Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
Eskom E-Tendering - Kriel - Eskom E-tender - 2271
Organization Type
GOVERNMENT
Published
25 Nov 2026
OCDS Reference
ocds-9t57fa-179824
ESKOM requires the refurbishment of coal plant chutes, rotary feeders, and tripper cars at matla power station under a five-year contract. Bidders must complete and sign the integrity declaration form (annexure a), disclosing any relationships with ESKOM or state employees and confirming compliance with fair tendering practices. The most consequential consideration is the strict integrity and disclosure obligations, as false declarations or undisclosed relationships can lead to tender rejection and action by ESKOM.
Continue with tenders sharing this issuer, category, or province.
Browse categories with current opportunities in this area.
Compare tender activity across provinces.
Explore organisations currently publishing tenders.
Tools and research to help you assess opportunities.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Browse categories with current opportunities in this area.
Compare tender activity across provinces.
Explore organisations currently publishing tenders.
Tools and research to help you assess opportunities.
Date & Time
Monday, 11 January 2027 - 10:00
Venue
MS TEAMS
Categories
Request for Bid(Open-Tender)
Eskom E-Tendering - Kriel - Eskom E-tender - 2271
AI Document Analysis Stages
Description
Source: SBD 1 - Invitation to Bid..pdf25 Nov
2026
Tender Published
Tender was published
11 Jan
2027
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Code of Ethics.pdf
Refurbishment of coal plant chutes, rotary feeders and tripper cars at Matla Power Station, contracted for a period of five (05) years. The work is procured by Eskom and closes on 11 January 2027 at 10:00.
No 5 ANNEXURE A Integrity Declaration Form (1).pdf
Eskom requires the refurbishment of coal plant chutes, rotary feeders and tripper cars at Matla Power Station over a five-year period. Bidders must submit a signed Integrity Declaration (Annexure A) covering declarations of interest and fair tendering practices.
Supplier Integrity Pack.pdf
Eskom - Standard Conditions of Tender - Copy.pdf
Declaration of Fair Bidding Practices.pdf
Refurbishment of coal plant chutes, rotary feeders, and tripper cars at Matla Power Station for a period of five years, issued by Eskom.
Conditions to tender.pdf
Refurbishment of coal plant chutes, rotary feeders and tripper cars at Matla Power Station in Mpumalanga, awarded as a five-year contract by Eskom Holdings SOC Limited. The work covers the ongoing refurbishment of coal handling plant equipment over the contract period.
Coal chutes tech Evaluation.pdf
Eskom Standard Condition.pdf
Eskom - Standard Conditions of Tender.pdf
Contractors Assessment Form.pdf
Environmental Contractors Assessment Form - Copy.pdf
SBD 6.1 - Preference Points Claims Form..pdf
TAX EVALUATION.pdf
Eskom - Standard Conditions of Tender - final - Copy.pdf
SWORN AFFIDAVIT – B-BBEE QUALIFYING SMALL ENTERPRISE - GENERAL.pdf
Authorisation Form - final.pdf
SBD 6.2.pdf
Invitation to Tender (ITT) for Coal chutes.final.2.rev signed.pdf
Eskom Supplier Integrity Pact - 02 June 2023.pdf
Eskom Supplier Integrity Pact.pdf
Standard Bidding Document (SDB) 4_Annexure A.pdf
Environmental Contractors Assessment Form.pdf
Annexure L – Authority to Submit a Tender (Returnable Schedule) Template.pdf
Declaration of Fair Bidding Practices - Copy.pdf
Annexure C.pdf
Annexure B Safety Requirements.pdf
Annexure D.pdf
E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025 - Copy.pdf
Annexure E.pdf
SBD 1.pdf
Eskom - Standard Conditions of Tender - final.pdf
SBD 1 - Invitation to Bid..pdf
Eskom requires the refurbishment of coal plant chutes, rotary feeders and tripper cars at Matla Power Station, under a contract period of five years. Bids close on 11 January 2027 at 10:00.
Supplier Evaluation Pack Template for 01 March 2023 to 29 February 2024.pdf
Eskom requires the refurbishment of coal plant chutes, rotary feeders and tripper cars at Matla Power Station over a five-year period. Bidders must also complete Eskom's PAYE questionnaire for service contracts so that the contractor's tax status — independent contractor, personal service provider, labour broker or dependent contractor — can be established before payments are made.
SWORN AFFIDAVIT – B-BBEE EXEMPTED MICRO ENTERPRISE - GENERAL.pdf
Authorisation Form - Final.f.pdf
Refurbishment of coal plant chutes, rotary feeders and tripper cars at Matla Power Station over a five-year period, for Eskom. Bidders must submit a signed authorisation form identifying their organisation type and the individual authorised to bind them to the tender and to any contract arising from it.
Authority to submit a tender Nov 2012.pdf
Eskom requires the refurbishment of coal plant chutes, rotary feeders and tripper cars at Matla Power Station, under a contract running for five years. The work is tendered on a national basis.
Supplier_Evaluation_Pack_Template_for_01_March_2024_to_29_February_2025.pdf
Eskom requires the refurbishment of coal plant chutes, rotary feeders and tripper cars at Matla Power Station, covering a contract period of five years. The supporting pack is a PAYE tax-status questionnaire that establishes how payments to the contractor will be taxed, rather than a scope or pricing document.
No 4 SBD 6.2 Local Content in terms of PPR 2017.pdf
Refurbishment of coal plant chutes, rotary feeders and tripper cars at Matla Power Station, contracted by Eskom for a period of five years. Bids close on 11 January 2027 at 10:00.
Contractors Assessment Form - Copy.pdf
ESKOM requires the refurbishment of coal plant chutes, rotary feeders and tripper cars at Matla Power Station over a five-year period. Contractors working on site must complete an environmental contractor assessment covering scope, duration, hazardous substances, waste and permit obligations before work proceeds.
NDA Vendors.pdf
Eskom requires the refurbishment of coal plant chutes, rotary feeders, and tripper cars at Matla Power Station over a five-year period. The document provided is a confidentiality agreement (NDA) that bidders must sign before receiving project information.
Coal chutes final scope.pdf
Eskom requires a contractor to refurbish coal plant chutes, rotary feeders, and tripper cars at Matla Power Station over a five-year period. The work includes sandblasting, welding, replacing ceramic liners, and installing new control circuits and Vahle rail systems. The contractor must comply with strict safety, environmental, and quality management procedures.
No 11 Designated items Local Content percentages THRESHOLDS.pdf
Refurbishment of coal plant chutes, rotary feeders, and tripper cars at Matla Power Station for a period of five years. The work is for Eskom and is advertised nationally.
Eskom General Conditions of Purchase - 31 May 2024.pdf
Refurbishment of coal plant chutes, rotary feeders, and tripper cars at Matla Power Station, under a five-year contract with Eskom. The work involves ongoing maintenance and repair of these coal handling components to ensure operational reliability.
Supplier Risks identified Rev 1 Oct 2009.pdf
Refurbishment of coal plant chutes, rotary feeders, and tripper cars at Matla Power Station over a five-year period, issued by Eskom. The work involves risk assessment and compliance with the Works Information.
BINDING TENDER DOCUMENT.pdf
Refurbishment of coal plant chutes, rotary feeders, and tripper cars at Matla Power Station over a five-year period, issued by Eskom.
E-tendering Help Manual for supplier - 27 January 2025.pdf
Refurbishment of coal plant chutes, rotary feeders, and tripper cars at Matla Power Station, with the contract running for five years. The work is for Eskom and involves the maintenance and repair of coal handling equipment.
E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf
Refurbishment of coal plant chutes, rotary feeders and tripper cars at Matla Power Station over a five-year period. Bids close on 11 January 2027 at 10:00.
Attachment 5_ANNEXURE A Integrity Declaration Form.pdf
Refurbishment of coal plant chutes, rotary feeders and tripper cars at Matla Power Station, contracted for a period of five (05) years. The works are procured by Eskom and the bid closes on 11 January 2027 at 10:00. Bidders must submit a completed and signed Integrity Declaration (Annexure A) covering declaration of interest, fair tendering practices and authorisation to sign.
To download these documents and access AI-powered analysis, visit the main tender page.
Organization
EskomWin Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
R 325 200
Range
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
The tender is for the refurbishment of coal plant chutes, rotary feeders, and tripper cars at Matla Power Station for a period of five (05) years.
The successful bidder will be required to sign a written contract form (SBD 7).
Bid response documents may be deposited in the bid box situated at the street address (not specified in the document).
No further scope details are provided in the document.
Submission Guidelines
Source: SBD 1 - Invitation to Bid..pdf (TENDER)Submission method: bids must be delivered to the correct address by the stipulated time; late bids will not be considered.
All bids must be submitted on the official forms provided (not re-typed) or online.
Returnable forms and documents:
Disqualification risks:
Evaluation Criteria
Source: SBD 1 - Invitation to Bid..pdf (TENDER)Preference point system: subject to the Preferential Procurement Policy Framework Act 2000 and the Preferential Procurement Regulations, 2017.
B-BBEE points: a valid B-BBEE status level verification certificate or sworn affidavit (for EMEs and QSEs) is required to qualify for preference points.
No specific scoring split or minimum qualifying score is stated in the document.
Technical Specifications
Source: SBD 1 - Invitation to Bid..pdf (TENDER)The tender is for the refurbishment of coal plant chutes, rotary feeders, and tripper cars at Matla Power Station for a period of five (05) years.
The successful bidder will be required to sign a written contract form (SBD 7).
No further technical specifications are provided in the document.
Compliance Requirements
Source: SBD 1 - Invitation to Bid..pdf (TENDER)CSD registration: bidders must be registered on the Central Supplier Database (CSD) to upload mandatory information: business registration, directorships/membership, identity numbers, tax compliance status, and banking information for verification.
If not registered on the CSD, mandatory information (business registration, directorships, tax compliance status) may not be submitted with the bid; B-BBEE certificate or sworn affidavit must still be submitted.
Tax compliance: bidders must submit their unique SARS tax compliance PIN to enable the organ of state to view the taxpayer's profile and tax status.
Tax compliance status (TCS) may be obtained via e-filing (www.sars.gov.za) or a printed TCS may be submitted with the bid.
Consortia, joint ventures, and subcontractors: each party must submit separate proof of TCS/PIN/CSD number.
If no TCS is available but the bidder is registered on the CSD, a CSD number must be provided.
Foreign suppliers: must complete the questionnaire on residency, RSA branch, permanent establishment, and RSA income source. If the answer is no to all, no TCS/PIN is required.
B-BBEE: a B-BBEE status level verification certificate or sworn affidavit (for EMEs and QSEs) must be submitted to qualify for preference points.
Description
Source: Supplier Evaluation Pack Template for 01 March 2023 to 29 February 2024.pdfThe document is a PAYE questionnaire for service contracts with Eskom Group. It determines whether a contractor (individual, company, close corporation, or trust) is classified as an Independent Contractor, Personal Service Provider, Labour Broker, or Dependent Contractor for tax purposes. The questionnaire applies to the 2023/2024 tax year and must be completed truthfully by the contractor or authorised representative.
Important Dates
Source: Supplier Evaluation Pack Template for 01 March 2023 to 29 February 2024.pdf (unknown)Closing date: 11 January 2027 at 08:00
Contact Information
Source: Supplier Evaluation Pack Template for 01 March 2023 to 29 February 2024.pdf (unknown)Group Tax email: [email protected]
Submission Guidelines
Source: Supplier Evaluation Pack Template for 01 March 2023 to 29 February 2024.pdf (unknown)Returnable documents:
Submission method: Submit the completed pack to the Eskom contractor representative.
Disqualification risks:
Evaluation Criteria
Source: Supplier Evaluation Pack Template for 01 March 2023 to 29 February 2024.pdf (unknown)The questionnaire determines the contractor's tax classification (Independent Contractor, Personal Service Provider, Labour Broker, or Dependent Contractor) based on responses to a series of tests.
Key tests for companies/CCs/trusts (Evaluation Pack A):
Key tests for individuals (Evaluation Pack B):
Outcome: The classification determines whether PAYE is withheld and the IRP5/IT3(a) code used.
Technical Specifications
Source: Supplier Evaluation Pack Template for 01 March 2023 to 29 February 2024.pdf (unknown)The document is a PAYE questionnaire for service contracts with Eskom Group. It applies to contractors supplying services or labour to Eskom Holdings SOC Ltd and its subsidiaries. The questionnaire determines the contractor's tax classification for the 2023/2024 tax year.
Pricing Schedule
Source: Supplier Evaluation Pack Template for 01 March 2023 to 29 February 2024.pdfPAYE withholding rules based on contractor classification:
Financial Requirements
Source: Supplier Evaluation Pack Template for 01 March 2023 to 29 February 2024.pdf (unknown)PAYE implications based on classification:
Failure to sign required affidavits results in PAYE being withheld from payments.
Compliance Requirements
Source: Supplier Evaluation Pack Template for 01 March 2023 to 29 February 2024.pdf (unknown)No specific compliance requirements beyond the PAYE questionnaire. The questionnaire requires accurate completion and truthful declarations. Non-residents must sign Appendix 9 and be referred to Eskom Group Tax.
Section
Source: Supplier Evaluation Pack Template for 01 March 2023 to 29 February 2024.pdfThe evaluation is based on the contractor's responses to the questionnaire, which determine tax classification. Key tests include residence, employee exclusion, connected person services, 80% income test, place/control/supervision test, and dominant impression test. The outcome affects PAYE withholding and IRP5/IT3(a) codes.
Evaluation Criteria
Source: Attachment 5_ANNEXURE A Integrity Declaration Form.pdf (RFP)Disclosure obligations under the Integrity Declaration Form:
Pricing Schedule
Source: Attachment 5_ANNEXURE A Integrity Declaration Form.pdfFor joint ventures, the lead partner must be authorised to sign all documents and receive instructions and payments. A copy of the joint venture agreement, stating that all partners are jointly and severally liable for contract execution, must be attached to the tender.
Compliance Requirements
Source: Attachment 5_ANNEXURE A Integrity Declaration Form.pdf (RFP)Integrity Declaration Form (Annexure A):
Section
Source: Attachment 5_ANNEXURE A Integrity Declaration Form.pdfThe Integrity Declaration Form requires disclosure of any relationship between the tenderer and Eskom personnel involved in the tender process, as detailed in the evaluation criteria section.
Important Dates
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)Closing date: 27 January 2025
Submission Guidelines
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)Returnable documents:
Submission method: e-tendering solution (electronic).
Evaluation Criteria
Source: E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.pdf (unknown)Submission of a fully completed e-Tendering Training Acknowledgement Form is a precondition to bid. An incomplete form renders the tenderer non-responsive and disqualified.
Submission Guidelines
Source: Conditions to tender.pdf (TENDER)Submission method: sealed hardcopy tender, original plus copies as stated in the Tender Data.
Evaluation Criteria
Source: Conditions to tender.pdf (TENDER)Responsiveness test before detailed evaluation:
Evaluation procedure and criteria are stated in the Tender Data (not included in this document).
Disqualification risks:
Technical Specifications
Source: Conditions to tender.pdf (TENDER)Scope: Refurbishment of coal plant chutes, rotary feeders, and tripper cars at Matla Power Station.
Financial Requirements
Source: Conditions to tender.pdf (TENDER)Pricing:
Insurance:
Security for performance:
Costs:
Compliance Requirements
Source: Conditions to tender.pdf (TENDER)CIDB registration:
COIDA / Compensation Fund:
Sheq:
Eskom standing:
General:
Section
Source: Conditions to tender.pdfEvaluation includes a responsiveness test and detailed evaluation per the Tender Data.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
Eskom E-Tendering - Kriel - Eskom E-tender - 2271
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
48
Last checked
25 Nov 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Get deep intelligence on Services: General. Unlock full pricing strategies, bid frequency, and historical win rates.
Learn how to submit a winning bid with these related articles
Everything South African general contractors need to know about how to write a winning tender proposal without an in-house bid team in gauteng — covering CSD, BBBEE, step-by-step processes, common disqualification mistakes, and how Tenders-SA.org helps you find and win relevant contracts in Gauteng.
Your meticulously crafted General sector tender submission can be disqualified for a single, seemingly minor compliance oversight. The reality for South African contractors is that technical competence is no longer sufficient; it is underpinned by a non-negotiable framework of documentary compliance. This regulatory guide: mastering CSD and BBBEE compliance for general sector tenders in south africa provides a comprehensive, step-by-step breakdown of the mandatory registrations and certificates you must secure and present. We detail the precise requirements for CSD, BBBEE, SARS TCS, CIPC, and COIDA, explaining their function within the procurement ecosystem governed by the PFMA and PPPFA. Learn the actionable steps to prepare your business, avoid the most common disqualifying errors, and leverage technology to streamline your compliance process for successful bidding in 2026 and beyond.
For South African General contractors, the path to government procurement is paved with non-negotiable regulatory requirements. The most common barrier to entry is not a lack of capability, but a failure to master the foundational compliance frameworks that govern every bid. This complete regulatory guide to CSD and BBBEE compliance for General sector tender suppliers in South Africa demystifies the process. It provides a meticulous, step-by-step field manual for ensuring your company is fully compliant and audit-ready, enabling you to confidently access the R billions in opportunities across infrastructure maintenance, facilities management, and service delivery within the General sector.
This definitive guide provides General sector contractors with the precise, actionable steps required to achieve and maintain CSD and BBBEE compliance for South African public tenders in 2026. Authored by Dr. Sarah Mokwena, a Legal Compliance Specialist, it meticulously walks through the regulatory framework, mandatory registrations, and the critical documentation needed to avoid disqualification. We dissect the common, costly errors made during submission and provide a clear checklist to ensure your bid is responsive and competitive. Learn how to navigate the Central Supplier Database, validate your BBBEE status, and integrate compliance into your tender preparation process.
💡 Want more tendering tips and strategies?
Explore Our Blog