf (TENDER)
Eligibility and compliance
CSD registration: the bidder must be registered on the Central Supplier Database, with business registration, director/member/identity details, tax status and banking details available for verification.
Tax compliance: a SARS tax compliance PIN or printed tax compliance status must be supplied. If the bidder has no tax compliance status but is CSD-registered, the CSD number must be given.
Joint arrangements: each consortium member, joint-venture party or subcontractor must provide its own tax compliance PIN, printed status or CSD number.
Foreign suppliers: a bidder with no South African residence, branch, permanent establishment or income source does not need a SARS tax compliance PIN.
B-BBEE: a B-BBEE verification certificate or sworn affidavit must be lodged with the bidding institution; this evidence is needed to claim B-BBEE preference points.
Risk: missing required particulars can make the bid invalid.
Eskom requires a Smart Plant digitalisation and AI solution at Kusile Power Station, a 4,800 MW coal-fired station (six 800 MW units) and one of the largest of its kind.
The aim is a fully integrated digital ecosystem across engineering, control and business systems, using real-time data acquisition, AI analytics and immersive technologies.
Strategic objectives
Operational efficiency: cut unplanned downtime through predictive maintenance and streamlined digital workflows.
Safety and compliance: automated inspection, real-time monitoring and maintained audit trails.
Data-driven decisions: a unified data platform integrating operational, maintenance and business data.
Workforce development: VR/AR training and knowledge transfer.
Future-ready infrastructure: a scalable, standards-compliant foundation that integrates with existing enterprise systems.
Functional intent
Real-time plant monitoring and AI analytics for predictive and prescriptive maintenance, with history interfaced into SAP and existing plant forms.
Mobile and remote access to live plant data for authorised engineering and maintenance teams.
Proposed solution must come from a manufacturer recognised as a Leader in the latest applicable Gartner Magic Quadrant for Enterprise Wired and Wireless LAN Infrastructure, Data Center Switching, and Enterprise Storage Platforms.
Bidder must provide verifiable evidence of that Leader position: Gartner report title, publication date, manufacturer name and supporting documentation.
Solution must operate as an Eskom-controlled private cloud hosted under South African law, with POPIA compliance.
Solution must comply with IEC 62443 cybersecurity standards.
AI-enabled functions must comply with Eskom's Responsible AI governance: inventory registration, risk assessment, validation, human oversight, monitoring and revalidation.
Design, supply, implementation, integration, testing, training and handover of a Smart Plant digital ecosystem at Kusile Power Station, delivered as five technology pillars over two phases.
Covers all hardware, software, professional services and training required for full operational capability.
Costing and deliverables must be phased.
Ongoing operational support beyond three months after go-live is excluded and will be handled under separate service level agreements.
Delivery phases
Phase 1: Pillar 1 (Network and Infrastructure); Pillar 2 (Intelligent Inspection and Digital Interaction); Pillar 3 (Digital Twin Interface and Integration).
Phase 2: Pillar 4 (Paperless Operations / Digitalised Routine Work Management, integrated with SAP PM/MM); Pillar 5 (Digitisation of existing plant documents and data books).
Pillar 1: Network and Infrastructure
Industrial-grade network, private cloud, storage, video and management infrastructure, hosted in an Eskom-controlled private cloud under South African law.
Industrial access switching with ingress protection, wide temperature range, redundant power, PoE/PoE++ and Layer 2/3.
Industrial wireless with current enterprise Wi-Fi standards, secure authentication, roaming and ruggedised ratings.
Wireless access controller managing at least 3,000 access points, compliant with IEEE 802.11n/ac/ax/be.
Support for at least 500 concurrent connected devices at initial deployment, with minimum 50% capacity headroom for expansion.
Minimum target availability of 99.9% for agreed critical services.
Cloud storage with minimum usable capacity of 200 TB at initial deployment.
Point-to-point microwave radio: fully outdoor, 7-38 GHz bands, switching capacity not less than 60 Gbit/s, dual RF ports (ODU), carrier aggregation and XPIC.
Cybersecurity aligned to IEC 62443 (segmentation, zones and conduits, firewalling, MFA, encryption, logging).
Pillar 2: Intelligent Inspection and Digital Interaction
AI-enabled cameras (explosion-proof, PTZ, bullet, IR and white-light options) with high-resolution video, tamper detection and edge or central inference.
Computer-vision use cases: oil/steam/water leak detection, equipment condition recognition, meter and indicator reading, PPE compliance, intrusion detection, conveyor monitoring, flame and smoke detection, and falling-person detection.
AI inference platform with GPU or accelerator capacity.
Perimeter and safety monitoring using distributed fibre-optic sensing and video surveillance.
Remote collaboration via video conferencing, smart helmets, body cameras and two-way communication.
Smart safety helmets with built-in camera, microphone, speaker, Wi-Fi and LTE, and SIM/TF slots; all hard hats must meet Eskom PPE standard 240-44175132.
Operations-centre visualisation with dashboards, 3D digital twin and integration to the large LED IOC screen.
AI-enabled NVR for large-scale video recording and analytics.
Pillar 3: Digital Twin Interface and Integration
Data interoperability and asset information model aligned to OPC UA and ISO 23247.
Documented APIs and interface specifications, data-quality and lineage controls, and synchronisation and change-control configuration.
Pillar 4: Paperless Operations / RWM
Digitised routine work management and outage functions, integrated with SAP PM/MM.
Pillar 5: Document Digitisation
Digitisation of more than 1,000,000 pages of existing plant documents and data books, using OCR, metadata capture and quality checks.
Key deliverables (Pillar 1)
Network and private cloud architecture design document.
Site survey and coverage assessment (RF survey, heatmaps, access-point placement).
Cybersecurity architecture and hardening plan.
Bill of materials and licensing register.
Network, private cloud/storage, and video management/storage configuration packs.
Integration and acceptance test report.
Operations, monitoring and handover manual.
Standards
Comply with ISO 9001, ISO 27001, ISO 55001, IEC 62443, IEC 62351, IEC 62264, IEC 62541, IEC 61850, IEC 61511 and IEC 60870-5-104.
Delivery is phased: Phase 1 covers Pillars 1 to 3 (network and infrastructure, intelligent inspection, digital twin); Phase 2 covers Pillars 4 and 5 (paperless operations/RWM with SAP integration, and document digitisation).
Each pillar requires design, documentation and acceptance, with defined key deliverables and an integration and acceptance test report before handover.
Contractor-supplied designs must follow Eskom documentation, format, naming and submission requirements.
Monitoring
Progress is monitored under four pillars: technical performance, operational adoption, cybersecurity and network integrity, and programme performance (schedule, budget, risk and change management).
Costing must be phased to align with the two delivery phases.
Support boundary
Three months of post-go-live support is included; ongoing operational support beyond that period is excluded and will be handled under separate service level agreements.
All data must be hosted on Eskom-controlled infrastructure governed by South African law; POPIA applies to personal information.
Any external access, support connection or data transfer requires explicit Eskom approval and must be logged.
Cybersecurity
IEC 62443-aligned segmentation with an Industrial DMZ, dual firewalls, VLAN segmentation, role-based access control and continuous OT network monitoring.
Direct ERP-to-DCS communication and direct internet access from the OT network are prohibited.
Remote OT access only via secure jump servers.
Encryption of data at rest and in transit.
Standards
Comply with ISO 9001, ISO 27001, ISO 55001 and the IEC 62443, 62351, 62264, 62541, 61850, 61511 and 60870-5-104 series.
Hard hats must meet Eskom PPE standard 240-44175132.
Responsible AI
All AI functions must be entered in Eskom's AI inventory, risk-assessed, validated through lifecycle gates, monitored in operation and kept under accountable human review; AI outputs are decision-support only unless Eskom approves otherwise.
Intellectual property
Foreground IP created specifically for the initiative, and all inspection data and AI outputs, are owned by Eskom.
Foreground IP created specifically for the Kusile initiative belongs to Eskom, including inspection data and AI outputs.
AI Apprenticeship Programme (AIAP)
The supplier must run a structured programme that transfers practical AI, data, cloud, integration, cybersecurity and Smart Plant operating skills to Eskom personnel.
Support and phasing
Delivery is phased across two phases; three months of post-go-live support is included, with ongoing support handled under separate service level agreements.
Document240-77471651 Annexure C 1 (3) High risk tender 2026.docxReview complete
Contact Information
Source: 240-77471651 Annexure C 1 (3) High risk tender 2026.docx (unknown)
Development team
Name: Diane Maunatlala
Submission Guidelines
Source: 240-77471651 Annexure C 1 (3) High risk tender 2026.docx (unknown)
Returnable OHS documents
Signed Annexure B confirming acceptance of Eskom OHS legal and other requirements.
A Health and Safety Plan covering the OHS risks of the project or scope and matching the health and safety specification or requirements.
Itemised OHS costing, not a lump sum, based on the whole scope of work or service.
A Baseline OHS Risk Assessment that identifies, assesses and manages OHS risks linked to the scope, with the method used.
A valid COIDA letter of good standing or equivalent.
An OHS policy signed by the CEO and meeting section 7 of the OHS Act.
Evidence of OHS competency through CVs and qualifications or certificates relevant to the scope, risks and OHS plan.
Evaluation Criteria
Source: 240-77471651 Annexure C 1 (3) High risk tender 2026.docx (unknown)
OHS returnables are checked before contract award.
Each item is recorded as submitted, not submitted or not applicable, with comments.
The result is a recommendation of recommended or not recommended.
Guidance on the OHS returnables is in 240-77433139 Annexure A: Supplier Risk Category.
Technical Specifications
Source: 240-77471651 Annexure C 1 (3) High risk tender 2026.docx (unknown)
OHS deliverables and standards
The Health and Safety Plan must cover the OHS risks of the project or scope and match the health and safety specification or requirements.
The Baseline OHS Risk Assessment must identify, assess and manage OHS risks linked to the scope, with the method used.
OHS competency must suit the scope, risks and OHS plan, supported by CVs and qualifications or certificates.
Financial Requirements
Source: 240-77471651 Annexure C 1 (3) High risk tender 2026.docx (unknown)
OHS costing
Must be itemised by cost component, not a lump sum.
Must cover the whole scope of work or service.
The scope and risk assessment may guide the costing.
Compliance Requirements
Source: 240-77471651 Annexure C 1 (3) High risk tender 2026.docx (unknown)
Mandatory OHS compliance documents
Signed Annexure B confirming acceptance of Eskom OHS legal and other requirements.
Valid COIDA letter of good standing or equivalent.
OHS policy signed by the CEO and meeting section 7 of the OHS Act.
Evidence of OHS competency through CVs and qualifications or certificates.
Guidance is in 240-77433139 Annexure A: Supplier Risk Category.
DocumentSBD 6.2 Local Content in terms of PPR 2017.pdfReview complete
Description
Source: SBD 6.2 Local Content in terms of PPR 2017.pdf
Local-content declaration details
Bidders must state whether any part of the offered goods or services contains imported content.
If imported content is present, exchange rates must be shown for US Dollar, Pound Sterling, Euro, Yen and other currencies.
The rates must be the South African Reserve Bank rates published at 12:00 on the bid advertisement date, with supporting proof.
If meeting the local-content threshold becomes problematic after award, the dti must be informed so that verification and directives can be provided.
Submission Guidelines
Source: SBD 6.2 Local Content in terms of PPR 2017.pdf (TENDER)
Returnable documents
SBD 6.2 Declaration Certificate for Local Production and Content, signed by the chief financial officer or another legally responsible person nominated in writing by the chief executive or senior management.
Annex C Local Content Declaration: Summary Schedule.
Evidence of the South African Reserve Bank exchange rates used, if imported content is declared.
Supporting records
Annex D Imported Content Declaration and Annex E Local Content Declaration must be kept for at least 5 years for verification.
The successful bidder must update Annex C, D and E with actual values throughout the contract.
Disqualification risk
The bid may be rejected if SBD 6.2 and Annex C are missing.
Evaluation Criteria
Source: SBD 6.2 Local Content in terms of PPR 2017.pdf (TENDER)
Evaluation approach
Consideration is limited to bids where the goods are locally produced or manufactured and meet the required minimum local-content threshold.
If a two-stage process is used, stage 1 checks compliance with the local-content threshold and stage 2 assesses price and B-BBEE.
Pricing Schedule
Source: SBD 6.2 Local Content in terms of PPR 2017.pdf
Pricing information for local content
Bid price excluding VAT in Rand.
Imported content in Rand.
Stipulated minimum local-content threshold.
Calculated local-content percentage.
Separate local-content percentages for each product where multiple products are offered.
Financial Requirements
Source: SBD 6.2 Local Content in terms of PPR 2017.pdf (TENDER)
Pricing data for local content
Bid price excluding VAT, in Rand.
Imported content, in Rand.
Applicable minimum local-content threshold.
Calculated local-content percentage.
If more than one product is offered, a local-content percentage for each product.
Compliance Requirements
Source: SBD 6.2 Local Content in terms of PPR 2017.pdf (TENDER)
Local production and content
Bids are limited to locally produced or manufactured goods that meet the required minimum local-content threshold.
SBD 6.2 and Annex C must be submitted with the bid; missing documents may lead to disqualification.
The declaration must be signed by the chief financial officer or a legally responsible person nominated in writing by the chief executive or senior management; signing cannot be delegated to an external representative, auditor or third party.
Local content is calculated according to SATS 1286:2011: local content % = [1 - (imported content in Rand / bid price excluding VAT in Rand)] × 100.
Imported content must be converted to Rand using the South African Reserve Bank rate published at 12:00 on the bid advertisement date, and proof of the rate must be provided.
Subcontracting must not reduce total local content below the required threshold.
Incorrect or unverifiable local-content information may trigger remedies under Regulation 14 of the Preferential Procurement Regulations, 2017.
B-BBEE may be considered in the second stage where a two-stage evaluation is used.
Contractual Terms
Source: SBD 6.2 Local Content in terms of PPR 2017.pdf
Local-content contract obligations
The successful bidder must not subcontract in a way that reduces overall local content below the required threshold.
If post-award difficulties arise in meeting the threshold, the dti must be notified for verification and possible directives.
Failure to include SBD 6.2 and Annex C in the bid may result in disqualification.
Section
Source: SBD 6.2 Local Content in terms of PPR 2017.pdf
Possible evaluation sequence
Stage 1: confirm that the bid meets the minimum local production and content threshold.
Stage 2: evaluate price and B-BBEE.
This two-stage method may be applied where necessary.
Annexure A - Integrity Declaration Form must be completed, signed and dated by an authorised representative of the bidder; for a joint venture, the lead partner must sign.
The declaration must provide full names, positions, identity or employee numbers, and details of any relationship or interest.
A false or incomplete declaration may lead to rejection of the bid and action against the bidder or joint venture.
Declaration of interest
Bidders must disclose if any employee, director, member, shareholder or owner is employed by the state, a state-owned entity, the procuring entity, or acts as a contractor, consultant or director alongside procuring entity personnel.
Bidders must disclose any relationship with a procuring entity employee, contractor, consultant or director involved in evaluation, adjudication or negotiation, including marriage or similar partnership, relatives within two degrees, control, subsidiaries, common control, or a shared controlling partner.
If a bidder’s employee, director, member, shareholder or owner is employed by the procuring entity, the bidder must state whether this has been declared and whether authorisation exists for remunerative work outside public-sector employment, with supporting proof.
If the bidder shares a controlling partner or relationship with another bidder that could provide access to information or influence the process, this must be declared with proof.
Fair tendering and disqualification
Bidders and their directors, members or shareholders must not be listed on National Treasury’s Database of Restricted Suppliers or the Register for Tender Defaulters under section 29 of the Prevention and Combatting of Corrupt Activities Act.
Bidders must not have been convicted of fraud or corruption relating to procurement or tendering in the past five years, including convictions outside South Africa.
Bidders must not be prohibited from doing business with an international financial development, funding agency or lending institution.
A bid may be disqualified for bid rigging, collusion, fraud or other improper conduct in the procurement process.
Joint ventures
A joint venture agreement must be attached, confirming joint and several liability and authorising the lead partner to incur liabilities, receive instructions and payments, and manage contract execution.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
KUSILE POWER STATION - WITBANK - EMALAHLENI/VICTOR KHANYE - 1035
Document-Backed
Recently Synced
Source Snapshot Available
AI Enhanced
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
33
Last checked
18 Nov 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.