Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
Lower Germiston Road - Rosherville - Johannesburg - 4000
Organization Type
GOVERNMENT
Published
04 Sept 2026
OCDS Reference
ocds-9t57fa-169021
ESKOM is inviting tenders for the refurbishment and upgrading of the electrical protection system at its corona cage test facility in sunninghill, gauteng, over a 12-month period. The work includes design, engineering, supply, installation, testing, commissioning and handover of a new protection system, a 110v dc battery and charger system, and all associated cabling, with a minimum 12-month warranty. Bidders must achieve a minimum functionality score of 70% and be registered on the csd prior to award.
Closing date and time: 08 October 2026 at 10h00 SAST, submitted electronically via the Eskom E-Tendering site; no hard copies accepted.
Non-compulsory clarification meeting: 15 September 2026 at 10h00 SAST via Teams; bidders must confirm attendance with the Eskom Representative.
Mandatory returnables at closing (disqualifiable if missing): Authorisation Form (Annexure A), Acknowledgement Form (Annexure B), Tenderer's Particulars (Annexure C), Integrity Pact Declaration (Annexure D), SBD 1 (Annexure H), SBD 4 (Annexure J), and SBD 6.2 local content declarations (Annexures G1-G4).
SBD 6.1 Preference Points Claim (Annexure I) must be submitted at closing for evaluation; failure to submit results in zero points for specific goals but not disqualification.
Tax compliance: provide SARS e-filing PIN or CSD number; otherwise a certified tax clearance certificate is required. Foreign suppliers with no SA footprint need only complete SBD 1.
CSD registration is mandatory prior to contract award; proof of CSD number/report required.
Functionality/technical threshold: minimum weighted final score of 70% to be considered; technical evaluation criteria are detailed in Annexure K.
Evaluation: 80/20 preference points system (price scored out of 80, specific goals out of 20) for tenders valued at or below R50 million.
Pricing schedule must be submitted in PDF and Excel format; upload size per document limited to 500 MB, total submission 4 GB; no zip files.
Tender validity period: 180 days from closing date.
Contract conditions: NEC (New Engineering Contract) will apply; no performance security required.
Warranty: minimum 12 months on the protection system from final commissioning and acceptance.
The new protection system must comply with IEC 60255, IEC 61850, IEC 61439, IEC 62208, IEC 60529, IEC 60445, IEC 61869, IEC 62485, IEC 61936-1, ISO 9001, SANS 1652:2023, SANS 62259:2005, SANS 1507, and the Occupational Health and Safety Act.
The DC system must provide a minimum 4-hour standby autonomy and 20% spare capacity.
All cabling must be new (existing cabling not reused) and comply with SANS 1507 standards series.
Bidders must not be restricted by Eskom, National Treasury, or on any sanctions list; must not have a conflict of interest; must not submit more than one tender; JV/consortium agreements must state joint and several liability.
Subcontracting 100% of the scope of work is not allowed; subcontracting with subsidiary companies must be declared.
Queries must be addressed in writing to the Eskom Representative, Monica Shuping ([email protected]), before 5 working days prior to closing.
Eskom payment terms: within 30 days for contracts below R50 million (incl. VAT), within 60 days for above R50 million.
Continue with tenders sharing this issuer, category, or province.
Return to this tenderβs issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Thursday, 08 October 2026 - 10:00
Venue
MS TEAMS
Categories
Request for Bid(Open-Tender)
Lower Germiston Road - Rosherville - Johannesburg - 4000
Tenders in this industry often require registration with these bodies.
Construction Industry Development Board (CIDB) registration is mandatory for almost all public sector construction tenders. Ensure your grading matches the tender value.
Recommended Certifications
Having these can improve your winning chances: NHBRC Registration, ISO 9001:2015 (Quality Management), ISO 14001:2015 (Environmental Management), ISO 45001:2018 (Occupational Health & Safety), SACPCMP Registration, ECSA Registration
AI Document Analysis Stages
Important Dates
Source: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage.zip (TENDER)04 Sept
2026
Tender Published
Tender was published
08 Oct
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage.zip
Eskom Holdings SOC Ltd invites tenders for the refurbishment and upgrading of electrical protection systems and associated components at the Eskom Research Corona Cage Test Facility in Sunninghill, Gauteng, over a twelve-month period. The work includes design, engineering, supply, installation, testing, commissioning, and handover of a new protection system for the high-voltage test facility.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
RΒ 3Β 155Β 171
Range
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically β no action required from you.
{"closingDate":"04 September 2026","closingTime":"10h00","briefingSession":"{"date":"15 September 2026","time":"10h00","venue":"ion A non-compulsory clarification meeting with representatives of","is_compulsory":true}"}
Contact Information
Source: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage.zip (TENDER){"name":null,"email":"[email protected]","phone":"017 779 8699","department":null,"address":"r which may be"}
Submission Guidelines
Source: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage.zip (TENDER)Returnable Documents: File name: Annexure I - SBD 6.1 Preference Points Claim Form in terms of The PPR 2022, A1 Technical/Project Schedule 20 All activities listed in order = 5, Few A program with the order in which irrelevant activities or few missing = 4, 1.1 60 main activities will be done Missing a lot of activities or mostly irrelevant = 2, no submission = 0 Duration makes sense with all activities = 5, Time durations of main activities Duration makes sense but missing few 1.2 40 from start to end activities = 4, Most duration does not make sense = 2, No duration specified = 0 A2 Method statements 30 2.1 Relevancy of method statements 100 Relevant, well detailed and all required with a description of how the main submitted = 5 (if any irrelevant submitted, activities will be constructed to be ignored), Missing 20% of the required or few important steps/activities missed = 4, Mostly irrelevant submitted and with very few relevant or basic submitted =2, Irrelevant or none provided = 0 A3 List of Subcontractors 10 3.1 Any company supplying material, 40 All companies with all relevant material, plant and equipment that the plant and/or equipment listed = 5, Few contractor may hire. List company supplies missing = 4, Only companies with the material, plant and listed or only material listed = 2, No equipment which they are supplying submission = 0 3.2 Specify if there will be any 60 Specified if there will be a subcontractor company/contractor performing any and specified which construction work or construction work not done by the specified no subcontractor = 5, Only main contractor specified if there will be a Subcontractor = 2, None provided = 0 A4 List of Tools, Plant and Machinery 10 4.1 All relevant tools and machinery to 100 All relevant listed and indicated if owned = be used during the project owned by 5, Few missing = 4, Mostly irrelevant = 2, the contractor. (All hired to be None provided = 0 included in the list of subcontractor) A5 Relevant company experience 20 List of relevant and comparable >5 Projects = 5; 4 to 2 projects = 4; 1 5.1 60 previous projects executed project = 2; none successfully Well defined project scope, completion Including project scope, completion 5.2 40 date and client contact person details date and client contact person and provided (When all 3 requirements are details provided) = 5; When any of project scope, completion date or client contact person and details is missing (When only 2 requirements are provided = 4; When one of project scope, completion date and client contact person and details is provided (When only one of the requirements is provided) = 2; None provided = 0 A6 Qualifications and experience of key 10 personnel CVs of Project Manager, Site All required CVs provided = 5; Missing 1 6.1 Manager/Site Agent and Site 40 CV = 4; Only 1 CV submitted = 2; none Supervisor provided = 0 All personnel meet the minimum CVs to include academic qualification and experience = 5. (All key qualifications and experience of key personnel to meet minimum requirements 6.2 personnel detailing relevant project 30 to achieve maximum score); Any of the key specific work experience personnel not meeting the required qualification and experience = 2 All qualifications mentioned in 6.1 & 6.2 provided = 5 (if all certified = 5 and not Proof/copies of certified academic certified = 0) βUncertified documents 6.3 30 qualifications cannot be verified and therefore will results in documents not being acceptedβ. TOTAL, 6. TECHNICAL EVALUATION CRITERIA FOR THE COMMISSIONING OF THE ELECTRICAL PROTECTION SYSTEM Each item will be assigned a score by the Eskom evaluation team using 5. The score for each item will be multiplied by its weight to obtain the total score per item. Table 5: Scoring for Contractor Commissioning Score Description 10 Deemed to fully meet requirements 7 Deemed to mostly meet requirements 2 Deemed as substantially not meeting requirements 0 Nonresponsive Note: Scores will be allocated in the range 0 - 10 with the above as a guideline The quality criteria will be adjudicated as a weighted score out of 100% and will comprise of scoring in the categories as defined in table 6. Each category has a minimum threshold score of 80%. Table 6: Installation, Testing & Commissioning Capability Criteria Threshold Score Sub- Category Item Weighting Score (%) Weight >80% 1. Engineering, 20% >80% 2. Procedure for Commissioning 20% >80% 3. Schedule for Commissioning 20% >80% 3.1 Tools, Test Equipment, Software 30% >80% 3.2 Training Courses 10% 40% >80% 3.3 Related Experience and references 60% Score 100% Copied by: Matimba Mathebula Date: 20 May 2026
Evaluation Criteria
Source: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage.zip (TENDER)Tenderers will be evaluated in stages. First, mandatory returnables are checked for completeness and compliance at closing. Non-submission or incomplete mandatory documents may lead to disqualification, but Eskom may request missing returnables within 5 working days if not submitted at closing. After that, functionality/technical criteria are assessed. The extracted text indicates a scoring method for project references: if all three requirements (project scope, completion date, client contact details) are provided, the score is higher; if only two are provided, score = 4; if only one is provided, score = 2. The exact weightings and pass marks are not fully extracted. Contractual requirements (e.g., CSD registration) are assessed after evaluation and ranking, and proof must be submitted prior to award. Failure to meet contractual requirements may result in disqualification. Additional evaluation criteria may include B-BBEE status and other prescribed requirements.
Technical Specifications
Source: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage.zip (TENDER)Annexure Attached (Y /
N / n/a)
1.1.1 *Authorisation Form Annexure A Y
1.1.2 *Acknowledgement form Annexure B Y
1.1.3 *Tendererβs particulars Annexure C Y
1.1.4 *Integrity Declaration Form (Suppliers are required to Annexure D Y
download and read the Supplier Integrity Pact. It is
accessible on the Eskom Tender Bulletin via Eskom
Supplier Integrity Pact (eskom.co.za) link)
1.1.5 *CPA Requirements for Local Goods/Services Annexure E N/A
1.1.6 *CPA(IG) for Foreign Goods/Services (if applicable) Annexure F N/A
1.1.7 SBD 6.2 Declaration Certificate for Local Production Annexure G1 Y
and Local Content (only applicable if designated
materials are included and then Tenderers will be
required to complete and submit Annexures G1 to
G4 as evidence of compliance with this
requirement).
Annexure C Local Content Declaration- Summary Annexure G2 Y
Schedule
Annexure D Imported Content Declaration β Supporting Annexure G3 Y
Schedule to Annexure C
Annexure E Local Content Declaration- Supporting Annexure G4 Y
Schedule to Annexure C
1.1.8 *SBD 1 Invitation to Bid must be filled out by all Annexure H Y
tenderers and submitted with the tender at tender
submission deadline
1.1
Eskom Research, Testing and Development (RT&D) owns and operates a Corona Cage test facility
located in Sunninghill, near the Megawatt Park Head Office. The facility is one of approximately four
such installations worldwide and is unique in that it is situated at a relatively high altitude of
approximately 1550 m above mean sea level. The facility was constructed in 1981 to support the
technical development and validation work required for South Africaβs first 765 kV AC transmission
lines (AlphaβBeta project).
The main design parameters that are investigated at the Corona Cage facility are corona power loss
(CPL), radio interference voltage (RIV) and corona generated audible noise (AN). At the time of
construction several technical issues related to corona performance at high altitude was not fully
understood, hence the need to conduct actual full-scale testing.
The facility steps up 11 kV AC incoming supply to a maximum of 800 kV AC using two special design
corona testing transformers, with a voltage regulation facility provided by a variac system. The
electrical protection of the primary plant is currently provided by an old protection scheme housed in
a single panel which is located indoor within the facility.
This document provides the functional and performance requirements for the design/engineering,
supply, installation, testing, commissioning, and handover of a new dedicated protection system for
this single-phase high-voltage (max 800kV) corona cage testing facility.
2.1 Scope
The Contractor shall:
a) provide a complete, end-to-end Corona Cage Facility Protection System solution. This shall
include, as a minimum, detailed design and engineering, manufacture, factory acceptance testing
(FAT), delivery, site installation, site acceptance testing (SAT), commissioning, training, and final
handover documentation.
b) provide the design, supply, installation, testing, and commissioning of a dedicated DC supply
system to power the protection panel
c) provide the decommissioning and removal from existing room/facility to a new location as
provided by Eskom, the existing/old protection system, including the existing DC equipment and
all the associated old cabling.
d) Prove the relocation of the existing facility monitoring panel from the existing location to a new
temporary location, and later for the temporary location to a new room (to be constructed by
others)
e) Provision of all associated Low Voltage protection, control, communication, and power cabling
required to achieve a fully functional and operational protection system.
2.1.1 Purpose
The purpose of this document is to define the functional and performance requirements for the
design, supply, installation, testing, commissioning, and handover of a dedicated protection system
for a single-phase high-voltage corona cage testing facility. The facility steps up an 11 kV supply to
approximately 800 kV using transformers, with voltage regulation provided by a variac system.
2.1.2 Applicability
This document shall apply to the Eskom Research Corona Cage Test Facility Protection System
replacement project.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30
Functional Specification for Eskom Corona Cage Unique Identifier: 559-1188133888
Protection System Revision: 1
Page:
2.1.3 Effective date
Effective from the date of authorization.
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
[1] ISO 9001 Quality Management Systems
[2] IEC 60255 series β Measuring relays and protection equipment (Performance, safety, EMC,
functional requirements, and disturbance recording)
[3] IEC 61850 β Communication networks and systems for power utility automation
[4] IEC 61439 β Low-voltage switchgear and controlgear assemblies
[5] IEC 62208 β Empty enclosures for low-voltage switchgear and controlgear assemblies
[6] IEC 60529 β Degrees of protection provided by enclosures (IP Code)
[7] IEC 60445 β Identification of terminals, conductors, and wiring
[8] IEC 61869 series β Instrument transformers
[9] IEC 62485 series β Safety requirements for secondary batteries and battery installations
[10] IEC 61936-1 β Power installations exceeding 1 kV AC and 1.5 kV DC
[11] Occupational Health and Safety Act, 1993 (Act No. ) and all applicable Regulations
[12] NRS002 Graphical Symbols for Electrical Diagrams
2.2.2 Informative
[1] 240-65336348 - Standard for Transmission and Distribution Protection Schemes- Common
appointment or election of,
directors of that company who control a majority of the votes at a meeting of the board;
(b) in the case of a juristic person that is a close corporation, that first person owns the majority
of the membersβ interest, or controls directly, or has the right to control, the majority of
membersβ votes in the close corporation;
C
of Full Title of Source Base Base
Reference portions/Weightings Index Index as Publisher Month Price/Base
of each index published of Index Index
Figure
A1
A2
A3
15% Fixed portion not subject to CPA
Total 100%
Note: Tenderers to take note that, if the Eskom proposed CPA breakdown is not populated,
they are required to refer to the Pricing Schedule in the NEC or other Contract or
standalone Pricing Schedule for Eskomβs proposed CPA breakdown.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 2
of Full Title of Source Base Base
Reference portions/Weightings Index Index as Publisher Month Price/Base
of each index published of Index Index
Figure
A1
A2
A3
15% Fixed portion not subject to CPA
Total 100%
Note: Tenderers to take note that, if the Eskom proposed CPA breakdown is not populated,
they are required to refer to the Pricing Schedule in the NEC or other Contract or
standalone Pricing Schedule for Eskomβs proposed CPA breakdown.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 9
of services, works or goods Stipulated minimum threshold
_______________________________ _______%
_______________________________ _______%
_______________________________ _______%
(Tick applicable box)
Yes NO
3..1 If yes, the rate(s) of exchange to be used in this bid to calculate the local content as
prescribed in paragraph 1.5 of the general conditions must be the rate(s) published by SARB
for the specific currency at 12:00 on the date of advertisement of the bid.
The relevant rates of exchange information is accessible on www.reservebank.co.za
Indicate the rate(s) of exchange against the appropriate currency in the table below (refer to
Annex A of SATS 1286:2011):
Currency Rates of exchange
US Dollar
Pound Sterling
Euro
Yen
Other
NB: Bidders must submit proof of the SARB rate (s) of exchange used.
threshold for local content the dti must be informed accordingly in order for the dti to verify and in
consultation with the AO/AA provide directives in this regard.
Controlled Disclosure
Bid response documents may be deposited in the bid box situated at (street address)
Bidding procedure enquiries may be directed to technical enquiries may be directed to:
Contact person contact person
Telephone number telephone number
Facsimile number facsimile number
E-mail address e-mail address
Supplier information
Name of bidder
Postal address
Street address
Telephone number code number
Cellphone number
Facsimile number code number
E-mail address
VAT registration
Number
Supplier tax central
Compliance status compliance supplier
Or
System pin: database
No: MAAA
Are you the
Accredited
REPRESENTATIVE IN ARE YOU A FOREIGN BASED Yes No
SOUTH AFRICA FOR Yes No SUPPLIER FOR THE GOODS
The goods /services offered? [If yes, answer the
/Services [if yes enclose proof] questionnaire below]
Offered?
Questionnaire to bidding foreign suppliers
Is the entity a resident of the republic of south africa (RSA)? yes NO
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 3
File name: Annexure H - SBD 1 - Part A - Invitation to Bid and Part B - Terms and Conditions for Bidding
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 23
Invitation to Tender/ Request Identifier
for Proposal Effective Date 21 February 2025
Review Date February 2030
Does the entity have a branch in the RSA? yes NO
Does the entity have a permanent establishment in the RSA? yes NO
Does the entity have any source of income in the RSA? yes NO
Is the entity liable in the RSA for any form of taxation? Yes NO
If the answer is βNOβ to all of the above, then IT is not a requirement to register for a tax compliance status
System pin code from the south african revenue service (SARS) and if not register as per 2.3 Below.
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 3
File name: Annexure H - SBD 1 - Part A - Invitation to Bid and Part B - Terms and Conditions for Bidding
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 23
Invitation to Tender/ Request Identifier
for Proposal Effective Date 21 February 2025
Review Date February 2030
Part b
Terms and conditions for bidding
1.1. Bids must be delivered by the stipulated time to the correct address. Late bids will not be
Accepted for consideration.
1.2. All bids must be submitted on the official forms provided (not to be re-typed) or in the manner
Prescribed in the bid document.
1.3. This bid is subject to the preferential procurement policy framework act, 2000 and the
Preferential procurement regulations, the general conditions of contract (gcc) and, if
Applicable, any other special conditions of contract.
1.4. The successful bidder will be required to fill in and sign a written contract form (sbd7).
2.1 Bidders must ensure compliance with their tax obligations.
2.2 Bidders are required to submit their unique personal identification number (pin) issued by SARS
To enable the organ of state to verify the taxpayerβs profile and tax status.
2.3 Application for tax compliance status (tcs) pin may be made via e-filing through the SARS website
2.4 Bidders may also submit a printed tcs certificate together with the bid.
2.5 In bids where consortia / joint ventures / sub-contractors are involved; each party must submit
A separate tcs certificate / pin / csd number.
2.6 Where NO tcs pin is available but the bidder is registered on the central supplier database (csd),
A csd number must be provided.
2.7 NO bids will be considered from persons in the service of the state, companies with directors
Who are persons in the service of the state, or close corporations with members persons in
The service of the state.β
Nb: failure to provide / or comply with any of the above particulars may render the bid invalid.
Signature of bidder: ...................................................
Capacity under which this bid is signed: ...................................................
(Proof of authority must be submitted e.g. company resolution)
Date: .................................
Controlled Disclosure
Anonymously report fraud, corruption at 0800 11 2722/ [email protected]
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom
Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 3
File name: Annexure H - SBD 1 - Part A - Invitation to Bid and Part B - Terms and Conditions for Bidding
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
income-generating contracts) shall be
Supply chain management system should this
Declaration prove to be false.
.............................. .....................................................
Signature Date
.............................. ......................................................
Position Name of bidder
Controlled Disclosure
Anonymously report fraud, corruption a
Supply Chain
Management Procedure 32-1034. Any addenda to an issued Invitation to Tender will be
published or issued in the same way as the Invitation to Tender was and will form part of the
Invitation to Tender documents.
Communication 1.5 Every communication between Eskom and a tenderer shall be made to or from the Eskom
Representative only, in w
1.1 Scope
The Eskom Supplier Integrity Pact (Integrity Pact) is applicable to Eskom Holdings SOC Ltd (including all
wholly owned subsidiaries) and all existing and potential suppliers (as per the definition hereunder).
1.2 Purpose
The integrity pact is a pact between Eskom and its suppliers that prescribes the βethical behaviourβ. Ethical
behaviour is desirable/acceptable conduct (actions and decisions) that will bring about good/appropriate
consequences/outcomes in the interaction with others. Ethical behaviour incorporates ethical values and
considers not only what is good for oneself, but also what is good for others. Eskom considers such behaviour
of paramount importance and expects every existing/potential supplier and its own employees/directors to
always act ethically and with integrity.
Eskom commits to ensuring that it implements a procurement policy/procedure that aligns to all applicable
South African laws and regulations, as well as the constitutional principles of fairness, transparency, equity,
cost effectiveness and competitiveness.
This document supplements all other relevant Commercial and Ethics related policies/codes/procedures.
1.3 Preamble
In order to achieve this purpose, all Eskom suppliers are required to read this Integrity Pact and to complete,
sign and submit the Integrity Declaration Form whenever they participate in any Eskom procurement process.
Eskom and its suppliers commit to honouring their respective obligations herein, and agree to refrain from
any form of dishonesty, fraud, and/or corruption throughout the entire procurement process, including
tendering practices that are in bad faith, unfair and anti-competitive (e.g., under-pricing/collusion/bid rigging)
Term Definition
Conflict of Interest A conflict of interest arises when oneβs personal interests, personal
financial interests or any other interests, affect, or could be perceived to
affect, or has the potential to affect oneβs objectivity and discretion and/or
the objectivity and discretion of another in performing Eskom duties or
making decisions on behalf of Eskom. This means that an employee or
director is in a position to make a decision (or influences a decision) that
is not fair and objective in order to benefit personally, or to benefit related
and /or inter-related persons.
Director Means a member of the board of Eskom, or a board of its subsidiary or
an alternate director of such board and includes a person occupying the
position of a director, by whatever name designated, or a prescribed
officer, or a person who is a member of a committee of the board or of
the audit committee, irrespective of whether the person is also a member
of such board.
Public
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third
parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Supplier Integrity Pact Unique Identifier: 240-113650212
Revision: 2
Page:
Employment equity The Employment Equity Act promotes equity in the workplace,
ensures that all employees receive equal opportunities and that
employees are treated fairly by their employers. The law protects a
person from unfair treatment and any form of discrimination.
Employee (s) Also referred to as staff members. These include individuals employed
by Eskom on a permanent basis, contract labour, temporary employees,
part-time employees, casual employees, occasional employees, fixed-
term contractors, learners, and others acting on behalf of Eskom or its
subsidiaries.
Eskom Registered Vendor Means a current or potential supplier who may be a natural or juristic
person and includes any employee of such supplier acting within the
course and scope of his/her employment, or any agent or manager acting
for or on behalf of, or in the interests of the supplier registered as a vendor
on the Eskom Vendor Database.
Supplier Means any natural person or juristic person that does business with
Eskom or tenders to do business with Eskom, or is registered on Eskomβs
Vendor Database, such as consultants, contractors, sub-contractors and
providers of goods and services.
Abbreviation Explanation
DOI Declaration of Interest
ETC EXCO Tender Committee
NDA Non-disclosure agreement
RFP Request for Proposal
RFQ Request for Quotation
Public
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third
parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Supplier Integrity Pact Unique Identifier: 240-113650212
Revision: 2
Page:
4.1 Eskomβs suppliers accept that they will at all times:
4.1.1 Maintain an impeachable standard of integrity in all their business and personal dealings and take all
reasonable measures necessary to prevent all dishonest, unfair, fraudulent, corrupt, and illegal
practices during any stage of the Eskom procurement process including the execution of contracts
and contract modifications.
4.1.2 Ensure that they are familiar with all publicly available Eskom policies/ procedures/codes that impact
the supply chain processes including, but not limited to Eskomβs Standard Conditions of Tender.
4.1.3 Reject all improper business practices (as may be prohibited by Eskom).
4.1.4 Not abuse the trust placed in them by Eskom employees, or misuse opportunities arising during their
interaction with Eskom for personal gain.
4.1.5 Seek to constantly maintain and enhance their standards of professional competence.
4.1.6 Adopt, where possible, policies and practices which align with those of Eskom (labour practices,
employment equity initiatives and human relations policies) to the highest ethical standards.
4.2 Eskomβs suppliers confirm specifically that:
4.2.1 All confidential information, to which they may have access in the course of their work, must not be
disclosed without the express consent from the authorised Eskom representative. The supplier is
required to complete a Non-Disclosure Agreement (NDA) to give effect to this.
4.2.2 They will not deliberately misrepresent information, submit false certifications or forged documents to
influence the tendering process to advantage themselves or to mislead Eskom in any way and that
Eskom has the right to request an audit of such information, and take further action against the supplier
should it be found that it has acted in a dishonest or fraudulent manner.
4.2.3 Although the establishment of long term and close relations between Eskom and its suppliers is
recognised, Suppliers are nevertheless, required to avoid relationships with Eskom
employees//directors, that may be perceived to be contrary to the constitutional principles of fairness,
equitability, transparency, competitiveness, and cost effectiveness. Suppliers are therefore required
to complete the Integrity declaration form wherein they are required to disclose any interest that they
may have with an Eskom employee/director, whether financial, personal, or private, in its business,
and/or any affiliation /relationship which affects, or may affect, or may be perceived to affect, the
decision-making during tender award. Should a supplier later become aware that its
owners/members/directors/partners/shareholders are an Eskom employee/director with respect to a
tender in which it participated, the supplier is required to disclose the interest/relationship to Eskom
and submit whatever information may be required regarding the parties involved.
Public
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third
parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Supplier Integrity Pact Unique Identifier: 240-113650212
Revision: 2
Page:
4.2.4 Although the entertainment of customers and provisions of business courtesies or gifts are generally
an accepted commercial practice, they must not in any way negatively affect Eskomβs image and
reputation. They should not exceed the R1500,00 value prescribed by Eskom and should not be of
such a nature (value or circumstances) as to be construed as placing an Eskom employee/director
under obligation to the supplier or in any way improperly influence the recipient.
4.2.5 They will avoid entering into unethical and/or fraudulent dealings with any Eskom employee/director
involved in the evaluation/adjudication/negotiation of a transaction in which it participates, involving
direct/indirect monetary or material benefits in order to be unfairly benefitted. In such circumstances,
no business courtesy, bribe, gift, fees commission or inducement may be offered to, or requested by
an Eskom employee/director involved in the evaluation/adjudication/negotiation of a transaction in
which the supplier is participating.
4.2.6 They will not enter any dishonest and/or illegal agreement or an understanding with other tenderers
involved in a tender/RFP process in which it participates. They will complete the integrity Declaration
Form which incorporates a Declaration of Fair Tendering Practices, when participating in any Eskom
tender/Request for Quotation (RFQ).
4.2.7 They understand that they may be subject to a supplier discipline process and that sanctions that
may be imposed on suppliers should they be found guilty of misconduct.
4.2.8 Should a supplier become aware of any dishonest, fraudulent or inappropriate behaviour of any Eskom
employee/director; the said supplier is required to report this behaviour to the Eskom Ethics office via
email at [email protected], or via the Eskom Forensic email at [email protected] or through
the Eskom toll free hotline 0800 11 27 22, wherein confidentiality is guaranteed.
5.1 Eskom undertakes to treat all tenderers during the tender process according to the constitutional
principles of fairness, transparency, equity, cost-effectiveness, and competitiveness.
5.2 All Eskom employees/directors are required to complete an annual Declaration of Interest (DOI),
wherein they are required to declare all interests, directorships, memberships, details of any of their
related or inter-related persons or other associates that conduct business with Eskom and all other
material personal interests, whether a conflict exists or not. During the financial year, all Eskom
employees/directors have an option of amending annual DOIs should there be changes in their
interests or what has been disclosed already. In addition to this annual declaration, employees are also
required to complete an additional DOI and NDA if involved in the procurement process.
5.3 Eskom employees will ensure that all gifts received in the normal course of business is declared,
recorded, and authorised by relevant managers. Employees/directors involved in the tender evaluation/
negotiation process, may not accept, demand, or accept a promise of any money, business courtesies,
gifts, rewards, gratuity, favours from any of the tenderers involved to benefit or as may be perceived to
benefit such tenderer. Further to this, employees and directors are prohibited from offering or accepting
loan(s) or other benefit(s) from suppliers, unless the supplier is in the business of granting such loans
or benefits and the terms and conditions of the loan that is offered to the employee/director is also
offered to the general members of the public or a section thereof.
5.4 Should Eskom become aware of any relationship/interest of any employee/director in a tender in which
it is involved in tender evaluation/negotiation process, then this employee/director will be excluded from
the said tender evaluation/negotiation process.
Public
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third
parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Eskom Supplier Integrity Pact Unique Identifier: 240-113650212
Revision: 2
Page:
5.5 Eskom will implement the Supplier Discipline Process if it becomes aware of any contravention of the
provisions of this integrity pact, any other misconduct by a supplier and/or any Eskom
employee/director who acts in bad faith to benefit themselves or a supplier. Eskom has the right, after
following a process of investigation and affording the supplier an opportunity to make representation,
to notify the supplier of the intention to suspend it from the Eskom Vendor Database, impose various
other sanctions and/or institute disciplinary actions against its employees/directors. Subsequently,
Eskom will forward the names of such suppliers including the directors of the company to National
Treasury, who will include the suppliers on the List of Restricted Suppliers on the National Database.
5.6 All Eskom employees/directors are prohibited from having any direct/ indirect personal or other
beneficial interest in any contract with Eskom, whether as a supplier, an advisor or by virtue of being a
director or owner of a business, or in any other capacity. This includes third-party related transactions
with an indirect link to an Eskom contract.
6.1 This Eskom Supplier Integrity Pact is governed by and interpreted in accordance with the laws,
regulations and legislation of the Republic of South Africa.
6.2 The actions stipulated in this Integrity Pact are without prejudice to any other civil or criminal
proceedings that may arise in accordance with the provisions of the law.
6.3 This Integrity Pact shall remain valid until replaced. Should one or more provisions of this Integrity
Pact be regarded as invalid, remainder of the provisions will remain valid.
Public
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third
parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Title: Supplier Quality Management: Document Identifier: 240-105658000
Alternative Reference QM 58
Number:
Area of Applicability: Eskom Holdings SOC Ltd
Functional Area: Quality Management
Revision: 3
Total Pages: 28
Next Review Date: October 2024
Disclosure Controlled Disclosure
Classification:
Compiled by Supported by Functional Authorized by
Responsibility
SA Sambo P Dondashe L Meyer K Pather
Chief Advisor Middle Manager Acting Senior General Manager
Quality Quality Manager Quality Risk and
Management Management Management Sustainability
Date: 15/10/2021 Date: 15/10/2021 Date: 15/10/2021 Date: 17 October 2021
EDC TN Formatted 15.10.2021
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Content
. Introduction ............................................................................................................................... 3
2.1 Scope ............................................................................................................................... 3
2.1.1 Purpose ................................................................................................................. 3
2.1.2 Applicability ........................................................................................................... 3
2.1.3 Effective date ......................................................................................................... 3
2.2 Normative/Informative References ................................................................................... 3
2.2.1 Normative .............................................................................................................. 3
2.2.2 Informative............................................................................................................. 3
2.3 Definitions ........................................................................................................................ 4
2.4 Abbreviations ................................................................................................................... 5
2.5 Roles and Responsibilities ............................................................................................... 6
2.6 Process for Monitoring ...................................................................................................... 6
2.7 Related/Supporting Documents ........................................................................................ 6
3.1 Supplier and Sub-Supplier Quality Management System Requirements .......................... 7
3.2 Quality Plan ...................................................................................................................... 8
3.3 Contract Quality Plan........................................................................................................ 8
3.4 Quality Control Plan ....................................................................................................... 10
3.5 Pre-Contract Award: Quality Requirement ...................................................................... 13
3.6 Main Supplier and Sub-supplier Capability and Capacity Assessment ........................... 16
3.7 Post-Contract Award ...................................................................................................... 17
3.7.1 Contract Execution .............................................................................................. 17
3.7.2 Supplier Quality Performance Monitoring Phase ................................................. 18
3.7.3 Supplier Quality Audit .......................................................................................... 18
3.8 Standard Conditions ....................................................................................................... 19
3.8.1 Rights of Access .................................................................................................. 19
3.8.2 Eskom Rights to Information ................................................................................ 20
3.8.3 Preservation ........................................................................................................ 21
3.8.4 Quality Audits Related Conditions ....................................................................... 25
3.8.5 Management of Nonconformities and Nonconforming Outputs Identified by
Eskom ................................................................................................................. 25
3.8.6 Special Processes ............................................................................................... 26
Acceptance ............................................................................................................................. 27
Revisions ................................................................................................................................ 27
Development Team ................................................................................................................ 27
Acknowledgements ................................................................................................................ 28
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The intention of this specification is to specify and describe the minimum quality requirements for all
existing and potential Eskom suppliers and define the quality criteria for the selection, evaluation,
vendor registration, management, monitoring, assessment and auditing of suppliers. Eskomβs
position is to partner with suppliers who fully demonstrate commitment to the development,
implementation, and maintenance of a quality management system (QMS) that conforms to the
requirements of ISO 9001 standard. The priority is to encourage suppliers to continually improve
their QMS and enhance service delivery by implementing and conforming to the standard.
2.1 Scope
2.1.1 Purpose
The purpose of this specification is to outline the requirements according to which suppliers shall
ο· develop,
ο· implement,
ο· maintain, and
ο· continually improve
a quality management system (QMS) based on ISO 9001, which should form the basis for conformity
to Eskom quality requirements and continually adhere to them throughout the duration of a contract
2.1.2 Applicability
This specification shall apply throughout Eskom Holdings Limited divisions, its subsidiaries,
suppliers, and sub-suppliers and shall form part of all Eskom requests for information (RFI)/ requests
for quotation (RFQ)/ requests for proposal (RFP), including contracts for the procurement of products
and services.
2.1.3 Effective date
Date of authorisation of the specification
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
[1] ISO 9001 Quality Management Systems β Requirements
[2] ISO 10005 Quality Management Systems β Guidelines for Quality Plans.
2.2.2 Informative
[3] ISO 9000 Quality Management Systems β Fundamentals and Vocabulary
[4] 32-727: Safety, Health, Environment, and Quality (SHEQ) Policy
[5] ISO 10006 Quality Management Systems β Guidelines for Quality Management in Projects
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
[6] ISO 9004 Quality Management β Quality of an Organisation β Guidance to Achieve Sustained
Success
[7] 32-1033: Eskomβs Procurement and Supply Chain Management Policy
[8] 32-1034: Eskomβs Procurement and Supply Chain Management Procedure
[9] PPPFA: Preferential Procurement Policy Framework Act, 2000 (Act No. )
[10] CIDB 1004: Best Practice Guideline A4: Evaluating Quality in Tender Submissions
[11] 240-12248652 Supplier Quality Management: List of Tender Returnables
[12] IAEA Safety Standard GS-R-3.1 Application of the Management System for Facilities and
Activities
[13] SANS 10845-1 Construction Procurement Part1: Processes, Methods and Procedures
2.3 Definitions
The vocabulary of ISO 9000 and the following definitions apply in the application of this specification.
2.3.1 Component: a constituent part of the product or sub-assembly of the product. The product
may comprise multiple individual components
2.3.2 Contract Quality Plan: a document of the supplierβs process for delivering the level of quality
required by the contract. It is a framework for the contractorβs process for delivering quality.
Purpose of a CQP is to outline how the results defined in the specifications will be achieved.
2.3.3 Hold Point: a predetermined stage in the quality control plan (QCP) beyond which work/
manufacturing shall not proceed without the attendance of, and written authorisation of, an
Eskom representative or Eskom inspection agency, whichever is applicable.
2.3.4 Intervention Points: those control points indicated by the various controlling bodies
concerned with the implementation of a specific QCP/ ITP. These can be in the form of
inspection, hold points, surveillances, witnesses, reviews and verifications.
2.3.5 Inspection Agency: an organisation or person appointed by Eskom for the purpose of
performing quality assurance/ quality control, monitoring, inspection and/ or expediting
services.
2.3.6 Level 1 Plant Items: equipment, whose failure has an effect on personnel safety and/ or
health, causes an environmental incident, cause a huge production loss or major equipment
damage. Equipment that are safety/ redundancy/ protective device or covered by statutory
regulations requirements.
2.3.7 Level 2 Plant Items: equipment, whose failure impacts plant availability and/or reliability,
causes significant costs or secondary damage.
2.3.8 Level 3 Plant Items: equipment that does not impact on personnel safety and/ or health,
environmental, cost, availability and/ or reliability of plant.
2.3.9 Nonconformity: a deficiency in material, composition, characteristic, or performance that
renders the quality of an item, component, or product unacceptable or indeterminate. The
term also covers a deficiency in, or deviation from/non-adherence to, the quality management
system requirements, prescribed production processes, and/or related documentation such
as procedures and instructions.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
2.3.10 Quality Plan: specification of the actions, responsibilities and associated resources to be
applied to a specific object.
2.3.11 Quality Control Plan: a document specifying the activities to be inspected throughout the
execution of the project, inclusive of test methods, procedures, and acceptance criteria (This
term is equivalent to QIP and ITP).
2.3.12 Requirement: the need or expectation that is stated, generally implied, or obligatory.
Requirements are generally specified in the purchase order and/or contract documentation,
but may not be limited to these.
2.3.13 Primary Plant (Power Plant): primary plant include High Voltage equipment situated inside
the control room (breakers, bus-bars, CTβs, VTβs and transformers).
2.3.14 Secondary Plant (Control Plant): secondary plant includes all equipment used to control
and protect the HV equipment on the primary plant side. (Protection, metering, AC/DC and
tele-control).
2.3.15 Special Process: is any production or service process which generates products or services
which cannot be measured, monitored, or verified prior to delivery and use.
2.3.16 Supplier: is a current or potential supplier, vendor, contractor, consultant, or service provider.
A supplier may be a natural or legal person and includes any employee acting within the
course and scope of his/her employment or any agent or manager acting for, or on behalf of,
or in the interests of, the person registered as supplier on the Eskom supplier database.
2.3.17 Sub-supplier: an organisation that provides a product/service to the supplier and/or that
enters into a subcontract and assumes some of the obligations of the supplier or prime
contractor.
2.3.18 Witness Point: a predetermined stage in the quality control plan where and inspection
activity will take place. Work may proceed, provided Eskom or its inspection agency has been
formally notified and confirmed that inspection is waived.
2.4 Abbreviations
Abbreviation Explanation
AIA Approved Inspection Authority
CA Corrective Action
CQP Contract Quality Plan
FIDIC Federation Internationale Des Ingenieurs- Conseils
FMECA Failure Mode, Effects and Criticality Analysis
HAZOP Hazard and Operability Study
ISO International Organisation for Standardisation
ITP Inspection and Test Plan
NC Nonconformity
NDT Non Destructive Testing
PMI Positive Material Identification
QCP Quality Control Plan
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Abbreviation Explanation
QMS Quality Management System
PQP Project Quality Plan
RFI Request for Information
RFQ Request for Quotation
RFP Request for Proposal
SHEQ Safety, Health, Environment, and Quality
SETA Skills Education Training Authorities
WPS Welding procedure specifications
WQR Welderβs Qualification Record
2.5 Roles and Responsibilities
Eskom Quality representative/ professional will select applicable requirements for existing and
potential Eskom suppliers using Form A (Tender and Contract Quality Requirements for Supplier
Quality Management: Specification 240-105658000/ QM 58 and Quality Requirements for ISO 9001
Standard).
The existing and/ or potential suppliers must complete, sign and return Form A with the other
returnable as listed in the List of Tender Returnable document (240-12248652). Other roles and
responsibilities for this standard are defined within the text of this specification.
2.6 Process for Monitoring
The application of this specification throughout Eskom shall be audited as per the management
system audit schedule.
2.7 Related/Supporting Documents
The documents superseded by this specification: all divisional and business unit supplier quality
requirements standards and/or specifications.
Forms and templates:
[1] 240-68099512 Tender and Contract Quality Requirements for Supplier Quality Management
Specification 240-105658000/ QM 58 and Quality Requirements for ISO 9001 Standard (Form
A)
[2] 240-109253698 Template for a Typical Contract Quality Plan
[3] 240-109253302 Quality Control Plan/Inspection and Test Plan
[4] 240-126469599 Method Statement Template.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The quality assessment criteria and Form A of this specification will be selected and completed by
an Eskom Quality representative/ professional who will identify the applicable supplier quality
requirements to be met.
Form A of this specification must also be completed and signed by the supplier responding to an
Eskom invitation to tender, in order to acknowledge and accept Eskom Supplier Quality requirements
as per this specification and ISO 9001 Standard or any additional quality requirements specific to
the scope of work.
3.1 Supplier and Sub-Supplier Quality Management System Requirements
3.1.1 The supplier and sub-supplier shall develop, implement, maintain and improve a formal QMS
that conforms to the latest ISO 9001 standard or any applicable standard of QMS (latest
applicable revision) and in accordance with the requirements of this specification.
3.1.2 Such a formal system shall consist of the appropriate documented information required by
ISO 9001 and may include a quality manual, quality plans, work procedures, work
instructions, method statements, work flow documentation, etc., as the case may be. This
requirement constitutes the most basic QMS requirements.
3.1.3 Unless specifically excluded from the quality list of tender returnable, as per the categories of
quality requirements (Category 1, 2, 3, or 4), such a QMS shall carry a valid ISO 9001
certificate from an accredited certification body, as indicated in the applicable Eskom
invitation (this requirement applies equally to both the supplier and any/ all manufacturing
third-party organisations mentioned above).
3.1.4 Unless specifically excluded in the quality list of tender returnable, as per the categories of
quality requirements (Category 1, 2, 3, or 4), the supplier shall have a fully developed,
documented, implemented, reviewed and maintained QMS that complies with the
requirements of ISO 9001 standard or any applicable standard of QMS. In the event that the
main supplier invariably requires the assistance of a sub-supplier in order to realise its own
supply obligations. The aforementioned requirement applies equally in all cases where any
such sub-supplierβs scope of responsibility includes the provision of any of the following
activities, namely, design and development, manufacturing, maintenance, testing, storage,
delivery, installation, commissioning, and project management, or in the cases the supplier
name changes, mergers, acquisitions and/ or cessions. Eskom Quality department must
ensure that the changed entity can still fulfil the requirements as set out in the contract
documentation.
3.1.5 Eskom reserves the right to request and perform necessary assessments at sub-supplier
facilities.
3.1.6 The main supplier shall be responsible for defining and managing the specific quality
assurance and control elements applicable to the respective sub-supplierβs scope of
work/supply and ensure that its sub-supplier(s) quality programmes support Eskom
requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.1.7 The supplier shall inform Eskom of any proposed changes to the QMS or staff that will affect
the quality system prior to implementation of these changes.
3.1.8 The main supplier shall develop and implement a performance management programme for
their sub-supplier. The programme shall include, but not limited to:
ο· Verification of the QMS
ο· Audits and surveillances
ο· Regular assessment of the CQPs and reviews of QCPs.
ο· NC and Defect Management
ο· Inspection and test plans
ο· Risk management
3.2 Quality Plan
The information in this section constitutes the minimum requirements for a quality plan.
3.2.1 Where specified in the Evaluation Criteria and/ or quality list of tender returnables , as per the
categories of quality requirements (Category 1, 2, 3, or 4); all individual products, services
and processes shall have a documented, implemented, reviewed and maintained contract
quality plan and/or quality control plan (inspection and test plan).
3.2.2 Where specified in the evaluation criteria and/ or quality list of tender returnables. All
production and/ or service provision shall be carried out in accordance with a documented
and agreed contract quality plan (CQP) and/ or quality control plan (QCP)/ inspection and test
plan (ITP).
3.2.3 The supplier shall plan for the required quality-related activities and interfaces within the
supplierβs quality system in order to demonstrate its ability towards both controlling and
meeting specified Eskom requirements.
Note 1: Contract Quality Plan should address the quality assurance elements related to the scope
of work and/ or technical specification.
Note 2: Quality Control Plan (QCP)/ Inspection and Test Plan (ITP) should address the quality
control elements related to the scope of work and/ or technical specification.
3.3 Contract Quality Plan
The main supplier shall require sub-suppliers to submit project quality plans (PQPs)/ contract quality
plans (CQPs) and associated documentation in accordance with the requirements of project QMS
processes applicable to the sub-supplierβs scope of work.
The supplier shall, where applicable, based on scope of work criticality, ensure that procurement
documents clearly and unambiguously require sub-supplier submission of a sub-supplier CQP for
supplier and Eskom review.
The main supplier shall ensure that sub-supplier CQPs are developed and implemented in
accordance with the ISO 10005 Quality Management System Guidelines for Quality Plans. In
addition to the elements specified in ISO 10005, the supplierβs and/ or sub-suppliersβ CQPs shall
include the following (as applicable):
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.3.1 The management of records, including material tests, positive material identification (PMI)
testing, material certification, etc.
3.3.2 The provision for free and uninhibited access by the supplier and/or personnel at the time of
inspection.
3.3.3 The proposals for submission of final documentation, the final manufacturing data book, prior
to shipment.
3.3.4 The special processes related to welding: management of the welderβs qualification record
(WQR), welding procedure specifications (WPS), and procedures qualification records (PQR)
that will be used in the performance of work for supplier review and acceptance prior to
commencing manufacture. Welders shall be qualified to the specified Codes of Construction
for the applicable procedures. The requirements for qualification shall be specified by the
supplier, and welder records shall be maintained by sub-suppliers performing the work.
3.3.5 The special installation procedures and other required fabrication or manufacturing
procedures (that is, those required for post-weld heat treatment, tube rolling, coatings, etc.)
that will be used in the performance of work shall require supplier review and acceptance
prior to commencing manufacture. The personnel carrying out special processes (for
example, NDE, welding, coating, heat treatment, etc.) where the results cannot be fully
verified by subsequent inspection and test shall be suitably qualified and, where applicable,
registered with statutory bodies as legally required, that is, as radiographic workers to conduct
radiography. The requirements for the qualification shall be specified, and personnel records
shall be maintained in accordance with the Project Quality Personnel Qualification
Specification and, where applicable, legal requirements.
3.3.6 The personnel required to perform special processes shall be certified competent through a
certificate of competency in accordance with the companyβs internal training management
and competency control procedures or an external certification body (for example, NDT)
through an accredited service provider as per Skills Education Training Authorities (SETA)
requirements.
3.3.7 All personnel who perform activities that affect quality shall have their training needs identified
and documented. The required training shall be implemented in accordance with the
companyβs training management and competency control procedures. All the training
certificates shall meet the SETA requirements in terms of having the unit standard completed
and the accreditation number of the service providers.
3.3.8 Instructions and requirements for equipment and materials storage, preservation, and
maintenance, including identification of materials required for preservation and maintenance,
are to be provided sufficiently prior to receipt (prior to shipment or earlier) to ensure that
appropriate resources are available at the time of delivery.
3.3.9 Specific quality monitoring and verification activities are to be undertaken on the supplierβs
sub-suppliers by Eskom or it agent.
3.3.10 The CQP information need to include, but not limited to:
ο· Spells out the aspects of the QMS to be applied within a specific Eskom project, and the
methods to be utilised to ensure quality.
ο· Outline the resources, the communication channels, applicable documents and records to be
generated.
ο· Management Authority and Responsibility from both supplier and client need to outline in the
Cqp.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
ο· List of documents and records that will be used and submitted during the execution of the
project.
ο· Communications channels should include contact person and contact details
ο· Monitoring & measurement procedures for activities need to be indicated.
3.3.11 The main supplier and sub-supplier CQPs shall comply with the Eskom Quality Requirements
Specifications and shall be submitted prior to the initial scope of work kick-off or initial pre-
fabrication meeting and prior to commencement of manufacturing, whichever is earlier.
3.3.12 The Eskom template for CQP provided shall be used as guideline, where the supplier does
not have a CQP template.
3.4 Quality Control Plan
The supplier shall develop and implement processes and procedures that efficiently and effectively
monitor, verify and document the quality of the scope of work for deliverables.
The main supplier shall ensure that sub-supplier QCPs/ ITPs are prepared at a level of detail
sufficient to address all quality-control-related activities in a chronological order, from contract review
through materials verification, manufacturing, fabrication, assembly, final testing, commissioning,
hand-over documentation, and certification. In addition, the supplier shall ensure compliance with
the following requirements:
3.4.1 All stages of manufacturing, fabrication, assembly and installation shall be controlled by a
supplierβs QCP/ ITP that clearly and unambiguously identifies the quality verifications to be
performed and special attention to controls related to critical products and services.
3.4.2 QCP/ ITP shall be reviewed and accepted by Eskom, its inspection authority or agency, and
they shall allow for the insertion of Eskom specific requirements, including hold and witness
points prior to the commencement of work.
3.4.3 Subsequent changes to the Eskom accepted QCP/ ITP shall require Eskom, its inspection
authority or agencyβs agreement prior to the commencement of work involving an activity
affected by such changes.
3.4.4 The ITPs should cover materials certification, fabrication works, in-process inspections, final
acceptance tests, packaging and pre- shipment/ transportation, shipping/ transportation
inspections where contracted, preservation, site acceptance tests, construction and erection
works, and pre-commissioning and commissioning tests.
3.4.5 All sub-supplier QCP/ ITP activity shall be performed using an Eskom-accepted supplier
Qcp/ itp.
3.4.6 All applicable codes, standards, and relevant acceptance criteria documents are available at
the work location, and Eskom representatives on site shall have on-going access to this
information. Workplace documentation shall be available in English and in any workforce-
appropriate language.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.4.7 Where activities subject to inspection and test procedures are to be undertaken by a sub-
supplier, the QCP/ ITP shall make reference to this fact and shall include descriptive details
of the sub-supplierβs involvement. A separate QCP/ ITP shall be required for each sub-
supplier scope of work.
3.4.8 The supplier shall be ultimately accountable and responsible for the development and proper
implementation of all sub-supplier QCPs/ ITPs, including those reviewed or developed by
sub-suppliers.
3.4.9 Eskom reserves the right to select intervention points on QCPs/ ITPs for Eskom oversight of
selected functions and to perform surveillance or audits of the work.
3.4.10 Once signed, the ITPs and QCPs become addendums to the main contract. These ITPs can
be reviewed at Eskomβs discretion based on its assessment of the supplierβs performance or
other risks.
3.4.11 A QCP/ ITP shall contain the following information:
ο· Eskom contract number and title
ο· The supplierβs order number
ο· Identification of the area of works/contract
ο· Description of the work, with components, item number, and activity date
ο· QCP/ITP unique number
ο· A list of the sequence of operations, including inspection and tests
ο· The identification of the specification, drawing number, or procedure for each operation,
with reference to the relevant criticality risk rating
ο· The acceptance criteria, with reference to the technical specification, in-house, national, or
international standard, with the relevant clause number for each operation
ο· The inspection and test activities that the supplier has nominated for its intervention points
ο· Provision for the inclusion of intervention points nominated by Eskom and/or its authority/
agency
ο· Provision for intervention point acceptance by date and signature for all parties having
intervention in the plan
ο· Inspection and test records to be generated by the supplier for each operation and an
indication of records to be provided to Eskom (as applicable)
3.4.12 The main supplier shall require sub-suppliers to submit QCPs/ ITPs and associated
documentation applicable to the sub-supplier scope of work. Any changes made to the QCP
after submission must be resubmitted to Eskom for further review. The supplier shall ensure
that all sub-supplier QCPs/ ITPs are in compliance with the Eskom Quality Requirements
Specifications, including, but not limited to, the following requirements:
ο· Clear and unambiguous description of the equipment and location(s) at which each activity
will take place, including facility location(s)
ο· Identification of quality verification activity and stage
ο· The details of reference documents, procedures, or method statements to be utilised in
performance of the activity, including specific reference to actual sections and pages of
procedures, standards, instructions, specifications, etc.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
ο· Definition of acceptance criteria
ο· Listing of certifying or verifying documents generated to provide evidence of compliance
with specified requirements; documents are to be provided using the proper Eskom
document numbering requirements
ο· Identification of main supplier and sub-supplier (where applicable) third-party/approved
inspection authority (AIA) and Eskom inspection activities defined in terms of witness, hold,
document review, and verification monitoring points and provision for sign-off of each of the
above-mentioned parties for each intervention point
ο· Qualification requirements for quality control inspectors, including any third-party/AIA
inspectors
ο· Listing of all proposed test procedures
ο· Acceptance criteria for each inspection or test in alignment with specified tolerances
ο· A section for signed acceptance of the QC/ITP by the supplier, sub-supplier (where
applicable), and Eskom prior to commencement of work
ο· Inspection or testing intervention points, including, but not limited to, factory acceptance test
and package acceptance test, witness, and hold points
3.4.13 A quality kick-off meeting will be held at the start of the contract and, if required, at the start
of each subsequent phase.
ο· The supplier shall arrange coordination meetings with Eskom prior to placement of orders
for items or equipment to ensure that all technical and commercial requirements are clear
and understood. Fourteen daysβ advance notice of meetings shall be given to Eskom.
ο· Supplier inspection personnel, including inspection agency personnel, shall be competent
and qualified to perform inspection and testing assignments. Mobilisation of all such
personnel shall be in compliance with the Project Quality Personnel Qualification
Specification.
3.4.14 Where QCP/ ITP is applicable, the supplier shall ensure that sub-suppliers are provided with
comprehensive, clearly written, and unambiguous inspection and testing protocols, including
processes, procedures, and methods that shall include, but not be limited to, the following:
ο· Requirements for inspection checklists and inspection assignments, with lists of items to be
inspected
ο· An inspection and testing report format, report content, schedule for report processing and
distribution, and report retention requirements
ο· Inspection and test report results response tracking (log) and resolution of nonconformity in
inspection and test processes, procedures, or methods and nonconformity identified in
inspection and test results
ο· Associated Failure Mode, Effects and Criticality Analysis (FMECA) reports relating to the
equipment and sub-systems (if applicable)
ο· Hazard and Operability Study (HAZOP) report, as applicable
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.4.15 The supplier shall establish processes and procedures for formal assessment of sub-supplier
inspection and testing programmes. These shall include review of sub-supplier inspection
reports and other quality control documentation. Additional formal assessment of
manufacturing, fabrication, and assembly facility operations shall be conducted by the
supplier to ensure continuing suitability, adequacy, and effectiveness of the sub-supplierβs
inspection and testing programmes. Assessment frequency shall be established in
consideration of the sub-supplier scope of work, criticality of scope of work deliverables, and
performance information. The assessment scope and schedule shall be developed in
consultation with Eskom.
3.4.16 Supplier processes and procedures for verification of supplier and sub-supplier purchased
product compliance with specifications shall obtain document return/review status prior to
implementation.
3.4.17 The objective is to finalise any outstanding procedural or other issues before proceeding to
deliver the works.
3.4.18 Eskom, in consultation with the supplier, develops an agenda for the meeting, and Eskom will
keep minutes of these meetings.
3.4.19 Mandatory pre-inspection meetings will be convened by Eskom or its inspection agency or
AIA to be attended by the supplierβs and sub-supplierβs representatives, including their quality
representatives who will be involved in the works, and records are to be kept.
3.4.20 Eskom reserves the right to appoint resident quality inspectors who can be based at the
supplierβs or sub-supplierβs premises and on site where the work is being performed. The
supplier is expected to provide workspace at no cost to Eskom for the inspector, as required.
3.4.21 Eskom may appoint any organisation it prefers to perform quality assurance and quality
control activities, either in the capacity as an AIA or inspection agency, on the works
contracted to the supplier, and the supplier or its sub-suppliers may not object, prevent,
hinder, undermine, circumvent, question, discredit, or in any way make it impossible for such
organisation to carry out its work on behalf of Eskom.
3.4.22 The Eskom template for QCP/ ITP provided shall be used as guideline, where the supplier
does not have a QCP/ ITP template.
3.5 Pre-Contract Award: Quality Requirement
3.5.1 Main Supplier and Sub-supplier Categories
Eskom supplier quality requirements for all existing and potential suppliers and sub-suppliers are
classified into four categories (category 1, 2, 3 and 4). Suppliers must prepare and submit quality
documentation as per the tender selected category (indicated in Form A) using the list of tender
returnables document.
NOTE: Only one (1) category must be applicable per procurement process e.g. [Eskom requests for
information (RFI)/ requests for quotation (RFQ)/ requests for proposal (RFP), including contracts for
the procurement of products and services].
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The following are the minimum returnable documentation for Categories 1 to 4:
3.5.2 Category 1: Quality Requirements
ο· The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
ο· The supplier shall submit a valid copy of ISO 9001 or any applicable certificate of a QMS (the
latest applicable revision). The QMS should drive the supplierβs business management
processes to ensure that all of Eskomβs requirements are fully met on a consistent basis.
ο· The supplier shall submit the latest copy of the management system internal and external
audit reports. The audit reports must include, if applicable, nonconformity identified, and the
resulting remedial actions (correction and/ or corrective action reports).
ο· The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
ο· Where applicable; the supplier shall submit a draft, or an example of an inspection and test
plan (ITP) or quality control plan (QCP) on similar and/ or previous work done.
ο· The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
ο· The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
ο· The supplier shall submit documented information retained (records) of management review
meetings that include agenda, meeting minutes, attendance registers, reports, presentations,
etc.
Note: specific requirements per tender will be selected using the List of Tender Returnable
documents (240-12248652).
3.5.3 Category 2: Quality Requirements
ο· The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
ο· The supplier shall submit objective evidence of a developed, implemented and maintained QMS
that complies with ISO 9001 or any applicable standard of quality management system (the latest
applicable revision). The following documents (approved/ signed copies) shall be submitted:
ο§ Quality Management System manual or a documented information that have defines and
describes the QMS and its scope
ο§ Quality Policy, aligned with the supplierβs strategic direction (documented information)
ο§ Quality Objectives (documented information)
ο§ Control of documented information (both maintain and retain documented information )
ο§ Internal audit procedure (documented information)
ο§ Control of nonconforming outputs (documented information)
ο§ Nonconformity and Corrective action procedure (documented information)
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The QMS should drive all the supplierβs business management processes to ensure that all of
Eskomβs requirements are fully met on a consistent basis.
ο· The supplier shall submit the latest copy of the management system internal audit reports. The
audit reports must include, if applicable, nonconformity identified, and the resulting remedial
actions (correction and/ or corrective action reports).
ο· The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
ο· Where applicable; the supplier shall submit an example of inspection and test plan (ITP) or
quality control plan (QCP) on similar or previous work done.
ο· The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
ο· The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
ο· The supplier shall submit documented information retained (records) of management review
meetings that include agenda, meeting minutes, attendance registers, reports, presentations,
etc.
Note: specific requirements per tender will be selected using the List of Tender Returnable
document (240-12248652).
3.5.4 Category 3: Quality Requirements
ο· The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
ο· The supplier shall submit objective evidence of a developed QMS that complies with ISO 9001
(or the latest applicable revision). The following documented information (approved/ signed
copies) shall be submitted:
o Quality management system manual or a (documented information) that have
defines and describes the QMS and its scope
o Quality Policy, aligned with the supplierβs strategic direction (documented
information)
o Quality Objectives (documented information)
o Control of documented information (both maintain and retain documented
information )
o Internal audit procedure (documented information)
o Control of nonconforming outputs (documented information)
o Nonconformity and Corrective action procedure (documented information)
The QMS should drive all the supplierβs business management processes to ensure that all of
Eskomβs requirements are fully met on a consistent basis.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
ο· The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
ο· Where applicable; the supplier shall submit an example inspection and test plan (ITP) or
quality control plan (QCP).
ο· The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
ο· The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
NB: specific requirements per tender will be selected using the List of Tender Returnables
document (240-12248652).
3.5.5 Category 4: Quality Requirements
ο· The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
ο· The supplier shall submit a quality method statement based on ISO 9001 and specific to the
scope of work.
ο· The quality method statement should address all the supplierβs business management
processes to ensure that all of Eskomβs requirements are fully met on a consistent basis.
ο· The supplier shall submit a signed/ approved quality policy (aligned with the supplierβs strategic
direction). (documented information)
ο· The supplier shall submit a copy of quality objectives. (documented information)
ο· The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
ο· The supplier shall submit a copy of the documented information for roles, responsibilities and
authorities, specific to the project/ scope of work/ technical requirements. Examples of relevant
documented information are; organization charts, job descriptions, work instructions, duty
statements, manuals, procedures.
Note: specific requirements per tender will be selected using the List of Tender Returnables
document (240-12248652).
3.6 Main Supplier and Sub-supplier Capability and Capacity Assessment
Supplier capability and capacity assessments shall be performed prior to contract award on potential
suppliers participating in Eskom Holdings procurement process to:
ο· provide products and services with high risk to operational sustainability
ο· work on critical plant and equipment
ο· supply of critical plant items or components
ο· provide special processes
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
All sub-suppliers used by the main supplier/ contractor, performing work on Eskom critical plant
equipment, supplying commodities and providing specialised services shall be subjected to the
capability and capacity assessment.
Critical plant includes the following:
ο· Generation Level 1 & 2 plant
ο· Transmission and Distribution Power Plant & Control Plant
ο· Mega Projects
All potential quality risks identified will be included in the assessment report provided for the tender
evaluation.
Note: Form A (Enquiry/ Contract/ Quality Requirements for Supplier Quality Management:
Specification 240-105658000/ QM 58 and ISO 9001) will be used to select and indicate whether
capability and capacity assessment will be conducted.
3.7 Post-Contract Award
3.7.1 Contract Execution
The supplier shall submit the following documents within 30 days or as per stated timeline after the
contract date, prior to the commencement of work, for acceptance by Eskom:
ο· The supplier shall complete a QCP before contract award. This shall be reviewed and
signed off by Eskom within 30 days or as per stated timeline after contract award.
ο· The supplier shall complete a quality control plan and ITP(s) for review and acceptance by
Eskom prior to the commencement of any work, inclusive of subcontracted work, within 30
days or as per stated timeline after contract award.
ο· The sub-supplier QCP/ ITP shall be submitted for review and comment by the supplier and
by Eskom within 30 days or as per stated timeline after the award of the tender. All supplier
and Eskom comments shall be resolved prior to commencing work.
ο· The equipment lists and an indication of pressurised components and systems.
Note: These plans are to be compiled in line with Eskomβs requirements and will have to be
discussed with, and approved by, Eskom prior to any work commencing.
ο· Correspondence shall be directed to the project manager, and periodic quality review
meetings shall be convened by Eskom with the supplier.
ο· The mandatory quality review meetings are to be convened by the nominated project quality
manager or his/her representative for the contract.
ο· Monthly quality performance and management reports are to be prepared by the supplier
during contract execution. The content of these reports shall be agreed by Eskom when
submitted to Eskom on a monthly basis.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.7.2 Supplier Quality Performance Monitoring Phase
During the contract execution phase, suppliers shall be monitored by Eskom for performance on
quality-related aspects.
The outcomes of such monitoring will enable Eskom to take any appropriate actions pertaining to
the supplier.
The monitoring shall be carried out periodically by Eskom or at predetermined intervals during the
execution of a contract using agreed key performance indicators. The monitored key performance
areas include the following:
ο· CQP and QCP /ITP
ο· Delivery
ο· Design
ο· Cost
ο· Management system
Subsequent key performance indicators associated with these areas will include the following:
ο· Nonconformity monitoring
ο· Audit and assessment evaluation scoring
ο· Management system compliance and accreditation
ο· Achievement of delivery targets as per contractual agreements
ο· Process improvements
ο· Correction and corrective action response and closure
3.7.3 Supplier Quality Audit
3.7.3.1 Quality audits and related quality performance reviews are intended to provide an objective
evaluation of compliance with performance expectations defined in this specification, in the
supplier contract quality plan (CQP), and in any other project scope of work specification.
3.7.3.2 Quality audits and related quality performance reviews include, but are not limited to, any
quality or other project functional area audits, assessments, verification of compliance
reviews, surveillance, inspections, or other interim or final assessments of scope of work
deliverables provided by the supplier or sub-suppliers
3.7.3.3 Quality audits and related quality performance reviews are intended to provide an objective
evaluation of compliance with performance expectations defined in this specification, in the
supplier contract quality plan (CQP), and in any other project scope of work specification.
3.7.3.4 Quality audits and related quality performance reviews include, but are not limited to, any
quality or other project functional area audits, assessments, verification of compliance
reviews, surveillance, inspections, or other interim or final assessments of scope of work
deliverables provided by the supplier or sub-suppliers.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.7.3.5 Quality audits and related quality performance reviews shall be carried out by trained,
accredited, and experienced personnel in accordance with procedures documented in the
Cqp.
3.7.3.6 The supplier shall submit, for Eskom review, documented processes for conducting project
scope of work quality audits and related quality performance reviews. Supplier quality audits
and related quality performance review processes shall be designed to address evaluation
of progress towards completion of project functional area deliverables as well as final
deliverable quality.
3.7.3.7 The supplier shall provide a schedule of anticipated quality audits covering all functional
areas and related quality performance reviews at the time of first post-contract award CQP
submission.
3.8 Standard Conditions
3.8.1 Rights of Access
Eskom:
3.8.1.1 shall be granted electronic and hard-copy access to all quality plans, procedures,
documentation, and other quality records relating to the work, including, but not limited to,
data extracts;
3.8.1.2 reserves the right to review, inspect, and audit any or all parts of the supplierβs QMS, as well
as any documentation, materials, or equipment associated with the work, at any time or
project work location; and
3.8.1.3 reserves the right to carry out assessments and audits on all new suppliers and sub-
suppliers.
The supplier:
3.8.1.4 shall support Eskomβs effort to monitor, verify, and/or witness any activities associated with
the work at any time;
3.8.1.5 shall cooperate with Eskom requests for documentation, records, and inspection and
witnessing. Eskom participation in audits, appraisals, assessment of plans, and verification
shall be conducted at no extra cost to Eskom;
3.8.1.6 shall ensure that a sub-supplier provides access to Eskom to all work procedures, records,
and supporting documentation through provision of access to view and photocopy, as
required, to support verification of scope of work requirements. Access shall include the
ability to photograph Eskom equipment, systems, system components, materials, etc.;
3.8.1.7 shall provide access to all quality-related information pertaining to activities performed by
itself or sub-suppliers, where Eskom might not have participated in the witnessing of their
quality assurance or control (this refers to inspections, audits, etc. performed by the supplier
on its own sub-suppliers);
3.8.1.8 shall allow Eskom to assess, audit, approve, or reject any sub-suppliers employed by
Eskomβs suppliers to assist with the product and/or service delivery to Eskom; and
3.8.1.9 shall ensure that the above requirements flow down to sub-suppliers.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.2 Eskom Rights to Information
3.8.2.1 To expect that the works will be conducted in accordance with the contract between the
parties.
3.8.2.2 To have access to the supplierβs information as determined by applicable legislation.
3.8.2.3 Eskom reserves the right to oversee the supplierβs audit programmes by participating in
selected audits as an observer and by assessing the supplier during key work stages.
Eskom will coordinate with the supplier to develop an oversight schedule aligned with the
supplierβs audit schedule.
3.8.2.4 To obtain access to any audit reports of audits performed by the supplier reflected in the
audit programme.
3.8.2.5 To conduct independent quality audits during all phases of the contract, and the supplier
shall provide all resources to support these activities.
3.8.2.6 Eskom shall have the right to participate in, or request that, a technical investigation be
launched and conducted at the supplierβs and sub-suppliersβ premises or other sites when
risk to Eskom products or service deliverables is identified.
3.8.2.7 To participate in, and/or lead, investigations related to incidents involving its products.
3.8.2.8 To require from suppliers to be responsible for the cost of re-inspections.
3.8.2.9 To withhold payment from suppliers as a result of outstanding nonconformities, irrespective
of the agreed payment schedule and in accordance with the conditions of contract.
3.8.2.10 Shall be granted electronic and hard-copy access to all quality plans, procedures,
documentation, and other quality records relating to the work, including, but not limited to,
data extracts.
3.8.2.11 Reserves the right to review, inspect, and audit any or all parts of the supplierβs QMS, as
well as any documentation, materials, or equipment associated with the work, at any time or
project work location.
3.8.2.12 Shall carry out assessments and audits on all new suppliers and sub-suppliers.
3.8.2.13 Reserves the right to appoint resident quality inspectors who can be based at the supplierβs
or sub-supplierβs premises and on site where the work is being performed.
3.8.2.14 Reserves the right to select intervention points within all developed supplier QCPs/ ITPs
for Eskom oversight of selected functions and to perform surveillance or audits of the work.
3.8.2.15 Shall be given access at all reasonable times before, during, and after manufacture and
before delivery, construction, erection, and commissioning to measure, test, and inspect the
products and workmanship, as necessary, at the supplierβs premises and at Eskom sites.
3.8.2.16 Reserves the right to suspend any pending deliveries by the issuing of a cease delivery
order at any time and for any portion of the work that is not being performed in accordance
with the specified/agreed requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3 Preservation
The supplier shall develop and implement a comprehensive preservation programme consisting of
plans, processes, procedures and actions undertaken for the purpose of planning for and
maintenance of material deliverables quality. The supplier preservation programme scope includes,
but is not limited to, the following:
3.8.3.1 Engagement of personnel suitably qualified for oversight of, and (as required) direct
implementation of, preservation programme requirements.
3.8.3.2 Development and implementation of preservation programme training appropriate to work
need.
3.8.3.3 Eskom may make use of its appointed service provider tasked to provide a full suite of
services encompassing an online monitoring system and asset tracking during, but not
limited to the following stages: inspections, testing, shipping, transportation, storage, and
commissioning. The supplier is to enable full access during all of these stages in order to
allow the installation of the devices on Eskom-identified products and equipment, which
include the sub-supplierβs testing facilities, processing plant, and any other processes
deemed important towards effective and efficient quality control.
3.8.3.4 Eskom seeks cooperation between the supplierβs designers and those of Eskomβs service
provider in ensuring seamless installation of the device and other associated installations.
Moreover, there is also a need to integrate data flows and systems between Eskom and the
supplier. Further details are included in the Eskom specifications and works information.
3.8.3.5 Review and tracking of compliance with Eskom and supplier engineering specification of
preservation requirements.
3.8.3.6 Review and tracking of compliance with sub-supplier provided preservation requirements
and recommendations.
3.8.3.7 Evaluation of prospective temporary and longer-term material storage sites for consistency
with preservation programme expectations.
3.8.3.8 Preservation work plan development and plan execution performance evaluation of all
parties engaged for provision of material transportation, handling, or storage services.
3.8.3.9 Oversight of material quality preservation plan preparation and plan execution performance
at all work locations.
3.8.3.10 Development of a preservation programme records management process, in compliance
with Eskom information management requirements, which comprehensively addresses
generation, maintenance, and ready access by Eskom to all preservation programme
records.
3.8.3.11 The supplier shall deploy a clearly defined documented programme providing for
identification of all physical asset pre-operation preservation of quality requirements. In this
reference, the term βphysical assetsβ should be understood to include bulk materials,
including consumable items, equipment systems, system components, and any other
procured or supplied materials or equipment transferred to project control, but not deployed
for operational purposes.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3.12 Where the project responsibility for equipment and materials management has been
formally delegated, the supplierβs preservation programme shall ensure clear and
unambiguous communication of pre-operation preservation of goods quality requirements
to sub-suppliers.
3.8.3.13 The supplierβs preservation programme shall clearly and unambiguously document
processes and procedures for efficient and effective monitoring of compliance with
programme requirements.
3.8.3.14 Compliance monitoring shall commence with ensuring comprehensive consideration of
preservation requirements in the engineering instruction and subsequent inclusion of said
instruction in procurement documentation and shall be applicable until such time as
equipment or materials have been incorporated in an operating or operational system or
structure.
3.8.3.15 Compliance evaluation frequency shall anticipate transfer of tactical-level responsibility for
management of preservation responsibilities between project functional areas, for example,
procurement to logistics, logistics to fabrication, fabrication to logistics, logistics to
construction, etc., and shall, in similar fashion, anticipate transfer of support for tactical-level
responsibility between various subcontracted service providers.
3.8.3.16 Supplier engineering shall ensure that preservation requirements for scope of work
systems, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented and that preservation requirements are efficiently and
effectively communicated to project procurement, logistics, construction management,
quality, security, and other project functional areas, as required, for efficient and effective
implementation of preservation requirements. This shall take the form of a preservation
programme applicable to all systems, system components, equipment, materials, customer-
supplied materials, and other goods procured or managed under the scope of work.
3.8.3.17 The supplierβs preservation management programme shall clearly and unambiguously
address temporary, long-term, and in-transit preservation requirements, including, but not
limited to:
ο· requirements for protection against, or insulation from, atmospheric conditions,
sunlight, temperature, soil, dust, humidity, salt spray, corrosive atmospheres, or
other physical environment conditions;
ο· detailed procedures for application, use, monitoring, and maintenance of coatings,
coverings, fasteners, lines, and other components for internal and external weather
proofing;
ο· requirements for electrical grounding or isolation;
ο· requirements for internal or external environment creation, for example, inert gas
charging, heating, cooling, etc., inclusive of gas storage, electric power supply, etc.;
ο· detailed procedures for initial set-up, charging, activation, and maintenance of
internal atmosphere generation, regeneration, monitoring, and relieving systems, for
example, inert gas management systems;
ο· requirements for protection against, or insulation from, vibration or long-period
cyclical motion in transit, for example, wave-generated movement during sea
transport;
ο· internal and external structural integrity protection, for example, internal and external
bracing, padding, framing, chocking, etc.;
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
ο· support structure requirements, for example, stools, pads, or other devices,
substrates, or support required to ensure in-storage and in-transit stability of
systems, system components, equipment, and material, or other discrete units or
items;
ο· provision for physical separation and/or barriers to prevent airborne or direct
transmittal of contaminants between work areas or between work areas and storage
areas, for example, prevention of carbon steel grinding or cutting debris impact on
stainless steel elements, airborne drift of blast aggregate into vessels or machinery,
etc.;
ο· provision for, and final disposition of, temporary and longer-term storage or transit
required supports and related binding devices, for example, stools, stands, sea
fasteners, platforms, chocks, spacers, cabling, etc.;
ο· provision of requirements for temporary work platforms or other support structures
required to ensure provision of preservation services, for example, provision of a
self-elevating work platform for periodic access to elevated fittings, gauges, man-
ways, etc.;
ο· requirements for protection against, or insulation from, contact with other objects, for
example, padding or other protection for external tubing, fittings, or other impact-
sensitive structures or components;
ο· clear physical delineation of temporary and longer-term storage areas supplemented
by hard and soft barriers, as required, to maintain a protective perimeter;
ο· documented agreements with storage facility and transportation provider
management regarding security management, including, but not limited to, facility
access and egress control and control of access to project goods and materials
within facility boundaries or aboard vehicles or vessels; and
ο· detailed procedures for inspection and testing to verify performance of preservation
procedures and to provide for timely notice and corrective action to maintain
preservation status.
3.8.3.18 The supplierβs preservation management programme scope shall encompass
management of preservation requirements, from initial transfer of ownership or management
responsibility to project scope of responsibility, through any period of temporary or longer-
term storage and through any period of transit, including transit for final delivery at point of
active use or installation.
3.8.3.19 The supplierβs preservation management programme shall clearly and unambiguously
address processes and procedures to ensure that storage and control of materials are
accomplished in accordance with manufacturer recommendations, specifications, and
project-specific requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3.20 The supplierβs preservation management programme shall incorporate special precautions
to address preservation and control of valves, electrical motors and components,
mechanical and rotating equipment, piping and fittings, instrumentation, flange faces,
gaskets, coatings, insulation, and other materials. Special precautions include, but are not
limited to, supplier-specified maintenance procedures related to engines, electric motors,
pumps, compressors, etc., such as periodic shaft rotation, engine turnover, lubrication, etc.
3.8.3.21 The supplier shall ensure that clear and unambiguous requirements for preservation of the
system, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented in purchase orders, work authorisations, and other
communications between the supplier and sub-suppliers.
3.8.3.22 Where sub-supplier expertise is utilised in determination of the preservation protocol,
supplier procurement processes shall ensure clear and unambiguous documentation of sub-
supplier input into preservation management programme requirements.
3.8.3.23 Supplier procurement shall ensure that preservation requirements for scope of work
systems, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented and that preservation requirements are efficiently and
effectively communicated to project logistics, construction management, quality, security,
and other project functional areas, as required, for efficient and effective implementation of
preservation requirements.
3.8.3.24 The supplier shall ensure comprehensive, clear, and unambiguous designation of sub-
supplier responsibility for execution of all preservation management programme elements,
including, but not limited to, all systems, processes, procedures, methods, ready access to
records, and provision of equipment, tools, or services essential to efficient and effective
execution of the preservation management programme.
3.8.3.25 The supplier shall ensure that preservation management programme responsibilities are
clearly and unambiguously defined within the project team and efficiently and effectively
implemented at all project scope of work locations. Inclusion of supplier and sub-supplier
scope of work in the development and implementation of a preservation management
programme shall be considered essential to efficient and effective preservation
management programme execution.
3.8.3.26 The supplier shall ensure clear and unambiguous designation of project team responsibility
for oversight and management of preservation management programme elements during
every stage of project development.
3.8.3.27 The supplier shall ensure that Eskom has free and unrestricted access to all preservation
records for inspection and audit.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.4 Quality Audits Related Conditions
3.8.4.1 The supplier shall maintain an accurate quality audit and related quality performance review
schedule and shall incorporate the current schedule as an attachment to the supplier CQP.
3.8.4.2 The supplierβs quality audit and related quality performance review schedule development
process shall be designed to incorporate consideration of information generated by
previously conducted audits and reviews, by input from project risk management evaluations
(risk register), or from Eskom or sub-supplier subject matter expertise.
3.8.4.3 Eskom reserves the right to oversee supplier audit programmes by participating in selected
audits as an observer and by assessing the supplier during key work stages. Eskom will
coordinate with the supplier to develop an oversight schedule aligned with the supplierβs
audit schedule.
3.8.4.4 Eskom will have the right to obtain access to any audit reports of audits performed by the
supplier reflected in the audit programme.
3.8.4.5 Eskom reserves the right to conduct independent quality audits, scheduled and
unscheduled, during all phases of the contract. The supplier shall provide all resources to
support these activities.
3.8.4.6 Eskom shall be given access at all reasonable times before, during, and after manufacture
and before delivery, construction, erection, and commissioning to measure, test, and inspect
the products and workmanship, as necessary, at the supplierβs premises and at Eskom sites.
3.8.4.7 The supplier shall obtain access for Eskom to measure, test, witness tests, and inspect
products that are being manufactured by any sub-supplier. This includes surveillances.
3.8.4.8 The assessments and audits shall be carried out on all new suppliers and their sub-
suppliers.
3.8.4.9 Eskom shall have the right to participate in, or request that, a technical investigation be
launched and conducted at the supplierβs and sub-suppliersβ premises or other sites when
risk to Eskom products or service deliverables is identified.
3.8.4.10 Qualification requirements for supplier and sub-supplier personnel engaged in conducting
quality audits and related quality performance reviews shall be defined in the supplier CQP
and shall be in compliance with the Project Quality Personnel Qualification Specification.
3.8.5 Management of Nonconformities and Nonconforming Outputs Identified by Eskom
3.8.5.1 Nonconformity reports raised by Eskom and issued against the supplier shall be investigated
by the supplier as a matter of urgency in order to determine the root cause, corrective action
measures, as required, with implementation time frames.
3.8.5.2 A formal response shall be prepared in respect of the defined criteria and submitted to
Eskom for its review, evaluation, and acceptance, within a maximum of 14 calendar days
from the date of issue of the nonconformity and should be aligned with the site
requirements/procedure.
3.8.5.3 Eskom may, at its discretion, request a response sooner and, in any case, before the
supplier proceeding with any pending/further intervention or corrective action, as may be
required by Eskom.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.5.4 Should Eskom or its inspection authority/agency identify any nonconforming products during
the conduct of its audits/surveillances/inspections, the supplier shall be deemed to be in
breach of contract and shall be held liable for any repair, rework, and/or associated
replacement costs. The supplier may, in such instances, also be held liable for the full costs
associated with the conducting of follow-up audits/surveillances/inspections.
3.8.5.5 The nature, magnitude, and/or frequency of nonconformity and inspection defect/rejection
reports raised by Eskom or its appointed inspection authority/agency shall form the basis of
any action to rescind/withdraw the supplierβs qualification status.
3.8.5.6 Nonconforming outputs identified by Eskom shall be documented via a NC Report and
issued to the suppliers via the contract communication protocol. The suppliers shall
investigate the matter and respond in writing to Eskom of disposition within the stated
contractual conditions.
Note: The dates for the disposition should align to contractual conditions.
3.8.5.7 Eskom shall identify repeat deficiencies as systematic failures of the supplierβs QMS and
shall notify the supplier of the trends. Eskom can initiate an internal audit to highlight the
system failures. The supplier with raise a Corrective Action Report and undertake Root
Cause Analysis. In such cases, QMS rectification and/ or update measures shall be taken
immediately.
3.8.5.8 Should the Supplier fail to respond and rectify nonconforming products within stipulated
contractual conditions. The Project Manager should apply contractual remedies in
accordance with Fidic/ NEC contract.
3.8.5.9 Repeated Nonconformities; if there are any identified repeat nonconformities from the same
supplier within a period of 6 months or less. This must then be escalated to the management
review committees of the BU/ OU/ Cluster/ or Divisions for adjudication. If not resolved, then
the matter must be escalated to the supplier review committee for recommendation.
3.8.6 Special Processes
The following requirements shall be applicable as well as additional requirements as specified in the
scope of work for the provision of the following special process services:
3.8.6.1 The supplier shall ensure that all processes which require that procedures be pre-qualified
or work methods and operators tested and qualified are controlled and all steps followed
before the work can commence.
3.8.6.2 This typically covers such activities as welding, non-destructive testing, special fabrication
techniques, coating, painting, etc.
3.8.6.3 All special processes (procedures and processes) shall be submitted for review and
acceptance by Eskom, accredited or certified agency. No work shall commence until these
are accepted.
3.8.6.4 Where applicable, a relevant Management System for the special process shall be certified
or approved by an accredited body and proof of certification shall be submitted to Eskom for
review. An example for this will be the Welding Management System based on ISO 3834.
3.8.6.5 Where samples are required for acceptance, these shall be submitted to Eskom for review
and acceptance.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.6.6 The supplier shall ensure that all operators are suitably qualified for these processes in
accordance with the procedures, processes and/ or applicable standards/ codes.
3.8.6.7 The records of qualification of procedures, processes and operators shall be maintained by
the supplier in accordance with the applicable procedure or code and these made available
to Eskom at all times.
This document has been seen and accepted by:
Name Designation
Kerseri Pather General Manager: Risk and Sustainability
Lenock Meyer Acting Senior Manager: Quality Management
Pamela Dondashe Middle Manager: Quality Assurance
Mandla Mkhwanazi Middle Manager: SHEQ Procurement and Supply Chain Management
Suzette Manthe Senior Advisor: Quality Performance and Planning
Lorna Ndlela Middle Manager: Eskom Document and Records Management
Date Rev. Compiler Remarks
October 2021 3 SA Sambo Specification was due for revision and in addition, to
align the requirements with the latest Eskom business
processes and systems.
October 2018 2 SA Sambo Specification reviewed to be aligned with the
requirements of ISO 9001:2015
March 2016 1 SA Sambo Specification was due for revision and also to
repackage the requirements and tender returnable
documents into four categories.
December 2011 0 A Hunter New document
The following people were involved in the development of this document:
ο· Andrew Else
ο· Bongi Tshabalala
ο· Feziwe Mogamisi
ο· Lesego Garegae
ο· Patrick Thwane
ο· Xolani Zuma
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Eskom Operational Quality Forum Members
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Quality Control Plan Approvals Name Signature Intervention Point Legend (KEY)
Contractor /Supplier Hold Point AP - Document Requires T1 β 100% Testing A1 β 100% Inspection
Approval T2- Sample Testing A2- Sample Inspection
Subcontractor (where applicable) Witness Point W1 β 100% witness W2 - Sample witness
Eskom Document IN - Document Requires for R1- 100% Document Review R2- Sample Document
Review information only Review
Approved Inspection Authority (AIA) Surveillance (S)
(Where applicable) Verification (V)
Activities Intervention Point Category Inspection and Test Method Supplier Inspection Eskom Inspection Records
No Description / Requirement Date Supplier Eskom S=Statutory Method Controlling Acceptance AIA/NOBO Internal/TPI AIA/NOBO Internal/TPI
/ N= Non- document Criteria
statutory
Notes: INSPECTION AND TEST METHOD (e.g. Visual, Microscopy, NDT, Liquid/ Dye Penetrant, Magnetic Particle, EDDY, etc.); ACCEPTANCE CRITERIA ( e.g. Functionality requirement,
Performance Measures, Regulatory Compliance, Chemical test , etc.)
Abbreviations: NOBO (Notification Body); TPI (Third Party Inspection)
Public
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on
the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30.
(Type in the Full description of the Works Information as described in the NEC or Fidic document)
Scope of work category ( Mark with X if Yes N/A Type in the scope of work in the appropriate
any activity below is included in SOW) column.
Design
Manufacturing
Supply and Delivery/ Transportation
Construction/ Installation/ Maintenance
Commissioning
Professional services
Other
Each person on site must know their own responsibilities as well as the responsibilities of others. Each party must keep the relevant
people informed. Indicate for this contract Communication regarding all quality related issues i.e. Documentation/ Supplier Representative
details and contacts - E-mails; Minutes of Meetings; Fixed Contract Meeting; /Weekly Progress Meetings & reporting;. All documentation
shall be submitted per the contract agreement).
(Include scope of work /contract related organogram showing designations with roles and responsibilities/ outputs, which shall include the
QA and QC functions with all personnel responsible for management of activities/processes during execution or delivery of product. Team
memberβs responsibilities and qualifications necessary to fulfil stated duties Work verification (e.g., who is responsible for carrying out a
task, as well as who is responsible for checking the work)
Specifications)
List of Supplierβs core processes to be used for executing scope of work / List of Documents to be used on this contract - Work Instructions;
Processes; policies; procedures for the scope of work; Industry standards; specifications; drawings applicable to the scope of work.
Name of document Type Revision
(for sow specific raw material/ required components; list all possible services/material to be sourced or services to be outsourced)
Material components to be purchased
Possible suppliers to be used for sourcing Material /components to be purchased
A
B
Public
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorised version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC
Ltd, Reg No 2002/015527/30.
of 7
Template Identifier 240-43921804 Rev 5
Template for a Typical Document Identifier 240-109253698 Rev 3
Contract Quality Plan Effective Date 01 April 2021
Next Review Date 01 April 2026
Scope of Work Sub-Suppliers or Sub-contractors- for specialised, complex SOW activities that will be
outsourced.
Outsourced Description of the activity Criteria for selection
Activity/Subcontractor
Eg - Drilling of holes in rocky areas Rock drilling when digging holes; Hiring additional ladders; Eg: Technical & Quality requirements
A
B
C
Note: Evaluation; selection and performance monitoring of suppliers shall be performed as defined in the supplierβs procedures for
managing externally supplied products and services.
(Description of how the tenderβs Supplier and contractors indicated in Section 6 will be monitored post award, mark with X the applicable
box- if there are sub-suppliers/ sub-contractors)
Supplier/contractor performance monitoring activities as per scope of work Yes N/A
Supplier inspection report or
supplier surveillance/audit report or /and audit schedule
Generate supplier/contractor inspection plan
Purchased Material verification checklist or report
(Description of the interface of the Sub-Supplier and Suppliers QMS and applicable documents, procedures and work instructions)
Purchased
(Submit a list of SOW items/activities that will be manufactured/refurbished or purchased which will be used on this project/contract
including full descriptions; production schedule and if produced in-house or out-sourced)
Item manufactured refurbished purchased serial number
(Description of all production products/processes which will be monitored by an approved QCP process- compilation; review and implementation and
compliance monitoring Inspection Management)
Public
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorised version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC
Ltd, Reg No 2002/015527/30.
of 7
Template Identifier 240-43921804 Rev 5
Template for a Typical Document Identifier 240-109253698 Rev 3
Contract Quality Plan Effective Date 01 April 2021
Next Review Date 01 April 2026
Governed by codes of manufacturing/fabrication standards
(Description of all products/processes/services which will require special controls, i.e. welding, NDT/NDE. For each of the deliverables
identified, describe the quality control activities you will execute to ensure the deliverable will meet quality expectations (QC). For example,
you could note that you will be completing a Quality Control Checklist for each major deliverable)
During project
All documents that will be submitted to Eskom - Technical records (Safe working procedure/ Method statements), Inspections reports, signed
off QCPβs, technical assurance report, warranty certificates, material certificates , dimension reports, tests reports etc) List of retained
information to be submitted as evidence - SOW has been executed, SOW outputs
(Example):
Title number
Submitted to Eskom prior to commencement /execution
QCP / ITP from Suppliers
Certificates of compliance
Index of ITP/QCP/PQP
Data book Index
Risk Register
offsite and offshore inspections
Submitted to Eskom during and at completion of the contract
Method statements/Safe Working Procedures/ PQRs; Repair Procedures)
Qcp / itp/pqp
Final DATA book
Captured in the QMS of the Supplier / Sub-Supplier
Quality Manual
Quality Policy
Risk Register
Audit findings report and Audit Findings Register / Action Register
Consolidated inspection register of all planned and completed inspections (Accepted,
Rejected, Postponed, Cancelled, Missed);
Monthly Inspection Analysis Report
Audit findings report and Audit Findings Register / Action Register β Analysis Report
Updated procedure registers (PQRs, Method Statements, Repair Procedures, etc.)
A register of NCs / Defects / Punch Items with all the necessary analysis β Analysis Report
Databook status registers β Monthly Analysis Report (Milestone Based)
Inspection rejection rate
(Some records submitted in Clause 12 of CQP- Description of how records shall be controlled (eg. identified, completed, retained and
disposition method - please do not attach procedure) A good retrievable filing system using an indexing and cross reference system should
be set up.
Public
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorised version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC
Ltd, Reg No 2002/015527/30.
of 7
Template Identifier 240-43921804 Rev 5
Template for a Typical Document Identifier 240-109253698 Rev 3
Contract Quality Plan Effective Date 01 April 2021
Next Review Date 01 April 2026
Record name Reference number Distributed to Retention period
(access):
(Share brief description (flowchart/process) of how the following processes will be implemented: Concession management process; Non-
Conformance (Defects; Repair & Rework) Management Process; Inspection Management Process.
Maintenance manual
If data book applicable to the scope of work, Submission of data books β reflect review; and acceptance; include list of purchase orders for
quality critical items.
Required to execute the contract scope of work.
(Provide a list of Tools & Equipment to be used for this contract; Provide a list of Calibration/ Maintenance or Test (for those applicable)
status of each of the tools and equipment to be used)
Provide a brief description or the process flow which details the manner in dealing with customer property as per latest ISO 9001
requirement.
Include a process flow which details the manner for the preservation, storage and handling of materials β identification; handling;
contamination control; packaging; storage; transmission or transportation, and protection
Indicate the identification and traceability methods to be used for SOW related activities affected by statutory and regulatory requirements
Indicate any post-delivery activities/support and how shall it be given to Eskom during commissioning and after SOW delivery - any
warranty period and conditions; customer satisfaction measurement; technical support; defect correction period/ retention funds. When
determining post-delivery activities consider statutory; regulatory and scope of work requirements
Public
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with
the user to ensure it is in line with the authorised version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC
Ltd, Reg No 2002/015527/30.
of 7
B.2 Documented information for Control of Externally Provided Processes, Products and Services - Must include criteria for evaluation, selection,
Research Corona Cage Test Facility, Sunninghill for the duration of six (8) monthsSECTION (TENDERER)
Clauses of 240- clause description indicate with an
105658000 (x) as applicable
Specification or (-) if not
Applicable
Pre-contract award quality requirements x
(*Select Only Applicable Category). NB: Not more than one category must be selected. Also indicate
whether site assessment is applicable.
Category 1 (refer to clause 3.5.-105658000) -
Category 2 (refer to clause 3.5.-105658000) -
Category 3 (refer to clause 3.5.-105658000) X
Category 4 (refer to clause 3.5.-105658000) -
Main Supplier and Sub-supplier Capability and Capacity Assessment (refer to clause 3.-105658000) -
3 post-contract award(eskom)
B Contract Execution (refer to clause 3.7.-105658000) X CLAUSE Supplier Quality Performance Monitoring Phase (refer to clause 3.7.-105658000) X
Standard conditionssection
Eskom Rights of Access (refer to clause 3.8.-105658000) X
Eskom Rights to Information (refer to clause 3.8.-105658000) X
Preservation (refer to clause 3.8.-105658000) X
Quality Audits Related Conditions (refer to clause 3.8.-105658000) X
Management of Nonconformities and Nonconforming Outputs Identified by Eskom (refer to clause 3.8.-
Special processes (refer to clause 3.8.-105658000) x
Clauses of iso iso 9001 standard indicate with an quality iso 9001 standard indicate with an
9001 standard clause description (x) as applicable principles principle description (x) as applicable
Or (-) if not or (-) if not
Applicable applicable
CLAUSE 4 Context of the Organisation X PRINCIPLE 1 Customer focus X
CLAUSE 5 Leadership X PRINCIPLE 2 Leadership X
CLAUSE 6 Planning X PRINCIPLE 3 Engagement of people X(ESKOM)
C CLAUSE 7 Support X PRINCIPLE 4 Process approach X
CLAUSE 8 Operation X PRINCIPLE 5 Improvement X
CLAUSE 9 Evidence based decision
Performance Evaluations X PRINCIPLE 6 XSECTION making
CLAUSE 10 Improvement X PRINCIPLE 7 Relationship Management X
D name designation date signature
Eskomβs quality
REPRESENTATIVE Duncan Ntshangase Snr Clerk/Quality 23/07/2026
RepresentativeSECTION (ESKOM)
Name designation date signature
E
Tendererβs
Quality
Representativesection (tenderer)
Public
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No
2002/015527/06.
of 2
(FORM A) Template Identifier 240-43921804 Rev 3
TENDER & CONTRACT QUALITY Document Identifier 240-68099512 Rev 9
Requirements for
Authorisation Date January 2022
240-105658000 and
QUALITY REQUIREMENTS FOR ISO 9001 Review Date January 2027
Standard
NB: The tenderer must complete and sign this form to acknowledge and accept Eskom Supplier Quality Requirements as per 240-
105658000 Specification and ISO 9001 Standard.
Public
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No
2002/015527/06.
of 2
provisions of the Act.
I undertake that ......................................................... [insert name of contractor/supplier] shall
strictly adhere to, and ensure that his/her employees adhere to, the provisions of the Occupational
Health and Safety Act, 1993 (Act ).
I have been provided with SHE specifications for project
appointment of contractors or suppliers for the commencement
of work
N/a
NOTE: Failure by the Contractor/Service Provider/Supplier to meet the CIDB CSDG mandatory %
will render their tender non-responsive.
Confidential
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No
2002/015527/30.
Upgrade)
Effective Date May 2021
Ref Environmental Tender Returnable Submission Comments
Y = Yes
N= No
1 Signed Environmental Policy:
2 Aspects and Impacts register as per scope of work
Title Date or Tick if publicly
revision available
General Specifications:
Health and Safety requirements
The Contractor shall:
shall include, as a minimum, detailed design and engineering, manufacture, factory
acceptance testing (FAT), delivery, site installation, site acceptance testing (SAT),
commissioning, training, and final handover documentation.
supply system to power the protection panel
as provided by Eskom, the existing/old protection system, including the existing DC
equipment and all the associated old cabling.
to a new temporary location, and later from the temporary location to a new room (to
be constructed by others)
cabling required to achieve a fully functional and operational protection system.
The scoring for each tender will be done as per the scoring table 1 shown below. The minimum
weighted average required for the tender to be considered for further evaluation is 70%.
Table 1: Evaluation Scoring Table
Score Percentage Definition
COMPLIANT Meet technical requirement(s) AND; No
5 100 foreseen technical risk(s) in meeting technical requirements.
Compliant with associated qualifications
Meet technical requirement(s) with,
Acceptable technical risk(s) AND/OR,
4 80 Acceptable exceptions AND/OR,
Acceptable conditions.
Non-compliant
Does not meet technical requirement(s) AND/OR,
Unacceptable technical risk(s) AND/OR,
Unacceptable exceptions AND/OR, 2 40
Unacceptable conditions.
0 0 totally deficient or non-responsive
Note: The scoring table does not allow for scoring of 1 and 3.
The following documents shall be submitted when tendering:
a) Technical/Project Schedule. A program with the order in which main
activities will be done with time durations from start to end.
b) Method statements (including detailed step-by-step procedures) for the
whole electrical protection system.
The contractor shall provide the following:
scope, substation name, completion date, project value and client contact person and
details. The contractor shall further include any concessions made during each
project execution.
experience for each employee) and academic qualifications. Also include total
number of manpower to be dedicated to this project.
Compliant tenders will be evaluated against a set of weighted qualitative evaluation criteria. The evaluation criterion has been broken
down into sections, and percentage weighting has been allocated to each section. Percentage weighting summary figures are
indicated in Table 4 below.
Table 4: Qualitative Technical Evaluation Criteria
Reference to
Technical Criteria Criteria Sub
Qualitative Technical Criteria Specification Weighting Weighting Score Clarification
Description / Tender (%) (%)
eTendering system is a web-based system that allows suppliers bidding for various tenders advertised
on Tender Bulletin system to βuploadβ their tender documents. Currently the tenderers or suppliers
submit tender documents at various Eskom tender offices. eTendering system replaces the manual or
physical submission of tender documents at various Eskom tender offices. eTendering system in a
nutshell is an electronic box where tender documents can be βdroppedβ or βuploadedβ. Suppliers will
be required to register their details before they can be granted access to the eTendering system. An
OTP (one time pin) will be sent to both their cell phone and email address.
Quick and direct access is also available by using the following links:
of the public, to view and access Eskom published tenders. eTendering hyperlink will be found
on this site. Members of the public may follow prompt instructions once they have clicked on
the eTendering link (https://eTendering.eskom.co.za). This link will allow them to upload the
required tender documentation.
members of the public, to view information about published tenders and submit their tender
documents.
eTendering system.
2 Problems
A channel of communication has been created in case users of the system experiences a problem
with the system. In a case users come across some difficulties in using Tender bulletin, eTendering
and OpenText systems they need to contact the buyer responsible for the published tender.
3 Whatβs New
A new functionality to βadd closed tendersβ. Closed tenders refers to the tenders which are not listed
on Tenderbulletin as normal tenders, but are tenders sent directly to the relevant and potential
suppliers who meet the selection and evaluation criteria to offer what the buyer needs. These
suppliers will be sent a link via email to bid privately.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
4 Getting Started
To gain access to eTendering portal
Open your web browser
Type TenderBulletin (eskom.co.za) or https://eTendering.eskom.co.za
eTendering system login page will be displayed:
Fig 1
Registration Form Steps to follow
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
Plus prefix e.g +27
capture picture to validate that you
are not a robot.
click on register button
the registerer to verify the email sent to
the provided email address.
click on βResend Verification Emailβ
button
on link provided on
the email.
etendering site with a login screen
displayed, now complete the login
with your verified email address
and password
Fig1.1
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
Fig2a.
Fig2b.
Fig3.
OTP page will be displayed
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
OTP sent to the registered cellphone number and email address
Insert the otp number then click βVerify OTPβ button, to resend OTP click on βResend OTPβ
button
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
Landing page once OTP is verified
Select the preferred βRef Noβ
A page with the preferred Tender information is displayed before tender documentation can
be submitted.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
Click on βCreate New Submissionβ button to submit required Tender documents
Landing page once clicked on βCreate New Submissionβ button. Take note of the
mentioned disclaimers.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
To submit tender documents, click on βAdd fileβ button
Upload required tender documents by:
Giving the file a name
Select the listed file type e.g.: Technical, commercial, finance and etc
Choose the file you need to upload
Then click on βUploadβ button, Fig5.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
Fig4.
Fig5.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
Continue to submit all the required documents under the correct category ,i.e: Technical
should be selected if technical documentation is uploaded and etc. Verify all required
documents are uploaded before making βFinal Submissionβ by clicking on βFinalize
Submissionβ button.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
all uploaded files should not exceed 900MB.
will pop-up
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
If not all documents were submitted or still wish to add or submit more documents, click on
βNo, continue adding filesβ button.
submission and closed time and date timestamp at the bottom.
submitted tenders will be displayed.
If you want to view or verify the submitted documents, click on βView Submissionβ button
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
submitted documents on email,Fig6.This is the final step for the submitter or tenderer.
It is vital to save the email with the submission ID for future enquiry if need be.
--------Originalmessage--------
From:Eskom E-Tender Document Submission 28 [email protected]
Date:Tue,23Aug2022,3:42pm
Subject: Response To Submitter
Eskom E-Tender Document Submission 28
Hi Monalisa
You have finalized a new submission with submission id:14 on tender #MPKUS10086PS
closing date : 2022-11-30 10:00:00.
Have started the submission from 2022-08-23 14:28:33 and finalized at 2022-08-23
15:42:28
Tender Description:
Award for Provision of Office Cleaning and Janitorial Services at Kusile Power Station
Project
Files Submitted:
ID Original Name Title Size Type
38 Test7.pdf testingCom 33141 Commercial
40 Test1.pdf testingTech 33502 Technical
41 Test15.pdf testingFin 33141 Finance
Thanks,
Eskom E-Tender Document Submission 28 Automated Mail
Β© 2022 Eskom E-Tender Document Submission 28. All rights reserved.
NB: This Email and its contents are subject to the Eskom Holdings SOC Ltd EMAIL
LEGAL NOTICE which can be viewed at
http://www.eskom.co.za/Pages/Email_Legal_Spam_Disclaimer.aspx
Fig6.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
5 Edit Registration
To edit already registered information such as Name, Organization, CSD and cell phone number
select βEdit Registrationβ on the drop down, Fig1. New window with information that needs to be
updated pop ups,Fig2. Click on βUpdateβ button to update registration details.
Fig1.
Fig2.
6 Log off Button
To logout, click βLog outβ on the dropdown next to your name
Fig1.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
7 Password reset
To reset a forgotten password, click βForgot your passwordβ Fig1. and a new screen will
pop up to enter an alternative email where the new password will be sent Fig2.Confirmation
message will be sent to the user, Fig3.
Fig1.
Fig2.
Fig3.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
An email confirming password reset will be sent to the email provided.
Click on the link or βReset Passwordβ button to reset the password.
Fig4.
A new window will pop up to reset and confirm the new password, Fig5.Enter new
password and confirm then click on βReset Passwordβ button.
Fig5.
OTP window will pop up, type in the OTP sent to either the cell phone or email address.
Fig6.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
OTP successfully goes through and lands on the below screen, password is successfully
reset.
Fig7.
8 General
This system is compatible to most web browsers however we recommend Ms Edge.
The end.
Β© 2023 Eskom of 19
eTendering system is a web-based system that allows suppliers bidding for various tenders advertised
on Tender Bulletin system to βuploadβ their tender documents. Currently the tenderers or suppliers
submit tender documents at various Eskom tender offices. eTendering system replaces the manual or
physical submission of tender documents at various Eskom tender offices. eTendering system in a
nutshell is an electronic box where tender documents can be βdroppedβ or βuploadedβ. Suppliers will
be required to register their details before they can be granted access to the eTendering system. An
OTP (one time pin) will be sent to both their cell phone and email address.
Quick and direct access is also available by using the following links:
of the public, to view and access Eskom published tenders. eTendering hyperlink will be found
on this site. Members of the public may follow prompt instructions once they have clicked on
the eTendering link (https://eTendering.eskom.co.za). This link will allow them to upload the
required tender documentation.
members of the public, to view information about published tenders and submit their tender
documents.
eTendering system.
2 Problems
A channel of communication has been created in case users of the system experiences a problem
with the system. In a case users come across some difficulties in using Tender bulletin, eTendering
and OpenText systems they need to contact the buyer responsible for the published tender.
3 Whatβs New
A new functionality to βadd closed tendersβ. Closed tenders refers to the tenders which are not listed
on Tenderbulletin as normal tenders, but are tenders sent directly to the relevant and potential
suppliers who meet the selection and evaluation criteria to offer what the buyer needs. These
suppliers will be sent a link via email to bid privately.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
4 Getting Started
To gain access to eTendering portal
Open your web browser
Type TenderBulletin (eskom.co.za) or https://eTendering.eskom.co.za
eTendering system login page will be displayed:
Fig 1
Registration Form Steps to follow
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
Plus prefix e.g +27
capture picture to validate that you
are not a robot.
click on register button
the registerer to verify the email sent to
the provided email address.
click on βResend Verification Emailβ
button
on link provided on
the email.
etendering site with a login screen
displayed, now complete the login
with your verified email address
and password
Fig1.1
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
Fig2a.
Fig2b.
Fig3.
OTP page will be displayed
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
OTP sent to the registered cellphone number and email address
Insert the otp number then click βVerify OTPβ button, to resend OTP click on βResend OTPβ
button
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
Landing page once OTP is verified
Select the preferred βRef Noβ
A page with the preferred Tender information is displayed before tender documentation can
be submitted.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
Click on βCreate New Submissionβ button to submit required Tender documents
Landing page once clicked on βCreate New Submissionβ button. Take note of the
mentioned disclaimers.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
To submit tender documents, click on βAdd fileβ button
Upload required tender documents by:
Giving the file a name
Select the listed file type e.g.: Technical, commercial, finance and etc
Choose the file you need to upload
Then click on βUploadβ button, Fig5.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
Fig4.
Fig5.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
Continue to submit all the required documents under the correct category ,i.e: Technical
should be selected if technical documentation is uploaded and etc. Verify all required
documents are uploaded before making βFinal Submissionβ by clicking on βFinalize
Submissionβ button.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
all uploaded files should not exceed 900MB.
will pop-up
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
If not all documents were submitted or still wish to add or submit more documents, click on
βNo, continue adding filesβ button.
submission and closed time and date timestamp at the bottom.
submitted tenders will be displayed.
If you want to view or verify the submitted documents, click on βView Submissionβ button
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
submitted documents on email,Fig6.This is the final step for the submitter or tenderer.
It is vital to save the email with the submission ID for future enquiry if need be.
--------Originalmessage--------
From:Eskom E-Tender Document Submission 28 [email protected]
Date:Tue,23Aug2022,3:42pm
Subject: Response To Submitter
Eskom E-Tender Document Submission 28
Hi Monalisa
You have finalized a new submission with submission id:14 on tender #MPKUS10086PS
closing date : 2022-11-30 10:00:00.
Have started the submission from 2022-08-23 14:28:33 and finalized at 2022-08-23
15:42:28
Tender Description:
Award for Provision of Office Cleaning and Janitorial Services at Kusile Power Station
Project
Files Submitted:
ID Original Name Title Size Type
38 Test7.pdf testingCom 33141 Commercial
40 Test1.pdf testingTech 33502 Technical
41 Test15.pdf testingFin 33141 Finance
Thanks,
Eskom E-Tender Document Submission 28 Automated Mail
Β© 2022 Eskom E-Tender Document Submission 28. All rights reserved.
NB: This Email and its contents are subject to the Eskom Holdings SOC Ltd EMAIL
LEGAL NOTICE which can be viewed at
http://www.eskom.co.za/Pages/Email_Legal_Spam_Disclaimer.aspx
Fig6.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
5 Edit Registration
To edit already registered information such as Name, Organization, CSD and cell phone number
select βEdit Registrationβ on the drop down, Fig1. New window with information that needs to be
updated pop ups,Fig2. Click on βUpdateβ button to update registration details.
Fig1.
Fig2.
6 Log off Button
To logout, click βLog outβ on the dropdown next to your name
Fig1.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
7 Password reset
To reset a forgotten password, click βForgot your passwordβ Fig1. and a new screen will
pop up to enter an alternative email where the new password will be sent Fig2.Confirmation
message will be sent to the user, Fig3.
Fig1.
Fig2.
Fig3.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
An email confirming password reset will be sent to the email provided.
Click on the link or βReset Passwordβ button to reset the password.
Fig4.
A new window will pop up to reset and confirm the new password, Fig5.Enter new
password and confirm then click on βReset Passwordβ button.
Fig5.
OTP window will pop up, type in the OTP sent to either the cell phone or email address.
Fig6.
Β© 2023 Eskom of 19
Proprietary and Confidential
Eskom eTendering System
User Manual
OTP successfully goes through and lands on the below screen, password is successfully
reset.
Fig7.
8 General
This system is compatible to most web browsers however we recommend Ms Edge.
The end.
Β© 2023 Eskom of 19
Financial Requirements
Source: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage.zip (TENDER)Payment Terms: payment terms as stipulated hereunder when
submitting tenders and concluding contracts with Eskom:
For contracts valued below R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed to paying
Suppliers within 30 days of receipt of undisputed invoices.
For contracts valued above R50 000 000 (Fifty Million Rand) including VAT, Eskom is committed
Compliance Requirements
Source: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage.zip (TENDER)ADDITIONAL CONTRACTUAL REQUIREMENTS SUPPORTING EVIDENCE Safety COIDA - Original certificate of good standing or proof β of application issued by the Compensation Fund (COID) or a licensed compensation insurer (South African tenderers only) Quality Quality Requirements - Category 3 as follows: β
List of Tender Returnable/Quality Requirement Document-Template ref 240- 12248652
FORM A: Tender & Contract Quality Requirements For QM 58 and Quality Requirements For ISO 9001 Standard- Template ref-240-68099512
Template for a Typical Contract Quality Plan- Template ref-240-109253698
Quality Control Plan / Inspection and Test Plan (QCP/ITP)-Template ref-240-109253302
Supplier Quality Management: Specification- Template ref-240-105658000 (QM 58) Other safety/quality
OHS policy signed by CEO.
37(2) Eskom Agreement Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 63 File name: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage_03 September 2026 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Invitation to Tender/ Request Identifier for Proposal Effective Date 07 April 2026 Review Date April 2031 Reference Returnable From Suppliers at at ** closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable) to Tender Returnable Returnable Returnable
Acknowledgement of Eskom Lifesaving rules Environmental
Environmental Aspect and Impact register as per scope of work.
Environmental Method Statement as per scope of work. Due
A signed copy of the public interest score (only applicable to South African entities that are not audited) o Giving the actual score o Indicating whether the company is owner managed or not o Confirming whether the annual financial statements were externally prepared or not. Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 63 File name: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage_03 September 2026 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Invitation to Tender/ Request Identifier for Proposal Effective Date 07 April 2026 Review Date April 2031 Reference Returnable From Suppliers at at ** closing (Non- prior Award. required required closing. required Tender (disqualifiable)* Contract disqualifiable) to Tender Returnable Returnable Returnable
Copies of the ITA34C for the current & previous years of assessment (only applicable to South African entities that are not audited)
For unincorporated JV or a SPV, each partner in the JV or a SPV must submit its annual financial statements including all items listed above. DOCUMENTS REQUIRED UNDER FUNCTIONALITY/TECHINICAL CRITERIA Functionality/Technical Refer to item 3.13 on of the document β Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 63 File name: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage_03 September 2026 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Invitation to Tender/ Request Identifier for Proposal Effective Date 07 April 2026 Review Date April 2031 ANNEXURE A AUTHORISATION FORM Indicate the status of the tenderer by ticking the appropriate box below. A B C D E F COMPANY CLOSE PARTNERSHIP JOINT SOLE TRUST CORPORATION VENTURE PROPRIETOR The tenderer must complete the appropriate certificate set out below for its category of organisation. If the tenderer is a company, close corporation, joint venture, or trust the tenderer must attach a certified copy the document that is proof of the contents of the certificate (resolution of the board of directors of a company, membersβ resolution of a close corporation, power of attorney in the case of a joint venture, or resolution of the board of trustees of a trust). Note further that, in addition to completing the relevant certificate for category of organisation, the authorised representative of the tenderer is also required to complete and sign the table at the end of this Authorisation Form.
Certificate for company I,_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ , in my capacity as _ _ _ _ _ _ _ _ _ _ _ of the board of directors of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, hereby confirm that by resolution of the board taken on _ _ _ __ _ _ _ _ (date), Mr/Ms _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ , acting in his/her capacity of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, is authorised to submit this tender on behalf of the company, and to sign all documents in connection with this tender and any contract that may result from it on behalf of the company. A certified copy of the resolution of the board is annexed to this Form. Signed: Date: Name: Position: Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 63 File name: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage_03 September 2026 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Invitation to Tender/ Request Identifier for Proposal Effective Date 07 April 2026 Review Date April 2031
Certificate for close corporation I,_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ , in my capacity as member of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, hereby confirm that by majority vote of the members taken on _ _ _ __ _ _ _ _ (date), Mr/Ms _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ , acting in his/her capacity of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, is authorised to submit this tender on behalf of the close corporation, and to sign all documents in connection with this tender and any contract that may result from it on behalf of the close corporation. A certified copy of the membersβ resolution is annexed to this Form. Signed: Date: Name: Position
Certificate for partnership We, the undersigned, being the key partners in the business trading as _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ hereby authorise Mr/Ms _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, acting in his/her capacity of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, to submit this tender on behalf of the partnership, and to sign all documents in connection with the tender and any contract that may result from it on behalf of the partnership. Name Address Signature Date Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 63 File name: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage_03 September 2026 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Invitation to Tender/ Request Identifier for Proposal Effective Date 07 April 2026 Review Date April 2031 NOTE: This certificate is required to be completed and signed by the full number of Partners necessary to commit the Partnership. Attach additional pages if more space is required.
Certificate for Joint Venture We, the undersigned, are submitting this tender offer in Joint Venture and hereby authorise Mr/Ms _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, an authorised signatory of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ , being the lead member in the Joint Venture, to sign all documents in connection with the tender and any contract that may result from it on behalf of all the members in the Joint Venture. This authorisation is evidenced by the attached power of attorney signed by the legally authorised signatories of all the members in the Joint Venture. We attach to this Form a certified copy of the Joint Venture Agreement which incorporates a statement that all members in the Joint Venture are liable jointly and severally for the execution of the contract, a term that indicates which member will be the lead member, and terms that indicate the ratios according to which work and payment will be divided amongst the members. Name of JV member Address Authorised signature, name and capacity Lead member Member Member Member NOTE: This certificate is required to be completed and signed by all members of the joint venture. Attach additional pages if more space is required.
Certificate for sole proprietor I, _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, hereby confirm that I am the sole proprietor of the business trading as _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 63 File name: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage_03 September 2026 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Invitation to Tender/ Request Identifier for Proposal Effective Date 07 April 2026 Review Date April 2031 Signed: Date: Name: Position:(Sole Proprietor)
Certificate for trust I,_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ , in my capacity as _ _ _ _ _ _ _ _ _ _ _ of the board of trustees of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, hereby confirm that by resolution of the board of trustees taken on _ _ _ __ _ _ _ _ (date), Mr/Ms _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ , acting in his/her capacity of _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _, is authorised to submit this tender on behalf of the trust and to sign all documents in connection with this tender and any contract that may result from it on behalf of the trust. A certified copy of the resolution of the board of trustees is annexed to this Form. Signed: Date: Name: Position: NOTE: The table below must also be fully completed by all tenderers in addition to the certificate that was selected and completed above. Name of tenderer: Full names of authorised signatory: Designation and capacity: Signature of authorised signatory Date of signature: Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 63 File name: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage_03 September 2026 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Invitation to Tender/ Request Identifier for Proposal Effective Date 07 April 2026 Review Date April 2031 Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 63 File name: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage_03 September 2026 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Invitation to Tender/ Request Identifier for Proposal Effective Date 07 April 2026 Review Date April 2031 ANNEXURE B ACKNOWLEDGEMENT FORM We are in receipt of the Invitation to Tender from Eskom Holdings SOC Ltd and the following addenda issued by Eskom: We confirm that the documentation received by us is: (Indicate by ticking the box) Correct as stated in the Invitation to Tender Content List, and that each document is complete. ο¨ Or: Incorrect or incomplete for the following reasons: ο¨ Cataloguing Acknowledgement: Please select the relevant statement by ticking the appropriate box below
We agree to provide the cataloguing information as described in the Invitation to Tender ο¨
We have already supplied Eskom with the cataloguing information pertaining to this Invitation to Tender in a previous contract/order [insert previous contract/order number] ο¨ __________
We do not intend to provide the required cataloguing information for the reasons stated hereunder: ο¨
We are a Distributor/Importer/Agent and our Principal, being the Original Equipment Manufacturer (OEM), is or is not [delete whichever is not applicable] in the position to supply cataloguing information for items. We attach the letter from the OEM confirming its position. ο¨ Controlled Disclosure Anonymously report fraud, corruption at 0800 11 2722/ [email protected] When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 of 63 File name: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage_03 September 2026 Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 240-114238630 Rev 28 Invitation to Tender/ Request Identifier for Proposal Effective Date 07 April 2026 Review Date April 2031 Invitation to Tender/Request for Proposal No: ____________________ Name of Tenderer: ___________ _ _ Country of registration: _______________________________________ Full names of contact person: __________________________________ Contact details: Tel (landline): Cell phone: e-mail address: Name of tenderer: Full names of authorised signatory
[2] 240-60725641 - Specification for Standard (19 Inch) Equipment Cabinets 2.3 Definitions Intelligent A microprocessor-based device that encompasses all or some of the following electronic functionalities: protection, control and automation, metering, telecontrol, device substation DC and auxiliary supply systems, quality of supply monitoring, and disturbance and event recording. 2.4 Abbreviations Abbreviation Explanation IED Intelligent electronic device AC Alternating Current DC Direct Current 2.5 Roles and Responsibilities N/A 2.6 Process for Monitoring N/A 2.7 Related/Supporting Documents 0.18/13135 - Corona Cage Single Line Diagram CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30 Functional Specification for Eskom Corona Cage Unique Identifier: 559-1188133888 Protection System Revision: 1 Page
Overview of the Existing Corona Cage Facility The electrical overview of the existing Eskom Research Corona Cage Test Facility is provided in 0.18/13135. The diagram provides the layout of both the primary plant (i.e. test transformers and auxiliary transformers) and as well as the existing protection system design. 3.1 Existing Primary Plant The test facility receives 3 phase 11 kV power supply via an incoming cable from Eskom Megawatt Park substation. The supply then passes through a 3-phase air insulated isolator and circuit breaker, after which only two of the phases (Blue and Red) are taken out and used for testing purpose. From the circuit breaker, a current limiting reactor is installed on the red phase before the two phases enter the voltage regulator which serves the purpose of test voltage control/regulation. The regulated supply then flows through two compensating reactors to compensate the capacitive cage load, before the first test transformer which steps up the incoming voltage to the required test voltage up to 400kV. The second test transformer which is insulated at 400kV above earth is used to raise the secondary voltage of the first test transformer further up to a maximum of 800kV. The interface to secondary plant is facilitated by the current and voltage transformers installed at various sections of the main power circuit as shown in 0.18/13135. 3.2 Existing Protection System The existing electrical protection system for the facility is housed in a single relay panel (RP) and provides for the protection of equipment, control of test supply to the facility and monitoring of the facility. The relay panel is located inside a room within the facility. The relay panel exchanges various analogue (current and voltage) and digital (trip, alarms and indication) signal with the primary plant through low voltage cabling which runs in covered trenches and enters the panel via bottom entry. Below is the list of main functions implemented in the protection and control panel
Overcurrent (50&51) β from CT1 located after the circuit breaker
Undervoltage (27) β from VT1 located after the current limiting reactor
Overcurrent (50) β from CT2 located after the voltage regulator
Transformer differential (87T) β from CT3 located after compensating reactor 2 and CT4 located on the neutral side of the test transformer 1
Overvoltage 1 and 2 (59) β from VT2 located before test transformer 1
Automatic Voltage Regulationβ from VT2 located before test transformer 1
Voltage Display (voltmeter) β from VT1 located after the current limiting reactor
Test Voltage Control (Raise and Lower)
Current Display (ammeter) β from CT2 located after the voltage regulator
Voltage Display (digital voltmeter) β from capacitive voltage transformer located on the secondary side of test transformer 1 CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30 Functional Specification for Eskom Corona Cage Unique Identifier: 559-1188133888 Protection System Revision: 1 Page: Description of Relays Trip Signals/Signs on the Protection and Control Panel (Refer to Figure 1) Figure 1: Existing Protection and Control Panel 3.2.1 Test Transformer Differential Relay Compares between primary current and secondary current of the transformers, if any unbalance is detected between primary and secondary currents the relay will send trip signal to the circuit breaker. It monitors the current in the live and the neutral (Earth leakage) and the trip signal will indicate the earth leakage. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30 Functional Specification for Eskom Corona Cage Unique Identifier: 559-1188133888 Protection System Revision: 1 Page: 3.2.2 Induction Type Overcurrent Relay It initiates corrective measures when current in the circuit exceeds the predetermined value, and it protects electrical power systems against excessive currents which are caused by short circuits, ground faults, etc. 3.2.3 High Speed Overcurrent Relay It operates only when the value of the current is greater than the relay setting time. It protects the equipment of the power system from the fault current. 3.2.4 B/U Trip Timer It is a timer for the trip relays which initiates a tripping time when faults occur. 3.2.5 Trip and Alarm Indicator It looks at all the trip signals coming from the transformers which will be the temperature, pressure and Buchholz relay. 3.2.6 Cascade Transformers Trip β It monitors the protection from the cascaded transformer; it will only trip if there is any fault on the cascaded transformers. DC Fail β it monitors the DC voltage for protection purposes, and the trip signal will be sent if DC is not available. 3.2.7 11 kV Supply Fail Trip This relay will trip when the circuit breaker has got a fault and if there is no 11 kV supply voltage. 3.2.8 Overvoltage Trip Relay It operates when the current produced by a load (Corona Cage) connected to the output of a circuit, exceeds a predetermined value. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30 Functional Specification for Eskom Corona Cage Unique Identifier: 559-1188133888 Protection System Revision: 1 Page: 3.3 New Protection System Requirements 3.4 Performance requirements 3.4.1 Sensitivity The sensitivity of the protection functions is the measure of the ability of the relay to detect faults, either with low primary quantities, or with small deviations from the healthy state. The protection system is required to respond correctly, including correct phase selection, without and with pre-fault load flow, for faults down to zero infeed conditions. Within the measurement capability of the IED, e.g. minimum current, minimum deviation from healthy state, voltage limit for accurate reach point measurement, the phase selection / directional determination shall be assured, and the variation in IED performance (tripping time) must be in accordance with the given acceptable tripping profiles. 3.4.2 Reliability: Security & Dependability 3.4.2.1 Security Security is defined as the probability of not having an unwanted operation under given conditions for a given time interval. The protection system shall have as high a security as possible. 3.4.2.2 Dependability Dependability is defined as the probability of not having a failure to operate under given conditions for a given time interval. The protection system shall have as high dependability as possible. 3.4.2.3 Directionality Directionality is the ability of a protection functions to distinguish between forward and reverse fault conditions, and in-zone and out of zone faults. The protection functions shall be capable of correctly determining the fault position, without any added delay to the overall tripping time, for any fault occurring and for any network condition. 3.4.3 Speed Clearance of electrical faults in the shortest practical time is a fundamental requirement of the protection system, particularly given the high-energy nature of HV test facilities. Protection operating times shall comply with the manufacturerβs published performance data and applicable IEC 60255 requirements. Fast operation shall not compromise security or dependability, and adequate grading and coordination shall be maintained with upstream protection systems. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30 Functional Specification for Eskom Corona Cage Unique Identifier: 559-1188133888 Protection System Revision: 1 Page: 3.4.4 Longevity The protection scheme/module shall be designed for a minimum operational life of 20 years. 3.5 Functional Requirements 3.5.1 Design Philosophy The primary objective of the new protection system is to ensure personnel safety and to protect all primary and secondary plant equipment by the accurate, selective, and rapid detection of abnormal electrical, operational, or unsafe conditions, followed by reliable isolation of the 11 kV supply. The system shall also provide comprehensive monitoring and control of the test facility. All functionality currently implemented in the existing protection system shall be retained as a minimum requirement and shall be implemented using modern, proven numerical protection technologies. The main protection functionality shall be provided by the latest and proven intelligent electronic device (IED), complaint with the IEC 60255 and IEC61850 standard. 3.5.2 Required Protection Functions The new Protection System shall provide comprehensive protection for the Corona Cage Test Facility primary and associated secondary plant. As a minimum requirement, the protection system shall include all protection functions currently implemented in the existing protection panel being replaced, with equivalent or improved performance, sensitivity, reliability, and availability. The protection functions listed below represent the baseline mandatory protection scope and shall be fully implemented using modern numerical protection relays (IEDs). The provision of these functions shall not preclude the Contractor from proposing additional or enhanced protection functions, provided such enhancements improve personnel safety, equipment protection, or system reliability and are approved by the Employer. As a minimum, the following protection functions shall be provided
Phase Overcurrent Protection (50/51) Derived from CT1 located downstream of the 11 kV circuit breaker, to provide protection against phase faults and abnormal current conditions on the incoming supply to the test facility.
Undervoltage Protection (27) Derived from VT1 located downstream of the current limiting reactor, to detect loss or abnormal reduction of supply voltage and initiate appropriate protective action in accordance with the protection philosophy.
Instantaneous Overcurrent Protection (50) Derived from CT2 located downstream of the voltage regulator, to provide fast-acting protection against severe fault conditions within the regulated test supply circuit
Transformer Differential Protection (87T) Derived from CT3 located downstream of compensating reactor 2 and CT4 located on the neutral side of Test Transformer 1, to provide sensitive and selective protection against internal faults within the test transformer, including earth faults.
Overvoltage Protection (59 β Stage 1 and Stage 2) Derived from VT2 located upstream of Test Transformer 1, to detect abnormal test voltage conditions and protect the test equipment and facility from excessive voltage stress. All protection functions shall be correctly coordinated, selectively graded, and securely implemented to ensure dependable operation for all credible fault and abnormal operating conditions. Protection settings shall be engineered specifically for the Corona Cage Test Facility operating characteristics. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30 Functional Specification for Eskom Corona Cage Unique Identifier: 559-1188133888 Protection System Revision: 1 Page: Where modern numerical protection techniques allow, the Contractor may propose enhancements such as additional stages, supervision, or adaptive features, provided that
The minimum protection functions listed above are fully retained
The original protection intent and operating philosophy are not compromised
No reduction in safety or reliability is introduced
All CT and VT connections shall be routed through test blocks. 3.5.3 Required Control Functions The new Protection System shall provide the functionality to raise and lower the test voltage of the Corona Cage Test Facility, in accordance with the same control philosophy currently implemented on the existing system. Voltage control shall be performed via the protection and control panel and shall interface with the existing voltage regulation equipment. The control functions shall allow controlled and incremental adjustment of the test voltage suitable for high-voltage testing operations. The control system shall include the necessary interlocks and permissive logic to prevent unsafe operation. Voltage raise commands shall only be enabled when all required operating conditions are satisfied, including healthy protection system status, availability of auxiliary and DC supplies, and the absence of active protection trips. On operation of any protection function, loss of permissive, loss of control power, or internal system failure, voltage raise shall be inhibited, and the system shall revert to a safe operating state, consistent with the protection philosophy. 3.5.4 Required Monitoring Functions The Protection System shall provide continuous monitoring of the primary and secondary plant associated with the Corona Cage Test Facility to support safe operation, fault detection, and operational awareness during high-voltage testing. Monitoring shall be implemented by means of IED front-panel displays and mimics, IED LEDs, and external hardwired LEDs mounted on the protection and control panel, as appropriate. All indications and alarms shall be clearly labelled, unambiguous, and visible from the normal operator position. As a minimum, the monitoring functions shall include
Circuit breaker status (Open/Closed/Tripped)
Protection operation and trip indications
DC supply healthy and failure indications
IED internal self-monitoring alarms
Transformer and auxiliary plant alarm inputs interfaced to the protection system
All critical alarms shall be latched and require operator acknowledgement. The new protection panel shall also provide real-time electrical measurements, derived from the connected CTs and VTs, displayed on a dedicated digital measurement display unit mounted on the front of the panel. As a minimum, the following measurements shall be provided
Power (active power; reactive power where available) The protection system shall provide event and alarm recording with time stamping to support fault investigation and post-event analysis. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30 Functional Specification for Eskom Corona Cage Unique Identifier: 559-1188133888 Protection System Revision: 1 Page: The monitoring and measurement functions shall comply with the applicable requirements of IEC 60255 (Measuring relays and protection equipment) 3.6 Protection and Control Panel The complete Protection System shall be housed within a single, free-standing Protection and Control Panel. The panel shall be designed for front access only, as the rear of the panel will be installed directly against a wall and will not be accessible after installation. The panel shall be designed, manufactured, and tested in accordance with IEC 61439 and IEC 62208, and shall be suitable for indoor installation. The enclosure shall have a minimum ingress protection rating of IP42 in accordance with IEC 60529. All cabling shall enter the panel via bottom cable entry only. The panel shall be fitted with suitable gland plates and internal wiring trunking to ensure orderly cable routing, correct segregation of AC, DC, protection, control, and communication wiring, and adequate capacity for future additions. The internal layout shall allow safe operation, maintenance, and testing from the front of the panel only. All equipment, terminals, and test points shall be clearly visible and accessible. All internal wiring shall be neatly installed, securely supported, ferruled, and clearly labelled. Conductor identification and colour coding shall comply with IEC 60445 / IEC 60446 and applicable Eskom practices. A dedicated internal earth bar shall be provided, and all exposed conductive parts shall be effectively earthed in accordance with IEC 61936-1. 3.7 Protection Settings and Configuration File The Contractor shall be responsible for the development and provision of all protection settings for the new Protection System, in accordance with the operating requirements of the Corona Cage Test Facility. The Final settings document to be submitted for review and acceptance by the Employer. Existing protection settings may be reviewed and reused where appropriate; however, the Contractor shall remain fully responsible for verifying the suitability, correctness, and coordination of all settings applied to the new system. The Contractor shall also carry out the complete configuration of the Intelligent Electronic Devices (IEDs), including protection functions, logic and interlocking, alarms, and control functions, in accordance with the OEM manuals, applicable IEC 60255 requirements, and good protection engineering practice. Final protection settings and IED configuration files shall form part of the handover documentation. 3.8 Other Requirements 3.8.1 DC system The Contractor shall be fully responsible for the sizing, detailed design, manufacture, supply, factory acceptance testing (FAT), site acceptance testing (SAT), installation, testing, commissioning, and handover of a new 110 V DC industrial type battery and charger system to provide a reliable auxiliary power supply for the new Corona Cage Protection System. The battery charger shall be in accordance with SANS 1652:2023 - Battery chargers β Industrial type. The batteries shall be in accordance with SANS 62259: 2005 or IEC 62259: 2003, Secondary cells and batteries containing alkaline or other non-acid electrolytes β Nickel-cadmium prismatic secondary single cells with partial gas recombination. The DC system shall be designed to supply all normal and emergency DC loads associated with the protection system and its auxiliaries, including tripping, alarms, indications, control functions, and communications. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30 Functional Specification for Eskom Corona Cage Unique Identifier: 559-1188133888 Protection System Revision: 1 Page: The battery system shall be sized to provide a minimum standby autonomy of four (4) hours, under worst-case DC load conditions, without AC supply, while maintaining DC voltage within acceptable limits for correct operation of all connected equipment. In addition, the DC system shall be designed with a minimum of 20% spare capacity to accommodate future DC load expansion within the facility, without requiring replacement of the battery or charger. The charger shall be suitable for continuous operation, capable of supplying the connected DC load and recharging the battery in accordance with the battery manufacturerβs recommendations. The DC system shall include appropriate supervision, alarms, and protection, including but not limited to
Charger healthy/fail indications
Battery undervoltage and earth fault supervision
tax compliance status ___________________
tax compliance certificate as a tender returnable by
CSD number
Central Supplier Database (CSD), please provide your supplier registration number with
No specific requirements found
Tax compliance status
Tax compliance requirements
Tax compliance status (tcs) pin may be made via e-filing through the SARS website
Tcs pin is available but the bidder is registered on the central supplier database (csd),
Csd number must be provided
Central supplier database (csd),
2.3 Application for tax compliance status (tcs) pin may be made via e-filing through the SARS website
A separate tcs certificate / pin / csd number.
2.6 Where NO tcs pin is available but the bidder is registered on the central supplier database (csd),
A csd number must be provided.
Joint Venture Agreement which incorporates a statement
power of attorney in the case of
power of attorney signed by the legally authorised
CSD report or as per certificate/affidavit provided
CSD number/CSD report) must be provided at the closing date and time for
CSD number or B-BBEE certificate/affidavit will need to be
NOTE: the supplier/contractor/tenderer has to ensure that he/she understands the OHS requirements listed hereunder.
The supplier/contractor/tenderer is expected to comply to the following documents when working at/rendering a service to Eskom but not limited to the following
Eskom contractor Health and Safety requirements standards 32-136
OHS specification/requirements provided
Occupational Health and Safety Act
Compensation for Occupational Diseases and Illnesses Act Note: Please note that after contract award, it is your responsibility to fully align the companyβs processes to Eskomβs OHS requirements (policies, procedures, standards etc).
Penalties shall be enforced on the main supplier for non-conformance/s (identified for the main supplier and/or its contractor and/or supplier) pertaining to Eskom and/or Statutory OHS requirement/s.
Ensure that all employees (contractors/suppliers) undergo the relevant Eskom induction and the companyβs
Management of Contractors/ Suppliers The main contractor/supplier
Has to demonstrate to Eskom the process and selection criteria applied when appointing contractors and suppliers.
Has to provide notification to Eskom, prior to the appointment of contractors or suppliers for the commencement of work.
Has to ensure that contractors/ suppliers have adequate resources and competencies.
Is accountable for the management of its contractors/ suppliers in order to ensure that the applicable legal and Eskom requirements (that are applicable to the main supplier during contract execution) are complied with by the contractors or suppliers.
The main supplier shall monitor contractors or suppliers through audits and assessments with regard to OHS compliance during the execution of the work.
The grounds for the termination of work done by contractors/suppliers shall be provided by the main supplier.
All non-conformances/non-compliance by the contractors/suppliers (all tiers) to the main supplier shall be dealt with directly with the main contractor/supplier in terms of performance and penalty processes.
Eskom reserves the right to verify this when deemed necessary. The contractor may be instructed to provide copies of testimonials/references and the contact detail of clients (including Eskom) for whom the Company has done previous work of a similar nature I, the undersigned, hereby acknowledge that I have obtained copies of the above documents and confirm that I fully understand them and the consequences of non-compliance. Signed at ................................................ on ........ day of .................................. 20............ Public When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system. No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30. of 2 Template Annexure B: Eskom Identifier 240-43921804 Rev 5 Acknowledgement Form for Document 240-77471499 Rev 3 OHS legal and other Identifier requirements Effective Date May 2021 Company/Supplier Name
Name of Authorised person (CEO/Director/ Managing Director)
Signature Date Witness 1 ......................................... Witness 2 ........................................ Public When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system. No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd, Reg No 2002/015527/30. of 2
CSD number to gain access to
Points Allocation: 20 points
B-BBEE Details: or form by third parties without the written consent of Eskom
Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
of 63
File name: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage_03 September 2026
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 240-114238630 Rev 28
Invitation to Tender/ Request Identifier
for Proposal Effective Date 07 April 2026
Review Date April 2031
A report containing a list of potential sub-contractors may be drawn by accessing the following link:
βproof of B-BBEE status level of contributorβ means-
(a) the B-BBEE status level certificate issued by an authorised body or person; or
(b) a sworn affidavit as prescribed by the B-BBEE Codes of Good Practice; or
(c) any other requirement prescribed in terms of the Broad-Based Black Economic Empowerment Act
1.2 Tender returnables
The tenderer must submit the returnable set out hereunder as part of its tender at the stipulated deadline.
Note the following: -
These returnables are required to be completed, signed (if required on the returnable) and submitted with
the tender at Tender closing date and time. If not completed, signed (if required on the returnable) and/or
submitted by tender closing, the tenderer will be disqualified.
** Returnable required at Tender closing (non-disqualifiable): -
These returnables are required to be completed, signed (if required on the returnable) and submitted with
Tender at Tender closing date and time; however, if not submitted by Tender closing, or submitted with
incomplete information or without a required signature, the Procurement Practitioner will, in writing,
request t
Section
Source: E3484CXMWP_Invitation to Tender (ITT)_Refurbishment and upgrading of Corona Cage.zip1.1.9 *SBD 6.1 Preference Points Claim Form in terms of Annexure I Y
PPPFA 2022 regulations
1.1.11 Tax Evaluation questionnaire to determine whether a Y
3.13 Functionality requirements Technical will form part of functionality. The Qualitative Evaluation
criterion. The minimum weighted final score (threshold) required for a
tender to be considered from a technical perspective is 70%.
Tenderers who do not meet the threshold for functionality scoring will
3.15 Evaluation of Price Prices will be evaluated as follows
evaluation parameters relating to uncertainty and risk, where
evaluation purposes but will be implemented when payment is
Prices will be scored out of 80 points
3.18 Evaluation of S
3.18 Evaluation of Specific Goals Specific goals will be scored out of 20 points in accordance with the
If a tenderer fails to submit evidence of its points claim for a Specific
Goal, it will not be disqualified. However, it will be awarded 0 points
the 80/20 system. Eskom will add the score from Pricing and Specific
80/20 for tender with rand value equal to or below R50 million
Contractual Requirements are not evaluation criteria. They will
be assessed after the evaluation and ranking of the tenders.
Quality Quality Requirements - Category 3 as follows: β
Requirements For QM 58 and Quality
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
Lower Germiston Road - Rosherville - Johannesburg - 4000
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
1
Last checked
08 Sept 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Learn how to submit a winning bid with these related articles
How consulting engineers, engineering firms, and multidisciplinary practices can win public sector infrastructure contracts in South Africa β from ECSA registration and CESA membership to fee proposals, QBS scoring, and building a winning tender response.
A comprehensive guide to civil engineering infrastructure tenders in South Africa. Covers CIDB requirements, major buyers, the tender pipeline, and how civil engineering firms win government work in roads, dams, water, and sanitation.
How mechanical and electrical engineers, contractors, and consultants can win public sector contracts in South Africa β HVAC, plumbing, fire systems, electrical infrastructure, ECSA registration, CIDB ME designation, and tender documentation essentials.
A professional guide for consulting engineers on bidding for government infrastructure projects. Understanding percentage-based fees, discounting ECSA guidelines, and managing professional indemnity risk.
π‘ Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Civil engineering. Unlock full pricing strategies, bid frequency, and historical win rates.