Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Issuing Organization
Air Traffic and Navigation Services Company LimitedLocation
National
Closing Date
20 Nov 2026
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
ATNS Company Limited, Eastgate Office Park, Block C, South Boulevard Road, Bruma, 2298 BID SUBMISSIO - Bruma - Bedfordview - 2298
Organization Type
GOVERNMENT
Published
22 Sept 2026
OCDS Reference
ocds-9t57fa-171354
Atns requires the supply, delivery, installation, commissioning, and support of fibre termination nodes at nine sites (cape town, george, port elizabeth, east london, bloemfontein, durban, upington, johannesburg, and the atns training academy). The contract covers a 15-year system lifespan, including a mid-life upgrade, and a 15-year maintenance and support contract. Bidders must meet strict system performance targets (99.98% Availability, 98.90% Reliability) and deliver a comprehensive set of draft logistics support plans at tender submission.
Closing: 6 November 2026 at 11:00; submission per the General Information and Instructions to Bidders document.
Mandatory (M) requirements: non-compliance disqualifies the bid; each paragraph must be declared C (2 pts), PC (1 pt), NC (0 pts), or Noted.
Phase 1A deliverables (draft plans) must be submitted with the tender: LSIP, LSP, RAMP, Training Plan, Spares Plan, Test Equipment Plan, Documentation Plan, PHS&T Plan, CMP, and Support Contract.
System performance: 99.98% availability (max 1.75 hrs downtime/site/year), restart <5 minutes, 98.90% reliability (max 3 failures/site/year) over 15 years.
Training: provide technical maintenance training to 8 personnel per station, in English, with competency assessments and certification; complete before SAT.
15-year Maintenance and Support Contract: prices only in Volume 1C; quarterly invoicing in arrears; submit labour/service rates for local and overseas resources.
PBU: starts at SAT of first site, ends 1 year after SAT of last site; extends by 12 months if performance requirements not met.
Continue with tenders sharing this issuer, category, or province.
Browse categories with current opportunities in this area.
Compare tender activity across provinces.
Explore organisations currently publishing tenders.
Tools and research to help you assess opportunities.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Browse categories with current opportunities in this area.
Compare tender activity across provinces.
Explore organisations currently publishing tenders.
Tools and research to help you assess opportunities.
Date & Time
Friday, 06 November 2026 - 11:00
Venue
Platform/Venue: Microsoft Teams Meeting ID: 321 122 620 256 376 Passcode: sK2in3WM
Important: Attendance at this briefing session is mandatory. Bids from suppliers who do not attend may be disqualified.
Categories
Request for Bid(Open-Tender)
ATNS Company Limited, Eastgate Office Park, Block C, South Boulevard Road, Bruma, 2298 BID SUBMISSIO - Bruma - Bedfordview - 2298
Tenders in this industry often require registration with these bodies.
Recommended Certifications
Having these can improve your winning chances: IITPSA Membership, ISO 27001 (Information Security Management), ISO 20000 (IT Service Management), CISSP
AI Document Analysis Stages
Description
Source: Volume 1A - Fibre Termination Nod.pdf22 Sept
2026
Tender Published
Tender was published
20 Nov
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Volume 2 - Fibre Termination Nod.pdf
Supply, delivery, installation, commissioning, and support of fibre termination nodes at nine ATNS sites (FACT, FAGG, FAPE, FALE, FAEL, FABL, FAKM, FAUP, and ATA). The project includes training, a maintenance and support agreement for the system lifespan, and decommissioning/disposal of existing nodes. The nodes form resilient fibre ring networks supporting monitoring, control, data exchange, and real-time communications.
Volume 1B - Fibre Termination Nod.pdf
Supply, delivery, commissioning, and support of fibre termination nodes at nine sites: Cape Town International (FACT), George (FAGG), Chief Dawid Stuurman International (FAPE), King Shaka International (FALE), King Phalo (FAEL), Bram Fischer International (FABL), Kimberley (FAKM), Upington International (FAUP), and the ATNS Aviation Training Academy (ATA). The project includes decommissioning and disposal of existing nodes, installation, commissioning, training, a 15-year maintenance and support phase, and a mid-life upgrade. The contract is a service level agreement with an 18-year period (3 years acquisition, 15 years maintenance and support).
Volume 1C - Price Schedules - Fibre Node.xlsx
Supply, delivery, commissioning, and support of fibre termination nodes at nine sites (FACT, FAGG, FAPE, FALE, FAEL, FABL, FAKM, FAUP, and the ATA) for the Air Traffic and Navigation Services Company Limited (ATNS). The tender covers equipment, installation, project management, integrated logistic support, a 10-year support contract, mid-life upgrade, and optional items, with pricing in both foreign and local currency.
Volume 4 - Fibre Termination Nod.pdf
Supply, delivery, installation, commissioning, and 15-year support of fibre termination nodes at nine ATNS sites (FACT, FAGG, FAPE, FALE, FAEL, FABL, FAKM, FAUP, and the ATNS Training Academy). The procurement is structured in four phases: development, implementation, validation (PBU), and application, with detailed logistics support, training, spares, and maintenance requirements.
Volume 3 - Fibre Termination Nod.pdf
Analysis completed but response format was invalid
Volume 1A - Fibre Termination Nod.pdf
Supply, delivery, installation, testing, commissioning, training, and lifecycle support of new Fibre Termination Nodes at nine ATNS sites (FACT, FAGG, FAPE, FALE, FAEL, FABL, FAKM, FAUP, and the Air Traffic Academy), including decommissioning of existing equipment and integration with the existing fibre ring network.
To download these documents and access AI-powered analysis, visit the main tender page.
Win ATNS tenders with AI Discovery, aviation-systems intelligence, compliance analysis, and structured support for navigation and training contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
R 11 122 453
Range
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
ATNS is a State-Owned Company providing air traffic management services across South Africa and Africa. This project involves the supply, delivery, installation, testing and commissioning of new Fibre Termination Nodes at FACT, FAGG, FAPE, FALE, FAEL, FABL, FAKM, FAUP and the Air Traffic Academy (ATA). The scope includes system integration, testing, commissioning, training of ATNS technical personnel, provision of technical documentation, lifecycle support, maintenance and support services, and decommissioning of existing equipment. The project forms part of ATNS's infrastructure modernisation programme.
Important Dates
Source: Volume 1A - Fibre Termination Nod.pdf (RFP)Closing date: 06 November 2026 at 11h00 CAT
Compulsory briefing session: 02 October 2026 at 12h00 CAT
Clarification deadline: 15 October 2026 at 17h00 CAT (queries must be submitted using the Form of Questionnaire, Appendix A)
Consolidated answers to queries: 22 October 2026 at 17h00 CAT
Briefing Session
Source: Volume 1A - Fibre Termination Nod.pdf (RFP)A compulsory briefing session will be held on 02 October 2026 at 12h00 CAT via Microsoft Teams (Meeting ID: 321 122 620 256 376, Passcode: sK2in3WM). Attendance is mandatory and verified via attendance registers.
Contact Information
Source: Volume 1A - Fibre Termination Nod.pdf (RFP)Enquiries before bid closure:
Enquiries after bid closure:
General contact (from SBD 1):
Submission address:
ATNS Company Limited
Eastgate Office Park, Block C
South Boulevard Road, Bruma, 2298, South Africa
Submission Guidelines
Source: Volume 1A - Fibre Termination Nod.pdf (RFP)Submission method: online via the National Treasury e-Submission (e-Tender) system, or manual/physical submission. Email submissions will not be accepted.
Physical submission address:
ATNS Company Limited
Eastgate Office Park, Block C
South Boulevard Road, Bruma, 2298, South Africa
Hard copy submissions must include one original, one copy, and one PDF version on USB.
Bids must be submitted in three parcels:
Returnable forms (all must be completed, signed and submitted):
Disqualification risks:
Evaluation Criteria
Source: Volume 1A - Fibre Termination Nod.pdf (RFP)Evaluation is conducted in four stages:
Stage 1 – Administrative: SARS Tax Compliance Status PIN must be valid for 60 days from submission. Failure may lead to rejection, or the bidder may be given 7 days to submit supplementary information.
Stage 2 – Mandatory requirements:
Stage 3 – Functionality/Technical evaluation (scored out of 100):
Stage 4 – Price and Preference Points (90/10 system):
Technical Specifications
Source: Volume 1A - Fibre Termination Nod.pdf (RFP)The project requires the supply, delivery, installation, testing and commissioning of new Fibre Termination Nodes (FTNs) at the following sites: FACT, FAGG, FAPE, FALE, FAEL, FABL, FAKM, FAUP, and the Air Traffic Academy (ATA).
The solution must form part of a resilient fibre ring network architecture supporting critical communications and data exchange between operational systems and ATNS facilities. It must be reliable, secure and scalable for current and future operational requirements.
Scope includes:
Pricing Schedule
Source: Volume 1A - Fibre Termination Nod.pdfThe pricing schedule (SBD 3.2 – Non-Firm Prices) must be completed and signed. It includes items for Project Management, Integrated Logistic Support, Installation and Materials for each site (FALE, FABL, FAKM, FAUP, FAPE, FAEL, FAGG, FACT, ATA), Miscellaneous, Support Contract (Base and Inflated), Mid-Life Upgrade, Options, VAT (15%), and Total Bid Price. Bidders must indicate whether the offer is strictly to specification, whether the price is fixed, and whether delivery and installation period is fixed. For imported goods, the contractor must hedge foreign content within seven days of the purchase order; exchange rate variations are handled as specified.
Financial Requirements
Source: Volume 1A - Fibre Termination Nod.pdf (RFP)Pricing must be submitted on SBD 3.2 (Pricing Schedule – Non-Firm Prices) and the Form of Contract (Volume 1C). The pricing schedule must include all costs; bids without a price or with an incomplete price will be deemed non-responsive.
Pricing schedule items include:
Prices must include all customs and/or other duties, delivery and installation costs. Bids on a c.i.f. or in bond basis may be disqualified.
The contract price for the Acquisition Phase is fixed in Rands. ATNS is not liable for rate of exchange variations; the contractor must hedge foreign content within seven days of the official purchase order. Any exchange rate variation is for the contractor's account.
Bidders must indicate whether the price is fixed, whether delivery and installation period is fixed, and whether the offer is strictly to specification.
Proposals must remain valid for 120 days from submission.
Compliance Requirements
Source: Volume 1A - Fibre Termination Nod.pdf (RFP)CSD registration:
Tax compliance:
B-bbee:
Declaration of Interest (SBD 4) must be completed and signed; bids without it are non-responsive.
OEM certification:
Company experience:
Professional body registrations:
Bidders must not be persons in the service of the state, nor companies/close corporations with directors/members in the service of the state.
Health & Safety
Source: Volume 1A - Fibre Termination Nod.pdfThe project must be executed with safety as a non-negotiable priority. Decommissioning and disposal of existing equipment must be undertaken in accordance with applicable environmental, safety and regulatory requirements.
Environmental
Source: Volume 1A - Fibre Termination Nod.pdfThe project must ensure economic, social, and environmental sustainability. Disposal of existing equipment must comply with applicable environmental regulations.
Contractual Terms
Source: Volume 1A - Fibre Termination Nod.pdfContract terms include:
Requirements
Source: Volume 1A - Fibre Termination Nod.pdf (RFP)Mandatory requirements include: attendance of the compulsory briefing session (verified via Microsoft Teams attendance registers); submission of an official OEM installer/reseller certificate or signed letter of endorsement (unless the bidder is the OEM); and submission of at least one contactable reference letter proving deployment of the proposed fibre termination nodes/industrial switching nodes within the past seven years, with specific details as outlined.
Section
Source: Volume 1A - Fibre Termination Nod.pdfThe bid is evaluated in four stages: Stage 1 Administrative (SARS tax compliance PIN valid for 60 days); Stage 2 Mandatory requirements; Stage 3 Functionality/Technical evaluation scored out of 100 with an overall threshold of 75% and sub-thresholds per volume (Volume 2 Technical Specifications 70% weight, Volume 3 Project Management 15%, Volume 4 Logistics Support 15%); Stage 4 Price and Preference Points using the 90/10 system. Price points are calculated using the formula Ps = 90(1 - (Pt - Pmin)/Pmin). Preference points are allocated for specific goals: 5 points for 51% Black Owned suppliers and 5 points for 30% Black Woman Owned suppliers.
Description
Source: Volume 2 - Fibre Termination Nod.pdfThe project involves supplying, delivering, installing, testing and commissioning new fibre termination nodes at nine sites (FACT, FAGG, FAPE, FALE, FAEL, FABL, FAKM, FAUP, ATA). The nodes form a resilient, low-latency fibre ring network supporting monitoring, control, data exchange and real-time communications. The scope also includes training technical personnel, a maintenance and support agreement for the system's lifespan, and decommissioning/disposal of existing nodes.
Important Dates
Source: Volume 2 - Fibre Termination Nod.pdf (RFP)Closing date: 6 November 2026 at 11:00
Submission Guidelines
Source: Volume 2 - Fibre Termination Nod.pdf (RFP)Responses must be submitted in English, following the format in the General Information and Instructions to Bidders document. Bidders must respond in full to each technical requirement, referencing supporting documents (chapter, section, page, paragraph). Responses that are unclear, inadequate, or missing will be marked 'Not Compliant'.
Returnable documents:
Disqualification risks:
Evaluation Criteria
Source: Volume 2 - Fibre Termination Nod.pdf (RFP)Bidders must declare compliance for each requirement as:
Mandatory requirements (marked 'M') must be met; non-compliance leads to disqualification. Desirable requirements (marked 'D') are scored. Responses must be complete and address each requirement; inadequate responses are treated as 'Not Compliant'.
Technical Specifications
Source: Volume 2 - Fibre Termination Nod.pdf (RFP)Scope: Supply, deliver, install, test and commission fibre termination nodes at FACT, FAGG, FAPE, FALE, FAEL, FABL, FAKM, FAUP and ATA. Includes training of technical personnel, maintenance and support agreement for system lifespan, and decommissioning/disposal of existing nodes.
Node quantities per site:
General requirements:
Fibre termination node specifications:
Legacy interfaces:
Compliance Requirements
Source: Volume 2 - Fibre Termination Nod.pdf (RFP)No specific compliance requirements stated in this volume (Volume 2 – Technical Specifications). Refer to Volume 1 for general instructions and compliance obligations.
Health & Safety
Source: Volume 2 - Fibre Termination Nod.pdfElectrical work must comply with South African National Standards (SANS). Surge protection devices must be provided per SANS. A Certificate of Compliance (COC) for all electrical work is required after commissioning at each site.
Contractual Terms
Source: Volume 2 - Fibre Termination Nod.pdfThe information in this document is confidential to ATNS and may only be used for preparing a response. It must not be disclosed to third parties without ATNS's written consent.
Section
Source: Volume 2 - Fibre Termination Nod.pdfBidders must declare compliance for each requirement as C (fully compliant, 2 points), PC (partly compliant, 1 point), or NC (not compliant, 0 points). Mandatory requirements must be met or the bid is disqualified. Responses must be complete and address each requirement; inadequate responses are treated as 'Not Compliant'.
Description
Source: Volume 1B - Fibre Termination Nod.pdfThe project involves the supply, delivery, commissioning, and support of Fibre Termination Nodes at nine sites: FACT, FAGG, FAPE, FALE, FAEL, FABL, FAKM, FAUP, and the ATA. This volume (1B) contains the conditions and form of contract (Service Level Agreement).
Contact Information
Source: Volume 1B - Fibre Termination Nod.pdf (RFP)No specific contact details are provided in this volume.
Submission Guidelines
Source: Volume 1B - Fibre Termination Nod.pdf (RFP)Returnable documents — all must be completed, signed and submitted with the bid:
Submission method: as specified in the tender documents (not detailed in this volume).
Disqualification risks:
Evaluation Criteria
Source: Volume 1B - Fibre Termination Nod.pdf (RFP)Evaluation will follow the PPPFA preference point system (80/20 or 90/10) as applicable.
Bidders must meet all mandatory requirements to be considered.
Preference points are claimed via SBD 6.1.
B-BBEE status level will be used to score preference points.
No minimum qualifying score is stated in this volume.
Technical Specifications
Source: Volume 1B - Fibre Termination Nod.pdf (RFP)Scope: Supply, delivery, commissioning, and support of Fibre Termination Nodes at:
Fibre Termination Nodes are managed industrial switching devices for traffic switching, multiplexing, and distribution, forming a resilient, deterministic, low-latency fibre ring network.
Project includes:
Contract period: 18 years total — 3 years acquisition phase (2 years acquisition + 1 year PBU) and 15 years maintenance and support phase.
System lifecycle: 15 years from acceptance.
Acceptance testing: FAT, SAT, Substantial Completion, and Final Acceptance required.
Quality Management
Source: Volume 1B - Fibre Termination Nod.pdfAcceptance testing and inspection requirements:
Financial Requirements
Source: Volume 1B - Fibre Termination Nod.pdf (RFP)Pricing: Fixed price or price subject to adjustment as per contract; price schedule (Schedule A) indicates total contract price.
Milestone payments: Based on measurable achievements, paid 30 days after presentation of a correct invoice.
Performance Guarantee: A bank guarantee for full and due performance of the contract is required.
Liquidated and ascertained damages: Applicable for delays (details in contract).
Insurance: Contractor must maintain appropriate insurance (details in contract).
Rates of exchange: Variations may apply if foreign currency is involved.
Compliance Requirements
Source: Volume 1B - Fibre Termination Nod.pdf (RFP)B-BBEE: Bidders must comply with the B-BBEE Act and Codes of Good Practice. B-BBEE status level is used for preference points (SBD 6.1).
Local content: Declaration required via SBD 6.2; local content is that portion of the price not imported.
Legal compliance: Contractor must comply with all applicable South African legislation, including customs, taxes, and anti-dumping duties.
Data sovereignty: Assurances and safeguards required for data handling.
Anti-bribery and anti-corruption: Contractor must comply with anti-bribery and anti-corruption provisions.
No CIDB grading or CSD registration is stated in this volume.
Health & Safety
Source: Volume 1B - Fibre Termination Nod.pdfSafety: Contractor must comply with all safety regulations, including those at operational airports. Work in airport security areas requires adherence to security and safety protocols. Additional requirements for construction activities, barricades, lights, markings, dust and pollution control are specified.
Contractual Terms
Source: Volume 1B - Fibre Termination Nod.pdfContract form: Service Level Agreement.
Contract period: 18 years — 3 years acquisition phase (2 years acquisition + 1 year PBU) and 15 years maintenance and support phase.
Guarantee period: Minimum 12 months from acceptance of each part.
Period of Beneficial Use (PBU): At least 12 months from site acceptance to final acceptance.
Acceptance testing: FAT, SAT, Substantial Completion, and Final Acceptance required. Contractor must give 14 days' notice before testing. Rehearsal acceptance required before notifying Engineer.
Interim Acceptance Certificate: May be issued for minor defects; rectification within 5 days.
Milestone payments: Paid 30 days after correct invoice, following acceptance.
Performance Guarantee: Bank guarantee for full and due performance.
Liquidated damages: Applicable for delays.
Force majeure: Defined and may excuse performance.
Termination: ATNS may terminate for default or other reasons as per contract.
Variations: Must be in writing and signed by both parties.
Anti-bribery and anti-corruption: Contractor must comply.
Data sovereignty: Assurances and safeguards required.
Intellectual property: Rights and licensing terms apply.
Confidentiality: Contractor must keep information confidential.
Cession: Contractor may not cede the contract without consent.
Sub-contracting: Subject to ATNS approval.
Insurance: Contractor must maintain appropriate cover.
Indemnity: Contractor indemnifies ATNS against certain claims.
Legal compliance: Contractor must comply with all laws.
Disputes: Resolution mechanism as per contract.
Notices: Must be in writing.
Amendments: Must be in writing and signed.
Accident liability: Contractor indemnifies ATNS for accidents to its employees.
Company property: Must be safeguarded.
Customs clearance: Contractor responsible for import duties and clearance.
Export license: Contractor must obtain necessary licenses.
Extension of time: Possible under certain conditions.
Incorrect information: If provided, may lead to termination.
Incapacity, death, sequestration, liquidation, business rescue: May affect contract.
Inspection, tests, analyses: ATNS may inspect and test.
Liability: Contractor liable for breaches.
ILSP: Integrated Logistic Support Plan required for 15-year lifecycle.
Failure to comply: May result in penalties or termination.
Options: ATNS may have options for additional quantities.
Operational airports: Work at operational airports with security restrictions.
Airport management and ATC: Coordination required.
Radio communication: Must comply with airport procedures.
Airport security: Must comply with security regulations.
Movement on airport: Must follow rules.
Construction activities: Additional requirements apply.
Identification numbers: Must be displayed.
Crossing points: Must be used.
Barricades, lights, markings: Required.
Dust and pollution: Must be controlled.
Orders: Must be followed.
Equipment: Must meet specifications.
Services: Must be provided as per contract.
Customs duties and surcharges: Contractor responsible.
Spares: Must be provided as per ILSP.
Documentation: Must be supplied as per CDRL.
Training: Must be provided for operating and maintenance staff.
Test equipment: Must be provided.
Acceptance test: As per procedures.
Price adjustment: Allowed if prices not fixed.
Statutory cost adjustments: May apply.
Price lists: Must be provided.
Total contract price: As per price schedule.
Method of payment: Milestone payments.
Rates of exchange: Variations may apply.
Programme: Must be submitted.
Packing: Must be adequate.
Participation in installation: Contractor must participate.
Procurement outside contract: Not allowed without consent.
Precedence: Order of precedence defined.
Performance: Must meet performance requirements.
Conduct of contract: Must act in good faith.
Quantities: May vary.
Quality: Must meet specifications.
Care of works: Contractor responsible.
Risk: Passes to ATNS upon acceptance.
Business continuity and disaster recovery: Plans required.
Relaxation: Not a waiver.
Services available: As per contract.
Site: Access and conditions.
Clearance of site on completion: Required.
Substitution for local products: Not allowed without consent.
Superintendence: Contractor must supervise.
Sub-contractors: Subject to approval.
Statements of supplies and services: Must be submitted.
Security: Must comply.
Safety: Must comply with OHS.
Taxes, levies, duties: Contractor responsible.
Anti-dumping duties: Must be paid.
Transport: Contractor responsible.
Termination: As per contract.
Default: Remedies available.
Miscellaneous matters: As per contract.
Variations: Must be in writing.
Anti-bribery and anti-corruption: Must comply.
Section
Source: Volume 1B - Fibre Termination Nod.pdfNo additional evaluation criteria are detailed in this volume beyond the standard PPPFA preference point system and mandatory compliance requirements.
Description
Source: Volume 1C - Price Schedules - Fibre Node.xlsxThe project involves the supply, delivery, commissioning, and support of fibre termination nodes at multiple sites (FACT, FAGG, FAPE, FALE, FAEL, FABL, FAKM, FAUP, and ATA). The pricing schedule covers equipment, installation, project management, integrated logistic support, a 10-year maintenance contract, mid-life upgrade, and optional items.
Submission Guidelines
Source: Volume 1C - Price Schedules - Fibre Node.xlsx (unknown)Returnable documents: the completed pricing schedule Excel workbook (Volume 1C) with all sheets filled in, including the G1 Summary, G2.1 PMP, G2.2 ILS, G3.1 to G3.9 per site, G4 Miscellaneous, G5.1 Support Contract (Base), G5.2 Support Contract (Inflated), G5.3 Mid-Life Upgrade, and G6 Options. VAT must be clearly indicated on the G1 Summary sheet. The bidder is responsible for verifying quantities, pricing, calculations, and totals in the submitted pricing schedule.
Evaluation Criteria
Source: Volume 1C - Price Schedules - Fibre Node.xlsx (unknown)Bidders must complete the pricing schedule in the provided Excel workbook. The document does not specify additional eligibility criteria such as CSD registration, tax clearance, B-BBEE level, CIDB grading, or local content percentages. Bidders must be able to provide items at no cost if priced at zero with a quantity greater than zero.
Technical Specifications
Source: Volume 1C - Price Schedules - Fibre Node.xlsx (unknown)Supply, delivery, commissioning, and support of fibre termination nodes at the following sites: FACT, FAGG, FAPE, FALE, FAEL, FABL, FAKM, FAUP, and ATA. Equipment per site includes fibre termination nodes of various port counts (e.g., 2, 6, 8, 12, 16, 22, 24, 32 ports), serial interface converters (RS232), 4-wire E&M gateways, 3kVA UPS, fibre patch cables, power cables, computers and monitors, 19-inch equipment racks, and software licences. Installation and integration services are required at each site. A 10-year maintenance contract is required, with base and inflated cost schedules. Mid-life upgrade costs must be provided. Optional items are listed separately.
Financial Requirements
Source: Volume 1C - Price Schedules - Fibre Node.xlsx (unknown)Pricing must be submitted in the provided Excel workbook, with separate columns for foreign and local items. A rate of exchange (ROE) of 1R = 0.1 is indicated. VAT (15%) must be shown on the G1 Summary sheet. Items with a quantity greater than zero and a cost of zero will be supplied at no cost to ATNS.
Compliance Requirements
Source: Volume 1C - Price Schedules - Fibre Node.xlsx (unknown)No specific requirements found
Description
Source: Volume 4 - Fibre Termination Nod.pdfThis document defines the minimum logistic support requirements for the supply, installation, commissioning, and operational acceptance of Fibre Termination Nodes at multiple ATNS sites. It describes the Logistic Support (LS) system required for total support during implementation and post-implementation until end of economic life. The maintenance model must integrate with existing ATNS processes and align with the ATNS maintenance and support concept.
Contact Information
Source: Volume 4 - Fibre Termination Nod.pdf (RFP)No contact details are provided in this document.
Submission Guidelines
Source: Volume 4 - Fibre Termination Nod.pdf (RFP)Submission method: as per the General Information and Instructions to Bidders document, in English.
Returnable documents (Phase 1A – Development):
All responses must be in the format provided, with references (chapter, section, page, paragraph) to supporting documents. Responses that are unclear, inadequate, or missing will be marked 'Not Compliant'.
Compliance declaration: For each paragraph, declare C (fully compliant, 2 points), PC (partly compliant, 1 point), NC (not compliant, 0 points), or Noted (for information-only paragraphs). For PC or NC, provide a statement of variation and supporting information.
Mandatory requirements (marked 'M') must be fully compliant; non-compliance disqualifies the bid.
Bidders must provide a compliance statement confirming all obligations will be met if appointed.
Evaluation Criteria
Source: Volume 4 - Fibre Termination Nod.pdf (RFP)Evaluation is based on compliance declarations for each requirement. Mandatory (M) requirements must be met or the bid is disqualified. Desirable (D) requirements are scored: C=2, PC=1, NC=0. Information (I) and Optional (O) requirements are not scored but must be responded to.
No minimum qualifying score is stated. No preference point system (80/20 or 90/10) is mentioned in this volume.
Methodology
Source: Volume 4 - Fibre Termination Nod.pdfImplementation phases:
Support concept: Three-tiered (Operator, Intermediate, Depot) support model.
PBU: Starts from SAT of first site, ends one year after SAT of last site. During PBU, warranty and verification of Phase 1 and 2 deliverables run concurrently. ATNS technical personnel maintain the system, but the Contractor remains responsible until end of PBU.
Pricing Schedule
Source: Volume 4 - Fibre Termination Nod.pdfPricing for the Maintenance and Support Contract must be provided only in Volume 1C. Other support contract aspects (excluding pricing) in Volume 4.
Quarterly invoicing in arrears.
Submit a schedule of all labour and service rates for local and overseas resources, for normal working hours, weekends, and public holidays.
Financial Requirements
Source: Volume 4 - Fibre Termination Nod.pdf (RFP)Pricing: Detailed prices for the Maintenance and Support Contract must be provided only in Volume 1C. Other support contract aspects (excluding pricing) in Volume 4.
Invoicing: Quarterly invoicing in arrears for maintenance and support.
Service and labour rates: Submit a schedule of all labour and service rates for local and overseas resources, for normal working hours, weekends, and public holidays.
No bid security, performance bond, or guarantee percentages are stated in this document.
Compliance Requirements
Source: Volume 4 - Fibre Termination Nod.pdf (RFP)No specific compliance requirements (e.g., CSD, tax, B-BBEE, CIDB) are stated in this document. Bidders must comply with all mandatory (M) requirements in the specification.
Health & Safety
Source: Volume 4 - Fibre Termination Nod.pdfNo specific health and safety requirements are stated in this document.
Contractual Terms
Source: Volume 4 - Fibre Termination Nod.pdfConfidentiality: Information provided in the tender document is confidential and must only be used for preparing a response.
Support Contract: A 15-year Maintenance and Support Contract proposal is required, signed concurrently with the system acquisition contract, commencing at the end of PBU.
System Performance Guarantee: The Support Contract must guarantee the system performance requirements (Section 5.1) for the complete system lifespan.
Software & Hardware Support: The Support Contract must cover the complete turnkey system, including third-party hardware and software corrections.
System to maintain current status: The Contractor must ensure the system is always equipped with the latest software and firmware versions throughout its 15-year lifespan.
PBU extension: If performance requirements are not met, PBU will be extended by 12 months.
Deficiency correction: Any deficiencies in Phase 1 and 2 deliverables during PBU are corrected at the Contractor's cost.
Warranty: Covers repairs, modifications, replacements of hardware, software, firmware, and correction of system errors not detected during FAT and SAT.
Section
Source: Volume 4 - Fibre Termination Nod.pdfEvaluation is based on compliance declarations. Mandatory (M) requirements must be met or the bid is disqualified. Desirable (D) requirements are scored: C=2, PC=1, NC=0. No minimum qualifying score is stated.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 4 of 2013
Relevant where personal information, data systems, biometrics, records or citizen information may be processed.
Relevant because this tender appears to involve ICT systems, software, digital services, or public-sector technology procurement.
Act 88 of 1998
Relevant to public-sector ICT procurement and government technology acquisition routes.
Relevant because this tender appears to involve ICT systems, software, digital services, or public-sector technology procurement.
Act 25 of 2002
Relevant to electronic transactions, digital procurement channels, e-signatures and online service delivery.
Relevant because this tender appears to involve ICT systems, software, digital services, or public-sector technology procurement.
Address
ATNS Company Limited, Eastgate Office Park, Block C, South Boulevard Road, Bruma, 2298 BID SUBMISSIO - Bruma - Bedfordview - 2298
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
6
Last checked
08 Nov 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Learn how to submit a winning bid with these related articles
South Africa's metros are evolving. Learn how to position your ICT firm for high-value smart city infrastructure and digital transformation contracts.
A guide for IT companies to navigate the dual procurement paths of the State Information Technology Agency (SITA) and the Gauteng Department of Education (GDE).
Avoid disqualification with our technical compliance checklist for IT bids. From OEM authorizations to POPIA and ISO standards.
Win government telecom contracts including fiber rollout, network infrastructure, mobile services, and broadband projects. ICASA licensing and compliance.
💡 Want more tendering tips and strategies?