Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Documents available on tender detail page
Tender Type
Request for Bid(Open-Tender)
Delivery Location
OR Tambo International Airport - Kempton Park - Johannesburg - 1627
Organization Type
GOVERNMENT
Published
13 Oct 2026
OCDS Reference
ocds-9t57fa-173937
The employer requires professional engineering services covering assessment, design, procurement support, construction-stage services and close-out for the replacement of sewerage pump systems and associated monitoring and control systems at or tambo international airport. The contract uses nec3 professional services contract main option a (priced contract with activity schedule) with a 36-month duration. The single most consequential bidder consideration is the mandatory provision of six named key personnel with specific qualifications and professional registrations, combined with the requirement for an annual compliant b-bbee certificate and a 2% performance bond.
Closing: 16 November 2026 at 12:00. Submission method and address are not stated in the extracted document; bidders must confirm through ACSA procurement channels.
Key personnel (six mandatory roles): Project Manager / Lead Professional Engineer; Control and Instrumentation Engineer; Mechanical Engineer; Electrical Engineer; Software / Cloud Engineer; Cybersecurity Specialist. Each requires name, qualifications, professional registration, responsibilities and relevant experience to be submitted.
B-BBEE: Annual compliant B-BBEE certificate required; failure is material breach and may result in contract cancellation.
Performance bond: 2% of total of the Prices (Secondary Option X13).
Delay damages: 1% per week of professional fees, capped at 10% of total professional fees.
OHS Agreement: Section 37(2) OHS Act Agreement must be concluded before any work commences; compliance with OHS Act and Construction Regulation 5.1(k) mandatory.
Professional registrations: Key personnel must hold applicable professional registrations (e.g., ECSA, SACPCMP, SACNASP).
Insurance: Joint-names insurance from starting date until Defects Certificate or termination; minimum employee death/injury cover per COID Act.
No compulsory briefing or site visit is mentioned in the extracted document.
Payment terms: 4 weeks after receipt of valid tax invoice (per Z2 amendment); assessment interval every 4 weeks on 25th of each month.
Date & Time
Monday, 16 November 2026 - 12:00
Venue
null
Categories
Request for Bid(Open-Tender)
OR Tambo International Airport - Kempton Park - Johannesburg - 1627
Recommended Certifications
Having these can improve your winning chances: WISA Membership, IWMSA Membership
AI Document Analysis Stages
Description
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)13 Oct
2026
Tender Published
Tender was published
16 Nov
2026
Closing Date
Tender closing date
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
These rules commonly apply to South African public-sector procurement.
Act 53 of 2003
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Act 108 of 1996 (s217)
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Tender document RFQ 72628 - 13 October 2026.pdf
Analysis completed but response format was invalid
RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf
Analysis completed but response format was invalid
To download these documents and access AI-powered analysis, visit the main tender page.
Matched by category & region
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Open Supplier Readiness HubMedian Estimate
R 509 540
Range
Based on 8 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Professional services for the replacement of sewerage pump systems, monitoring systems, and control panels at O.R. Tambo International Airport. The service provider will deliver both design and construction supervision aspects of the project in accordance with the Framework for Infrastructure Delivery and Procurement Management (FIPDM), ensuring compliance with required standards and specifications throughout the construction phase.
Important Dates
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)Issue date: 13 October 2026
Query closing date: 22 October 2026
Bid closing date and time: 16 November 2026 at 12:00
Briefing session/site inspection: not applicable (N/A)
Bid validity period: 120 business/working days from closing date
Contact Information
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)Enquiries (SCM and technical):
Submission email: [email protected]
Organisation address:
Western Precinct, Aviation Park
O.R. Tambo International Airport
1 Jones Road
Kempton Park, Gauteng, 1632
South Africa
Postal address:
PO Box 75480
Gardenview, Gauteng, 2047
South Africa
Fraud hotline:
Submission Guidelines
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)Submission method: email to [email protected]
Closing date and time: 16 November 2026 at 12:00
Email attachments: split submission into at least four attachments of 4 MB each
No physical bid box; electronic submission only
Late bids will not be accepted
Bid validity period: 120 business/working days from closing date
All returnable forms must be completed, signed and submitted with the bid
Mandatory returnable documents:
Disqualification risks: any mandatory form omitted or unsigned; submission after closing time; alteration of bid document; failure to provide valid tax compliance status
Evaluation Criteria
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)Four-stage evaluation:
Stage 1: Mandatory administrative compliance — all mandatory returnable documents submitted
Stage 2: Functionality/technical evaluation — minimum threshold 70/100 points required to proceed
Stage 3: Price and Preference evaluation — 80/20 preference point system (price 80 points, specific goals 20 points)
Stage 4: Post-tender negotiations (where applicable)
Functionality scoring (total 100 points):
Construction Project Manager (Mechanical/Electrical Engineer): up to 10 points — BTech + PrTech + SACPCMP registration + 3 years construction project management experience = 5 pts; BEng/BSc + PrEng + SACPCMP registration + 3 years experience = 10 pts
Controls and Instrumentation Engineer: up to 30 points — BTech + PrTech + 3 years post-qualification experience + 2 years PrEng/PrTech registration = 15 pts; BEng/BSc + PrEng + same experience = 30 pts
Mechanical Engineer: up to 30 points — BTech + PrTech + 3 years post-qualification experience + 2 years PrEng/PrTech registration = 15 pts; BEng/BSc + PrEng + same experience = 30 pts
Occupational Health and Safety Practitioner: up to 10 points — diploma/degree + SACPCMP safety agent registration + 2 years experience = 5 pts; postgraduate degree + SACPCMP safety agent registration + 2 years experience = 10 pts
Price evaluation formula (80/20): Ps = 80(1 - (Pt - Pmin)/Pmin)
Specific goals points (max 20): B-BBEE Level 1 = 5, Level 2 = 4.5, Level 3 = 4, Level 4 = 3, Level 5 = 2, Level 6 = 0.5, Level 7 = 0.3, Level 8 = 0.1, non-compliant = 0; Black youth majority-owned = 5; Black women majority-owned = 5; Company majority owned by people with disabilities = 5
Objective criteria may justify award to a bidder other than highest scorer
Technical Specifications
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)Scope: Professional services for the replacement of sewerage pump systems, monitoring systems, and control panels at O.R. Tambo International Airport
Service provider responsible for both design and construction supervision in accordance with the Framework for Infrastructure Delivery and Procurement Management (FIPDM)
Deliverables: design development, implementation oversight, technical guidance throughout construction phase, compliance with required standards and specifications
Location: O.R. Tambo International Airport, Gauteng
Key personnel requirements (must be demonstrated in CVs):
Team organogram must show balanced key and support personnel with clear responsibilities dedicated to the project
Company experience: contactable references for completed Professional Construction Project Management Services or Professional engineering consultant services (reference letters/completion certificates required, not purchase orders)
Methodology
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)Staged evaluation methodology:
Stage 1: Mandatory administrative compliance check
Stage 2: Functionality/technical evaluation (minimum 70/100 threshold)
Stage 3: Price and Preference evaluation (80/20 system)
Stage 4: Post-tender negotiations where applicable
Bidders must demonstrate project-specific organogram with clear responsibilities and resource allocation
Team approach: key and support personnel must be balanced and appropriately qualified; prior collaboration on projects scores higher
Experience & Qualifications
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)Key personnel qualifications and experience (must be evidenced in CVs):
Company experience: 0, 1, or 2+ contactable references for Professional Construction Project Management Services or Professional engineering consultant services (reference letters/completion certificates with client name, work type, value, contact details; purchase orders/appointment letters not accepted)
Quality Management
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)Quality requirements not explicitly detailed in the extracted text beyond compliance with required standards and specifications per FIPDM framework
Professional services must be delivered in accordance with the Framework for Infrastructure Delivery and Procurement Management (FIPDM)
No specific quality management system certification (e.g. ISO 9001) stated as mandatory
Pricing Schedule
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)Pricing schedule: SBD 3.3 for professional services (must be completed and submitted with bid)
Price evaluation uses 80/20 preference point system
Price points formula: Ps = 80(1 - (Pt - Pmin)/Pmin)
Specific goals points (max 20): B-BBEE status levels 1-8 (5 to 0.1 points), black youth majority-owned (5), black women majority-owned (5), disability majority-owned (5), non-compliant (0)
Bid validity: 120 business/working days — prices must remain firm
No bill of quantities, schedule of rates, or detailed pricing breakdown specified in extracted text
No advance payment, retention, or guarantee percentages stated
Financial Requirements
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)Pricing schedule: SBD 3.3 for professional services (must be completed and submitted)
Price evaluation: 80/20 preference point system (price 80 points, specific goals 20 points)
Price points formula: Ps = 80(1 - (Pt - Pmin)/Pmin) where Pt = tender price, Pmin = lowest acceptable tender price
Bid validity: 120 business/working days — prices must remain firm and valid for this period
No bid security, bond, guarantee, retention or insurance requirements stated in the document
No minimum turnover or financial capacity thresholds stated
Payment terms not specified in the extracted text
Compliance Requirements
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)Mandatory eligibility and compliance:
No CIDB grading requirement stated (professional services, not construction works)
No professional body registration beyond those specified for key personnel (SACPCMP, ECSA)
No local content percentage requirement stated
Security vetting may be required (ACSA is a National Key Point)
Health & Safety
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)Occupational Health and Safety Practitioner required on project team with SACPCMP safety agent registration and minimum 2 years post-registration experience
Construction-related, safety-related or environmental-related qualification required (diploma/degree for 5 points, postgraduate degree for 10 points)
No detailed HSE plan requirements or specific safety standards stated in the extracted text
Contractual Terms
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)Contract form: NEC Contract (Form of Offer and Acceptance)
General Conditions of Contract (GCC) apply, plus any special conditions
ACSA reserves the right to: award whole or part of the bid; split the award; negotiate with shortlisted bidders; award to other than highest scorer where objective criteria allow; reject lowest acceptable bid; cancel the bid
Bid document may not be altered — any change leads to disqualification
Confidentiality: ACSA will not disclose bidder information without written approval; bidder names not disclosed until process finalised; bidders may not disclose bid information to third parties without ACSA written approval; third-party consultants must sign confidentiality agreements
Security vetting: ACSA is a National Key Point; bidders may be subjected to security vetting; ACSA will not contract with non-compliant bidders
Validity of submitted information: all documents and information must remain valid for contract duration; bidder must provide updated documents immediately upon expiry or change
Fraud and corruption reporting: ACSA Tip-Offs Anonymous hotline (0800 00 80 80 / 086 726 1681, [email protected])
Section
Source: Tender document RFQ 72628 - 13 October 2026.pdf (RFQ)Evaluation stages and criteria fully covered in the main evaluationCriteria section above. No additional evaluation criteria beyond those already summarised.
Description
Source: RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf (unknown)Professional engineering services for the assessment, design, procurement support, construction-stage services and close-out of the replacement of sewerage pump systems and associated control systems at OR Tambo International Airport. Contract: NEC3 Professional Services Contract (PSC), Main Option A (Priced contract with activity schedule). Duration: 36 months from signing. Location: OR Tambo International Airport, Gauteng.
Important Dates
Source: RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf (unknown)Closing date and time: 16 November 2026 at 12:00
Starting date: Upon signing of contract by ACSA/Employer
Completion date: 36 months after starting date
First (preliminary) programme due: by tender closing date
Revised programmes: at intervals no longer than 4 weeks
Quality policy statement and quality plan due: within 4 weeks of Contract Date
Defects date: 52 weeks after Completion of the whole of the services
Defects correction period: 2 weeks
Assessment interval: every 4 weeks, on the 25th day of each month
Payment period: 4–6 weeks after receipt of tax invoice (Z2 amends to 4 weeks)
Retention period: 5 years after Completion or earlier termination
Period of reply: 3 working days
End of liability date: 52 weeks after Completion
No compulsory briefing or site visit mentioned in the extracted text.
Contact Information
Source: RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf (unknown)Employer:
Employer's Agent:
Adjudicator nominating body: Chairman of Johannesburg Advocates Bar Council
Arbitration venue: Johannesburg, South Africa
Arbitrator nominating body: Chairman of Johannesburg Advocates Bar Council
Submission Guidelines
Source: RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf (unknown)Submission requirements:
Evaluation Criteria
Source: RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf (unknown)Evaluation methodology not explicitly detailed in the extracted document. Key indicators:
Technical Specifications
Source: RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf (unknown)Scope: Professional engineering services for assessment, design, procurement support, construction-stage services and close-out of the replacement of sewerage pump systems and associated control systems at OR Tambo International Airport.
Key personnel required (names, qualifications, professional registration, responsibilities and relevant experience to be provided):
Additional roles listed in Contract Data Part 2: Occupational Health and Safety Practitioner, Environmental Control Officer, Corrosion Specialist, Civil/Structural Engineer, Quantity Surveyor/Cost Engineer.
Project stages and fee allocation:
Risk Register includes: existing-information gaps, live-station access, sewage and confined-space hazards, service continuity, uncertain hydraulic duties, equipment condition, temporary pumping, shutdowns, construction interfaces, airport operations.
Access to as-built information, existing services, and ACSA engineering/operational/maintenance personnel granted upon award.
Quality policy statement and quality plan due within 4 weeks of Contract Date.
Defects correction period: 2 weeks.
Retention period for records: 5 years after Completion.
Experience & Qualifications
Source: RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf (unknown)Key personnel (names, qualifications, professional registration, responsibilities, relevant experience to be submitted):
Additional roles required per Contract Data Part 2:
Risk Register matters: Availability of As-Built Information, Access to Site, Progress vs Programme, Cash Flow Management.
Access to as-built information, existing services, and ACSA engineering/operational/maintenance personnel granted upon award.
Quality Management
Source: RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf (unknown)Quality policy statement and quality plan must be provided within 4 weeks of the Contract Date (clause 40.2).
Defects date: 52 weeks after Completion of the whole of the services (clause 41.2).
Defects correction period: 2 weeks (clause 43.2).
Extended defects date provisions: If Employer cannot use works due to a defect after Completion but before defects date, the defects date is delayed by the period of inability to use (Z7.1). If part of works is replaced due to defect, defects date for that part is delayed by the period between Completion and replacement (Z7.2). Project Manager notifies Consultant of change (Z7.3). Maximum extension: twice the original defects period (Z7.3).
Pricing Schedule
Source: RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf (unknown)Pricing Data (Part C2) contains the Activity Schedule.
Contract type: Priced contract with activity schedule (Main Option A).
Staff rates: as stated in the Pricing Data.
Tendered total of Prices: entered in Form of Offer and Acceptance (inclusive of VAT).
Fee allocation by project stage (percentage of total professional fees):
Payment made against completed and accepted activities in the activity schedule; no fixed percentage allocation unless stated by tenderer and accepted by Employer.
Assessment interval: every 4 weeks on the 25th day of each month.
Payment period: 4–6 weeks after receipt of tax invoice (Z2 amends to 4 weeks).
Financial Requirements
Source: RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf (unknown)Pricing format: Activity schedule (Part C2) – priced contract with activity schedule (Main Option A).
Staff rates: as stated in the Pricing Data.
Tendered total of Prices: entered in Form of Offer and Acceptance (inclusive of VAT).
Payment: against completed and accepted activities in the activity schedule; no fixed percentage allocation unless agreed.
Assessment interval: every 4 weeks, on the 25th day of each month.
Payment period: 4–6 weeks after receipt of tax invoice (Z2 amends core clause to 4 weeks).
Currency: South African Rand.
Interest rate: prime lending rate of Nedbank Bank.
Performance bond: 2% of the total of the Prices (Secondary Option X13).
Delay damages: 1% per week of the professional fees, up to a maximum of 10% of total professional fees (Secondary Option X7).
Insurance: as per Insurance Clauses attached to Contract Data; joint names; cover from starting date until Defects Certificate or termination; minimum indemnity for employee injury/death as per COID Act.
Limitation of liability:
End of liability date: 52 weeks after Completion.
Retention period: 5 years after Completion or earlier termination.
Compliance Requirements
Source: RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf (unknown)B-BBEE: Annual compliant B-BBEE certificate required (Z15); failure constitutes material breach and may lead to contract cancellation.
Occupational Health & Safety: Section 37(2) OHS Act Agreement (C1.3) must be concluded before any consultant/subcontracted work commences; compliance with OHS Act and Construction Regulation 5.1(k) mandatory.
Professional registration: Key personnel must hold relevant professional registration (e.g., ECSA for engineers, SACPCMP for project manager, SACNASP for environmental officer, etc.).
CSD registration and valid tax compliance status (SARS tax PIN) implied as standard for ACSA tenders.
Confidentiality: All information obtained under the contract treated as confidential (Z11); prior written consent required for disclosure; images of works require Project Manager consent.
Ethics/Anti-corruption: Compliance with Prevention and Combating of Corrupt Activities Act; no illegal/corrupt practices (Z10); breach grounds for termination.
Intellectual Property: IP rights remain with originator; Employer receives irrevocable, transferable, non-exclusive, royalty-free licence for constructing, repairing, operating, maintaining works (Z13); Consultant indemnifies Employer against IP infringement claims.
Dispute resolution: Adjudication (Option W1) with panel of adjudicators; arbitration (Rules for Conduct of Arbitrations 2013, 7th Edition) in Johannesburg; termination disputes referred directly to arbitration (Z14).
Cession/assignment: Consultant may not cede, delegate or assign without Employer’s written consent (not unreasonably withheld); Employer may cede/delegate on written notice (Z9).
Employer’s step-in rights: If Consultant defaults and fails to remedy within 2 weeks, Employer may remedy at Consultant’s cost (Z12).
Termination: Employer may terminate for reasons not stated in contract (X11); additional termination triggers include business rescue proceedings (Z8).
Law and language: South African law; English language.
Health & Safety
Source: RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf (unknown)Occupational Health & Safety Agreement (C1.3) required in terms of Section 37(2) of the OHS Act and Construction Regulation 5.1(k).
Objectives: Assist ACSA to comply with OHS Act and Regulations, and Compensation for Occupational Injuries & Diseases Act (COID Act).
Agreement must be concluded before any consultant/subcontracted work commences.
Parties: ACSA (Client) and the Consultant (Mandatary/Principal Contractor).
Mandatary must be familiar with OHS Act (Sections 1–50) and applicable Regulations.
Mandatary using own sub-contractors must conclude similar written agreements with them.
Mandatary must contact Client in event of... (text truncated in source).
Key personnel include Occupational Health and Safety Practitioner (name, qualifications, experience to be provided).
Insurance for death/bodily injury to employees: minimum limit as prescribed by COID Act (clause 81.1).
Contractual Terms
Source: RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf (unknown)Contract: NEC3 Professional Services Contract (April 2013) with Main Option A (Priced contract with activity schedule), Dispute Resolution Option W1, Secondary Options X7 (Delay damages), X10 (Employer’s Agent), X11 (Termination by Employer), X13 (Performance bond), X18 (Limitation of liability), and Additional Conditions Z1–Z15.
Law: Republic of South Africa.
Language: English.
Period of reply: 3 working days.
Starting date: Upon signing by ACSA/Employer.
Completion date: 36 months after starting date.
Performance bond: 2% of total Prices.
Delay damages: 1% per week up to 10% of professional fees.
Limitation of liability: Total direct liability capped at total of Prices; consequential loss excluded; end of liability 52 weeks after Completion.
Insurance: Joint names, from starting date to Defects Certificate; minimum indemnity per COID Act.
Payment: Assessment every 4 weeks (25th of month); payment within 4–6 weeks of invoice (Z2: 4 weeks); currency ZAR; interest at Nedbank prime rate.
Retention: 5 years after Completion or termination.
Defects date: 52 weeks after Completion; defects correction period 2 weeks; defects date extended if Employer cannot use works due to defect (Z7).
Termination: Employer may terminate for convenience (X11); Consultant breach of ethics (Z10) or failure to provide annual B-BBEE certificate (Z15) constitutes material breach; business rescue proceedings added as termination trigger (Z8).
Cession: Consultant requires Employer’s written consent; Employer may cede on notice (Z9).
Confidentiality: All contract information confidential; prior written consent for disclosure; images require Project Manager consent; sub-consultants bound (Z11).
Employer’s step-in: On Consultant default unremedied after 2 weeks, Employer may remedy at Consultant’s cost (Z12).
Intellectual Property: Originator retains IP; Employer gets broad licence; Consultant indemnifies against infringement claims (Z13).
Dispute resolution: Adjudication from panel (written submissions only, no oral hearings); termination disputes direct to arbitration; arbitration in Johannesburg under Association of Arbitrators rules; adjudicator/arbitrator nominated from panels, deadlock to Chairman of Johannesburg Advocates Bar Council (W1, Z4, Z14).
Ethics: Anti-corruption compliance; breach allows termination and civil/criminal action (Z10).
Communications: Deemed receipt rules for hand delivery, post, electronic (Z3).
Tax invoices: Must show details per Scope and valid tax invoice requirements (Z2).
Fee estimation: Fees charged in terms of agreed rates (Z1).
Interpretation: No waiver/estoppel without written agreement (Z5).
Works provision: Consultant supervises works; warrants fitness for purpose (Z6).
Section
Source: RFQ 72628 - Professional Services for the Replacement of Sewerage Pump Systems and Control Systems NEC3 PSC.pdf (unknown)No explicit evaluation criteria (price/functionality split, minimum scores, preference point system) stated in the extracted document. Evaluation likely based on:
Refer to ACSA’s standard evaluation policy for PPPFA 80/20 or 90/10 application.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
Act 5 of 2000
Covers preferential procurement and preference-point systems used in public tenders.
Relevant because this is a South African public-sector procurement opportunity.
Act 12 of 2004
Supports anti-corruption controls and supplier integrity in procurement processes.
Relevant because this is a South African public-sector procurement opportunity.
Act 28 of 2024
Provides the national framework for public procurement across government.
Relevant because this is a South African public-sector procurement opportunity.
Act 2 of 2000
Supports access to tender records, award decisions and public-sector procurement information.
Relevant because this is a South African public-sector procurement opportunity.
Act 3 of 2000
Supports lawful, reasonable and procedurally fair administrative tender decisions.
Relevant because this is a South African public-sector procurement opportunity.
Address
O. R. Tambo International Airport, Shop R7, First Floor, Domestic Terminal, O.R. Tambo Airport Rd, O.R. Tambo, Kempton Park, 1627, South Africa
Source confidence
High source confidence
Official source
eTenders.gov.za
Documents found
2
Last checked
14 Oct 2026
AI status
Enhanced
Data conflicts
None detected
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.
Contact
010-207-2000[email protected]www.acsa.co.zaO. R. Tambo International Airport, Shop R7, First Floor, Domestic Terminal, O.R. Tambo Airport Rd, O.R. Tambo, Kempton Park, 1627, South Africa
Key Personnel
Provinces Active
Industries
Learn how to submit a winning bid with these related articles
Everything South African general contractors need to know about how to write a winning tender proposal without an in-house bid team in gauteng — covering CSD, BBBEE, step-by-step processes, common disqualification mistakes, and how Tenders-SA.org helps you find and win relevant contracts in Gauteng.
How small office supplies, stationery, and general goods suppliers use Joint Ventures to win government procurement contracts by combining inventory with B-BBEE credentials.
How the Protection of Personal Information Act affects tender submissions, data handling, and supplier contracts with government. A practical POPIA compliance guide for South African tender bidders covering lawful processing, data subject rights, and consequences of non-compliance.
A meticulously organised tender submission can be the difference between a winning bid and one that hits the rejection pile. Learn how to package, structure, and present your tender response for maximum evaluator impact on South African government contracts.
💡 Want more tendering tips and strategies?
Explore Our BlogGet deep intelligence on Sewerage. Unlock full pricing strategies, bid frequency, and historical win rates.