Repair of the sludge sump walls and execution of isolations at matla power station over a 12-month contract period. Bidders submit a completed excel returnable workbook, signed as a pdf or signed and locked, selecting category 3 (implemented quality management system) on the cover tab. The bid is decided on a quality scorecard weighted across five sections, with NO price or preference formula stated, so the decisive risk is documentary: a missing or weak quality management system evidence pack, draft contract quality plan or itp will cost score.
Key Requirements
Closing: 7 December 2026 at 08:00; submit the completed returnable workbook as a signed PDF, or signed and locked, to the Eskom buyer.
Category selection: mark only one category on the Cover tab β Category 3 (implemented QMS) applies; selecting more than one box produces an error.
Quality scorecard weighting: Section A Quality Management System 25%, Section B Evidence of QMS in operation 25%, Section C Contract Quality Plan 20%, Section D Quality Control Plan/ITP 20%, Section E Additional requirements 10%.
Section A: choose one scoring option only β a valid ISO 9001:2015 certificate (scope relevance, approved certification authority, international accreditation, expiry) or documented QMS evidence (QMS manual or method statement, approved quality policy and objectives, document and record control, control of nonconforming outputs, corrective action, internal audit).
Section B evidence: organisation chart and responsibility matrix including the quality function, external provider evaluation and re-evaluation criteria, latest internal audit report with nonconformity and corrective action reports, certification audit report not older than 12 months, and management review records.
Section C and D deliverables: a draft Contract Quality Plan specific to the scope of work (ISO 10005) and a Quality Control Plan, checklist or ITP for the scope, plus an example ITP or QCP from similar or previous work.
Section E: Form A completed and signed, plus any customer-specific requirements in the scope of work or specification; no minimum qualifying score is stated, so every section must be fully evidenced.
Tenders in this industry often require registration with these bodies.
CIDB Registration
Construction Industry Development Board (CIDB) registration is mandatory for almost all public sector construction tenders. Ensure your grading matches the tender value.
Typical Documents
10 items
Company Registration (CIPC)
Tax Clearance Certificate
B-BBEE Certificate
CSD Registration
Company Profile
CIDB Registration Certificate
NHBRC Registration (if applicable)
Health & Safety Plan
Insurance Certificates
Previous Project Completion Certificates
Recommended Certifications
Having these can improve your winning chances: NHBRC Registration, ISO 9001:2015 (Quality Management), ISO 14001:2015 (Environmental Management), ISO 45001:2018 (Occupational Health & Safety), SACPCMP Registration, ECSA Registration
Document read. The full tender notice and its supporting documents are read end-to-end. Key sections, requirements, dates, and contact details are identified and pulled into a working summary you can act on.
Compliance review. The working summary is checked against South African procurement standards β PFMA, PPPFA, B-BBEE, CIDB, local content, and preferential procurement β so nothing critical is missed before you start your bid response.
DocumentSupplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx.pdfReview complete
Description
Important Dates
17 Nov
2026
PUBLICATION
Tender Published
Tender was published
07 Dec
2026
DEADLINE
Closing Date
Tender closing date
Procurement Rules & Compliance ContextThis tender may be governed by South African public procurement rules covering fairness, transparency, preferential procurement, anti-corruption, administrative justice and access to information.
11 rules
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
Core procurement rules
These rules commonly apply to South African public-sector procurement.
7
Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
high
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Constitution of the Republic of South Africa, 1996 β Section 217
Act 108 of 1996 (s217)
high
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Repair of the sludge sump walls and associated isolations at Matla Power Station, for a contract period of 12 months. The appointed contractor must run an environmental management system aligned to ISO 14001:2015 on site and accept the polluter-pays housekeeping regime.
Eskom requires a contractor to repair sludge sump walls and perform isolations at Matla Power Station over a 12-month period. The tender uses a quality-based evaluation with Category 3 requirements, focusing on the bidder's quality management system documentation and project-specific quality plans.
The tender seeks a 12βmonth NEC3 Engineering & Construction Contract for the repair and isolation of sludge sump walls at Eskomβs Matla Power Station in Mpumalanga, including mandatory CSI spending, local labour sourcing, and comprehensive safety, insurance and defectβcorrection obligations.
Slush Sump Wall Form A Tender & Contract Quality Requirements.pdf
Repair and isolation works on the sludge sump walls at Matla Power Station for a period of 12 months. The procurement requires compliance with Category 3 pre-contract award quality requirements and ISO 9001 standard clauses. The contract includes specific quality performance monitoring and Eskom's standard rights of access, information, and preservation.
SDL&I Strategy for Sludge Sump Walls Repair and Isolations project.pdf
ESKOM requires the repair and isolation of sludge sump walls at Matla Power Station for a period of 12 months. Tenderers must comply with specific B-BBEE, local content, and skills development targets to score preference points and avoid penalties.
Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx.pdf
Eskom requires a contractor for the Matla Power Station Sludge Sump Walls Repair and Isolations project for a period of 12 months. Bidders must complete a PAYE Questionnaire for Service Contracts to determine tax status and Employees' Tax withholding obligations under the 2026/2027 tax year.
Repair of sludge sump walls and associated isolations at Matla Power Station for a period of 12 months. The available content covers only the health and safety returnables and site access conditions bidders must satisfy before contract signature.
ESKOM requires the repair and isolation of sludge sump walls at Matla Power Station for a period of 12 months. Bidders must comply with extensive environmental management, waste management, and safety requirements, including submitting an Environmental Management Plan, Waste Management Plan, Environmental Bill of Quantities, and a commitment and indemnity letter.
Environmental Contractors Assessment Form (002).pdf
Sludge sump walls repair and isolations at Matla Power Station for Eskom over a 12-month period. Bidders must complete an Environmental Contractors Assessment Form disclosing scope, duration, hazardous chemicals, waste, and permit requirements. Corrective actions for environmental non-conformance under procedure OMOP 2255 and polluter pays principles are the contractor's liability.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Similar Tenders
Matched by category & region
Supplier Readiness Hub
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Draw, Fabricate, Supply, Deliver, Replace, and Install new pipework with fittings inside the cable tunnels and pipe trenches at Kriel Power Station for a period of
six months
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
Bid-ready summary. The submission guidelines, evaluation criteria, technical, financial, and compliance sections are refined into professional, easy-to-scan prose. This is the final version you can rely on when preparing your bid or briefing your team.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically β no action required from you.
Document read
Compliance review
Bid-ready summary
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx.pdf
Purpose
The pack supports PAYE classification for contractors supplying services or labour to Eskom Holdings SOC Ltd and its subsidiaries.
It applies to companies, close corporations, trusts and individuals.
It is based on the 2026/2027 tax year and may be affected by changes in tax law.
Contractor obligations
The contractor or authorised representative must provide accurate and complete information.
The contractor must notify Eskom in writing if circumstances change.
Eskom may withhold taxes, interest and penalties from payments if information is inaccurate.
Important Dates
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx.pdf (unknown)
Closing
Bid closing: 7 December 2026 at 08:00.
Pack validity
Supplier evaluation pack applies from 1 March 2026 to 28 February 2027.
Contact Information
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx.pdf (unknown)
Companies, close corporations and trusts: Evaluation Pack A.
Individuals: Evaluation Pack B.
Supporting details
Provide contractor registration, tax, contact, address and banking details.
Provide the authorised representative or individual particulars.
Validity
The pack is for the 2026/2027 tax year and is subject to tax-law changes.
Evaluation Criteria
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx.pdf (unknown)
Tax-status assessment
The pack determines whether the contractor is an independent contractor, personal service provider, labour broker or dependent contractor.
Residence: non-residents must sign Appendix 9 and refer the pack to Eskom Group Tax.
Employee exclusion: three or more full-time employees, engaged in the business and not connected persons, may support independent status.
Connected-person services: if a connected person will personally render services to Eskom, further PAYE tests apply.
Income concentration: if more than 80% of income is likely to come from one client or an associated institution, PAYE may be withheld.
Place and control: if duties are mainly performed at Eskom premises (more than 50%) and Eskom controls or supervises the work, PAYE may be withheld.
Dominant impression test: eleven factors are assessed, including payment by deliverable, control of tools, exclusivity, subcontracting, risk, attendance, financial dependence, organisational integration, benefits, office and equipment.
Outcome: personal service provider or dependent contractor status leads to PAYE withholding; labour broker status depends on a valid IRP30 certificate.
Scoring: no scoring or minimum qualifying score is stated.
Financial Requirements
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx.pdf (unknown)
Tax withholding
Personal service provider or dependent contractor status: PAYE is withheld at the applicable individual tax rate.
IRP5/IT3(a) codes: 3601 or 3616 for dependent contractor or personal service provider; 3617 for labour broker.
Labour broker with valid IRP30: no PAYE is withheld; IT3(a) code 3617 and reason code 07 apply.
Labour broker without valid IRP30: PAYE is withheld until a valid IRP30 is provided; IRP5 code 3617 applies.
Banking
Accurate banking details are required for payment.
Compliance Requirements
Source: Supplier Evaluation Pack for 01 March 2026 to 28 February 2027.docx.pdf (unknown)
Registration and tax details
Companies, close corporations and trusts: CO/CC/Trust registration number and income tax registration number.
Individuals: ID number or passport details and income tax registration number.
VAT registration number where applicable.
Banking details and authorised representative or individual particulars.
Declarations
The contractor or authorised representative must confirm that the information is true and complete.
Applicable affidavits or declarations must be signed; unsigned documents can lead to PAYE being withheld.
Changes in status or information must be notified to Eskom in writing.
Forms
Evaluation Pack A: companies, close corporations and trusts.
Evaluation Pack B: individuals.
Appendix 1: confirms three or more full-time employees who are not connected persons.
Appendix 2: confirms no connected person will personally render services to Eskom.
Appendix 3: confirms services are not mainly performed at Eskom and are not controlled or supervised by Eskom.
Appendix 4: confirms no more than 80% of income is or is likely to be received from one client.
Appendix 5: individual confirms a service is provided, not people.
Appendix 6: labour broker declaration and IRP30 status.
Appendix 7: dependent contractor or personal service provider declaration.
Appendix 8: independent supplier or contractor declaration.
Appendix 9: non-resident declaration.
DocumentInvitation to Tender (ITT) or Request for Proposal (RFP) - Sludge Sump Refurbishment Re-issue 1.pdfReview complete
Description
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) - Sludge Sump Refurbishment Re-issue 1.pdf
Tender pack contents:
Invitation to Tender and Tender Data.
Annexures A to J covering authorisation, acknowledgement, particulars, integrity, local content, SBD 1, SBD 6.1 and SBD 4.
Tax evaluation questionnaire for service contracts.
E-tendering help manual and acknowledgement.
CIDB Contract Skills Development Goals, where applicable.
Scope of Work, NEC contract and pricing schedule/BOQ.
Important Dates
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) - Sludge Sump Refurbishment Re-issue 1.pdf (RFP)
Closing date and time: 07 December 2026 at 10:00.
Clarification meeting: 19 November 2026 at 11:00, non-compulsory, via MS Teams.
MS Teams meeting ID: 317 709 779 182 642 7.
Passcode: Ce2wR9hQ.
Attendance confirmation: tenderers intending to attend must confirm with the Eskom Representative and provide attendee names, positions and contact details.
Clarification query deadline: 5 working days before the tender submission deadline.
Tender validity: 24 weeks from closing, ending 24 May 2027 at 10:00.
CIDB-related date: 01 March 2027 at 10:00.
Contact Information
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) - Sludge Sump Refurbishment Re-issue 1.pdf (RFP)
COIDA: certificate of good standing or proof of application, for South African tenderers.
Financial due diligence: latest approved annual financial statements and related documents.
Technical/functionality documents: evidence required by the published technical criteria.
Additional professional documents: ECSA, SACPCMP, CVs, permits, licences or registrations where relevant to the scope.
Disqualification risks:
Missing or incomplete mandatory returnables at closing.
Failure to upload required documents electronically.
Late submission.
Unauthorised signature.
Non-compliance with eligibility restrictions.
Failure to meet the functionality threshold.
Evaluation Criteria
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) - Sludge Sump Refurbishment Re-issue 1.pdf (RFP)
Evaluation sequence:
Eligibility and basic compliance: bidder must not be restricted, sanctioned, on the Tender Defaulters list, in conflict of interest, or submitting multiple tenders; JV/consortium members must be jointly and severally liable.
Mandatory returnables: complete commercial, financial and technical submission required; missing mandatory documents make the bid non-responsive.
Functionality: technical criteria apply; bidders below the functionality threshold are disqualified.
Price score: 80 points.
Specific goals score: 20 points under the PPPFA 80/20 system.
Price evaluation basis:
Prices inclusive of VAT.
Corrected for arithmetic errors.
Contingencies excluded.
Adjusted for acceptable variations, deviations or alternatives.
Net present value may be compared where relevant.
Unconditional discounts considered; conditional discounts not considered for scoring but applied at payment.
Specific goals:
Claimed through SBD 6.1.
Failure to submit evidence does not disqualify but results in zero points for that goal.
Ranking:
Price and specific goal scores are combined; highest total ranks first.
Objective criteria:
SDL&I may be considered; award may go to a tenderer other than the highest scorer if objective criteria justify it.
Contractual requirements:
Assessed after ranking; failure to meet them by the required deadline may make the bidder non-responsive.
Reverse e-auction: not applicable.
Technical Specifications
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) - Sludge Sump Refurbishment Re-issue 1.pdf (RFP)
Scope: sludge sump refurbishment at Matla Power Station, including repair of sludge sump walls and isolations.
Duration: 12 months.
Location: Matla Power Station.
Contract basis: NEC3 ECC, main option A priced contract with price list; secondary options include changes in law, sectional completion, delay damages, performance bond, retention, low-performance damages, limitation of liability and additional conditions.
Cataloguing: if required, the successful tenderer must provide item cataloguing information after award and label materials according to Eskom specifications; the pricing schedule must include a cataloguing line item.
Detailed technical criteria: bidders must submit the technical/functionality evidence required by the published technical criteria.
Whole contract: the tender must cover the whole contract.
Pricing Schedule
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) - Sludge Sump Refurbishment Re-issue 1.pdf
Pricing schedule requirements:
Completed pricing schedule or BOQ must be submitted.
Upload in PDF and Excel.
Include a cataloguing line item if cataloguing is required.
Prices evaluated inclusive of VAT, with arithmetic corrections and exclusion of contingencies.
Unconditional discounts considered for evaluation; conditional discounts applied at payment.
Financial Requirements
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) - Sludge Sump Refurbishment Re-issue 1.pdf (RFP)
Pricing format: completed pricing schedule or bill of quantities; price list must be submitted in PDF and Excel.
Payment terms: Eskom payment terms are 30 days for undisputed invoices on contracts below R50 000 000 including VAT, and 60 days for undisputed invoices on contracts above R50 000 000 including VAT.
Security: no performance security is stated as required in the tender data, but the NEC contract options include performance bond and retention.
Financial capacity: latest approved annual financial statements are required; draft statements or management accounts are not accepted.
Financial documents: signed director's report, auditor/reviewer/compiler/accounting officer report, statement of financial position, comprehensive income, changes in equity, cash flows, notes, company background, public interest score where applicable, ITA34C copies for non-audited South African entities; each JV/SPV partner must submit its own statements.
Discounts: conditional discounts are not used for evaluation but will be applied when payment is made.
Price negotiation: Eskom may negotiate with preferred bidders if prices are not market-related.
Compliance Requirements
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) - Sludge Sump Refurbishment Re-issue 1.pdf (RFP)
Eligibility restrictions:
Bidder and principals must not be restricted from doing business with Eskom or state-owned companies.
Bidder must not be subject to international sanctions, National Treasury restriction, or appear on the Tender Defaulters list.
No conflict of interest; no multiple tenders; no 100% subcontracting of the scope.
JV/consortium agreement must confirm joint and several liability.
Mandatory registrations and compliance:
CSD registration: valid CSD number or report required.
Tax compliance: SARS e-filing PIN or CSD tax profile; otherwise certified tax clearance certificate. Foreign suppliers without South African footprint do not need tax compliance proof but must complete SBD 1.
B-BBEE: proof of status level by certificate, sworn affidavit, or other B-BBEE Act evidence; claimed through SBD 6.1.
Employment Equity: designated employers must provide proof of compliance and submission of the Employment Equity report.
COIDA: certificate of good standing or proof of application from the Compensation Fund or licensed insurer, for South African tenderers.
CIDB: evidence of 6CE grading for the main contractor at closing, or within 21 working days if agreed; JV or subcontractor grading may also be required.
Professional registrations: ECSA, SACPCMP, CVs, permits, licences or specific registrations where applicable.
Integrity: signed Integrity Declaration / Supplier Integrity Pact.
Local content: SBD 6.2 and local content schedules only where designated materials apply.
Safety, quality and environmental: attached SHEQ, quality and environmental requirements must be met.
Additional contractual requirements may include SHEQ, SDL&I and 2% CSI where applicable.
CSDG and CPG: not applicable.
Subcontracting: subcontracting with subsidiaries must be declared and may be treated as fronting.
Health & Safety
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) - Sludge Sump Refurbishment Re-issue 1.pdf
Health and safety requirements:
COIDA certificate of good standing or proof of application required from South African tenderers.
SHEQ requirements may apply.
Safety documents required by the scope of work must be submitted.
Attached safety requirements form part of the tender.
Contractual Terms
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) - Sludge Sump Refurbishment Re-issue 1.pdf
Contract form: NEC3 ECC with main option A, W1 dispute resolution, and secondary options X2, X5, X7, X13, X16, X17, X18 and Z.
Duration: 12 months.
Payment: 30 days for contracts below R50 000 000 including VAT; 60 days for contracts above R50 000 000 including VAT.
CIDB: 6CE grading required for main contractor.
CSDG: not applicable.
CPG: not applicable.
Tender validity: 24 weeks from closing.
Precedence: Tender Data prevails over the Eskom Standard Conditions of Tender if there is ambiguity or inconsistency.
Submission of a tender is deemed acceptance of Eskom Standard Conditions of Tender.
Section
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) - Sludge Sump Refurbishment Re-issue 1.pdf
Additional evaluation points:
Functionality is a pass/fail threshold before price scoring.
Price score: 80 points.
Specific goals score: 20 points.
Specific goal evidence is not disqualifiable but scores zero if absent.
Contractual requirements are checked after ranking and can affect award.
Repair of sludge sump walls and execution of isolations at Matla Power Station over a 12-month period. The returnable workbook requires the bidder to select a single quality category; Category 3 applies, requiring an implemented Quality Management System with documented evidence.
Evaluation is by quality scorecard, weighted across five sections:
Section A β Quality Management System (ISO 9001): 25%
Section B β Evidence of QMS in operation: 25%
Section C β Contract Quality Plan: 20%
Section D β Quality Control Plan / ITP: 20%
Section E β Additional requirements and miscellaneous: 10%
Section A scoring options
Option 1: valid ISO 9001 certificate assessed on scope relevance, approved certification authority, international accreditation and certificate validity.
Option 2: documented QMS evidence assessed on QMS manual or method statement, approved quality policy, approved quality objectives, document and record control, control of nonconforming outputs, nonconformity and corrective action, and internal audit.
Section B scoring
Organisation chart and responsibility matrix including the quality management function.
Control of externally provided processes, products and services, including evaluation, selection, monitoring and re-evaluation criteria.
Latest internal management system audit report with nonconformity, correction and corrective action reports.
Latest certification management system audit report not older than 12 months, with nonconformity, correction and corrective action reports.
Management review records (minutes, attendance registers).
Section C scoring
Draft Contract Quality Plan specific to the scope of work, including QA deliverables.
Section D scoring
Quality Control Plan, checklist or ITP for the scope of work, with an example from similar or previous work.
Section E scoring
Form A completed and signed.
Any additional customer-specific requirements stated in the scope of work or specification.
Repair of sludge sump walls and execution of isolations at Matla Power Station.
Contract period: 12 months.
Quality management category
Category 3 applies: implemented Quality Management System with documented evidence.
Required quality deliverables: Form A, implemented QMS evidence, internal management system audit report with nonconformity, correction and corrective action reports, draft Contract Quality Plan and ITP per the scope of work (ISO 10005), and information on defined roles, responsibilities and authorities.
Category 3: an implemented Quality Management System is required, evidenced by the documents listed under submission guidelines.
ISO 9001:2015 certification is required for Category 1 and 2; Category 3 and 4 accept documented QMS evidence.
Internal and external management system audit reports must include nonconformity, correction and corrective action reports.
A draft Contract Quality Plan and ITP must be submitted with the bid.
No CIDB grading, B-BBEE level, CSD registration, tax clearance or local content requirement is stated in the available document.
DocumentCONTRACTORS COMMITMENT AND INDEMNITY LETTER.pdfReview complete
Compliance Requirements
Source: CONTRACTORS COMMITMENT AND INDEMNITY LETTER.pdf (unknown)
Mandatory returnable:
Annexure D (Contractors Commitment and Indemnity Letter): completed, signed and dated by the site manager on behalf of the contractor, committing to the environmental management obligations and the polluter-pays housekeeping principle.
Environmental
Source: CONTRACTORS COMMITMENT AND INDEMNITY LETTER.pdf
Context: Matla Power Station is ISO 14001 certified; contractors must run an Environmental Management System (EMS) within the station's defined scope.
EMS: establish, implement and maintain an EMS consistent with ISO 14001:2015.
Compliance: fulfil all environmental compliance obligations and manage environmental aspects under applicable legislation, including licences, sections of acts and regulations, development approvals, guidelines, operating procedures, legislatively defined management plans, reports and agreements.
Performance: set performance indicators, reviewed regularly, to measure environmental performance and ensure continual improvement.
Risks: identify environmental risks and opportunities; set and review objectives and targets for significant aspects; develop an environmental management programme to achieve intended outcomes.
Training: provide necessary training and awareness for employees.
Resources: provide adequate resources to achieve and sustain effective environmental management.
Operational controls: fully comply with environmental operational controls and planning per OMOP 4402 and OMOP 4090.
Polluter pays: the supplier and contractor manager must assess the environmental state of the designated site and submit the housekeeping check sheet (Annexure C) to the environmental department before commencement; a further assessment is conducted at the end of the contract; the contract manager processes the final payment together with the last check sheet; any housekeeping or waste findings are charged to the supplier.
Records: maintain an EMS file as proof of compliance, based on ISO 14001:2015.
Signature: the site manager signs and dates the letter on behalf of the contractor.
DocumentSludge Sump refurbishment NEC Rev0.pdfReview complete
Description
Source: Sludge Sump refurbishment NEC Rev0.pdf
Contract form and scope:
NEC3 Engineering and Construction Contract, April 2013, Option A, with secondary options X2, X5, X7, X13, X16, X17, X18 and Z conditions.
Procurement is for sludge sump refurbishment at Matla Power Station over 12 months.
Works include cleaning of the sump, civil works, structural steel works, mechanical works and professional engineering services.
Site is Matla Power Station, Delmas Road, Kriel, 2271.
Contract administration:
Project manager and supervisor are based at Matla Power Station.
Law: South African law; language: English.
Dispute resolution: adjudication through the ICE-SA panel, then arbitration in Johannesburg under Association of Arbitrators rules.
Ethics and confidentiality:
Coercive, collusive, corrupt, fraudulent and obstructive actions are prohibited and may lead to termination.
Confidentiality applies to contract information; images of the works require prior written consent.
Special site matters:
Asbestos requirements apply; the employer manages asbestos under its standard, and removal or disposal is by a registered asbestos contractor at employer expense.
Nuclear liability provisions apply because the employer operates a nuclear installation, but the employer indemnifies the contractor for nuclear damage except in limited circumstances.
Important Dates
Source: Sludge Sump refurbishment NEC Rev0.pdf (unknown)
Defects date: 52 weeks after completion of the whole works.
Defect correction period: 1 week; 24 hours for production loss and SHE requirements; 1 week for low-risk defects.
Assessment interval: by the 25th day of each successive month.
Payment period: 30 days from submission of a correct tax invoice.
Programme updates: every 2 days during project execution; weekly during procurement and engineering.
Site access: after contract award.
Contact Information
Source: Sludge Sump refurbishment NEC Rev0.pdf (unknown)
Project manager
Role: Project Manager
Address: Matla Power Station, Delmas Road, Kriel, 2271
Telephone: 013 699 7871
Supervisor
Address: Matla Power Station, Delmas Road, Kriel, 2271
Employer's registered office
Address: Megawatt Park, Maxwell Drive, Sandton, Johannesburg
Site location
Matla Power Station, Delmas Road, Kriel, 2271
Submission Guidelines
Source: Sludge Sump refurbishment NEC Rev0.pdf (unknown)
Returnable contract documents:
C1.1 Form of Offer and Acceptance: signed offer by a duly authorised representative; CIDB registration number must be inserted where applicable.
C1.2b Contract Data Part 2: contractor details, key persons, fee percentages, working areas and tendered total.
C1.3 Proforma Guarantees: retention money guarantee and SDL&I guarantee in the prescribed form.
C2.2 Activity Schedule: lump-sum prices for each listed activity.
Post-award delivery:
Within two weeks of receiving the signed agreement, the contractor must contact the employer's agent to deliver securities, bonds, guarantees, proof of insurance and other required documents.
Failure to deliver these documents is treated as repudiation.
Alternative offers:
A separate Form of Offer and Acceptance must be used for each alternative tender.
Technical Specifications
Source: Sludge Sump refurbishment NEC Rev0.pdf (unknown)
Scope:
Repair and refurbishment of sludge sump walls and associated isolation work at Matla Power Station.
Contract period: 12 months.
Work is divided into cleaning of the sump, civil works, structural steel works, mechanical works, and professional civil/structural and mechanical engineering services.
Preliminaries include SHEQ compliance, site establishment and de-establishment, office overheads, and management of the works.
Site and access:
Site: Matla Power Station, Delmas Road, Kriel, 2271, Mpumalanga Highveld, approximately halfway between Bethal and Ogies on the R545 and 13 km north-west of Kriel.
Access: after contract award.
Site boundaries: Matla Power Station.
No takeover of works before completion; full takeover only from commissioning.
Programme and completion:
Key dates for site establishment, cleaning, civil works and mechanical works are to be set in the accepted or approved programme.
Revised programmes are required every 2 days during execution and weekly during procurement and engineering.
Risk and site conditions:
Risk register includes statutory SHE and legal non-compliance, poor workmanship, excessive dust, disease outbreak and Covid-19.
Weather compensation events are based on recorded weather at Matla Power Station main security area and SA Weather Bureau data.
Asbestos requirements apply; work must comply with the employer's asbestos standard and OHS asbestos regulations.
Deliverables:
Completed sludge sump refurbishment, cleaned sump, civil and mechanical works, and professional engineering services as priced in the activity schedule.
Experience & Qualifications
Source: Sludge Sump refurbishment NEC Rev0.pdf
Experience and key persons:
Bidders must provide CVs and key-person data in the tender schedule.
Contractor key persons are to be identified in Contract Data Part 2.
Joint ventures must notify the employer of the key person authorised to bind the venture within two weeks of the Contract Date.
Quality Management
Source: Sludge Sump refurbishment NEC Rev0.pdf
Defects and correction:
Defects date is 52 weeks after completion.
Defect correction period is 1 week, except 24 hours for production loss and SHE issues, and 1 week for low-risk defects.
Contractor must repair or replace loss or damage to the works, plant and materials until the defects certificate is issued.
Latent defects liability lasts one year after the defects date.
Low performance damages may apply for housekeeping, poor workmanship and rework.
Workmanship and SHEQ compliance are part of the risk register and preliminaries.
Pricing Schedule
Source: Sludge Sump refurbishment NEC Rev0.pdf
Pricing schedule:
NEC3 ECC3 Option A activity schedule with lump-sum prices.
Activity schedule items:
1.0 Preliminaries and general
1.1 SHEQ requirements, standards and legislation
1.2 Site establishment and de-establishment
1.3 Office overheads and other obligations
1.4 Management of the works
2.0 Building works
2.1 Civil works
2.2 Structural steel works
2.3 Mechanical works
2.4 Professional civil/structural engineering service
2.5 Professional mechanical engineering service
Total price excludes VAT; VAT at 15% is added in the offer.
Prices are fixed lump sums; quantity variations do not adjust prices unless a compensation event applies.
Payment is assessed only for completed activities.
Financial Requirements
Source: Sludge Sump refurbishment NEC Rev0.pdf (unknown)
Pricing format:
NEC3 ECC3 Option A lump-sum activity schedule.
Bidders price each activity; only completed activities are assessed for payment.
No price adjustment for quantity differences; changes only through compensation events.
VAT at 15% is shown separately in the offer.
Activity schedule:
1.0 Preliminaries and general: SHEQ, site establishment and de-establishment, office overheads, management.
2.0 Building works: civil works, structural steel works, mechanical works, professional civil/structural engineering service, professional mechanical engineering service.
Payment:
Currency: South African Rand.
Assessment date: by the 25th day of each month.
Payment: within 30 days of a correct tax invoice.
Tax invoice: within one week of the payment certificate; must show the amount due and the employer's VAT number 4740101508.
A late or incorrect tax invoice extends the payment date; interest is charged at the Standard Bank prime rate for Rand amounts and the applicable LIBOR rate for other currencies.
Security and guarantees:
Performance bond: amount to be advised at award.
Retention: 5% of each payment; 50% released after completion and 50% after 52 weeks; retention free amount is nil.
Retention money guarantee and SDL&I guarantee may be provided in the prescribed proforma.
Delay and performance:
Delay damages: 1% of total order value per week of delay, capped at 2.5% of order value.
Low performance damages: may apply for housekeeping, poor workmanship and rework.
Liability and insurance:
Contractor liability for indirect or consequential loss: R0.
Total contractor liability is capped at the total prices, excluding additional excluded matters; additional excluded matters are unlimited.
Contractor insurance covers works, plant and materials, equipment, property damage and bodily injury or death as set out in Insurance Table A.
Employer provides the Insurance Table B policies.
Other financial obligations:
Contractor must spend 2% of contract value on CSI projects.
Compliance Requirements
Source: Sludge Sump refurbishment NEC Rev0.pdf (unknown)
Registration and tax:
CIDB registration number must be provided in the Form of Offer where applicable.
A contractor registered in South Africa must comply with the Value Added Tax Act and quote the employer's VAT number 4740101508 on invoices.
B-bbee:
Any change in B-BBEE status must be notified within 7 days.
An updated verification certificate and supporting documents must be submitted within 30 days.
If the status falls, the employer may renegotiate or terminate; failure to notify may lead to termination.
Local content and social obligations:
2% of contract value must be spent on CSI projects selected by Matla Power Station.
Non-skilled labour must be hired from the Kriel community and local skilled labour must be developed.
Joint ventures and assignment:
Joint ventures or consortia are jointly and severally liable.
The key person authorised to bind the venture must be notified within two weeks of the Contract Date.
The composition of the venture cannot change without employer consent.
No cession, delegation or assignment without the employer's written consent.
Forms:
C1.1 Form of Offer and Acceptance.
C1.2b Contract Data Part 2.
C1.3 Proforma Guarantees.
C2.2 Activity Schedule.
Other compliance:
Confidentiality applies to contract information; taking images of the works requires prior written consent.
Coercive, collusive, corrupt, fraudulent and obstructive actions are prohibited and may lead to termination.
Asbestos work must follow the employer's asbestos standard and registered asbestos contractor requirements.
Health & Safety
Source: Sludge Sump refurbishment NEC Rev0.pdf
Health and safety:
Contractor must take all reasonable precautions to protect health and safety.
Employer may appoint the contractor as Principal Contractor under the Construction Regulations 2014.
Prices must include sufficient allowance for the Construction Regulations, OHS laws and contract SHE rules.
Risk register includes statutory SHE and legal non-compliance, injuries, near misses and penalties.
Asbestos: the employer ensures ambient air meets asbestos standards; the contractor may stop work and leave contaminated areas until declared safe.
Asbestos removal and disposal must be by a registered asbestos contractor instructed by the employer at employer expense.
Covid-19 and disease outbreak are listed risk register matters.
Environmental
Source: Sludge Sump refurbishment NEC Rev0.pdf
Environmental:
Contractor must comply with applicable environmental laws, regulations and contract procedures.
Subcontractors and employees must also comply.
Dust is a risk; excessive dust is listed in the risk register.
Asbestos-containing material and waste must be handled and disposed of under South African legislation by a registered asbestos contractor.
Site air quality context includes power station emissions, ash handling, coal stockyard dust, road dust, ploughing dust and ash dam surfaces.
Contractual Terms
Source: Sludge Sump refurbishment NEC Rev0.pdf
Contract basis:
NEC3 ECC3 Option A priced contract with activity schedule.
Secondary options: X2 changes in law, X5 sectional completion, X7 delay damages, X13 performance bond, X16 retention, X17 low performance damages, X18 limitation of liability, Z additional conditions.
Completion date and sectional completion dates are to be set in the accepted programme.
Defects date: 52 weeks after completion of the whole works.
Defect correction periods: 1 week generally; 24 hours for production loss and SHE requirements; 1 week for low-risk defects.
Delay damages: 1% of total order value per week, capped at 2.5%.
Performance bond: amount to be advised at award.
Retention: 5% of each payment; 50% after completion, 50% after 52 weeks.
Contractor liability for indirect or consequential loss: R0; total liability capped at total prices except additional excluded matters, which are unlimited.
Termination may follow prohibited actions, unremedied delay damages reaching the cap, business rescue, or a fall in B-BBEE status.
B-BBEE status changes must be notified within 7 days and verified within 30 days.
No assignment or cession without consent; joint ventures are jointly and severally liable and must notify the key person within two weeks.
Confidentiality and image rights vest in the employer.
Insurance: contractor provides Table A insurances; employer provides Table B insurances.
Asbestos: employer manages asbestos; contractor may stop work in contaminated areas; removal by registered asbestos contractor at employer expense.
Disputes: adjudication under the ICE-SA panel, then arbitration in Johannesburg.
Section
Source: Sludge Sump refurbishment NEC Rev0.pdf
Mandatory award and delivery conditions:
Contractor must spend 2% of contract value on CSI projects; the project list is provided by Matla Power Station.
Contractor must develop local skilled labour at Kriel and hire non-skilled employees from the Kriel community; the potential employee list is provided by Matla Power Station.
Only deviations recorded in the Schedule of Deviations are valid; covering letters are excluded from the final contract unless agreed and recorded.
Key dates for cleaning, civil and mechanical works follow the approved schedule.
DocumentEnvironmental Contractors Assessment Form (002).pdfReview complete
Description
Source: Environmental Contractors Assessment Form (002).pdf
Contractor assessment particulars:
Record the contractor name, assessment date, responsible contractor representative and assessor.
Identify the work category as outage/project, maintenance or other, with details where other is selected.
Provide a brief scope of the work and the duration of the contractor's work at Matla Power Station.
Contact Information
Source: Environmental Contractors Assessment Form (002).pdf (unknown)
Department: Matla Environmental Department
Technical Specifications
Source: Environmental Contractors Assessment Form (002).pdf (unknown)
Project context:
The work concerns repair and isolation of sludge sump walls at Matla Power Station, with a 12-month duration.
Contractor assessment:
Capture the contractor name, assessment date, responsible contractor representative and assessor.
Select the work category: outage/project, maintenance or other; provide details if other.
Summarise the scope and state the period the contractor will be on site at Matla Power Station.
Hazardous materials and facilities:
List any hazardous substances intended for use, such as oils, greases, SAF-Heavy, hydrochloric acid, cleaning agents or pesticides.
Provide a 16-point Material Safety Data Sheet for hazardous substances.
Confirm whether a hazardous substance storage area is needed.
Confirm whether workshop facilities are needed.
Waste and authorisations:
If waste will be produced, inform Matla and identify the waste type, such as hazardous or domestic.
Indicate whether the work arises from a Matla permit or Record of Decision, for example a Water Use License or Waste Permit.
If waste will be transported, send the transport and disposal certificate to the Matla Environmental Department.
Environmental accountability:
The contractor must know non-conformance procedure OMOP 2255 and the polluter-pays principle.
The contractor bears the cost of corrective actions for non-conformance.
Quality Management
Source: Environmental Contractors Assessment Form (002).pdf
Environmental quality controls:
Waste transport must be supported by a transport and disposal certificate supplied to the Matla Environmental Department.
The contractor must be familiar with non-conformance procedure OMOP 2255 and polluter-pays principles.
Corrective actions required for non-conformance are the contractor's cost.
Compliance Requirements
Source: Environmental Contractors Assessment Form (002).pdf (unknown)
Environmental obligations:
Provide a 16-point Material Safety Data Sheet for hazardous substances.
Notify Matla of waste generation and identify the waste type.
Supply a transport and disposal certificate to the Matla Environmental Department if waste is transported.
Identify any Matla permit or Record of Decision driving the work, such as a Water Use License or Waste Permit.
Comply with OMOP 2255 and polluter-pays principles; corrective actions are the contractor's responsibility.
Health & Safety
Source: Environmental Contractors Assessment Form (002).pdf
Hazardous materials and site controls:
Identify hazardous chemicals to be used and provide a 16-point Material Safety Data Sheet where applicable.
Declare whether hazardous chemical storage is required.
Declare whether workshop facilities are required.
Identify waste types and notify Matla if waste will be generated.
DocumentSlush Sump Wall Form A Tender & Contract Quality Requirements.pdfReview complete
Description
Source: Slush Sump Wall Form A Tender & Contract Quality Requirements.pdf
Quality requirements schedule
Category 3 applies.
Categories 1, 2 and 4 do not apply.
The main supplier and sub-supplier capability and capacity assessment does not apply.
Submission Guidelines
Source: Slush Sump Wall Form A Tender & Contract Quality Requirements.pdf (unknown)
Returnable form
Form A Tender & Contract Quality Requirements: the tenderer must indicate which quality clauses apply.
Evaluation Criteria
Source: Slush Sump Wall Form A Tender & Contract Quality Requirements.pdf (unknown)
Quality compliance assessment
Category 3 pre-contract award quality requirements apply.
ISO 9001 clauses 4 to 10 and quality principles 1 to 7 apply.
Post-contract award quality monitoring and Eskom standard conditions apply.
Technical Specifications
Source: Slush Sump Wall Form A Tender & Contract Quality Requirements.pdf (unknown)
Scope
Repair and isolation of sludge sump walls at Matla Power Station for 12 months.
Quality requirements
Category 3 pre-contract award quality requirements apply.
ISO 9001 clauses 4 to 10 apply.
Eskom rights of access, information, preservation, quality audits, nonconformity management and special processes apply.
Methodology
Source: Slush Sump Wall Form A Tender & Contract Quality Requirements.pdf
Quality management framework
ISO 9001 clauses 4 to 10 apply.
Quality principles 1 to 7 apply.
Quality Management
Source: Slush Sump Wall Form A Tender & Contract Quality Requirements.pdf
Quality management requirements
Pre-contract award: Category 3 applies.
ISO 9001: clauses 4 to 10 and principles 1 to 7 apply.
Post-contract: contract execution, supplier quality performance monitoring, Eskom access, information, preservation, audits, nonconformities and special processes apply.
Compliance Requirements
Source: Slush Sump Wall Form A Tender & Contract Quality Requirements.pdf (unknown)
Quality compliance
Category 3 pre-contract award quality requirements apply.
ISO 9001 clauses 4 to 10 and quality principles 1 to 7 apply.
The bidder must accept Eskom standard conditions for access, information, preservation, audits, nonconformities and special processes.
Section
Source: Slush Sump Wall Form A Tender & Contract Quality Requirements.pdf
Quality compliance checkpoints
Category 3 pre-contract award requirements apply.
ISO 9001 clauses 4 to 10 apply.
Post-contract quality monitoring and Eskom standard conditions apply.
DocumentSDL&I Strategy for Sludge Sump Walls Repair and Isolations project.pdfReview complete
Description
Source: SDL&I Strategy for Sludge Sump Walls Repair and Isolations project.pdf
SDL&I objectives
Bidders must complete and submit the SDL&I objectives
Failure to meet Eskom targets does not disqualify a bidder
SDL&I objectives are not scored, but commitments become contractual obligations
Transformation objective: submit a B-BBEE improvement or retention plan
Important Dates
Source: SDL&I Strategy for Sludge Sump Walls Repair and Isolations project.pdf (unknown)
Post-award deadlines
B-BBEE improvement or retention plan: submit within 30 days after contract signature
SDL&I Implementation Schedule: return to the SDL&I representative within 28 days after contract award
SDL&I compliance reports: submit quarterly
Eskom review of SDL&I reports: within 30 days after receipt
Corrective action: implement before the next reporting period after written notice of non-compliance
Contact Information
Source: SDL&I Strategy for Sludge Sump Walls Repair and Isolations project.pdf (unknown)
Buyer
Name: Gloria Marebane
Business unit: Matla Power Station
Compiler
Name: Thomas Chuene
Role: Senior Advisor, Supplier Development, Localisation and Industrialisation
Submission Guidelines
Source: SDL&I Strategy for Sludge Sump Walls Repair and Isolations project.pdf (unknown)
Returnable documents
SBD 6.2 Declaration for Local Production and Content, where local content requirements apply
Annex C Local Content Declaration Summary Schedule, where local content requirements apply
B-BBEE certificate or sworn affidavit, with ownership, certified ID and disability evidence where applicable, to claim preference points
Consolidated B-BBEE verification certificate for a trust, consortium or joint venture
Bid consequences
Failure to meet a designated-sector local content threshold may make the bid non-compliant
Missing B-BBEE preference documentation does not automatically disqualify, but limits price scoring to 90 or 80 points and gives zero specific-goal points
Evaluation Criteria
Source: SDL&I Strategy for Sludge Sump Walls Repair and Isolations project.pdf (unknown)
Evaluation
Specific-goal points: maximum 10 points under the 90/10 system or 20 points under the 80/20 system
Specific-goal points are added to price points; total is rounded to two decimals
Contract award: highest total score, subject to PPPFA section 2(1)(f)
B-BBEE points
Level 1: 10 points under 90/10 or 20 points under 80/20
Level 2: 9 or 18
Level 3: 6 or 14
Level 4: 5 or 12
Level 5: 4 or 8
Level 6: 3 or 6
Level 7: 2 or 4
Level 8: 1 or 2
Non-compliant: 0
Objective criteria
Designated-sector local content thresholds must be met in full: steel pipes 100%; bolts and nuts 100%; valves 70%; pumps 70%
Failure to meet objective criteria may result in the next-ranked bidder being recommended
SDL&I objectives
SDL&I targets are not scored, but submitted commitments become contractual obligations
Technical Specifications
Source: SDL&I Strategy for Sludge Sump Walls Repair and Isolations project.pdf (unknown)
Project scope
Repair of sludge sump walls and isolation works at Matla Power Station
Contract duration: 12 months
Buyer: Gloria Marebane
SDL&I requirements
Local procurement content target: 100%
Bidders must state the type and number of jobs to be created and retained in South Africa
Skills development proposal required for work-integrated learning or training
Eskom skills target: 3 candidates
Entry requirement: N3 or matric equivalent
Output: on-the-job training or training
Candidates must come from all provinces and reflect South African demographics
Eskom employees and registered learners are excluded
Bidder bears the full cost of skills development; Eskom provides no funding
Methodology
Source: SDL&I Strategy for Sludge Sump Walls Repair and Isolations project.pdf
Skills development delivery
Skills development may be delivered directly by the bidder and through its supply network
SETA-accredited training providers may be used for critical and scarce skills
Candidates must be unemployed South Africans from all provinces and demographically representative
Eskom employees and registered learners are excluded
Bidder bears all skills development costs; Eskom makes no contribution
Bidders may seek SETA grants, subsidies, incentives and SARS tax rebates
SDL&I security
1.5% of contract value penalty for SDL&I non-performance
1.5% retention on each invoice excluding VAT until SDL&I obligations are met
Pricing Schedule
Source: SDL&I Strategy for Sludge Sump Walls Repair and Isolations project.pdf
Price Schedule
Where a contract combines local and imported goods or services, the price response must be split into components
Local procurement content is total spending less the imported component
Eskom target for local procurement content: 100%
Financial Requirements
Source: SDL&I Strategy for Sludge Sump Walls Repair and Isolations project.pdf (unknown)
Pricing
Price Schedule must separate local and imported components where the contract combines them
Local procurement content is total spend minus imported content
Eskom local procurement content target: 100%
SDL&I financial security
Retention: 1.5% of each invoice, excluding VAT, retained for the contract duration
Release: retained amounts are released only after all SDL&I obligations are fulfilled
Penalty
1.5% of contract value for failure to meet SDL&I obligations
Compliance Requirements
Source: SDL&I Strategy for Sludge Sump Walls Repair and Isolations project.pdf (unknown)
B-bbee
Valid B-BBEE certificate from a SANAS-accredited agency, sworn affidavit or CIPS affidavit is required for contract award
Annual revenue up to R10 million: Exempted Micro Enterprise may submit a sworn affidavit
Annual revenue up to R50 million: Qualifying Small Enterprise must meet applicable QSE scorecard elements unless at least 51% black-owned, in which case a sworn affidavit is required
Preference-point evidence: B-BBEE certificate or affidavit, ownership/shareholding proof preferably via CIPC, certified IDs of shareholders, disability proof where applicable, consolidated certificate for trusts, consortia or joint ventures
Deponent electronic signature is not accepted
Commissioner of Oaths must be independent, sign and stamp on the same date as the deponent
SBD 6.2 and Annex C are returnable where local content applies
Affidavit validity
Deponent identity details, designation, enterprise details, ownership percentages, revenue, financial year-end, B-BBEE level and empowering-supplier status must be completed
No blank spaces; specialised enterprises must show black beneficiary percentages
Health & Safety
Source: SDL&I Strategy for Sludge Sump Walls Repair and Isolations project.pdf
Sworn affidavit validity
Deponent names and identity numbers must match identity documents
Deponent must be identified as director, owner or member
Enterprise name and business address must match CIPC registration where applicable
Black ownership, black female ownership and designated-group percentages must be stated; specialised enterprises must show black beneficiary percentages
Total revenue and basis, whether audited financial statements or management accounts, must be indicated
Financial year-end must be stated
Only one B-BBEE status level may be selected
Empowering-supplier status must be indicated; QSEs must select the basis
Deponent and Commissioner of Oaths must sign on the same date; the Commissioner must sign and stamp
Commissioner of Oaths cannot be an employee or ex officio of the enterprise
Section
Source: SDL&I Strategy for Sludge Sump Walls Repair and Isolations project.pdf
Preference scoring
Specific-goal points are added to price points
Maximum specific-goal points: 10 under 90/10 or 20 under 80/20
SBD 6.2 and Annex C apply where local content is relevant
DocumentHEALTH AND SAFETY REQUIREMENTS.pdfReview complete
Important Dates
Source: HEALTH AND SAFETY REQUIREMENTS.pdf (unknown)
Outstanding OHS documents
Time limit: within 7 working days.
Submission Guidelines
Source: HEALTH AND SAFETY REQUIREMENTS.pdf (unknown)
OHS returnables and close-out
Required OHS returnables must be submitted at tender close-out.
The returnables include Annexure B acknowledgement, Health and Safety Plan, OHS costing, Baseline Risk Assessment, COIDA Letter of Good Standing, CEO-signed OHS policy, competency certificates and three-year health and safety statistics.
Missing OHS documents may be submitted only once, within 7 working days.
If outstanding documents are not provided within that period, the bid may be treated as non-responsive and excluded from award.
Evaluation Criteria
Source: HEALTH AND SAFETY REQUIREMENTS.pdf (unknown)
Bid assessment
OHS compliance forms part of the procurement process and must be satisfied before contract signature.
Returnable OHS documents are submitted at close-out.
Assessment occurs after the mandatory and functionality stages are completed.
The bidder has one chance to provide outstanding documents within 7 working days.
If outstanding documents are not provided in time, the bid may be treated as non-responsive and excluded from award.
Financial Requirements
Source: HEALTH AND SAFETY REQUIREMENTS.pdf (unknown)
OHS costing
A detailed OHS management cost must be submitted.
Costs must be itemised and not presented as a lump sum.
The cost must cover the overall scope of work or service.
The scope of work and risk assessment may guide the cost breakdown.
Compliance Requirements
Source: HEALTH AND SAFETY REQUIREMENTS.pdf (unknown)
Mandatory OHS compliance documents
Annexure B: signed acknowledgement of Eskom OHS legal and other requirements.
Health and Safety Plan: must address project-specific OHS risks and align with the health and safety specification or requirements.
OHS costing: detailed and itemised, not a lump sum.
Baseline Risk Assessment: must identify, assess and manage OHS risks linked to the scope of work, with the methodology included.
Letter of Good Standing: valid COIDA letter or equivalent.
OHS policy: signed by the CEO and compliant with OHS Act Section 7 and ISO 45001 Clause 5.2.
Competency certificates: Health and Safety Officer with National Diploma in Safety Management NQF 6 or SAMTRAC Certificate NQF 5; Risk Assessment (HIRA); Incident Investigation; First Aid; ISO 45001 awareness.
Health and safety statistics: records for the past three financial years, including medical cases, lost-time injuries, occupational diseases and fatalities.
Site safety file: must meet Matla Power Station safety file requirements and be approved by the contract custodian and OHS professional before work starts.
Health & Safety
Source: HEALTH AND SAFETY REQUIREMENTS.pdf
Site access and work control
Site access depends on compliance with Matla Power Station safety file requirements.
Work cannot start until the site contract custodian and OHS professional approve the safety file.
OHS obligations must be met before contract signature.
Required OHS returnables
Annexure B: signed acknowledgement of Eskom OHS legal and other requirements.
Health and Safety Plan: must cover the project scope and OHS risks and align with the health and safety specification or requirements.
OHS costing: detailed, itemised and based on the overall scope of work or service; not a lump sum.
Baseline Risk Assessment: must identify, assess and manage OHS risks related to the scope of work, with the methodology used included.
Letter of Good Standing: valid COIDA letter or equivalent.
OHS policy: signed by the CEO and compliant with OHS Act Section 7 and ISO 45001 Clause 5.2.
Competency certificates: Health and Safety Officer with National Diploma in Safety Management NQF 6 or SAMTRAC Certificate NQF 5; Risk Assessment (HIRA); Incident Investigation; First Aid; ISO 45001 awareness.
Health and safety statistics: incident statistics for the past three financial years, including medical cases, lost-time injuries, occupational diseases and fatalities.
Evaluation consequence
Outstanding OHS documents may be submitted once within 7 working days.
If outstanding documents are not submitted in time, the bid may be treated as non-responsive and excluded from award.
Section
Source: HEALTH AND SAFETY REQUIREMENTS.pdf
Bid assessment
OHS compliance is assessed as part of the procurement process before contract signature.
Returnable OHS documents are submitted at close-out.
Assessment follows completion of the mandatory and functionality stages.
Missing OHS documents may be submitted only once, within 7 working days.
If outstanding documents are not submitted in time, the bid may be treated as non-responsive and excluded from award.
Environmental deliverables for the sludge sump walls repair and isolations work
Environmental Management System, aligned to ISO 14001 or equivalent, covering: environmental policy; objectives and targets; aspects and impacts register; emergency preparedness; non-conformance, corrective and preventive action; roles and responsibilities.
Environmental Management Plan addressing: handling of hazardous chemical substances; site establishment; water management; access control; environmental human resources; environmental training; environmental incident reporting; compliance with other legal requirements; a method statement tied to the scope of work.
Waste Management Plan addressing: submitted procedure or method statement; a register of waste likely to be generated by the project; waste segregation; waste minimisation; a template for recording quantities of waste disposed; applicable legislative requirements.
Environmental Bill of Quantities itemising environmental costs, including the purchase of waste bins.
Contractor's commitment and indemnity letter, signed.
Financial Requirements
Source: Environmental Requirements.pdf (unknown)
Pricing of environmental costs
Environmental costs must be itemised in the Environmental Bill of Quantities.
Items include the purchase of waste bins and other environmental provisions for the site.
Compliance Requirements
Source: Environmental Requirements.pdf (unknown)
Environmental compliance
An Environmental Management System, such as ISO 14001, must be in place and evidenced across policy, objectives and targets, aspects and impacts, emergency preparedness, corrective and preventive action, and roles and responsibilities.
An Environmental Management Plan must be submitted covering hazardous chemical substances, site establishment, water management, access control, environmental staffing, training, incident reporting, legal compliance and a scope-specific method statement.
A Waste Management Plan must be submitted covering the waste register, segregation, minimisation, disposal record-keeping and legislation.
Compliance with legal requirements beyond the environmental authorisation must be demonstrated.
A signed contractor's commitment and indemnity letter is required.
Health & Safety
Source: Environmental Requirements.pdf
Environmental management plan obligations
Hazardous chemical substances: handling procedures must be documented before work starts.
Site establishment: environmental controls must be in place from mobilisation.
Water management: measures to control and protect water on site.
Access control: restricted and controlled entry to the work area.
Environmental human resources: named environmental personnel with defined roles.
Environmental training: awareness and task-specific training for site staff.
Environmental incident reporting: incidents recorded and reported through a defined channel.
Legal compliance: all applicable environmental legislation to be met.
Method statement: a scope-specific method statement for the sludge sump wall repair and isolation work.
Environmental
Source: Environmental Requirements.pdf
Waste management
A procedure or method statement for waste handling must be submitted.
A register of waste types expected from the project must be compiled.
Waste must be segregated on site.
Waste minimisation measures must be applied.
Quantities of waste disposed must be recorded using the prescribed template.
Legislative requirements governing waste must be complied with.
Environmental costing
Environmental costs, including the purchase of waste bins, must be priced in the Environmental Bill of Quantities.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.