Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
Kendal Power Station (Near Ogies,on Jhb/Witbank Road) - Ogies - Witbank - 2230
Organization Type
GOVERNMENT
Published
12 Aug 2026
OCDS Reference
ocds-9t57fa-165343
ESKOM is procuring the supply and delivery of lubricants to kendal power station on an as-and-when required basis for a period of 5 years (60 months). The contract covers specified hydraulic oil, open gear grease, turbine oil, diesel engine oil, and other lubricants with stated quantities, delivered to the station. Bidders must price per the nec3 supply contract price schedule and comply with eskom's additional conditions, including strict delivery and performance penalties.
Contract term: 5 years (60 months) on an as-and-when required basis, with delivery to Kendal Power Station, Private Bag X7272, Ogies/Witbank, 1035.
Pricing: Tenderers must complete the NEC3 SC3 price schedule, stating the tendered total of Prices exclusive of VAT, VAT at 15%, and total inclusive of VAT; lump sum items are not adjusted if quantities differ.
Delivery and programme: A preliminary programme is required for tender evaluation; the first programme must be submitted within 1 week of the contract date, with revised programmes every 3 days after a missed delivery date and bi-weekly updates.
Penalties: Delay damages of 2.5% of the purchase order item value per week, up to a maximum of 10%; low performance damages of 1.5% of line item value per day, up to a maximum of 5%.
Payment terms: 30 days after submission of an undisputed tax invoice; 60 days if the total contract value is R50 million or above; interest at the prime rate (365-day year) from Standard Bank of South Africa.
B-BBEE and compliance: Bidders must be registered on the Central Supplier Database, hold a valid tax clearance, and provide B-BBEE status; any change in B-BBEE status must be notified within 7 days, with an updated verification certificate within 30 days.
Insurance and liability: Supplier must provide insurances per Insurance Table A; total liability is limited to the total of the Contract Price, and indirect/consequential loss liability is limited to R0.00.
Continue with tenders sharing this issuer, category, or province.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Friday, 28 August 2026 - 10:00
Venue
Horticulture Boardroom, Kendal Power Station
Categories
Request for Bid(Open-Tender)
Kendal Power Station (Near Ogies,on Jhb/Witbank Road) - Ogies - Witbank - 2230
Recommended Certifications
Having these can improve your winning chances: SABS Product Certification, NRCS Certification
AI Document Analysis Stages
Review in progress
The information shown on this card is preliminary. Our procurement team is currently finalising the submission guidelines, evaluation criteria, technical specifications, financial requirements, and compliance sections so you have a clean, bid-ready summary to work from. Documents being finalised: SOW for Lubricants at Kendal - 5years contract.pdf, TES.pdf. You don’t need to refresh — this page will pick up the updated review automatically.
12 Aug
2026
Tender Published
Tender was published
28 Aug
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
TES.pdf
SOW for Lubricants at Kendal - 5years contract.pdf
E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf
Eskom is procuring the supply and delivery of lubricants to Kendal Power Station on an 'as and when' required basis for a five-year period. Bidders must complete mandatory e-tendering training and submit the accompanying acknowledgement form to remain responsive.
Supply & Delivery of Lubricants OHS Specification - Medium Risk.pdf
Eskom is procuring the supply and delivery of lubricants to Kendal Power Station in Mpumalanga on an as-and-when required basis for a five-year period. The contract is governed by a detailed Occupational Health and Safety specification that bidders must comply with.
Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf
Eskom is inviting tenders for the supply and delivery of lubricants to Kendal Power Station on an as-and-when required basis over a five-year period. The contract will be governed by the NEC conditions and requires electronic submission through Eskom's e-tendering portal.
SDLi strategy - Supply and delivery of lubricants.pdf
Eskom is procuring the supply and delivery of lubricants for Kendal Power Station on an as-and-when required basis for a five-year period. The tender includes specific goals for B-BBEE preference points and SDL&I obligations covering transformation, local procurement, job creation, subcontracting, and skills development.
E-tendering Help Manual for supplier - 27 January 2025 (1).pdf
Eskom is procuring the supply and delivery of lubricants for Kendal Power Station on an as-and-when required basis for a five-year period. Bidders must submit their tender documents electronically through Eskom's eTendering system.
NEC (SC) Supply Contract for Kendal Power Station Lubricants.pdf
Eskom Holdings SOC Ltd is procuring the supply and delivery of lubricants to Kendal Power Station on an as-and-when required basis for a 60-month contract, using the NEC3 Supply Contract (SC3) with Eskom-specific additional conditions.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
R 2 880 272
Range
Based on 10 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Description
Source: Supply & Delivery of Lubricants OHS Specification - Medium Risk.pdf (unknown)Eskom requires contractors to meet its SHEQ policy and legislative obligations. The contractor must develop an OHS plan that complies with Eskom's minimum requirements and all applicable legislation. Eskom does not assume the contractor's legal responsibilities; the contractor remains accountable for the health and safety programme of their employees and appointed contractors. The OHS specification is not all-encompassing and does not supersede organizational OHS requirements.
Important Dates
Source: Supply & Delivery of Lubricants OHS Specification - Medium Risk.pdf (unknown){"briefingSession":"{"date":null,"time":null,"venue":"ion reports to the relevant management.","is_compulsory":false}"}
Contact Information
Source: Supply & Delivery of Lubricants OHS Specification - Medium Risk.pdf (unknown)Eskom Contract's Manager: Nolutho Mgijima
Eskom Safety Officer: Wesley Adam
Project Address: Kendal Power Station
Evaluation Criteria
Source: Supply & Delivery of Lubricants OHS Specification - Medium Risk.pdf (unknown)Bidders must be registered with the Compensation Commissioner and hold a valid Letter of Good Standing. They must comply with the OHS Act and all applicable legislation. They must sign a Section 37(2) agreement with Eskom. They must not use child labour. They must comply with Eskom's Substance Abuse Procedure and Life-Saving Rules. They must provide a company organogram and statutory appointments as required.
Technical Specifications
Source: Supply & Delivery of Lubricants OHS Specification - Medium Risk.pdf (unknown)Supply and delivery of lubricants for Kendal Power Station on an 'as and when' required basis for a period of 5 years.
Experience & Qualifications
Source: Supply & Delivery of Lubricants OHS Specification - Medium Risk.pdf (unknown)Main contractor and appointed contractors must have appropriate qualifications and certificates. Employees must always be under competent supervision.
Quality Management
Source: Supply & Delivery of Lubricants OHS Specification - Medium Risk.pdf (unknown)Contractor must maintain satisfactory standards and document inspection results. The OHS plan will be audited against a compliance checklist; approval is granted only after compliance. Eskom personnel will assess implementation regularly. Non-conformance procedures must be in place, and corrective actions must be submitted within one week after audits. Contractors must provide adequate PPE and enforce its use.
Compliance Requirements
Source: Supply & Delivery of Lubricants OHS Specification - Medium Risk.pdf (unknown)B-BBEE Minimum Level: 2
Contractor must be competent to perform required supervisory tasks.
Must comply with Eskom OHS specification, including Section 37(2) agreement, OHS Act, and Eskom Life-Saving Rules.
Must have appropriate qualifications and certificates for all employees, with competent supervision.
Health & Safety
Source: Supply & Delivery of Lubricants OHS Specification - Medium Risk.pdf (unknown)Contractor must comply with Eskom OHS specification, including legal compliance, Section 37(2) agreement, child labour regulations, OHS Act, and legislative compliance. Must follow Eskom's SHEQ policy, COVID-19 requirements, COID, and statutory appointments. Must adhere to Eskom Life-Saving Rules, substance abuse policy (0% alcohol/drug level), and vehicle management. Must conduct risk assessments, safe work procedures, method statements, fire equipment maintenance, first aid, OHS communication, toolbox talks, training, housekeeping, and incident investigation. Must maintain OHS files and comply with work stoppage and hours of work.
Environmental
Source: Supply & Delivery of Lubricants OHS Specification - Medium Risk.pdf (unknown)Contractor must meet environmental legislation and municipal by-laws. Waste must be disposed of in designated waste areas. Materials/objects must not be left unsecured in elevated areas to prevent falling object injuries.
Contractual Terms
Source: Supply & Delivery of Lubricants OHS Specification - Medium Risk.pdf (unknown)Contractor must be competent to perform required supervisory tasks, including HIRA, incident investigation training, supervisor training, authorised person & PSR, and legal liability.
Section
Source: Supply & Delivery of Lubricants OHS Specification - Medium Risk.pdf (unknown)OHS department will issue the 37(2) agreement to the project prior to the start of work. The contractor must comply with Eskom's SHEQ policy and legal responsibilities.
Important Dates
Source: SOW for Lubricants at Kendal - 5years contract.pdf (unknown)Closing date: 2026-08-28 at 10:00 (UTC).
Submission Guidelines
Source: SOW for Lubricants at Kendal - 5years contract.pdf (unknown)Returnable documents must be completed, signed, and submitted with the quotation. Specific returnable forms are not detailed in the available text.
Compliance Requirements
Source: SOW for Lubricants at Kendal - 5years contract.pdf (unknown)Insufficient searchable text - AI extraction recommended.
Description
Source: E-tendering Help Manual for supplier - 27 January 2025 (1).pdf (TENDER)The document provided is the Eskom eTendering System Suppliers Help Manual, which describes how to register and submit bids electronically. It does not contain tender-specific details about the lubricants contract.
Important Dates
Source: E-tendering Help Manual for supplier - 27 January 2025 (1).pdf (TENDER)Closing date and time: 2026-08-28 at 10:00 (as per tender record). No other dates are stated in the document.
Contact Information
Source: E-tendering Help Manual for supplier - 27 January 2025 (1).pdf (TENDER)For system problems, contact the buyer responsible for the published tender. No specific contact details are provided in the document.
Submission Guidelines
Source: E-tendering Help Manual for supplier - 27 January 2025 (1).pdf (TENDER)Bids must be submitted electronically through the Eskom eTendering system at https://eTendering.eskom.co.za. Access requires a CSD number and prior registration on the system, including email and cellphone verification via OTP.
Evaluation Criteria
Source: E-tendering Help Manual for supplier - 27 January 2025 (1).pdf (TENDER)No tender-specific evaluation criteria are provided in the available document. The document only describes the eTendering system's closed tender functionality, which is not applicable to this open tender.
Technical Specifications
Source: E-tendering Help Manual for supplier - 27 January 2025 (1).pdf (TENDER)The tender is for the supply and delivery of lubricants to Kendal Power Station on an as-and-when required basis for five years. No further technical specifications, quantities, or standards are provided in the available document.
Compliance Requirements
Source: E-tendering Help Manual for supplier - 27 January 2025 (1).pdf (TENDER)Bidders must have a valid CSD number to access the eTendering system. No other compliance requirements are stated in the available document.
Important Dates
Source: SDLi strategy - Supply and delivery of lubricants.pdf (unknown)Closing date: 28 August 2026 at 10:00 (as per tender record).
No other dates (briefing, site visit, clarification deadlines) are stated in the document.
Contact Information
Source: SDLi strategy - Supply and delivery of lubricants.pdf (unknown)Buyer: Caxwell Mkhabele (name only, no contact details provided).
Business unit: Kendal Power Station.
No email, phone, or address provided in the document.
Submission Guidelines
Source: SDLi strategy - Supply and delivery of lubricants.pdf (unknown)Returnable documents: all must be completed, signed and submitted with the bid.
Disqualification risks:
Evaluation Criteria
Source: SDLi strategy - Supply and delivery of lubricants.pdf (unknown)Preference point system: maximum 10 points (90/10 system) or 20 points (80/20 system) for specific goals, added to price points, total rounded to two decimals. Contract awarded to highest scorer per PPPFA.
B-BBEE status level points (90/10, 80/20): Level 1: 10/20; Level 2: 9/18; Level 3: 6/14; Level 4: 5/12; Level 5: 4/8; Level 6: 3/6; Level 7: 2/4; Level 8: 1/2; Non-compliant: 0/0.
Specific goals include: B-BBEE improvement/retention, local procurement content (target 100%), job creation, subcontracting to designated groups (target 10% Black-owned EME/QSE), and skills development (4 bursaries).
B-BBEE improvement milestones are non-negotiable: Level 4 must reach Level 3 by end of first year; Level 5-8 or non-compliant must reach Level 4 by end of first year, then improve one level each subsequent year.
Tenderers who submit objectives but do not meet Eskom's targets are not disqualified; commitments become contractual obligations.
Technical Specifications
Source: SDLi strategy - Supply and delivery of lubricants.pdf (unknown)Scope: Supply and delivery of lubricants to Kendal Power Station on an 'as and when required' basis.
Duration: 5 years (60 months).
No quantities, specifications, or delivery schedules are stated in the document.
Methodology
Source: SDLi strategy - Supply and delivery of lubricants.pdf (unknown)Skills development: obligation for duration of contract, monthly progress demonstration. Candidates from previously disadvantaged groups, particularly at site. Bursary minimum 24 months. Eskom target: 4 bursaries to university/university of technology learners (1st or 2nd year, National Diploma/Bachelor's degree). Targets exclude Eskom employees and registered learners. Tenderer bears full cost; Eskom makes no financial contribution. Tenderers advised to approach SETAs for grants and SARS for tax rebates.
Financial Requirements
Source: SDLi strategy - Supply and delivery of lubricants.pdf (unknown)Pricing: Tender response must separate local and imported components as per the Price Schedule included with the tender documents.
Local procurement content is total spending minus the imported component; Eskom target is 100%.
SDL&I performance security: Eskom retains 3% of every invoice (excluding VAT) as security for fulfilment of SDL&I obligations; retained amounts released only upon full fulfilment.
Penalty: 3% of contract value for failure to meet SDL&I obligations.
No bonds, guarantees, or payment terms are stated.
Compliance Requirements
Source: SDLi strategy - Supply and delivery of lubricants.pdf (unknown)B-BBEE documentation required to claim preference points:
B-BBEE affidavit validity requirements: must include deponent's name and ID number, designation, enterprise registration details, percentage of black ownership (including female and designated group), total revenue and basis, financial year end, B-BBEE status level, empowering supplier status, and must be signed in presence of Commissioner of Oath (who cannot be an employee or ex officio of the enterprise).
B-BBEE improvement plan is an essential document, to be submitted within 30 days of contract signing.
SDL&I Implementation Schedule to be completed and returned within 28 days of contract award.
Quarterly SDL&I compliance reports required.
B-BBEE Requirements
Source: SDLi strategy - Supply and delivery of lubricants.pdf (unknown)Validity of Sworn Affidavits: Affidavits must include: name of deponent as per ID and ID number; designation (director, owner, member) to show authority; enterprise name as per CIPC and business address; percentage of black ownership, black female ownership, designated group (or black beneficiaries for specialised enterprises); total revenue for year under review and basis (audited or management accounts); financial year end; B-BBEE status level (only one); empowering supplier status (for QSEs, basis must be selected); date signed by deponent and Commissioner of Oath must be same; Commissioner cannot be employee or ex officio of the enterprise.
Contractual Terms
Source: SDLi strategy - Supply and delivery of lubricants.pdf (unknown)Reporting and Monitoring: Suppliers shall submit quarterly reports per Data Collection Template on compliance with SDL&I obligations. Eskom reviews reports within 30 days and notifies in writing if obligations not met. Supplier must implement corrective measures before next report, failing which retention clauses invoked. Each contract accompanied by SDL&I Implementation Schedule, completed and returned to SDL&I representative for acceptance 28 days after contract award, used for monitoring and reporting.
Section
Source: SDLi strategy - Supply and delivery of lubricants.pdf (unknown)Specific goals: maximum 10/20 points added to price points, total rounded to two decimals. Contract awarded to highest scorer per PPPFA. B-BBEE status level points table as per standard preference point system. Documents required to claim preference points: valid B-BBEE certificate (SANAS accredited) or sworn affidavit/CIPS affidavit, proof of ownership/shareholding (preferably CIPC) with breakdown, certified ID copies of shareholders, proof of disability where applicable, consolidated B-BBEE certificate for trust/consortium/JV. Tenderer failing to provide documentation will not be disqualified but may only score out of 90/80 for price and 0 for specific goals.
Description
Source: NEC (SC) Supply Contract for Kendal Power Station Lubricants.pdfSupply and delivery of lubricants on an 'as and when required' basis at Kendal Power Station for a period of 5 years (60 months).
Contact Information
Source: NEC (SC) Supply Contract for Kendal Power Station Lubricants.pdf (unknown)Eskom Holdings SOC Ltd, registered office at Megawatt Park, Maxwell Drive, Sandton, Johannesburg, 2199. Telephone: 011 800 2111. Supply Manager address: Eskom Holdings SOC Ltd, Kendal Power Station, Private Bag X7272, Witbank, 1035.
Submission Guidelines
Source: NEC (SC) Supply Contract for Kendal Power Station Lubricants.pdf (unknown)Returnable documents: the Form of Offer and Acceptance (C1.1) must be completed, signed by a duly authorised representative, and submitted with the tender. The offered total of the Prices (exclusive of VAT), VAT at 15%, and the total inclusive of VAT must be stated. Any deviations from the tender documents must be recorded in the Schedule of Deviations; no other deviations are valid. The tenderer must submit a preliminary programme for evaluation purposes within one week of the contract date. Failure to provide required securities, bonds, guarantees, proof of insurance, or other documentation within two weeks of receiving the signed contract constitutes repudiation.
Evaluation Criteria
Source: NEC (SC) Supply Contract for Kendal Power Station Lubricants.pdf (unknown)Bidders must be registered on the Central Supplier Database (CSD) and hold a valid tax clearance. B-BBEE status is required for preference points. The contract is awarded under the NEC3 Supply Contract (SC3) with Eskom's additional conditions Z1 to Z15. Joint ventures are jointly and severally liable. The Supplier must notify Eskom of any B-BBEE status change within 7 days and submit an updated verification certificate within 30 days; a decrease in status may lead to re-negotiation or termination.
Technical Specifications
Source: NEC (SC) Supply Contract for Kendal Power Station Lubricants.pdf (unknown)Supply and delivery of lubricants on an 'as and when required' basis to Kendal Power Station for 5 years (60 months). Goods include hydraulic oil, open gear grease, turbine oil, diesel engine oil, and other specified lubricants with stated quantities and units. Delivery place: Eskom Holdings SOC Ltd, Kendal Power Station, Private Bag X7272, Ogies/Witbank, 1035. Supplier must deliver material in good quality, on time, complete purchase order lines, provide transport, and bear transport liability. Supplier must give notice of delivery, check packing and marking, arrange access, and provide packing lists, invoices, delivery notes, test results, and maintenance manuals. Defects date is 52 weeks after delivery; defect correction period is 4 weeks.
Methodology
Source: NEC (SC) Supply Contract for Kendal Power Station Lubricants.pdf (unknown)Supply requirements include delivering material in good quality, on time, complete purchase order lines, providing transport to Kendal Power Station, and carrying liability of transport. Delivery place: Eskom Holdings SOC Ltd, Kendal Power Station, Private Bag X7272, Ogies/Witbank, 1035. Actions during supply: give notice of delivery, check packing and marking, contract for transport, pay costs of transport, arrange access, load and unload. Information to be provided: packing lists, invoices, delivery notes, test results, and maintenance manuals.
Quality Management
Source: NEC (SC) Supply Contract for Kendal Power Station Lubricants.pdfDefects date is 52 weeks after delivery. Defect correction period is 4 weeks, depending on defect, after inspection and completion date to be agreed by both parties.
Pricing Schedule
Source: NEC (SC) Supply Contract for Kendal Power Station Lubricants.pdfPricing data includes pricing assumptions and a price schedule with items such as hydraulic oil, open gear grease, turbine oil, diesel engine oil, gear oil, solvent degreaser, general purpose grease, compressor oil, and heat transfer fluid, with quantities and units specified. Lump sum items and rates per quantity. No adjustment to lump sum prices if quantities differ from tender estimate; changes only via compensation events.
Financial Requirements
Source: NEC (SC) Supply Contract for Kendal Power Station Lubricants.pdf (unknown)Payment terms: 30 days after submitting an undisputed tax invoice; 60 days if total contract value is R50 million and above. Interest at prime rate (365-day year) charged by Standard Bank of South Africa Limited. Currency: South African Rand. Pricing per NEC3 Supply Contract (SC3) price schedule; lump sum items and rates per quantity. No adjustment to lump sum prices if quantities differ from tender estimate; changes only via compensation events. Supplier must include costs for defect correction and spread costs of unspecified work across other prices. Delay damages: 2.5% of purchase order item value per week, up to a maximum of 10%. Low performance damages: 1.5% of line item value per day, up to a maximum of 5%.
Compliance Requirements
Source: NEC (SC) Supply Contract for Kendal Power Station Lubricants.pdf (unknown)B-BBEE minimum level: 1. Supplier must notify Purchaser within 7 days of any change in B-BBEE status, submit updated verification certificate within 30 days, and if status decreases, Purchaser may re-negotiate or terminate. Supplier must comply with all applicable health, safety, and environmental laws and ensure subcontractors comply. Asbestos removal and disposal must be done by a registered asbestos contractor at Purchaser's expense. Supplier must provide insurances per Insurance Table A; Purchaser provides insurances per Insurance Table B. Nuclear liability: Purchaser indemnifies Supplier against nuclear damage, except for unlawful intent or unauthorized presence. Supplier must not cede, delegate, or assign rights without written consent. Joint ventures are jointly and severally liable.
Health & Safety
Source: NEC (SC) Supply Contract for Kendal Power Station Lubricants.pdfSupplier must take reasonable precautions to maintain health and safety of persons, comply with all applicable health & safety laws and regulations, and ensure subcontractors comply. Asbestos management: Purchaser ensures ambient air conforms to asbestos standards; Supplier may perform parallel measurements; control measures per AAIA-approved work plan; removal/disposal by registered asbestos contractor at Purchaser's expense.
Environmental
Source: NEC (SC) Supply Contract for Kendal Power Station Lubricants.pdfSupplier must comply with all applicable environmental laws and regulations and ensure subcontractors comply. Asbestos removal and disposal must be done by a registered asbestos contractor at Purchaser's expense, in line with South African legislation.
Contractual Terms
Source: NEC (SC) Supply Contract for Kendal Power Station Lubricants.pdfContract is NEC3 Supply Contract (SC3) between Eskom Holdings SOC Ltd and Supplier. Law: South African law. Language: English. Period for reply: 24 hours for emergencies, 1 week for other matters. Delivery dates per agreed lead times or purchase order. Defects date: 52 weeks after delivery. Defect correction period: 4 weeks. Payment assessment interval: 5 days after delivery. Payment within 30 days (60 days if contract value R50 million and above). Interest at prime rate. Supplier's liability for indirect/consequential loss limited to R0. Liability for property damage limited to deductible. Total liability limited to total contract price. End of liability: 24 months after delivery. Adjudicator from ICE-SA. Tribunal: arbitration in Johannesburg. Delay damages: 2.5% per week up to 10%. Low performance damages: 1.5% per day up to 5%. Additional conditions Z1-Z15 cover cession, joint ventures, B-BBEE status changes, confidentiality, waiver, health/safety/environment, tax invoices, compensation events, limitation of liability, termination, ethics, insurance, nuclear liability, and asbestos.
Important Dates
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown){"closingDate":"27 January 2025"}
Contact Information
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown){"name":"__________________________________________________________","email":null,"phone":null,"department":null,"address":null}
Submission Guidelines
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)The E-Tendering Training Acknowledgement Form is a mandatory returnable document. It must be fully completed, signed by an authorised representative, and submitted to Eskom within the prescribed period. Failure to do so will render the bidder non-responsive and disqualified from the procurement process.
Returnable Documents
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)The E-Tendering Training Acknowledgement Form is a mandatory returnable document. It must be fully completed and submitted to Eskom within the prescribed period; failure to do so will render the tenderer non-responsive and disqualified from the procurement process.
Evaluation Criteria
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)Submission of the E-Tendering Training Acknowledgement Form is mandatory for responsiveness. The form must be fully completed and signed by an authorised representative.
Compliance Requirements
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)No specific requirements found
Important Dates
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)Clarification meeting: 18 August 2026 at 10h00, venue Horticulture, Kendal Power Station. Non-compulsory; bidders must confirm attendance with the Eskom Representative. If a meeting is made compulsory, non-attendance disqualifies.
Clarification queries must be submitted 5 working days before the tender deadline.
Tender validity period: 150 days from closing date.
Briefing Session
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)Non-compulsory clarification meeting on 18 August 2026 at 10h00, venue Horticulture, Kendal Power Station. Bidders must confirm attendance with the Eskom Representative. If a meeting is made compulsory, non-attendance disqualifies.
Contact Information
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)Eskom Representative: Caxwell Mkhabele, Tel 013 647 6541, E-mail [email protected].
Procurement Manager: Thandi Mathye, Generation: Kendal Power Station.
Fraud and corruption reporting: 0800 11 2722 or [email protected].
Submission Guidelines
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)Tenders must be submitted electronically via the Eskom e-tendering site (https://etendering.eskom.co.za) before the closing date and time. No hard copies will be accepted. Documents must be uploaded in PDF format under the folders Technical, Commercial, Financial, and other. The upload size per document is 500 megabytes and total submission is restricted to 4 gigabytes. No zip/condensed files can be uploaded. If resubmitting, only the latest version will be accepted; previous submissions become null and void. Ensure the submission status is indicated as complete. Late tenders will not be accepted.
Mandatory returnables at closing (disqualifiable if missing or unsigned):
Non-disqualifiable returnable at closing:
Returnables required prior to contract award:
Disqualification risks:
Returnable Documents
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)Mandatory returnables at closing (disqualifiable): Authorisation Form (Annexure A), Acknowledgement Form (Annexure B), Tenderer's Particulars (Annexure C), Integrity Pact Declaration (Annexure D), CPA for local/foreign goods (Annexures E/F), SBD 6.2 and Annexures G1-G4, SBD 1 (Annexure H), SBD 4 (Annexure J), E-tendering Help Manual acknowledgement, JV documents if applicable, tax clearance certificates, tax evaluation questionnaire, Employment Equity compliance, CIDB grading if applicable, completed NEC contract, pricing schedule in NEC contract, additional documents (ECSA/SACPCMP/CVs/permits). Non-disqualifiable returnables: SBD 6.1 Preference Points Claim Form (Annexure I). Returnables required prior to award: CSD registration, COIDA certificate, quality management system documents (ISO 9001), SHE documents (SHE Plan, Baseline Risk Assessment, COID letter, SHE Policy), environmental documents (Environmental Policy ISO14001, EMP, Spillage Management Plan, Waste Management Plan), financial statements for due diligence.
Evaluation Criteria
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)Evaluation stages:
Objective criteria are applicable; Eskom may award to a tenderer other than the highest scorer if objective criteria justify. Refer to attached SDL&I strategy. Reverse e-auction is not applicable.
Contractual requirements (CSD registration, SHEQ, financial viability) are not evaluation criteria; they are assessed after ranking and must be met prior to award.
Quality Management
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)Supplier must submit objective evidence of a QMS complying with ISO 9001:2015 (Category 3). Required documents: QMS manual or documented information describing the QMS and scope, Quality Policy aligned with strategic direction, completed and signed Form A, Quality Objectives, Internal audit procedure, Control of nonconforming outputs, Nonconformity and Corrective action procedure, Draft Contract Quality Plan, example of ITP/QCP on similar work, documented information for roles/responsibilities/authorities, and documented information for Control of Externally Provided Processes, Products and Services.
Pricing Schedule
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)Completed pricing schedule must be submitted in the NEC Contract. Only the price schedule submitted in the NEC contract will be evaluated. If cataloguing is required, pricing schedule must include a line item for cataloguing.
Financial Requirements
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)Pricing schedule: completed pricing schedule must be submitted in the NEC Contract. Only the price schedule submitted in the NEC contract will be evaluated.
Payment terms: for contracts below R50 000 000 (including VAT), Eskom pays within 30 days of receipt of undisputed invoices. For contracts above R50 000 000, payment within 60 days.
Eskom reserves the right to negotiate with preferred bidders if tendered prices are not market-related.
Due diligence: latest approved annual financial statements of the tendering company (not parent/holding) required, including background, signed director's report, signed auditor's/reviewer's/compiler's/accounting officer's report, statement of financial position, comprehensive income, changes in equity, cash flows, and notes. For unincorporated JV or SPV, each partner must submit its own statements. Public interest score and ITA34C required for non-audited South African entities.
Security for performance: if a performance bond or demand guarantee is required, tenderer must select at least two financial institutions from Eskom's approved list.
Compliance Requirements
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)Mandatory contractual requirement: CSD registration (CSD number/report) - required prior to award.
Additional contractual requirements (assessed after evaluation):
Eligibility criteria:
B-BBEE: proof of B-BBEE status level of contributor required - certificate from authorised body, sworn affidavit per B-BBEE Codes, or other prescribed requirement. SBD 6.1 Preference Points Claim Form (Annexure I) is non-disqualifiable but scores zero if not submitted.
Local content: SBD 6.2 Declaration Certificate for Local Production and Content (Annexures G1-G4) required if designated materials are included.
Employment Equity: designated employers must furnish proof of compliance, including submission of EE report to Department of Labour (South African tenderers only).
Tax: tax clearance certificate required from foreign tenderers with SA footprint not on CSD and local tenderers without SARS e-filing PIN. Foreign suppliers with no SA footprint complete SBD 1 but no tax proof required.
Health & Safety
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)SOW categorised as high risk. Returnables: Annexure B (Acknowledgement Form), SHE Plan (as per SHE Spec), Baseline Risk Assessment, Letter of good standing (valid COID certificate), SHE Policy. Work may only commence once the SHE file is approved. Suppliers given one opportunity to submit outstanding SHEQ documents within 7 working days; failure may render tender non-responsive.
Environmental
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)Supplier to provide Environmental Policy in terms of ISO14001:2015, signed Contractor's Environmental Management Plan (EMP) for site-specific activities, Spillage Management Plan for emergencies (oil, chemical, ash, coal), and Waste Management Plan.
Contractual Terms
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)Conditions of contract will be the NEC Engineering and Construction Contract. Tender must be for the whole of the contract. Alternative tenders are not allowed. Eskom reserves the right to negotiate with preferred bidders if prices are not market-related. Main contractors are discouraged from subcontracting with subsidiaries; if they do, it must be declared. Payment terms: 30 days for contracts below R50 million (incl. VAT), 60 days for above. Performance security may be required; if so, tenderer must select at least two Eskom-approved financial institutions.
Requirements
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)Eligibility criteria: not under restriction to do business with Eskom or State-Owned Companies; not a national of a sanctioned country; no conflict of interest; not on National Treasury restricted list or Tender Defaulters list; not restricted by Eskom; must not subcontract 100% of scope. Basic compliance: meet eligibility, submit complete tender with commercial, financial and technical information, submit mandatory returnables. Mandatory contractual requirement: CSD registration. Additional contractual requirements may include SHEQ and financial viability.
Section
Source: Invitation to Tender (ITT) or Request for Proposal (RFP) Template Rev. 28 - 21 April 2026 (004) (003).pdf (RFP)Functionality threshold 70%. Prices scored out of 90 points. Specific goals scored out of 10 points. Ranking using 90/10 system. Prices evaluated inclusive of VAT, corrected for arithmetical errors, excluding contingencies, adjusted for variations, NPV comparison, unconditional discounts considered. Objective criteria applicable; Eskom may award to other than highest scorer. Reverse e-auction not applicable.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
Kendal Power Station (Near Ogies,on Jhb/Witbank Road) - Ogies - Witbank - 2230
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
8
Last checked
12 Aug 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Supplies: General. Unlock full pricing strategies, bid frequency, and historical win rates.