Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Proposal
Delivery Location
1 Jones Road - Kempton Park - Gauteng - 1632
Organization Type
GOVERNMENT
Published
03 Sept 2026
OCDS Reference
ocds-9t57fa-168911
Airports company south africa is procuring a contractor to design, supply, install, programme, test, commission and integrate an automated fixed fire-foam deluge system at the fuel farm at or tambo international airport, under an nec3 engineering and construction contract (option a, priced contract with activity schedule) for a 24-month period. The contract is a lump-sum arrangement with key dates for design acceptance, hazop, lopa, fat, sat, wet foam testing and final asset information, and requires a 5% performance bond and a 5% retention. Bidders must be able to work in a live airport environment with airside permit and night work restrictions, and must complete the contract within two years of signature.
Bidders must submit a tender in a sealed envelope marked with the tender number and description, including all required schedules and forms; late submissions will not be accepted.
The contract is an NEC3 Engineering and Construction Contract (April 2013) with main Option A (priced contract with activity schedule), so the bidder must price each activity as a lump sum and provide an activity schedule linked to the programme.
The works must be completed within 2 years of contract signature, with key dates including acceptance of detailed design (Contract Date + 4 months), HAZOP (+5 months), LOPA (+6 months), Cause & Effect Matrix (+7 months), completion of FAT (+14 months), SAT (+21 months), wet foam testing (+22 months) and final asset information (+23 months).
The bidder must provide a performance bond of 5% of the contract value (excluding VAT) within 10 working days of award notification, in the form of an unconditional on-demand guarantee from an accepted bank or insurer.
A retention of 5% of the invoiced amount applies, and delay damages are 0.05% of the contract value per day, up to a maximum of 10% of the contract value.
The bidder must submit a first programme within 2 weeks of the contract date, a quality plan within 4 weeks, and revised programmes at intervals no longer than 4 weeks.
The works are to be conducted in a live airport environment, with risks including airside permit delays, statutory and ACSA approvals, night work restrictions and power supply outages; the bidder must include these in the risk register.
The bidder must provide key persons with specified qualifications and experience, and must notify the Project Manager and Employer of the key person authorised to bind the contractor within 1 week of the contract date.
All designs, drawings, BIM models, software, PLC code, SCADA configurations, databases and documentation produced under the contract become the property of ACSA upon payment, and all hardware and software must comply with ACSA cybersecurity standards.
The bidder must complete the Contract Data Part Two (data provided by the Contractor) in full, including fee percentages, working areas, key persons and risk register matters.
Date & Time
Friday, 02 October 2026 - 11:00
Venue
https://teams.microsoft.com/meet/334262209399208?p=rajIAfkS4t87nnyUrn Meeting ID: 334 262 209 399 2
Request for Proposal
1 Jones Road - Kempton Park - Gauteng - 1632
03 Sept
2026
Tender Published
Tender was published
02 Oct
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
Contract for Automation of fixed fire foam deluge systems.docx.pdf
No summary available
Continue with tenders sharing this issuer, category, or province.
Median Estimate
R 3 614 164
Range
Based on 20 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
Tenders in this industry often require registration with these bodies.
Recommended Certifications
Having these can improve your winning chances: Good Manufacturing Practice (GMP), SABS Product Certification, NRCS Certification
AI Document Analysis Stages
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Review in progress
The information shown on this card is preliminary. Our procurement team is currently finalising the submission guidelines, evaluation criteria, technical specifications, financial requirements, and compliance sections so you have a clean, bid-ready summary to work from. Document being finalised: ORTIA81732026RFP Automation of Fixed Fire Foam Deluge System.pdf. You don’t need to refresh — this page will pick up the updated review automatically.
Important Dates
Source: ORTIA81732026RFP Automation of Fixed Fire Foam Deluge System.pdf (RFP){"briefingSession":"{"date":"11 September 2026","time":"10h00am","venue":"Microsoft Teams meeting","is_compulsory":true}"}
Contact Information
Source: ORTIA81732026RFP Automation of Fixed Fire Foam Deluge System.pdf (RFP){"name":null,"email":"[email protected]","phone":"011 723 1400","department":"representatives after the approval of a","address":"AT THE TANK FARMS AT ORTIA FOR A N"}
Evaluation Criteria
Source: ORTIA81732026RFP Automation of Fixed Fire Foam Deluge System.pdf (RFP)Valid CSD registration is required for the bid to be considered.
SBD 4 (B-BBEE) form must be completed and submitted as part of the offer.
The bidder must have a firm intention to contract and the legal capacity to enter into the contract.
The bidder must not be under restrictions preventing participation in the employer’s procurement.
The bidder must not be insolvent, in business rescue, or have its affairs managed by a legal representative.
Compliance Requirements
Source: ORTIA81732026RFP Automation of Fixed Fire Foam Deluge System.pdf (RFP)No specific requirements found
B-BBEE Minimum Level: 1
B-BBEE Details: price of tender under consideration
Pt = Price of tender under consideration
Pmin = Price of lowest acceptable tender
Evaluation of Preference
ACSA will score specific goals out of 20 in accordance with the PPP Regulations 2022/2023. If a
bidder fails to meet the Specific goals as outlined on the table below and to submit proof, the
bidder will score zero (0) out of 20 . ACSA will not disqualify the bidder. See below Specific goals
that must be achieved for this bid:
Paste applicable goal here:
of 73
Confidential
Confidential
Number of
Specific Goals points
(80/20 system)
B-BBEE Status Level 1 5
B-BBEE Status Level 2 4.5
B-BBEE Status Level 3 4
B-BBEE Status Level 4 3
B-BBEE Status Level 5 2
B-BBEE Status Level 6 0.5
B-BBEE Status Level 7 0.3
B-BBEE Status Level 8 0.1
Black youth majority-owned entities 5
Black women majority-owned entities 5
Sub-contracting of South African EMEs and/or QSEs 5
51% owned by black people, youth, women or
disabled people.
Non- compliant contributor 0
Bidder to provide proof to support The Preference Points being Claimed.
a)Provide original or certified copy Valid sworn Affidavit OR
b) B-BBEE Certificate from a SANAS accredited rating agency
accredited agency must be provided
as prescribed by the B-BBEE Act and its relevant/most recent Codes of Good Practice
a) Any other supporting information..
In order to score for preference points, bidder must provide
Supporting information (proof)that is relevant to the specific goals.
C.3.12 Insurance provided by the employer
Refer to Contract Data
C.3.13 C.3.13 Acceptance of tender offer
Accept the tender offer; if in the opinion of the employer, it does not pres
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
ORTIA81732026RFP Automation of Fixed Fire Foam Deluge System.pdf
ACSA is inviting tenders for the appointment of a contractor to design, supply, install, and integrate a fixed fire detection and suppression system for the hazardous goods store at O.R. Tambo International Airport. The contractor must be knowledgeable in and compliant with SANS 10139 standards.
To download these documents and access AI-powered analysis, visit the main tender page.
Organization
Airports Company South Africa (ACSA)Contact Person
davis.mthethwa
Phone
010-207-2594
[email protected]
Address
1 Jones Road - Kempton Park - Gauteng - 1632
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
2
Last checked
08 Sept 2026
AI status
Enhanced
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Win ACSA tenders with AI Matching Engine, airport-infrastructure intelligence, compliance analysis, and application support for aviation operations.
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubLearn how to submit a winning bid with these related articles
Contact Information
Source: Contract for Automation of fixed fire foam deluge systems.docx.pdf (unknown){"name":null,"email":null,"phone":null,"department":null,"address":"conditions of contract"}
Submission Guidelines
Source: Contract for Automation of fixed fire foam deluge systems.docx.pdf (unknown)Submit tender in a sealed envelope marked with the tender number and description. Include all required schedules and forms. No late submissions will be accepted.
Evaluation Criteria
Source: Contract for Automation of fixed fire foam deluge systems.docx.pdf (unknown)Tenders will be evaluated on price, technical compliance, and contractor capability. Preference points may be awarded for B-BBEE status.
Technical Specifications
Source: Contract for Automation of fixed fire foam deluge systems.docx.pdf (unknown)Construction Contract
Between Airports Company South Africa
(Registration no: 1993/004149/06)
and [Insert at award stage]
(Reg No. ___________ )
for Design, Supply, Installation, Programming, Testing, Commissioning
and Integration of Automated Fixed Fire Foam Deluge Systems fuel
farm for a period of 24 months at ORTIA
Contents: No of
pages
Part C1 Agreements & Contract Data 2
Part C2 Pricing Data 35
Part C3 Scope of Work
Methodology
Source: Contract for Automation of fixed fire foam deluge systems.docx.pdf (unknown)Contractor's main Data responsibilities provided in Part 2; Design Months; Testing 22 Months; Fuel Farm depot Contract Date +; Contractor to submit first [document]
Experience & Qualifications
Source: Contract for Automation of fixed fire foam deluge systems.docx.pdf2 Name:
Job
Responsibilities:
1 Available from Engineering Contract Strategies Tel 011 803 3008, Fax 011 803 3009 or see
Confidential
Confidential
CV's (and further key persons data including
CVs) are appended to Tender Schedule
entitled .
11.2(14) The following matters will be included in
the Risk Register
Confidential
Airports company south africa soc limited contract NO. _________
Project & contract title
Part 2: pricing data
Document Title No of
reference pages
C2.1 Pricing assumptions: Option A
C2.2 The activity schedule
Part c2: pricing data c2 ECC3/A cover
Airports company south africa soc limited contract NO. _________
Project & contract title
C2.1 Pricing assumptions: Option A
The conditions of contract
How work is priced and assessed for payment
Clause 11 in NEC3 Engineering and Construction Contract, April 2013 (ECC3) Option A states:
Identified and 11
defined terms 11.2 (20) The Activity Schedule is the activity schedule unless later changed in
accordance with this contract.
(22) Defined Cost is the cost of the components in the Shorter Schedule of
Cost Components whether work is subcontracted or not excluding the cost of
preparing quotations for compensation events.
(27) The Price for Work Done to Date is the total of the Prices for
each group of completed activities and
each completed activity which is not in a group.
A completed activity is one which is without Defects which would either delay
or be covered by immediately following work.
(30) The Prices are the lump sum prices for each of the activities on the Activity
Schedule unless later changed in accordance with this contract.
Option A is a lump sum form of contract where the work is broken down into activities, each of which is
priced by the tendering contractor as a lump sum. Only completed activities are assessed for
payment at each assessment date; no part payment is made if the activity is not completed by the
assessment date. Function of the Activity Schedule
Clause 54.1 in Option A states: “Information in the Activity Schedule is not Works Information or Site
Information”. This confirms that instructions to do work or how it is to be done are not included in the Activity
Schedule but in the Works Information. This is further confirmed by Clause 20.1 which states, “The Contractor
Provides the Works in accordance with the Works Information”. Hence the Contractor does not Provide the
Works in accordance with the Activity Schedule. The Activity Schedule is only a pricing document.
Link to the programme
Clause 31.4 states that “The Contractor provides information which shows how each activity on the Activity
Schedule relates to the operations on each programme which he submits for acceptance”. Hence when
compiling the activity schedule, the tendering contractor needs to show each activity on the programme he
submits with his tender.
Preparing the activity schedule
The tendering contractor prepares the activity schedule and should study the ECC3 Guidance Notes pages
19 and 20 before doing so. The Employer may have instructed the tendering contractor to include particular
activities which he has specified and requires the Contractor to identify them in his activity schedule.
1 Generally it is the Contractor who prepares the Activity Schedule as part of his tender by breaking down
the work described within the Works Information into suitable activities which can be well defined, priced as
a lump sum and shown on the programme. The Employer, in his Conditions of Tender or in a Tender
Part c2: pricing data c2.1 ECC3/A pricing assumptions
Airports company south africa soc limited contract NO. _________
Project & contract title
Schedule, may have listed some items that he requires the Contractor to include in his activity schedule and
be priced accordingly.
2 The Prices are defined in clause 11.2(20) as the lump sum for each activity in the activity schedule and
the Price for Work Done to Date (PWDD) (the amount due to the contractor) is defined in clause 11.2(24)
as the total of the Prices for each activity that has been completed. Hence activities in the activity schedule
should be structured so as to provide an acceptable monthly cash flow as they are only assessed for
payment on the assessment date if they have been completed.
3 As the Contractor has an obligation to correct Defects (core clause 43.1) and there is no compensation
event for this unless the Defect was due to an Employer’s risk, the lump sum Prices must also include for
the correction of Defects.
4 If the Contractor has decided not to identify a particular activity, the cost to the Contractor of doing the
work must be included in, or spread across, the other Prices in order to fulfil the obligation to complete the
works for the tendered total of the Prices.
5 There is no adjustment to the lump sum activity schedule price if the amount, or quantity, of work within
that activity later turns out to be different to that which the contractor estimated at time of tender. The only
basis for a change to the Prices is as a result of a compensation event. See Clause 60.1.
6 Hence the Prices tendered by the Contractor in the activity schedule are inclusive of everything
necessary and incidental to Providing the Works in accordance with the Works Information, as it was at the
time of tender, as well as correct any Defects not caused by an Employer’s risk.
7 However, the Contractor does not have to allow in his Prices for matters that may arise as a result of a
compensation event. It should be noted that the list of compensation events includes those arising as a
result of an Employer's risk event listed in core clause 80.1.
An activity schedule could have the following format:
Item Programme Activity description Price
No. Reference
Part c2: pricing data c2.1 ECC3/A pricing assumptions
Airports company south africa soc limited contract NO. _________
Project & contract title
C2.2 the activity schedule
NEC3 ECC Option A – Priced Contract with Activity Schedule
Item No. Activity Description Amount (Excl. VAT)
Project management and
Design
Contract initiation, mobilisation and kick-
1.1
off meeting complete
Existing installation verification report
1.2
accepted
1.3 HAZOP Study completed and accepted
1.4 LOPA Study completed and accepted
Safety Requirements Specification
1.5
completed and accepted
SIL determination and verification
1.6
completed and accepted
Fire Detection Philosophy completed
1.7
and accepted
Cause and Effect Matrix completed and
1.8
accepted
1.9 Safety Matrix completed and accepted
Control Narrative completed and
1.10
accepted
Detailed Design Report completed and
1.11
accepted
1.12 IFC Drawings issued and accepted
Subtotal 1 Project Management and Design ___________________________
2 procurement
Four 10-inch actuated ball valves
2.1
procured and delivered
Four 6-inch actuated ball valves
2.2
procured and delivered
Four 4-inch actuated valves procured
2.3
and delivered
One 6-inch actuated gate valve procured
2.4
and delivered
Fire detection equipment procured and
2.5
delivered
ET200 Safety Remote I/O equipment
2.6
procured and delivered
2.7 Control panels procured and delivered
Fibre optic communication equipment
2.8
procured and delivered
Instrumentation and ancillary equipment
2.9
procured and delivered
Part c2: pricing data c2.1 ECC3/A pricing assumptions
Airports company south africa soc limited contract NO. _________
Project & contract title
Foam concentrate for wet foam
2.10
discharge testing procured and delivered
Subtotal 2 Procurement ___________________________
3 mechanical installation
Installation of four 10-inch actuated ball
3.1
valves complete
Installation of four 6-inch actuated ball
3.2
valves complete
Installation of four 4-inch actuated valves
3.3
complete
Installation of one 6-inch actuated gate
3.4
valve complete
Replacement of small bore valves
3.5
complete
Replacement of pressure gauges
3.6
complete
Mechanical inspection and acceptance
3.7
completed
Subtotal 3 Mechanical Installation ___________________________
4 fire detection system
Existing fire detection assessment
4.1
completed
Removal of obsolete fire detection
4.2
equipment completed
4.3 Flame detection installation completed
4.4 Heat detection installation completed
Fire detection interfaces installed and
4.5
tested
Fire detection inspection and acceptance
4.6
completed
Subtotal 4 Fire Detection System ___________________________
Electrical, control and
Instrumentation
ET200 Safety Remote I/O stations
5.1
installed
5.2 Control panels installed
5.3 Instrumentation installed
5.4 Fibre optic network installed
5.5 Power supplies installed
Electrical and instrumentation inspection
5.6
completed
Subtotal 5 Electrical, Control and Instrumentation ___________________________
Part c2: pricing data c2.1 ECC3/A pricing assumptions
Qualifications:
Experience:
2 Name:
Qualifications:
Experience:
1 Available from Engineering Contract Strategies Tel 011 803 3008, Fax 011 803 3009 or see
Pricing Schedule
Source: Contract for Automation of fixed fire foam deluge systems.docx.pdfPart C1 Agreements and Contract Data, (which includes this Form of Offer and
Acceptance)
Part C2 Pricing Data
Part C3 Scope of Work: Works Information
Part C4 Site Information
and drawings and documents (or parts thereof), which may be incorporated by reference into the above
listed Parts.
Part 2: pricing data
reference pages
C2.1 Pricing assumptions: Option A
C2.2 The activity schedule
Part c2: pricing data c2 ECC3/A cover
Airports company south africa soc limited contract NO. _________
C2.1 Pricing assumptions: Option A
the work described within the Works Information into suitable activities which can be well defined, priced as
a lump sum and shown on the programme. The Employer, in his Conditions of Tender or in a Tender
Part c2: pricing data c2.1 ECC3/A pricing assumptions
Airports company south africa soc limited contract NO. _________
Part c2: pricing data c2.1 ECC3/A pricing assumptions
Airports company south africa soc limited contract NO. _________
2.9
procured and delivered
Part c2: pricing data c2.1 ECC3/A pricing assumptions
Airports company south africa soc limited contract NO. _________
5.6
completed
Subtotal 5 Electrical, Control and Instrumentation ___________________________
Part c2: pricing data c2.1 ECC3/A pricing assumptions
Compliance Requirements
Source: Contract for Automation of fixed fire foam deluge systems.docx.pdf (unknown)No specific requirements found
Health & Safety
Source: Contract for Automation of fixed fire foam deluge systems.docx.pdfsignature of Date
witness
Note: If a tenderer wishes to submit alternative tenders, use another copy of this Form of Offer and
Z1 Interpretation and the law
Z1.1 Add to core clause 12.3: Any extension, concession, waiver or relaxation of any action stated in this
contract by the Parties, the Project Manager, the Supervisor, or the Adjudicator does not constitute a
waiver of rights, and does not give rise to an estoppel unless the Parties agree otherwise and confirm
such agreement in writing.
Z1.2 Add the following as a new core clause 12.5:
Z1.2.1 In this contract:
Z1.2.1.1 references to any Party to the Contract include its successors or permitted assigns;
Z1.2.1.2 references to the Contractor include the obligations of its personnel;
CV's (and further key persons data including
CVs) are appended to Tender Schedule
entitled .
11.2(14) The following matters will be included in
the Risk Register
1.8
accepted
1.9 Safety Matrix completed and accepted
2.5
delivered
ET200 Safety Remote I/O equipment
2.6
procured and delivered
2.7 Control panels procured and delivered
ET200 Safety Remote I/O stations
5.1
installed
5.2 Control panels installed
5.3 Instrumentation installed
5.4 Fibre optic network installed
5.5 Power supplies installed
Contractual Terms
Source: Contract for Automation of fixed fire foam deluge systems.docx.pdfPart C1: Agreements & Contract Data
Contents: No of
pages
C1.1 Form of Offer and Acceptance 3
C1.2a Contract Data provided by the Employer 6
C1.2b Contract Data provided by the Contractor 32
C1.3 Proforma Guarantees 34
Schedule of Deviations (if any), contact the Employer’s agent (whose details are given in the Contract
Data) to arrange the delivery of any securities, bonds, guarantees, proof of insurance and any other
documentation to be provided in terms of the conditions of contract identified in the Contract Data at, or
just after, the date this agreement comes into effect. Failure to fulfil any of these obligations in
accordance with those terms shall constitute a repudiation of this agreement.
Unless the tenderer (now Contractor) within five working days of the date of such receipt notifies the
clauses and the clauses for main Option
A: Priced contract with activity
schedule
dispute resolution Option W1: Dispute resolution procedure
and secondary Options
X2 Changes in the law
X5: Sectional Completion
X7: Delay damages
X13: Performance Bond
X16: Retention
X18: Limitation of liability
Z: Additional conditions of contract
of the NEC3 Engineering and Construction
Contract, April 2013 (ECC3)
10.1 The Employer is (Name): Airports Company South Africa SOC Limited (reg.
no: 1993/004149/06), a juristic person
incorporated in terms of the company laws of the
80.1 These are additional Employer's risks 1. None.
84.1 The Employer provides these insurances See Annexure D to this Contract Data provided by
from the Insurance Table the Employer.
84.1 The Employer provides these additional The terms and other matters applicable to these
insurances insurances provided by the Employer (and to
insurances generally) are detailed in the
insurance schedule attached as section C1.4 to
the contract (“the insurance Schedule)
84.1 The Contractor provides these additional As stated in C1.4
insurances
84.2 The minimum limit of indemnity for Nil (0)
insurance in respect of loss of or damage
to property (except the works, Plant,
Materials and Equipment) and liability for
bodily injury to or death of a person (not
an employee of the Contractor) caused by
activity in connection with this contract for
any one event is
84.2 The minimum limit of indemnity for As prescribed by the Compensation for
insurance in respect of death of or bodily Occupational Injuries and Diseases Act No. 130 of
injury to employees of the Contractor 1993 and the Contractor’s common law liability for
arising out of and in the course of their people falling outside the scope of the Act
employment in connection with this
contract for any one event is
elsewhere in this Contract Data.
11 Data for Option W1
W1.1 The Adjudicator is (Name) The person selected from the panel of adjudicators
listed in Annexure C of this Contract Data, by the
party intending to refer a dispute to him.
W1.2(3) The Adjudicator nominating body is: The Chairman of the Johannesburg Society of
elsewhere in this Contract Data.
X7 Delay damages (but not if Option X5 is
also used)
X7.1 Delay damages for Completion of the Amount per day is 0.05% of the contract value, up
whole of the works are to the maximum of 10% of the contract value
X13 Performance bond
X13.1 The amount of the performance bond is 5% of Contract value excluding VAT.
X16 Retention (not used with Option F)
X16.1 The retention percentage is 5 % of the invoiced amount
X18 Limitation of liability
X18.1 The Contractor’s liability to the Employer Nil - Neither Party is liable to the other for any
for indirect or consequential loss is limited consequential or indirect loss, including but not
to: limited to loss of profit, loss of income or loss of
revenue
X18.2 For any one event, the Contractor’s Total of the losses incurred and/or repairs to the
liability to the Employer for loss of or damages caused
damage to the Employer’s property is
limited to:
X18.3 The Contractor’s liability for Defects due to Total of the losses incurred and/or repairs to the
his design which are not listed on the damages caused
X18.4 The Contractor’s total liability to the The total of the losses incurred and/or repairs to
connection with this contract, other than excluded matters.
excluded matters, is limited to:
The Contractor’s total liability for the additional
excluded matters is not limited.
outside the Site,
loss of or damage to property (other than the
works, Plant and Materials),
death of or injury to a person;
damage to third party property; and
infringement of an intellectual property right.
X18.5 The end of liability date is The date on which the liability in question
prescribes in accordance with the Prescription Act
No. (as amended or in terms of any
replacement legislation) for any other matter.
Z4.2 The Contractor warrants that the completed Works shall be fit for their intended purpose, namely the
provision of a fully operational fire water pumping system capable of meeting the performance
requirements stated in the Works Information.
Z4.3 The Contractor warrants that the completed fire water pumping system shall achieve the hydraulic
performance, flow rates, pressures, reliability and availability requirements specified in the Works
Z9.3 If any changes are made to the quality plan, the Contractor provides the Project Manager with the
changes quality plan for acceptance.
Z9.4 The Project Manager may instruct the Contractor to correct a failure to comply with the quality plan. This
instruction is not a compensation event.
Z10 Assessing the amount due:
Z10.1 Delete the second bullet point of core clause 50.1 and replace with the following: “within thirteen
weeks of termination of this Contract”
Z11 Final assessment: add the following as a new core clause 53:
Z11.1 The Project Manager makes a final assessment and certifies final payment in accordance with the
Z11.2 An assessment of the final amount due is conclusive evidence of the final amount due under or in
connection with the Contract, unless a Party raises a dispute in relation to the assessment of the final
amount due.
Z11.3 The assessment of the final amount due is changed to include any agreement the Parties reached and/or
a decision of the Adjudicator which has not been referred to the tribunal within four weeks of that decision.
with the Contract.
Z12 Notifying compensation events:
Z12.1 Delete the last sentence in core clause 61.3 and replace with the following: “If the Contractor
does not notify a compensation event within four weeks of becoming aware of the event, he is not
entitled to a change in the Prices, the Completion date or a Key Date and the Employer is absolved
from all liability in relation to such event.”
Z13 Assessing compensation events:
Z13.1 The following is added at the end of core clause 63.4: “the Contractor shall only be entitled to
changes to the Prices, the Completion Date and/or the Key Date if the compensation event affects the
critical path.”
Z14 Termination
Z14.1 Add the following to core clause 91.1, at the second main bullet, fifth sub-bullet point, after the
words “assets or”: “business rescue proceedings are initiated or steps are taken to initiate business
recue proceedings”.
Z15.1 A change in law is defined as:
Z15.1.1 the adoption, enactment, promulgation, coming into effect, repeal, amendment, reinterpretation,
change in application or other modification after the Contract Date of any law, excluding (i) the
enactment of any bill inside the country, but only if such bill is enacted without any material changes
being made to the contents of such bill from the form published in the Gazette (as defined in the
Interpretation Act, 1957) as at the Contract Date, and (ii) any such modification in law relating to any
taxes, charges, imposts, duties, levies or deductions that are assessed in relation to a person’s
income
Z15.1.2 any permit being terminated, withdrawn, amended, modified or replaced, other than (i) in accordance
with the terms upon which it was originally granted, (ii) as a result of the failure by the Contractor to
comply with any condition set out therein, or (iii) as a result of any act or omission of the Contractor,
any Subcontractor or any affiliate to the Contractor.
Z16. Delay damages: add the following to secondary Option X7 (if applicable in this contract)
Z16.1 If the amount due for the Contractor’s payment of delay damages reaches the limits stated in this
Contract Data for Option X7, the Employer may, at its sole discretion, terminate the Contractor’s
obligation to Provide the Works.
Z16.2 If the Employer terminates in terms of this clause, the procedures and payment on termination as
those applied for reasons R1 to R15 or R18 stated in the Termination Table
Z17 Performance Bond
Z17.1 Amend the first sentence of clause X13.1 to read as follows: The Contractor gives the Employer
an unconditional, on-demand performance bond, provided by a bank or insurer which the Project
set out in Annexure B of this Contract Data.
2Z17.2 Add the following new clause as Option X13.2: The Contractor ensures that the performance bond
is valid and enforceable until the end of the contract period. If the terms of the performance bond
specify its expiry date and the end of the contract period does not coincide with such expiry date, four
weeks prior to the said expiry date, the Contractor extends the validity of the performance bond until
the end of the contract period. If the Contractor fails to so extend the validity of the performance bond,
the Employer may claim the full amount of the performance bond and retain the proceeds as cash
security
Z18 Limitation of liability: Insert the following new clause as Option X18.6:
Z18.1 The Employer's liability to the Contractor for the Contractor's indirect or consequential loss is limited to
R0.00.
Z18.2 Notwithstanding any other clause in this contract, any proceeds received from the security bonds and
guarantees provided by the Contractor in terms of this Contract and any insurances or any proceeds
which would have been received from any insurances but for the conduct of the Contractor shall be
excluded from the calculation of the limitations of liability listed in the contract.
Z19.2 The Employer may, on written notice to the Contractor, cede and delegate its rights and obligations
under this contract to any person or entity.
Z20 Joint and several liability
Z20.1 If the Contractor constitutes a joint venture, consortium or other unincorporated grouping of two or
more persons, these persons are deemed to be jointly and severally liable to the Employer for the
performance of the Contract.
Z20.2 The Contractor shall, within 1 week of the Contract Date, notify the Project Manager and the Employer
of the key person who has the authority to bind the Contractor on their behalf.
Z20.3 The Contractor does not materially alter the composition of the joint venture, consortium or other
unincorporated grouping of two or more persons without prior written consent of the Employer.
Z21 Ethics
Z21.1 The Contractor undertakes:
Z21.1.1 not to give any offer, payment, consideration, or benefit of any kind, which constitutes or could be
construed as an illegal or corrupt practice, either directly or indirectly, as an inducement or reward for
the award or in execution of this contract;
Z21.1.2 to comply with all laws, regulations or policies relating to the prevention and combating of bribery,
corruption and money laundering to which it or the Employer is subject, including but not limited to the
Z21.2 The Contractor’s breach of this clause constitutes grounds for terminating the Contractor’s obligation
to Provide the Works or taking any other action as appropriate against the Contractor (including civil
or criminal action). However, lawful inducements and rewards shall not constitute grounds for
termination.
Z21.3 If the Contractor is found guilty by a competent court, administrative or regulatory body of participating
in illegal or corrupt practices, including but not limited to the making of offers (directly or indirectly),
payments, gifts, gratuity, commission or benefits of any kind, which are in any way whatsoever in
connection with the contract with the Employer, the Employer shall be entitled to terminate the
contract in accordance with the procedures stated in core clause 92.2. The amount due on termination
is A1.
Z22 Confidentiality
Z22.1 All information obtained in terms of this contract or arising from the implementation of this contract
shall be treated as confidential by the Contractor and shall not be used or divulged or published to any
person not being a party to this contract, without the prior written consent of the Project Manager or
the Employer, which consent shall not be unreasonably withheld.
Z22.2 If the Contractor is uncertain about whether any such information is confidential, it is to be regarded as
such until otherwise notified by the Project Manager.
Z22.3 This undertaking shall not apply to –
Z22.3.1 Information disclosed to the employees of the Contractor for the purposes of the implementation of
this agreement. The Contractor undertakes to procure that its employees are aware of the confidential
nature of the information so disclosed and that they comply with the provisions of this clause;
Z22.3.2 Information which the Contractor is required by law to disclose, provided that the Contractor notifies
the Employer prior to disclosure so as to enable the Employer to take the appropriate action to protect
such information. The Contractor may disclose such information only to the extent required by law and
shall use reasonable efforts to obtain assurances that confidential treatment will be afforded to the
information so disclosed;
Z22.3.3 Information which at the time of disclosure or thereafter, without default on the part of the Contractor,
enters the public domain or to information which was already in the possession of the Contractor at
the time of disclosure (evidenced by written records in existence at that time);
Z22.4 The taking of images (whether photographs, video footage or otherwise) of the works or any portion
thereof, in the course of Providing the Works and after Completion, requires the prior written consent
of the Project Manager. All rights in and to all such images vests exclusively in the Employer.
Z22.5 The Contractor ensures that all his Subcontractors abide by the undertakings in this clause.
Z23 Liens and Encumbrances
Z23.1 The Contractor keeps the Equipment used to Provide the Services free of all liens and other
encumbrances at all times. The Contractor, vis-a-vis the Employer, waives all and any liens which he
may from time to time have, or become entitled to over such Equipment and any part thereof and
procures that his Subcontractors similarly, vis-a-vis the Employer, waive all liens they may have or
become entitled to over such Equipment from time to time
Z24 Intellectual Property
Z24.1 Intellectual Property (“IP”) rights means all rights in and to any patent, design, copyright, trade mark,
trade name, trade secret or other intellectual or industrial property right relating to the Works.
Z24.2 IP rights remain vested in the originator and shall not be used for any reason whatsoever other than
carrying out the works.
Z24.3 The Contractor gives the Employer an irrevocable, transferrable, non-exclusive, royalty free licence to
use and copy all IP related to the works for the purposes of constructing, repairing, demolishing,
operating and maintaining the works.
Z24.4 The written approval of the Contractor is to be obtained before the Contractor's IP made available to
any third party which approval will not be unreasonably withheld or delayed. Prior to making any
undertaking from any such third party on terms no less onerous than the terms the Employer would use
to protect its IP.
Z24.5 The Contractor shall indemnify and hold the Employer harmless against and from any claim alleging
an infringement of IP rights (“the claim”), which arises out of or in relation to:
Z24.5.1 the Contractor’s design, manufacture, construction or execution of the Works;
Z24.5.2 the use of the Contractor’s Equipment, or
Z24.5.3 the proper use of the Works.
Z24.6 The Employer shall, at the request and cost of the Contractor, assist in contesting the claim and the
Contractor may (at its cost) conduct negotiations for the settlement of the claim, and any litigation or
arbitration which may arise from it.
Z24.7 All designs, drawings, BIM models, software, PLC code, SCADA configurations, databases and
documentation produced under this contract shall become the property of ACSA upon payment.
Z24.8 The Contractor shall ensure that all hardware, software, PLCs, HMIs, SCADA systems and
communication systems supplied under the Contract comply with ACSA cybersecurity standards.
Annexure B: Pro forma Security Bonds and Guarantee
Pro forma Performance Bond – Demand Guarantee (for use
with Option X13)
(to be reproduced exactly as shown below on the letterhead of the Bank providing the Bond / Guarantee)
[Insert Contractor’s name and registered address] Bank reference No.
Date:
Performance Bond – Demand Guarantee for [insert name of Contractor] required in terms of
contract [insert Contractor’s contract reference number or title]
In this Guarantee the following words and expressions shall have the following meanings: -
1.1 “Bank” means [Insert name of Bank], [●] Branch, Registration No. [●]
1.2 “Bank’s Address” means [Insert physical address of Bank]
1.3 “Contract” means the written agreement relating to providing the works, entered into
between the Employer and the Contractor, on or about the [●] day of
[●] 20[●] (Contract Reference No. [●]) as amended, varied, restated,
novated or substituted from time to time;
1.4 “Contractor” means [●] a company registered in accordance with the laws of [●] under
Registration No [●].
1.5 “Employer” means Airports Company South Africa SOC Limited a company registered
in accordance with the laws of the Republic of South Africa under
Registration Number 1993/004149/30
1.6 “Expiry Date” means the earlier of
stating that all amounts due from the Contractor as certified in
terms of the contract have been received by the Employer and
that the Contractor has fulfilled all his obligations under the
lesser or higher amount as may be required by the Employer.
1.7 “Guaranteed Sum” means 5% of contract value excluding VAT which must be submitted within
10 working days from notification of award
1.8 “works” means Design, Supply, Installation, Programming, Testing,
Deluge Systems fuel farm for a period of 24 months at ORTIA as
set out in the Section C3, Works Information
At the instance of the Contractor, we the undersigned ______________ and ______________, in our
respective capacities as _____________ and ___________ of the Bank, and duly authorized thereto,
confirm that we hold the Guaranteed Sum at the disposal of the Employer as security for the proper
performance by the Contractor of all of its obligations in terms of and arising from the Contract and
A demand for payment under this guarantee shall be made in writing at the Bank’s address and shall:
the Contract.
principal and not as surety and the Bank’s obligation/s to make payment:
The Bank’s obligations in terms of this Guarantee:
Guaranteed Sum; and
terms hereof shall not be delayed, by the fact that a dispute may exist between the Employer
and the Contractor.
without advising us and without affecting our liability under this Guarantee. This includes, without
limitation, any extensions, indulgences, release or compromise granted to the Contractor or any
variation under or to the Contract.
permitted under the Contract, then the Employer shall be entitled to cede to such third party the rights
of the Employer under this Guarantee on written notification to the Bank of such cession.
and is neither negotiable nor transferable;
hereof;
shall be subject to the jurisdiction of the Courts of the Republic of South Africa.
the Expiry Date.
Annexure D: ACSA Insurance Clauses
Section
Source: Contract for Automation of fixed fire foam deluge systems.docx.pdfNote:
the Parties and is not the result of a process of competitive tendering.
to those permitted in terms of the Conditions of Tender.
constitutes a deviation as aforesaid be the subject of agreement reached during the process of Offer and Acceptance,
the outcome of such agreement shall be recorded here and the final draft of the contract documents shall be revised
to incorporate the effect of it.
No. Subject Details
By the duly authorised representatives signing this Schedule of Deviations below, the Employer and
the tenderer agree to and accept this Schedule of Deviations as the only deviations from and
amendments to the documents listed in the Tender Data and any addenda thereto listed in the Tender
Schedules, as well as any confirmation, clarification or changes to the terms of the Offer agreed by the
tenderer and the Employer during this process of Offer and Acceptance.
It is expressly agreed that no other matter whether in writing, oral communication or implied during the
period between the issue of the tender documents and the receipt by the tenderer of a completed
signed copy of this Form shall have any meaning or effect in the contract between the parties arising
from this Agreement.
For the tenderer: For the Employer
Data conflicts
None detected