Issuing Organization
Eskom National Transmission Company of South AfricaLocation
Gauteng
Closing Date
21 Oct 2026
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
The Farm Witkoppies JR 393 - Olifantsfontein - Ekurhuleni - 1665
Organization Type
GOVERNMENT
Published
21 Sept 2026
OCDS Reference
ocds-9t57fa-171192
Bidders must submit tenders electronically via the Eskom Tender Bulletin site on the Eskom E-tendering page; no late tenders will be accepted.
Bidders must complete and submit the Acknowledgement Form, stating whether the tender is for the whole or part of the works, services or supply.
Bidders must submit the Declaration Certificate and Annex C (Local Content Declaration: Summary Schedule) at the stipulated deadline; failure to do so may disqualify the bid.
For designated sectors, only locally produced or manufactured goods with a stipulated minimum threshold for local content are required; the local content percentage must be calculated per SATS 1286:2011.
Bidders must submit a B-BBEE certificate or sworn affidavit; if not submitted, the bidder will score zero under PPPFA point allocation but will not be disqualified if otherwise responsive.
Bidders must comply with CIDB registration requirements; proof of application for CIDB registration may be submitted by the closing date and time, but the actual registration must be provided later.
Bidders must state rates and prices in South African Rand (ZAR) and must not use correction fluid or tape on tender documents.
Continue with tenders sharing this issuer, category, or province.
Return to this tenderβs issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Wednesday, 21 October 2026 - 10:00
Venue
NTCSA Apollo Converter-Station Substation
A non-compulsory site clarification will be held on: date: 29 september 2026 venue: ntcsa apollo converter station (cs) substation adress: the farm witkoppies jr 393 olifantsfontein 1665 time: 09:00 AM (sast) GPS coordinates: s25Β° 55.239β E28Β° 16.753β *Refer to invitation to tender for more information* and a non-compulsory virtual clarification will be held on: date: 02 october 2026 venue: ms teams (virtual) time: 09:00 AM (sast) meeting link: https://teams.microsoft.com/meet/365125571303367?p=oeJEl77PliZw6r2yun Meeting ID: 365 125 571 303 367 passcode: h34kg9qo
Categories
Request for Bid(Open-Tender)
The Farm Witkoppies JR 393 - Olifantsfontein - Ekurhuleni - 1665
Tenders in this industry often require registration with these bodies.
Construction Industry Development Board (CIDB) registration is mandatory for almost all public sector construction tenders. Ensure your grading matches the tender value.
Recommended Certifications
Having these can improve your winning chances: NHBRC Registration, ISO 9001:2015 (Quality Management), ISO 14001:2015 (Environmental Management), ISO 45001:2018 (Occupational Health & Safety), SACPCMP Registration, ECSA Registration
AI Document Analysis Stages
Important Dates
Source: E3574NTCSAMWP.zip (TENDER){"closingDate":"21 September 2026","closingTime":"10:00 AM","briefingSession":"{"date":"02 October 2026","time":"09:00 AM","venue":"must wear the relevant","is_compulsory":true}"}
21 Sept
2026
Tender Published
Tender was published
21 Oct
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
E3574NTCSAMWP.zip
Eskom NTCSA is procuring civil works for the replacement of a 1 million litre water deluge tank and associated pipework at the Apollo Converter Station substation in Gauteng. The scope includes demolition of the existing steel tank, construction of a new reinforced concrete water tank, refurbishment of an existing concrete reservoir, and installation of associated pipework, hydrants, valves and security measures.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
RΒ 1Β 983Β 750
Range
Based on 21 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically β no action required from you.
Contact Information
Source: E3574NTCSAMWP.zip (TENDER){"name":"MS Teams","email":null,"phone":null,"department":null,"address":"tions of Tender which may be"}
Submission Guidelines
Source: E3574NTCSAMWP.zip (TENDER)Returnable Documents: The five-working-day period stated above does not apply to proof of CIDB contractor grading., Where CIDB registration and grading are applicable, proof must be submitted by the tender closing, (Shall be used in conjunction with strategy), Construction Program/technical 20
Evaluation Criteria
Source: E3574NTCSAMWP.zip (TENDER)Bidders must be eligible to do business with Eskom and not under any restriction. Tenderers must not subcontract 100% of the scope of work. Bidders must complete and submit the mandatory returnables including the Acknowledgement Form, the signed Form of Offer, the Local Content Declaration (SBD 6.2) with Annex C, and the Confidentiality Agreement. The tender must be submitted by the closing time via the specified method (Eskom Tender Bulletin e-tendering or physical tender box). Bidders must comply with the local production and content requirements as stipulated in the designated sectors, with the minimum threshold to be specified in the bid documents. The Safety Officer must be registered with SACPCMP.
Technical Specifications
Source: E3574NTCSAMWP.zip (TENDER)Cell B4: PROJECT LOCATION: APOLLO CONVERTER STATION SUBSTATION
I. National Transmission company south africa SOC LTD a company incorporated under the laws of the Republic of South Africa, having its registered office at Megawatt Park, Maxwell Drive, Sunninghill ext.3, Sandton, Republic of South Africa, with registration number 2021/539129/30 [hereinafter referred to as βthe Disclosing Partyβ.
of services, works or goods Stipulated minimum threshold
_______________________________ _______%
_______________________________ _______%
_______________________________ _______%
(Tick applicable box)
Yes NO
3..1 If yes, the rate(s) of exchange to be used in this bid to calculate the local content as
prescribed in paragraph 1.5 of the general conditions must be the rate(s) published by
SARB for the specific currency at 12:00 on the date of advertisement of the bid.
The relevant rates of exchange information is accessible on www.reservebank.co.za
Indicate the rate(s) of exchange against the appropriate currency in the table below (refer
to Annex A of SATS 1286:2011):
Currency Rates of exchange
US Dollar
Pound Sterling
Euro
Yen
Other
NB: Bidders must submit proof of the SARB rate (s) of exchange used.
threshold for local content the dti must be informed accordingly in order for the dti to verify and
in consultation with the AO/AA provide directives in this regard.
Local content declaratio
Supply Chain
Management Procedure 32-1034. Any addenda to an issued Invitation to Tender will be
published or issued in the same way as the Invitation to Tender was and will form part of the
Invitation to Tender documents.
Communication 1.5 Every communication between Eskom and a tenderer shall be made to or from the Eskom
Representative only, in w
Controlled Disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests
with the user to ensure it is in line with the authorized version on the system. No part of this document may be
reproduced in any manner or form by third parties without the written consent of NTCSA SOC Ltd, Β© copyright NTCSA
SOC Ltd, Reg No 2021/539129/30
of 69
File name: 559-235050781 E3574NTCSAMWP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 559-235050781 Rev 4
Identifier
Invitation to Tender
Effective Date July 2024
Review Date July 2027
-Refer to βSafety
and Healthβ
folder
1.1.37 Environmental Attached Y β
-Refer to Separately
βEnvironmentalβ
folder
1.1.38 Due Diligence / N β
financial analysis
Audited Financial
Statements of the
tenderer for the
previous 18
months, or to the
extent that such
statements are
not available, for
the last year.
In the case of a
joint venture or
special purpose
vehicle (SPV)
specially formed
for this tender,
audited financial
statements for
each participant
in the JV / SPV
must be
submitted.
Start-up
enterprises
formed within the
last 12 months
are not required
to submit audited
financial
statements, but if
successful in this
enquiry; will be
required to
furnish
statements for the
first year once
available.
Controlled Disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests
with the user to ensure it is in line with the authorized version on the system. No part of this document may be
reproduced in any manner or form by third parties without the written consent of NTCSA SOC Ltd, Β© copyright NTCSA
SOC Ltd, Reg No 2021/539129/30
of 69
File name: 559-235050781 E3574NTCSAMWP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 559-235050781 Rev 4
Identifier
Invitation to Tender
Effective Date July 2024
Review Date July 2027
Documents required under functionality/techinical criteria
1.1.39 Functionality / Attached Y β
Technical Separately
-Refer to
βTechnicalβ
Folder
Controlled Disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests
with the user to ensure it is in line with the authorized version on the system. No part of this document may be
reproduced in any manner or form by third parties without the written consent of NTCSA SOC Ltd, Β© copyright NTCSA
SOC Ltd, Reg No 2021/539129/30
of 69
File name: 559-235050781 E3574NTCSAMWP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 559-235050781 Rev 4
Identifier
Invitation to Tender
Effective Date July 2024
Review Date July 2027
1.2. Tender Data
The Tender Data makes several references to the Standard Conditions of Tender and in those instances,
the clause numbers are referenced hereunder. If the Standard Conditions of Tender are not attached to
the enquiry, then tenderers are required to download this from www.ntcsa.co.za. The βTender Dataβ as
detailed herein shall take precedence over the Standard Conditions of Tender in the event of any
ambiguity or inconsistency between the two documents.
Clause Number from Standard
Tender Data
Conditions of Tender
1.1 Parties The Employer is NTCSA SOC Ltd
The NTCSA Representative is:
Name: Refiloe Mabula / Matidi Seabela
Tel: +27 11 800 5003
E-mail: [email protected] / [email protected]
1st Escalation: Procurement Manager
Name: Takalani Nemavhulani
Tel: +27 11 800 3198
Email: [email protected]
2nd Escalation: Middle Manager
Name: Frans Pooe
Tel: +27 11 800 5661
Email address: [email protected]
1.3 Enquiry documents The Invitation to tender number is: E3574NTCSAMWP
See the content list above for the enquiry documents.
1.4 Type of enquiry This enquiry is an open invitation to tender
1.6 NTCSA's rights to accept or The tender shall be for the whole of the contract.
reject any tender
2.1 Eligibility Tenderers (whether a single company or an incorporated or
unincorporated joint venture or consortium) must meet the eligibility
criteria stated in the Tender Data. The tenderer, or any of its
principals, must not be under any restriction to do business with
NTCSA or State-Owned Companies.
Tenderers are ineligible to submit a tender if:
sanctions list. A tenderer shall be found to have the nationality of
a country if the tenderer is a national or is constituted,
incorporated, or registered and operates in conformity with the
provisions of the laws of that country. This criterion shall also
apply to the determination of the nationality of proposed
Controlled Disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests
with the user to ensure it is in line with the authorized version on the system. No part of this document may be
reproduced in any manner or form by third parties without the written consent of NTCSA SOC Ltd, Β© copyright NTCSA
SOC Ltd, Reg No 2021/539129/30
of 69
File name: 559-235050781 E3574NTCSAMWP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 559-235050781 Rev 4
Identifier
Invitation to Tender
Effective Date July 2024
Review Date July 2027
subcontractors or suppliers for any part of the Contract including
related services.
individually or as a partner in a joint venture (JV) or consortium,
except on an E-Tendering system where there is a limit size (The
upload size per document is 500 megabytes and total submission
is restricted to 4 gigabytes).
JV/consortium agreement does not explicitly state that the parties
of the JV or consortium shall be jointly and severally liable for the
execution of the Contract in accordance with the Contract terms.
found to have a conflict of interest shall be disqualified. Prima facie
evidence that a tenderer has a conflict of interest with one or more
parties in this [tendering/RFP] process is:
(a) they have a controlling partner or majority shareholder in
common; or
(b) they have a relationship with each other, directly or through
common third parties, that puts them in a position to have
access to information about or influence on the tender of
another tenderer, or to influence the decisions of the Employer
regarding this bidding process;
Ineligible of the flagged suppliers/tenderers will be due to the
following reasons:
a) Those suppliers implicated in serious misconduct by the Zondo
Report or the SIU pending the finalisation of supplier disciplinary
measures against these suppliers; and
b) Other suppliers implicated in serious misconduct and a breach of
the Eskom Supplier Integrity Pact by a forensic report or other
source of credible information, such as the SAPS, the NPA, the
SIU or other related source.
c) List of Restricted Suppliers and Defaulters as per PRECCA as
issued by National Treasury
The implications of this βflagβ are as follows:
o No new contracts or extension of existing contracts may be
awarded to the supplier pending finalisation of supplier disciplinary
processes against the supplier. Where a As such, the supplierβs
bid should be removed from any tender evaluation at the βeligibilityβ
or βcomplianceβ assessment stage of the evaluation.
Controlled Disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests
with the user to ensure it is in line with the authorized version on the system. No part of this document may be
reproduced in any manner or form by third parties without the written consent of NTCSA SOC Ltd, Β© copyright NTCSA
SOC Ltd, Reg No 2021/539129/30
of 69
File name: 559-235050781 E3574NTCSAMWP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 559-235050781 Rev 4
Identifier
Invitation to Tender
Effective Date July 2024
Review Date July 2027
NTCSA will disqualify tenderers that are found not to have met
the eligibility criteria.
2.2 -2.5 Tender Closing The deadline for tender submission is:
Date: 21 October 2026
Time: 10:00 AM (SAST)
Tenders are uploaded via NTCSA Tender bulletin site on the
Eskom E- tendering .9 Submitting a tender -Original For Electronic Tender Submissions:
tender and copy
The tenderer must upload the tender via NTCSA Tender bulletin site
on the Eskom E- tendering page. The documents need to be upload
under the folder Technical, Commercial, Financial, and other.
All documents need to be submitted in a PDF format (The upload size
per document is 500 megabytes and total submission is restricted to 4
gigabytes). The price list needs to be submitted in PDF and a copy in
excel format.
No Zip/condense files can be uploaded
No hard copy will be accepted
If for some reason you resubmit your tender, then the latest version of
the tender submitted will only be accepted and all previous
submission/s will be null and void.
Please ensure that the submission status is indicated as complete.
Supplier Help Manual guide and video can be found on Eskom E-
Tendering .12 Tender Validity Period The tender validity period is 90 days.
NTCSA may extend the validity period for a specified additional
period. Should extension of validity be required by NTCSA,
tenderers agreeing to the request will not be required or
permitted to modify a tender. If a tenderer modifies a tender, such
a tender will be disqualified from the tender process.
2.15 Site visit and/or clarification A Non-Compulsory site clarification will be held on:
meeting
Date: 29 September 2026
Venue: NTCSA Apollo Converter Station (CS) Substation
Adress: The Farm Witkoppies JR 393 Olifantsfontein 1665
Time: 09:00 AM (SAST)
GPS Coordinates: S25Β° 55.239β E28Β° 16.753β
Controlled Disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests
with the user to ensure it is in line with the authorized version on the system. No part of this document may be
reproduced in any manner or form by third parties without the written consent of NTCSA SOC Ltd, Β© copyright NTCSA
SOC Ltd, Reg No 2021/539129/30
of 69
File name: 559-235050781 E3574NTCSAMWP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 559-235050781 Rev 4
Identifier
Invitation to Tender
Effective Date July 2024
Review Date July 2027
Note: Failure to attend the non-compulsory site visit will not result in
your tender being disqualified.
Special Requirements:
All personnel visiting the venue must wear the relevant PPE (i.e.,
safety shoes and hard hats) and adhere to NTCSA Lifesaving rules.
Tenderers will also be required to bring their identity documents on
the day of the site visit to be granted access to the premises.
And
A Non-Compulsory Virtual clarification will be held on:
Date: 02 October 2026
Venue: MS Teams (Virtual)
Time: 09:00 AM (SAST)
Meeting Link:
https://teams.microsoft.com/meet/365125571303367?p=oeJEl77PliZ
w6r2yun
Meeting ID: 365 125 571 303 367
Passcode: H34kg9Qo
2.16 Seeking clarification The tenderer will notify NTCSA of any clarifications required before
the closing time for clarification queries, which is 10 working days
before the deadline for tender submission. This includes the requests
for extension for tender closing date.
Any addenda or clarifications to the Invitation to Tender (ITT) will be
posted on the e-tender portal and the Tender Bulletin. Tenderers must
review these platforms for updates before finalizing their bid
submissions. NTCSA will not be responsible for any disadvantages or
disqualifications resulting from Tenderers not accessing the latest ITT
information.
2.22 Alternative tenders Alternative tenders are not allowed.
2.33 Cataloguing The successful tenderer may be required to provide the cataloguing
information per item after contract award, and in that instance, will
need will to ensure that all materials delivered to NTCSA are labelled
in line with NTCSAβs labelling specifications as may be stipulated.
Where cataloguing is a requirement, the Pricing Schedule must also
include a line item for cataloguing, which tenderers are required to
quote for. NTCSA will pay for the cataloguing.
2.34 Provision of Security for Where applicable, at the negotiation stage, the provision of security
Performance for performance in the form of a performance bond or a demand
guarantee is a requirement, the tenderer must select a minimum of
two (2) financial institutions that it is likely to approach from the list
provided of NTCSA-approved financial institutions.
Controlled Disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests
with the user to ensure it is in line with the authorized version on the system. No part of this document may be
reproduced in any manner or form by third parties without the written consent of NTCSA SOC Ltd, Β© copyright NTCSA
SOC Ltd, Reg No 2021/539129/30
of 69
File name: 559-235050781 E3574NTCSAMWP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 559-235050781 Rev 4
Identifier
Invitation to Tender
Effective Date July 2024
Review Date July 2027
Kindly refer to: βLIST OF PREVETTED GUARANTORS - Aug2026β
in enquiry pack for list of NTCSA-approved financial institutions.
3.4 Tender Opening For E-tendering. There will be no public opening of tenders. Tenders
will be downloaded electronically.
3.5 Prices to be read out or not Prices will not be read out.
3.9 Basic Compliance Basic compliance with this enquiry requires a tenderer to meet all the
following requirements:
Basic compliance for this invitation to tender are:
technical information
as at stipulated deadlines.
For E-Tendering, a tendererβs failure to have submitted/uploaded
tender documents will render the tender non-responsive.
3.10 Mandatory tender returnables A tenderer that does not submit mandatory documents or the
complete information required in mandatory documents by the
deadlines stipulated in the Tender Returnable section will be deemed
non-responsive.
3.13 Functionality requirements Functionality requirements are applicable.
The following criteria will be applicable for this transaction under
functionality criteria:
Criteria Criteria Weighting
Construction Program /
20%
Technical Schedule
Method Statement 30%
List of Subcontractors 10%
List of Tools, Plant and
10%
Machinery
Relevant Previous Project
20%
Completed
CV and Qualification of Key
10%
Personnel
Total 100%
Minimum Threshold 70%
*Refer to the attached detailed Technical Evaluation document
(240-170000109 β Rev 5) for more information.
NB: Tenderers who do not meet the minimum threshold of 70%
for functionality scoring will be disqualified.
Controlled Disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests
with the user to ensure it is in line with the authorized version on the system. No part of this document may be
reproduced in any manner or form by third parties without the written consent of NTCSA SOC Ltd, Β© copyright NTCSA
SOC Ltd, Reg No 2021/539129/30
of 69
File name: 559-235050781 E3574NTCSAMWP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 559-235050781 Rev 4
Identifier
Invitation to Tender
Effective Date July 2024
Review Date July 2027
3.14 Evaluation of Price Prices will be evaluated as follows:
scheduleβ
alternative tenders submitted; and
adjusted tender based on the tendered programme
(if provided) and prices, on the estimated effect of Price
Adjustment Factors and rate of exchange fluctuations (if
applicable) and on other evaluation parameters relating to
uncertainty and risk, where applicable.
evaluation purposes.
evaluation purposes but will be implemented when
payment is effected.
Prices will be scored out of 80 points
3.18 Evaluation of Specific Goals Specific goals will be scored out of 20 points in accordance with the
PPPFA.
If a tenderer fails to submit evidence of its points claim for a Specific
Goal, it will not be disqualified. However, it will be awarded 0 points
for that Specific Goal.
3.19 Ranking of tenders Tenderers will be ranked by applying the preferential point scoring for
the 80/20 system. NTCSA will add the score from Pricing and Specific
Goals together and rank the suppliers from the highest to the lowest.
B-BBEE Status Level of Number of points
Contributor (80/20 system)
1 20
2 18
3 14
4 12
5 8
6 6
7 4
8 2
Non-Compliant 0
Controlled Disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests
with the user to ensure it is in line with the authorized version on the system. No part of this document may be
reproduced in any manner or form by third parties without the written consent of NTCSA SOC Ltd, Β© copyright NTCSA
SOC Ltd, Reg No 2021/539129/30
of 69
File name: 559-235050781 E3574NTCSAMWP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 559-235050781 Rev 4
Identifier
Invitation to Tender
Effective Date July 2024
Review Date July 2027
3.2 Objective Criteria (applicable) Objective criteria are applicable.
Please note that NTCSA may award the contract to a tenderer
other than the highest scoring if objective criteria justify the
award.
The following objective criteria apply to the enquiry:
The inclusion of objective criteria is not mandatory but a condition for
contract award. If the tenderer does not meet objective criteria; it may
lead to the second-ranked tenderer being recommended for
award.
Designated Sectors
When applicable the following stipulated minimum threshold for Local
Production and Content must be achieved in full by the tenderer
Yes NO
a) Is this Commodity or part of it a ο β
Designated Sector?
Please indicate below Designated
Components
Construction Bank
Danske Bank A/S
ING Bank NV
Macquarie Bank Ltd
Mizuho Bank Ltd
Mizuho Corporate Bank Ltd
SACE SpA
Siemens Financial Services
Business name/JV: _______________________________________________________
eTendering system is a web-based system that allows suppliers bidding for various tenders advertised on Tender Bulletin system to βuploadβ their tender documents. Currently the tenderers or suppliers submit tender documents at various Eskom tender offices. eTendering system replaces the manual or physical submission of tender documents at various Eskom tender offices. eTendering system in a nutshell is an electronic box where tender documents can be βdroppedβ or βuploadedβ. Suppliers will be required to register their details before they can be granted access to the eTendering system. An OTP (one time pin) will be sent to both their cell phone and email address.
Non - Compulsory Clarification meeting - E3574NTCSAMWP
| |
Construction Contract
Between NATIONAL TRANSMISSION COMPANY SOUTH
AFRICA SOC Ltd
(Reg No. 2021/539129/30)
and
for The Apollo CS Water Deluge and Tank Replacement
project
Closest Junction: 43rd Street and Plane Road, Bronkhorstspruit Outlying
Apollo converter-station (cs) substation water deluge system and 1 million litre (ml) tank replacement project β civil works
A maximum of 10/20 points may be awarded to a tenderer for the specific goal specified for the
Construction Skills Development 0.00%
Goal % (CSDG)
If the answer above is Yes, it will then be mandatory for contract award
Mandatory CIDB Grading: 5CE or higher
2.3 National Industrial Participation Programme
Eskom will implement the NIPP requirement, which determines that the contractor/supplier
must contact the Department of Trade, Industry and Compe
Apollo Substation is an electrical substation in the City of Ekurhuleni Metropolitan Area. Access is
restricted, only with permission. Apollo Substation is situated nearby to Rietvlei. It is in the
Olifantsfontein area in Gauteng.
The proposed project is part of the refurbishment and/or maintenance of the Apollo Converter Station
(CS). This Internal environmental management programme (EMPr) describes the proposed
mitigation measures that are in line with the defined scope of work. The project focus on the following.
Apollo CS - Deluge System Water Storage Tank Replacement: The aim of the project is based
on the importance of ensuring a reliable network in support of Eskom NTCSAβs service delivery goals
in terms of customer satisfaction and continuity of supply. Replacing the Apollo CS Deluge System
Water Storage Tank will ensure a reliable and efficient supply to customers by reducing the risk of
having uncontrolled fire at Apollo CS Grid HV yard should a fault occur either on the transformers or
reactors.
It shall, therefore, be noted that should new aspects and impacts arise in addition to what has been
outlined below, this document may be amended or appointed Principal Contractor shall develop
project and/or site-specific method statements / safe work procedures that will detail specific aspects
and impacts associated with such significant activities.
2.1 Scope of the EMPr
NB: This EMPr document only caters for the scope of work contained in it. Any activities outside the
given scope of work will need to be addressed through the correct process (i.e., method statements
or safe work procedure for any other significant activities).
2.1.1 Purpose
This EMPr has been compiled to address the potential environmental impacts that might occur during
the implementation of the above-mentioned project. This document serves as the environmental
specification to NTCSA personnel and Contractors with regards to addressing the environmental
issues identified prior to and during the construction phase. It is the responsibility of the Project
Manager (PM), Contractors and the Environmental Practitioners to ensure compliance with all the
environmental requirements in this document, Environmental Requirements for Contractors and/or
Suppliers Standard as well as the relevant compliance obligations.
This EMPr should also ensure the sustainable management of the environment whilst replacement
of Deluge Water Storage Tank are undertaken. It shall be noted that the works only going to happen
at identified portions of the substation that may not be changed. This EMPr must be viewed as a
contractual document to which all NTCSA personnel and contractors involved should adhere to.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System Revision: 3
Tank
Page:
2.1.2 Applicability
This document shall apply to Eskom NTCSA Project Delivery and Contractors contracted to work on
the Replacement of Apollo CS Deluge Water System Tank.
2.1.3 Effective date
This EMPr is effective as from the date of signature.
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
[1] ISO 9001 Quality Management Systems
[2] ISO 14001 Environmental Management System
[3] 240-180100134 Environmental Requirements for Contractors and /or Suppliers
These documents are indispensable for the application of this document, i.e., documents to be used
together with this document.
2.2.2 Informative
[4] National Environmental Management Act, 1998 (NEMA) (Act No ), and all
amendments and supplementary listings and/or regulations.
[5] Environment Conservation Act, 1989 (ECA) (No ) and amendments.
[6] National Environmental Management: Waste Act, 2008 (NEMWA, Act ).
[7] National Environmental Management: Biodiversity Act, 2004 (NEM:BA) (Act No. )
and amendments.
[8] National Forest Act, 1998 (NFA) (No ).
[9] National Veld and Forest Fire Act, 1998 (Act No. ).
[10] Conservation of Agricultural Resources Act, 1983 (CARA) (Act No. ) and
amendments.
[11] National Heritage Resources Act, 1999 (Act ).
[12] National Water Act, 1998 (Act ).
[13] The Occupational Health and Safety Act, 1993 (Act No. ).
[14] The National Fencing Act, 1963 (Act No ) as amended by Act .
[15] The National Environmental Management: Protected Areas Act, 2003 (Act No. ) and
itβs Regulations.
[16] The National Environmental Management: Air Quality Act, 2004 (Act ).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System Revision: 3
Tank
Page:
[17] South African National Standard (SANS) 10228 β The identification and classification of
dangerous goods.
2.3 Definitions
Include all definitions applicable to this document, in alphabetical order. Explain all terms used,
including documents, titles and departmental references that may cause confusion if not explained.
Definition Explanation
Construction work The erection, maintenance, alteration, renovation, repair, demolition or
dismantling of or addition to a building or any similar structure
The installation, erection, dismantling or maintenance of a fixed plant where
such work includes the risk of a person falling
The construction, maintenance, demolition or dismantling of any bridge, dam,
canal, road, railway, runway, sewer or water reticulation system or any similar
civil engineering structure
Contractor The Contractor has overall responsibility for ensuring that all work, activities,
and actions linked to the delivery of the contract, are in line with the
Environmental Management Programme and that Method Statements are
implemented as described
Works The works to be executed in terms of the Contract
2.4 Abbreviations
Provide explanations of terms and abbreviations including documents, titles and departmental
references that may cause confusion if not explained, and that are used in this document.
Abbreviation Explanation
CEO Contractor Environmental Officer
EMPr Environmental Management Programme
HCS Hazardous Chemical Substance
IAPs Interested and Affected Parties
NEMA National Environmental Management Act, 1998 (Act No. )
2.5 Roles and Responsibilities
Function roles and responsibilities
Eskom Environmental
Practitioner (EMPr) for the project is compiled and approved.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System Revision: 3
Tank
Page:
and post construction
Eskom Project
Manager/ Site
Manager contractor occupies the site.
Contractor
Environmental Officer Principal Contractor abide by the requirements of the EMPr.
(CEO)
to the project.
conditions, and constraints with respect to all their activities on
site.
requirements as stipulated within the EMPr and Method
Statements
and Environmental site meetings.
compliances are registered within the stipulated timeframes.
site documentation.
submission to Eskom.
and ensure that the receiving environment is suitably
safeguarded against the identified potential impacts, and to
ensure that the environmental management requirements are
adequately implemented and adhered to during the execution of
the project.
Contractor Project
Manager/ Site project. He/ She should be available on site all the time.
Manager
acceptable manner.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System Revision: 3
Tank
Page:
risks associated with the different activities that should be avoided
during the construction process and lessen significant impacts to
the environment.
2.6 Process for Monitoring
All documents shall be kept on site and be available for monitoring purposes. Site inspections by an
Environmental team or Project management team may require access to this documentation for
auditing purposes. The documentation shall be signed by all parties to ensure that such documents
are legal. Regular monitoring of site works by the CEO is imperative to ensure that all problems
encountered are solved punctually and amicably. When the CEO is not available, the Site Supervisor
shall keep abreast of all works to ensure no problems arise.
The following documentation shall be kept in a file on site:
10.1. Site Daily Diary.
10.2. Complaints Register.
10.3. Incidents and Non-Conformance Registers and Reports.
10.4. Records of all remediation / rehabilitation activities.
10.5. Copy of this Environmental Management Programme.
10.6. Photographic record (before, during and post construction/ refurbishment).
10.7. Project specific Method Statements / Procedures.
10.8. Inspections and Audit (monitoring and evaluation) Records.
10.9. Waste Records.
2.7 Related/Supporting Documents
This EMPr shall be read in conjunction the following documents that provide the details of the project
scope and/or requirements.
Deluge System Water Storage Tank Replacement
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System Revision: 3
Tank
Page:
3.1 Geographical Site Location and Environmental Condition
Apollo substation is situated 20 km south of Pretoria at an altitude of 1 510 m. It is a strong nodal
point in Eskomβs 400 and 275 kV national grid and houses the Apollo converter station which is
the receiving terminal in the Cahora Bassa/Apollo High-Voltage Direct Current (HVDC) scheme.
The geographical co-ordinates for the substation is - S25.91945, E28.27608.
Figure 1: Overview of the Transmission Network including Apollo CS β Gauteng Province
3.2 Public Involvement/Participation Process
The potential environmental impacts associated with the proposed project are required to be
considered in compliance with the Environmental Impact Assessment (EIA) Regulations of 2014 (As
amended) published in Government Notice R982 to R985 on, in terms of Chapter 5 of the National
Environmental Management Act, 1998 (Act ) (as amended). The above scope of work
was assessed against the Listing Notices of the EIA Regulations 2014 and the following is noted:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System Revision: 3
Tank
Page:
permits/agreements e.g., water use licenses or heritage permits.
All the required replacement works will be done directly on the existing substation footprint;
therefore, the project would not trigger the EIA listed activities.
3.3 Project Specific Scope of Work and Design
The details on the scope of works are outlined in the user requirement specifications (URS) in the
documents mention under 2.7 above. The following are the detailed scope of works.
3.3.1. Deluge System Water Storage Tank Replacement High Level Scope
grid deluge system water storage tank replacement including the following:
Assessment of the foundation integrity after removing the whole tank.
The tank should have of an outlet pipe, leak detection system and level indicators.
Isolation for the inlet and outlet valve.
Earthing for the tank.
This document has been seen and accepted by:
Name Designation
Transmission Project Delivery Project Managers
Note: Start with the latest Revision History in the first row and go backwards.
Date Rev. Compiler Remarks
July 2024 1 Tshinanne Mutshatshi New document
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System Revision: 3
Tank
Page:
The following people were involved in the development of this document:
Note: Acknowledgements to all those who had contribution to the standardization of the EMPr
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System
Revision: 3 Tank
Page:
Table 1: Project Specific Environmental Controls
This section specifies standard mitigation measures to be followed by the parties responsible for environmental management during
the construction of the project.
Note: An activity may have multiple aspects that might need to be looked at
No. Activity Aspect Impact Management Mitigation Measure Measurable Frequency Responsible
Objective Targets of Action Party
Contract and Enquiry to legal minimising negative as part of the tender signed stage Buyer/
programme requirements and impacts anticipated documentation thereby Environmental
non-conformance to occur during the making it part of the enquiry Practitioner
Declaration on to other construction/ document to make the
Environmental requirements and refurbishment recommendations and
Requirements conditions set out phase. constraints, as set out in this
Pro-forma. in the EMPr. document, enforceable
under the general conditions
of contract.
Ensure
environmental
awareness and A contractor shall Project Manager
formalise acknowledge or complete
environmental Declaration on
responsibilities and Environmental Requirements
implementation. Pro-forma before
commencement of the
works.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System
Revision: 3 Tank
Page:
A copy of this EMPr must be During CEO
always available at the works construction/
site. The Contractor shall refurbishment
ensure that all the personnel
on site, sub-contractors and
their teams, suppliers, etc.
are familiar with and
understand the specifications
contained in this EMPr.
Statements specific to legal and other minimising negative require method statements Method commencement
documentation requirements and impacts anticipated may only commence once Statements and of activities
conditions set out to occur during the the method statements have relevant
in the EMPr. construction/ been approved by the documents. As and when
refurbishment NTCSA PM and required
phase. Environmental Practitioner.
contractor shall provide job-
specific training on an ad hoc
basis when workers are
Contractor engaged in activities, which Training records
require Method Statements.
Eskom Policies, Guidelines
and Standards are consulted
to ensure that Method
Statements meet
requirements as set out in
those documents.
demarcation demarcation of site contravention, and minimising negative (i.e., Environmental place within the commencement
and damage to the impacts anticipated Department or Property demarcated of construction/
development environment to occur during the Management Team) shall be area. refurbishment
construction/ consulted before site activities on site
refurbishment demarcations and
phase.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System
Revision: 3 Tank
Page:
development, including the As and when
camp site. required
in this EMPr must be
adhered to and considered
when site demarcation and
development takes place.
allowed outside the
demarcated area.
It is also advisable for not
allowing the Contractor to
establish their site camp
inside the substation as it
attracts some security
attentions (i.e., theft of
equipment)
Awareness Environmental understanding by training and environmental awareness/ impact because commencement
Training Awareness Training workforce of the awareness of training. of construction/ of construction/
responsibilities in construction/
terms of this EMPr refurbishment staff onto site shall receive activities is activities.
contribute to environmental minimised
Legal minimisation of the awareness/training which through the As and when
contravention, occurrence of shall include the impact of development of required
environmental their activities and effective damage to the
impact to the work responsibilities on environmental environment and
area. environmental management awareness private property.
system. training material
and execution of
environmental awareness/training shall be
awareness available as and when
training for all required.
staff.
aware of the conditions and
controls linked to the EMPr.
of their individual roles and
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System
Revision: 3Tank
Page:
responsibilities in achieving
compliance with the EMPr.
erect and maintain
information posters at key
locations on site.
Wastewater management
procedures.
conservation.
management procedures.
-A record of all
environmental awareness
undertaken as part of the
EMPr must be available.
-Educate workers on the
dangers of open and/or
unattended fires.
Environmental
awareness/training should
include as a minimum the
following:
environmental impacts,
actual or potential, related to
their work activities.
be implemented when
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System
Revision: 3Tank
Page:
carrying out specific
activities.
preparedness and response
procedures.
followed when working
near or within sensitive
areas.
management procedures.
conservation.
management procedures.
-A record of all
environmental awareness
undertaken as part of the
EMPr must be available.
-Educate workers on the
dangers of open and/or
unattended fires
-A staff attendance registers
of all staff to have received
environmental awareness
training must be available
-Course material must be
available and presented in
appropriate languages that
all staff can understand
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System
Revision: 3 Tank
Page:
Establishment camp environment by environmental method statement shall be environment project
unnecessary issues are taken provided by the contractor during site commences
clearing the into consideration in prior to any onsite activity establishment is
surface/ ground. the planning and that includes the layout of minimised and
construction of site the construction camp in the the development
establishment. form of a plan showing the footprint are Land pollution/
location of key infrastructure kept to contamination.
and services (where demarcated
applicable), including but not development
Chemical pollution limited to offices, vehicle area.
caused by vehicle parking areas, stores, the
oils, grease or workshop, stockpile and lay
solvents down areas, hazardous
materials storage areas
(including fuels), the
batching plant (if one is
located at the construction
camp), designated access
routes, equipment cleaning
areas, ablution facilities,
waste and wastewater
management;
camps must be carefully
considered and approved by
the Substation/ Grid Team
and Tx. Projects Delivery to
ensure that the site does not
impact on sensitive areas.
where possible on previously
disturbed areas.
shall be fenced where
necessary.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System
Revision: 3 Tank
Page:
6 Environmental Response to all types Land, water Emergency
emergencies of environmental pollution/ procedures are in Response Plan prior to the situations are commencement
emergencies. contamination. place to enable a commencement of the managed in
rapid and effective proposed project. accordance with As and when
Chemical pollution response to all
types of must deal among other procedures. caused by vehicle
environmental things with accidents harsh oils, grease or
emergencies. weather conditions, Rapid and solvents
disasters, wildlife effective
interactions, potential response to all
spillages and fires in line with types of
relevant legislation. environmental
aware of emergency
procedures as part of
environmental awareness
training.
authority shall be made
aware of a fire as soon as it
starts.
emergency necessary
mitigation measures to
contain the spill or leak shall
be implemented.
Chemical use and disposal of and water pollution of the provide method statements the environment. CEO/ SHE
Substances hazardous pollution/ environment. for the βhandling & storage of Representative
(incl. oil) substances contamination. hazardous chemical No litigation due
substancesβ, βfireβ, and Minimise chances to transgression
βemergency spills Damage to the of transgression of of pollution
proceduresβ. environment. the acts controlling control Acts.
pollution.
confined to specific and
No complaints secured areas within the
from Interested contractorβs site, and in a
& Affected way that does not pose a
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System
Revision: 3Tank
Page:
danger of pollution even Parties (I &
during times of high rainfall. APs).
These areas must be
imperviously bunded with Method
adequate containment (at statements
least 1.5 times the volume of
the fuel) for potential spills or
leaks
10cm deep) must be placed
under all vehicles, including
plant and equipment that
stand for more than 24
hours. Vehicles suspected of
leaking must not be left
unattended, drip trays must
be utilised.
drip trays will be dependent
on the vehicle and must be
large enough to catch any
hydrocarbons that may leak
from the vehicle/plant while
stationery.
substances must be
contained in impermeable
containers for removal to a
licensed hazardous waste
management facility/ site,
(this includes contaminated
soils, and drenched spill kit
material).
(SDS) must be prepared for
all hazardous substances on
site and supplied by the
supplier where relevant.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System
Revision: 3 Tank
Page:
SDSβs must be updated as
required.
clearly marked to indicate
contents, quantities and
safety requirements.
oil, paint, herbicide and
insecticides must be sealed
and stored in bunded areas
or under lock and key, as
appropriate, in well-
ventilated areas.
All employees working
with HCS must be trained in
the safe use of the
substance and according to
the safety data sheet.
No smoking must be
allowed within the vicinity of
the hazardous storage
areas.
Adequate fire-fighting
equipment must be made
available at all hazardous
storage area.
An appropriate number
of spill kits must be available
and must be located in all
areas where activities are
being undertaken.
eating areas and management influx of vermin and conjunction with the Eskom vermin and flies.
of waste. flies. Environmental Practitioner or
Neat workplace and PM designate restricted No complaints
Littering of waste. hygienic eating areas for eating from I & APβs.
environment. during normal working hours.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System
Revision: 3 Tank
Page:
bins must be provided and
cleaned daily.
outside the camp) and
concrete bags etc. must be
picked up daily and put into
suitably closed bins.
Management management of storing, handling and mitigate waste management shall be management is
waste and unsafe potential impacts to undertaken using an undertaken in
disposal of at a the environment integrated waste accordance with
unrecognised/ caused by the management approach. relevant national
unregistered incorrect storage,
waste facility. handling and waste collection bins legislation and
disposal of general (scavenger and local by-laws; as
and hazardous solid weatherproof) shall be well as
waste. provided. Transmission
Industry Waste
Management and clearly demarcated
Plan. waste collection site shall be
identified and provided.
shall be maintained in a
clean and orderly fashion.
segregated into separate
bins and clearly marked for
each waste type.
waste segregation.
shall be maximised.
regularly.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without
the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Management Programme for Unique Identifier: 240-131566734
Replacement of Apollo CS Deluge Water System
Revision: 3 Tank
Page:
disposed of at recognised
and registered waste
disposal sites/ recycling
company.
be disposed of at a
registered waste disposal
site.
for general, hazardous, and
recycled waste shall be
maintained and submitted to
NTCSA together with the
performance reports.
Under no circumstances
shall any waste be disposed
of, burned, or buried on site.
All waste shall be treated or
disposed of at licensed
Matidi Seabelana B
Eskom is committed to creating and sustaining a Zero Harm culture and standard of safety, health,
the environment, and quality (SHEQ). Zero Harm means ensuring that the Eskom operational
activities do not inflict harm on Eskomβs assets, its employees, contractors, and members of the
public affected by its operations, and the environment in terms of compliance obligations. All
procurement has some level of impact on the environment that needs to be minimised to ensure
sustainable procurement practices. Most environmental impacts occur before goods, works or
services are procured, for example, resource extraction, design development, manufacturing,
transportation and storage, etc. Environment is an integral part of Eskom sustainable procurement
strategy.
This standard sets the minimum criteria for assessing supplier environmental conformity, based on
standards, procedures, policies, and compliance obligations with which Transmission suppliers need
to comply. It specifies a pre-determined set of environmental criteria to evaluate and monitor
potential and contracted Transmission suppliers. The objective is to ensure a common
understanding and consistent implementation of environmental requirements for procurement of
assets, goods, and services.
2.1 Scope
The standard outlines the key responsibilities of Procurement Practitioner, Contractor/Supplier,
Clients, Environmental Practitioner and Contract or Project managers (contract custodians). It also
provides the minimum environmental requirements to be addressed during:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Requirements for Contractors and/or Unique Identifier: 240-180100134
Suppliers
Revision: 1
Page:
a) Design phase.
b) Tender enquiry, evaluation, and contract award.
c) Supplier registration on the Transmission vendor data base.
d) Site access /site mobilization.
e) Monitoring of performance during the contract execution period.
f) Contract completion, close out, and post-contract review and
g) Instances and criteria where works or services under a contract can be stopped, suspended or
termination of contracts.
2.1.1 Purpose
The purpose of this standard is to ensure that Suppliers, Contractors, and Sub-Contractors
contracted to Transmission have established an Environmental Management System for goods,
works, or services they provide.
2.1.2 Applicability
This document shall apply throughout Transmission including Suppliers, Service providers,
Contractors, and Sub-Contractors.
2.1.3 Effective date
This standard shall be effective from the date of the signature.
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
[1] 32-1034 Eskom Procurement and Supply Chain Management Procedure.
[2] 32-196 Eskom Disciplinary Code Standard.
[3] Project Specific Environmental Management Programmes/Environmental Management Plan.
[4] Project Specific Permits and Licenses (Construction stage).
[5] 240-43921804 Environmental Tender Evaluation Template.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Requirements for Contractors and/or Unique Identifier: 240-180100134
Suppliers
Revision: 1
Page:
[6] 240-151560800 Environmental Evaluation-Commencement of work.
[7] 240-180100148 Pre-construction Access Agreement Form.
[8] 240-110600836 Contractor Environmental Requirements Proforma.
2.2.2 Informative
[9] National Environmental Management Act No
[10] ISO 14001: Environmental Management Systems
[11] National Environmental Management: Waste Act (Act )
[12] Environmental Impact Assessment Regulation (2014)
[13] National Water Act (Act )
[14] National Environmental Management: Air Quality Act (Act )
[15] National Environmental Management: Biodiversity Act (Act )
[16] National Environmental Management: Protected Areas Act (Act )
[17] National Heritage Resources Act (Act )
[18] National Veld and Forest Fire Act (Act )
[19] 240-82410629 Environmental Management Strategy
[20] 240-81146134 Implementing SHEQ as Objective Criteria Position Paper
2.3 Definitions
Definition Explanation
Environmental Any change to the environment, whether adverse or beneficial, wholly, or
Impact partially resulting from an organisationβs environmental aspects.
Environmental Authorisation obtained from a competent authority responsible for
Authorisation authorising listed activities in terms of the National Environmental
Management Act No .
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Requirements for Contractors and/or Unique Identifier: 240-180100134
Suppliers
Revision: 1
Page:
Environmental It is a programme/plan of action for achieving organisational objectives
Management relating to the mitigation of environmental impacts of its activities, products,
Programme and services.
Environmental A programme for achieving organisational objectives and targets relating to
Management Plan mitigation of the environmental impacts of an organisationβs activities,
products, and services.
Project Means an activity or a group of activities that has a defined start and end
date, a defined scope, and as defined sum of money allocated to complete
the activities.
Project Life Cycle The project life cycle is a step-by-step framework of best practices used to
manage a project from its beginning to its end. It provides Project Managers
a structured way to create, execute, and finish a project.
Environmental file Means a permanent record containing information about the Environmental
management system during construction and all information relating to the
post-construction phase after the handover to the client, so that the client
can maintain the works in a healthy and safe way.
Method Statement Means a written document detailing the key environmental activities to
reduce the hazards identified in any risk assessment. In the case of internal
work, it includes procedures, safe work procedures, and work standards.
Environmental The measurable results of an organization's management of its
Performance environmental aspects.
Organisation A company, corporation, firm, enterprise, authority or institution, or part or
combination thereof, whether incorporated or not, public or private, that has
its own functions and administration.
Note: For organisations with more than one operating unit, a single
operating unit may be defined
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Requirements for Contractors and/or Unique Identifier: 240-180100134
Suppliers
Revision: 1
Page:
Environmental authorisation obtained from a competent authority responsible for
Authorisation authorising listed activities in terms of the National Environmental
Management Act, 1998 (Act No.) Environmental Impact
Assessment Regulations (2014).
Contractor/Supplier Organisation or person that provides a product or service.
Organisation Example: Producers, distributor, retailer or vendor of a product, or provider
of a service or information.
Note 1: A supplier can be internal or external to the organisation.
Note 2: In a contractual situation, a supplier is sometimes called
βcontractorβ.
Document Controlled disclosure to external parties (either enforced by law or
Controlled discretionary).
Disclosure
Environmental Is a system which integrates policy, procedures, and processes for training
Management of personnel, monitoring, summarizing, and reporting of specialized
System environmental performance information to internal and external
stakeholders of an organisation.
2.4 Abbreviations
Abbreviation Explanation
EA Environmental Authorisation
ECO Environmental Control Officer
EMPr Environmental Management Programme
EMP Environmental Management Plan
EMS Environmental Management System
ISO International Organisation for Standardization
SDS Safety Data Sheet
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Requirements for Contractors and/or Unique Identifier: 240-180100134
Suppliers
Revision: 1
Page:
Abbreviation Explanation
TDP Transmission Projects Delivery
SHE Safety Health and Environmental
SHEQ Safety Health Environment and Quality
P&SCM Procurement and Supply Chain Management
SHERQS Safety Health Environment Risk Quality & Security
2.5 Roles and Responsibilities
Procurement Practitioner shall:
Environmental Practitioners for the preparation of the relevant environmental requirements
for the enquiry.
the appropriate environmental practitioners prior to the release of tender documents.
input into the relevant meetings or forums, processes, and reports that lead to the awarding
of the contract (e.g., supplier evaluation, squad check meetings, contracting strategies,
negotiations, clarification meetings, tender evaluations and evaluation report compilations,
contract award, briefing meetings).
Environmental Practitioner to ensure that all applicable rules and requirements are
referenced in this form for Tenderers to acknowledge and comply with and ensure that its
completed and included in their tender.
Business Unit Manager shall be responsible for:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Requirements for Contractors and/or Unique Identifier: 240-180100134
Suppliers
Revision: 1
Page:
The Environmental Practitioner shall:
lead to the awarding of the contract.
requirements together with members of the cross functional team for each tender/enquiry
and shall ensure that these requirements are handed over to commercial representative
for inclusion in the tender/enquiry.
work and environmental risk assessment conducted for the contract.
are submitted with the tender returnables.
execution and post-contract review and assessment and must also ensure that all reports
are provided to contracts management.
interventions taken and provide the report to the contract custodian and submit to
contracts management.
technical evaluation criteria for the contract.
The Contract Custodian (Contract Executor) shall:
Ensure that the Supplier adheres to the relevant contract environmental requirements.
Ensure that project-specific environmental specifications together with specific
environmental aspects and other relevant procedures and documents are developed in
conjunction with the Environmental Practitioner and provided with the tender package.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Requirements for Contractors and/or Unique Identifier: 240-180100134
Suppliers
Revision: 1
Page:
environmental obligations during contract execution, environmental intervention or
standoff, post contract review, supplier reconsideration are adequately addressed,
recorded, and submitted to contracts management for record and future references.
impractical to comply with and suggested recommendations shall be submitted in writing
to contract management where it is impractical to implement and /or comply with
environmental requirements as set out in this standard.
results of such assessment are recorded, documented, and kept.
of the Bills of Quantities in the contract.
Supplier /Service Provider:
documentation for evaluation.
Practitioners during the tender clarification meeting to fully comply with the requirements
of this standard. Such support, guidance and advise shall be levelled in writing with the
Eskom Representative whose details are in the tender document. Direct communication
between tenderers and Environmental Practitioners shall not be allowed. .
Transmission environmental requirements always when contracted with Transmission
Business Units.
related to the works, services or goods tendered for.
site requirements, and it is the responsibility of the Supplier to ensure that these
requirements are met before work can commence.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30
Environmental Requirements for Contractors and/or Unique Identifier: 240-180100134
Suppliers
Revision: 1
Page:
2.6 Process for Monitoring
Compliance to this standard will be monitored during tender evaluations, periodic inspections and
audits on the works, goods or services rendered. The procedure / process shall include documenting
information to monitor performance, applicable operational controls (method statements) and
conformity with the Transmission EMPr/EMP and/or the EA.
environmental management procedures, and/or any inspection authority acting on
supplierβs behalf, to make available all information at its disposal certificates for review
by Transmission or its appointed inspection agency.
shall be made available to Transmission business units. These shall not be limited to:
o A procedure for Monitoring, Measurement, Analysis and Evaluation of
Provisions ............................................................................................................................................. 54
Transmission must provide budgets for the implementation of the waste management plan. ................ 54
The aim of the Health & Safety (H&S) specification is to provide principal contractor/s and suppliers
with:
compliance to legal and Eskom Holdings (NTCSA) H&S requirements.
contract.
NTCSA strives to exceed the minimum standards prevailing in the construction industry and requires
full commitment from all parties to be pro-active to achieve best H&S business practice.
This H&S Specification is intended for principal contractor and their contractors to develop a H&S
plan that meets the specified requirements.
2.1 Scope
This H&S specification sets out the minimum legal and NTCSA requirements for construction work
that is specific to the scope of work, site, and type of project.
2.2 Purpose
To indicate to principal contractor the H&S requirements on the project, upon which their planning
for the management of H&S will be based on and thus produce their H&S plan.
2.3 Applicability
This specification is only applicable to the project as mentioned on the first page, title all principal
contractors, contractors, service providers, suppliers and all the activities and processes carried out
for and on behalf of PD.
This specification shall be implemented from the date of approval.
Parties using this specification shall apply the most recent edition of the documents listed below.
3.1 Normative
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
Standards β SANS)
3.2 Informative
[1] ISO 45001, Occupational Health and Safety Management Systems-Requirements
[2] ISO 9001, Quality Management Systems- Requirements
[3] Construction Regulations of 2014
[4] Council for the Built Environment Act
[5] Project and Construction Management Profession Act
Authorised person: a competent person who has been given permission in writing to perform
specific duties and responsibilities in terms of the Operating Regulations for High Voltage Systems.
Baseline risk assessment: (32-520) baseline operational risks refer to the H&S risks associated
with all standard processes, as well as routine and non-routine activities in the business.
Critical Lifts: (1) any lift weighing in excess of 20 tons, (2) any lift involving a crane suspended work
platform (man cage), (3) any lift over critical operating and/or process equipment and (4) any lift that
exceeds 85 % of the craneβs load chart (5) any lift that utilises more than one lifting device (Tandem
Lift).(6) Load transfers.(7) night lifting.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
Eskom Holdings (NTCSA) Requirements: Eskom Holdings (NTCSA) requirements, which evolve
from directives, policies, standards, procedures, specifications, work instructions, guidelines, or
manuals.
Hazard identification: the identification and documenting of existing or expected hazards to the
health and safety of persons, which are normally associated with the type of construction work being
executed or to be executed.
Medical surveillance: a planned programme or periodic examination (which may include clinical
examinations, biological monitoring, or medical tests) of employees by an occupational health
practitioner or, in prescribed cases, by an occupational medicine practitioner.
Method Statement: is a written document detailing work procedures and sequences of operations.
On Site/Site: any workplace where the contractor or his employees perform construction related
work as agreed contractually with the client.
Planned Task Observation: an independent observation made during the planned period in which
the task is being executed.
Pre-Task Risk Assessment: a meeting held prior to the commencement of the dayβs work with
relevant personnel (client representative included) associated with the task at hand.
Risk Assessment: a programme to determine any risk associated with any hazard at a construction
site in order to identify the steps needed to be taken to remove, reduce, or control such hazard.
H&S File: a file or other record in permanent form, containing the information on the H&S
management system during construction including all information relating to construction phase after
the handover to Client.
Safe Work Procedures: a series of specific steps that guide a worker through a task from start to
finish in a chronological order. Safe work procedures are designed to reduce the risk by minimizing
potential exposure.
Abbreviation Explanation
AIA Approved Inspection Authority
COIDA Compensation for Occupational Injuries and Diseases Act
CR Construction Regulations
CHSA Construction Health & Safety Agent
CWP Construction Work Permit
DMR Driven Machinery Regulations
DSTI Daily Safety Task Instruction
EA Environmental Authorization
ECO Environmental Control Officer
FAS Fall Arrest Systems
GSR General Safety Regulations
RHCA Regulations for Hazardous Chemical Agents, 2020
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
Abbreviation Explanation
H&S Health and Safety
HIRA Hazard identification and risk assessment
HV High Voltage
LDV Light Delivery Vehicles
LMI Lifting Machine Inspector
LME Lifting Machine Entity
LTIR Lost Time Incident Rate
NEC New Engineering Contract
NEMA National Environmental Management Act
NTCSA National Transmission Company South Africa
NQF National Qualifications Framework
OHNP Occupational Health Nursing Practitioner
OHS Act Occupational Health and Safety Act No.
OHS Occupational Health and Safety
ORHVS Operating Regulations for High Voltage Systems
PPE Personal Protective Equipment
PTO Planned Task Observations
RSA Republic of South Africa
SANAS South African National Accreditation System
SANS South African National Standards
SACPCMP South African Council for the Project & Construction Management Professions
SAQA South African Qualifications Authority.
SDS Safety Data sheets
SHEQ Safety, Health, Environment Quality
SETA Skills Education Training Authorities
SWP Safe Work Procedure
PD Project Delivery
VFL Visible Felt Leadership
Manages the contract signed with the principal contractor and ensures that H&S specifications are
developed and issued with tender enquiries, and that the principal contractorβs H&S plan is approved
prior to commencement of work. He must ensure that applicable legal and other requirements are
complied with by the principal contractor and (if applicable) their contractors. The project manager,
thus takes the overall accountability of this project as
Is responsible for the overall management of the project design as well as ensuring the management
of the compliance of the completed works to the design during and after construction on site.
Where a construction permit is required, the Agent shall act as the representative of the client on
issues of H&S. The duties of the client shall, as far as is reasonably practical, apply to the Agent.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
The Agent shall approve the principal contractor H&S plan. He/she will be responsible for auditing
and ensuring compliance to legal requirements as per the condition of the CWP.
Provides assurance, advice, and support to the project in the management of the H&S issues on the
project. They will also assist in the development of projectβs H&S Specifications which will be issued
with enquiry documents, and that the principal contractorβs H&S plan is submitted; evaluated and
approved. They will be responsible for auditing and ensuring compliance to legal requirements. The
H&S Senior Advisor shall approve the principal contractor H&S plan in all projects that does not have
a CWP.
7.1 Visible Commitment
Visible commitment is essential in providing a safe work environment. managers, supervisors, and
employees at all levels must demonstrate their commitment by being proactively involved in the day-
to-day operations, in particular H&S aspects of the project / contract.
A minimum of one (1) Visible Felt Leadership engagement (VFL) per month shall be conducted by
the contractorβs project manager. The contractor General Manager/Chief Executive or executive
representative shall one (1) VFL quarterly that shall be submitted to Client Project Manager.
7.2 Designers
The designer of a structure must comply with Construction Regulations 6 and ensure that cognizance
is taken of ergonomic design principles and foreseeable constructability health and safety risks
during construction and life cycle of the structure.
7.3 Principal Contractorβs Accountabilities
a. The principal contractor shall comply with provisions of Construction Regulations 7.
b. Where a principal contractor procures the services of a contractor, the principal
contractor shall first inform the client. Such contractor shall also comply with relevant
sections of this H&S specification.
c. The principal contractor must demonstrate how activities of various contractors will be
coordinated to mitigate the risks.
d. The principal contractor shall ensure that his/her H&S plan is approved by the client
before gaining access to site. The same principle will apply to its contractor, where he/she
shall approve his/her contractors H&S plan.
e. A comprehensive & updated list of all contractors on site, also indicating the type of work
being done.
f. The principal contractor shall coordinate, consolidate, and submit H&S performance and
that of contractors on the last day of each month to the client.
g. The principal contractor must ensure that their senior management conduct VFL, at least
once a quarter.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
h. The principal contractor must incorporate the client's induction into their induction and
induct their contractors before site access. The principal contractor shall keep all
induction material including registers.
a. The principal contractor shall comply with provisions of Construction Regulations 8.
b. The principal contractor shall appoint one (1) full-time competent construction manager
responsible for a single site. In a case where a construction manager is not available, an
alternate construction manager shall be appointed in writing for a specified duration.
c. Having considered the size of the site one or more assistant construction manager shall
be appointed in writing.
d. The principal contractor must, in writing, appoint Full Time safety officer in accordance
with the requirements of Construction Regulations 8(5). For part-time safety officer the
frequency of their presence on site must be clearly specified in the safety plan.
e. Construction supervisors and their assistance must be appointed in accordance with
Construction Regulations 8(7) & (8) respectively.
f. The appointed construction manager and safety officer shall be registered with
Sacpcmp.
The appointment of a registered or non-registered construction manager shall be
done in accordance with the provisions of the PD SACPCMP Registration Categories
attached on the Appendix A, annexure B.
Note: No construction work must commence or continue without a competent construction manager,
a supervisor, and a safety officer (except for a parttime safety officer) being on site.
This document is under revision control and is valid for the duration of the works and will be
amended, as and when necessary, as requirements are being amended and therefore it will be
required for the principal contractor and contractorβs H&S plan to be amended accordingly.
Conformance to this document shall be via regular safety inspections and by Monthly Audits.
9.1 Related/Supporting Documents
Annexure A β Eskom Holdings (NTCSA) SHEQ Policy Statement 32-727
Annexure B β 20241010 SACPCMP Registration Categories
Annexure C β Contractor Manpower Sourcing and Verification
Annexure D β Pre-Task Planning Template
Annexure E β Flash Report template
Annexure F β Portable Toilet Specification
Annexure G β Contractor OHS File Handover Record Template
Annexure H β PD Loading and Offloading
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
Annexure I β Tender Evaluation Criteria
Annexure J β Site Readiness Evaluation Criteria
Annexure K - Health and Safety Requirements Acknowledgement
Annexure L - Appointments and Competencies Guide_559-1762006876
Project Details
9.2 Scope of Work
Construction of a concrete one million litre deluge water storage tank
At apollo converter station
9.3 Location: Insert where the construction site is situated:
GPS Coordinates: TBC
Apollo Substation, situated in Ekurhuleni ,Gauteng.
9.4 Program details:
Anticipated date for the commencement of work on site:
Project completion date or project duration:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
9.5 The Client Project Organogram:
Senior Manager
Projects:Harish
Mohabir
Name & Surname
Safety
Programme Intergration Risk Construction H&S
Manage:Ray Asalan Manager Senior Advisor H&S Manager:Lindiwe Agent:N/A
Masoeu
Name & Surname Name & Surname Name & Surname Nama & Surname Name & surname
Project
Manager:Thabo Project Scheduler H&SShabalalaOfficer:Linda
Aphne
Name & Surname Name & Surname Name & Surname
Project Site
coordinator:Olga Supervisor:Nanda Cost Engineer Risk Advisor
Rampokanyo Moonsamy
Name & Surname Name & Surname
Name & Surname Name & Surname
Project Officer Quantity Survey
Name & Surname Name & Surname
9.6 Principal Contractor Organogram
The principal contractor shall provide an organisational organogram related to this project, listing all
the levels of responsibility from the Chief Executive down to the supervisors responsible for the
project. The organogram must list the names of appointees and their roles and responsibilities
including the statutory requirements appointees. All organograms shall be updated timeously when
appointments are changed and filed in the project H&S file.
For the duration of the contract, the principal contractor shall ensure that competent persons are
appointed in writing in terms of the requirements of the OHS Act and its Regulations; and
or other statutory and Eskom Holdings (NTCSA) requirements and that all their appointees are made
aware of their accountabilities and responsibilities and have been suitably trained in terms of their
appointment.
The principal contractor shall notify in writing in a form similar to annexure 2 the relevant Provincial
Director (Labour Centre) of the Department of Employment and Labour of the intention to carry out
construction work as defined in the Construction Regulations 4, at least 7 days before construction
work is to be carried out. No construction work shall commence without a proof of submission of
such notification to the client.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
11.1 OHS Act Section 37 (2) (Legal) Agreement
a. An OHS section 37(2) agreement shall be signed between the client and the principal
contractor at the time of contract award.
b. The original copy of an OHS section 37(2) agreements shall be retained by the contractor
and a copy retained by the client project manager.
c. A copy of OHS section 37(2) agreement must form part of the respective contractorβs H&S
file.
11.2 CR 5(1)(k) Appointment
a. At contract award the principal contractor shall be appointed in writing by the PD Project
Manager for the construction site. Therefore, site access shall be granted once all the
contractual requirements are met.
b. A copy of CR 5(1)(k) appointment must form part of the respective contractorβs H&S file.
11.3 Designated employer, Sec 16(2) and other competencies appointments
The principal contractor shall ensure that a designated employer is appointed in writing for the for
the duration of the project.
The principal contractor shall ensure that competent persons are appointed in writing for OHS
statutory and non-statutory functions in line with their organisational structure. See Annexure L
The principal contractor shall ensure that the appointees understand their roles, responsibilities and
accountabilities. Copies of relevant appointments shall be kept on an OHS site safety file.
The scope of training shall include, but not limited to, the type of work being performed and the
relevant procedures. Where training is provided by the external service providers, the principal
contractor shall ensure that the service providers are accredited by SAQA or QCTO (Appropriate
qualifications and training registered in terms of the National Qualifications Framework Act No. ).
The principal contractor must demonstrate how he/she intends managing training/awareness within
their organisation including method of informing visitors and other persons entering the site about
hazards prevalent onsite.
Persons with foreign qualifications and registrations to convert these to equivalent local registrations
in that level or category (this shall be in accordance with SAQA and SETA requirements). The letter
from SAQA shall form part of the tender and site readiness submissions to PD.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
The principal contractor shall develop an OHS Policy authorised by their Chief Executives that states
overall OHS objectives and commitment to improving OHS performance and must be conspicuously
displayed and shared with all stakeholders.
The principal contractor shall comply with relevant legal and other requirements as part of the
contract. Expenses to the principal contractor, which result from such compliance, as well as any
site-specific requirements, will be for the principal contractorsβ account.
Where the principal contractor appoints another contractor(s), the same roles, and responsibilities
in relation to the contractor as the client has in relation to the principal contractor shall apply.
The client reserves the right to stop work and issue a non-conformance report and/ Prohibition
notice(s) whenever H&S violations are observed from the principal contractors and their contractors,
after engaging and making both aware of such. Expenses incurred because of such work stoppage
and standing time shall be for the principal contractorβs account. Any non-
conformances/findings/observations found during the audits/inspections on the contractor shall be
raised and discussed with the relevant principal contractor (with whom the contractor is contracted
with).
15.1 Legal and Other Requirements
The principal contractors shall comply with the relevant applicable legislation, specifications, and
standards in accordance with the scope of the project.
The principal contractor shall compile a legal register listing all applicable legislation and standards
that may have an impact on the scope of work that they are performing on the construction project.
The register shall be updated as and when there are amendments.
The Bill of Rights in the Constitution of the Republic of South Africa is clear on the rights of
children, especially when it comes to child labour. Child labour shall not be permitted in any of
NTCSA, PD sites.
The principal contractor shall develop a Risk Assessment in line with Construction Regulation 9 in
alignment to Eskom/NTCSA, 32-520 procedure.
Detailed Risk Assessment must be conducted to ensure that all the applicable scenarios are covered
and documented per site activities including practical controls. High Risk Activities
When the principal contractor and/or his/her contractors are working in an area where a high health
and safety hazard exists, the principal contractor shall:
a) Develop a SWP.
b) Ensure that permanent and adequate supervision is available for the duration of the work
performed.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
c) Work within visible earths (Standard Line Construction Method).
d) Ensure the use of safety standbys in areas of high-risk activities, and activities that fall within
the scope of the permit to work system.
e) Provide, erect and maintain the required barricading, lighting, flags, flashing lights, or other
safety control equipment to enable operations to proceed in a safe manner.
f) Maintain defined access ways, which are clear of obstructions, to allow for emergency vehicle
entry.
g) Provide any temporary protective shielding required for protecting nearby operations from
the construction activities, at their own cost.
h) When Crossing roads, railway tracks and other power lines during stringing operations, the
principal contactor shall ensure that:
i). βRugby polesβ are properly erected at all road crossings and that the public is warned,
ii). Flagmen placed at strategic positions to warn traffic/ motorists.
iii). Whenever mobile cranes/ lifting machinery are operated onsite, the booms are retracted
and safe clearances from overhead power lines; communication lines or other overhead
obstructions are observed and maintained as per Electrical Machinery Regulations 19 &
21, Eskom Holdings (NTCSA) Procedure "Operating Regulations for High Voltage
Systems (ORHVS), 240-114967625" clause 5.03.6.3 (working in the close proximity to
live line/conductors).
iv). Supervisors are trained in the Eskom Holdings (NTCSA) ORHVS.
v). Detailed risk assessment shall be conducted prior the activities and a hierarchy of control
measures shall be considered before resorting to PPE. Where PPE are required, risk-
specific PPE shall be identified and issued to the specific team that will be working in the
close-proximity to live line/conductors.
i) Height restriction barriers/crossbars must be erected on both sides of the overhead power
lines, communication lines or other overhead obstructions. Establish the permitted safe
clearances in consultation with the owner of the line.
a. To ensure the safety of workers, visitors and other persons who may be affected, the
operating regulations for high voltage systems shall apply during construction of high voltage
apparatus (construction of transmission/distribution lines) or working in live yard inside a
substation.
b. The principal contractor shall ensure that workers in prohibited areas inside a sub-station are
under supervision of an authorised person, under a work permit. When an authorised person
resigns from a company and is employed by another company, his authorisation shall expire
immediately.
c. The authorised person shall be present throughout the operations.
Reference: ORHVS, 240-114967625 and Power Delivery Operating Assessment,
Authorisation and Training Standard, 240-70413865.
The principal contractor shall ensure that the submitted tender adequately makes provision for the
cost of H&S.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
Note: the costing for H&S must be itemised based on the overall scope of the project e.g.: resources,
provision of PPE, occupational hygiene, occupational health, etc.
The principal contractor shall not permit any person to enter the construction site where their health
and safety may be at risk. Notices at every entrance prohibiting the entry of unauthorised persons
shall be posted:
a. No one should enter the construction site without being inducted. The principal contractor
shall demonstrate how site access shall be manage on site.
b. Entering or leaving the site shall only take place at official access control points and may only
be done via the official designated walkways.
c. Where construction line is being constructed the principal contractor shall ensure that:
i). Members of the public are not allowed to be in the proximity where the activities are
being executed.
ii). Domestic animals are managed not to be in the proximity where the activities are being
executed.
Symbolic safety signs shall comply with the requirements of SANS 1186.The display of the following
signage is mandatory:
a. The principal contractor sign shall be posted at their site offices and shall have the name
and contact details of the: Construction Supervisor; Health and Safety Manager/ Officer; First
Aider; Health and Safety Representative and Evacuation warden, Construction Health and
Safety Agent and Construction Permit (where applicable). Emergency numbers, principal
contractor name (including a logo), construction manager and contact number.
b. The Contractors shall provide signage in accordance with the scope and work area.
c. All safety and warning signs shall be always obeyed.
Site facilities shall be established and maintained by the principal contractor. The facilities include
but are not limited to the following (refer to OHS Act, Construction Regulations 30). See also
Annexure F for portable toilet specifications. The design of the toilet should not expose employees
to splashes of other peopleβs human waste.
Principal contractors shall in their H&S plan, factor how they would safeguard members of the public
against their activities during the project.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
24.1 Life Saving Rules
The Eskom Holdings (NTCSA) Life Saving rules applies to NTCSA employees, agents, consultants,
contractors, and visitors. Visitors to NTCSA sites are expected to respect and comply with these
rules. Anyone who refuses to do so may be instructed to leave to leave NTCSA premises
immediately. Failure to adhere to these rules will be regarded a serious transgression, and it is
expected that the employer will take appropriate disciplinary action. The client also reserves the right
to suspend the contractorβs activities pending the outcome of such disciplinary processes.
These rules are enforced to prevent serious injury or loss of life among employee, labour broker or
contractor working in any area within Eskom Holdings (NTCSA) area.
The rules are:
Rule description of rule
Open, isolate, test, earth and create an equipotential zone
Before touch
To ensure a safe electrical work environment, no person may work/operate on, around
or near any electrical network, line or apparatus, electrically connected to the power
Rule 1
system and/or electrically charged and/or not electrically charged unless if trained,
authorised, competent and supervised. The equipotential zone is only applicable for
work being done on medium and high voltage apparatus.
(That is plant, any plant operating above 1000 V)
Hook up at height
Working at height means any work performed above a stable work surface or where a
person puts himself/herself in a position where he/she exposes himself/herself to a fall
Rule 2 from or into.
Working at height is a significant part of work in NTCSA and is regarded as a high-risk
activity, as a result, all precautions must be taken to prevent incidents while working at
height.
Buckle up
Where required, the proper wearing of seat belts for any driver, operator and passenger
Rule 3 is mandatory in all vehicles/equipment when driving and/or travelling for NTCSA
business purposes.
.
Be sober
No person who is under the influence or who appears to be under the influence of
Rule 4
intoxicating liquor or drugs will be permitted to enter or remain on a NTCSA site conduct
NTCSA business or drive/operate a vehicle/equipment for NTCSA business purposes.
Ensure that you have a permit to work
Rule 5 No person shall work without the required Permit to Work (PTW). This includes driverβs
license and other statutory permits
Rule 6 ENSURE SAFE LIVE WORKING
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
To ensure safe live work: Each live worker shall ensure all live work basic principles are
adhered to, as outlined (for the method being used) in the High Voltage Live Working
Standard; Observe and maintain the Minimum Approach Distance; Only perform live
work and tasks that are authorised for and that are documented in the respective Task
Manual.
24.2 Smoking
Smoking is only permitted at designated areas in accordance with the requirements of the
smoking policy (32-1126: Eskom Holdings (NTCSA) Smoking Policy). Add to the appendix A.
24.3 Cellular Phones
A contractor shall develop and implement a risk-based cell phone policy for a particular
construction site. Cellular phones shall not be used in areas where their usage is prohibited.
24.4 Fire Extinguishers
A Principal Contractor shall have a layout plan (site offices, laydown area) where fire-fighting
equipment is located. Fire extinguishers should be inspected monthly and be maintained annually
by a competent service provider. These records shall be kept in the project safety file.
24.5 Vehicles and Traffic Rules
a. The principal contractor shall ensure that the driver of the vehicle has a valid driverβs licence.
b. Principal contractor shall ensure that drivers and passengers wear seatbelts while travelling
in a motor vehicle.
c. No passengers shall be permitted to be transported at the back of trucks or light delivery
vehicles (LDV).
d. Passengers shall only be permitted to be transported at the back of such vehicles if fitted with
a specially designed crew cab with appropriate seating and seat belt per passenger, by the
manufacturer and manufacturer appointed fitment centre. The test certificate shall be
submitted for consideration to the client.
e. Where a vehicle licence condition stipulates the number of persons to be transported on the
vehicle, such number shall not be exceeded.
f. The principal contractor shall ensure that the vehicles are inspected daily and maintained
regularly as per the manufactureβs specification.
24.6 Substance and Drug Abuse Management
a. The principal contractor must develop a substance abuse management procedure to manage
substance abuse on site. The procedure shall be in line with the client substance abuse
management procedure were applicable. Eskom Holdings (NTCSA) Substance Abuse
Procedure 32-37.
b. All testing equipment shall be calibrated as per the manufacturerβs recommendation and the
calibration be available on the safety file.
c. The alcohol testers must be trained and appointed in writing.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
The principal contractor shall conduct a daily pre-task risk assessment with employees involved with
the task, such as DSTI. This assessment will be the basis of daily pre-job briefings or toolbox talks
before work begins, highlighting critical steps from the SWP to ensure safety. Proof of
communication and confirmation of understanding will be recorded and kept at the job site during
execution. The signed pre-task risk assessment form shall be filed in the safety file.
Upon receipt of the task for the day, the principal contractor manager or his/her assignee the site
supervisor, shall perform a pre-task planning in accordance with Line Construction; Substation
Works and Telecommunication Projects, 559-1432317009 Rev 1, Pre-Task Planning Template, see,
Annexure D.
The principal contractor shall compile a project/ site-specific SWP for all the high-risk activities as
identified in the risk assessment and scope of work, which will be submitted to client. Proof that the
SWPβs are discussed with all employees on site should be available in the site safety file.
The construction manager / supervisor shall conduct Planned Task Observations (PTO).
PTOs shall be conducted in such a way that the employee is observed against the actual steps of
the safe work procedure (SWP)/ method statements and marked against compliance with each step.
This will assist in determining employee competence and compliance. Record shall be kept. The
findings raised on the PTOs must be addressed/discussed with all employees on site to ensure
conformance and adherence to safe work procedures and method statements.
The minimum items that must be in the PTO but not limited to:
a. Project name.
b. Title of the SWP, reference number and revision number.
c. Specific activity.
d. Steps.
e. Safety Steps.
f. Critical steps.
g. Follow-up action.
h. Observation conducted by (full name).
i. Designation (e.g., supervisor).
j. Individual/Team observed names.
k. Date of observation.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
l. Signature.
Work at Elevated Positions and Roof Work
The Principal Contractor shall ensure that all work performed at elevated positions conform to
the requirements of the Construction Regulations, the relevant Unit Standard (US) and 32-418
(Working at Height Procedure).
assessments will be compiled, implemented, reviewed, and communicated to all employees
working at heights.
at intervals to be determined by the principal contractor, and taking into consideration:
a. Incident trend analysis, or new/revised technology.
b. Changes to scope of work, changes to work methods/procedures/equipment, etc.
weather.
safety harness shall be worn when working at an elevated position. All FAS equipment in use
must meet the specifications outlined in the OHS Act and the following applicable standards:
a. SANS 50361:2003
b. SANS 50363:2003
c. SANS 50353-1:2003
d. SANS 50354:2003
e. Eskom Work at Heights Standard 32-418
f. Eskom Personal Protective Equipment (PPE) for Work-at-Heights Specification 240-
Working in elevated positions shall only be carried out under the supervision of a competent
person in accordance with US 229995.
possible:
a. Fall protection equipment shall comply with Unit Standards and other recognised
international standards.
b. The Principal Contractor and/or his contractor shall compile a fall protection equipment
inspection, testing and maintenance procedure (Refer to SANS 50365 and manufactures
requirements for safe use and for inspections).
the protection of persons working below. A drop zone shall be established with barricading and
necessary signs.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
29.1 Ladders (Portable)
a) Ladders used on the site shall comply with the OHS Act and Regulations, the relevant
SANS standards, or other recognised international standards.
b) Damaged ladders shall be clearly marked and quarantined and removed from the project
site.
c) Prior to work being performed, an adequate risk assessment shall be conducted, and
work shall be conducted in accordance with General Safety Regulation 6 and 13A and
Construction Regulation 10 of the OHS Act
29.2 Training and authorization
a) Every employer shall ensure that no person engages in any activity in relation to work at
heights unless they are competent to do so.
b) Only training providers that use competent training instructors and assessors who are
SETA-Accredited and SAQA-registered in terms of the relevant unit standards shall be
used.
c) All persons who work at heights or who are required to do rescue at heights shall receive
three days of Fall Arrest System (FAS) training and two days of rescue training in
accordance with the Unit standards 22998 and 229995.
d) The Contractor must ensure that all persons who work at heights and those who will be
required to do rescue at heights shall receive training according to the relevant unit
standards. As a minimum, individuals who work at height and are not responsible for
performing a rescue must undergo three days of FAS training (Unit Standard 229998)
and rescuers must further undergo two days rescue training in accordance with the Unit
Standard 229995. Rescuers must be appointed in writing for the site/project.
e) Official FAS training shall not have an expiry date on the certificate.
f) Only the training date shall be indicated on the certificate.
g) Official rescue training shall expire every three years from the date of issue.
h) The principal contractor shall ensure that there is a Level 2 First Aider trained for every
team working at height. See Annexure L - all line construction First Aider shall be level 3
NB: All work at heights appointments and competency certificates shall be kept in the Health and
Safety File.
The principal contractors and contractors shall identify the occupational stressors which could
include exposure to chemical and biological hazards, noise, dust, vibration, heat, etc., to which any
person may be exposed because of his work activities.
30.1 Occupational Hygiene Management Program
Principal Contractors and contractors shall develop, implement, and maintain an occupational
hygiene management programme to ensure that the occupational hygiene stressors are identified
assessed (monitored) and controlled. The occupational hygiene programme shall include, but not
limited to the following elements:
a. Occupational health risk assessment as a foundation.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
b. Occupational hygiene monitoring program. Monitoring shall be performed by a SANAS
accredited AIA.
c. Communication of occupational hygiene results and requirements.
d. Conduct awareness trainings and keep registers; and
e. Keep Occupational Hygiene surveys reports for a period of 40 years.
Where there are occupational hygiene stressors, principal contractors and contractors shall ensure
that occupation surveys are conducted to assess stressors. These programs may include but not
be limited to:
a. Hearing Conservation Programme.
b. Heat and cold stress Management Program.
The principal contractors and contractors shall report to the Department of Employment and Labour
on occupational hygiene milestones (e.g., crystalline silica). Evidence of reporting and copies of
such reports shall be made available to the client senior advisor H&S / H&S officer.
Copies of all occupational hygiene surveys conducted by the principal contractor and contractor shall
be submitted to PD Management/Occupational Hygiene Practitioners for information and record
keeping.
The principal contractor shall provide and adhere to effective monitoring procedures. These
procedures shall include the planning, carrying out and recording of the results of the measurement
programme. This is to confirm the effectiveness of the implemented control measures, and the
results shall be made available to the Contracts Manager/Employerβs Representative on request.
Note: Principal contractors and contractors are responsible to measure and monitor all Occupational
Hygiene stressors as contemplated in the Occupational Health and Safety act 85 0f 1993.
30.2 Medical Surveillance Programme
The Principal Contractor and contractor shall ensure that their employees are registered on a
medical surveillance programme and are in possession of a valid medical fitness for duty certificate
specific to the construction work to be performed. The Fitness for duty certificate shall be in form of
Construction Regulation, Annexure 3, and be relevant to the type of work (risk based) that the
employee will be exposed to.
The principal contractor and contractors shall ensure that employees have undergone pre-entry
medical examination before starting work on site. No employee shall access site without a valid
medical fitness for duty certificate.
The principal contractor and contractors shall ensure that employees undergo a periodic medical
examination as and when a need arise.
The Principal Contractor and contractors shall ensure that employees undergo an exit medical
examination at the end of the project or when the service of the specific employee has been
terminated or has expired.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
Note.: The client will only accept medical surveillances conducted by an Occupational Health
Practitioner who holds a qualification in occupational health and registered with Health Professions
Council of South Africa (HPCSA).
30.3 Pre-Existing / Current Medical Condition
30.3.1 Disclosure of pre-existing injuries or medical conditions
A pre-existing condition as defined by the OHS Incident Management Definitions and Classification
Parameters Standard (240-131838225), is a medical condition/medical impairment as a result of an
incident arising out of, and in the course of employment, shall be considered:
a) Non-work-related if the incident arises solely because of a pre-existing medical
condition/medical impairment and if a worker without such a condition/medical impairment
would not have suffered such an incident; or
b) Work-related if the incident arises where the pre-existing condition/medical impairment may
have been a contributing factor.
Note 1: Principal contractors are to follow their own processes and procedures for classification. At
a minimum, the decision about the impact/implication of such pre-existing medical condition/medical
impairment must be confirmed by an occupational medicine practitioner (as defined in the OHS Act,
section 1).
Pre-existing medical conditions can include health issues such as cancer, diabetes, lupus,
depression, acne, hypertension, asthma, arthritis, ulcerative [Allergies] colitis etc or just about any
other health condition such as previous medical operational condition in any part of the body.
An injury are any old injuries that existed prior to the work injury that may or may not have fully
healed. Some workplace environments could aggravate pre-existing conditions even if they would
not necessarily have caused a new condition in an otherwise healthy individual. Examples may
include amongst others, traumatic injury worsening back pain, joint pain (condition), sore neck, knee
injuries etc.
30.3.2 A prospective employer / Supplier expectations/ duties
A prospective employer / supplier shall:
a) request a prospective worker to disclose all pre-existing injuries or medical conditions existing
during the period of the employment process that could reasonably be expected to be
aggravated by performing their employment related duties.
b) request disclosure in writing and this request must be accompanied by details of the nature
of the duties that are subject to the employment.
c) advise prospective workers that if they knowingly supply false or misleading information, they
will not be entitled to compensation or damages under the Compensation for Occupational
Injuries and Diseases Act, Act for any event that aggravates the non-disclosed
pre-existing injury or condition.
d) ensure that pre-existing or current condition is part of:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
i). Individual employment contract. Because the contract defines the terms and
conditions of employment
ii). Included in the employment induction.
iii). Person Job Specification shall be developed to have a portion where the individual
when visiting the occupational medical practitioner, it has been completed by the
employer, employee and the medical practitioner can complete the document.
iv). The employee shall reveal any pre-existing or current medical condition to the
Occupational Medical Practitioner prior the assessment.
v). Part of toolbox talk at least monthly, and awareness conducted more often, and
vi). Records shall be kept.
30.3.3 A prospective contractor employee duty
A prospective employee must, where requested in writing by a prospective employer, disclose all
pre-existing injuries or medical conditions of which they are aware of, that could reasonably be
expected to be aggravated by performing the employment related duties. If the prospective
employee is engaged before making the disclosure (or being requested to make the disclosure),
his or her entitlement to compensation is unaffected.
However, if the prospective employee does not disclose pre-existing medical condition or injury,
this may have an impact on the future management of incidents in particular the work relatedness
or not of an incident which may be attributed or not to pre-existing conditions.
30.3.4 Key considerations for employers
Employers considering implementing changes to their employment conditions and processes in
relation to these amendments shall note:
a) it is the prospective employer's duty to request disclosure of pre-existing injuries or medical
conditions from prospective workers during the pre-employment, periodic and post
screening process, and such information shall be kept confidential.
b) when providing details of the nature of the duties that are subject to the employment, it is
important that this information is accurate and provides specific details of the nature of the
duties. The prospective employee must receive information that will enable them to make
an informed decision about whether their pre-existing injury or condition might be
aggravated by the duties.
c) if the Workers' Compensation Commissioner has previously provided a copy of the
employee's claims history summary the employer shall not:
i). disclose to anyone else the contents of or information contained in the
summary.
ii). give access to the document to anyone else.
iii). use the contents of or the information contained in the summary for any
purpose other than for the purposes of the employment process (penalties
apply).
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
d) changes to employment conditions and processes should be made in consultation with the
employer's human resources or advisor and employee representative. Employers who may
have queries concerning equal employment condition and processes should seek
independent advice.
e) employers shall keep accurate records relating to this disclosure as this information will be
requested where applicable during the claim determination process.
f) The employer shall follow their own disciplinary procedure and share the outcome with the
client.
Note:
I. The employer shall ensure that the employees are not exposed or expected to execute
an activity that will exacerbate the pre-existing or current medical condition. Risk
assessment shall be conducted to determine the area where the individual shall be
expected to execute the duties.
II. The pre-existing or current medical condition shall be applicable to new or current
employees within a specific employer.
III. The employer shall manage all the pre-existing or current medical condition (this
include referrals medical conditions) as per legal requirements as all information shall
be kept private and confidential all the time.
30.4 Emergency Care
A list of emergency numbers (local emergency numbers and Eskom Holdings (NTCSA)
ER24(084 124/010 205 3400) numbers) shall be posted where it is visible in the officeβs places such
as information H&S board, eating area etc. The principal contractor and contractor(s) shall ensure
that all employees are familiar with the emergency numbers. Where the principal contractor or/and
contractor(s) has established their own contract with a specific service provider, those numbers must
be part of the induction and be used in conjunction with local or Eskom Holdings (NTCSA) numbers.
The principal contractor must make clear to the employees that in any event one of the numbers
must be used or the combination to ensure that the life of the individual is preserved.
30.5 Employee Assistance Programs (EAP)
The contractor will engage the local clinics on HIV/AIDS Awareness programme. This will include
voluntary counselling and testing (VCT) of individuals, with chronic illnesses such as diabetes;
hypertension; HIV/AIDS awareness training. Ensure access to ongoing support for affected
individuals. The Contractor shall communicate the programme to all personnel.
30.6 Rehabilitation
The principal contractor and contractor(s) shall ensure rehabilitation of employees injured where
rehabilitation is required.
The treating Doctor/Hospital will recommend and refer. The principal contractor must comply with
recommendations, communicate with employee and provide transport according to the planned
appointment.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any
manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No
2021/539129/30
File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1
Construction of a concrete one million litre deluge Unique Identifier: 559-790983792
water storage tank at Apollo Conveter Station
Revision: 1
Page: of 39
The process shall continue until the rehabilitation of an employee is declared fit by the
Doctor/Hospital.
30.7 Compensation of Occupational Injuries and Diseases Act (COIDA)
The principal contractor and contractor(s) shall submit a valid letter of good standing with the
compensation fund or a licensed compensation insurer relevant for the construction sector.
a) The principal contractor shall provide a site-specific emergency preparedness and
response plan of which it shall include the specific activities being executed for site and
offices and submit this plan to the client for review.
b) The Emergency Preparedness Plans must be relevant to the scope of works and to the
prevailing surrounding environmental risks.
c) The principal contractor shall ensure that all the employees are fully conversant with this
plan.
d) The Principal Contractor shall plan, conduct emergency drills at specific intervals and
identify areas for improvement. The report shall be written and action plan where
applicable be developed and all the records shall be made available for inspection/audit
by the client and/or authorities.
e) When preparing worksite Emergency Preparedness Plans, cognisance must be made
as to the locality of the site and the response time for the emergency services. Where
sites are remote, contractor management shall ensure that enough employees are
trained in the various disciplines to be able to afford prompt response attention.
Contractors shall develop a fire safety procedure for the office/ campsite, which must meet the
requirements of the local authority fire department and Section 9 of the Environmental Regulations
for Workplaces.
The principal contractor must develop a comprehensive site layout plan with the following as a
supply on site; Regulations for
Inadequate rehydration / water/fluid Surveyors; shall develop and implement additional
Work
appointment of any contractor or supplier and before the commencement
of work
construction
work.
in SANS 10280 and ORHVS is prohibited.
Title: Supplier Quality Management: Document Identifier: 240-105658000
Alternative Reference QM 58
Number:
Area of Applicability: Eskom Holdings SOC Ltd
Functional Area: Quality Management
Revision: 3
Total Pages: 28
Next Review Date: October 2024
Disclosure Controlled Disclosure
Classification:
Compiled by Supported by Functional Authorized by
Responsibility
SA Sambo P Dondashe L Meyer K Pather
Chief Advisor Middle Manager Acting Senior General Manager
Quality Quality Manager Quality Risk and
Management Management Management Sustainability
Date: 15/10/2021 Date: 15/10/2021 Date: 15/10/2021 Date: 17 October 2021
EDC TN Formatted 15.10.2021
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Content
. Introduction ............................................................................................................................... 3
2.1 Scope ............................................................................................................................... 3
2.1.1 Purpose ................................................................................................................. 3
2.1.2 Applicability ........................................................................................................... 3
2.1.3 Effective date ......................................................................................................... 3
2.2 Normative/Informative References ................................................................................... 3
2.2.1 Normative .............................................................................................................. 3
2.2.2 Informative............................................................................................................. 3
2.3 Definitions ........................................................................................................................ 4
2.4 Abbreviations ................................................................................................................... 5
2.5 Roles and Responsibilities ............................................................................................... 6
2.6 Process for Monitoring ...................................................................................................... 6
2.7 Related/Supporting Documents ........................................................................................ 6
3.1 Supplier and Sub-Supplier Quality Management System Requirements .......................... 7
3.2 Quality Plan ...................................................................................................................... 8
3.3 Contract Quality Plan........................................................................................................ 8
3.4 Quality Control Plan ....................................................................................................... 10
3.5 Pre-Contract Award: Quality Requirement ...................................................................... 13
3.6 Main Supplier and Sub-supplier Capability and Capacity Assessment ........................... 16
3.7 Post-Contract Award ...................................................................................................... 17
3.7.1 Contract Execution .............................................................................................. 17
3.7.2 Supplier Quality Performance Monitoring Phase ................................................. 18
3.7.3 Supplier Quality Audit .......................................................................................... 18
3.8 Standard Conditions ....................................................................................................... 19
3.8.1 Rights of Access .................................................................................................. 19
3.8.2 Eskom Rights to Information ................................................................................ 20
3.8.3 Preservation ........................................................................................................ 21
3.8.4 Quality Audits Related Conditions ....................................................................... 25
3.8.5 Management of Nonconformities and Nonconforming Outputs Identified by
Eskom ................................................................................................................. 25
3.8.6 Special Processes ............................................................................................... 26
Acceptance ............................................................................................................................. 27
Revisions ................................................................................................................................ 27
Development Team ................................................................................................................ 27
Acknowledgements ................................................................................................................ 28
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The intention of this specification is to specify and describe the minimum quality requirements for all
existing and potential Eskom suppliers and define the quality criteria for the selection, evaluation,
vendor registration, management, monitoring, assessment and auditing of suppliers. Eskomβs
position is to partner with suppliers who fully demonstrate commitment to the development,
implementation, and maintenance of a quality management system (QMS) that conforms to the
requirements of ISO 9001 standard. The priority is to encourage suppliers to continually improve
their QMS and enhance service delivery by implementing and conforming to the standard.
2.1 Scope
2.1.1 Purpose
The purpose of this specification is to outline the requirements according to which suppliers shall
ο· develop,
ο· implement,
ο· maintain, and
ο· continually improve
a quality management system (QMS) based on ISO 9001, which should form the basis for conformity
to Eskom quality requirements and continually adhere to them throughout the duration of a contract
2.1.2 Applicability
This specification shall apply throughout Eskom Holdings Limited divisions, its subsidiaries,
suppliers, and sub-suppliers and shall form part of all Eskom requests for information (RFI)/ requests
for quotation (RFQ)/ requests for proposal (RFP), including contracts for the procurement of products
and services.
2.1.3 Effective date
Date of authorisation of the specification
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
[1] ISO 9001 Quality Management Systems β Requirements
[2] ISO 10005 Quality Management Systems β Guidelines for Quality Plans.
2.2.2 Informative
[3] ISO 9000 Quality Management Systems β Fundamentals and Vocabulary
[4] 32-727: Safety, Health, Environment, and Quality (SHEQ) Policy
[5] ISO 10006 Quality Management Systems β Guidelines for Quality Management in Projects
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
[6] ISO 9004 Quality Management β Quality of an Organisation β Guidance to Achieve Sustained
Success
[7] 32-1033: Eskomβs Procurement and Supply Chain Management Policy
[8] 32-1034: Eskomβs Procurement and Supply Chain Management Procedure
[9] PPPFA: Preferential Procurement Policy Framework Act, 2000 (Act No. )
[10] CIDB 1004: Best Practice Guideline A4: Evaluating Quality in Tender Submissions
[11] 240-12248652 Supplier Quality Management: List of Tender Returnables
[12] IAEA Safety Standard GS-R-3.1 Application of the Management System for Facilities and
Activities
[13] SANS 10845-1 Construction Procurement Part1: Processes, Methods and Procedures
2.3 Definitions
The vocabulary of ISO 9000 and the following definitions apply in the application of this specification.
2.3.1 Component: a constituent part of the product or sub-assembly of the product. The product
may comprise multiple individual components
2.3.2 Contract Quality Plan: a document of the supplierβs process for delivering the level of quality
required by the contract. It is a framework for the contractorβs process for delivering quality.
Purpose of a CQP is to outline how the results defined in the specifications will be achieved.
2.3.3 Hold Point: a predetermined stage in the quality control plan (QCP) beyond which work/
manufacturing shall not proceed without the attendance of, and written authorisation of, an
Eskom representative or Eskom inspection agency, whichever is applicable.
2.3.4 Intervention Points: those control points indicated by the various controlling bodies
concerned with the implementation of a specific QCP/ ITP. These can be in the form of
inspection, hold points, surveillances, witnesses, reviews and verifications.
2.3.5 Inspection Agency: an organisation or person appointed by Eskom for the purpose of
performing quality assurance/ quality control, monitoring, inspection and/ or expediting
services.
2.3.6 Level 1 Plant Items: equipment, whose failure has an effect on personnel safety and/ or
health, causes an environmental incident, cause a huge production loss or major equipment
damage. Equipment that are safety/ redundancy/ protective device or covered by statutory
regulations requirements.
2.3.7 Level 2 Plant Items: equipment, whose failure impacts plant availability and/or reliability,
causes significant costs or secondary damage.
2.3.8 Level 3 Plant Items: equipment that does not impact on personnel safety and/ or health,
environmental, cost, availability and/ or reliability of plant.
2.3.9 Nonconformity: a deficiency in material, composition, characteristic, or performance that
renders the quality of an item, component, or product unacceptable or indeterminate. The
term also covers a deficiency in, or deviation from/non-adherence to, the quality management
system requirements, prescribed production processes, and/or related documentation such
as procedures and instructions.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
2.3.10 Quality Plan: specification of the actions, responsibilities and associated resources to be
applied to a specific object.
2.3.11 Quality Control Plan: a document specifying the activities to be inspected throughout the
execution of the project, inclusive of test methods, procedures, and acceptance criteria (This
term is equivalent to QIP and ITP).
2.3.12 Requirement: the need or expectation that is stated, generally implied, or obligatory.
Requirements are generally specified in the purchase order and/or contract documentation,
but may not be limited to these.
2.3.13 Primary Plant (Power Plant): primary plant include High Voltage equipment situated inside
the control room (breakers, bus-bars, CTβs, VTβs and transformers).
2.3.14 Secondary Plant (Control Plant): secondary plant includes all equipment used to control
and protect the HV equipment on the primary plant side. (Protection, metering, AC/DC and
tele-control).
2.3.15 Special Process: is any production or service process which generates products or services
which cannot be measured, monitored, or verified prior to delivery and use.
2.3.16 Supplier: is a current or potential supplier, vendor, contractor, consultant, or service provider.
A supplier may be a natural or legal person and includes any employee acting within the
course and scope of his/her employment or any agent or manager acting for, or on behalf of,
or in the interests of, the person registered as supplier on the Eskom supplier database.
2.3.17 Sub-supplier: an organisation that provides a product/service to the supplier and/or that
enters into a subcontract and assumes some of the obligations of the supplier or prime
contractor.
2.3.18 Witness Point: a predetermined stage in the quality control plan where and inspection
activity will take place. Work may proceed, provided Eskom or its inspection agency has been
formally notified and confirmed that inspection is waived.
2.4 Abbreviations
Abbreviation Explanation
AIA Approved Inspection Authority
CA Corrective Action
CQP Contract Quality Plan
FIDIC Federation Internationale Des Ingenieurs- Conseils
FMECA Failure Mode, Effects and Criticality Analysis
HAZOP Hazard and Operability Study
ISO International Organisation for Standardisation
ITP Inspection and Test Plan
NC Nonconformity
NDT Non Destructive Testing
PMI Positive Material Identification
QCP Quality Control Plan
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Abbreviation Explanation
QMS Quality Management System
PQP Project Quality Plan
RFI Request for Information
RFQ Request for Quotation
RFP Request for Proposal
SHEQ Safety, Health, Environment, and Quality
SETA Skills Education Training Authorities
WPS Welding procedure specifications
WQR Welderβs Qualification Record
2.5 Roles and Responsibilities
Eskom Quality representative/ professional will select applicable requirements for existing and
potential Eskom suppliers using Form A (Tender and Contract Quality Requirements for Supplier
Quality Management: Specification 240-105658000/ QM 58 and Quality Requirements for ISO 9001
Standard).
The existing and/ or potential suppliers must complete, sign and return Form A with the other
returnable as listed in the List of Tender Returnable document (240-12248652). Other roles and
responsibilities for this standard are defined within the text of this specification.
2.6 Process for Monitoring
The application of this specification throughout Eskom shall be audited as per the management
system audit schedule.
2.7 Related/Supporting Documents
The documents superseded by this specification: all divisional and business unit supplier quality
requirements standards and/or specifications.
Forms and templates:
[1] 240-68099512 Tender and Contract Quality Requirements for Supplier Quality Management
Specification 240-105658000/ QM 58 and Quality Requirements for ISO 9001 Standard (Form
A)
[2] 240-109253698 Template for a Typical Contract Quality Plan
[3] 240-109253302 Quality Control Plan/Inspection and Test Plan
[4] 240-126469599 Method Statement Template.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The quality assessment criteria and Form A of this specification will be selected and completed by
an Eskom Quality representative/ professional who will identify the applicable supplier quality
requirements to be met.
Form A of this specification must also be completed and signed by the supplier responding to an
Eskom invitation to tender, in order to acknowledge and accept Eskom Supplier Quality requirements
as per this specification and ISO 9001 Standard or any additional quality requirements specific to
the scope of work.
3.1 Supplier and Sub-Supplier Quality Management System Requirements
3.1.1 The supplier and sub-supplier shall develop, implement, maintain and improve a formal QMS
that conforms to the latest ISO 9001 standard or any applicable standard of QMS (latest
applicable revision) and in accordance with the requirements of this specification.
3.1.2 Such a formal system shall consist of the appropriate documented information required by
ISO 9001 and may include a quality manual, quality plans, work procedures, work
instructions, method statements, work flow documentation, etc., as the case may be. This
requirement constitutes the most basic QMS requirements.
3.1.3 Unless specifically excluded from the quality list of tender returnable, as per the categories of
quality requirements (Category 1, 2, 3, or 4), such a QMS shall carry a valid ISO 9001
certificate from an accredited certification body, as indicated in the applicable Eskom
invitation (this requirement applies equally to both the supplier and any/ all manufacturing
third-party organisations mentioned above).
3.1.4 Unless specifically excluded in the quality list of tender returnable, as per the categories of
quality requirements (Category 1, 2, 3, or 4), the supplier shall have a fully developed,
documented, implemented, reviewed and maintained QMS that complies with the
requirements of ISO 9001 standard or any applicable standard of QMS. In the event that the
main supplier invariably requires the assistance of a sub-supplier in order to realise its own
supply obligations. The aforementioned requirement applies equally in all cases where any
such sub-supplierβs scope of responsibility includes the provision of any of the following
activities, namely, design and development, manufacturing, maintenance, testing, storage,
delivery, installation, commissioning, and project management, or in the cases the supplier
name changes, mergers, acquisitions and/ or cessions. Eskom Quality department must
ensure that the changed entity can still fulfil the requirements as set out in the contract
documentation.
3.1.5 Eskom reserves the right to request and perform necessary assessments at sub-supplier
facilities.
3.1.6 The main supplier shall be responsible for defining and managing the specific quality
assurance and control elements applicable to the respective sub-supplierβs scope of
work/supply and ensure that its sub-supplier(s) quality programmes support Eskom
requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.1.7 The supplier shall inform Eskom of any proposed changes to the QMS or staff that will affect
the quality system prior to implementation of these changes.
3.1.8 The main supplier shall develop and implement a performance management programme for
their sub-supplier. The programme shall include, but not limited to:
ο· Verification of the QMS
ο· Audits and surveillances
ο· Regular assessment of the CQPs and reviews of QCPs.
ο· NC and Defect Management
ο· Inspection and test plans
ο· Risk management
3.2 Quality Plan
The information in this section constitutes the minimum requirements for a quality plan.
3.2.1 Where specified in the Evaluation Criteria and/ or quality list of tender returnables , as per the
categories of quality requirements (Category 1, 2, 3, or 4); all individual products, services
and processes shall have a documented, implemented, reviewed and maintained contract
quality plan and/or quality control plan (inspection and test plan).
3.2.2 Where specified in the evaluation criteria and/ or quality list of tender returnables. All
production and/ or service provision shall be carried out in accordance with a documented
and agreed contract quality plan (CQP) and/ or quality control plan (QCP)/ inspection and test
plan (ITP).
3.2.3 The supplier shall plan for the required quality-related activities and interfaces within the
supplierβs quality system in order to demonstrate its ability towards both controlling and
meeting specified Eskom requirements.
Note 1: Contract Quality Plan should address the quality assurance elements related to the scope
of work and/ or technical specification.
Note 2: Quality Control Plan (QCP)/ Inspection and Test Plan (ITP) should address the quality
control elements related to the scope of work and/ or technical specification.
3.3 Contract Quality Plan
The main supplier shall require sub-suppliers to submit project quality plans (PQPs)/ contract quality
plans (CQPs) and associated documentation in accordance with the requirements of project QMS
processes applicable to the sub-supplierβs scope of work.
The supplier shall, where applicable, based on scope of work criticality, ensure that procurement
documents clearly and unambiguously require sub-supplier submission of a sub-supplier CQP for
supplier and Eskom review.
The main supplier shall ensure that sub-supplier CQPs are developed and implemented in
accordance with the ISO 10005 Quality Management System Guidelines for Quality Plans. In
addition to the elements specified in ISO 10005, the supplierβs and/ or sub-suppliersβ CQPs shall
include the following (as applicable):
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.3.1 The management of records, including material tests, positive material identification (PMI)
testing, material certification, etc.
3.3.2 The provision for free and uninhibited access by the supplier and/or personnel at the time of
inspection.
3.3.3 The proposals for submission of final documentation, the final manufacturing data book, prior
to shipment.
3.3.4 The special processes related to welding: management of the welderβs qualification record
(WQR), welding procedure specifications (WPS), and procedures qualification records (PQR)
that will be used in the performance of work for supplier review and acceptance prior to
commencing manufacture. Welders shall be qualified to the specified Codes of Construction
for the applicable procedures. The requirements for qualification shall be specified by the
supplier, and welder records shall be maintained by sub-suppliers performing the work.
3.3.5 The special installation procedures and other required fabrication or manufacturing
procedures (that is, those required for post-weld heat treatment, tube rolling, coatings, etc.)
that will be used in the performance of work shall require supplier review and acceptance
prior to commencing manufacture. The personnel carrying out special processes (for
example, NDE, welding, coating, heat treatment, etc.) where the results cannot be fully
verified by subsequent inspection and test shall be suitably qualified and, where applicable,
registered with statutory bodies as legally required, that is, as radiographic workers to conduct
radiography. The requirements for the qualification shall be specified, and personnel records
shall be maintained in accordance with the Project Quality Personnel Qualification
Specification and, where applicable, legal requirements.
3.3.6 The personnel required to perform special processes shall be certified competent through a
certificate of competency in accordance with the companyβs internal training management
and competency control procedures or an external certification body (for example, NDT)
through an accredited service provider as per Skills Education Training Authorities (SETA)
requirements.
3.3.7 All personnel who perform activities that affect quality shall have their training needs identified
and documented. The required training shall be implemented in accordance with the
companyβs training management and competency control procedures. All the training
certificates shall meet the SETA requirements in terms of having the unit standard completed
and the accreditation number of the service providers.
3.3.8 Instructions and requirements for equipment and materials storage, preservation, and
maintenance, including identification of materials required for preservation and maintenance,
are to be provided sufficiently prior to receipt (prior to shipment or earlier) to ensure that
appropriate resources are available at the time of delivery.
3.3.9 Specific quality monitoring and verification activities are to be undertaken on the supplierβs
sub-suppliers by Eskom or it agent.
3.3.10 The CQP information need to include, but not limited to:
ο· Spells out the aspects of the QMS to be applied within a specific Eskom project, and the
methods to be utilised to ensure quality.
ο· Outline the resources, the communication channels, applicable documents and records to be
generated.
ο· Management Authority and Responsibility from both supplier and client need to outline in the
Cqp.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
ο· List of documents and records that will be used and submitted during the execution of the
project.
ο· Communications channels should include contact person and contact details
ο· Monitoring & measurement procedures for activities need to be indicated.
3.3.11 The main supplier and sub-supplier CQPs shall comply with the Eskom Quality Requirements
Specifications and shall be submitted prior to the initial scope of work kick-off or initial pre-
fabrication meeting and prior to commencement of manufacturing, whichever is earlier.
3.3.12 The Eskom template for CQP provided shall be used as guideline, where the supplier does
not have a CQP template.
3.4 Quality Control Plan
The supplier shall develop and implement processes and procedures that efficiently and effectively
monitor, verify and document the quality of the scope of work for deliverables.
The main supplier shall ensure that sub-supplier QCPs/ ITPs are prepared at a level of detail
sufficient to address all quality-control-related activities in a chronological order, from contract review
through materials verification, manufacturing, fabrication, assembly, final testing, commissioning,
hand-over documentation, and certification. In addition, the supplier shall ensure compliance with
the following requirements:
3.4.1 All stages of manufacturing, fabrication, assembly and installation shall be controlled by a
supplierβs QCP/ ITP that clearly and unambiguously identifies the quality verifications to be
performed and special attention to controls related to critical products and services.
3.4.2 QCP/ ITP shall be reviewed and accepted by Eskom, its inspection authority or agency, and
they shall allow for the insertion of Eskom specific requirements, including hold and witness
points prior to the commencement of work.
3.4.3 Subsequent changes to the Eskom accepted QCP/ ITP shall require Eskom, its inspection
authority or agencyβs agreement prior to the commencement of work involving an activity
affected by such changes.
3.4.4 The ITPs should cover materials certification, fabrication works, in-process inspections, final
acceptance tests, packaging and pre- shipment/ transportation, shipping/ transportation
inspections where contracted, preservation, site acceptance tests, construction and erection
works, and pre-commissioning and commissioning tests.
3.4.5 All sub-supplier QCP/ ITP activity shall be performed using an Eskom-accepted supplier
Qcp/ itp.
3.4.6 All applicable codes, standards, and relevant acceptance criteria documents are available at
the work location, and Eskom representatives on site shall have on-going access to this
information. Workplace documentation shall be available in English and in any workforce-
appropriate language.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.4.7 Where activities subject to inspection and test procedures are to be undertaken by a sub-
supplier, the QCP/ ITP shall make reference to this fact and shall include descriptive details
of the sub-supplierβs involvement. A separate QCP/ ITP shall be required for each sub-
supplier scope of work.
3.4.8 The supplier shall be ultimately accountable and responsible for the development and proper
implementation of all sub-supplier QCPs/ ITPs, including those reviewed or developed by
sub-suppliers.
3.4.9 Eskom reserves the right to select intervention points on QCPs/ ITPs for Eskom oversight of
selected functions and to perform surveillance or audits of the work.
3.4.10 Once signed, the ITPs and QCPs become addendums to the main contract. These ITPs can
be reviewed at Eskomβs discretion based on its assessment of the supplierβs performance or
other risks.
3.4.11 A QCP/ ITP shall contain the following information:
ο· Eskom contract number and title
ο· The supplierβs order number
ο· Identification of the area of works/contract
ο· Description of the work, with components, item number, and activity date
ο· QCP/ITP unique number
ο· A list of the sequence of operations, including inspection and tests
ο· The identification of the specification, drawing number, or procedure for each operation,
with reference to the relevant criticality risk rating
ο· The acceptance criteria, with reference to the technical specification, in-house, national, or
international standard, with the relevant clause number for each operation
ο· The inspection and test activities that the supplier has nominated for its intervention points
ο· Provision for the inclusion of intervention points nominated by Eskom and/or its authority/
agency
ο· Provision for intervention point acceptance by date and signature for all parties having
intervention in the plan
ο· Inspection and test records to be generated by the supplier for each operation and an
indication of records to be provided to Eskom (as applicable)
3.4.12 The main supplier shall require sub-suppliers to submit QCPs/ ITPs and associated
documentation applicable to the sub-supplier scope of work. Any changes made to the QCP
after submission must be resubmitted to Eskom for further review. The supplier shall ensure
that all sub-supplier QCPs/ ITPs are in compliance with the Eskom Quality Requirements
Specifications, including, but not limited to, the following requirements:
ο· Clear and unambiguous description of the equipment and location(s) at which each activity
will take place, including facility location(s)
ο· Identification of quality verification activity and stage
ο· The details of reference documents, procedures, or method statements to be utilised in
performance of the activity, including specific reference to actual sections and pages of
procedures, standards, instructions, specifications, etc.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
ο· Definition of acceptance criteria
ο· Listing of certifying or verifying documents generated to provide evidence of compliance
with specified requirements; documents are to be provided using the proper Eskom
document numbering requirements
ο· Identification of main supplier and sub-supplier (where applicable) third-party/approved
inspection authority (AIA) and Eskom inspection activities defined in terms of witness, hold,
document review, and verification monitoring points and provision for sign-off of each of the
above-mentioned parties for each intervention point
ο· Qualification requirements for quality control inspectors, including any third-party/AIA
inspectors
ο· Listing of all proposed test procedures
ο· Acceptance criteria for each inspection or test in alignment with specified tolerances
ο· A section for signed acceptance of the QC/ITP by the supplier, sub-supplier (where
applicable), and Eskom prior to commencement of work
ο· Inspection or testing intervention points, including, but not limited to, factory acceptance test
and package acceptance test, witness, and hold points
3.4.13 A quality kick-off meeting will be held at the start of the contract and, if required, at the start
of each subsequent phase.
ο· The supplier shall arrange coordination meetings with Eskom prior to placement of orders
for items or equipment to ensure that all technical and commercial requirements are clear
and understood. Fourteen daysβ advance notice of meetings shall be given to Eskom.
ο· Supplier inspection personnel, including inspection agency personnel, shall be competent
and qualified to perform inspection and testing assignments. Mobilisation of all such
personnel shall be in compliance with the Project Quality Personnel Qualification
Specification.
3.4.14 Where QCP/ ITP is applicable, the supplier shall ensure that sub-suppliers are provided with
comprehensive, clearly written, and unambiguous inspection and testing protocols, including
processes, procedures, and methods that shall include, but not be limited to, the following:
ο· Requirements for inspection checklists and inspection assignments, with lists of items to be
inspected
ο· An inspection and testing report format, report content, schedule for report processing and
distribution, and report retention requirements
ο· Inspection and test report results response tracking (log) and resolution of nonconformity in
inspection and test processes, procedures, or methods and nonconformity identified in
inspection and test results
ο· Associated Failure Mode, Effects and Criticality Analysis (FMECA) reports relating to the
equipment and sub-systems (if applicable)
ο· Hazard and Operability Study (HAZOP) report, as applicable
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.4.15 The supplier shall establish processes and procedures for formal assessment of sub-supplier
inspection and testing programmes. These shall include review of sub-supplier inspection
reports and other quality control documentation. Additional formal assessment of
manufacturing, fabrication, and assembly facility operations shall be conducted by the
supplier to ensure continuing suitability, adequacy, and effectiveness of the sub-supplierβs
inspection and testing programmes. Assessment frequency shall be established in
consideration of the sub-supplier scope of work, criticality of scope of work deliverables, and
performance information. The assessment scope and schedule shall be developed in
consultation with Eskom.
3.4.16 Supplier processes and procedures for verification of supplier and sub-supplier purchased
product compliance with specifications shall obtain document return/review status prior to
implementation.
3.4.17 The objective is to finalise any outstanding procedural or other issues before proceeding to
deliver the works.
3.4.18 Eskom, in consultation with the supplier, develops an agenda for the meeting, and Eskom will
keep minutes of these meetings.
3.4.19 Mandatory pre-inspection meetings will be convened by Eskom or its inspection agency or
AIA to be attended by the supplierβs and sub-supplierβs representatives, including their quality
representatives who will be involved in the works, and records are to be kept.
3.4.20 Eskom reserves the right to appoint resident quality inspectors who can be based at the
supplierβs or sub-supplierβs premises and on site where the work is being performed. The
supplier is expected to provide workspace at no cost to Eskom for the inspector, as required.
3.4.21 Eskom may appoint any organisation it prefers to perform quality assurance and quality
control activities, either in the capacity as an AIA or inspection agency, on the works
contracted to the supplier, and the supplier or its sub-suppliers may not object, prevent,
hinder, undermine, circumvent, question, discredit, or in any way make it impossible for such
organisation to carry out its work on behalf of Eskom.
3.4.22 The Eskom template for QCP/ ITP provided shall be used as guideline, where the supplier
does not have a QCP/ ITP template.
3.5 Pre-Contract Award: Quality Requirement
3.5.1 Main Supplier and Sub-supplier Categories
Eskom supplier quality requirements for all existing and potential suppliers and sub-suppliers are
classified into four categories (category 1, 2, 3 and 4). Suppliers must prepare and submit quality
documentation as per the tender selected category (indicated in Form A) using the list of tender
returnables document.
NOTE: Only one (1) category must be applicable per procurement process e.g. [Eskom requests for
information (RFI)/ requests for quotation (RFQ)/ requests for proposal (RFP), including contracts for
the procurement of products and services].
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The following are the minimum returnable documentation for Categories 1 to 4:
3.5.2 Category 1: Quality Requirements
ο· The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
ο· The supplier shall submit a valid copy of ISO 9001 or any applicable certificate of a QMS (the
latest applicable revision). The QMS should drive the supplierβs business management
processes to ensure that all of Eskomβs requirements are fully met on a consistent basis.
ο· The supplier shall submit the latest copy of the management system internal and external
audit reports. The audit reports must include, if applicable, nonconformity identified, and the
resulting remedial actions (correction and/ or corrective action reports).
ο· The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
ο· Where applicable; the supplier shall submit a draft, or an example of an inspection and test
plan (ITP) or quality control plan (QCP) on similar and/ or previous work done.
ο· The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
ο· The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
ο· The supplier shall submit documented information retained (records) of management review
meetings that include agenda, meeting minutes, attendance registers, reports, presentations,
etc.
Note: specific requirements per tender will be selected using the List of Tender Returnable
documents (240-12248652).
3.5.3 Category 2: Quality Requirements
ο· The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
ο· The supplier shall submit objective evidence of a developed, implemented and maintained QMS
that complies with ISO 9001 or any applicable standard of quality management system (the latest
applicable revision). The following documents (approved/ signed copies) shall be submitted:
ο§ Quality Management System manual or a documented information that have defines and
describes the QMS and its scope
ο§ Quality Policy, aligned with the supplierβs strategic direction (documented information)
ο§ Quality Objectives (documented information)
ο§ Control of documented information (both maintain and retain documented information )
ο§ Internal audit procedure (documented information)
ο§ Control of nonconforming outputs (documented information)
ο§ Nonconformity and Corrective action procedure (documented information)
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
The QMS should drive all the supplierβs business management processes to ensure that all of
Eskomβs requirements are fully met on a consistent basis.
ο· The supplier shall submit the latest copy of the management system internal audit reports. The
audit reports must include, if applicable, nonconformity identified, and the resulting remedial
actions (correction and/ or corrective action reports).
ο· The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
ο· Where applicable; the supplier shall submit an example of inspection and test plan (ITP) or
quality control plan (QCP) on similar or previous work done.
ο· The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
ο· The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
ο· The supplier shall submit documented information retained (records) of management review
meetings that include agenda, meeting minutes, attendance registers, reports, presentations,
etc.
Note: specific requirements per tender will be selected using the List of Tender Returnable
document (240-12248652).
3.5.4 Category 3: Quality Requirements
ο· The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
ο· The supplier shall submit objective evidence of a developed QMS that complies with ISO 9001
(or the latest applicable revision). The following documented information (approved/ signed
copies) shall be submitted:
o Quality management system manual or a (documented information) that have
defines and describes the QMS and its scope
o Quality Policy, aligned with the supplierβs strategic direction (documented
information)
o Quality Objectives (documented information)
o Control of documented information (both maintain and retain documented
information )
o Internal audit procedure (documented information)
o Control of nonconforming outputs (documented information)
o Nonconformity and Corrective action procedure (documented information)
The QMS should drive all the supplierβs business management processes to ensure that all of
Eskomβs requirements are fully met on a consistent basis.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
ο· The supplier shall submit a draft contract quality plan that is specific to the scope of work as
described in the tender documents. The plan must address the minimum requirements as per
Iso 10005.
ο· Where applicable; the supplier shall submit an example inspection and test plan (ITP) or
quality control plan (QCP).
ο· The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
ο· The supplier shall submit a copy of documented information for roles, responsibilities and
authorities in relation to the QMS. Examples of relevant documented information are;
organization charts, job descriptions, work instructions, duty statements, manuals, procedures.
NB: specific requirements per tender will be selected using the List of Tender Returnables
document (240-12248652).
3.5.5 Category 4: Quality Requirements
ο· The supplier shall complete and sign Form A (Enquiry/Contract/Quality Requirements for
Supplier Quality Management Specification 240-105658000/ QM 58 and ISO 9001).
ο· The supplier shall submit a quality method statement based on ISO 9001 and specific to the
scope of work.
ο· The quality method statement should address all the supplierβs business management
processes to ensure that all of Eskomβs requirements are fully met on a consistent basis.
ο· The supplier shall submit a signed/ approved quality policy (aligned with the supplierβs strategic
direction). (documented information)
ο· The supplier shall submit a copy of quality objectives. (documented information)
ο· The supplier shall submit documented information for Control of Externally Provided Processes,
Products and Services.
ο· The supplier shall submit a copy of the documented information for roles, responsibilities and
authorities, specific to the project/ scope of work/ technical requirements. Examples of relevant
documented information are; organization charts, job descriptions, work instructions, duty
statements, manuals, procedures.
Note: specific requirements per tender will be selected using the List of Tender Returnables
document (240-12248652).
3.6 Main Supplier and Sub-supplier Capability and Capacity Assessment
Supplier capability and capacity assessments shall be performed prior to contract award on potential
suppliers participating in Eskom Holdings procurement process to:
ο· provide products and services with high risk to operational sustainability
ο· work on critical plant and equipment
ο· supply of critical plant items or components
ο· provide special processes
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
All sub-suppliers used by the main supplier/ contractor, performing work on Eskom critical plant
equipment, supplying commodities and providing specialised services shall be subjected to the
capability and capacity assessment.
Critical plant includes the following:
ο· Generation Level 1 & 2 plant
ο· Transmission and Distribution Power Plant & Control Plant
ο· Mega Projects
All potential quality risks identified will be included in the assessment report provided for the tender
evaluation.
Note: Form A (Enquiry/ Contract/ Quality Requirements for Supplier Quality Management:
Specification 240-105658000/ QM 58 and ISO 9001) will be used to select and indicate whether
capability and capacity assessment will be conducted.
3.7 Post-Contract Award
3.7.1 Contract Execution
The supplier shall submit the following documents within 30 days or as per stated timeline after the
contract date, prior to the commencement of work, for acceptance by Eskom:
ο· The supplier shall complete a QCP before contract award. This shall be reviewed and
signed off by Eskom within 30 days or as per stated timeline after contract award.
ο· The supplier shall complete a quality control plan and ITP(s) for review and acceptance by
Eskom prior to the commencement of any work, inclusive of subcontracted work, within 30
days or as per stated timeline after contract award.
ο· The sub-supplier QCP/ ITP shall be submitted for review and comment by the supplier and
by Eskom within 30 days or as per stated timeline after the award of the tender. All supplier
and Eskom comments shall be resolved prior to commencing work.
ο· The equipment lists and an indication of pressurised components and systems.
Note: These plans are to be compiled in line with Eskomβs requirements and will have to be
discussed with, and approved by, Eskom prior to any work commencing.
ο· Correspondence shall be directed to the project manager, and periodic quality review
meetings shall be convened by Eskom with the supplier.
ο· The mandatory quality review meetings are to be convened by the nominated project quality
manager or his/her representative for the contract.
ο· Monthly quality performance and management reports are to be prepared by the supplier
during contract execution. The content of these reports shall be agreed by Eskom when
submitted to Eskom on a monthly basis.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.7.2 Supplier Quality Performance Monitoring Phase
During the contract execution phase, suppliers shall be monitored by Eskom for performance on
quality-related aspects.
The outcomes of such monitoring will enable Eskom to take any appropriate actions pertaining to
the supplier.
The monitoring shall be carried out periodically by Eskom or at predetermined intervals during the
execution of a contract using agreed key performance indicators. The monitored key performance
areas include the following:
ο· CQP and QCP /ITP
ο· Delivery
ο· Design
ο· Cost
ο· Management system
Subsequent key performance indicators associated with these areas will include the following:
ο· Nonconformity monitoring
ο· Audit and assessment evaluation scoring
ο· Management system compliance and accreditation
ο· Achievement of delivery targets as per contractual agreements
ο· Process improvements
ο· Correction and corrective action response and closure
3.7.3 Supplier Quality Audit
3.7.3.1 Quality audits and related quality performance reviews are intended to provide an objective
evaluation of compliance with performance expectations defined in this specification, in the
supplier contract quality plan (CQP), and in any other project scope of work specification.
3.7.3.2 Quality audits and related quality performance reviews include, but are not limited to, any
quality or other project functional area audits, assessments, verification of compliance
reviews, surveillance, inspections, or other interim or final assessments of scope of work
deliverables provided by the supplier or sub-suppliers
3.7.3.3 Quality audits and related quality performance reviews are intended to provide an objective
evaluation of compliance with performance expectations defined in this specification, in the
supplier contract quality plan (CQP), and in any other project scope of work specification.
3.7.3.4 Quality audits and related quality performance reviews include, but are not limited to, any
quality or other project functional area audits, assessments, verification of compliance
reviews, surveillance, inspections, or other interim or final assessments of scope of work
deliverables provided by the supplier or sub-suppliers.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.7.3.5 Quality audits and related quality performance reviews shall be carried out by trained,
accredited, and experienced personnel in accordance with procedures documented in the
Cqp.
3.7.3.6 The supplier shall submit, for Eskom review, documented processes for conducting project
scope of work quality audits and related quality performance reviews. Supplier quality audits
and related quality performance review processes shall be designed to address evaluation
of progress towards completion of project functional area deliverables as well as final
deliverable quality.
3.7.3.7 The supplier shall provide a schedule of anticipated quality audits covering all functional
areas and related quality performance reviews at the time of first post-contract award CQP
submission.
3.8 Standard Conditions
3.8.1 Rights of Access
Eskom:
3.8.1.1 shall be granted electronic and hard-copy access to all quality plans, procedures,
documentation, and other quality records relating to the work, including, but not limited to,
data extracts;
3.8.1.2 reserves the right to review, inspect, and audit any or all parts of the supplierβs QMS, as well
as any documentation, materials, or equipment associated with the work, at any time or
project work location; and
3.8.1.3 reserves the right to carry out assessments and audits on all new suppliers and sub-
suppliers.
The supplier:
3.8.1.4 shall support Eskomβs effort to monitor, verify, and/or witness any activities associated with
the work at any time;
3.8.1.5 shall cooperate with Eskom requests for documentation, records, and inspection and
witnessing. Eskom participation in audits, appraisals, assessment of plans, and verification
shall be conducted at no extra cost to Eskom;
3.8.1.6 shall ensure that a sub-supplier provides access to Eskom to all work procedures, records,
and supporting documentation through provision of access to view and photocopy, as
required, to support verification of scope of work requirements. Access shall include the
ability to photograph Eskom equipment, systems, system components, materials, etc.;
3.8.1.7 shall provide access to all quality-related information pertaining to activities performed by
itself or sub-suppliers, where Eskom might not have participated in the witnessing of their
quality assurance or control (this refers to inspections, audits, etc. performed by the supplier
on its own sub-suppliers);
3.8.1.8 shall allow Eskom to assess, audit, approve, or reject any sub-suppliers employed by
Eskomβs suppliers to assist with the product and/or service delivery to Eskom; and
3.8.1.9 shall ensure that the above requirements flow down to sub-suppliers.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.2 Eskom Rights to Information
3.8.2.1 To expect that the works will be conducted in accordance with the contract between the
parties.
3.8.2.2 To have access to the supplierβs information as determined by applicable legislation.
3.8.2.3 Eskom reserves the right to oversee the supplierβs audit programmes by participating in
selected audits as an observer and by assessing the supplier during key work stages.
Eskom will coordinate with the supplier to develop an oversight schedule aligned with the
supplierβs audit schedule.
3.8.2.4 To obtain access to any audit reports of audits performed by the supplier reflected in the
audit programme.
3.8.2.5 To conduct independent quality audits during all phases of the contract, and the supplier
shall provide all resources to support these activities.
3.8.2.6 Eskom shall have the right to participate in, or request that, a technical investigation be
launched and conducted at the supplierβs and sub-suppliersβ premises or other sites when
risk to Eskom products or service deliverables is identified.
3.8.2.7 To participate in, and/or lead, investigations related to incidents involving its products.
3.8.2.8 To require from suppliers to be responsible for the cost of re-inspections.
3.8.2.9 To withhold payment from suppliers as a result of outstanding nonconformities, irrespective
of the agreed payment schedule and in accordance with the conditions of contract.
3.8.2.10 Shall be granted electronic and hard-copy access to all quality plans, procedures,
documentation, and other quality records relating to the work, including, but not limited to,
data extracts.
3.8.2.11 Reserves the right to review, inspect, and audit any or all parts of the supplierβs QMS, as
well as any documentation, materials, or equipment associated with the work, at any time or
project work location.
3.8.2.12 Shall carry out assessments and audits on all new suppliers and sub-suppliers.
3.8.2.13 Reserves the right to appoint resident quality inspectors who can be based at the supplierβs
or sub-supplierβs premises and on site where the work is being performed.
3.8.2.14 Reserves the right to select intervention points within all developed supplier QCPs/ ITPs
for Eskom oversight of selected functions and to perform surveillance or audits of the work.
3.8.2.15 Shall be given access at all reasonable times before, during, and after manufacture and
before delivery, construction, erection, and commissioning to measure, test, and inspect the
products and workmanship, as necessary, at the supplierβs premises and at Eskom sites.
3.8.2.16 Reserves the right to suspend any pending deliveries by the issuing of a cease delivery
order at any time and for any portion of the work that is not being performed in accordance
with the specified/agreed requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3 Preservation
The supplier shall develop and implement a comprehensive preservation programme consisting of
plans, processes, procedures and actions undertaken for the purpose of planning for and
maintenance of material deliverables quality. The supplier preservation programme scope includes,
but is not limited to, the following:
3.8.3.1 Engagement of personnel suitably qualified for oversight of, and (as required) direct
implementation of, preservation programme requirements.
3.8.3.2 Development and implementation of preservation programme training appropriate to work
need.
3.8.3.3 Eskom may make use of its appointed service provider tasked to provide a full suite of
services encompassing an online monitoring system and asset tracking during, but not
limited to the following stages: inspections, testing, shipping, transportation, storage, and
commissioning. The supplier is to enable full access during all of these stages in order to
allow the installation of the devices on Eskom-identified products and equipment, which
include the sub-supplierβs testing facilities, processing plant, and any other processes
deemed important towards effective and efficient quality control.
3.8.3.4 Eskom seeks cooperation between the supplierβs designers and those of Eskomβs service
provider in ensuring seamless installation of the device and other associated installations.
Moreover, there is also a need to integrate data flows and systems between Eskom and the
supplier. Further details are included in the Eskom specifications and works information.
3.8.3.5 Review and tracking of compliance with Eskom and supplier engineering specification of
preservation requirements.
3.8.3.6 Review and tracking of compliance with sub-supplier provided preservation requirements
and recommendations.
3.8.3.7 Evaluation of prospective temporary and longer-term material storage sites for consistency
with preservation programme expectations.
3.8.3.8 Preservation work plan development and plan execution performance evaluation of all
parties engaged for provision of material transportation, handling, or storage services.
3.8.3.9 Oversight of material quality preservation plan preparation and plan execution performance
at all work locations.
3.8.3.10 Development of a preservation programme records management process, in compliance
with Eskom information management requirements, which comprehensively addresses
generation, maintenance, and ready access by Eskom to all preservation programme
records.
3.8.3.11 The supplier shall deploy a clearly defined documented programme providing for
identification of all physical asset pre-operation preservation of quality requirements. In this
reference, the term βphysical assetsβ should be understood to include bulk materials,
including consumable items, equipment systems, system components, and any other
procured or supplied materials or equipment transferred to project control, but not deployed
for operational purposes.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3.12 Where the project responsibility for equipment and materials management has been
formally delegated, the supplierβs preservation programme shall ensure clear and
unambiguous communication of pre-operation preservation of goods quality requirements
to sub-suppliers.
3.8.3.13 The supplierβs preservation programme shall clearly and unambiguously document
processes and procedures for efficient and effective monitoring of compliance with
programme requirements.
3.8.3.14 Compliance monitoring shall commence with ensuring comprehensive consideration of
preservation requirements in the engineering instruction and subsequent inclusion of said
instruction in procurement documentation and shall be applicable until such time as
equipment or materials have been incorporated in an operating or operational system or
structure.
3.8.3.15 Compliance evaluation frequency shall anticipate transfer of tactical-level responsibility for
management of preservation responsibilities between project functional areas, for example,
procurement to logistics, logistics to fabrication, fabrication to logistics, logistics to
construction, etc., and shall, in similar fashion, anticipate transfer of support for tactical-level
responsibility between various subcontracted service providers.
3.8.3.16 Supplier engineering shall ensure that preservation requirements for scope of work
systems, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented and that preservation requirements are efficiently and
effectively communicated to project procurement, logistics, construction management,
quality, security, and other project functional areas, as required, for efficient and effective
implementation of preservation requirements. This shall take the form of a preservation
programme applicable to all systems, system components, equipment, materials, customer-
supplied materials, and other goods procured or managed under the scope of work.
3.8.3.17 The supplierβs preservation management programme shall clearly and unambiguously
address temporary, long-term, and in-transit preservation requirements, including, but not
limited to:
ο· requirements for protection against, or insulation from, atmospheric conditions,
sunlight, temperature, soil, dust, humidity, salt spray, corrosive atmospheres, or
other physical environment conditions;
ο· detailed procedures for application, use, monitoring, and maintenance of coatings,
coverings, fasteners, lines, and other components for internal and external weather
proofing;
ο· requirements for electrical grounding or isolation;
ο· requirements for internal or external environment creation, for example, inert gas
charging, heating, cooling, etc., inclusive of gas storage, electric power supply, etc.;
ο· detailed procedures for initial set-up, charging, activation, and maintenance of
internal atmosphere generation, regeneration, monitoring, and relieving systems, for
example, inert gas management systems;
ο· requirements for protection against, or insulation from, vibration or long-period
cyclical motion in transit, for example, wave-generated movement during sea
transport;
ο· internal and external structural integrity protection, for example, internal and external
bracing, padding, framing, chocking, etc.;
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
ο· support structure requirements, for example, stools, pads, or other devices,
substrates, or support required to ensure in-storage and in-transit stability of
systems, system components, equipment, and material, or other discrete units or
items;
ο· provision for physical separation and/or barriers to prevent airborne or direct
transmittal of contaminants between work areas or between work areas and storage
areas, for example, prevention of carbon steel grinding or cutting debris impact on
stainless steel elements, airborne drift of blast aggregate into vessels or machinery,
etc.;
ο· provision for, and final disposition of, temporary and longer-term storage or transit
required supports and related binding devices, for example, stools, stands, sea
fasteners, platforms, chocks, spacers, cabling, etc.;
ο· provision of requirements for temporary work platforms or other support structures
required to ensure provision of preservation services, for example, provision of a
self-elevating work platform for periodic access to elevated fittings, gauges, man-
ways, etc.;
ο· requirements for protection against, or insulation from, contact with other objects, for
example, padding or other protection for external tubing, fittings, or other impact-
sensitive structures or components;
ο· clear physical delineation of temporary and longer-term storage areas supplemented
by hard and soft barriers, as required, to maintain a protective perimeter;
ο· documented agreements with storage facility and transportation provider
management regarding security management, including, but not limited to, facility
access and egress control and control of access to project goods and materials
within facility boundaries or aboard vehicles or vessels; and
ο· detailed procedures for inspection and testing to verify performance of preservation
procedures and to provide for timely notice and corrective action to maintain
preservation status.
3.8.3.18 The supplierβs preservation management programme scope shall encompass
management of preservation requirements, from initial transfer of ownership or management
responsibility to project scope of responsibility, through any period of temporary or longer-
term storage and through any period of transit, including transit for final delivery at point of
active use or installation.
3.8.3.19 The supplierβs preservation management programme shall clearly and unambiguously
address processes and procedures to ensure that storage and control of materials are
accomplished in accordance with manufacturer recommendations, specifications, and
project-specific requirements.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.3.20 The supplierβs preservation management programme shall incorporate special precautions
to address preservation and control of valves, electrical motors and components,
mechanical and rotating equipment, piping and fittings, instrumentation, flange faces,
gaskets, coatings, insulation, and other materials. Special precautions include, but are not
limited to, supplier-specified maintenance procedures related to engines, electric motors,
pumps, compressors, etc., such as periodic shaft rotation, engine turnover, lubrication, etc.
3.8.3.21 The supplier shall ensure that clear and unambiguous requirements for preservation of the
system, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented in purchase orders, work authorisations, and other
communications between the supplier and sub-suppliers.
3.8.3.22 Where sub-supplier expertise is utilised in determination of the preservation protocol,
supplier procurement processes shall ensure clear and unambiguous documentation of sub-
supplier input into preservation management programme requirements.
3.8.3.23 Supplier procurement shall ensure that preservation requirements for scope of work
systems, system components, equipment, materials, and other procured goods are clearly
and unambiguously documented and that preservation requirements are efficiently and
effectively communicated to project logistics, construction management, quality, security,
and other project functional areas, as required, for efficient and effective implementation of
preservation requirements.
3.8.3.24 The supplier shall ensure comprehensive, clear, and unambiguous designation of sub-
supplier responsibility for execution of all preservation management programme elements,
including, but not limited to, all systems, processes, procedures, methods, ready access to
records, and provision of equipment, tools, or services essential to efficient and effective
execution of the preservation management programme.
3.8.3.25 The supplier shall ensure that preservation management programme responsibilities are
clearly and unambiguously defined within the project team and efficiently and effectively
implemented at all project scope of work locations. Inclusion of supplier and sub-supplier
scope of work in the development and implementation of a preservation management
programme shall be considered essential to efficient and effective preservation
management programme execution.
3.8.3.26 The supplier shall ensure clear and unambiguous designation of project team responsibility
for oversight and management of preservation management programme elements during
every stage of project development.
3.8.3.27 The supplier shall ensure that Eskom has free and unrestricted access to all preservation
records for inspection and audit.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.4 Quality Audits Related Conditions
3.8.4.1 The supplier shall maintain an accurate quality audit and related quality performance review
schedule and shall incorporate the current schedule as an attachment to the supplier CQP.
3.8.4.2 The supplierβs quality audit and related quality performance review schedule development
process shall be designed to incorporate consideration of information generated by
previously conducted audits and reviews, by input from project risk management evaluations
(risk register), or from Eskom or sub-supplier subject matter expertise.
3.8.4.3 Eskom reserves the right to oversee supplier audit programmes by participating in selected
audits as an observer and by assessing the supplier during key work stages. Eskom will
coordinate with the supplier to develop an oversight schedule aligned with the supplierβs
audit schedule.
3.8.4.4 Eskom will have the right to obtain access to any audit reports of audits performed by the
supplier reflected in the audit programme.
3.8.4.5 Eskom reserves the right to conduct independent quality audits, scheduled and
unscheduled, during all phases of the contract. The supplier shall provide all resources to
support these activities.
3.8.4.6 Eskom shall be given access at all reasonable times before, during, and after manufacture
and before delivery, construction, erection, and commissioning to measure, test, and inspect
the products and workmanship, as necessary, at the supplierβs premises and at Eskom sites.
3.8.4.7 The supplier shall obtain access for Eskom to measure, test, witness tests, and inspect
products that are being manufactured by any sub-supplier. This includes surveillances.
3.8.4.8 The assessments and audits shall be carried out on all new suppliers and their sub-
suppliers.
3.8.4.9 Eskom shall have the right to participate in, or request that, a technical investigation be
launched and conducted at the supplierβs and sub-suppliersβ premises or other sites when
risk to Eskom products or service deliverables is identified.
3.8.4.10 Qualification requirements for supplier and sub-supplier personnel engaged in conducting
quality audits and related quality performance reviews shall be defined in the supplier CQP
and shall be in compliance with the Project Quality Personnel Qualification Specification.
3.8.5 Management of Nonconformities and Nonconforming Outputs Identified by Eskom
3.8.5.1 Nonconformity reports raised by Eskom and issued against the supplier shall be investigated
by the supplier as a matter of urgency in order to determine the root cause, corrective action
measures, as required, with implementation time frames.
3.8.5.2 A formal response shall be prepared in respect of the defined criteria and submitted to
Eskom for its review, evaluation, and acceptance, within a maximum of 14 calendar days
from the date of issue of the nonconformity and should be aligned with the site
requirements/procedure.
3.8.5.3 Eskom may, at its discretion, request a response sooner and, in any case, before the
supplier proceeding with any pending/further intervention or corrective action, as may be
required by Eskom.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.5.4 Should Eskom or its inspection authority/agency identify any nonconforming products during
the conduct of its audits/surveillances/inspections, the supplier shall be deemed to be in
breach of contract and shall be held liable for any repair, rework, and/or associated
replacement costs. The supplier may, in such instances, also be held liable for the full costs
associated with the conducting of follow-up audits/surveillances/inspections.
3.8.5.5 The nature, magnitude, and/or frequency of nonconformity and inspection defect/rejection
reports raised by Eskom or its appointed inspection authority/agency shall form the basis of
any action to rescind/withdraw the supplierβs qualification status.
3.8.5.6 Nonconforming outputs identified by Eskom shall be documented via a NC Report and
issued to the suppliers via the contract communication protocol. The suppliers shall
investigate the matter and respond in writing to Eskom of disposition within the stated
contractual conditions.
Note: The dates for the disposition should align to contractual conditions.
3.8.5.7 Eskom shall identify repeat deficiencies as systematic failures of the supplierβs QMS and
shall notify the supplier of the trends. Eskom can initiate an internal audit to highlight the
system failures. The supplier with raise a Corrective Action Report and undertake Root
Cause Analysis. In such cases, QMS rectification and/ or update measures shall be taken
immediately.
3.8.5.8 Should the Supplier fail to respond and rectify nonconforming products within stipulated
contractual conditions. The Project Manager should apply contractual remedies in
accordance with Fidic/ NEC contract.
3.8.5.9 Repeated Nonconformities; if there are any identified repeat nonconformities from the same
supplier within a period of 6 months or less. This must then be escalated to the management
review committees of the BU/ OU/ Cluster/ or Divisions for adjudication. If not resolved, then
the matter must be escalated to the supplier review committee for recommendation.
3.8.6 Special Processes
The following requirements shall be applicable as well as additional requirements as specified in the
scope of work for the provision of the following special process services:
3.8.6.1 The supplier shall ensure that all processes which require that procedures be pre-qualified
or work methods and operators tested and qualified are controlled and all steps followed
before the work can commence.
3.8.6.2 This typically covers such activities as welding, non-destructive testing, special fabrication
techniques, coating, painting, etc.
3.8.6.3 All special processes (procedures and processes) shall be submitted for review and
acceptance by Eskom, accredited or certified agency. No work shall commence until these
are accepted.
3.8.6.4 Where applicable, a relevant Management System for the special process shall be certified
or approved by an accredited body and proof of certification shall be submitted to Eskom for
review. An example for this will be the Welding Management System based on ISO 3834.
3.8.6.5 Where samples are required for acceptance, these shall be submitted to Eskom for review
and acceptance.
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
3.8.6.6 The supplier shall ensure that all operators are suitably qualified for these processes in
accordance with the procedures, processes and/ or applicable standards/ codes.
3.8.6.7 The records of qualification of procedures, processes and operators shall be maintained by
the supplier in accordance with the applicable procedure or code and these made available
to Eskom at all times.
This document has been seen and accepted by:
Name Designation
Kerseri Pather General Manager: Risk and Sustainability
Lenock Meyer Acting Senior Manager: Quality Management
Pamela Dondashe Middle Manager: Quality Assurance
Mandla Mkhwanazi Middle Manager: SHEQ Procurement and Supply Chain Management
Suzette Manthe Senior Advisor: Quality Performance and Planning
Lorna Ndlela Middle Manager: Eskom Document and Records Management
Date Rev. Compiler Remarks
October 2021 3 SA Sambo Specification was due for revision and in addition, to
align the requirements with the latest Eskom business
processes and systems.
October 2018 2 SA Sambo Specification reviewed to be aligned with the
requirements of ISO 9001:2015
March 2016 1 SA Sambo Specification was due for revision and also to
repackage the requirements and tender returnable
documents into four categories.
December 2011 0 A Hunter New document
The following people were involved in the development of this document:
ο· Andrew Else
ο· Bongi Tshabalala
ο· Feziwe Mogamisi
ο· Lesego Garegae
ο· Patrick Thwane
ο· Xolani Zuma
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
Supplier Quality Management: Specification Unique Identifier: 240-105658000
Revision: 3
Page:
Eskom Operational Quality Forum Members
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the
user to ensure it is in line with the authorized version on the system.
No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Ltd,
Reg No 2002/015527/30.
B.2 Documented information for Control of Externally Provided Processes, Products and Services - Must include criteria for evaluation, selection,
Indicate with an
105658000 (x) as applicable
Specification or (-) if not
Applicable
Pre-contract award quality requirements x
(*Select Only Applicable Category). NB: Not more than one category must be selected. Also indicate
whether site assessment is applicable.
Category 1 (refer to clause 3.5.-105658000) -
Category 2 (refer to clause 3.5.-105658000) -
Category 3 (refer to clause 3.5.-105658000) X
Category 4 (refer to clause 3.5.-105658000) -
Main Supplier and Sub-supplier Capability and Capacity Assessment (refer to clause 3.-105658000) -
3 post-contract award(eskom)
This document establishes the technical evaluation criteria for the evaluation of the tenders that will
be received in response to the request to tender for the civil works to be done at Transmission
Substations. It is a high-level consideration of the key aspects that will give direction to the technical
evaluation process. It is in accordance with the Tender Engineering Evaluation Procedure (24048929482) [4]
2.1 Scope
This evaluation criteria document applies to all civil engineering aspects of the Transmission
Substations
2.1.1 Purpose
The purpose of this document is to establish a standardized framework for assessing the technical
capabilities and compliance of the civil works proposals.
2.1.2 Applicability
This document shall apply throughout Eskom Holdings Limited Divisions/ National Transmission
Company South Africa SOC Ltd Reg No 2021/539129/30.
2.1.3 Effective date
The date from which the document is effective is from the authorisation date.
2.2 Normative/Informative References
Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.
2.2.1 Normative
[1] ISO 9001 Quality Management Systems
[2] OHS Act, 1993: Construction Regulations, 2014
[3] SANS 1200: Standard Specification for Civil Engineering Construction
[4] 240-48929482: Tender Engineering Evaluation Procedure
2.2.2 Informative
None
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30
Transmission Substations Civil Qualitative Technical Unique Identifier: 240-170000109
Evaluation Criteria Revision: 5
Page:
2.3 Definitions
2.3.1 Controlled Disclosure: Controlled Disclosure to external parties (either enforced by law, or
discretionary)
2.3.2 Tender: A written competitive offer, quotation, proposal made by the supplier in a prescribed
or stipulated form in response to an invitation to tender/competitive enquire for provision of
assets/goods or services and or the disposal thereof.
2.4 Abbreviations
Abbreviation Explanation
CV Curriculum Vitae
EDWL Engineering Design Work Lead
LDE Lead Discipline Engineer
N/A Not Applicable
OHSA Occupational Health and Safety Act
SANS South African National Standards
TET Technical Evaluation Team
2.5 Roles and Responsibilities
Engineering Manager: All Engineering Managers throughout Eskom shall ensure that all staff, in
their respective areas understand and adhere to this procedure.
Engineering Design Work Lead (EDWL): The EDWL is responsible to manage the execution and
adherence to this procedure. Typically, on New Build projects the EDWL role is fulfilled by the Lead
Discipline Engineer (LDE) and in existing asset projects the EDWL role is fulfilled by the relevant
System Engineer/plant Engineer.
Technical Evaluation Team (TET) member: The delegated engineers/technical specialists who
are responsible to review and evaluate technical aspects of the tender documentation as per the
Tender Technical Evaluation Strategy.
2.6 Process for Monitoring
N/a
2.7 Related/Supporting Documents
N/a
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30
Transmission Substations Civil Qualitative Technical Unique Identifier: 240-170000109
Evaluation Criteria Revision: 5
Page:
3.1 Scope of Work
The following is a high-level applicable scope of work ticked, refer to a detailed scope of work
document for the tendered project:
Scope Applicable
Foundations and/or plinths
Cable Trenches
Earthworks/Terrace
Roads
Drainage
Yard stone
Buildings
Fencing
Steelwork
(i.e. Main columns and beams, equipment support
and/or floodlight mast)
Security Lighting
Earthmat & Earthtails
Substation Electrical in Buildings
(i.e. Lighting installation, ventilation installation
and/or electrical installation-DB)
3.2 Technical Evaluation Threshold
The minimum weighted final score (Threshold) required for a tender to be considered from a
technical perspective is 70%. The tenderers will be evaluated using the criteria listed in section 3.3.
Each criterion is allocated a weight. An overall scoring will be given for each tenderer. The overall
score is a sum of the individual scores allocated for each criterion.
3.3 Qualitative technical Evaluation Criteria
Compliant tenders will be evaluated against a set of weighted qualitative evaluation criteria. The
evaluation criterion has been broken down into sections and a percentage weighting has been
allocated to each section. Percentage weighting summary figures is indicated in the table below:
Controlled disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by
third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30
Transmission Substations Civil Qualitative Technical Unique Identifier: 240-170000109
Evaluation Criteria Revision: 5
Page:
Table 1: Qualitative Evaluation Criteria
Qualitative Technical Criteria Reference to Criteria Criteria Score Clarification
Description Technical Weighting Sub
Specification (%) Weighting
/ Tender (%)
Drawn chkd auth date reference drawings
Drawn chkd auth date reference drawings
250 site plan
Of finishes
1900 u4 finish to horizontal or slightly inclined see detail 1 see detail 1
Surfaces of concrete struck off with
An accurate straight edge to provide an
Even uniform surface and steel floated
4050 NEW 4050 NEW 4050 NEW 4050 NEW 3000 NEW TO REMOVE SCREED MARKS. (TOLERANCE = 3 mm)
J j
200 ex. 200 ex. 200 ex. 200 ex. 200 ex. F1 as from close jointed sawn boards. Sheet
20200 metal or other approved material which will
Prevent loss of grout.
F2 as from wrought formwork with all joints
Between formwork panels horizontal or
Vertical or parallel to supporting members section a-a
To produce an accuracy ii high quality smooth
Finish of even texture and colour. Joints
Shall be tight to prevent loss of grout - sealed
With grout or similar.
ROOF SLAB 200 mm THICKK K
300 sq. 300 sq. 300 sq.
Col. Col. Col.
0 first issue
A
Rev revision description drawn chkd auth date reference drawings
4250 4250 4250 4250 approved by
Drawn chkd auth date
Drawn chkd auth date cj
Drawn chkd auth date cj
Cj approved byg 2900 cjpanel b panel b g ESKOM holdings limited
Panel c
CJ CJ REG No
Panel e panel e 2002/015527/06
Date venterjm
A
Checked by
Cj cj 1 2650
5550 3100 3100 2900 date panel c
1 2 3 drawn by reinforcement detailing
Drawn chkd auth date cj
Drawn chkd auth date cj
Drawn chkd auth date cj
Drawn chkd auth date 0.18/ Reference drawings
Apollo Converter Substation (CS) has 24 single phase 90.8 MVA converter transformers and 2
smoothing reactors. Due to internal or external sustained faults, these assets are vulnerable to
explosion and the spread of fire. In such a case, it is important to have a mechanism to contain the
fire to prevent equipment from fire damage. In the event of a fire, each transformer and reactor are
furnished with its own sprinkler as a form of containment.
Currently, the water used in the fire system is stored in two separate tanks, each with a capacity of
one million litres. There is a fire pump house where water is pumped from the storage tanks to the
relevant deluge systems. The first storage tank was installed in the 1970s and has reached its life
span. The tank is showing signs of structural degradation with leakages in multiple sections of the
tank as well as visible cracking of the concrete support structure. The second tank was added at a
later stage and is still in good working condition.
To ensure adequate water storage (2Ml) for the deluge system, this tank will need to be replaced.
A new storage system with continuous supply is required to reinstate the integrity of the fire system
to mitigate adverse impacts on the substation equipment in the event of fire.
This report details the hydraulic design of the new reinforced concrete 1.2Ml water storage tank.
[1] South African Grid Code
[2] Occupational Health and Safety Act (OHS Act)
[3] (SANS 1200) β General Civil
[4] SANS 10400 β The application of the National Building Regulations
[5] (240-55922824) - Substation Layout Design Guideline
[6] (240-109644476) - Standard for Implementation of Substation Layouts for Transmission
Substations
[7] (32-727) - Eskom Safety, Health, Environment and Quality policy
[8] SANS 10100 β The Structural Use of Concrete
[9] SANS 10100 Part 3 β Design of Concrete Water Retaining Structures
[10] SANS 10160 - Basis of Structural Design
[11] National Building Regulations and Building Standards Act No.
[12] BS8110 β Structural Use of Concrete
[13] BS8007 β Design of concrete structures for retaining aqueous liquids
[14] The Redbook β The Neighbourhood Planning and Design Guideline
[15] Design of Liquid Retaining Concrete Structures, R.D Anchor
[16] Reinforced Concrete Guide, Greg Parrott
ESKOM copyright protected
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
<Select from list>SCOPE OF WORKS FOR THE APOLLO DELUGE TANK Unique Identifier: APO23P28-SE-D82
Replacement
Revision: 0
Page:
Upgrades to the waste storage areas are required for compliance to be achieved. Designs and
construction are in accordance with [1] β [16]. All construction is to be carried out in accordance with
Eskomβs Safety, Health and Environmental Specification. During construction all necessary safety
procedures must be strictly adhered to. This document should be referenced in conjunction with the
relevant drawings.
The Civil Scope of Work involves the following design aspects:
Earthworks
Reinforced concrete tank
Pipes and specials
3.1 Earthworks
3.2 Reinforcent concrete tank
SE-D69, APO23P28-SE-D70 Sheet 01, APO23P28-SE-D70 Sheet 02, APO23P28-SE-D71,
APO23P28-SE-D72, and APO23P28-SE-D73.
3.3 Pipes and specials
APO23P28-SE-D65 Sheet 02
accordance with drawing 0.54-390- Sheet 06
ESKOM copyright protected
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
<Select from list>SCOPE OF WORKS FOR THE APOLLO DELUGE TANK Unique Identifier: APO23P28-SE-D82
Replacement
Revision: 0
Page:
4 list of drawings
Table 1 below shows the list of drawings applicable to the design.
Table 1: List of Drawings
Drawing Number Description
APO23P28-SE-D65 Sheet 01 LAYOUT
APO23P28-SE-D65 Sheet 02 PIPE DETAILS
APO23P28-SE-D68 general arrangement
APO23P28-SE-D69 reinforcement details
APO23P28-SE-D70 Sheet 01 REINFORCEMENT DETAILS PANEL C
APO23P28-SE-D70 Sheet 02 REINFORCEMENT DETAILS PANEL C
0.54-390 Sheet 6 REINFORCEMENT DETAILS PANEL D
0.54-8806 reinforcement details panel f
0.54-4963 reinforcement details panel e
5 authorisation
This document has been seen and accepted by:
Name Designation
Azhar Mayet Senior Engineer
Andile Maneli Senior Manager
6 revisions
Date Rev. Compiler Remarks
18 September 2025 0 Itani Mathoma First issue
ESKOM copyright protected
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
<Select from list>SCOPE OF WORKS FOR THE APOLLO DELUGE TANK Unique Identifier: APO23P28-SE-D82
Replacement
Revision: 0
Page:
7 development team
The following people were involved in the development of this document:
8 acknowledgements
None
ESKOM copyright protected
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Financial Requirements
Source: E3574NTCSAMWP.zip (TENDER)Payment Terms: Payment Terms Tenderers are requested to bear in mind NTCSA's standard
payment terms as stipulated hereunder when submitting
tenders and concluding contracts with NTCSA:
For contracts valued below R50 000 000 (Fifty Million Rand)
including VAT, NTCSA is committed to paying Suppliers within 30
days of receipt of undisputed invoices.
2.29-2.30 Sign form of
Compliance Requirements
Source: E3574NTCSAMWP.zip (TENDER)No specific requirements found
Insufficient searchable text - AI extraction recommended
CSD report or as per certificate/affidavit provided
CSD number/CSD report) must be provided at the closing date and time for
CSD number or B-BBEE certificate/affidavit will need to be
A certified copy of a tax clearance certificate is required from foreign tenderers (with a footprint in South Africa but Controlled Disclosure When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of NTCSA SOC Ltd, Β© copyright NTCSA SOC Ltd, Reg No 2021/539129/30 of 69 File name: 559-235050781 E3574NTCSAMWP Template ID: 240-43921804 (Rev 7) Header and Footer portrait template Document 559-235050781 Rev 4 Identifier Invitation to Tender Effective Date July 2024 Review Date July 2027 that are not registered on CSD and have not provided a SARS pin number) and local tenderers (that have not provided their SARS e- filing PIN number for verification by NTCSA and/or their CSD profile / CSD number). Foreign suppliers with no footprint in South Africa must complete the SBD1 document; however, no proof of tax compliance is required. 1.1.14 *SBD 6.1 Annexure I Y β Proof of valid and current CSD Registration (CSD number/CSD Report) ADDITIONAL CONTRACTUAL REQUIREMENTS SUPPORTING EVIDENCE 1.1.34 Safety β COIDA - Original certificate of good standing or proof of application issued by the Compensation Fund (COID) or a licensed compensation insurer (South African tenderers only) 1.1.35 Quality Attached Y β
Refer to Separately βQualityβ Folder 1.1.36 Other Attached Y β safety/quality Separately documents as required per
Completion Certificate to the Project Manager
CIDB grading/category: 5CE or higher
CIDB Grading: 5CE or higher
Proof of ownership / shareholding (preferably CIPC documentation) inclusive of shareholding
o Document specific checklists and registers o Monitoring/Inspection reports o Findings and close out reports. o Natural resource consumption (water, fuel, electricity usage etc.) 2.7 Related/Supporting Documents [1] 32-1034 Eskom Procurement and Supply Chain Management Procedure [2] 240-106082683 SHEQ Requirements for the Procurement and Supply Chain Processes in Eskom CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 Environmental Requirements for Contractors and/or Unique Identifier: 240-180100134 Suppliers Revision: 1 Page
The Contractor Environmental Management Model Transmission has adopted a six-phase environmental contractor management model to effectively manage contracts and suppliers. Phase 2: Phase Phase 4: Site Phase Tender Phase 5:Contract Phase 6: Post Mobilisation 1:Design Enquiry, 3:Supplier Execution -Contract /Access to Phase Evaluation Registration and Continual Review site and Award Monitoring Figure 1: illustrate the six phases environmental contractor management model 3.1 Phase 1: Design Phase
Environmental Practitioners to provide the designer with an environmental specification that are specific to the contract or services to ensure integration of the environmental requirements into the design.
The designer and the responsible environmental practitioner to conduct a site visit before commencing with the design or contract goods and services environmental specification can be developed. 3.2 Phase 2: Tender Enquiry, Evaluation, and Award
Functional environmental requirements will form part of the tender/enquiry. The tender/ enquiry shall be accompanied by a contract specific environmental specification and risk assessment and applicable SHE policies and procedures. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 Environmental Requirements for Contractors and/or Unique Identifier: 240-180100134 Suppliers Revision: 1 Page: Transmission Supplier Conduct due diligence on All environmental documentation, records, reports shall be the supplier prior the work made available for review when requested by Transmission or is executed its appointed inspection agency. The supplier shall provide suitable facilities and safe working environmental to Transmission or its appointed environmental agency 3.3 Contractors Environmental Management System Requirements
The Contractor/supplier shall have a documented, implemented and maintained environmental management system, preferably guided by the ISO 14001:2015 Standard. New Suppliers can provide evidence of their compliance by maintaining accurate and up-to- date documentation and records related to their environmental management practices. This can include policies, procedures, training records, audits, and monitoring reports.
The Contractor shall be responsible for ensuring that all their Supplier Organisationβs environmental programmes comply with the Transmission requirements. The Contractor shall define the specific environmental control elements applicable to the scope of works, goods or services.
The Contractor shall inform Transmission of any changes to the environmental requirements that were evaluated during the tendering stage prior to implementation of these changes. 3.4 Environmental Planning
Any revisions to the plans/programmes shall require the agreement of Transmission or its environmental representatives prior to the commencement of work involving an activity affected by such changes.
The revision of environmental documents shall be subjected to review and approval by all parties previously responsible for evaluation prior to implementation. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 Environmental Requirements for Contractors and/or Unique Identifier: 240-180100134 Suppliers Revision: 1 Page
The following will form part of the supplierβs documented EMS, and shall be internally reviewed, and formally approved. The environmental management system must cover each distinct stage of work performed/undertaken and it shall include but not be limited to: o Site establishment. o Access control to site. o Site construction and installation work (civil, electrical, power lines etc.). o Manufacturing (site, factory, temporary workshops etc.). o Storage areas (plant, equipment, free issue material etc.). o Waste Management Plan (or method statement); Site and Vegetation Clearing. o Handling of Hazardous Chemical substances. o Site management (water management, dust and noise, landowner liaison, final release and settlement of disputes and claims). o Rehabilitation. o Site demobilization.
Different physical locations where the supplierβs work will be performed, the significant environmental conditions will be included and mitigated.
Work to be performed by the supplier and their pre-determined scoping requirements.
Waste management plan/procedure that includes waste segregation and minimisation, waste disposal register, anticipated waste streams to be generated and related legal requirements applicable to waste management for specific scope of work.
Environmental records to be retained at site for the specific scope of work and, shall include but not be limited to: o Environmental Authorisation (including all other permits and licenses). o Project specific Environmental Management Plan/Programme. o Aspects and Impacts register. o Incident register and Investigation reports. o Non β Conformance register. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 Environmental Requirements for Contractors and/or Unique Identifier: 240-180100134 Suppliers Revision: 1 Page: o Complaints register. o Waste statistics (reused, recycled, donated and disposal records). o Water use records. o Hazardous Substances registers and Safety Data Sheets. o Records of internal and external audits and inspections (reports, findings, action plans and close outs). o Records of site inspections conducted (checklists and reports). o ECO reports (where applicable). o Energy Efficiency Checklists. o Appointed environmental representative (Appointment Letter). 3.5 Organisational Environmental Aspects and Impacts Registers
Transmission Aspects and Impacts register shall identify/indicate/define/reflect the supplierβs scope as per the requirements of ISO 14001: 2015.
Transmission requires that the service providers βs environmental requirements documentation meet the additional requirements below as a minimum
Identify and list all environmental aspects per activity.
Determine all the possible environmental impacts for each of the identified aspects.
All environmental aspects shall be assessed before and after controls.
Identify significant Aspects and Impacts and establish programmes/ procedures on how to address the impact to the environment.
The impacts shall be rated and must be included in a compiled Environmental Aspects and Impacts register (See Appendix A).
Aspects and Impacts register by the contractors/suppliers must be a revision-controlled document; An example of the Environmental Criteria for determining the significant impacts are explained in Appendix A. Note: this shall be managed according to the level of environmental risk. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 Environmental Requirements for Contractors and/or Unique Identifier: 240-180100134 Suppliers Revision: 1 Page: Transmission Supplier Significant aspects shall be considered in the Planned actions and impact control (corrective) setting of Objectives and Targets and the measures for the medium and high significant determination of the environmental risks and impacts shall be undertaken through opportunities at the project level. environmental management programme/plan and/or through operational controls. Note: These records shall be kept in a hard copy and submitted to the environmental practitioners
The supplierβs organisational structure shall indicate the current management hierarchy as per scope of work (include SHEQ representatives). The structure must clearly show lines of responsibility and authority and shall reflect both the names of the appointed persons and their respective designations and positions. The management representative (i.e. appointed responsible authority of site) having overall responsibility for environmental management and planning.
A qualified person (National Diploma or a degree e.g., Environmental Sciences/Management or Nature Conservation or relevant Natural Sciences) having the responsibility for monitoring environmental planning and activities and their relationship within the management structure according to the project EMPr/EMP and/or EA requirement. For low risk projects an environmental representative with two weeks environmental training will be sufficient to be an environmental representative.
Environmental tender returnable must be clear to suppliers. The environmental practitioner to identify and list all applicable environmental requirements in relation to the scope of work
Where applicable, the tenders or potential suppliers must conduct a site visit of the area where the work shall be executed before tendering.
The site visit will be conducted with the supervision of contract custodian together with the commercial practitioner. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of Eskom Holdings SOC Ltd, Β© copyright Eskom Holdings SOC Ltd, Reg No 2002/015527/30 Environmental Requirements for Contractors and/or Unique Identifier: 240-180100134 Suppliers Revision: 1 Page: Items for informing the Tenderer
For the environmental requirements that were not met during the evaluation phase, the Tenderer will be given seven (7) days to submit the outstanding requirements. failure to submit the outstanding requirements within the seven (7) days period will render the tenderer non-compliant and the evaluated score will not change. As environmental requirements in a tender are contractual requirements, the non-compliance will not lead to a tendererβs disqualification but will be highlighted in the submission report to the Delegated Approval Authority (DAA) for the Tenderer to address during the negotiations or post contract award.
Outstanding environmental issues at the clarification must be provided for in the contract with the tenderer given a specific period post contract award to address.
A site plan must indicate evacuation routes and emergency assembly point locations.
Zones for particular activities.
Cranes (including radii and capacities).
Site offices.
Welfare facilities.
Off-loading, temporary storage and storage areas (laydown areas).
Sub-contractor facilities were applicable.
Car parking including reverse parking. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30 File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1 Construction of a concrete one million litre deluge Unique Identifier: 559-790983792 water storage tank at Apollo Conveter Station Revision: 1 Page: of 39
Access (must consider people with disability), entrances, security and access controls, temporary roads, and separate pedestrian routes.
Site hoardings and existing boundaries.
Temporary services (including electrical power, lighting, water distribution, drainage, information and communications technology, site security systems, and so on).
Location of fire extinguishers and first aid kits including blood spill kit where applicable.
Fire hazard The Contractor shall develop emergency protocols for dealing with fires, which may include a Fire Management Plan in accordance with the National Veld and Forest Fire Act (No ) and ensure that all staff is trained / informed in fire prevention. No area shall be denuded of vegetation to create firebreaks. Open fires are not allowed on site. The Contractor Environmental Officer shall ensure that in areas with a high fire danger rating, staff is informed of this. Smoking shall be restricted to designated areas or shall not be allowed, particularly in areas that have a high fire danger rating. Contractor shall ensure that adequate Fire Fighting equipment is available on site, particularly near hot work and/or where it is specifically identified as a requirement by either the landowner or during the risk assessment.
Environmental factors to H&S The principal contractor shall monitor dust and noise caused by mobile equipment, generators and other equipment during construction. Factors such as wind can often affect the intensity to which these impacts are experienced. To ensure that noise does not constitute a disturbance during construction activities. Dust suppression measures shall be in place to reduce the dust caused by the movement of heavy vehicles and other contractor activities in order not obscure visibility.
Signing off the contract No project shall be signed off before the client has assessed the activities completed in relation to health & safety outstanding issues.
Forums for Governance and Communication Governance and communication structures shall be established on site where project H&S matters shall be discussed. The agenda, minutes and attendance registers of H&S meetings shall be available. NOTE: These meetings do not replace or act as a substitute for the required statutory meetings. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30 File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1 Construction of a concrete one million litre deluge Unique Identifier: 559-790983792 water storage tank at Apollo Conveter Station Revision: 1 Page: of 39 Statutory H&S Committees in terms of Section 19 and 20 and General Administrative Regulations 5 of the OHS Act and Eskom Holdings (NTCSA) requirements shall be established.
Construction Vehicles and Mobile Plant Construction vehicles and equipment shall comply with the relevant legal and other requirements like Construction Regulations 23, the National Road Traffic Act, the Mine Health and Safety Act, National Environmental Act and Eskom Holdings (NTCSA) Vehicle Safety Specification Procedure 240-62946386. The following requirements are applicable during operation of construction vehicles: A principal contractor shall ensure that construction vehicles and mobile plant are operated by persons with appropriate training, certified competent and in possession of proof of competency, and authorised in writing to operate those construction vehicles and mobile plant
Designated drivers shall be in possession of an appropriate valid driverβs licence for the class of vehicle operated. The driverβs license shall be kept by the person so authorised who shall produce such card on request.
All construction vehicle operators, flagman/banksman/signalman/pointsman shall wear visible PPE at identified high-risk construction sites and shall be visible to the operators during the day or night.
Heavy construction vehicle parking sites, driveways, or any site shall be designed in such a way that no reversing is required. Where reversing is unavoidable, it shall only be done in the presence of a flagman or a banksman.
The contractor shall develop a vehicle and pedestrian management plan.
Relevant traffic signs shall be displayed.
Reverse beepers shall be fitted on construction vehicles.
Drivers of construction vehicles and mobile plant shall have medical certificates of fitness to operate those construction vehicle and mobile plant, issued by an occupational health practitioner in the form of Annexure 3 of the Construction Regulations.
The speed limit within the bounds of the construction site shall be clearly stipulated and communicated to everyone and be part of the induction.
Drivers / operators shall not text or talk on cell phones or two-way radios while driving.
The Principal Contractor/ contractor shall ensure that employees do not: i). Ride on back of light delivery vehicles, cranes or other mobile plant equipment. ii). Leave vehicles unattended with the engine running. iii). When unattended, vehicles shall be locked, chock blocks fitted, and keys removed.
Vehicle shall be searched on the premises or when entering or leaving the premises.
The Principal Contractor/ contractor shall be responsible for the safety and security of his vehicles (including private vehicles) on the premises.
The Principal Contractor/ contractor shall maintain his vehicles in roadworthy condition with valid licenses. These vehicles shall be subject to inspection by the Client representative. Un- roadworthy vehicles shall not be allowed to site. CONTROLLED DISCLOSURE When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorized version on the system. No part of this document may be reproduced in any manner or form by third parties without the written consent of National Transmission Company South Africa SOC Ltd Reg No 2021/539129/30 File name: Construction of a concrete one million litre deluge water storage tank at Apollo Conveter Station_C.TXA0069_Rev 1 Construction of a concrete one million litre deluge Unique Identifier: 559-790983792 water storage tank at Apollo Conveter Station Revision: 1 Page: of 39
completion certificates for the mentioned projects in 5
B-BBEE Details: Claim Form in
terms of PPPFA
2022 regulations.
1.1.15 # Specific Goals β
A tendererβs
failure to submit
proof that it meets
the specific goals
will not result in
its
disqualification.
The tenderer will,
however, be
scored zero for
Specific Goals for
purposes of
PPPFA scoring
and ranking.
1.1.16 Compliance with N β
Employment
Equity Act
Controlled Disclosure
When downloaded from the document management system, this document is uncontrolled and the responsibility rests
with the user to ensure it is in line with the authorized version on the system. No part of this document may be
reproduced in any manner or form by third parties without the written consent of NTCSA SOC Ltd, Β© copyright NTCSA
SOC Ltd, Reg No 2021/539129/30
of 69
File name: 559-235050781 E3574NTCSAMWP
Template ID: 240-43921804 (Rev 7) Header and Footer portrait template
Document 559-235050781 Rev 4
Identifier
Invitation to Tender
Effective Date July 2024
Review Date July 2027
To the extent that
the tenderer falls
within the
definition of a
βdesignated
Employerβ as
contemplated in
the Employment
Equity Act , the
tenderer is
required to
furnish the
Employer with
proof of
compliance with
the Employment
Equity Act,
including proof of
submission of the
Employment
Equity report to
the Department of
Labour. (South
African tenderers
only)
1.1.17 **SBD 4 β Annexure J Y β
Bidders
Disclosure
1.1.18 Additional Documents required in event of JV:-
1.1.18 Letter of intent to β
.1 form a
JV/consortium or
Valid joint venture
agreement
confirming the
rights and
obligations of
each of the joint
venture partners
and their profit-
sharing ratios.
1.1.18 Separate written β
.2 confirmation that
the joint venture
will operate as a
single business
e
Section
Source: E3574NTCSAMWP.zipNo explicit evaluation criteria beyond eligibility/compliance stage. Tender Data may contain specific evaluation methodology. Local content preference may apply for designated sectors.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
Lake Street, Germiston, Johanessburg, 1401, South Africa
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
1
Last checked
22 Sept 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Contact
011-800-8111[email protected]www.eskom.co.za/Pages/Landing.aspxLake Street, Germiston, Johanessburg, 1401, South Africa
Key Personnel
Learn how to submit a winning bid with these related articles
How consulting engineers, engineering firms, and multidisciplinary practices can win public sector infrastructure contracts in South Africa β from ECSA registration and CESA membership to fee proposals, QBS scoring, and building a winning tender response.
A comprehensive guide to civil engineering infrastructure tenders in South Africa. Covers CIDB requirements, major buyers, the tender pipeline, and how civil engineering firms win government work in roads, dams, water, and sanitation.
How mechanical and electrical engineers, contractors, and consultants can win public sector contracts in South Africa β HVAC, plumbing, fire systems, electrical infrastructure, ECSA registration, CIDB ME designation, and tender documentation essentials.
A professional guide for consulting engineers on bidding for government infrastructure projects. Understanding percentage-based fees, discounting ECSA guidelines, and managing professional indemnity risk.
π‘ Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Civil engineering. Unlock full pricing strategies, bid frequency, and historical win rates.