This tender is for the replacement of roller shutter doors at king shaka international airport over a 24-month period, using the nec3 engineering and construction contract. IT is issued by the airports company south africa and is aimed at qualified construction contractors capable of handling decommissioning, supply, installation, and commissioning at an operational airport.
Key Requirements
The contract duration is 36 months from the starting date upon signing, with a defects liability period of 52 weeks after completion.
Bidders must submit a compliant BEE Certificate annually; failure is a material breach that may lead to contract cancellation.
A performance bond, public liability insurance, and compliance with the OHS Act and COID Act are mandatory.
The pricing model is a Priced Contract with Bill of Quantities (NEC3 Option B), with payments assessed every 4 weeks.
The scope includes all works detailed in Part C3 'Scope of Works' at both landside and airside areas of the airport.
Key personnel CVs must be provided, and the contractor is responsible for correct setting out and rectifying errors at own cost.
The closing date for submissions is 21 August 2026 at 12:00.
Tenders in this industry often require registration with these bodies.
CIDB Registration
Construction Industry Development Board (CIDB) registration is mandatory for almost all public sector construction tenders. Ensure your grading matches the tender value.
Typical Documents
10 items
Company Registration (CIPC)
Tax Clearance Certificate
B-BBEE Certificate
CSD Registration
Company Profile
CIDB Registration Certificate
NHBRC Registration (if applicable)
Health & Safety Plan
Insurance Certificates
Previous Project Completion Certificates
Recommended Certifications
Having these can improve your winning chances: NHBRC Registration, ISO 9001:2015 (Quality Management), ISO 14001:2015 (Environmental Management), ISO 45001:2018 (Occupational Health & Safety), SACPCMP Registration, ECSA Registration
Review in progress · 0 of 2 documents being finalised
AI Document Analysis Stages
Document read. The full tender notice and its supporting documents are read end-to-end. Key sections, requirements, dates, and contact details are identified and pulled into a working summary you can act on.
Compliance review. The working summary is checked against South African procurement standards — PFMA, PPPFA, B-BBEE, CIDB, local content, and preferential procurement — so nothing critical is missed before you start your bid response.
Procurement Rules & Compliance ContextThis tender may be governed by South African public procurement rules covering fairness, transparency, preferential procurement, anti-corruption, administrative justice and access to information.
11 rules
These references help suppliers understand the public-procurement framework around this opportunity. They are generated from the tender category, issuing organisation type and procurement context.
Core procurement rules
These rules commonly apply to South African public-sector procurement.
7
Broad-Based Black Economic Empowerment Act (B-BBEE Act)
Act 53 of 2003
high
Provides the empowerment-compliance context often used in public-sector supplier evaluation.
Relevant because this is a South African public-sector procurement opportunity.
Constitution of the Republic of South Africa, 1996 – Section 217
Act 108 of 1996 (s217)
high
This is general procurement context, not legal advice. Always verify requirements in the official tender documents and issuing authority notices.
Contract Document - Replacement of Roller Shutter Doors.pdf
Airports Company South Africa (ACSA) invites bids for the replacement of roller shutter doors at King Shaka International Airport. The contract is for a 24-month period under the NEC3 Engineering and Construction Contract (ECC), Main Option B (Priced contract with Bill of Quantities). The scope includes decommissioning, supply, installation, and commissioning.
Airports Company South Africa invites bids for the decommissioning, supply, installation, and commissioning of roller shutter doors at King Shaka International Airport. The tender follows CIDB Standard Conditions of Tender, includes a functionality evaluation, and uses the 80/20 price/preference scoring system. Bids close on 21 August 2026.
Win ACSA tenders with AI Matching Engine, airport-infrastructure intelligence, compliance analysis, and application support for aviation operations.
Similar Tenders
Matched by category & region
Supplier Readiness Hub
Free guidance to prepare before you bid
Not sure if your business is ready for this tender? Check CSD, CIDB, and B-BBEE requirements, run a readiness assessment, and move from opportunity to submission.
Based on 21 comparable awarded tenders. Companies with similar profiles typically bid near the median.
* Estimates are based on historical data and do not guarantee actual award values.
Bid-ready summary. The submission guidelines, evaluation criteria, technical, financial, and compliance sections are refined into professional, easy-to-scan prose. This is the final version you can rely on when preparing your bid or briefing your team.
We refine every tender document through these stages so you can brief your team and prepare your bid with confidence. Anything marked as "in progress" will be upgraded automatically — no action required from you.
Document read
Compliance review
Bid-ready summary
Tender Available From: 23 July 2026.
Non-Compulsory Briefing: 3 August 2026 at 11:00 AM via Microsoft Teams (online).
Query Closure Date: 7 August 2026.
Closing Date and Time: 21 August 2026 at 12:00 PM (South African Time).
Submit by 21 August 2026 at 12:00 PM (South African Time). Late bids will not be accepted.
Deliver to the Tender Box at Airports Company SA SOC Ltd, King Shaka International Airport, La Mercy, MSO Building (Multi Storey Office Block) outside Main Terminal Building, Ground Floor, Reception, Near Pick Up Zone.
Submit during working hours Monday to Friday.
Complete the Bid Register upon submission with the tendering entity name and contact details.
Submit one original and one copy, plus an electronic copy on a USB flash drive.
Seal original and copy in separate packages clearly marked "ORIGINAL" and "COPY". Include tenderer's name, contact details, reference number KSIA8029/2025/RFP, and tender description.
Use only the issued tender documentation; do not re-type official forms.
Telegraphic, telephonic, telex, facsimile, or emailed submissions will not be accepted.
Bids must be valid for 12 weeks (84 days) from the closing date.
Failure to comply with submission requirements may render the bid invalid.
CIDB contractor grading 4ME or higher. Must provide valid tax compliance status. Must achieve minimum 70 points in functionality evaluation. Must submit all required documentation completely and correctly. Foreign suppliers must answer tax residency questionnaire.
Scope: Decommissioning, supply, installation, and commissioning of roller shutter doors at King Shaka International Airport.
Deliverables: Industrial roller shutter doors, including sectional roller doors and overhead sectional roller doors.
Standards: Works must comply with CIDB Standard for Uniformity in Construction Procurement.
Key Personnel Requirements:
Site Supervisor: Must have relevant qualifications (SAQA trade test, N4 Engineering or higher) and experience in industrial door installation and supervision.
Technician: Must have relevant qualifications (SAQA trade test, N4 Engineering or higher) and experience in industrial door installation.
Technical Assistants (Mechanical and Electrical): Must have N2 or higher qualifications and experience in mechanical/electrical systems.
Company Experience: Minimum of two successful similar projects in industrial roller shutter door installation.
CIDB Registration: Contractor grading of 4ME or higher is mandatory.
Tax Compliance: Submit SARS Tax Compliance Status (TCS) PIN or CSD number. For consortia/JVs, each party must submit separately.
B-BBEE: Provide proof (B-BBEE certificate from SANAS-accredited agency or sworn affidavit) to claim preference points.
Central Supplier Database (CSD): Registration required if no TCS PIN is available.
Company Authority: Submit proof of authority to sign the bid (e.g., company resolution).
Foreign Suppliers: Must meet tax obligations in South Africa if they have income or establishment in RSA.
DocumentContract Document - Replacement of Roller Shutter Doors.pdfReview complete
Description
Source: Contract Document - Replacement of Roller Shutter Doors.pdf
This is a construction contract for the replacement of roller shutter doors at King Shaka International Airport over a 24-month period.
The contract is between Airports Company South Africa SOC Limited and the successful contractor.
The document is structured into five parts: Part C1 Agreements & Contract Data, Part C2 Pricing Data, Part C3 Scope of Works, Part C4 Site Information, and Part C5 Annexures.
Important Dates
Source: Contract Document - Replacement of Roller Shutter Doors.pdf (unknown)
Closing date for submissions: 21 August 2026 at 12:00.
Contract starting date: Upon signing by ACSA.
Completion date: 36 months from starting date.
Defects date: 52 weeks after completion of the whole works.
Defects correction period: 4 weeks.
Preliminary programme must be submitted within 2 weeks of contract start date.
Revised programmes must be submitted at intervals no longer than 4 weeks.
Assessment interval for payments: Every 4 weeks, on the 20th day of each successive period.
Payment is made within 4–6 weeks after receipt of tax invoice.
Contact Information
Source: Contract Document - Replacement of Roller Shutter Doors.pdf (unknown)
Employer: Airports Company South Africa SOC Limited, King Shaka International Airport, King Shaka Drive, La Mercy, 4407. Telephone: 032 436 6000, Fax: 032 436 6672.
Project Manager: Andile Mkhize, Airports Company South Africa, King Shaka International Airport, King Shaka Drive, La Mercy, 4407. Telephone: 032 436 6000, Email: [email protected].
Adjudicator and Arbitrator panels are listed in the contract data; appointments are made from these panels when a dispute arises.
Submission Guidelines
Source: Contract Document - Replacement of Roller Shutter Doors.pdf (unknown)
Submit your offer using the Form of Offer and Acceptance included in Part C1.
The tenderer must sign the Offer signature block and include the total price inclusive of VAT.
The tenderer must examine all documents listed in the Tender Data and addenda listed in Returnable Schedules.
If accepted, the Contractor must within two weeks contact the Employer’s agent to arrange delivery of securities, bonds, guarantees, proof of insurance and other required documentation.
Failure to provide required documentation constitutes a repudiation of the agreement.
The Contractor has five working days after receipt of the signed agreement to notify the Employer of any objections, otherwise it becomes a binding contract.
Evaluation Criteria
Source: Contract Document - Replacement of Roller Shutter Doors.pdf (unknown)
Bidder must be a legally registered entity (registration number required). Must have the capacity to enter into the contract. Joint ventures/consortia are accepted but result in joint and several liability. No cession/delegation without Employer's written consent. Must not be involved in corrupt practices (ethics clause). Must be able to provide the required insurances (public liability, etc.) and performance bond.
Technical Specifications
Source: Contract Document - Replacement of Roller Shutter Doors.pdf (unknown)
Scope: Replacement of Roller Shutter Doors at King Shaka International Airport for a 24-month period.
Works Information is detailed in Part C3 ‘Scope of Works’.
Site boundaries: King Shaka International Airport – Landside and Airside.
Site Information is in Part C4.
The Contractor must provide the works in accordance with the Works Information and warrant that the results shall be fit for purpose.
The Contractor is responsible for correct setting out of the Works and rectifying any positioning errors at own cost.
Key personnel CVs must be appended to the Tender Schedule; the contract data requires details for up to 10 key people (names, job titles, responsibilities, qualifications, experience).
Experience & Qualifications
Source: Contract Document - Replacement of Roller Shutter Doors.pdf
The Contractor must provide CVs for key personnel as part of the tender submission.
The contract data requires details for up to 10 key people, including names, job titles, responsibilities, qualifications, and experience.
The Contractor must appoint competent persons as per OHS Act Section 16(2).
Quality Management
Source: Contract Document - Replacement of Roller Shutter Doors.pdf
The Contractor must maintain hygiene and cleanliness on site, clearing waste regularly.
Substance abuse policy: No intoxication allowed on site; Client reserves right to conduct testing.
Records of substance abuse testing must be filed and made available.
Pricing Schedule
Source: Contract Document - Replacement of Roller Shutter Doors.pdf
Pricing information is contained in Part C2 ‘Pricing Data’.
The contract uses a priced contract with Bill of Quantities (Main Option B).
The offered prices must be stated in the Pricing Schedule within the Form of Offer and Acceptance.
Financial Requirements
Source: Contract Document - Replacement of Roller Shutter Doors.pdf (unknown)
Contract uses Main Option B: Priced contract with Bill of Quantities.
Pricing data and instructions are in Part C2 ‘Pricing Data’.
The offered total prices inclusive of VAT must be stated in the Form of Offer and Acceptance.
Currency: South African Rand.
Retention: 10% of the Prices, with 50% released at Practical Completion and 50% after the Defects Period.
Delay damages: 1% per week up to a maximum of 10% of the Contract value.
Payment terms: Assessment every 4 weeks, payment within 4–6 weeks after receipt of tax invoice.
The Contractor must provide an unconditional, on-demand performance bond for the amount stated in the Contract Data, valid until the end of the contract period.
Compliance Requirements
Source: Contract Document - Replacement of Roller Shutter Doors.pdf (unknown)
B-BBEE: The Contractor must annually present a compliant BEE Certificate. Failure is a material breach and may lead to contract cancellation.
Occupational Health and Safety: The Contractor must comply with the OHS Act, COID Act, and Construction Regulations 2014. A detailed OHS agreement (OHS 040) must be signed.
Insurance: The Contractor must provide insurance as stated in the Contract Data, including public liability insurance, and ensure employees are covered under COID Act.
Ethics: The Contractor must comply with anti-bribery and corruption laws, including the Prevention and Combating of Corrupt Activities Act.
Confidentiality: All contract information must be treated as confidential.
Subcontractors: Any subcontractors must meet the same compliance requirements.
Legal compliance: The contract is governed by South African law and conducted in English.
Health & Safety
Source: Contract Document - Replacement of Roller Shutter Doors.pdf
The Contractor must sign a detailed OHS agreement (OHS 040) complying with the OHS Act, COID Act, and Construction Regulations.
A baseline risk assessment must be conducted before work commences.
A full-time dedicated Health and Safety resource must be appointed if 5 or more people are working.
All employees must be trained on hazards and safe work procedures.
PPE must be provided and worn at all times; compliance monitored.
Plant, machinery, and equipment must be safe and comply with Section 10 of OHS Act.
Permit-to-work system: Required work must not proceed without an approved permit.
Incident reporting: All incidents must be reported within 2 hours, with formal report within 48 hours.
Emergency response procedure must be submitted.
Health and safety committees must be established and meetings attended monthly.
Medical examinations required for all employees, with certificates kept on file.
Subcontractors must meet the same OHS requirements.
Environmental
Source: Contract Document - Replacement of Roller Shutter Doors.pdf
The Contractor must maintain the work site, ablution, offices, and surrounding area to a reasonably practicable level of hygiene and cleanliness.
No loose materials shall be left lying about unnecessarily; waste must be cleared regularly and on completion of work.
Contractual Terms
Source: Contract Document - Replacement of Roller Shutter Doors.pdf
Contract duration: 36 months from starting date.
Defects liability: 52 weeks after completion, with a 4-week correction period.
Delay damages: 1% per week up to a maximum of 10% of contract value.
Retention: 10% of Prices, half released at Practical Completion, half after Defects Period.
Limitation of liability: Neither party liable for consequential or indirect loss.
Termination: Applicable as per NEC3 TSC3, including for business rescue proceedings.
Performance bond: Unconditional, on-demand bond required, must be kept valid until contract end.
Confidentiality: Contractor must treat all contract information as confidential.
Intellectual property: IP rights remain with originator; Employer gets a royalty-free licence.
Dispute resolution: Adjudication and arbitration procedures specified, with panels listed.
Ethics: Strict anti-bribery and corruption clauses; breach may lead to termination.
Subcontracting: Requires Employer consent; subcontractors must meet same terms.
OHS compliance: Detailed OHS agreement (OHS 040) must be adhered to.
Sets the constitutional standard for fair, equitable, transparent, competitive and cost-effective public procurement.
Relevant because this is a South African public-sector procurement opportunity.
This tender has strong source evidence, including source metadata and supporting tender information synced from the government tender portal.
Tenders SA is not the issuing authority. All tenders are automatically synced from the official government tender portal. Always confirm final submission details, closing dates, briefing sessions, eligibility requirements, and documents on the official government portal before applying.