Airports Company South Africa (ACSA)Location
KwaZulu-Natal
Closing Date
29 Jan 2027
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
King Shaka Drive - La Mercy - Durban - 4405
Organization Type
GOVERNMENT
Published
20 Nov 2026
OCDS Reference
ocds-9t57fa-179076
Airports company south africa requires a principal contractor to refurbish sliding doors across airside and landside locations at king shaka international airport, including passenger departure drop-off zones, arrivals areas, bus gates, and multistorey facilities. The 20-month nec3 engineering and construction contract (main option b, priced with bill of quantities) covers replacement of wheel kits, track inserts, drive belts, pulleys, drive controls, sensors, and commissioning, with a provisional sum of r500,000 for other maintenance. Bidders must price a vat-exclusive bill of quantities, provide key personnel cvs, sign the OHS agreement, and secure aviation liability insurance of at least r300,000. The most consequential consideration is the strict airport security regime: all personnel must hold acsa permits, requiring airside induction training, and the contractor has NO claim if permit requests are refused.
Closing: 29 January 2027 at 10:00; submission method and address not stated in the document.
Contract period: 20 months from signing by ACSA; defects date 12 months after completion; defects correction period 2 weeks.
Pricing: Complete the Bill of Quantities with VAT-exclusive rates; prices must cover all risks, profit, and obligations; payment per completed activity, 4 weeks after valid tax invoice.
Insurance: Provide aviation liability cover of at least R300,000 before work starts and annually; maintain COID good standing and public liability insurance per OHS agreement.
OHS: Sign the Section 37(2) OHS Agreement by a Section 16.2 appointee; submit safety file and baseline risk assessment; safety file approval required before site access.
ACSA permits: All personnel (main and subcontractor) must hold valid ACSA permits; airside induction training required; fees apply; no claim against ACSA if permit refused.
Returnables: Signed Form of Offer and Acceptance, Contract Data Part Two with key personnel CVs, OHS Agreement, proof of insurance, and standard National Treasury forms (SBD 1, SBD 4, SBD 6.1, SBD 9).
B-BBEE: Valid B-BBEE certificate required and must be presented annually; failure is a material breach and may lead to contract cancellation.
Retention and delay damages: 5% retention; delay damages 0.05% per day up to 10% of contract value; performance bond marked not applicable.
Continue with tenders sharing this issuer, category, or province.
Browse categories with current opportunities in this area.
Compare tender activity across provinces.
Explore organisations currently publishing tenders.
Tools and research to help you assess opportunities.
Return to this tenderβs issuing organisation, province, or category.
Continue with tenders sharing this issuer, category, or province.
Browse categories with current opportunities in this area.
Compare tender activity across provinces.
Explore organisations currently publishing tenders.
Tools and research to help you assess opportunities.
Date & Time
Friday, 29 January 2027 - 12:00
Venue
Microsoft Teams meeting Join: https://teams.microsoft.com/meet/317421753115222?p=YIVNA5NeFQ4av8uWm1
Categories
Request for Bid(Open-Tender)
King Shaka Drive - La Mercy - Durban - 4405
Tenders in this industry often require registration with these bodies.
Construction Industry Development Board (CIDB) registration is mandatory for almost all public sector construction tenders. Ensure your grading matches the tender value.
Recommended Certifications
Having these can improve your winning chances: NHBRC Registration, ISO 9001:2015 (Quality Management), ISO 14001:2015 (Environmental Management), ISO 45001:2018 (Occupational Health & Safety), SACPCMP Registration, ECSA Registration
AI Document Analysis Stages
Important Dates
Source: CIDB Bid document Template - Sliding Doors.pdf (RFP)20 Nov
2026
Tender Published
Tender was published
29 Jan
2027
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
CIDB Bid document Template - Sliding Doors.pdf
Airports Company South Africa requires a principal contractor for the refurbishment of sliding doors at King Shaka International Airport, including installation, refurbishment, or replacement of sliding doors. The contract is for a fixed price and requires a CIDB grading of 5EB or higher.
APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdf
Refurbishment of sliding doors at King Shaka International Airport, including replacement of wheel kits, track inserts, drive belts, idler pulleys, drive controls, and activation/safety sensors, plus testing and commissioning. The contract is a 20-month NEC3 Engineering and Construction Contract (Option B, priced with Bill of Quantities) with Airports Company South Africa SOC Limited as the Employer.
To download these documents and access AI-powered analysis, visit the main tender page.
Organization
Airports Company South Africa (ACSA)Win ACSA tenders with AI Matching Engine, airport-infrastructure intelligence, compliance analysis, and application support for aviation operations.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
RΒ 744Β 980
Range
Based on 25 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically β no action required from you.
Briefing session (non-compulsory): 01 December 2026 at 11:00, online via Microsoft Teams. Meeting ID: 317 421 753 115 222, Passcode: GP25UN9o. Attendance is not compulsory, but tenderers must sign the attendance list to receive addenda and to have their tenders considered.
Clarification closing date: 15 January 2026 (note: the document also states a query closure date of 01 December 2026; the later date is likely the intended clarification deadline).
Closing date and time: 29 January 2027 at 12:00 (South African time).
Tender validity: 12 weeks (84 days) from closing date.
Contact Information
Source: CIDB Bid document Template - Sliding Doors.pdf (RFP)Enquiries (bidding procedure and technical):
All communication during the tender period must be directed to ACSA's Supply Chain Department, not to the Principal Agent. Bidders may not contact any other ACSA employee regarding this tender.
Submission address (tender box):
Airports Company SA SOC Ltd
King Shaka International Airport
La Mercy
MSO Building (Multi Storey Office Block) outside Main Terminal Building
Ground Floor, Reception, near Pick Up Zone
Submission Guidelines
Source: CIDB Bid document Template - Sliding Doors.pdf (RFP)Submission method: physical delivery only. Bids must be deposited in the tender box at the MSO Building, Ground Floor, Reception, near the Pick Up Zone, King Shaka International Airport, La Mercy, 4405. The Tender Deposit Register must be completed and signed by the person depositing the bid.
Packaging: Submit 1 original and 1 copy, each sealed in a separate package clearly marked "ORIGINAL" and "COPY". Each package must show the bidder's name and contact details, the bid reference number (KSIA8364/2026/RFP), and the tender title. An outer package may be used, but it must be sealed and marked with the employer's address and identification details.
Late bids: Bids received after the closing time will not be accepted and will be returned unopened. Proof of posting is not proof of delivery. Telephonic, telegraphic, telex, facsimile, or e-mailed tenders will not be accepted.
Returnable documents (all must be completed, signed, and returned in full):
Disqualification risks:
Evaluation Criteria
Source: CIDB Bid document Template - Sliding Doors.pdf (RFP)Evaluation is staged:
Stage 1: Test for responsiveness (compliance with conditions, completeness, signing).
Stage 2: Mandatory administration criteria:
Stage 3: Functionality evaluation (minimum threshold: 70 out of 100 points to proceed):
Stage 4: Price and Preference (80/20 system, for bids up to R50 million):
Stage 5: Security vetting (if applicable).
Contract award: The employer will accept the tender offer if the tenderer is not under restrictions, has the legal capacity, is not insolvent or under business rescue, and can demonstrate the necessary professional, technical, and financial capability.
Technical Specifications
Source: CIDB Bid document Template - Sliding Doors.pdf (RFP)Scope: Refurbishment of sliding doors at King Shaka International Airport. The successful bidder will act as the principal contractor for this work.
Key personnel requirements:
Company experience: Minimum of two (2) relevant trade reference letters for sliding door installation/refurbishment/replacement, completed within the last 10 years.
Contract conditions:
Financial Requirements
Source: CIDB Bid document Template - Sliding Doors.pdf (RFP)Pricing: Bidders must complete the pricing/activity schedules (C2.2). Prices must be in Rand, fixed for the contract duration, and include all duties, taxes (except VAT), and levies applicable 14 days before closing. VAT must be shown separately.
No bid security, performance bond, or retention is explicitly stated in the document. However, the employer may request securities, bonds, guarantees, policies, and insurance certificates before contract formation, as per the contract data.
Insurance: The employer's insurance may not cover all risks; bidders should seek qualified advice.
Tender offer validity: 12 weeks (84 days) from closing date. If the validity period lapses before evaluation, the contractor may review the price based on CPI.
Compliance Requirements
Source: CIDB Bid document Template - Sliding Doors.pdf (RFP)CSD registration: Bidders must be registered on the Central Supplier Database (CSD) and provide a CSD number, or provide a SARS Tax Compliance Status (TCS) PIN. For joint ventures, each party must submit a separate TCS certificate/PIN/CSD number.
Tax compliance: Bidders must be tax compliant and submit their SARS TCS PIN or a printed TCS certificate. Failure to provide may render the bid invalid.
CIDB grading: Bidders must be registered with the CIDB with a contractor grading designation of 5EB or higher, or be capable of being so prior to evaluation. Joint ventures: every member must be CIDB registered, the lead partner must have 5EB or higher, and the combined grading must meet the required designation.
B-BBEE: Bidders must provide proof of B-BBEE status to claim preference points. Proof can be a valid sworn affidavit (for EMEs/QSEs as per B-BBEE Act) or a B-BBEE certificate from a SANAS accredited agency. Joint ventures must provide a consolidated B-BBEE certificate from a SANAS accredited agency.
Other eligibility:
Description
Source: APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdfThe contract is for the refurbishment of sliding doors at King Shaka International Airport, using the NEC3 Engineering and Construction Contract (April 2013). The employer is Airports Company South Africa SOC Limited. The contract comprises Part C1 (Agreements and Contract Data), Part C2 (Pricing Data), Part C3 (Scope of Works), Part C4 (Site Information), and Part C5 (Annexures).
Important Dates
Source: APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdf (RFP)Closing date: 29 January 2027 at 10:00.
Contract duration: 20 months from the starting date (upon signing of contract by ACSA).
Defects date: 12 months after completion of the whole of the works.
Defects correction period: 2 weeks.
Payment period: 4 weeks after receipt of a valid tax invoice.
Assessment interval: 2 weeks.
Period of reply: 7 days.
No briefing or site visit dates are stated.
Contact Information
Source: APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdf (RFP)Employer: Airports Company South Africa SOC Limited
Address: King Shaka Drive, La Mercy, 4407
Telephone: (032) 436 6000
Project Manager: TBC
Address: King Shaka Drive, La Mercy, 4407
Supervisor: TBC
Address: King Shaka Drive, La Mercy, 4407
No email addresses or named contacts are provided in the document.
Submission Guidelines
Source: APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdf (RFP)Returnable documents:
Submission method and address: not stated in the provided document.
Closing time: 10:00 on 29 January 2027.
Evaluation Criteria
Source: APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdf (RFP)Evaluation criteria are not detailed in the provided document. The contract is a NEC3 Engineering and Construction Contract, Main Option B (priced contract with bill of quantities). No scoring split, minimum qualifying score, or preference point system (80/20 or 90/10) is stated.
Technical Specifications
Source: APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdf (RFP)Scope: Refurbishment of sliding doors at King Shaka International Airport, covering both airside and landside areas.
Locations and quantities (per Bill of Quantities):
Preliminary and general items: site establishment, tools/equipment/barricades, health/safety/environmental compliance (PPE, safety file, risk assessment), access on site (training, induction, permit β provisional sum R25,000), vehicle access requirements (amber strobe light, reflective strip, decals β provisional sum R10,000).
Experience & Qualifications
Source: APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdfKey personnel: The contractor must provide CVs for key people as per Contract Data Part Two, including name, job, responsibility, qualifications, and experience. No minimum experience or qualification levels are specified in the provided document.
Quality Management
Source: APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdfQuality requirements are implied through the Bill of Quantities, which specifies testing and commissioning of each sliding door unit after refurbishment. No separate quality management system or certification is stated.
Pricing Schedule
Source: APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdfPricing is based on a Bill of Quantities (Option B). Prices must be VAT-exclusive and cover all costs, risks, and obligations. Payment is made per activity only when complete. Provisional sums are only payable upon written order; unspent amounts are deducted. No alterations to the original text are allowed. Mark-up on bought-out items and labour rates for ad hoc works are to be provided.
Financial Requirements
Source: APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdf (RFP)Pricing: Bill of Quantities, priced VAT-exclusive. Prices must cover all risks, liabilities, obligations, profit, expenses, allowances, and costs for completing the contract.
Payment: Made per activity only when complete. Payment period is 4 weeks after receipt of a valid tax invoice.
Retention: 5% of contract value (Option X16).
Delay damages: 0.05% per day, maximum 10% of contract value (Option X7).
Performance bond: Pro forma provided, but marked "NOT APPLICABLE" in the document.
Insurance: Aviation liability insurance with indemnity limit of at least R300,000, proof submitted before work starts and annually. Contractor must also maintain COID cover and public liability insurance as per OHS agreement.
Provisional sums: Only payable if written order issued; unspent amounts deducted from contract sum.
No bid security or turnover requirements are stated.
Compliance Requirements
Source: APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdf (RFP)CSD registration: Required (implied by standard tender requirements, not explicitly stated in the document).
Tax clearance: Valid SARS tax clearance required (implied, not explicitly stated).
B-BBEE: Valid B-BBEE certificate required; must be presented annually. Failure to do so is a material breach and may lead to contract cancellation.
OHS: Must comply with Section 37(2) of the OHS Act and Construction Regulations. A Section 16.2 appointee must sign the OHS agreement. Baseline risk assessment required before work starts. Safety file must be approved before site access.
COID: Must be in good standing with the Compensation Fund or licensed insurer; letter required before work commences.
CIDB grading: Not stated in the document.
Local content: Not stated.
Health & Safety
Source: APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdfOHS requirements:
Environmental
Source: APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdfEnvironmental compliance is included in the preliminary and general items (item 1.3: Health, Safety and Environmental Compliance). No specific environmental impact or sustainability requirements are stated.
Contractual Terms
Source: APPENDIX 1 - Contract Document Refurbishment of Sliding Doors at KSIA.pdfContract type: NEC3 Engineering and Construction Contract, Main Option B (priced contract with bill of quantities), with dispute resolution option W1 and secondary options X7 (delay damages), X16 (retention), X18 (limitation of liability), and additional Z clauses.
Duration: 20 months from starting date (upon signing of contract by ACSA).
Defects date: 12 months after completion; defects correction period 2 weeks.
Payment: Assessment every 2 weeks; payment within 4 weeks of valid tax invoice.
Delay damages: 0.05% per day, max 10% of contract value.
Retention: 5% of contract value.
Limitation of liability: Neither party liable for indirect or consequential loss; employer's liability for contractor's indirect loss limited to R0.00.
Insurance: Contractor must provide insurance as per contract data, including aviation liability of at least R300,000.
Permits: All personnel must hold ACSA permits; airside induction training required; fees apply.
Additional conditions (Z clauses):
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
These rules are linked to the work category, industry, or regulated service area.
Act 38 of 2000
Important for public-sector construction and infrastructure tenders that require contractor grading or construction procurement standards.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 107 of 1998
Relevant where environmental authorisations, EIAs or environmental compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 85 of 1993
Sets health and safety duties for contractors, employers and service providers working on public-sector sites.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Act 103 of 1977
Relevant where building standards, renovations, maintenance or construction compliance may apply.
Relevant because this tender appears to involve construction, building work, infrastructure, or site-based delivery.
Address
King Shaka Drive - La Mercy - Durban - 4405
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
2
Last checked
20 Nov 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Key Personnel
Provinces Active
Industries
Learn how to submit a winning bid with these related articles
Everything South African construction contractors need to know about how procurement officers verify cidb grades: what gauteng contractors must ensure is correct β april 2026 update β covering CIDB grading certificate, NHBRC registration (residential), step-by-step processes, common disqualification mistakes, and how Tenders-SA.org helps you find and win relevant contracts in Gauteng.
How established construction firms use Joint Ventures with EMEs and QSEs to meet B-BBEE preferential procurement targets and access set-aside contracts.
Everything South African construction contractors need to know about cidb grading system explained: what every gauteng contractor must know in 2026 β april 2026 update β covering CIDB grading certificate, NHBRC registration (residential), step-by-step processes, common disqualification mistakes, and how Tenders-SA.org helps you find and win relevant contracts in Gauteng.
Everything South African construction contractors need to know about cidb vs nhbrc: understanding dual registration requirements for residential projects in gauteng β april 2026 update β covering CIDB grading certificate, NHBRC registration (residential), step-by-step processes, common disqualification mistakes, and how Tenders-SA.org helps you find and win relevant contracts in Gauteng.
π‘ Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Construction. Unlock full pricing strategies, bid frequency, and historical win rates.