Kendal Power Station - Ogies/Balmoral - Witbank - 1035
Organization Type
GOVERNMENT
Published
26 Aug 2026
OCDS Reference
ocds-9t57fa-167025
ESKOM is inviting bids for the provision of an ash dump chemical dust suppression system on an as-and-when-required basis for a period of five years at kendal power station. Bidders must submit electronically via the ESKOM etendering system and must complete and return mandatory forms including the e-tendering training acknowledgement form, a non-disclosure agreement, and a paye questionnaire with applicable appendices. The most consequential requirement is the mandatory e-tendering training acknowledgement form, as failure to fully complete and submit IT will render the bid non-responsive.
Submit electronically via the Eskom eTendering system at https://eTendering.eskom.co.za before the closing date and time of 2026-09-22 at 11:00.
Have a CSD (Central Supplier Database) number to gain access to the eTendering system.
Complete and submit the E-Tendering Training Acknowledgement Form (Annexure) – failure to fully complete and submit it will render the bid non-responsive.
Complete and sign the Non-Disclosure Agreement (NDA) – Eskom template 240-63152171 Rev 5.
Complete and sign the applicable PAYE Questionnaire (Evaluation Pack A for companies/CCs/trusts, or Pack B for individuals) with the correct affidavit from Appendices 1–10, as this determines tax classification and PAYE withholding.
Upload tender documents under the correct category (Technical, Commercial, Finance); each file must not exceed 50MB and total upload must not exceed 900MB.
Finalise and close the submission before the closing time; a timestamp is recorded and a confirmation email with the submission ID is sent – keep this email for reference.
Continue with tenders sharing this issuer, category, or province.
Return to this tender’s issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Date & Time
Tuesday, 22 September 2026 - 11:00
Venue
Horticulture Boardroom, Kendal Power Station
Important: Attendance at this briefing session is mandatory. Bids from suppliers who do not attend may be disqualified.
Compulsory clarification meeting date: 07 september 2026 time: 11:00am till 12:00am venue: horticulture boardroom, kendal power station transport will depart kendal power station main gate at 10:30am ID document compulsory for entrance
Categories
Request for Bid(Open-Tender)
Kendal Power Station - Ogies/Balmoral - Witbank - 1035
Tenders in this industry often require registration with these bodies.
Recommended Certifications
Having these can improve your winning chances: CA(SA) - Chartered Accountant, PMI-PMP (Project Management Professional), Prince2 Practitioner, Six Sigma Certification
AI Document Analysis Stages
Description
Source: Chemical Dust Suppression BoQ.pdf (unknown)26 Aug
2026
Tender Published
Tender was published
22 Sept
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
SCOPE OF WORK.pdf
Provision of an as-and-when chemical dust suppression service at Eskom's Kendal Power Station Ash Disposal Facility in Mpumalanga for a five-year (60-month) period. The contractor must supply and apply dust suppressant to inactive ash areas, ash hips and the emergency dump to prevent dust fall in line with the National Dust Control Regulations.
Chemical Dust Suppression BoQ.pdf
Eskom requires a contractor to provide a chemical dust suppression system for the ash dump at Kendal Power Station on an as-and-when-required basis for five years. The contract is an NEC3 Engineering and Construction Contract Option B (priced contract with a bill of quantities).
Invitation to Tender (ITT) chemical dust suppression 26 August.pdf
Provision of an ash dump chemical dust suppression system on an as-and-when-required basis for a period of five years at Kendal Power Station, issued by Eskom Holdings SOC Ltd.
E3403GXMPKEN NEC 3 COVER.zip
Eskom is procuring an as-and-when-required chemical dust suppression service for the ash dump facility at Kendal Power Station, under an NEC3 Term Service Contract (TSC3) for a period of 60 months. The contract is a priced contract with a price list (Option A), with task orders issued as needed, and includes provisions for low service damages, delay damages, and extensive Z-clauses covering health, safety, security, and compliance.
TES.pdf
Provision of an ash dump chemical dust suppression system on an as-and-when-required basis for five years at Kendal Power Station (Eskom, Mpumalanga). The work involves applying chemical dust suppressants to the Ash Disposal Facility to prevent ash dust spreading to surrounding communities, in line with the National Dust Control Regulations (GNR 827). The tender will be evaluated using a weighted score-card method with a minimum technical threshold of 70%.
Commercial - E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.zip
Eskom requires an as-and-when-required chemical dust suppression system for the ash dump at Kendal Power Station in Mpumalanga, for a five-year contract period.
SDLI STRATEGY for Chemical dust suppression.pdf
Eskom is procuring a chemical dust suppression system for the ash dump at Kendal Power Station, on an as-and-when-required basis for five years. The tender includes specific goals for B-BBEE, local procurement, job creation, subcontracting, and skills development, with penalties for non-compliance.
To download these documents and access AI-powered analysis, visit the main tender page.
Win Eskom tenders with AI Tender Matching, technical document analysis, compliance scoring, and structured bid support for energy and engineering contracts.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubLearn how to submit a winning bid with these related articles
Median Estimate
R 4 666 240
Range
Based on 7 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
The works comprise the provision of a chemical dust suppression system at Kendal Power Station, covering the ash dump (250,000 m²) and emergency dump (30,000 m²). The contract is for five years on an as-and-when-required basis. The scope includes employer's objectives, overview, extent, location, temporary works, preparation of as-built drawings, preferential procurement deliverables, employment and skills development opportunities, participation goals, social and economic deliverables, work specifications, applicable SANS 2001 and national/international standards, particular/generic specifications, materials/samples/shop drawings, instruction manuals and guarantees, training of employer's staff, construction equipment, existing services, dimensional accuracy, treatment of existing services, use of detection equipment for underground services, damage and reinstatement of services, site establishment, services (electricity, water, ablution, storage, laboratory, telecommunication), security, compliance with manufacturer instructions, protection/isolation of existing works, notice boards, notice before covering works, site usage, permits and way leaves, inspection of adjoining properties, water for construction, management of works, recording of weather, site meetings, health & safety, protection of the public, and AIDS awareness. Daywork rates are required for artisan, labourer, supervisor, and contractor's manager.
Evaluation Criteria
Source: Chemical Dust Suppression BoQ.pdf (unknown)Bidders must complete the Form of Offer and Acceptance and the bill of quantities. The contract data (Part C1.2) contains further variables. No specific pre-qualification thresholds (e.g., CIDB grade, B-BBEE level, or tax clearance) are stated in the extracted document.
Technical Specifications
Source: Chemical Dust Suppression BoQ.pdf (unknown)Scope of works includes provision of a chemical dust suppression system on an as-and-when-required basis for five years at Kendal Power Station. The bill of quantities lists two areas: Ash dump (250,000 m²) and Emergency dump (30,000 m²). The contract is a priced contract with bill of quantities (NEC3 Option B). The contractor must provide and keep on site a copy of the NEC3 contract and the procurement document, accessible to the Project Manager and Supervisor at all times. The works include site establishment, provision of services (electricity, water, ablution, storage, laboratory, telecommunication), security, protection of existing services, reinstatement of damaged services and structures, compliance with manufacturer instructions, and preparation of as-built drawings. The contractor must also provide employment and skills development opportunities to targeted labour, and meet preferential procurement and social/economic deliverables. Applicable SANS 2001 standards and national/international standards apply. The contractor must train the employer's staff, provide instruction manuals and guarantees, and submit materials, samples and shop drawings. Daywork rates are required for artisan, labourer, supervisor, and contractor's manager.
Quality Management
Source: Chemical Dust Suppression BoQ.pdf (unknown)The contract includes clauses on testing and defects (Clause 4.0) and time (Clause 3.0). The contractor must comply with manufacturer instructions and applicable SANS 2001 and national/international standards. The contractor must provide instruction manuals and guarantees, and submit materials, samples and shop drawings for approval. The contractor must train the employer's staff.
Pricing Schedule
Source: Chemical Dust Suppression BoQ.pdf (unknown)Final Summary: Section 1 Preliminaries (page 26), Section 2 Chemical Suppression (page 27). Sub-total excluding VAT, VAT amount, total carried to Form of Tender.
Financial Requirements
Source: Chemical Dust Suppression BoQ.pdf (unknown)Pricing format: Priced contract with bill of quantities (NEC3 Option B). Preliminaries are prorated to the value of work executed in each monthly payment certificate, excluding contingency sums and contract price adjustments. If the initial contract period is extended, the monthly charge is recalculated based on the revised period. Adjustment of preliminaries: 10% fixed, 15% value related, 75% time related (unless otherwise specified in the bill). Items not priced in preliminaries are deemed included elsewhere. Materials and goods stored off site are not included in payment amounts. Quantities in provisional bills are subject to remeasurement. Payment terms: monthly payment certificates based on value of work executed. The final summary requires sub-total excluding VAT, VAT amount, and total carried to Form of Tender.
Compliance Requirements
Source: Chemical Dust Suppression BoQ.pdf (unknown)No specific compliance requirements stated in the document.
Health & Safety
Source: Chemical Dust Suppression BoQ.pdf (unknown)The scope includes health & safety requirements, protection of the public, and AIDS awareness. The contractor must comply with health and safety requirements as part of the works.
Contractual Terms
Source: Chemical Dust Suppression BoQ.pdf (unknown)The contract is the NEC3 Engineering and Construction Contract - Option B: Priced contract with bill of quantities (Third edition June 2005 with amendments June 2006), incorporated with the Contract Data. The Contract Date is the date the contractor receives one fully completed signed copy of the document, including the schedule of deviations (if any) as contained in the Form of Offer and Acceptance. The contractor must provide and keep a copy of the NEC3 contract and the Procurement Document on site, accessible to the Project Manager and Supervisor at all times. The contract includes core clauses (general, contractor's main responsibilities, time, testing and defects, payment, compensation events, title, risks and insurance, termination), main option clauses (priced contract with bill of quantities), dispute resolution (Option W1), and secondary option clauses (price adjustment for inflation, changes in law, multiple currencies, parent company guarantee, sectional completion, bonus for early completion, delay damages, partnering, performance bond, advanced payment, limitation of liability for design, retention, low performance damages, limitation of liability, key performance indicators, additional conditions). Materials and goods stored off site are not included in payment amounts. Quantities in provisional bills are subject to remeasurement.
Description
Source: TES.pdf (unknown)Kendal Power Station is considering employing chemical dust suppression to address ash spreading to the surrounding community. This document outlines the technical requirements for ash dust suppression and the area of exposed ash to be covered on the Ash Disposal Facility, in line with the National Dust Control Regulations (GNR 827).
Contact Information
Source: TES.pdf (unknown)TET members: Mfanelo Mkhize (System Engineer), Siphiwe Mashele (Coal and Ash Snr Supervisor), Mfanelo Hlongwani (System Engineer). No contact details or submission address are stated in this document.
Submission Guidelines
Source: TES.pdf (unknown)Returnable documents: valid ISO 14001 certificate in the name of the contractor or sub-contractor; if sub-contracting, a signed agreement between both parties must be submitted. No other submission instructions are stated in this document.
Evaluation Criteria
Source: TES.pdf (unknown)Technical evaluation uses a weighted score-card approach. Mandatory criteria are gatekeepers assessed on a Yes/No basis; a 'No' on any mandatory criterion disqualifies the bidder. Qualitative criteria are weighted; bidders must achieve a minimum overall weighted technical score of 70% to qualify. Scoring: 5 (100%) Compliant, 4 (80%) Compliant with associated qualifications, 2 (40%) Non-compliant, 0 (0%) Totally deficient or non-responsive. Qualitative criteria weights: Company profile and background on dust suppression (10%), Assessing reference for similar work done within the past 5 years (30%), Environmental compliance (15%), Understanding of scope of work (5%), Proposed methodology (40%). Unacceptable technical risk: proposal partly covering the scope of work. No acceptable technical risks or exceptions are foreseen.
Technical Specifications
Source: TES.pdf (unknown)Scope: Provision of chemical dust suppression on the Ash Disposal Facility at Kendal Power Station to prevent ash dust spreading to the surrounding community, in line with the National Dust Control Regulations (GNR 827). The document defines mandatory and qualitative technical evaluation criteria and TET member responsibilities. Applicable to Kendal Power Station. Normative references include Eskom procedures and policies, the National Water Act and Regulation GN 704, the Ash Dump Environmental Management Plan, and the Ash Dump Operational and Maintenance Manual. Informative reference: Scope of work – ADF Dust Suppression Scope of Work.
Methodology
Source: TES.pdf (unknown)Qualitative criteria: Understanding of scope of work (5% weighting) – estimate BOQ showing full understanding (5/5), no BOQ or datasheets (0/5). Proposed methodology (40% weighting) – detailed methodology and data demonstrating effectiveness in reducing dust emissions (5/5), detailed methodology but no data (4/5), data but no detailed methodology (2/5), no submission (0/5).
Experience & Qualifications
Source: TES.pdf (unknown)Qualitative criteria: Company profile and background on dust suppression (10% weighting) – profile with chemical dust suppression background (5/5), general dust suppression background (4/5), general dust suppression background only (2/5), no submission (0/5). Minimum of three verifiable references for chemical dust suppression work done within the past 5 years (30% weighting) – proof in the form of purchase orders, signed completion letters, or signed delivery notes; 5+ years experience with traceable references (5/5), 5 years experience with traceable references (4/5), less than 5 years with traceable references (2/5), no proof (0/5).
Quality Management
Source: TES.pdf (unknown)Mandatory: Provide a valid ISO 14001 certificate in the name of the contractor or sub-contractor. If sub-contracting, a signed agreement between both parties must be submitted.
Compliance Requirements
Source: TES.pdf (unknown)Mandatory: Provide a valid ISO 14001 certificate (environmental management) in the name of the contractor or sub-contractor. If work is sub-contracted, a signed agreement between both parties must be submitted. No other compliance requirements are stated in this document.
Environmental
Source: TES.pdf (unknown)Qualitative criterion (15% weighting): Contractor must provide proof that products used are environmentally friendly and do not contravene environmental regulations. Must provide Material Safety Data Sheets (MSDS) of all products used and a detailed management plan for preventing soil and water contamination (e.g., managing chemical run-off). Scoring: both MSDS and management plan (5/5), either one (2/5), no MSDS (0/5).
Requirements
Source: TES.pdf (unknown)Mandatory: Provide a valid ISO 14001 certificate in the name of the contractor or sub-contractor. If work is sub-contracted, a signed agreement between both parties must be submitted.
Section
Source: TES.pdf (unknown)Technical evaluation uses a weighted score-card approach. Tenderers need an overall weighted score of 70% or more to technically qualify. Scoring: 5 (100%) Compliant, 4 (80%) Compliant with associated qualifications, 2 (40%) Non-compliant, 0 (0%) Totally deficient or non-responsive. Mandatory criteria are gatekeepers assessed on a Yes/No basis – a 'No' disqualifies the tenderer. Qualitative criteria are weighted to identify the highest technically ranked tenderer, with a minimum threshold of 70%. TET member responsibilities: Mandatory criteria 1 and 2 are assessed by TET 1, TET 2, and TET 3. Qualitative criteria 1 through 5 are assessed by TET 1, TET 2, and TET 3. Foreseen acceptable/unacceptable qualifications: Acceptable technical risks – none. Unacceptable technical risks – tender proposal partly covering the scope of work to be executed. Acceptable technical exceptions/conditions – none. Unacceptable technical exceptions/conditions – N/A.
Description
Source: SDLI STRATEGY for Chemical dust suppression.pdf (unknown)Provision of ash dump chemical dust suppression system on an 'as and when required' basis for a period of five years at Kendal Power Station.
Important Dates
Source: SDLI STRATEGY for Chemical dust suppression.pdf (unknown)Closing date: 22 September 2026 at 11:00 (from tender record).
No other dates (briefings, site visits, clarification deadlines) are stated in the provided document.
Contact Information
Source: SDLI STRATEGY for Chemical dust suppression.pdf (unknown)Buyer: Absalom Mbokazi (name only, no contact details provided).
Business unit: Gx Kendal Power Station.
No email, phone, or submission address stated in the provided document.
Submission Guidelines
Source: SDLI STRATEGY for Chemical dust suppression.pdf (unknown)Returnable documents:
Submission method and address not stated in the provided document. Closing date and time: 2026-09-22T11:00:00.000Z (from tender record).
Evaluation Criteria
Source: SDLI STRATEGY for Chemical dust suppression.pdf (unknown)Preference point system: 90/10 or 80/20 depending on tender value. Maximum 10 points for specific goals (B-BBEE status level). Points for specific goals added to price points, total rounded to two decimals.
B-BBEE points table (90/10 system / 80/20 system):
If preference point documents not provided, bidder is not disqualified but scores only out of 90 for price and 0 for specific goals.
SDL&I objectives (transformation, local procurement, job creation, subcontracting, skills development) do not form part of scoring but commitments become contractual obligations.
Technical Specifications
Source: SDLI STRATEGY for Chemical dust suppression.pdf (unknown)Scope: Provision of ash dump chemical dust suppression system on an 'as and when required' basis at Kendal Power Station.
Duration: 5 years (60 months).
No detailed technical specifications (quantities, standards, service levels) are provided in the extracted document.
Methodology
Source: SDLI STRATEGY for Chemical dust suppression.pdf (unknown)Skills development must involve participation by tenderers directly and through their supply network. SETA-accredited training providers may be approached for critical and scarce skills. Tenderers bear full cost of skills development; Eskom makes no financial contribution. Tenderers advised to approach SETAs for grants and SARS for tax rebates.
Financial Requirements
Source: SDLI STRATEGY for Chemical dust suppression.pdf (unknown)Pricing format: Tender response must be separated into components as per the Price Schedule included with the tender documents, especially where a combination of local and imported goods/services is involved.
Local procurement content = total spending minus imported component.
SDL&I penalty: 3% of contract value for failure to meet SDL&I obligations.
SDL&I retention: 3% of every invoice (excluding VAT) retained as security, released upon fulfilment of SDL&I obligations.
No bond, guarantee, or payment terms stated.
Compliance Requirements
Source: SDLI STRATEGY for Chemical dust suppression.pdf (unknown)B-BBEE: Valid certificate (SANAS accredited) or sworn affidavit or CIPS affidavit required to claim preference points. Revenue thresholds: ≤R10m – sworn affidavit (EME); ≤R50m – QSE compliance unless 51% black-owned (sworn affidavit); >R50m – valid B-BBEE certificate.
B-BBEE improvement plan: Essential document, submit within 30 days of contract signing. Level 4 must achieve Level 3 by end of first year; Level 5-8 or non-compliant must achieve Level 4 by end of first year and improve one level each subsequent year.
Sworn affidavit validity: Must meet specific requirements (deponent details, ownership percentages, revenue, financial year end, status level, empowering supplier status, signatures).
No CSD, tax clearance, CIDB, or CIPC registration requirements stated in the provided document.
B-BBEE Requirements
Source: SDLI STRATEGY for Chemical dust suppression.pdf (unknown)Preference points: B-BBEE status level determines points (90/10 or 80/20 system). Documents required: valid B-BBEE certificate (SANAS accredited), sworn affidavit, or CIPS affidavit; proof of ownership/shareholding (CIPC); certified ID copies of shareholders; proof of disability (if applicable); consolidated certificate for trusts/consortia/JVs. Failure to provide documents results in 0 points for specific goals and scoring out of 90 for price.
Transformation: B-BBEE improvement or retention plan required within 30 days of contract signing. Level 4 must achieve Level 3 by end of first year; Level 5-8 or non-compliant must achieve Level 4 by end of first year and improve one level each subsequent year.
Local procurement: Target 100% local content. Tender response must separate local and imported components.
Job creation: Submit proposals for type and number of jobs created and retained. Encourage sourcing from Kendal Feeder areas.
Subcontracting: Successful supplier must subcontract to EME/QSE with at least 51% black ownership, preferably local to site. Target: 15% procurement from Black Owned (EME/QSE). Potential scope: PPE, accommodation, other.
Skills development: Bursary to learners (minimum 24 months) in fields like Environmental Sciences, Environment Management, Water Science, Soil Science. Target: 3 learners. Candidates from previously disadvantaged groups, particularly at site. Tenderer bears full cost.
Health & Safety
Source: SDLI STRATEGY for Chemical dust suppression.pdf (unknown)PPE and accommodation are listed as potential scope to be subcontracted/outsourced. No specific OHS requirements stated.
Environmental
Source: SDLI STRATEGY for Chemical dust suppression.pdf (unknown)Possible courses for skills development include Environmental Sciences, Environment Management, Water Science, Soil Science. No specific environmental impact or sustainability requirements stated.
Special Conditions
Source: SDLI STRATEGY for Chemical dust suppression.pdf (unknown)SDL&I penalty: 3% of contract value for failure to meet SDL&I obligations. SDL&I retention: 3% of every invoice (excluding VAT) retained as security, released upon fulfilment of SDL&I obligations.
Reporting and monitoring: Quarterly reports to Eskom per Data Collection Template. Eskom reviews within 30 days and notifies in writing if obligations not met. Corrective measures required before next report, failing which retention clauses invoked. SDL&I Implementation Schedule to be completed and returned within 28 days after contract award.
Market research: No current suppliers; open tender.
Sworn affidavit validity: Must include deponent name and ID, designation, enterprise name and address, percentage of black ownership, total revenue, financial year end, B-BBEE status level, empowering supplier status, signatures dated same day, Commissioner of Oath cannot be employee/ex officio of enterprise.
Section
Source: SDLI STRATEGY for Chemical dust suppression.pdf (unknown)Maximum 10 points for specific goals (B-BBEE status level). Points added to price points, total rounded to two decimals. B-BBEE points table as per 90/10 or 80/20 system. Failure to provide preference point documents results in 0 points for specific goals and scoring out of 90 for price.
Description
Source: SCOPE OF WORK.pdf (unknown)The contract is for supplying and applying chemical dust suppression on ash at Kendal Power Station's Ash Disposal Facility to prevent dust fall, in line with National Dust Control Regulations (GNR 827). The service is required on an as-and-when-required basis for 5 years (60 months).
Submission Guidelines
Source: SCOPE OF WORK.pdf (unknown)Returnable documents: none specified in the scope of work document. The tender is an open request for bid; submission details (channel, format, returnable forms) are not stated in this document.
Evaluation Criteria
Source: SCOPE OF WORK.pdf (unknown)No evaluation criteria are stated in the scope of work document. The document references ISO 9001, Eskom SHEQ Policy, National Environmental Management: Air Quality Act, and the National Water Act as normative references, but no scoring or qualification thresholds are provided.
Technical Specifications
Source: SCOPE OF WORK.pdf (unknown)Scope: Supply and apply chemical dust suppression on the Kendal Power Station Ash Disposal Facility (ADF) on an as-and-when-required basis for 5 years (60 months).
Areas to be treated:
Solution requirements:
Documentation: Contractor must compile a report after every application, including at least the area covered.
Compliance with National Dust Control Regulations (GNR 827).
Compliance Requirements
Source: SCOPE OF WORK.pdf (unknown)Compliance with the following standards and regulations (most recent editions apply):
Environmental approvals: All dust suppression materials must be approved by Eskom Environmental Department before use; contractor must supply Material Safety Data Sheets (MSDS).
Safety approvals: Equipment must be inspected and accepted by Eskom Safety Department before entering premises; plant must be capable of operating on unstable ash terrain; personnel must be vetted by Eskom Security and hold access control; contractor must provide adequate PPE for dusty operational conditions.
Health & Safety
Source: SCOPE OF WORK.pdf (unknown)Safety requirements:
Compliance with OHS Act, Eskom OHS procedures, Life Saving Rules, and Contractor OHS Management standards is required.
Environmental
Source: SCOPE OF WORK.pdf (unknown)Environmental requirements:
Requirements
Source: SCOPE OF WORK.pdf (unknown)The dust suppression solution must be suitable for ash dust suppression, produce a resilient, crack-resistant surface crust that accommodates substrate shifting without failure, and completely mitigate dust particle emissions on the treated footprint. The binding effect must last at least 6 months. The contractor must compile a report after every application, detailing at least the area covered.
Description
Source: E3403GXMPKEN NEC 3 COVER.zip (unknown)The service is the provision of ash dump chemical dust suppression on an 'as and when required basis' for a period of 60 months at Kendal Power Station, Ash Dump Facility. The contract is a NEC3 Term Service Contract (TSC3) with main Option A (priced contract with price list). The service is to be provided in accordance with the Service Information (Part 3: Scope of Work).
Contact Information
Source: E3403GXMPKEN NEC 3 COVER.zip (unknown)Service Manager: Phumelele Thanjekwayo, Eskom Holdings SOC Ltd, Kendal Power Station, Private Bag X 7272, Witbank, 1035. Tel: 013 647 6255. Email: [email protected]. Employer registered office: Megawatt Park, Maxwell Drive, Sandton, Johannesburg. Tel: 011 800 2111.
Submission Guidelines
Source: E3403GXMPKEN NEC 3 COVER.zip (unknown)Returnable documents: the Form of Offer and Acceptance (C1.1) must be completed, signed and submitted, including the Schedule of Deviations if any. Contract Data Part 2 (C1.2b) must be completed. Pricing Data (C2.1 and C2.2) must be submitted. The tenderer's CIDB registration number must be stated on the offer form. The offer must remain valid for the period stated in the Tender Data. Any deviations must be listed in the Schedule of Deviations; no other amendments are valid.
Evaluation Criteria
Source: E3403GXMPKEN NEC 3 COVER.zip (unknown)The contract is a NEC3 Term Service Contract (TSC3) with main Option A (priced contract with price list). No specific evaluation scoring split or minimum qualifying thresholds are stated in the extracted document. The contract includes provisions for termination if the Contractor's B-BBEE status decreases after the Contract Date. No specific B-BBEE level or CIDB grading is stated.
Technical Specifications
Source: E3403GXMPKEN NEC 3 COVER.zip (unknown)Scope: provision of ash dump chemical dust suppression on an 'as and when required basis' for a period of 60 months at Kendal Power Station, Ash Dump Facility. The service includes chemical suppression of the ash dump (250,000 m²) and emergency dump (30,000 m²). The contract is a term service contract with task orders. The Contractor must submit a first plan for acceptance within 2 weeks of the Contract Date. Testing and defect correction for final quality inspection will be done at Kendal Power Station.
Financial Requirements
Source: E3403GXMPKEN NEC 3 COVER.zip (unknown)Pricing: Option A priced contract with price list. The price list includes items for chemical suppression (ash dump and emergency dump) and preliminaries and general, including health and safety. The offered total of the Prices exclusive of VAT is to be stated in the Form of Offer and Acceptance. Payment: assessment interval is between the 25th day of each successive month. Payment is due within 30 calendar days after signed assessment by both parties and a valid tax invoice. Interest on late payment is at the publicly quoted prime rate of Standard Bank. The Contractor must provide a tax invoice within one week of receiving a payment certificate. The Employer's VAT number 4740101508 must be included on each invoice.
Compliance Requirements
Source: E3403GXMPKEN NEC 3 COVER.zip (unknown)CIDB registration: the tenderer's CIDB registration number must be stated on the offer form. B-BBEE: the Contractor must notify the Employer within seven days of any change in B-BBEE status and submit an updated verification certificate within thirty days. A decrease in B-BBEE status may lead to re-negotiation or termination. Security clearance: personnel requiring access to Eskom premises must hold criminal verification record security clearance certificates issued by a SAPS-accredited screening company, no older than four weeks, and valid for the access period. The Employer may require updated certificates every 26 to 52 weeks. POPIA: the Contractor must comply with the Protection of Personal Information Act when processing personal information.
Section
Source: E3403GXMPKEN NEC 3 COVER.zip (unknown)Testing and defects: final quality inspection will be done at Kendal Power Station. If a test or inspection shows a defect, the supplier corrects the defect and the test or inspection is repeated. The defect correction period is 52 weeks after the respective Task Order Completion Date.
Description
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Annexure Attached (Y /
N / n/a)
1.1.1 *Authorisation Form Annexure A Y
1.1.2 *Acknowledgement form Annexure B Y
1.1.3 *Tenderer’s particulars Annexure C Y
1.1.4 *Integrity Declaration Form (Suppliers are required to Annexure D Y
download and read the Supplier Integrity Pact. It is
accessible on the Eskom Tender Bulletin via Eskom
Supplier Integrity Pact (eskom.co.za) link)
1.1.5 *CPA Requirements for Local Goods/Services Annexure E Y
1.1.6 *CPA(IG) for Foreign Goods/Services (if applicable) Annexure F Y
1.1.7 SBD 6.2 Declaration Certificate for Local Production Annexure G1 Y
and Local Content (only applicable if designated
materials are included and then Tenderers will be
required to complete and submit Annexures G1 to
G4 as evidence of compliance with this
requirement).
Annexure C Local Content Declaration- Summary Annexure G2 Y
Schedule
Annexure D Imported Content Declaration – Supporting Annexure G3 Y
Schedule to Annexure C
Annexure E Local Content Declaration- Supporting Annexure G4 Y
Schedule to Annexure C
1.1.8 *SBD 1 Invitation to Bid must be filled out by all Annexure H Y
tenderers and submitted with the tender at tender
submission deadline
1.1.9 *
Important Dates
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Closing date: 07 April 2026 at 10:00 am. Compulsory clarification meeting: 07 September 2026 at 11h00 am (venue: Horticulture Boardroom, Kendal Power Station; transport departs main gate at 10h30; ID and PPE compulsory). Clarification queries deadline: 5 working days before tender submission deadline.
Contact Information
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Email: [email protected]. Phone: 013 647 6815. Fraud/corruption reporting: 0800 11 2722.
Submission Guidelines
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Submit electronically via Eskom E-Tendering by 10:00 am on 07 April 2026. Upload size per document is 500 MB, total submission restricted to 4 GB. No hard copies or zip files. Pricing schedule must be submitted in PDF and Excel format. Mandatory returnables (marked with *) must be submitted by closing; non-submission is disqualifying. Required forms include Annexures A–J, SBD 1, SBD 6.1, SBD 6.2 (if applicable), Tax Evaluation questionnaire, E-tendering Help Manual acknowledgement, and completed pricing schedule. Alternative tenders are not allowed. Clarification queries must be submitted 5 working days before the tender submission deadline.
Returnable Documents
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Returnable documents include Annexures A–J, SBD 1, SBD 6.1, SBD 6.2 (if applicable), Tax Evaluation questionnaire, E-tendering Help Manual acknowledgement, completed pricing schedule, financial statements, safety/quality/environmental documents as listed. Mandatory returnables marked with
Evaluation Criteria
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Evaluation stages: 1) Basic compliance (attendance at compulsory clarification meeting, eligibility, complete tender). 2) Functionality/technical evaluation with a minimum threshold of 70%. 3) Price evaluation scored out of 80 or 90 points. 4) Specific goals (B-BBEE) scored out of 20 or 10 points per PPPFA. Tenderers who fail to submit B-BBEE evidence are not disqualified but score 0 for specific goals. Ranking is by total score (price + specific goals) under the 90/10 or 80/20 system. B-BBEE points: Level 1 = 10 (90/10) or 20 (80/20); Level 2 = 9 or 18; Level 3 = 6 or 14; Level 4 = 5 or 12; Level 5 = 4 or 8; Level 6 = 3 or 6; Level 7 = 2 or 4; Level 8 = 1 or 2; Non-compliant = 0.
Technical Specifications
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Scope: chemical dust suppression at Kendal Power Station. Requires a developed, implemented and maintained QMS compliant with ISO 9001:2015, including QMS manual, quality policy, quality objectives, document control, nonconforming output control, corrective action procedure, internal audit procedure, roles/responsibilities, control of externally provided processes, draft contract/project quality plan, and example ITP/QCP. Environmental requirements: signed environmental policy aligned with ISO 14001:2015, Environmental Management Plan (EMP) covering supply, delivery, storage, handling, disposal, aspects/impacts, mitigation, roles, monitoring, emergency preparedness; Environmental Aspects and Impacts Register; environmental representative appointment letter; signed Spillage Management and Emergency Preparedness Plan; Waste Management Plan; list of hazardous substances with SDS; training matrix and competency records; permits/licenses; signed Environmental Compliance Declaration. Experience: minimum 5 years verifiable references in chemical dust suppression within the past 5 years, with proof via purchase order, signed completion letter, or signed delivery note. Company profile and background on chemical dust suppression required.
Experience & Qualifications
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Experience requirements: minimum 5 years verifiable references for chemical dust suppression work done within the past 5 years. Proof must be in form of valid purchase order, signed completion letter, or signed delivery note. Company profile and background on chemical dust suppression required. Scoring: 5/5 for 5+ years with traceable references, 4/5 for 5 years with traceable reference, 2/5 for less than 5 years, 0/5 for no proof. Company profile scoring: 5/5 for detailed chemical dust suppression background, 4/5 for company profile and background on chemical dust suppression, 2/5 for general dust suppression background only, 0/5 for no submission.
Quality Management
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Supplier must submit objective evidence of a QMS compliant with ISO 9001:2015, including QMS manual, quality policy, quality objectives, document control, nonconforming output control, corrective action procedure, internal audit procedure, roles/responsibilities, control of externally provided processes, draft contract/project quality plan, and example ITP/QCP. Supplier must complete and sign Form A (Enquiry/Contract/Quality Requirements for Supplier).
Pricing Schedule
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Pricing schedule/BOQ must be submitted in PDF and Excel format. Prices evaluated inclusive of VAT, corrected for errors, and compared on NPV basis. Tender response must be separated into components as per the Price Schedule. Local procurement content is total spending minus imported component. Unconditional discounts taken into account for evaluation but implemented at payment. Cataloguing line item required if applicable.
Financial Requirements
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Payment terms: Eskom commits to paying suppliers within 30 days of receipt of undisputed invoices for contracts valued below R50,000,000 (including VAT), and within 60 days for contracts valued above R50,000,000 (including VAT). Prices evaluated inclusive of VAT, corrected for errors, and compared on NPV basis. Pricing schedule must be submitted in PDF and Excel format. Unconditional discounts taken into account for evaluation but implemented at payment. Financial statements required: latest approved annual financial statements (no drafts) of the tendering company (not parent/holding), including background, signed director's report, signed auditor's/reviewer's/compiler's/accounting officer's report, statement of financial position, comprehensive income, changes in equity, cash flows, notes. Public interest score (if not audited), ITA34C for current and previous years (if not audited). For unincorporated JV or SPV, each partner must submit its own financial statements.
Compliance Requirements
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Mandatory eligibility: not under any restriction to do business with Eskom or state-owned companies, not on international sanctions list, no conflict of interest, not restricted by National Treasury or Eskom, not on Tender Defaulters list, not subcontract 100% of scope. Attendance at compulsory clarification meeting is mandatory; non-attendance disqualifies. Mandatory returnables marked as disqualifiable must be submitted by closing. CSD registration required. Safety: COIDA certificate of good standing or proof of application (South African tenderers only). Health and Safety: Health and Safety Plan aligned with SHE Spec 240-73416879 and 32-726 Eskom Contractor H&S requirements, Baseline OHS Risk Assessment (BRA) including Covid-19 as hazard, valid Letter of Good Standing (COIDA or equivalent), OHS policy signed by CEO, health and safety management costing (broken down, not lump sum), proof of OHS competency. Quality: ISO 9001:2015 QMS documentation as listed. Environmental: ISO 14001:2015 aligned policy, EMP, aspects/impacts register, spillage management plan, waste management plan, SDS, training records, permits, compliance declaration. B-BBEE: valid B-BBEE certificate (SANAS accredited), sworn/CIPS affidavit, proof of ownership/shareholding (CIPC), certified ID copies of shareholders, proof of disability (where applicable), consolidated B-BBEE certificate for trust/consortium/JV. Tax Evaluation questionnaire required.
Health & Safety
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Health and Safety requirements: COIDA certificate of good standing or proof of application (South African tenderers only). Health and Safety Plan aligned with SHE Spec 240-73416879 and 32-726 Eskom Contractor H&S requirements. Baseline OHS Risk Assessment (BRA) with methodology, Covid-19 added as hazard. Valid Letter of Good Standing (COIDA or equivalent). OHS policy signed by CEO. Health and safety management costing broken down, not lump sum. Proof of OHS competency. PPE, accommodation, and other scope to be specified by supplier.
Environmental
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Environmental requirements: signed environmental policy aligned with ISO 14001:2015, signed by Company Owner/CEO/MD, covering protection of environment, pollution prevention, compliance with legislation, continual improvement. Environmental Management Plan (EMP) specific to scope covering supply, delivery, storage, handling, disposal, aspects/impacts, mitigation, roles, monitoring, emergency preparedness. Environmental Aspects and Impacts Register. Environmental representative appointment letter. Signed Spillage Management and Emergency Preparedness Plan addressing chemical and vehicle hazardous substance spillages, including spill response procedures, spill kits, incident reporting, remediation. Waste Management Plan covering used rags, contaminated materials, waste minimisation, segregation, safe handling, storage, disposal, licensed waste service providers. List of hazardous substances with SDS. Training matrix and competency records. Permits/licenses. Signed Environmental Compliance Declaration confirming compliance with legislation, Eskom SHEQ policies, Kendal Power Station environmental requirements, and responsibility for environmental incidents.
Contractual Terms
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)Contract will be NEC 3 Term Service Contract. Successful tenderer may be required to provide cataloguing information per item after award and label materials per Eskom specifications; pricing schedule must include a cataloguing line item if required. Tenderers must not submit more than one tender individually or as a partner in a JV/consortium, except on E-Tendering system with size limits. Nationality restrictions apply to tenderers, subcontractors, and suppliers.
Section
Source: Invitation to Tender (ITT) chemical dust suppression 26 August.pdf (TENDER)1.1.9 *SBD 6.1 Preference Points Claim Form in terms of Annexure I Y
PPPFA 2022 regulations
1.1.11 Tax Evaluation questionnaire to determine whether a Y
3.13 Functionality requirements Functionality requirements are applicable.
functionality criteria
Threshold 70%
Tenderers who do not meet the threshold for functionality scoring will
3.15 Evaluation of Price Prices will be evaluated as follows
evaluation parameters relating to uncertainty and risk, where
evaluation purposes but will be implemented when payment is
Prices will be scored out of [80 or 90] points
3.18 Evaluation of Specific Goals Specific goals will be scored out of [20 or 10] points in accordance
with the PPPFA.
If a tenderer fails to submit evidence of its points c
If a tenderer fails to submit evidence of its points claim for a Specific
Goal, it will not be disqualified. However, it will be awarded 0 points
Specific Goals
Number of points Number of points B-BBEE Status Level of
Contributor (90/10 system) (80/20 system)
NB: The following documents are required to claim preference points,
preference points will not be disqualified, but’
the 90/10 or 80/20 system. Eskom will add the score from Pricing and
Description
Source: Commercial - E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.zipThe document is a user manual for the Eskom eTendering system, which replaces physical tender submission. Bidders must register on the system, verify their email, and use OTP authentication. Tenders are uploaded electronically; closed tenders may be sent directly to selected suppliers via email link. The manual does not describe the ash dump dust suppression scope.
Important Dates
Source: Commercial - E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.zip (TENDER)Closing date and time: 2026-09-22 at 11:00 (per tender record). No briefing or site visit dates are stated in the document.
Contact Information
Source: Commercial - E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.zip (TENDER)No specific contact names or phone numbers are provided. For system problems, contact the buyer responsible for the published tender. For the PAYE questionnaire, email [email protected]. Submission is via the eTendering portal; no physical address is given.
Submission Guidelines
Source: Commercial - E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.zip (TENDER)Submit electronically via the Eskom eTendering system at https://eTendering.eskom.co.za. Registration on the system is required; a CSD number is needed for access. Upload documents under the correct category (Technical, Commercial, Finance). File size per document must not exceed 50MB; total upload size must not exceed 900MB. Finalise and close the submission before the closing time; a timestamp is recorded. Keep the confirmation email with the submission ID for reference.
Returnable forms (all must be completed, signed and submitted):
Evaluation Criteria
Source: Commercial - E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.zip (TENDER)The document pack does not state the scoring split, minimum qualifying thresholds, or preference point system. Evaluation criteria are not detailed in this extract.
Technical Specifications
Source: Commercial - E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.zip (TENDER)The tender is for the provision of an ash dump chemical dust suppression system on an 'as and when required' basis for five years at Kendal Power Station. No further technical details (quantities, standards, service levels) are provided in this extract.
Financial Requirements
Source: Commercial - E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.zip (TENDER)No pricing format, bonds, guarantees, payment terms, or financial capacity thresholds are stated in the document.
Compliance Requirements
Source: Commercial - E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.zip (TENDER)Mandatory returnable forms:
Registration requirements:
No CIDB grading, B-BBEE level, local content, or other compliance thresholds are stated in this extract.
Section
Source: Commercial - E-Tenderers E-Tendering Training Acknowledgement Form - 27 January 2025.zipThe document mentions that closed tenders are sent to suppliers who meet selection and evaluation criteria, but no specific evaluation criteria for this tender are provided.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
Kendal Power Station - Ogies/Balmoral - Witbank - 1035
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
7
Last checked
26 Aug 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Services: Professional. Unlock full pricing strategies, bid frequency, and historical win rates.