Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
Robert Sobukwe - Bellville - Bellville - 7507
Organization Type
GOVERNMENT
Published
07 Aug 2026
OCDS Reference
ocds-9t57fa-165036
TRANSNET is procuring preventative, corrective, emergency and ad hoc maintenance services for its buildings, wet services, electrical and mechanical assets in bellville and surrounding areas within a 300 km radius of the bellville tp depot, on an as-and-when-required basis for 36 months. Bidders must hold a CIDB 6 gb grading and provide trade-tested artisans in plumbing, electrical and refrigeration/air-conditioning, with a minimum technical score of 70 out of 100 to qualify.
Bidders must hold a CIDB 6 GB grade.
Bidders must submit a trade test certificate for a Plumbing Artisan.
Bidders must submit a trade test certificate for an Electrician Artisan.
Bidders must submit a Refrigeration and/or Airconditioning Artisan certificate.
Bidders must submit proof of registration as an Electrical contractor with the Department of Labour (this may be subcontracted).
Bidders must achieve a minimum technical score of 70 out of 100 (70%).
Technical evaluation awards points for key personnel experience, quality plan (ISO 9001 accreditation earns full points), company experience in similar general building works, method statement, and health and safety plan.
Date & Time
Wednesday, 26 August 2026 - 16:00
Venue
https://teams.microsoft.com/meet/353561102425784?p=7LJLXVoPYIhJbK7Dut
Categories
Request for Bid(Open-Tender)
Robert Sobukwe - Bellville - Bellville - 7507
AI Document Analysis Stages
Review in progress
The information shown on this card is preliminary. Our procurement team is currently finalising the submission guidelines, evaluation criteria, technical specifications, financial requirements, and compliance sections so you have a clean, bid-ready summary to work from. Document being finalised: RFP.pdf. You don’t need to refresh — this page will pick up the updated review automatically.
07 Aug
2026
Tender Published
Tender was published
26 Aug
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
RFP.pdf
Transnet SOC Ltd is procuring preventative maintenance, corrective maintenance, emergency maintenance, and ad hoc services for its assets in Bellville and surrounding areas. The contract will be for a period of 36 months.
C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf
Transnet SOC Ltd is procuring preventative maintenance, corrective maintenance, emergency maintenance, and ad hoc services for its assets in Bellville and surrounding areas within a 300km radius for a period of 36 months
Technical Evaluation Criteria GBM Bellville.pdf
Transnet SOC Ltd is procuring preventative maintenance, corrective maintenance, emergency maintenance, and ad hoc services for its assets in Bellville and surrounding areas. The contract will be for a period of 36 months.
To download these documents and access AI-powered analysis, visit the main tender page.
Secure Transnet tenders using AI Matching & Recommendations, logistics infrastructure intelligence, compliance analysis, and application support for rail, ports, and pipelines.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubLearn how to submit a winning bid with these related articles
Median Estimate
R 344 781
Range
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Description
Source: Technical Evaluation Criteria GBM Bellville.pdf (unknown)Provision of preventative, corrective, emergency, and ad hoc maintenance for Transnet assets (buildings, wet services, electrical, and mechanical) in Bellville and surrounding areas within a 300 km radius of the Bellville TP Depot, on an as-and-when-required basis for 36 months.
Contact Information
Source: Technical Evaluation Criteria GBM Bellville.pdf (unknown){"name":null,"email":null,"phone":null,"department":"of Labour","address":null}
Evaluation Criteria
Source: Technical Evaluation Criteria GBM Bellville.pdf (unknown)Technical evaluation is scored out of 100. Bidders must achieve a minimum of 70 points (70%) to qualify. The evaluation covers key personnel experience, quality plan, company experience, method statement, and health and safety plan. Points are awarded per sub-criteria as detailed in the technical specification.
Technical Specifications
Source: Technical Evaluation Criteria GBM Bellville.pdf (unknown)Scope: Preventative, corrective, emergency, and ad hoc maintenance for Transnet assets (buildings, wet services, electrical, and mechanical) in Bellville and surrounding areas within a 300 km radius of the Bellville TP Depot. Contract period: 36 months, on an as-and-when-required basis.
Mandatory gatekeepers (disqualification if not met):
Technical evaluation sub-criteria (maximum 100 points):
Experience & Qualifications
Source: Technical Evaluation Criteria GBM Bellville.pdf (unknown)Proof of experience must be attached on client letterhead in the form of award letter, reference letter, or contract with client contact details, project title, and description of works.
Quality Management
Source: Technical Evaluation Criteria GBM Bellville.pdf (unknown)Quality Plan: up to 15 points. Points based on coverage of six key elements: Quality Policy, Quality Manual, Organizational Structure & Responsibility, Internal Process, Continuous Improvement, Document Control. ISO 9001 accreditation earns full 15 points. Partial coverage earns 3, 6, 9, or 12 points depending on number of elements included.
Compliance Requirements
Source: Technical Evaluation Criteria GBM Bellville.pdf (unknown)Mandatory gatekeepers (disqualification if not met):
Returnable forms (standard Transnet/National Treasury):
Health & Safety
Source: Technical Evaluation Criteria GBM Bellville.pdf (unknown)Health and Safety Plan: up to 20 points. Points based on coverage of fifteen key elements: Health and Safety Policy, Hazard Identification and Risk Assessment, Legal and Other Requirements, Health and Safety Objectives, Resources/Accountabilities/Responsibilities, Competence/Training/Awareness, Communication/Participation/Consultation, Operational Control, Emergency Preparedness and Response, Management of Change, Sub-contractor Alignment, Incident Reporting and Investigation, Non-conformance and Action Management, Performance Assessment and Auditing, Measuring and Monitoring. Partial coverage earns 4, 8, 12, or 16 points depending on number of elements included.
Requirements
Source: Technical Evaluation Criteria GBM Bellville.pdf (unknown)Registration as an Electrical contractor can be subcontracted. Bidders who fail to submit all mandatory requirements shall be disqualified.
Section
Source: Technical Evaluation Criteria GBM Bellville.pdf (unknown)Technical scoring: Minimum threshold is 70/100 (70%). Maximum possible score is 100.
Important Dates
Source: RFP.pdf (RFP)Non-compulsory clarification session: the briefing date corresponds with the system-generated closing date and time; attendance is not compulsory but the certificate of attendance is a returnable document. Closing date and time: as per the TDPS system-generated date and time. Tender validity period: 12 weeks from the closing date; bidders may be asked to extend it.
Contact Information
Source: RFP.pdf (RFP)Employer's Agent: Senior Buyer, name Seipati Sebakamotse, address Transnet Park, Bellville, Cape Town. Email: [email protected]. Submission is via the e-Tender Submission Portal (https://transnetetenders.azurewebsites.net). Fraud and corruption may be reported to Tip-offs Anonymous at 0800 003 056 or [email protected].
Submission Guidelines
Source: RFP.pdf (RFP)Submissions are electronic only, via the Transnet e-Tender Submission Portal at https://transnetetenders.azurewebsites.net. Uploads must be completed before the closing time; late tenders are rejected. Each upload is limited to 30mb and multiple uploads are permitted; upload well in advance to avoid technical issues. Telephonic, telegraphic, facsimile or e-mailed offers are not accepted. Returnable documents must be uploaded together and include: CIDB certificate (6GB or higher), trade test certificates for Plumbing, Electrician, and Refrigeration/Air-conditioning artisans, proof of registration as an electrical contractor with the Department of Labour (may be subcontracted), TAX Clearance Certificate with PIN, B-BBEE certificate or sworn affidavit, CSD registration proof, Letter of Good Standing from the Compensation Fund, and certificate of attendance of the non-compulsory clarification session. Additional returnables include: Authority to Submit Tender, Non-Disclosure Agreement, RFP Declaration Form, Breach of Law disclosure, Certificate of Acquaintance, Service Provider Integrity Pact, Supplier Code of Conduct, two years' audited financial statements, enterprise questionnaire, specific goals points claim, Form of Offer and Acceptance, Contract Data, pricing schedule, price list, service information, and site information. All returnable schedules must be completed and signed; failure to provide mandated documents disqualifies the bid.
Evaluation Criteria
Source: RFP.pdf (RFP)Evaluation proceeds in stages: Stage One (eligibility) requires CIDB grading 6GB or higher, plus the mandatory artisan and electrical contractor certificates; failure disqualifies. Stage Two (functionality) is scored by at least three evaluators on Management and CVs of key persons (based on experience of Electrical, Plumbing, and Air-conditioning/Refrigeration artisans), Quality Plan, Company Previous Experience, Method Statement for General Building maintenance works, and Health and Safety Plan; the maximum score is 100 and the minimum qualifying threshold is 70 points. Stage Three (price and preference) applies the 80/20 preference points system under Preferential Procurement Regulations 6 and 7. Functionality is a pass/fail gate; bidders below 70 are disqualified and not evaluated further. The procedure is Functionality, then Price and Preference.
Technical Specifications
Source: RFP.pdf (RFP)The scope covers preventative, corrective, emergency and ad hoc maintenance of Transnet assets (buildings, wet services, electrical and mechanical) in Bellville and surrounding areas, within a 300km radius measured from the Bellville TP Depot, on an 'as and when required' basis for 36 months. The contract is an NEC3 Term Service Contract. The tenderer must provide qualified artisans: a licensed electrician, a plumbing artisan, and an air-conditioning/refrigeration artisan, each with specified experience and trade test certificates. The works include general building and civil maintenance, with a method statement required covering health and safety, maintenance approach, quality control/assurance, applicable standards, compliance to maintenance schedules and key performance indicators. A Health and Safety Plan is required covering 15 key elements including policy, risk assessment, legal requirements, training, operational control and incident reporting.
Financial Requirements
Source: RFP.pdf (RFP)The tender is subject to the 80/20 preference points system, applicable where the financial value of responsive tenders is equal to or below R50 million inclusive of all applicable taxes. Bidders must submit two years' audited financial statements as a returnable document. Transnet may request audited financial statements for due diligence and may conduct a risk analysis on the preferred tenderer, including assessing unduly high or low tendered rates. Price is evaluated after functionality. The employer is not committed to accept the lowest priced tender and may go to the open market if quoted rates are unreasonable. Pricing schedule and price list are returnable documents.
Compliance Requirements
Source: RFP.pdf (RFP)Mandatory eligibility: CIDB registration in grading designation 6GB or higher for General Building works; JV members must each have CIDB registration with the lead partner not lower than one level below the required grading, and the combined grading must meet 6GB or higher. Submit a certified copy of the signed JV agreement. Mandatory returnables: CIDB certificate, trade test certificates for Plumbing and Electrician artisans, Refrigeration/Air-conditioning artisan certificate, and proof of registration as an electrical contractor with the Department of Labour (may be subcontracted). Essential returnables: valid TAX Clearance Certificate with TCS PIN, B-BBEE certificate from a SANAS-accredited verification agency (or a sworn affidavit for EMEs/QSEs with 51%+ black ownership), proof of CSD registration, Letter of Good Standing from the Compensation Fund (COID), and certificate of attendance of the non-compulsory clarification session. The RFP Declaration Form and Compulsory Enterprise Questionnaire must disclose any conflicts of interest; bidders must not appear on the Register of Tender Defaulters or Transnet's restricted list, and must disclose any serious breach of law in the past five years. A Non-Disclosure Agreement and Service Provider Integrity Pact are required. Tenders must be in English; alternative offers are not considered.
Description
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)The scope covers preventative, corrective, emergency, and ad hoc maintenance for Transnet assets (buildings, wet services, electrical, mechanical) in Bellville and surrounding areas within a 300 km radius, on an as-and-when basis, for 36 months. Work is issued via Task Orders; the Employer is not obliged to issue any Task Order and liability is limited to each Task Order's price.
Important Dates
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)Closing time: 16h00. No briefing session is stated.
Contact Information
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)No specific contact names, emails, or phone numbers are provided in the extracted document.
Submission Guidelines
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)Returnable documents:
Employer's site entry and security rules apply: permits, site regulations, employee lists with identity numbers, and conduct requirements. Contracted staff must be English-speaking, physically fit, and presentable; serious breaches may lead to removal from the premises.
Evaluation Criteria
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)Evaluation includes SBD 4 (Declaration of Interest), SBD 6.1 (Preference Points Claim), SBD 6.2 (Declaration for Local Production and Content), and CIDB grading. Training and evaluation costs under the contract are shared between the Service Manager and the Contractor.
Technical Specifications
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)Scope covers preventative, corrective, emergency, and ad hoc maintenance for Transnet assets (buildings, wet services, electrical, mechanical) in Bellville and surrounding areas within a 300 km radius, as and when required.
Methodology
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)The Contractor must submit a Contractors Plan / Maintenance Plan within 3 months of notification of acceptance. The plan must be approved by the Employer; no deviation from programmed dates is allowed. The first payment certificate is only passed after plan approval. The Contractor must work in accordance with the plan and ensure minimal disruption to installations. Procedures for medium and high voltage work: notify Service Manager 5 working days in advance, obtain permits, and use trained/certified personnel. The Contractor must provide detailed feedback reports daily or as required during emergencies, attend management meetings, and submit monthly written reports on services rendered.
Quality Management
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)Installations must comply with SANS standards and Employer requirements. Specific electrical compliance: plug circuits labelled at source and outlet, max 8 plugs per new circuit, earth leakage tests, light circuits max 14 lights, correct lamp ratings, distribution board labelling and blank covers, earth leakage devices must disconnect both phase and neutral, earthing conductors must be crimp-ferruled/lugged/soldered, bonding conductor at least 2.5mm², earth continuity path not exceeding 0.2 Ω. Extra low voltage lighting: transformer output max 25 A, conductor size not less than 1.5mm², secondary circuit current sum not exceeding 90% of transformer rating. The Contractor must check and maintain Certificates of Compliance, reporting defects to the Service Manager. All checks and tests must be recorded in the site maintenance register.
Pricing Schedule
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)Labour rates during normal working hours plus material content (excluding equipment) based on proven costs (supplier quotations with deductions for discounts, rebates, recoverable taxes) plus agreed percentage mark-ups. Materials not covered in the contract are charged at net cost plus a fee. The Employer may obtain its own quotations for materials and the Contractor must consider the lowest price. Transport and off-loading costs are included in the bill of activity schedules. Job cards must break down costs into labour (for after-hours work) and materials (for non-activity schedule work). Guarantees for workmanship and repairs must be stated on invoices.
Financial Requirements
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)Pricing is based on labour rates for normal working hours plus material content (excluding equipment) using proven costs with agreed percentage mark-ups.
Compliance Requirements
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)Comply with the Occupational Health and Safety Act, 1993, and all relevant regulations.
Health & Safety
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)Contractor must comply with the Occupational Health and Safety Act, 1993, and keep a safety file on site. All relevant documentation (OHS Act, SANS 10142-1 & 2, SANS 10400, local by-laws, fire regulations, BCEA, Hazardous Substances Act, National Water Act, CIDB Act) must be kept on site. Work on high voltage equipment requires training and certification (ORHVS or equivalent), and access is only permitted with Transnet's competent person. The Service Manager must be notified 5 working days in advance for high voltage work. Site entry and security control apply, including permits and employee lists. The Contractor must protect the Employer and employees from injury and damage, and is liable for any damage caused. Emergency repairs must be reported immediately. All incidents must have a flash/notice report within the same shift and a detailed report within 48 hours.
Contractual Terms
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)close corporation incorporated or registered in terms of any law, and other body of persons corporate
or unincorporated.
or corresponding to criteria and intended to reduce the probability of failure or the performance
degradation of an Installation or equipment.
“property” means any movable, immovable or intellectual property or any right to such property.
“repair” means put into good condition after damage or wear, any component that forms part of the
3.1. Service Information:
3.1.1. Task orders will be issued by the Service Manager on an “as and when” required basis. The
liability of the Employer is limited to the total of the Prices stated in the specific Task Order and
Contract C3.1
Part C3: Scope of Work Service Information
3.3.14. Inform the Employer of all improvements or revisions related to the Installation. These
notifications shall take the form of technical notices or sales releases under a covering letter from
the Contractor.
3.3.15. Approval given by the Employer shall not relieve the Contractor from responsibility for due
performance of this Contract and adherence to Technical Information provided by the Employer.
3.3.16. Protect the Employer and Employer’s employees against all losses, expenses, demands, errors
or omissions, including faulty design and / or detailing of the Contractor, its subContractors,
agents or employees in the provision of any documentation under the terms of the Contract. To
this end, it shall be the Contractor’s responsibility to arrange professional indemnity cover through
an insurance company acceptable to the Employer, the limits of such cover to be determined by
the Employer in relation to the Service.
3.3.17. Carry out the various service activities as detailed in the maintenance plan. The schedules clearly
state the frequencies at which these services are to be performed i.e., on a weekly, monthly,
quarterly, six monthly etc. basis. The maintenance plan shall not limit in any way the Contractor’s
responsibility to undertake whatever tasks are required during this Contract period to ensure
achievement of the maintenance objectives on receival of request from Employer.
3.3.18. Ensure that the Installation at all times comply with provisions of all Laws, Provincial Ordinances,
3.5.9. Should repairs not be possible within the downtime as indicated in this clause, Emergency call
out services and downtime of equipment above, it will be the responsibility of the Contractor to
obtain extension of time. The request must describe the breakdown, the cause of it, and state
clearly all the reasons for the extension and the actual extension required in regard to the repair.
3.5.10. No extra payment will be made for the standby service availability and attendance to breakdowns
or other emergencies whether or not during or after normal working hours and the costs thereof
shall be included in the Price list/ Rate.
3.5.11. All breakdowns shall be analysed by the Contractor and relevant action shall be taken. The fault
analysis (call-out rate) shall be compiled by the Contractor and shall be recorded. This history
shall be kept for at least three (3) years
3.5.12. Failure of the Contractor to meet the response-time or downtimes under normal circumstances
may indicate the Contractor’s inability to provide the required Service and may invoke termination
of this Contract.
Contract C3.1
Part C3: Scope of Work Service Information
Contractor as indicated in Low Service Damages, Table 1 below.
4.1.2. The Employer’s right to impose penalties does not in any way detract the Employer’s right to claim
damages instead of penalties in the event of a breach by the Contractor of any or all of the terms
and conditions of this Agreement.
Table 1: Low Service Damage
(Contractor’s delays in responding to the 0.5% of the Task Order value
emergency call-out as set out in clause 3.5 - 10% of the Task Order value per hour Emergency Call Out Service and Downtime
of Equipment.)
2% of the Task Order value per
Rework due to poor workmanship 10% of the Task Order value day
1% of the Task Order value per No response of NCR within 3 days 10% of the Task Order value day
The Low Service Damage is applicable per Task Order.
Value of Low Service Damage is the minimum penalty per Task Order to be imposed on a Contractor in an
event of such breach. The maximum penalty to be imposed per Task Order per breach is limited to 10% of the
this Contract in a clean, tidy and sanitary condition and shall at the termination of this Contract for
whatsoever reason, reinstate any such facility to the same condition in which it was when handed
to the Contractor, fair wear and tear excepted. The Contractor will be liable for all electricity cost.
Contract C3.1
Part C3: Scope of Work Service Information
4.2.16. If the Employer requires any information regarding any of the employees of the Contractor who are
involved in the rendering of the Service in terms of this Contract, the Contractor will furnish such
available information immediately.
4.3.Deliverables
4.3.1. The service Contractors shall submit the following reports, attached to all invoices:
4.3.1.1. Report on services delivered/performed;
4.3.1.2. Service delivered performance;
4.3.1.3. Chemicals used;
4.3.1.4. Completed checklist where applicable;
4.3.1.5. Ad hoc services requested where applicable;
4.3.1.6. Any and all staff and labour issues that can affect service delivery to Transnet;
4.3.1.7. Incident report summary as compiled. All incidents shall be reported as soon as they occur and
a flash/notice report generated within the same shift. A detailed investigative report with
corrective and preventative detail shall be submitted within 48 hours from the occurrence of the
incident.
4.3.2. The weekly and monthly reports shall have a summary of key issues affecting the plant, major
breakdowns etc. The Employer reserves the right to alter the format and information required on this
report.
4.4.Documentation Control
4.4.1. The Employer will provide the Contractor at the appropriate times with the Technical Information
necessary to enable the Contractor to complete the Services in accordance with the Accepted Plan
and schedules. All Technical Information shall be and remains the property of the Employer and on
demand and on termination of the Contract shall be returned to the Employer.
4.4.2. During the progress of the Services/Task and prior to their completion, the Contractor will submit to
the Employer any Documentation as requiring submission to the Employer prior to completion of the
the terms of the Contract. To this end, it shall be the Contractor’s responsibility to arrange
professional indemnity cover through an insurance company acceptable to the Employer, the limits
of such cover to be determined by the Employer in relation to the Service.
4.4.11. The Contractor shall inform the Employer in writing prior to carrying out of any modification to the
existing Installation by the Contractor, even if this modification may benefit the Installation or if the
cost of this modification is for the Contractor's account.
4.4.12. The Contractor shall inform the Employer of all improvements or revisions related to the Installation.
the Accepted Plan and schedules. All Technical Information shall be and remains the property
of the Employer and on demand and on termination of the Contract shall be returned to the
are handed over to or have been officially accepted by the Employer.
5.1.16. The Contractor shall cede to the Employer any suppliers or factory guarantees of repaired or
replaced components and ensure that such guarantees are not jeopardized in any way. All
workmanship and repairs shall be guaranteed for twelve (12) months and so stated on all invoices
(failure to do so will delay payment).
5.1.17. All plant, parts, machinery etc., removed from Site / Affected Property for repair purposes shall be
signed for by the Contractor if it is removed from the Site. The appropriate receipt form (model
number, serial number, part etc.) shall be in duplicate form and available for inspection at any time
at either the Service Manager or called for from the Contractor.
5.1.18. The Contractor shall be responsible for the provisioning of all material, products, consumables
(disposable materials, grease, oils, hacksaw blades, insulation tape required, cleaning materials
etc.), replacement of nuts, bolts, washers, self-tapping screws etc. plus Equipment (including but
not be limited to ladders, scaffolding or specialised tools) that might be needed in order to render an
efficient Service at his own cost and included in the Price List / Rates.
5.1.19. The Employer reserves the right to take samples of any consumables and or material supplied by
the Contractor for analysis if deemed necessary
5.2.Correction of defects
5.2.1. If the Employer decide that any work done by the Contractor or any sub-contractor is defective or
not in accordance with the Contract or does not fulfil the requirements of the Contract and as soon
as reasonably practicable give to the Contractor notice in writing of such decision giving particulars
of the alleged defect, the Contractor shall with all speed make good the defects so specified.
5.2.2. The cost of making good such defects shall form part of the Contract Bill of schedule, including
where a defect is due to negligence or failure of the Contractor, his servants, agents or sub-
contractors, to exercise good faith or the standard or care which would normally be exercised by
duly qualified persons engaged in the business of the Contractor.
5.2.3. Should the Contractor fail to fulfil any of its obligations in terms of this Contract or should such
satisfaction of the Employer and should the Contractor fail to remedy such breach within the
timeframe from the date of written notice from the Employer calling upon to do so, the Employer
shall have the right without prejudice in terms of this Contract or at law, without further notice to the
5.2.3.1. Appoint another person other than the Contractor to complete the Service in question and to
recover from the Contractor all cost to complete the work in question plus an administration
costs of twenty-five (25) percent (%) of the price the other Contractor charged the Employer to
complete the Service, or
5.2.3.2. Cancel this Contract and recover from the Contractor any damages that it may suffer as a result
of such cancellation and / or breach.
Special Conditions
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)Employer's site entry and security control, permits, and site regulations apply. The Contractor must provide employee lists, identity numbers, and ensure conduct. Hours of work are normal working hours (07h30-16h00 Monday to Friday, excluding public holidays). Standby requirements and incident reporting are specified. Contracted staff must be able to communicate in English, be physically fit, and presentable. Serious breaches of conduct (e.g., absence without notification) may result in removal of staff from premises.
Section
Source: C3_1_Scope_of_Work_Term_Service_Contract_Western_Region_-_Bellville.pdf (unknown)Training and evaluation costs are shared between the Service Manager or Employer representative and the Contractor, as part of quality assurance.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
Level 200, Carlton Centre, 150 Commissioner St, Cbd, Johannesburg, 2001, South Africa
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
3
Last checked
07 Aug 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
subsidiary of Transnet
Contact
031-361-8589[email protected]www.transnet.netLevel 200, Carlton Centre, 150 Commissioner St, Cbd, Johannesburg, 2001, South Africa