SANParks Head Office, 643 Leyds Street - Muckleneuk - Pretoria - 0002
Organization Type
GOVERNMENT
Published
25 Nov 2026
OCDS Reference
ocds-9t57fa-179818
Summary
South african national parks requires a service provider to develop a stakeholder participation strategy, an a5 brochure, and a park-level stakeholder participation strategy template to guide engagement during the development and revision of management plans for protected areas. The project runs for a maximum of 12 months and involves close collaboration with sanparks staff, with deliverables submitted in ms word and print-ready formats. Bidders must achieve at least 70% in the functional evaluation to be considered, and the contract is awarded under the 80/20 preference point system.
Key Requirements
Closing: 04 December 2026 at 12:00, submitted by email only to [email protected]; bids to any other address are rejected.
Mandatory CSD registration: proof of registration on the Central Supplier Database must be submitted or the bid is disqualified.
Functional threshold: bidders must score at least 70% overall on the functional/technical criteria to proceed to price evaluation.
Team leader: must have a CV showing relevant stakeholder participation experience and project management experience; scoring favours more than 10 years' relevant experience and more than 5 years' project management.
Company experience: provide documented proof of at least 10 relevant organisational instruments (policy/strategy/framework) and at least 10 electronic brochures developed within the last 5–10 years; projects without proof are not scored.
Stakeholder engagement: demonstrate a track record of 15 or more completed stakeholder engagement processes within the last 5 years for maximum points.
Returnable documents: fully completed SBD 1, SBD 3.3, SBD 4, SBD 6.1 (with original or certified B-BBEE certificate or sworn affidavit), SBD 7.2, plus a detailed quotation on company letterhead, technical and financial proposals, CVs, references, and proof of authority to sign.
The Appointment of a Service Provider to Develop a Stakeholder Participation Strategy (and Brochure) in Support of the Development / Revision of Management Plans
Tender context
Return to this tender’s issuing organisation, province, or category.
The appointment of a service provider to develop a stakeholder participation strategy (and brochure) in support of the development / revision of management plans
SANParks Head Office, 643 Leyds Street - Muckleneuk - Pretoria - 0002
Professional Services & Consulting Industry Profile
Regulatory Bodies
SAGCSAICA
Tenders in this industry often require registration with these bodies.
Typical Documents
5 items
Company Registration (CIPC)
Tax Clearance Certificate
B-BBEE Certificate
CSD Registration
Company Profile
Recommended Certifications
Having these can improve your winning chances: CA(SA) - Chartered Accountant, PMI-PMP (Project Management Professional), Prince2 Practitioner, Six Sigma Certification
Document read. The full tender notice and its supporting documents are read end-to-end. Key sections, requirements, dates, and contact details are identified and pulled into a working summary you can act on.
Compliance review. The working summary is checked against South African procurement standards — PFMA, PPPFA, B-BBEE, CIDB, local content, and preferential procurement — so nothing critical is missed before you start your bid response.
Procurement Rules & Compliance ContextThis tender may be governed by South African public procurement rules covering fairness, transparency, preferential procurement, anti-corruption, administrative justice and access to information.
7 rules
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
Core procurement rules
These rules commonly apply to South African public-sector procurement.
7
Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
high
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Constitution of the Republic of South Africa, 1996 – Section 217
Act 108 of 1996 (s217)
high
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
South African National Parks (SANParks) requires a service provider to develop a Stakeholder Participation Strategy, an A5 brochure, and a park-level stakeholder participation strategy template to support the development and revision of management plans for protected areas. The work involves close collaboration with SANParks staff, includes three milestones (inception meeting, strategy development, and brochure/template production), and must be completed within 12 months.
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Bid-ready summary. The submission guidelines, evaluation criteria, technical, financial, and compliance sections are refined into professional, easy-to-scan prose. This is the final version you can rely on when preparing your bid or briefing your team.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Document read
Compliance review
Bid-ready summary
Purpose
Appoint a suitably qualified and experienced service provider to develop the SANParks Stakeholder Participation Strategy, an accompanying A5 brochure and a park stakeholder participation strategy template, working closely with SANParks staff.
Background
SANParks is a public entity under the National Environmental Management: Protected Areas Act (NEM: PAA) and manages national parks, marine protected areas, protected environments, estuaries and world heritage sites.
Management plans for these areas must be developed and reviewed under NEM: PAA, the World Heritage Convention Act, 1999, the National Environmental Management: Integrated Coastal Management Act, 2008 and the Biodiversity Act, 2004.
Engaging interested and affected parties during the development or revision of management plans is a legal requirement, and the strategy must guide that engagement.
Participation principles
Affected parties should have a say in decisions affecting them, and decisions should be sustainable.
The process must identify and involve those potentially affected, publicise the opportunity to participate, give participants the information and time they need to participate meaningfully, allow several opportunities for comment, and report back on how input influenced decisions.
It must recognise indigenous and ordinary knowledge and the diversity of values and opinions, and remain transparent, honest, cost-effective and sensitive to cultural, socio-economic, language and communication differences.
Context
The Table Mountain National Park and its Marine Protected Area management plans were revised during 2025/26 through stakeholder workshops, whose input informed the revised plans.
Bids sent to any other email address will not be accepted.
Late bids will not be considered.
Bids must be submitted on the official forms provided; the forms may not be retyped.
Returnable documents
SBD 1 (Invitation to Bid): bidder and contact details, signed as the offer cover page.
SBD 3.3 (Pricing Schedule – Professional Services) plus a detailed quotation on the bidder's company letterhead.
SBD 4 (Bidder's Disclosure): discloses state employment or relationships involving the bidder's directors, members or shareholders.
SBD 6.1 (Preference Points Claim) with the original or certified B-BBEE Status Level Verification Certificate or B-BBEE sworn affidavit (DTIC/CIPC).
SBD 7.2 (Contract Form – Rendering of Services).
Technical proposal: understanding of the assignment, methodology, team, work plan and contact details of at least three current or recent clients (projects completed within the past 36 months).
Financial proposal: fees (number of days and rate per day), disbursements and VAT, on company letterhead.
CVs and qualifications of key personnel.
References of similar completed projects.
Proof of registration on the Central Supplier Database.
Proof of authority to sign, such as a company resolution.
Disqualification risks
Any listed form not fully completed and submitted.
No CSD registration, or no proof of registration submitted.
Submission to an email address other than the designated one.
Bids received after the closing time.
Contacting SANParks staff other than the two designated officials.
70% overall on the functional / technical criteria. Bidders below 70% are eliminated and do not proceed to Phase 2.
Functional / technical criteria (100 points)
Methodology and workplan of the project: 20 points (20 = clear understanding with all milestones and targets; 10 = basic understanding with some milestones and targets; 0 = limited or no information).
Team leader experience: 20 points (20 = more than 10 years' relevant experience and more than 5 years' project management; 15 = 8–10 years with 4–5 years; 10 = 5 to under 8 years with 3 to under 4 years; 5 = 4 to under 5 years with 2 to under 3 years; 0 = under 4 years' relevant experience and under 2 years' project management).
Company practical experience – organisational instruments such as policy, strategy, framework or standard operating procedure: 15 points (15 = 10 or more projects with proof of more than six instruments; 10 = 6–9 projects with proof of four to six instruments; 5 = 1–5 projects with proof of one to three instruments; 0 = none or no proof).
Company practical experience – electronic brochures, including design software proficiency: 15 points (15 = 10 or more projects; 10 = 6–9 projects; 5 = 1–5 projects; 0 = none or no proof).
All three developed in close collaboration with SANParks staff.
Milestone 1 – inception
Attend an in-person inception meeting to confirm the project approach, workplan and required output formats.
Agree the workplan and the templates for the strategy and the park-level strategies.
Confirm the format and design approach for the brochure and infographic.
Milestone 2 – strategy
Convene one virtual meeting with key SANParks staff on the concept document, record decisions and capture inputs in a comments and responses document.
Circulate the revised draft for internal input, update the comments and responses document, revise and circulate for final input, then finalise and submit the strategy.
Milestone 3 – brochure and template
Convene one virtual meeting with key SANParks staff on the concept for the brochure and template.
Produce drafts, circulate for input, revise and circulate for final input, then produce the final brochure and template.
Formats and reporting
Strategy document in MS Office (Word).
Brochure in MS Office (Word), in an electronic format suitable for upload to the SANParks website, and in print-ready format for a publisher or printing house.
Reporting and accountability to the Manager: Park Planning.
Duration
Maximum 12 months from signature of the agreement.
Reference framework
National Environmental Management: Protected Areas Act, 2003; World Heritage Convention Act, 1999; National Environmental Management: Integrated Coastal Management Act, 2008; National Estuarine Protocol (2021); Biodiversity Act, 2004; SANParks Co-ordinated Policy Framework (2023); the existing brochure; and an example park stakeholder participation strategy.
Contact details of at least three current or recent clients, with recent clients being those for whom projects were completed within the past 36 months.
Scoring of the methodology and workplan
20 points: clear understanding of the project and workplan covering all milestones and targets.
10 points: basic understanding of the project and workplan covering some milestones and targets.
0 points: limited or no information, with no clear understanding of the project.
A detailed workplan and methodology must be submitted as evidence.
CV showing relevant years of experience in stakeholder participation and proven project management ability, with a list of projects delivered in a comparable role.
20 points: more than 10 years' relevant experience and more than 5 years' project management.
10 points: 5 to under 8 years' relevant experience and 3 to under 4 years' project management.
5 points: 4 to under 5 years' relevant experience and 2 to under 3 years' project management.
0 points: under 4 years' relevant experience and under 2 years' project management, or no relevant experience submitted.
The CV must show project achievements and contactable references for each project.
Company experience – organisational instruments (15 points)
Projects undertaken within the last 10 years, listed in Excel with client or contracting authority, description and relevance, start and completion dates, and contactable references.
15 points: 10 or more projects with proof of more than six instruments.
10 points: 6–9 projects with proof of four to six instruments.
5 points: 1–5 projects with proof of one to three instruments.
0 points: no relevant projects or no supporting proof.
Company experience – electronic brochures (15 points)
Projects undertaken within the last 5 years, listed in Excel with the same project information.
15 points: 10 or more projects with proof of brochures developed.
10 points: 6–9 projects with proof of brochures developed.
5 points: 1–5 projects with proof of brochures developed.
0 points: no relevant projects or no supporting proof.
Stakeholder engagement track record (30 points)
Projects undertaken within the last 5 years, listed in Excel with the same project information.
30 points: 15 or more completed stakeholder engagement processes.
25 points: 9–14 completed processes.
15 points: 5–8 completed processes.
5 points: 2–4 completed processes.
0 points: 0–1 completed processes.
Evidence must show achievements directly related to stakeholder participation, such as final products delivered and accompanying participation reports.
Only projects with the required documentary proof are evaluated.
Registration on National Treasury's Central Supplier Database (CSD) before submitting a bid, with proof of registration submitted. Failure to register or to provide proof leads to disqualification.
Tax
A valid SARS Tax Compliance Status PIN, or a printed TCS certificate, or a CSD number where no TCS PIN is available.
Consortia, joint ventures and sub-contractors must each submit a separate TCS certificate, PIN or CSD number.
B-bbee
An original or certified B-BBEE Status Level Verification Certificate, or a sworn affidavit for EMEs and QSEs, must accompany SBD 6.1 to claim preference points.
Standard forms
SBD 1 (Invitation to Bid), SBD 3.3 (Pricing Schedule), SBD 4 (Bidder's Disclosure), SBD 6.1 (Preference Points Claim) and SBD 7.2 (Contract Form) must be fully completed and submitted.
Proof of authority to sign, such as a company resolution.
Exclusions
Bids are not considered from persons in the service of the state, companies with directors in the service of the state, or close corporations with members in the service of the state.
Bidders listed on the Register for Tender Defaulters or the List of Restricted Suppliers are disqualified.
Other
POPIA applies to personal information collected in this process.
The service provider is an employer in its own right under the Occupational Health and Safety Act.
SANParks may conduct due diligence on documentary proof such as reference letters.
The service provider is an employer in its own right under the Occupational Health and Safety Act and carries the duties and responsibilities the Act places on employers.
Maximum 12 months from signature of the agreement.
Contract framework
The contract is subject to the Preferential Procurement Policy Framework Act, 2000, the National Treasury General Conditions of Contract (GCC) and any Special Conditions of Contract (SCC).
SANParks cannot amend the GCC; it appends SCC for clauses requiring specific information. Where the SCC and GCC conflict, the SCC prevails.
The successful bidder must complete and sign SBD 7.2 (Contract Form – Rendering of Services).
Appointment and confirmation
The recommended bidder must confirm it can deliver in line with the terms of reference; if it does not, SANParks may cancel the purchase order.
Final award is confirmed by issuing a purchase order.
Award goes to the bidder that quoted on all items, submitted the required administrative documents and complied with all terms and conditions.
Payment
Payment is against milestones achieved, within 30 days of receipt of invoice, with no payment before services are rendered.
Invoices must be addressed to the Manager: Park Planning.
Due diligence
SANParks may verify documentary proof such as reference letters.
Minimum qualifying score: 70% overall. Bidders scoring below 70% are eliminated.
Methodology and workplan: 20 points. 20 = clear understanding of the project with all milestones and targets; 10 = basic understanding with some milestones and targets; 0 = limited or no information.
Team leader experience: 20 points. 20 = more than 10 years' relevant experience and more than 5 years' project management; 15 = 8–10 years with 4–5 years; 10 = 5 to under 8 years with 3 to under 4 years; 5 = 4 to under 5 years with 2 to under 3 years; 0 = under 4 years' relevant experience and under 2 years' project management.
Company practical experience, Part A – organisational instruments such as policy, strategy, framework or standard operating procedure: 15 points. 15 = 10 or more projects with proof of more than six instruments; 10 = 6–9 projects with proof of four to six instruments; 5 = 1–5 projects with proof of one to three instruments; 0 = none or no proof.
Company practical experience, Part B – electronic brochures, including design software proficiency: 15 points. 15 = 10 or more projects; 10 = 6–9 projects; 5 = 1–5 projects; 0 = none or no proof.
Project lists in Excel format, with client or contracting authority, description of services and relevance to this RFQ, start and completion dates, and contactable references.
Organisational instrument projects must have been undertaken within the last 10 years; brochure projects and stakeholder engagement projects within the last 5 years.
Only projects supported by the required documentary proof are evaluated.
Phase 2 – price and specific goals
80/20 preference point system: 80 points for price, 20 points for specific goals.
Women-owned enterprises with at least 30% shareholding: up to 10 points (71–100% = 10; 61–70% = 8; 51–60% = 6; 41–50% = 4; 30–40% = 2; less than 29% = 0).
Black-owned enterprises with at least 51% shareholding: up to 10 points (91–100% = 10; 81–90% = 8; 71–80% = 6; 61–70% = 4; 51–60% = 2; 0–50% = 0).
Preference points are forfeited if the required proof is not submitted with the bid.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.